Attachment Report Building
Attachment Report Building
COUNCIL
TRADE PROJECT
FOR
A PROPOSED CONSTRUCTION OF MODERN TUITION
BLOCK AT ELDORET NATIONAL POLYTECHNIC.
PROJECT OBJECTIVES:
3. To encourage institution to admit more learners and provide best technological knowledge.
RATIONALE
The institute has intention of constructing a Modern Tuition Block to create more space for the students.
The Modern Tuition Block will comprise: Classes, Computer Lab, school hall.
Due to the increasing number of students in the institute, it has proposed to build a modern tuition
block for students.
The Tuition block for the school shall create job opportunity for those who shall be working there,
thus improving the living standards of those people.
The modern tuition block shall reduce the current learning crisis in the institute in terms of space.
The institute shall be encouraged to admit more students and provide best technical knowledge.
My dedication first goes to my parents for support and encouragement during my project work. I also
I also dedicated to my very dedicated and supportive project Supervisor for the assistance and guidance. Not
forgetting all lectures involved and to the entire Eldoret National Polytechnic fraternity for the provision of
My utmost sincere gratitude goes to the almighty God for his unending love and care throughout the entire
period, also for the good health and enabling to learn and have knowledge to be able to accomplish
everything.
My dear parents also had a very huge role in supporting me morally, spiritually and financially in order for
me to successfully complete the proposed trade project in time and without any constraints. My siblings’
efforts won’t go unnoticed because of their relentless support and sacrifice in terms of time and financial
support.
Mr. Jacob Omondi also had a very phenomenal effect in his guidance in our preparation for the write up of
the proposed trade project. Her words of inspiration and directions will not go unnoticed. LAXCOM
HOLDINGS LIMITED for their idea’s advice and encouragement and their useful criticism made my
project even more success. May almighty God bless you abundantly.
ABSTRACT
The main objective of this project is to test the student’s capability of applying the knowledge and skill
gained after the three-year course in Higher Diploma in Construction (Building and Civil Engineering
Option). The project is intended to cover various disciplines under construction industry and also to meet
the syllabus requirements as stipulated by the technical education program.
LIST OF ACRONYMS AND ABBREVIATIONS USED
LL: liquid limit LS: linear shrinkage
Ac: net cross-sectional area of concrete in a Au: deflection at ULS for each column
column. calculated from equation 32.
Contents
CHAPTER ONE: INTRODUCTION............................................................................................................9
Background information............................................................................................................................9
Solution to the problem..............................................................................................................................9
Research questions.....................................................................................................................................9
1: Questionnaires...................................................................................................................................9
2: Interviews...........................................................................................................................................9
3: Observation........................................................................................................................................9
PROJECT OBJECTIVES..........................................................................................................................9
CHAPTERTWO: LITERATURE REVIEW...............................................................................................10
Reviews on similar projects and their usefulness....................................................................................10
Vision 2030 realization............................................................................................................................10
CHAPTER THREE: METHODOLOGY....................................................................................................11
PART I: SURVEY...................................................................................................................................11
INTRODUCTION...............................................................................................................................11
Objectives of conducting surveying...................................................................................................11
PART II: SOIL MECHANICS................................................................................................................15
SOIL INVESTIGATION.....................................................................................................................15
Plasticity index/ Atterberg limit...........................................................................................................15
Moisture content tests (proctor)...........................................................................................................18
Bearing capacity tests (CBR)...............................................................................................................20
CHAPTER FOUR: DATA ANALYSIS, FINDINGS AND RECOMMENDATIONS..............................22
DISCUSSIONS........................................................................................................................................22
PART I: ARCHITECHTURAL DESIGN AND DRAWINGS...........................................................22
PART II: STRUCTURAL DESIGN AND DRAWINGS.......................................................................23
Loadings and Analysis.........................................................................................................................23
PART III: MEASUREMENTS................................................................................................................52
PART V: BILL OF QUANTITY.............................................................................................................67
