Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
This is a Controlled Document that complies with Wesfarmers Chemicals, Energy & Fertilisers formatting and Quality Control standards. Please check that this is the latest available version before use. Title:
MANUFACTURERS DATA REPORT (MDR) - PLANT PROJECTS EP-08-030-37
7.0 07 January 2013 Harish Chopra Manoj Thakur
Number: Version Number: Date Revised: Owner: Authoriser: Reasons for Creating or Amending Document Actual Change Details:
Full Review of Document
Control block updated
TABLE OF CONTENTS
1. 2. 3. 4. 5. 6. 6.1 6.2 6.3 6.4 6.5 6.6 6.7 6.8 INTRODUCTION ................................................................................................................................. 3 PURPOSE .............................................................................................................................................. 3 RELATED STANDARDS AND GUIDES .......................................................................................... 4 MDR PREPARATION AND SUBMISSION ..................................................................................... 4 MDR FORMAT .................................................................................................................................... 5 MDR CONTENTS ................................................................................................................................ 6 SCOPE OF WORK ........................................................................................................................... 6 SECTION 1 - DESIGN ..................................................................................................................... 6 SECTION 2 - OFF SITE FABRICATION........................................................................................ 7 SECTION 3 - SITE CONSTRUCTION AND INSTALLATION .................................................... 8 SECTION 4 - COMMISSIONING ................................................................................................... 8 SECTION 5 - EQUIPMENT TECHNICAL DATA ......................................................................... 9 SECTION 6 - DRAWINGS ............................................................................................................ 10 SECTION 7 - STATUTORY APPROVALS, REGISTRATION AND CERTIFICATES ............. 11
APPENDIX 1 - MDR CONTENTS CHECK LIST ..................................................................................... 12 SCOPE OF WORK ...................................................................................................................................... 12 SECTION 1 - DESIGN ................................................................................................................................ 12 SECTION 2 - OFF SITE FABRICATION .................................................................................................. 12
Version No. 7.0
Page 1 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
SECTION 3 - ON SITE CONSTRUCTION AND INSTALLATION ........................................................ 13 SECTION 4 - COMMISSIONING .............................................................................................................. 14 SECTION 5 - EQUIPMENT TECHNICAL DATA .................................................................................... 14 SECTION 6 - DRAWINGS ......................................................................................................................... 15 SECTION 7 - STATUTORY APPROVALS, REGISTRATION & CERTIFICATES ............................... 15 APPENDIX 2 FILE NAMING CONVENTION OF TECHNICAL DATA SHEETS & EQUIPMENT MAINTENANCE MANUALS ...................................................................................................................... 17 APPENDIX 3 EXAMPLE EQUIPMENT PARTS LIST ......................................................................... 18
Version No. 7.0
Page 2 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
1.
INTRODUCTION
The Manufacturers Data Report (MDR) is the compilation of all the technical details and records of activities performed by a contractor as part of an engineering construction or modification project. This may include any of the following activities. a. b. c. d. e. Design Supply of materials, proprietary plant and equipment Off site fabrication, surface treatment, assembly On site construction, assembly, erection and installation of plant and equipment Inspection, testing, and commissioning.
The MDR is provided by a Contractor to the Superintendent on completion of the Work under the Contract, usually as a precondition to the issue of the Certificate of Practical Completion. The primary purpose of the MDR is to provide CSBP with the information required to safely operate the plant and equipment provided under the contract and to service and maintain the equipment to achieve reliable operation over its expected life. The MDR also serves as a historical record and can be useful in helping to identify the cause of problems with quality, performance or reliability of the plant and equipment later in its life.
2.
PURPOSE
The purpose of this procedure is to define the requirements for preparation and submission of a MDR, and to provide a contents checklist for typical engineering projects. This document is focussed primarily to mechanical engineering contracts which include design, supply of equipment, off site fabrication, site installation and commissioning of mechanical equipment and piping. It is also relevant to civil, structural, electrical and instrumentation works, and should be used as a guide to format the MDR for these works. Note: It is usual for special equipment items such as pumps, control valves, and relief valves to be purchased by CSBP's Project Responsible Officer and free-issued to the contractor for installation. The technical data for these free-issued items will be assembled by the CSBP Responsible Officer and passed on to Reliability Support and to the CSBP Customer in the form of an MDR as described in this document.
