- 1 -
Bellevue        Bothell         Burien         Duvall       Gig Harbor      Issaquah        Kenmore        Kirkland         Mercer Island               
 
 
Special Inspections Manual 
April 2009 
Mill Creek       Mukilteo        Renton       Sammamish         SeaTac      Snohomish County        Snoqualmie       Woodinville 
 
 
TABLE OF CONTENTS 
 
      Purpose.  2 
A.  Types of Special Inspections 2 
B.  Determining Types Applied to Project. 2 
C.  Preconstruction Meetings.. 2 
D.  Designating the Special Inspection Agency 3 
E.  Special Inspector Qualifications ...3 
F.  Field Inspections  4 
G.  Procedural Requirements for Special Inspectors.. 5 
  Reinforced Concrete.. 6 
  Soils, Excavation, Filling, Drilled Piers, Pilings.. 8 
  Structural Steel (Welding, Bolting, Fabricators,  
Spray-Applied Fire Resistant Materials, Mastics &  
Intumescent Fire-Resistant Coatings) . ......... 9 
  Structural Masonry....11  
  Seismic Resistance (Steel, Structural Wood, Equipment, 
Components, etc.)....12  
  Exterior Insulation and Finish Systems (EIFS).13 
  Smoke Control Systems . 13   
H.  Single Family Homes14 
I.  Structural Observation  15 
J.  Special Cases ............. 15 
 
References: 
2006 IBC Chapters 17 and 19 
WABO Standard 1701, 4
th
 Edition 
Seattle DPD Directors Rule 35-96 
Kansas City Special Inspection Manual 
 
 
  - 2 - 
 
 
 
 
MyBuildingPermit.com 
SPECIAL INSPECTIONS MANUAL 
 
The  purpose  of  this  Special  Inspection  Manual  is  to  establish  the  minimum 
inspection  and  testing  requirements  for  special  inspections  as  required  by 
Chapter 17 of the International Building Code. Particular emphasis is given to the 
duties  and  responsibilities  of  the  registered  special  inspector  and  the  Authority 
Having Jurisdiction (AHJ) building inspector. 
 
 
A. TYPES OF SPECIAL INSPECTIONS- CATEGORIES 
 
1.  Fabricators 
2.  Steel Construction 
3.  Concrete Construction 
4.  Masonry 
5.  Lateral Wood 
6.  Soils 
7.  Pile Foundations 
8.  Piers 
9.  Spray Applied Fire-resistant Materials 
10.  Mastic & Intumescent Fire-resistant Coatings 
11.  EIFS (exterior insulation & finish systems) 
12.  Special Cases 
13.  Smoke Control 
 
B. DETERMINING TYPES APPLIED TO PROJECT 
A Statement of Special Inspections shall be completed  by the registered design 
professional  and  submitted  as  part  of  the  plan  submittals  for    projects  requiring 
special  inspection.    This  form  shall  state  which  special  inspection  types  are 
required  as  determined  by  the  designer.  The  AHJ  plan  reviewer  will  review  this 
for accuracy, and then indicate the appropriate types on the front of the approved 
set of plans on the Special Inspection Schedule.   
C. PRECONSTRUCTION MEETINGS 
A preconstruction meeting is required at the beginning of the project prior to the 
initial  placement  and  inspection  of  materials  requiring  inspection.    The 
preconstruction meeting shall be coordinated through the building inspector.  The  
building  inspector  shall  be  responsible  for  facilitating  this  meeting  or  make 
necessary  arrangements  for  one  of  the  other  primary  parties  to  do  so.  
Attendance is required by the special inspector and the contractor and may  also 
  - 3 - 
 
 
 