MATERIAL SCHEDULE.......................................................................................................................70
CONSTRUCTION METHODOLOGY AND PHASING.......................................................................71
ANTICIPATED PROGRAMME........................................................................................................71
INDICATIVE CONSTRUCTION PHASING....................................................................................71
WORK SCHEDULE...............................................................................................................................72
PAVEMENT AND DRAINAGE DESIGN.............................................................................................74
DATA ANALYSIS AND FINDINGS....................................................................................................78
RECOMMENDATIONS AND CONCLUSIONS..................................................................................79
CHAPTER FIVE:....................................................................................................................................80
SITE ORGANISATION AND ADMINISTRATION.............................................................................80
SITE ORGANISATION..........................................................................................................................80
Site layout and planning...........................................................................................................................81
SAFETY..............................................................................................................................................81
SITE ACCESSIBILIY.........................................................................................................................81
SECURITY..........................................................................................................................................81
INFORMATION SIGNS.....................................................................................................................81
OFFICES..............................................................................................................................................81
WATER SUPPLY AND SANITATION.............................................................................................81
STORAGE AND SITE CLEANING...................................................................................................82
REFERENCES............................................................................................................................................83
BIBLIOGRAPHY........................................................................................................................................84
CHAPTER ONE: INTRODUCTION
Background information
The site for the modern lecture halls will be situated at The Eldoret National Polytechnic. The project was
identified following the full transition of candidates who sat for KCSE to the tertiary institution which has
experienced huge influx in population.
The institution has few lecture halls that accommodate the population that it receives in every intake. With
the world pandemic that has adversely affected all sectors of the economy; the ministry of health came with
measure of re-opening the economy and learning institutions. With the guidelines given in social distancing,
this problem escalated even further thus need for creation of more lecture spaces.
The temporary solution of tents has helped in de-escalating the problem though it may not last for long since
the collage is expecting more population in future.
Solution to the problem
I saw it fit to bring on board a long-lasting solution to the problem which is the proposed construction of
modern lecture halls.
In my proposal the proposed project shall host 60 lecture halls that can accommodate about 3000 students.
This is long lasting solution to current problem.
Research questions
During my research is used the following methods:
1: Questionnaires
2: Interviews
3: Observation
From these methods of research, I concluded that, the lecture halls were few and could not accommodate the
current population and meet all the covid 19 regulations. The temporary use of tents as classes has solved
this problem by 25%.
The institution has adequate land to construct the proposed building with limited congestion. During my
research you could see how the student strained for classes and took some pictures.
PROJECT OBJECTIVES
4. To provide more and large lecture halls
6. To encourage institution to admit more learners and provide best technological knowledge.
CHAPTER TWO: LITERATURE REVIEW.
Reviews on similar projects and their usefulness
The current structures are in good state though they are overwhelmed with steadily growing population. The
institution has maintained a well culture of carrying out maintenance on the lecture hall when needed.
The currents lecture hall is small hence they can’t accommodate large classes since they we designed to
accommodate 45 learners. They have occupied large areas and they are not exceeding four stories.
The project proposal is the best for solving out problems to meet all needs required for good level of
education and job market skills demands. The proposed project will be constructed courtesy of donors
(European Union and US AID) and the ministry of education.
The proposed project shall occupy less area compared to the existing one and accommodate more students
and in large extent utilize the unlimited space in the atmosphere. It shall have seven stories with an
estimated population of 500 learners.
INTRODUCTION
Definition of surveying- is the act of determining the relative positions of points on, above, beneath the
surface of the earth with respect to each other by means of direct or indirect measurement of horizontal or
vertical distances, angles and directions. It’s conducted by a surveyor.
Since Grid method of taking survey points and coming up of contours is easy. It was picked since its
comprehensive considering availability of survey equipment which had to be shared in groups.
Survey procedures
a) Reconnaissance survey
b) Chain survey
c) Leveling
d) Contouring
Reconnaissance Survey
This is pre-visit to the site in order to identify and familiarize with the area. This activity was carried out on
the 19th of April 2021 by a team which I lead.
