HEC Vol 1
HEC Vol 1
.
.
.
(4.2)
Where the variables are defined as for Equation 4.1. This equation is suggested here for
estimating local scour at the nose of a transverse structure projecting into the flow when the
conditions for Equation 4.1 are not met.
4.3.4 Scour at Longitudinal Structures
Variations in bed elevation during flow events or after bank hardening can result in the
undermining of bank protection structures including longitudinal structures. Therefore,
methods are needed for estimating maximum scour in order to design stable bank
protection. The following sections provide methods for estimating scour along longitudinal
countermeasures such as bulkheads and vertical walls.
Scour with Flow Parallel to a Vertical Wall. The probable mechanism causing scour along a
vertical wall when the flow is parallel to the wall is an increase in boundary shear stress
produced by locally increased velocity gradients that result from the reduced roughness of
the vertical wall, as compared to the natural channel. It is reasonable to conclude that this
scour will continue until the local flow area has increased enough to reduce the local velocity,
and hence the local boundary shear stress, to values typical of the rest of the channel cross
section (RCE 1994).
The magnitude of boundary shear stress around the perimeter of a channel is not constant.
In channels of uniform roughness, the boundary shear stress has a maximum value near the
channel centerline, and a secondary peak about one-third of the way up the sideslope. On
average, the maximum on the bottom is about 0.97 times the average boundary shear stress
(e.g., as defined by (RS) for the cross section and the maximum on the side is about 0.76
times the average boundary shear stress. However, experimental data indicate a range of
values, with maximum shear stresses as much as 1.6 times the average. In general, the
boundary shear stress distribution is more uniform as the width to depth ratio increases.
Similar information is not available for channel cross sections of nonuniform roughness;
however, reasonable conclusions can be drawn from intuitive arguments. For a straight
channel with a vertical wall with smoother roughness than the rest of the channel along one
side, the boundary shear stress distribution would be skewed towards the wall side of the
channel. The sideslope peak value would be larger and could possibly be greater than the
peak along the channel bed, which would also be shifted off the centerline location. These
effects would be more pronounced in narrow channels and/or channels with steep
sideslopes. As the channel gets wider, or the sideslope flattens, these effects would be
diminished.
Insight on the magnitude of these effects can be obtained by considering local velocity
conditions as determined by conveyance weighting concepts (see HEC-18 and HEC-20).
The analysis assumes that the boundary roughness within the channel can be divided into
4.8
two distinct regions: one region defining the roughness of the channel banks and the other
defining the roughness of the channel bottom (note that this division of roughness, while
logical, is not always analytically useful as it can create numerical problems leading to errors
in the computation of conveyance for the entire cross section).
For purposes of illustration, a wide, shallow natural channel has a uniform roughness with a
Manning's n value of 0.03, but with a concrete vertical wall the n value of the bank region
is reduced by a factor of two, to 0.015. Evaluation of the distribution of discharge by
conveyance weighting shows that this reduction of "n" nearly doubles the conveyance,
discharge, and velocity adjacent to the bank (i.e., next to the wall). Recognizing that
boundary shear stress is proportional to velocity squared, this increase in velocity increases
the boundary shear stress by a factor of 4.
Based on the experimental results for a uniform roughness channel, the maximum boundary
shear stress along the vertical wall could be as much as 3 times the average boundary shear
stress. However, this is not totally accurate given the simplistic assumptions made and the
likely changes in the distribution pattern that would result under conditions produced by a
vertical wall. Nonetheless, this simplified analysis suggests that significant increases in the
boundary shear stress are possible adjacent to the wall.
To apply this concept, it is appropriate to define a shear stress multiplier that can be applied
to the average boundary shear stress to define the locally increased boundary shear stress
adjacent to a vertical wall. Based on the above argument, a shear stress factor of 3 is
suggested. Recognizing that boundary shear stress is proportional to velocity squared, the
reduction in velocity necessary to lower the shear stress to an acceptable value is defined by
the inverse of the square root of the shear stress multiplier (0.577) for the shear stress factor
of 3. For the reduction in velocity to occur, the flow area must then be increased by the
inverse of this factor (1/0.577 = 1.73). For a vertical wall, this calculation simplifies to a unit
width basis and the scour depth is a multiplier of the average flow depth (0.73 y
1
).
It is important to understand that this provides a first approximation of the potential scour
along a vertical wall due to flow parallel to the wall. Using this relation, the total scour along
the wall due to parallel flow can be approximated as the sum of the above relation, which
results from a differential in shear stress, plus scour associated with the passage of
antidunes (see HDS 6). This results in the following relationship:
y
y
F
s
r
1
2
0 73 014 = + . .
(4.3)
where:
y
s
= Equilibrium depth of scour (measured from the mean bed level to the
bottom of the scour hole), ft (m)
y
1
= Average upstream flow depth in the main channel, ft (m)
F
r
= Upstream Froude Number
This equation is applicable only where parallel flow can be assured (e.g., vertical walls along
both banks).
Scour with Flow Impinging at an Angle on a Vertical Wall. When an obstruction such as an
abutment or vertical wall projects into the flow, the depth of scour at the nose or face of the
obstruction can be estimated from Equation 4.1. Considering the physical configuration of
the channels for which the data on which this relation is based, this can reasonably be
4.9
assumed to be the upper limit of the scour that could be expected for flow along a vertical
wall when the flow impinges on the wall at an approximately 90E angle. The total scour along
a vertical wall, thus, will vary as a proportion of that given by Equations 4.1 and 4.3.
Assuming that the relative significance of the two scour mechanisms is related to the change
in momentum associated with the change in flow direction from some angle 2 relative to the
wall, the two relations can be combined using a weighting factor based on the sine or cosine,
respectively, of the angle of the flow to the wall (0E to 90E). The resulting relationship is
given by (RCE 1994):
y
y
F Cos F Sin
s
r r
1
2 0 33
0 73 014 4 = + + ( . . )
.
(4.4)
where:
2
= Angle between the impinging flow direction and the vertical wall
Scour Along a Vertical Wall Relative to Unconstrained Valley Width. The potential scour that
could occur along a vertical wall due to changes in planform as the channel evolves can be
estimated by combining Equation 4.4 with the relationships for ideal meander geometry (see
HEC-20). Using these relationships, it can be shown that the maximum angle will vary from
zero, when the width of the valley is constrained to the width of the channel, to approximately
71E, when the unconstrained valley width is approximately 3.5 times the width of the
channel. These values are based on the assumption that the meander wavelength is 14
times the channel width. The resulting dimensionless scour depth as a function of the
unconstrained valley width is plotted in Figure 4.2 for a range of Froude Numbers (F
r
).
It is possible for the channel to impinge perpendicular to the wall due to local flow deflection
or other local factors. For this case, the angle of impingement is no longer related to the
valley width, and the maximum scour depth can best be estimated based strictly on Equation
4.1.
Figure 4.2. Scour along a vertical wall as a function of unconstrained valley width (RCE 1994).
4.10
In using Figure 4.2, it is important to recognize that the relationships are based on an
assumed ideal meander geometry and scour relationships that, while they are the best
available, are very approximate. Considering the extreme local variability that can occur in a
given stream and the approximate nature of the relationships upon which these results are
based, engineering judgment is critical in evaluating the reasonableness of the results for a
specific problem. In particular, the potential for flow deflection and its effect on the angle of
impingement on the wall should be considered and a conservatively large angle applied in
Equation 4.4. If there is any reasonable possibility of flow perpendicular to the wall, an angle
of 90E (thus, Equation 4.1) is recommended. When the results of this analysis are used to
design the burial depth for a vertical wall, a safety factor of at least 1 ft (0.3 m) should be
added to the predicted scour depth.
4.3.5 Scour at Protected Bendways
Deep sections at the toe of the outer bank of a bendway are the result of scour. High velocity
along the outer bank is caused by secondary currents and greater outer-bank depths, and
together with the resultant shear stress, produce scour and cause a difference between the
sediment load entering and exiting the outer-bank zone. Since secondary currents transport
sediment supplied, in large part, from outer bank erosion toward the inner bank of a bend,
hardening of the outer bank by longitudinal bank protection structures may cause the
channel cross section to narrow and deepen by preventing the recruitment of eroded outer
bank sediments.
Experience is usually the most reliable means of estimating scour depth when designing a
bank protection project for a particular stream. Lacking experience on a particular stream,
scour depths may be estimated using physically based analytical models or empirical
methods. Although scour-depth can be estimated analytically or empirically, empirical
methods were generally found to provide better agreement with observed data.
Maynord (1996) provides an empirical method for determining scour depths on a typical
bendway bank protection project. Although his studies are restricted to sand bed streams,
the Maynord method agrees reasonably well with the limited number of gravel-bed data
points obtained by Thorne and Abt (1993). Nonetheless, the techniques presented by
Maynord are restricted to meandering channels having naturally developed widths and
depths, and cannot be applied to channels that have been confined to widths significantly
less than a natural system.
Maynord's method of estimating scour depth is based on a regression analysis of 215 data
points. The scour data used in developing his equation were measured at high discharges
that were within the channel banks and had return intervals of 1-5 years. Maximum depth as
defined in his best-fit equation for scour depth estimation is a function of R
c
/W, width to
depth ratio, and mean depth as follows:
D
D
R
W
W
D
mxb
mnc
c
mnc
=
18 0 051 0 0084 . . .
(4.5)
where:
R
c
= Centerline radius of the bend, ft (m)
W = Width of the bend, ft (m)
D
mxb
= Maximum water depth in the bend, ft (m)
D
mnc
= Average water depth in the crossing upstream of the bend, ft (m)
4.11
The terms D
mxb
and D
mnc
are defined in Figure 4.3.
Figure 4.3. Definition sketch of width (W) and mean water depth (D
mnc
) at the crossing
upstream of the bend and maximum water depth in the bend (D
mxb
).
The applicability of Maynord's equation is limited to streams with R
c
/W from 1.5 to 10 and
W/D
mnc
from 20 to 125 because of the lack of data outside these ranges. He recommends
that for channels with R
c
/W <1.5 or width to depth ratios less than 20, the scour depth for
R
c
/W = 1.5 and W/D
mnc
= 20, respectively, be used.
In addition, Thorne and Abt (1993) suggest these methods are valid until there is significant
interaction between the main channel flow and overbank flow. Therefore, Maynord (1996)
recommends that application of these empirical methods to overbank flow conditions should
be limited to overbank depth less than 20% of main channel depth.
4.3.6 Hydraulic Stress on a Bendway
The ratio of bend radius of curvature to flow width provides insight into the force on the
meander bend margin, but this parameter does not include discharge. A quantitative
technique which considers a single-event discharge and an estimate of the radial stress on a
meander bend margin was developed to evaluate the performance of alternative streambank
erosion protection techniques for the U.S. Army Corps of Engineers, Vicksburg District
(WET 1990). This technique could also be used by highway engineers to evaluate
alternative channel instability countermeasures for a bridge located in a meander bend.
Begin (1981) defines radial stress as the centripetal force divided by the outer bank area.
The centripetal force is responsible for deflecting the flow around the bend and is equal to
the apparent reactive force of the flow on the bend. Based on this concept of centripetal
force, the equation for the radial stress (N
r
) of flow on a meander bend is:
r
b c
F
A
QV
Y R W
= =
+ ( / ) 2
(4.6)
4.12
where:
F
= Centripetal force, lbs, (N)
A
b
= Area of outer bank, ft
2
(m
2
)
D
= Fluid density, lbs/ft
3
(kg/m
3
)
Q = Discharge, ft
3
/s (m
3
/s)
V = Flow velocity, ft/s (m/s)
Y = Mean flow depth, ft (m)
R
c
= Radius of curvature, ft (m)
W
= Topwidth, ft (m)
Thus, the radial stress is defined as a force per unit area (lbs/ft
2
or N/m
2
). Although it is not
suggested that the radial stress is directly responsible for meander bend migration or failure
of bank protection countermeasures, Begin did show that the radial stress is related to
meander migration (Begin 1981). It is assumed that shear stress is related to radial stress
because of water surface superelevation and increased near-bank velocity gradients.
Field investigations and computation of radial stress on banklines for channels in the Yazoo
River basin in Mississippi clearly showed that rudimentary countermeasures, such as used-
tire revetment were generally unsuccessful in bends with even low to moderate radial stress
(WET 1990). The study also showed that stone structures including longitudinal stone dikes
and stone spurs performed well in reaches of high radial stress. Isolated failures of stone
structures did occur at locations with the highest radial stress. The 2-year storm discharge
was used in the computations for radial stress at these sites.
As an alternative, the increased shear force on the outside of bends can be calculated by
multiplying the bed shear stress
0
by a dimensionless bend coefficient K
b
. The sharper the
bend, the greater the shear stress imposed on the outer bank. The bend coefficient K
b
is
related to the ratio of the bend radius of curvature R
c
divided by the top width of the channel
T, as shown in Figure 4.4.
1
1.5
2
2 3 4 5 6 7 8 9 10 11 12
R
c
/T
B
e
n
d
C
o
e
f
f
i
c
i
e
n
t
K
b
=
b
/
0
K
b
= 2.0 for R
c
/T < 2
K
b
= 2.38 - 0.206(R
c
/T) + 0.0073(R
c
/T)
2
for 2 < R
c
/T < 10
K
b
= 1.05 for R
c
/T >10
Figure 4.4. Shear stress multiplier K
b
for bends (HEC-15, 2005).
5.1
CHAPTER 5
RIPRAP DESIGN, FILTERS, FAILURE MODES, AND ALTERNATIVES
5.1 OVERVIEW
Riprap consists of a layer or facing of rock, dumped or hand-placed on channel and
structure boundaries to limit the effects of erosion. It is the most common type of
countermeasure due to its general availability, ease of installation and relatively low cost.
Any successful riprap design must account for several possible modes of failure. These
include riprap particle erosion, substrate material erosion and mass failure. Riprap particle
erosion is minimized by sizing the riprap to withstand hydraulic and turbulence forces, but is
also affected by riprap slope, impact and abrasion, ice, waves and vandalism. Substrate
particle erosion occurs when the base material erodes and migrates through the riprap voids
causing the riprap to settle. Substrate particle erosion is limited by placing a granular or
geotextile filter between the riprap and the base material. Mass failure occurs when large
sections of the riprap and/or base material slide or slump due to gravity forces. Mass failure
can be caused by excess pore water pressures, bank steepness and loss of basal support
through scour or channel migration. Also, a filter fabric that is too fine can clog and cause
the buildup of pore water pressures in the underlying soil.
Riprap that is large enough to resist all the hydraulic forces can fail if channel migration or
scour undermines the toe support. When the riprap toe is undermined it can shift and remain
functional to some degree. Often an extra volume of riprap is included at the toe for this
purpose, or the riprap toe is trenched to the depth of potential degradation and contraction
scour.
Graded riprap is more stable than uniform riprap because the range of sizes helps the riprap
layer to interlock. Care must be taken during construction to ensure that the graded rocks
are uniformly distributed. If large rocks roll to the base of the bank and the smaller rocks
accumulate at the top, the benefits of using graded riprap will be lost. Also, a relatively
uniform riprap surface will be more stable than an extremely uneven riprap surface.
Riprap design requires hydraulic, scour, and stream instability analyses as well as
geotechnical investigations of channel and bank stability. Pier riprap can fail if contraction
scour or channel bed degradation causes the stones to launch and roll away from the pier,
or on rivers with mobile bed forms, by bedform undermining. Abutment riprap can fail if
channel migration undermines the toe support of the rock. Channel bank riprap can fail if
excess pore pressures or toe scour produce a mechanically unstable bank. These failures
could occur even if the riprap size was appropriate for the particular application.
In summary, design of a riprap erosion control system requires knowledge of: river bed,
bank, and foundation material; flow conditions including velocity, depth and orientation;
riprap characteristics of size, density, durability, and availability; location, orientation and
dimensions of piers, abutments, guide banks, and spurs; and the type of interface material
between riprap and underlying foundation which may be geotextile fabric or a filter of sand
and/or gravel. Adequate "toe down" and termination details are essential to the performance
of the riprap system. Thus, riprap should be considered an integrated system where
successful performance of a riprap installation depends on the response of each component
of the system to hydraulic and environmental stresses throughout its service life.
5.2
5.2 RIPRAP DESIGN
5.2.1 Introduction
Most of the guidelines and recommendations of this chapter are derived from NCHRP
Report 568, "Riprap Design Criteria, Recommended Specifications, and Quality Control," the
final report for NCHRP Project 24-23 (Lagasse et al. 2006). The basic objectives of this
study were to develop design guidelines, material specifications and test methods,
construction specifications, and construction, inspection and quality control guidelines for
riprap for a range of applications, including: revetment on streams and riverbanks, bridge
piers and abutments, and bridge scour countermeasures such as guide banks and spurs.
NCHRP Project 24-23 was a synthesis study and did not involve any original laboratory
experimental work, but some analytical work (specifically 1- and 2-dimensional computer
modeling) was necessary to address issues related to input hydraulic variables for design.
Additional guidance for riprap at bridge piers is based on results of the NCHRP Project 24-
07(2) provided in NCHRP Report 593, "Countermeasures to Protect Bridge Piers from
Scour" (Lagasse et al. 2007). This study involved extensive laboratory testing at Colorado
State University of a range of bridge pier scour countermeasures, including: riprap, partially
grouted riprap, articulating concrete blocks, gabion mattresses, and grout-filled mattresses.
NCHRP Report 593 includes detailed, stand-alone guidelines for the design of these five pier
scour countermeasure alternatives.
Sizing the stone is only the first step in the comprehensive design, production, installation,
inspection, and maintenance process required for a successful riprap armoring system.
Filter requirements, material and testing specifications, construction and installation
guidelines, and inspection and quality control procedures are also necessary. This section
recommends riprap design approaches for a range of riprap applications. Riprap design
(sizing) is covered in more detail in application-specific design guidelines in Volume 2.
Subsequent sections provide an overview of filter design requirements and
recommendations for specification, testing, and quality control for revetment riprap
installations. In general, these recommendations are applicable to riprap for other
applications such as at bridge piers and abutments, and for countermeasures such as spurs
and guide banks.
Generalized construction/installation guidance is also summarized in this chapter. Failure
modes for revetment and bridge pier riprap are described to underscore the integrated
nature of riprap armoring systems and as a basis for developing inspection and maintenance
guidance. Finally, an overview of concrete armor units (artificial riprap) that could be used in
lieu of rock for selected applications is provided.
5.2.2 Riprap Revetment
Based on a screening of the many riprap revetment design equations found in the literature,
seven equations were evaluated with sensitivity analyses using both field and laboratory data
during NCHRP Project 24-23 (Lagasse et al. 2006). One, the U.S. Army Corps of Engineers
EM 1601, was recommended for streambank revetment design (USACE 1991). Factors
considered were the ability of the basic equation to discriminate between stable and failed
riprap using field and laboratory data, bank and bend correction factors, and the
reasonableness of safety/stability factors. Detailed design guidance using the EM 1601
equation is provided in Volume 2, Design Guideline 4. A standard riprap gradation
specification which considers design, production, and installation requirements is
recommended in Design Guideline 4, together with a standardized riprap size classification
system. Installation guidance for toe down and transitions is also provided for the revetment
5.3
application. General riprap specifications, testing, and quality control guidance can be found
in Design Guideline 4.
5.2.3 Riprap for Bridge Piers
According to Hoffmans and Verheij (1997) riprap can be sized using either the Isbash or
Shields stability criteria if turbulence intensity is incorporated into the velocity component.
The effect of turbulence is to increase instantaneous velocities well above the levels for
unobstructed flow. This concept is particularly applicable to the pier riprap equations.
The standard Isbash (1936) formula for sizing riprap on a channel bed is:
)) 1 S ( g 2 (
) KV ( 692 . 0
D
s
2
50
= (5.1)
where:
D
50
= Riprap size, ft (m)
V = Velocity, ft/s (m/s)
S
s
= Specific gravity of the riprap (usually 2.65)
K = 1.0
To incorporate the effects of turbulence intensity, Hoffmans and Verheij (1997) recommend
that the value of K be adjusted above a value of 1.0. In the specific case of circular piers,
they recommend using the local velocity upstream of the pier and values of K up to 2.0. This
amount of adjustment is equivalent to increasing shear stress by a factor of four.
This approach is similar to the equations presented in Design Guideline 8 and in the riprap
sizing formula presented by Parola (1993). The only difference is the recommended values
of K in the design guideline are 1.5 for circular piers and 1.7 for square piers. The
recommended values of K by Parola ranged from 1.44 to 1.90 depending on pier and footing
geometry and approach flow angle of attack.
After a preliminary screening during NCHRP Project 24-23, the HEC-23 (Second Edition)
equation, which was derived from work by Parola and Jones, was compared to several other
equations using three laboratory data sets. Based on this sensitivity analysis, it was
concluded that the HEC-23 and Parola equations provide the best balance between the
objective of rarely (if ever) undersizing bridge pier riprap and the desire to not be overly
conservative. As these equations are very similar, the HEC-23 (Second Edition) equation
was recommended for design practice.
The laboratory results and design recommendations from a concurrent study of
countermeasures to protect bridge piers from scour (NCHRP 24-07(2)) were evaluated
regarding filter requirements, riprap extent, and other construction/ installation guidelines for
pier riprap (Lagasse et al. 2007). Specifically, guidelines for the use of sand-filled geotextile
containers as a means of placing a filter for pier riprap derived from European practice were
investigated. Construction and installation guidelines and constructability issues were also
addressed. The findings and recommendations from NCHRP Projects 24-23 and 24-07(2)
are combined in Volume 2, Design Guideline 11 to provide comprehensive design guidance
for bridge pier riprap.
5.4
5.2.4 Riprap for Bridge Abutments
For NCHRP 24-23, only the abutment riprap sizing approach as developed by FHWA
(Pagn-Ortiz 1991, Atayee 1993) and presented in HEC-23 (Second Edition) was considered
to be a candidate for further investigation. The approach consists of two equations, one for
Froude numbers less than 0.8 and the other for higher Froude numbers. There are no field
data available to test these equations and the only available laboratory data set was used to
develop the equations. The FHWA equations rely on an estimated velocity, known as the
characteristic average velocity, at the abutment toe. Rather than evaluating these equations
using the same laboratory data set used to develop them, the method for estimating the
velocity at the abutment was investigated in detail. Two-dimensional modeling was
performed to evaluate the flow field around an abutment and to verify or improve the Set
Back Ratio (SBR) method for estimating velocity for the design equations. Results of the
modeling indicated that if the estimated velocity does not exceed the maximum velocity in
the channel, the SBR method is well suited for determining velocity at an abutment as a
basis for riprap design.
The findings and recommendations from NCHRP Project 24-23 (Lagasse et al. 2006) and
NCHRP Project 24-18 (Barkdoll et al. 2007) are presented in Volume 2, Design Guideline 14
for the sizing, filter, and layout of abutment riprap installations. Material and testing
specifications, construction and installation guidelines, and inspection and quality control for
revetment riprap are suitable for abutment riprap (see Section 5.5 and Design Guideline 4).
5.2.5 Riprap Protection for Countermeasures
In general, design guidelines and specifications for riprap to protect countermeasures are
similar to those for bankline revetment or abutments. Consequently, recommendations for
revetment riprap can be adapted to the countermeasure application. Guidance for sizing
and placing riprap at zones of high stress on countermeasures (e.g., the nose of a guide
bank or spur) was developed during NCHRP Project 24-23 (Lagasse et al. 2006). The
feasibility of using an abutment-related characteristic average velocity for countermeasure
riprap sizing was also evaluated, and a recommendation on an adjustment to the
characteristic average velocity approach for guide bank riprap design was developed.
Guidance from the U.S. Army Corps of Engineers (EM 1601) can be used for sizing riprap
for spurs (USACE 1991). The findings and recommendations from NCHRP Project 24-23
are the basis for design guidance for sizing riprap for spurs in Design Guideline 2 and for
guide banks in Design Guideline 15.
NCHRP 24-23 also investigated methods for sizing riprap under overtopping conditions on
roadway embankments and the embankment portion of countermeasures. The
recommended methodology, based on laboratory testing at Colorado State University, is
presented in Design Guideline 5.
5.2.6 Riprap for Special Applications
Environments subject to wave attack frequently require some type of protection to ensure
the stability of highway and/or bridge infrastructure. Design Guideline 17 provides
information on wave characteristics and procedures for designing rock riprap as protection
against wave attack.
5.5
Bottomless (or three-sided) culverts are structures that have natural channel materials as the
bottom. These structures may be rectangular in shape or may have a more rounded top.
They are typically founded on spread footings and can be highly susceptible to scour.
Recent laboratory studies by FHWA (Kerenyi 2003, 2007) show that scour is greatest at the
upstream corners of the culvert entrance. Based on these studies and other guidance
(MDSHA 2005), Design Guideline 18 presents riprap sizing, filter, and layout details to
protect against scour at bottomless culverts.
5.2.7 Termination Details
Undermining of the edges of armoring countermeasures like riprap is one of the primary
mechanisms of failure (see Section 5.4). The edges of the armoring material (head, toe, and
flanks) should be designed so that undermining will not occur. For channel bed armoring,
this is accomplished by keying the edges into the subgrade to a depth which extends below
the combined expected contraction scour and long-term degradation depth. For side slope
protection, this is achieved by trenching the toe of the revetment below the channel bed to a
depth which extends below the combined expected contraction scour and long-term
degradation depth. When excavation to the contraction scour and degradation depth is
impractical, a launching apron can be used to provide enough volume of rock to launch into
the channel while maintaining sufficient protection of the exposed portion of the bank.
Additional guidelines on edge treatment for riprap countermeasures can be found in Design
Guidelines 4, 11, and 14.
5.2.8 Riprap Size, Shape, and Gradation
Riprap design methods typically yield a required size of stone that will result in stable
performance under the design loadings. Because stone is produced and delivered in a
range of sizes and shapes, the required size of stone is often stated in terms of a minimum
allowable representative size. For example, the designer may specify a minimum d
50
or d
30
for the rock comprising the riprap, thus indicating the size for which 50% or 30% (by weight)
of the particles are smaller. Stone sizes can also be specified in terms of weight (e.g., W
50
or W
30
) using an accepted relationship between size and volume, and the known (or
assumed) density of the particle.
Shape: The shape of a stone can be generally described by designating three axes of
measurement: Major, intermediate, and minor, also known as the "A, B, and C" axes, as
shown in Figure 5.1.
Figure 5.1. Riprap shape described by three axes.
5.6
Riprap stones should not be thin and platy, nor should they be long and needle-like.
Therefore, specifying a maximum allowable value for the ratio A/C, also known as the shape
factor, provides a suitable measure of particle shape, since the B axis is intermediate
between the two extremes of length A and thickness C. A maximum allowable value of 3.0
is recommended:
0 . 3
C
A
(5.2)
For riprap applications, stones tending toward subangular to angular are preferred, due to
the higher degree of interlocking, hence greater stability, compared to rounded particles of
the same weight.
Density: A measure of density of natural rock is the specific gravity S
g
, which is the ratio of
the density of a single (solid) rock particle
s
to the density of water
w
:
w
s
g
S
=
(5.3)
Typically, a minimum allowable specific gravity of 2.5 is required for riprap applications.
Where quarry sources uniformly produce rock with a specific gravity significantly greater
than 2.5 (such as dolomite, S
g
= 2.7 to 2.8), the equivalent stone size can be substantially
reduced and still achieve the same particle weight gradation.
Size and weight: Based on field studies, the recommended relationship between size and
weight is given by:
) d ( 85 . 0 W
3
s
=
(5.4)
where: W = Weight of stone, lb (kg)
s
= Density of stone, lb/ft
3
(kg/m
3
)
d = Size of intermediate ("B") axis, ft (m)
Table 5.1 provides recommended gradations for ten standard classes of riprap based on the
median particle diameter d
50
as determined by the dimension of the intermediate ("B") axis.