require attendance by the engineer of record (EOR), the architect and the plans 
examiner.  Questions regarding AHJ inspection requirements, special inspection 
requirements,  special  inspection  personnel,  protocol  and  project  design 
requirements will be discussed at this meeting. 
Separate  preconstruction  meetings  shall  also  be  held  prior  to  starting  shotcrete 
or  post  tension  concrete  construction.    Contact  the  local  AHJ  building  inspector 
for  any  additional  precon  requirements  for  inspection  types  listed  in  section  A.  
For  shotcrete  procedures  see  Shotcrete  Preconstruction  Meeting  Agenda 
(contact AHJ for information). For post tension slab procedures see Post-tension 
Preconstruction Meeting Agenda (contact AHJ for information). 
D. DESIGNATING THE SPECIAL INSPECTION AGENCY 
The  Statement  of  Special  Inspections  required  in  section  B  will  indicate  the 
agency  designated  to  perform  special  inspections  and  tests.    In  the  event  that 
there is a subsequent change to a different agency, the owner shall submit to the 
AHJ, another statement naming the new agency, and the reason for the change. 
E. SPECIAL INSPECTOR QUALIFICATIONS 
Special Inspector: IBC Section 1704 specifies the special inspector shall be a 
qualified  person  who  shall  demonstrate  competence,  to  the  satisfaction  of  the 
building  official,  for  inspection  of  the  particular  type  of  construction  or  operation 
requiring  special  inspection.  Special  inspectors  shall  be  certified  by  the 
Washington  Association  of  Building  Officials  (WABO)  for  the  particular  type  of 
inspection they are performing.  
Placement Inspector (assistant): An employee of an agency, certified by WABO 
as  a  placement  inspector,  and  is  assigned  to  perform field  concrete  testing  and 
concrete  placement  inspection  for  non-complex  structures.  This  includes 
placement  of  concrete  into  elements  such  as  footings,  walls,  slab-on-grade  and 
slabs  on  metal  deck,  drilled  piers,  caissons  and  tilt-up  walls  in  which  the 
reinforcing steel (and other embedded structural elements such as anchor bolts, 
deck  welding,  welded  studs  and  expansion  anchors)  has  been  previously 
inspected  by  a  WABO  Reinforced  Concrete  Inspector.    Placement  inspector 
tasks do not include independent monitoring of high strength concrete 6,000 psi 
or greater, or complex structures such as post-tension decks, reinforced concrete 
decks,  special  moment  resisting  concrete  frames  or  other  structures  deemed  to 
be  complex  by  the  building  official  unless  under  direct    supervision  of  a  WABO 
Reinforced  Concrete  Inspector.    Placement  Inspectors  may  also  perform  batch 
plant inspection. 
 
 
Field Testing Technicians are not registered by WABO, but must possess 
  - 4 - 
 
 
 
an unexpired ACI Concrete Field Testing Technician-Grade 1 certification.  
                           Field Technicians may perform and record the results of basic concrete field tests 
on projects where such work is required, if approved by the building inspector. 
A field testing technician shall operate at all times under the on-site supervision 
of a special inspector registered for Reinforced Concrete or Reinforced Concrete 
and Prestressed Concrete.  If more than one field testing technician is to be used 
on a project, it must be approved by the building inspector. 
 
F. FIELD INSPECTIONS 
AHJ building inspectors are encouraged to personally meet special inspectors on 
site  whenever  inspections  take  place,  in  order  to  verify  credentials,  exchange 
contact information, oversee that work is being properly inspected and recorded, 
and generally work together if needed to address specific issues of the project. 
Note: Special inspections are in addition to AHJ required inspections and as such 
the  contractor  shall  submit  requests  for  AHJ  inspections  at  each  stage  or 
placement of the work.  
Verification  of  Credentials.  AHJ  building  inspectors  shall  confirm  the  special 
inspectors qualifications by requesting to see their WABO certification card and 
photo  ID.  If  the  AHJ  inspector  is  unable  to  make  direct  contact  with  the  special 
inspector  on  site,  the  general  contractor  is  highly  encouraged  to  obtain  a 
photocopy  of  the  certification  card  (front  and  backside)  and  provide  this  to  the 
AHJ inspector at the next site visit. For large projects, the contractor shall obtain 
photocopies  of  certification  cards  of  all  special  inspectors  anticipated  to  be  on 
site  during  the  duration  of  the  project,  and  make  these  available  to  the  AHJ 
inspector as needed.  
Special inspections performed by non-WABO certified inspectors will not 
be approved. 
On  projects  involving  welding,  the  building  inspector  will  be  responsible  for 
verifying  each  welder  is  WABO  certified  by  requesting  to  see  both  their  WABO 
card  and  photo  ID.  The  special  inspector  for  welding  may  also  perform  this 
verification if he/she has the opportunity.     
Building inspector level of inspection. AHJ building inspectors are expected to 
perform  substantial  inspections  on  all  concrete  and  masonry  construction, 
including  forms,  reinforcement,  PT  and  shotcrete  setups,  CMU,  etc.  The 
presence of special inspectors shall not preclude AHJ inspectors from evaluating 
the quality of the actual work. On large projects, however, where a positive track 
record has been established with special inspection personnel on inspections of 
a repetitive nature, the AHJ inspector may, at his/her own discretion, reduce the 
  - 5 - 
 
