Electric Service Handbook: June 2014
Electric Service Handbook: June 2014
Electric
Service
Handbook
TABLE OF CONTENTS
Table of Contents
Preface
What this handbook contains . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PSEs service availability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Glossary of terms used in this handbook . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Codes, permits, and inspections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Electrical service equipment inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Reconnecting existing electric service after repair or replacement . . . . . . . . . . . . . . . . . . . . . . . . .
vii
vii
vii
vii
viii
viii
Scheduling/Timelines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . viii
Underground or overhead service? . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . viii
Which type of electrical system is available in your area? . . . . . . . . . . . . . . . . . . . . . . . . . viii
Underground service . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ix
Overhead service . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ix
Questions or assistance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ix
Other electric service information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
x
How to contact Puget Sound Energy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
xi
...................................................................
1
1
1
2
2
2
3
3
3
3
3
3
4
ii
TABLE OF CONTENTS
Transformer locations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Outbuildings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Service line installation responsibilities for outbuildings . . . . . . . . . . . . . . . . . . . . . . . . . .
Cost for service . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
9
9
10
10
11
12
12
12
12
12
13
13
14
15
16
16
16
19
19
19
20
20
20
21
21
21
23
24
Clearance requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Service line ground clearance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Minimum clearances from structures, building openings, and gas meters . . . . . . . . . . . . .
Intermediate service pole . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Service mast . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Service mast requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Height requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Additional mast supports (guy or brace) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Screw-in service knobs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Service entrance equipment installation requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
24
24
25
26
26
26
26
29
29
29
TABLE OF CONTENTS
Manufactured homes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Meter base/socket installation requirements for manufactured homes . . . . . . . . . . . . . . . .
Customer-owned meter pole . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Meter pole requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Installation requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
30
30
30
30
30
33
Inspection/Coordination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
33
Site preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
33
Customer-provided trench . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Trench width . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Trench excavating requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Trench and backfill requirements for primary electric line extension trenches (no gas) . .
Trench and backfill requirements for primary electric line extension trenches (with gas) .
Vaults . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Vault excavation procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Vault location and access . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Vault backfill material . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Continuous conduit systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
34
34
35
35
36
36
36
38
38
39
Customer-supplied conduits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
39
39
41
Responsibilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Puget Sound Energy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Customer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Meter bases/sockets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
General requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Meter base/socket location . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Grounding requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Clearance requirements for meter installations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
41
41
41
41
41
42
42
42
200 A services . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Single-family residential . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Underground . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Overhead . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Outbuildings (overhead or underground service) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
400 A services . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Underground . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Overhead . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Outbuildings (overhead or underground service) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
400 A current transformer (CT) services . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
44
44
44
44
44
46
46
47
47
48
49
iii
iv
TABLE OF CONTENTS
51
Definition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
51
51
Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
52
52
52
52
52
53
54
56
56
56
56
57
59
Modified services . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
59
Glossary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
61
List of Tables
Table 1
Table 2
Table 3
Table 4
Table 5
Table 6
Table 7
Table 8
x
3
3
4
5
9
49
60
TABLE OF CONTENTS
List of Figures
Figure 1
Figure 2
Figure 3
Figure 4
Figure 5
Figure 6
Figure 7
Figure 8
Figure 9
Figure 10
Figure 11
Figure 12
Figure 13
Figure 14
Figure 15
Figure 16
Figure 17
Figure 18
Figure 19
Figure 20
Figure 21
Figure 22
Figure 23
Figure 24
Figure 25
Figure 26
Figure 27
Figure 28
Figure 29
Figure 30
Figure 31
Figure 32
Figure 33
Figure 34
Figure 35
Underground facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Overhead facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Clearances for transformers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Clearances for transformers from structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Minimum clearances from oil-filled equipment to LP, hazardous liquid, or fuel tanks .
Minimum clearances from LP storage tanks to sources of ignition . . . . . . . . . . . . . . . .
Typical underground service from overhead power facilities . . . . . . . . . . . . . . . . . . . . .
Example of continuous conduit in underground electric service . . . . . . . . . . . . . . . . . .
Example of discontinuous conduit in underground electric service . . . . . . . . . . . . . . . .
Two types of meter bases/sockets for permanent underground service . . . . . . . . . . . . .
401800 A service entrance equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Permanent underground service for manufactured homes, 0200 A . . . . . . . . . . . . . . .
Remote metering for underground residential services . . . . . . . . . . . . . . . . . . . . . . . . .
Typical overhead service installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Minimum overhead service line vertical clearances from ground level . . . . . . . . . . . . .
Minimum clearances over other structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Intermediate service pole location . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Unguyed service masts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Guyed service masts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Permanent overhead meter pole installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Typical joint utility trench with primary voltage cable on your private property . . . . . .
Padmount transformer vault excavation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Aboveground junction box vault excavation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Location of customer conduit in PSE vaults . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Meter base/socket minimum clearances . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Recessed meter installation clearances . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Residential meter socket wiring diagrams . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Typical arrangement of service conductors for underground class 320
meter base/socket . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Typical arrangement of service conductors for overhead class 320 meter base/socket .
Instrument-rated (CT) meter bases/sockets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Single-phase CT mounting base . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Trenching requirements for power stubout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Temporary underground service installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Minimum clearance requirements upon installation . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Temporary overhead service installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Back pocket
Joint Utility Mainline Trench Excavation Requirements handout
Electric Underground Service Installation Requirements handout
ELECTRIC SERVICE HANDBOOK/SINGLEFAMILY RESIDENTIAL PROJECTS
ix
ix
6
7
8
9
11
14
15
17
18
20
21
24
25
25
26
27
28
31
34
37
37
38
43
43
45
46
47
48
49
53
55
57
58
vi
TABLE OF CONTENTS
PREFACE
vii
Preface
This handbook is your guide to Puget Sound Energys (PSE) requirements for new,
altered/modified, or temporary electric service for permanent single-family residential
structures. We have also included additional requirements for electric service to
outbuildings (barns, shops, pump houses, garages, etc.).
General boundaries for PSEs gas and electric service area are available on
PSE.com\customerconstruction. A Customer Construction Services (CCS)
Representative can help you to determine the closest available service line and can
provide you with cost information for establishing new service.
Glossary of terms used in this handbook
For your convenience, glossary words appear in bold italics throughout the text the first
time they appear (e.g., meter pole).
viii
PREFACE
Once your service equipment is installed, the state of Washington, or the city with
jurisdiction over your area, requires that your installation pass an electrical inspection
before PSE can energize your system.
NOTE: It is your responsibility to request an electrical inspection.