The activities carried out include;
i. Site selection
ii. Marking of obstacles
iii. Noting of obstacles
iv. Pre-existing features’ identification
v. Running the survey lines
vi. Taking notes
Site selection
The proposed site is located in Eldoret polytechnic. The site is clear with enough space for the construction
of modern lecture halls preparation of a reference sketch of the ground arrangement of lines, principle
features as shown below.
The proposed space where the structure is going to be built on half an acre land.
i. Marking of obstacles
Being selected as the team leader I lead my team to the site to be able to identify obstacles that might hinder
our process of survey work
v. Taking notes
I had to take notes on the procedures. The materials needed were;
Field book Pencil
Tape Hammers
Ranging rods Dumpy level
Staff
Problems encountered
Initial confusion due to unfamiliarity with the site
Unfavorable weather condition, hot sun all day long.
Inexperienced reading of the dumpy level.
Chain surveying
Linear measurements were taken by using a tape measure. A skeleton framework was made consisting of
number of lines forming regular shaped squares on the proposed site. The intervals between lines were 10m
and the whole proposed site was a 600m square.
Materials used include;
Tape measure Pangas
Hammers and mallets Ranging rods
Pegs
Leveling
The grids were established on the day of chaining. This was a 60m by 100m grid. They were marked using
wooden pegs. During leveling the dumpy level was used to take readings on the leveling staff taking
readings of each point on the grid. An assumed datum of 100.00m was used to calculate the reduced levels
of all 20 points surveyed.
Field levels were taken as follows;
A2 0.870 1199.528
A3 0.860 1199.538
A4 0.609 1199.789
A5 1.245 1199.153
B1 1.275 1199.272
B3 1.448 1198.779
B4 1.350 1198.877
B5 1.210 1199.017
B6 1.109 1199.118
C1 1.115 1199.112
CONTOURING
After reducing the levels of each of the grid points which is at the intersections, the levels were then put into
excel format in a systematic manner to help with coming up with the contours using AutoCAD which is a
computer software used in most civil engineering projects. I being competent and well conversant with
AutoCAD operation I came up with the contour lines without any difficulty.
PART II: SOIL MECHANICS
SOIL INVESTIGATION
This is aimed at determining the characteristics of the soil at the proposed site in order to carry out soil tests.
Samples are taken from various parts of the site in order to get the correct data to be used in design which is
carried out in the geo-technology laboratory. Soil sampling was done from different trial pits. These tools
were required:
Two spades
Tamping rod
Moisture bags
The following soil tests were conducted:
a) Plasticity Index
b) Moisture content test(proctor)
c) Bearing capacity test (CBR)
Plasticity index is the range of moisture content at which soil remain plastic (moldable) condition.
PI = LL - PL
Plastic Index PI = LL - PL
Plasticity Modulus PM = PI × % passing 0.425mm sieve
Plasticity Product PP = PI × % passing 0.075mm sieve
Liquid Index LI = (w-PL)/LL -PL
Where w=the natural moisture content.
Plastic Index
Plastic index is the minimum moisture content that changes from solid (dry state) to plastic (moldable) state.
It is determined as the moisture content which allows soil sample to be molded into a loop that cracks when
its diameter is about 3mm.
Test procedure
1. Sieve the air-dried soil on 0.425mm sieve to obtain 200g and take about 20g of the material for the test.
Reserve the remaining amount of sample for liquid limit test.
2. Place the sample on a glass plate and mix thoroughly with distilled water using a spatula.
3. Mold a ball between the fingers and then roll it between the palms of the hands until a slight crack
appears on the surface.
4. Form the thread of about 6mm between the first finger and the thumb.
5. Roll the thread between tips of the finger and the glass plate until it cracks
6. Collect broken pieces of the thread into two containers and determine the moisture content.
Apparatus
Mixing plate
Procedure
MOULD NO
Tin no TA TB TC TD TE
Weight of wet soil+ tin (g) 51.1 102.1 87.0 68.6 80.6
Weight of dry soil+ tin (g) 47.0 82.5 76.3 60.2 69.7
Apparatus
Swell disc
Procedure
Using the obtained proctor results, weigh the dry sample and measure the amount of water then mix
to obtain a wet material.
