The document provides a detailed status report on the construction of ongoing substations with a voltage rating of 220 kV and above as of August 31, 2011. It includes information on various substations across different regions, their capacities, progress percentages, land acquisition status, and anticipated commissioning dates. Key challenges such as delays in land acquisition and threats from extremism are noted, impacting the completion timelines of several projects.

Uploaded by

Ashish Gaurav
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
130 views27 pages

Aug 11

The document provides a detailed status report on the construction of ongoing substations with a voltage rating of 220 kV and above as of August 31, 2011. It includes information on various substations across different regions, their capacities, progress percentages, land acquisition status, and anticipated commissioning dates. Key challenges such as delays in land acquisition and threats from extremism are noted, impacting the completion timelines of several projects.

Uploaded by

Ashish Gaurav
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 27

STATUS OF CONSTRUCTION OF ONGOING SUB-STATIONS (220 KV and above)

As on 31.08.2011 Sl. No. Name of the Sub-Station Voltage ratio (kV/kV) Capacity MW/MVA Date of Award Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, completed station sub station eqpt.received eqpt.erected 7 8 9 Transf. received/ erected/ tested 10 Commissioning Original Target Date 11 Actual/ Now Anticipated date 12 13 Remarks

765/400kV Substations

(a) Central Sector


1 Common Scheme for 765kV pooling Station and Network Associated with DVC & Maithon RB Project and import by NR & WR via ER a Gaya 765/400 3x1500 Aug-08

70%

68%

45%

Trf. received.

Aug-12

Mar-12

Efforts being made to complete the sub station earlier. Threats from Maoist extremis is hampering progress * To be accomodated in the existing HVDC station. Efforts being made to complete progressively from Dec'11 matching with associate line completion. Engg., civil works & erection under progress. Engg., civil works & erection under progress.

b Sasaram

765/400

2x1500

UA

Aug-12

Aug-12

c Fatehpur d Lucknow

765/400 765/400

2x1500 2x1500

A A

70% 75%

80% 85%

50% 75%

Trf. received. Erection in progress.

Aug-12 Aug-12

Mar-12 Mar-12

e Ranchi

765/400

2x1500

25%

Aug-12

Aug-12

Completion likely to be delayed. Land acquired in May'11. Engg. & supply under progress. Engg., civil works & erection under progress. Engg., civil works & erection under progress. Completion affected due to delay in land acquisation.

f 400 kV Balia Aug. to 765 kV g 400 kV Agra Aug. to 765 kV

2x1500 2x1500

A A

75% 55%

85% 75%

65% 35%

Trf. received.

Aug-12 Aug-12

Dec-11 Aug-12

Transmission System of Vindhyachal-IV and Rihand III (1000MW each) Gen. Proj. a Vindhyachal Pooling station 765/400 2x1500

Mar-10 Nov-12 Award placed in Feb'11.. Completion affected due to land acquisation.

pspm(cea)

Sub Stns 1 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 8 9 Transf. received/ erected/ tested 10

Commissioning Original Target Date 11 Actual/ Now Anticipated date 12

Remarks

1 3

5 Dec-10

13

Transmission System for Phase-I Generation Projects in ORISSA - Part - B. a Jabalpur Pooling station 765/400 2x1500

Dec-13

Award placed. In july'2011.

Northern Region
4 765KV System for Central Part of Northern Grid PART-II a Jhatikara b Meerut (Aug.) c Moga (Aug.) 765/400 765/400 765/400 4x1500 2x1500 2x1500 Jul-09 A A A 50% 50% 50% 60% 50% 30% 30% 15% 5% Jan-12 Jan-12 Jan-12 Award placed in Sep'09. Engg. civil works & erection in progress. Engg. & civil works under progress. Award placed in Nov'09. Engg. & civil works under progress.

5 765KV System for Central Part of Northern Grid PART-III a Bhiwani 765/400 2x1500 A 1% May-12 Award placed in Dec'09. Engg. in progress. Delay in commencement of works due to now availability of S/S land. Now part land handed over & work being started. Completion to be delayed.

Northern Regional System Strengthening Scheme - XXI a Bareilly (with 125 MVAR Reactor) 765/400 2x1500

Aug-10 UA Apr-13 Award under progress.

Western Region
7 Trans. System associated with Mundra Ultra Mega Power Project a Wardha 8 765/400 3x1500 Oct-08 Jul-09 A 90% 45% 30% Oct-12 Oct-12 Engg., supply & civil works under progress.

Trans. System associated with Sasan Ultra Mega Power Project Part-A- Tr. System of Sasan(4000) UMPP

pspm(cea)

Sub Stns 2 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 90% 8 86% 9 27% Transf. received/ erected/ tested 10

Commissioning Original Target Date 11 Dec-12 Actual/ Now Anticipated date 12 Jun-13

Remarks

1 a Satna

3 765/400

4 2x1000

6 A

13 Engg., supply & civil works under progress.

Part-B- Regional System Strengthening in WR for Sasan a Indore b Bina c Gwalior 9 765/400 765/400 765/400 2x1500 2x1000 2x1500 Feb-09 2x1500 Feb-09 1x1500 A 20% 25% 10% Feb-12 Feb-12 Civil work & supply under progress. A 80% 40% 25% Feb-12 Feb-12 Engg., civil works & erection in progress. A A A 5% 44% 5% 82% 35% Dec-12 Dec-12 Dec-12 Dec-12 Dec-12 Dec-12 Award placed in Aug'10. Civil work under progress. Engg., supply & civil works under progress. Award placed in Aug'10.Civil work under progress.

Western Region System Strengthening-X a WR Pooling Station near Sipat 765/400

10 Western Region System Strengthening-XI a WR Pooling Station near Sipat (3rd ICT) 765/400

11 Establishment of Pooling Station at Raigarh (Korba) and Raipur for IPP Gen. Proj. in Chhatisgsrh a Raigarh Pooling Station b Raipur Pooling Station 765/400 765/400 4x1500 1x1500 May-11 Aug-13 Aug-13 Aug-13 Aug-13 Award under progress. Award under progress.

12 Establishment of Pooling Station at Champa and Raigarh (near Tamnar) for IPP Gen. Proj. in Chhatisgsrh - B a Champa Pooling Station b Raigarh Pooling Station (near Tamnar) 765/400 765/400

6x1500 3x1500

May-14 May-14

Award under progress. Award under progress.

