Construction Details Part 2-Earthwork: Section 201-Clearing and Grubbing
Construction Details Part 2-Earthwork: Section 201-Clearing and Grubbing
76
CONSTRUCTION DETAILS
Part 2-Earthwork
SECTION 201-CLEARING AND GRUBBING
201.01-Description ....................................................................................77
201.02-Equipment .....................................................................................77
201.03-Clearing and Grubbing................................................................77
201.04-Disposal of Debris .........................................................................78
201.05-Method of Measurement ..............................................................79
201.06-Basis of Payment...........................................................................79
201
77
SECTION 201-CLEARING AND GRUBBING
201.01-Description. This work shall consist of clearing, grubbing, removal
and disposal of all vegetation and debris within the limits of the rights-of-
way and easement areas, except objects designated to remain, or are to be
removed in accordance with other sections of these Specifications, as
indicated otherwise on the Plans or as directed by the Engineer. This work
shall also include the preservation from injury or defacement of all
vegetation and objects designated to remain.
EQUIPMENT
201.02-Equipment. All equipment necessary for the satisfactory
performance of the work shall be on the project and approved before the
work will be permitted to begin.
CONSTRUCTION REQUIREMENTS
201.03-Clearing and Grubbing. The Engineer or Contractor when
required will establish rights-of-way lines and construction lines, and the
Engineer will designate all trees, shrubs, plants, and other objects to remain.
The rights-of-way necessary for construction, as directed by the Engineer,
shall be cleared of all dead trees, stumps, brush, projecting roots, hedge,
weeds, pole stubs, logs, and other objectionable material. All trees, stumps,
roots, pole stubs, brush, hedge, and other protruding obstructions within the
area bounded by lines 5 ft. (1.5 m) outside the construction lines shall be
completely grubbed except sound undisturbed stumps and roots which will
be a minimum of 5 ft. (1.5 m) below subgrade or slope of embankment may
be allowed to remain in place provided undercutting or other corrective
measures, or topsoil stripping is not stipulated in the Plans or directed by
the Engineer and providing stumps do not extend more than 6 in. (15 cm)
above the ground surface. This work shall be done in advance of
excavation and embankment operations.
When embankments are to be constructed in swampy areas, and
undercutting or other corrective measures are not stipulated in the Plans or
directed by the Engineer for these areas, undisturbed trees and stumps may
be cut off at not more than 6 in. (15 cm) above the ground surface or low
water level and the stump and root mass remain in place, if approved by the
Engineer.
Unless marked for removal by the Engineer, living trees more than 5 ft.
(1.5 m) outside the construction lines of the road are to be undisturbed, and
are to be protected by the Contractor during construction of the project.
Cut or scarred surfaces of trees or shrubs shall be treated with a paint
prepared especially for tree surgery.
Clearing of hedge, weeds, pole stubs, logs, and other objectionable
material inside the rights-of-way but outside the construction lines shall be
completed to the ground surface.
Low hanging branches and unsound or unsightly branches on trees or
shrubs designated to remain shall be removed as directed. Branches of
201
78
trees extending over the roadbed shall be trimmed to give a clear height of
20 ft. (6 m) above the roadbed surface. All trimming shall be done by
skilled workmen and in accordance with good tree surgery practices.
Trees more than 5 ft. (1.5 m) outside the construction lines and marked
for removal by the Engineer shall be cut off within 6 in. (15 cm) of the
ground surface. All stumps more than 5 ft. (1.5 m) outside the construction
lines shall be trimmed to within 6 in. (15 cm) of the ground surface.
Wood debris that is chipped on site shall be properly disposed of so
that does not become part of embankment. Within the areas where
embankments are to be constructed, all depressions resulting from grubbing
operations shall be backfilled with suitable excavation material and
compacted in accordance with the provisions of Section 205 to natural
ground elevation before embankment construction is started.
Depressions in excavation areas which are below finished subgrade
elevation resulting from grubbing operations shall be backfilled with
suitable material and compacted to finished subgrade in accordance with
the provisions of Section 205 during the excavation operations.
Backfilling shall be completed a satisfactory distance ahead of
embankment construction operations.
All slopes of cuts, embankments, ditches, channels, waterways and all
structures both old and new, shall be cleared of all brush, hedges, weeds,
heavy vegetation, and other objectionable material; and shall be maintained
in a neat and satisfactory condition until the project is accepted.
Areas approved as borrow pits by the Engineer shall be cleared and
grubbed of all trees, stumps, brush and heavy vegetation. Areas designated
for obtaining construction material other than borrow material shall be
cleared and grubbed of trees, stumps, brush and vegetation, and in addition
shall be stripped of overburden laying above the material to be obtained.
This work shall be completed well in advance of the removal of borrow or
construction materials.
Areas within the limits of all drainage structures shall be cleared of all
objectionable material to within 3 in. (75 mm) of the ground surface. Such
areas shall extend the full length of the structures, as measured along the
center-line of the highway, and to the rights-of-way lines along lines
parallel to the centerline of the inlet and outlet channel or drainage of the
structure. These areas shall also include the entire area of all easements
obtained for drainage purposes.
201.04-Disposal of Debris. If perishable material is burned, it shall be
burned under the constant care of competent watchmen at such times and in
such a manner that the surrounding vegetation, other adjacent property, or
anything designated to remain on the rights-of-way will not be jeopardized.
Burning shall be done in accordance with applicable laws and ordinances.
When permitted by the Engineer, perishable materials and debris may
be removed from the rights-of-way and disposed of at locations off the
project, outside the limits of view from the project during all seasons with
the written permission of the property owner on whose property the
materials and debris are to be placed. The Contractor shall make all
necessary arrangements with property owners for obtaining suitable
disposal locations and the cost involved shall be included in the unit price
201
79
bid for other items of construction. A copy of each agreement with
property owners is to be furnished the Engineer. In addition the material
shall be disposed of in accordance with all applicable laws and ordinances
regarding solid wastes as per Tennessee Department of Environment and
Conservation requirements.
If the construction is through land subject to scour, the Engineer may
direct the Contractor to dispose of stumps, logs, brush, etc. in the scoured
ditches within the limits of the rights-of-way and cover the material so
deposited with suitable excavation or borrow material. If the Contractor
secures permission to dispose of such material in scoured ditches on private
property but within view of the roadway, he will be required to cover the
material so deposited thoroughly with suitable material at his own expense.
All merchantable timber in the clearing area which has not been
removed from the rights-of-way prior to the beginning of construction shall
become the property of the Contractor unless otherwise provided.
COMPENSATION
201.05-Method of Measurement. When the bid schedule contains an item
for Clearing and Grubbing on a lump sum basis, no measurement of area
will be made. In cases where changes in the contract documents affect the
rights-of-way area or when additional Clearing and Grubbing is required in
conjunction with the item for, Road and Drainage Excavation (Additional
Material), a proportionate adjustment for the increased or decreased area
will be made except when the item for Adjusted Clearing and Grubbing is
in the bid schedule and then these adjustments in area will be measured and
paid for by the acre(hectare).
Unless otherwise indicted by the Plans, no separate measurement or
payment will be made for the items of work defined under Clearing and
Grubbing and such will be considered incidental to the work.
When borrow material is obtained from borrow pits furnished by the
Contractor, the clearing and grubbing cost shall be included in the unit price
bid for Borrow Excavation. On areas obtained by the Department and
designated as borrow pits, the cost of clearing and grubbing will be
measured and paid for by the acre(hectare), provided the item for Clearing
and Grubbing (Borrow Pits) is in the contract. When the item for Clearing
and Grubbing (Borrow Pits) is not in the contract, the costs of clearing and
grubbing areas obtained by the Department and designated as borrow pits,
shall be included in the unit price bid for Borrow Excavation.
When the contract does not contain an item for Clearing and Grubbing,
Clearing and Grubbing will be required within the construction limits of
work being performed and will not be paid for directly but will be
considered as a subsidiary obligation of the Contractor under other contract
items.
201.06-Basis of Payments. Payment for Clearing and Grubbing shall be
made at the contract unit price per lump sum and payment for adjustments
to Clearing and Grubbing under the item for Adjusted Clearing and
Grubbing at the contract unit price per acre(hectare), shall be full
201
80
compensation for completing the Clearing and Grubbing as outlined on the
Plans and in these Specifications.
When proportionate payments are made, they will be based on a price
per unit of area obtained from the total area of rights-of-way acquired
within the limits of the project before any change and the lump sum amount
bid for Clearing and Grubbing.
Payment for Clearing and Grubbing (Borrow Pits) at the contract unit
price per acre (hectare) shall be full compensation for completing the
Clearing and Grubbing of Department furnished borrow pits as outlined in
the Plans and in these Specifications.
202
81
SECTION 202-REMOVAL OF STRUCTURES AND
OBSTRUCTIONS
202.01-Description .................................................................................... 82
202.02-Equipment..................................................................................... 82
202.03-General .......................................................................................... 82
202.04-Removal of Bridges, Culverts, & Other Drainage Structures.. 83
202.05-Removal of Pipe............................................................................ 84
202.06-Removal of Pavement, Sidewalks, Curbs, Etc. Constructed of
Portland Cement Concrete .......................................................... 85
202.07-Removal of Underground Storage Tanks................................... 85
202.08-Water Well Abandonment........................................................... 86
202.09-Method of Measurement.............................................................. 87
202.10-Basis of Payment........................................................................... 88
202
82
SECTION 202-REMOVAL OF STRUCTURES AND
OBSTRUCTIONS
202.01-Description. This work shall consist of the removal, wholly or in
part, and satisfactory disposal of all buildings, fences, structures, old
pavements, abandoned pipe lines, and any other obstructions which are not
designated or permitted to remain, except for the obstructions to be
removed and disposed of under other items in the Contract. It shall also
include the salvaging of designated materials and backfilling the resulting
trenches, holes, and pits. When the Proposal does not include pay items for
Removal of Structures and Obstructions as set out in this Section, such
work shall be performed and the costs thereof shall be included in the prices
bid for other items of construction.
EQUIPMENT
202.02-Equipment. All equipment necessary for the satisfactory
performance of this work shall be on the project and approved before the
work will be permitted to begin.
CONSTRUCTION REQUIREMENTS
202.03-General. The Contractor shall raze, remove and dispose of all
buildings and foundations, structures, fences and other obstructions, any
portions of which are on and off the rights-of-way as indicated on the plans,
except utilities and those for which other provisions have been made for
removal. All material from such work designated to become the property of
the Department shall be removed without unnecessary damage, in sections
or pieces which may be readily transported, and shall be stored and
protected by the Contractor at specified places within the project limits or
indicated by the plans, and all material not so designated will become the
property of the Contractor and shall be disposed of outside the limits of
view from the project. If the material is disposed of on private property, the
Contractor shall secure written permission from the property owner. A
copy of each agreement with property owners is to be furnished the
Engineer.
The Department reserves the right to dispose of buildings on any tract
prior to their being torn down or removed by the Contractor. Structures
containing friable asbestos and specified to be removed by the Contractor
shall be demolished by the Contractor in accordance with the policy and
regulations of the Tennessee Department of Environment and Conservation
(TDEC), including prior notification to TDEC of all pending demolitions.
The Department will remove any friable asbestos from the other structures
to be demolished either prior to, or concurrently with, the Work. Such
removal of friable asbestos by the Department may, or may not, include
complete demolition of the structure. Any structure, or portion of a
structure, remaining after removal of the asbestos by the Department shall
be removed by the Contractor under the appropriate bid item or under the
provisions of Subsection 202.01, as applicable.
202
83
Buildings and other structures, which are indicated on the Plans to be
removed or disposed of by other agencies, will not be held as a charge or
responsibility of the Contractor except that the Contractor waives any and
all claims for interference, delay or damage due to their removal or
nonremoval.
Foundations of buildings and other structures shall be removed to a
depth of not less than 1 ft.(30 cm) below natural ground, except that within
construction limits removal shall be to a depth of not less than 2 ft.(60 cm)
below subgrade elevation. Basement floors shall be broken up to prevent
holding of water. Basements or cavities left by structure removal shall be
filled to the level of the surrounding ground or to Subgrade elevation within
the prism of construction. The material placed in these cavities shall be
compacted in accordance with the provisions of Section 205,
Embankments.
202.04-Removal of Bridges, Culverts, and Other Drainage Structures.
Bridges, culverts and other drainage structures in use by traffic shall not be
removed until satisfactory arrangements have been made to accommodate
traffic.
Unless otherwise specified or directed, such portions of the
substructures of bridges located in a stream shall be removed to 1 ft. (30
cm) below the adjacent ground level or natural stream bottom or the lowest
scour elevation shown on the contract plans if shown to uncover the
existing portion of the substructure. An exception to the above rule may
occur if such portions of the substructure of a bridge is located in a
navigable stream, and then it shall be subject to the requirements set out in
the permit form of the applicable Federal agency approving the location and
plans and authorizing the construction of the bridge. Where such portions
of existing structures lie wholly or in part within the limits for a new
structure, they shall be removed as necessary to accommodate the
construction of the proposed structure.
Steel bridges, precast or precast prestressed bridges and wood bridges
designated to become the property of the Department shall be carefully
dismantled without unnecessary damage. All such material shall be stored
as specified in Subsection 202.03.
The removal of bridge decks shall be governed by the following:
1. Where bridge decks are to be wholly removed, but the girders are
to remain in service;
A. If the contractor elects to employ concrete saws to aid in the
removal of the concrete deck, sawing transverse, the depth of
the cut may not exceed the following :
o Decks supported by steel beams or girders, 3-in. (75mm.)
o Decks supported by prestressed concrete beams, 3-in.
(75mm.)
o Decks of cast-in-place hollow box or t-beam bridges, 1-
in. (25mm.)
202
84
B. The remainder of the slab depth under the cuts must be
completed using pneumatically or electrically operated
chipping hammers, not exceeding 60 lbs. (27.2 kgs.) in
weight.
C. Longitudinal saw cuts may be full depth, but no closer than
o Decks supported by steel beams or girders, within 1-in.