Take a portion of the wet material for moisture content determination.
From the proctor result calculations, weigh the required wet material to be mound.
-For dynamic method, three molds are used placing the material in three layers, compacting each
layer with 62 blows for the first mound, 25blows for the second and 10 blows for the last mound.
-in static method, the wet material is placed in CBR mound then using a jack, the material is
compressed in the mound.
Placing a swell disc on top of the mound, the initial swell readings are taken.
Place the mound in water for 4 days in case of neat material.
After soaking, the final swell readings are taken.
The mound is left to drain then placed on CBR penetration machine penetrating the top and bottom.
The penetration readings are taken at intervals of 0.25 up to 5.00.
To obtain the strength, the values at 2.50mm and 5.00mm are multiplied by the ring factor for both the top
and bottom then averaged.
CHAPTER FOUR: DATA ANALYSIS, FINDINGS AND RECOMMENDATIONS
DISCUSSIONS
The structural analysis of the proposed construction was undertaken with focus on the design of the basic
structural elements involved which are; beams, columns, slabs, retaining walls and ramps. These were
designed to support the various loads involved.
Challenges were faced in coming up with the optimum story building both in term of static and dynamic
capacity. The overall economic design of the building was also a challenge, considering member sizing and
location.
INTRODUCTION
The proposed learning units design is intended to provide and enhance learning standard within the
institution, this will ensure proper use of available spaces other than congestion in the available classes. The
design matches the available structures hence the aesthetic outlook is put into consideration. The building
will be equipped with modern security system, fire alarm and 24hrs surveillance to enhance its efficiency.
FEASIBILITY STUDY
The client having factored the availability of space, have seen it wise have seen it wise to do the project
within the plot. The resources shall be sourced from the government through the ministry of Education and
other donors and well-wishers. This resource shall be consolidated and project awarded to a suitable
contractor for construction.
RELEVANCY OF MY DESIGN
My design has factored in limit state design ensuring all the members are within the factors of safety. The
limit state design method is considered as an ideal method of design as it includes the structural safety of
structure against collapse as well as serviceability. The design beings from the foundation to the roof, un-
aliasing the soil condition, loading, the kind of material to be considered and carrying out various test to
ascertain the efficiency of the design. The proposed design factors in the modern technology, that’s precast
elements, steel technology and modern security system.
This section includes floor plan, section, elevations, and site plan
PART II: STRUCTURAL DESIGN AND DRAWINGS
It includes foundation layout, bases, columns, beams, slab and roof
LIST OF TABLES
Number of bars
Diameter Mass 1 2 3 4 5 6 7 8 9 10
Mm Kg/m
8 0.395 50 101 151 201 252 302 352 402 453 502
10 0.617 79 157 236 314 393 471 550 628 707 785
12 0.888 113 226 339 452 565 678 791 904 1017 1130
16 1.58 201 402 603 804 1005 1206 1407 1608 1809 2010
20 2.47 314 628 942 1256 1570 1884 2198 2512 2826 3140
25 3.86 491 938 1474 1966 2457 2948 3439 3932 4423 4915
32 6.31 804 1608 2412 3216 4020 4824 5628 6432 7236 8040
40 9.87 1257 2513 3770 5027 6283 7540 8796 10053 11310 12566
Table 3.19 — Values of _ for braced columns
1 2 3
1 2 3
3 1.6 1.8 -
4 2.2 - -
2023
ELEMENT: COLUMN C1
SHEET NO.