Eastern Region
13 Transmission System for Phase-I Generation Projects in ORISSA - Part - A. a Jharsuguda Pooling Station b Angul Pooling Station 765/400 765/400 2x1500 4x1500 Sep-10

UA UA

Mar-13 Mar-13

Award placed in Mar'11. * Land acquisation critical. Award placed in Mar'11. * Land acquisation critical.

pspm(cea)

Sub Stns 3 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 8 9 Transf. received/ erected/ tested 10

Commissioning Original Target Date 11 Actual/ Now Anticipated date 12

Remarks

13

(b) State Sector


UTTAR PRADESH (UPPCL) : 1 Unnao 765/400 2x1000 50% 85% Mar-11 Oct-11 LOI issued on 23.01.2010.Work awarded to M/s Crompton Greaves. Soil testing completed. 3 one phase transformers received.Overall 65% work completed. Control room completed. Soil investigation completed. Work in progress Proposed under PPP mode.

2 Anpara D 3 Mainpuri

765/400 765/400

2x600+ 1000 2x1000

50%

Mar-11 May-12

Mar-12 May-12

400/220kV Substations

(a) Central Sector


1 Supplementary Transmission system Associated with DVC & Maithon Right Bank Project a Fatehpur Extn. b Gaya Extn. 400/220 400/220 2x315 2x315 Aug-08

A A

75%

75%

50%

one Trf. received.

Aug-12 Aug-12

Dec-11 Mar-12

Engg. ,civil works & erection in progress * Being constructed under DVC (main) project. Award placed in Aug'09.

2 Part-A : North East - Northern/ Western


Interconnector -I

Feb-09 2x200 UA Aug-13 Sep-14 Award placed in Mar'11.Completion affected due to delayed in award (ant. in Mar'14) Completion matching with Gen.

a Biswanath Chariyali Pooling


Station

400/132

b Aug. of 400KV Agra S/Stn.

400/220

4x105

Aug-13

Aug-13

3 North East - NR/WR Inter - connector (Subansiri &


Kameng)

a Misa (2nd ICT)

400/220

315

10%

5%

Feb-13

Dec-11

Awarded. Engg. & civil work in progres. Transformer supply anticipated by Sep./Oct'11.

NORTHERN REGION

pspm(cea)

Sub Stns 4 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 8 9 Transf. received/ erected/ tested 10

Commissioning Original Target Date 11 Actual/ Now Anticipated date 12

Remarks

1 4

5 Sep-07

13

Eastablishment of 400/220 kV GIS Pooling Station near Chamera-II HEP 400/220 630

a* Part-I, GIS Pooling Station near Chamera-II HEP 5

A Feb-09 A

100%

100%

100%

Erected

Mar-10

Aug-11

Ready for commissioning 8/11.

Northern Region System Strengthening Scheme - XV a Neemrana 400/220 2x315

40%

55%

10%

Nov-11

Feb-12

Engg. & civil works under progress. Completion affectted due to delay in land acquisation. Engg. in progress. Completion delayed due to land acquisation (ant. in Dec'12).

b Kotputli

400/220

2x315

UA

Nov-11

Dec-12

Northern Region System Strengthening Scheme - XVIII a Dehradun 400/220 2x315

Feb-09

UA

Nov-11

Dec-12

Engg. in progress. Completion delayed due to land acquisation (ant. in Mar'13).

Northern Region System Strengthening Scheme - XIX a Bagpat (GIS) 400/220 2x500

Feb-09 UA Feb-12 Dec-12 Engg. in progress. Completion delayed due to land acquisation (ant. in Mar'13).

Northern Region System Strengthening Scheme - XIII a Manesar (GIS) 400/220 2x500

Feb-09 A 30% 20% Nov-11 Mar-12 Engg. & civil works under progress. Completion matching with line.

Northern Region System Strengthening-XIV a Extn. Patiala (1x500) b Extn. Malerkotla (1x500) 400/220 400/220 500 500

Feb-09 A 100% 100% 100% Erected Aug-11 Jul-11 Transformer Test Charged 7/11 Commissioned 3/11

10 765KV System for Central Part of Northern Grid - Nov-09 PART-III

pspm(cea)

Sub Stns 5 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 1% 8 9 Transf. received/ erected/ tested 10

Commissioning Original Target Date 11 Actual/ Now Anticipated date 12 May-12

Remarks

1 a Bhiwani

3 400/220

4 2x315

6 Part land acquired

13 Award placed in Dec'09. Engg. in progress. Delay in commencement of works due to now availability of S/S land. Now part land handed over & work being started. Completion expected by Mar'13.

11 System Strengthening in Northern Region for SASAN & MUNDRA (UMPP) a Sikar b Panchkula 400/220 400/220 2x315 2x315

Dec-09 A A Dec-09 1x500 1x500 Mar-10 A A 45% 70% 40% 70% 25% Dec-11 Dec-11 Award placed in Mar'10.Engg. & civil works under progress. Award placed in Mar'10. Engg. & civil works under progress. 60% 50% 60% 50% 30% Aug-12 Aug-12 Award placed in Mar'10. Civil works under progress. Award placed in Mar'10. Engg. in progress. Civil works under progress.

12 Northern Region System Strengthening-XXIII a Extn. Bahadurgarh b Extn. Lucknow 13 Northern Region Transmission Strengthening Scheme a Sohawal b Shahajanpur 400/220 400/220 2x315 2x315 400/220 400/220

A A

15% 8%

20% 10%

Nov-12 Nov-12

Award placed in Aug'10. Engg., supply & civil works under progress. Award placed in Aug'10. Engg., supply & civil works under progress.

c Saharanpur d Jind

400/220 400/220

2x315 2x315

A UA

Nov-12 Mar-13

Award placed in Nov'10 Tendering under progress. Land acquiation delayed . Renotification Section-4 again issue in June'11.Section -6 awaited. Engg. & civil works under progress. Award placed in Nov'10. Engg., supply & civil works under progress.

e Jaipur (South) f Bhiwadi Extn.

400/220 400/220

2x500 1x315

A A

10% 5%

20% 10%

Nov-12 Mar-13

pspm(cea)

Sub Stns 6 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 8 9 Transf. received/ erected/ tested 10

Commissioning Original Target Date 11 Actual/ Now Anticipated date 12

Remarks

5 Jul-10

13

14 Northern Regional System Strengthening Scheme - XVI a Wanpoh 400/220 2x315

Jul-13

Award placed in July'10. Engg. in progress. Civil works commenced.

15 Northern Regional System Strengthening Scheme - XX a Hamirpur GIS (with 80 MVAR B. Reactor) 400/220 2x315

Aug-10 UA Mar-13 Award placed in Nov'10. Engg. in progress. Land acqusition to be expedited.

16 Northern Regional System Strengthening Scheme - XXII a Samba (with 80 MVAR B. Reactor) WESTERN REGION 17 Western Region System Strengthening-V a Navi Mumbai (GIS) 400/220 630 400/220 2x315

Dec-10 UA Aug-13 Award placed in May'11. Land acquisation to be expedited. Sec.-6 done in April'11.