These gradations were developed under NCHRP Project 24-23, "Riprap Design Criteria,
Recommended Specifications, and Quality Control" (Lagasse et al. 2006). The proposed
gradation criteria are based on a nominal or "target" d
50
and a uniformity ratio d
85
/d
15
that
results in riprap that is well graded. The target uniformity ratio d
85
/d
15
is 2.0 and the allowable
range is from 1.5 to 2.5.
To specify riprap using the standard classes shown in Table 5.1, the "next larger size"
approach should be adopted. For example, if a riprap sizing calculation results in a required
d
50
of 16.8 inches, Class V riprap should be specified because it has a nominal d
50
of 18
inches.
Based on Equation 5.4, which assumes the volume of the stone is 85% of a cube, Table 5.2
provides the equivalent particle weights for the same ten classes, using a specific gravity of
2.65 for the particle density.
5.7
Table 5.1. Minimum and Maximum Allowable Particle Size in Inches.
Nominal Riprap Class
by Median Particle
Diameter
d
15
d
50
d
85
d
100
Class Size Min Max Min Max Min Max Max
I 6 in 3.7 5.2 5.7 6.9 7.8 9.2 12.0
II 9 in 5.5 7.8 8.5 10.5 11.5 14.0 18.0
III 12 in 7.3 10.5 11.5 14.0 15.5 18.5 24.0
IV 15 in 9.2 13.0 14.5 17.5 19.5 23.0 30.0
V 18 in 11.0 15.5 17.0 20.5 23.5 27.5 36.0
VI 21 in 13.0 18.5 20.0 24.0 27.5 32.5 42.0
VII 24 in 14.5 21.0 23.0 27.5 31.0 37.0 48.0
VIII 30 in 18.5 26.0 28.5 34.5 39.0 46.0 60.0
IX 36 in 22.0 31.5 34.0 41.5 47.0 55.5 72.0
X 42 in 25.5 36.5 40.0 48.5 54.5 64.5 84.0
Note: Particle size d corresponds to the intermediate ("B") axis of the particle.
Table 5.2. Minimum and Maximum Allowable Particle Weight in Pounds.
Nominal Riprap
Class by Median
Particle Weight
W
15
W
50
W
85
W
100
Class Weight Min Max Min Max Min Max Max
I 20 lb 4 12 15 27 39 64 140
II 60 lb 13 39 51 90 130 220 470
III 150 lb 32 93 120 210 310 510 1100
IV 300 lb 62 180 240 420 600 1000 2200
V 1/4 ton 110 310 410 720 1050 1750 3800
VI 3/8 ton 170 500 650 1150 1650 2800 6000
VII 1/2 ton 260 740 950 1700 2500 4100 9000
VIII 1 ton 500 1450 1900 3300 4800 8000 17600
IX 2 ton 860 2500 3300 5800 8300 13900 30400
X 3 ton 1350 4000 5200 9200 13200 22000 48200
Note: Weight limits for each class are estimated from particle size by: W = 0.85(sd
3
) where d corresponds to
the intermediate ("B") axis of the particle, and particle specific gravity is taken as 2.65.
5.3 FILTER REQUIREMENTS
5.3.1 Overview
The importance of the filter component of a countermeasure for stream instability or bridge
scour installation should not be underestimated. Filters are essential to the successful long-
term performance of countermeasures, especially armoring countermeasures. There are two
basic types of filters: granular filters and geotextile filters. Some situations call for a
composite filter consisting of both a granular layer and a geotextile. The specific
characteristics of the base soil determine the design considerations for the filter layer. In
general, where dune-type bedforms may be present during flood events, it is strongly
recommended that only a geotextile filter be considered for use with
countermeasures.
5.8
The filter must retain the coarser particles of the subgrade while remaining permeable
enough to allow infiltration and exfiltration to occur freely. It is not necessary to retain all the
particle sizes in the subgrade; in fact, it is beneficial to allow the smaller particles to pass
through the filter, leaving a coarser substrate behind. The filter prevents excessive migration
of the base soil particles through the voids in the armor layer, permits relief of hydrostatic
pressure beneath the armor, and distributes the weight of the armor to provide more uniform
settlement.
Guidance for the design of both granular and geotextile filters is provided in National
Cooperative Highway Research Program (NCHRP) Report 568, "Riprap Design Criteria,
Recommended Specifications, and Quality Control" (Lagasse et al. 2006), and is found in
Volume 2 as Design Guide 16. When using a granular filter, the layer should have a
minimum thickness of 4 times the d
50
of the filter stone or 6 inches, whichever is greater.
When placement must occur under water, the layer thickness should be increased by 50%.
In flowing water, the placement of both granular and geotextile filters becomes challenging.
Under these conditions, special materials and placement techniques have been developed
to ensure that a quality filter installation is achieved, as discussed in the next section.
5.3.2 Placing Geotextiles Under Water
Placing geotextiles under water is problematic for a number of reasons. Most geotextiles
that are used as filters beneath riprap are made of polyethylene or polypropylene. These
materials have specific gravities ranging from 0.90 to 0.96, meaning that they will float
unless weighted down or otherwise anchored to the subgrade prior to placement of the
armor layer (Koerner 1998). In addition, unless the work area is isolated from river currents
by a cofferdam, flow velocities greater than about 1.0 ft/s (0.3 m/s) create large forces on the
geotextile. These forces cause the geotextile to act like a sail, often resulting in wavelike
undulations of the fabric (a condition that contractors refer to as "galloping") that are
extremely difficult to control. In mild currents, geotextiles (precut to length) have been placed
using a roller assembly, with sandbags to hold the fabric temporarily.
To overcome these problems, engineers in Germany have developed a product known as
SandMat
TM
. This blanket-like product consists of two nonwoven needle-punched geotextiles
(or a woven and a nonwoven) with sand in between. The layers are stitch-bonded or sewn
together to form a heavy, filtering geocomposite. The composite blanket exhibits an overall
specific gravity ranging from approximately 1.5 to 2.0, so it sinks readily.
According to Heibaum (2002), this composite geotextile has sufficient stability to be handled
even when loaded by currents up to approximately 3.3 ft/s (1 m/s). At the geotextile base
soil interface, a nonwoven fabric should be used because of the higher angle of friction
compared to woven geotextiles. Figure 5.2 shows a close-up photo of the SandMat
TM
material. Figure 5.3 shows the SandMat
TM
blanket being rolled out using conventional
geotextile placement equipment.
In deep water or in currents greater than 3.3 ft/s (1 m/s), German practice calls for the use of
sand-filled geotextile containers. For specific project conditions, geotextile containers can be
chosen that combine the resistance against hydraulic loads with the filtration capacity
demanded by the application. Geotextile containers have proven to give sufficient stability
against erosive forces in many applications, including wave-attack environments. The size
of the geotextile container must be chosen such that the expected hydraulic load will not
transport the container during placement (Heibaum 2002). Once placed, the geotextile
containers are overlaid with the final armoring material (e.g., riprap or partially grouted
riprap) as shown in Figure 5.4.
5.9
Figure 5.2. Close-up photo of SandMat
TM
geocomposite blanket.
(photo from NCHRP Project 24-07(2), courtesy Colcrete Von Essen Inc.)
Figure 5.3. SandMat
TM
geocomposite blanket being unrolled.
(photo from NCHRP Project 24-07(2), courtesy Colcrete Von Essen Inc.)
5.10
FLOW
Geotextile containers
filled with sand
Rock riprap placed
flush with channel bed
Pier
FLOW
Geotextile containers
filled with sand
Rock riprap placed
flush with channel bed
Pier
Figure 5.4. Sand-filled geotextile containers.
Figure 5.5 shows a geotextile container being filled with sand. Figure 5.6 shows the sand-
filled geotextile container being handled with an articulated-arm clam grapple. The filled
geotextile container in the photograph is a nominal 1-metric-tonne (1,000 kg or 2,200 lb) unit.
The preferred geotextile for these applications is always a non-woven needle punched fabric,
with a minimum mass per unit area of 500 grams per square meter. Smaller geotextile
containers can be fabricated and handled by one or two people for smaller-sized
applications.
As a practical minimum, a 200-lb (91 kg) geotextile container covering a surface area of
about 6 to 8 square ft (0.56 to 0.74 m
2
) can be fashioned from nonwoven needle punched
geotextile having a minimum mass per unit area of 200 grams per square meter, filled at the
job site and field-stitched with a hand-held machine. Figure 5.7 illustrates the smaller
geotextile containers being installed at a prototype-scale test installation for NCHRP Project
24-07(2) (Lagasse et al. 2007) in a pier scour countermeasure application (see also Design
Guidelines 11 and 12, Volume 2).
5.4 RIPRAP FAILURE MODES
As discussed in Section 5.1, riprap can be considered an integrated system for which
successful performance of a riprap installation depends on the response of each component
of the system to hydraulic and environmental stresses throughout its service life. This
section provides an overview of failure modes for revetment and bridge pier riprap to
underscore the integrated nature of riprap armoring systems and support development of
inspection guidance.
5.11
Figure 5.5. Filling 1.0 metric tonne geotextile container with sand.
(photo from NCHRP Project 24-07(2), courtesy Colcrete Von Essen Inc.)
Figure 5.6. Handling a 1.0 metric tonne sand-filled geotextile container.
(photo from NCHRP Project 24-07(2), courtesy Colcrete Von Essen Inc.)
5.12
Demonstrating puncture resistance of
geotextile containers
Placing geotextile containers with small
front-end loader into scour hole at pier
Figure 5.7. Two hundred lb (91 kg) sand-filled geotextile containers,
NCHRP Project 24-07(2).
5.4.1 Riprap Revetment Failure Modes
In a preliminary evaluation of various riprap design techniques, Blodgett and McConaughy
(1986) concluded that a major shortcoming of all present design techniques is the assumption
that failures of riprap revetment are due only to particle erosion. Procedures for the design of
riprap protection need to consider all the various causes of failures which include: (1) particle
erosion; (2) translational slide; (3) modified slump; and (4) slump.
Particle erosion is the most commonly considered erosion mechanism (Figure 5.8). Particle
erosion occurs when individual particles are dislodged by the hydraulic forces generated by the
flowing water. Particle erosion can be initiated by abrasion, impingement of flowing water,
eddy action/reverse flow, local flow acceleration, freeze/thaw action, ice, or toe erosion.
Probable causes of particle erosion include: (1) stone size not large enough; (2) individual
stones removed by impact or abrasion; (3) side slope of the bank so steep that the angle of
repose of the riprap material is easily exceeded; and (4) gradation of riprap too uniform. Figure
5.9 provides a photograph of a riprap failure due to particle displacement.
Figure 5.8. Riprap failure by particle erosion (Blodgett and McConaughy 1986).
5.13
Figure 5.9. Damaged riprap on left bank of Pinole Creek at Pinole, CA, following flood of
January 4, 1982. Note deposition of displaced riprap from upstream locations
in channel bed (photographed March 1982) (Blodgett & McConaughy 1986).
A translational slide is a failure of riprap caused by the downslope movement of a mass of
stones, with the fault line on a horizontal plane (Figure 5.10). The initial phases of a
translational slide are indicated by cracks in the upper part of the riprap bank that extend
parallel to the channel. This type of riprap failure is usually initiated when the channel bed
scours and undermines the toe of the riprap blanket. This could be caused by particle
erosion of the toe material, or some other mechanism which causes displacement of toe
material. Any other mechanism which would cause the shear resistance along the interface
between the riprap blanket and base material to be reduced to less than the gravitational
force could also cause a translational slide. Probable causes of translational slides are as
follows: (1) bank side slope too steep; (2) presence of excess hydrostatic (pore) pressure;
and (3) loss of foundation support at the toe of the riprap blanket caused by erosion of the
lower part of the riprap blanket. Figure 5.11 provides a photograph of a riprap failure due to
a translational sliding-type failure.
Modified slump failure of riprap (Figure 5.12) is the mass movement of material along an
internal slip surface within the riprap blanket. The base soil underlying the riprap does not
fail. This type of failure is similar in many respects to the translational slide, but the geometry
of the damaged riprap is similar in shape to initial stages of failure caused by particle
erosion. Probable causes of modified slump are: (1) bank side slope is so steep that the
riprap is resting very near the angle of repose, and any imbalance or movement of individual
stones creates a situation of instability for other stones in the blanket; and (2) material critical
to the support of upslope riprap is dislodged by settlement of the submerged riprap, impact,
abrasion, particle erosion, or some other cause. Figure 5.13 provides a photograph of a
riprap failure due to a modified slump-type failure.
5.14
Figure 5.10 . Riprap failure by translational slide (Blodgett and McConaughy 1986).
Figure 5.11. Riprap on Cosumnes River at Site 2 near Sloughhouse, CA, looking
downstream, showing translational slide failure (photographed May 31,
1983) (Blodgett & McConaughy 1986).
5.15
Figure 5.12. Riprap failure by modified slump (Blodgett and McConaughy 1986).
Figure 5.13. Riprap on Consumnes River at Site 3 near Sloughhouse, CA, looking
downstream, showing modified slump failure (photographed May 31,
1983) (Blodgett & McConaughy 1986).
Slump failure is a rotational-gravitational movement of material along a surface of rupture
that has a concave upward curve (Figure 5.14). The cause of slump failures is related to
shear failure of the underlying base soil that supports the riprap. The primary feature of a
slump failure is the localized displacement of base material along a slip surface, which is
usually caused by excess pore pressure that reduces friction along a fault line in the base
material. Probable causes of slump failures are: (1) non-homogeneous base material with
layers of impermeable material that act as a fault line when subject to excess pore pressure;
(2) side slopes too steep and gravitational forces exceeding the inertia forces of the riprap
and base material along a friction plane; and (3) too much overburden at the top of the slope
(may be caused in part by the riprap). Figure 5.15 provides a photograph of a riprap failure
due to a slump-type failure.
5.16
Figure 5.14. Riprap failure due to slump (Blodgett and McConaughy 1986).
Figure 5.15. Riprap on left bank Cosumnes River at Site 1 near Sloughhouse, CA,
showing slump failure (photographed May 31, 1983) (Blodgett &
McConaughy 1986).
Summary: Blodgett and McConaughy (1986) conclude that certain hydraulic factors are
associated with each of the four types of riprap failure (particle erosion, translational slide,
modified slump, and true slump). While the specific mechanism causing failure of the riprap
is difficult to determine, and a number of factors, acting either individually or combined, may
be involved, they identify the reasons for riprap failures as:
1. Particle size was too small because:
Shear stress was underestimated
Velocity was underestimated
Inadequate allowance was made for channel curvature
Design channel capacity was too low
Design discharge was too low
Inadequate assessment was made of abrasive forces
Inadequate allowance was made for effect of obstructions
5.17
2. Channel changes caused:
Impinging flow
Flow to be directed at ends of protected reach
Decreased channel capacity or increased depth
Scour
3. Riprap material had improper gradation
4. Material was placed improperly
5. Side slopes were too steep
6. No filter blanket was installed or blanket was inadequate or damaged
7. Excess pore pressure caused failure of base material or toe of riprap
8. Differential settlement occurred during submergence or periods of excessive precipitation
5.4.2 Pier Riprap Failure Modes
A study of the causes of riprap failure at model bridge piers (Chiew 1995) under clear-water
conditions with gradually increasing approach flow velocities defined three modes of pier
riprap failure:
1. Riprap shear failure whereby the riprap stones cannot withstand the downflow and
horseshoe vortex associated with the pier scour mechanism.
2. Winnowing failure whereby the underlying finer bed material is removed through voids
or interstices in the riprap layer.
3. Edge failure whereby instability at the edge of the coarse riprap layer and the bed
sediment initiates a scour hole beginning at the perimeter and working inward that
ultimately destabilizes the entire layer.
Since live-bed conditions are more likely to occur during flood flows, additional experiments
were conducted to evaluate the stability of pier riprap under live-bed conditions with
migrating bed forms (Lim and Chiew 1996). These experiments and subsequent research
Melville et al. (1997), Lauchlan (1999), and Lauchlan and Melville (2001) indicates that bed-
form undermining is the controlling failure mechanism at bridge piers on rivers with mobile
bed forms, especially sand bed rivers. The most important factors affecting the stability of
the riprap layer under live-bed conditions were the turbulent flow field around the pier and
the fluctuations of the bed level caused by bed forms (e.g., dunes) as they migrate past the
pier. The three failure modes defined for clear-water conditions also exist under live-bed
conditions and they may act independently or jointly with migrating bed forms to destabilize
the riprap layer.
Once sediment transport starts and bed forms associated with the lower flow regime (i.e.,
ripples and dunes) begin to form, the movement of sediments at the edge of the riprap layer
remove the support of the edge stones. When the trough of a bed feature migrated past the
riprap layer, stones would slide into the trough, causing the riprap layer to thin. Depending
on the thickness of the remaining riprap layer following stone sliding and layer thinning,
winnowing may occur as a result of exposure of the underlying fine sediments to the flow.
Winnowing can cause the entire remaining riprap layer to subside into the bed. With thicker
riprap layers winnowing is not a factor and there is no subsidence.
5.18
Under steady flow conditions, the inherent flexibility of a riprap layer can provide a self-
healing process (Chiew 1995). As scour occurs and sediment is removed from around the
riprap layer through the three modes of erosion described above, the riprap layer, if it has
sufficient thickness, can adjust itself to the mobile channel bed and remain relatively intact
while providing continued scour protection for the pier. However, when flow velocity is
steadily increased, riprap shear, winnowing, and edge erosion combine to cause either a
total disintegration or embedment failure of the riprap layer in the absence of an underlying
filter (either geotextile or granular).
Total disintegration, which is characterized by a complete breakup of the riprap layer
whereby the stones are washed away by the flow, occurs when the self-healing ability of the
riprap layer is exceeded by the erosive power created by higher flow velocity. Total
disintegration occurs when the riprap stone size to sediment size ratio is small. Embedment
failure occurs when: (1) the riprap stones are large compared to the bed sediment and local
erosion around the individual stones causes them to embed into the channel bed (i.e.,
differential mobility); and (2) the riprap stones lose their stability as bed forms pass and drop
into the troughs of the migrating bed forms (i.e., bed feature destabilization).
5.4.3 Pier Riprap Failure Modes Schoharie Creek Case Study
The failure of the I-90 bridge over Schoharie Creek near Albany, New York on April 5, 1987,
which cost 10 lives, was investigated by the National Transportation Safety Board (NTSB)
(Richardson and Davis 2001). The peak flow was 64,900 cfs (1,838 m
3
/s) with a 70- to 100-
year return period. The foundations of the four bridge piers were large spread footings 82 ft
(25 m) long, 18 ft (5.5 m) wide, and 5 ft (1.5 m) deep without piles. The footings were set 5
ft (1.5 m) into the stream bed in very dense ice contact stratified glacial drift, which was
considered nonerodible by the designers (Figure 5.16). However, flume studies of samples
of the stratified drift showed that some material would be eroded at a velocity of 4 ft/s (1.5
m/s), and at a velocity of 8 ft/s (2.4 m/s) the erosion rates were high.
Figure 5.16. South elevation - Schoharie Creek Bridge showing key structural features
and a schematic geological section (Richardson et al. 1987).
5.19
A 1 to 50 scale, 3-dimensional, model study indicated a prototype flow velocity of 10.8 ft/s
(3.3 m/s) at the pier that failed. Also, the 1 to 50 scale and a 1 to 15 scale, 2-dimensional
model study gave 15 ft (4.6 m) of maximum scour depth. The scour depth of the prototype
pier (pier 3) at failure was 14 ft (4.3 m) (Figure 5.17).
Figure 5.17. Pier scour holes at Schoharie Creek Bridge in 1987. Pier 2 in
the foreground with pier 3 in the background.
Design plans called for the footings to be protected with riprap. Over time (1953 to 1987),
much of the riprap was removed by high flows. NTSB gave as the probable cause ".... the
failure of the New York State Thruway authority to maintain adequate riprap around the
bridge piers, which led to severe erosion in the soil beneath the spread footings.
Contributing to the severity of the accident was the lack of structural redundancy in the
bridge" (NTSB 1988).
The NYSTA inspected the bridge annually or biennially with the last inspection on April 1,
1986. A 1979 inspection by a consultant hired by NYSDOT indicated that most of the riprap
around the piers was missing (Figures 5.18 and 5.19); however, the 1986 inspection failed to
detect any problems with the condition of the riprap at the piers. Based on the NTSB
findings, the conclusions from this failure are that inspectors and their supervisors must
recognize that riprap does not necessarily make a bridge safe from scour, and inspectors
must be trained to recognize when riprap is missing and the significance of this condition.
Summary: Examples of the most common modes of riprap failure at piers provide guidance for
post-flood and post-construction performance evaluation. Inspectors need to be aware of, and
understand, the causes of riprap inadequacies that they see in the field. While the specific
mechanism causing failure of the riprap is difficult to determine, and a number of factors,
acting either individually or combined, may be involved, the reasons for riprap failures at
bridge piers can be summarized as follows:
5.20
Figure 5.18. Photograph of riprap at pier 2, October 1956.
Figure 5.19. Photograph of riprap at pier 2, August 1977 (flow is from right to left).
5.21
1. Particle size was too small because:
Shear stress was underestimated
Velocity was underestimated
Inadequate allowance was made for channel curvature
Design channel capacity was too low
Design discharge was too low
Inadequate assessment was made of abrasive forces
Inadequate allowance was made for effect of obstructions (such as debris)
2. Channel changes caused:
Increased angle of attack (skew)
Decreased channel capacity or increased depth
Scour
3. Riprap material had improper gradation
4. Material was placed improperly
5. No filter blanket was installed or blanket was inadequate or damaged
5.5 RIPRAP INSPECTION GUIDANCE
5.5.1 General
Inspection of riprap placement typically consists of visual inspection of the installation
procedures and the finished surface. Inspection must ensure that a dense, rough surface of
well-keyed graded rock of the specified quality and sizes is obtained, that the layers are
placed such that voids are minimized, and that the layers are the specified thickness.
If the riprap installation is part of channel stability works in the vicinity of a bridge, it is
typically inspected during the biennial bridge inspection program. However, more frequent
inspection might be required by the Plan of Action for a particular bridge or group of bridges.
In some cases, inspection may be required after every flood that exceeds a specified
magnitude. Underwater inspection of a riprap system should only be performed by divers
specifically trained and certified for such work.
The following general guidance for inspecting riprap is presented in the National Highway
Institute (NHI) training course 135047, "Stream Stability and Scour at Highway Bridges for
Bridge Inspectors:"
1. Riprap should be angular and interlocking (Old bowling balls would not make good
riprap). Flat sections of broken concrete paving do not make good riprap.
2. Riprap should have a granular or synthetic geotextile filter between the riprap and the
subgrade material.
3. Riprap should be well graded (a wide range of rock sizes). The maximum rock size
should be no greater than about twice the median (d
50
) size.
4. For bridge piers, riprap should generally extend up to the bed elevation so that the top of
the riprap is visible to the inspector during and after floods.
5.22
5. When inspecting riprap, the following are strong indicators of problems:
Has riprap been displaced downstream?
Has angular riprap blanket slumped down slope?
Has angular riprap material been replaced over time by smoother river run material?
Has riprap material physically deteriorated, disintegrated, or been abraded over
time?
Are there holes in the riprap blanket where the filter has been exposed or breached?
5.5.2 Guidance for Recording Riprap Condition
To guide the inspection of a riprap installation, a recording system is presented in Appendix
D. This guidance establishes numerical ratings from 0 (worst) to 9 (best). Recommended
action items based on the numerical rating are also provided (Lagasse et al. 2006).
5.5.3 Performance Evaluation
The evaluation of any revetment system's performance should be based on its design
parameters as compared to actual field experience, longevity, and inspection / maintenance
history. To properly assess the performance of revetment riprap, the history of hydraulic
loading on the installation, in terms of flood magnitudes and frequencies, must also be
considered and compared to the design loading. Guidance for the performance evaluation of
riprap armoring systems is provided in NCHRP Report 593 (Lagasse et al. 2007).
Changes in channel morphology may have occurred over time subsequent to the installation
of the riprap. Present-day channel cross-section geometry and planform should be
compared to those at the time of installation. Both lateral and vertical instability of the
channel can significantly alter hydraulic conditions at the site. Approach flows may exhibit
an increasingly severe angle of attack (impinging flow) over time, increasing the hydraulic
loading on the riprap.
Deficiencies noted during the inspection should be corrected as soon as possible. As
with any armor system, progressive failure from successive flows must be avoided by
providing timely maintenance intervention.
5.6 GROUTED AND PARTIALLY GROUTED RIPRAP
Grouted riprap is rock slope paving with voids filled with concrete grout forming a monolithic
armor. Because fully grouted riprap is a rigid structure, it will not conform to bank settlement
or toe undermining as loose riprap does. Therefore, fully grouted riprap is susceptible to
mass failure, especially if pore water is not allowed to drain properly. Although the revetment
is rigid, it is not particularly strong and even a small loss of toe or bank support can result in
the failure of large portions of the structure.
The primary advantage of fully grouted riprap is that the grout anchors the rock and
eliminates particle erosion of the revetment. Therefore, smaller rock can be used for the
revetment, and the total thickness of the revetment can be reduced as compared with
traditional riprap revetment. Another advantage is that a relatively smooth surface can be
achieved and, therefore, the hydraulic efficiency of the waterway is improved. Filters are not
required for fully grouted riprap but drainage of pore water must be provided. A significant
disadvantage of fully grouted riprap is that a complete layer of grout converts a
5.23
flexible revetment to a rigid cover, subject to the potential problems of any rigid slope
paving, including undercutting at the toe, out flanking, and the possibility of sudden
catastrophic failure.
An alternative to fully grouted riprap is partially grouted riprap. In general, the objective is to
increase the stability of the riprap without sacrificing its flexibility. Partial grouting of riprap
may be well suited for areas where rock of sufficient size is not available to construct a loose
riprap revetment.
The River and Channel Revetments design manual published by H.R. Wallingford in the
United Kingdom (Escarameia 1998) provides design guidance for grouting "hand pitched
stone" with both bituminous and cement grout. For grouting riprap in the United Kingdom,
bitumen is the material most commonly used. Although various degrees of grouting are
possible, effective solutions are usually produced when the bituminous mortar envelopes the
loose stone and leaves relatively large voids between rock particles. The degrees of
bituminous grouting available are:
Surface grouting (which does not penetrate the whole thickness of the revetment and
corresponds to about one-third of the voids filled)
Various forms of pattern grouting (where only some of the surface area of the revetment
is filled, between 50 to 80% of voids)
Full grouting (an impermeable type of revetment)
Partial grouting of riprap with a cement slurry is presented as one of several standard design
approaches for permeable revetments in a discussion of considerations regarding the
experience and design of German inland waterways (Heibaum 2000). Partially grouted
riprap consists of appropriately sized rocks that are grouted together with grout filling only
1/3 to 1/2 of the total void space (Figure 5.20). In contrast to fully grouted riprap, partial
grouting increases the overall stability of the riprap installation unit without sacrificing
flexibility or permeability. It also allows for the use of smaller rock compared to standard
riprap, resulting in decreased layer thickness. Design, specification, and construction
guidance for partially grouted riprap is provided in Design Guideline 12, Volume 2.
The holes in the grout allow for drainage of pore water so a filter is required. The grout
forms conglomerates of riprap so the stability against particle erosion is greatly improved
and, as with fully grouted riprap, a smaller thickness of stone can be used (Figure 5.21).
Although not as flexible as riprap, partially grouted riprap will conform somewhat to bank
settlement and toe exposure.
An important consideration for partially grouted riprap is that construction methods must be
closely monitored to insure that the appropriate voids and surface openings are provided.
Contractors in Germany have developed techniques and equipment to achieve the desired
grout coverage and the right penetration. Various European countries have developed
special grout mixes and construction methods for underwater installation of partially grouted
riprap (see Design Guideline 12).
5.24
Figure 5.20. Close-up view of partially grouted riprap.
Figure 5.21. "Conglomerate" of partially grouted riprap, Federal Waterway Engineering and
Research Institute, Karlsruhe, Germany (Heibaum 2000).