Electrical inspections for most areas in the PSE service territory are done by the
Washington State Department of Labor and Industries. However, electrical inspections
are performed by city personnel in several jurisdictions. Please consult
PSE.com\PermitsandInspections for a list of the cities and current contact information.
Scheduling/Timelines
The time needed for engineering, scheduling, and construction of the work will vary
depending upon the complexity of the job, possible right-of-way permits, easements, and
the volume of work requested by PSE customers. Contact your CCS Representative at
1-888-321-7779 for current construction scheduling.
You can determine if PSEs system is underground or overhead by checking for our
facilities along your road. If the power system is underground, youll see facilities like
those in Figure 1. If the power system is overhead, a series of poles similar to Figure 2
will be visible.
Use Table 1 to help you determine which type of electrical service can be provided. For
help determining which type of system is in your area, call your CCS Representative at
1-888-321-7779. If none of the items in Figures 1 or 2 exist in your area, or if you have
questions, call 1-888-321-7779 and a CCS Representative will be glad to assist you.
PREFACE
ix
Underground service
If your area is served underground, one or more underground facilities should be visible
(see Figure 1). Please request a permanent underground service (Chapter 2).
Detail
STUBOUT
HANDHOLE
PEDESTAL
PADMOUNT TRANSFORMER
If the power system in your area is overhead, poles should be visible (see Figure 2).
Please request a permanent overhead service (Chapter 3).
Transformer
Pole
If none of the items in Figures 1 or 2 exist in your area, or if you have questions, call
1-888-321-7779 and a CCS Representative will be glad to assist you.
PREFACE
And if . . .
Then your
service line
will be . . .
Underground
Underground
Overhead
Underground
Overhead
Overhead or
Underground
NOTE: If your situation does not fit the criteria presented, please contact your
CCS Representative.
PREFACE
Overview:
New Permanent and Temporary Electric Service Hookup
to Existing PSE Power Facilities for SingleFamily Residential Projects
This information applies only if PSE has existing power facilities in your area.
If electric power is not readily available, please contact
CUSTOMER CONSTRUCTION SERVICES
1-888-321-7779 or PSE.com/CustomerConstruction
Customer Responsibilities:
H Determine if you need overhead or underground service.
H Call PSE to set up an account and submit an order. Allow adequate time for possible
engineering, right-of-way permits, and easement review.
H Obtain an electrical work permit.
H If temporary service, install temporary service facility and meter base.
H If permanent service, determine the service size amp rating you want (200, 320, or 400 A).
H Determine an approved permanent meter location.
H Ensure that existing underground utilities are located before you dig. Call 811 two business
days prior to digging for a free service that will mark the location of underground lines.
H Prepare job site by providing a clear path/trench for your service line for proper vault entrance
requirements per PSE standards.
H Obtain an approved electrical inspection.
H After the electrical inspection has been completed and approved, request PSE to install and
energize your system.
Puget Sound Energys Responsibilities:
H Connect temporary service.
H Determine if engineering is required.
H Install your overhead or underground permanent service line conductors.
H Install your meter and energize your system.
Scheduling/Time Frame:
H If engineering is not required, services are typically installed and energized 3 to 5 days after you
have passed your inspection. Engineering, right-of-way permits, etc., can extend time frames
an estimated 2 to 4 weeks.
Permanent and Temporary Service Charge:
H Charges vary due to the type of service you request and the type of system we have in your
area. Contact your Customer Construction Services Representative for current rate information.
xi
xii
PREFACE
Chapter 1
Steps to a Successful Permanent Electric Service
Installation for Single-Family Residences
Definitions
as a single-family residence.
Customer
CHAPTER 1
You may establish your billing account when you are ready to initiate your temporary
service order, order your permanent service, or after the state electrical inspection is
complete and your trench is ready (if applicable).
To establish an account with PSE, call CCS at 1-888-321-7779. The CCS Representative
will ask for your billing information and the address for new service. (New addresses are
obtained from the U.S. Postal Service or the County Addressing Department.)
To order a new service, submit an Electric Service Application Single-Family Residential
100E to your CCS Representative. All forms can be downloaded from
PSE.com\customerconstruction.
Will your project need engineering?
A CCS Representative will ask you the following questions to help determine how your
project is handled:
H What kind of residential building is this service for (home, barn, shop, etc.)?
H What is the buildings square footage?
H What kind of electrical or gas appliances will you have (furnace, heat pump, air
conditioning, water heater, etc.)?
H What size service panel will you be installing?
H When will you be ready for service?
H Do you need underground or overhead service?
H Is the PSE utility connection point adjacent to your property or across the street?
NOTE: If a transformer or electrical service stubout is located on your property, your
CHAPTER 1
Voltage
Single-phase
120/240 V, 3-wire *
Three-phase
120/208 V, 4-wire
277/480 V, 4-wire
*Available for loads to a maximum demand of 100 kW. Larger loads may
be served, if determined feasible by a PSE engineer. All motors must be
rated 7-1/2 HP or less.
Service sizes
PSE offers several service sizes for single-family residential structures and for
outbuildings. The service size you need depends on both the size of your home and the
power requirements of the equipment you will be installing in it. Table 3 explains the
sizes that are available.
Table 3 Service sizes available from PSE
Voltage
120/240
Ampere Rating
200 A
320 or 400 A
Over 400 A
Typical Use
You may install a service panel or meter base/socket that is sized less than 200 A, but the
service line and meter that PSE installs will be sized as if you were installing a 200 A
service.
If you are installing an underground service that is less than 200 A, your meter
base/socket must meet the dimensional requirements for a 200 A underground meter
base/socket, refer to Chapter 5, Meter Installation, located in this handbook.
You are required to install your meter base/socket in a place that is accessible to PSE. All
locations are subject to approval by a PSE Representative.
If you have questions regarding meter locations, call your CCS Representative at
1-888-321-7779.
Continued on next page
CHAPTER 1
Utility
White
Proposed excavation
Pink
Red
Yellow
Orange
Blue
Potable water
Purple
Green
NOTE: Use white paint to mark the area within which you want utility locations.
CHAPTER 1
Transformer locations
PSE will install padmount transformers using the clearances listed in Table 5 and shown
in Figures 3 through 6.
Clearances between padmount transformers and structures must be measured from the
metal portion of the transformer closest to the building or structure (including any
overhangs).
