1.1.1 Company Profile: Figure 1:department List Tree
1.1.1 Company Profile: Figure 1:department List Tree
1. 1 Introduction 
 
1.1.1 Company Profile 
 
Energia cables is a new contributor to the Helal El-Sewedy cables Group. 
Material options are copper or aluminum conductors PVC or XLPE insulation 
with protections of steal tape  wire or aluminum tape  wire and jackets of 
PVC or HDPE. 
The capability to provide lead covering allows the production of submarine 
cables. 
The factory is located on zone A3 of the 10th of Ramadan City and Occupies 
50,000 square meter. 
Energia will produce of 132 and 220 KV cables. 
 
1.1.2 Departments List Tree 
   
Any successful organization must have departments with desired objective and 
responsibilities and I found this concept in the EGYTECH Cables Factory . . . . 
And now let me tell a little a bout factory departments 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Figure 1:Department list tree 
2 
 
 
 
1.1.3 Departments Cycle 
 
As we see in the previous figure (fig.1.1) the departments list tree but we must 
know the most important operation named by (Departments Cycle) and that's 
shown in the next figure (fig.1.2). 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Fig. 1.2 Departments Cycle 
 
 
Sales Department 
 
Customer 
 
Technical Department 
Planning Department 
 
Production Department 
Quality Department 
Final Product 
Customer 
1 
2 
3 
4 
5 
6 
3 
 
 
 
1.1.4Diagram Description: 
 
1.  The customer makes a discussion with sales department about the order 
technical specifications. 
2.  Sales department told technical department about the order specification 
and wait feed back as acknowledge that the specifications can 
manufacture and suitable with the standard specifications.  
3.  Technical department after send the acknowledge repair TDS technical 
data sheet for this order then repair report to the planning department 
with the specification of order. 
4.  Planning department make analysis of the orders and the materials then 
repair job order send to the production department with priority of the 
jobs. 
5.  Production department receive the job order and start to finish it in the 
desired time. 
6.  Quality department make a tests every section to be sure that the 
product suitable with the standard values. Then the quality department 
passed the product to be the final product then it be delivered to the 
customer. 
 
1.2Cables 
 
Power cable (a type of electrical cable) is an assembly of two or more 
electrical conductors held together with, and typically covered with, an overall 
sheath. The conductors may be of the same or different sizes, each with their 
own insulation and possibly a bare conductor. Larger single conductor 
insulated cables are also called power cables in the trade. The sheath may be 
4 
 
 
 
of metal, plastic, ceramic, shielded, sunlight-resistant, waterproof, oil-
resistant, fire-retardant, flat or round, and may also contain structural 
supports made of high-strength materials. 
 
1.2.1Cables Types 
 The two major cables types 
   - Over Head Transmission Lines (OHTL) 
   - Under Ground Cable 
 
1.2.1.1 Over Head Transmission Lines (OHTL) 
      It's used for the long distance transmission lines and distribution between 
the villages and towns, metals towers is used to carry the cable in the air. 
  O.H.T.L. is cheaper than the under ground cable. 
  Some kinds of O.H.T.L. : 
  All Aluminum Conductor (AAC) 
  All Aluminum Alloy Conductor (AAAC) 
  All Conductor Steel Reinforced (ACSR) 
  All Copper Conductor (ACC) 
 
5 
 
 
 
Bare soft and hard drawn strande 
 
 
Soft drawn type is used for grounding electrical systems, while hard drawn 
type is used in over head distribution networks. 
All aluminium conductors  
  
used for aerial distribute  lines have relatively short spans, aerial feeders and 
bus bars of substations.   
All aluminium alloy conductors 
       
used for transmission and distribution networks, having relatively long spans 
Conductors Comparison Between Different Types of Aluminum 
(for 185 mm2 Conductor as an example) 
 
AAC  AAAC  ACSR 
Tensile (KN)  43.66  71.55  85.12 
Weight (Kg/Km)  671.1  670.3  980.1 
Figure 2 copper conductors 
Figure 3 A.A.C 
Figure 4:A.C.S.R 
6 
 
 
 
1.2.1.2 Under Ground Cable 
 
  Used in the towns because it's very safe for the customers. 
  It's expensive because the isolation operation and armoring operation .  
  Some kinds of Under Ground Cable : 
 
Low Voltage Cable: 
 
It's used for transmission high capacity of 
power voltage; maximum conductors in 
the cable are four cores and can 
transmission up to 1 kV. 
 
Medium Voltage Cable: 
 
This cable can have single core and can 
reached to three core, cable support from 1 kV 
to 35 kV 
 
High voltage Cable : 
 
it's contain a single core and voltage range 
that can the cable carry from 35 KV to 150 KV 
 
Extra High voltage Cable : 
It's support more than 150 KV 
 
Figure 5:low voltage cable 
Figure 6 :MV cable 
Figure 7 :HV cable 
7 
 
 
 
Cable Manufacturing process 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Drawing 
O.H.T.L.  Stranding 
Insulation 
Assembly  Bedding 
Sheathing 
Warehouses 
Testing 
Screening 
Armoring 
Delivery 
Customer 
M.V
. 
L.V. 
Un armoring 
Cable 
Armoring Cable 
8 
 
 
 
2.1 Metal Section 
 
 
2.1.1 Introduction: 
 
The metal section is the area of the production factory where the first step for 
cables 
Manufacturing is carried out, the conductor manufacturing process. This 
section is divided basically in two main areas, one for the drawing process 
and another for the stranding process. 
 
 
Figure 8 :metal section 
          
As we see in the fig.2.1 the sections of the metal section split to 2 sections 
named Drawing section and Stranding section . . . . . 
We will take about the two sections but first we will take about the Row 
material that can be used in the two sections . . . . . .  
 
There are three types of metals are used in cables manufacturing: 
                  A- Copper with diameter 8 mm and weight (3-4) ton.    
                  B- Aluminum with diameter 9 mm and weight 1.5 ton. 
                  C- Aluminum Alloys with diameter 9.5 mm and weight 2.5 ton 
9 
 
 
 
There are three types of raw material used in the metal section: 
Copper, Aluminum, and Aluminum Alloy. Copper arrives from El Sewedy UMC. 
Before entering into the drawing process, a welding machine must join the 
different coils, therefore in this way it becomes a non stop process. We can 
have copper with all possible cross-sectional areas. 
There are two types of aluminum used here to manufacture conductors: H12 
used to obtain underground cables, and H14 used to obtain overhead lines. 
There is just one type of aluminum alloy, the H17, used to obtain overhead 
lines too. 
And now we will find table show us description of Diameter, electric resistive, 
tensile strength, elongation and Specific weight of the rows material. 
 
  Diameter 
(mm) 
Ele. Resistive 
(.m
2
/km) 
Tensile 
Strength 
(Kg/mm
2
) 
Elongation   Weight 
(g/mm
2
/m) 
AL. H12  9  28.264  8:10.5  20%  2.7 
AL. H14  9  28.264  10.5:14  15%  2.7 
AL. Alloy  9.5  32.53  17:22  3.5%  2.7 
Copper  8  17.241  Max. 250  40%  8.89 
 
Notes: 
 
  The max. Tensile strength of the copper thats mean the maximum force 
that can applied over cross section area. 
  Not good efficiency of conductor when Elongation and CSA increasing 
because the resistance will increase too.  
  Aluminum Alloy put additives with the alloy contains silicon and 
magnesium to avoid the tensile strength increasing.   
 
10 
 
 
 
Advantage of copper or Aluminum 
 
  CU is approx. 60% lower specific resistance than AL. 
  CU has small cross section area than AL for the same power. 
  AL has lower weight than CU for the same power. 
  AL is cheaper than CU. 
  AL is used for cables needing flexibility and copper for cables needing 
high stresses. 
  AL mainly using for over head cables and copper mainly using for under 
ground cables. 
 
2.1.2 Drawing Section 
 
 
2.1.2.1 Definition 
 
Drawing is a mechanical process to reduce the wire diameter by tension force 
between 17 to 33 % of the first diameter by passing the wire through number 
of dies of certain sequence till we get the required diameter 
 
 
2.1.2.2 Main Machine Component 
 
  Pay Off 
  Drawing Block 
  Final capstan Block 
  Annealer 
  Dancer 
  Take Up 
 
 
11 
 
 
 
 
 
 
 
 
 
 
 
 
Pay Off 
 
 
 
 
 
 
 
 
 
Drawing Block 
 
The drawing block is the most important block in this machine cause it's make 
the main process of the machine. 
 
Block Component: 
1- Wire guide (die holder) this block is die holder and die. 
2- Gear box, for rotate all capstans. 
3- Final Die Holder. 
4- Capstan. 
5- Drawing Lubricate. 
 