Version No. 7.0
Page 3 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
3.
RELATED STANDARDS AND GUIDES
The following CSBP documents shall form the basis of MDR requirements. a. b. c. Technical Data Requirements for Plant and Equipment (GM-05-043-01) Equipment Numbering System (ES-14-101-06) Technical Data Sheets - Mechanical, Electrical and Instrumentation (ES-14-101-12). (These sheets should be provided to the Contractor early in the project to ensure standardisation of presentation of information) Fabrication and Installation of Piping (ES-14-602-01) Inspection and Testing of Piping Systems (ES-14-602-02) CSBP Stage 1 Commissioning Inspection Report and Stage 2 Commissioning Test Report forms. Note: These forms are available in Dom.doc in Business Support - Engineering Engineering Forms - Commissioning Reports g. h. i. j. Repairs and Minor Alterations to Existing Pressure Equipment, Piping and Tanks (DP-05095-06) Major Alterations and Replacement to Existing Pressure Equipment, Piping and Tanks (DP-05-095-08) Drawing Preparation (ES-14-101-03 Testing and Commissioning of Electrical and Instrumentation Installations (ES-14-902-02).
d. e. f.
4.
MDR PREPARATION AND SUBMISSION
The Contractor shall compile an MDR for the contract work in the format detailed in 5. below. For large complex projects, the MDR may be submitted in several parts, for example, MDR for off-site manufacture and supplied equipment, MDR for on-site installation, erection and pre-commissioning; MDR for commissioning. In addition, operational information shall be filed separately to QA/QC information. For larger, multi discipline projects, separate MDRs shall be produced for each discipline eg MDR for Civil Works, MDR for equipment supply/fabrication/assembly, MDR for mechanical installation, MDR for Electrical Installation. The Contractor and the Superintendent will review the check list provided in Appendix 1 at an early stage of the contract to agree the content of the MDR. The MDR shall be progressively compiled during the course of the work and kept up to date as the work progresses so that delivery of the MDR is not delayed at the completion of the work. Presentation of the required number of copies of a full and comprehensive MDR at the conclusion of construction is a contractual requirement under all CSBP engineering contracts and, unless
Version No. 7.0
Page 4 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
specifically stated otherwise in the contract, is a precondition for the issue of the Certificate of Practical Completion to the Contractor and payment of a certain percentage of the contract sum. The MDR shall be presented to the Superintendent for review upon request to ensure compliance to the Contract requirements and to ensure that progressive compilation is being maintained. Initially, a single draft copy shall be submitted for review and approval by the Superintendent. MDR documentation covering fabrication, welding, heat treatment and testing of pressure piping or pressure equipment shall be submitted to and approved by the CSBP Senior Inspector before final acceptance by the Superintendent. On approval of the draft copy of the MDR, one final hardcopy of the MDR shall be prepared and submitted by the contractor. An electronic copy shall also be supplied by the Contractor. The hard copy of the MDR shall be distributed by the CSBP Responsible Officer to the CSBP Customer. The electronic MDR documents shall be submitted to the CSBP Responsible Officer who shall provide copies for: the CSBP Customer CSBP Project Electronic Filing System and/or Electronic Document Management System CSBP Reliability Support
5.