Table 5 Clearances for padmount transformers
Feature
Clearance distance
CHAPTER 1
Transformer
100i
Well Head
15i
Pools or bodies
of water
10i
Gas
Meter
Relief
Vent
Fuel
Tank
Sprinkler Valve,
Standpipe, or
Hydrant
3i
Transformer
6i
10i
Fire Escape
20i
CHAPTER 1
10i
Approved
Transformer
Area
10i
Approved
Transformer
Area
10i
3i
Combustible
roof or soffit
Noncombustible
roof and soffit
10i
Approved
Transformer
Area
3i
3i
3i
3i
10i
10i
Approved
Transformer
Area
3i
CHAPTER 1
6i
Min
OilFilled Electrical
Equipment
(Pad or Pole Mounted)
20i Min
LP Tank
LP Tank
10i Min
OilFilled
Electrical
Equipment
(Pad or Pole
Mounted)
Top View
Figure 5 Minimum clearances from oil-filled equipment to LP, hazardous liquid, or fuel tanks
CHAPTER 1
Primary Voltage
Power Line
Electric Meter
Base or Switch
Gauge, Vent, or
Fill Connections
6i Min
10i Min
5i Min
5i Min
LP GAS
Outbuildings
An outbuilding is a stand-alone structure which is located on residential property and is
not a living space. Typical outbuildings are barns, pump houses, garages, shops, and
storage sheds.
Service line installation responsibilities for outbuildings
Customer
Puget Sound Energy
NOTE: Installation costs and billing rates are different for the each type of primary use
CHAPTER 1
10
acceptable to customers. If you need to be served with a higher quality of service, contact
your CCS Representative.
CHAPTER 1
Chapter 2
Permanent Underground Service
Steps to a successful underground service installation
The following list details the key steps in the installation of your underground service
resulting in PSEs installation of your underground service line and meter (see Figure 7).
H Confirm where your service line will originate by contacting Customer Construction
Services (CCS) at 1-888-321-7779.
H Call PSE to set up an account and submit an order. Allow adequate time for possible
engineering, right-of-way permits, and easement review.
H Obtain an electrical work permit.
H Determine an acceptable location for your meter base/socket.
H Order underground utility locate service by contacting the 811 Call Before You Dig
hotline two business days before digging.
H Dig a trench and provide proper conduit between your meter location and the service
line origination (transformer, handhole, pole, or stubout).
Provide 4-foot-square work pits at poles, stubouts, handholes, and meter service
entrance.
Provide conduit for electrical service lines that are less than 100 feet and a
3/8-inch pull rope if over 60 feet.
H Install your meter base/socket service entrance equipment.
H Obtain a city or state electrical inspection and approval of your installation.
H Call CCS at 1-888-321-7779 to have your service installed and energized.
Pole
Meter Riser
Secondary
Handhole
CHAPTER 2
multiple residential class customers residing on differing properties with separate legal
ownership.
PSE will allow customer-owned facilities within the service line trench, if the following
minimum horizontal clearances from PSE facilities are maintained:
H 18 inches minimum for customer-owned tight-line sewer (not tile), storm drain lines,
roof drain lines, natural gas line, propane gas line, fuel oil line, and water mains up to
6 inches.
H 12 inches minimum for water services, irrigation pipes, lighting, security and electric
supply circuits, closed-system roof drains/storm drains (not French drains), and
culverts.
NOTE: The Electric Underground Service Installation Requirements handout illustrates
If your service line will be crossing under any permanent structure (driveways,
sidewalks, decks, patios, rockeries, retaining walls, or through your backyard), you are
required to provide and install conduit under those obstructions.
You are required to provide an electrical service line conduit for services 100 feet long or
less. However, PSE recommends the use of conduit for all services.
CHAPTER 2
H The service line conduit shall be gray, schedule 40 PVC conduit with a minimum
2-1/2 inches in diameter for runs of less than 100 feet.
H If you are installing a heat pump with a 320 A service panel and/or the length is
100 feet or longer, the conduit must be 3 inches in diameter.
H White water pipe or green sewer pipe is not acceptable.
H The service line conduit shall contain no more than a total of 180 degrees of bends of
which no individual bend is less than a 24-inch radius.
H Install a 3/8-inch pull rope in the conduit (if conduit runs are 60 feet or more).
H Stop the conduit 4 feet from the pole in the work pit with the pole butt exposed.
H Do not provide a conduit elbow at the base of PSEs pole, and do not install conduit
on a PSE pole.
H When installing conduit at a transformer, stop 2 feet from the entrance at the bottom
of the transformer minipad (Figure 8 and 9).
NOTE: Details of a service line trench with customer-installed conduit is shown in the
CHAPTER 2
Meter Socket
(Surface or Flush Mounted)
PSE Transformer
(Or Pedestal, Handhole, Pole, or Stubout)
24I Min
24I Min
Choose to install a continuous conduit system for your electrical service if:
H Your electrical service length is 100 feet or less.
H The sum total of the degrees of bends in the conduit run (including the bend required
at the bottom of the meter base riser) does not exceed 180_.
H The elevation at the location of available power is less than the elevation of your
meter socket (i.e., your meter socket is uphill from the location of available power).
NOTE: By choosing to install a continuous conduit system, the customer assumes
responsibility for recognizing potential surface and sub-grade water flows that may create
an entry of water into the customers electrical equipment. PSE is not responsible for
damage caused by water entering a customers meter base or equipment.
CHAPTER 2
Meter Socket
(Surface or Flush Mounted)
PSE Transformer
(Or Pedestal, Handhole, Pole, or Stubout)
24I Min
24I Min
24I Min
Choose to install a discontinuous conduit system for your electrical service if:
H Your electrical service length is 101 feet or longer.
H The sum total of the degrees of bends in the conduit run (including the bend required
at the bottom of the meter base riser) exceeds 180_ requiring additional work pits for
cable pulling.
H The elevation at the location of available power is greater than the elevation of your
meter socket (i.e., your meter socket is downhill from the location of available
power).
A table for selecting the required conduit size in a continuous conduit system is provided
in the Electric Underground Service Installation Requirements handout found in the back
pocket of this handbook.
Contact CCS at 1-888-321-7779 if you have questions on whether to install continuous
or discontinuous conduit for your underground electric service.
CHAPTER 2
CHAPTER 2
10
10
Customer
Service Panel
3
4
6i Max.
5i Preferred
4i Min
Customer
Service Panel
6i Max.
5i Preferred
4i Min
2i *
Min
6
7
11
12
13
2i *
Min
11
2i3 i
12
13
2i3 i
NOTE: Conductor slack shall be left at the base of the service entrance for ground settlement, to relieve tension on meter connections.
Items Owned and Installed by Customer
1
2
3
12
13
Bell end
Bell end
Lock washer
Meter base/socket
10
Meter
Insulating bushing
11
Service line
PSE Owned but Customer Purchased and Installed
Figure 10 Two types of meter bases/sockets for permanent underground service, home built
on permanent foundation
CHAPTER 2
SINGLEPHASE INSTALLATION
6i Max.