(25 mm) of the widest top flanges.
o Decks supported by prestressed beams, within 1 in. (25
mm) of the top flange.
o Decks of hollow boxes or t-beam bridges, within 1-in. (25
mm) of the web, unless otherwise noted on the contract
plans.
2. Where only the slab overhangs are to be removed, and if the
contractor elects to employ concrete saws to aid in the removal of
overhangs, only the top 1-in. (25 mm) of the slab may be saw cut.
Pneumaticly or electrically operated chipping hammers, not
exceeding 60 lbs. (27.2 kgs.) in weight may be used to remove the
remainder of the concrete. Care shall be taken not to damage
transverse slab reinforcing bars.
3 Where bridge decks are to be removed as part of complete bridge
demolition and the contractor elects to employ concrete saws in the
removal of the deck, the depth of the cuts may not exceed the
following:
A. Decks supported by steel beams or girders, the plans depth of
slab minus 1-in. (25 mm).
B. Decks of hollow box or t-beam bridges; if not otherwise
shown on the contract plans, the contractor shall submit a plan
to the engineer for approval.
The use of hoe rams, pneumatic shears, pavement breakers, or other
heavy equipment to remove slabs, where girders or adjacent slab portions
are to remain, is strictly prohibited.
Blasting or other operations necessary for the removal of an existing
structure or obstruction, which may damage new construction, shall be
completed prior to placing the new work, or adequate precautions shall be
taken to prevent such damage.
202.05-Removal of Pipe. Pipe designated to become the property of the
Department shall be carefully removed and every precaution taken to avoid
breaking or damaging the pipe. Pipes shall be removed, and stored when
necessary, so that there will be no loss or damage. The Contractor will be
required to replace sections damaged by negligence or by use of improper
methods.
202
85
202.06-Removal of Pavement, Sidewalks, Curbs, Etc. Constructed of
Portland Cement Concrete. All pavement, base course, sidewalks, curbs,
and gutters, etc. constructed of portland cement concrete designated for
removal shall be disposed of as directed. Failure of the Plans to identify the
existence of concrete pavement under asphaltic pavement shall not be
construed to imply that concrete is not present. It shall be the Contractor's
responsibility to determine the presence of concrete pavement when not
identified by the Plans.
Concrete pavement, parking strip, and base, all with or without
bituminous overlay, concrete curb and gutter, sidewalk, driveways, etc.
shall be removed and disposed of as follows:
o If the items are below subgrade elevation, but by not more than 2
ft.(60 cm), they shall be removed, disposed of, and the work paid
for in accordance with this Section 202.
o If the items are more than 2 ft.(60 cm) below subgrade elevation,
they shall be broken into sizes not to exceed 2 ft.(60 cm) in
maximum dimension and remain in place, unless it interferes with
succeeding items of construction. The cost of this work shall be
included in the unit price bid for other items of construction and
shall not be paid for directly.
o If the items are above subgrade elevation, the removal and disposal
of same shall be paid for as provided in Section 203.
o When specified, ballast, gravel, bituminous pavement or other
pavement materials shall be removed and stockpiled as required in
Subsection 202.03; otherwise, such materials shall be disposed of
as directed.
202.07-Removal of Underground Storage Tanks The Department will
remove and dispose of all Petroleum Underground Storage Tanks or Tank
Systems through its Environmental Consultant. This work shall include
removal and disposal of piping, pumps, and other tank fixtures, the
investigation and testing of the tank(s) for leakage, and backfilling the
resulting holes or trenches as specified on the plans or as approved by the
Engineer. This work shall be done in accordance with the "Tennessee
Petroleum Underground Storage Tank Act", the policies and regulations of
the Tennessee Department of Environment and Conservation, the United
States Environmental Protection Agency, and local ordinances or statutes
governing removal of Underground Storage Tanks.
A Petroleum Underground Storage Tank shall be defined as any one or
combination of tanks including underground piping which are used or have
been used to contain an accumulation of petroleum substances, and the
volume of which is 10% or more beneath the surface of the ground.
In the event the Department includes the pay item for this Removal and
Disposal in the contract then before work begins, the Contractor shall
submit an application for closure of each Petroleum Underground Storage
Tank or Tank System to the Tennessee Department of Environment and
Conservation, Division of Underground Storage Tanks.
The Contractor shall furnish the Engineer copies of his application for
closure, the approval of that application from the Tennessee Department of
202
86
Environment and Conservation, laboratory test reports, closure notification
form and all pertinent correspondence.
The Contractor shall engage a laboratory approved by the Tennessee
Department of Environment and Conservation, to perform all required
sampling and testing for leakage and/or contamination before and after
removal of the tank(s). Upon receipt of written approval from the
Tennessee Department of Environment and Conservation, the Contractor
may proceed with removal of the tank(s) in strict adherence to the
regulations of that Department. If soil testing either before or after tank
removal reveals contamination of the soil, the Contractor shall remove and
dispose of the contaminated soil in accordance with Tennessee Department
of Environment and Conservation regulations.
If the volume of contaminated soil to be removed is 500 C.Y. (m
3
) or
less, removal and disposal of the contaminated soil will be paid for under
the item for Road and Drainage Excavation (Unclassified). However, the
removal, disposal and replacement of contaminated soil in excess of 500
C.Y. (m
3
) may be considered Extra Work as set forth in Subsection 104.03
of the Standard Specifications and paid for as such in accordance with
Subsection 109.04, Methods of Payment for Extra Work.
After removal, the tank(s) and tank fixtures shall become the property
of the Contractor unless otherwise stipulated in the plans. Ownership of the
tank(s), however, shall not relieve the Contractor of the responsibility of
labeling, transporting, and disposing of the tank(s) according to regulations
of the Tennessee Department of Environment and Conservation.
After removal of the tank(s) and contaminated soil, the hole or trench
shall be backfilled if required with material specified on the plans or
approved by the Engineer. Cost of backfill material including hauling,
placement, and compaction shall be included in the lump sum price bid for
Removal of Underground Tanks.
202.08-Water Well Abandonment. This work shall consist of locating
and sealing abandoned water wells and shall include the removal and
satisfactory disposal of pumps, pipe, and other related items not provided
for elsewhere in the contract. This work shall be performed in accordance
with all applicable regulations of the Tennessee Department of
Environment and Conservation.
Flowable fill used for sealing wells shall be as specified herein.
All abandoned wells shall be sealed by one of the following methods:
1. Wells with a diameter of 1 ft.(30 cm) or less.
All pumps and related plumbing shall be removed by a
licensed driller or pump installer. Then the bore hole shall be
cleared of all other obstructions and cleaned by a licensed well
driller by drilling, blowing or bailing as applicable. Laundry
bleach shall be added to the water in the well to equal 1 qt. (2.5
liters) of bleach for each 100 gal. (m
3
) of water to disinfect the
well. The number of gallons of water in the well can be obtained
by subtracting the depth (in feet) to static water level from the total
202
87
depth of the well and then multiplying the result by the factor
0.0408D
2
where D is the diameter of the well in in.. The number
of cubic meters of water in the well can be obtained by subtracting
the depth (in meters) to static water level from the total depth of
the well and then multiplying the result by the factor 0.7854D
2
where D is the diameter of the well in meters)
After disinfecting the well, the licensed well driller shall fill
the well using flowable fill. Bentonite or other approved colloidal
reagent in an amount equal to 1 1/2% by volume of the cement
shall be used as an additive.
The flowable fill material shall extend from the bottom of the
well to within 5 ft. (1.5 m) of the final surface where the well is in
a roadway cut or to within 5 ft. (1.5 m) of the existing ground
surface where the well is located under roadway embankment or
where the well is outside of the construction limits. The flowable
fill shall be piped directly to the point of application by a tremie or
dump bailer to avoid segregation or dilution. The well casing shall
be cut off flush with the top of the flowable fill material.
2. Wells with diameter greater than 1 ft. (30 cm).
All pumps and related plumbing shall be removed and the
well cleared of all other obstructions as described in Item 1 above.
The water in the well shall be disinfected by adding 1 qt. (2.5
liters) of bleach for each 100 gal. (m
3
) of water. The amount of
bleach to be used shall be computed as described in Item 1 above.
The bottom 5 ft. (1.5 m) of the well or a depth equal to the
depth of the water, whichever is greater, shall be filled with
flowable fill as specified in Item 1 above. The remainder of the
well shall be filled with compacted soil. Any projecting well
casing or wall shall be removed or cut off 5 ft. (1.5 m) below the
existing or proposed ground surface, as applicable.
In the event that flowable fill loss is excessive due to crevices in the
wall of the borehole, Mineral Aggregate, Type A Base, Grading "D" shall
be used to seal the crevices. Once the crevices are sealed, filling with
flowable fill shall be resumed.
Immediately after the wells have been sealed, an affidavit shall be sent
to the Tennessee Water Supply Division stating the name of the licensed
Contractor(s) who performed the cleaning and sealing of the wells, the
project number, location of the wells, type and sequence of material used,
volume of material used, and date completed.
COMPENSATION
202.09-Method of Measurement. When the Contract stipulates that
payment will be made for removal of structures and obstructions on a lump
sum basis, the pay item, Removal of Structures and Obstructions, will
include all structures and obstructions encountered within the rights-of-
way, except for any structures and obstructions specified for removal on a
202
88
unit basis with measurement and payment made by the unit stipulated in the
Contract.
Removal of Rigid Pavements, Sidewalks, etc. to be paid for under
Section 202, as provided for under Subsection 202.06, will be measured
for payment by the square yard (square meter) in accordance with the
provisions of Section 109, Measurement and Payment.
Where the removal of pipe is designated as a specific item, it will be
measured in linear feet (meter).
When the contract stipulates that payment will be made for removal of
Underground Storage Tanks on a lump sum basis, the pay item, Removal of
Underground Tanks (Tract No.________), will include all Underground
Storage Tanks, piping, pumps, and other tank fixtures, any portion of which
is on the designated tract.
The sealing of abandoned wells shall be measured per each, which
includes the cost of the flowable fill.
The sealing of abandoned wells shall be measured per each except for
the flowable fill for which measurement will be made by the cubic yard
(cubic meter).
202.10-Basis of Payment. The accepted quantities of Removal of
Structures and Obstructions will be paid for at the contract lump sum price
bid, which price shall be full compensation for removing and disposing of
the obstructions in accordance with the Contract.
The accepted quantities for Removal of Underground Tanks(Tract
No.________) will be paid for at the contract lump sum price bid, which
price shall be full compensation for locating, drilling, testing, removing and
disposing of the tank(s), and backfilling where required.
The lump sum payment for Water Well Abandonment shall be full
compensation for all labor, equipment, materials, including flowable fill,
and incidentals necessary to complete the work.
Specific obstruction items, including pipe removal, stipulated for
removal and disposal under unit price pay items and Removal of Rigid
Pavements, Sidewalks, etc. will be paid for at the contract unit price bid per
unit specified in the proposal, which price shall be full compensation for
removal and disposal of such items, excavation and subsequent backfill
incidental to their removal. The price shall also include salvage of
materials removed, their custody, preservation, storage on the rights-of-
way, or disposal as provided herein.
Payment will be made only when payment for all or any part thereof is
provided for in a "Pay Item."
203
89
SECTION 203-EXCAVATION AND
UNDERCUTTING
203.01-Description .................................................................................... 90
203.02-Classification................................................................................. 90
203.03-Equipment..................................................................................... 92
203.04-General .......................................................................................... 92
203.05-Undercutting ................................................................................. 96
203.06-Stripping, Stockpiling and Placing Topsoil ................................ 97
203.07-Disposal of Excess or Unsuitable Material ................................. 97
203.08-Sloping, Shaping and Dressing.................................................... 99
203.09-Method of Measurement............................................................ 100
203.10-Basis of Payment......................................................................... 102
203
90
SECTION 203-EXCAVATION AND
UNDERCUTTING
203.01-Description. This work shall consist of excavating and grading the
roadway (including the removal of slides), borrow pits, waterways, ditches
(including structure inlet and outlet ditches, channels, waterways, etc., even
though they extend beyond the highway limits); intersections, approaches,
benches under the side-hill embankments; excavating of unsuitable material
from roadbed and beneath embankment areas; excavating selected material
found in the roadway which is ordered for specific use in the construction;
the construction and removal of detours authorized by the Engineer or
otherwise detailed on Contract drawings; trimming and shaping of all
slopes; and disposing of all excavated material all in accordance with these
Specifications and in reasonably close conformity with the lines, grades and
typical cross sections shown on the Plans or established by the Engineer. It
shall include all embankment construction, Section 205, shoulder and ditch
construction, Section 208, and in cases where construction of pavement or
other surfacing is included in the Contract, Subgrade Construction and
Preparation, Section 207.
203.02-Classification. The work will be classified and paid for as follows:
(a) Road and Drainage Excavation (Unclassified).
All excavation performed under this Section, including
portland cement concrete located above subgrade elevation, other
than Borrow Excavation, Channel Excavation, and Undercutting,
will be considered unclassified excavation regardless of the nature
of the material excavated.
(b) Borrow Excavation.
Borrow Excavation shall consist of material required for the
construction of embankments or other portions of the work and
shall be obtained from approved sources outside the right-of way
limits, unless otherwise designated in the Plans. However, any
material, other than Borrow Excavation (Unclassified), as may be
found in the excavation that meets the specifications of the
designated borrow material may be used in the project in
accordance with the conditions prescribed in Subsection 104.10.
However, if the flattening of certain cut slopes on projects graded
under previous contracts is desirable and approved in writing by
the Engineer, the Contractor will be permitted to use this material
for borrow provided the material is satisfactory and in accordance
with plans approved by the Engineer, and provided he complies
with the requirements of Subsection 203.04 regarding borrow
areas. Borrow material shall not be obtained from wetland areas,
unless otherwise noted on the Plans.