Dec-07 A 100% 98% 85% Trf. received. Sep-10 Mar-13


Engg., supply, civil works & erection under progress. Sub station to be completed matching with commissioning associated line.

18 WESTERN REGION Strengthening Scheme-VI a Wardha Extn. b Pune Extn. *c Raipur Extn. 400/220 400/220 400/220 315 315 315

Feb-08 A A A Apr-08 630 A


completed completed completed

95% 95%
completed

95% 95%
completed

95% 98%
completed completed

Nov-10 Nov-10 Nov-10

Dec-11 Dec-11 Jun-11

Supply & erection under progress. Supply & erection under progress. Test Charged 6/11.

19 WESTERN REGION Strengthening Scheme-IX a* Shujalpur 400/220

50%

Jan-11

Oct-11

Sub station charged (without ICT) alongwith LILO line in May'11. ICT-I test charged & ready for commissioning in Jun'11. Balance works under progress.

20 Transmission System Associated with Mundra Ultra Mega Power Project


pspm(cea)

Oct-08

Sub Stns 7 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7
100%

Commissioning Transf. received/ erected/ tested 10


100%

Remarks

Original Target Date 11 Oct-12 Oct-12 Oct-12

Actual/ Now Anticipated date 12 Aug-11 Mar-12 Oct-12 13 Ready for commissioning 8/11. Award placed in July'09. Engg. & civil works under progress. Tendering under progress.

1 a* Bachchau b Navsari GIS c Aurangabad

3 400/220 400/220 400/220

4 630 630 630

6 A A UA

8
100%

9
100%

20%

80%

20%

80%

SOUTHERN REGION 21 Kaiga 3 & 4 Trans. System a Kozhikode S/Stn. (2x315) 400/220 630 Mar-05 A
100% 100% 100%

95%

Dec-07

Mar-13

Civil work completed & erection under progress. Completion matching with line.

22 Kundankulam - APP Transmission System (Balance portion) a Muvattapuzha ( 2nd Trf.) 23 System Strenghthening -XI of SR a Chulliar (Palakkad)

Mar-05

400/220

315 Mar-09

100%

100%

90%

80%

Nov-08

Mar-12

* Completion matching with line.

400/220

2x315 Dec-09 2x500

60%

80%

20%

Trf. received.

Jul-11

Feb-12

Civil works & erection under progress.

24 System Strengthening - X of SR GRID a Bidadi (GIS) 400/220

80%

90%

15%

Mar-12

Award placed in Dec'09. Engg.,supply, civil works & erection under progress.

25 System Strengthening - XII of SR a Yelahanka (GIS) 400/220 2x500

Feb-10 A 40% 30% 2% Jun-12 Supply & Civil works under progress.

EASTERN REGION 26 Transmission System for Transfer of Power from Generation Project in SIKKIM to NR/WR Part - A. a Kishanganj 400/220 2x315 May-10

UA

Jan-13

Award placed in Jun'10. Engg. in progress.* Land acquisation critical.

pspm(cea)

Sub Stns 8 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 8 9 Transf. received/ erected/ tested 10

Commissioning Original Target Date 11 Actual/ Now Anticipated date 12

Remarks

5 Jul-10

13

27 Eastern Region Strengthening Scheme - III a Daltonganj 400/220 2x315

UA

Nov-12

Tendering under progress. Completion likely to be delayed (ant. in Mar13). Land yet to be acquired. Award placed in July'10. Engg. in progress. Civil work commenced. Award placed in July'10.Engg. In progress. Tendering under progress. Completion likely to be delayed (ant. in Mar13). Land yet to be acquired. Tendering under progress. Completion likely to be delayed (ant. in Mar13). Land yet to be acquired. Award placed in Feb'11.Engg. In progress. Award placed in Feb'11.Engg. In progress.

b Bolangir c Kenonjhar d Chaibasa

400/220 400/220 400/220

2x315 2x315 2x315

A A UA

8%

5%

Nov-12 Nov-12 Nov-12

e Uttara

400/220

2x315

UA

Nov-12

f Lakhisarai

400/132

2x200

UA

Nov-12

g Banka

400/132

2x200 Mar-11

Nov-12

28 Transmission System for Transfer of Power from Generation Project in SIKKIM to NR/WR Part - B. a Rangpo (GIS) 400/220/ 132KV 16x105 3x100

UA Feb-10

Nov-13

Tendering under progress.

29 Transmission System associated with Pallatana gas Based Power Project and Bongaigaon Thermal Power Station (BTPS) a Silchar (New) (b) STATE SECTOR (SS) 400/220 2x200

40%

Mar-12

Work under progress.

NORTHERN REGION (NR) : DELHI (DTL) 1 Harsh Vihar GIS 400/220 315 Dec-11 Dec-11

pspm(cea)

Sub Stns 9 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 8 9 Transf. received/ erected/ tested 10

Commissioning Original Target Date 11 Dec-10 Actual/ Now Anticipated date 12 Sep-11

Remarks

1 2 Loni S/S (2x315)

3 400/220

4 630

13
(i) Contract awarded on 31.3.2010 with 18 months completion period .Soil testing done. (ii) Out of 80 hec.,60 hec.land has been accquired. (iii) Boundary wall construction obstructed by villagers

HARYANA (HVPNL) 1 2 3 System Strengthening Nawada Nuhiawali Dhanoda(Mohindergarh) 400/220 400/220 400/220 2x315 3x315 2x315 A A A 50% 90% 83% 100% 65% Trf. Received 80% 5% Mar-11 Jun-11 Mar-11 Sep-11 Sep-11 Dec-11 Work in progress. Work in progress. Work in progress.

UTTAR PRADESH (UPPCL) : Parichha TPS (2x250MW) 1 2 Orai S/S Paricha Ext. System Strengthening 1 Srinagar 400/220 2x315 Partially completed Partially received. Jun-12 Dec-12 Layout of S/S has been finalized. Land development and other civil work is in progress. Equipment received is in progress. 400/220 400/220 2x315 2x315 Apr-11 Dec-10 May-12 Jun-12 Land available.

UTTARAKHAND (PTCUL) :

WESTERN REGION (WR) : Chhattisgarh (CSPTCL) Bhilai TPP (P) (JV- NSPCL) 1 NSPCL (2x315 MVA) ICT - II ATS of Korba (W) 1 Raipur (2x315 MVA) 400/220 630 A 80% 91% 91% Place on plinth Oct.07 Dec-11 WIP. 400/220 630 Oct.07 Sep-11 Failed during S C test. Under repair.