5i Preferred
4i Min
15I Min
2i Min
*
12
12
No conduit
in this area
14
Load
10
1
15
16
2i3 i
Line
Meter
Insulating bushing
Insulating bushing
15
16
Bell end
10
11
12
13
14
Bell end
CHAPTER 2
If you are installing an underground service to your manufactured home, your service
equipment can be installed one of two ways:
H On a customer-owned pedestal or meter post (see Figure 12).
H On the manufactured home, if both of the following conditions are met:
The manufacturer installed the service equipment at the time your home was built.
The service equipment meets the meter base/socket requirements listed
below.
Meter base/socket requirements
CHAPTER 2
1
11
11
8
2
Weatherproof
Panel
3i Min
6i Max.
3i Min
3
Conduit to be rigidly
fastened to support.
24I Min
12 24I Min
14
10
24I Min
Load
36I Min
12
14
10
3
Load
Line
7
13
Line
2i3 i
7
13
2i3 i
METER PEDESTAL
Manufactured homes only
METER POST
Items Owned and Installed by Customer
11
Meter
12
13
14
Bell end
9
10
Normally, a meter base/socket and associated devices (current transformers, etc.) are
attached to a permanent fixed structure that contains the load being served (such as a
house). If the metering equipment is not attached to the permanent structure, it is called
remote metering. In this case, the conductors that run from the meter to your house are
installed, owned, and maintained by you.
Requirements for residential remote metering, 200 A or less
CHAPTER 2
Bell end
9
2
6i Max.
3 Min
3
Conduit to be rigidly
fastened to support.
24I Min
12
10 24I Min
Load
36I Min
Line
Meter
7
11
11
12
Bell end
2i3 i
METER POST
Other requirements specified in this handbook for meter bases/sockets and current
transformer (CT) enclosures apply.
Remote services greater than 800 A
Remote services 800 A or greater require EUSERC outdoor switchgear. Ask your
CCS Representative for more information.
Meter post and pedestal locations
minimum of 3 feet from the transformer and not installed in front of the transformer.
CHAPTER 2
CHAPTER 2
23
Chapter 3
Permanent Overhead Service
Steps to a successful overhead service installation
The following checklist will assist you in preparing for the installation of an overhead
service (see Figure 14). After you have completed these items, PSE can install the
overhead service line and meter.
H Check for any local ordinances/covenants that prevent you from obtaining an
overhead service.
H Call PSE to set up an account and submit an order. Allow adequate time for possible
engineering, right-of-way permits, and easement review.
H Obtain an electrical work permit.
H Complete Electric Service Application Single-Family Residential 100E. All forms can
be downloaded at PSE.com\customerconstruction.
H Supply site drawings and load information to your PSE Customer Construction
Services (CCS) Representative.
H Call CCS to find out where your service line will originate.
H Determine an acceptable location for your meter base/socket.
H Provide a path clear of obstructions between PSEs service pole and your
service mast.
H Provide the location of any domestic or community water well on your property.
H Install the required service entrance equipment.
H Install the service entrance conductors (leave a minimum of 18 inches exposed at the
weatherhead).
H Verify that the service mast height requirements have been met (see Figure 15).
H Provide payment for any preconstruction costs determined by CCS.
H Have the city or state inspect and approve your installation.
H Call CCS at 1-888-321-7779 to have your service installed and energized.
CHAPTER 3
24
Transformer
Service Line
(Utility Owned and Installed)
Service Entrance
Conductor
Weatherhead
Service Mast Guy
Power Pole
Service Mast
Meter
Service Panel
Clearance requirements
Service line ground clearance
The National Electric Safety Code (NESC) establishes minimum clearance requirements
to maintain safe height requirements for electrical conductors over various terrain
(see Figure 15).
The NESC requires the lowest point of a service conductor to be at least 12 feet above
the ground. The bottom of the drip loop must be a minimum of 10 feet above the ground.
If the service line will pass through any trees, you are required to prune those trees to
provide a clear path for the service line. You are also responsible for regular tree
pruning, and if necessary, tree removal to keep the path clear.
It is not your responsibility to string the conductor, but you are required to provide a
point of attachment at your service mast that will allow PSE to install the conductor and
maintain the required clearances.
If you need further details, please contact the state or local electrical inspector for
your area.
CHAPTER 3
25
Service Line
(Utility Owned)
Service Mast
Connection Point
26i
171/2i
13i
12i
State Highways
Residential Property
Figure 15 Minimum overhead service line vertical clearances from ground level
Minimum clearances from structures, building openings, and gas meters
Service Line
(Utility Owned)
11i Min
31/2i Min
11i Min
3i
Min
Deck
Roofs with
Permanent Access
Electric
Meter
Gas
Meter
Roofs without
Permanent Access
CHAPTER 3
26
When the length of an overhead service line exceeds 125 feet or the clearances shown in
Figure 16 cannot be achieved, an intermediate service pole may be required to maintain
safe ground clearance (see Figure 17) for the wire and to relieve excessive tension at the
service mast.
This intermediate service pole is set and owned by PSE and the cost is in addition to the
service line costs. Please contact CCS for installations that may require an intermediate
service pole to determine additional costs.
Power Pole
Secondary Line
(Utility Owned)
Intermediate
Service Pole
(Utility Set & Owned)
Service Mast
Service Line
(Utility Owned)
Water Well
50i Min
50i Min
Service mast
A service mast is a rigid steel conduit that runs vertically from the top of your meter
base/socket up through your roof. It contains your service entrance conductors and
typically supports one end of your service line. Service masts are necessary when
installing an overhead service and are installed by you or your electrical contractor.
Service mast requirements
The service requirements for the installation of the service mast are located in the
National Electric Code (NEC). Some of the more common methods are included in this
section (see Figures 18 and 19).
Height requirements
The service bracket (the point of connection with PSEs service wire at the top of your
service mast) must be at least 13 feet above final grade or terrain so that the minimum
clearances over your property can be maintained. Additional height may be required
depending on the location and type of structure or terrain which your service line passes
over.
The NEC also requires that your service mast maintain minimum clearances above your
roof (see Figure 18). The clearance required depends on the slope of your roof, and
whether or not your service line is attached to the structure.
For other options and details refer to the NEC. Your CCS Representative can assist you
with determining the proper mast height.
