NEC Work Information Guidance
NEC Work Information Guidance
Chapter  1   Introduction
The  purpose  of  this  guide  is  to  help  users  to  produce  Works  Information  for  the  NEC3
Engineering and Construction Contract (ECC).
The  convention  of  using  italics  for  terms  which  are  identied  in  the  Contract  Data  of
the ECC and capital initials for terms dened in the ECC has been used in this guide.
Good  quality  Works  Information  is  vital   to  achieving  better  outcomes  for  projects  and
reducing misunderstandings and  disputes.  Works Information  should  be prepared  with
individual project requirements and the operation of the ECC in mind.
All  NEC  contracts  refer  to  information  which  sets  out  what  the  Parties  are  required  to
do  under   the  contract.   The  obligation  to  work  in  accordance  with  that   information  is
set out in the conditions of contract.
The  diagram  below  shows  the  relationship  between  the  constituent  parts  of  a  contract
including   the   Works   Information.   Contract   Data   identies   the   documents   forming
the  contract.   The conditions  of contract  refer  to  each  part  of  the  contract  and  require
information  to  be  stated  in  them.   The  form  of  agreement  may  be  used  to  record  the
agreement  between  the  Parties  on  the  basis  of  the  Contract  Data,   or  the  Parties  may
rely on an exchange of correspondence to establish the contract.
Contract Data
ECC Documents
part two
part one
Site
Information
Prices
Activity Schedule or
Bill of Quantities
Form of Agreement
conditions of contract
core clauses
main Option clauses
secondary Option clauses
identifies
requires information
to be stated in
Works Information (Contractor s)
Works Information (Employer s)
www.neccontract.com
  #
 copyright nec  2012   1
C
h
a
p
t
e
r
6
W
I
p
r
o
v
i
d
e
d
b
y
t
h
e
C
o
n
t
r
a
c
t
o
r
f
o
r
h
i
s
d
e
s
i
g
n
C
h
a
p
t
e
r
5
E
m
p
l
o
y
e
r
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
Information  and  documents  required  for  the  contract  must  be  in  the  right  part  of  the
contract. If documents are located in the wrong place, it may cause confusion and risk
that   the   documents   are   not   properly   incorporated.   For   example,   information   which
describes  the  works  must  be  identied  in  the  Works  Information.   The  diagram  shows
that   Works  Information  is  identied  in  Contract   Data.   Therefore,   all   documents  and
information  which  describe  the works  or  state  constraints  must  be  identied  as  Works
Information  and  listed  in  Contract   Data.   This  includes  information  contained  within
correspondence  and  minutes  of   meetings  which  describes  the  works  to  be  provided.
The  approach  which  results  in  the  least  uncertainty  is  to  extract  relevant  information
from  correspondence  and  minutes  of  meetings  and  properly  integrate  it  in  the  Works
Information.   Works  Information  will   often  consist  of  multiple  documents  and  sections,
in which case a contents list should be provided.
The clarity achieved by this contract structure and the separation of its parts is helpful
to users and signicantly reduces ambiguity and the potential for disputes.
This   guidance   will   help   users   to   draft   and   assemble   Works   Information   correctly.
Chapter   2  describes  the  status  of   Works  Information  and  the  relationship  between
Works  Information  and  the  other  parts  of  the  ECC.  Chapter  3  provides  advice  on  draft-
ing  and  how  to  achieve  clarity.   Chapter  4  is  a  checklist  of  information  to  be  provided
in Works Information,  as required  by the conditions of contract. Chapter  5 suggests  an
outline  structure,   including  a  list  of  topics  to  be  considered  for  inclusion  in  the  Works
Information.
The  requirement  for  good  information   describing  the  work  or  services  to  be  provided
applies to all contracting systems. It is an objective of NEC to provide a contract which
is clear and simple and promotes effective management and delivery of the works.
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
The conditions of contract  make  frequent  reference  to  Works  Information  as  illustrated
above  and  later  in  Chapter  4.   Works  Information  is  therefore  central   to  the  operation
of the contract.
Works  Information  should  be  drafted  in  accordance  with  the  three  key  objectives  of
NEC, namely exibility, clarity and stimulus to good management.
The  Relationship  between  Works  Information  and  Contract  Data
Contract   Data   contains   information   needed   to   operate   the   contract,   including   the
choice  of  main  and  secondary  Options.   Contract  Data  is  the  type  of  information  often
described  in  other  forms  of  contract  as  the  contract  particulars  or  appendix.  There  are
two  parts.  Part  one  contains  the  information  provided  by  the Employer  and  part  two  is
where the Contractors data and proposals are identied.
The  ECC  Guidance  Notes  contain  detailed  information  on  completion  of   the  Contract
Data.
The  information  set  out  in  the  Contract  Data  is  not  Works  Information  or  Site  Informa-
tion,   but   it   identies  the  documents  which  contain  Works  Information.   The  Employer
identies  the  documents  which  contain  his  Works  Information  in  Contract   Data  part
one.   The Contractor  identies  the  documents  which  contain  the  Works  Information  for
his  design  in  Contract   Data  part   two.   Where  information  is  in  non-documentary  form
such as models, they should be identied and their availability and location stated.
Works   Information   should   not   contain   information   which   repeats,   contradicts   or
creates  an  ambiguity  with  any  information  contained  within  Contract  Data  or  with  the
conditions of contract.
The   following   documents   are   identied   within   Contract   Data   and   are   not   Works
Information
.
  boundaries of the site,
.
  Partnering Information (if Option X12 is used),
.
  incentive schedule (if Option X20 is used),
.
  matters to be included in the initial Risk Register,
.
  information describing the Working Areas and
.
  the programme (if required at tender stage).
A   further   distinction   is   that   the  Project   Manager   can   instruct   a   change   to   Works
Information but cannot change Contract Data once the contract is formed.
The  Relationship  between  Works  Information  and  Site  Information
The Contractors  obligations  regarding  Works  Information  and  Site  Information  are  dif-
ferent.   A  clear  separation  between  Works  and  Site  Information  is  required.   Site  Infor-
mation   describes   the   condition   of   the   Site   before   work   starts.   Works   Information
describes what is to be done on the Site.
Site Information is dened as follows
11.2(16)   Site Information is information which
.
  describes the Site  and its  surroundings  and
.
  is in the documents  which  the Contract Data states  it is in.
Site is dened as
11.2(15)   The  Site  is  the  area  within  the  boundaries  of   the  site  and  the  volumes
above  and below  it  which  are affected  by work  included in this  contract.
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
Site Information, as with Works Information, is incorporated by reference to documents
listed  in  Contract   Data.   There  are  several   distinctions  between  Site  Information  and
Works Information, for example
.
  Site Information cannot be changed once the contract is formed.
.
  Site  Information  is  used  to  assess  compensation  events  resulting  from  physical
conditions (subclauses 60.1(12) and 60.2).
.
  Ambiguities  or   inconsistencies  in  the  Site  Information  are  resolved  in  favour   of
the  Contractor   (subclause  60.3).   This  encourages  full   disclosure  of   information
on the condition of the Site.
Site Information may include the following
.
  Subsoil investigation borehole records and test results.
.
  Reports  obtained  by  the Employer  concerning  the  physical   conditions  of  the  Site
or   its   surroundings.   This   may   include   mapping,   hydrographic   data   and
hydrological information.
.
  References   to   publicly   available   information  about   the   Site  and  surroundings,
such as published papers and interpretations of the geological survey.
.
  Information about pipes, services and other objects below the surface of the Site.
.
  Information  about   buildings,   structures  and  other   features  (including  machinery
adjacent to and on the Site).
