MUD BRICK (ADOBE) CONSTRUCTION
Contents 
Background .......................................................................................................................................... 2 
Resources ............................................................................................................................................ 3 
Advantages and Disadvantages ...................................................................................................... 4 
Structural Considerations ............................................................................................................... 6 
Resistance to Erosion by Rainfall .................................................................................................. 8 
Case Studies ..................................................................................................................................... 12 
 
 
 
The information presented in this module is for general guidance only for those considering the 
use of mud brick construction and Engineers Without Borders strongly recommends that advice 
be sought from a suitably qualified engineer for particular projects. 
This module has been prepared by Dr Kevan Heathcote (Kevan.Heathcote@gmail.com) based on 
his experience in earth building and his research into earth wall durability.  He was a member 
of  the  standards  committee  which  produced  New  Zealand  standard  NZS  4297  Engineering 
Design of Earth Buildings.  The sections on structural considerations and resistance to erosion 
have been based on that standard and on Dr Heathcotes experience and have been simplified 
to reflect the low technology inherent in mud brick construction. 
   
Background 
Unstabilised  mud  bricks  are  made  by  mixing  wet  clayey  soil  with  straw  and  forming  them  into 
brick  shaped  molds.    The  molds  are  then  removed  and  the  bricks  allowed  to  dry  in  the  sun.  
Adobe  bricks  are  typically  250mm  by  350mm  by  100mm  and  are  laid  flat  to  produce  250  mm 
thick  walls.    Their  mass  is  around  14  kg  (density  around  1600  kg/m
3
)  and  mortar  of  similar 
material is used to build walls.  Mud bricks are made from low clay content soils stabilised with 
bitumen  emulsion  in  New  Mexico  but  in  other  areas  unstabilised  bricks  are  made  from  higher 
clay content soils. 
Next  to  timber  mud  brick  construction  is  the  oldest  construction  technique  in  the  world, 
originating  in  biblical  times  in  Mesopotamia.    Whilst  it  is  a  common  form  of  low  cost 
construction in low rainfall areas such as the  Middle East (Egypt, Yemen, Iran, Irak, Pakistan, 
India and Afganistan) and parts of China it is also historically common in higher rainfall regions 
such  as  the  Andes  regions  of  South  America,  Spain  and  Portugal.    Adobe  itself  is  an  Arabic 
word and we can assume that this type of construction was transferred to Spain by the Arab 
conquest  and  was  then  taken  by  the  Spanish  to  their  colonies  in  South  America.    Mud  brick 
construction  is  prevalent  in  New  Mexico  and  the  style  of  construction  there  is  commonly 
referred to as the Adobe style.  More recently mud brick construction has been revived as an 
environmentally  sympathetic  material  in  places  such  as  the  southern  states  of  Australia  and 
New Zealand. 
     900 Year Old Taos Pueblo in New Mexico           Mud Brick House in Australia 
Traditionally mud brick construction has relied on external renders for protection from the 
weather in relatively low rainfall areas (repaired each year in the case of the Taos Pueblo) or 
on large roof overhangs in higher rainfall areas to prevent rainfall damage.   
 
Resources 
  Building with earth bricks & rammed earth in Australia, Earth Building Association of 
Australia (EBAA), no date.  EBAA has been established for some time and has a lot of 
experience in this area.  See http://www.ebaa.asn.au/ 
  Bulletin 5  Earth-Wall Construction (4
th
 Ed) National Building Technology Centre, 1987. 
Used to be referenced in the Building Code of Australia as the de-facto standard but 
removed in 2008.  Earth building for BCA now requires an earth building to be certified 
by an expert person  
  Adobe bricks in New Mexico, Edward W. Smith, New Mexico Bureau of Mines and 
Mineral Resources, 1982  Comprehensive technical coverage of adobe building in New 
Mexico. 
  The Earthbuilders Encyclopedia by Joseph M. Tibbets, Southwest Solaradobe School, 
New Mexico, 1988.  Detailed coverage of all aspects of earth building with particular 
reference to New Mexico. 
  Dirt Cheap  The Mud Brick Book, John and Jerry Archer,Compendium, 1976. Practical 
construction handbook from Australia 
  Making the Adobe Brick, Eugene H. Boudreau, Fifth Street Press, 1971. Practical 
construction handbook from the USA 
  New Zealand Earth Building Standards NZS 4297:1998 Engineering Design of Earth 
Buildings, NZS 4298:1998 Materials and Workmanship For Earth Buildingsand NZS 
4299:1998 Earth Buildings Not Requiring Specific Design  very comprehensive set, 
NZS 4297 probably too detailed for mud brick construction though. 
  http://www.youtube.com/watch?v=qCEdDM-c7RQ Video of owner builder construction 
of mud brick house in South Africa. 
 