CHAPTER 3
Weatherhead
Service Drop
Weatherhead
Service Drop
Service Bracket
Service Bracket
Flashing
Flashing
18I Minimum
24I Maximum *
2I x 6I Installed
Solidly Between
Rafters and Against
Roof Sheathing
27
Flashing in Courses
of Shingles
18I Minimum
24I Maximum *
Minimum 2I x 6I
Installed Solidly
Between Rafters
or Studs with Hole
Bored for Snug Fit
Rigid Steel
Conduit
Detail
Blocking Between
Mast and Building
Rigid Steel
Conduit
5/16I UBolts
2I x 6I Backing
Structural
Framing and
Finish Materials
Shim Meter
Base/Socket
and Fasten
with Screws
Structural
Framing and
Finish Materials
Flush Meter
Socket
Stud
Ground
Ground
Weatherhead
Service Drop
* Additional support guys required for attachments
greater than 24I above roofline or if service line
exceeds 100i in length.
Service Bracket
Flashing
18I Minimum
24I Maximum *
Galvanized LagBolt
into Framing Member
HeavyWall
StrutType
Channel
Minimum 2I x 6I
Between Rafters with
Hole Bored for Snug Fit
Rigid Steel Conduit
FRONT VIEW
CHAPTER 3
28
Service Bracket
Weatherhead
Weatherhead
No. 6 Copperweld,
Aircraft Cable or
Equivalent
3/4I Rigid Galvanized Conduit
or Equivalent Ends Flattened
and Drilled
45_
Minimum
18I Minimum
45_
Minimum
See
Detail 1
Flashing
Structural Framing
and Finish Materials
Blocking Between
Mast and Building
5/16I UBolt
2I x 4I Backing
5/16I UBolt
2I x 4I Backing
Rigid Steel
Conduit
Rigid Steel
Conduit
Structural
Framing and
Finish Materials
Ground
Ground
Galvanized Thimble
and Cable Clamp
Flashing or Mastic
Galvanized Bolt;
EyeBolt Optional
Attachment
See Detail 1
Pull
60d 90d
Guy Wires
60d 90d
Apart
Pull
METHOD OF GUYING
DETAIL 1
DETAIL 2
CHAPTER 3
29
Additional mast supports, typically a guy or a brace, are required for any service line if:
H The service line is over 100 feet long; or,
H The point of attachment is more than 24 inches above your roof (see Figure 19).
Guys and braces are installed to prevent the weight of the service line from pulling your
service mast away from your home or damaging your roof.
Further information regarding guying and bracing service masts is available in the NEC.
Screw-in service knobs
For new or altered overhead service lines, you must provide a substantial point of
attachment that meets NEC requirements. Older type screw-in service knobs attached to
the homes wall are often inadequate to support modern triplexed service lines. PSE may
prohibit use of service knobs if deemed inadequate.
CHAPTER 3
30
Manufactured homes
If you are installing an overhead service to a manufactured home, our service equipment
can be installed one of two ways:
1. On a customer-owned meter pole, or
2. On the manufactured home, if both of these conditions are met:
a. The manufacturer installed the service equipment at the time the home was
built, and
b. The service equipment meets the meter base/socket requirements listed
below.
Meter base/socket installation requirements for manufactured homes
If a meter pole is required for the project, it is your responsibility to purchase and install
it. The meter pole must meet the following requirements:
H Be sound, round, reasonably straight, and made of wood.
H Fully pressure treated.
H Class 6 or better with a minimum diameter of 5-1/2 inches at the top.
H 30 feet long minimum (25 feet with prior approval).
H Butt gain cut 12 feet from the bottom of the pole (2-inch by 1/2-inch cut into the face
of the pole), or a manufacturers tag attached at 12 feet from the bottom of the pole.
Installation requirements
pole.
If you have any questions, contact your CCS Representative for further assistance.
CHAPTER 3
UtilityOwned
and Installed
CustomerOwned
and Installed
UtilityOwned
and Installed
31
CustomerOwned
and Installed
Point of Attachment
Point of
Delivery
Point of Attachment
Point of
Delivery
Overhead service
load if applicable
6i Max.
5i Preferred
4i Min
10% of Pole
Length, + 2i
6i Max.
5i Preferred
4i Min
10% of Pole
Length, + 2i
Anchor
Rod *
Anchor
Rod *
OVERHEAD TO UNDERGROUND
OVERHEAD TO OVERHEAD
Insulated clevis
Service line
Meter
CHAPTER 3
32
CHAPTER 3
33
Chapter 4
Primary Line Extensions
If your new residence is not located close to existing primary electrical facilities, a
primary line extension is required to place a transformer close to your structure. Primary
line extensions are typically underground facilities.
Customer responsibility
PSEs Electric Tariff G, Schedule 85 requires customers to provide the trenching,
excavation for vaults and backfill in accordance with PSE standards and work sketch, or
contract with PSE to provide this work at its estimated cost.
If you require a primary line extension, submit Electric Service Application
Single-Family Residential 100E. All forms can be downloaded at
PSE.com\customerconstruction.
Inspection/Coordination
PSE shall assign a Project Manager to oversee the trenching, equipment
placement/installation, and backfilling.
H Work shall be subject to the inspection and satisfaction of PSE.
H No work shall be backfilled, covered, or concealed until it has been inspected and
approved by the inspector.
Site preparation
The following site requirements must be met before the installation can begin.
H The trench route shall be clear of spoils, construction materials, and any other
obstacles.
H The site shall be at final grade or acceptable subgrade in the area of construction.
H The front property line shall be surveyed and staked.
CHAPTER 4
34
Customer-provided trench
Trench width
The minimum trench width is 18 inches. The excavator may need to increase the trench
width depending on the other conduits/lines being installed in the trench.
When increasing the trench width, remember to allow adequate horizontal separation
between PSEs electrical conduits/cables, gas lines, and other utility-owned conduits and
lines in the trench (see Figure 21).
Customer-owned facilities may not be in the same trench with PSE-owned gas lines.
PSE will allow customer-owned facilities within an electric power trench if the following
minimum horizontal clearances from PSE electric facilities are maintained:
H 18 inches minimum for customer-owned tight-line sewer (not tile), storm drain lines,
roof drain lines, natural gas line, propane gas line, fuel oil line, and water mains up to
6 inches.
H 12 inches minimum for water services, irrigation pipes, lighting, security and electric
supply circuits, communication lines, closed-system roof drains/storm drains (not
French drains), and culverts.
Figure 21 illustrates PSEs width and depth requirements for primary voltage cable
residential line extension trenches on private property with and without a gas line
present.
ROADSIDE
18I
Typical
24I Min
(To Excavated Dirt Pile)
Final Grade
Final Grade
36I
Min
Cover
Backfill for
DB120 Conduit/Direct Buried Cable
(No Rocks over 10I Diameter)
4I Min
Separation
48I
Max.