203
91
Borrow shall be classified as Borrow Excavation (Solid
Rock), Borrow Excavation (Graded Solid Rock), Borrow
Excavation (Unclassified), or Borrow Excavation (Select
Material). Borrow Excavation (Solid Rock) shall consist of the
removal and satisfactory placement of non-degradable rock which
cannot be economically excavated by the proper use of a power
shovel or without the use of explosives. Borrow Excavation
(Unclassified) shall consist of the removal and satisfactory
placement of all approved material encompassed under the
classification of Borrow Excavation (Solid Rock) and all other
approved material.
Borrow Excavation (Graded Solid Rock) shall consist of the
removal and satisfactory placement of sound, non-degradable rock
with a maximum size of 3 ft. (1 m). At least 50 percent of the rock
shall be uniformly distributed between 1 ft. (30 cm) and 3 ft. (1 m)
in diameter and no greater than 10 percent shall be less than 2 in.
(50 mm) in diameter. The material shall be roughly equi-
dimensional in shape. Thin, slabby material will not be accepted.
The Contractor shall be required to process the material with an
acceptable mechanical screening process that produces the
required gradation. When the material is subjected to five
alternations of the sodium sulfate soundness test (AASHTO T
104), the weighted percentage of loss shall be not more than 12.
The material shall be approved by the Engineer before use.
Borrow Material other than solid rock shall be AASHTO M
145, classification A-6 or better if reasonably available. If
classification A-6 is not reasonably available, the borrow shall be
no worse than the predominant soil type in the roadway excavation
based on AASHTO classification.
Borrow Excavation (Select Material) for special construction
purposes shall meet the requirements set forth in the Contract.
Material obtained from an approved borrow source off the
right-of-way as provided in this Subsection shall not be utilized to
produce processed aggregate as described in Section 903. In no
case shall material excavated from an off site borrow source be
utilized in base or other paving courses above the elevation of the
subgrade.
Unless otherwise designated in the Contract, the Contractor
shall make his own arrangements for obtaining borrow material
and shall pay all the costs involved including Archeological
approval of source along with permits as required by the
Tennessee Department of Environment and Conservation.
(c) Channel Excavation (Unclassified).
This item shall consist of the removal and satisfactory disposal
of all material, regardless of its nature and the manner in which it
may be removed, that is excavated for channel changes in
widening, deepening, and straightening existing channels or
constructing new ones, which have a width at the bottom of more
than 14 ft. (4 m) as indicated on the Plans. All other similar
203
92
excavation with a bottom width 14 ft. (4 m) or less, as shown on
the Plans, shall be paid for as Road and Drainage Excavation
(Unclassified).
(d) Undercutting.
This item shall consist of removing and disposing of
unsatisfactory materials below grade in cut sections, from areas
upon which embankments are to be placed, and may also include
material excavated below the Foundation elevation for pipe, box
culverts and box bridges as described in Subsection 204.12.
Undercutting does not include the stripping, stockpiling and
placing of topsoil, described in Subsection 203.06, nor does it
include step-benching in the preparation of embankment areas on
hillsides.
EQUIPMENT
203.03-Equipment. All equipment necessary for the satisfactory
performance of this work shall be on the project and approved before work
will be permitted to begin.
CONSTRUCTION REQUIREMENTS
203.04-General. Prior to beginning excavation, grading, and embankment
operations in any area, all necessary Clearing and Grubbing, Removal of
Structures and Obstructions and placement of Erosion Control Devices in
that area shall have been performed in accordance with Section 201,
Section 202 and Section 209, respectively, of these Specifications.
Balance points, controlling the balancing of earthwork quantities as
indicated on the Plans, are approximate only and it is the prerogative and
obligation of the Engineer to make such changes in balance points as are
necessary to aid further in balancing of earthwork quantities, or to dispose
of surplus excavation.
Balance points, controlling the balancing of earthwork quantities as
indicated on the Plans, are approximate only and it is the prerogative and
obligation of the Engineer to make such changes in balance points as are
necessary to aid further in balancing of earthwork quantities, or to dispose
of surplus excavation, provided such changes do not move any balance
point more than 2,000 ft. (600 m). The Contractor will not be allowed any
additional compensation due to changing any or all of the balance points on
the project no more than 2,000 ft. (600 m).
If the earthwork cannot be balanced without shifting the balance points
more than 2,000 ft. (600 m), the Engineer may direct that excavation
materials be hauled anywhere within the project limits. Overhaul of Road
and Drainage Excavation (Unclassified) or Channel Excavation
(Unclassified) from one balance to another balance after the balance points
have been adjusted as provided above, shall be measured and paid for
according to the provisions of Subsection 203.09 and Subsection 203.10.
Excavation materials shall be removed in such a manner that the slopes
may be neatly trimmed to the lines given. The Engineer may change the
203
93
slopes shown on the original cross sections, depress raised medians or
islands, raise depressed medians or islands or daylight cuts to increase or
decrease the quantity of Road and Drainage Excavation (Unclassified)
provided the material can be excavated without blasting and these changes
are set in the slope stakes prior to commencement of excavation of the
affected slopes, medians or islands. Any additional material thus obtained
shall be paid for at the contract unit price bid for Road and Drainage
Excavation (Unclassified).
Excavation required to correct slides, regardless of its location relative
to the theoretical slope line, or excavation required to prevent potential
slides including blasting, and the dressing, reshaping or flattening of the
affected slopes as directed by the Engineer, shall be paid for under the Item
for Road and Drainage Excavation (Additional Material) in accordance
with Subsection 203.10. If it becomes necessary to flatten a slope to
correct a slide or prevent a potential slide after the cut has been started but
not completed, payment under Road and Drainage Excavation (Additional
Material) will be limited to material removed between the original staked
slope line and the newly established slope line above the elevation to which
the cut has been made. All other material will be paid for at the contract
unit price of Road and Drainage Excavation (Unclassified). Seeding, sod
and other incidental items required to repair the slide area will be paid for at
the contract unit price bid for the respective items.
If more material is required to complete the embankments after all cuts
have been brought to grade and all Road and Drainage Excavation
(Unclassified) has been removed from within the balance, additional
materials shall be obtained from within the rights-of-way by flattening,
widening or daylighting cut slopes, and by depressing raised medians or
islands at locations designated and as directed by the Engineer provided:
(a) The cost of this material is more economical than borrow
excavation.
(b) The material is available within the adjusted balance where the
shortage exists or the material may be hauled outside the limits of
adjusted balance if the cost of the material is more economical
than borrow when the additional cost of overhaul is considered.
(c) The material can be excavated without blasting.
(d) There is a minimum of 20 ft. (6 m) between the top of the existing
slope and the top of the new slope and minimum of 5 ft. (1.5 m)
between the top of the new slope and Rights-of-Way Line or
Control Access fence. The 20 ft. (6 m) minimum will not apply
when the existing slope is 4:1 or flatter or to overlapping or near
overlapping slopes in medians or between parallel roads or ramps.
The 20 ft. (6 m) minimum may be reduced at the written request of
the Contractor.
203
94
This additional material is to be paid for under the item for Road and
Drainage Excavation (Additional Material) in accordance with Subsection
203.10.
When additional material is paid for under the item for Road and
Drainage Excavation(Additional Material) and additional clearing and
grubbing is required, the additional clearing and grubbing will be measured
and paid for by the acre (hectare), provided the item for Adjusted Clearing
and Grubbing is in the Contract, otherwise a proportionate payment under
the item for Clearing and Grubbing will be made. No additional payment
will be made for extra handling of stockpiled topsoil made necessary by the
use of the item for Road and Drainage Excavation (Additional Material).
The roadbed through rock cuts shall be constructed to the grading line
shown on the Plans, with an allowable working tolerance of plus 1 to minus
3 in. (plus 25 to minus 75 mm). The portions of the roadway that are less
than 3 in. (75 mm) below grade shall be brought to grade with spalls or
other suitable granular material that is available from the excavation within
the balance. If such excavation is not available, the Engineer may direct the
Contractor to use approved base material for capping. Payment for
furnishing and placing said base material will be made at the contract unit
price bid per ton (metric ton) for the applicable Item in Subsection 303.14.
When base material is not a bid item in the Contract, the material shall be
furnished under the provisions of Subsection 104.03. If the roadbed is
excavated in excess of 3 in. (75 mm ) below the grading line shown on the
Plans, the Contractor will be required to furnish and place at his own
expense sufficient amounts of spalls or base material to bring the roadbed to
a line 3 in. (75 mm) below the grading line.
Where sodding is indicated on the Plans to be placed on rock cuts, the
rock shall be removed to 1 ft. (30 cm) below the grading line and backfilled
to grade with earthen material prior to placing the sod. Measurement and
payment of this work will be made under Items for Roadway and Drainage
Excavation (Unclassified) and Sodding (New Sod).
All suitable materials removed from the excavation areas shall be used
in the construction of embankments, intersecting road approaches, and in
such other places as directed. Embankment construction shall be performed
in accordance with the provisions of Section 205 of these Specifications.
When boulder formations occur, the roadbed in the excavation area
shall be scarified and all boulders removed to a depth of 12 in. (30 cm)
below grade. The cavities thus formed shall be backfilled with suitable
material and compacted.
All rock cuts shall be presplit at the outside limits of the cut areas.
Presplitting shall consist of forming a plane of split rock prior to any
primary blasting. The plane shall be formed for the entire depth of the cut
or to a predetermined bench level. Presplitting shall be accomplished by
drilling holes of appropriate size to the desired depth along the outside
limits of the cut area, loading such holes with appropriate charges of
explosives, stemming with minus 3/8 in. (9.5 mm) clean stone chips to the
collar of the holes and detonating simultaneously. The initial horizontal
spacing of holes and vertical spacing of charges and blasting cord for
simultaneous detonation shall be as recommended by a reliable powder
company. Adjustments of horizontal hole spacing and vertical spacing of
203
95
charges shall be made as necessary to obtain a relatively smooth shear
plane. Sand, gravel, clay, or dirt will not be permitted for stemming. In
drilling holes for presplitting, the drills shall be plumbed for vertical slopes
or set on the required slope when other than vertical slopes are specified,
and all holes shall be drilled in the same plane. Presplitting will not be
required on slopes flatter than 1 to 1. After presplitting is done, the drilling
of primary blast holes shall be kept at least 3 ft. (1 m) or more from the
presplit face. Presplitting of rock cuts under bridge sites shall be in
accordance with the provisions of this Subsection and hole spacing shall be
as specified under Subsection 204.08. Blasting records shall be made
available on request by the Engineer. Blasting shall not be permitted within
300 ft. (100 m) of any Structure or concrete until at least 72 hours have
elapsed after placement of the concrete. The Contractor will be responsible
and replace and/or repair any and all damages at no expense to the
Department.
All loose rock on cut slopes shall be removed immediately. Excavation
material shall not be wasted, deposited or disposed of outside the
construction lines unless directed by the Engineer. Obliteration of old
roadways shall include all grading operations necessary to incorporate the
old roadway into the new roadway and surroundings in order to provide a
pleasing appearance from the new roadway.
Removal of concrete pavement, base, parking strip, sidewalk, curb and
gutter, etc. will be paid for under the classifications as prescribed in
Subsections 202.06 and 203.02(a). Roadway obliteration will be paid for
as Road and Drainage Excavation (Unclassified).
When the Contractor's excavating operations encounter remains of
prehistoric people's dwelling sites or artifacts of historical or archaeological
significance, the operations shall be temporarily discontinued. The
Engineer will contact archaeological authorities to determine the disposition
thereof.
The Engineer shall designate as unsuitable those soils that cannot be
properly compacted in embankments. All unsuitable soil shall be disposed
of as directed at no additional cost.
When the location of unstable soil is shown on the Plans, its removal
and replacement shall be as shown.
The Contractor shall notify the Engineer sufficiently in advance of
opening any borrow area so that, after stripping, cross section elevations
and measurements of the ground surface may be taken, and so that the
borrow material can be tested before being used. At least 14 days' time
shall be allowed for testing borrow materials or other material from
roadside pits that is proposed for construction purposes.
Unless otherwise permitted, borrow material shall not be placed until
after the roadway excavation has been placed in the embankments. If the
Contractor places more borrow than is required and thereby causes a waste
of excavation, the amount of such waste will be deducted from the borrow
volume as measured in the borrow area. The Contractor shall not excavate
beyond the dimensions and elevations established.
When the Contractor elects to remove highway fencing to obtain
borrow materials, the fencing shall be replaced with new fence at the
203
96
Contractor's expense. The Contractor shall be responsible for the
confinement of livestock when a portion of the fence is removed.
Borrow pits shall be excavated in such a manner that they will be self-
draining where possible and practicable, and shall be of a shape that can be
easily cross sectioned.
When the Contractor's excavation operations are completed the area
shall have a neat appearance. All borrow areas, except those portions
which are under water in the case of pits which are not self-draining, shall
be covered with topsoil and seeded.
Furnishing and placing of topsoil and seeding (with mulch) shall be
performed in accordance with the provisions of Subsection 203.06 and
Section 801, respectively.
Furnishing and placing topsoil and seeding of borrow areas, as
specified above, will not be paid for directly, and the costs thereof will be
included in the prices bid for other items of construction.
The Contractor's attention is called to Sections 53-801 through 53-809
of the Tennessee Code, Annotated, the provisions of which apply to
borrow pits 1 acre (4047 m
2
) or more in size that are not self-draining. Full
information regarding the requirements to be complied with and the
necessary permits which the property owner must secure for the
construction of a pond, lake, borrow pits, etc., one acre or larger which is
not constructed to drain, will be supplied upon application to the Tennessee
Department of Environment and Conservation.
All existing roads within the right-of-way and not in the graded area
that are to be abandoned shall be scarified, obliterated, top-soiled, and
seeded. Scarifying and obliterating the pavement will not be measured and
paid for directly, but the cost will be included in the cost of other items.
Topsoil will be measured and paid as outlined in Section 203.09 and
203.10. Seeding, in accordance with Section 801 of these Specifications,
will be measured and paid for under the item for Seeding.
203.05-Undercutting. This work shall consist of the removal and disposal
of unsatisfactory materials below grade in cut sections, and the removal and
disposal of unsatisfactory material from areas upon which embankments are
to be placed. It shall also include undercutting for pipe and box culverts
where required.
