Gas Production and Handling Advances
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29
 th
, 2008                                  Page 1         
Experiences in Upgrading of 
PGT5 Gas Turbines 
PDVSA Gas, S.A. - Venezuela            
Authors: 
Jos G. Martnez  Maintenance  Suptte.    
Carlos D. Blanca  Turbomachinery Suptte.  
Luis Vera. Turbomachinery Major Technician. 
Jorge L. Gonzlez  Maintenance Supv.   
JANUARY  2008 
Gas Production and Handling Advances              
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29 
th
, 2008                                  Page 2   
Experiences in Upgrading of PGT5 Gas Turbines 
by Carlos Blanca, Jos Martnez, Lus Vera, Jorge Gonzlez   
ABSTRACT  
Santa  Barbara  Extraction  Plant  is  located  in  the  Monagas  state  Republica 
Bolivariana de Venezuela- and it is part of four (04) extraction plants of Natural Gas 
Liquid  (NGL)  which  belong  to  East  Criogenic  Complex  of  PDVSA  GAS.  This  Plants 
has  two  (02)  trains  of  processing  gas,  each  train  has  a  system  of  mechanical 
refrigeration with propane and it has centrifugal compressors. Those compressors are 
driven  by  gas  turbines,  PGT5  model.  The  Refrigeration  system  guarantee  suitable 
temperature to obtain NGL, then it is a very important system.  
During 2004 a second cycle of major maintenance (80.000Hrs), for PGT5 gas turbine 
was  reached    and  it  was  a  opportunity  to  improve  the  mechanical  performance  in 
these  gas  turbines.  This  work  consisted  of  upgrading  of  low  pressure  rotor  and  
internal  components  parts  of  the  system  of  compression  and  expansion  with  the 
purpose  of  increasing  power,  since  6800  HP  to  7300  HP.  Additionally,    we  could 
standardize spares part  stock  in Santa brbara  Extraction Santa Barbara  and Jose 
Fractionation  and shipping Plant, which already had a gas turbine of 7300Hp. Also it 
had a project  to upgrade two (02) units of 6400 HP and one of 6800 HP to 7300 HP. 
The  upgrading  could  guarantee  better  conditions  of  operation  in  the  refrigeration 
system and more mechanical benefits.   
The  upgrading  consisted  in  to  change  some  internal  components  and  adjust  few 
parameters  of  the  system  of  control  gas  turbine,  with  the  purpose  of  increase  the 
power.  
Gas Production and Handling Advances              
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29 
th
, 2008                                  Page 3  
This work will expose aspects in orden to explain the modifications made, as well the 
experiences and the present gas turbine conditions. 
INTRODUCTION 
The upgrading of equipment is not a new idea; it is used in the oil industry since many 
years ago; in order to increase the levels of production, to increase reliablity or simply 
to  improve  the  conditions  of  operation,  also  for  obsolesence  of  spare  part.    Gas 
turbine technology is  always improving,  with the purpose of increasing the efficiency 
of the turbines. Actually this efficiency does not reach 40%, for a simple cycle. In that 
way,  the  manufacturers  offer  packages  of  upgrading,  which  consist  of  the 
replacement  of  improved  internal  pieces,  with  the  purpose  of  obtaining  greater 
benefits  either  in  the  unit  and  the  process.  The  client  is  who  will  decide  by  an 
technical-economic  evaluation  if  it  is  recommendable  to  maintain  the  unit  in  original 
characteristics or to accept the offer. 
The  Santa  Barbara  extraction  plant  was  officially  inaugurated  in    1995  and    the  gas 
turbine  model selected -for its refrigeration system- it was the PGT5 gas turbine. This 
model of turbine had been used in Jose Fractionation and shipping Plant, which was 
inaugurated  in  1985.  The  PGT  5  gas  turbine  was  a  improvement  made  to  MS1002 
gas turbine of 6400 HP - in Jose there are three (03) MS1002. After that a PGT5 had 
other modification and now it can develop a power of 7300 Hp. This turbine is called 
PGT5A. 
MAINTENANCE PLAN REVIEW 
When  PDVSA  overcome  the  strike  in  2002,  a  review  of  gas  turbine  maintenances 
plans and strategies was possible in the East Cryogenic Complex . The results were 
not  encouraging  because  of  a  lot  of  maintenance  pending  for  next  years  and  few 
thechnicians  in  that  area  to  supervise  this  work.  Additionally,  It  was  necessary  to 
continue  with  a  revamping  of  control  sytems  which  had  been  starting  years  ago. 