BY: ERIC OYOMO
DESIGN OF COLUMNS C1
600 x 300mm
600 x 300mm
Procedures
Fcu=40N/mm²
Fy=500N/mm²
End condition at the bottom of the column for the x-x axis = 3
x y
Le and 6 < if the column is short
h h
β=0.9
x 2700
Le = = 6.8
h 400
6.8 < 15
3.13
6 y 2850
= = 7.1
h 400
= 7.1 < 15
N = LxWxDXH
14(180000-Asc) + 350Asc
336Asc= 1380000
LINKS
Provide 6 Y32 at
Spacing of links should be ≤ (12x shortest diameter) Asc 6432mm²
= (12x32) = 384mm
3.12:7.1
NUMBER OF LINKS
2400/390= 6.1
BASE B
Fcu=40N/mm²
Fy=500N/mm²
1200+1000= 2200KN
N=2200KN
Area of base
12.941/2 = 3.6m
Adopt 4m by 4m footing
2200/16= 137.5mm
Adopt h= 600mm
H= 600mm
Self-weight
24×0.6×16= 230.4
24×0.6×3.62=186.624
DESIGN LOAD
2430.4÷16=151.9KN/m2
M˂S.B.P
EFFECTIVE DEPTH
151.9 KN/M2
H
d
d= 600-( 35+32/2+32)
d= 515mm
2.37≤4.73
It’s ok in thickness
4000
d=512mm
COLUM
N
4000
600×3
00
Vc= 2.39
1850×151.9×925×10-6= 259.94
1700×151.9×850×10-6= 219.50
Tensile members
K1= 0.028
K2=0.024
DESIGN OF BEAMS
Bottom 1 Z2=486.4
Bottom 2
1228.54mm2
Provide Y32 @ 250mm300mm
Characteristic
NUMBER load due to self-weight of the slab
OF BARS
As B2=
0.2x50x24= 240kN/m
1+(4000÷250) = 17 1037.41mm2
Characteristic
Provide 17 Y32 load due toofself-weight
spacing @250mm of the rib
0.3x0.65x24= 4.68kN/m
12x50= 60 kN/m
NATIONAL POLYTECHNIC
Design loading
G.K.= 120KN
Q.K= 65KN
=(1.4gk) + (1.6Qk)
=(1.4x120) + (1.6x65)
table 2.1 Use this table to determine bending moment and shear force near middle
of end span.
= 0.4x272 = 108.8 kN
POLYTECHNIC
Checklist
i. Site clearance
ii. Excavation of the top soil.
iii. Trench excavation
iv. Base excavation
v. De-watering
vi. Planking and strutting
vii. Concrete blinding in bases
viii. Concrete blinding in trenches
ix. Concrete to bases
x. Form work to column
xi. Concrete to column
xii. Foundation walling
xiii. Hardcore filling
xiv. Marram blinding
xv. DPM
xvi. BRC
xvii. Form work to slab
xviii. Rendering to plinth
xix. Concrete to slab
xx. DPC
SITE CLEARANCE
LENGTH WIDTH
49200mm 29100mm
4000mm 4000mm
51200mm 33100mm
1751.04m2
Clear site of all bushes, scrubs and burn them or carry
away from site
51.2
46200mm
30100mm
LENGTH WIDTH
46200mm 30100mm
2/1000 2/1000
47200mm 31100mm
Deduct void
29425mm 15000mm
47.2 Deduct void
13600mm 9900mm
31.1
Excavate over site to remove top vegetable soil to an
29.425 average depth of 175mm and store on site in hips
75/ 4.0
2.1
&
3
300m
Cast concrete blinding in bases to an average depth of
35mm. concrete ratio of 1:4:8
0.25
28.35m3
FORM WORK TO COLUMN
1.8
WIDTH HEIGHT
75/ 2.0
1800mm 2000mm
Provide firm formwork to columns to rest on bases and
adequately supported.
0.6
2.1
654.71
Cast concrete of mix 1:2:4 to columns and adequately
vibrated
0.7
75/ 3.7
3.4
CONCRETE BLINDING TO TRENCHES
1.0 &
0.45
BACK FILLING
1.45 To bases
To trench
41.6
12.3
HARDCORE LAYING
LENGTH WIDTH
41600mm 7000mm
add
26000mm 9500mm
add
31475mm 12300mm
203.15
45.2
7.9
&
10.4
Lay marram blinding to an average depth of 50 mm,
27.425 leveled, adequately compacted and treated using
approved insecticides.