5.25
5.7 CONCRETE ARMOR UNITS
Concrete armor units, also known as artificial riprap, consist of individual pre-cast concrete
units with complex shapes that are placed individually or in interconnected groups. These
units were originally developed for shore protection to resist wave action during extreme
storms. All are designed to give a maximum amount of interlocking using a minimum
amount of material. These devices are used where natural riprap is unavailable or is more
costly to obtain than fabrication of the artificial riprap units. Parker et al. (1998) provide a
review of studies conducted on the use of concrete armor units as pier scour
countermeasures.
Various designs for size and shape of concrete armor units are available and include such
commercial names as Tetrapods, Tetrahedrons, Toskanes, Dolos, Tribars, Accropodes,
Core-Loc
TM
, and A-Jacks
).
Tetrapod Tetrahedron Toskane A-Jacks
Core-Loc
TM
Accropode Dolos Tribar
Figure 5.22. Concrete armor units.
The primary advantage of armor units is that they usually have greater stability compared to
riprap particles of equivalent weight. This is due to the interlocking characteristics of their
complex shapes. The increased stability allows their placement on steeper slopes or the use
of lighter weight units for equivalent flow conditions as compared to riprap. This is significant
when riprap of a required size is not available.
The design of armor units in open channels is based on the selection of appropriate sizes
and placement patterns to be stable in flowing water. The armor units should be able to
withstand the flow velocities without being displaced. Hydraulic testing is used to measure
the hydraulic conditions at which the armor units begin to move or "fail," and dimensional
5.26
analysis allows extrapolation of the results to other hydraulic conditions. Although a standard
approach to the stability analysis has not been established, design criteria have been
developed for various armor units using the following dimensionless parameters:
Isbash stability number (Parola 1993; Ruff and Fotherby 1995; Bertoldi et al. 1996)
Shields parameter (Bertoldi et al. 1996)
Froude number
( Brown and Clyde 1989)
The Isbash stability number and Shields parameter are indicative of the interlocking
characteristics of the armor units. Froude number scaling is based on similitude of stabilizing
and destabilizing forces. Quantification of these parameters requires hydraulic testing and,
typically, regression analysis of the data. Prior research and hydraulic testing have provided
guidance on the selection of the Isbash stability number and Shields parameter for riprap
and river sediment particles, but stability values are not available for all concrete armor units.
Therefore, manufacturers of concrete armor units have a responsibility to test their products
and to develop design criteria based on the results of these tests. Since armor units vary in
shape and performance from one proprietary system to the next, each system will have
unique performance properties.
Installation guidelines for concrete armor units in streambank revetment and channel armor
applications should consider subgrade preparation, edge treatment (toe down and flank)
details, armor layer thickness, and filter requirements. Subgrade preparation and edge
treatment for armor units is similar to that required for riprap. Considerations for armor layer
thickness and filter requirements are product specific and should be provided by the armor
unit manufacturer.
Concrete armor units have shown potential for mitigating the effects of local scour in the
laboratory; however, only limited data are available on their performance in the field.
Research efforts are currently being conducted to test the performance of concrete armor
units as pier scour countermeasures in the field.
Design methods which incorporate velocity (a variable which can be directly measured) are
commonly used to select local scour countermeasures. Normally an approach velocity is
used in the design equation (generally a modified Isbash equation) with a correction factor
for flow acceleration around the pier or abutment (see Section 5.2.3).
Although tetrahedrons are currently used for bank protection (Fotherby 1995), they have
garnered very little interest with regard to pier scour protection in the United States. This
may be primarily related to their lack of appendages and interlock (i.e., their simple compact
shape is similar to riprap and spheres). Dolos also have not been seriously considered for
use as pier scour protection because they have no inherent interlocking property to resist
movement under steady state turbulent flow (Brebner 1978). Extensive testing and research
has been conducted on the Core-Loc
- Source(s): Testing at Colorado State University
- Application: Pier scour protection
8.1
CHAPTER 8
OTHER COUNTERMEASURES AND CASE HISTORIES OF PERFORMANCE
8.1 INTRODUCTION
Design Guidelines 1 through 19 contain specific design procedures for a variety of stream
instability and bridge scour countermeasures that have been applied successfully on a state
or regional basis. Other countermeasures such as retarder structures, longitudinal dikes,
bulkheads, and even channel relocations may be used to mitigate scour at bridges or stream
bank erosion. Some of these measures are discussed and general guidance is summarized
in this chapter. Chapter 4 (Section 4.3.6) illustrates the use of the concept of radial stress
on a meander bend to evaluate the performance of fence, dike, and retarder type structures
in protecting an eroding bankline.
Case histories of hydraulic problems at bridge sites can provide information on the success
(or failure) of the various countermeasures used to stabilize streams. This chapter also
summarizes the evaluation of countermeasure performance compiled for FHWA from case
histories at 224 bridge sites (Brice and Blodgett 1978).
8.2 HARDPOINTS
Hardpoints consist of stone fills spaced along an eroding bank line, protruding only short
distances into the channel. A root section extends landward to preclude flanking. The crown
elevation of hardpoints used by the USACE at demonstration sites on the Missouri River was
generally at the normal water surface elevation at the toe, sloping up at a rate of about 1 ft in
10 ft (1 m in 10 m) toward the bank. Hardpoints are most effective along straight or relatively
flat convex banks where the streamlines are parallel to the bank lines and velocities are not
greater than 10 ft/s (3 m/s) within 50 ft (15 m) of the bank line. Hardpoints may be
appropriate for use in long, straight reaches where bank erosion occurs mainly from a
wandering thalweg at lower flow rates. They would not be effective in halting or reversing
bank erosion in a meander bend unless they were closely spaced, in which case spurs,
retarder structures, or bank revetment would probably cost less. Figure 8.1 is a perspective
of a hardpoint installation. Hardpoints have been used effectively as the first "spur" in a spur
field (see Design Guideline 2).
8.3 RETARDER STRUCTURES
Retarder structures are permeable or impermeable devices generally placed parallel to
streambanks to reduce velocities and cause deposition near the bank. They are best suited
for protecting low banks or the lower portions of streambanks. Retarder structures can be
used to protect an existing bank line or to establish a different flow path or alignment.
Retards do not require grading of the streambank, and they create an environment which is
favorable to the establishment of vegetation.
8.2
Figure 8.1. Perspective view of hardpoint installation with section detail (after Brown 1985).
8.3.1 Jacks and Tetrahedrons
Jacks most commonly consist of three linear members fixed together at their midpoints so
that each member is perpendicular to the other two. Wires are strung on the members to
resist distortion and to collect debris. Cables are used to tie individual jacks together and for
anchoring key units to deadmen. Tetrahedrons consist of six members of equal length fixed
together so as to form three faces, each of which is an equilateral triangle, i.e., a
tetrahedron. The tetrahedron unit may be braced as shown in Figure 8.2 and wire mesh
added to enhance flow retardance. Tetrahedrons are not as widely used as are jacks.
Jacks and tetrahedrons are effective in protecting banks from erosion only if light debris
collects on the structures thereby enhancing their performance in retarding flow. However,
heavy debris and ice can damage the structures severely. They are most effective on mild
bends and in wide, shallow streams which carry a large sediment load.
Where jacks are used to stabilize meandering streams, both lateral and longitudinal rows are
often installed to form an area retarder structure rather than a linear structure. Lateral rows
of jacks are usually oriented in a downstream direction from 45 to 70. Spacing of the lateral
rows of jacks may be 50 to 200 ft (15 to 75 m) depending on the debris and sediment load
carried by the stream. A typical jack unit is shown in Figure 8.3 and a typical area installation
is shown in Figure 8.4.
Outflanking of jack installations is a common problem. Adequate transitions should be
provided between the upstream bank and the structure, and the jack field should be
extended to the overbank area to retard flow velocities and provide additional anchorage.
Jacks are not recommended for use in corrosive environments or at locations where they
would constitute a hazard to recreational use of the stream.
8.3
Figure 8.2. Typical tetrahedron design (after Brown 1985).
Figure 8.3. Typical jack unit (after Brown 1985).
8.4
Figure 8.4. Retarder field schematic (after HDS 6, Richardson et al. 2001).
8.3.2 Fence Retarder Structures
Fence retarder structures provide protection to the lower portions of banks of relatively small
streams. Posts may be of wood, steel, or concrete and fencing may be composed of wood
planks or wire.
Scour and the development of flow channels behind linear structures are common causes of
failure of longitudinal fences. Scour at the supporting members of the structure can be
reduced by placing rock along the fence or the effects of scour can be overcome by driving
supporting members to depths below expected scour. Tiebacks can be used to retard
velocities between the linear structure and the streambank, thus reducing the ability of the
stream to develop flow channels behind the structure.
8.3.3 Timber Pile
Timber pile retarder structures may be of a single, double, or triple row of piles with the
outside of the upstream row faced with wire mesh or other fencing material. They have been
found to be effective at sharp bends in the channel and where flows are directly attacking a
bank. They are effective in streams which carry heavy debris and ice loads and where
barges or other shipping vessels could damage other countermeasures or a bridge. As with
other retarder structures, protection against scour failure is essential. Figure 8.5 illustrates a
design.
8.3.4 Wood Fence
Wood fence retarder structures have been found to provide a more positive action in
maintaining an existing flow alignment and to be more effective in preventing lateral erosion
at sharp bends than other retarder structures. Figure 8.6 is an end view of a typical wood
fence design with rock provided to protect against scour.
8.5
Figure 8.5. Timber pile bent retarder structure (after Brown 1985).
Wire fence retarder structures may be of linear or area configuration, and linear
configurations may be of single or multiple fence rows. Double-row fence retards are
sometimes filled with brush to increase the flow retardance. Figures 8.7 and 8.8 illustrate
two types of wire fence retarder structures.
8.4 LONGITUDINAL DIKES
Longitudinal dikes are essentially impermeable linear structures constructed parallel with the
streambank or along the desired flow path. They protect the streambank in a bend by
moving the flow current away from the bank. Longitudinal dikes may be classified as earth or
rock embankment dikes, crib dikes, or rock toe-dikes.
8.4.1 Earth or Rock Embankments
As the name implies, these dikes are constructed of earth with rock revetment or of rock.
They are usually as high or higher than the original bank. Because of their size and cost,
they are useful only for large-scale channel realignment projects.
8.6
Figure 8.6. Typical wood fence retarder structure (modified from USACE 1981,
after Brown 1985).
Figure 8.7. Light double row wire fence retarder structure (after Brown 1985).
8.7
Figure 8.8. Heavy timber-pile and wire fence retarder structures (Modified from USACE
1981, after Brown 1985).
8.4.2 Rock Toe-Dikes
Rock toe-dikes are low structures of rock riprap placed along the toe of a channel bank.
They are useful where erosion of the toe of the channel bank is the primary cause of the loss
of bank material. The USACE has found that longitudinal stone dikes provide the most
successful bank stabilization measure studied for channels which are actively degrading and
for those having very dynamic beds. Where protection of higher portions of the channel bank
is necessary, rock toe-dikes have been used in combination with other measures such as
vegetative cover and retarder structures.
8.8
Figure 8.9 shows the typical placement and sections of rock toe-dikes. The volume of
material required is 1.5 to 2 times the volume of material that would be required to armor the
sides of the anticipated scour to a thickness of 1.5 times the diameter of the largest stone
specified. Rock sizes should be similar to those specified for riprap revetments (see Design
Guideline 4). Tiebacks are often used with rock toe-dikes to prevent flanking, as illustrated
in Figure 8.10. Tiebacks should be used if the toe-dike is not constructed at the toe of the
channel bank.
Rock toe-dikes are useful on channels where it is necessary to maintain as wide a
conveyance channel as possible. Where this is not important, spurs could be more
economical since scour is a problem only at the end projected into the channel. However,
spurs may not be a viable alternative in actively degrading streams (Design Guideline 2).
8.4.3 Crib Dikes
Longitudinal crib dikes consist of a linear crib structure filled with rock, straw, brush,
automobile tires or other materials. They are usually used to protect low banks or the lower
portions of high banks. At sharp bends, high banks would need additional protection against
erosion and outflanking of the crib dike. Tiebacks can be used to counter outflanking.
Crib dikes are susceptible to undermining, causing loss of material inside the crib, thereby
reducing the effectiveness of the dike in retarding flow. Figure 8.11 illustrates a crib dike
with tiebacks and a rock toe on the stream side to prevent undermining.
8.4.4 Bulkheads
Bulkheads are used for purposes of supporting the channel bank and protecting it from
erosion. They are generally used as protection for the lower bank and toe, often in
combination with other countermeasures that provide protection for higher portions of the
bank. Bulkheads are most frequently used at bridge abutments as protection against
slumping and undermining at locations where there is insufficient space for the use of other
types of bank stabilization measures, and where saturated fill slopes or channel banks
cannot otherwise be stabilized.
Bulkheads are classified on the basis of construction methods and materials. They may be
constructed of concrete, masonry, cribs, sheet metal, piling, reinforced earth, used tires,
gabions, or other materials. They must be protected against scour or supported at elevations
below anticipated total scour, and where sections of the installation are intermittently above
water, provisions must be made for seepage through the wall. Some bulkhead types, such
as crib walls and gabions, should be provided with safeguards against leaching of materials
from behind the wall.
Bulkheads must be designed to resist the forces of overturning, bending and sliding, either
by their mass or by structural design. Figure 8.12 illustrates anchorage schemes for a
sheetpile bulkhead. Because of costs, they should be used as countermeasures against
meander migration only where space is not available to construct other types of measures.
8.9
Figure 8.9. Typical longitudinal rock toe-dike geometries (after Brown 1985).
Figure 8.10. Longitudinal rock toe-dike tiebacks (after Brown 1985).
8.10
Figure 8.11. Timber pile, wire mesh crib dike with tiebacks (modified from USACE
1981, after Brown 1985).
Figure 8.12. Anchorage schemes for a sheetpile bulkhead (after Brown 1985).
8.11
8.5 CHANNEL RELOCATION
At some locations, it may be advantageous to realign a stream channel, either in
combination with the use of other countermeasures against meander migration or in lieu of
other countermeasures.
Figure 8.13 illustrates hypothetical highway locations fixed by considerations other than
stream stability. To create better flow alignment with the bridge, consideration could be given
to channel realignment as shown in this figure (parts a and b). Similarly, consideration for
realignment of the channel would also be advisable for a hypothetical lateral encroachment
of a highway as depicted in part c of the figure. In either case, criteria are needed to
establish the cross-sectional dimensions.
Figure 8.13. Encroachments on meandering streams (after HDS 6, Richardson et al. 2001).
Before realigning a stream channel, the stability of the existing channel must be examined.
The stream classification, recent and older aerial photographs, and field surveys are
necessary. The realigned channel may be made straight without curves, or may include one
or more curves. If curves are included, decisions regarding the radius of curvature, the
number of bends, the limits of realignment (hence the length and slope of the channel) and
the cross-sectional area have to be made. Different streams have different historical
backgrounds and characteristics with regard to bend migration, discharge, stage, geometry,
and sediment transport, and an understanding and appreciation of river hydraulics and
morphology is important to decision making. It is difficult to state generalized criteria for
channel relocation applicable to all streams. HEC-20 (Lagasse et al. 2001a) provides
quantitative techniques for evaluating and predicting lateral channel migration and analyzing
vertical channel stability, as well as an introduction to channel restoration concepts that
should be considered for channel relocation projects.
8.12
Based on a study of the stability of relocated channels, Brice presented the following
recommendations and conclusions regarding specific aspects of planning and construction
of channel realignment (Brice 1981):
Channel Stability Prior to Realignment.
Assessment of the stability of a channel prior to realignment is needed to assess the risk
of instability. An unstable channel is likely to respond unfavorably. Bank stability is
assessed by field study and by stereoscopic examination of aerial photographs (see
HEC-20). The most useful indicators of bank instability are cut or slumped banks, fallen
trees along the bank line, and exposed wide point bars. Bank recession rates are
measured by comparison of time-sequential aerial photographs. Vertical instability is
equally important but more difficult to determine. It is indicated by changes in channel
elevation at bridges and gaging stations. Serious degradation is usually accompanied by
generally cut or slumped banks along a channel and by increased debris transport.
Erosional Resistance of Channel Boundary Materials.
The stability of a channel, whether natural or relocated, is partly determined by the
erosional resistance of materials that form the wetted perimeter of the channel (see
HEC-20). Resistant bedrock outcrops in the channel bottom or that lie at shallow depths
will provide protection against degradation, but not all bedrock is resistant. Erosion of
shale, or of other sedimentary rock types interbedded with shale, has been observed.
Degradation is not a problem at most sites where bed sediment is of cobble and boulder
size. However, degradation may result from the relocation of any alluvial channel,
whatever the size of bed material, but the incidence of serious degradation of channels
relocated by DOTs is small in number. The erosional resistance of channel beds tends to
increase with clay content. Banks of weakly cohesive sand or silt are clearly subject to
rapid erosion, unless protected with vegetation. No consistent relation has been found
between channel stability and the cohesion of bank materials, probably because of the
effects of vegetation.
Length of Realignment.
The length of realignment contributes significantly to channel instability at sites where its
value exceeds 250 channel widths. When the value is below 100 channel widths, the
effects of length of relocation are dominated by other factors. The probability of local
bank erosion at some point along a channel increases with the length of the channel.
The importance of vegetation, both in appearance and in erosion control, would seem to
justify a serious and possibly sustained effort to establish it as soon as possible on
graded banks.
Bank Revetment.
Revetment makes a critical contribution to stability of relocated stream channels at many
sites. Rock riprap is by far the most commonly used and effective revetment (see Design
Guideline 4). Concrete slope paving is prone to failure. Articulating concrete block is
effective where vegetation can establish within the open cells of the blocks (Design
Guideline 8).
8.13
Check Dams (drop structures).
In general, check dams are effective in preventing channel degradation in relocated
channels. The potential for erosion at a check dam depends on its design and
construction, its height and the use of revetment on adjoining banks. A series of low
check dams, less than about 1.5 ft (0.5 m) in height, is probably preferable to a single
higher structure, because of increased safety and reduced potential for erosion and
failure. By simulating rapids, low check dams may add visual interest to the flow in a
channel. One critical problem arising with check dams relates to improper design for
large flows. Higher flows have worked around the ends of many installations to produce
failure (see Design Guideline 3).
Maintenance.
Problems which could be resolved by routine maintenance were observed along
relocated channels. These were problems with the growth of annual vegetation,
reduction of channel conveyance by overhanging trees, local bank cutting, and bank
slumping. The expense of routine maintenance or inspection of relocated channels
beyond the highway right-of-way may be prohibitive; however, most of the serious
problems could be detected by periodic inspection, perhaps by aerial photography,
during the first five to ten years after construction. Hydraulic engineers responsible for
the design of relocated stream channels should monitor their performance to gain
experience and expertise.
8.6 CASE HISTORIES OF COUNTERMEASURE PERFORMANCE
Case histories of hydraulic problems at bridge sites can provide information on the relative
success of the various countermeasures used to stabilize streams. The following case
histories are taken from Brice and Blodgett (1978), Brice (1984), and Brown et al. (1980).
Site data are from Brice and Blodgett (1978). This compilation of case histories at 224 bridge
sites is recommended reference material for those responsible for selecting
countermeasures for stream instability. Additional case histories are given in HDS 6
(Richardson et al. 2001).
8.6.1 Flexible Revetment
Rock Riprap. Dumped rock riprap is the most widely used revetment in the United States.
Its effectiveness has been well established where it is of adequate size, of suitable size
gradation, and properly installed. Brice and Blodgett (1978) documented the use of rock
riprap at 110 sites (Volume 1, Table 2). They rated the performance at 58 sites and found
satisfactory performance at 34 sites, partially satisfactory performance at 12 sites, and
failure to perform satisfactorily at 12 sites. Keeley concluded that riprap used in Oklahoma
performed without significant failure and provides basic and efficient bank control on the
meandering streams in Oklahoma (Keeley 1971). Additional discussion of riprap revetment
failure modes and inspection guidance can be found in Chapter 5 and Appendix D.
A review of the causes of failure at the sites studied by Brice and Blodgett (1978) is
instructive. They found the absence of a filter blanket clearly the cause of the failure at a
site subject to tides and wave action. The riprap was placed on a fill of sand and fine gravel
which eroded through the interstices of the riprap.
8.14
Internal slope failure was the cause of failure of riprap at the abutment of bridges at two
sites. At one site, failure was attributed to saturation of a high fill by impounded water in a
reservoir. Wave action also probably contributed to the failure. The other site is difficult to
include as a riprap failure because the rock was not placed as riprap revetment. Thirty-three
freight car loads of rock were dumped as an emergency measure to stop erosion at a bridge
abutment during high-flow releases from a reservoir. The rock was displaced, and the high
streambanks and highway fill were still susceptible to slumps. At both sites, riprap failed to
prevent slumps in high fills.
Inadequate rock size and size gradation was given as the cause of failure at eight sites. All
of these sites are complex, and it is difficult to assign failure to one cause, but rock size was
definitely a factor.
Channel degradation accounted for failure at three sites in Mississippi. Channel degradation
at these sites is due to channel straightening and clearing by the SCS (NRCS) and USACE.
Riprap installations on the streambanks, at bridge abutments and in the streambed have
failed to stop lateral erosion. At one site, riprap placed on the banks and bed of the stream
resulted in severe bed scour and bank erosion downstream of the riprap.
Failure of riprap at one site was attributed to the steep slope on which the riprap was placed.
At this site, rock riprap failed to stop slumping of the steep banks downstream of a check
dam in a degrading stream.
Successful rock riprap installations at bends were found at five sites. Bank erosion was
controlled at these sites by rock riprap alone. Installations rated as failing were damaged at
the toe and upstream end, indicating inadequate design and/or construction, and damage to
an installation of rounded boulders, indicating inadequate attention to riprap specifications.
Other successful rock riprap study sites were sites where bank revetment was used in
conjunction with other countermeasures, such as spurs or retards. The success of these
installations was attributed more to the spurs or retards, but the contribution of the bank
revetment was not discounted.
Broken Concrete. Broken concrete is commonly used in emergencies and where rock is
unavailable or very expensive. No specifications were found for its use. Performance was
found to be more or less unsatisfactory at three sites.
Rock-and-Wire Mattress and Gabions. The distinction made between rock-and-wire mattress
and gabions is in the dimensions of the devices (see Design Guideline 10). Rock-and-wire
mattress is usually 1.0 ft (0.3 m) or less in thickness and a gabion is thicker and nearly
equidimensional. The economic use of rock-and-wire mattress is favored by an arid climate,
availability of stones of cobble size, and unavailability of rock for dumped rock riprap.
Corrosion of wire mesh is slow in arid climates, and ephemeral streams do not subject the
wire to continuous abrasion. Where large rock is not available, the use of rock-and-wire
mattress may be advantageous in spite of eventual corrosion or abrasion of the wire.
Rock-and-wire mattress performance was found to be generally satisfactory although local
failure of the wire mesh and spilling out of the rock was not uncommon. Mattresses are held
in place against the bank by railroad rails at sites in New Mexico and Arizona where good
performance was documented (see Design Guideline 6). This is known locally as "railbank
protection." The steel rail supported rock-and-wire mattress stays in place better than
dumped rock riprap on the unstable vertical banks found on the ephemeral streams of this
area. Mattress held in place by stakes has been found to be effective in Wyoming.
8.15
The use of rock-and-wire mattress has diminished in California because of the questionable
service of wire mesh, the high cost of labor for installation, and the efficiency of modern
methods of excavating for dumped riprap toe protection. The Los Angeles Flood Control
District, however, has had installations in-place for 15 years or more with no evidence of wire
corrosion. On the other hand, Montana and Maryland reported abrasion damage of wire.
These experiences illustrate that economical use of countermeasures is dependent on the
availability of materials, costs, and the stream environment in which the measure is placed.
Several sites were identified where gabions were installed, but the countermeasures had
been tested by floods at only one site where gabions placed on the downstream slope of a
roadway overflow section performed satisfactorily.
Other Flexible Revetment. Favorable performance of precast-concrete blocks at bridges was
reported in Louisiana. Vegetation is reported to grow between blocks and contribute to
appearance and stability. Vegetation apparently is seldom used alone at bridges. Iowa relies
on sod protection of spur dikes, but Arkansas reported failure of sod as bank protection.
8.6.2 Rigid Revetments
Failure of rigid revetment tends to be progressive; therefore, special precautions to prevent
undermining at the toe and termini and failure from unstable soils or hydrostatic pressure are
warranted.
Concrete Pavement. Well-designed concrete paving is satisfactory as fill slope revetment, as
revetment on streams having low gradients, and in other circumstances where it is well
protected against undermining at the toe and ends. The case histories include at least one
location where riprap launching aprons were successful in preventing undermining at the toe
from damaging the concrete pavement revetment. Weep holes for relief of hydrostatic
pressure are required for many situations (see Design Guideline 4).
Documented causes of failure in the case histories are undermining at the toe (six sites),
erosion at termini (five sites), eddy action at downstream end (two sites), channel
degradation (two sites), high water velocities (two sites), overtopping (two sites), and
hydrostatic pressure (one site). Good success is reported with concrete slope paving in
Florida, Illinois, and Texas.
Sacked Concrete. No DOT reported a general use of sacked concrete as revetment.
California was reported to regard this as an expensive revetment almost never used unless
satisfactory riprap was not available. Sacked concrete revetment failures were reported
from undermining of the toe (two sites), erosion at termini (one site), channel degradation
(two sites), and wave action (one site) (see Design Guideline 4).
Concrete-Grouted Riprap. Fully-grouted riprap permits the use of smaller rock, a lesser
thickness, and more latitude in gradation of rock than in dumped rock riprap. No failures of
grouted riprap were documented in the case histories, but it is subject to the same types of
failures as other rigid revetments (see Chapter 5, Section 5.6 and Design Guideline 12).
Concrete-Filled Fabric Mat. Concrete-filled fabric mat is a patented product (Fabriform)
consisting of porous, pre-assembled nylon fabric forms which are placed on the surface to
be protected and then filled with high-strength mortar by injection. Variations of Fabriform
and Fabricast consist of nylon bags similarly filled. Successful installations were reported by
the manufacturer of Fabriform in Iowa, and North Dakota reported successful installations
(see Design Guideline 9).
8.16
Soil Cement. In areas where any type of riprap is scarce, use of in-place soil combined with
cement provides a practical alternative. The resulting mixture, soil cement, has been
successfully used as bank protection in many areas of the Southwest (see Design Guideline
7). Unlike other types of bank revetment, where milder side slopes are desirable, soil cement
in a stairstep construction can be used on steeper slopes (i.e., typically one to one), which
reduces channel excavation costs. For many applications, soil cement is generally more
aesthetically pleasing than other types of revetment.
8.6.3 Bulkheads
A bulkhead is a steep or vertical wall used to support a slope and/or protect it from erosion
(See Section 8.4). Bulkheads usually project above ground, although the distinction between
bulkheads and cutoff walls is not always sharp. Most bulkhead applications were found at
abutments. They were found to be most useful at the following locations: (1) on braided
streams with erodible sandy banks, (2) where banks or abutment fill slopes have failed by
slumping, and (3) where stream alignment with the bridge opening was poor, to provide a
transition between streambanks and the bridge opening. It was not clear what caused
failures at five sites summarized in Brice and Blodgett (1978), but in each case, the probable
cause was undermining.
8.6.4 Spurs
Spurs are permeable or impermeable structures which project from the bank into the
channel. Spurs may be used to alter flow direction, induce deposition, or reduce flow
velocity. A combination of these purposes is generally served. Where spurs project from
embankments to decrease flow along the embankment, they are called embankment spurs.