Dies Construction 
                                                          
 
 
 
Pay Off  Drawing Block  Final capstan Block 
 
Dancer 
Annealer 
 
Take Up 
 
  This part is the first stage in the drawing machine, its function is 
take  the  row  material  (copper  or  aluminum  wire)  to  the  second 
stage and it can be bobbin or Basket  
Figure 9:Drawing machine block diagram 
Figure 10 Dies contruction 
12 
 
 
 
  Entrance angle: give chance for oil to pass with wire in die. 
  Reduction zone: reduce the diameter of wire (elongation process). 
  Boaring: die diameter and this zone is response of output wire. 
  Back relief: this zone is curvature to give smooth surface. 
 Reduction angle : copper (18)      Aluminum(20)         Alloy (14)  
 The length of die related to the kind of material and the desired diameter 
of the wire. 
  The die and wire is lubricating continuously for cooling the wire and die. 
 
Types of Dies: 
 
  Ceramic die (using as a guide not for boaring). 
  Tungsten die (using in Stranding operation). 
Note: 
           We use diamond in the boaring area when we care of quality of wire 
surface and using in fine boaring machine. 
 
Diamond types: 
 
  natured diamond dies (very expensive) 
  synthetic diamond dies (more cheep that the natured) 
 
-Gear Box 
 
Slip Machine:  thats mean in the draw machine gear box to rotate all the 
capstans synchronies with one motor. 
Non slip machine:  that's mean for each capstan motor to control the motion. 
 
-Final die holder 
Driver by separate motor to give circular motion to reduce the scrap in the die. 
 
13 
 
 
 
-Capstans 
We turn the wire over the capstan by 3 turns to save the tension of the wire. 
 
-Drawing lubricate  
This soap is for: reduce the fraction between the wire and the die and to give a 
smooth surface. 
Change mineral oil every 6 months 
Soap oil mixed with fixed amount of water 85% 
 
 
Figure 11drawing lubricata cooler 
 
-Emulsion percentage: 
Heavy drawing machine: 10  14 % 
Intermediate drawing machine: 8  10 % 
For Annealer: 0.5  1 % 
 
-Final Capstan Block 
 
The function of the last capstan to be sure that the diameter of wire not 
changed, to reduce the cut of wire and the number of turns in technical 
recommendation catalog. 
 
-Annealer 
 
This block is exist only in copper wire , This operation is temperature process 
for copper metal after drawing operation done, done by increase the heat to 50 
14 
 
 
 
degree but system isolating from air to decrease the hardiness of copper again 
because it's increasing in the drawing operation. 
Aluminum alloy is annealed in a special oven, by putting the whole spool/coil 
in it after drawing. 
 
Annealer construction 
 
boiler steam generator : to reduce the oxidation 
Brushes transform: closed electric circuit current reach to 8000 A to heating 
the wire. 
Cooling zone: cooling by emulsion. 
We need to decrease the hardness because the relation between the hardness 
and the resistance. 
R H  
Where H  Hardiness of metal        & R  Resistance of metal 
 
Dancer 
 
It's constructing from two capstans and pneumatic system and its function to 
make synchronization speed between take up and the feed speed of drawing 
block. 
This part using in the start up of the machine and when the end of the 
machine to avoid the wire cutting. 
 
Figure 12Dancer diagram 
15 
 
 
 
-Tae up 
Take up kinds: Bobbin (400 mm up to 800 mm) 
Take up kind depend on the diameter of the wire. 
 
- Types of Drawing Machines 
 
1.  Heavy Drawing Machine 
  Single wire 
  Double wire 
2.  Intermediate Machine  
3.  Fine Machine. 
- EGYTECH Drawing Machines 
 
DO  Drawing operation 
 
  DO.1  DO.2  DO.3  DO.4  DO.5 
Kind of M/C  Heavy 
drawing M/C 
Single wire 
Slipping M/C 
Heavy 
drawing M/C 
Single wire 
Slipping M/C 
Heavy 
drawing M/C 
Single wire 
Slipping M/C 
Intermediate  
drawing M/C 
8 wires 
Slipping M/C 
Heavy 
drawing M/C 
Double wire 
Slipping M/C 
Supported 
Metal 
Copper  Aluminum  Aluminum  Copper  Copper 
Aluminum 
Max. no. of 
dies 
13  15  11  8 X 11  2 X 16 
Min. diameter 
(mm) 
1.2  Inlet dia.  Inlet dia.  0.26  1.35 
9.5  9  9.5  9     
1.7  1.53  2  1.9     
Max. diameter 
(mm) 
4.5  Inlet dia.  Inlet dia.  1.35  4.5 
9.5  9  9.5  9     
4.5  5.2  4.5  5.2     
Max. Speed 
(m/s) 
31.5  37.5  37.5  30.5  35 
16 
 
 
 
Focusing in DO.5: 
  It is a copper drawing M/C. 
  This machine consists of 11 pair of dies (22 die). 
  The maximum and minimum diameters I can get from this machine are 
4.5&1.4mm respectively. 
  This machine can draw two wires in the same time. 
  The wires out from this machine can be turned on pulleys or baskets 
according to the stranding machine that will strand it. 
The following table contains the sizes of the dies that used in the machine: 
2.1.3 Stranding Section 
 
2.3.1 Definition 
The need of making the stranding operation can be explained as follows. The 
current  flows  typically  along  the  surface  of  the  conductor  (skin  effect),  so  to 
allow  the  conductor  to  carry  more  current,  more  wires  of  smaller  cross-
sectional areas are used instead of using just one of larger area. In this way, 
conductors are made of layers of wires. 
The operation of stranding can be summarized as follows:  
One wire is placed in the center of the conductor; a second layer containing 6 
wires is stranded around it, then becoming the "1 + 6" conductor the center of 
the next third layer, which is made of a total of twelve wires; if the conductor 
needs to have another layer, the previous "1 + 6+ 12" becomes the center of 
the this new fourth layer. 
17 
 
 
 
The  conductor  of  cables  consists  of  a  number  of  strands  of  wire  of  circular 
cross section so that it may become flexible and array more current. 
To  avoid  the  bending  and  deformation  of  the  cable  conductor  under  normal 
conditions. 
The number of strands in cables is 7, 19, 37, 61, 127 and 169. 
For example the arrangement of 7 strands cables six strands spiraled around a 
central strand.  
 
 
 
 
 
 
 
 
As we see in the table the formation of wires with the number of layer 
 
 
 
 
 
 
 
 
 
 
 
Lay length:  
It is the distance in mm between two consecutive ups or downs of a certain 
component of the cable. 
 
Conductor  Number of layers  Layers 
7 wires  2  1 + 6 
19 wires  3  1 + 6 + 12 
37 wires  4  1 + 6 + 12 + 18 
61 wires  5  1 + 6 + 12 + 18 + 24 
Figure 13:formation of wires 
18 
 
 
 
 
 
 
 
 
 
 
 
Calculation method of stranding conductor diameter 
 
  Calculation method of circular conductor diameter 
By this equation 
Dc = .Dw 
Where:-  
Dc  The diameter of conductor of the cable 
Dw  The diameter of the wire. 
  Lay factor 
 
 
  3  5  7  9  11  13  15 
No. of wires  7  19  37  61  91  127  169 
 
  Calculation method of core of ACSR conductor diameter 
By this equation  
 
Dc = n.Dw.DS 
Where  
Dc  The diameter of conductor of the cable 
Conductor  Factor 
91 wires  8  10 
61 wires  10  12 
37 wires  12  14 
19 wires  14  16 
7 wires  16  18 
19 
 
 
 
n .. .Factor. 
Dw  The diameter of the wire. 
DS  The diameter of the steel. 
 
n  2  4  6 
No. of Layers  1  2  3 
 
Stranding lay direction 
  The alternate layers have right and left spirals the arrangement of 7 
strands conductor six strands spiraled around a central strand. 
  Te direction of spiraling of this layer (12 strands) is in the opposite 
direction to the previous layer.  
 
Stranding Cables 
 
  Sector cables (used for low voltage range 3 X 120  4 X 90  3 X 100 + 
60 ) 
  Compact Cables (used for medium and high voltage range) 
  Over Head Transmission Line (O.H.T.L.) 
  AAC 
  ACC 
  ACSR 
  AAAC 
 
 
 
 
 
 
 
Figure 14:Rotating cage 
20 
 
 
 
 
The stranding M/Cs classification 
1- Rigid stranded M/Cs. 
   This M/Cs consists of: 
  Feeding carrier. 
  Rotating cage contains 6 pulley carriers. 
  Rotating cage contains 12 pulley carriers.  
  Rotating cage contains 18 pulley carriers. 
  Rotating cage contains 24 pulley carriers. 
  Double capstan of diameter 2m. 
  Receiving carrier. 
  After each cage there are rollers used in compressed and sector 
conductors. 
2- Double twist M/Cs. 
   This M/C strands the wires by using a rotating arm which rotates fast 
twisting the wires, and then the wires are reversed to be turned on the 
receiving pulley which rotates around itself and that is the other twist. 
 