8.2
LAYING B.R.C
&
LENGTH WIDTH
203150mm 300mm
LENGTH WIDTH
45200mm 7900mm
add
27200mm 10400mm
add
27425mm 8200mm
DPC
PART IV: BUILDING UP RATES
FINAL TRADE PROJECT
Assume it takes 40 minutes to dip efficiency of the lorry 100% works for
8hrs a day
Hiring cost
1550x8 = 12400
Fuel
4000 00
8 per hour = (8x8x112) = 7616
Skilled labor 2448 00
(65.4x53.0x3.5) = 12131.7m³
125
Add bulking factor ( × 12131.7) = 15164.625
100
1hr = 45m³
8hr =?
1 day = 360m³
= 15163.625m³
42 days to dip all the excavated soil
1 day = 7,248
30 days =?
= 217440
= 268
304,416 00
Assume
Price build up
a. Plant
b. Labor
Cost 1m³ = 2(50+30) = 160
25
Add ×1160 = 290
100
Add
Hence, the unit rate of extra over foundation trench excavation for
excavating in rock at Kshs 1368.25 1000 00
Assumption
160 00
1. Concrete is mixed on site using 10/7 mixer 290 00
2. Concrete is transported in wheelbarrows
3. Prices:
a) mixer hire is 800 per hour
b) cement Kshs is 750/50 Kg bag
c) vibrator hire Kshs 250 per hour
d) sand Kshs 1600 per m³ c/f1450 00
e) ballast Kshs 1000 per m³
f) labor Kshs 50 per hour for unskilled labor
81 75
Price build up (m³)
1. Materials
a) Cement
i. Density of cement is 1442kg/m³
ii. Loading 1m³ of cement per hour 1368 25
cost
Cost of cement per m³ = × density
mass
750
= ×1442=21630
50
b) Sand
c) Ballast
40
Allow 40% consolidation = ×28880=11552
100
5
Allow 5% for wastes = × 40432=2021.60
100
21630 00
2. Plant
50 00
3200 00
1hr = 2.4m³ = 800
= 1m³=?
1× 800
=333.33
2.4
1 m³ =?
1× 250
=104.20 28880 00
2.4
3. Labor 11552 . 00
40432 00
Assume that - charger = 2
- wheelers = 6
2021 . 60
- spreaders = 2
42453 60
10
500
Cost per m³ = =208.33
2.4
333 33
437 53
HARDCORE
Assumptions
Item A
Materials
208 . 33
4000
Cost 1m³ = =800 645 86
5
807 33
25
× 800=200
100
5
Allow 5% waste = ×1000=50
100
1m³ = 1050
9m³ =?
9
× 1050=9450 1hr = Kshs 9450
1
Item B
Labor 800 00
72m³ = Kshs 50
9m³ =?
9 200 . 00
×50=6.25
72
1000 00
50 . 00
30
×6.25=1.88 1050 00
100
9450 00
6 25
1. 88
9458 13
BLOCK
ESTIMATOR: ERIC OYOMO PAPER NO: 3082
POLYTECHNIC
T Y
SUBSTRUCTURE WORKS
A Clear site of all bushes, shrubs and trees girth not M2 1200
exceeding 600mm, grub out root’s stamps and
dispose.
B M2 1400
directed.
M2 120
C
Allow to keeping excavations free from storm and
underground waters
M3 14550
M2 2800
E Reinforcements
F M2 1800
Formwork
G M2 2100
Hardcore filling
H M2 1455
I Marram blinding M2 1940
backfilling
MATERIAL SCHEDULE
MATERIAL UNIT QUANTITY COST PER UNIT
ANTICIPATED PROGRAMME
The construction of the proposed development is anticipated to start from with subject to gaining planning
permission and span approximately 3yrs. Following the discharge of pre-commencement planning
conditions and period of procurement and tendering for the construction of the development, project
mobilization and construction activities.