These may project into the floodplain rather than the channel, and thus function as spurs
only during overbank flow. According to a summary prepared for the Transportation
Research Board, spurs may protect a streambank at less cost than riprap revetment, and by
deflecting current away from the bank and causing deposition, they may more effectively
protect banks from erosion than revetment (Richardson and Simons 1984). Uses other than
bank protection include the constriction of long reaches of wide, braided streams to establish
a stable channel, constriction of short reaches to establish a desired flow path and to
increase sediment transport capacity, and control of flow at a bend. Where used to constrict
a braided stream to a narrow flow channel, t he structure may be more correctly
referred to as a dike or a retard in some locations (see Design Guideline 2).
Several factors enter into the performance of spurs, such as permeability, orientation,
spacing, height, shape, length, construction materials, and the stream environment in which
the spur is placed.
Impermeable Spurs. The case histories show good success with well-designed impermeable
spurs at bends and at crossings of braided stream channels (eight sites). At one site,
hardpoints barely projecting into the stream and spaced at about 100 to 150 ft (30 to 45 m)
failed to stop bank erosion at a severe bend. At another site, spurs projecting 40 ft (12 m)
into the channel, spaced at 100 ft (30 m), and constructed of rock with a maximum diameter
of 1.5 ft (0.5 m) experienced erosion between spurs and erosion of the spurs. At a third site,
spurs constructed of timber piling filled with rock were destroyed. Failure was attributed to
the inability to get enough penetration in the sand-bed channel with timber piles and the
unstable wide channel in which the thalweg wanders unpredictably. Spurs (or other
countermeasures) are not likely to be effective over the long term in such an unstable
channel unless well-designed, well-built, and deployed over a substantial reach of stream.
8.17
Although no failures from ice damage were cited for impermeable spurs, North Dakota uses
steel sheet pile enclosed earth fill spurs because of the potential for ice damage. At one
site, such a spur sustained only minor damage from 2.5 ft (0.75 m) of ice.
Permeable Spurs. A wide variety of permeable spur designs were also shown to successfully
control bank erosion by the case histories. Failures were experienced at a site which is
highly unstable with rapid lateral migration, abundant debris, and extreme scour depths.
Bank revetments of riprap and car bodies and debris deflectors at bridge piers, as well as
bridges, have also failed at this site. At another site, steel H-pile spurs with wire mesh have
partially failed on a degrading stream.
8.6.5 Retardance Structures
A retardance structure (retard) can be a permeable or impermeable linear structure in a
channel, parallel with and usually at the toe of the bank. The purposes of retardance
structures are to reduce flow velocity, induce deposition, or to maintain an existing flow
alignment. They may be constructed of earth, rock, timber pile, sheet pile, or steel pile.
Steel jacks or tetrahedrons are also used (see Section 8.3).
Most retardance structures are permeable and most have good performance records. They
have proved to be useful in the following situations: (1) for alignment problems very near a
bridge or roadway embankment, particularly those involving rather sharp channel bends and
direct impingement of flow against a bank (ten sites), and (2) for other bank erosion
problems that occur very near a bridge, particularly on streams that have a wandering
thalweg or very unstable banks (seven sites).
The case histories include a site where a rock retardance structure similar to a rock toe dike
was successful in protecting a bank on a highly unstable channel where spurs had failed.
There were, however, deficiencies in the design and construction of the spur installation. At
another site, a rock retardance structure similar to a rock toe-dike has reversed bank erosion
at a bend in a degrading stream. The USACE (1981) reported that longitudinal rock toe
dikes were the most effective bank stabilization measure studied for channels having very
dynamic and/or actively degrading beds.
8.6.6 Dikes
Dikes are impermeable linear structures for the control or containment of overbank flow (see
Section 8.4). Most are in floodplains, but they may be within channels, as in braided streams
or on alluvial fans. Dikes at study sites were used to prevent flood water from bypassing a
bridge at four sites, or to confine channel width and maintain channel alignment at two sites.
Performance of dikes at study sites was judged generally satisfactory.
8.6.7 Guide Banks
The major use of guide banks (formerly referred to as spur dikes) in the United States is to
prevent erosion by eddy action at bridge abutments or piers where concentrated flood flow
traveling along the upstream side of an approach embankment enters the main flow at the
bridge (see Design Guideline 15). By establishing smooth parallel streamlines in the
approaching flow, guide banks improve flow conditions in the bridge waterway. Scour, if it
occurs, is near the upstream end of the guide bank away from the bridge. A guide bank
differs from dikes described above in that a dike is intended to contain overbank flow while a
guide bank only seeks to align overbank flow with flow through the bridge opening. An
8.18
extension of the usual concept of the purpose for guide banks, but not in conflict with that
concept, is the use of guide banks and highway fill to constrict braided channels to one
channel. At three sites studied, guide banks only or guide banks plus revetment on the
highway fill were used to constrict wide braided channels rather severely, and the
installations have performed well.
Guide bank performance was found to be generally satisfactory at all study sites.
Performance is theoretically affected by construction materials, shape, orientation, and
length.
Most guide banks are constructed of earth with revetment to inhibit erosion of the dike. At
two sites, guide banks of concrete rubble masonry performed well. Riprap revetment is most
common, but concrete revetment with rock riprap toe protection, rock-and-wire mattress,
gabions, and grass sod have also performed satisfactorily. Since partial failure of a guide
bank during a flood usually will not endanger the bridge, wider consideration should be given
to the use of vegetative cover for protection. Partial failure of any countermeasure is usually
of little significance so long as the purpose of protecting the highway stream crossing is
accomplished.
Guide banks of elliptical shape, straight, and straight with curved ends performed
satisfactorily at study sites, although there is evidence at one site that flow does not follow
the nose of the straight guide bank. Clear evidence of the effect of guide bank orientation
was not found at study sites although the conclusion from a study of guide banks in
Mississippi that guide banks should be oriented with valley flow for skewed crossings of
wooded floodplains was cited (Colson and Wilson 1973). There was evidence at one site
that a guide bank may be severely tested where a large flow is diverted along the roadway
embankment, as at a skewed crossing or on a wide floodplain which is severely constricted
by the bridge. At these locations, embankment spurs may be advisable to protect the
embankment from erosion and to reduce the potential for failure of the guide bank.
Guide banks at study sites tended to be longer than recommended by Bradley (1978) at
most sites, except at five sites where they ranged from 16 to 75 ft (5 to 23 m). All guide
banks appeared to perform satisfactorily. Not enough short guide banks were included in
the study to reach conclusions regarding length.
8.6.8 Check Dams
Check dams are usually used to stop degradation in the channel in order to protect the
substructure foundation of bridges (see Design Guideline 3). At one site, however, a check
dam was apparently used to inhibit contraction scour in a bridge waterway. The problem
with vertical scour was resolved, but lateral scour became a problem and riprap revetment
on the streambanks failed (Brice and Blodgett 1978).
Scour downstream of check dams was found to be a problem at two sites, especially lateral
erosion of the channel banks. Riprap placed on the streambanks at the scour holes also
failed, at least in part because of the steep slopes on which the riprap was placed. At the
time of the study, lateral erosion threatened damage to bridge abutments and highway fills.
At another site, a check dam placed at the mouth of a tributary stream failed to stop
degradation in the tributary and the delivery of damaging volumes of sediment to the main
stream just upstream of a bridge.
No structural failure of check dams was documented. Failures are known to have occurred,
however, and the absence of documented failures in this study should not be given undue
weight. Failure can occur by bank erosion around the ends of the structure resulting in
8.19
outflanking; by seepage or piping under or around the structure resulting in undermining and
structural or functional failure; by overturning, especially after degradation of the channel
downstream of the structure; by bending of sheet pile; by erosion and abrasion of wire fabric
in gabions or rock-and-wire mattress; or by any number of structural causes for failure.
8.6.9 Jack or Tetrahedron Fields
Jacks and tetrahedrons function as flow control measures by reducing the water velocity
along a bank, which in turn results in an accumulation of sediment and the establishment of
vegetation. Steel jacks, or Kellner jacks which consist of six mutually perpendicular arms
rigidly fixed at the midpoints and strung with wire are the most commonly used (see Section
8.3). Tetrahedrons apparently are not currently used by DOTs. Jacks are usually deployed
in fields consisting of rows of jacks tied together with cables.
Four sites where steel jack fields were used are included in the case histories. At two sites,
the jack fields performed satisfactorily. Jacks were buried in the streambed and rendered
ineffective at one site, and jacks were damaged by ice at one site, but apparently continued
to perform satisfactorily. From Keeley's (1971) observations of the performance of jack fields
used in Oklahoma and findings of the study of countermeasures by Brice and Blodgett
(1978), the following conclusions were reached regarding performance:
C The probability of satisfactory performance of jack fields is greatly enhanced if the
stream transports small floating debris and sediment load in sufficient quantity to form
accumulations during the first few years after construction.
C Jack fields may serve to protect an existing bank line, or to alter the course of a stream if
the stream course is realigned and the former channel backfilled before the jack field is
installed.
C On wide shallow channels, which are commonly braided, jack fields may serve to shift
the bank line channelward if jacks of large dimensions are used.
8.6.10 Special Devices for Protection of Piers
Countermeasures at piers have been used to combat abrasion of piers, to deflect debris, to
reduce local scour, and to restore structural integrity threatened by scour. Retrofit
countermeasures installed after problems develop are common. The usual countermeasure
against abrasion consists of steel armor on the upstream face of a pier in the area affected
by bed load. At one site, a pointed, sloping nose on a massive pier, called a special
"cutwater" design, and a concrete fender debris deflector has functioned to prevent debris
accumulation at the pier. At another site, a steel rail debris deflector worked until channel
degradation caused all countermeasures to fail.
Countermeasures used to restore structural integrity of bridge foundations included in the
case histories include underpinning, sheet pile driven around the pier, and a grout curtain
around the pier foundation.
8.20
8.6.11 Channel Alterations
Although channel alterations or modifications have been curtailed due to environmental
concerns, their judicious use can be a viable countermeasure not to be dismissed. It is
recognized that extensive channelization projects, usually made to reduce floodplain
damage, have resulted in serious channel degradation and lateral erosion. However, there
is little documentation of upstream or downstream environmental damage of an alteration of
a short reach in the vicinity of a bridge (Brice and Blodgett 1978).
In a United States Geological Survey study for FHWA of 103 stream channels that were
altered for purpose of bridge construction mostly during the period of 1960-1970, the stability
of the relocated channel was rated as good at 36 sites, as fair to good at 42 sites, as fair at
15 sites, and as poor at 7 sites. In comparison with bank stability of the channels where such
data was available before and after relocation, bank stability was about the same at 45 sites,
better at 28 sites, and worse at 14 sites. At sites where the value of channel relocation
length to channel width was below 100, the effects of length of channel relocation were
dominated by other factors (Brice 1981) (see Section 8.5).
8.6.12 Modification of Bridge Length and Relief Structures
A countermeasure for contraction scour and lateral movement of stream banks that may not
always be considered for an existing bridge but may be needed is to increase its length.
Increased bridge length was used at 11 sites and increased freeboard was provided at 2
sites.
Other techniques that have been used by State DOTs include the design of abutments
as piers so that the bridge may be extended to accommodate future movement of the
stream. Other means of providing additional relief to flow would be the use of a relief bridge.
8.6.13 Investment in Countermeasures
While it may be possible to predict that bank erosion will occur at or near a given location in
an alluvial stream, one can frequently be in error about the location or magnitude of potential
erosion. At some locations, unexpected lateral erosion occurs because of a large flood, a
shifting thalweg, or from other actions of the stream or activities of man. Therefore, where
the investment in a highway crossing is not in imminent danger of being lost, it is often
prudent to delay the installation of countermeasures until the magnitude and location of the
problem becomes obvious. In many, if not most, of the case histories collected by Brice et
al., DOTs invested in countermeasures after a problem developed rather than in anticipation
of a problem (Brice and Blodgett 1978, Brice 1984).
9.1
CHAPTER 9
SCOUR MONITORING AND INSTRUMENTATION
9.1 INTRODUCTION
There are many scour critical bridges on spread footings or shallow piles in the United
States and a large number of bridges with unknown foundation conditions (Lagasse et al.
1995). With limited funds available, these bridges cannot all be replaced or repaired.
Therefore, they must be monitored and inspected following high flows. During a flood, scour
is generally not visible and during the falling stage of a flood, scour holes generally fill in.
Visual monitoring during a flood and inspection after a flood cannot fully determine that a
bridge is safe. Instruments to measure or monitor maximum scour would resolve this
uncertainty. As introduced in Chapter 2 (Section 2.3), monitoring as a countermeasure for a
scour critical bridge involves two basic categories of instruments: portable instruments and
fixed instruments.
Whether to use fixed or portable instruments in a scour monitoring program depends on
many different factors. Unfortunately, there is not one type of instrument that works in every
situation encountered in the field. Each instrument has advantages and limitations that
influence when and where they should be used. The idea of a toolbox, with various
instruments that can be used under specific conditions, best illustrates the strategy to use
when trying to select instrumentation for a scour monitoring program. Specific factors to
consider include the frequency of data collection desired, the physical conditions at the
bridge and stream channel, and traffic safety issues.
Fixed instrumentation is used when frequent measurements or regular, ongoing monitoring
(e.g., weekly, daily, or continuous) are required. Portable instruments would be preferred
when only occasional measurements are required, such as after a major flood, or when
many different bridges must be monitored on a relatively infrequent basis. The physical
conditions at the bridge, such as height off the water and type of superstructure, can
influence the decision to use fixed or portable equipment. For example, bridges that are
very high off the water, or that have large deck overhang or projecting geometries, would
complicate portable measurements from the bridge deck. Making portable measurements
from a boat assumes that a boat ramp is located near the bridge, and/or there are no issues
with limited clearance under the bridge that would prohibit safe passage of a boat. Bridges
with large spread footings or pile caps, or those in very deep water can complicate the
installation of some types of fixed instruments. Stream channel characteristics include
sediment and debris loading, air entrainment, ice accumulation, or high velocity flow, all of
which can adversely influence various measurement sensors used in fixed or portable
instruments. Traffic safety issues include the need for traffic control or lane closures when
either installing or servicing fixed instruments, or attempting to make a portable
measurement from the bridge deck.
It is apparent that the selection of the instrument category (fixed or portable) and the specific
instrument types to be used in a monitoring plan is not always straightforward. In some
situations there is no clearly definable plan that will be successful, and the monitoring plan is
developed knowing that the equipment may not always work as well as might be desired.
Ultimately, the selection of any type of instrumentation must be based on a clear
understanding of its advantages and limitations, and in consideration of the conditions that
exist at the bridge and in the channel.
9.2
To improve the state-of-practice when adopting fixed instrumentation as a countermeasure,
the Transportation Research Board (TRB) under the National Cooperative Highway
Research Program (NCHRP) completed NCHRP Project 21-3 "Instrumentation for
Measuring Scour at Bridge Piers and Abutments" in 1997 (Lagasse et al. 1997, Schall et al.
1997a, 1997b). NCHRP Project 21-7, "Portable Scour Monitoring Equipment," was
completed in 2004 and developed an articulated arm truck as a platform for deploying a
variety of portable scour monitoring instruments (Schall and Price 2004). In addition, to
facilitate the technology transfer of instrumentation-related research to the highway industry,
particularly those in inspection and maintenance operations, the Federal Highway
Administration (FHWA) developed a Demonstration Project (DP97) on scour monitoring and
instrumentation. The purpose of Demonstration Project 97 was to promote the use of new
and innovative equipment, both fixed and portable, to measure scour, monitor changes in
scour over time, detect the extent of past scour, and serve as countermeasures (FHWA
1998, Ginsberg and Schall 1998). This chapter provides information on the use of portable
and fixed instrumentation for scour monitoring. The portable instrument discussion includes
lessons learned from NCHRP 21-7 and concepts developed during DP97. The fixed
instrument discussion includes results from NCHRP Project 21-3 and highlights fixed
instrument installations completed in the last ten years. Information on implementation and
experience of several State DOTs with scour monitoring instrumentation is also summarized.
9.2 PORTABLE INSTRUMENTATION
9.2.1 Components of a Portable Instrument System
Portable instrumentation is typically used when a fixed instrument has not been installed at a
bridge; however, portable instruments are also useful when it is necessary to supplement
fixed instrument data at other locations along the bridge. Physical probing has been used
for many years as the primary method for portable scour monitoring by many DOTs. More
recently, sonar has seen increased use, in part due to the technology transfer provided
through FHWA's Demonstration Project 97 (FHWA 1998). The use of these methods during
low-flow conditions has been very successful, for example during the 2-year inspection
cycle; however, their success during flood conditions, when the worst scour often occurs,
has been more limited. When appropriate, portable instrumentation is an important part of a
scour monitoring program.
A portable scour measuring system typically includes four components (Mueller and Landers
1999):
1. Instrument for making the measurement
2. System for deploying the instrument(s)
3. Method to identify and record the horizontal position of the measurement
4. Data-storage device
9.2.2 Instrument for Making the Measurement
A wide variety of instruments have been used for making portable scour measurements. In
general, the methods for making a portable scour measurement can be classified as:
1. Physical probing
2. Sonar
3. Geophysical
9.3
Physical Probes. Physical probes refer to any type of device that extends the reach of the
inspector, the most common being sounding poles and sounding weights. Sounding poles
are long poles used to probe the bottom (Figure 9.1). Sounding weights, sometimes
referred to as lead lines, are typically a torpedo shaped weight suspended by a
measurement cable (Figure 9.2). This category of device can be used from the bridge or
from a boat. An engineer diver with a probe bar is another example of physical probing.
Physical probes only collect discrete data (not a continuous profile), and can be limited by
large depth and velocity (e.g., during flood flow condition) or debris and/or ice accumulation.
Advantages of physical probing include not being affected by air entrainment or high
sediment loads, and it can be effective in fast, shallow water.
Sonar. Sonar instruments (also called echo sounders, fathometers or acoustic depth
sounders) measure the elapsed time that an acoustic pulse takes to travel from a generating
transducer to the channel bottom and back (FHWA 1998). Sonar is an acronym for SOund
NAvigation and Ranging that was developed largely during World War II. However, early
sonar systems were used during World War I to find both submarines and icebergs and
called ASDICs (named for the Antisubmarine Detection Investigation Committee). As
technology has improved in recent years better methods of transmitting and receiving sonar
and processing the signal have developed, including the use of digital signal processing
(DSP). The issues of transducer frequency (typically around 200 kHz) and beam width are
important considerations in the use of sonar for scour monitoring work. Additionally, sonar
may be adversely impacted by high sediment loads or air entrainment.
Applications of single beam sonar range from fish finders to precision survey-grade
hydrographic survey fathometers. Low-cost fish-finder type sonar instruments have been
widely used for bridge scour investigations (Figure 9.3) with a tethered float to deploy the
transducer. Float platforms have included kneeboards (Figure 9.4) and pontoon-style floats
(Figure 9.5).
Other types of sonar, such as side scan, multi-beam and scanning sonar, are specialized
applications of basic sonar theory. These devices are commonly used for oceanographic
and hydrographic survey work, but have not been widely utilized for portable scour
monitoring. Side scan sonar transmits a specially shaped acoustic beam to either side of the
support craft. These applications often deploy the transducer in a towfish, normally
positioned behind and below the surface vessel.
While side scan sonar is one of the most accurate systems for imaging large areas of
channel bottom, most side scan systems do not provide depth information. Multi-beam
systems provide a fan-shaped coverage similar to side scan, but output depths rather than
images. Additionally, multi-beam systems are typically attached to the surface vessel, rather
than being towed. Scanning sonar works by rotation of the transducer assembly or sonar
"head," emitting a beam while the head moves in an arc. Since the scanning is accomplished
by moving the transducer, rather than towing, it can be used from a fixed, stationary position.
Scanning sonar is often used as a forward looking sonar for navigation, collision avoidance
and target delineation.
The Sonar Scour Vision system was developed by American Inland Divers, Inc (AIDI) using
a rotating and sweeping 675 Khz high resolution sonar (Barksdale 1994). The transducer is
mounted in a relatively large hydrodynamic submersible, or fish, that creates a downward
force adequate to submerge the transducer in velocities exceeding 20 ft/s (6 m/s) (Figure
9.6). Given the forces created, the fish must be suspended from a crane or boom truck on
the bridge. From a single point of survey, the system can survey up to 328 ft (100 m)
radially. Data collected along the face of the bridge can be merged into a real-time 3-
dimensional image with a range of 295 ft (90 m) both upstream and downstream of the
bridge.
9.4
Figure 9.1 Sounding pole measurement.
Figure 9.2. Lead-line sounding weight.
9.5
Figure 9.3. Portable sonar in use.
Figure 9.4. Kneeboard float.
9.6
Figure 9.5. Pontoon float.
Figure 9.6. AIDI system (Barksdale 1994).
9.7
Geophysical. Surface geophysical instruments are based on wave propagation and reflection
measurements. A signal transmitted into the water is reflected back by interfaces between
materials with different physical properties. A primary difference between sonar and
geophysical techniques is that geophysical methods provide sub-bottom, while sonar can
only "see" the water-soil interface and is not able to penetrate the sediment layer. The main
difference between different geophysical techniques are the types of signals transmitted and
the physical property changes that cause reflections. A seismic instrument uses acoustic
signals, similar to sonar, but at a lower frequency (typically 2-16 kHz). Like sonar, seismic
signals can be scattered by air bubbles and high sediment concentrations. A ground
penetrating radar (GPR) instrument uses electromagnetic signals (typically 60-300 mHz),
and reflections are caused by interfaces between materials with different electrical
properties. In general, GPR will penetrate resistive materials and not conductive materials.
Therefore, it does not work well in dense, moist clays, or saltwater conditions.
The best application of geophysical technology in scour monitoring may be as a forensic
evaluation tool, used after the flood during lower flow conditions to locate scour holes and
areas of infilling. In general, the cost and complexity of the equipment and interpretation of
the data are limiting factors for widespread use and application as a portable scour
monitoring device. These issues have moderated as newer, lower cost GPR devices with
computerized data processing capabilities have been developed. However, GPR may still
be limited by cost and complexity, and often the need for bore hole data and accurate bridge
plan information to properly calibrate and interpret the results.
9.2.3 System for Deploying the Instrument
The system for deploying the scour instrument is a critical component in a successful
portable scour measurement system. In practical application, particularly under flood flow
conditions, the inability to properly position the instrument is often the limiting factor in
making a good measurement. The use of different measurement technologies from different
deployment platforms can produce a wide variety of alternative measurement approaches.
Deployment methods for portable instruments can be divided into two primary categories:
1. From the bridge deck
2. From the water surface
Bridge Deck Deployment. Bridge deck deployment can be defined by two categories, non-
floating and floating. Non-floating systems generally involved standard stream gaging
equipment and procedures, including the use of various equipment cranes and sounding
weights for positioning a sensor in the water. This category could also include devices that
use a probe or arm with the scour measurement device attached to the end. Probes or arms
include things as simple as an extendable pole or rod (such as a painter's pole), to a
remotely controlled articulated arm. Hand held probes or arms are not generally useable at
flood flow conditions.
A prototype articulated arm to position a sonar transducer was developed under an FHWA
research project (Bath 1999). An onboard computer calculated the position of the transducer
based on the angle of the boom and the distance between the boom pivot and transducer.
Additionally, the system could calculate the position of the boom pivot relative to a known
position on the bridge deck. The system was mounted on a trailer for transport and could be
used on bridge decks from 16 - 50 ft (5 - 15 m) above the water surface (Figure 9.7). Field
testing during the 1994 floods in Georgia indicated that a truck mounted system would
provide better maneuverability, and that a submersible head or the ability to raise the boom
pivot was necessary to allow data collection at bridges with low clearance (less than 16 ft (5
m)).
9.8
Figure 9.7. FHWA articulated arm in use.
NCHRP Project 21-7 (Schall and Price 2004) resulted in a truck mounted articulated arm to
facilitate portable scour measurements during flood conditions (Figure 9.8). The truck was
designed to operate in high velocity flow while providing accurate positioning information and
efficient data collection procedures. These measurements can be completed from a variety
of bridge geometries including limited clearance, overhanging geometry, and high bridges.
Scour measurement can be by a streamlined sonar probe, sounding weights, kneeboards, or
physical probing. A dual winch system was developed to facilitate cable suspended
operations. Crane location is tracked by a variety of sensors installed on the articulated arm,
and by a survey wheel on the back of the truck. Data loggers manage data, and a laptop is
used for data reduction. Sonar data and positioning data collected at the end of the crane
are transmitted by a wireless link that eliminates any wires from the water surface to the
truck (Figure 9.9).
Figure 9.8. NCHRP 21-3 articulated arm truck (Schall and Price 2004).
9.9
Figure 9.9. Sonar instrument deployed from articulated arm truck.
Float based systems permit measurement beneath the bridge and along side the bridge
piers. Tethered floats are a low-cost approach that have been used with some success
during flood flow conditions. A variety of float designs have been proposed and used to
varying degrees for scour measurements, typically to deploy a sonar transducer. Common
designs include foam boards, PVC pontoon configurations, spherical floats, water skis and
kneeboards (FHWA 1998). The size of the float is important to stability in fast moving,
turbulent water.
Floating or non-floating systems can be also be deployed from a bridge inspection truck, an
approach that is particularly useful when the bridge is high off the water. For example,
bridges that are greater than 50 ft (15 m) off the water are typically not accessible from the
bridge deck without using this approach.
Water Surface Deployment. Water surface deployment typically involves a manned boat,
however, safety issues under flood conditions have suggested the use of unmanned vessels.
The use of manned boats generally requires adequate clearance under the bridge and
nearby launch facilities. This can be a problem at flood conditions when the river stage may
approach or submerge the bridge low chord, and/or boat ramps may be underwater.
Smaller boats may be easier to launch, but safety at high flow conditions may dictate use of
a larger boat, further complicating these problems.
When clearance is not an issue, the current and turbulence in the bridge opening may be
avoided using one of the tethered floating or nonfloating methods described above from a
boat positioned upstream of the bridge. For example, a pontoon or kneeboard float with a
sonar transducer could be maneuvered into position from a boat holding position upstream
of the bridge, thereby avoiding the current and turbulence problems at the bridge itself.
The safety, launching and clearance issues have suggested that an unmanned or remote
control boat might be a viable alternative. A prototype unmanned boat using a small flat
bottom jon boat and an 8 hp outboard motor with remote controls (Figure 9.10) was
successfully tested during six flood events (Mueller and Landers 1999).
9.10
Figure 9.10. Unmanned, remote control boat.
9.2.4 Positioning Information
In order to evaluate the potential risk associated with a measured scour depth it is necessary
to know the location of the measurement, particularly relative to the bridge foundation.
Location measurements can range from approximate methods, such as "3 ft (1 m) upstream
of pier 3," to precise locations based on standard land and hydrographic surveying
technology.
The most significant advancement for portable scour measurement positioning may be in the
use of Global Positioning Systems (GPS). GPS is a positioning system based on a
constellation of satellites orbiting the earth. An advantage of GPS over traditional land-
based surveying techniques is that line-of-sight between control points is not necessary. A
GPS survey can be completed between control points without having to traverse or even see
the other point. GPS also works at night and during inclement weather, which could be a
real advantage for scour monitoring during flood conditions. The most significant
disadvantage of GPS is the inability to get a measurement in locations where overhead
obstructions exist, such as tree canopy or bridge decks. However, GPS measurements up
to the bridge face, without venturing under the bridge, have been successful.
9.11
9.2.5 Data Storage Devices
Portable scour monitoring data are typically manually recorded in a field book, however,
there has been a growing interest in more automated data collection using various data
storage devices. Available data storage devices include hydrometeorological data loggers,
laptop computers and more recently palm computers and organizers. Data loggers provide
a compact storage device, however, they are generally not very user friendly with each
company typically having a unique programming language and approach. In field
applications, laptop computers are bulky and need to be ruggedized to survive the rain, dirt
and dust of a field environment. Palm computers and organizers may have an application as
their capability and user-friendliness continue to improve. The advantage of laptop
computers and palm computers is the ability to integrate data reduction software, such as
plotting or topographic mapping programs to display the results, often in real time mode
while the data collection occurs.