36I
Min
Cover
Phone & TV
24I Min
(To Excavated Dirt Pile)
Backfill for
Schedule 40
Conduit
(NO Rocks over
10I Diameter)
4I Min
Separation
48I
Max.
Phone & TV
18I
Typical
ROADSIDE
32I Typical
24I Min
Final Grade
12I Min
Separation
36I Min
Cover
12I Min
Separation
48I
Max.
4I Min
Separation
Excavated
Dirt Pile
Backfill
(No rocks over 10I diameter)
4I Sand Bedding
Gas
Communications
Primary Power
Cables or Conduit
Figure 21 Typical joint utility trench with primary voltage cable on your private property (cross-section view)
CHAPTER 4
35
The following requirements for the trench must be met before power conduits/cables will
be installed.
H When you trench in right-of-way on PSEs behalf, the governing jurisdictions issue
public roadway use permits to PSE.
H For trench work provided by you within a public right-of-way or a PSE easement,
PSE requires that you use a Washington State licensed and bonded contractor and
complete and sign a PSE trenching agreement form.
H Trench work within a public right-of-way must meet the erosion and sediment control
requirements of the local jurisdiction.
NOTE: Acquiring permits for excavation-related activity can take up to a month or
H
H
H
H
H Water shall be removed by pumping or draining following the erosion and sediment
control requirements of the local jurisdiction.
NOTE: Trenches or vault excavations that are 4 feet deep or greater require special
sloping. Contact your PSE Project Manager for these requirements.
Trench and backfill requirements for primary electric line extension trenches (no PSE gas)
CHAPTER 4
36
Trench and backfill requirements for primary electric line extension trenches (with PSE gas)
You must provide a 12-inch layer of sand above and a 4-inch layer of sand bedding
below the utilities before backfilling (see Figure 21). If native backfill is completely free
of foreign objects and rocks in excess of 8 inches in diameter, sand shading over utilities
can be reduced to 6 inches after compaction.
You are responsible for the following:
H Completing backfill as soon as practical after facilities are placed and inspected.
H Carefully placing backfill to prevent damage or movement of the cables or conduit.
H Cost of damages to PSE facilities caused by improper backfill or compaction.
H Relocation costs due to change in grade or alignment.
CAUTION: Do not use a compactor directly over the power conduit(s) until at least
30 inches of backfill is in place, so that the compactor will not damage the cables or
conduit. Do not penetrate the soil deeper than 3 inches during compaction with a
backhoe compactor.
Vaults
PSE is responsible for furnishing and installing all primary vaults required for your
electric service.
CHAPTER 4
37
PLAN VIEW
38I
24I
Customer
Provided
42I
6i0I
6i0I
2I
PSE to complete
conduit run
SIDE
VIEW
48I
6I
Crushed
Rock
3i6I
PLAN VIEW
4I
6i0I
38I
6i0I
2I
Wire access hole
42I
48I
SIDE
VIEW
6I
Crushed
Rock
3i10I
CHAPTER 4
38
Vault Wall
PSE Conduit
Knockouts
Backfill around vaults should consist of good compactable material such as clean earth
fill, crushed rock, or sand. No voids should remain between the vault walls and the sides
of the excavation.
Backfill beneath the vault shall be crushed rock, six inches deep, to stabilize the vault.
If the vault is located in a concrete drive or sidewalk, a felt joint is to be installed around
its perimeter.
CHAPTER 4
39
Customer-supplied conduits
You may supply and install discontinuous primary conduit for construction convenience.
If you supply the conduit for primary voltage cable, it will be owned and maintained by
PSE and shall meet the following specifications:
H PVC electrical grade, Schedule 40 (or Schedule 80 if required in poor soil
conditions).
H Gray in color.
H 2-, 3-, 4-, or 6-inch diameters as specified on the work sketch.
H Conduit bends shall be long radius bends, 36-inch minimum radius.
H Meet requirements in ASTM F 512 and NEMA TC 2.
CHAPTER 4
40
CHAPTER 4
METER INSTALLATION
41
Chapter 5
Meter Installation
This chapter provides you with PSEs requirements for the metering equipment that you
must provide to hook up your new service. Please follow these requirements to avoid a
delay in your service hookup. If you have any questions about this information, call your
Customer Construction Services (CCS) Representative.
Ampere Rating
120/240
200 A
120/240
400 A
120/240
over 400 A *
* If
you need a three-phase service, please contact your CCS Representative. Such services
require the approval of PSEs Meter Department, and are not covered in this handbook.
Responsibilities
Puget Sound Energy
PSE is responsible for installing the meter, service line, and current transformer (CT).
Customer
You are responsible for providing and installing all service entrance equipment
(including the meter base/socket and current transformer CT enclosure).
Meter bases/sockets
General requirements
The meter base/socket you purchase and install shall meet the following general
requirements:
H Be a ring-type socket that includes a screw-type, stainless steel, or aluminum meter
ring (snap-type rings must be stainless steel).
H Be Underwriters Laboratories (UL) approved.
H Be rated for exterior use and be rain-tight according to NEMA-3R.
H Have all unused openings tightly sealed from the inside of the socket.
H Be plumb and securely fastened to the supporting structure.
H Have a cover that is securely attached to the meter base/socket case.
NOTE: Meter base/socket and current transformer enclosures shall not be used as a
junction box.
ELECTRIC SERVICE HANDBOOK/SINGLEFAMILY RESIDENTIAL PROJECTS
CHAPTER 5
42
METER INSTALLATION
For single-family residences and manufactured and mobile homes, you are required to
install your meter base/socket in a place that is accessible to PSE. All locations are
subject to approval by a PSE Representative. If you have questions regarding meter
locations, call your CCS Representative.
Meter bases/sockets and current transformer (CT) enclosures must be located:
H Outside.
H On the front one-third of your home closest to normal public access.
H In an area that is not subject to being fenced or walled in (such as patios, decks,
porches, breezeways, backyards, and carports).
H On a structure that is owned by you.
These locations allow PSE to:
H Read your meter in a cost-effective manner.
H Maintain your meter efficiently.
H Disconnect your service in case of fire.
Grounding requirements
All meter bases/sockets, enclosures, and conduit shall be bonded and grounded in
accordance with the NEC.
CHAPTER 5
METER INSTALLATION
3i Min
43
18I Min
Working
Space
10I Min
3i Min
Top View
4i Min
6i Max.
5i Preferred
6I Min
6i Max.
3i Min
3i Min
10I Min
10I Min
4I
Max.
