Quarry Specialist Training Guide

This document provides administrative details for a lesson to teach students how to set up a 150-ton per hour crusher plant. The lesson requires 21 hours to complete and includes classroom instruction as well as hands-on training with equipment. Students will learn to set up and operate a 150-TPH crusher plant according to technical manuals and job specifications using tools and safety equipment. Instructors must ensure the classroom and equipment are prepared before presenting the hands-on lesson.

Uploaded by

Lo Shun Fat
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views4 pages

Quarry Specialist Training Guide

This document provides administrative details for a lesson to teach students how to set up a 150-ton per hour crusher plant. The lesson requires 21 hours to complete and includes classroom instruction as well as hands-on training with equipment. Students will learn to set up and operate a 150-TPH crusher plant according to technical manuals and job specifications using tools and safety equipment. Instructors must ensure the classroom and equipment are prepared before presenting the hands-on lesson.

Uploaded by

Lo Shun Fat
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

SET UP A 150-TPH CRUSHER PLANT

SECTION I. ADMINISTRATIVE DATA


All Courses Including this Lesson COURSE NUMBER(S) 713-62G10 COURSE TITLE(S) Quarry Specialist Course

Task(s) Taught or Supported

TASK NUMBER (S) 051-251-XXXX

TASK TITLE (S) Set Up a 150-TPH Crusher Plant

Reinforced Task(s)

TASK NUMBER (S) None

TASK TITLE (S)

Academic Hours

The academic hours required to teach this lesson are as follows: Peacetime Hrs Meth 2.0 CO 3.0 DM 6.0 PE1 2.0 PE2 6.0 TE1 2.0 TE2 Mobilization Hrs Meth 2.0 CO 3.0 DM 6.0 PE1 2.0 PE2 6.0 TE1 2.0 TE2 IDT Hrs Meth 00.0 00.0 00.0 00.0 00.0 00.0 Hrs 2.0 3.0 6.0 2.0 6.0 2.0 ADT Meth CO DM PE1 PE2 TE1 TE2 Hrs 00.0 00.0 00.0 00.0 00.0 00.0 DL Meth

Test

Total Hours

21.0

21.0

00.0

21.0

00.0

Test Lesson Number

Refer to Appendix C, Test and Test Solutions

09/25/98 62G1@BCL@24010A59

C-I-1

SET UP A 150-TPH CRUSHER PLANT

Prerequisite Lesson(s)

LESSON NUMBER(S) 051-62G1-B01 051-62G1-B02 051-62G1-B03 051-62G1-B04 051-62G1-C01

LESSON TITLE(S) Introduction to Course Introduction to Safety Introduction to Environmental Stewardship Utilize The Army Maintenance Management System (TAMMS) Introduction to Rock Crushing Operations

Clearance and Access

Unclassified

References Required

Number
*TM 5-332 TM 5-3820-255-12&P TM 5-3820-256-14&P TM 5-3820-257-14&P TM 5-3820-258-14&P TM 5-3820-259-14&P TM 5-3820-260-14&P TM 5-3820-262-14&P TM 5-3820-263-14&P Pits and Quarries

Title
Operation, Model M150 Primary Crusher Unit, Model M3042 Portable Surge Bin Feeder, Model PSF-12 Secondary Crusher and Screening Unit, Model M1313 Tertiary Crusher Unit, Model MC45 Washing and Screening Unit, Model M1122 Product Conveyor, Model PC1245 Water Pump Unit, Model GB2060

Date
Dec 67 Jun 97 Jun 97 Jun 97 Jun 97 Jun 97 Jun 97 Jun 97 Jun 97

Additional Information

Instructor Requirements

Two ITC certified instructors

Additional Support Personnel Requirements

Assign alternate instructors as needed.

09/25/98 62G1@BCL@24010A59

C-I-2

SET UP A 150-TPH CRUSHER PLANT


* This reference is currently being revised as a Field Manual. Equipment Required 150-TPH crusher plant General mechanics tool kit drive set with sockets 18 pipe wrench 24 adjustable wrench 12 ruler Replacement screens Cone and jaw adjustment pump Grease gun

Materials Required

Instructor Materials TM 5-3820-255-12&P TM 5-3820-256-14&P TM 5-3820-257-14&P TM 5-3820-258-14&P TM 5-3820-259-14&P TM 5-3820-260-14&P TM 5-3820-262-14&P TM 5-3820-263-14&P Job specifications C02 TSP Equipment records folder Coveralls Safety boots Goggles Gloves Double hearing protection Hard hat

Student Materials TM 5-3820-255-12&P TM 5-3820-256-14&P TM 5-3820-257-14&P TM 5-3820-258-14&P TM 5-3820-259-14&P TM 5-3820-260-14&P TM 5-3820-262-14&P TM 5-3820-263-14&P Job specifications Equipment records folder Student guides Coveralls Safety boots Goggles Gloves Double hearing protection Hard hats Pencils Paper

Classroom, Training Area, and Range Requirements

NOTE: Refer to the Facilities Summary of the POI.

Ammunition Requirements

None

09/25/98 62G1@BCL@24010A59

C-I-3

SET UP A 150-TPH CRUSHER PLANT

Instructional Guidance

Before presenting this lesson, a. Ensure classroom is available and ready for training b. Ensure overhead projector, screen, and VGTs are on hand c. Ensure all materials are on hand and in quantities needed. d. Read and understand C02 TSP prior to conducting training. e. Ensure equipment is available and on site.

Proponent Lesson Plan Approvals

Name

Rank

Position

Date

09/25/98 62G1@BCL@24010A59