MDR FORMAT
The hard copy of the MDR shall be prepared by the Contractor in one or more hard cover, A4 size, loose leaf, lever arch binders, with file separators clearly segregating each section. The MDR shall have a detailed table of contents at the front of each of the binders. The outside front cover and spine of the binders shall be identified with: The name of the Project Manufacturer's Data Report for Manufacture (or installation, etc, as applicable) The description of the subject work The CSBP Contract or Purchase Order number
All documents for inclusion in MDR shall be written in the English language, in SI units, shall be complete and shall be originals or clearly legible copies. Documents and drawings larger than A4 size, which cannot be reduced clearly, shall be folded into A4 plastic pockets. MDRs shall be divided into the sections described below, as appropriate, and each section shall be divided by tabbed separator sheets. All of the separator sheet tabs shall carry the applicable section number and the title of the section. If a particular section is not applicable, the section may be omitted. The electronic copy of the MDR shall be prepared by the Contractor and include all documents contained in the hard copy.
Version No. 7.0
Page 5 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
The electronic MDR shall be in a similar folder structure as the approved hard copy but with additional sub-folders for grouping of associated documents. Individual electronic files shall be provided for all documents and grouped by equipment number and discipline. Large single PDF MDR files, containing all documents, will not be accepted. Documents pertaining to quality assurance are to clearly legible scanned copies of original documents (material certificates and material test reports, etc.). Documents that may need to be maintained and updated post construction/commissioning shall be supplied in an editable electronic format (Word, Excel, etc). All drawings shall be in fully functional AutoCAD compatible format. 3D CAD models and where applicable model databases, shall be supplied in native format. Where the native format is not AutoCAD dwg or dxf a separated web-friendly reduced file size format such as Navisworks or similar format, for which a cost-free viewer is available, shall be provided in addition to the native format files.
6.
MDR CONTENTS
The MDR shall be divided into the sections described below, as appropriate to the scope of the contract. The check list attached as Appendix 1 should be reviewed to check that all relevant documents for each aspect of the work have been included in the relevant section of the MDR as detailed below and in Appendix 1. If not already covered in this procedure, MDRs shall also contain those documents identified in the approved Inspection and Test Plan / Inspection and Test Program for the subject work as well as those identified in Contract/Order and in the applicable codes, Standards and legislation.
6.1
SCOPE OF WORK
Insert as the front of MDR a brief description of the contract Scope of Work applicable to the MDR.
6.2
SECTION 1 - DESIGN
This section shall include all design calculations required to be submitted under the contract including design criteria, assumptions made and any references for design method selected. Calculations shall be sufficiently detailed to enable independent verification. Copies of all technical queries and their replies shall be included. Details of any authorised deviations from the contract specifications and the reasons for the deviations shall be included. Lists of all equipment, valves, pipelines and vessels provided by the contractor shall be included for reference.
Version No. 7.0
Page 6 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
6.3
SECTION 2 - OFF SITE FABRICATION
This section shall contain records of all activities associated with off site fabrication and assembly of materials and equipment to be incorporated into the works. The extent of the information to be included in the MDR will depend on the requirements of the contract. 6.3.1 Material Certificates and Test Reports
Where material traceability is required under the contract, this section shall contain an indexed list identifying material certificates and material test reports referenced to the locations of the materials used by their part, piece or item number and the applicable drawing(s). The material certificates and traceability shall include welding consumables. A copy of the certificates and reports shall be included in this section of the MDR indicating the certificate or report number, Heat, lot, plate number, etc, and the name of Mill. For clarity, the section shall also contain a drawing of the equipment or piping marked up to show the certificate number and heat number for the materials used at each location. 6.3.2 Weld Records
Details of all welding procedures and qualifications relevant to the subject work, including evidence of CSBP's approval, shall be included in this section. If more than one welder is used, then traceability sheets and / or marked up drawings, sketches or maps shall be included to identify the welder responsible for each weld, and what WPS was used. 6.3.3 Non Destructive Examination (NDE)
This section shall include a list of all NDE carried out on the subject works. The listing shall include for each test location, the type of NDE, the NDE procedure, the NDE report number and the result of the examination. The listing may be incorporated into the welding control and record sheets. The section shall include a marked up drawing, sketch or map to identify the NDE report numbers relevant to each test location together with a copy of all NDE certificates/reports in the order in which they are included in the above list. The section shall also include a list of all non-destructive testing personnel employed on the subject work and evidence of their qualifications. 6.3.4 Heat Treatment
If applicable, certificates and properly scaled furnace charts for all heat treatment performed shall be included. Charts shall include the complete heat treatment cycle including heating, soak period and cooling. The charts shall clearly show the calibrated temperature and time scales and provide a reference to the heat treatment procedure and to the specific item or weld that was heat treated. The charts shall be dated and signed by the person responsible for verifying the correctness of the heating cycle.