GUJARAT (GETCO) : Adani Power Limited (State) 1000 MW (Bid-1) 1 Rajkot(Hadala) ICT-II 400/220 1x315 Mar-08 Sep-11

pspm(cea)

Sub Stns 10 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 15% 95% 8 20% 99% 9 0% 90% Transf. received/ erected/ tested 10 5% 100%

Commissioning Original Target Date 11 Actual/ Now Anticipated date 12 Jan-12 Sep-11

Remarks

1 1 2 Halvad

2 system strengthening

3 400/220 400/220

4 315 2x315

6 A

13 Major equipment will be provided by GETCO.

Dinod (Kosamba)

MAHARASHTRA(MSETCL) Khaperkheda TPS 1 Khaperkheda S/S (2x500) 400/220 1000 Existing 98% 100% 95% Oct-10 Oct-11 220 kV switchyard precommissioning and relay panel testing is in progress.

System Strengthening 1* 2 3 4 5 Bhusaval (2x500) Koradi -II Warora Lonikhand Chandrapur-II 400/220 400/220 400/220 400/220 400/220 1000 500 500 500 500 A Existing Existing A Existing 100% 27% 20% 77% 15% 100% 60% 90% 95% 90% 70% 95% Mar-11 Oct-11 Sep-11 Sep-11 Sep-11 Sep-11 Oct-11 Oct-11 Oct-11 Oct-11 1st 500 MVA Commissioned 8/11. 27% Civil Work & 5% Electrical completed. Civil Work is in progress. 220 KV side equipment is in progress. Work in progress.

SOUTHERN REGION (SR) : Andhra Pradesh (APTRANSCO) 1 2 Shankarapally (3x315) Sattenapally (2x315) 400/220 400/220 945 630 A 50% 10% Feb-12 Jun-12 Feb-12 Jun-12

KARNATKA (KPTCL): 1 Nelamangala (Addl. 3rd Trf.) 400/220 500 Existing Dec-11 May-12 LOA issued on 04.02.11 . Work to be commenced.

TAMILNADU (Tantransco) : 1 Sunguvarchatram 400/230 2x315 A 100% 100% 100% 100% Jul-10 Aug-11 Commissioned 8/11. EASTERN REGION (ER) : ORISSA (OPTCL) System Strengthening

pspm(cea)

Sub Stns 11 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 Completed 8 100% 9 100% Transf. received/ erected/ tested 10 Erected

Commissioning Original Target Date 11 May-08 Actual/ Now Anticipated date 12 Nov-11

Remarks

1 1

2 Dubri 400/220 (2x315)

3 400/220

4 630

13
220 kV S/Y charged on July05.commissioning of 400/220 kV transformer to be done. Due to non complection of 400kV MeramundaliDuburi line the transformer could not be charged.

WEST BENGAL (WBSTCL) : System Strengthening 1 2 Kharagpur Arambag (Aug.) 400/220 400/220 2x315 315 Apr-09 A A 70% 15% 75% 30% Trf. Received. Mar-10 Mar-12 Mar-12 Equipment supply work in progress. LOA placed on 09.03.2011. Order for transformer placed on 26.05.2011. Delivery expected by Dec,11. LOA placed on 09.03.2011. Order for transformer placed on 26.05.2011. Delivery expected by Dec,11.

Jeerat (Aug.)

400/220

315

Mar-12

EASTERN REGION (ER) : TRIPURA (TSECL) 1 a Palatana Gas Power Project , (2x363.3MW) Surajmaninagar S/S 400/132 2x200 Dec-11 Tender will be issued by Aug'11.In first phase, out of nine no. bays, PGCIL will complete two no. bays and balance seven bays by TSECL by Dec,11 and for balance nine no. bay by 31.08.2012.

ASSAM (AEGCL) 1 Palatana Gas Power Project , (2x363.3MW)

pspm(cea)

Sub Stns 12 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 8 9 Transf. received/ erected/ tested 10

Commissioning Original Target Date 11 Dec-11 Actual/ Now Anticipated date 12 Dec-13

Remarks

1 a

2 Kukurmara S/S (2x315)

3 400/220

4 630

13 Civil works including the boundary wall , approach road,bridge,land development , site office etc. are in progress.Work order have been issued for supply and erection of 220 kV and 400 kV switchyard structures and stringing of buses in July 2011. Work order for Transformers to be issued in Aug. 2011.

MEGHALAYA (MePTCL) 1 a Palatana Gas Power Project , (2x363.3MW) Killing (Byrnihat) S/S 400/220 630 Dec-11 Dec-12
Contract Agreement was signed between POWERGRID and MeECL on 6th August, 2010 for execution of the work by PGCIL. Evaluation of Tender for the substation (GIS) is in progress.Acquisition of the additional land required for the 400/220 kV substations is in the final stage.Evaluation of Tender for Transformer and Reactor Package completed. LOA will be issued shortly.

2 a

Essar Mahan TPP. Hazira 400/220 1500 Jun-09 50% 20% 50% Nov-11 Dec-11

C
(a)

220 KV Substations
CENTRAL SECTOR (CS)

POWERGRID (PGCIL) : 1 Augmentation of 220/132KV Transformation Capacity at Raebareli (PG) by 1x100 MVA Transformer

a Raebareli (POWERGRID) 2

220/132

100

Aug-10 Feb-10

95%

80%

60%

Trf. received

Mar-12

Sep-11

Transmission System associated with Pallatana gas Based Power Project and Bongaigaon Thermal Power Station (BTPS)
pspm(cea)

Sub Stns 13 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 8 9 Transf. received/ erected/ tested 10

Commissioning Original Target Date 11 Actual/ Now Anticipated date 12 Dec-12

Remarks

2 a Mokokchung (New)

3 220/132

4 2x50

6 A

13 Engg. in progress.

3 Eastern Region Strengthening Scheme - IV a Extn. Siliguri S/stn. 220/132 1x160

Jul-11 A Apr-13 Award placed in Aug'11.

DAMODER VALLEY CORPORATION (DVC) : Mejia TPS Unit-6 (1x250MW) 1 Gola (2x50 MVA) 220/33 2x80 Jun-11 Mar-12 Order placed on 24-11-09. Initial drawing and design documents submitted. The site could not be taken under possession by DVC. The matter is subjudice at Hon'ble High Court of Jharkhand due to filing of case by land loosers against Govt. of Jharkhand.DVC Board has approved compensation formula for out of court settlement with land losers for getting possession of land.

Chandrapura TPS Extn.(2x250) 1 2 Giridih (2x150+2x80) Dhanbad (2x80) MVA 220/132 220/33 460 80 A A Partially completed 100% Partially received 100% Partially erected 100% Oct-10 Erected Mar-09 Mar-12 Jun-11 Order placed on 27-08-09 .Erection work in progress. 1st Transformer Commissioned 6/11. Order placed in July 08 and precommissioning work in progress. Transformer and equipment erection work completed. Transformer and equipment erection work completed.