 
 
 
 
 
 
 
 
 
 
 
21 
 
 
 
2.2. Extrusion Section 
 
2.2.1 Introduction 
 
The Extrusion section function is insulate the conductor from the any behind 
air and insulate the conductor from the others conductors. 
This stage is very important stage in manifactor the cables because the ability 
of using this cable mainly depend on the insulation stage. 
The Extrusion section made insulation to the L.V. cables and for H.V. cables 
made in the C.V. section and this will be described in other chapter. 
 
    
 
 
 
 
 
 
 
2.2.2 Type of Material 
 
The material is divided two main parts 
1- Thermoplastic material. 
2- Thermosetting material. 
The difference between the two material is that the 1st can be recycled but the 
other can't. 
Thermoplastic such as PVC and thermosetting such as XLPE 
The XLPE material consists of PE (polyethylene) with Catalyst material and by 
operating condition it's converted to XLPE 
Figure 15 Extrusion section 
22 
 
 
 
PE + CATALYST =XLPE 
There are types of materials are used in insulation section but the materials 
which used to insulation the cable are 
1- PVC (polyvinyl chloride) 
2- XLPE (Cross Linked Polyethylene) 
The material is used for insulation depend on the type of screw which used in 
insulation, bedding or sheathing process 
 
And we will find the different between the materials that we used in this table: 
  
  PVC  XLPE 
Cost  Cheaper than XLPE  More Expensive than PVC 
Made in  Egypt  Imported 
Recycling  Yes  No 
Operating 
Temperature 
70C  90C 
Density  From 1.4 to 1.6 g/cm
3 
0.92 g/cm
3 
Cooling 
trough 
The conductor pass cool 
water 14C in cooling system 
Must be pass in hot water 
60C to 10m from cooling 
system 
 
 
Generally materials are used in Extrosion section as follows 
1- PVC (polyvinyl chloride) 
2- XLPE (Cross Linked Polyethylene) 
3- LDPE (Low Density polyethylene) 
4- LLDPE (Low Liner Density polyethylene) 
5- MDPE (Medium Density polyethylene) 
6- HDPE (High Density polyethylene) 
23 
 
 
 
7- LSOH (Low smoke zero halogen) 
8- LSHF (Low Smoke halogen free) 
 
The material (LLDPE, MDPE and HDPE) are used for sheathing 
The material (LSHF and LSOH) are used for insulation 
And the recycled PVC is used for bedding (inner covering), if wanted PE for 
bedding so used MDPE. 
 
Properties of cable insulation 
 
1- Must have specific resistance. 
2- Must be high dielectric strength (KV/mm) 
3- Rigid and flexible. 
4- Must non flammable. 
 
2.2.3 Extrusion Machine Components  
 
 
 
 
 
 
 
 
 
Figure 16: Insulation Machine block diagram 
 
 
 
The main component of each Extrusion machine can be summarized as follow 
 
1- Pay off this feed the machine with conductor. 
Pay Off  Caterpillar  Extruder 
 
Spark Tester 
Cooling Trough 
 
Take up 
 
Caterpillar 
 
24 
 
 
 
2- Caterpillar the aim of this part to pull the conductor, there are two 
caterpillars one at the beginning the machine and other at the end, the 
speed of two caterpillar must be synchronized. 
3- Extruder it's consists of screw, barrel and crosshead the screw part 
consists of five zones which used to heat the insulation material PVC or 
XLPE before going to the crosshead of the machine, the head part consists 
of four heaters 
4- Cooling trough it is necessary to cool it before going into the reel. 
5- Spark Tester it's apart that response of the test insulation its idea that 
applied DC voltage reached to 10 KV to test the insulation of the wire. 
6- Take up the reel is ready to go to the assembly process. 
 
 
   
 
 
 
 
 
 
 
 
 
 
 
1- Tube tooling  
T1 inner diameter of tip = C1 (diameter of conductor of pay off X 1.1) 
D1 inner diameter of die = T2 outer diameter of T1 X ([3 to 4] thickness of 
insulation) 
2- Pressure tooling 
T1 inner diameter of tip = C1 (diameter of conductor of pay off + [0.1 to 
0.5] mm) 
D1 inner diameter of die = C2 desired diameter after insulation 
Figure 17:Extruaion method 
25 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
2.2.4 EGYTECH Extrusion M/Cs 
 
Figure 19:INdulation line 
 
NMB 80 
 
  Processes made : Insulation 
  Diameter of the cable from 0.5 mm2 to 10 mm2 it's better to run 10 
mm2 cable in the BM 100 because it is too heavy, therefore in 
general it is preferred to insulate cables from 1 mm2 to 6 mm2 
  Materials used in this machine : PVC and XLPE 
  The next conductors are insulated with this machine: stranded 
,flexible and solid. 
  Max. line speed 1000 m/min 
  Spark detector is installed to verify that the insulation has no faults. 
  Pay off: two units with reel of maximum diameter of 1000 mm and 
minimum diameter of 630 mm and maximum weight of 1 Ton. 
Figure 18:tooling of head method 
26 
 
 
 
  This machine has no caterpillars instead it is using two cabstands to 
apply tension to the conductor. 
  Take up: two units with reel of maximum diameter of 1000 mm and 
minimum diameter of 630 mm and maximum weight of 1 Ton one 
units is in operation and the other one is standing by as a backup. 
 
NMB 100 
 
  Processes made : Insulation and sheathing  
  Diameter of the cable:  
a- Copper conductors from 10 mm2 (round) to 35 mm2 (round and 
sector). 
b- Aluminum with 50 mm2. 
  Materials used in this machine : PVC and XLPE 
  The next conductors are insulated with this machine: stranded. 
  Max. line speed 400 m/min 
  Spark detector is installed to verify that the insulation has no faults in 
this machine if alarm enabled the machine stop immediately. 
  Pay off: two units with reel of maximum diameter of 1600 mm and 
minimum diameter of 630 mm and maximum weight of 6 Ton. 
  This machine has no caterpillars instead it is using two cabstands to 
apply tension to the conductor. 
  Take up: two units with reel of maximum diameter of 1600 mm and 
minimum diameter of 800 mm and maximum weight of 6 Ton. 
 
NMB 120 
 
  Processes made : Insulation, bedding and sheathing  
  Diameter of the cable: copper or aluminum conductors from 5 mm2 
(round) to 57 mm2 (sector or round). 
27 
 
 
 
  Materials used in this machine : PVC and XLPE 
  The next conductors are insulated with this machine: stranded. 
  Max. line speed 200 m/min 
  Spark detector is installed to verify that the insulation has no faults. 
  Pay off: two units with reel of maximum diameter of 2200 mm and 
minimum diameter of 1000 mm and maximum weight of 10 Ton. 
  This machine has two caterpillars. 
  Take up: two units with reel of maximum diameter of 2200 mm and 
minimum diameter of 1000 mm and maximum weight of 10 Ton. 
 
NMB 150 
 
  Processes made : Insulation, bedding and sheathing  
  Diameter of the cable: copper or aluminum conductors from 11 mm2 
(round) to 115 mm2 (sector or round). 
  Materials used in this machine: PVC and XLPE, low smoke material 
etc. 
  Max. line speed 150 m/min 
  Spark detector is installed to verify that the insulation has no faults. 
  Pay off: one unit with reel of maximum diameter of 3400 mm and 
minimum diameter of 1400 mm and maximum weight of 15 Ton. 
  This machine has two caterpillars. 
  Take up: one unit with reel of maximum diameter of 3400 mm and 
minimum diameter of 1400 mm and maximum weight of 15 Ton. 
   
NMB 160 
 
  Processes made : Bedding and sheathing  
28 
 
 
 
  Diameter of the cable : copper or aluminum conductors from 10 mm2 
(round) to 130 mm2 (sector or round). 
  Materials used in this machine : PVC and recycled material (just for 
bedding). 
  The next conductors are insulated with this machine: stranded. 
  Max. line speed 140 m/min 
  Pay off: two units with reel of maximum diameter of 3400 mm and 
minimum diameter of 1200 mm and maximum weight of 15 Ton. 
  This machine has two caterpillars. 
  Take up: two units with reel of maximum diameter of 3400 mm and 
minimum diameter of 1200 mm and maximum weight of 15 Ton. 
 