 
 
level of scrutinization done by the AHJ. This does not alleviate the AHJ inspector 
from  the  responsibility  of  oversight  of  the  special  inspection  process  nor  from 
doing general evaluations of the physical work being performed. In any case, the 
AHJ inspector shall ensure that all types and phases of work within a project are 
covered by appropriate inspections, whether personally or by special inspection. 
In  the  event  that  the  AHJ  inspector  becomes  aware  of  deficiencies  in  the 
performance  of  the  special  inspector,  the  AHJ  inspector  shall  address  the 
deficiencies with the special inspector in an attempt to correct the situation. If the 
special  inspector  does  not  make  the  appropriate  adjustments  to  the  satisfaction 
of the AHJ inspector, the AHJ inspector will notify the contractor and the special 
inspection  agency  that  the  individual  in  question  will  no  longer  be  allowed  to 
perform inspections on any projects within that jurisdiction.  
G. PROCEDURAL REQUIREMENTS FOR SPECIAL INSPECTORS 
 
The  general  contractor  shall  ensure  that  up to  date  copies  of the  AHJ  reviewed 
plans,  specifications  and  shop  drawings  are  provided  to  the  special  inspector 
prior to the start of the affected work. 
 
It  is  the  special  inspectors  responsibility  to  review  the  AHJ  reviewed  plans 
thoroughly and sufficiently in advance of construction to establish that adequate 
information is available to conduct the required inspections and tests.  All errors 
and/or  omissions  in  the  reviewed  plans  that  create  any  form  of  uncertainty  or 
ambiguity shall be resolved through the architect or engineer of record. 
 
The contractor is responsible for notifying the special inspection agency when the 
work is ready for inspection.  A minimum of 24-hours notice shall be provided so 
that the special inspector has time to inspect the work prior to concealment.  The 
contractor  shall  provide  access  to  and  means  for  safe  and  proper  inspection  of 
the  work.    It  is  the  contractors  responsibility  to  verify  that  all  work  requiring 
special inspections is inspected and/or tested prior to concealment. 
Special  inspectors  shall  perform  inspections  and/or  tests  of  the  work  for 
conformance  with  the  AHJ  reviewed  plans,  specifications,  shop  drawings  and 
applicable  provisions  of  the  International  Building  Code.  Special  inspectors,  like 
AHJ  building  inspectors,  shall  use  only  AHJ  approved  plans  and  details  when 
performing  inspections.  Significant  revisions  to  the  approved  plans  will  be 
required  to  be  submitted  to  the  Building  Department  for  review,  and  must  be 
approved prior to the work being approved on site. 
Discrepancies  in  the  work  being  performed  shall  be  brought  to  the  immediate 
attention  of  the  contractor  for  correction.  If  the  discrepancies  are  not  corrected, 
the discrepancies shall be brought to the attention of the building inspector and to 
the  registered  design  professional  in  responsible  charge  prior  to  the  completion 
  - 6 - 
 
 
 
of  that  phase  of  the  work.  In  the  event  that  the  contractor  continues  to  perform 
work  that  the  special  inspector  knows  to  be  non-conforming,  that  inspector  will 
contact  the  AHJ  inspector  immediately  to  inform  him/her  of  the  situation,  and  to 
ask direction as to what course of action to take. 
 
After  each  inspection,  the  special  inspector  shall  give  the  contractor  a  daily 
inspection  report.  The  special  inspector  shall  also  furnish  these  reports  to  the 
AHJ  building  inspector,  and  to  the  registered  design  professional  in  responsible 
charge.  Reports  shall  indicate  what  work  was  inspected  and  whether  it  was  in 
was done in conformance to approved construction documents.  
 
The general contractor shall maintain a designated file for the special inspectors 
daily  reports.  This  file  shall  be  located  in  a  conspicuous  place  in  the  project 
trailer/office to allow review by AHJ inspectors.  The file shall be kept up-to-date. 
 
Final  Report. When  the  work  requiring  special  inspections  is  completed  and all 
nonconforming items have been resolved, the general contractor shall notify the 
special  inspector  of  record  to  submit  a  Final  Special  Inspections  Report  to  the 
AHJ,  engineer  and/or  architect  of  record,  and  the  general  contractor.  It  is  the 
responsibility  of  the  Special  Inspection  Agency  to  verify  that  all  construction 
under  the  assigned  responsibility  of  the  Agency  has  been  inspected  and 
approved prior to completing the final report.  A Certificate of Occupancy will not 
be issued until the final report has been reviewed and approved by the AHJ. 
 