Undercutting does not include the stripping, stockpiling and placing of
topsoil, described in Subsection 203.06; neither does it include step
benching in the preparation of embankment areas on hillsides, as provided
for under Subsection 205.03.
Areas to be undercut will be designated on the Plans if appropriate
information is available. However, the Engineer may increase, decrease, or
shift such designated areas as conditions require as the construction
progresses.
Undercut areas shall be backfilled with suitable material from within
the grading balance, or in the first 1,000 ft. (300 m) of the adjacent balances
if obtainable. If road and drainage excavation is not available, borrow
excavation shall be used for backfilling.
The Contractor shall conduct his operations in such a manner that the
Engineer can take the necessary cross sectional measurements.
203
97
Backfill materials shall be compacted as specified in Section 205,
Embankments.
203.06-Stripping, Stockpiling and Placing Topsoil. The Engineer will
designate areas between slope stake points in both cut and fill from which
the existing topsoil shall be stripped and stockpiled. The quantity of topsoil
to be stripped shall be sufficient to provide, over all areas to be seeded, a
depth of 2 to 3 in. (50 to 75 mm) of the material. If the quantity of topsoil
available in such areas is insufficient, the Contractor shall make up the
deficiency with topsoil from a source outside the rights-of-way. The
quantity of topsoil from such a source shall be measured by cross sectioning
the area before and after removal.
The Engineer will designate areas to be deleted from stripping
operations because of rock or other unsuitable material.
Prior to the stripping operation, the Contractor shall notify the Engineer
in order that the latter may designate the areas on which the topsoil material
will be stockpiled. The stockpile areas shall be located along the project at
locations approved by the Engineer. Each stockpile, when completed, shall
be neatly dressed so that they may be readily measured.
Immediately prior to the preparation of an area for seeding, the
Engineer will cross section the stockpiles of material to be used in the
operation. No stockpiles shall be cross sectioned or topsoil spread until the
construction sequence for seeding has been established and is ready to
proceed. A 2 to 3 in. (50 to 75 mm) layer of topsoil shall be placed where
seeding is required except on cut slopes steeper than 2:1. On cut slopes
steeper than 2:1 that are to be seeded, topsoil shall be spread to a depth of 1
to 2 in. (25 to 50 mm), as directed by the Engineer. Rock slopes and other
rock areas which are to be seeded shall be capped with 9 in. (22.5 cm) of
suitable material, plus 2 to 3 in. (50 to 75 mm) of topsoil. After the
stockpiled topsoil has been placed as specified above, the areas upon which
the topsoil was stockpiled shall be neatly dressed and final cross sections
taken.
203.07-Disposal of Excess or Unsuitable Material. Excess excavation
material shall be used to raise, widen or flatten the slopes of embankments;
to fade embankments into cuts; or be placed in such other locations and for
such purposes as the Engineer may direct.
Specific instructions will be given by the Engineer regarding the
disposal of surplus material. Excess or unsuitable material placed within
the rights-of-way limits shall be placed and compacted in accordance with
Subsection 205.04. Foundation preparation for and drainage through these
waste areas shall be equivalent to that provided for the adjacent roadway
embankment.
If no suitable place can be found to dispose of excess or unsuitable
material within the limits of the rights-of-way, the Engineer may direct the
Contractor to provide a suitable site off the rights-of-way at no additional
cost. Waste material (earth and rock) not required for the construction of
the project will be disposed of by the Contractor. The Contractor will be
required to obtain any and all necessary permits including, but not limited
to, NPDES, Aquatic Resources Alteration Permits, Corps of Engineers
203
98
Section 404 Permits, and TVA Permits. The Contractor will provide copies
of these approved permits prior to commencement of any work. Excess or
unsuitable material placed off the rights-of-way shall be disposed of as
follows:
When waste material is placed contiguous to the rights-of-way, the
requirements for its disposal shall be the same as noted above for waste
areas on the rights-of-way. An exception to these requirements may be
granted for excess or unsuitable material placed contiguous to the
rights-of-way provided the Engineer approves a different procedure
based on a geotechnical investigation of the proposed waste area, made
by an approved geotechnical engineering firm retained by the
Contractor.
Neither a waste area plan nor a geotechnical investigation will be
required for excess or unsuitable material placed in waste areas off the
rights-of-way which, in the judgment of the Engineer, are so removed from
the rights-of-way as to not constitute a potential threat to the stability of the
project provided that:
1. The slope of the existing ground in the proposed waste area site is
not steeper than 4:1.
2. The height of the waste area embankment does not exceed 40 ft.
(12 m).
3. The side slopes of the waste area are constructed on a 2:1 slope or
flatter, except waste rock may be placed on a 1-1/2:1 slope where
approved by the Engineer.
When the waste area does not meet all of criteria (1), (2) and (3) above,
the following requirements apply:
(a) The excess or unsuitable material shall be placed and spread in
horizontal layers not to exceed 10 in. (25 cm), except excess rock
material may be placed in the waste area in layers not exceeding 3
ft. (1 m) in depth. Rock greater than 3 ft. (1 m) in diameter may be
placed in the perimeter of the waste area provided the Contractor's
plan for placing the oversized rock is approved in writing by the
Engineer. Side slopes of material in waste areas shall be 2:1 or
flatter, except side slopes of waste rock material may be 1-1/2:1
when approved by the Engineer.
(b) The Contractor shall submit a plan of each waste area for approval
of the Engineer showing:
1. The location and limits of the area.
2. The original and proposed ground contours.
3. The proposed foundation preparation including benching
where the waste material will be deposited on slopes steeper
than 4:1.
4. The proposed drainage through and/or around the waste area.
203
99
5. The estimated quantity of waste material in cubic yards(cubic
meters).
6. An erosion control plan for the construction of the waste area.
(c) The placement procedures in (a) above may be waived provided
the Engineer approves a different placement procedure based on a
geotechnical investigation conducted by an approved geotechnical
engineering firm retained by the Contractor. The geotechnical
investigation shall include the geologic conditions, boring logs,
materials and strength parameters, stability analysis and proposed
design and construction requirements.
When shown on the Plans, the geotechnical investigation of waste
areas described in paragraph (c) above, shall be a requirement, not an
option of the Contractor. A minimum safety factor will be included on the
plans for this case.
The Contractor shall not dispose of any material either on or off the
R.O.W. in a regulatory floodway as defined by the Federal Emergency
Management Agency without approval by same. All material shall be
disposed of in upland (non-wetland) areas and above ordinary high water of
any adjacent watercourse. This does not eliminate the need to obtain any
other licenses or permits that may be required by any other Federal, State or
local agency.
All waste areas shall be approved in writing by the Engineer prior to
placement of any waste material.
All costs associated with the disposal of excess or unsuitable material
in waste areas shall be borne by the Contractor unless otherwise specified
on the Plans.
Waste areas that are formed by the disposal of excess or unsuitable
material outside of the construction limits shall be covered with topsoil and
seeded. Furnishing and placing the topsoil and seeding (with Mulch) shall
be performed in accordance with the provisions of Subsection 203.06 and
Section 801, respectively.
Furnishing and placing topsoil and seeding waste area inside the
Rights-of-Way shall be measured and paid for at the contract unit prices bid
for the respective items. Furnishing and placing topsoil and seeding on
waste areas outside the Rights-of-Way in accordance with the above
provisions will not be paid for directly, and the costs thereof shall be
included in the unit price bid for other items of construction.
203.08-Sloping, Shaping and Dressing. The slopes of all excavated areas,
ditches, waterways, channels, borrow pits and embankments shall be so
trimmed and shaped as to be in reasonably close conformity with the cross
sections shown on the Plans or as directed by the Engineer.
Rock cuts shall be scaled of all loose fragments, projecting points, etc.
and left in a neat, safe and workmanlike condition.
Excess material created by trimming slopes, resloping, and shaping
shall be disposed of as stipulated in Subsection 203.07 of these
Specifications.
203
100
Final Dressing shall be performed in accordance with the provisions of
Section 206.
COMPENSATION
203.09-Method of Measurement. Road and Drainage Excavation will be
computed by the cubic yard (cubic meter). All accepted excavation
including borrow shall be measured in its original position by cross
sectioning the area excavated. At the option of the Engineer, cross sections
may be determined from conventional manual surveys, aerial surveys,
Digital Terrain Modeling, or a combination of the 3 methods. Hauling of
excavation and borrow materials shall be considered incidental to the
construction and the costs thereof shall be included in the unit price bid for
excavation items.
Excavation required to bench side-hill slopes of embankment
construction will be measured for payment in accordance with the
following requirements:
(a) Excavation in Solid Rock.
1. Will be paid for as Road and Drainage Excavation
(Unclassified) whether the excavation material is bladed and
dozed or picked up and hauled.
(b) Excavation other than Solid Rock.
1. Excavated material that is picked up and hauled will be paid
for as Road and Drainage Excavation (Unclassified).
2. Excavation material that is moved by blading or dozing will
not be paid for directly but the cost shall be included in the
contract price for other items of work.
Authorized excavation of rock, shale, or unsuitable material below
grade shall consist of that excavation necessary to provide the designed
thickness of backfill. If the plane of the designated bottom of excavation
falls within a layer or stratum of rock, the below-grade excavation to the
bottom of the layer, not exceeding 3 in. (75 mm) below grade, will be
considered as authorized and will be measured for payment. If the roadway
is excavated in excess of 3 in. (75 mm) below the grading line shown on
Plans, the Contractor will be required to furnish and place at his own
expense sufficient amount of spalls or approved base course material, or
other suitable approved granular material to bring the roadway to a line 3
in. (75 mm) below the grading line.
Rock cuts which have been presplit in Road and Drainage Excavation
(Unclassified) and Channel Excavation (Unclassified) shall be measured
and paid for by the square yard (square meter). The quantity of presplitting
shall be the s.y. (m
2
) of rock face as determined by the difference in
elevation in yards (meters) between the bottom and top of face, multiplied
by the length of face in yards (meters). The quantity of presplitting shall be
the square yards (square meters) of rock face as determined by the
203
101
difference in elevation in yards (meters) between the bottom and top of face
at each station and intermediate stations (where break sections are needed to
accurately show the work) multiplied by the length of face in yards (meters)
taken from cross sections.)
When a contract does not have an item for presplitting the required
presplitting will not be paid for separately, but shall be included in the price
bid for either Road and Drainage Excavation or Channel Excavation
(Unclassified).
Measurements will be made for unsuitable materials excavated and
removed to obtain proper compaction in cut sections, in foundations for fill
sections and that required for pipe and box culverts as described in
Subsection 204.12. The removal and disposal of this unsuitable material
will be classified as "Undercutting," unless otherwise designated.
No measurement will be made of suitable material temporarily
removed and replaced to facilitate compaction of the material for the full
depth shown on the Plans.
Where it is impractical to measure material by the cross section method
due to the erratic location of isolated deposits, acceptable methods
involving three-dimensional measurements may be used.
Borrow excavation will be measured and paid for by the cubic yard
(cubic meter) in accordance with Section 109, Measurement and Payment.
Water used in the Work will be measured by the M. G. (1,000 gal.)
(m
3
) by means of calibrated tanks or distributors, or by means of accurate
water meters.
Where excavation of different classifications overlap, the following
order of measurement and computation for payment is designated as a
contract provision, namely:
o Road and Drainage Excavation (Unclassified) or Channel
Excavation (Unclassified) shall supersede Structure Excavation
and Foundation Preparation. Road and Drainage Excavation
(Unclassified) shall supersede Channel Excavation
(Unclassified).
o Excavation, the cost of which is included in lump sum items or
unit price bid for other items of construction, shall supersede all
other classifications.
Excavation of embankment will not be measured for payment unless
said excavation is specifically ordered in writing by the Engineer.
Stripping and stockpiling of topsoil will be measured by the cubic yard
( cubic meter) in its original position, and except for topsoil obtained from a
source outside the rights-of-way limits, paid for as unclassified excavation.
Placing and spreading of stockpiled topsoil on slopes and elsewhere shall
be measured by the cubic yard (cubic meter) in the stockpile by the cross
section method. Furnishing and Spreading Topsoil obtained from a source
outside the rights-of-way shall be measured by the cubic yard (cubic meter)
in accordance with the provisions of Subsection 203.06.
Undercutting shall be measured by the cubic yard (cubic meter) on the
basis of cross sectional measurement, or the most feasible method.
203
102
Overhaul of Road and Drainage Excavation (Unclassified), Road and
Drainage Excavation (Additional Material), or Channel Excavation
(Unclassified), unless otherwise specified, shall be measured and paid for
by the station-yard (100 m- m
3
).. The quantity of overhaul in station-yards,
measured for payment, will be the product of the number of cubic yards of
excavation hauled a distance greater than the free haul distance multiplied
by the overhaul distance in stations of 100 linear feet (The quantity of
overhaul in 100 meter-cubic meters, measured for payment, will be the
product of the number of cubic meters of excavation hauled a distance
greater than the free haul distance multiplied by the number of 100 meter
segments in the overhaul)). The overhaul distance is defined as the total
distance the material is hauled from the center of gravity of the remaining
mass of excavation to the center of gravity of the remaining mass of
embankment, as measured along the center line of the main roadway, minus
the free haul distance. For material that is obtained and placed within the
limits of the same balance as shown on the plans or as adjusted by the
Engineer according to Subsection 203.04, the entire length of the balance
shall be considered the free haul distance and no payment of overhaul will
be made. If the Engineer requires the Contractor to haul material from one
balance to any other balance, the free haul distance will be considered as
2,500 ft. (750 m). No allowance will be made for any lateral haul distances.
The Engineer will not require the Contractor to haul material from one
balance to another balance unless the cost of overhaul is less than the cost
of Borrow Excavation.
When the Plans specify or the Engineer directs that rock embankment
material be obtained from the roadway excavation, all costs of constructing
the rock embankment material, including, but not limited to, excavating,
reserving, hauling and placing, shall be measured and paid for under the
item for Road and Drainage Excavation (Unclassified) and no additional
compensation shall be allowed for this work.