3.6 comparisons between the M/Cs 
 
  BM80  BM100  BM120  BM150  BM160 
Processes 
mode 
Insulation  Insulation and 
sheathing 
Insulation 
bedding and 
sheathing 
Insulation 
bedding and 
sheathing 
bedding and 
sheathing 
Size of the 
cable 
0.5 mm2 
to 6 mm2  
For cu 10 mm2 
to 35 mm2 
for AL 50 mm2 
5 mm2 
to 57 mm2 
11 mm2 
to 115 mm2 
10 mm2 
to 130 mm2 
Materials used  PVC and XLPE  PVC and XLPE  PVC and XLPE 
and LSHF 
PVC and XLPE 
and LSHF 
Recycled PVC 
Max. linear 
speed 
1000 m/min  400 m/min  200 m/min  150 m/min  140 m/min 
caterpillar  no  No  two  two  two 
 
 
 
 
29 
 
 
 
2.3 Assembly Section 
 
 
2.3.1 Introduction 
 
In fact the Rotating Machine section divided in four main tasks : 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Fig. 5.1 Assembly section 
 
The description of each section: 
  An Assembly, to put in one cables all phases together; and covers them 
with propylene tape. 
  Armoring which covered cables by (steel or aluminum) (tape or wire), to 
protect the cable against mechanical stresses like for example ground 
pressure 
30 
 
 
 
  Lead the cable or conductor is covered by layer of layer of lead to protect 
the cable against water penetration or chemicals Reaction 
  Screening the cable is covered by layer of cupper (tape or wire), to earth 
the cable. 
 
Not all these steps need to be followed to manufacture a cable it depends 
mainly on the customer requirements or the final conditions and situation of 
the cable (marine, petroleum, etc. 
 
2.3.2 Assembly Section 
 
As said before the main function of this stage to put in one cables all phases 
together; and covers them with propylene tape. 
During this first step all conductors are assembled together in one cable and 
after that the cable is covered with polypropylene tape  
Any kind of cable can be assembled in this step. 
For section conductors with higher cross section areas the performing lay 
length can be done during the stranding operation but for small areas this 
operation is done directly during the assembly operation. 
If the performing lay length was made in the stranding machines the RPM of 
the pay off and take up of the assembly machine must be very high to 
maintain the lay length however if the lay length is carried out in the assembly 
section the RPM of pay off is fixed while the take up is rotating to be able to 
apply the lay length to the complete assembled cable. 
 
Assembly Machine Block Diagram 
 
 
 
 
Figure 20:assembly machine block diagram 
Pay Off  Assembly Block   Correct Angle 
 
Tape or Armoring Stage 
Dies Stage 
 
Take up 
31 
 
 
 
 
Pay off this stage is very important because 
we must care about the tension between it 
and the take up stage. For assembly we used 
motor because we need a low tension but in 
armoring case we using pneumatic system 
cause we need a high tension 
 
 
 
Assembly Block this block to assemble the phases and can assemble with it 
filler. 
 
 
Figure 22Assembly block 
 
Correct angle when we perform the lay with sector cable we must to be sure 
that all lays have correct angle with each other this block do this job by 
determine range of angles for trying to correct the angle but if angle be larger 
or less than the range the machine stopped immediately and trying to correct 
the angle manually. 
 
Die Stage this stage generally is three dies first die make the assembly function 
only the second die make the assembly with compact the cable the third and 
the last die used with the second die when we need segmental cable used for 
installed the long die. 
Figure 21pay off 
32 
 
 
 
 
Tape or Armoring Block this in real is two block the first is tape block for put 
taping to the cable and the kind of the tape is polypropylene and the second is 
for armoring the cable and this stage is optional depend on the customer 
requirements. 
 
                                                           
 
 
Figure 23:taping and armoring 
 
 
Take up this block as we said before must its tension synchronized with the 
pay off 
 
 
Assembly M/Cs 
  Assembly 3000 
  Assembly 2200 
  Assembly 1600 
 
Assembly 3000 
 
This machine is used with all kind of process: Assembly armoring (steel wire 
armoring SWA or steel tape armoring STA) and screening. 
 
Figure 24take up 
33 
 
 
 
 
Figure 25assembly 3000 pay off 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Pay offs there are five pay offs one with a maximum diameter of 3000 mm used 
with long bobbin and four with a maximum diameter 2200 mm. the big pay off is 
used for armoring and the other four for assembling up to four conductors. 
Maximum weight supported with pay off 3000 is 15 TON and for pay off 2200 
is 8 TON. 
 
 
Take ups one take which is rotating at low speed because in this machine the 
lay length is high used for both the assembly and armoring operation. 
Figure 26assembly 3000 take up and pay off 
34 
 
 
 
The maximum weight of take up 3000 is 15 TON. 
Max. Formation lay length from 300 to 3000 mm 
Max. Number of armoring wire is 60 wires  
 
The assembly Head contains the Screw 
axis and two Die holders. The first die 
has a diameter equal to the diameter of 
the cable with an extra 2 or 3 mm and 
it  fixes  the  cable  to  avoid  movement 
during  the  entire assembly  operation;  the  second  die  has  a suitable  diameter 
with  no  tolerance  to  compact  the  cable,  and  to  make  it  as  much  rounded  as 
possible. 
Cage  with  propylene  tape  device.  It  is  possible:  (a)  to  put  one  tape  with  a 
percentage  of  over  lap,  (b)  to  put  two  tapes  at  the  same  time,  with  over  lap 
between  them  to  increase  the  speed  of  the  machine  and  the  production.  The 
speed of the assembly machine is determined by the RPM of that device. This 
tape is added to separate the insulation from the bedding. 
 
Assembly 2200 
 
This machine is similar to Assembly 3000 in the technique and in the Block 
diagram  
 
Pay offs there are four pay offs one with a maximum diameter of 2200 mm and 
the other sizes supported is 1600 and 1250 mm. 
 
Take up 
Fig. 5.9 Two tapes operation 
Figure 27 two tabes operation 
35 
 
 
 
The maximum weight of take up 2200 is 10 TON. 
This machine assembly two kinds of cables the power cable and the control 
cable 
The definition (n X C) 
Where: n ... number of wires assembled       C  is the cross section area of 
one wire 
The sizes supported with this machines: 
For control: 24 X 4  -  37 X 4 (two stages) 
For power: 4 X 240 
Max. Formation lay length from 150 to 1500 mm 
Max. Number of armoring wire is 72 wires 
Assembly 1600 
Assembly  machine  1600.  It  is  used  just  for  assembling  and  armoring  (steel 
wire).  In  the  assembly  operation,  this  machine  is  used  just  with  round 
conductors  with  small  sizes,  basically  control  cables,  and  made  up  to  24 
phases. 
The Machine description  
 
 
Figure 28Assembly 1600 Machine 
 
 
36 
 
 
 
 
Five  Pay  offs,  one  with  a  maximum  diameter  of  1600  mm  used  with  long 
bobbins and used for either assembling or armoring operations, and four with 
the  same  maximum  size  but  fixed  used  just  for  assembling  Can  support  630 
too. 
 
One Take up, which is rotating at a very high speed because the lay length in 
this  case  is  small,  used  for  both  the  assembly  and  armoring  operations;  For 
safety reasons because of the high speed, it is kept inside a cage. 
 
Roller  with  four  bases,  to  collect  and 
change the direction of the phases. 
 
Two Guides with holes to guide the 
conductors up to the head; it is possible to 
decide which holes to use depending on the 
number of phases to be assembled. 
Max. Formation lay length from 50 to 550 
mm 
Max. Number of armoring wire is 50 wires 
 
 
2.3.3 Armoring Section 
 
5.3.1 Armoring Operation 
 
The armoring stage is carried out to protect the 
cable  against  any  mechanical  stresses  like  for 
example  ground  pressure  appeared  over  the 
Figure 29Assembly hesd in Assmbly 1600 machine 
Figure 30Armoring section 
37 
 
 
 
underground  cable  when  a  big  truck  is  passing  over  generating  a  pressure 
force through the soil that may reach the cable. 
When  the  cable  is  working  under  normal  conditions,  the  current  flowing 
through  the  conductors  generates  a  magnetic  field  which  products  current 
circulating  along  the  layer  of  armoring;  therefore  it  needs  to  be  grounded  in 
some point. 
 