Version No. 7.0
Page 7 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
Traceability sheets and / or marked up drawings, sketches or maps shall be included to identify the heat treatment charts relevant to each weld or item being heat treated. 6.3.5 Hydrostatic Testing
Where required by the contract, records of hydrostatic testing performed offsite, along with supporting documentation such as NATA test certificates for test gauges, shall be included in this section of the MDR. Stage 1 Commissioning inspection report forms should be completed prior to the commencement of such tests, and be included in this section of the MDR, whether included in the ITP or not. 6.3.6 Combination of Traceability Information
The traceability sheets and drawings, sketches or maps for material certificates, welder identification, NDT and heat treatment may be combined partially, or fully, in a format to be approved by the Superintendent.
6.4
SECTION 3 - SITE CONSTRUCTION AND INSTALLATION
This section shall contain records of all activities associated with site fabrication, assembly, installation and construction and Stage 1 commissioning of materials, plant and equipment incorporated into the works. Material traceability information, weld records, non destructive examination records, heat treatments records, etc, as detailed in 6.2 above and in Appendix 1, when applicable to the work done on site, shall be included in this section of the MDR. This section shall contain a copy of the approved ITP with evidence that the Contractor has complied with the ITP. Evidence of compliance shall be by signature of the persons responsible for verifying satisfactory performance of the identified inspections and tests in the relevant spaces provided in the ITP. Where applicable, this shall include the Superintendent and the Owner's inspector. This section shall contain all those inspection and test records required by the ITP except for those that are identified for inclusion in other sections of the MDR. Where a standard CSBP Stage 1 Commissioning Inspection Report form is available for a particular item of equipment, the form shall be completed and included in this section of the MDR, whether indicated in the ITP or not. The records shall be filed in this section in the order in which they are identified on the ITP, or in some other logical order, clearly referenced to the particular inspection or test stage identified on the ITP.
6.5
SECTION 4 - COMMISSIONING
This section shall contain records of all activities associated with Stage 2 and Stage 3 commissioning.
Version No. 7.0
Page 8 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
Where a standard CSBP Stage 2 Commissioning Test Report form is available for a particular item of equipment, the form shall be completed and included in this section of the MDR, whether indicated in the ITP or not. The records shall be filed in this section of the MDR in the order in which they are identified on the ITP, or in some other logical order, clearly referenced to the particular inspection or test stage identified on the ITP.
6.6
SECTION 5 - EQUIPMENT TECHNICAL DATA
This section shall contain technical information for all items of equipment supplied under the contract to allow ongoing operation, servicing and maintenance to be carried out. 6.6.1 Technical Data Sheets
Individual Technical Data Sheets shall be provided for each maintainable equipment item in an editable electronic format. Technical data in this section should address service conditions and operating parameters, e.g. temperatures, pressures, etc. This information should contain sufficient detail to enable purchase of a replacement equipment assemblies and items able to perform the same function even if from another manufacturer. Name plate details for tanks, vessels, heat exchangers, etc., should also be included in this section of the MDR. Supplier Technical Data Sheet can be used or blank CSBP Technical Data Sheets can be sourced from Technical Data Sheets - Mechanical, Electrical and Instrument (ES-14-101-12) The file naming convention shall be in accordance with APPENDIX 1 - File naming convention of technical data sheets & equipment maintenance manuals 6.6.2 Equipment Parts
A complete parts list shall be supplied for each maintainable equipment assembly together with a drawing showing a complete breakdown of all parts. The parts list is indicate the quantity of each part required and the manufacturers part number. Any specific overhaul / repair kit must also have a part number and identify the items comprising the kit. Detail of each part shall contain sufficient information to uniquely identify, catalogue and purchase the parts. The equipment parts list for each maintainable equipment item should detail, but not be limited to the following: CSBP Equipment Number, original manufacturers part name and number, Vendors part name and number, part description, quantity, recommended stock levels, lead time (in days) to obtain, cost of each item (in Australian Dollars), and
Version No. 7.0
Page 9 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
Vendors name and contact details.