9.3 FIXED INSTRUMENTATION
9.3.1 NCHRP Project 21-3
The basic objective of NCHRP Project 21-3 was to develop, test, and evaluate fixed
instrumentation that would be both technically and economically feasible for use in
measuring or monitoring maximum scour depth at bridge piers and abutments (Lagasse et
al. 1997). The scour measuring or monitoring device(s) were required to meet the following
mandatory criteria.
Mandatory Criteria
C Capability for installation on or near a bridge pier or abutment
C Ability to measure maximum scour depth within an accuracy of 1 ft ( 0.3 m)
C Ability to obtain scour depth readings from above the water or from a remote site
C Operable during storm and flood conditions
Where possible, the devices should meet the following desirable criteria:
Desirable Criteria
C Capability to be installed on most existing bridges or during construction of new bridges
C Capability to operate in a range of flow conditions
C Capability to withstand ice and debris
C Relatively low cost
C Vandal resistant
C Operable and maintainable by highway maintenance personnel
Since the mandatory criteria required that the instruments be capable of installation on or
near a bridge pier or abutment, the research was limited to fixed instruments only. While the
research was conducted in phases, a final project report was prepared to integrate and
summarize the findings, interpretation, conclusions and recommendations for the total
research effort (Lagasse et al. 1997). A separate Installation, Operation, and Fabrication
Manual was developed for both the magnetic sliding collar device and low-cost sonic
instrument system that resulted from this research (Schall et al. 1997a, 1997b).
9.12
9.3.2 Scour Measurement
Although a vast literature exists relating to bridge scour, relatively few reports deal
specifically with instrumentation. The final report for NCHRP Project 21-3 includes an
extensive bibliography on equipment for scour measurement and monitoring (Lagasse et al.
1997). A detailed survey of the evolution of scour measuring instrumentation was presented
at the Transportation Research Board Third Bridge Engineering Conference in 1991
(Lagasse et al. 1991). This section summarizes the development of scour measuring
equipment and techniques that had particular relevance to the instrumentation developed
under the NCHRP project.
Major advances in instrumentation such as sonar, sonic sounders, electronic positioning
equipment, and radar occurred during World War II. By the mid 1950s, many devices
became commercially available and were introduced into scientific studies of rivers. A dual
channel sonic stream monitor was used in the 1960s to study alluvial channel bed
configurations and the scour and fill associated with migrating sand waves. Commercial
sonic sounders became available about the same time and soon were used extensively in
hydrographic surveys.
In the 1970s, many scour studies were undertaken in New Zealand. One of the instruments
used in the field to measure maximum scour depth at bridge piers was called the
"Scubamouse." The device consists of a vertical pipe buried or driven into the streambed in
front of the bridge pier around which is placed a horseshoe-shaped collar that initially rests
on the streambed. The collar slides down the pipe and sinks to the bottom of the scour hole
as scour progresses during a flood. The position of the collar is determined by sending a
detector down the inside of the pipe after the flood. Earlier models involved a metal detector
inside a PVC pipe, but the pipe was sometimes damaged by debris, so the current models
use a steel pipe, a radioactive collar, and a radiation detector inside the pipe. This device
has been installed on many bridges in New Zealand (Melville et al. 1989).
In the United Kingdom, Hydraulic Research Limited of Wallingford has developed and
deployed a buried rod instrument system to monitor bed scour during flood events (Waters
1994). This 'Tell Tail' scour monitoring system is based on omni-directional motion sensors,
buried in the river or sea bed adjacent to the structure. The sensors are mounted on flexible
'tails' and are connected to the water surface via protected cables. Under normal flow
conditions, the detectors remain buried and do not move. When a scour hole develops, the
sensors are exposed and transmit alarm signals to the surface.
In the early 1990s, there were no accepted methods or off-the-shelf equipment for collecting
scour data in the United States. In part, this was because there had been no coordinated
long-term effort to study scour processes. Also, most scour studies were site-specific and
the equipment and techniques that were used were tailored to the geometry of the site and
its hydrology and hydraulic conditions. The Brisco Monitor, a sounding rod device, was
available, but had not been tested extensively in the field.
Scour studies in the United States were carried out with a great variety of portable
equipment and techniques, and, through the U.S. Geological Survey (USGS) National Scour
Study, conducted in cooperation with the Federal Highway Administration (FHWA), efforts
were made to standardize the collection of scour data (Landers and Trent 1991).
Techniques for determining the extent of local scour include the use of divers and visual
inspection, direct measures of scour with mechanical and electronic devices, and indirect
observations using ground-penetrating radar and other geophysical techniques (Gorin and
Haeni 1989).
9.13
In the early 1990s, the USGS investigated the use of fixed instruments for scour
measurement at a new bridge on U.S. Highway 101 across Alsea Bay near Walport,
Oregon. Depth soundings were made using commercially available sonic sounders. The
transducers for sounding were mounted on brackets attached to the piers and pointed out
slightly to avoid interference from the side of the pier. The system worked well, but the
installation was not subject to debris, ice, or air entrainment from highly turbulent flows
(Crumrine et al. 1996).
The initial literature search on scour instrumentation in 1990 revealed, and a resurvey of
technology in 1994 confirmed, that fixed scour-measuring and -monitoring instruments can
be grouped into four broad categories:
1. Sounding rods - manual or mechanical device (rod) to probe streambed
2. Buried or driven rods - device with sensors on a vertical support, placed or driven into
streambed
3. Fathometers - commercially available sonic depth finder
4. Other Buried Devices - active or inert buried sensor (e.g., buried transmitter)
As a result of the literature review a laboratory testing program was designed to test at least
one device from each category and to select devices for field testing that would have the
greatest potential for meeting mandatory and desirable criteria.
9.3.3 Summary of NCHRP Project 21-3 Results
No single methodology or instrument can be utilized to solve the scour monitoring problems
for all situations encountered in the field. Considering the wide range of operating conditions
necessary, environmental hazards such as debris and ice, and the variety of stream types
and bridge geometries encountered in the field, it is obvious that several instrument systems
using different approaches to detecting scour will be required.
Under NCHRP Project 21-3, a variety of scour measuring and monitoring methods were
tested in the laboratory and in the field, including sounding rods, driven rod devices,
fathometers, and buried devices. Two instrument systems, a low-cost bridge deck (above
water) serviceable fathometer and a magnetic sliding collar device using a driven rod
approach were installed under a wide range of bridge substructure geometry, flow, and
geomorphic conditions. Both instrument systems met all of the mandatory criteria and most
of the desirable criteria established for the project and were considered fully field deployable
in 1997.
The Installation, Operation, Fabrication Manuals for the low-cost sonic system and magnetic
sliding collar devices (Schall et al. 1997a, 1997b) provide complete instrument
documentation, including specifications and assembly drawings. That information, together
with the findings, appraisal, and applications information of the final report (Lagasse et al.
1997), provide a potential user of a scour monitoring device complete guidance on selection,
installation, operation, maintenance, and if desired, fabrication of two effective systems, one
of which could meet the need for a fixed scour instrument at most sites in the field.
Of the devices tested extensively in the field, the low-cost sonic system and the manual-
readout sliding collar device are both vulnerable to ice and debris; however, both proved to
be surprisingly resistant to damage from debris or ice impact at field test sites. The sonic
system can be rendered inoperative by the accumulation of debris, and presumably ice,
between the transducer face and streambed. The manual-readout sliding collar requires an
extension conduit, generally up the front face of a pier, which can be susceptible to debris or
ice impact damage unless the extension can be firmly anchored to a substructure element.
9.14
From this perspective, the automated sliding collar device has the distinct advantage of
having a configuration which places most of the device below the streambed, and therefore,
less vulnerable to ice or debris. The connecting cable from the device to a data logger on
the bridge deck can be routed through a buried conduit and up the downstream face of a
bridge pier or abutment where it is much less vulnerable to damage. An overview of these
and other operational instrument systems is provided in the next section.
9.3.4 Operational Fixed Instrument Systems
A scour monitoring system at a bridge may be comprised of one or more types of fixed
instruments. The various devices are either mounted on the bridge or installed in the
streambed in the vicinity of the bridge. Remote units with data loggers may be installed so
that the scour measuring device transmits data to the unit. The data from any of these fixed
instruments may be downloaded manually at the site, or it can be telemetered to another
location. The early scour monitoring devices measured streambed elevations using simple
on-site manually read units. The more recent installations use remote technology for data
retrieval. Each bridge may have one or more remote sensor units that transmit data to a
master unit on or near the bridge (Figure 9.11). The scour monitoring data is then
transmitted from the master unit to a central office for data analysis. Remote technology
transmits data by modem using cellular or landline telephones, or by satellite. Recent
installations include systems that post the data on the Internet so that authorized persons
may access the data from any location using a computer with Internet access.
Figure 9.11. Master station with data logger for use with any of the fixed instruments.
Sonars. The sonar scour monitors are mounted onto the pier or abutment face (Figures
9.12 and 13) to take streambed measurements. Currently new sonar monitors range from
fish finders to smart sonar transducers, both of which are commercially available. The sonar
transducer is connected to the sonar instrument or directly to a data logger. The sonar
instrument measures distance based on the travel time of a sound wave through water to the
stream bed and back to the transducer. The data logger controls the sonar system
operation and data collection functions and can be programmed to take measurements at
prescribed intervals. Sonar sensors normally take a rapid series of measurements and use
an averaging scheme to determine the distance from the sonar transducer to the streambed.
These instruments can track both the scour and refill (deposition) processes. The early
sonar monitors used off-the-shelf "fish finders."
9.15
Figure 9.12. Above-water serviceable low-cost fathometer system (Schall et al. 1997b).
9.16
Figure 9.13. Sonar scour monitor installation including remote station and solar panel.
Magnetic Sliding Collars. Magnetic sliding collars (Figures 9.14, 9.15, and 9.16) are rods or
masts that are attached to the face of a pier or abutment and driven or augered into the
streambed. A collar with magnetic elements is placed on the streambed around the rod. If
the streambed erodes, the collar moves or slides down the rod into the scour hole. The
depth of the collar provides information on the scour that has occurred at that particular
location.
The early version of the sliding magnetic collar used a battery operated manual probe that
was inserted down from the top and a buzzer sounded when the probe tip sensed the level
of the magnetics on the collar (Figure 9.14). More recent instruments have a series of
magnetically activated switches inserted in the rod at known distances. Magnets on the steel
collar come into proximity with the switches as the collar slides into the scour hole. The
switches close sequentially as the collar slides by, and their position is sensed by the
electronics (Figures 9.15 and 9.16). A data logger reads the level of the collar via the auto
probe and tracks scour activity. Sonar scour monitors may be used to provide the infill scour
process at a bridge, whereas magnetic sliding collars can only be used to monitor the
maximum scour depth.
Float-out Devices. Buried devices may be active or inert buried sensors or transmitters.
Float-out devices (Figure 9.17) are buried transmitters. This device consists of a radio
transmitter buried in the channel bed at pre-determined depth(s). If the scour reaches that
particular depth, the float-out device floats to the stream surface and an onboard transmitter
is activated. It transmits the float-out device's digital identification number with a radio
signal. The signal is detected by a receiver in an instrument shelter on or near the bridge.
The receiver listens continuously for signals emitted by an activated float-out device. A
decoded interface decodes the activated float-out device's unique digital identification
number that will determine where the scour has occurred. A data logger controls and logs
all activity of the scour monitor. These devices are particularly easy to install in dry
riverbeds, during the installation of an armoring countermeasure such as riprap, and during
the construction of a new bridge. The float-out sensor is a small low-powered digital
electronics position sensor and transmitter. The electronics draws zero current from a
lithium battery which provides a 9-year life expectancy when in the inactive state buried in
the streambed.
9.17
Figure 9.14. Manual read out magnetic sliding collar device (Schall et al. 1997a).
9.18
Figure 9.15. Automated read out magnetic sliding collar system (Schall et al. 1997a).
9.19
Figure 9.16. Detail of magnetic sliding collar on the streambed.
Figure 9.17. Float-out devices prior to installation. Color coded
and numbered for identification purposes.
Tilt Sensors. Tilt sensors (Figure 9.18) measure movements and rotations of the bridge
itself. An X, Y tilt sensor or clinometer monitors the bridge position. Should the bridge be
subject to scour causing one of the support piers or abutments to settle, one of the tilt
sensors would detect the change. A pair of clinometers is installed on the bridge piers or
abutments (Figure 9.19). One tilt meter senses rotation parallel to the direction of traffic (the
longitudinal direction of the bridge), while the other senses rotation perpendicular to traffic
(usually parallel with the stream flow).
9.20
Figure 9.18. Tilt meter on California bridge.
Figure 9.19. Detail of tilt meter.
Time Domain Reflectometers. In Time Domain Reflectometry (TDR) an electromagnetic
pulse is sent down two parallel pipes that are buried vertically in the streambed (Figure 9.20)
(Zabilansky 2002). When the pulse encounters a change in the boundary conditions (i.e.,
the soil-water interface), a portion of the pulse's energy is reflected back to the source from
the boundary. The remainder of the pulse's energy propagates through the boundary until
another boundary condition (or the end of the probe) causes part or all of the energy to be
reflected back to the source. By monitoring the round-trip travel time of a pulse in real time,
the distance to the respective boundaries can be calculated and this provides information on
any changes in streambed elevation. Monitoring travel time in real time allows the
processes affecting sediment transport to be correlated with the change in bed elevation.
Using this procedure, the effects of hydraulic and ice conditions on the erosion of the
riverbed can be documented.
9.21
Figure 9.20. Time domain reflectometry probe.
(Courtesy of USACE Cold Regions Research and Engineering Laboratory)
Sounding Rods. Sounding-rod or falling-rod instruments are manual or mechanical
(automated) gravity based physical probes (Figure 9.21). As the streambed scours, the rod,
with its foot resting on the streambed, drops following the streambed and causing the system
counter to record the change. The foot must be of sufficient size to prevent penetration into
the streambed caused by the weight of the rod and the vibration of the rod from flowing
water. These devices are susceptible to streambed surface penetration in sand bed
channels and this influences their accuracy. Consequently, they are best suited to monitoring
coarse bed streams or riprap stability (as shown in Figure 9.21)
Figure 9.21. Brisco Monitor sounding rods installed at a bridge pier in
New York to monitor movement of riprap (Butch 1996).
9.22
Summary. If recording a series of streambed elevations over time is of interest, sonars,
magnetic sliding collars and sounding rod monitors may be used (only the sonar will record
scour and fill). If a bridge owner is interested only in when a certain streambed elevation is
reached, float-outs may be employed. For specific information on a pier or abutment, tilt
sensors record relative rotation and movement of the structure. Additional fixed instruments
may be added to the scour monitoring system to gather information on water elevations,
water velocities and/or temperature readings.
Data from any of these fixed instruments may be downloaded manually at the site, or may
be telemetered to another location. A scour monitoring system at a bridge may use one of
these devices, or include a combination of two or more of these fixed instruments all
transmitting data to a central control center. These types of scour monitors are being used
in a wide variety of climates and temperatures, and in a wide range of bridge and channel
types throughout the United States.
9.3.5 NCHRP Project 20-5
Most of the information in Section 9.3.4 is derived from NCHRP Project 20-5 (Topic 36-02)
which was a synthesis study entitled Practices for Monitoring Scour Critical Bridges (Hunt
2008). The study assessed the state of knowledge and practice for fixed scour monitoring of
scour critical bridges. It included a review of the literature and research, and a survey of
transportation agencies and other bridge owners to obtain their experience with fixed scour
monitoring systems.
The study found that 30 of the 50 states use, or have employed fixed scour monitoring
instrumentation for their highway bridges. A total of 120 bridge sites were identified that
have been instrumented with fixed monitors. The five types of fixed instruments being used
in 2007 included sonars, float-outs, tilt meters, magnetic sliding collars and time domain
reflectometers.
The site conditions and the types of bridges that were monitored with fixed scour
instrumentation varied in many aspects. There were small to long span bridges with lengths
ranging from 41 ft (12.5 m) to 12,865 ft (3,921 m). The Average Daily Traffic (ADT) ranged
from 400 to 175,000 vehicles per day, and the bridges were constructed between 1920 and
1986. The site conditions included both riverine and tidal waterways, intermittent to perennial
flows, and water depths ranging from less than 10 to 75 ft (3 m to 30 m). The soil conditions
ranged from clay to gravel, and some had riprap protection.
The scour monitors were installed between 1992 and 2007. The earlier installations included
sounding rods, magnetic sliding collars and sonars. More recent installations also include
float-outs, tilt sensors and TDRs. The sonar scour monitoring system is the most commonly
used device, installed at 70 of the 120 bridge sites. This was followed by the magnetic sliding
collar at 21 sites. The bridge owners reported that 90% of the structures monitored with
fixed instruments were piers. The remaining devices were on abutments, or in the vicinity of
the bridge on bulkheads or downstream countermeasure protection.
The survey respondents indicated that high velocity flows, debris, ice forces, sediment
loading and/or low water temperatures were extreme conditions that were present at the
monitored bridge sites. The debris and ice forces caused the majority of damage and
interference to the scour monitoring systems. They noted that the extent and frequency of
the damage was often not anticipated by the bridge owner and this resulted in much higher
maintenance and repair costs than anticipated.
9.23
The bridge owners provided information on their future needs for improved scour monitoring
technology which include:
More robust devices increased reliability and longevity
Decreased costs
Less maintenance
Devices more suitable for larger bridges
Devices that measure additional hydraulic variables and/or structural health
9.3.6 Application Guidelines
Bridge Pier and Abutment Geometry. It is clear that no single device is applicable to all
bridge pier and abutment geometries. However, most bridge geometries can be
accommodated with one of the scour measuring devices described in Section 9.3.4.
Most instruments are adaptable in some degree to vertical piers and abutments. Sloping
piers and spill-through abutments present difficulties for most instrument configurations;
however, driven rod instruments, such as the automated sliding collar, that are not fastened
to the substructure can be used on sloping piers and abutments. Adapting scour
instrumentation to a large spread footing or pile cap configuration also presents challenges.
Flow and Geomorphic Conditions. Each class of scour measuring instrument will not be
applicable to all flow and geomorphic conditions. While some limitations stem from the
capabilities of the device itself, some pertain to whether the device is installable given the
geomorphic and flow conditions. For example, sounding rods have not performed well in
sand-bed streams, although the addition of a large base plate to the sounding rod could help
correct the problem, and sonar devices may be best suited for tidal waterways where
problems with debris are not as common as they are for riverine bridges.
All devices using a driven rod configuration (including TDR) will have limitations imposed by
bed and substrate characteristics. Pre-drilling, jetting, or augering may permit installation
under a wide range of conditions, but these techniques may be expensive and could be
difficult over water. The connecting conduit required by the manual-readout sliding collar
device is vulnerable to ice and debris impact, but the instrument proved surprisingly durable
at field test sites with significant debris.
Low-cost fathometers are applicable to a wide range of streambed characteristics and flow
and geomorphic conditions, but ice and debris in the stream can quickly render a fathometer
inoperable. Strategies such as placing the transducer close to the streambed may reduce,
but won't eliminate, the vulnerability of this instrument to ice and debris.
Float out devices are simple to fabricate and relatively inexpensive. Installation in the dry on
an ephemeral stream or where a coffer dam can be installed can be accomplished with
drilling equipment available to most DOTs. Installation under water, however, would be
difficult.
Tilt Meters. Tilt meters are placed on the bridge superstructure and above-water
substructure components making installation easier and less expensive than other fixed
instruments. Tilt meters measure the movement of the bridge itself, therefore the bridge
must be redundant enough to withstand some movement without failure (Avila et al. 1999).
This will allow maintenance forces sufficient time to remotely observe the movement and
9.24
send crews to inspect the bridge and close it, if necessary. However, it is difficult to set the
magnitude of the angle at which the bridge is in danger. Bridges are not rigid structures, and
movement can be induced by traffic, temperature, wind, hydraulic and earthquake loads. It
is necessary to observe the "normal" movement of the bridge and then determine the
"alarm" angle that would provide sufficient time for crews to travel to and close the bridge to
traffic. The California Department of Transportation (Caltrans) has accomplished this by
installing the tilt meters, monitoring normal pier movement for several months (ideally, they
recommend one year), and setting the "alarm" angles based on the unique "signature" of
each monitored pier on any given bridge.
9.4 SELECTING INSTRUMENTATION
Developing the monitoring program in a Plan of Action requires identifying the specific
instruments, portable and/or fixed, and how they will be used to monitor scour. Selection of
the appropriate instrumentation will depend on site conditions (streambed composition,
bridge height off water surface, flow depth and velocity, etc.) and operational limitations of
specific instrumentation (e.g., as related to high sediment transport, debris, ice, specialized
training necessary to operate a piece of equipment, etc.).
Engineering judgment will always be required in designing instrument specifications to
maximize the scour information collected within the given resources. Specific issues related
to the use of either fixed or portable instruments include:
1. For fixed instrumentation, the number and location of instruments will have to be defined,
as it may not be practical or cost effective to instrument every pier and abutment.
2. For portable instrumentation, the frequency of data collection and the detail and accuracy
required will have to be defined, as it may not be possible to complete detailed
bathymetric surveys at every pier or abutment during every inspection.
Some monitoring programs will involve a mix of fixed, portable and geophysical instruments
to collect data in the most efficient manner possible. Furthermore, portable instrumentation
should be used to ground-truth fixed instrumentation to insure accurate results and to
evaluate potential shifting of the location of maximum scour.
Table 9.1 summarizes the advantages and limitations of the various instrumentation
categories. In general, fixed instrumentation is best used when ongoing monitoring is
required, recognizing that the location of maximum scour may not always be where the
instrument was originally installed. This could be the result of geomorphic conditions and
changes in the river over time, or an initial miscalculation when the instrument was installed.
Portable instruments are best used where more areal coverage is required, either at a given
bridge or at multiple bridges. Portable instruments provide flexibility and the capability to
respond quickly to flood conditions; however, if a portable monitoring program becomes
large, collecting data may become very labor intensive and costly. Additionally, deployment
of portable instruments may require specialized platforms, such as trucks with cranes or
booms, or the use of an under bridge inspection truck. Geophysical instrumentation is best
used as a forensic tool, to evaluate scour conditions that existed during a previous flood.
The primary limitation of geophysical equipment is the specialized training and cost involved
in deploying this type of measurement.
9.25
Table 9.1. Instrumentation Summary by Category.
Instrument
Category
Advantages
Limitations
Fixed Continuous monitoring, low
operational cost, easy to use
Maximum scour not at instrument location,
maintenance/loss of equipment
Portable Point measurement or complete
mapping, use at many bridges
Labor intensive, special platforms often
required
Geophysical Forensic investigations Specialized training required, labor
intensive
Positioning Necessary for portable and
geophysical instruments
9.4.1 Portable Instruments
Within the portable instrument category, the use of physical probes is generally limited to
smaller bridges and channels (Table 9.2). It is a simple technology that can be effectively
used by personnel with limited training, but may be of limited use as the flow depth or
velocity increase, such as during flood conditions. Portable sonar instruments may be better
suited for large bridges and channels, but they too can be limited by flow conditions based
on the deployment options available. Sonar may also be limited in high sediment or air
entrainment conditions, or when debris or ice accumulation are present.
Table 9.2. Portable Instrumentation Summary.
Best Application Advantages Limitations
Physical Probes Small bridges and
channels
Simple technology Accuracy, high flow
application
Sonar Larger bridges and
channels
Point data or complete
mapping, accurate
High flow application
Positioning equipment is required to provide location information with any portable or
geophysical measurement (Table 9.3). The approximate methods are useful for any type of
reconnaissance or inspection level monitoring, but are obviously limited by accuracy. The
use of standard land survey techniques, using a total station type instrument or in the case
of hydrographic surveying, an automated range-azimuth type device, can provide very
accurate positional data. However, these instruments require a setup location on the
shoreline that may be difficult to find during flooding, when overbank water and/or riparian
vegetation limit access and line-of-sight. These approaches can also be somewhat slow and
labor intensive. In contrast, the use of GPS provides a fast, accurate measurement, but will
not work under the bridge.
Table 9.3. Positioning System Summary.
Best Application Advantages Limitations
Approximate
methods
Recon or inspection No special training or
equipment
Accuracy
Traditional land
survey methods
Small channels or areal
surveys
Common technique
using established
equipment
Shore station
locations, labor
intensive
GPS Measurement up to
bridge face
Fast, accurate Cannot work under
bridge
9.26
Another important factor in designing a monitoring program is the cost of the instrumentation
and data collection program. Portable instrument costs can be readily identified, but the cost
of installation and operation are more difficult to quantify, since this will depend on site
specific conditions and the amount of data needed. Based on field experience, Table 9.4
provides general guidelines on cost information. These costs should be used cautiously in
an absolute sense, given unique site-specific conditions and/or the changes in cost that can
occur with time and new research and development. This information may be most useful
as a relative comparison between different approaches.
Table 9.4. Estimated Cost Information for Portable Instruments.
Instrument
Cost
Cost for
Installation or
Use
Operation
Cost
Physical Probes < $500 varies by use varies, minimum
2-person crew for safety
Portable Sonar fish-finder - $500;
survey grade - $15,000 +/-
varies by use varies, minimum
2-person crew for safety
Traditional land survey $10,000 +/- varies 2-3 person crew
GPS $5,000 for submeter accuracy,
$20,000 + for centimeter
varies 1-2 person crew
9.4.2 Fixed Instruments
Fixed instrument devices include sonar, sounding rods (automated physical probe),
magnetic sliding collar, float out devices, tilt sensors, and time domain reflectometers (Table
9.5). Based on field experience, the sonar type devices work best in coastal regions and can
be built using readily available components. They provide a time history of scour, yet have
difficulty in conditions with high debris, ice, and air entrainment (Zabilansky 1996).
Therefore, if a sonar device is selected for a riverine environment, these conditions may limit
when data is collected and the quality of the data record.
Table 9.5. Fixed Instrumentation Summary.
Type of Fixed
Instrumentation
Best
Application
Advantages
Limitations
Sonar Coastal regions Records infilling; time history;
can be built with off the shelf
components
Debris, high sediment loading,
ice, and air entrainment can
interfere with readings
Magnetic Sliding Collar Fine bed channels Simple, mechanical device Vulnerable to ice and debris
impact; only measures
maximum scour; unsupported
length, binding
Tilt Sensors All May be installed on the bridge
structure and not in the stream-
bed and/or underwater
Provides bridge movement
data which may or may not be
related to scour
Float-Out Device Ephemeral
channels
Lower cost; ease of installation;
buried portions are low main-
tenance and not affected by
debris, ice or vandalism
Does not provide continuous
monitoring of scour; battery life
Sounding Rods Coarse bed
channels
Simple, mechanical device Unsupported length, binding,
augering
Time Domain
Reflectometers
Riverine ice
channels
Robust; resistance to ice,
debris, and high flows
Limit on maximum lengths for
signal reliability of both cable
and scour probe
9.27
Sounding rods, typically a dropping rod with a method to measure the displacement
occurring, have been found to work best in coarse bed channels, and are a simple
mechanical type of device. They have had difficultly in channels with fine sediments where
sediment accumulation around the sliding components has led to binding. Additionally, they
are limited by the maximum amount of travel that the sounding rod can realistically achieve,
given problems with unsupported length vibration and augering. In contrast, the magnetic
sliding collar device works best in fine bed channels, where it is possible to drive the
supporting rod into the streambed. It, too, is a simple mechanical type device, but it is also
limited by concerns with unsupported length, binding and debris.
The float-out type sensors have worked well in ephemeral channels, and are a low-cost
addition to any other type of fixed instrument installation. They have been successfully used
when buried either in the channel bed, or in riprap, and can be placed at locations away from
structural members of the bridge, which may not be possible with the other types of fixed
instruments.