2.3.2.1 Types of Armoring 
 
1)  Steel tape armoring 
 
Two types of steel tape armoring: Normal or galvanized; since the first one 
can be corroded easily, the second type, although more expensive, is used 
to protect the armoring against corrosion. 
This  type  of  armoring  is  carried  out  basically  to  protect  the  cable  against 
any horizontal mechanical stresses as explained before. Apart from that, it 
can also carry the earthing fault current. 
This  type  of  armoring  is  done  with  two  steel  tapes  by  using  an  over  gap 
process: The second layer of tape is placed over the first one by 50 % over 
gap  of  the  tape  width,  the  size  of  the  tape  is  specified  by  its  width  and 
thickness as follows 
   
  Tape width  x  Tape thickness   
The next sizes are available: 15 x 0.2, 20 x 0.2, 30 x 0.2, 40 x 0.2, 40 x 
0.5, 50 x 0.5, 60 x 0.5, 50 x 0.8, and 60 x 0.8. The tape width depends on 
the  diameter  of  the  cable;  its  value  is  typically  near  the  value  of  the 
diameter of the cable; for example if the diameter is 25 mm the size of the 
38 
 
 
 
tape chosen is 30 x 0.2. The tape thickness depends on the voltage of the 
cable: (a) 0.2 and 0.5 are used in LV, (b) 0.5 and 0.8 are used in MV. The 
values  for  widths  and  thicknesses  must  be  according  to  the  Standards 
specifications. 
2) Aluminum tape armoring and Aluminum wire armoring (not galvanized) 
Aluminum is used with single core cables to avoid the magnetic field appeared 
in  the  armoring  layer;  There  is  no  magnetic  field  appeared  in  this  material. 
Aluminum  does  not  allow  carrying  the  earthing  fault  current  because  its 
conductivity is very low. 
3) Steel wire armoring (galvanized) 
This type of armoring is carried out to protect the cable against strains, i.e. 
horizontal tensions appeared along the cable, the same as for the steel tape 
armoring, the wires can also carry the earthing fault current. 
The  operation  is  carried  out  by  covering  all  the  surface  area  of  the  cable 
with wire; the called "Armoring Lay" (one period of wire moving around the 
cable) can be determined as follows 
  Armoring lay = factor X diameter of the cable   
The value of this factor is around 10 or 11, and it is calculated from several 
formulas. It is important to differentiate the armoring lay from the 
performing lay carried out during the stranding or the assembly operations. 
 
 
2.3.2.2 Armoring machines 
Armoring  machine  3000  (maximum  diameter  of  Pay  off).  It  can  be  used  for 
armoring (steel wire or steel tape) and screening (copper wire). 
39 
 
 
 
A very general description of the different parts of the machine is given as 
follows: 
- One Pay off and one Take up. The Pay off has a break to be able to apply 
tension  to  the  cable.  The  Take  up  has  two  movements:  One  straight  to 
accumulate  the  cable  on  the  bobbin,  and  another  one  in  rotation  to  make 
the lay. 
- One Guide to center the cable. 
- Two Cages to put tape before  armoring. It is used copper tape and / or 
semi-conducting  tape.  Sometimes  it  is  necessary  to  use  just  one  type  of 
tape;  therefore  one  of  the  two  machines  can  be  switched  off.  The  same 
technique used in the assembly operation is used here too to put the tapes. 
- Big Caterpillar which needs to rotate due to the rotation of the Take up. 
Two types of belts can be used in this caterpillar: Flat used with cables of 
small diameter, and concave for bigger diameters. 
- The Control of the machine is carried out by means of a computer. The 
main  parameters  to  be  introduced  are:  (a)  Rotation  of  the  Pay  off,  left  or 
right,  and  maintaining  always  opposite  directions  for  assembling  and 
armoring, specially in LV cables because of the use of sector conductors; 
(b) for the cages, to specify whether the armoring or screening head will be 
used or not, the armoring lay (right or left side), and the rotation speed. 
Assembly 3000 and Assembly 2200 can use too in the Armoring  
Assembly  3000  support  up  to  100  wires  armoring;  but  in  case  of  Assembly 
2200 support up to 72 wires. 
   
 
40 
 
 
 
2.3.4 Screening Section 
 
Screening operation 
 
 
 
 
 
 
 
 
 
 
 
LV cables carry typically three phases and one neutral. However, MV (multi 
core) and HV  (single core) cables carry just three phases, being necessary 
to have an "extra" neutral to carry the fault current, short circuit current, etc; 
this is done by means of the screening. 
Customers  determine  the  quantity  of  screening  being  used  by  specifying 
the  weight  of  screening  per  meter  of  cable  or  also  by  giving  the  cross-
sectional  area  of  screening.  As  a  result  of  this,  it  needs  to  be  determined 
the type of material used for screening: Copper wire or copper tape, being 
necessary to specify the diameter in case of using copper wire, or the over 
lapping in case of using tape. 
Figure 31screening operation 
41 
 
 
 
The maximum over lap is 48 % with higher percentages it is necessary to 
use copper wire instead of copper tape, with the same technique as the one 
used for armoring. 
Two main benefits of using copper tape are: (a) possibility of deviating the 
current (electric field) far away from the point where an existing insulation 
problem may appear (impurities, etc); there is no surface area covered with 
the copper wire to make the deviation (there is a distance between wires); 
(b)  possibility  of  having  the  earthing  for  the  cable.  The  main  benefit  of 
using copper wire is to earth the cable. 
In  the  case  of  using  copper  wire,  a  new  technique  is  being  carried  out  to 
avoid using copper tape: To decrease the diameter of the wire and increase 
the  number  of  wires.  However,  some  customers  still  prefer  to  use  copper 
tape to ensure the connection. 
 
Screening machines 
There  are  two  screening  machines  in  the  Production  Area  with  3000  mm  of 
maximum diameter for the Pay off. Both of them can be used with all kinds of 
tape  (cooper  tape,  blocking  water  tape,  semi-conductor  tape,  etc).  The  main 
difference between both machines lays just in the design of the cages. There 
are  two  cages  in  each  machine  to  allow  using  two  different  types  of  tapes  if 
necessary. 
 
 
 
 
42 
 
 
 
2.4C.V. Line. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
The Continuous or Cattenary Vulcanization Line (C.V. Line) is a special case in 
insulation for the production Department.
 The objective here is to assemble multi core cables
Drawing  
 
Stranding 
Insulation 
Screening 
Single core 
Triple core 
Bedding 
Aluminum 
wire 
armoring 
Sheathing  Sheathing  Sheathing  Sheathing 
 
Bedding 
Steel 
 wire 
armoring 
43 
 
 
 
 for Medium Voltage (3.6 kV - 33 kV),
 High Voltage (66 kV - 132 kV),
 and Extra High Voltage (132 kV - 220 kV), with insulation machine of cross-
linked polyethylene (XLPE)
INSULATION 2. 
Any cable manufactured in this section (MV, HV, and EHV) must have three 
layers of insulation: 
Inner semi-conductor, insulation, and outer semi-conductor. 
 
  Inner layer: Inner semi-conductor. This chemical composite is made of 
XLPE45% used for insulation with a percentage of carbon 55%to give the 
 
 
semi-conductivity property to the material. Carbon also gives the black color 
to this material
 
Figure 32 splice box
44 
 
 
 
The use of this inner semi-conductor layer is very important. the Figure  
shows this concept. If no semi-conductor is used, there would be two 
different areas of contact between insulation and conductor, the called 
"weak" and "strong" areas (the thickness of the insulation is thinner along 
the "weak" area and "thicker" in the strong area, while the electric field is 
smaller in the "weak" areas and higher in the "strong" areas). The addition of 
this layer of semi-conductor has the objective of filling the gaps for the 
"strong" areas and distributes the current properly along all inner part of the 
insulation, removing all "weak" areas, and maintaining equal its thickness. If 
no semi-conductor layer is used, the insulation may break after a few 
years.
 
 
 
 
 
 
Figure shows  Inner semi-conductor layer.
 
Another important function of this inner layer is to allow the voltage 
decrease gradually from the conductor to the insulation, taking advantage 
of the main property of a semi-conductor, it is neither total conductor nor 
total insulation.
  Middle layer: Insulation. As explained before, the only material used as 
insulation in the C.V. Line is the XLPE. The main differences between both 
PVC and XLPE as explained as follows
Figure 33 show inner semi _coductor layer
45 
 
 
 
 
- PVC is a thermoplastic material that can be recycled if necessary, while 
XLPE is a thermo set material that can not be recycled because it would 
burn if the material is overheated again. This is the main difference between 
them.
 
- The maximum temperature that the PVC can reach before the insulation 
breaks down is 70 C, while for XLPE is 90 C.
 
In the previous report, for the Insulation Section, it was explained the 
curing process of XLPE (vulcanization) to cross-link its molecules. With 
this process, the insulation material becomes stronger, and more difficult to 
break.
 In the C.V. Line, the curing process is made during the insulation 
operation, instead of being done at the end by means of a sauna; coils 
obtained from the insulation area are placed in a room with water (steam) at 
60 C -70 C, and the time of this process depends on the thickness of the 
insulation (it can be even up to 16 hours). The C.V. Line process can not 
afford that long period of time for curing. The complete package of XLPE 
(raw material) used here in the C.V. Line has internally small particles of 
catalyst, while in the Insulation Section, the catalyst
is added apart.
   
In the C.V. Line, the process to cross-link the molecules of XLPE is made 
just under one condition, the application of high temperature Max.(450 C). 
46 
 
 
 
The duration of the curing process depends on the temperature, and the 
heat must be applied gradually; 
 
 
for example, if the material is maintained at 160 C the curing process can 
take around 30 min, but if the temperature is increased up to 400 C it can 
takes just 2 min, therefore, at higher temperatures the process is faster.
 