However,  the  greater  challenge  was  a  situacin  with  a  gas  turbine  in  refrigeration 
Gas Production and Handling Advances              
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29 
th
, 2008                                  Page 4  
systems. Those turbines had 80.000 hrs working and its manufacture recommended 
major maintenance rotors, replacement of axial compressor blades and other internal 
parts. This work had to be made in Italy and it was important a good strategy to have 
that rotors on time for each maintenances. 
The East Cryogenic complex had two (02) set of rotors (2 rotors of low pressure and 
2  rotors  of  high  pressure),  but  they  were  not  interchangeable  due  to  differences  in 
models in each Plant.            
Figure N1. Equipments summary in Jose and Santa Brabra Plants  
Figure  N 1  shows  the  turbines  by  models  in  each  plant  mentioned  and  control 
systems  which  were  updated  to  Mark  V  and  those  that  had  SUVIMAC.  It  required 
replacement of four (04) systems of control (3 in Santa Barbara and 1 in Jose) and to 
do  five  (05)  major  maintenances  (4  in  Santa  Barbara  and  1  in  Jose),  during  a 
estimted of 3 years approximately.  
Five (05) Gas Turbines  
Tres (03)   to 6400 BHP ISO 
One (01)   to  6800 BHP ISO 
One (01)   to  7300 BHP ISO   
Control Sytems 
4 Mark V 
1 Suvimac  
Four (04) Gas Turbines 
6400 BHP ISO  
Control Sytems 
1 Mark V 
4 Suvimac  
Gas Production and Handling Advances              
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29 
th
, 2008                                  Page 5  
The disposition of one (01) of rotors of 6400 HP and one (01) set of rotors of 6800 HP 
did not offer any advantage to make the logistics of maintenance in Italy, due to time 
since the rotor is sent, repaired and received again, to be installed. This situation was 
consulted to the manufacturer and it offered two alternatives: 
1)  Buy other set of rotors to 6800 HP. 
2)  Upgrading : 
a.  Upgrading to 6800 HP. 
b.  Upgrading to 7300 HP.  
PROPOSALS ANALYSIS.  
In  order  to  make  an  analysis  of  the  manufacturers  proposals,  the  following  aspects 
were considerated: storage of spare parts, stock spares, costs, technical aspects.  
1) Buy other set of rotors to 6800 HP. 
This option represented a simple option, which consisted of buying an additional set 
of  rotors  for  Santa  Barbara  Extraccion  Plant  with  the  purpose  of  having  one  set 
available in each maintenance. It would be made the logistic of transport and repair in 
such  way  that  it  was  always  a  set  of  rotor  in  Italy,  and  another  in  Venezuela  to  be 
installated.  However  differences  of  spare  parts  between  the  units  it  was  keeping, 
therefore  it  would  not  be  possible  to  use  that  set  in  another  gas  turbines  models. 
Aditionally  a  third  set  of  rotors  requested  of  a  space  to  be  stored  and  they  had  the 
same costs by repair of rotors with same power. 
2) Upgrading Rotor. 
  a) Upgrading to 6800 HP. 
This option was quite feasible.  It does not buy a new set of rotor, old sets are used; 
Gas Production and Handling Advances              
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29 
th
, 2008                                  Page 6  
one is repaired and one is upgrading to 6800 HP. But there was the condition of one 
gas turbine in Jose with a power of 7300 HP, and it would be keeping in that power. 
In consequence the difference in the spare parts would not be eliminated. Additionally 
the costs associated to the maintenance of the rotors were greater than the costs to 
upgrade  to  7300  HP,  because  of  offer  supplied  by  the  manufacturer;  it  will  be 
exposed in next part of this paper. 
  b) Upgrading to 7300 HP. 
A quite tentative offer was supplied by the manufacturer of the gas turbines, in orden 
to  upgrade  to  7300  HP  all  units.  According  to  the  information  provided  by  the 
manufacturer,  this  offer  was  motivated    they  will  not  manufactured  MS  1200  (6400 
Hp)  and  PGT5  (6800  Hp)  anymore  -only  PGT5A  (7300  Hp)-  they  guaranteed  the 
spare parts but the manufacture costs would be elevated and long time of response in 
case of fail.  