 
REINFORCED CONCRETE 
(PLACEMENT, TESTING, BOLTS, REINFORCING STEEL) 
 
Placement  of  Reinforced  Concrete;  IBC  Table  1704.4,  (Item  4,6  &  7)  Section 
1905 
 
A special inspector shall be on-site during the placement of reinforced concrete.  
The inspector shall provide a continuous inspection of the conveying, depositing, 
and  consolidation  of  concrete,  for  conformance  with  the  AHJ  reviewed  plans, 
specifications  and  Chapter  19  of  the  IBC.    The  special  inspector  shall  observe 
placement  procedures  for  evidence  of  segregation,  possible  cold  joints, 
displacement  of  reinforcing  or  forms,  and  proper  support  of  embedded  items, 
anchor bolts, etc.  When the point of deposit of concrete cannot be observed by 
the individual monitoring the discharge from trucks or the batch plant, additional 
personnel shall be provided. 
 
Concrete  delivery  tickets  shall  be  checked  to  verify  that  the  class  of  concrete 
ordered  is  being  delivered  and  conforms  to  project  plans,  specifications  and/or 
code requirements. 
 
  - 7 - 
 
 
 
Testing of Reinforced Concrete; IBC Table 1704.4 (Item 5), Section 1905.6. 
 
For each class of concrete placed each day, the special inspector shall obtain a 
sample for strength tests at the frequency stated in Section 1905.6.2 of the IBC 
or  AHJ  reviewed  specifications.    A  strength  test  shall  be  the  average  of  the 
strengths  of  two  cylinders,  made  from  the  same  sample  of  concrete,  laboratory 
cured, and tested at 28 days.  Additional cylinders shall be cast if any changes in 
the mix consistency are noted or when directed by the architect or EOR. 
 
Concrete  test  cylinders  shall  be  cast,  stored  and  tested  in  accordance  with 
Chapter  19  of  the  IBC.  The  size  of  the  cylinders  shall  be  specified  by  the 
engineer of record in the construction documents. If the strength test of cylinders 
falls  below  the  specified  value  of  f  c  by  more  than  500  psi,  the  special 
inspections  agency  shall  notify  the  general  contractor  immediately  so  remedial 
action can be taken in accordance with Section 1905.6.5 of the IBC. 
 
Slump,  air-content,  and  temperature  tests  shall  be  conducted  when  strength 
specimens are made, or at the option of the inspector, as often as necessary for 
control  checks.    All  other  concrete  testing  shall  be  conducted  as  stated  in  the 
project specification and per ASTM Standards. 
 
Bolts Installed in Concrete; IBC Table 1704.4 (Item 3) and Section 1912. 
 
An  inspection  is  required  prior  to  and  during  the  placement  of  concrete  around 
bolts.    The  special  inspector  shall  verify  that  the  bolt  size,  location  and 
embedment  length  are  in  conformance  with  the  AHJ  reviewed  plans, 
specifications and shop drawings. 
 
Placement  of  Reinforcing  Steel;  IBC  Table  1704.4  (Item  1),  Sections  1907  &  
1915.4. 
 
Prior to the closing of forms or the delivery of concrete to the job site, the special 
inspector  shall  verify  that  the  reinforcing  steel  is  of  correct  size  and  grade  and 
ensure that the proper spacing, clearances, splice lengths and embedded items 
have been provided.  All reinforcing steel shall be in place prior to the placement 
of concrete and be secured against displacement. 
 
Post-tensioned Concrete; IBC Table 1704.4 (Item 8) 
 
Prior to the placement of concrete, the special inspector shall verify that the rebar 
and tendons have the proper chair heights, tendon profiles, clearances, and steel 
anchorage  as  detailed  in  the  AHJ  reviewed  plans,  specifications  and  shop 
drawings. 
  - 8 - 
 
 
 
The special inspector shall be present during the entire  placement and stressing 
operations. The special inspector shall calibrate or review current calibration data 
on  the  proposed  stressing  equipment  and  verify  that  the  concrete  meets  the 
minimum  required  compressive  strength  prior  to  post-tensioning.  For  more 
detailed requirements contact AHJ for information. 
Shotcrete:   IBC Table 1704.4, (Item 4,6 & 7) Section 1905, 1913 
 