 
 
 
 
 
 
 
I 
I 
 
   
 
 
 
 
10V 
400V 
 
 
 
   
 
   
 
 
 
 
 
 
 
 
 
 
 
 
 
47 
 
 
 
  Outer layer: Outer semi-conductor. The main function of this layer is to 
protect the insulation from the screen of the cable. The copper screening 
process is used for earthing the cabl
 
CONDUCTORS
 
 
Two situations are considered in the C.V. Line in order to put the insulation for 
the conductors: 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 1)To insulate each core or phase separately, and after that to collect all of 
them in the assembly machine; although previously making the copper 
screening operation. 
For MV the next conductor cross-sectional areas are considered: 50 mm2, 
70 mm2, 95 mm2, 120 mm2, 150 mm2, 185 mm2, 240 mm2, and 300 
mm2. 
Figure 34twister 
48 
 
 
 
 
2)  To insulate one single core or phase without collecting all of them later. 
 
For MV the next conductor cross-sectional areas are considered: 400 mm2, 
500 mm2, 630 mm2, 800 mm2, 1000 mm2, and 1200 mm2.
 For HV and EHV any scale can be considered.
The necessary thickness of the insulation comes with the Technical Data Sheet 
(TDS) provided by the Technical Department.
 
2.4.1Types of C.V. Lines
The main factor to decide which type of C.V. Line use is the curing process. 
During this operation, the cable can not touch any surface because of the high 
temperature applied, the insulation is not solid at that time, it is almost melted, 
therefore, if the insulation touches any part of the heating tubes there would 
appear faults in the insulation & it needs min. 16 hours to restart.
There are three possible types of C.V. Lines depending on the position of the 
cable
 
  vertical, 
  horizontal, and 
  catenaries. 
 
All these three systems allow the cable to be exactly placed in the center of 
the large tube. The vertical configuration is the best one, but it is very 
49 
 
 
 
expensive and it is also necessary to use a very high structure to contain the 
complete C.V. Line.
 
There is a problem with the catenaries configuration called "gravity sag effect", 
which is not observed in the vertical configuration. In normal conditions the 
high temperature of the insulation makes it going downwards and being 
accumulated in the lower part forming the called "sag". To solve this problem, 
the conductor does not begin in the center of the cable but in the bottom 
position, so when the insulation is hot, the correction is done automatically by 
the conductor going upwards being push by the insulation. This problem 
happens above all in 220 kV cables because the thickness of the insulation is 
larger. It is not a real problem for smaller insulation thicknesses.
Catenaries configuration can be made in different angles.
 
 
 
 
 
 
.
 
Catenaries C.V. Line
In general, the C.V. Line is the "same" machine as those ones seen in the L V 
Insulation Area, but with a different idea of operation. The insulation process 
carried out in this section can be summarized as follows, 
Figure 35shows gravite sag effect 
50 
 
 
 
  are two drums to carry out a nonstop process, one of them  There PAY OFF
is running and the other one is standing by until the first one finishes. At 
that moment, the connection between conductors is made by means of a 
join, as shown in Figure  the first layer of the two conductors is removed, 
the tube connecting the two parts is added, and finally hydraulic 
compression is applied to make the proper joint.
 
 
 
Figure 36 shows conductors joint
 
 
51 
 
 
 
ACCUMULATOR
The accumulator has two poleis that allow rounding the conductor between 
them  seven  times,  with  a  total  length  of  210  m,  with  a  distance  of  50  m 
between  poleis.  In  this  way,  the  conductor  is  running  above  the 
accumulator while doing the joint operation between conductors below the 
accumulator, and allowing in this way, a non stop process while changing 
drums in the pay off. While doing the joint operation, the left pulley moves 
to the right pulley allowing the accumulated cable to continue the process; 
once the joint is finished, the left pulley goes back again. In general, not all 
the  210  m  of  accumulated  cable  are  necessary,  for  example,  with  a  line 
speed  of  10  m/min,  20  min  are  necessary  to  finish  with  the  250  m  of 
accumulated  conductor,  so  it  means  20  min  are  necessary  to  carried  out 
the  joint  process,  but  in  general,  no  more  than  10  min  are  necessary, 
although  it  is  very  important  to  have  some  extra  time  for  possible 
unexpected problems.
CATERPILLARS
 
 
 
 
 
 
 
 
 
52 
 
 
 
 
There are a 3 caterpillars a long the C.V. line. Their main function is to pull 
the cable.
  PRE-HEATER
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
53 
 
 
 
.
 
 
It is not a fundamental 
machine for the process, 
however, it is considered to 
be as 
a very important accessory. It 
has two main uses:
 
a)  To allow the semi-conductor be correctly attached to the surface of the 
conductor.  The  inner  semi-conductor  is  hot  and  the  conductor  is 
cold,  so  those  differences  in  temperature  make  the  layer  of  material 
not to distribute properly along the conductor, There are two possible 
solutions:  To  decrease  the  line  speed  allowing  the  material  having 
more  time  to  be  attached  properly,  although  in  this  case  the 
production  can  decrease  considerably;  or  using  a  pre-heater,  and 
maintain the same speed. 
 
b)  The temperature of the cable after passing the cross head is not equally 
distributed, higher temperatures are closer to the surface of the outer 
semi-conductor,  while  the  coldest  ones  are  closer  to  the  surface  of 
the conductor, with those lower temperatures being not enough high 
to cure the XLPE. There are again two possible solutions:  
 
54 
 
 
 
c)  To  decrease  the  line  speed  to  allow  having  more  time  for  heating  and 
curing,  or  using  a  pre-heater  for  a  better  distribution  of  the 
temperature along the diameter of the cable, allowing the first layers 
of  the  insulation  receiving  heat  from  the  center  to  cure  properly  the 
XLPE, see Figure  
 
Figure 73 Inner semi -condudtor wrong attachment
 
 
 
 
 
 
 
 
Figure shows. Insulation. Distribution of temperature after the extrusion operation.
 
  TRIPLE HEAD
 
 
 
 
 
55 
 
 
 
It is also called Cross head. There are three extrusions machines to place 
the  insulation  of  the  cable:  One  for  injecting  the  inner  semi-conductor, 
another  one  for  the  insulation,  and  the  final  one  for  the  outer  semi-
conductor.  The  head  of  the  machine  is  triple  because  there  are  three 
extrusions, as shows in the Figure these three extruders. The temperature 
inside is around 120 C. The diameter of each one of the three layers placed 
from  each  of  the  extrusion  machines  is  controlled  by  an  x-ray  device 
(Sikora 8800 num. 1). The operation of injecting the insulation is the same 
as that one carried out with the insulation machines.
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
56 
 
 
 
TABLE OF MANUFACURING FIGURES 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
57 
 
 
 
 
 
 
 
 
 
 
 
58 
 
 
 
 
59 
 
 
 
ELECTRICAL TESTS
 
3.1 INTRODUCTION
Power cables can be divided into four categories depending on the voltage:
 
  Low Voltage, up to 1kV (included), 
  Medium Voltage, from 1 kV to 36 kV (included), 
  High Voltage, from 36 kV to 170 kV (included), 
  Extra High Voltage, from 170 kV to 500 kV (included). 
 
Transmission of energy is done at high voltages and low currents to decrease 
losses. Voltage is generated in a power station, an immediately is stepped up 
to higher voltages by means of a transformer. The transmission is made with 
overhead  lines  (OHTL).  The  voltage  then  is  step  down  with  a  transformer  to 
distribute the electricity, which is carried out at lower voltages and typically by 
means of underground cables (UGC).
 
Each  of  them,  OHTL  and  UGC,  has  advantages  and  disadvantages,  for 
example
 
  UGC are costly compared to OHTL. The cost of manufacturing a cable can 
be divided into two categories, fix and variable; fix cost is very high in UGC 
because it includes digging the site, the insulation of the cable, etc, while 
in  general  for  OHTL  the  installation  is  not  so  expensive;  variable  cost, 
60 
 
 
 
which  includes  basically  the  maintenance,  is  almost  zero  for  UGC,  but 
expensive  for  OHTL  because  on  the  one  hand  it  is  necessary  to  take  into 
account  the  atmospheric  pollution  or  humidity,  and  on  the  other  hand 
having a fault, for example due to birds, is much easier than in UGC. 
  Safety reasons. For example, it  is not possible to use OHTL inside a town 
or city, so it is necessary to install them preferably over large empty areas 
like deserts. 
  War areas. One of the first and main objectives to be destroyed are OHTL, 
with focus on cutting the electricity, whereas UGC are difficult to locate. 
 
The tests carried out in the Electrical Tests Facility are summarized. Only one 
mechanical test is made in this facility, the bending test. The rest of 
mechanical and chemical tests are carry out in the Quality Control Lab.
 
3.2 TESTS CLASSIFICATION
 
A cable is considered to be made of insulated cores, and each different core is 
made of a conductor with its insulation. The insulation is the most important 
electrical layer when manufacturing cables, although there are other ones like 
armoring or screening.
 