Tilt sensors are installed above water on the bridge superstructure or substructure and may
be used on a wide variety of bridges and sites. They measure overall structure movement
and, therefore, do not have to be located at the specific location of the scour, as is the case
with the other fixed instruments discussed in this chapter. Tilt sensors do not provide
information on scour depths. The bridge must be redundant enough to ensure that when
movement is detected there is enough time to close or repair the bridge. In addition, bridge
movements and rotations may be caused by a variety of load factors, and it may take some
time to establish the "signature" movements particular to a bridge which are not due to
scour.
The fixed instrumentation selection matrix, Table 9.6 was developed during the synthesis
study (Hunt 2008) to complement the countermeasure selection matrix (Table 2.1). See
Chapter 2, Section 2.3 for a discussion of the various symbols used in both tables. If fixed
instrumentation is to be used to monitor a bridge, this table provides additional items to be
considered in deciding between the various fixed instrument options. It was developed
based on the results of the synthesis study state survey and literature search (Section 9.3.5).
Table 9.6 includes additional categories for suitable river environment for the various fixed
instruments:
Type of waterway riverine / tidal Bed material
Flow habit Extreme conditions
Water depth
The bridge geometry includes information on the characteristics of the bridges for the
different types of instruments:
Foundation type
The table includes additional items regarding the monitoring system capabilities which may
be mandatory or desirable criteria for a particular bridge site:
Continuous data monitoring
Remote technology
Additional river environment factors listed in Table 2.1 (river type, stream size, bend radius,
bank slope, and floodplain) are not listed in Table 9.6 as they do not directly influence the
selection of fixed instrumentation.
9.28
9.29
The installation experience by state for each type of fixed monitor for those that responded
to the synthesis survey (Section 9.3.5) and also from the literature search are included in the
last two columns of Table 9.6.
The cost of fixed instrumentation and the data collection program is an important factor in
the selection process. Table 9.7 provides general guidelines on cost information. This table
may be used with Table 9.4 for portable instruments to compare relative cost information
between the different monitoring approaches. As with portable instruments, the most
quantifiable cost for fixed instrumentation is the equipment cost. The installation, operation,
maintenance and repair costs are more difficult to ascertain.
Table 9.7. Estimated Cost Information for Fixed Instruments.
Typed of Fixed
Instrumentation
Instrument Cost
with Remote
Technology ($)
(1)
Instrument Cost for
Each Additional
Location ($)
Installation Cost Maintenance/
Operation Costs
Sonar 12,000 - 18,000 10,000 - 15,500 Medium to high; 5 to 10-
person days to install
Medium to High
Magnetic Sliding
Collar
13,000 15,500 10,500 12,500 Medium, minimum 5-person
days to install
Medium
Tilt Sensors 10,000 11,000 8,000 9,000 Low Low
Float-Out
Device
10,100 10,600 1,100 1,600 Medium; varies with number
installed
Low
Sounding Rods 7,500 10,000 7,500 10,000 Medium; minimum 5-person
days to install
High
Time Domain
Reflectometers
5,500 21,700 500 Low Medium
(1)
Cost per device will decrease when multiple devices share remote stations and/or the master station.
Instrument costs generally include the basic scour monitoring instrument and mounting
hardware, as well as power supply, data logger and instrument shelter/enclosure, where
applicable. This cost may not include miscellaneous items to install the equipment such as
electrical conduit, brackets and anchor bolts which may be included as part of the contractor
installation cost.
The cost of the scour monitoring installations can vary dramatically due to different factors
such as site conditions, the group and/or the experience of the personnel installing the
equipment, the type of contract, and the installation requirements. Larger bridges and
deeper waterways are more expensive to instrument than smaller bridges in ephemeral or
low water crossings. Scour monitors may be installed at certain sites by the state
maintenance group, or another agency with equipment they own, or by students. More
complicated installations and sites may require specialized contractors and construction
equipment to install the scour monitoring devices.
Most recent installations of fixed instrumentation have used remote technology to download
data to avoid repeated visits to the bridge site. Although this increases the initial equipment
cost, it can substantially reduce the long-term operational costs of data retrieval. Site data
retrieval involves sending crews to the bridge and access may include security clearance,
lane or bridge closures, and equipment such as snooper trucks or boats. Remote
technology can also increase safety to the traveling public because it permits real-time
monitoring during the storm events which may result in earlier detection of scour.
9.30
Factors that contribute to increased scour monitoring installation, inspection, maintenance
and repair costs include: larger bridges; complex pier geometries; bridges with large deck
heights off the water; deeper waterways; long distance electrical conduit runs; more durable
materials required for underwater tidal installations; the type of data retrieval required (i.e.,
Internet, satellite); lane or bridge closures and maintenance-of-traffic; and installation and
access equipment such as boats, barges, snooper trucks, drills and diving teams.
9.5 FIXED INSTRUMENT CASE HISTORIES
9.5.1 Introduction
The following case histories were selected for this section because they cover a range of
geographical locations and types of fixed scour monitoring instrumentation. This section
provides descriptions of the systems as well as details on the installations and
implementation of the scour monitoring programs.
9.5.2 Typical Field Installations
Alaska Installations. To better understand the scour process and to monitor bed elevation at
bridge piers, the U.S. Geological Survey (USGS) and the Alaska Department of
Transportation and Public Facilities operate a network of streambed scour-monitoring
stations in Alaska (Conaway 2006a). To date they have instrumented 20 bridges with sonar
and river stage instrumentation (Figure 9.22). In 2007, 16 bridges remained in the scour
monitoring program. These stations provide state engineers with near real-time bed
elevation data to remotely assess scour at bridge piers during high flows. The data also
provide a nearly continuous record of bed elevation in response to changes in discharge and
sediment supply. Seasonal changes as well as shorter duration scour and fill have been
recorded. In addition to the near real-time data, channel bathymetry and velocity profiles are
collected at each site several times per year.
Each bridge is instrumented with a retractable, pier-mounted sonar device. At locations with
multiple scour critical piers, sonar transducers were mounted at each pier. The sonar
transducers were mounted either at an angle on the side of the piers near the nose or on the
pier nose in order to collect data just upstream of the pier footing. Many of Alaska's bridges
are situated in locations too remote for landline or cellular telephone coverage. The scour
monitoring instrumentation on the remote bridges has incorporated Orbcomm, a
constellation of low-earth-orbiting satellites. Data is sent from the bridge to a passing
satellite, which then relays it on to an earth station which then forwards the data to specified
email addresses. The network of scour monitoring sites is dynamic, with locations being
added and removed annually based on monitoring priority and the installation of scour
countermeasures. Instrumentation is subject to damage by high flows, debris and ice, and
repairs at some sites can only be made during low-flow conditions.
In 2002 one sonar scour monitor was installed at the Old Glenn Highway Bridge over the
Knik River near Palmer (Figure 9.23) (Conaway 2006b). There are two bridges that cross
the Knik River at this location. The active bridge was built in 1975, is 505 ft (154 m) in
length, and is supported by two piers. The roadway approaches to the active bridge
significantly contract the channel. Approximately 98 ft (30 m) upstream is the original bridge
which is no longer open to vehicular traffic. Two guide banks extend upstream of both
bridges and route flow through a riprap lined bridge reach. All piers are approximately
aligned with the flow. The Knik River is a braided sand and gravel channel that transports
large quantities of sediment from the Knik Glacier. The braided channel narrows from
approximately 3 mi (4.8 km) wide at the glacier mouth to 0.07 mi (0.12 km) at the Old Glenn
Highway Bridge where the channel is subject to a 4:1 contraction during summer high flows.
9.31
Figure 9.22. Active streambed scour monitoring locations in Alaska (Conaway 2006a).
9.32
Figure 9.23. Oblique aerial photograph of the Knik River Old Glenn Highway bridges during
a summer high flow (Courtesy of U.S. Geological Survey).
The right-bank pier of the new bridge was instrumented with a retractable, pier-mounted
sonar monitor. This retractable arm was designed to prevent ice and debris flows from
damaging the sonar bracket, as had occurred in other scour monitoring installations in
Alaska. Stage data were measured by a nearby USGS stream gage. The sonar was
mounted at an angle on the side of pier near the nose in order to collect data just upstream
of the pier footing. Data are collected every 30 minutes and transmitted every 6 hours via
satellite. When bed elevation or stage thresholds are exceeded, data transmissions
increase in frequency. The Knik River was the only site within the monitoring network that
had large changes in bed elevation each year. Annual scour ranged from 17.2 to 20 ft (5.2
m to 6.0 m). These near real-time data for the Knik River and other sites in Alaska are
available on the USGS website.
New York Installations. NYSDOT has installed twenty-seven sonar scour monitors at three
bridges on the South Shore of Long Island in Nassau and Suffolk Counties in New York
(Hunt 2003). Wantagh Parkway over Goose Creek is a 93 ft (28.3 m) bascule bridge (Figure
9.24), Wantagh Parkway over Sloop Channel was a 576 ft (175.6 m) long bridge, and Robert
Moses Causeway over Fire Island Inlet, a 1,068 ft (326 m) bridge (Figure 9.25). These have
served as both short and long-term solutions to the scour problems at these bridges. In
1998, following a partial pier collapse at Wantagh Parkway over Goose Creek, it was found
that the streambed at one pier had experienced approximately 29 ft (8.8m) of localized scour
since it was built in 1929. In order to ensure that these bascule piers were safe, several
options were investigated and a scour monitoring system and program was designed for the
bridge.
9.33
A nearby bridge, Wantagh Parkway over Sloop Channel was also examined. It was found to
have similar problems with respect to scour of the piers. As a result, four scour monitors
were installed at the bascule piers of Goose Creek, and ten monitors were installed at Sloop
Channel. In addition, a water stage sensor was installed at each bridge. The scour monitors
were approved by NYSDOT within one week of the 1998 failure, and they were designed,
custom-built and arrived at the site ten weeks later. The sonar mounting brackets were
made of stainless steel due to the harsh tidal environment. For data retrieval the system
employed remote telemetry via a modem and telephone landline. The power was supplied
using solar panels for the fixed bridge at Sloop Channel and using the electrical system on
the bascule bridge at Goose Creek.
Figure 9.24. Conduit to sonar scour monitor at Wantagh Parkway
over Goose Creek.
A scour monitoring program and manual were developed for the Wantagh Parkway Bridges.
This was the first procedural manual to be developed for scour monitors. The manual
provided the opportunity to work through various scenarios should these bridges continue to
experience scour. The program included round-the-clock monitoring even during storms. It
included critical streambed elevations for each pier, procedures for normal and emergency
situations, a Plan of Action should certain scour elevations be reached and troubleshooting,
maintenance and servicing instructions. An effective communication system for all
responsible parties was established.
The installation of sonar scour monitors at Robert Moses Causeway over Fire Island Inlet is
a long-term solution to the scour issues at that bridge. The flow rate was estimated to be
over 492,000 cfs (13,932 m
3
/sec) for the 100-year storm. Riprap scour protection had been
placed at some piers over the years, and according to the FHWA guidance, riprap should be
monitored when used as a countermeasure at piers. In 2001, sonar scour monitors were
placed at 13 piers, a water stage sensor was installed, and the Long Island scour monitoring
manual was revised to include the new system. This was a complex design and installation
due to the proximity of the bridge to the Atlantic Ocean, the deep-water conditions, the pier
configurations and the high flow rates. In order to ensure that the underwater sonar
brackets could clear the pier footings to measure the streambed elevations, this design
incorporated a new type of adjustable tripod stainless steel bracket (Figure 9.26).
9.34
Figure 9.25. Solar panel, remote station and (inset) conduit to sonar monitor at Robert
Moses Causeway over Fire Island Inlet.
Figure 9.26. Adjustable stainless steel sonar mounting
bracket prior to underwater installation.
9.35
Summary New York Installations. The scour monitoring systems at Goose Creek and Fire
Island have been in operation for since 1998 and 2001, respectively (Hunt and Price 2004).
When the Sloop Channel Bridge was replaced in 1999, the monitoring system was salvaged
and has been used for spare parts for the other bridges. The scour monitoring program
includes the routine monitoring of these bridges, including data acquisition and analysis;
round-the-clock monitoring during scour critical events; the preparation of bi-weekly graphs
of the streambed elevations and tide gage data; periodic data reduction analyses and
graphs; and routine maintenance, inspection, and repairs. In 2004, a total refurbishment of
the Goose Creek system was completed. This included the installation of the latest operating
system software and a new bracket for the sonar transducer at one monitor location. An
underwater contractor installed the new bracket and also strengthened the scour monitor
mountings at the other three pier locations. The condition of the scour monitors and the
accuracy of their streambed elevation readings are checked during the regularly scheduled
diving inspections at each bridge. Also, substantial marine growth and/or debris on the
underwater components is cleared away during these inspections.
California, Arizona and Nevada Installations. In preparation for El Nio driven storm events,
a variety of instruments were installed at bridges in the southwest in late 1997 and early
1998. Five bridges were instrumented in California, five in Arizona and four in Nevada.
The equipment included automated sliding collar devices, low-cost sonar, multi-channel
sonar, float-out transmitters and sliding rod devices (Figures 9.27 and 9.28). These
installations provided an opportunity to test a number of new concepts, including 2- and 4-
channel sonar devices, application of early warning concepts (by defining threshold scour
levels and automated calls to pagers when that threshold was exceeded), and development
and refinement of the float-out instrument concept.
Figure 9.27. Installation of a sonar scour monitor on Salinas River Bridge near Soledad,
California (Highway 101) by CALTRANS.
9.36
Figure 9.28. Close up of sonar scour monitor on Salinas River Bridge near Soledad, CA.
To support the California, Arizona, and Nevada installations, a buried transmitter float-out
device was developed for application on bridge piers over ephemeral stream systems. As
summarized in Section 9.3.4, this device consists of a radio transmitter buried in the channel
bed at a pre-determined depth. When the scour reaches that depth, the float out device
rises to the surface and begins transmitting a radio signal that is detected by a receiver in an
instrument shelter on the bridge. Installation requires using a conventional drill rig with a
hollow stem auger (Figure 9.29). After the auger reaches the desired depth, the float out
transmitter is dropped down the center of the auger (Figure 9.30). Substrate material refills
the hole as the auger is withdrawn.
The float out device can be monitored by the same type of instrument shelter/data logger
currently being used to telemeter low-cost fathometer or automated sliding collar data. The
instrument shelter contains the data logger, cell-phone telemetry, and a solar panel/gell-cell
battery for power (Figure 9.31). The data logger monitors the sliding collar and sonar scour
instruments, taking readings every hour and transmitting the data once per day to a
computer at a central location (e.g., DOT District). A threshold elevation is defined that,
when reached, initiates a phone call to a pager network. The bridge number is transmitted
as a numeric page, allowing identification of the bridge where scour has occurred. The float
out devices are monitored continuously, and if one of these devices floats to the surface, a
similar call is automatically made to the pager network.
Although the float out devices had not been tested extensively in the field, in late 1997 and
early 1998 more than 40 float-out devices were installed at bridges in Arizona (4 bridges),
California (1 bridge), and Nevada (4 bridges). Most devices were installed at various levels
below the streambed as described above; however, several devices at bridges in Nevada
were buried in riprap at the base of bridge piers to monitor riprap stability (Figure 9.32).
9.37
Figure 9.29. CALTRANS drilling with hollow stem auger for installation of float out devices
at Salinas River Bridge (Highway 101) near Soledad, CA.
Figure 9.30. Installation of float out device on Salinas River Bridge near Soledad, CA.
9.38
Figure 9.31. Typical instrument shelter with data logger, cell-phone telemetry, and a
solar panel/gel-cell for power.
Figure 9.32. Installation of a float out device by Nevada DOT to monitor riprap stability.
9.39
One of the bridges instrumented experienced several scour events that triggered threshold
warnings during February 1998. In one case the automated sliding collar dropped 5 ft (1.5
m) causing a pager call-out. Portable sonar measurements confirmed the scour recorded by
the sliding collar. Several days later, another pager call-out occurred from a float-out device
buried about 13 ft (4 m) below the streambed.
In both cases, the critical scour depth was about 20 ft (6 m) below the streambed. However;
pager call-out was ineffective in alerting maintenance personnel during non-office hours and
no emergency action was called for to insure public and/or bridge safety. Consequently, a
programmed voice synthesizer call-out to human-operated 24-hour communications centers
was implemented at other bridges. This illustrates the importance of effective and well-
defined communication procedures, and the on-going need for comprehensive scour training
at all levels of responsibility.
9.40
(page intentionally left blank)
10.1
CHAPTER 10
REFERENCES
Atayee, A. Tamin, 1993, "Study of Riprap as Scour Protection for Spill Through Abutment,"
presented at the 72nd Annual TRB meeting in Washington, D.C., January.
Avila, C.M.C., Racin, J.A. and Davies, P., 1999, "Talk to Your Bridges and They Will Talk
Back Caltrans Bridge Scour Monitoring Program," Proceedings from the ASCE Hydraulic
Engineering Conference, Seattle, WA.
Ayres Associates Inc, 1999, "A-Jacks Concrete Armor Units Channel Lining and Pier Scour
Design Manual," Prepared for Armortec, Inc., Bowling Green, KY.
Barkdoll, B.D., Ettema, R., and Melville, B.W., 2007, "Countermeasures to Protect Bridge
Abutments from Scour," NCHRP Report 587, Transportation Research Board, National
Academies of Science, Washington, D.C.
Barksdale, G. 1994, "Bridge Scour During the 1993 Floods in the Upper Mississippi River
Basin," proceeding of the 1994 ASCE Hydraulic Engineering Conference.
Bath, W.R., 1999, "Remote Methods of Underwater Inspection of Bridge Structures," FHWA
Report RD-99-100, Turner-Fairbank Highway Research Center, McLean, VA.
Begin, Z.B., 1981, "Stream Curvature and Bank Erosion: A Model Based on the Momentum
Equation," Journal of Geology, Vol. 89, pp. 497-504.
Bentrup, G. and Hoag, J.C., 1998, "The Practical Streambank Bioengineering Guide: User's
Guide for Natural Streambank Stabilization Techniques in the Arid and Semi-Arid Great
Basin and Intermountain West," Interagency Riparian/Wetland Plant Development Project,
USDA Natural Resources Conservation Service.
Bertoldi, D. and Kilgore, R., 1993, "Tetrapods as a Scour Countermeasure, Proceedings
Hydraulic Engineering '93," Vol. 2, 25-30 July 1993, San Francisco, CA, pp. 1385-1390.
Bertoldi, D.A., Jones, S.J., Stein, S.M., Kilgore, R.T., and Atayee, A.T., 1996, "An
Experimental Study of Scour Protection Alternatives at Bridge Piers," FHWA-RD-95-187,
Federal Highway Administration, Washington, D.C.
Blodgett, J.C. and McConaughy, C.E., 1986, "Rock Riprap Design for Protection of Stream
Channels Near Highway Structures," Volume 1 Hydraulic Characteristics of Open
Channels, U.S. Geological Survey, Water Resources Investigations Report 86-4127,
prepared in Cooperation with Federal Highway Administration, Sacramento, CA.
Blodgett, J.C. and McConaughy, C.E., 1986, "Rock Riprap Design for Protection of Stream
Channels Near Highway Structures," Volume 2 Evaluation of Riprap Design Procedures,
U.S. Geological Survey, Water Resources Investigations Report 86-4128, prepared in
Cooperation with Federal Highway Administration, Sacramento, CA.
10.2
Bradley, J.N., 1978, "Hydraulics of Bridge Waterways," Hydraulic Design Series No. 1, U.S.
Department of Transportation, FHWA, Washington, D.C.
Brebner, A., 1978, "Performance of Dolos Blocks in an Open Channel Situation,"
Proceedings 16th Annual Conference on Coastal Engineering, Hamburg, West Germany,
August, pp. 2305-2307.
Brice, J.C., 1981, "Stability of Relocated Stream Channels," FHWA/RD-80/158, Federal
Highway Administration, Washington, D.C., March.
Brice, J.C., 1984, "Assessment of Channel Stability at Bridge Sites," Transportation
Research Record, Vol. 2, No. 950, Transportation Research Board, 2101 Constitution
Avenue, Washington, D.C. 20418.
Brice, J.C. and Blodgett, J.C., 1978, "Countermeasure for Hydraulic Problems at Bridges,
Volumes 1 and 2," FHWA-RD-78-164 and 163, USGS, Menlo Park, CA.
Brown, S.A., 1985, "Streambank Stabilization Measures for Highway Engineers," FHWA/RD-
84/100, Federal Highway Administration, Washington, D.C.
Brown, S.A. and Clyde, E.S., 1989, "Design of Riprap Revetment," Hydraulic Engineering
Circular No.11, FHWA-IP-89-016, prepared for the Federal Highway Administration,
Washington, D.C.
Brown, S.A., R.S. McQuivey, and T.N. Keefer, 1980, "Stream Channel Degradation and
Aggradation: Analysis of Impacts to Highway Crossings," FHWA/RD-80-159, Federal
Highway Administration, Washington, D.C.
Butch, G., 1996, "Evaluation of Scour Monitoring Instruments in New York," 1996 North
American Water and Environment Congress '96--Bridge Scour Symposium, Hydraulics
Division, American Society of Civil Engineers, Anaheim, CA , June 22-28.
Bunte, K. and Abt, S.R., 2001, "Sampling Surface and Subsurface Particle-Size Distributions
in Wadable Gravel- and Cobble-Bed Streams for Analyses in Sediment Transport,
Hydraulics, and Streambed Monitoring," Gen. Tech. Rep. RMRS-GTR-74, U.S. Department
of Agriculture, Forest Service, Rocky Mountain Research Station, Fort Collins, CO, 428 p.
Burns, R.S., Fotherby, L.M., Ruff, J.F., and Carey, J.M., 1996, "Design Example for Bridge
Pier Scour Measures Using Toskanes," Transportation Research Board, Transportation
Research Record 1523, pp. 173-177.
Chiew, Y.M., 1995, "Mechanics of Riprap Failure at Bridge Piers," ASCE Journal of Hydraulic
Engineering, Vol. 121, No. 9, pp. 635-643.
Colson, B.E. and Wilson, K.V., 1973, "Hydraulic Performance of Bridges - Efficiency of
Earthen Spur Dikes in Mississippi," MSHD-RD-73-15-SD, Mississippi State Highway
Department, Jackson, Mississippi, in cooperation with the Federal Highway Administration.
Comit Europen Normalisation (CEN), 2002, "European Standard for Armourstone," Report
prEN 13383-1, Technical Committee 154, Brussels, Belgium.
10.3
Conaway, J.S., 2006(a), "Temporal Variations of Scour and Fill Processes at Selected
Bridge Sites in Alaska," Proceedings from the Federal Interagency Sedimentation
Conference.
Conaway, J.S., 2006(b), "Comparison of Long-Term Streambed Scour Monitoring Data with
Modeled Values at the Knik River, Alaska," Proceedings from the 3
rd
International
Conference on Scour and Erosion, Amsterdam, The Netherlands.
Crumrine, M.D., Lee, K.K., and Kittelson, R.L., 1996, "Bridge-Scour Instrumentation and
Data for Nine Sites in Oregon, 1991-94," U.S. Geological Survey Open-File Report 95-366,
prepared in cooperation with the Oregon Department of Transportation, Portland, OR.
Eisenhauer, N.O. and Rossbach, B. 1999, "Testing the Effectiveness of Scour Counter-
measures by Physical Modeling," Federal Waterways Engineering and Research Institute
(BAW), Karlsruhe, Germany, proceedings of the Transportation Research Board, 5th
International Bridge Engineering Conference, April 3-5, 2000, Tampa, FL.
Escarameia, M., 1998, "River and Channel Revetments - A Design Manual," Environment
Agency R&D Publication 16, Thomas Telford, London.
Federal Highway Administration, 1981, "Standard Specifications for Construction of Roads
and Bridges on Federal Highway Projects," U.S. Department of Transportation, FP-79
(Revised June 1981, Washington D.C.
Federal Highway Administration, 1995, "Recording and Coding Guide for the Structure
Inventory and Appraisal of the Nation's Bridges, Report No. FHWA-PD-96-001, U.S.
Department of Transportation, Washington, D.C.
Federal Highway Administration, 1998, "Scour Monitoring and Instrumentation,"
Demonstration Project 97 Participants Workbook, FHWA-SA-96-036, Office of Technology
Applications, Washington, D.C.
Federal Highway Administration, 2001, "Revision of Coding Guide, Item 113 Scour Critical
Bridges," Memorandum, HIBT-30, April 27, Washington, D.C.
Federal Interagency Stream Restoration Working Group (FISRWG), 1998, "Stream Corridor
Restoration: Principles, Processes, and Practices," U.S. Dept. of Commerce, National
Technical Information Service, Washington, D.C.
Fotherby, L.M., 1992, "Footings, Mats, Grout Bags, and Tetrapods; Protection Methods
Against Local Scour at Bridge Piers," MS Thesis, Colorado State University, Fort Collins,
CO.
Fotherby, L.M., 1993, "Alternatives to Riprap for Protection Against Local Scour at Bridge
Piers," Transportation Research Record 1420, pp. 32-38.
Fotherby, L.M., 1995, "Scour Protection at Bridge Piers: Riprap and Concrete Armor Units,"
Ph.D. Dissertation, Colorado State University, Fort Collins, CO.
Fotherby, L.M. and Ruff, J.F., 1998, "Sizing Riprap and Concrete Armor Units at Bridge
Piers," Transportation Research Board, 77th Annual Meeting, 11-15 January 1998,
Washington, D.C., Paper No. 980633.
10.4
Fotherby, L.M. and Ruff, J.F., 1999, "Riprap and Concrete Armor to Prevent Pier Scour," In:
Richardson, E.V. and Lagasse, P.F. (Eds.), Stream Stability and Scour at Highway Bridges,
Compendium of Papers ASCE Water Resources Engineering Conferences 1991 to 1998,
pp. 893-904.
Freeman, G.E. and Fischenich, J.C., 2000, "Gabions for Streambank Erosion Control,"
EMRRP Technical Notes Collection, ERDC TN-EMRRP-SR-22, U.S. Army Engineer
Research and Development Center, Vicksburg, MS.
Galay, V.J., Yaremko, E.K, and Quazi, M.E., 1987, "River Bed Scour and Construction of
Stone Riprap Protection," in Hey, R.D., Bathurst, J.C., and Thorne, C.R. (Eds.), Sediment
Transport in Gravel-Bed Rivers, John Wiley & Sons Ltd., pp. 353-383.
Ginsberg, A. and Schall, J.D., 1998, "Impact of Scour Monitoring and Instrumentation in the
United States," ASCE, Proceedings of Water Resources Engineering '98, Memphis, TN,
August 3-7.
Gorin, S.R. and Haeni, F.P., 1989, "Use of Surface-Geophysical Methods to Assess
Riverbed Scour at Bridge Piers," Water Resources Investigations Report 88-4212, U.S.
Geological Survey, Reston, Virginia, Water Resources Div., in cooperation with Federal
Highway Administration, Hartford, CT, 33 pp.
Gray, D.H. and Sotir, R., 1996, "Biotechnical and Soil Bioengineering Slope Stabilization,"
John Wiley and Sons, New York, NY.
Harris County Flood Control District, 2001, "Design Manual for Articulating Concrete Block
Systems," prepared by Ayres Associates, Project No. 32-0366.00, Fort Collins, CO.
Heibaum, M.H., 2000, "Scour Countermeasures Using Geosynthetics and Partially Grouted
Riprap," Federal Waterways Engineering and Research Institute (BAW), Karlsruhe,
Germany, proceedings of the Transportation Research Board, 5
th
International Bridge
Engineering Conference, April 3-5, 2000, Tampa, FL.
Heibaum, M.H., 2002, "Geotechnical Parameters of Scouring and Scour Countermeasures,"
Mitteilungsblatt der Bundesanstalt fr Wasserbau Nr. 85. (J. Federal Waterways Engineering
and Research Institute, No. 85), Karlsruhe, Germany.
