CONSTRUCTION INDUSTRY INSTITUTE CONSTRUCTION INDUSTRY INSTITUTE CONSTRUCTION INDUSTRY INSTITUTE CONSTRUCTION INDUSTRY INSTITUTE CONSTRUCTION INDUSTRY INSTITUTE
Research Summary 130-1
REFORMING  OWNER,
CONTRACTOR,  SUPPLIER
RELATIONSHIPS:
A  PROJECT  DELIVERY  SYSTEM
TO  OPTIMIZE  SUPPLIER  ROLES
IN  EPC  PROJECTS
Construction Industry Institute
Air Products & Chemicals, Inc.
AlliedSignal Inc.
Aluminum Company of America
Amoco Corporation
Anheuser-Busch Companies, Inc.
Aramco Services Company
Atlantic Richfield Company
Bayer Corporation
Celanese
Champion International Corporation
Chevron Corporation
CITGO Petroleum Corporation
Commonwealth Edison Company
DuPont
Eastman Chemical Company
Exxon Research & Engineering Company
FPL Energy, Inc.
General Motors Corporation
Houston Lighting & Power Company
Intel Corporation
Eli Lilly and Company
Mobil Technology Corporation
NASA
Naval Facilities Engineering Command
Ontario Hydro
Phillips Petroleum Company
The Procter & Gamble Company
Rohm and Haas Company
Shell Oil Company
Solutia Inc.
Tennessee Valley Authority
Texaco
U.S. Army Corps of Engineers
U.S. Department of Commerce
U.S. Department of State
U.S. Generating Company
U.S. Steel
Union Carbide Corporation
The University of Texas System
Weyerhaeuser Company
ABB Lummus Global Inc.
BE&K, Inc.
Bechtel Group, Inc.
Belcan Corporation
Black & Veatch
BMW Constructors, Inc.
Brown & Root, Inc.
Bufete Industrial
Burns and Roe Enterprises, Inc.
CDI Engineering Group, Inc.
Chemtex International Inc.
Cherne Contracting Corporation
Cianbro Corporation
Day & Zimmermann International, Inc.
Dick Corporation
Dillingham Construction Holdings Inc.
Eichleay Holdings Inc.
Fisher Controls International, Inc.
Fluor Daniel, Inc.
Foster Wheeler USA Corporation
Fru-Con Construction Corporation
James N. Gray Company, Inc.
Graycor
H+M Construction Co., Inc.
Hilti Corporation
Honeywell Inc.
International Technology Corporation
Jacobs Engineering Group, Inc.
J. A. Jones Inc.
The M. W. Kellogg Company
Kiewit Construction Group, Inc.
Kvrner Process
Morrison Knudsen Corporation
M. A. Mortenson Company
Murphy Company
North Bros., Inc.
The Parsons Corporation
Raytheon Engineers & Constructors
S&B Engineers and Constructors Ltd.
Stone & Webster Engineering Corporation
TPA, Inc.
H. B. Zachry Company
Reforming Owner, Contractor, Supplier
Relationships:
A Project Delivery System
to Optimize Supplier Roles in EPC Projects
Prepared by
The Construction Industry Institute
Reforming Supplier Relationships Research Team
Research Summary 130-1
September 1998
 1998 Construction Industry Institute.
The University of Texas at Austin.
CII members may reproduce and distribute this work internally in any medium at
no cost to internal recipients.  CII members are permitted to revise and adapt this
work for the internal use provided an informational copy is furnished to CII.
Available to non-members by purchase; however, no copies may be made or
distributed and no modifications made without prior written permission from CII.
Contact CII at http://construction-institute.org/catalog.htm to purchase copies.
Volume discounts may be available.
All CII members, current students, and faculty at a college or university are eligible
to purchase CII products at member prices.  Faculty and students at a college or
university may reproduce and distribute this work without modification for
educational use.
Printed in the United States of America.
Contents
Chapter Page
Executive Summary  v
1. Introduction  1
2. Development of the Breakthrough Model  4
3. Measuring and Quantifying Its Effects  16
4. Implementation  21
5. Recommendations  27
6. Postscript  29
References  33
v
Executive Summary
By expanding its membership to include suppliers, CII recognizes that
suppliers of key engineered systems and components can and should play
a significant role in the pursuit of CII goals. CII, therefore, established the
Reforming Supplier Relationships Research Team to explore the potential
for  reforming  traditional  owner/contractor/supplier  relationships  in
engineer-procure-construct  (EPC)  projects  to  enhance  the  ability  of
suppliers to contribute more meaningfully to this process.
Believing  that  a  breakthrough  approach  would  be  required  to
facilitate such a reformation, this research team concluded that if the
role  of  suppliers  of  the  most  critical  components  and  systems  in  a
project is to be enhanced, then one must both enhance and prioritize
the  point  of  definitive  contact  with  those  suppliers:  the  procurement
process. A new project delivery system was envisioned that divides the
procurement  process  into  big  P    strategic  procurement  items,
including  complex  engineered  equipment  and  systems  essential  for
project  performance,  and  little  p    the  balance  of  items  to  be
procured;  and  then  reconfigures  the  traditional  EPC  model  into
Procurement, Engineering, procurement, and Construction, or PEpC.
In  traditional  EPC,  procurement  follows  engineering,  both
sequentially and in the fact that engineering specifies and defines the
items  to  be  procured.  In  PEpC,  the  most  strategic  and  project-critical
procurement transactions occur prior to detail engineering, and those
procured  items  then  influence  and  define  subsequent  detailed
engineering. Further, the core competencies of the supplier, which are
often  unique  and  beyond  those  possessed  by  either  the  owner  or
contractor, are provided directly into the project delivery system.