Set up site 4
Substructures works 14
Roofing 21
Superstructure 40
Fit out 44
Installations services 12
Drainage connection 8
No demolition is required to facilitate the construction of the development. The main construction
WORK SCHEDULE
PROPOSED CONSTRUCTION OF MODERN TUITION BLOCK FOR ELDORET NATIONAL
POLYTECHNIC
WORK DURATION
W WK WK WK WK WK WK WK WK WK1 WK WK WK WK WK WK WK
K1 2 3 4 5 6 7 8 9 0 11 12 13 14 15 16 17
FOUNDATIO
N
EXCAVATIO
N
STEEL
FIXING TO
FOUNDATIO
N
CONCRETE
TO
FOUNDATIO
N
FORMWOR
K TO
COLUMNS
CONCRETIN
G COLUMNS
FOUNDATIO
N WALLING
BACK
FILLING TO
FOUNDATIO
N
HARD CORE
LAYING
MARRUM
BLINDING
FORM
WORK TO
SLAB
CONTRETE
TO SLAB
STEEL
FIXING TO
COLUMNS
FORMWOR
K TO
COLUMNS
FORM
WORK TO
SOFITS
STEEL
FIXING
FIRST
FLOOR
CASTING
CONCRETE
TO SLAB
STEEL
FIXING TO
COLUMN
GHANTT CHART
CRITICAL PATH ANALYSIS.
PART VI: PAVEMENT AND DRAINAGE DESIGN
PAVEMENT DESIGN
The pavement design of the access roads to building by vehicles and by foot. Pavement design is done
according to road design manual part III (materials and pavement design for new roads)
Design factors
Climatic factors
Traffic
Drainage
CBR tests
Materials
The results obtained testing soil from the proposed site gave a CBR value ranging from 7-13.
The table below shows the soil classification and the soil of the proposed site fall under S³ with a medium of
10.
According to the road design manual part III, the subgrade needs to be improved. The grade will be
improved by material of a subgrade class S₄ in order to increase the bearing capacity.
The road will give the standard pavement structure type 1 as defined by the Road Design Manual Part III.
Materials requirements
1. Sub-base
Sub-base is 200mm thick natural gravel.
Materials requirements
Materials shall have a CBR at 95% MDD (Modified AASHTO) CBR of 30% after four days of dry soak.
From chart SB₁ of the road design manual, part III, the following are the recommendations and the natural
gravel.
Materials requirements
DRAINAGE WORK
The main aim of the drainage pattern in the proposed site is to ensure that the rain water and surface water is
removed from the site so that it cannot affect the compound in general.
There is an existing drainage system in the college compound which collects all the rain water which is
directed to drainage along the main pavement towards the main gate. The drainage gently slopes hence
water moves by use of gravity. The new structure won’t require much drainage since all the rain water
collected from the roof will be channeled to the underground water tank. The pavement runaway water will
be channeled to the existing drainage system.
The principle used was the wetted perimeter: maximum discharge depends on the wetted perimeter, given
the coefficient of roughness and slope.
Manning’ Roughness Coefficient
Metals 0.010-0.024
Glass 0.009-0.013
Concrete 0.011-0.017
Wood 0.012-0,016
Clay 0.013-0.016
Grave 0.020-0.033
The architectural designs and drawings consumed most of my time and also gave me the expertise unto
which I am to be pursuing during my professionalism. Measurements, estimation and costing proved that
the rate of buying materials is rising steadily and that is the key reason as to why the rate of improving the
infrastructure in Kenya is still slow.
RECOMMENDATIONS AND CONCLUSIONS
Design of the learning facility was undertaken satisfactorily in accordance with BS 8110. It is recommended
that to further improve on the output, investigation should be done on the most economic choice of material,
member sizes and general layout.
The Kenyan government through the ministry of education should ensure that the quality of training is
meeting the required competence for skilled personnel to acquire tedious and complex design skills.