Henry, K.S., 1999, "Geotextile Reinforcement of Low-Bearing-Capacity Soils," Special
Report 99-7, U.S. Army Corps of Engineers Cold Regions Research and Engineering
Laboratory, Hanover, NH 03755.
Hoffmans, G.J.C.M. and Verheij, H.J., 1997, "Scour Manual," A.A. Balkema: Rotterdam,
Brookfield.
Hunt, B.E., 2003, "Pier Pressure," Bridge Design & Engineering, Issue No. 30, First Quarter.
Hunt, B.E., 2008, "Practices for Monitoring Scour Critical Bridges," NCHRP Project 20-5,
Topic 36-02, Transportation Research Board, National Academies of Science, Washington,
D.C. (to be published).
10.5
Hunt, B.E. and Price, G.R., 2004, "Scour Monitoring Lessons Learned," Proceedings from
the 2
nd
International Conference on Scour and Erosion, Nanyang Technological University,
Singapore, pp.69-84.
Isbash, S.V., 1936, "Construction of Dams by Depositing Rock in Running Water,"
Transactions, Second Congress on Large Dams, U.S. Government Report No. 3,
Washington D.C.
Johnson, A.W. and Stypula, J.M. (Eds.), 1998, "Guidelines for Bank Stabilization Projects in
the Riverine Environments of King County," King County Department of Public Works,
Surface Water Management Division, Seattle, WA.
Jones, J.S., 1989, "Laboratory Studies of the Effect of Footings and Pile Groups on Bridge
Pier Scour," Proceeding of 1989 Bridge Scour Symposium, FHWA, Washington, D.C.
Jones, J.S., Bertoldi, D., and Stein, S., 1995, "Alternative Scour Countermeasures,"
Proceedings ASCE 1st International Conference Water Resources Engineering, Vol. 2, 14-
18 August 1995, San Antonio, TX, pp. 1819-1823.
Keeley, J.W., 1971, "Bank Protection and River Control in Oklahoma," Federal Highway
Administration, Washington, D.C.
Kellerhals, R. and Bray, D., 1971, "Sampling Procedures for Coarse Fluvial Sediments,"
Proc. Am. Soc. Civ. Engrs., J. Hyd. Div., 97(HY7).
Kerenyi, K., Jones, J.S., and Stein, S., 2003, "Bottomless Culvert Scour Study: Phase I
Laboratory Report," Federal Highway Administration, Report No. FHWA-RD-02-078.
Kerenyi, K., Jones, J.S., and Stein, S., 2007, "Bottomless Culvert Scour Study: Phase II
Laboratory Report," Federal Highway Administration, Report No. FHWA-HRT-07-026.
Koerner, R.M., 1998, "Designing with Geosynthetics," 4th Edition, Prentice-Hall, Inc.,
Englewood Cliffs, NJ, 761 p.
Lagasse, P.F., Thompson, P.L., and Sabol, S.A., 1995, "Guarding Against Scour," Civil
Engineering, American Society of Civil Engineers, June, pp. 56-59.
Lagasse, P.F., Richardson, E.V., and Schall, J.D., 1998, "Instrumentation for Monitoring
Scour at Bridges," Transportation Research Record No. 1647, Highway Facility Design,
Transportation Research Board, National Research Council, National Academies of Science,
Washington, D.C.
Lagasse, P.F., Schall, J.D., and Richardson, E.V., 2001a, "Stream Stability at Highway
Structures," Hydraulic Engineering Circular 20, Third Edition, FHWA NHI 01-002, Federal
Highway Administration, U.S. Department of Transportation, Washington, D.C.
Lagasse, P.F., Nordin, C.F., Schall, J.D., and Sabol, G.V., 1991, "Scour Monitoring Devices
for Bridges," Third Bridge Engineering Conference, Transportation Research Record No.
1290, Denver, CO, Transportation Research Board, National Research Council,
Washington, D.C., March 10-13, pp. 281-294.
10.6
Lagasse, P.F., Richardson, E.V., Schall, J.D., Price, G.R., 1997, "Instrumentation for
Measuring Scour at Bridge Piers and Abutments," NCHRP Report 396, Transportation
Research Board, National Academies of Science, Washington, D.C.
Lagasse, P.F., Zevenbergen, L.W., Schall, J.D., and Clopper, P.E., 2001b. "Bridge Scour
and Stream Instability Countermeasures," Hydraulic Engineering Circular No. 23, Second
Edition, Report FHWA NHI -01-003, Federal Highway Administration, Washington, D.C.
Lagasse, P.F., Spitz, W.J., Zevenbergen, L.W., and Zachmann, D.W., 2004, "Handbook for
Predicting Stream Meander Migration," NCHRP Report 533, Transportation Research Board,
National Academies of Science, Washington, D.C.
Lagasse, P.F., Clopper, P.E., Zevenbergen, L.W., and Ruff, J.F., 2006, "Riprap Design
Criteria, Recommended Specifications, and Quality Control," NCHRP Report 568,
Transportation Research Board, National Academies of Science, Washington, D.C.
Lagasse, P.F., Clopper, P.E., Zevenbergen, L.W., and Girard, L.G., 2007,
"Countermeasures to Protect Bridge Piers from Scour," NCHRP Report 593, Transportation
Research Board, National Academies of Science, Washington, D.C.
Landers, M.N. and Trent, R.E., 1991, "National Bridge Scour Data Collection Program,"
1991 National Conference, Hydraulics Division, American Society of Civil Engineers,
Nashville, TN (July 29-August 2), pp. 221-226.
Lauchlan, C.S., 1999, "Pier Scour Countermeasures," Ph.D. Thesis, University of Auckland,
Auckland, NZ.
Lauchlan, C.S. and Melville, B.W., 2001, "Riprap Protection at Bridge Piers," ASCE Journal
of Hydraulic Engineering, Vol. 127, No. 5, pp. 412-418.
Lim, F.H. and Chiew, Y.M., 1996, "Stability of Riprap Layer Under Live-Bed Conditions," In:
Maxwell, W.H.C., Preul, H.C., and Stout, G.E. (Eds.), Proceedings Rivertech96: 1st
International Conference on New/Emerging Concepts for Rivers, Volume 2, Chicago, IL, pp.
830-837.
Maynord, S.T., 1996, "Toe-Scour Estimation in Stabilized Bendways," ASCE Journal of
Hydraulic Engineering, Vol. 122, No. 8, pp. 460-464.
McCullah, J.A. and Gray, D., 2005, "Environmentally Sensitive Channel- and Bank-
Protection Measures," NCHRP Report 544, Transportation Research Board, National
Academies of Science, Washington, D.C.
MDSHA (Maryland State Highway Agency) 2005, "Office of Bridge Development Manual for
Hydrologic and Hydraulic Design, Chapter 11, Evaluating Scour at Bridges, Appendix C,
Estimating Scour at Bottomless Arch Culverts, September 2005.
Melville B.W., Ettema, R., and Jain, S.C., 1989, "Measurement of Bridge Scour," Bridge
Scour Symposium, Turner-Fairbank Highway Research Center, cosponsored by Federal
Highway Administration and Subcommittee of Sedimentation, Interagency Advisory
Committee on Water Data, OWDC, USGS, October 17-19, pp. 183-194.
10.7
Melville, B,W., Lauchlan, C.S., and Hadfield, A.C., 1997, "Bridge Pier Scour Counter-
measures," In: Wang, S.S.Y., Langendoen, E.J., and Shields, F.D., Jr. (Eds.), Proceedings
of the Conference on Management of Landscapes Disturbed by Channel Incision:
Stabilization, Rehabilitation, Restoration, Oxford, MS.
Molinas, A., 1990, "Bridge Stream Tube Model for Alluvial River Simulation" (BRI-STARS),
User's Manual, National Cooperative Highway Research Program, Project No. HR15-11,
Transportation Research Board, Washington, D.C.
Morgan, R.P.C., Collins, A.J., Hann, M.J., Morris, J., Dunderdale, J.A.L., and Gowing,
D.J.G., 1997, "Waterway Bank Protection: A Guide to Erosion Assessment and
Management," Environment Agency, R&D Draft Technical Report W5/i635/3.
Mueller, D.S. and Landers, M.N., 1999, "Portable Instrumentation for Real-Time
Measurement of Scour at Bridges," Federal Highway Administration Publication No.
FHWA-RD-99-085, Turner-Fairbank Highway Research Center, McLean, VA.
National Transportation Safety Board (NTSB), 1988, "Collapse of the New York Thruway (I-
90) Bridge over the Schoharie Creek, Near Amsterdam, New York, April 5, 1987,"
NTSB/HAR-88/02, NTSB, Washington, D.C.
Pagn-Ortiz, Jorge E., 1991, "Stability of Rock Riprap for Protection at the Toe of Abutments
Located at the Floodplain," FHWA Research Report No. FHWA-RD-91-057, U.S. Department
of Transportation, Washington, D.C.
Parker, G., Toro-Escobar, C., and Voigt, R.L. Jr., 1998, "Countermeasures to Protect Bridge
Piers from Scour," Users Guide (revised 1999) and Final Report, NCHRP Project 24-07,
prepared for Transportation Research Board by St. Anthony Falls Laboratory, University of
Minnesota, MN, 360 pp.
Parola, A.C., 1993, "Stability of Riprap at Bridge Piers," ASCE, Journal of Hydraulic
Engineering, Vol. 119, No. 10, New York, NY, pp. 1080 - 1093.
Pearson, D.R., Jones, J.S., and Stein, S.M., 2000, "Risk-Based Design of Bridge Scour
Countermeasures," Fifth International Bridge Engineering Conference, Transportation
Research Record 1696, Paper No. 560056, Transportation Research Board, National
Research Council, Washington, D.C.
Racin, J.A., Hoover, T.P., and Crossett-Avila, C.M., 2000, "California Bank and Shore Rock
Slope Protection Design," Final Report No. FHWA-CA-TL-95-10, Caltrans Study No.
F90TL03 (Third Edition - Internet), California Department of Transportation, Sacramento,
CA.
Resource Consultants & Engineers (RCE), 1994, "Sediment and Erosion Design Guide,"
prepared for Albuquerque Metro Arroyo and Flood Control Authority (AMAFCA),
Albuquerque, NM.
Richardson, E.V. and Simons, D.B. 1984, "Use of Spurs and Guidebanks for Highway
Crossings," Transportation Research Board, Vol. 950, No. 2, Transportation Board,
Washington, D.C., pp. 184-193.
10.8
Richardson, E.V. and Davis, S.R., 2001, "Evaluating Scour at Bridges," Hydraulic
Engineering Circular 18, Fourth Edition, FHWA NHI 01-001, Federal Highway Administration,
U.S. Department of Transportation, Washington, D.C.
Richardson, E.V., Simons, D.B., and Lagasse, P.F., 2001, "River Engineering for Highway
Encroachments - Highways in the River Environment," Report No. FHWA NHI 01-004,
Hydraulic Design Series No. 6, Federal Highway Administration, Washington, D.C.
Richardson, E.V., Lagasse, P.F., Schall, J.D., Ruff, J.F., Brisbane, T.E., and Frick, D.M.,
1987, "Hydraulic, Erosion and Channel Stability Analysis of the Schoharie Creek Bridge
Failure, New York," Resource Consultants, Inc. and Colorado State University, Fort Collins,
CO.
Ruff, J.F. and Fotherby, L.M., 1995, "Bridge Scour Protection System Using Toskanes -
Phase 1," Final Report Research Project 91-02, Prepared for Pennsylvania Department of
Transportation.
Schall, J.D. and Price, G.R., 2004, "Portable Scour Monitoring Equipment," NCHRP Report
515, Transportation Research Board, National Academies of Science, Washington, D.C.
Schall, J.D., Price, G.R., Fisher, G.A., Lagasse, P.F., and Richardson, E.V., 1997a,
"Magnetic Sliding Collar Scour Monitor-Installation, Operation, and Fabrication Manual,"
NCHRP Report 397B, Transportation Research Board, National Research Council, National
Academy Press, Washington, D.C.
Schall, J.D., Price, G.R., Fisher, G.A., Lagasse, P.F., and Richardson, E.V., 1997b, "Sonar
Scour Monitor-Installation, Operation, and Fabrication Manual," NCHRP Report 397A,
Transportation Research Board, National Research Council, National Academy Press,
Washington, D.C.
Schiechtl, H.M. and Stern, R., 1997, "Water Bioengineering Techniques for Water Course,
Bank and Shoreline Protection," Blackwell Science, Inc., Cambridge, MA.
Sharp, J.J., 1981, "Hydraulic Modeling," Butterworth & Co., United Kingdom.
Shen, H.W., 1979, "Modeling of Rivers," John Wiley & Sons, NY.
Shields, F.D., Cooper, C.M., and Testa, S., 1995, "Towards Greener Riprap: Environmental
Microscale to Macroscale," In: River, Coastal, and Shoreline Protection: Erosion Control
Using Riprap and Armourstone, C.R. Thorne, S.R. Abt, F.B.J. Barends, S.T. Maynord, and
K.W. Pilarczyk (Eds.), Wiley, New York, pp. 557-574.
Simon, A. and Collison, A.J.C., 2002, "Quantifying the mechanical and hydrologic effects of
riparian vegetation on streambank stability," Earth Surface Processes and Landforms 27(5):
527-546.
Sotir, R.B. and Nunnally, N.R., 1995, "Use of Riprap in Soil Bioengineering Streambank
Protection," In: River, Coastal and Shoreline Protection: Erosion Control Using Riprap and
Armourstone, C.R. Thorne, S.R. Abt, F.B.J. Barends, S.T. Maynord, and K.W. Pilarczyk
(Eds.), Wiley, New York.
10.9
Stein, S., Jones, J.S., Bertoldi, D., and Umbrell, E., 1998, "Alternatives to Riprap as a Scour
Countermeasure," In: Richardson, E.V., and Lagasse, P.F. (Eds.), Stream Stability and
Scour at Highway Bridges, Compendium of Papers ASCE Water Resources Engineering
Conferences 1991 to 1998, pp. 893-904.
Thorne, C.R. and Abt, S.R., 1993, "Velocity and Scour Prediction in River Bends," Contract
Rep. HL-93-1, U.S. Army Engrs., Waterways Experiment Station, Vicksburg, MS.
Thornton, C.I., Watson, C.C., and Abt, S.R., 1999, "Flume Testing of A-Jacks Protection
Units," ASCE-EWRI 1999 International Water Resources Engineering Conference, Seattle,
WA.
Transportation Research Board (TRB), 1999, "1998 Scanning Review of European Practice
for Bridge Scour and Stream Instability Countermeasures," National Cooperative Highway
Research Program, Research Results Digest, Number 241, Washington, D.C.
U.S. Army Corps of Engineers, 1981, "The Streambank Erosion Control Evaluation and
Demonstration Act of 1974," Final Report to Congress, Executive Summary and
Conclusions.
U.S. Army Corps of Engineers, 1991, "Hydraulic Design of Flood Control Channels," EM
1110-2-1601, Department of the Army, Washington, D.C.
U.S. Army Corps of Engineers, 1993, "Scour and Deposition in Rivers and Reservoirs,"
User's Manual, HEC-6, Hydrologic Engineering Center, Davis, CA.
U.S. Army Corps of Engineers, 1995, "Construction Quality Management," Engineering
Regulation No. 1180-1-6, Washington, D.C.
U.S. Army Engineers Waterways Experiment Station (WES), 1998, "Streambank
Stabilization Handbook," Veri-Tech, Inc., Vicksburg, MS.
USACE and FHWA, 1997, "Agreement for the Implementation of Scour Countermeasures to
Protect Foundations of Scour Critical Bridges," Memorandum, Washington, D.C., February.
U.S. Department of Transportation, Federal Highway Administration, 1988, "Scour at
Bridges," Technical Advisory T5140.20, updated by Technical Advisory T5140.23, October
28, 1991, "Evaluating Scour at Bridges," U.S. Department of Transportation, Washington,
D.C.
U.S. Department of Transportation, Federal Highway Administration, 2004, "National Bridge
Inspection Standards," Federal Register, Volume 69, No. 239, 23CFR Part 650, FHWA
Docket No. FHWA-2001-8954, Final Rule, December 14, 2004, effective January 13, 2005,
Washington, D.C.
Washington Dept. of Fish & Wildlife, 2003, "Integrated Streambank Protection Guidelines,"
published in co-operation with Washington Dept. of Transportation and Washington Dept. of
Ecology.
Water Engineering & Technology, Inc. (WET), 1990, "Re-evaluation of the Streambank
Erosion Control Evaluation and Demonstration Project," Report to U.S. Army Corps of
Engineers, Vicksburg District, Contract No. DACW38-88-D-0099.
10.10
Waters, C.R., 1994, "The HR Wallingford Scour Monitoring System," Centenary Year Bridge
Conference, Cardiff, United Kingdom, September 26-30, pp. 323-328.
Whitlow, T.H. and Harris, R.W., 1979, "Flood Tolerance in Plants: A State-of-the-Art
Review," Technical Report E-79-2, U.S. Army Engineer Waterways Experiment Station,
Vicksburg, MS.
Wolman, M.G., 1954, "A Method of Sampling Coarse Bed Material," American Geophysical
Union, Transactions, 35: pp. 951-956.
Zabilansky, L.J., 1996, "Ice Force and Scour Instrumentation for the White River, Vermont,"
U.S. Army Corps of Engineers, Special Report 96-6, Cold Regions Research & Engineering
Laboratory, Hanover, NH, April, 53 pp.
Zabilansky, L.J., 2002, "Ice Cover Effects on Bed Scour: Case Studies," Proceedings from
the 11
th
ASCE Cold Regions Engineering, Anchorage, AK.
APPENDICES
A.1
APPENDIX A
METRIC SYSTEM, CONVERSION FACTORS, AND WATER PROPERTIES
A.2
(page intentionally left blank)
A.3
APPENDIX A
Metric System, Conversion Factors, and Water Properties
The following information is summarized from the Federal Highway Administration, National
Highway Institute (NHI) Course No. 12301, "Metric (SI) Training for Highway Agencies." For
additional information, refer to the Participant Notebook for NHI Course No. 12301.
In SI there are seven base units, many derived units and two supplemental units (Table A.1).
Base units uniquely describe a property requiring measurement. One of the most common
units in civil engineering is length, with a base unit of meters in SI. Decimal multiples of
meter include the kilometer (1000m), the centimeter (1m/100) and the millimeter (1 m/1000).
The second base unit relevant to highway applications is the kilogram, a measure of mass
which is the inertial of an object. There is a subtle difference between mass and weight. In
SI, mass is a base unit, while weight is a derived quantity related to mass and the
acceleration of gravity, sometimes referred to as the force of gravity. In SI the unit of mass is
the kilogram and the unit of weight/force is the newton. Table A.2 illustrates the relationship
of mass and weight. The unit of time is the same in SI as in the English system (seconds).
The measurement of temperature is Centigrade. The following equation converts Fahrenheit
temperatures to Centigrade, EC = 5/9 (EF - 32).
Derived units are formed by combining base units to express other characteristics. Common
derived units in highway drainage engineering include area, volume, velocity, and density.
Some derived units have special names (Table A.3).
Table A.4 provides useful conversion factors from English to SI units. The symbols used in
this table for metric units, including the use of upper and lower case (e.g., kilometer is "km"
and a newton is "N") are the standards that should be followed. Table A.5 provides the
standard SI prefixes and their definitions.
Table A.6 provides physical properties of water at atmospheric pressure in SI system of
units. Table A.7 gives the sediment grade scale and Table A.8 gives some common
equivalent hydraulic units.
A.4
Table A.1. Overview of SI Units.
Units
Symbol
Base units
length
mass
time
temperature*
electrical current
luminous intensity
amount of material
meter
kilogram
second
kelvin
ampere
candela
mole
m
kg
s
K
A
cd
mol
Derived units
Supplementary units
angles in the plane
solid angles
radian
steradian
rad
sr
*Use degrees Celsius (EC), which has a more common usage than kelvin.
Table A.2. Relationship of Mass and Weight.
Mass
Weight or
Force of
Gravity
Force
English slug
pound-mass
pound
pound-force
pound
pound-force
metric kilogram newton newton
A.5
Table A.3. Derived Units With Special Names.
Quantity Name Symbol Expression
Frequency hertz Hz s
-1
Force newton N kg A m/s
2
Pressure, stress pascal Pa N/m
2
Energy, work, quantity of heat joule J N A m
Power, radiant flux watt W J/s
Electric charge, quantity coulomb C A A s
Electric potential volt V W/A
Capacitance farad F C/V
Electric resistance ohm V/A
Electric conductance siemens S A/V
Magnetic flux weber Wb V A s
Magnetic flux density tesla T Wb/m
2
Inductance henry H Wb/A
Luminous flux lumen lm cd A sr
Illuminance lux lx lm/m
2
A.6
Table A.4. Useful Conversion Factors.
Quantity
From English
Units
To Metric
Units
Multiplied
By*
Length mile
yard
foot
inch
km
m
m
mm
1.609
0.9144
0.3048
25.40
Area square mile
acre
acre
square yard
square foot
square inch
km
2
m
2
hectare
m
2
m
2
mm
2
2.590
4047
0.4047
0.8361
0.09290
645.2
Volume acre foot
cubic yard
cubic foot
cubic foot
100 board feet
gallon
cubic inch
m
3
m
3
m
3
L (1000 cm
3
)
m
3
L (1000 cm
3
)
cm
3
1233
0.7646
0.02832
28.32
0.2360
3.785
16.39
Mass lb
kip (1000 lb)
kg
metric ton (1000
kg)
0.4536
0.4536
Mass/unit length plf kg/m 1.488
Mass/unit area
psf
kg/m
2
4.882
Mass density pcf kg/m
3
16.02
Force lb
kip
N
kN
4.448
4.448
Force/unit length plf
klf
N/m
kN/m
14.59
14.59
Pressure, stress,
modulus of elasticity
psf
ksf
psi
ksi
Pa
kPa
kPa
MPa
47.88
47.88
6.895
6.895
Bending moment,
torque, moment of
force
ft-lb
ft-kip
N A m
kN A m
1.356
1.356
Moment of mass lb A ft m 0.1383
Moment of inertia lb A ft
2
kg A m
2
0.04214
Second moment of
area
in
4
mm
4
416200
Section modulus in
3
mm
3
16390
Power ton (refrig)
Btu/s
hp (electric)
Btu/h
kW
kW
W
W
3.517
1.054
745.7
0.2931
*4 significant figures; underline denotes exact conversion
A.7
Table A.4. Useful Conversion Factors (continued).
Quantity
From English
Units
To Metric Units
Multiplied by*
Volume rate of flow
ft
3
/s
cfm
cfm
mgd
m
3
/s
m
3
/s
L/s
m
3
/s
0.02832
0.0004719
0.4719
0.0438
Velocity, speed
ft/s
m/s
0.3048
Acceleration
f/s
2
m/s
2
0.3048
Momentum
lb A ft/sec
kg A m/s
0.1383
Angular momentum
lb A ft
2
/s
kg A m
2
/s
0.04214
Plane angle
degree
rad
mrad
0.01745
17.45
*4 significant figures; underline denotes exact conversion
Table A.5. Prefixes.
Submultiples Multiples
deci 10
-1
d deka 10
1
da
centi 10
-2
c hecto 10
2
h
milli 10
-3
m kilo 10
3
k
micro 10
-6
mega 10
6
M
nano 10
-9
n giga 10
9
G
pica 10
-12
p tera 10
12
T
femto 10
-15
f peta 10
15
P
atto 10
-18
a exa 10
18
E
zepto 10
-21
z zetta 10
21
Z
yocto 10
-24
y yotto 10
24
Y
A.8
A.9
A.10
A.11
A.12
(page intentionally left blank)
B.1
APPENDIX B
STANDARD TEMPLATE FOR A PLAN OF ACTION
B.2
B.3
STANDARD TEMPLATE FOR A PLAN OF ACTION
B.1 Overview
In order to facilitate the development of a POA, the FHWA has created a "standard"
template for bridges that are scour critical. This template includes the minimum information
recommended by FHWA for a POA.
The template is intended to be a guide and tool for bridge owners to use in developing their
POAs. The template provides the program manager with a summary of the type of
information required to develop a plan of action for bridges that are scour critical or have
unknown foundations.
All the fields in the template may be modified so that local terminology is employed, unique
information may be added regarding local and site-specific scour and stream stability
concerns, and local sources of information may be included. The electronic Microsoft Word
document template may be downloaded from the FHWA website:
http://www.fhwa.dot.gov/engineering/hydraulics/bridgehyd/poa.cfm
Blocks in this template will expand automatically to allow additional space. Where check
boxes are provided, they can be checked by double-clicking on the box and selecting the
"checked" option.
To provide guidance and training on preparation of a POA for scour critical bridges, the
FHWA National Highway Institute has prepared an on-line module (NHI Course No. 135085)
which includes the suggested template for a POA and illustrates its application to field case
studies. This training module can be accessed (see site reference, p. 2.6).
A state's Bridge Management System is a useful source of data for developing a POA.
Many DOTs are now using information technology (IT) systems that provide immediate
access via the bridge engineers desktop computer to an integrated system of bridge
management information and data bases. Much of the information outlined in the template
may be obtained from these systems.
B.2 Executive Summary
The standard template contains ten sections. Sections 1 through 4 are intended as an
executive summary for the busy reviewer/manager who may not need the details of Sections
5 through 10, and show:
Section 1: General information
Section 2: Who prepared the POA
Section 3: The source of the problem
Section 4: What actions are recommended and their status
To assist in completing a POA using the template, the remaining sections of this appendix
contain general guidance for each section of the template. Note that an abbreviated set of
instructions is appended to the template.
B.4
B.3 Standard Template Sections
Section 1 General Information
Section 1 of the POA Standard Template covers general information about the bridge. This
information is usually available from the bridge owners Bridge Management System or
bridge-specific files.
The bridge replacement information provides a framework for decisions regarding the need
for a structural or hydraulic countermeasure.
The bridge type information provides insight on how the bridge could fail, if significant scour
were to occur. For example, a simply-supported span bridge can fail suddenly, so the bridge
should be closed as soon as scour becomes close to critical. Bridges with structural
redundancy may allow more time to respond to an emergency situation.
Also, identified in this section is whether the bridge provides service to emergency facilities
or is part of an evacuation route. This information is important in bridge closure plans, since
early communication of a bridge closure to emergency responders could help them
effectively detour their normal routes.
Section 2 Responsibility for POA
Section 2 of the POA Standard Template provides information on who are the people
responsible for preparing and maintaining the POA.
Author or Authors refers to the individual or company that developed the POA, such as
the State Bridge Maintenance Engineer or a consultant.
Concurrences on POA refers to the individuals or organizations which must concur with the
contents of the POA. The individuals or organizations may also refer to upper management
who approve funding or county officials and law enforcement agencies who must agree with
the bridge closure plans and the disruption the closure will have on the public. Gaining
concurrence before an emergency occurs helps to minimize inter-agency conflicts during an
emergency.
Also, in Section 2 is information on the POA update: who will do the update, when, and what
was updated. The POA should be reviewed and updated on a routine basis to ensure that
the contents of the plan are still valid.
Section 3 Scour Vulnerability
Section 3 of the POA Standard Template provides a summary of the scour status of the
bridge.
Section 3a shows the current scour coding. If Other is selected, the appropriate code would
be provided. For example, if the foundation is unknown U would be entered in the Other
field.
In Section 3b indicate how the Item 113 code was determined. If the bridge has a U code,
unknown must be written in the Other field.
B.5
Section 3c, provides space for a narrative description to summarize the information from the
scour evaluation. The template has been developed to expand automatically as information
is entered. Some items to include are:
Scour critical flood flow and scour depth
100- or 500-year flood flows
Overtopping flow
Section 3d provides space to summarize the scour history, including when, where and how
much scour or stream instability has been observed at the bridge. Also, information on scour
countermeasures previously installed at the bridge and their performance should be
included.