The offer o package consisted of:   
1)  Engineering Documentation. 
2)  Compressors blades.  
3)  A new antisurge vlve and pipelines. 
4)  Internal Parts (Shourd, nozzles, buckets and bearings). 
Costs associated to this package were compared with the prices of spare parts offer 
for  a  Major  Maintanance;  keeping  same  power  and  knowing  that  five  (05)  sets  of 
rotors it would have to be repaired.    
Gas Production and Handling Advances              
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29 
th
, 2008                                  Page 7             
Table N1. Repair and upgarding rotors sumamry. 
Table  N1  presents  the  costs  associated  with  a  can  be  observed  the  associated  to 
maintenance  of  the  rotors  without  upgrade,  the  cost  was  of  2,38  MMBsF  and  the 
upgrading  offer    (spare  parts  and  services  were  Incluided)  was1,85  MMBsF. 
Therefore  the  offer  upgarding  represented  a  saving  of  0.54  MMBSF  by  unit  and  a 
saving total of 2,69 MMBsF. Other advantages to make the upgrade to 7300 HP are:  
the  possibility  of  use  of  spare  parts  in  both  plants  and  the  availability  of  additional 
power  for  the  system  of  refrigeration  in  the  Santa  Barbara  Extraction  plant.  In  that 
sytem the gas turbine always presented control for temperature, since 10:00 a.m. to 
4:30  p.m.  approximately,  it  is  means  that  exhaust  temperature  is  up  1050  F,  and 
sometimes this casused a trip.  
Gas Production and Handling Advances              
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29 
th
, 2008                                  Page 8  
Due  to  the  conditions  above  mentioned  and  lack  of  supervisors,  it  was  approved  by 
respective  instances,  the  upgrading  of  gas  turbines  to  7300  HP.  That  the  process 
took  approximately  20  months,  from  the  beginning  of  the  process  until  signature  of 
the  contract.  This  due  to  different  situations  such  as:  Review  of  the  engineering 
specifications,  estaimation  of  cost,  economical  analysis,  approval  of  PDVSA  Gas 
Directors,  expires  of  documents  of  the  manufacturer  in  the  National  System 
Contractors.  
ACTIVITIES SCHEDULE. 
Activities  of  Maintenance  began  in  the  second  quarter  of  2005,  as  soon  as  the 
manufacturer gave the sets of rotors, upgrading to 7300 Hp, and all necessary spare 
parts for the Major Maintenance of 80,000 Hrs.          
Figure N2. Activities schedule. 
The figure N2, shows the execution of the activities from the phase of engineering to 
the  implantation  of  the  project,  at  the  present  moments  the  project  is  going  on;  in 
Gas Production and Handling Advances              
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29 
th
, 2008                                  Page 9  
order to upgrade all the  PGT5 gas turbine units in Jose.    
ACTIVITIES EXECUTED IN MAINTENANCE.  
From  the  beginning  of  the  maintenances,  five  (05)  Major  Maintenances  of  80,000 
hours were executed and six (06) set of rotors were upgraded. Those activities were 
contained in a Contract called  Gas Turbine Major Maintanance and  upgrading, East 
Criogenic  complex.  The  activities  incluided  in  that  contract  and  costs  are  show  in 
next figure.          
Figure N3. Activities included in the Gas Turbine major Maintenance and Upgrading, 
East criogenic Complex. 
In the first quarter of 2008 a second contract for 18 MMBsF is going to be signed, it is 
important highlight that one disadvantage was the export and import of rotors, which 
were not on time with a previuos schedule time.  
Gas Production and Handling Advances              
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29 
th
, 2008                                  Page 10  
In order to increase the power, the next specific activities were executed: 
1)  Replacement of the axial compressor antisurge valve 
 An old antisurge valve was replaced for a fast action one and greater capacity to vent 
air. In the following figures, the differences are showed:     
Figure N4. Old antisurge Valve                Figure N5. New Antisurge Valve 
2) Replacement of internal 
parts.
Figure N6. Internal Part upgrading. 
Gas Production and Handling Advances              
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29 
th
, 2008                                  Page 11  
Figure N6 shows internal parts replaced to increase the power to 7300 hp and they 
were: 0 to 5th blades stages in the housing of the axial compressor, variable nozzle 
or 2nd nozzle stage and rotors buckets. 