CHAPTER 5
44
METER INSTALLATION
200 A services
Single-family residential
The 120/240 V, 200 A service is the most common service installed by PSE. Typically, it
is installed on homes with a living area of less than 2,500 square feet. However,
depending upon what type of equipment you are installing, you may want a larger
service. It is your responsibility to determine your electrical requirements and to notify
PSE of the size of service you would like. Refer to Chapter 1, Table 3, for service size
information.
Underground
Overhead
Meter bases/sockets for 200 A (or less) services to single-family residential use
outbuildings (such as garages, shops, single-family wells, or noncommercial barns) must
meet all the requirements listed in this chapter for either underground or overhead
services.
NOTE: If outbuilding is used for a commercial operations please refer to PSEs Electric
CHAPTER 5
METER INSTALLATION
45
Service Line
(PSE Provided)
11I Min
2I Rigid Steel or
21/2 I PVC Conduit
Neutral Lug
14I
Min
Alternate Neutral
Lug Position
Neutral Lug
Alternate Neutral
Lug Position
2I Rigid Steel or
21/2 I PVC Conduit
Customer Wire
Service Line
(PSE Provided)
UNDERGROUND
Customer Wire
OVERHEAD
CHAPTER 5
46
METER INSTALLATION
required to install a CT service (refer to the 400 A current transformer (CT) services
section in this chapter).
Underground
In addition to the meter base/socket requirements listed earlier in this chapter, Class 320
meter bases/sockets for 400 A underground services shall:
H Be rated for 120/240 V and 320 A continuous current.
H Contain four meter jaws and one connection point for the neutral conductor.
H Contain a Class 320 manual block bypass (see Figure 28).
H Have lugs that will accept 350 MCM aluminum wire.
H Accept 3-inch steel or Schedule 40 or 80 conduit through a knockout in the bottom
left corner or center of the enclosure.
H Have at least an 8-1/2-inch clearance between the bottom of the lugs and the bottom
of the enclosure (see Figure 28).
NOTE: Meter base/socket
must be grounded per
NEC.
Bypass
Studs
Line Lug
81/2I
Min
Bypass Studs
LOAD
LUGS
Line Lug
Neutral Block
Customer
Wires
PSE's 4/0 or
350 Cable
Figure 28 Typical arrangement of service conductors for underground class 320 meter base/socket
CHAPTER 5
METER INSTALLATION
Overhead
47
In addition to the meter base/socket requirements listed earlier in this chapter, Class 320
meter bases/sockets for 400 A overhead services shall:
H Be rated for 120/240 V and 320 A continuous current.
H Contain four meter jaws and one connection point for the neutral conductor
(see Figure 29).
H Contain a Class 320 manual block bypass.
Service Conductors
(CustomerInstalled)
Line Lug
Bypass Studs
Load Lug
Line Lug
Bypass Studs
Load Lug
Neutral Block
Customer Wires
Figure 29 Typical arrangement of service conductors for overhead class 320 meter base/socket
Outbuildings (overhead or underground service)
The metering requirements for 400 A services to outbuildings are the same as the
metering requirements for 400 A services to single-family residential structures.
CHAPTER 5
48
METER INSTALLATION
9I
9I
20I
Min
20I
Min
To CT CAN 1
1 Min
Conduit Dia
Test Switch
Space
12I
Min
11I
4I Min
DIAGRAM A
120/240V SINGLEPHASE METER BASE/SOCKET
NOTE 1
No more than four 90_ bends
50 feet maximum length
No Condulets in the run
To CT CAN 1
Test Switch
Space
1 1/4 min
Conduit Dia
12I
Min
11I
41/2I Min
DIAGRAM B
THREEPHASE SINGLE METER BASE/SOCKET
Diagram B
120/208 V, 4Wire Wye
277/480 V, 4Wire Wye
All dimensions are minimum
CHAPTER 5
METER INSTALLATION
49
Phase
Switch
Ampacity
No. of
Transformers
Width
Height
Depth
1*
400800
24I
48I
11I
3*
201800
36I
48I
11I
over 800
Enclosure with a sideopening singlehinged door is required when cabinet dimension is larger
than 24 in. x 48 in.
Services over 800 A require a switchboard designed to EUSERC specifications.
Services from 201800 A may be switchboard designed to EUSERC specifications.
3/4I
CT Mounting Bolts
(Typical 4 Places See Note 3)
5I
13/4I
11/2I
11/2I
13/8I
7/8I
N
1032 Machine
Screw & Washer
Drilled and
Tapped into Bus
81/8I
13/8I
13/4I
3/4I
Cable Term. Bolts
(Typical 4 Places See Note 3)
8I Min
Bus Marking CT
(Typical 2 Places)
1/4I
31/2I
Insulating Barrier
1.
Insulated supports shall be rated for the serving voltage and have sufficient mechanical strength
for the application.
2.
3.
Two 1/2inch steel bolts shall be provided for each cable terminating position and each bolt shall
be furnished with a spring washer and a nut. The spring washer may be either a conetype
(belleville) or a splitring washer and a flat washer. Bolts shall be secured in place and spaced
as shown. All parts shall be plated to prevent corrosion.
CHAPTER 5
50
METER INSTALLATION
CHAPTER 5
TEMPORARY SERVICES
51
Chapter 6
Temporary Services
What this chapter contains
In this chapter you will find answers to questions such as:
H What are the installation requirements for underground and overhead service?
H What are the trenching requirements?
H How do I locate existing underground utilities before I dig?
H How do I get my temporary service energized?
Definition
A temporary (temp) service is a means of supplying electricity to your site for less
than one year. Typically, a temporary service provides power for the construction phase
of your project, while provisions are being made for your permanent power system.
Temp service is provided underground or overhead depending on available PSE facilities.
CHAPTER 6
52 TEMPORARY SERVICES
Scheduling
Most temp services are connected to existing power facilities and engineering is not
required. In these cases temp services are typically energized 3 to 5 days after your
installation has passed inspection. Depending on complexity and work volume, time
frames will vary.
CHAPTER 6
TEMPORARY SERVICES
53
by hand.
Customer Post,
Meter Base,
and Panel
6i Maximum
5i Preferred
4i Minimum
PSE Stubout
Stubout conduit covering the
temporary connection
NOTE: 4ix4i work pit
required to allow working
room for the tools
necessary to connect
temporary service
26I
4i
4i
PSE Conductor
CHAPTER 6
54 TEMPORARY SERVICES
CHAPTER 6
TEMPORARY SERVICES
55
1
Top of meter base shall not
be above top of structure
8
3
6i Maximum
5i Preferred
4i Minimum
5i
Max.