Dhanbad (2x150) MVA

220/132

300

98%

98%

98%

Erected

Jul-10

Oct-11

Koderma (2x80) MVA

220/33

160

100%

100%

100%

Erected

Jul-10

Sep-11

Koderma (2x150 ) MVA

220/132

300

98%

99%

99%

Erected

Jul-10

Oct-11

(b)

STATE SECTOR (SS) :

NORTHERN REGION (NR) : DELHI (DTL) : Commonwealth Games


pspm(cea) Sub Stns 14 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 8 9 Transf. received/ erected/ tested 10

Commissioning Original Target Date 11 Mar-08 Actual/ Now Anticipated date 12 Sep-11

Remarks

1 1

2 Electric Lane (GIS)

3 220/33

4 2x100

13 Delay due to tree cutting permission from forest department. S/Stn is ready. Electircal Inspector clearance awaited.

2 3

Trauma Centre/AIIMS (GIS) Mundka(2nd Trf.) System Strengthening

220/33 220/66

2x100 160

Mar-08 Mar-10

Sep-11 Sep-11

1 2 3

Wazirpur Rohini Harsh Vihar GIS

220/33 220/66 220/66

100 160 160

Sep-11 Sep-11 Dec-11

HARYANA (HVPNL) : System Strengthening 1 2 3 4 5 6 7 8 9 10* Masudpur A-5 Faridabad Dhanonda Lula Ahir Sampla Mohana IMT Manesar (2nd) Tepla Aug Nuhiawali Gurgoan Sector-72 220/132 220/66 220/132 220/66 220/132 220/132 220/66 220/132 220/132 220/33 100 100 100 100 100 100 1x100 2x100 2x100 100 Mar-06 Jun-09 Mar-11 Dec-11 Sep-11 Sep-11 Sep-11 Jul-11 Commissioned 7/11. Trf. Received at site erection by HSIDC. A A 50% 50% A 30% 25% 25% 60% 90% 90% 75% 75% Trf. Received Sep-11 Sep-11 Sep-11 Sep-11 Work in progress. Work in progress. Work in progress. Work in progress. Commissioned 3/11

HIMACHAL PRADESH (HPPTCL) : 1 Baddi (Addl.) 1x100 MVA 220/66 1x100 80% 80% 80% Trf. Received. Trf. Received Mar-08 Mar-12 Delay due to forest case in HC

JAMMU & KASHMIR (J&K): 1 Alusteng 220/132 320 A 30% 10% Sep-09 Sep-11 Levelling&construction walls/ control room building under progress.

pspm(cea)

Sub Stns 15 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 70% 70% 80% 100% 100% 8 9 65% 60% 80% 100% Transf. received/ erected/ tested 10 Trf. Received Trf. Received Trf. Received Erected

Commissioning Original Target Date 11 Mar-09 Mar-09 Sep-09 Mar-09 Actual/ Now Anticipated date 12 Sep-11 Sep-11 Jan-12 Jul-11

Remarks

1 2 3 4 5 Mirbazar Budgam Amargarh Bishnah

3 220/132 220/132 220/132 220/132

4 320 320 160 2x160

6 A A A A

13 transformers received transformers received


WIP

Commissioned 7/11.

6 7

Ramban (3x40) Ziankote System Strengthening

220/132 220/132

1x120 3x150

Jun-09 Jun-09

Mar-12 Mar-12

WIP

PUNJAB (PSTCL) : 1 2 3 4 5 6 7 8 9 10 11* 12* 13* 14* 15* Mastewala Jhunir Mandi Govindgarh Mehal Kalan Rehana Jattan Ghobaya Patran Lalru Ferozepur Road Ludhiana (1x100 MVA) Doraha (U/G) (1x100 MVA) Khassa (Aug.) Malerkotla (Aug.) Focal Point Nabha (2nd Trf.) Kapurthala (Kanjli) (New) Algaon 220/66 220/66 220/66 220/66 220/66 220/66 220/66 220/66 220/66 220/66 220/66 220/66 220/66 220/66 220/66 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 Jul-11 Jul-11 Aug-11 Aug-11 95% A 85% 100% 100% 100% Erected Mar-07 Jun-10 Dec-11 Aug-11 Feb-12 Sep-11 Commissioned 8/11 Civil/Erection work in progress 10% electrical work completed Commissioned 6/11 Commissioned 7/11 Commissioned 7/11 Commissioned 8/11 Commissioned 8/11 75% 22% 70% Sep-11 Dec-11 Dec-11 10% electrical work completed Commissioned 3/11 76% Sep-11 5% electrical work completed Commissioned 3/11 10% electrical work completed

pspm(cea)

Sub Stns 16 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 8 9 Transf. received/ erected/ tested 10

Commissioning Original Target Date 11 Actual/ Now Anticipated date 12

Remarks

2 System Strengthening

13

RAJASTHAN (RRVPNL) :

1 2 3 4 5 6

Madri (Udaipur) Kishangarh Dechu Gajner Gangapurcity Barli

220/132 220/132 220/132 220/132 220/132 220/132

100 100 100 100 100 100 A A

90%

80%

70%

Trf. Erected Trf. Received Trf. Received

Sep-11

Test charged from 132 kV side on 12.01.11. Line work held up due to ROW problem. 3/11 Commissioned Transformer Test charget. WIP. Transformer alloted. Land possession taken. Civil works tenders under process. Land possession taken on 15.01.11. Boundary wall order placed. Laboue contract awarded for associated line. Work under progress. Transformer received. civil work under progress. Civil work started. Transformer received. Deffered. To be taken up after load growth in the area. Commissioned 3/11 Commissioned 6/11

90% 60% 5%

95% 70% 70%

95% 40%

Dec-11 Mar-12 Jan-12 Mar-12

7 8 9 10 11 12

Manoharpur Padampur Aspur Jhalmand Sawa Sanchore(1x100)

220/132 220/132 220/132 220/132 220/132 220/132

100 100 100 100 100 100 A

80% 2% 10%

50% 10%

60%

Trf. Received

Jan-12 Mar-12

Trf. Received

Mar-12 Mar-12

Jun-09

Jun-11 Dec-11

UTTAR PRADESH (UPPCL) : System Strengthening 1 Bhelupur 220/33 120 100% 50% One 60 MVA TXR on plinth. Erection of 33 kv side equipments completed. Overall 85 % work completed. Earthmat laid. Dec-11 Work in progress.Overall 85% work completed. Earthmat completed.Transformer placed on plinth.