Site  Information  is  provided  to  help  the Contractor  to  prepare  his  tender,  to  decide  his
method  of  working  and  programme  and  prepare  designs  for  which  he  is  responsible.
Only  factual   information  about  the  physical   condition  of  the  Site  and  its  surroundings
is  included  in  Site  Information.   Statements  of  opinion    for  example  interpretation  of
soil investigation surveys  are not Site Information.
Some   documents   may   contain   both   Works   Information   and   Site   Information.   For
example,   a   document   may   show  an   existing   structure   alongside   details   of   a   new
structure.   The  following  example  shows  how  Site  Information  and  Works  Information
can be separated.
Works  Information  
Example  Drawing  List
  Drawing  No.
0100
0200
Description
New Factory Building
Existing Factory Building (proposed features)
Site  Information  
Example  Drawing  List
  Drawing  No.
0200
0300
Description
Existing Factory Building (existing features)
Existing Mains Services
The  Relationship  between  Works  Information  and  pricing  documents
A  clear   distinction  exists  between  Works  Information  and  the  pricing  documents  i.e.
the   Activity   Schedule   or   Bill   of   Quantities.   Information   in   the   pricing   documents
explains  the  Prices  and  should  not  describe  the  works.   The  Contractors  obligation  is
to Provide the Works in accordance with the Works Information.
Statements  about   pricing  of   work  should  not   be  in  the  Works  Information,   as  they
neither specify or describe the works, nor do they state constraints.
Information  in  the  pricing  documents  does  not  change  the  obligation  of  the Contractor
to Provide the Works in accordance with the Works Information.
Chapter 2   The status of Works Information
www.neccontract.com
  #
 copyright nec  2012   5
C
h
a
p
t
e
r
6
W
I
p
r
o
v
i
d
e
d
b
y
t
h
e
C
o
n
t
r
a
c
t
o
r
f
o
r
h
i
s
d
e
s
i
g
n
C
h
a
p
t
e
r
5
E
m
p
l
o
y
e
r
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
Works  Information  as  a  contract  document
Some   forms   of   contract   use   provisions   creating   a   hierarchy   or   priority   of   docu-
mentation  as   a  means   of   resolving  ambiguities   and  inconsistencies  in  or   between
documents. This is not the approach taken by NEC.
Priority  clauses  can  interfere  with  the  natural  interpretation  of  documents  as  intended
by the Parties. Such an indiscriminate approach to resolving ambiguities and inconsis-
tencies can cause problems.
As  explained  in  Chapter  1,   the  ECC  describes  the  function  of  each  document  forming
part   of   the  contract.   This  provides  clarity   as  to  the  relevance  and  purpose  of   each
document   in  the  contract.   The  conditions  of   contract   then  deal   with  any   remaining
ambiguity or inconsistency in or between the documents.
The  ECC  deals  with  ambiguities  and  inconsistencies  between  the  documents  forming
the contract at subclause 17.1.
The  Project  Manager  or  the  Contractor  noties  the  other  as  soon  as  either  becomes
aware  of an  ambiguity  or  inconsistency  in or  between  the  documents  which are  part  of
this   contract.   The   Project   Manager   gives   an   instruction   resolving   the   ambiguity   or
inconsistency.
Such  an  instruction  from  the  Project   Manager   changing  the  Works  Information  is  a
compensation  event  (subclause  60.1(1),   second  bullet)  except  where  the  instruction
is a
change  to  the  Works  Information  provided  by  the  Contractor  for   his  design  which  is
made  either  at  his  request  or  to  comply  with  other  Works  Information  provided  by  the
Employer.
There  is  no  priority  of  documents  in  ECC  other  than  the  hierarchy  of Employers  Works
Information  compared  to Contractors  Works  Information  in  subclause  60.1(1).  Works
Information  should  be  drafted  to  avoid  any  conicts  or  contradictions.   Works  Informa-
tion  may  consist   of   several   documents  drafted  by  different   contributors.   Ambiguities
or  inconsistencies  between  documents  should  be  corrected  before  the  documents  are
issued.
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
The  substitution  of   Project   Manager   for   Engineer   as  a  drafting  short-cut   can
cause confusion for the following reasons.
.
  The  ECC  Project  Manager  may  not  have  the  same  duties  as  the  Engineer  in
other   contracts.   Some  of   the  Engineers  duties  may   be  undertaken  by   the
Project Manager and some by the Supervisor or Adjudicator.
.
  The  ECC  is  more  prescriptive  on  what  can  be  done  by  the Project Manager  on
certication than other standard contracts.
.
  The acceptance of a communication by a Project Manager  may differ  from an
approval given by an Engineer in other contracts. ECC subclause 14.1 states
The  Project  Managers  or  the  Supervisors  acceptance  of   a  communication  from
the  Contractor   or   of   his  work  does  not   change  the  Contractors  responsibility  to
Provide  the Works  or  his liability for  his design.
W1.2   After satisfactory completion of pressure testing, each valve on and adjacent
to, the pipeline shall be examined to witness that the opening/closing
mechanisms function satisfactorily and are capable of functioning for their
designated purpose. Isolating valves shall be examined by opening and
closing the isolating gate three times. All tests and examinations shall be
witnessed by the Engineers staff and the Contractor shall provide a
witnessed certicate to this effect to the Engineer.
[Note subjective word satisfactorily and the use of the wrong terminology.
The witnessing of the tests should be by the Supervisor. If a preface had
been included in this specication to the effect that read Project Manager for
Engineer, then the Project Manager would have an obligation that is the
Supervisors under the conditions of contract and a conict would exist. Note
also that the Contractor is required to provide notication of results under
the conditions of contract and this Works Information paragraph requires an
extra obligation of the Contractor.]
W2   Swabbing of water  mains
W2.1   Swabs will be provided by the Purchaser. Temporary pipework shall be
provided by the Contractor.
[Note wrong terminology in Purchaser, where it should refer to Employer.
Note also the vague nature of the statement. How many swabs will be
provided? Where will/can they be obtained from?]
W3   Water  supply  for testing and  swabbing
W3.1   For the purpose of the hydraulic testing of water-retaining structures and
pipelines, the Purchaser will make available water from existing mains, at
times and rates of ow to be decided by the Purchaser and agreed with the
Engineer.
[Note wrong terminology: should be Project Manager and Employer, not
Purchaser and Engineer. Note also that if the Contractor were to do the test,
he is not involved in the decision of when the water is to be provided,
although this could affect his programme.]
W3.2   Water will be provided free of charge to the Contractor for the rst test. In
the event of any part of the work having to be retested the Contractor shall
be required to pay for the supply of water on a volume basis at the prevailing
rate of the Purchaser.
[Note wrong terminology: should be Employer, not Purchaser.]
G1   Standards  of materials
G1.1   15th Statement of the DoE Committee on Chemicals and Materials of
Constructions for use in Public Water Supplies and Swimming Pools.
G1.2   The use of materials, including chemicals that do not meet the above
criteria, shall be subject to the approval of the Engineer.
[Note under the conditions of contract acceptance and not approval is the
terminology used. Also should be the Project Manager, not Engineer.]
G2   Disinfection  of pipework and  structures
Pipes, pumps and structures shall be disinfected in accordance with the
following procedure:
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
(a)   The Contractor shall provide, at least three weeks before carrying out the
disinfection process, a Method Statement to the Engineer for his Approval.
[Note that under the conditions of contract a method statement is part of the
Contractors programme. The Contractor submits his programme to the
Project Manager (not the Engineer) for acceptance (not approval). There are
several programme revisions provided for in the conditions of contract,
including where the Project Manager can ask for one at any time.]