Tests  are  made  in  this  facility  to  verify  some  properties  of  conductors  and 
insulations, in order to carry out a preventive maintenance of the material.
 
Tests can be classified in the next way:
61 
 
 
 
  Destructive:  Just  one  test  is  made  over  a  sample,  which  finishes 
unuseful  after  ending  specific  test.  It  is  unthinkable  to  make  this  kind  of 
tests  over  the  entire  product.  Flame  retardant  test  is  just  one  example  of 
destructive tests. 
  Non  destructible:  It  is  done  over  the  entire  product,  which  does  not 
suffer or is damaged. Typical electrical and mechanical tests are considered 
here. 
Another type of classification can be done as follows:
 
  Sample  Tests:  A  sample  is  taken  from  each  different  part  of  the 
manufacturing  cable  process.  These  kinds  of  tests  begin  at  the  starting 
point  of  the  production.  If  the  product  passes  the  specific  test  then  it  can 
continue  to  the  next  stage  of  the  process.  The  goal  is  to  measure  if  the 
product in each step accomplishes the customer requirements. 
  Routine Tests: They are made upon 100 % of the product. These kind of 
tests always need to be done. 
  Type  Tests:  They  are  carried  out  just  in  special  cases:  When  a  new 
material  arrives,  when  new  machines  are  purchased,  or  when  a  new 
technology  or  design  is  introduced  in  the  process;  for  that  reason,  these 
tests  are  typically  called  "3M"  (Material,  Machine,  Method).  In  all  these 
situations,  it  is  necessary  to  compare  the  new  stuff  to  the  older  one  in 
order to see the benefits. These kinds of tests are made over samples. 
Two types of testing can be carried out depending on the material (sample or 
product)  properties:  Electrical,  and  mechanical.  In  fact  it  is  preferable  to  use 
62 
 
 
 
the  term  "physical"  properties  instead  of  mechanical,  because  the  chemical 
properties  are  also  included  under  this  one.  The  function  of  each  different 
cable makes the decision over what type of test need to be done, electrical or 
physical.  In  general,  the  function  of  power  cables  can  be  divided  in  three 
stages  depending  on  the  operation  voltage:  Generation,  transmission,  and 
distribution. For that reason, the most important parameters to be considered 
in low voltage cables are different to those ones with medium or high voltages. 
For example, the tensile strength is the most important property in OHTL, but 
not in UGC.
 
3.3 ELECTRICAL TESTS
   
3.1. Low voltage cables
 
Two main requirements need to be accomplished in order to get a proper 
voltage in buildings, factories, etc,
  voltage stability, which depends basically on the government, 
  specified current, which depends on the cable. 
It is very important to check two parameters with low voltage cables:
 
1)  Dielectric strength of the material (insulation) 
 
This test is carried out just one time, and no value is obtained, the result is 
just to know whether the cable passes or not the test.
63 
 
 
 
The test is made between conductors, and it is done in order to verify the 
capacitive effect of the insulation. Cables can be tested in two ways:
 
a)  If  there  is  a  three-phase  transformer  available,  it  will  allow  directly  to 
energize the three conductors of the cable (terminal one), maintaining 
open the conductors in terminal two, see Figure 1. 
 
 
 
 
 
 
 
 
 
Figure 1. Low voltage tests. Dielectric strength measurement.
 
b) if there is no three-phase transformer available (just single-phase), tests 
need to be carried out separately: Test made between conductor 1 
(positive terminal of the transformer) and conductors 2 + 3 (negative 
terminal of the transformer); test voltage depends on the operation 
voltage of the cable, Table 1 shows an example; the other two tests are 
made between conductor 2 (positive terminal of the transformer) and 
conductors 1 + 3 (negative terminal of the transformer), and between 
conductor 3 (positive terminal of the transformer) and conductors 1 + 2 
64 
 
 
 
(negative terminal of the transformer); metallic layers such as armoring 
or lead need to be also treated as a conductor in order to be tested.
 
 
TABLE 1  DIELECTRIC STRENGTH TEST.
 
Operation 
voltage
Standard Test voltage Test Duration
450 / 750 V IEC 60502 2.5 kV 5 min
600 / 1000 V IEC 60227 3.5 kV 5 min
 
2)  Electrical resistance of the conductor 
 
If the value of the resistance increases, there will be also an increment in 
the temperature of the cable, heating, and possibly over passing its melting 
point as a consequence, therefore damaging the insulation.
Following the IEC 60228 Standard, the DC resistance at 20 C is measured. 
A correction factor is used if the measurement is taken in other conditions 
of temperature.
The value of the resistance vary depending on the frequency of the current 
flowing, mainly due to skin effect and proximity effect. Skin effect is caused 
by the nonuniform distribution of the magnetic field caused by currents 
flowing within the conductor; as the frequency of the current increases, 
more current flows near the surface of the conductor, thus increasing the 
effective resistance. Proximity effect is due to external magnetic fields 
65 
 
 
 
generated from current in surrounding conductors. Skin effect dominates 
the losses up to a certain frequency, above which proximity effect also 
becomes apparent.
 
At 50 Hz, typical operation of cables: (i) value for resistance is quite close 
to its DC resistance value, (ii) both skin and proximitty efects can be 
neglected.
 
3.2. Medium voltage cables
 
Same two tests as those for low voltage, and a third one specific for medium 
voltage: Partial discharges.
 
The partial discharge effect is a kind of ionization, similar to that one observed 
with the corona effect. Since the insulation of a cable is not perfect, not totally 
solid, it is possible to find very small bubbles or voids of air inside it. Figure 2 
shows a layer of insulation, the voltage gradient from the conductor, and how 
these small voids can lead to a very small spark.
 
 
 
 
 
 
 
66 
 
 
 
 
 
Figure 2. Medium voltage tests. Partial discharges measurement.
 
There are two mediums, insulation material and air (void), which affect the 
creation of a discharge inside the void. These small discharges make the voids 
increase in size, and with time the insulation fails.
Continue voltage operation, especially areas with high temperature or 
overloads, makes the conductor to expand or contract. However, the 
insulation does not have this property, it suffers with expansions and 
contractions creating voids after some time, or expanding those existing ones.
The IEC Standard requires to verify the insulation and locate those voids that 
can be dangerous in the future.
If the cable has a screening layer made of copper tape, it needs necessary to 
verify the % of overlap.
3.3. High voltage cables
Same previous tests, and a fourth one specific for high voltages: Dielectric 
loss angle (DLA), also called "tan ".
Figure 3 shows the meaning of this angle. At those so high operation 
voltages, the insulation is not only described as a capacitive effect, but also 
as a resistive effect; Figure 3a shows both couplings between two cores; it is 
very important to notice that core 2 can be any metallic surface such as 
conductor, armoring, screening, or lead; Figures 3b and 3c show how this 
leakage current (I0) is divided in those two effects, resistive and capacitive.
67 
 
 
 
The ideal situation would be to have angle  = 0, which means not to have 
losses in the insulation.
 
 
 
 
 
Figure 3. High voltage tests. Dielectric loss angle measurement.
3.4. MECHANICAL TESTS
 
The only one mechanical test carried out in this facility is the bending test.
The test is made by coiling and uncoiling four times the cable around the 
drum.
This test allows knowing if
 
1)  the drum is appropriate, 
2)  the insulation separates from the conductor in some point, 
3)  new voids appear in the insulation. 
 
6. CONCLUSIONS
 
Tests can be classified in different ways. For example, one classification 
considers if the sample or product after testing is useful or not; these type of 
tests are called destructive or non destructible. Another classification 
considers if the test is done over a sample taken from each stage of the 
68 
 
 
 
manufacturing process, or done upon 100 % of the product, or done just in 
special occasions; these tests are called sample, routine and type, 
respectively.
The function of each different type of cable makes the decision over what type 
of tests need to be done, electrical or physical. The function of power cables 
can be divided in three stages depending on the operation voltage: 
Generation, transmission, and distribution.
 