203.10-Basis of Payment. The accepted quantities of the items listed
below will be paid for at the contract price per unit of measurement for each
of the pay items that is listed in the bid schedule.
The item for, Road and Drainage Excavation (Additional Material) will
be paid for at a rate per cubic yard (cubic meter) equal to 1.5 times the unit
price bid for the item for Road and Drainage Excavation (Unclassified).
Undercutting, will be paid for at the contract unit price per cubic yard
(cubic meter), except when no contract unit price has been established for ,
Undercutting, it will be paid for at a rate per cubic yard (cubic meter) equal
to 1 1/2 times the contract unit price for Road and Drainage Excavation
(Unclassified).
Overhaul, will be paid for at a rate per Station-yards (100 m- m
3
) equal
to 4 % of the unit price bid for Road and Drainage Excavation
(Unclassified) or 4 cents whichever is less. Overhaul, will be paid for at a
rate per Station-yard (100 m- m
3
) equal to 1% of the unit price bid for
Road and Drainage Excavation (Unclassified) or 1 cent whichever is less.)
204
103
SECTION 204-STRUCTURE EXCAVATION
FOUNDATION PREPARATION, AND BACKFILL
204.01-Description .................................................................................. 104
204.02-Classification............................................................................... 104
204.03-Foundation Fill Material............................................................ 105
204.04-Bedding Material ........................................................................ 105
204.05-Concrete ...................................................................................... 105
204.06-Backfill Material......................................................................... 105
204.07-Equipment................................................................................... 108
204.08-Excavation................................................................................... 108
204.09-Protection of Excavation............................................................ 109
204.10-Foundation Preparation............................................................. 110
204.11-Backfilling ................................................................................... 113
204.12-Method of Measurement............................................................ 115
204.13-Basis of Payment......................................................................... 118
204
104
SECTION 204-STRUCTURE EXCAVATION,
FOUNDATION PREPARATION AND BACKFILL
204.01-Description. Structure Excavation and Foundation Preparation
shall consist of necessary excavating, removal, and satisfactory disposal of
all material within the limits hereinafter stipulated, and preparing the
foundation for the installation or construction of bridges, culverts,
underdrains, and other structures not otherwise provided for by the
Specifications, all in accordance with these Specifications and in reasonably
close conformity with the lines, grades and typical cross sections shown on
the Plans or established by the Engineer.
This work shall also include the construction and subsequent removal
of all bracing, shoring, cribbing, cofferdams, etc., all pumping and bailing,
all backfilling, and the disposal of excess or unsuitable material.
204.02-Classification. Structure Excavation and Foundation Preparation
will be classified and paid for under the following designations:
(a) Culvert Excavation (Unclassified).
Structure Excavation and Foundation Preparation performed
within the limits stipulated in Subsection 204.08 and 204.10, for
all box bridges, pipe culverts, sewers, conduits, all other culverts,
all minor structures of any type and description, will not be
measured and paid for directly but the cost will be incidental in
other items, unless otherwise noted on the Plans.
(b) Dry Excavation (Bridges).
Structure Excavation and Foundation Preparation performed
above the datum line(established by elevation and definitely set
out on the Plans) and within the limits stipulated in Subsection
204.08(a) and 204.10(a) and not classified as Rock Excavation
(Bridges), as indicated or directed, will be classified and paid for
as Dry Excavation (Bridges).
(c) Wet Excavation (Bridges).
Structure Excavation and Foundation Preparation performed
below the datum line(established by elevation and definitely set
out on the Plans) and within the limits stipulated in Subsections
204.08(a) and 204.10(a) and not classified as Rock Excavation
(Bridges), as indicated or directed, will be classified and paid for
as Wet Excavation(Bridges).
(d) Rock Excavation (Bridges).
Structure Excavation and Foundation Preparation performed
either above or below the datum line (established by elevation and
definitely set out on the Plans) and within the limits stipulated in
Subsections 204.08(a) and 204.10(a) and consisting of material
which cannot be economically excavated without the use of
explosives, also any boulder, slab, or fragment of rock having a
volume of not less than 1/2 C.Y. (m
3
), all portland cement
204
105
concrete, all masonry (dry mortar), as indicated or directed, will be
classified and paid for as Rock Excavation (Bridges).
Cemented gravel, cemented chert, soft shale, or soft slate,
even though requiring the use of explosives for economical
excavation, will not be classified as rock.
(e) Bridge Excavation (Unclassified)
Bridge Excavation (Unclassified) shall be structure excavation
and foundation preparation performed either above or below the
datum line (established by elevation and definitely set out in the
plans) as stipulated in Subsection 204.08(a) and 204.10(a)
regardless of the nature of the material excavated.
(f) Rock Drilling (Bridges).
Rock Drilling as herein set out covers the drilling or sinking
of test holes through or in rock in order to verify the condition of
the foundation.
(g) Bedding Material for Support for Pipe Culverts.
Class A-Portland Cement Concrete, Class A.
Class B-Specially selected granular soil.
MATERIALS
204.03-Foundation Fill Material. Material for foundation fill shall consist
of suitably graded sand, gravel, slag or stone, as approved by the Engineer.
204.04-Bedding Material. Material for Class B bedding for pipe culverts
shall consist of sand or a natural sandy soil, all of which passes a 3/8-in.
(9.5 mm) sieve and not more than 10% passes a No. 200 (75 m) sieve, or
stone, gravel, chert or slag meeting the grading requirements for either
Grading C, D, or E of Subsection 903.05.
In rock cuts or other areas designated by the Engineer where a free
drainage bedding or backfill material is required, the material shall be
crushed stone, crushed slag, or washed gravel meeting the requirements of
Subsection 903.17.
204.05-Concrete. Concrete shall conform to the requirements of Section
604 (Concrete Structures). Unless otherwise shown on the Plans or in the
Special Provisions, Class A concrete shall be used for foundation seals and
shall meet the requirements of Subsection 604.19. Concrete for culvert
pipe cradles shall be Class A.
204.06-Backfill Material. Material for backfill shall be fine compatible
soil selected from structure excavation if approved by the Engineer as being
suitable. Additional material needed shall be obtained from roadway or
borrow excavation as described in Section 203.
Granular Backfill Material for Structures shall be Type A aggregate,
Grading D meeting the requirements of Subsection 903.05.
204
106
When required by the plans, backfill material shall be a controlled low
strength material (CLSM) (flowable fill) placed at locations shown on the
plans or as directed by the Engineer.
Materials used in the placement of (CLSM) (flowable fill) shall meet
the following requirements:
Material Subsection
Fine Aggregate 903.01(f)
Portland Cement, Type I 901.01
Fly Ash, Class C or Class F 918.31
Ground granulated blast furnace slag (GGBFS) 918.32
Water 918.01
Chemical Additives 918.09
Air Entraining Admixtures 918.09
As defined herein, there are three (3) types of CLSM: general use
flowable fill, excavatable flowable fill, and early strength flowable fill.
(a) General Use flowable fill: When not otherwise specified in the
plans, or Contract, all flowable fill shall be general use and shall be
proportioned to meet the following:
Property Specification Limit
Load Application
(ASTM D6024)
24 hours maximum in any condition
Consistency 8 in. (20 cm) min. tested in accordance
with the below
The above proportions may be adjusted by the Engineer to obtain
the consistency required for satisfactory flow. Consistency shall be
determined as follows:
Place an open-ended cylinder (pipe) 3 in. (75 mm) in diameter by
6 in.(15 cm) in height in an upright position on a smooth, level surface.
Fill the cylinder with a representative sample of the flowable fill
proposed for use. Remove the cylinder by lifting it straight up thus
allowing the sample to diffuse on the smooth, level surface. The
flowable fill should diffuse into a circular shape having an approximate
diameter of not less than 8 in. (20 cm).
Each consistency test shall represent up to 100 C.Y. (m
3
) of
flowable fill at each installation.
204
107
(b) Excavatable flowable fill (EFF) When specified on the plans, an
EFF shall be designed, proportioned, and delivered to the project
meeting the following performance requirements:
Property Specification Limit
Air content (ASTM D 6023) Maximum 30 %
1
Load Application (ASTM
D6024)
24 hours maximum in any
condition
Consistency 8 in. (20 cm) min. as tested in (a)
Compressive strength (ASTM D
4832)
2
30-psi(207kPa) minimum at 28-
days
Compressive strength (ASTM D
4832)
2
140-psi(965kPa) maximum at
98-days
1- when using air entrained mixture design
2- ASTM D 4832- 4 x 8 in. (10 x 20 cm)cylinder molds may be used.
The preferred capping method to be used is wet suit neoprene
restrained in rigid retainers. Specifiers should be aware that EFF
designs will take longer periods of time to have sufficient bearing
strength before backfilling is allowed.
The ready mix producer must complete a test trench (at least 3 ft. wide x 3
ft. deep x 8 ft. long(1 m wide x 1 m deep x 2.4 m long)), during the mixture
design process, with the proportioned materials to demonstrate the mixture
will meet the performance criteria. The mixture design may be adjusted
with approval by the Engineer to obtain the required properties.
(c) Early strength flowable fill (ESFF)- When specified on the plans ESFF
shall be designed, proportioned, and provided that meets the following
performance specifications:
Property Specification Limit
Air content (ASTM D 6023) Maximum 30%
1
Load Application (ASTM D6024) 6 hours maximum in any
condition
Consistency 8 in. (20 cm) min. as tested in (a)
Compressive strength (ASTM D
4832)
2
30-psi(207kPa) minimum in 24-
hours
1- When using air entrained mixture design
2- ASTM D 4832- 4 x 8 in. (10 x 20 cm)cylinder molds may be used.
The preferred capping method to be used is wet suit neoprene
restrained in rigid retainers.
204
108
The proportions of ESFF shall include sufficient amounts of cementitious
materials, high range water reducers, accelerators, and other chemical
admixtures so the ESFF can be loaded/backfilled as specified.
The ready mix producer must complete a test trench at least 3 ft. wide x 3
ft. deep x 8 ft. long(1 m wide x 1 m deep x 2.4 m long), during the mixture
design process, with the proportioned materials to demonstrate the mixture
will meet the performance criteria. The mixture design may be adjusted
with approval by the Engineer to obtain the required properties.
The Contractor shall furnish certification that all flowable fill delivered to
the project has been batched in accordance with the approved mixture
design and meets the designated properties as specified. Chemical
Additives and/or Air Entraining Admixture may be used to produce the
desired consistency with no additional payment to be made for such
additives.
EQUIPMENT
204.07-Equipment. All equipment necessary for the satisfactory
performance of this work shall be on the project, and approved, before
work will be permitted to begin.
CONSTRUCTION REQUIREMENTS
204.08-Excavation.
(a) Bridges, Box Culverts and Other Major Structures.
Before excavation is started the Engineer or Contractor when
required, will set stakes locating and outlining the structure and
cross section for excavation computations. No excavation shall be
started prior to that time.
All structure excavation shall be cut to the lines and elevations
indicated on the Plans, or as directed by the Engineer. Working
variations outside the neat lines will be permitted; however, only
that excavation outlined under Subsection 204.12 will be
measured for payment.
No excavated materials shall be deposited or disposed of
outside the construction lines unless directed by the Engineer.
When solid rock is encountered in roadway cut sections and
channel sections under bridges, presplitting operations shall be
performed in accordance with the provisions of Subsection
203.04. Hole spacing along bridge abutment sites shall not exceed
12 in. (30 cm). Where overshooting of rock, beyond the cut
sections shown on the bridge plans cause modification of bridge
abutments or span lengths, such modifications shall be made at the
contractors expense.
Inclined surfaces of rock used as foundation shall be
excavated either level or in steps. When necessary, as determined
by the Engineer, to obtain good bond, the surface of rock
204
109
foundation shall be roughened, or suitable anchors installed. Over-
excavations that require re-design, or increased bridge length
and/or quantities, or supplemental retaining walls or other earth
retaining structures shall be paid at the expense of the Contractor.
Existing concrete foundations, boulders, or ledge streaks of
rock projecting into the bottom of the excavation shall be removed
to a depth of 6 in. (15 cm) below foundation elevation, and the
space backfilled with approved material and thoroughly
compacted.
Excavation below bridge foundation elevations as given shall
be done only upon direction of the Engineer. All materials moved
without such authority shall be replaced by the Contractor without
compensation by constructing a sub-footing of the same materials
as the footing of the structure unit and 6 in. (15 cm) wider on
every side.
(b) Pipe Culverts.
In addition to any of the foregoing provisions that are
applicable, the following procedures will be required:
In excavating for pipe culverts, the width of the pipe trench
shall be as identified in the plans to permit satisfactory jointing of
the pipe, thorough tamping of the bedding material under and
around the pipe, and for placement of flowable fill.
When rock, hardpan or other unyielding material is
encountered in the pipe trench, it shall be removed below the
foundation grade for a depth of 6 in. (15 cm), or as directed by the
Engineer.
(c) Utilization of Excavated Materials.
All suitable excavated material shall be utilized as backfill or
embankment. Excess or unsuitable material shall be disposed of in
such a manner as not to obstruct the stream or otherwise impair the
efficiency or appearance of the structure. No excavated material
shall be deposited at any time in such a manner as to endanger a
partly finished structure.
The Contractor shall handle and deposit excavated materials
in such a manner as to furnish proper protection to materials which
will be incorporated in the structure.
In streams the disposal of material will be subject to the laws
of the U.S. Government and requirements set out in the standard
permit form of the applicable government agency approving the
location and Plans, and authorizing the construction of the
structure.
204.09-Protection of Excavation. The Contractor will be held responsible
for protecting his excavation and shall take every precaution to maintain the
excavation intact.
Cofferdams or cribs, used in the preparation and protection of the
foundation, in general, shall be carried well below the bottom of the
footings, shall be substantially braced in all directions; and shall be of such
204
110
construction as will permit them to be pumped and maintained free of water
until the construction therein has been completed. Unless otherwise
specifically indicated on the Plans, the interior dimensions of the cofferdam
will be such as to give sufficient clearance to provide for the construction
and inspection of forms; and to provide for the handling and pumping of
leakage outside of the footing area. Cofferdams or cribs which tilt or move
out of position during the process of sinking shall be righted or enlarged in
order to provide the necessary clearance.