Utilizing  a  sophisticated  simulation  model  of  the  classic  EPC
process, the research team compared the impact of a PEpC approach to
project  execution  with  traditional  EPC.  In  both  theoretical  and  field
implementations,  the  results  indicated  that  PEpC  could  produce
savings  in  excess  of  10  percent  to  15  percent  of  the  time  and  four  to
eight percent of the cost of the traditional EPC process.
1
1
Introduction
A Challenging Mission
Membership  in  CII  traditionally  has  been  limited  to  the  principal
consumers  and  principal  providers  of  engineering  and  construction
services,  i.e.,  owners  and  contractors.  Recently,  CII  expanded  its
membership  categories  to  include  the  suppliers  of  major  materials,
equipment,  and  systems  that  are  incorporated  into  construction
projects.  This  membership  expansion  arose  from  the  recognition  that
suppliers  of  key  materials,  equipment,  and  systems  can  and  should
play  a  significant  role  in  pursuit  of  CIIs  mission  to  improve  the  cost,
schedule, quality, and safety of the construction industry.
With this new recognition of the supplier community, CII created
the Reforming Supplier Relationships Research Team and tasked it with
examining  the  relationships  and  roles  of  suppliers  in  traditional  EPC
construction.  More  specifically,  the  research  team  was  asked  to
explore  the  potential  for  reforming  the  traditional  owner-contractor-
supplier relationships in EPC projects in order to enhance the ability of
suppliers to contribute more meaningfully to the process.
The  research  team  recast  this  assignment  into  the  following
problem statement:
Strategic  procurement  items,  including  complex  engineered
equipment and systems essential for project performance, are
frequently designed, manufactured, and delivered by suppliers
who  are  outside  the  traditional  circle  of  cooperation
between owner and contractor. The expertise embedded in the
design of this equipment, as well as the expertise needed for its
successful  integration,  operation,  and  maintenance  is
frequently  lost  or  under  utilized.  The  resulting  inefficiencies
have  an  impact  on  the  time,  cost,  and  quality  of  engineering
and  construction  as  well  as  on  the  life  cycle  performance  of
constructed facilities.
2
After  considerable  discussion,  and  believing  that  a  meaningful
solution  could  be  found,  the  research  team  posed  the  following
hypothesis that would become the subject of its future efforts:
It  is  possible  to  systematically  reform  relationships  between
owner,  contractor,  and  supplier  so  that  suppliers  of  strategic
procurement items and/or systems can be included in the full
EPC process and thereby have a significant positive impact on
the  time,  cost,  and  quality  of  the  entire  engineering  and
construction process, as well as on the life cycle performance
of constructed facilities.
The hypothesis was based on the belief that substantial savings in
time and cost could be realized if a step change in traditional owner/
contractor/supplier relationships could be achieved in such a way as to
make it possible for suppliers to contribute effectively in every phase of
the  total  facility  life  cycle.  It  was  clearly  felt  that  owners,  design
contractors, and construction contractors would benefit from new and
dramatically  different  relationships  with  suppliers,  who  should  no
longer be silent partners in the EPC process.
An Innovative Methodology
Addressing  the  problem  statement  and  confirming  the  hypothesis
required  a  research  effort  that  extended  beyond  the  classic  steps  of
identifying  a  problem,  gathering  data,  examining  results,  and
recommending  change.  A  suitable  methodology  was,  therefore,
developed that included the following four key steps:
1. Initiating  an  extensive  search  for  innovation  within  and
beyond the boundaries of the industrial construction industry.
2. Defining  a  breakthrough  project  delivery  system,  which
would  make  it  possible  to  utilize  supplier  expertise  in  all
phases of the project life cycle.
3. Measuring  and  quantifying  the  effect  of  implementing  the
breakthrough in both theoretical and field implementations.
3
4. Developing  the  required  tools  to  facilitate  the  routine
implementation of the breakthrough throughout the industry.
The results of Steps 1 and 2 are covered in the following chapter.
The  measurement  process  is  discussed  in  Chapter  3;  and
implementation procedures are in discussed in Chapter 4.
4
2
Development of the Breakthrough Model
A Search for Innovation
The  research  team  set  out  to  identify  instances  or  trends  of
enhanced  supplier  involvement,  both  within  and  beyond  the
construction  industry.  A  literature  survey,  a  mail  questionnaire  of  CII
member companies, and a number of structured interviews by research
team  members  were  used  to  identify  and  study  instances  where
owners,  contractors,  or  suppliers  had  successfully  developed  or
employed innovative or atypical relationships within the EPC process.
Four principal conclusions flow from this effort:
1. There  is  both  need  and  precedent  for  the  development  of  a
step  change  to  the  EPC  process  that  brings  suppliers  of
strategic  components  and/or  systems  for  a  project  into  the
circle of cooperation between owner and contractor.
2. The  analysis  of  the  questionnaire  results  showed  that
suppliers  were,  in  numerous  cases,  being  used  in  an
expanded role with regard to status, time of involvement, and
expected role, but that business and commercial relationships
remained narrowly and traditionally defined.
3. The  interviews  conducted  by  research  team  members
confirmed  pockets  of  innovation  within  the  industry  and
presented  strong  anecdotal  evidence  of  reductions  in  time
and cost due to the early involvement of strategic suppliers.
4. The survey of associated industries showed that at least two
industries,  the  automotive  manufacturing  industry  and  the
micro-electronics  construction  industry,  had  improved
performance  by  expanding  the  role  played  by  suppliers  and
that  many  of  their  lessons  could  be  transferred  to  the
mainstream industrial construction sector.
5
Defining a Breakthrough Delivery System Model
The  research  team  was  convinced  that  a  step  change  to  the  EPC
process  that  would  bring  suppliers  of  strategic  items  and/or  systems
into  the  circle  of  cooperation  between  owners  and  contractors  was
both necessary and possible.