Mud Bricks Drying (Source virginmedia.com) 
Advantages and Disadvantages 
The advantages of mud brick construction are 
  Well designed mud brick buildings look warm and inviting 
  Mud  brick  manufacture  utilises  the  natural  material  of  the  site  and  requires  no 
artificial additives (except bitumen when that is used as a stabiliser). 
  Mud  brick  manufacture  need  not  require  mechanical  equipment  and  has  negligible 
embodied energy if material sourced at site. 
  The technology is very simple and almost anyone can build in this material. 
 
  Because they have high thermal mass mud brick buildings are very effective in reducing 
temperature  swings  in  climates  where  the  daily  temperature  swings  are  large.    When 
combined  with good passive  solar design  mud brick houses are  extremely comfortable, 
warm in winter and cool in summer. 
  Unreinforced  round  mud  brick  buildings  have  good  earthquake  resistance.    See  B. 
Samali, W. Jinwuth, K. Heathcote, and C. Wang,  Seismic Capacity Comparison between 
Square  and  Circular  Plan  Adobe  Construction,    The  Twelfth  East  Asia-Pacific 
Conference  on  Structural  Engineering  and  Construction,  January  26-28,  2011,  Hong 
Kong SAR, China 
 
   
 
The main disadvantages are 
  Unreinforced rectangular mud brick buildings perform extremely poorly in earthquakes.   
In  the  2003  earthquake  in  Bam,  Iran  many  mud  brick  buildings  were  completely 
destroyed.  Note however that Dominic Dowling of UTS in Sydney has devised a system 
of  reinforcing  rectangular  mud  brick  buildings  with  bamboo  to  withstand  earthquakes.  
See  http://www.thinkbigmagazine.com/mindset/258-earthquake-proof-housing  and    
www.world-housing.net/uploads/WHETutorial_Adobe_English.pdf  
 
  The  insulation  properties  of  earth  walls  is  not  good  (R  approximately  0.5  m
2
K/W  for 
250  thick  walls)  and  therefore  thermal  performance  is  poor  in  very  hot  or  very  cold 
climates with small daily temperature fluctuations. 
  Local  soils  are  not  always  suitable  for  use  or  straw  or  bitumen  may  not  be  readily 
available. 
  Can  require  frequent  maintenance  if  exposed  to  extreme  weather  unless  stabilised  or 
rendered. 
  Drying of bricks prior to laying can be a problem in areas of high humidity. 
 
   
Structural Considerations 
  Soil  Composition    In  general  mud  bricks  can  be  made  with  most  soils  having  clay 
contents between 5% and 45% and with at least 30% sand and not more than 50% silt. 
In  Australia  and  New  Zealand  mud  brick  soils  tend  to  have  clay  contents  in  the  upper 
range  with  straw  added  to  reduce  shrinkage  cracks.    In  New  Mexico  there  is  a 
requirement  for  soils  to  have  at  least  50%  sand  to  reduce  cracking  and  clay  contents 
are  generally  in  the  lower  range.    These  bricks  are  typically  stabilised  with  bitumen 
emulsion  (5-12%  by  mass)  to  prevent  excessive  water  absorption.      The  figure  below 
shows the general range of soil types used but in the end an acceptable soil is one that 
produces bricks which are suitable for their exposure environment (see rainfall erosion 
resistance below) 
 