An example of an Equipment Parts List form and information required is contained in Technical Data Requirements for Plant and Equipment (GM-05-043-01), Appendix 3 Dimensional details of all non-proprietary parts shall be provided by the Contractor, to allow CSBP to source replacements at a competitive price e.g. bearings, gaskets, oil-seals, packing materials, etc. Detailed drawings for all purpose-built parts, unavailable off-the-shelf, shall be included in this section, specifying materials and all dimensions required to manufacture a replacement. E.g. gaskets for heat exchanger end covers, non-standard pipework components, etc. Nozzle drawings, showing flange details, should also be included in this section, to assist in linking gaskets to items of equipment. 6.6.3 Installation, Operating and Maintenance Manuals
Commissioning, Operating and Maintenance Manuals shall be included for all items provided under the contract in sufficient detail to enable CSBP to safely and reliably commission, start up, operate, service, maintain and overhaul the items supplied by the contractor. The file naming convention shall be in accordance with APPENDIX 1 - File naming convention of technical data sheets & equipment maintenance manuals
6.7
6.7.1
SECTION 6 - DRAWINGS
Drawing List
A complete list of all drawings including revision numbers produced by the Contractor for construction purposes, and which have been passed to CSBPs drawing office for electronic storage, shall be included in this section of the MDR. 6.7.2 Vendor Drawings
Vendor drawings including assembly and sectional drawings showing details of overall width, height, base-to-shaft centres, base plate holes, etc, shall be provided with the MDR. 6.7.3 As-built Drawings
As-built drawings shall be provided with the MDR. All drawings including original and all As Built revisions are to be supplied in fully functional (native) AutoCAD dwg format unless otherwise approved by the Superintendent. As-built details shall be marked up with a red pen onto a paper copy of the contract drawing to clearly show changes that were made during manufacture or construction and to record any particular details not included in the original drawings. In particular, the exact location of buried pipework or buried other services shall be accurately recorded. All As Built drawings shall conform to Drawing Preparation (ES-14-101-03)
Version No. 7.0
Page 10 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
6.7.4
3D Model
3D CAD models and/or model databases shall be supplied as detailed in section 5.0 above.
6.8
SECTION 7 - STATUTORY APPROVALS, REGISTRATION AND CERTIFICATES
This section shall list the various parts, equipment, materials and activities which require statutory approval and registration. Evidence of the required approval and compliance for each item shall be included in this Section.
Version No. 7.0
Page 11 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
APPENDIX 1 - MDR CONTENTS CHECK LIST
SCOPE OF WORK
Insert a brief description of the contract Scope of Work applicable to the MDR at the front of MDR.