Discussion among the varied interests represented by the research
team membership led to a discussion during which the members came
to the following conclusion:
If  one  really  desires  to  enhance  the  role  of  suppliers  of  the
most  critical  components  and  systems  in  a  project,  then  one
must  both  enhance  and  prioritize  the  point  of  definitive
contact with those suppliers: the procurement process.
This  led  the  research  team  to  envision  a  project  delivery  system
that takes the big P for procurement in the EPC process and places it
before  the  E  for  engineering  so  that  the  technical  knowledge  and
expertise  of  major  suppliers  can  be  integrated  into  all  phases  of  the
project from the beginning, thus PEC.
In  recognition  of  this  change  and  the  fact  that  a  number  of  non-
strategic  procurement  items  would  continue  to  be  procured  in  the
traditional  way  (little  p),  the  research  team  designated  the  process
PEpC.
This, together with the need to accommodate a variety of interests
and applications, led to the following broad definition:
PEpC  (Procurement,  Engineering,  procurement,  and
Construction)  is  an  innovative  project  delivery  system  which
makes it possible to utilize key supplier expertise in all phases
of  the  project  life  cycle  by  developing  an  advance
procurement strategy and by actually reaching full commercial
and  contractual  agreement  with  suppliers  of  strategic
procurement  items  and/or  systems  prior  to  the  principal
project engineering activities.
6
Refining the Breakthrough
The  fundamental  and  essential  characteristic  of  PEpC  compared
with  classic  EPC  is  that  procurement  of  the  most  project-critical
components  is  accomplished  prior  to  all  but  the  most  preliminary
engineering efforts. (In this context, procurement means concluding a
full, complete, and binding contractual agreement between the buyer
and seller for one or more specified products and or services.)
In  traditional  EPC,  procurement  follows  engineering,  both
sequentially and in the fact that engineering specifies and defines the
items  to  be  procured.  In  PEpC,  the  most  strategic  and  project-critical
procurement transactions occur prior to detail engineering, and those
procured  items  then  influence  and  define  subsequent  detail
engineering.  More  importantly,  the  suppliers  of  such  project-critical
components  are  no  longer  passive  compliers  with  specifications
generated by engineering, but can now play an active role in defining
their own contribution to the engineering and design process, as well
as those of other related and downstream suppliers.
The  big  P  procurement  in  PEpC  should  not  be  confused  with
early  or  advanced  purchasing  strategies  frequently  utilized  in  EPC
projects to deal with long-lead items. In traditional EPC, early purchase
of long-lead items occurs principally, and often solely, to preserve the
scheduling  interests  of  the  project.  In  PEpC,  however,  early
procurements  are  concluded  with  the  principal  intent  of  bringing
selected  suppliers  of  project-critical  components  into  the  owner  and
contractor  circle  of  cooperation  so  that  suppliers  can  more
effectively  contribute  to  and  influence  downstream  engineering  and
other  front-end  activities  and  decisions,  i.e.,  to  deliver  supplier  core
competencies  directly  into  the  project  delivery  system  and  not
indirectly via the owner or contractor.
The  idea  of  utilizing  supplier  knowledge  and  expertise  in
developing project designs and specifications is certainly not new. Any
experienced  engineering  designer  or  specifier  knows  the  value  of
supplier  input,  just  as  any  supplier  representative  knows  the
importance of maintaining contact with engineering.
7
The  problem  traditionally  faced  by  engineering  specifiers  has
been generating a suitable specification or design that is sufficiently
generic  to  maintain  a  competitive  environment.  Specifiers  could
utilize  some  supplier  knowledge  and  expertise  in  generating  a
design or specification, but not too much  lest they inadvertently
create  the  dreaded  sole-source  specification.  Once  a  supplier  is
finally  selected,  it  is  often  too  late,  too  time-consuming,  or  too
costly to take full advantage of the suppliers expertise, and thus the
opportunity  to  incorporate  supplier-specific  refinements,  improve-
ments, or suggestions that could provide savings in time or cost, or
enhancements to quality is lost.
In  PEpC,  however,  there  is  no  impediment  to  the  flow  of
knowledge  and  expertise  since  the  commercial  relationship  of  the
supplier  and  purchaser  has  already  been  defined  as  the  result  of  a
conclusive procurement transaction (a supply contract, purchase order,
or  subcontract);  and  there  is  no  longer  a  need  to  maintain  a  generic
engineering  design  solely  for  the  sake  of  preserving  a  competitive
environment.
Procurement without Engineering?
How  does  one  purchase  the  most  important  systems  and
components in a particular project without an engineering design and
detailed  specifications?  PEpC  does  not  banish  engineering  to  the
hinterlands;  in  fact,  PEpC  actually  creates  new  and  challenging
opportunities  that  enhance  the  roles  of  both  the  engineering  and
procurement functions in the project delivery process.
In a PEpC approach, the engineering function, based on the most
preliminary and conceptual of designs for a project, would identify the
strategic and project-critical systems and components. Instead of then
producing  detailed  designs  and  design  specifications,  however,
engineering  would  define  the  desired characteristics  of  those  systems
and  components  in  terms  of  their  role  or  contribution  to  the  overall
project  objectives.  Detailed  engineering  designs  and  design
specifications  would  be  replaced  with  conceptual  designs,
8
performance specifications, or even broader supplier services concepts
as the basis for procurement transactions  creating opportunities for
suppliers  to  offer  components,  systems,  and  services  which  best
support  the  overall  process  or  project  objectives.  Instead  of  low-bid
compliance  with  a  detailed  design  specification  being  the  basis  for
procurement  awards,  PEpC  allows  broader  and  more  comprehensive
evaluation  criteria  that  ultimately  measure  the  total  value  of  a
suppliers offering, including the suppliers expertise and competencies
associated with its products and services.