Section 4 Recommended Action(s)
Section 4 of the POA Standard Template contains highlights from the recommended actions
from Sections 6 and 7 of the template. Items 4a, 4b, and 4c refer to the main parts of the
POA monitoring program. Item 4d refers to the hydraulic or structural countermeasure
selected in Section 7. This section cannot be completed until Sections 6 and 7 are
completed.
Section 5 NBIS Coding Information
Section 5 of the POA Standard Template contains previous and current codes for the
hydraulic related items of the NBI. This information provides a quick indication of observed
or potential long-term problems or adverse trends that may affect the stability of the bridge
foundations.
The Inspection Date corresponds to the date of the inspection when the NBI items were
coded. If the Items were coded on a date different than the inspection date, this different
date is indicated in the Comments block.
For additional details on Items 113 and 60, see the FHWA Policy Memorandum Revision of
Coding Guide, Item 113 Scour Critical Bridges dated April 27, 2001.
Section 6 Monitoring Program
There are three types of countermeasures which should be considered as part of the
countermeasure program:
1. Monitoring
2. Hydraulic
3. Structural
A monitoring countermeasure can be considered a key component of a POA, either alone or
in combination with other countermeasures. Monitoring is highlighted in its own section,
Section 6, in the POA Standard Template. Section 6 is subdivided into three additional
subsections including:
Inspection Frequency
Fixed Monitoring
Flood Monitoring
B.6
The first subsection of Section 6 covers information on the frequency of inspection. Bridges
are usually inspected biennially. Bridge owners may choose to keep this schedule but may
also specify inspectors look at certain items at the bridge to ensure stability with regard to
scour. In this case, the Regular Inspection Program box would be selected along with a list
of the items to be watched. These items may include countermeasures, channel bed
elevations, signs of movement or settlement.
Some bridge owners may choose to increase the frequency of inspection to less than the 2-
year cycle. In this case, the Increased Inspection Frequency box would be checked and the
number of months between inspections would be indicated. Usually only items pertinent to
scour and stream stability would be observed and inspected.
Underwater inspections may also be required at the bridge. If the Underwater Inspection
cycle remains on the regular schedule, then the Underwater Inspection Required box would
be checked. If an increased cycle is needed, then the Increased Underwater Inspection
Frequency box would be selected and the months between inspections indicated. In both
cases the items for inspection and observation are indicated on the POA.
The second subsection of Section 6 covers information on Fixed Monitoring Devices. Fixed
monitoring devices can provide continuous information about scour at the bridge site (see
Chapter 9). This information can lead to early identification of potential scour problems.
The Fixed Monitoring box would be selected if a bridge owner opts to use fixed monitoring
devices at the bridge. The type of devices and location of devices would be described in the
plan. Details about the devices may be included in Attachment F to the POA.
In most cases, the fixed monitoring device can send information continuously from the bridge
site. However, this amount of information can become cumbersome, so most bridge owners
obtain or sample the information periodically. The sampling interval should be indicated on
the POA and can be modified during flood events. If modified, the rationale for the change
would be noted on the POA.
The information received from the fixed monitoring device should be reviewed for developing
scour problems. During normal flow, the information may be reviewed daily, weekly, or
monthly. During flood events, the review frequency may increase. The POA should detail
the frequency of review and identify who is conducting the review.
Scour Critical Criteria should be determined from a scour evaluation study. This criteria
should be indicated on the plan. Selecting an elevation higher than the scour critical
elevation ensures sufficient time needed to take action in protecting the traveling public and
possibly the bridge. This elevation, called the Scour Alert Criteria, should also be presented
on the POA.
The third subsection of Section 6 describes monitoring actions that should be implemented
during an actual flood event. If the bridge owner inspects the bridge visually during a flood,
then the Visual Inspection box is selected. Those individuals visually observing the bridge
may look for movement or settlement in the bridge or for a certain elevation of water, which
could trigger the actions prescribed in the POA. If some kind of instrumentation is used to
measure scour or water elevation, the Instrument box is selected and the applicable
instrumentation type indicated. Both the Visual Inspection and the Instrument boxes may be
selected.
B.7
The POA should document thresholds for the start and end of flood monitoring and note the
frequency of the monitoring (see Chapter 2, Section 2.1.4). These thresholds may include:
Flood discharge
Stage
Water surface elevation
Rainfall data
The POA should clearly describe the thresholds and how the threshold is determined. For
example, the threshold discharge or stage may be tied to a nearby USGS gage. Some
bridge owners have opted to mark their bridges with the threshold water surface elevations
to ensure inspectors know when action should be taken. The POA should also describe the
actions required when threshold values are reached.
The agency, department, position, or person responsible for inspecting or reviewing
instrumentation data should be listed at the end of Section 6 in the POA Standard Template.
Some bridge owners may have maintenance staff rather than bridge inspectors monitor the
bridge during a flood and then have bridge inspection staff conduct the post-flood inspection.
All staff with responsibilities in implementing the POA should be listed. More than one person
may be listed, especially to provide back up points-of-contact.
In some cases, the person at the bridge site during a flood event must confer with someone
of greater authority in order to decide to close the bridge. This decision maker should also
be listed in Section 6 of the POA Standard Template.
Finally, if action must be taken, the agency, department, position, or person responsible for
taking the action would be listed. For example, if the local law enforcement is to close the
bridge and set up the detour route, this agency is listed in Section 6 of the POA Standard
Template.
Section 7 Countermeasure Recommendations
Section 7 of the POA Standard Template summarizes the alternative countermeasures
considered for the bridge, as well as the final countermeasures selected and rationale (see
Chapter 2, Sections 2.3 2.5).
If a monitoring countermeasure were selected for the countermeasure program, the
Monitoring box would be selected. If a structural and/or hydraulic countermeasure were
selected, then the Structural/Hydraulic Scour Countermeasures Considered box would be
selected. Both boxes may be selected, if needed.
Under the Priority Ranking and Estimated Cost columns, the various countermeasures for
consideration along with their corresponding estimated costs. The selected
countermeasures are indicated and the reasons for selecting the countermeasures should
be explained on the Basis for selection line. Supporting information for the considered
countermeasures can be included in Attachment F. Sufficient information to help
independent reviewers understand the countermeasure selection process and the resulting
decisions should be included.
This section also includes boxes for indicating the countermeasure implementation project
type.
B.8
The last part of Section 7 of the POA Standard Template requires information on
agency/department/position/person responsible for designing and implementing the
countermeasure program. More than one person may be listed, if appropriate.
Target design and construction dates should are also required.
Section 8 Bridge Closure Plan
Section 8 of the POA Standard Template provides instructions for closing a bridge.
Specifically, this section should include:
Specific criteria indicating when to close the bridge
Who should close the bridge
Contact information, such as management or local law enforcement
Several examples of bridge closing conditions are provided. If the bridge owner has closure
instructions specified in another document, these instructions should be referenced on the
Emergency repair plans line.
The POA should also detail the process for reopening the bridge. In some cases, the bridge
may be reopened when the floodwater has receded sufficiently. In other cases, the bridge
will require inspection to ensure it is structurally sound. The reopening criteria should be
listed. The agency or person who will inspect or make the decision to reopen the bridge
should be identified in the plan.
Section 9 Detour Route
Section 9 of the POA Standard Template describes potential detour routes, if the bridge is
closed. The description should include route numbers, from/to locations, distances from
closed bridge, as well as any other pertinent information. A map of the detour routes should
be provided in Attachment E to the POA.
The bridges on the detour route should be listed in the Bridges on Detour Route table, along
with restrictive factors for each bridge on the detour route, such as:
Load restrictions
Clearance restrictions
Scour vulnerability condition
Additional items to present in Section 9 include:
Required traffic control equipment
Critical issues, such as flood overtopping vulnerability for bridges and roadways along
the detour route, waterway adequacy of the detour bridges, and lane restrictions
Authority to communicate with the media and public
Concurrence from local law enforcement agencies on the proposed detour and the closing
procedures should be obtained and copies of the POA provided to these agencies.
B.9
Detour routes are not set in stone, but information should be provided on potential detours.
Some factors to be considered in documenting in advance a detour route for a particular
bridge include:
Detours must be set up, taking into consideration the conditions existing at the time a
detour is needed. For some bridges, it may not be possible to foresee what these
conditions might be, which roads might be flooded, which bridges may already be closed,
what will be the load and clearance restrictions for the proposed detour route, etc.
DOT or bridge owner may have a designated department/office which is intimately
familiar with their bridges and road systems, and are in the best position to quickly
decide upon and coordinate a detour route for the given set of circumstances. This would
be noted in the POA.
Decisions are made on the basis of the conditions that exist at the time of the closure.
Consideration needs to be given to floods that may overtop bridges and approach roadways
on the detour route. Actual detour routes should be based on roadway and bridge network
status at the time the detour is proposed.
Section 10 Attachments
Section 10 is the final section of the template and contains the following Attachments.
Attachment A should reference or include all available boring logs, probes, construction
inspection and monitoring records, monitoring well readings, test pits, soil laboratory data,
and anecdotal information.
Attachment B should reference or include all available channel cross sections for the
bridge. Historic cross section comparisons, if available, should also be included.
Attachments C, D, and E are for documenting bridge elevation and plan views, and maps
necessary to show detour routes.
Attachment F should include documentation on scour countermeasure alternatives. A
comprehensive plan of action should provide enough information that an independent
reviewer could arrive at the same conclusion regarding the preferred countermeasure
alternative. For proposed scour countermeasures, a conceptual design should be prepared
and details including reference to any hydraulic, structural or geotechnical studies that have
been completed for the purpose of scour mitigation should be provided. Estimated costs of
all proposed scour countermeasures should also be provided.
Details and dates of any recent scour countermeasure that has been implemented to
address the current scour critical/unknown foundation status of the bridge should be
included. All applicable studies, lead agencies, subcontractors and as-builts should be noted
or included in Appendix F.
Attachment G may also reference or include historic and current aerial photographs of the
site.
Attachment H may be used for any additional information such as: (1) standard closing and
reopening procedures, (2) information on public transit, or (3) special circumstances such as
access to emergency facilities, evacuation routes, etc. In some situations, public
transportation (e.g., bus routes) may be of importance to the public with respect to detours.
If additional information is included, indicate this in Section 10 of the template.
B.10
(page intentionally left blank)
SCOUR CRITICAL BRIDGE - PLAN OF ACTION
1. GENERAL INFORMATION
Structure number:
City, County, State:
Waterway:
Structure name:
State highway or facility carried:
Owner:
Year built: Year rebuilt:
Bridge replacement plans (if scheduled):
Anticipated opening date:
Structure type: Bridge Culvert
Structure size and description:
Foundations: Known, type: Depth: Unknown
Subsurface soil information (check all that apply): Non-cohesive Cohesive Rock
Bridge ADT: Year/ADT: % Trucks:
Does the bridge provide service to emergency facilities and/or an evacuation route (Y/N)?
If so, describe:
2. RESPONSIBILITY FOR POA
Author(s) of POA (name, title, agency/organization, telephone, pager, email):
Date:
Concurrences on POA (name, title, agency/organization, telephone, pager, email):
POA updated by (name, title, agency/organization): Date of update:
Items updated:
POA to be updated every months by (name, title, agency/organization):
Date of next update:
3. SCOUR VULNERABILITY
a. Current Item 113 Code: 3 2 1 Other:
b. Source of Scour Critical Code: Observed Assessment Calculated Other:
c. Scour Evaluation Summary:
d. Scour History:
4. RECOMMENDED ACTION(S) (see Sections 6 and 7)
Recommended Implemented
a. Increased Inspection Frequency Yes No Yes No
b. Fixed Monitoring Device(s) Yes No Yes No
c. Flood Monitoring Program Yes No Yes No
d. Hydraulic/Structural Countermeasures Yes No Yes No
5. NBIS CODING INFORMATION
Current Previous
Inspection date
Item 113 Scour Critical
Item 60 Substructure
Item 61 Channel & Channel Protection
Item 71 Waterway Adequacy
Comments: (drift, scour holes, etc. - depict in
sketches in Section 10)
6. MONITORING PROGRAM
Regular Inspection Program w/surveyed cross sections
Items to Watch:
Increased Inspection Frequency of mo. w/surveyed cross sections
Items to Watch:
Underwater Inspection Required
Items to Watch:
Increased Underwater Inspection Frequency of mo.
Items to Watch:
Fixed Monitoring Device(s)
Type of Instrument:
Installation location(s):
Sample Interval: 30 min. 1 hr. 6 hrs. 12 hrs. Other:
Frequency of data download and review: Daily Weekly Monthly Other
Scour alert criteria for each pier/abutment:
Scour critical criteria for each pier/abutment
Survey ties:
Criteria for termination of fixed monitoring program:
Flood Monitoring Program
Type: Visual inspection
Instrument (check all that apply):
Portable Geophysical Sonar Other:
Flood monitoring required: Yes No
Flood monitoring event defined by (check all that apply):
Discharge Stage
Elev. measured from Rainfall (in/mm) per (hour)
Flood forecasting information:
Flood warning system:
Frequency of flood monitoring: 1 hr. 3 hrs. 6 hrs. Other:
Post-flood monitoring required: No Yes, within days
Frequency of post-flood monitoring: Daily Weekly Monthly Other:
Criteria for termination of flood monitoring:
Criteria for termination of post-flood monitoring:
Scour alert criteria for each pier/abutment:
Scour critical criteria for each pier/abutment:
Note: Additional details for action(s) required may be included in Section 8.
Action(s) required if scour alert criteria detected (include notification and closure
procedures):
Action(s) required if scour critical criteria detected (include notification and closure
procedures):
Agency and department responsible for monitoring:
Contact person (include name, title, telephone, pager, e-mail):
7. COUNTERMEASURE RECOMMENDATIONS
Prioritize alternatives below. Include information on any hydraulic, structural or monitoring
countermeasures.
Monitoring countermeasure (see Section 6 and Section 10 - Attachment F)
Estimated cost $
Structural/hydraulic countermeasures (see Section 10 - Attachment F):
Priority Ranking Estimated cost
(1) $
(2)
$
(3) $
(4)
$
(5)
$
Basis for the selection of the preferred scour countermeasure:
Countermeasure implementation project type:
Proposed Construction Project Maintenance Project
Programmed Construction - Project Lead Agency:
Bridge Bureau Road Design Other
Agency and department responsible for countermeasure program (if different from Section 6
contact for monitoring):
Contact person (include name, title, telephone, pager, e-mail):
Target design completion date:
Target construction completion date:
Countermeasures already completed:
8. BRIDGE CLOSURE PLAN
Scour monitoring criteria for consideration of bridge closure:
Water surface elevation reaches at
Overtopping road or structure
Scour measurement results / Monitoring device (See Section 6)
Observed structure movement / Settlement
Discharge: cfs/cms
Flood forecast:
Other: Debris accumulation Movement of riprap/other armor protection
Loss of road embankment
Emergency repair plans (include source(s), contact(s), cost, installation directions):
Agency and department responsible for closure:
Contact persons (name, title, agency/organization, telephone, pager, email):
Criteria for re-opening the bridge:
Agency and person responsible for re-opening the bridge after inspection:
9. DETOUR ROUTE
Detour route description (route number, from/to, distance from bridge, etc.) - Include map in
Section 10, Attachment E.
Bridges on Detour Route:
Bridge Number Waterway
Sufficiency Rating/
Load Limitations
Item 113 Code
Traffic control equipment (detour signing and barriers) and location(s):
Additional considerations or critical issues (susceptibility to overtopping, limited waterway
adequacy, lane restrictions, etc.):
News release, other public notice (include authorized person(s), information to be provided
and limitations):
10. ATTACHMENTS
Please indicate which materials are being submitted with this POA:
Attachment A: Boring logs and/or other subsurface information
Attachment B: Cross sections from current and previous inspection reports
Attachment C: Bridge elevation showing existing streambed, foundation depth(s) and
observed and/or calculated scour depths
Attachment D: Plan view showing location of scour holes, debris, etc.
Attachment E: Map showing detour route(s)
Attachment F: Supporting documentation, calculations, estimates and conceptual designs
for scour countermeasures.
Attachment G: Photos
Attachment H: Other information:
INSTRUCTIONS FOR COMPLETING THE PLAN OF ACTION
The existing bridge management system in your state will provide much of the information
required to fill out this template. Note that all blocks in this template will expand automatically
to allow as much space as you require. All fields can be modified to accommodate local
terminology, as desired. Where check boxes are provided, they can be checked by double-
clicking on the box and selecting the checked option. If you include additional attachments,
please indicate this in Section 10.
Section 1
Foundations It is recommended that substructure depths be shown in the bridge elevation,
Attachment C (see Section 10). The minimum depth should be reported in Section 1 as a
worst-case condition.
Subsurface soil information If conditions vary with depth and/or between substructure units,
this should be noted and included in Attachments A and/or C (see Section 10).
Sections 1, 2, 3, and 4
These sections are intended as an executive summary for the reviewer/manager who may not
need the details of Sections 5 through 10, and show:
Section 1: General information
Section 2: Who prepared the POA
Section 3: The source of the problem
Section 4: What actions are recommended and their status
Section 3
Reasons why the bridge has been coded scour critical for Item 113:
Scour Critical
Aggressive stream or tidal waterway (high velocity, steep slope, deep flow)
Actively degrading channel
Bed material is easily eroded
Large angle of attack (> 10)
Significant overbank or floodplain flow (floodplain >50 m or 150 ft wide)
Possibility of bridge overtopping (potential for pressure flow through bridge)
Evidence of scour and/or degradation
Evidence of structural damage due to scour
Foundations are spread footings on erodible soil, shallow piles, or embedment unknown
Exposed footing in erodible material
Exposed piles with unknown or insufficient embedment
Loss of abutment and/or pier protection
No countermeasures or countermeasures in poor condition
Needs countermeasures immediately
Unknown Foundations
No record of foundation type (spread footing vs. piles)
Depth of foundation or pile embedment unknown
Condition of foundation or pile embedment unknown
Subsurface soil strata not documented
Section 5
This section highlights recent changes in the scour/hydraulics coding items as an indication of
potential problems or adverse trends. See FHWA Policy Memorandum on Revision of Coding
Guide, Item 113 Scour Critical Bridges dated April 27, 2001 for details on Items 113 and 60.
A link to this memorandum is provided below:
(www.fhwa.dot.gov/engineering/hydraulics/policymemo/revguide.cfm).
Section 6
Multiple individuals responsible for various monitoring activities may be listed, as appropriate.
Section 7
Guidance on the selection and design of scour countermeasures may be found in FHWA
Hydraulic Engineering Circular No. 23, Bridge Scour and Stream Instability Countermeasures,
Third Edition, 2009. To facilitate the selection of alternative scour countermeasures, a matrix
describing the various countermeasures and their attributes is presented in this circular. A link
to this document is provided below:
http://isddc.dot.gov/OLPFiles/FHWA/010592.pdf
Section 8
Standard closure and reopening procedures, if available, may be appended to the POA (see
Section 10, Attachment H).
Section 9
In some situations, public transportation (e.g., bus routes) may be of importance to the public,
and therefore could be included in the POA (see Section 10, Attachment H).
(page intentionally left blank)
C.1
APPENDIX C
PIER SCOUR COUNTERMEASURE SELECTION METHODOLOGY
C.2
(page intentionally left blank)
C.3
PIER SCOUR COUNTERMEASURE SELECTION METHODOLOGY
C.1 Overview
This selection methodology provides a quantitative assessment of the suitability of six
armoring-type countermeasures for pier scour based on selection factors that consider river
environment, construction considerations, maintenance, performance, and estimated life-
cycle cost (Lagasse et al. 2007). With the exception of life-cycle costs, the methodology
analyzes the design factors by stepping the user through a series of decision branches,
ultimately resulting in a site-specific numerical rating for each selection factor (see Section
3.2.5). The following countermeasures are evaluated by this methodology:
Standard (loose) riprap
Partially grouted riprap
Articulating concrete blocks
Gabion mattresses
Grout-filled mattresses
Grout-filled bags
To facilitate the decision-making process, the procedure was automated using a Microsoft
Excel spreadsheet format. In the spreadsheet, the decision-making process can easily be
modified to consider new situations or include additional information. Detailed directions are
included in the program file, and automated features are incorporated in the program to step
the user through the process.
C.2 Selection Index
Five factors are used to compute a Selection Index (SI0 for each countermeasure:
S1: Bed Material size and transport
S2: Severity of debris or ice loading
S3: Constructability constraints
S4: Inspection and maintenance requirements
LCC: Life-cycle costs
The selection Index is calculated as:
SI = (S1 x S2 x S3 x S4)/LCC (C.1)
The countermeasure that has the highest value of SI is considered to be most appropriate for
a given site, based not only on its suitability to the specific riverine and project site
conditions, but also in consideration of its economy. The approach is sensitive to
assumptions regarding initial construction cost, remaining service life, assumed frequency of
maintenance events, and extent of maintenance required. Each of these factors requires
experience and engineering judgment, as well as site- or region-specific information on the
cost of materials and delivery, construction practices, and prevailing labor rates. It should be
noted that the methodology can be used simply to rank the countermeasures in terms of
suitability alone by assuming that the life-cycle costs are the same for all countermeasures.
C.4
In Section 3.2.5 the five factors that compose the methodology are described in detail. Flow
charts illustrating selection factors S1 through S4 and reference to Excel spread sheet
support follows.
C.3 Additional Considerations and Support
Federal or state regulations that preclude and use of a particular countermeasure because of
environmental considerations and permitting issues are beyond the scope of NCHRP Project
24-07(2). The practitioner in any particular state must be aware of circumstances that may
warrant the exclusion of a countermeasure for consideration at a specific site.
A feature allowing the user to easily include an additional design consideration, such as
state-specific environmental concerns, to the computation of the Selection Index was added
to the Excel-based selection methodology program. Inclusion of an additional selection
criterion will require the user to assign values in the context of the selection factors for all
countermeasures considered.
In addition, a feature was added to the selection methodology Excel spreadsheet capability
to permit a user to introduce another countermeasure and generate selection factor values
for that countermeasure. Inclusion of an additional countermeasure will require the user to
assign values in the context of the design considerations and selection factors. The
supplementary countermeasure feature and design consideration feature can be used
independently or together, as described in the countermeasure selection Excel file available
on the TRB website (http://trb.org/news/blurb_detail.asp?id=7998).
C.5
C.6
C.7
C.8
D.1
APPENDIX D
RIPRAP INSPECTION RECORDING GUIDANCE
D.2
D.3
APPENDIX D
Riprap Inspection Recording Guidance
To guide the inspection of a riprap installation, a recording system is presented in this
appendix. This guidance establishes numerical ratings from 0 (worst) to 9 (best).
Recommended action items based on the numerical rating are also provided (Lagasse et al.
2006).
A single-digit code is used as indicated below to identify the current status of the rock riprap
regarding its condition compared to the design intent, and the immediacy of need for
maintenance activities to return it to the design condition.
This guidance covers riprap installations that may be: (1) located on stream banks for lateral
stream stability purposes; (2) placed against bridge piers or abutments for protection against
scour at the structure; (3) placed across the stream to provide vertical grade stabilization; or
(4) other applications in riverine environments (e.g., guide banks or spurs).
Code Description
U UNINSPECTABLE:
The riprap is uninspectable, due to burial by sediment, debris, or other
circumstance. Until the condition of the riprap can be reliably determined, a plan
of action should be developed that considers the degree of risk posed by
potential failure of the installation.
9 THE RIPRAP INSTALLATION IS STABLE:
Riprap stones are angular to subangular with no evidence of deterioration or
segregation of sizes; and the distribution of stone sizes and overall thickness of
riprap layer conform to design specifications; and there is no evidence of
displacement of individual stones.
8 THE RIPRAP INSTALLATION IS STABLE:
Riprap stones are angular to subangular with no evidence of deterioration or
segregation of sizes; and the distribution of stone sizes and overall thickness of
riprap layer conform to design specifications; and some displacement of
individual stones is evident, but only smaller sized particles significantly smaller
than the design d
50
size have moved.
7 THE RIPRAP INSTALLATION IS STABLE:
Evidence of some deterioration of stones due to surficial weathering (abrasion,
freeze-thaw or wet-dry spalling); and stone shape is primarily subangular.
OR
A minor decrease in overall layer thickness is evident, and/or particle
displacement noted with displaced particles approaching the design d
50
size;
and the geotextile or granular filter has NOT been exposed.
6 THE RIPRAP INSTALLATION HAS EXPERIENCED EROSION:
Individual stones are primarily subrounded in shape due to surficial weathering;
and the distribution of stone sizes still exhibits a d
50
particle greater than the
minimum allowable d
50
size.
OR
D.4
Minor decrease in overall layer thickness is evident; and some particles greater
than the design d
50
size have been displaced; and the geotextile or granular
filter has NOT been exposed.
5 THE RIPRAP INSTALLATION HAS EXPERIENCED EROSION:
Similar condition as Code 6, except that the geotextile or granular filter has
been exposed in local areas, or around the periphery of the installation. The
inspector should attempt to identify whether stone displacement has occurred
due to gravity slump or slide, or by hydraulic forces.
4 THE RIPRAP INSTALLATION HAS EXPERIENCED SIGNIFICANT EROSION:
Individual stones are subrounded to rounded in shape due to significant
deterioration, and the distribution of stone sizes exhibits a d
50
particle smaller
than the minimum allowable d
50
size.
OR
Significant decrease in overall layer thickness is evident in local areas; and
some particles greater than the design d
50
size have been displaced; and the
geotextile or granular filter has been exposed in local areas.
3 THE RIPRAP INSTALLATION IS UNSTABLE:
The riprap matrix consists primarily of stones smaller than the minimum
allowable d
50
particle size; and the overall layer thickness is less than 50% of
specification.
OR
A significant portion of the particles greater than the design d
50
size has been
displaced, and the geotextile or granular filter has been exposed over more
than 20% of the installation area.
2 THE RIPRAP INSTALLATION IS UNSTABLE:
The riprap matrix consists almost entirely of stones smaller than the minimum
allowable d
50
particle size; and the overall layer thickness is less than 2 particles
thick.
OR
Most of the particles greater than the design d
50
size has been displaced, and
the geotextile or granular filter has been exposed over more than 50% of the
installation area.
1 THE RIPRAP INSTALLATION IS ERODED AND CAN NO LONGER SERVE
ITS FUNCTION. IMMEDIATE MAINTENANCE IS REQUIRED:
Most of the riprap matrix has been displaced or is missing; and native subgrade
soil is exposed.
OR
Large patches or voids in the riprap matrix have been opened; and stones are
no longer in contact with structural elements.
0 THE RIPRAP INSTALLATION IS ESSENTIALLY GONE AND SCOUR IS
IMMINENT. IMMEDIATE MAINTENANCE IS REQUIRED:
The riprap has deteriorated to the point that it cannot perform its protective
function even in minor events.
Particle Size Distribution. During inspection, the existing particle size distribution should be
determined and compared with the design particle size distribution to assess whether the
riprap particles have deteriorated over time. NCHRP Report 568 (Lagasse et al. 2006) and
Design Guideline 4 provide guidance for determining particle size distribution in the field.
D.5
Recommended action.
Code U: The riprap cannot be inspected. A plan of action should be developed to determine
the condition of the installation. Possible remedies may include: removal of debris,
excavation during low flow, probing, or nondestructive testing using ground penetrating radar
or seismic methods.
Codes 9, 8, or 7: Continue periodic inspection program at the specified interval.
Codes 6, 5, or 4: Increase inspection frequency. The rating history of the installation should
be tracked to determine if a downward trend in the rating is evident. Depending on the
nature of the riprap application, the installation of monitoring instruments might be
considered.
Codes 3 or 2: The Maintenance Engineer's office should be notified and maintenance should
be scheduled. The cause of the low rating should be determined, and consideration given to
redesign and replacement. Materials other than standard riprap might be considered.
Code 1 or 0: The Maintenance Engineer's office should be notified immediately. Depending
upon the nature of the riprap application, other local officials and/or law enforcement
agencies may also need to be notified.
D.6
(page intentionally left blank)