(b)   After satisfactory hydraulic testing, pipes, pumps, structures etc shall be
cleaned of all deleterious material.
[Note the use of vague words such as satisfactory. The expected results of
the test, as well as the details of how and when the test is to be carried out,
should be provided.]
(c)   The volume to be disinfected shall be lled with chlorinated water at a
dose level of 2025mg/l free chlorine and left to stand for 24 hours.
Large structures may have all surfaces thoroughly scrubbed down with
heavily chlorinated water and the volume then lled with a lower dose level,
0.5mg/l chlorinated water and left for 24 hours.
(d)   The chlorinated water shall be drained away and disposed of in a safe and
satisfactory manner. All necessary approvals for discharge shall be obtained
by the Contractor. De-chlorination will be necessary to ensure that free
chlorine discharged is below 0.1mg/l, where discharge is a watercourse, or
drain leading to a watercourse.
[Note the vague words safe, satisfactory and necessary. What is safe
and satisfactory to the Contractor could be different from the Project
Manager. Unless a published standard is quoted, the requirements should
be stated in the Works Information.]
(e)   The volume shall then be relled with potable water and left a further 24 hours.
(f )   The Purchaser will take samples for bacteriological testing. The results of his
test will take a minimum of three working days to provide a conclusive test.
[Note the incorrect terminology by the use of Purchaser rather than Employer.
The Works Information is required to state who provides samples, materials
and facilities for testing. The criteria of the test should also be stated.]
(g)   If test results are unsatisfactory to the Purchaser, the above procedure shall
be repeated until satisfactory results are achieved.
[Note: use of incorrect terminology Purchaser and satisfactory. The
uncertainty of this statement could leave the Contractor having difculties
pricing accurately, or potentially adding conservative amounts of risk into his
price.]
Health  and  safety  information
Subclause  27.4  requires   the  Contractor   to   act   in  accordance   with  the  health  and
safety  requirements  stated  in  the  Works  Information.   Further  comment  on  this  clause
is given in Chapters 4 and 5.
Chapter 3   Drafting Works Information
www.neccontract.com
  #
 copyright nec  2012   9
C
h
a
p
t
e
r
6
W
I
p
r
o
v
i
d
e
d
b
y
t
h
e
C
o
n
t
r
a
c
t
o
r
f
o
r
h
i
s
d
e
s
i
g
n
C
h
a
p
t
e
r
5
E
m
p
l
o
y
e
r
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
Employers  should  consider  how  to  deal  with health  and  safety  requirements  and  docu-
mentation  carefully  when  preparing  Works  Information.   The  associated  constraints  on
how  the  Contractor   Provides  the  Works  should  be  included  in  the  Employers  Works
Information.
Many   jurisdictions  require  health  and  safety   risks  to  be  evaluated  by   the  Employer
and  then  communicated  to  the Contractor  as  part  of  the  procurement  process.   It  may
not   be   necessary   to   include  the   risk   evaluation  as   a  contract   document,   but   it   is
necessary  to  check  for  consistency  between  the  health  and  safety  information,   Works
Information and Site Information.
General   drafting  advice
The  following  description  of  NEC  drafting  style  will   help  users  draft  Works  Information
and other contract documents clearly.
1.   A  basic  objective  of   NEC  contracts  is  that   they  should  be  clear   and  simple.
The  drafting  delivers  clarity  and  simplicity  of  language.  Simplicity  also  follows
from the design of the management processes in the contracts.
2.   One  of   the  objects   of   using  simple  language  in  the  contracts   is   that   they
should  be  easy  for  people  whose  rst  language  is  not  English to  use.  A  further
advantage   is   that   the   contracts   can   be   translated   into   other   languages
accurately.
Vocabulary   3.   Use the simplest possible words. Simple words have few syllables.
4.   Do not use words which are not needed.
Sentences   5.   Sentences  should  be  as  short   as  possible.   Twenty  words  is  ne.   Never   have
more  than  forty.   Use  several   short   sentences  instead  of   one  sentence  with
several clauses.
6.   Many  statements  are  conditional.   If   this  happens,   the  Contractor   does  this.
Put   the  condition  rst,   not   last   and  use  if,   not   when.   If   this  happens,   the
UK Specic illustration:
The   Construction   (Design   and   Management)   Regulations   2007   requires   the
preparation  of   Pre-Construction  Information  relating  to  health  and  safety  and  for
this  information  to  be  provided  to  the  Contractor.   This  may   contain  information
which  is  both  Works  Information  and  Site  Information.   Care  should  be  taken  in
deciding   whether   and   how  to   include   the   Pre-Construction   Information   in   the
contract. Consider
.
  whether   the   information   is   Works   Information   or   Site   Information   (see
Chapter 2),
.
  how   changes   and   developments   to   the   information   will   be   administered
which  changes  can  only  be  made  by  an  instruction  of   the  Project   Manager
and which can be changed by the Contractor to suit his own proposals,
.
  the  legal   requirement   for   Pre-Construction  Information  to  be  issued  to  the
Contractor and
.
  the  time  difference  between  formation  of  the  contract  and  the starting date  
during which the Pre-Construction Information may change.
In most cases, clarity  will be achieved  by keeping  the Pre-Construction  Information
as  a  separate  document.   However,   the  Works  Information  must   include  informa-
tion  from  the  Pre-Construction  Information  which  describes  the  works   or   states
constraints  and  the  Site  Information  must   include  or   identify   information  which
describes the Site.
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
Contractor  does  this.  [not:  The Contractor  does  this  when this  happens.]  Use
when only if timing is implied as in subclause 36.4.
7.   Use  commas   properly.   The  pause  which  a  comma  creates   can  help  under-
standing.
Bullets   8.   Bullets  are  used  when  a  clause  includes  a  list.   Do  not   use  bullets  for   short
lists with short descriptions. The following does not need to be bulleted:
The Contractor  arranges  for  Hail   to  the  Chief    to  be  played  by  a  brass  band
outside the Project Managers ofce at 9 a.m. on
.
  Mondays,
.
  Wednesdays,
.
  Fridays and
.
  his birthday.
9.   A  useful   check  is  that   punctuation  of   bulleted  sentences  should  work  if   the
bullets  are  removed.   Bullets  end  with  a  comma  except  the  last  but  one  which
ends  with  and   or  or   and  the  last  which  ends  with  a  full   stop.   Do  not  put  a
comma  before  and.   And   replaces  the  comma  before  the  last  item  on  a  list
as above.
10.   Whenever  possible,  put  bullets  at  the  end  of  a  sentence.  Having  a  bit  more  of
the  sentence  after  a  bulleted  list  is  clumsy  as  the  reader  does  not  expect  the
text and the sentence can become very long and not easy to understand.
11.   Bullets  are  indented.   Bullets  within  bullets  should  be  avoided  if   possible.   If
used, as in subclause 31.2, use a double indent.
Adjectives  and Adverbs   12.   Old-fashioned  contracts  use  a  lot   of   adjectives  and  adverbs.   NEC  contracts
use  the  absolute  minimum,   which  is   hardly   any.   This   is   perhaps   the  most
important  drafting  convention  for  NEC.   Use  an  adverb  or  adjective  only  if  it  is
really unavoidable.
13.   Verbs   and   nouns   are   usually   precise,   adverbs   and   adjectives   are   usually
imprecise.  The Contractor  does  all  urgent  work  quickly  is  easy  to  understand.