3) Changes in the control curves. 
Due to air flow increases, the curves of heating and acceleration change.  Parameters 
in control system are modified to fit them; some conditions that can be mentioned are: 
Increase  of  gas  combustible  pressure,  variation  in  constants  of  control  of  curves 
heating  and  acceleration,  however,  control  exhaust  temperature  is  keeping.  But,  in 
next part it will show that it is not a problem. 
TEST AND RESULTS. 
In order to demonstrate the benefits obtained with the upgarding a "Perfomance test 
is  neccesary.  This  test  takes  some  parameters  of  gas  turbine  and  compressor 
process, after they are sending to the manufaturer and through computation software 
it can determinate the performance of the machine. But, due to lack of a flow meter in 
the  gas  combustible  pipeline,  it  was  not  possible  to  do  a  test.    That  value  is  quit 
importance  for  do  the  calculations.  However,  some  tests  were  made  and  through 
observations  of  process  parameters  before  and  after.  Therefore  it  was  possible 
determined qualitatively benefits in the refrigeration system.   
 1)  Test  N 1.  Gas  turbine  7300  hp  (PGT5A)  hp  working  and  Gas  turbine  6800  hp 
PGT5 stopped.  
The  operational  parameters  observed  are  better.  The  system  has  better  pressure  in 
first stage suction, because of that; it can handle greater flow through the centrifugal 
compressor.  The  presin  can  arrive  to  20  PSI,  in  the  other  hand  with  a  PGT5  gas 
turbine  the    pressure  was  around  the  28  PSI,  being  the  normal  pressure  14,  5  PSI. 
That value represents an improvement of 55 %. 
Gas Production and Handling Advances              
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29 
th
, 2008                                  Page 12  
2) Test N2. Both units working at the same time. ( PGT5 and PGT5A). 
This test was made in two parts: 
 a) Both gas turbines at the same Speeds.  
In  this  condition  the  centrifugal  compressors  associated  to  the  PGT5A  can  handle 
greater  flow  than  the  compressor  associated  to  the  PGT5.  Also,  some  time  the 
procces antisurge valve is open. Annex N1 shows that conditions. 
b) Both gas turbines at different Speeds.  
This condition is the normal operation - when the system has one PGT5 gas turbine 
and  one  PTG5A.  With  a  review  of  parameters  data  since  the  first  upgrading,  it  was 
determinated that the gas turbine has never been in temperature control. Even when 
the  filter  house  was  with  a  high  pressure  differential,  because  of  the  exhaust 
temperature exaust were lower than ever before. 
CONCLUSIONS AND RECOMMENDATIONS.  
The tests made and the results give some benefits, obtained through the upgrading; 
in  conclusion  a  PGT5A  Gas  turbine  improves  the  conditions  in  the  refrigeration 
system. The benefits are:  
  Better succion pressure with a unit is stopped, around 55%.  
  More flexibility 
  Better conditions of exhaust temperatures. 
  Now it possible to have only one spare part stock. 
It  is  important  mentioned  that  the  time  in  exporting  and  importing  rotors  was  longer 
than scheduled, for that reason it was recommended, in meeting of high directors of 
the  manufacturing  company,  to  develop  an  infrastructure  in  Venezuela,  to  make  the 
maintenance  of  rotors  here.  Additionally  with  the  new  vision  of  the  company  in  the 
Gas Production and Handling Advances              
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29 
th
, 2008                                  Page 13  
social matter, socila project were maden and this also was exposed in that meeting.  
It  is  recommended  to  install  the  necessary  instrumentation  in  order  to  make  a 
"Perfomance Test". Then, it will be possible quantified how much power was gained. 
Finally, it is recommended to continue with the upgrading and to make the same tests 
in Jose.               
Gas Production and Handling Advances              
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29 
th
, 2008                                  Page 14        
             ANEXOS      
Gas Production and Handling Advances              
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29 
th
, 2008                                  Page 15  
Annex N 1. Operacional Parameters          
Gas Production and Handling Advances              
XVIII Gas Convention, AVPG, Caracas, Venezuela, May 27 - 29 
th
, 2008                                  Page 16  
Annex N 2. Pictures        
         Tubine Area                                                      Accesory compartment               
          Centrifugal compressor                              Combustin Chamber               
  Axial Compressor Housing                                   Axial Compressor