Gajokhar

220/132

100

95%

75%

pspm(cea)

Sub Stns 17 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 8 9 90% Transf. received/ erected/ tested 10 50%

Commissioning Original Target Date 11 Dec-07 Actual/ Now Anticipated date 12 Dec-11

Remarks

1 3 Jhansi

3 220/132

4 100

13 Earthmat laying 85% completed. Transf. Plinth 75% completed.Overall 93% work completed. Commissioned 7/11. 60 MVA Trf. Commissioned 5/11. Work in progress.Overall 45 % work completed. Boundary wall complete. Work in progress.Overall 80 % work completed. One Transformer placed on plinth. Control room upto lintel level.

4 5 6 7

Bithoor Kanpur South (3x60) Partapgarh Jhusi

220/132 220/132 220/132 220/132

160 160 100 160

A A

100% 99%

100% 100%

100% 100% 41% 100%

100% 67%

Jul-11 Sep-11 Mar-12

40%

Mar-12

UTTARAKHAND (PTCUL) : 1 Dehradun 220/132 1x160 Jun-06 Dec-11 Land acquisition under progress.

2 3

Ghansali Mahuakhedaganj

220/132 220/132

2x50 2x100

Dec-10 Dec-10

Sep-11 Oct-11

Bid evaluation completed.WIP. Work in progress.Equipment supply completed.Total progress 90% .

WESTERN REGION (WR) : CHHATTISGARH (CSPTCL) : ATS of Korba (E) 1 Bishrampur System Strengthening Mungeli Saraipally Chhuri(korba) Kotmikala (Addl.) Barsoor 220/132 220/132 100 160 220/132 160 A 90% 80% 80% Erected Dec-10 Dec-11 Work in progress.

1 2 3 4* 5

220/132 220/132

160 160

A A PA A A 100% 100% 100% 90% 100% 90% 100% To be arranged

Mar-12 Mar-12

Work to be awarded shotly. Engg. Work in progress. Order placed. Work started after handing over of site.

Jul-11 Dec-11

Commissioned 7/11. Work in progress.

pspm(cea)

Sub Stns 18 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 100% 80% 8 100% 90% 9 100% 90% Transf. received/ erected/ tested 10 100% To be arranged

Commissioning Original Target Date 11 Actual/ Now Anticipated date 12 Aug-11 Dec-11

Remarks

1 6* 7 Bemetara Thelkadih

3 220/132 220/132

4 160 160

6 A A

13 Commissioned 8/11. Work in progress.

GUJARAT(GETCO) : System Strengthening 1 2 3 4 5 6 7 Shapur Vadala Popda Suva Bhatiya Lunawada Jasdan 220/132 220/66 220/66 220/66 220/132 220/66 220/132 300 100 100 2x100 4x100 100 200 Apr-11 Mar-11 A A A A A 0% 11% 100% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% Mar-12 Sep-12 A 99% 30% 0% 3 nos. Trf. Received Dec-11 Mar-12 Mar-12 Oct-12 Mar-12 Mar-12 Mar-12 Tender for CR and foundation is under process. Tender for EPC also under process.to be approved.Major Estimated get equipments are to be supplied by GETCO. 8 9 10 11 13 14* 15* 16* 17* Tankara Saria Vyankatpura Kalawad Kosamba Vadavi (Aug.) Nakhatrana (Aug.) Achchalia (Aug.) Jarod 220/66 220/132 220/66 220/66 220/66 220/66 220/66 220/66 220/66 100 100 100 100 1x100 50 50 50 200 0% 0% 0% 0% Mar-12 Mar-08 Mar-12 Mar-12 Mar-12 Mar-12 Sep-11 Jun-11 Jun-11 Jun-11 Mar-12 Commissioned 6/11. Commissioned 6/11. Commissioned 6/11. Estimate yet to be get approved. Major equipments are to supplied by GETCO. Commissioned 7/11. BOQ under preparation. Agency finalised .Major equipments are to be supplied by GETCO.

18*

Kangasiyali

220/66

100

Feb-09

100%

100%

100%

100%

Jul-11

pspm(cea)

Sub Stns 19 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 99% 8 85% 9 78% Transf. received/ erected/ tested 10 Received and Erected. (all 3 nos.)

Commissioning Original Target Date 11 Actual/ Now Anticipated date 12 Sep-11

Remarks

1 19* Lalpar

3 220/132/ 66

4 3x100

5 Jun-10

6 A

13 Isolators/Panels/Battery sets. Major equimpments will be provided by GETCO.

20*

Sadla

220/66

100

0%

0%

0%

0%

Mar-12

Mar-12

Tender Published. Major equipments will be supplied by GETCO.

GOA : 1 Cuncolim 220/33 3x50 A Dec-10 Sep-11 Work order with IRCON.Due to prolonged mansoon upto Dec-10,work could not be taken up in time which has slipped the target date of complection. Work is in progress. Administration and expenditure approval has been accorded on July 2010. Commissioned 5/11. Commissioned 5/11.

2 3

Tivim (3rd Trf.) (Aug.) New Verna

220110 220110

1x100 1x100

A UA

Sep-11 Sep-11

4* 5*

Ponda Xeldem System Strengthening

220/110 220/110

100 100

May-11 May-11

MADHYA PRADESH (MPPTCL) : 1 2 Daloda Chichali 220/132 220/132 160 160 A A 30% Mar-12 Aug-12 work in progress. work delayed due to court case on acquisition of land. Case resolved recently. Fencing under progress. Test charged.

Ashta

220/132

160

100%

100%

100%

100%

Dec-11

Seoni

220/132

160

30%

20%

15%

Trf. Recd.

Mar-12

WIP.

MAHARASHTRA (MSETCL) : 1 System Strengthening Paranda 220/132 200 A 90% 100% 95% Trf. Recd. Sep-11 Cable laying & termination work, cable is in progress.

pspm(cea)

Sub Stns 20 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 90% 8 95% 9 60% Transf. received/ erected/ tested 10

Commissioning Original Target Date 11 Actual/ Now Anticipated date 12 Dec-11

Remarks

1 2 Patoda

3 220/33

4 50

6 A

13 220 kV gantry erection , bus stringing , equipment support structure completed. 33 kV yard erection is in progress. 70% Civil Work & 42% Electrical completed. 100 MVA Trf. charged on 5/11. 98% Civil Work & 96% Electrical completed. Relay testing at 220 kV side in progress is in progress. SCADA is in progress. 100 MVA Trf. charged on 5/11 and 2nd 100 Mva Trf. Charged on 7/11. 99% Civil Work & 92% Electrical completed.Mass opposing from Villagers.File court case dated 06.03.10. Commissioned 5/11.