  Foundations  Foundations can be the most expensive part of the  construction if made 
of concrete.  For stable soils 400 wide by 300 deep footings are needed with 2  /12 mm 
diameter reinforcement bars top and bottom.  For moderately reactive soils  the depth 
needs  to  be  600  mm  with  4  bars  top  and  bottom.    For  more  detail  see  AS2870 
Residential  Slabs  and  Footings.    Alternatives  to  concrete  on  stable  soils  can  be  stone 
slabs  or  small  pieces  placed  in  wire  boxes  (gabions)  and  in  some  cases  the  natural  soil 
stabilised with 10-15% cement may be suitable.  For all footings a durable plinth such as 
fire  clayed  bricks,  rendered  stone  or  mud  bricks  with  10-15%  cement  should  be 
constructed to provide  protection from splashing rain at the base of the  wall.  Such a 
plinth should be at least 225 mm above ground level. 
  Compressive  Strength  of  Walls    the  overall  compressive  strength  of  load  bearing 
walls is generally not a problem with light roof loads. The compressive strength of mud 
brick walls may be assumed to be 0.5 MPa, provided individual bricks do not break when 
dropped  from  waist  high  onto  a  hard  surface  (See  EBAA  reference  in  Resources 
section).  Load factors of 1.2 for dead load and 1.5 for live load should be used together 
with  a  capacity  reduction  factor  ()  of  0.6  (If  all  loads  are  dead  loads  this  gives  an 
allowable stress of 0.25 MPa).  Reduction factors of [1-2.3(eccentricity of load/wall 
thickness)]  should  be  applied  for  eccentric  loads  and  [1.18-0.03(wall  height/wall 
thickness)] for wall height (maximum 1.0).  Wall heights should not be greater than [12 
wall thickness] for walls supported at the top and bottom and 6 for free standing walls. 
For  localised  bearing  stresses  such  as  lintels  compressive  stress  of  1  MPa  can  be 
assumed  but  it  must  be  remembered  that  lintels  should  be  stiff  enough  to  provide  an 
even bearing.  A timber top plate is usually provided on the top of walls to spread the 
roof loads and concentrated loads should receive special attention. 
  In-Plane Shear Strength of Walls a wall shear stress of 0.035 MPa can be assumed 
for determining resistance to wind loading (shear walls) and low earthquake loading.  
  Out-Of-Plane Loads - for determining resistance to wind loading it is suggested that a 
yield  line  approach  be  used  with    =  0.6  and  a  flexural  tensile  strength  of  0.1  MPa 
(100  kPa).    [For  a  long  wall  the  yield  line  method  gives  M
y
  =  wH
2
/8  and  for  a  square 
panel M
y
 = wH
2
/24] 
As  an  example  consider  a  3  metre  by  3  metre  panel  which  is  250  thick 
M
capacity
 = 0.61000.25
2
/6 = 0.625 kN.m/m 
M
yield
 = w3
2
/24 = 0.375w 
Equating the two gives an ultimate wind load resistance of 1.67 kPa  (0.5 kPa for a long 
3 metre high wall). 
This  approach  can  also  be  adopted  to  give  a  guide  to  the  resistance  of  rectangular 
buildings  to  low  earthquake  loading,  bearing  in  mind  that  the  corners  of  rectangular 
buildings  are  the  main  weak  points  in  out  of  plane  loading  (and  need  to  be  well 
reinforced). 
For example the above wall has a mass of around 400 kg/m
2
 (Density of 1600kg/m
3
) 
In this case w = 400a/9.8 = 40.82a  giving M
yield
 of 15.3a kN.m  which when equated 
to a wall capacity of 0.625 kN.m gives an earthquake resistance of 0.04g 
For  a  more  detailed  analysis  of  earthquake  loading  refer  to  Appendix  B  of  NZS 
4287:1998 
  Quality Control  at least one brick for every 1000 used should be subjected to the 
drop strength test (see above) and one brick in every 2500 should be assessed for 
resistance to rainfall (see below) where walls are to be exposed to the weather.  
 