PEpC also creates enhanced opportunities for suppliers to offer and
accept  broader  roles  in  the  project  delivery  process.  Depending  on
their  individual  capabilities  and  competencies,  suppliers  can  expand
their  roles  beyond  the  traditional  ship  the  specified  product  to
include  enhanced  design  responsibilities,  installation,  maintenance,
and even operation of their equipment in the completed facility.
Both  engineering  and  procurement  will  be  challenged  to  break
their  traditional  molds  and  generate  procurement  packages,  and
associated evaluation criteria, that create and maximize opportunities
for suppliers to offer and deliver greater value and a broader range of
responsibilities in the overall project delivery process.
The Great Debate
Two major questions arose among the research team members in
their efforts to precisely define their new creation which led to several
vigorous and highly spirited debates:
First, does PEpC require that the procuring entity have or establish
strategic  alliances  or  partnering  relationships  with  the  suppliers  of
strategic components and systems?
The  answer  is  no.  The  PEpC  model  requires  simply  that  the
procurement  of  certain  project-critical  and  strategic  components  be
accomplished  prior  to  detailed  engineering.  There  are  many  ways  to
9
initiate  and  conclude  a  procurement  transaction    from  the  most
hard-nosed,  low-bid,  sign-the-killer-contract  approach,  to  the  warm-
and-fuzzy, we-trust-you, you-trust-us relationships.
The essential requirement in PEpC is simply that the procurement
transaction  be  consummated,  including  all  of  its  commercial  and
contractual details, utilizing the means and methods most appropriate
under  the  circumstances,  while  preserving  the  competitive  technical
and  commercial  interests  of  the  purchaser.  Just  as  partnering  and
strategic alliances have been shown to be of benefit in some traditional
EPC  relationships,  so  too  they  may  also  be  of  value  in  initiating  and
concluding  the  procurement  transactions  under  PEpC.  They  are  not
essential, however.
In this context, the role and value of the competitive bid process in
both traditional EPC as well as in PEpC were also examined. Managers
responsible  for  the  fiscal  interests  of  a  project  are  often  concerned
when supposedly noncompetitive procurement practices are engaged.
How do we know we are getting the best price? they ask.
As  was  mentioned,  PEpC  does  not  require  the  abandonment  of
competitive  bidding  practices;  it  simply  suggests  that  the  basis  of  the
competition  should  be  on  a  broader  and  more  conceptual  basis
focusing  on  a  suppliers  ability  to  deliver  greater  value  to  the  project
rather than simply lower price.
Further,  our  infatuation  with  the  competitive  bid  process  may  be
overvalued. A low bid to a fully defined detail specification is simply
the competitive market value for what was specified, or for what was
perhaps  over-specified,  misspecified,  or  not  even  needed.  The
infamous $400 government hammer was the product of a competitive
bid  process.  The  traditional  competitive  process  based  on  detailed
specifications  assumes  that  the  specifier  knows  best  and  greatly
diminishes the opportunity for suppliers to contribute their knowledge,
expertise, and competencies in response to the purchasers true needs.
10
For  the  most  critical,  complex,  and  strategic  components  in  a
particular project, the purchasers interests will often be better served
by  exploring  alternative  methodologies  which  permit  the  developers
and  suppliers  of  those  components  to  assume  a  greater  role  in  the
design, specification, and selection of components consistent with the
purchasers needs, expectations, and fiscal restraints.
Second,  does  a  PEpC  approach  to  a  project  imply  that  the
procurement  of  the  most  project-critical  components,  since  it  is
accomplished prior to detailed engineering, must be accomplished by
owners rather than contractors?
Again, the answer is no. If an owner has the capability, resources,
and experience to undertake the procurement of strategic and project-
critical  items,  and  such  items  are  central  to  a  proprietary  owner
process or a branded end-product of the facility, then the owner should
more likely be responsible for the big P procurement. If, on the other
hand, an owner does not have the capability, resources, or experience
required,  or  the  strategic  and  project-critical  items  are  integral  to  a
broader  contractual  responsibility  assigned  to  an  engineering  or
construction contractor, then the contractor should execute the big P
procurement.
Defining the Benefits
Utilizing  a  sophisticated  simulation  model  of  the  classic  EPC
process,  the  research  team  was  able  to  document  and  measure  the
impact  of  a  PEpC  approach  to  project  execution  compared  with
traditional  EPC.  In  both  theoretical  and  field  implementations,  the
results  indicated  that  PEpC  could  produce  savings  in  excess  of  10
percent to 15 percent of the time and four to eight percent of the cost of
the traditional EPC process.
11
In addition to the measured benefits of PEpC, however, there are a
number  of  other  benefits  that  may  flow  from  the  implementation  of
PEpC  and  the  enhanced  supplier  contributions  it  envisions.  These
include:
 Improved quality of the detail design.
 Improved system and facility performance.
 Earlier deployment of new technologies.
 More equitable allocation of risk.
 Improved utilization of supplier core competencies.
 Reduction or elimination of redundant work processes.
 Diminished need for owners or contractors to maintain non-
core competencies that are more effectively maintained and
delivered by suppliers.
Utilizing Core Competencies
As  an  essential  ingredient  in  the  discussion  of  optimizing  the
relationships  among  owners,  contractors  and  suppliers,  the  research
team examined the issue of core competencies. In doing so, it utilized
the  CII  publication,  Owner/Contractor  Work  Structure:  A  Process
Approach  (Research  Summary  111-1).  That  publication  identifies  30
competencies required for the successful execution of an EPC project.
A  few  are  identified  as  essential  or  core  competencies  of  owners,
others  of  contractors.  The  majority  of  the  listed  competencies,
however,  were  in  the  middle-ground,  subject  to  what  is  called
structural  alignment  on  a  project-by-project  basis  according  to  the
unique demands of each project. Figure 1 illustrates the assignment of
a  few  competencies  to  either  the  owner  or  contractor,  and  the
unaligned balance in the middle.