A  special  inspector  shall  be  on-site  during  the  placement  of  shotcrete  used  for 
permanent  construction  elements.    Contact  the  AHJ for  requirements  or  placing 
shotcrete  for  temporary  shoring.    The  inspector  shall  provide  a  continuous 
inspection of the placing, and consolidation of concrete, for conformance with the 
AHJ  reviewed  plans,  specifications  and  Chapter  19  of  the  IBC.    The  special 
inspector  shall  observe  placement  procedures  for  evidence  of  segregation, 
proper  joints,  displacement  of  reinforcing  or  forms,  and  proper  support  of 
embedded  items,  anchor  bolts,  etc.    The  special  inspector  will  also  observe 
nozzel-men  prequalification  test  panels  as  well  as  evaluating  cores.    When  the 
point of deposit of concrete cannot be observed by the individual monitoring the 
discharge from trucks or the batch plant, additional personnel shall be provided. 
 
Concrete  delivery  tickets  shall  be  checked  to  verify  that  the  class  of  concrete 
ordered  is  being  delivered  and  conforms  to  project  plans,  specifications  and/or 
code requirements.  For more detailed requirements contact AHJ for information. 
 
SOILS, EXCAVATION, FILLING, DRILLED PIERS, PILINGS 
 
Verification of Soils; IBC Section 1704.7 and Chapter 18 
 
The  sub  grade  supporting  the  footings  of  buildings  or  structures  shall  be 
inspected immediately prior to the placement of reinforced concrete.  The special 
inspector  (the  geotechnical  engineer)  shall  observe  and  test  all  footing 
excavations to verify conformance with  AHJ reviewed plans and/or geotechnical 
engineers report.  The foundation shall be of proper size and depth and free of 
any loose, deleterious or foreign material. 
 
Where unsuitable bearing conditions are observed, the geotechnical engineer of 
record  and  project  engineer  of  record  shall  be  notified  immediately  so  that 
remedial procedures can be established. 
 
Excavation and Filling; IBC Sections 1704.7, 1803, 3304. 
 
During the placement of engineered structural fill, the geotechnical engineer shall 
provide sufficient observation to verify that the preparation of the natural ground 
and  placement  of  compacted  fill  is  being  performed  in  accordance  with  the 
geotechnical  engineers  recommendations.    The  geotechnical  engineer  shall 
  - 9 - 
 
 
 
monitor  the  placement  of  each  lift  of  engineered  structural  fill  supporting  the 
foundation of any structure. 
 
The geotechnical engineer shall monitor and test all fill to determine whether the 
type  of  material,  moisture  content  and  degree  of  compaction  are  within  the 
recommended limits set forth by the geotechnical engineer of record.   
 
Drilled Piers and Piles; IBC Sections 1704.8-9, 1802.2.4 and 1807-11. 
 
A geotechnical engineer shall be on-site during the construction of all piers, piles 
(including pin piles) and pressure-injected footings.  Work shall be in accordance 
with the AHJ reviewed drawings and as specified by the geotechnical engineer of 
record. For cast in place concrete piles and piers, a special inspector certified for 
Reinforced  Concrete  shall  also  monitor  the  installation  of  reinforcing  steel,  and 
the placement and testing of the concrete. 
 
Earth  Retaining  Structures  (Retaining  Walls),  IBC  Section  1610,  1622.4.2, 
1704.13, 1802, 1803, and 2304.11.7. 
 
A  slope  retention  system  designed  to  resist  active  earth  pressure  shall  have 
special  inspections.  The  special  inspector  shall  perform  the  necessary 
inspections  and  tests  to  ensure  the  system  is  installed  per  the  AHJ  reviewed 
plans  and  specifications.  For  more  detailed  requirements  contact  AHJ  for 
information. 
 
Earth  retaining  structures  (modular,  stacked  stone,  etc.)  shall  be  installed  in 
accordance  with  plans  and  specifications  prepared  by  a  registered  design 
professional  in  accordance  with  the  geotechnical  exploration  and  results  of  the 
global stability analysis.   
 
STRUCTURAL STEEL 
 
(WELDING, HIGH STRENGTH BOLTING, STEEL FRAME) 
INSPECTION OF FABRICATOR, SPRAYED FIRE RESISTANT MATERIAL 
AND INTUMESCENT PAINT 
 
Field Welding of Structural Steel; IBC Section 1704.3, 2204.1. 
 