3 4

Bhokardhan Jath (2x100)

220/132 220/132

100 100

A A

10% 100% 100%

20% 90% 100%

Dec-11 Sep-11

Bhambori (Jalgaon)

220/132

100

100%

100%

85%

100%

Sep-11

6 7

Vasai Bapgaon

220/100 220/132 220/33

200 2x200 2x50

A A

100% 100%

100% 100%

100% 100%

Erected Mar-08

Jul-11 Sep-11

8*

Urse

220/22

1x50

May-11

SOUTHERN REGION (SR) : ANDHRA PRADESH (APTRANSCO) : System Strengthening 1 2 3 4 Rachagunneri Osmania University Erragadda lmliban (GIS) 220/132 220/132 220/132 220/132 2x100 2x160 3x160 2x160 A A A A Partially completed. Partially completed. Partially completed. Excavation Under progress. Partially completed. Partially completed. Partially received. Partially erected. Erected Partially received. Partially erected. Mar-12 Dec-11 Dec-11 Sep-11 Work commenced and are in progress. Excavation under progress. Foundation works and structure erection works under progress.

5 6

Gunrock Nagari

220/132 220/132

2x160 2x100 +2x50

A A

Dec-11 Dec-11

75% foundation work completed. Sub-station work completed with 1 no transform. Connected line works under progress.

pspm(cea)

Sub Stns 21 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 Completed 8 Received 9 Erected Transf. received/ erected/ tested 10 Erected

Commissioning Original Target Date 11 Dec-09 Actual/ Now Anticipated date 12 Sep-11

Remarks

1 7 Palamaneru

3 220/132

4 2x100

6 A

13 All works completed with 1 no transformer. Connected line works are under progress. 100 MVA Transformer Commissioned 7/11. Substation is charged from 132 kV side. Change of scope of line works due to 400 kV Yeddumailaram evacuation lines. 220 kV progress and may be completed by Jan, 2012.

8* 9

Bellampally (Mandamarri) Sadasivpet

220/132 220/132

2x100 2x100

A A

Completed

Received Partially received.

Erected Partially erected.

Erected

Oct-08

Jul-11 Jan-12

10 11 12 13 14 15 16 17 18 19 20 21 22 23* 24*

Jurala Settipally Yellanur Gaddamvaripalli Goddumarri Kambalapadu Thimmapuram Kondapuram Nansuralla Vemnur Medaram Krishnagiri Lakkasagaram Brahmanakotkur Malyala

220/132 220/11 220/11 220/11 220/11 220/11 220/11 220/132 220/11 220/11 220/11 220/11 220/11 220/11 220/11

2x100 3x25 2x25 2x25 2x50 3x25 2x25 2x100 3x25 2x50 2x50 3x25 3x25 3x25 126

A A A A A A A A A A A A A A A

100%

100% 99% 70% 90% 50% 100% 95% 100% 100% 70% 95% 95% 100%

100%

Sep-11 Sep-11 Sep-11

All works completed. Except PTR erection.

50%
20% 100% 90% 100% 100% 50% 20% 22% 100%

Sep-11 Sep-11 Sep-11 Sep-11 Sep-11 Sep-11 Sep-11 Sep-11 Sep-11 Sep-11 Apr-11 Apr-11 25 MVA Trf. Commissioned 4/11. 95 MVA Trf. Commissioned 4/11.

KARNATAKA (KPTCL) : 1 2 Jigani (2x150) MVA Vikas Tech Park (2x150) MVA 220/66 220/66 300 300 A A
Nearing completion. Partially completed 100% Partially received 100% Partially erected Erected Erected

Oct-08 Oct-11

Mar-12 Mar-12

Pre- commissioning test to be taken up.

pspm(cea)

Sub Stns 22 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7
Partially completed 100% 100%

Commissioning Transf. received/ erected/ tested 10 Original Target Date 11 Jul-11


Erected Erected

Remarks

Actual/ Now Anticipated date 12 Dec-11 Mar-12 Sep-11 2x100 MVA transformer erected. All equipments erected. Road formation and PC test under progress. Commissioned 5/11 Oil to be filtered. Work to be taken up by the firm. Commissioned 6/11 13

1 3 4 5

2 Halbarga (2x100) MVA Ramanagar(Kothipura) Chikkmagalur (2nd Trf.)

3 220/110 220/66 220/66

4 200 100 100

6 A A A

8
Partially received 100% 100%

9
Partially erected 100% 100%

Dec-07 Dec-09

6 7 8*

Kushalanagara (2nd Trf.) Somanahalli (Addl.) A'station Compound (Anand Rao Circle) (2nd Trf.)

220/66 220/66 220/66

100 100 150

A A

completed Completed

Received Existing

Erected Existing

Erected Erected

Aug-07 Aug-08

May-11 Dec-11 Jun-11

KERALA (KSEB) : 1 Punnapra 220/110 2x200 A 100% 100% 100%


Trf. Erected.

Jun-07

Dec-11

Erectionof yard structure,cable trench,Equipment foundation completed. Overall 92% completed.

2 3 4

Kanjikkod(Add.Tr.) (2x25) Pothencode(3 Trf.) Kattakkada(New)


rd

220/110 220/110 220/110

50 200 200 A 99% 100% 9%


Received

Mar-12 Commissioned 3/11 Mar-12 Overall 87% completed.

TAMILNADU (Tantransco) : 1 2 3 4 5 6 7* 8* 9* 10* Karambayam Karamdai (2x100) Aliyar (2x100) Nallamanaickenpaty (2x100) Vyasarpadi Athipet Sadayapalayam Oragadom Alundur (Aug.) (100-50) Amulhapuram (Add.Tr.) 230/110 230/110 230/110 230/110 230/110 230/110 230/33 230/110 230/110 230/33 2x100 100 100 100 100 100 100 100 50 50 A A A A A A 100% 20% 100% 80% 20% 100% Partially Received Partially Received Partially Received 90% 80% 20% 10% 75% 5% 80% 80% Dec-10 Nov-11 Mar-12 Sep-11 Nov-11 Mar-12 Dec-11 Apr-11 Apr-11 Apr-11 Jun-11

Commissioned 4/11. Commissioned 4/11. 50 MVATrf. Commissioned 4/11. Commissioned 6/11.

PUDUCHERRY

pspm(cea)

Sub Stns 23 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 Partially received. 8 Partially received. 9 Partially erected Transf. received/ erected/ tested 10 Trf. Received

Commissioning Original Target Date 11 Jun-10 Actual/ Now Anticipated date 12 Dec-11

Remarks

1 1

2 Thondamanatham

3 230/110

4 2x100

6 A

13 Both transformers placed on plinth. The work is being executed by M/S PGCIL.

EASTERN REGION (ER) : BIHAR (BSEB) : System Strengthening 1 Hazipur (2x100) 220/132 2x100 May-08 Dec-11 Order placed and work has been stated.Work is going on all fronts. The expected date for commissioning shall be Dec,2011 Works are being executed by PGCIL. Work is going on all fronts. The expected date for commissioning shall be Dec,2011. Work is progressing on all fronts. Part land required for construction of SubStation in 220 kV side has been received recently. The expected commissioning time is March, 2012.