Unfortunately,   you   can   argue   about   the   meaning   of   urgent   (adjective)
and  quickly  (adverb).  The Contractor  (noun),  does  (verb)  and  work  (noun)
are  precise.  To  make  the  point  absurdly,  George  ate  a  hefty  meal  unhurriedly
is   vague   but   not   meaningless.   George   ate   a   meal   of   42   mouthfuls   in
21  minutes   is  boring  but   precise.   Contracts  are  not   intended  to  be  a  good
read.  They  have  to  state  who  does  what  in  words  of  unarguable  precision  and
clarity.
14.   Some  adverbial   phrases  are  as  imprecise  as  adverbs,   e.g.   quickly   in  come
quickly   is  obviously  an  adverb.   So,   in  effect,   is  as  soon  as  you  can   in  come
as soon as you can.
15.   This  text,   for  example,   about   extension  of   time,   comes  from  clause  44(1)  of
the ICE conditions fth edition, adverbs and adjectives in italics.
. . . . . . . . . . . . . . . . . .   or   exceptional   adverse  weather   conditions  or   other   special
circumstances of any kind . . . . . . . . . . . . . . . . . . . . . . . . . . . be such as fairly to entitle
the  Contractor  to  an  extension  of  time  . . . . . . . . .   the  Contractor  shall  within  28
days   after   the   cause   of   the   delay   has   arisen   or   as   soon  thereafter   as   is
reasonable  in  all   the  circumstances  deliver   to  the  engineer   full   and  detailed
particulars of any claim to extension of time . . . . . . . . . . . . . . . . . .
16.   It  is impossible to  decide  whether  an  extension  of time should  be  given  and,  if
so,  for  how  much,  when  and  how  described until the  courts  have  decided  what
the adjectives and adverbs mean.
17.   NEC  drafting  requires  the  absolute  minimum  of  adverbs  and  adjectives.  Some
are  innocuous  as  in  subclause  65.2  which  uses  the  adjective  wrong   as  in
wrong forecast.
Clauses   18.   Clauses  should  be  as  short   as  possible  with  no  more  than  two  sentences.
They should cover only one subject.
Chapter 3   Drafting Works Information
www.neccontract.com
  #
 copyright nec  2012   11
C
h
a
p
t
e
r
6
W
I
p
r
o
v
i
d
e
d
b
y
t
h
e
C
o
n
t
r
a
c
t
o
r
f
o
r
h
i
s
d
e
s
i
g
n
C
h
a
p
t
e
r
5
E
m
p
l
o
y
e
r
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
Tenses   19.   Use  the present tense for all statements of what somebody must do or not do.
It  is  seldom  necessary  to  use  another  tense.   If  the  sky  has  fallen  down,   the
Project Manager  decides what  the Contractor  will  do  uses  three  tenses.  If  the
sky  falls  down,   the  Project   Manager   decides  what   the  Contractor   does   uses
only the present.
Capitals   20.   Capital  initials  show  that  a term  is dened in  the contract.  When drafting,  test
that   a  denition  is  right   by   putting  it   into  the  sentences  where  the  dened
term  is   used.   These   denitions   are   only   abbreviations   and   must   only   be
abbreviations.   If  there  is  anything  to  say  about  the  dened  term,   it  has  to  be
in the clauses.
21.   There  are  exceptions.   Project   Manager,   Supervisor,   Employer   and  Contractor
have capitals but are not dened.
Particular words   22.   May   in  NEC  means  is  allowed  to   as  in  the  Supervisor   may  instruct   . . . . . .
Do not use it to mean that something might happen.
23.   Any can usually be deleted.
Multiple  Alternatives   24.   Either a, b, c or d. Bullet the alternatives if they are phrases of some length.
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
ECC
subclause
ref
Chapter  5   ECC subclause description   Guidance on what should  be
included in  the Works
Information
21.1   WI 305   The Contractor designs the parts of the
works which the Works  Information
states he is to design.
Dene the parts of the works
which the Contractor is to
design.
This can be done in a number
of different ways. See Chapter
5 for further guidance.
21.2   WI 310   The Contractor submits the particulars of
his design as the Works  Information
requires to the Project Manager for
acceptance. A reason for not accepting
the Contractors design is that it does
not comply with either the  Works
Information or the applicable law.
The Contractor does not proceed with the
relevant work until the Project Manager
has accepted his design.
State any procedures which
the Contractor is to follow in
carrying out his design and
procedures for the
submission of designs for
acceptance by the Project
Manager and Others.
22.1   WI 335   The Employer may use and copy the
Contractors design for any purpose
connected with construction, use,
alteration or demolition of the works
unless otherwise stated in the  Works
Information and for other purposes as
stated in the Works  Information.
State any restriction or
additional purpose for which
the Employer may wish to use
and copy the Contractors
design.
25.1   WI 905   The Contractor co-operates with Others
in obtaining and providing information
which they need in connection with the
works. He co-operates with Others and
shares the Working Areas with Others as
stated in the Works  Information.
Detail the activities of Others
within the Working Areas.
25.2   WI 1005,
1010
The Employer and the Contractor provide
services and other things as stated in
the Works  Information. Any cost incurred
by the Employer as a result of the
Contractor not providing the services and
other things which he is to provide is
assessed by the Project Manager and
paid by the Contractor.
State the services and other
things that are to be provided
by the Employer and
Contractor.
27.4   WI 1105   The Contractor acts in accordance with
the health and safety requirements
stated in the Works  Information.
State any health and safety
requirements for the project
which the Contractor must
follow.
31.2   WI 505   The Contractor shows on each
programme which he submits for
acceptance
.
  the starting date, access dates, Key
Dates and Completion Date,
.
  planned Completion,
.
  the order and timing of the operations
which the Contractor plans to do in
order to Provide the Works,
.
  the order and timing of the work of the
Employer and Others as last agreed
with them by the Contractor or, if not
so agreed, as stated in the Works
Information,
State any additional
information that the
Contractor is to show on the
programme. This may include
dates for submission of
designs and samples, dates
for information or actions by
the Employer and Project
Manager and the timing of any
test or inspection.
Any requirements for the
format of the programme
should be stated, including
the use of specic software
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
ECC
subclause
ref
Chapter  5   ECC  subclause description   Guidance on what  should be
included in  the Works
Information
.
  the dates when the Contractor plans
to meet each Condition stated for the
Key Dates and to complete other work
needed to allow the Employer and
Others to do their work,
.
  provisions for
.
  oat,
.
  time risk allowances,
.
  health and safety requirements and
.
  the procedures set out in this
contract,
.
  the dates when, in order to Provide the
Works in accordance with his
programme, the Contractor will need
.
  access of a part of the Site if later
than its access date,
.
  acceptances,
.
  Plant and Materials and other things
to be provided by the Employer and
.
  information from Others,
.
  for each operation a statement of how
the Contractor plans to do the work
identifying the principal Equipment
and other resources which he plans to
use and
.
  other information which the Works
Information requires the Contractor to
show on a programme submitted for
acceptance.
and the requirement for hard
or electronic copies. Any
requirements for resource or
nancial data in the
programme should also be
stated.
31.3   WI 600   Within two weeks of the Contractor
submitting a programme to him for
acceptance, the Project Manager either
accepts the programme or noties the
Contractor of his reasons for not
accepting it. A reason for not accepting
the programme is that
.
  the Contractors plans which it shows
are not practicable,
.
  it does not show the information which
this contract requires,
.
  it does not represent the Contractors
plans realistically or
.
  it does not comply with the  Works
Information.
Refer to subclause 31.2
above.
35.2   WI 440   The Employer may use any part of the
works before Completion has been
certied. If he does so, he takes over a
part of the works when he begins to use
it except if the use is
.
  for a reason stated in the Works
Information or
.
  to suit the Contractors method of
working.