SECTION 1 - DESIGN
a. b. c. d. e. f. g. h. i. Design calculations Technical Queries Authorised Deviations Equipment lists Valve List Pipeline lists Pressure Vessel List Instrument List Motor List
SECTION 2 - OFF SITE FABRICATION
Fabrication and Welding of Pressure Vessels, Pipe Spools and Steelwork a. b. c. d. e. f. g. h. i. j. k. l. m. n. o. p. q. r. Signed off ITPs for each stage of the work Material Certificates, including all items directly welded to piping or pressure vessels Material and consumable map for traceability Consumables Certificates Weld Procedure Records (WPR) Weld Procedure Qualification Records (WPQR) Welder Qualification Records (WQR) Material Heat Traceability Records Inspection and Non Destructive Testing (NDT) Records Weld maps identifying NDT records against location Weld maps identifying welders and WPS used for each weld Hardness Test Records (to be included in NDT traceability) Heat Treatment Records Map for identifying heat treatment records against welds and/or location Pressure Test Records Pressure Test instrument calibration records (NATA) Stage 1 Pre-commissioning Inspection Reports completed prior to pressure tests Non-conformances, concessions and technical queries
Version No. 7.0
Page 12 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
Valves a. b. a. b. Test Certificates Material Certificates Surface preparation Records Coating application and thickness records
Surface Treatment and Protective Coatings
SECTION 3 - ON SITE CONSTRUCTION AND INSTALLATION
Inspection and Test Plans (ITPs) a. Civil Works a. Earthworks 1. 2. 3. b. 1. 2. 3. 4. 5. c. 1. a. a. b. Piping a. b. c. d. e. f. Approved repair procedure as per DP-05-095-06 for welded tie-ins to existing piping and equipment Welding Procedure Specifications / WPQR Welder Qualifications Records Material Heat Number Index Material Certificates Material and consumable map for traceability Survey and set out records Backfill Checklist Compaction Checklist Formwork Inspection and Pre-Pour Records Concrete Placing Records Concrete Delivery Dockets Reinforcing Schedule Coating record sheets Compressive Strength Testing Signed off ITPs for each stage of the work
Concrete Works
Concrete Testing
Structural Steel Erection Installation record sheets Pre-commissioning Inspection Reports Pump alignment records Mechanical Equipment Installation
Version No. 7.0
Page 13 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
g. h. i. j. k. l. m. n. o. p.
Weld Maps for welder, WPS and NDT traceability Weld & Material Heat Number Traceability Records Non Destructive Testing (NDT) Records Post Weld Heat Treatment (PWHT) Records PWHT traceability maps Hardness Test Records (include in NDT traceability) Pressure Testing Records and test packs, including NATA calibration certificates for test instruments Completed Punch-lists Non-conformances, concessions and technical queries Stage 1 Pre-commissioning Inspection Reports
Insulation / Cladding Records Refractory Inspection and Test Records Electrical and Instrument installation records a. b. c. d. e. f. a. Commissioning Test Reports as detailed in CSBP Engineering Standard ES-14902-02 Testing and Commissioning of Electrical and Instrumentation Installations Cable Test Result Sheets Instrument Calibration Record Sheets Loop Check Sheets Hazardous Area Check Sheets Trip Settings Record Sheets Test equipment certificates
Miscellaneous Records
SECTION 4 - COMMISSIONING
a. b. c. d. Approved commissioning procedure Stage 2 Dry Commissioning Test Reports Stage 3 Wet Commissioning records Completed punchlists resulting from b and c.
SECTION 5 - EQUIPMENT TECHNICAL DATA
Vendor details a. b. c. Equipment number and description Vendor and Order number Vendor contact details (address, telephone number, fax number, email address, contact name)
Technical Data
Version No. 7.0
Page 14 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
a. b. c. d. e. a. b. c. d. e. f. g. h. i. j. k. l.
Technical Data Sheets Equipment Parts Lists Name Plate Details Test certificates Calibration certificates General Information Safety Precautions Assembly and Installation Instructions Start-up Procedures Maintenance and inspection requirements, intervals, checks, etc Lubrication schedules including grease and oil types, quantities Repair / Overhaul Procedures Assembly Torque settings Storage instructions Test Certificates Recommended Spare Parts Lists Calibration procedures
Operating and Maintenance Information
SECTION 6 - DRAWINGS
a. b. c. d. e. f. g. Drawing List including revision number General arrangement drawings Layout drawings Marking plans Vendor drawings Assembly drawings As-Built Drawings 1. 2. 3. h. Piping isometrics and details Buried pipe and services Red pen markups to contract drawings
3D model(s)
SECTION 7 - STATUTORY APPROVALS, REGISTRATION & CERTIFICATES
a. b. c. Pressure Vessel Design Registration details Lifting equipment certification Development approval and Building license
Version No. 7.0
Page 15 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
d. e. f.