Sipara (Patna) (2x150)

220/132

2x150

May-08

Dec-11

Madhepura (2x100)

220/132

2x100

Mar-12

4 5

Dehri (Aug.) Muzaffarpur TPS (kanti) (Aug.)

220/132 220/132

1x100 1x100 Dec-08

Sep-11 Sep-11 Work in progress

JHARKHAND (JSEB) : 1 Chaibasa System Strengthening Bolangir Mendhasal Bonai 220/132 2x150 Jun-10 Sep-11 Land under development.

ORISSA (OPTCL ) : 1 2 3 220/132 220/33 220/33 100 20 80 A A 10% Received Mar-12 Jun-12 Commissioned 3/11
Work Order (LOI) issued on Dt.09.06.2010. Work in progress.

Work Order issued on Dt.18.11.09. Substations boundary wall in progress. Contour survey of the S/S site completed. Work Order issued on Dt.18.11.09.

WEST BENGAL (WBSETCL) : System Strengthening


pspm(cea) Sub Stns 24 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 70% 90% 8 75% 95% 9 30% 100% Transf. received/ erected/ tested 10 Trf. Received. Trf. Received.

Commissioning Original Target Date 11 Mar-12 Jun-11 Actual/ Now Anticipated date 12 Mar-12 Sep-11

Remarks

1 1 2 Kharagpur Dalkhola

3 220/132 220/132

4 320 320

5 Apr-09 Jun-09

6 A A

13 Equipment supply work in progress. Control room building is completed. Fire fighting , Air conditioning & illumination work yet to be done.Equipment erection work in progress.
c & R panel delivered at site. Tender for supply of Transformers completed. Order to be placed by 15.08.2011. delivery expected by Jan,12. LOA placed on 09.03.2011. Tender for supply of Transformers completed. Order to be placed by 15.08.2011. delivery expected by Jan,12. NIT being processed. Tender for supply of Transformers completed. Order to be placed by 15.08.2011. delivery expected by Jan,12.

Kasba (Aug)

220/132

160

50%

100%

90%

Trf. Received.

Jun-11

Mar-12

Laxmikantapur (Aug)

220/132

160

5%

Mar-12

Howrah (Aug)

220/132

160

Mar-12

6*

Rishra(aug.)

220/132

160

Jul-09

100%

100%

100%

Trf. Erected

Jul-11

Commissioned 7/11.

NORTH-EASTERN REGION (NER) : AEGCL 1 a ATS of Palatana Gas Power Project , (2x363.3MW) Kukurmara S/S (2x50) System Strengthening 1 1 Rangia S/S (2x100) Nangalbibra 220/132 220/132 200 100 Dec-11 Dec-11 MEGHALAYA(MeSEB) 220/132 100 Dec-11 Drawing/ designe is finalized. Preliminary civil works in progress.

220 kV Private Sector : ATS of Malana II HEP (EPPL) Chhaur S/S 132 kV STATE SECTOR :

132/220

4x42.5

Jun-09

Sep-11

Ready for commissioning.

pspm(cea)

Sub Stns 25 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 8 9 Transf. received/ erected/ tested 10

Commissioning Original Target Date 11 Actual/ Now Anticipated date 12

Remarks

5 Feb-10

13

PGCIL
1 Transmission System associated with Pallatana gas Based Power Project and Bongaigaon Thermal Power Station (BTPS) Melriat S/S (Upgradable to 400 KV) Extn. Imphal S/S Roing S/S Tezu S/S Nimsai S/S ASSAM (AEGCL) 1 a b Transmission System associated with Pallatana gas Based Power Project Panchgram(Aug.) S/S (2x25) Hailakandi S/S (2x16) 132/33 132/33 50 32 Feb-10 Sep-11 Nov-13 25 MVA commissioned 7/11.
The Loan agreement with ADB has been signed.Land acquisition is in final stage and compensation amount has been deposited with the District Authority for necessary action.

a b c d e

132/33 132/33 132/33 132/33 132/33

2x50 2x50 2x15 2x15 2x15

A A A A A

Dec-12 Dec-12 Dec-12 Dec-12 Dec-12

Engg. In progress. Completin likely to be delayed. Engg. In progress. Engg. In progress. Land yet to be acquired.

Tripura (TSECL) 1 Transmission System associated with Pallatana gas Based Power Project and Bongaigaon Thermal Power Station (BTPS) Surajmaninagar S/S (upgrdable to 400 kV) 132/33 2x50 Feb-10

15-1-11

Complete

20%

Dec-11

Aug-12

In 1st phase , out of nine nos. bay PGCIL will complete two nos. bay and balance seven nos. bay by TSECL by Dec'11 and for balance nine nos. bay by Aug.,2012. Side leveling work already completed and control room have already started and completed around 20 % . Equipment foundation will be started shortly.Equipment receiving is in progress.

E D , Govt. of Manipur 1 Transmission System associated with Pallatana gas Based Power Project and Bongaigaon Thermal Power Station (BTPS)
pspm(cea)

Feb-10

Sub Stns 26 of 27

Sl. No.

Name of the Sub-Station

Voltage ratio (kV/kV)

Capacity MW/MVA

Date of Award

Cummulative progress till date Land Acqusition Civi works Structure, sub Structure, station sub station completed eqpt.received eqpt.erected 7 8 9 Transf. received/ erected/ tested 10

Commissioning Original Target Date 11 Actual/ Now Anticipated date 12 Dec-11

Remarks

1 a

2 Yurembam(Aug.) S/S

3 132/33

4 3x33.5

13

LEGEND:

* S/C D/C M/C S/C on D/C kV CKm LILO TPS NHPC Aug CS SS NER

Outside programme Single circuit Double circuit Multi circuit Single circuit on Double circuit Kilo- volt Circuit kilometer Loop in Loop out Thermal Power station National Hydro Power Corporation Augmentation Central Sector State Sector North-East Region NR WR SR ER Northern Region Western Region Southern Region Eastern Region MVA MW ckt S/S C.R. Struct. Transf. SG Mega Volt Ampere Mega watt Circuit Sub-station Control Room Structure Transformer Switch gear A UA Available/Acquired Under Acquisition

CR Panel Control and Relay panel

pspm(cea)

Sub Stns 27 of 27