Cofferdams or cribs shall be so constructed as to protect the foundation
and the construction therein against damage from a rise in the stream.
Timber, or bracing of a cofferdam or crib may extend into or through
the substructure only with the written permission of the Engineer, obtained
before the construction of the cofferdam or crib has been started. In
addition, the cofferdams for structure widening shall not be braced off of
the existing structure.
The Contractor shall submit drawings, prepared by and stamped by a
Professional Engineer licensed in Tennessee, showing details of his
proposed cofferdam, or crib construction to the Engineer, prior to starting
any work. The type and clearance of cofferdams, or cribs, insofar as they
affect the finished structure or part thereof, will be subject to the approval
of the Engineer but the design and successful construction shall be the
responsibility of the Contractor.
Cofferdams or cribs, with all falsework, sheeting, bracing, etc. shall be
removed by the Contractor after the completion of the sub-structure therein,
unless otherwise directed. The removal shall be affected in such a manner
as not to disturb nor mar the completed work.
If the foundation excavation has become disturbed or distorted, it shall
be cleaned out and restored to satisfactory condition at the Contractor's
expense.
204.10-Foundation Preparation.
(a) Bridges, Box Culverts, and Other Major Structures.
The preparation of foundations for bridges, box culverts and
other major structures, in addition to the stipulations set out in
Subsections 204.08 and 204.09, shall be in accordance with the
following:
When the foundation has been completed to foundation
elevation as given, the Engineer shall be notified and the
construction therein withheld pending his inspection and approval
of the foundation.
When directed by the Engineer, unless piles are indicated, the
Contractor shall test each foundation in the presence of the
Engineer, by sinking not less than 3 holes, or more than 6 holes to
a depth of between 6 and 10 ft. (1.8 and 3 m) in order to verify the
apparent conditions of the foundations.
Should these test holes disclose unsatisfactory foundation
conditions, the excavation shall be carried lower, as directed by the
Engineer, and new tests made, until a satisfactory foundation is
secured. The costs incurred in sinking test holes will not be paid
204
111
for directly but shall be included in the price bid for other items of
construction unless specified otherwise on the Contract drawings.
When rock is encountered in the excavation for the
foundation, it shall be cleared off and the Engineer notified. Test
holes shall then be drilled in the rock as shown on the Plans or
directed by the Engineer to determine the lines of demarcation, the
classification and the stability of the rock. The excavation shall
then be continued to the elevation designated by the Engineer and
test holes, if required by the Engineer, shall again be drilled and
excavation continued until a foundation approved by the Engineer
is secured.
Rock used as foundation shall be stripped and cleaned of all
overlying materials. All loose, disintegrated, or light slabby
portions of the rock shall be removed.
In rock foundations, when the rock is shattered below the
foundation elevation, the shattered material shall be removed and
the space so created rebuilt with the same type of construction as
the proposed overlying construction. The additional quantities
thus made necessary shall not be included in the pay quantities for
this item.
When the Plans indicate that piles shall be driven, or if after
the foundation excavation has been completed it becomes
necessary to reinforce the foundation by driving piles therein, any
bulge of the foundation material, caused by the driving of the
piles, shall be removed at the Contractor's expense, to the elevation
indicated or directed and the foundation trued to an even surface
over its entire area.
Unsatisfactory material in the foundation shall be removed
and replaced with satisfactory material designated by the Engineer.
This material shall be placed in layers not exceeding 6 in. (15 cm)
in loose depth and compacted to 100 % of maximum density up to
the foundation elevation.
Any pumping that may be permitted from the interior of any
foundation enclosure shall be done in such a manner as to preclude
the possibility of any portion of concrete material being carried
away. Any pumping required during the placing of concrete, or
for a period of at least 24 hours thereafter, shall be done from a
suitable sump located outside the concrete forms.
When conditions are encountered which render it
impracticable to dewater the foundation before placing the footing,
the Engineer may permit the construction of a concrete foundation
seal of such dimensions as he may consider necessary and of such
thickness as to resist any possible uplift. Before pouring the seal,
the foundation shall be cleaned of all objectionable material by the
use of sand pumps, spud bars or other means which will
accomplish the purpose satisfactorily. The seals shall then be
constructed in accordance with the provisions of Subsection
604.19. Pumping to dewater a sealed cofferdam shall not
commence until the seal has set sufficiently to withstand the
hydrostatic pressure. The foundation shall then be dewatered and
204
112
the seal thoroughly cleaned of all laitance and generally prepared
for further construction.
Measurement and payment for concrete foundation seal will
be as provided for under Subsections 604.31 and 604.32 except as
provided for in 204.13.
(b) Pipe Culverts.
Bedding for pipe culverts shall conform to the requirements
given below for Class A, B, or C bedding, whichever is shown on
the Plans or in the special provisions. If the class of bedding is not
shown, Class C bedding shall be placed.
Class A bedding for pipe culverts shall consist of a continuous
concrete cradle constructed in conformity with the details shown
on the Plans and the applicable requirements of Section 604
(Concrete Structures).
Class B bedding shall be constructed by bedding the culvert
pipe in a trench cut in natural ground or compacted embankment to
a depth as shown on the Plans. The pipe shall be bedded on a 6 in.
(15 cm) thickness of Class B Material and sufficient additional
Class B material accurately shaped by a template to fit the lower
part of the pipe exterior for at least 10% of its overall height.
Class B material shall then be rammed and tamped in layers not
over 6 in. (15 cm) in loose thickness around the pipe to a minimum
depth of that shown on the Plans. The remaining depth of trench
shall then be backfilled and compacted as outlined in Subsection
204.11(b). When bell and spigot pipe is to be placed, recesses
shall be dug in the bedding material of sufficient width and depth
to accommodate the bell without its resting on the bottom of the
recess. The width of the recess shall not exceed the width of the
bell by more than 2 in. (50 mm).
Class C bedding shall be constructed by bedding the culvert
pipe in a shallow trench cut in natural ground or compacted
embankment to a depth of not less than 10% of the outside vertical
pipe diameter, and shall be shaped to fit the lower pipe exterior for
the specified embedment. When bell and spigot pipe is to be
placed, recesses shall be dug in the earth foundation of sufficient
width and depth to accommodate the bell without its resting on the
bottom of the recess. The width of the recess shall not exceed the
width of the bell by more than 2 in. (50 mm).
When flowable fill is requrired by the plans, class B bedding
shall be constructed by bedding the culvert pipe in a trench cut in
natural ground or compacted embankment to a depth as shown on
the Plans. The pipe shall be bedded on a 6 in.(15 cm) thickness of
Class B Material and sufficient additional Class B material
accurately shaped by a template to fit the lower part of the pipe
exterior for at least 10 % of its overall height. Flowable fill shall
then be placed around the pipe as specified in Subsection
204.11(c).
204
113
204.11-Backfilling. General. All backfill, other than flowable fill if called
for on the plans, that becomes a part of the roadway prisms or their
foundations shall be placed in layers and compacted to 100% density in
accordance with the provisions of Section 205, Embankments. Flowable
fill shall be placed in accordance with Subsection 204.06
(a) Bridges, Box Culverts and Other Major Structures.
All areas which have been excavated, the volume of which is
not occupied by the structure, shall be refilled with acceptable
earth material to the normal ground surface, unless otherwise
directed. This backfill shall be accomplished by building up in
layers, not more than 6 in. (15 cm) in loose depth for mechanical
tamps and 10 in. (25 cm) in loose depth for tamping rollers, on
both sides of the structure or around the structure unit, maintaining
the layers at equal elevation and thoroughly compacting each layer
by tamping with suitable rapid-striking power-driven mechanical
tampers or sheepsfoot rollers before the succeeding layer is placed.
Granular Backfill Material for Structures (Class A Grading D)
will be placed such that the compacted depth shall not exceed 6 in.
(15 cm) per layer. Density requirements will be 100% with testing
performed on every 6 in. (15 cm) layer.
When any part of the structure is to function as a retainer for
backfill, such as abutments, retaining walls, wing walls, arches,
side walls of box culverts, or minor structures, the boundary slopes
shall be stepped in order to prevent any wedge action.
Backfill shall not be placed against a structure or a section or
unit thereof, until the work described under Subsection 604.20
(Removal of Forms) and 604.22 (Finishing Concrete Surfaces) has
been performed and representative specimens of the concrete in
the structure, section or unit, cured by the methods and in the
manner the concrete which the test specimens represent is cured,
attain a compressive strength of 3,000 psi (20.7 MPa). In addition
to the above requirements the concrete shall have been placed a
minimum of 7 days, not counting the days of 24 hours each in
which the temperature falls below 40F (4C), or 21 calendar days,
whichever occurs first. Backfill behind abutments held at the top
by a superstructure, and behind the sidewalls of culverts, shall be
carried up simultaneously behind abutments or sidewalls.
Box culverts and bridge ends shall be backfilled promptly
after and as permitted by the strength requirements notes above,
but no longer than 30 days following strength attainment, and
before placing a bridge deck, or as directed by the Engineer.
(b) Pipe Culverts.
After the bedding has been prepared and the pipe installed, the
trench shall be backfilled with bedding material and/or fine
compactable soil selected from excavation or borrow in
accordance with the Plans. Prior to backfilling concrete pipe, the
joints shall be cured in accordance with the provisions of
Subsection 607.07. The material shall be placed along each side
204
114
of the pipe in layers not over 6 in.(15 cm) in loose depth. Each
layer shall be moistened or dried, if necessary, to near optimum
moisture content and thoroughly compacted with mechanical
tampers. Special care shall be taken to compact thoroughly the
material under the haunches of the pipe and to insure that the
backfill material is in intimate contact with the side of the pipe.
The backfill shall be brought up evenly on both sides of the pipe
for the full required length. Except as may be required where the
imperfect trench method is prescribed, the backfill material shall
be placed for the full depth of the trench.
When the top of the pipe is above the top of the trench,
embankment material shall be placed and compacted in layers not
more than 6 in. (15 cm ) in loose depth for a width on each side of
the pipe equal to at least twice the horizontal inside diameter of the
pipe or 12 ft. (3.5 m), whichever is less. The embankment on each
side of the pipe, for a distance equal to the horizontal inside
diameter of the pipe, shall be of the same material and compacted
in the same manner as required for backfill in the foregoing
paragraph. The remainder of the fill material shall be soil which
can be readily compacted and shall contain no frozen lumps,
chunks or plastic clay, stones that would be retained on a 3-in. (75
mm) sieve, or other objectionable material. It shall be compacted
as required for backfill or by rolling in accordance with the
applicable requirements of Section 204. The embankment shall be
placed evenly on both sides of the pipe for the full width of the
roadbed up to an elevation a minimum of 1 ft. (30 cm) above the
top of the pipe. Above this elevation, and also above the top of a
backfilled trench that is 1 ft. (30 cm) or more above the top of the
pipe, embankment shall be placed in accordance with the
applicable requirements of Section 205, except those requirements
where the imperfect trench method is prescribed.
When the imperfect trench method is required by the Plans,
the pipe shall be bedded, the trench backfilled, and the
embankment placed, as prescribed above, to a height above the top
of the pipe equal to the vertical outside diameter of the pipe plus 1
ft. (30 cm). A trench equal in width to the outside horizontal
diameter of the pipe shall then be excavated in the newly placed
backfill or embankment directly over the pipe, keeping the trench
walls as nearly vertical as possible, and down to an elevation 1 ft.
(30 cm) above the top of pipe. The lower 1/4 of the trench shall be
backfilled with straw or other highly compressible material and the
remainder of the trench backfilled with the excavated trench
material deposited in the loosest possible manner. After the trench
backfill has been completed, the remainder of the embankment
shall be constructed by normal methods to the finished grade line.
When the material specified in Subsection 903.17 is used for
Class B bedding, the compaction and density requirements will be
waived. The height of the lift may be increased up to a maximum
of 3 ft. (1 m) after the material has been thoroughly forced under
the haunches of the pipe.
204
115
(c) Backfill Material (Flowable Fill).
Flowable fill shall be placed at locations shown on the plans
or as directed by the Engineer. The flowable fill shall be covered
or otherwise protected while in the plastic state. No embankment
or base shall be placed on the flowable fill prior to final set or
hardening as determined by the Engineer.
Prior to placement of the flowable fill, pipe and bedding shall
be installed in accordance with the Standard Specifications and
with details shown on the Plans. All sections of pipe shall be
securely braced or anchored both horizontally and vertically, if
necessary, to prevent movement of the pipe during placement of
the flowable fill. Pipe sections shall be joined so as to prevent the
influx of flowable fill around the joints. The Contractor shall
replace at his expense any pipe or sections of pipe which do not
conform to the above requirements. The contractor shall also
make provisions to form up, or provide earthen berms to prevent
the flowable fill from escaping at the ends of the trench and around
headwalls.
COMPENSATION
204.12-Method of Measurement. Structure excavation will be measured
by the C.Y. (m
3
) in its original position only.
Water and its removal will not be measured as it is a necessary part of
the work.
Excavation below foundation elevation, as indicated or as directed, by
the Engineer, will be measured and computed for payment provided the
cause which made this extra excavation necessary is not attributable to the
Contractor.
No allowance will be made for excavation necessary in connection
with the construction of box bridges, box culverts, retaining walls or minor
structures, including pipe culverts and sewers, unless otherwise indicated
on the Plans, except that undercutting for these structures made at the
direction of the Engineer to remove unsuitable foundation material will be
classified and paid under the item for Undercutting, as provided in Section
203.