If the Employer requires to
use any part of the works
prior to Completion without
taking it over, describe the
part and set out the reason
for its use.
40.1   WI 705   The subclauses in this clause only apply
to tests and inspections required by the
Works  Information or the applicable law.
Detail the tests and
inspections required, the
results expected and which
parties are involved in the
test and inspection process.
Chapter 4   ECC references to Works Information
www.neccontract.com
  #
 copyright nec  2012   15
C
h
a
p
t
e
r
6
W
I
p
r
o
v
i
d
e
d
b
y
t
h
e
C
o
n
t
r
a
c
t
o
r
f
o
r
h
i
s
d
e
s
i
g
n
C
h
a
p
t
e
r
5
E
m
p
l
o
y
e
r
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
ECC
subclause
ref
Chapter  5   ECC subclause description   Guidance on what should  be
included in  the Works
Information
40.2   WI 705   The Contractor and the Employer provide
materials, facilities and samples for
tests and inspections as stated in the
Works Information.
State the materials, facilities
and samples to be provided
by the Contractor and the
Employer for tests and
inspections and the timing of
these.
41.1   WI 705   The Contractor does not bring to the
Working Areas those Plant and
Materials which the Works
Information states are  to be  tested  or
inspected before  delivery  until the
Supervisor has notied the Contractor
that they have passed the test or
inspection.
State the Plant and Materials
which are to be tested and
inspected before delivery to
the Working Areas, including
details of tests or
inspections.
45.1   WI 440   If the Contractor is given access in order
to correct a notied Defect but he has
not corrected it within its defect
correction period, the Project Manager
assesses the cost to the Employer of
having the Defect corrected by other
people and the Contractor pays this
amount. The Works  Information is
treated as having been changed to
accept the Defect.
45.2   WI 440   If the Contractor is not given access in
order to correct a notied Defect before
the defects date, the Project Manager
assesses the cost to the Contractor of
correcting the Defect and the Contractor
pays this amount. The  Works
Information is treated as having been
changed to accept the Defect.
60.1(5)   WI 905   The Employer or Others
.
  do not work within the times shown on
the Accepted Programme,
.
  do not work within the conditions
stated in the Works  Information or
.
  Carry out work on the Site that is
not stated in the  Works
Information.
Refer to subclauses 25.1 and
25.2
60.1(16)   WI 705   The Employer does not provide
materials, facilities and samples for
tests and inspections as stated in the
Works Information.
Refer to subclause 40.2.
71.1   WI 1305   The Supervisor marks Equipment, Plant
and Materials which are outside the
Working Areas if
.
  this contract identies them for
payment and
.
  the Contractor has prepared them for
marking as the  Works Information
requires.
State the requirements for
marking Equipment, Plant
and Materials which are
outside the Working Areas by
the Supervisor, for payment
and transfer of title to the
Employer. The Works
Information should state
which items are to be
prepared for marking and
how this is to be done.
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
ECC
subclause
ref
Chapter  5   ECC  subclause description   Guidance on what  should be
included in  the Works
Information
73.2   WI 1310   The Contractor has title to materials
from excavation and demolition only as
stated in the Works Information.
The Works Information should
state which materials arising
from excavations and
demolitions the Contractor
has title to.
C, D and
E 11.2
(25)
WI 1405,
1410
Disallowed Cost is cost which the Project
Manager decides
.
  is not justied by the Contractors
accounts and records,
.
  should not have been paid to a
Subcontractor in accordance with his
contract,
.
  was incurred only because the
Contractor did not
.
  follow an acceptance or
procurement procedure stated in
the Works  Information or
.
  give an early warning which this
contract required him to give
and the cost of
.
  correcting Defects after Completion,
.
  correcting Defects caused by the
Contractor not complying with a
constraint on how he is to Provide the
Works stated in the Works
Information,
.
  Plant and Materials not used to
Provide the Works (after allowing for
reasonable wastage) unless resulting
from a change to the  Works
Information,
.
  resources not used to Provide the
Works (after allowing for reasonable
availability and utilisation) or not
taken away from the Working Areas
when the Project Manager requested
and
.
  preparation for and conduct of an
adjudication or proceedings of the
tribunal.
State any acceptance or
procurement, procedures to
be followed by the Contractor.
State any constraints on how
the Contractor is to Provide
the Works.
This is relevant to Options C,
D and E where payment to
the Contractor is based upon
Dened Cost.
F 11.2
(26)
WI 1405,
1410
Disallowed Cost is cost which the Project
Manager decides
.
  is not justied by the accounts and
records provided by the Contractor,
.
  should not have been paid to a
Subcontractor in accordance with his
contract,
.
  was incurred only because the
Contractor did not
.
  follow an acceptance or
procurement procedure stated in
the Works  Information or
.
  give an early warning which this
contract required him to give or
.
  is a payment to a Subcontractor for
.
  work which the Contract Data states
that the Contractor will do himself or
.
  the Contractors management.
State any acceptance or
procurement, procedures to
be followed by the Contractor.
This is relevant to Option F
where payment to the
Contractor is based upon
Dened Cost.
Chapter 4   ECC references to Works Information
www.neccontract.com
  #
 copyright nec  2012   17
C
h
a
p
t
e
r
6
W
I
p
r
o
v
i
d
e
d
b
y
t
h
e
C
o
n
t
r
a
c
t
o
r
f
o
r
h
i
s
d
e
s
i
g
n
C
h
a
p
t
e
r
5
E
m
p
l
o
y
e
r
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
ECC
subclause
ref
Chapter  5   ECC subclause description   Guidance on what should  be
included in  the Works
Information
C, D, E
and F
52.2
WI 1505   The Contractor keeps
.
  accounts of his payments of Dened
Cost,
.
  proof that the payments have been
made,
.
  communications about and
assessments of compensation events
for Subcontractors and
.
  other records as stated in the Works
Information.
Detail any other records to be
kept by the Contractor.
X4.1   WI 1600   If a parent company owns the
Contractor, the Contractor gives to the
Employer a guarantee by the parent
company of the Contractors
performance in the form set out in the
Works Information. If the guarantee was
not given by the Contract Date, it is
given to the Employer within four weeks
of the Contract Date.
Set out the form of parent
company guarantee required.
X13.1   WI 1700   The Contractor gives the Employer a
performance bond, provided by a bank or
insurer which the Project Manager has
accepted, for the amount stated in the
Contract Data and in the form set out in
the Works  Information. A reason for not
accepting the bank or insurer is that its
commercial position is not strong
enough to carry the bond. If the bond
was not given by the Contract Date, it is
given to the Employer within four weeks
of the Contract Date.
Set out the form of
performance bond required.
X14.2   WI 1800   The advanced payment is made either
within four weeks of the Contract Date
or, if an advanced payment bond is
required, within four weeks of the later of
.
  the Contract Date and
.
  the date when the Employer receives
the advanced payment bond.
The advanced payment bond is issued
by a bank or insurer which the Project
Manager has accepted. A reason for not
accepting the proposed bank or insurer
is that its commercial position is not
strong enough to carry the bond. The
bond is for the amount of the advanced
payment which the Contractor has not
repaid and is in the form set out in the
Works Information. Delay in making the
advanced payment is a compensation
event.
Set out the form of advanced
payment bond required.
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
Example  Works  Information  Structure
The numbering used below is indicative.