Special  inspections  are  required  for  the  welding  of  structural  members  or 
connections  for  compliance  with  the  AHJ  reviewed  plans,  shop  drawings, 
specifications and Chapter 22 of the IBC.  The special inspector shall provide a 
continuous inspection of the structural welding unless the requirements of Table 
1704.3  Item 5  and/or Section 1704.3  (Items  2.1-2.5)  are  satisfied,  thus  allowing 
periodic  inspections.    For  periodic  inspection,  the  special  inspector  shall  check 
  - 10 - 
 
 
 
qualifications of welders at the start of work and then make final inspection of all 
welds for compliance prior to completion of welding.   
 
The special inspector shall inspect the equipment, material and technique being 
employed and verify that the welding is performed by certified welders qualified in 
the  procedure  being  used.    A  visual  inspection  of  the  completed  work  shall  be 
made to ensure proper type, size, length and quality of the welds. 
 
Field Bolting of Structural Steel; IBC Section 1704.3.3, 2204.2 
 
Structural  steel  joints  using  A325  high-strength  bolts,  A490  heat-treated  high-
strength bolts or equivalent fasteners shall have special inspections.  The special 
inspector  shall  monitor  the  prequalification,  installation  and  tightening  of  bolted 
connections in accordance with the AHJ reviewed plans and Table 1704.3 (Items 
1 and 2). 
 
When  bolted  connections  require  full  pretension,  the  special  inspector  shall 
prequalify the pretensioning method and verify that the specified procedure was 
used to achieve the design tension.  A tension calibrator shall be provided, at the 
job  site,  to  verify  fastener  assemblies,  train  installation  crews,  and  calibrate 
wrenches  (if  calibrated  wrench  method  is  used).    The  AHJ  recommends  a 
meeting  between  AHJ  inspector,  the  special  inspector  and  the  steel  erector  to 
establish the  procedures  to be  used as  required  prior  to any  erection  especially 
when full pretension is specified. 
 
Bolts  in  connections  identified  as  not  being  slip  critical  not  subject  to  direct 
tension  need  not  be  inspected  for  bolt  tension.    The  special  inspector  does  not 
need to be present during the entire installation and tightening operation provided 
that  the  bolts  are  installed  in  properly  aligned  holes  and  tightened  to  the  snug-
tight condition.  Bolts required to be tightened only to a snug-tight condition shall 
be clearly identified on the reviewed drawings. 
 
Steel  Frame  Inspection;  IBC  Section  1704.3,  Table  1704.3  (Items  3  and  6), 
Chapter 22. 
 
The special inspector shall perform an inspection of the structural steel frame to 
verify  compliance  with  the  details  shown  on  the  AHJ  reviewed  plans  and  shop 
drawings,  such  as  bracing,  stiffening,  member  size  and  location,  and  proper 
application of joint details at each connection. 
 
Inspection of Fabricator; IBC Section 1704.2, and Chapter 22. 
 
The following organizations are locally recognized as being qualified to certify 
fabricators.  Contact the AHJ for confirmation.  See also MyBuildingPermit.com 
policy statement regarding approved fabricator. 
  - 11 - 
 
 
 
 
  American Institute of Steel Construction (AISC), 
  International Accreditation Service, Inc. (IAS), 
  Canadian Welding Bureau (CWB), 
  Steel Joist Institute (SJI). 
 
Structural  steel,  bar  joists  and  metal  buildings  fabricated  on  the  premises  of  a 
facility/plant  not  certified  by  a  nationally  recognized  organization  shall  have  in-
plant special inspections as follows: 
 
The  special  inspector  shall  inspect  the  work,  during  fabrication,  for  compliance 
with  the  AHJ  reviewed  plans,  shop  drawings,  specifications  and  Chapter  22  of 
the IBC.  Each member shall be inspected and approved by the special inspector 
prior  to  shipment.    It  is  the  responsibility  of  the  fabricator  to  notify  the  special 
inspections agency and have the reviewed plans on-site for the inspection.  The 
general  contractor  shall  coordinate  this  inspection.    Daily  reports  indicating  the 
members  inspected  shall  be  available  on  the  site  where  the  steel  is  being 
installed for review by the Building Inspector. 
 
Spray-Applied Fire Resistant Materials; IBC Section 1704.10 & 1704.11. 
 