When the Plans provide for direct payment of excavation, necessary in
connection with the structures enumerated in the preceding paragraph, the
excavation, including any undercutting made at the direction of the
Engineer to remove unsuitable foundation material, will be classified and
paid as the item for Culvert Excavation (Unclassified) with the following
exception:
Excavation within the limits of box bridges, box culverts with a
bottom width between the inner faces of the outside walls greater than
14 ft.,(4 m), that is performed above the flow line of the structure, and
with a bottom width equal to the distance between the inner faces of
the outside walls on a 1:1 slope to the normal ground surface, will be
204
116
measured and paid for under the Item for Channel Excavation
(Unclassified).
Material used to replace approved undercutting for box bridges, box
culverts, retaining walls or minor structures, including pipe culverts and
sewers, will be paid under the item for Foundation Fill Material, and the
measurement will be the same quantity as the approved undercutting it
replaces.
Materials excavated prior to the necessary measurements having been
obtained by the Engineer cannot be measured in their original position and
therefore will not be computed for payment.
Slides, cave-ins, and excavation extending outside of the workable
limits will not be computed for payment.
Material in a foundation which has bulged due to the driving of piles
and which must be removed will not be measured or computed for payment.
No excavation above the normal ground surface will be measured for
payment, unless otherwise shown on the Plans.
The normal ground surface, as used in this Section, is defined as the
bottom of channel excavations when channel excavation is indicated in the
contract documents, the template section of the roadway in cuts, or the
natural ground surface, whichever is at the lower elevation. When it is
required that the structure excavation be made in new embankment, the
normal ground surface shall be the planes of the new embankment at the
elevation specified or directed for construction in advance of performing
the required structure excavation, but in no case shall the normal ground
surface be above the planes of the new embankment.
Unless otherwise provided on the Plans, no separate measurement or
payment will be made for the construction and /or removal of cofferdams,
cribs, sheet piles or other protective measures provided to safeguard an
excavation, such being considered incidental to the work. When items for
cofferdams or cribs for individual piers or bents are provided by the Plans,
such will be measured in individual lump sum items for the pier or bent
designated.
When a bid item for sheet piles is provided by the Plans, payment will
be as specified. Where payment for the sheet piles is by the square foot
(square meter), measurement will be based on the sheet pile length required
by design to retain and counteract lateral earth forces, plus 1 foot. Where
shoring is required by the regulations of the Occupational Safety & Health
Administration (OSHA), the Contractor shall submit to the Engineer, prior
to starting work, computations and drawings, prepared by and stamped by a
Professional Engineer licensed in Tennessee, showing the basis for the
design.
When the Plans indicate that direct payment will be made for
excavation for box bridges, box culverts, retaining walls or minor
structures, including pipe culverts and sewers, the volume of Culvert
Excavation (Unclassified) will be determined by measuring the actual
quantity excavated between the normal ground surface and the foundation
elevation, as approved, provided the limits of the excavation do not extend
beyond the vertical planes located 18 in. (45 cm), horizontally, outside the
neat lines of the section of the structure at foundation elevation, as indicated
204
117
or directed. For box bridges and box culverts without bottom slabs the
foundation elevation is considered to be the bottom of footings and the flow
line elevation between footings. No allowance will be made for
overlapping areas.
Where internal forming is required as for cut off walls, etc. the limits of
excavation to be measured for payment will be 12 in. (30 cm), horizontally,
outside the neat lines of the completed work and vertically from foundation
elevation to the bottom of the completed excavation.
No increase or decrease in payment will be allowed for changes in
amount of excavation due to the shifting of location of structures from that
shown on the plans or for the addition of structures to those shown on the
Plans when the Plans do not indicate that direct payment will be made for
this excavation. Further, if this area of excavation, namely 18 in. (45 cm)
horizontally outside of the neat line of the structure at foundation elevation,
overlaps an area in which the excavation is computed on a separate unit
price, the excavation in the overlapping area will not be allowed.
The volume of Culvert Excavation (Unclassified) for pipe culverts,
when direct payment for this excavation is indicated on the Plans, will be
determined by measuring the actual quantity excavated between the normal
ground surface and the bottom of the excavation for the pipe, as approved,
provided the limits of the excavation do not extend beyond 2 vertical planes
separated by a horizontal distance equal to the outside diameter of the pipe
plus 3 ft. (1 m ).
Rock required to be removed and the space backfilled in order to
prepare a satisfactory bed for pipe culverts will be computed only for a
depth of 6in. (15 cm) below the bed of the pipe, as approved. No allowance
will be made for the material used in backfilling, except bedding material
when specified.
No allowance will be made for shaping necessary to accommodate the
bells of the pipe.
The volume of Dry Excavation (Bridges), Wet Excavation (Bridges),
Rock Excavation (Bridges) and Bridge Excavation (Unclassified) will be
determined by measuring the actual quantity excavated between the normal
ground surface and the bottom of the excavation as approved, provided the
limits of the excavation do not extend beyond vertical planes located 18 in.
(45 cm) horizontally outside of the neat lines of the section of the structure
at foundation elevation, or where a concrete seal is used, do not extend
beyond the neat lines of the concrete seal, as specified or directed.
The volume of excavation necessary to form struts, diaphragms, beams,
etc. will be determined by measuring the actual volume excavated between
the normal ground surface and a plane located 12 in. (30 cm) below the
members, provided the limits of the excavation do not extend beyond
vertical planes located 18 in. (45 cm), horizontally, beyond the limits of the
members.
In computing extra depth excavation, the working limits established
herein will be adhered to.
Rock Drilling performed in accordance with Subsection 204.10(a) will
be measured by the linear foot (meter).
The volume of Class A bedding shall be based on the theoretical
quantity, in C.Y./ft. (m
3
/m) of pipe, on the standard drawings.
204
118
The volume of Class B bedding shall be based on the theoretical
quantity, in cubic yards per foot (cubic meters per meter) of pipe, as shown
on the standard drawings.
Backfill Material (Flowable Fill) shall be based on a theoretical
quantity in cubic yards (cubic meters), as shown on the standard drawings.
Measurement shall be made along the centerline of the pipe for the width of
trench shown on the Plans.
204.13-Basis of Payment. Structure Excavation and Foundation
Preparation of the various classes will be paid for only on the volume
computed as set out in Subsection 204.12, Method of Measurement.
Embankment construction, sloping, shaping, dressing, disposal of
excess or unsuitable material, final cleaning up, etc. will not be paid for
directly but the cost of performing the requirements therewith shall be
absorbed in the pay items hereinafter provided.
Unless otherwise indicated on the Plans, no direct payment will be
made for Foundation Preparation and Backfill; and the costs involved shall
be included in the unit prices bid for other items of construction.
Material moved prior to securing the necessary measurement; material
specified to be moved under Excavation and Undercutting Section 203;
slides or cave-ins occurring outside of the working limits stipulated in
Subsections 204.08 and 204.10; material excavated outside of said working
limits; material excavated, even though within the said working limits,
below foundation elevation, as indicated or directed, and made necessary on
account of the construction methods of the Contractor, or failure on his part
to provide sufficient, or proper protection; presplitting of rock; material
excavated below foundation when shooting; bulged material caused by
driving piles in a foundation; water and its removal; and in general, material
moved which it would have been unnecessary to move in order to complete
the structure in accordance with the Plans, these Specifications, or the
directions of the Engineer, will not be paid for.
(a) Culvert Excavation (Unclassified).
When direct payment is provide by the plans, this item will be
paid for at the contract unit price per cubic yard (cubic meter) for
Culvert Excavation(Unclassified), which price shall be full
compensation for all Structure Excavation and Foundation
Preparation, classified as Culvert Excavation(Unclassified),
performed within the limits stipulated in Subsections 204.08 and
204.10 and which has been performed in accordance with the
conditions, stipulations, provisions, and requirements contained
therein.
(b) Dry Excavation (Bridges).
This item will be paid for at the contract unit price per cubic
yard (cubic meter) for Dry Excavation (Bridges), which price shall
be full compensation for all Structure Excavation and Foundation
Preparation, classified as Dry Excavation(Bridges), which has
been performed in accordance with the conditions, stipulations,
provisions, and requirements contained herein.
204
119
(c) Wet Excavation (Bridges).
This item will be paid for at the contract unit price per cubic
yard (cubic meter) for Wet Excavation (Bridges), which price shall
be full compensation for all Structure Excavation and Foundation
Preparation, classified as Wet Excavation(Bridges) which has been
performed in accordance with the conditions, stipulations,
provisions and requirements contained herein.
(d) Rock Excavation(Bridges).
This item will be paid for at the contract unit price per cubic
yard (cubic meter) for Rock Excavation(Bridges), which price
shall be full compensation for all Structure Excavation and
Foundation Preparation, classified as Rock Excavation (Bridges),
and which has been performed in accordance with the conditions,
stipulations, provisions, and requirements contained herein.
(e) Bridge Excavation (Unclassified)
This item will be paid for at the contract unit price per cubic
yard (cubic meter) for Bridge Excavation (Unclassified), which
price shall be full compensation for all Structure Excavation which
has been performed in accordance with the conditions,
stipulations, provisions and requirements contained herein.
(f) Extra Depth Structure Excavation and Foundation Preparation.
Extra Depth Structure Excavation and Foundation
Preparation, classified as Culvert Excavation (Unclassified), made
necessary by the Engineer establishing the foundation below the
elevation indicated on the Plans, will be paid for at the contract
unit price per cubic yard( cubic meter) for Culvert Excavation
(Unclassified), and this price shall be accepted by the Contractor
as full compensation for performing this extra depth structure
excavation and foundation preparation in accordance with the
conditions, stipulations, provisions, and requirements set out in
these Specifications for Structure Excavation and Foundation
Preparation of this class.
Extra Depth Structure Excavation and Foundation Preparation
for bridges made necessary by the Engineer requiring excavation
below the foundation elevation indicated on the Plans, will be paid
for on a basis of the contract price per cubic yard (cubic meter) for
Dry Excavation(Bridges), Wet Excavation(Bridges), Rock
Excavation(Bridges), as classified for the actual quantity in cubic
yard (cubic meter), excavated from the designated zone, this zone
being between the elevation shown on the Plans and the final
approved elevation, as directed by the Engineer, plus the
additional percentages for each zone corresponding to the depths
lowered below Plan elevation as set out in the following schedule:
204
120
Depth Lowered Below
Plan Elevation
Sub-Item Zone Additional
Designation No. More Than Not Over Per cent
None 0 0 ft. 4 ft. 0.0
(0 m) (1.2 m)
a 1 4 ft. 8 ft. 50.0
(1.2 m) (2.4 m)
b 2 8 ft. 80.0
(2.4 m )
In the above table, the depths to be used for computing the
volumes of material for payment under any sub-item will be the
depths applicable to each zone between the foundation elevation as
indicated on the Plans and the final foundation elevation as
approved by the Engineer, for example: If the foundation has been
lowered 7-1/2 ft. (2.3 m) below the foundation elevation as
indicated on the Plans, the volume for the sub-item shall be
computed for a depth of 3-1/2 ft. (1 m) and multiplied by the
contract unit price for the class of material excavated plus 50%.
The volume of material down to a level 4 ft. (1.2 m) below the
foundation elevation as indicated on the Plans shall be paid for at
the contract unit price for the class of material excavated.
The contract unit price for the class of material excavated plus
the additional percentage above provided shall be accepted by the
Contractor as full compensation for performing Extra Depth
Structure Excavation and Foundation Preparation, classified as
Dry Excavation (Bridges), Wet Excavation (Bridges), or Rock
Excavation (Bridges), in accordance with the conditions,
stipulations, provisions, and requirements set out in these
Specifications for Structure Excavation and Foundation
Preparation of the respective classes.
(g) Rock Drilling (Bridges).
This item will be paid for at the contract unit price per linear
foot (meter) for Rock Drilling (Bridges).
(h) Concrete for Class A Bedding.
Concrete for Class A Bedding will be paid for at the contract
unit price per cubic yard (m
3
) for Bedding Material (Pipe) Class A,
complete in place.
(i) Material for Class B Bedding.
Material for Class B Bedding will be paid for at the contract
unit price per cubic yard (cubic meter) for Bedding Material (Pipe)
Class B, complete in place.
(j) Cofferdams or Cribs.
204
121
When items for cofferdams or cribs have been provided for
and installed for a designated pier or bent, the lump sum item shall
be full compensation for the furnishing and installation of all
material, maintenance, removal, satisfactory clean up of the area
and for all tools, equipment, labor and incidentals necessary to
complete the work. Concrete seal shall also be included except
when otherwise noted on the plans.
(k) Foundation Preparation
When the Plans indicate that direct payment will be made for
foundation preparation, the lump sum item shall be full
compensation for the preparation of foundations for all
substructures. The cost for cofferdams, shoring, pumping or seal
concrete required to establish the approved footing shall be
incidental to the lump sum bid for Foundation Preparation, except
payment will be made at 40% of the price bid for the footing
concrete when approved by the Engineer:
(1) For leveling placed within the neat lines of the bottom of
the footing, where permitted, and
(2) For additional seal concrete required by changes directed
by the Engineer. Payment will be made only for the
additional seal concrete placed within vertical planes
located 18 in. (45 cm) horizontally outside of the neat
lines of the bottom of the footing. No payment of seal
concrete shall be made for any depth the seal is embedded
in sound material below the elevation of the bottom of the
pier footing as shown on the plans in order to permit
placement of an adequate seal.
Excavation required for the foundation preparation shall be
paid as defined by these specifications except no percent increase
will be allowed for extra depth excavation.
(l) Backfill Material (Flowable Fill)
Accepted quantities of Backfill Material (Flowable Fill) shall
be paid for at the contract unit price bid per cubic yard (cubic
meter) which shall be full compensation for all materials, mixing,
transporting, placing and finishing of the flowable fill as well as all
labor, tools, equipment and other incidentals necessary for the
satisfactory completion of the work.