Section   Works  Information  (Employers)
WI 100   Description of the works
WI 200   General constraints on how the Contractor Provides the Works
WI 300   Contractors design
WI 400   Completion
WI 500   Programme
WI 600   Quality assurance
WI 700   Tests and inspections
WI 800   Management of the works
WI 900   Working with the Employer and Others
WI 1000   Services and other things to be provided
WI 1100   Health and safety
WI 1200   Subcontracting
WI 1300   Title
WI 1400   Acceptance or procurement procedure (Options C, D, E and F)
WI 1500   Accounts and records (Options C, D, E and F)
WI 1600   Parent company guarantee (Option X4)
WI 1700   Performance bond (Option X13)
WI 1800   Advanced payment bond (Option X14)
WI 1900   Low performance damages (Option X17)
WI 2000   Employers work specications and drawings
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
Guidance  and  Checklist
This  relates  to  the  example  Works  Information  structure  shown  above.   Guidance  relat-
ing  to  each  Works  Information  section  is  provided  in  the  grey   boxes.   A  checklist   of
optional topics is also provided.
WI  100  Description  of the works
Provide a general description of the work to be carried out under the contract. Do
not repeat the denition of the works.
The general description should be consistent with the description in Contract Data
part one, and identify the outline scope of the works to be provided. A general
description of the Contractors design responsibility may be included here. A
detailed description is included in section WI 300.
The Employers overall objectives for the project may also be stated, so that the
Contractor understands them and can work with the Employer to achieve them.
A description of works to be undertaken by the Employer or Others is in section WI 900.
Checklist   Explanation
WI 105 Description of the works   As above.
WI 110 Project objectives   Explain why the project is being undertaken.
Specic objectives may include outcomes on
safety, quality, time and functionality.
WI  200  General  constraints  on how  the  Contractor  Provides  the Works
State any general constraints on how the Contractor Provides the Works, which are
not covered by other Works Information sections.
If project objectives are included, state the requirements imposed on the
Contractor in helping to achieve them.
Constraints may include the checklist topics listed below. Constraints are
restrictions on how the Contractor Provides the Works, not issues related to cash
ow, funding or other requirements which conict with the conditions of contract.
Checklist   Explanation
WI 205 General constraints   Examples of constraints.
.
  Use of the Site.
.
  Access to the Site.
.
  Deliveries.
.
  Noise and vibrations.
.
  Working hours,
.
  Parking.
.
  Use of cranes.
.
  Use (or non-use) of explosives.
.
  Restrictions on the use of hazardous materials.
.
  Storage of fuel and chemicals.
.
  Pollution, ecological or environmental impacts.
.
  Archaeological requirements.
.
  Interfaces between the works and existing things.
.
  Occupied premises and users.
.
  Employer specic policies and procedures.
.
  Constraints imposed to meet the requirements
of Others (for example funders).
Chapter 5   Employers Works Information
www.neccontract.com
  #
 copyright nec  2012   21
C
h
a
p
t
e
r
6
W
I
p
r
o
v
i
d
e
d
b
y
t
h
e
C
o
n
t
r
a
c
t
o
r
f
o
r
h
i
s
d
e
s
i
g
n
C
h
a
p
t
e
r
5
E
m
p
l
o
y
e
r
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
Checklist   Explanation
WI 210 Condentiality   Condentiality and publicity restriction, and any
acceptance procedures.
WI 215 Security and protection
of the Site
Security requirements for the Site and protection
of the public.
WI 220 Security and
identication of people
Security, vetting and identication of people
working on or visiting the Site.
Requirements for people visiting Site.
WI 225 Protection of existing
structures and services
Specic requirements for the protection of
existing structures, services, mains, trees and
other plants. Requirements for maintenance of
existing services. Procedures for working on
existing structures and services.
Refer to Site Information for location of existing
things to be protected or procedures for
identifying them.
WI 230 Protection of the works   Specic requirements for the protection of the
works against damage.
WI 235 Cleanliness of roads   Requirements agreed with authorities for
protecting and cleaning of access roads to the
Site.
WI 240 Trafc management   Requirements and procedures for management of
trafc, road closures and public highways.
Communication and information requirements.
WI 245 Condition survey   Condition surveys to be carried out by the
Contractor and any associated reinstatement
works.
WI 250 Consideration of Others   Restrictions on work to avoid disturbance to the
general public or occupiers of adjacent premises.
WI 255 Industrial relations   Specic requirements for the Contractor to comply
with any industrial relations policies.
WI 260 Control of site
personnel
Requirements for control of people working on or
visiting Site.
Permits and licences (for example permits to
work).
WI 265 Site cleanliness   Keeping the Site clean and tidy.
WI 270 Waste materials   Removal of waste and restrictions on the disposal
of waste material. Requirements for recycling.
WI 275 Deleterious and
hazardous materials
Restrictions on the use of deleterious and
hazardous materials.
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
WI  300 Contractors design
Dene the parts of the works which the Contractor is to design. The ECC is exible
in this respect. The responsibility for design can be described in a number of
different ways, but in all cases, the part to be designed by the Contractor must be
clearly identied. If the Employer carries out most of the design, a list of items
designed by the Contractor may be stated. If the Contractor carries out most of the
design, a list of items designed by the Employer may be stated.
State the procedures which the Contractor is to follow in carrying out his design
and procedures for the submission of design for acceptance by the Project
Manager and Others. Identify which parts of the design are required to be
submitted to the Project Manager for acceptance.
Checklist   Explanation
WI 305 Design responsibility
ECC  21.1
As above.
WI 310 Design submission
procedures
ECC  21.2
As above.
WI 315 Design approvals from
Others
ECC  27.1
State any requirement for design checks and
approvals by Others.
WI 320 Employers
requirements
Identify the Employers requirements for the
parts of the works to be designed by the
Contractor. Examples of this information are
listed below.
.
  Specications, including reference to relevant
standards.
.
  Design standards and codes of practice.
.
  Size and/or space limitations.
.
  Loading and capacity requirements.
.
  Operational performance requirements and
design life.
.
  Planning drawings and planning consents.
.
  Energy consumption targets
.
  Environmental standards
.
  Sustainability requirements
.
  Design quality evaluation criteria
.
  Employers design reports
.
  Employers standard design guidance.
WI 325 Design co-ordination   State what responsibility the Contractor has for
co-ordination with Others in preparing his design
and any responsibility for the coordination of
design by Others.
WI 330 Requirements of Others   Explain the Contractors responsibility for
obtaining and satisfying any necessary authority
requirements (for example planning ofcials or
government departments).
WI 335 Copyright/licence
ECC  22.1
State any purpose for which the Employer may
wish to use and copy the Contractors design if it
is not as stated in subclause 22.1.
Chapter 5   Employers Works Information
www.neccontract.com
  #
 copyright nec  2012   23
C
h
a
p
t
e
r
6
W
I
p
r
o
v
i
d
e
d
b
y
t
h
e
C
o
n
t
r
a
c
t
o
r
f
o
r
h
i
s
d
e
s
i
g
n
C
h
a
p
t
e
r
5
E
m
p
l
o
y
e
r
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
Checklist   Explanation
WI 340 Access to information
following Completion
.
  State the Employers requirements for access
to information once the Defects Certicate is
issued including timescale for the retention of
information after Completion. Consider any
need for computer software source code for
example.
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
WI  400  Completion
Completion is when the Contractor has done all the work which the Works
Information states he is to do by the Completion Date and corrected notied
Defects which would have prevented the Employer from using the works and
Others from doing their work. If the work which the Contractor is to do by the
Completion Date is not stated in the Works Information, then Completion is when
the Contractor has done all the work necessary for the Employer to use the works
and for Others to do their work.