12
The work of CIIs Owner/Contractor Work Structure Research Team
focused  only  on  two  entities,  owner  and  contractor.  The  Reforming
Supplier  Relationships  Research  Team  attempted  to  expand  that
discussion  of  competencies  to  include  a  third  entity    suppliers.  If
suppliers of strategic and project-critical items are to be invited into the
circle  of  cooperation  between  owner  and  contractor,  what
competencies do they offer? More importantly, what competencies do
they possess which might supplement or even displace competencies
currently  maintained  by  owners  and  contractors?  Finally,  what  core
competencies should a supplier possess as a minimum requirement for
admission into the circle of cooperation?
Ultimately,  the  30  original  competencies  did  not  adequately
handle the additional considerations that resulted when suppliers were
added  to  the  discussion.  The  research  team  identified  six  additional
competencies and then attempted to redistribute all 36 competencies
among  the  owner,  contractor,  and  supplier  entities.  The  results  were
interesting,  but  inconclusive,  indicating  that  to  varying  degrees,  each
Figure 1. Owner/Contractor Distribution of Competencies
Contractor Structural Alignment Owner
Construction Lessons Learned
Maint. & Operability
Prelim. Design/Scope
Process/Concept.Design
Procurement
Project Controls
Project Management
Planning &  Scheduling
Risk Management
Safety
Team Building
Technical Expertise
TQM
Alliances/Partnering
Benchmarking/Metrics
Commissioning/Startup/
Perf. Testing
Conceptual Cost Est.
Constructability
Construction Mgmt.
Convert Research to
Project/Scale Up
Definitive Cost Est.
Detail Design
Environmental/Permits
Field Quality Control
Legal/Contract Admin.
Business
Dev.
Financial
Approval
PM
Oversight
Setting
Project
Goals,
Objectives
& Priorities
13
entity  could  or  should  possess  some  element  of  nearly  each  of  the
competencies. The competency commissioning and startup is a good
example:  the  project  facility  will  be  operated  by  the  owner  and,
therefore, the owner should have a significant role; so too should the
engineering  and  construction  contractors  who  designed  and  built  it;
and then consider the suppliers of the major system components who,
in  many  cases,  will  actually  provide  startup  technicians  for  their
systems and equipment.
In an effort to resolve this dilemma, the research team attempted to
distribute the competencies based on which entity should take the lead
role in delivering the competency to the project. Here too, the results
were again inconclusive and prompted the conclusion that an abstract
attempt  to  permanently  assign  competency  roles  was  not  useful;
leading to assignments that were ambiguous, misleading, or disputed.
Ultimately,  the  research  team  concluded  that  assignments  of
competency  roles  should  be  based  on  the  particular  needs  of  a
particular  project,  and  the  actual  competencies  of  the  actual  project
participants.
Since  many  projects  involve  a  single  owner,  a  single  contractor,
and numerous suppliers, the global assignment of competencies at the
project  level  is  useful  in  establishing  a  general  allocation  of
responsibilities  among  the  owner,  the  contractor,  and  the  supplier
community.  Specific  allocations  of  competencies,  however,  can  be
more  meaningfully  achieved  in  a  system,  sub-system,  or  component
context  by  focusing  on  the  available  competencies  of  the  particular
supplier(s) involved.
Figure  2a  provides  a  useful  means  of  depicting  a  three-way
distribution  of  the  various  competencies  utilizing  a  triangular
allocation.  Competencies  possessed  or  led  exclusively  by  one  of  the
entities  are  in  the  respective  corners,  while  competencies  shared
between  two  entities  run  along  one  of  the  sides,  and  those
14
Maintenance & Operability
Performance Guarantee *
Planning & Scheduling
Preliminary Design/Scope
Price a Bid & Build to It *
Process/Conceptual Design
Procurement
Project Controls
Project Management
Project Management Oversight
Proper Equipment Sizing *
Risk Management
Safety
Setting Project Goals
Supplier Engineering *
Team Building
Technical Expertise
Total Quality Management
Figure 2a. PEpC Competencies and
Owner, Contractor, Supplier Competency Distribution
Alliance/Partnering
Benchmarking/Metrics
Business Development
Commissioning/Startup/Performance Testing
Conceptual Cost Estimating
Constructability
Construction
Construction Management
Convert Research to Project/Scale-Up
Defining Facility Requirements *
Definitive Cost Estimating
Detail Design
Equipment Manufacturing *
Environmental/Permits
Field Quality Control
Financial Approval
Legal/Contract Administration
Lessons Learned
Supplier
Competencies
Contractor
Competencies
Owner
Competencies
Supplier Contractor
Owner
Supplier/
Contractor Shared
Competencies
Owner/Supplier
Shared
Competencies
Owner/Contractor
Shared
Competencies
Owner/
Contractor/
Supplier Shared
Competencies
* Competencies added by Research Team
competencies  properly  shared  by  all  three  entities  are  in  the  middle.
Further, the magnitude of a particular competency, or the magnitude of
the  role  of  an  entity  (supplier,  contractor,  or  owner)  delivering  or
leading one or more competencies can expand or contract according
15
to the particular characteristics of a project and the entitys capabilities.
In an extreme implementation of PEpC, for example, where a project is
dominated  by  a  few  critical  components  that  will  be  designed,
fabricated  and  installed  by  a  supplier,  the  Supplier  sub-triangle  in
Figure 2b could grow, becoming more dominant in the project delivery
system,  and  perhaps  displacing,  to  an  appropriate  degree,
competencies traditionally delivered by the owner or contractor.