Tests studied in this report appear in the next Standards: IEC 60270 (general), 
IEC 60502-1 (low voltage), IEC 60502-2 (medium voltage), IEC 60840 (high 
voltage), IEC 62067 (extra high voltage). Two different types of tests are 
carried out in this facility for low voltage cables: Dielectric strength of the 
insulation, and electrical resistance of the conductor. One more test is done 
for medium voltages: Partial discharges; if the cable has a screening layer 
made of copper tape, it needs necessary also to verify the % of overlap. One 
more test is done for high voltage cables: Dielectric loss angle. Only one 
mechanical test is carried out in this facility: Bending test.
In low voltage cables, see Table 1, the dielectric strength test can be done at 
3.5 kV for 5 minutes as routine test, or at 2.4 kV for 4 hours as type test. The 
measurement of the dielectric loss angle may be required for low voltage 
cables in some special situations, being classified then as type test. Standard 
IEC 60502-2 (page 47) give sequences of tests to be done, for example: 1) 
Partial discharges, 2) Bending, 3) Partial discharges, 4) Tan , etc.
Special tests for special situations (marine, petroleum, etc) can be carried out 
upon customer requiremen
69 
 
 
 
     IEC         
      
 
          
    mm  diameter of wire  d
w 
   mm  conductor diameter  d
c 
     mm  cable diameter after assembly  d
ass 
     mm  cable diameter after bedding  d
bed 
     mm  cable diameter after armouring  d
arm 
     ------  cable diameter after sheathing  d
sh 
     mm  cable diameter after insulaion  d
ins 
      mm  cable diameter after screen copper 
tape 
d
sc 
   mm  insulaion thickness  t 
   mm  filling thickness  t
fill 
   mm  bedding thickness  t
bed 
   ------  sheathing thickness  t
sh 
      ------  Sector copper cables  ------ 
    ------  Sector Aluminum Cables  ------ 
    ------  Round copper cables  ------ 
   ------  number of wires  No. 
   mm
2 
cross section Area  A 
  ------  coefficient  K 
   mm  stranding lay length  ------ 
   mm  Assembly lay length  ------ 
    gm  diameter ofter screen copper tape  W
sc 
   ------  main phase  m.ph 
   ------  neutral phase  n.ph 
 
DRAWING PROCESS:- 
70 
 
 
 
Sector copper cables 
 
d
w.m.ph.      
=   1.1281.1A/No.     =    mm 
d
w.n.ph.       
=   1.1281.05 A/No.   =    mm 
 
Sector Aluminum Cables 
 
d
w.m.ph.      
=   1.1281.06A/No.    =   mm 
d
w.n.ph.       
=   1.1281.03A/No.    =   mm 
 
Round copper cables 
 
d
w.m.ph.      
=   1.128 A/No.              =   mm 
d
w.n.ph.       
=   1.128  A/No.             =   mm 
 
Cu.annealing 
 
1.1  0.5 : 1.1  0.15 : 0.40  d
w
 (mm) 
35 %  30 %  20 %  elongation 
 
0.2 mm  0.5 : 0.2 mm  1 : 0.5 mm  >1 mm  d
w
 copper 
(+ - 0.004)  (+ - 0.006)  (+ - 0.01)  (+ - 1%)  tolerance 
 
< 2.5 mm  >2.5 mm  d
w
 Al(H12  H14  Alloy) 
(+ - 0.025 )  ( + - 1%)  Tolerance 
 
 
 
 
 
 
STRANDING PROCESS:- 
71 
 
 
 
d
c   
=   K   x   d
w
       =    mm 
 
61  37  19  7  No. 
9  7  5  3  K 
 
Stranding lay length for sector cables 
AL     =   28 : 30        x       d
ass             
=    mm 
CU     =   30 : 35        x       d
ass
        =    mm 
 
Stranding lay length for round cables 
 
=    18 : 20       x       d
ass
        =    mm 
ASSEMBLY PROCESS:- 
 
Diameter of Round cables         d
ass
 = K x d
c
  = mm 
 
Diameter of Sector cables  d
ass
 =1.31  A  +  5t  = mm 
 
ASSEMBLY lay length for Round cables   =  
18 :20        x      d
ass
   = mm 
 
ASSEMBLY lay length for Sector (AL) cables   =  
28 :30  x d
ass
   = mm 
 
ASSEMBLY lay length for Sector (CU)  cables   = 
 30 :35  x    d
ass
   = mm 
 
SCREENNING PROCESS:- 
d
sc
 = d
ins
 + 4 t
sc
 = mm 
 
w
sc
 = (2.8   x   d
c
) / (1  over lap %)    = gm / mt 
 
FILLING AND BEDDING PROCESS:- 
72 
 
 
 
 
t
fill
 = 0.02   x   d
ass
  + 0.6   =  mm 
 
t
bed
 = 0.02   x   d
ass
  + 0.6   =  mm 
 
Tolerance  Thickness  PROCESS 
(+ - 0.2)   mm  1 mm  FILLING 
( + - 0.2)  mm  1.2 mm  BEDDING 
 
 
ARMOURING PROCESS:- 
 
d
arm
 = d
bed
 + 4   x   t
arm  
= mm 
 
Armour Tape Steel or AL 
 
t
arm 
t
bed
 
To (mm)  From (mm) 
0.2 mm  30  -------- 
0.5 mm  70  30 
0.8 mm  -------  70 
 
Armour Wire AL or AL Alloy 
 
d
arm 
d
bed 
To (mm)  Form (mm) 
0.8 mm  15  ------ 
1.6 mm  25  15 
2.0 mm  35  25 
2.5 mm  60  35 
3.15 mm  -------  60 
 
SHEATHING PROCESS:- 
73 
 
 
 
 
t
sh
 =0.035   x   d
arm
 + 1 = mm 
 
d
sh
 = d
arm
 + 2   x   t
sh 
 = mm 
 
 
         3 x 120 + 70       
 
d
ass
 =1.31  A  +  5t                  
    = 1 . 31    3 X 120 +70 + 5 X 1 . 6 
    = 35 . 16 mm. 
 
t
bed
 = 0.02   x   d
ass
  + 0.6   =  mm 
                       
    = 0 . 02  X 35 . 16 + 0 . 6 
    = 1 . 3   mm 
 
d
bed
    = d
ass
 + 2 t
bed
                   
   
    = 35 . 16 + 2 X 1 . 3 
    = 37 . 77   mm 
 
t
arm
   = 0 . 5                      
 
 
d
arm
  = d
bed
 + 4 t
arm
                      
    = 37 . 77 + 4 X 0 . 5 
    = 39 . 77   mm 
     
 
d
sh
    = 0 . 035   d
arm
      + 1               
    = 0 . 035 X 39 . 77 + 1 
    = 2 . 39   mm 
d
sh
 = d
arm
 + 2   x   t
sh 
 = mm 
74 
 
 
 
                       
    = 39 . 77 + 2 X 2 . 39 
    = 44 . 55   mm 
 
 
 
Weight of Bedding                        
 
    =   0 . 785    (  dbed2      dass2  )  
    = 0 . 785 X 1 . 35  (  37 . 77  35 . 16  ) 
    = 20 kg 
Weight of Sheathing                       
 
    =   0 . 785     (  dsh2      darm2  )  
    = 0 . 785 X 1 . 53 X (  44 . 55  39 . 77  ) 
    = 480 kg 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
75 
 
 
 
REFERENCES 
TABLE OF FIG 
Figure 1:Department list tree ................................................................................................................ 1 
Figure 2 copper conductors ................................................................................................................... 5 
Figure 3 A.A.C ...................................................................................................................................... 5 
Figure 4:A.C.S.R................................................................................................................................... 5 
Figure 5:low voltage cable .................................................................................................................... 6 
Figure 6 :MV cable ............................................................................................................................... 6 
Figure 7 :HV cable ................................................................................................................................ 6 
Figure 8 :metal section .......................................................................................................................... 8 
Figure 9:Drawing machine block diagram ......................................................................................... 11 
Figure 10 Dies contruction.................................................................................................................. 11 
Figure 11drawing lubricata cooler ...................................................................................................... 13 
Figure 12Dancer diagram ................................................................................................................... 14 
Figure 13:formation of wires .............................................................................................................. 17 
Figure 14:Rotating cage ...................................................................................................................... 19 
Figure 15 Extrusion section ................................................................................................................ 21 
Figure 16: Insulation Machine block diagram .................................................................................... 23 
Figure 17:Extruaion method ............................................................................................................... 24 
Figure 18:tooling of head method ....................................................................................................... 25 
Figure 19:INdulation line .................................................................................................................... 25 
Figure 20:assembly machine block diagram....................................................................................... 30 
Figure 21pay off .................................................................................................................................. 31 
Figure 22Assembly block ................................................................................................................... 31 
Figure 23:taping and armoring............................................................................................................ 32 
Figure 24take up ................................................................................................................................. 32 
Figure 25assembly 3000 pay off ......................................................................................................... 33 
Figure 26assembly 3000 take up and pay off ..................................................................................... 33 
Figure 27 two tabes operation ............................................................................................................. 34 
Figure 28Assembly 1600 Machine ..................................................................................................... 35 
Figure 29Assembly hesd in Assmbly 1600 machine .......................................................................... 36 
Figure 30Armoring section ................................................................................................................. 36 
Figure 31screening operation .............................................................................................................. 40 
Figure   23 splice box ............................................................................................................................. 43 
Figure   22 show inner semi _coductor layer ......................................................................................... 44 
Figure 34twister .................................................................................................................................. 47 
Figure 35shows gravite sag effect....................................................................................................... 49 
Figure   23 shows conductors joint ........................................................................................................ 50 
Figure   23 Inner semi -condudtor wrong attachment ............................................................................ 54 
 
 REFERENCES 
ENERGYA CABLES