2i Min Cover
3i Min
Meter
NOTE: Trench and backfill from meter base to transformer, handhole, pedestal, or stubout is customer provided.
CHAPTER 6
56 TEMPORARY SERVICES
TEMPORARY SERVICES
57
Service Line
(Utility Owned)
Temporary
Service
26i
171/2i
12i
10i
State
Highways
Residential
NonTraffic
Property
CHAPTER 6
58 TEMPORARY SERVICES
45_
1
2
10i Min
to drip
loop
12i
Min
6i Maximum
5i Preferred
4i Minimum
4
5
24I Min
Ground
Line
8i Min
Service line
Meter
CHAPTER 6
59
Chapter 7
Disconnection and Modification of Service
There may be a time when your electric service needs to be modified. You may wish to
have your service disconnected, reconnected, moved from its current location, relocated,
or simply de-energized. This may involve lengthening, shortening, transferring, or
rerouting the existing service.
Modified services
PSE classifies work done on a service as a modified service when a customer requests
a change in their secondary service that alters its current point of delivery or location to a
new point of delivery without requiring the replacement of the entire service entrance
conductor.
A modified service still must meet all the new service installation requirements. You are
responsible for equipment from the meter socket into your building.
An electrical work permit must be present on your property for all work done on the
customer side of the meter. You must apply for the permit before the work is started.
After the work is completed, your local government agency must inspect the work before
PSE can energize the service.
We know at times the electrical inspection is not completed or feasible by the time we
arrive to reconnect your service. For modified services, if the permit is present and the
work is completed, but the inspection has not been done, the service may still be
energized by PSE if the work looks safe, clean, and completed. The inspection can take
place the following day.
The customer requesting a modified service shall be required to pay PSE the costs of
altering, transferring, or extending the existing electric service to the new point of
delivery or location.
Modified service requirements can vary depending on the scope of the change
(see Table 8).
CHAPTER 7
60
CHAPTER 7
GLOSSARY
61
Glossary
Approved - Acceptable to the authority having jurisdiction.
Backfill - Native soil or soil brought in from another area, free from sharp objects, rocks,
scrap building material, and corrosive material.
Clearance - A set distance between two objects.
Conduit - A listed or approved wireway with a smooth interior surface to permit easy
drawing-in of the electrical conductors. A conduit may be metallic or nonmetallic,
depending on its usage, in accordance with codes and Puget Sound Energy Standards.
Current Transformer (CT) Enclosure - A sealable cabinet designed for surface or flush
mounting, and provided with a frame or trim in which doors or removable covers are
hung.
Customer Construction Services (CCS) Representative - The designated representative
of Puget Sound Energy, responsible for design and/or coordination of new or revised
services to PSE customers. The CCS Representative responds to inquiries on policies,
standards, practices, rates, and energy utilization.
Demand - The maximum average kilowatt load used by the customer for a specific
period of time during the billing period.
Direct Burial - The installation of electrical conductors in a trench, without the use of
conduit.
Drip Loop - A loop formed in overhead secondary conductors at the weatherhead to
prevent water from entering into the service entrance conduit and equipment.
EUSERC - Electrical Utility Service Equipment Requirements Committee
Ground Rod - A ground electrode made up of a rod not less than 8i in length and 5/8I in
diameter, typically made of zinc or copper coated steel. More information on ground rods
is available in the National Electric Code.
Guy - Cable or brace used to relieve the strain of overhead conductors on masts and
poles.
Locked Rotor Current - Locked rotor current is associated with the amount of current
drawn from your electric service necessary to start an electric motor. Typically, a motor
requires more current for the rotor to transition from being stationary or stopped, to
spinning. Once the rotor of a motor is spinning, the current needed to power the motor is
typically reduced. Locked rotor current is sometimes referred to as Locked Rotor
Amperes, In-Rush Current, or Starting Current. Not all motorized devices have a unique
starting current.
Manual Block Bypass (Circuit-Closing Block) - A provision for paralleling the meter
circuit, allowing the meter to be removed without interrupting service to the customer.
Meter Jaw - A spring-loaded receptacle installed inside a meter socket, interfacing the
terminals of the meter to the source and load conductors of the service.
ELECTRIC SERVICE HANDBOOK/SINGLEFAMILY RESIDENTIAL PROJECTS
62
GLOSSARY
Meter Loop - Any provision in which an electrical meter may be installed. Does not
include the service disconnect device.
Meter Pole - A pole which supports the metering equipment owned and maintained by
the customer.
Meter Base/Socket - The mounting device consisting of meter jaws, connectors, and
enclosure for accommodating socket-type meters. The mounting device may be either a
single socket or a trough to accommodate more than one mounting unit.
Metering Equipment - Any equipment associated with measuring electric energy.
Municipal or State Inspector - The qualified representative of a city or the
Washington State Department of Labor and Industries, who has been authorized by
governmental agencies to inspect electrical service installations on their behalf.
NEC - National Electrical Code
NESC - National Electrical Safety Code
Neutral - The grounded conductor in a single-phase, three-wire or three-phase, four-wire
system. The service conductor that is at zero potential to ground.
Point of Attachment (Point of Service) - The point at which Puget Sound Energys
service conductors are attached to the customers premises by an approved insulated
clevis.
Point of Delivery - The connection point of the meter base, on the customers premises,
where Puget Sound Energys circuit and the customers system are interconnected.
Primary Voltage - The higher voltage, before transformation, used to distribute electrical
energy through neighborhoods and local areas. Normally in excess of 600 V.
RCW - Revised Code of Washington
Seal - The locking device used to secure meter and/or service entrance equipment to
assure safety and security for the unit.
Secondary Voltage- The lower voltage, after transformation, used to supply the customer
with electrical energy. Normally less than 600 V.
Self-Contained - In reference to meter sockets: a device designed and rated to
continuously carry the entire capacity of the service entrance equipment through the
meter.
Service Entrance Conductors - Those conductors which extend between the customers
load center and point of delivery.
Service Entrance Equipment - Service conduit, conductors, weatherhead, meter base,
enclosures, service disconnect, and load center.
Service Mast - The conduit above the meter used to provide mechanical protection for
the service conductors and to support the service drop from Puget Sound Energys
system.
Temporary Service - An electrical service installed by Puget Sound Energy to provide
power to a customer on a temporary basis (12 months or less).
UL - (Underwriters Laboratories) A nationally recognized test laboratory which lists
materials it has tested and accepted.
UULC - Utilities Underground Location Center
WAC - Washington Administrative Code
ELECTRIC SERVICE HANDBOOK/SINGLEFAMILY RESIDENTIAL PROJECTS
Notes
Notes