Figure 2b. Potential Expansion of Competency Delivery Role
Contractor
Competencies
Owner
Competencies
Supplier
Competencies
16
3
Measuring and Quantifying Its Effects
Measuring the Unimplemented
Although the preliminary research indicated that the PEpC concept
offered the potential for significant reductions in project time and cost
compared  with  the  traditional  EPC  process,  the  research  team
recognized the need to validate these expectations by measuring and
quantifying the effects of applying the model. Because PEpC, however,
by definition involved new and fundamental changes to the traditional
EPC  process,  the  difficulty  of  measuring  the  unimplemented  was
encountered.
In order to document the expected benefits of PEpC, the research
team developed two different measurement processes, one theoretical
and  one  practical,  that  would  permit  the  measurement  of  both  the
expected  ultimate  potential  of  PEpC  as  well  as  provide  practical
validation of those expectations based on actual project experiences.
The EPC Model
As  a  measurement  tool,  the  research  team  adopted  a  baseline
model  of  the  classic  EPC  process  developed  by  the  CII  Information
Management  Impacts  Research  Team  (See  CII  Implementation
Resource  125-2,  Determining  the  Impact  of  Process  Change  on  the
EPC Process). That model consists of 164 activities, 16 milestones, and
12  major  phases  commonly  found  in  conventional  EPC  projects.  The
model  includes  a  logic  diagram  that  defines  the  sequence  and  logic
relationships  between  and  among  the  164  activities,  and  includes
detailed data defining the associated cost and duration of each activity.
The  model  can  be  manipulated  to  modify  any  of  the  activities,
sequences,  relationships,  costs,  and  durations.  Utilizing  sophisticated
computer  modeling  software,  the  research  team  was  able  to  measure
and  document  the  cost  and  schedule  impact  of  changes  to  the
traditional EPC process.
17
Based  on  the  methodology  and  definitions  established  by
Information  Management  Impacts  Research  Team,  the  terms  cost  and
time  refer  to  the  total  costs  and  total  durations  of  the  engineering,
procurement,  and  construction  processes,  but  exclude  the  cost  of
procured materials and equipment.
Imagining the Optimum
Selected  research  team  members  were  asked  to  envision  a  full-
scale  implementation  of  PEpC  in  a  particular  project  from  their
particular  industry  or  background.  Each  member  then  individually
reconfigured the baseline EPC model to reflect the implementation of
the  PEpC  concept  in  their  particular  project  environment.  This  was
accomplished by examining each of the 164 activities, reordering them
as appropriate, and adjusting the expected costs and durations of each
activity.  Each  members  modified  model  was  then  run  through  the
simulation program to determine the impact on total project time and
cost.
The results of 10 such theoretical PEpC implementations indicated
that  savings  ranging  from  5.6  percent  to  19.6  percent  in  project
duration and from 0.3 percent to 17.8 percent in project cost could be
expected from a full-scale implementation of the PEpC concept.
Comparison with the Real World
Next,  the  research  team  sought  to  test  these  theoretical
implementation  results  against  actual  field  implementations  of  PEpC.
Although no full-scale implementations of PEpC were found (or were
even  thought  to  exist),  four  projects  were  identified  where  partial
PEpC-like characteristics were implemented. These included:
 A new paper mill for a major paper company.
 A  chemical  reactor  train  project  for  a  major  chemical
company.
 The  expansion  of  a  wood  chip  screening  plant  for  another
major paper company.
18
 A  new  bottling  line  installation  for  a  major  brewing
company.
In each of the four cases, one or more suppliers of the most critical
project components were engaged early in the project and generally in
conjunction with or just following preliminary conceptual engineering.
In all cases, the suppliers were selected based on expanded selection
criteria including their expertise with the components to be installed,
their  willingness  and  ability  to  accept  broader  contractual
responsibilities,  and  their  ability  to  contribute  to  overall  project
objectives rather than low-bid to a detailed specification. In each case
the  selected  suppliers  participated  in  the  detail  engineering  phase  of
the  project,  contributing  cost  and  time-saving  expertise,  information,
and suggestions.
The  benefits  of  the  application  of  PEpC-like  strategies  in  the  four
projects  studied  indicate  cost  savings  from  zero  to  6.6  percent,  but
more significantly, duration savings from 5.6 percent to 18.6 percent.
Upon  detailed  analysis,  the  difference  in  the  ranges  of  savings,
particularly the time savings, could be attributed to the aggressiveness
of the application of PEpC-like innovations.
Measurement Conclusions
Figure  3  compares  the  cumulative  reductions  in  schedule
durations achieved in the theoretical implementations of PEpC against
the actual savings achieved in the PEpC-like project applications; with
both  compared  to  the  baseline  of  the  EPC  model.  Three  conclusions
are noteworthy:
1. The savings achieved in the four field implementations have
significant  correlations  to  the  aggressiveness  of  the
application of PEpC-like concepts.
2. The savings achieved in the field implementations are within
or exceed the savings range contemplated in the theoretical,
full-scale PEpC implementations.
1
9
Figure 3. Range of Time Savings from Theoretical Scenarios Compared to Case Studies
1 - Preliminary Feasibility
2 - Team Selection
3 - Preliminary Design, Est., & Scope
4 - Estimate, Schedule, & Review
5 - Procure Std. & Spec. Equip.
6 - Procure Fab. & Bulk Materials
7 - Detail Design
8 - Work Packages
9 - Preliminary Construction
10 - Field Construction
11 - Startup
12 - Documentation
5 0 5 10 15 20
Case Study 1
Case Study 2
Case Study 3
Case Study 4
Envelope of Savings for
Theoretical Implementations
20
3. In  both  the  theoretical  and  field  implementations,  negative
savings, i.e., prolonged activity durations, are experienced in
the  first  three  or  four  major  phases  of  a  project.  These  are
then  recovered  and  exceeded  in  a  positive  fashion  in  the
remaining  project  phases.  This  is  logically  consistent  with
both the envisioned PEpC concept as well as the frequently
quoted  CII  tenant  that  the  early  application  of  proven
beneficial  techniques  in  a  project  cycle,  even  though
momentarily  time-consuming,  reap  desirable  downstream
rewards.