In order for the Project Manager to decide that Completion has occurred, the Works
Information must state clearly and unambiguously what work is to be done before
Completion.
Examples might include successful passing of stated key tests and provision of
as-built documentation. Refer to section WI 700 for test and inspection
requirements.
An alternative approach could be in the form of a statement of which part of the
works can remain incomplete at the Completion Date.
It may also be useful to state the procedures to be adopted to ensure a smooth
transition from construction to operation of the asset. This may also include
procedures leading up to Completion and between Completion and the Defects
Date.
Checklist   Explanation
WI 405 Completion denition
ECC  11.2(2)
Work to be done by the Completion Date.
WI 410 Sectional Completion
denition
ECC  X5.1  (Option  X5)
As above for each Sectional Completion.
WI 415 Training   Training required for the Employer or Others and
associated timescales.
WI 420 Final clean   Details of nal clean, removal of temporary
structures, materials, protection and tools.
WI 425 Security   Details of security arrangements and handover at
Completion.
WI 430 Correcting Defects   Procedures for access for the correction of any
Defects and process for liaison with the Project
Manager and Employer.
WI 435 Pre-Completion
arrangements
Requirements for preparing for take over.
WI 440 Take over
ECC  35.2
Identify parts of the works that the Employer
requires to use prior to Completion without taking
it over. Details to include
.
  location of parts of the works and
.
  reasons for use.
Contractors access provision during period of
use.
Chapter 5   Employers Works Information
www.neccontract.com
  #
 copyright nec  2012   25
C
h
a
p
t
e
r
6
W
I
p
r
o
v
i
d
e
d
b
y
t
h
e
C
o
n
t
r
a
c
t
o
r
f
o
r
h
i
s
d
e
s
i
g
n
C
h
a
p
t
e
r
5
E
m
p
l
o
y
e
r
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
WI  500  Programme
State any information additional to the requirements of ECC subclause 31.2 that
the Contractor is to include in the programme. This may include dates for
submission of designs and samples, dates for information or actions by the
Employer and Project Manager, and the timing of any test and inspection.
Any requirements for the format and content of the programme should be stated,
including the use of specic software (if necessary) and the requirement for hard
or electronic copies.
Checklist   Explanation
WI 505 Programme
requirements
ECC  31.2
As above.
WI 510 Programme
arrangement
Any specic arrangement of the programme,
including any requirement for the programme to
be produced in levels (summary level to detail
level).
WI 515 Methodology statement   Particular requirements for methodology
statements, including any specic requirement for
resource information.
WI 520 Work of the Employer
and Others
The order and timing of the work of the Employer
and Others to be included in the programme and
information to be provided. Refer as necessary to
sections WI 905 and WI 910.
WI 525 Information required   A schedule of information to be provided, who it is
to be provided by, and the date by which it is to
be provided.
WI 530 Revised programme   Any specic requirements for the submission of
revised programmes, such as an explanation of
changes.
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
WI  600  Quality  management
Detail the requirements for quality control and management.
Checklist   Explanation
WI 605 Samples   State the materials and samples required
including any procedures for submission and
acceptance.
WI 610 Quality statement   Any requirement for a quality statement from the
Contractor.
WI 615 Quality management
system
Any requirements for a quality management
system, including accreditations or legislative
standards.
WI  700  Tests  and inspection
Detail the tests and inspections required and which parties are involved in the test
and inspection process. Tests and inspections may also be detailed within work
specications. Ensure consistency of drafting between this section and the
contents of WI 2000.
Tests and inspections might be required for
.
  Samples of plant or materials provided by the Contractor.
.
  Samples of workmanship.
.
  Equipment,   Plant   and  Materials  outside  the  Working  Areas  before  payment   or
delivery.
.
  Work in the Working Areas.
.
  Plant and Materials, and work prior to Completion (see WI 400).
.
  Plant and Materials, and work after take over but before the defects date.
.
  System tests.
.
  Computer software tests.
.
  Performance tests.
State the materials, facilities and samples to be provided by the Contractor and the
Employer for tests and inspections, and the timing of these.
State the Plant and Materials which are to be tested and inspected before delivery to
the Working Areas, including details of the test or inspection.
Any test or inspection of Equipment, Plant and Materials outside the Working Areas
which have to be passed before marking by the Supervisor for payment should also
be stated.
If secondary Option X17 Low performance damages applies, detail the relevant
performance tests.
State any requirements for commissioning or performance tests in this section, in
the same way that other tests and inspections are described.
Further guidance is in the NEC3 ECC Guidance Notes.
Checklist   Explanation
WI 705 Tests and inspections
ECC  40.1
ECC  40.2
ECC  41.1
ECC  60.1(16)
Consider the following checklist for test and
inspection details.
.
  Objective, procedure and standards to be used.
.
  When they are to be done.
.
  Where they are to be done.
Chapter 5   Employers Works Information
www.neccontract.com
  #
 copyright nec  2012   27
C
h
a
p
t
e
r
6
W
I
p
r
o
v
i
d
e
d
b
y
t
h
e
C
o
n
t
r
a
c
t
o
r
f
o
r
h
i
s
d
e
s
i
g
n
C
h
a
p
t
e
r
5
E
m
p
l
o
y
e
r
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
Checklist   Explanation
.
  Who does the tests, and who is in attendance.
.
  Testing and inspection method.
.
  The Equipment required and who provides it.
.
  Access arrangements.
.
  Information or instructions required to be
provided.
.
  Materials, facilities and samples to be provided.
.
  Involvement of specialists.
.
  Acceptable results and deviations.
.
  Test environment.
.
  Documents to be provided before and after the
test.
.
  Whether or not authorisation to proceed to the
next stage of the work depends in the test
results.
WI 710 Management of tests
and inspections
Consider the requirement for a test and
inspection schedule, containing all relevant
information.
State the procedures for submission and review.
WI 715 Covering up completed
work
State timescales for the covering up of works
which have been tested.
WI 720 Supervisors procedures
for inspections and watching
tests
State any inspection procedures required by the
Supervisor.
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
WI  800  Management of the works
The Contract Data identies the Employer, Project Manager, Supervisor and
Contractor and states what each is required to do. It is important, in using this
section, not to contradict these obligations and duties. If any of their duties are
delegated to Others, the extent of the delegation should be set out.
The ECC establishes a procedural framework based on good project management
practice. It may be helpful to detail the communication procedures required to
support this.
This may include a framework of regular meetings, attendees required and
outputs. Explain how people will be involved in the management of the works and
how communications are to be managed. Consider the use of a chart setting out
the roles and responsibilities of the various parties involved.
State whether an internet based collaboration tool or other electronic
communication system is to be used.
Checklist   Explanation
WI 805 Project team  Others   As above.
WI 810 Communications   State any communication procedures which the
Contractor is required to follow. Consider the
following.
.
  Meetings, attendees and meeting records.
.
  Reporting requirements (e.g. progress reports).
.
  Information requirements.
.
  Electronic systems and communications.
.
  Use of standard forms and templates.
.
  Terminology and abbreviations.
Chapter 5   Employers Works Information
www.neccontract.com
  #
 copyright nec  2012   29
C
h
a
p
t
e
r
6
W
I
p
r
o
v
i
d
e
d
b
y
t
h
e
C
o
n
t
r
a
c
t
o
r
f
o
r
h
i
s
d
e
s
i
g
n
C
h
a
p
t
e
r
5
E
m
p
l
o
y
e
r
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
WI  900  Working  with the Employer and Others
Detail the activities of Others within the Working Areas.
The Contractor is required to co-operate with Others in obtaining and providing
information which they need in connection with the works. State any requirements
that have been agreed with Others.