When  spray-applied  fire  resistant  materials  are  provided  for  the  fire-resistive 
protection  of  structural  steel  members,  special  inspections  are  required  for 
conformance  to  the  manufacturers  instructions  per  1704.10.   When  mastic  and 
intumescent  fire-resistant  coatings  are  applied  to  structural  steel  members, 
special  inspections  are  required  for  conformance  to  the  manufacturers 
instructions per 1704.11. 
 
Surface conditions shall be inspected prior to the application.  Minimum substrate 
ambient temperature shall be verified before and after application. 
 
The  special  inspector  shall  inspect  the  fireproofing  in  accordance  with  IBC 
1704.10  or  1704.11  as  applicable,  and  the  AHJ  reviewed  plans  and 
specifications.    The  thickness  and  density  of  the  fireproofing  shall  not  be  less 
than  the  requirements  of  the  listing  of  the  fire-resistive  assembly.    The 
cohesive/adhesive  bond  strength  shall  be tested  as  required for  the  appropriate 
application. 
 
Just  prior  to  concealment,  a  complete  visual  inspection  of  the  fireproofed 
members shall be conducted.  The special inspector shall verify that the sprayed 
fire  resistant  material  has  no  voids,  spalls,  and  delamination  or  that  no  material 
has been scraped or knocked off during construction. 
 
 
 
  - 12 - 
 
 
 
 
STRUCTURAL MASONRY   
 
The  special  inspector  shall  provide  the  inspection  and  testing  of  structural 
masonry  for  conformance  with  the  AHJ  reviewed  plans,  specifications  and 
Section 1704.5 and 1708.1 of the IBC. 
 
The  special  inspector  shall  provide  a  continuous  inspection  of  the  handling, 
storage preparation and placement of all elements involved in structural masonry 
construction.  During cold weather construction, the special inspector shall verify 
that the provisions of IBC Section 2104.3 are being observed. 
 
Mortar and grout shall be property mixed using the specified material proportions 
per  the  mix  design.    The  method  of  measuring  shall  be  such  that  the  material 
proportions are controlled. 
 
For  empirically  designed  masonry,  glass  unit  masonry,  and  masonry  veneer  in 
essential facilities, or engineered masonry in nonessential facilities the minimum 
special inspection program shall comply with IBC Table 1704.5.1. 
 
For  engineered  masonry  in  essential  facilities  the  minimum  special  inspection 
program shall comply with IBC Table 1704.5.3. 
 
 
SEISMIC RESISTANCE 
 
The special inspections for seismic resistance are in addition to those required in 
Section  1704  when  required  in  Sections  1705,  1707,  1708  and  1709.    The 
engineer-of-record  shall  identify  the  seismic-force-resisting  systems  and  other 
designated seismic systems in the structure. 
 
Steel.  Continuous inspection of welding in accordance with Section 1707.2 and 
AWS D1.1 is required for steel and is the same as in Table 1704.3, Item 5. 
 
Structural  wood.    Special  inspections  in  accordance  with  Section  1707.3  to 
ensure continuity of load path with the seismic-force-resisting system.  Particular 
care  should  be  given  to  the  nailing  of  diaphragms  and  shear  walls.    Also  of 
particular  importance  is  the  connection  of  drag  struts  or  collectors  to  the  shear 
walls and the proper installation and tightening of hold-down bolts in shear walls. 
 
  Exception:  Fastening of wood sheathing used for wood shear 
  walls, shear panels and diaphragms where the fasteners spacing 
  are more than 4 on center. 
 
  - 13 - 
 
 
 
Cold-formed  steel  framing.    Special  inspections  in  accordance  with  Section 
1707.4 to ensure continuity of load path within the seismic-force-resisting system. 
 
Storage  racks  and  access  floors.    Periodic  inspections  in  accordance  with 
Section 1707.6 required during the anchorage of access floors and storage racks 
8 or greater in height in Seismic Design Categories D, E or F. 
 
Architectural  components.    Special  inspection  in  accordance  with  Section 
1707.7 of architectural components in Seismic Design Categories D, E or F. 
 
Mechanical  and  electrical  components.      Special  inspection  in  accordance 
with  Section  1707.8  for  components  that  must  function  in  post  earthquake 
conditions such as emergency electrical systems or for anchorage of mechanical 
equipment,  piping,  and  ducting  using  or  carrying  flammable  or  hazardous 
material. 
 