21
4
Implementation
The Challenge to Change
Little is achieved by simply identifying and defining a new process.
Results come from implementing change and achieving the anticipated
benefits. PEpC could be superficially dismissed with a, We already do
that.  PEpC  as  envisioned  and  documented  by  the  research  team,
however, is a fundamentally different or breakthrough project delivery
system that, by definition, is not in current routine use. Thus leadership
and  a  firm  commitment  to  explore  innovative  and  promising
methodologies  will  be  needed  to  sponsor  a  PEpC  implementation,  to
overcome the expected barriers, and to learn the important lessons that
can only come from real experience.
An Implementation Program
The  PEpC  concept  is  an  innovative  project  delivery  system  that
modifies and reorders the sequence of several critical project planning
and  execution  steps  of  the  classic  EPC  process.  For  this  reason,  the
implementation of PEpC must begin with and be incorporated into the
earliest  pre-project  planning  processes  of  the  project  life  cycle.
Figure  4  illustrates  the  five  elements  of  the  recommended  PEpC
implementation  process  and  how  they  relate  to  the  traditional  pre-
project planning process.
Implementation Steps
Familiarization and Awareness. Because PEpC really is a new and
different project delivery system, it will be necessary to ensure that all
involved  parties    owners,  contractors,  suppliers  and,  particularly,
members of the project team  are aware of and understand the PEpC
concept.  They  must  be  informed  and  understand  how  it  changes  the
EPC  process,  re-allocates  risks,  and  re-defines  required  core
competencies.
22
PEpC  Strategy  Development.  A  common  product  of  the  pre-
project planning process is the work breakdown structure. For effective
PEpC implementation, this breakdown should identify all major project
components and systems, which will make it possible to then:
 identify  the  strategic  procurement  items  and/or  systems
critical to project success.
 identify members of the initial project team who will lead in
the selection and procurement of each strategic procurement
item and/or system.
 develop  a  detailed  procurement  and  contracting  strategy
suited to each strategic procurement item and/or system.
Figure 4. PEpC Implementation Incorporated into Traditional Pre-
Project Planning Phase
 Familiarization and
Awareness
 PEpC Strategy
Development
 PEpC Execution Plan
 PEpC Supplier
Selection
 PEpC Commitment
Business Plan
Product Technical Plan Facility Scope Plan
Project Execution Plan
Contract Strategy
PEpC Implementation Steps
23
 identify  possible  suppliers  with  the  core  competencies
required  by  the  unique  nature  of  the  project  and  each
strategic procurement item and/or system.
PEpC Execution Plan. The execution plan builds on the previously
developed strategy and provides the guidelines and assurances needed
to contain risk and proceed with the process. The following steps are
required:
 Obtain  agreement  and  commitment  to  the  PEpC  strategy
from all project stakeholders.
 Establish  target  cost  and  time  baselines  for  each  of  the
strategic procurement items and/or systems.
 Define the commercial and contractual terms to be used and
define greatest total value criteria for supplier selection.
PEpC Supplier Selection and Award. Supplier selection and award
follows on the development of the strategy and the execution plan. The
following steps are required:
 Formulate  and  issue  requests  for  proposals  from  identified
suppliers  in  a  manner  that  invites  and  encourages  suppliers
to offer products and services that provide the greatest total
value  to  the  project  and  maximize  the  utilization  of  the
suppliers core competencies.
 Review proposals relative to the established commercial and
contractual  terms  and  evaluation  criteria,  and  interview
potential suppliers.
 Discuss  and  agree  on  core  competencies  and  ensure  that
roles and responsibilities are defined.
 Refine  and  finalize  appropriate  contracting  strategies,  and
select and engage strategic suppliers.
24
Project  Team  Integration.  An  effective  PEpC  implementation
requires  that  owner,  contractor,  and  supplier  organizations  must  be
integrated into a single project team. The organizational considerations
needed for a successful implementation will require:
 a clear definition of roles and responsibilities.
 a  strong  focus  on  team  building  and  acceptance  of  the  fact
that  firm  functional  boundaries  are  less  important  than
project team requirements.
 addressing  and  managing  a  change,  together  with  its
attendant fear and uncertainty.
Selecting the Big P Candidates
A pivotal task in implementing PEpC is identifying the strategic or
project-critical  components  or  systems  that  should  be  procured  in
advance of principal engineering activities. The characteristics of these
components  and/or  systems  would  include  one  or  more  of  the
following:
1. System performance depends on a technology that is a core
competency of the supplier, or is unique or fast-changing.
2. System  performance  characteristics  vary  significantly  from
supplier to supplier.
3. Delivery  configurations  vary  substantially,  and  there  is
potential for change in configuration.
4. The  system  and  its  associated  components  are  highly
engineered and closely integrated.
5. The  system  or  process  is  complex  and  there  is  substantial
potential for simplification or standardization.
25
6. Knowledge  of  system  engineering,  configuration,  and
integration is a supplier core competency.
7. Design  interfaces  between  the  component  or  system  and
other  portions  of  the  project  are  complex,  variable,  and
subject to interpretation.
8. System or component sizing, configuration, and selection are
critical to the principal engineering activities.
9. System  or  component  design  can  influence  principal
engineering activities.
10. Lead  times  for  system  or  component  selection,  design,  and
delivery are long with strong dependencies in the overall project
schedule.
27
5
Recommendations
In concluding its work, the research team offers the following three
recommendations.