Resistance to Erosion by Rainfall 
The  resistance  of  mud  brick  walls  to  rainfall  depends  on  the  composition  of  the  soil,  the 
intensity  of  wind-driven  rain  and  on  the  exposure  of  the  wall.    In  general  it  is  best  to  avoid 
exposure  by  providing  wide  eaves  to  buildings,  although  some  soils  produce  bricks  that  are 
remarkably  resistant  to  erosion  by  wind-driven  rain.    External  coatings  such  as  renders  or 
linseed oil may be used to improve erosion resistance but these may require frequent renewal. 
Walls  that  are  not  protected  from  the  weather  or  otherwise  coated  with  a  proven  erosion 
resistant  coating  shall  be  of  sufficient  durability  to  withstand  the  effect  of  driving  rain 
appropriate to their exposure situation. Such durability may be verified as follows. 
a)  Wall  exposure  situations  shall  be  classified  as  Exposure  Category  1  to  7  according  to  the 
following Table. 
  Typical Wind Speed During Rainfall 
Annual Rainfall (mm)  Low  Medium   High 
<600 mm  1  3  5 
600-899 mm  2  4  6 
900-1300 mm  3  5  7 
Where  eaves  extend  away  from  the  wall  greater  than  one  quarter  of  the  wall  height  an 
Exposure Category one less  than  given  by the above table  may  be assumed  with  a  minimum 
Exposure Category of 1. Where  eaves  extend  away  from  the  wall greater than one  half  of 
the  wall  height  an  Exposure  Category  two  less  than  given  by  the  above  table  may  be 
assumed with a minimum Exposure Category of 1. 
b)  Resistance  of  walls  to  erosion  due  to  driving  rain  shall  be  indicated  by  a  Test 
Resistance Number (TRN) determined for samples subjected to the Geelong Drip test in the 
case  of  walls  of  Exposure  Categories  1-3  and  by  the  UTS  Spray  Test  for  Exposure 
Categories  4-7  Wall  samples  shall  have  a  TRN  greater  than  or  equal  to  their  Exposure 
Category to be considered acceptable. 
 
NOTE:  To  the  best  of  available  knowledge  walls  that  meet  the  above  criteria  may  in 
normal circumstances be expected to have an acceptable (less than 15 mm) erosion over a 
50  year  period.  In  the  event  that  the  Designer  of  the  building  requires  a  better 
performance the required TRN of the wall material shall be  stated on the drawings. 
 
GEELONG DRIP TEST 
a)  The specimen is mounted inclined at 27 degrees to the horizontal. 
b)  The specimen shall be tested without any surface coating. 
c)  lOO ml of water is discharged vertically 400mm onto the sloped surface of the 
sample. 
d)  The water must be discharged onto the sample within 20 - 60 minutes. 
e)  The pit depth is to be measured with a cylindrical probe with an end diameter of 
3mm. 
(Sourced from EBAA Publication) 
 
Classification of Results 
Pit Depth <5 mm  TRN = 3 
Pit Depth > 5mm but < 10 mm  TRN = 2 
Pit Depth >10 mm but< 15 mm  TRN = 1 
Pit Depth >15 mm  Sample suitable for Internal Use Only 
 
 
10 
 
UTS SPRAY TEST 
a )   G e n e r a l  
The test consists of spraying the face of a sample of the material (brick or rammed earth 
wall) with water for a period of one hour 
b)   Test  Detai l s 
  The spray nozzle to be used shall be a Fulljet 1550 nozzle (Available from 
Spraying Systems Company) 
  Water pressure shall be 70 kPa measured with a reliable pressure guage 
  The specimen shall be positioned 350 mm from the nozzle and at right angles to 
it. The nozzle shall be horizontal and the specimen face vertical.  
  The specimen is to be protected with a 150 mm diameter shroud with the gap 
between brick and shroud sealed with a gasket 
  The erosion depth shall be measured by placing a straight edge across the erosion 
crater and measuring the deepest extent of the crater using a pencil as a depth 
guage. 
 
 
 
Classification of Results 
Depth of Erosion <5 mm  TRN = 7 
Depth of Erosion <10 mm  TRN = 6 
Depth of Erosion >10 but < 20mm  TRN = 5 
Depth of Erosion >20 but <30mm  TRN = 4 
Depth of Erosion >30 mm  Suitable for Internal Use Only 
 
 
11 
 
   
 
12 
 
 
 
Case Studies 
  Mud Brick Building in Gaza 
See http://ingaza.wordpress.com/2009/05/07/denied-cement-re-building-with-mud/  
 
 
 
Small Mud Brick Test Building