Designated  Seismic  System  Verifications.    Special  inspection  in  accordance 
with Section 1707.9 and 1708.5 and verify that the label, anchorage or mounting 
conforms to the certificate of compliance. 
 
Seismic  Isolation  Systems.    Periodic  special  inspection  is  required  during  the 
fabrication  and  installation  of  isolator  units  and  energy  dissipation  devices  that 
are part of the seismic isolation system. 
 
 
 
EXTERIOR INSULATION AND FINISH SYSTEMS (EIFS) 
 
Special inspection for EIFS systems shall be based on manufacturers installation 
instructions.  Critical areas necessary for adequate EIFS performance are proper 
installation  of  waterproofing  membrane  and  installation  of  flashings  at  windows, 
doors, joints, eaves, corners and penetrations (IBC Section 1704.12). 
Exceptions:  
1. Special inspections shall not be required for EIFS applications installed over a 
water-resistive barrier with a means of draining moisture to the exterior. 
2.  Special  inspections  shall  not  be  required  for  EIFS  applications  installed  over 
masonry or concrete walls. 
 
 
SMOKE CONTROL SYSTEMS 
 
  - 14 - 
 
 
 
Special  Inspection  of  smoke-control  systems  (IBC  Section  1704.14,  Section 
909.3). 
 
Although this inspection is related to mechanical systems rather than structural or 
architectural  systems,  it  is  required  because  the  mechanical  ductwork  and 
signaling devices are likely to be concealed during the building construction and 
the  ductwork  must  be  leakage  tested  prior  to  concealment.    The  design 
submission  accompanying  the  construction  documents  shall  clearly  detail 
procedures  and  methods  to  be  used  and  the  items  subject  to  such  inspections 
and tests. 
 
The  final  performance  test  shall  be  coordinated  with  the  final  occupancy 
inspection and also witnessed by the AHJ building and/or mechanical and/or fire 
inspector.  Contact the AHJ for specific process and inspection requirements. 
 
Smoke  control  systems  installed  for  the  following  purposes  are  subject  to  the 
requirements of IBC Section 909 and require special inspection: 
 
  A covered mall building (IBC 402.9). 
  An atrium (IBC 404.4). 
  An underground building (IBC 405.5). 
  A Group I-3 windowless building (IBC 408.8). 
  A smokeproof enclosure (IBC 403.13, 405.8.2, 909.20,1019.1.8). 
  A stage (IBC 410.3.7.2). 
  Smoke-protected assembly seating (IBC 1025.6.2.1). 
 
The  special  inspector  shall  verify  compliance  to  the  sections  noted  above  and 
IBC  909,  and  to  the  design  documents.    The  test  scope  shall  be  in  accordance 
with IBC Section 1704.14.1: 
 
  During erection of ductwork and prior to concealment for the 
purpose of leakage testing and recording of device location. 
 
  Prior to occupancy and after sufficient completion for the 
purposes of pressure difference testing, flow measurements 
and detection and control verification. 
 
The  special  inspection  agency  for  smoke  control  shall  have  expertise  in  fire-
protection engineering, mechanical engineering and certification as air balancers 
(IBC Section 1704.14.2). 
H. SINGLE FAMILY HOMES 
Special  inspections  for  residential  applications  shall  generally  follow  the  same 
guidelines  as  for  commercial  projects.  Typical  categories  may  include 
  - 15 - 
 
 
 
requirements  for  soils,  site  drainage,  pilings,  high  strength  concrete  or  epoxy 
bolting.  The  AHJ approved  plans  will  indicate  those  categories  requiring  special 
inspections.  As  with  commercial  construction,  residential  structures  will  not 
receive  a  certificate  of  occupancy  until  all  required  inspections  have  been 
completed and the final report is furnished to the AHJ. 
I. STRUCTURAL OBSERVATION when required by Section 1709, shall be the 
visual  observation  of  the  structural  system  by  a  design  professional  for  general 
conformance to the approved construction documents.  At the conclusion of the 
work  included  in  the  permit,  the  structural  observer  shall  submit  to  the  building 
official  a  written  statement  that  the  site  visits  have  been  made  and  identify  any 
reported  deficiencies  which,  to  the  best  of  the  structural  observers  knowledge, 
have not been resolved. 
J. SPECIAL CASES Special inspections may be required by the building official 
for  work  that  is  unusual  or  nontypical  in  nature.    See  IBC  Section  1704.13  for 
examples.