1. Based on the positive results documented in its study of the
PEpC concept, the research team recommends that full-scale
implementations of PEpC be undertaken:
 in  accordance  with  the  implementation  guidelines
provided; and
 in  instances  where  suitable  champions  of  innovation
can  be  relied  upon  to  find  opportunities  rather  than
barriers,  to  maximize  the  benefits  to  be  derived  from
this promising new approach to project execution.
2. The  PEpC  concept  as  presented  should  be  the  subject  of
further measurement, study, and refinement through industry
implementations.
3. CII  and  its  member  companies  should  continue  to  explore,
expand,  and  develop  its  focus  on  the  supplier  community
and on enhanced supplier involvement in the capital project
delivery process.
29
6
Postscript
Is PEpC a Breakthrough?
One  might  conclude  that  the  suggested  reordering  of  the  core
elements  of  the  traditional  EPC  project  delivery  system  would
automatically  qualify  for  breakthrough  status.  In  some  preliminary
presentations  of  the  PEpC  concept,  however,  the  research  team
received a number of we already do that reactions. So, at the risk of
redundancy, let us review the essential elements of PEpC:
The research concludes that to implement a PEpC project delivery
system one must:
 identify the project-critical components in a project prior to
all but the most conceptual project engineering; and then
 consummate commercially-complete transactions to engage
the  most  project-favorable  suppliers  of  those  components
(according  to  project-specific  selection  criteria);  for  the
purpose of
 facilitating the delivery of those suppliers core competencies
into  the  project  delivery  process,  including  the  suppliers
ability to accept broader roles in project execution and risk
management; and thereby
 influence,  define,  and  benefit  the  overall  project  execution
strategy and the detail engineering effort; and
 that  this  process  should  be  undertaken  strategically,
deliberately, and consistently.
30
The research team is hesitant to claim that a PEpC approach to a
project  has  never  been  utilized.  Many  of  the  done  that  examples,
however, were actually instances of what the research team identified
and documented as PEpC-like applications. In fact, the research team
utilized  a  number  of  these  PEpC-like  project  examples  in  its
measurement and validation process. These were, indeed, innovative
variations to the traditional project delivery process and were, in most
cases,  successful  and  beneficial  in  terms  of  their  cost  and  schedule
impact;  and  the  research  team  infers  no  diminishment  of  the
innovation and value of these efforts.
The  research  team,  however,  found  no  situations  where  a  PEpC
approach as defined above was utilized strategically, deliberately, and
consistently  (with  the  possible  exception  of  the  Nucor  approach
documented in CII Research Summary 112-1, 2% Engineering  Can It
Work  for  You?).  In  many  cases  where  one  or  more  key  suppliers  or
components were selected early, often as a means of providing some
anchor  points  for  detailed  engineering,  or  to  select  a  particular
proprietary supplier technology, the definitive commercial transactions
were concluded later in the process. In other cases, supplier selection
arose  from  the  use  or  re-use  of  new  or  pre-existing  supplier
relationships. Finally, some of the examples of early supplier selection,
although  beneficial  to  the  detailed  engineering  effort,  were  really
initiated out of schedule considerations.
Again,  all  of  the  PEpC-like  applications  were  valuable  and
innovative  variations  of  EPC.  The  research  teams  concept  of  PEpC,
however, suggests taking these innovations even further, perhaps to the
point  where  the  reaction  is  We  cant  do  that  as  opposed  to  We
already do that, and to the point that a PEpC concept is commonplace
rather than anecdotal.
31
So, is PEpC a breakthrough? The research team believes that it is.
But that decision is ultimately left to the reader and the readers use of
this  research  effort.  PEpC  is  only  a  breakthrough  if  it  is  applied  and
implemented  as  a  breakthrough  and  prompts  the  practitioners  of
traditional  EPC  to  dramatically  change  the  way  suppliers  of  the  most
project-critical  components  are  integrated  into  the  project  delivery
process.
The  research  team  urges  the  industry  to  stretch  its  view  of  the
supplier community, to find ways to maximize suppliers contributions
to traditional EPC projects, and at the same time, to stretch the supplier
community to become more participative in the design and execution
of EPC-type projects. The research team believes that a PEpC approach
to  project  delivery  is  an  effective  tool  in  achieving  these  objectives,
and  believes  that  its  research  documents  the  benefits  such  a  process
delivers.
33
References
Sullivan, G. R., Yupari, M. A., and Anderson, S. D., Owner/Contractor
Work  Structure:  A  Process  Approach,  A  Report  to  the
Construction  Industry  Institute,  Research  Report    111-11, Austin,
TX, 1997.
Vorster,  M.  C.,  PEpC:  A  Breakthrough  Project  Delivery  Sytem  That
Improves  Performance  by  Reforming  Owner-Contractor-Supplier
Relationships,  A  Report  to  the  Construction  Industry  Institute,
Research Report 130-11, Austin, TX, 1998.
Reforming Supplier Relationships Research Team
Robert J. Anderson, Hoechst Celanese
Gary Beachman, Weyerhaeuser Company
Donald A. Ben, Anheuser-Busch Companies, Inc.
John G. Berra, H. B. Zachry Co.
Larry Cessnun, Hilti Corp.
Robert E. Fielitz, DuPont
Jamie Fowlkes, Rohm and Haas
John E. Futcher, Bechtel Corp.
Philip G. Luzier, Champion International
Frank B. Lynott, Honeywell, Inc.
Mark A. Meek, QuikWater
* Edward M. Ruane, J. A. Jones Construction Co.
James A. Scotti, Brown & Root, Inc.
James E. Steenbergen, Union Carbide Corporation, Chairman
Michael C. Vorster, Virginia Tech
* Principal Author
Not printed with state funds
The Construction Industry Institute
The University of Texas at Austin
3208 Red River, Suite 300
Austin, Texas 78705-2650
(512) 471-4319
FAX (512) 499-8101
Bureau of Engineering Research
The University of Texas at Austin