CHAPTER FIVE:
SITE ORGANISATION AND ADMINISTRATION
Introduction
The site organization and administration are per the project direction and guidelines
Site work plan and material storage, the site space has to be able to accommodate office, material
storage, working areas and general circulation areas.
SITE ORGANISATION
Director / CEO
Operations Finance
Project
t Mmanager
s
Building & civil Eng. sor Telecom & Electro Works TradingServices
Increase in productivity
Safety
Save space in areas needed for temporary construction
Maximizing utilization
The following key areas should be considered in layout
SAFETY
Fire prevention; fire extinguishers should be installed on the site immediately on the site as
construction commences.
Medical services; first aid kit is very important and should be kept in safety office to be used in case
of an emergency.
Construction safety gear; the contactor who will be the best bidder and given a contract should
ensure that he supplies his employees at the construction site with basic site attire. This includes the
safety boots, hard hat (helmet), gloves, goggles and the ear muffs.
SITE ACCESSIBILIY
Easy accessibility will help keep the equipment operators and vehicle drivers’ morale high, minimize
the chances of accidents saves time when maneuvering and leaving the site. Therefore, should be
located adjacent to flexible pavement.
SECURITY
Entrance; the entrance guard should be provided with a booth to keep track of all visitors going into
the site.
Lighting; electrical installation should be done immediately as construction commences to avoid
accidents and maintain lighting.
Fencing; hoarding should be done all round the site to prevent unwanted access and for the safety of
anyone passing near the site.
INFORMATION SIGNS
Site map; site details of the project should be placed at the polytechnic entrances.
Traffic regulatory signs; this should be displayed to guide traffic on site and to avoid accidents to
considerable extents.
OFFICES
The offices should be close together, close to the site and in safe area. These offices include; job
office, general contractor office, sub contactors office and clerk of works office.
Alberta Environment. (n.d.). Construction & demolition waste reduction program. Retrieved
from http://environment.alberta.ca/documents/Construction-Demolition-programbackgrounder.pdf
Agamuthu, P. (2008). Challenges in sustainable management of construction and demolition
waste. Waste Management Resources, 26, 491. American Plastics Council. (1997). Vinyl
siding recycling: A how-to guide. Retrieved from
http://www.p2pays.org/ref/04/03185.pdf
Armstrong World Industries. (2011). Recycling program- overview. Retrieved from
http://www.armstrong.com/commceilingsna/article45691.html
assessing the Potential of Plastics Recycling in the Construction and Demolition Activities
(APPRICOD). (2004). Guide: Towards sustainable plastic construction and demolition
waste management in Europe. Retrieved from
http://ec.europa.eu/environment/life/themes/waste/documents/guide_appricod.pdf
Barker, A.V. & Bryson, G.M. (2002). Bioremediation of heavy metals and organic toxicants by
composting. Scientific World Journal, 2, 407–420.
Bio Cycle (2007). Regional roundup. Bio cycle 48 (4), 14-18.
James, P. R., Pell, E., Sweeney, C. & St John-Cox, C. (2006). Review of plasterboard material
flows and barriers to greater use of recycled plasterboard. Oxon, UK: Waste & Resources
Action Programme.
Merino, M. R., Gracia, P. I. & Azevedo, I. S. W. (2010). Sustainable construction: construction
and demolition waste reconsidered. Waste Management & Research, 28, 118–129.
Recycling Council of Ontario. (2006). let’s climb another molehill, an examination of
construction, demolition and renovation (CRD) waste diversion in Canada and associated
greenhouse gas emission impacts. Retrieved from http://www.nrcan.gc.ca/smmmms/busi-indu/rad-rad/pdf/f-
molehill-r-eng.pdf
BIBLIOGRAPHY
During my research about this project, I visited various places from where I acquired different information
about the design and construction which included the Ministry of public works and transport, planning
housing for the building codes of practice. After then I thoroughly go through various books in the college
library for the construction and design purposes. This includes the following;