Gas and electrical installation certificates Electrical equipment hazardous area rating certification Test certificates for pressure safety valves and bursting disks
Version No. 7.0
Page 16 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
APPENDIX 2 FILE NAMING CONVENTION OF TECHNICAL DATA SHEETS & EQUIPMENT MAINTENANCE MANUALS
Domino - File Name The file name is to be the full equipment number (no gaps or dashes), as per engineering standard: Equipment Numbering System (ES-14-101-06); followed immediately by a dash and the initials TDS or EMM, as applicable.
EXAMPLES: 1162P1012-TDS 1100TX0006-TDS 1166LT0507-TDS 1162P1012-EMM 1100TX0006-EMM 1166LT0507-EMM
Note:
If there are multi technical data sheets or equipment maintenance manuals for a specific item of equipment, each data sheet or manual should be given a unique identifier as per the following examples:
1124X0821-TDS-01 (tech data sheet 1) 1124X0821-TDS-02 (tech data sheet 2) etc 1124X0821-EMM-01 (manual 1) 1124X0821-EMM-02 (manual 2) etc
Domino - Technical Data Sheet Title The title is to comprise the Equipment Number; and the Equipment Type / Duty Description. Note:
(space dash space is required between equipment number & equipment type / duty description). 1162P1012 - Pump Cooling Tower Water 1100TX0006 - Transformer Compound Despatch (Q205) 1166LT0507 - Level Compactor Hopper
EXAMPLES:
Domino - Equipment Maintenance Manual Title For Generic manuals the title is to comprise the Manufacturers Name; Equipment Type and Model Number.
EXAMPLE: Lightnin Mixer 15Q-3
For manuals that are specific for and reference the CSBP Equipment Number, the title is to comprise the CSBP Equipment Number; Manufacturers Name; Equipment Type and Model Number.
EXAMPLE: 1162M0261 - Lightnin Mixer 15Q-3
Note:
space dash space is required between CSBPs equipment number and the Manufacturers name.
Version No. 7.0
Page 17 of 18
Document last modified: 07 January 2013. PDF created: 06 February 2013.
Manufacturers Data Report (MDR) - Plant Projects EP-08-030-37
APPENDIX 3 EXAMPLE EQUIPMENT PARTS LIST
The recommended equipment spare parts list for each maintainable equipment item should detail, but not be limited to the following:
Ln#
CSBP Equipment Number
Lvl
Original Manufacturers Part Number
Original Manufacturer Part Description
Manufacturer
uantit!
"OM
#ecom men$e$ stoc% levels 1
Lea$ time &Da!s'
"nit Cost &()"D'
*en$ors name an$ contact $etails &p+one an$ email'
1150PIT2201
EJA110A-EMS4B 94EB/SU2/X1 -92!0AM
TRANSMITTER; DP;
ACME
EA
90
$3,500.00
ACME, JOE BLO ,1!00 555 112, ".#$%&'()*+.)%*.(, ACME, JOE BLO ,1!00 555 112, ".#$%&'()*+.)%*.(, ACME, JOE BLO ,1!00 555 112, ".#$%&'()*+.)%*.(, ACME, JOE BLO ,1!00 555 112, ".#$%&'()*+.)%*.(, CITE6EN, 7JO5N MURP548, 0499929992, J.*,/:;<')=0=>+?.)%*
1150PIT2201
O-RIN., PROCESS -LAN.E
ACME
P+/ SET
2 S+01
14
$20.00
1150PIT2201
D0114RB
.AS3ET; -LAN.E; TE-LON
ACME
P+/ SET
4 S+01
14
$25.00
1150TIT2202
4TA110-EA4DB/X1 A--3NE-BE-3B-S-2-02-5T-R115
TRANSMITTER TEMPEARTURE
ACME
EA
20
$2,000.00
1150TIT2202
3 T4PE T5ERMOCOUPLE
CITE6EN
EA
$120.00
2 ! 9 9
Version No. 7.0
Page 18 of 18 Document last modified: 07 January 2013. Date printed: 06 February 2013.