Checklist   Explanation
WI 905 Sharing the Working
Areas with the Employer and
Others
ECC  25.1
ECC  60.1(5)
Provide a list of activities to be undertaken,
explaining the following.
.
  What is being done.
.
  Who is doing it.
.
  When it is being done, and for how long.
.
  Where it is being done.
.
  How the Contractor is to co-operate and share
the Working Areas.
WI 910 Co-operation   Identify known information requirements, for the
Contractor to obtain from Others or provide to
Others, and timing.
WI 915 Co-ordination   State how the Contractor is to liaise with the
Employer and Others for the co-ordination of
works and access.
WI 920 Authorities and utilities
providers
Identify works to be carried out by authorities and
utilities providers. State the responsibility for
enquiry, management, procurement, provision of
notices and payment.
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
WI  1000  Services  and other  things to  be provided
State the services and other things that are to be provided by the Employer for use
by the Contractor, and by the Contractor for use by the Employer, Project Manager
or Others. Identify who they are provided for. It is not necessary to list things that
the Contractor requires for his own use to Provide the Works.
State any requirements for quality and maintenance of services to be provided.
Checklist   Explanation
WI 1005 Services and other
things for the use of the
Employer, Project Manager or
Others to be provided by the
Contractor
ECC  25.2
May include the following.
.
  Accommodation.
.
  Meeting rooms.
.
  Storage facilities.
.
  Catering.
.
  Medical facilities and rst aid.
.
  Recreation.
.
  Sanitation.
.
  Security.
.
  Copying.
.
  Telephone, fax, radio or CCTV.
.
  Computer equipment and services.
.
  Sign boards and other signage.
.
  Safety equipment and services.
.
  Fences, screens and hoardings.
.
  Postage.
.
  Maintenance of access roads.
.
  Temporary facilities.
.
  Utilities, e.g. water and power.
.
  Meter readings.
WI 1010 Services and other
things to be provided by the
Employer
ECC  25.2
Same checklist as above. Consider the following
also.
.
  Access to the Site.
.
  Space for accommodation.
.
  Plant and Materials.
Chapter 5   Employers Works Information
www.neccontract.com
  #
 copyright nec  2012   31
C
h
a
p
t
e
r
6
W
I
p
r
o
v
i
d
e
d
b
y
t
h
e
C
o
n
t
r
a
c
t
o
r
f
o
r
h
i
s
d
e
s
i
g
n
C
h
a
p
t
e
r
5
E
m
p
l
o
y
e
r
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
WI  1100  Health  and safety
State any health and safety requirements for the project which the Contractor
must follow, in addition to the requirements of law.
Refer to Chapter 4 for guidance on the inclusion of health and safety information
in Works Information and Site Information.
Checklist   Explanation
WI 1105 Health and safety
requirements
ECC  27.4
Details of any additional health and safety
requirements for the project, all which may
include the following.
.
  Employers safety requirements.
.
  Reporting requirements.
.
  Safety management, supervision and
qualications.
.
  Management of Subcontractors.
.
  Drug and alcohol policy.
.
  Site induction procedures.
WI 1110 Method statements   Detail the operations for which the Contractor is
required to submit method statements and risk
assessments to the Project Manager for
acceptance.
WI 1115 Legal requirements   If any health and safety duties are required by
law, state who will perform them.
WI 1120 Inspections   State any requirement for review and inspection
of Contractors health and safety procedures by
the Project Manager.
WI  1200  Subcontracting
The Contractor may subcontract work using an NEC contract. Any restrictions on
the Contractor subcontracting work need to be set out.
The ECC does not provide for nomination of subcontractors, for the reasons
explained in the NEC3 ECC Guidance Notes. Alternatives to achieve similar
objectives are
.
  make  the  Contractor   responsible  for   all   work;   he  may   then  subcontract   parts
and   the   Project   Manager   retains   some   control   over   the   identity   of   the
Subcontractors using ECC clause 26 or
.
  provide for separate contracts, with the Project Manager managing  the time and
physical interfaces between them.
Checklist   Explanation
WI 1205 Restrictions or
requirements for subcontracting
State any restrictions and additional procedures
which the Contractor must follow.
WI 1210 Acceptance procedures
ECC  26.3
ECC 11.2(25)  Options C, D and E
ECC  11.2(26)  Option F
State any specic submission and acceptance
procedures for proposed subcontracts not based
upon an NEC contract. The basic requirement for
submission and acceptance is dealt with at
subclause 26.3.
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
WI  1300  Title
State the requirements for marking Equipment, Plant and Materials which are
outside the Working Areas by the Supervisor, for payment and transfer of title to
the Employer. The Works Information should state which items are to be prepared
for marking, and how this is to be done. Identify any tests which must be passed
before items are accepted for marking.
The Works Information should state which materials arising from excavations and
demolitions the Contractor has title to.
Checklist   Explanation
WI 1305 Marking
ECC  71.1
As above.
WI 1310 Materials from
excavation and demolition
ECC  73.2
Decide the title of materials from excavation and
demolition. State whether the Employer wishes to
salvage any such materials, and if so where they
are to be delivered to or collected from, and by
whom.
WI  1400  Acceptance or  procurement procedure  (Options C, D, E and  F)
State any acceptance or procurement procedures which apply in addition to the
constraints set out within section WI 1210. This is relevant to Options C, D, E and
F where payment to the Contractor is based upon Dened Cost. The denition of
Disallowed Cost refers to acceptance and procurement procedures stated in the
Works Information.
WI  1500  Accounts  and records (Options C,  D, E and F)
Detail any records to be kept by the Contractor, in addition to those listed in
subclause 52.2.
Checklist   Explanation
WI 1505 Additional Records
ECC  52.2  (Options  C, D, E and F)
List the additional records to be kept by the
Contractor. This may include the following.
.
  Timesheets and Site allocations sheets.
.
  Equipment records.
.
  Forecasts of the total Dened Cost.
.
  Specic procurement and cost reports.
Dene the format and presentation of records to
be kept.
Chapter 5   Employers Works Information
www.neccontract.com
  #
 copyright nec  2012   33
C
h
a
p
t
e
r
6
W
I
p
r
o
v
i
d
e
d
b
y
t
h
e
C
o
n
t
r
a
c
t
o
r
f
o
r
h
i
s
d
e
s
i
g
n
C
h
a
p
t
e
r
5
E
m
p
l
o
y
e
r
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
WI  1600  Parent company  guarantee (Option X4)
Include the form of parent company guarantee required.
WI  1700  Performance bond  (Option X13)
Include the form of performance bond required.
WI  1800  Advanced payment bond  (Option X14)
Include the form of advanced payment bond required.
WI  1900  Low performance damages  (Option  X17)
State the detailed requirements, performance standards and required tests,
relating to any performance levels stated in the Contract Data for Option X17, if
not already stated in section WI 705.
WI  2000 Employers work specications and drawings
Include here the detailed work specications and drawings which describe the
works. A contents list may be provided or the documents themselves may be
included or both.
Guidance for including work specications is in Chapter 3.
Checklist   Explanation
WI 2005 Employers work
specication
Contents list or documents or both.
WI 2010 Drawings   Contents list or documents or both.
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n
s
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
4
E
C
C
r
e
f
e
r
e
n
c
e
s
t
o
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
3
D
r
a
f
t
i
n
g
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
2
T
h
e
s
t
a
t
u
s
o
f
W
o
r
k
s
I
n
f
o
r
m
a
t
i
o
n
C
h
a
p
t
e
r
1
I
n
t
r
o
d
u
c
t
i
o
n