205
122
SECTION 205-EMBANKMENTS
205.01-Description ..................................................................................123
205.02-Equipment ...................................................................................123
205.03-Preparation of Embankment Areas..........................................123
205.04-Formation of Embankments......................................................124
205.05-Stability of Embankments and Cut Slopes...............................128
205.06-Disposal of Excess or Unsuitable Material ...............................128
205.07-Method of Measurement ............................................................128
205.08-Basis of Payment.........................................................................129
205
123
SECTION 205-EMBANKMENTS
205.01-Description. This work shall consist of constructing roadway
embankments, including preparation of the area upon which they are to be
placed; the construction of dikes within or outside the rights-of-way; the
placing and compacting of approved material within roadway areas where
unsuitable material has been removed; and the placing and compacting of
embankment material in holes, pits, and other depressions within the
roadway area all in accordance with these Specifications and in reasonably
close conformity with the lines, grades, and typical cross sections shown on
the Plans or established by the Engineer. Only approved materials shall be
used in the construction of embankments and backfills. These materials
shall consist of Road and Drainage Excavation, Channel Excavation, and
Borrow Excavation material described in Section 203, or excess material as
described in Section 204.
EQUIPMENT
205.02-Equipment. All equipment necessary for the satisfactory
performance of embankment construction shall be on the project and
approved by the Engineer before the work will be permitted to begin.
Compaction shall be accomplished by the use of any type of compacting
equipment that will produce the required result.
CONSTRUCTION REQUIREMENTS
205.03-Preparation of Embankment Areas. Before embankment
construction in any area is begun, Clearing and Grubbing, Removal of
Structures and Obstructions and preliminary erosion control measures per
the approved Storm Water Pollution Prevention Plan (SWPPP) shall have
been performed in accordance with the provisions of Section 201, 202 and
209 respectively, of these Specifications.
The original ground surface, or the surface of any embankment layer in
place, shall not be in frozen condition, and shall be free from quantities of
snow, ice, and mud when a subsequent layer is placed thereon.
All depressions or holes below the natural ground surface, whether
caused by grubbing or otherwise, shall be filled with suitable material and
compacted to ground surface before embankment construction is started.
Unless shown otherwise on the Plans or in the Special Provisions,
where embankment of less than 3 ft. (1 m) below subgrade is to be made,
all sod and vegetable matter shall be removed from the surface upon which
the embankment is to be placed, unsuitable material removed and replaced
with suitable material and the cleared surface shall be completely broken up
by plowing, scarifying or stripping to a minimum depth of 6 in. (15 cm).
This area shall then be re-compacted. Sod not required to be removed shall
be thoroughly cultivated before construction of the embankment.
Whenever a compacted road surface containing granular materials lies
within 3 ft. (1 m) of the subgrade, such old road surface shall be scarified to
205
124
a depth of at least 6 in. (15 cm). This scarified material shall then be re-
compacted.
Concrete pavement, parking strip, and base, all with or without
bituminous overlay, concrete curb and gutter, sidewalk, driveways, etc.
shall be removed and disposed of as follows:
o If the items are below subgrade elevation, but by not more than 2
ft. (60 cm), they shall be removed, disposed of, and the work paid
for in accordance with the provisions of Subsection 202.06.
o If the items are more than 2 ft. (60 cm) below subgrade elevation,
they shall be broken into sizes not to exceed 2 ft. (60 cm) in
maximum dimension and remain in place, unless otherwise
directed. The cost of this work shall be included in the unit price
bid for other items of construction and shall not be paid for
directly.
o If the items are above subgrade elevation, the removal and disposal
of same shall be measured and paid as Road and Drainage
Excavation (Unclassified) as provided for in Section 203.
When the embankment is to be placed and compacted on hillsides, or
when new embankment is to be compacted against existing embankments,
or when the embankment is to be built in phases, the slopes that are steeper
than 4:1 as measured at right angles to the roadway shall be continuously
benched over those areas as the work is brought up in layers. Measurement
for payment for benching side-hill slopes for embankment construction
shall be in accordance with the applicable requirements of Section 203.09.
Benching shall be of sufficient width to permit the operation of placing and
compacting equipment. Each successive cut shall begin at the intersection
of the original ground and the vertical side of the previous cut. Material
thus cut shall be re-compacted along with the new embankment material at
the Contractor's expense.
Backfilling around a structure, or any unit thereof, shall have been
completed and thoroughly compacted to ground surface before any
embankment materials are placed thereon.
205.04-Formation of Embankments. Perishable materials, such as brush,
hedge, roots, stumps, parts of trees, etc. shall not be incorporated or buried
in the embankments. Rock, broken concrete, etc., shall not be placed in
embankment area where piling is to be placed or driven.
Embankments shall be so constructed that adequate surface drainage
will be provided at all times. Roadway embankment materials that consist
predominantly of soil shall be placed in horizontal layers not to exceed 10
in. (25 cm) in depth before compaction, and each layer shall be compacted
to a density not less than 95% of maximum density. Unless otherwise
specified, the top 6 in. (15 cm) of the roadbed in both cut and fill sections
shall be compacted to 100% of maximum density.
Maximum density and optimum moisture will be determined by the
Engineer in accordance with the "Standard Method of Test for Moisture
Density Relationship of Soils Using a 5.5 lbs. (2.5 kgs) Rammer and a 12-
in. (30.5 cm) Drop"(AASHTO T-99). For material with less than 5%
205
125
retained on a No. 4 (4.75 mm) sieve, use method A with 4 in. (10 cm) mold.
For material with more than 5% retained on a No. 4 (4.75 mm) sieve but
less than 50% retained on a in. (19 mm) sieve, use Method D with
corrections according to T-224.
The correction is to be used on soils containing less than 50% plus
in. (19 mm) material.
The determination of the density of the soil in place will be in
accordance with an approved AASHTO method. Each layer of
embankment shall be compacted to required density, and shall be approved
before material for the next succeeding layer is placed. Placing and
compacting areas shall be kept separate.
Where embankment is to be constructed across low swampy ground
that will not support the earth moving equipment, the lower part of the fill
shall be constructed in a uniformly distributed layer of a thickness not
greater than necessary to support the hauling equipment while placing
subsequent layers. The embankment shall be constructed full width unless
otherwise noted on the Plans or approved by the Engineer. In the
construction of such a lift the density requirement will be waived but the
moisture content of the material used shall not exceed the optimum
moisture range for 95% density for that material. Maximum thickness and
minimum density requirements will apply to all succeeding layers of the
embankment.
When a minimum of 95% of maximum density is required, the
moisture content of the material being compacted shall meet both the
following conditions: (1) The moisture content shall be within the range of
values at which 95% of the maximum density can be obtained as indicated
by the moisture-density relationship curve and (2) the moisture content
shall not exceed the optimum moisture content to the extent that the
material pumps under loads applied by the construction equipment. Even if
the required density is achieved and the moisture content is in range, if
pumping occurs, these sections will be removed. The contractor will
receive no payment in fill sections; however, in cut sections, undercutting
will be paid per cubic yard(cubic meter).
When 100% of maximum density is required, the moisture content of
the material being compacted shall meet condition (2) above and shall not
vary from the optimum moisture content by more than plus or minus 3
percentage points.
The Contractor shall aerate the material or distribute and incorporate
water uniformly therein, as necessary, to control the moisture content
within the applicable limits set out above.
When the excavated material consists predominantly of rock the
following shall apply:
(a) Definition of Material.
If deemed necessary by the Engineer, the Contractor will be
required to conduct test or tests with a 60,000 lbs (27,200 kgs)
static tamping foot roller (costs to be included in other items) to
determine whether the material is degradable or non-degradable.
Material that readily breaks down under 3 passes of the 60,000 lbs
205
126
(27,200 kgs) static tamping foot roller will be considered as
degradable.
(b) Non-degradable Rock.
When sound, non-degradable rock is encountered in the
unclassified excavation, the Contractor may be required to provide
a mechanical means for separating the sound rock from degradable
rock and other soils. The Engineer may direct the use of sound
non-degradable rock in such areas as the backfilling of benches,
lower and/or outside portions of embankments, rock buttresses or
others in addition to embankment construction. All costs for the
preceding to be included in the unit price bid for Road and
Drainage Excavation (Unclassified).
Embankments composed of sound non-degradable rock of
such size that the material cannot be placed in layers with a 10 in.
(25 cm) thickness may be placed in layers not exceeding 3 ft. (1
m) in thickness. Rock fragments shall not exceed 2 ft (60 cm) in
maximum dimension except that occasional individual rocks and
boulders not exceeding 4 ft. (1.2 m) in height may be placed in the
exterior portions of the embankment next to the slope face if
permitted by the Engineer. If allowed, they are to be placed to
prevent nesting and the adjacent voids filled with fine fragments to
form a dense and compact mass.
Rock material shall not be dumped into its final position but
shall be placed by blading or dozing in a manner that will
minimize voids, pockets and bridging. Each layer shall be leveled
the full width of the embankment. Rolling will not be required in
the construction of a rock embankment of sound non-degradable
material with layers in excess of 10 in. (25 cm).
(c) Degradable Rock.
When degradable rock, as defined in (a), is encountered and is
designated to be used in the embankment, compaction of the
degradable rock shall be accomplished with an approved vibratory
tamping-foot roller in conjunction with a static tamping-foot roller.
The minimum weight for the static tamping-foot roller shall be
60,000 lbs (27,200 kgs). The minimum compaction effort, as rated
by the manufacturer, for the vibratory tamping-foot roller shall be
55,000 lbs (25,000 kgs). Roller specifications shall be submitted
to the project Engineer for approval prior to use.
Embankments constructed of degradable rock shall be placed
in 10 in. (25 cm) maximum loose lifts and shall receive a minimum
3 coverages with the static roller and 2 coverages with the
vibratory roller. The Engineer may direct additional coverages
with either or both rollers until satisfactory breakdown and
compaction is accomplished. No additional compensation will be
allowed for the compaction equipment and requirements specified
herein, the costs of which shall be included in other items of
205
127
construction. Degradable rock shall not be placed in the top 5 ft.
(1.5 m) of any embankment unless approved by the Engineer.
When embankment composed of degradable rock is found to
be dry, the Contractor will be required to apply water to this
material in order to facilitate its compaction. The amount of water
will be that required to achieve approximate optimum moisture for
the particular material involved. The added water shall be
uniformly mixed with the material for the entire depth of the lift by
blading, discing or other approved methods.
(d) Combination of Degradable and Non-Degradable Rock.
Blending or combining of degradable rock and non-
degradable rock in a common lift will not be allowed unless
approved in writing by the Engineer.
If approved, embankments constructed of a mixture of
degradable rock and non-degradable rock or rock and soil, shall be
placed in layers not exceeding 10 in. (25 cm) in thickness unless
directed otherwise by the Engineer. If the combined material is
predominantly sound, non-degradable rock with the thickness of
the rock fragments in excess of 10 in. (25 cm), the layers may be
increased as directed by the Engineer consistent with the size of
the material, not to exceed 3 ft. (1 m). The mixture shall be placed
by blading or dozing in a manner that will minimize voids,
pockets, and bridging. The mixture shall be compacted with
suitable compaction equipment as defined in (a) and when
directed, shall be wetted to facilitate compaction. Water, if
required, shall be uniformly mixed with the material for the entire
depth of the lift by blading, disking, or other approved methods.
(e) Density Requirements.
Density requirements will not apply to portions of
embankments constructed of materials that cannot be tested by
approved methods.
(f) Payment
Water required and furnished by the Contractor to facilitate
compaction shall be paid for at the price bid per M.G. (1,000 gal.)
(cubic meter) for "Water" which price shall include full payment
for furnishing and applying the water, mixing, labor, and
equipment. All other costs associated with the preceding is to be
included in the unit price bid for Road and Drainage Excavation
(Unclassified).
When the Plans require Solid Rock Fill, the material shall consist of
sound, non-degradable rock (granite, gneiss, limestone or other approved
material). When the material is subjected to five alternations of the sodium
sulfate soundness test (AASHTO T 104), the weighted percentage of loss
shall be not more than 12. Plastic soil or shale material will not be allowed.
The Solid Rock Fill shall be placed where specified in the Plans or directed
by the Engineer.
205
128
The roadway through rock fills shall be constructed to the grading line
shown on the Plans with an allowable working tolerance of plus 1 to minus
3 in. (plus 25 to minus 75 mm). The portions of the roadway that are then
below grade shall be brought to grade with spalls or other suitable granular
material that is available from the excavation within the balance. If no such
excavation is available, the Engineer may direct the Contractor to use
approved base material for bringing the fill to grade, not to exceed the 3 in.
(75 mm) limit as specified above. Payment for furnishing and placing said
base material will be made at the unit price bid per ton (metric ton) for the
applicable item in Subsection 303.14. When base material is not a bid item
in the Contract, the material shall be furnished under the provisions of
Subsection 104.03.
Compaction of each layer of embankment shall be accomplished by the
use of any type of compacting equipment that will produce the required
results.
Embankment to be placed on both sides of a concrete wall or box type
structure shall be so constructed that the embankment is always
approximately the same elevation on both sides of the structure.
Embankment to be placed at the location of abutments, bents, etc. shall
be constructed to finished grade prior to commencing excavation on the
respective section of the substructure, unless otherwise specified on the
plans. Embankment to be constructed on one side only of abutments wing
walls, piers, etc. shall not be constructed until the super-structure is in
place. Construction operations shall be so conducted that wedge action and
excessive pressure against the structure is avoided.
205.05-Stability of Embankments and Cut Slopes. The Contractor shall
be responsible for the stability of all embankments and cut slopes until final
acceptance and shall replace at his own expense any portions which, in the
opinion of the Engineer, have become displaced or damaged due to his
carelessness or negligence. If the work has been constructed and protected
properly, and damage to the embankments or cut slopes occurs due to
unusual natural causes such as cloudbursts, floods, slides or subsidence, the
Contractor will be paid for the material used in making the necessary
repairs at the contract unit price for the classification covering the material
designated by the Engineer to be used for this purpose. The removal of
slides will be measured and paid for in accordance with the provisions of
Section 203.
205.06-Disposal of Excess or Unsuitable Material. Disposal of excess or
unsuitable material shall be performed in accordance with the provisions of
Section 203, Excavation and Undercutting; or Section 204, Structure
Excavation, Foundation Preparation, and Backfill.
COMPENSATION
205.07-Method of Measurement. Embankment will not be measured.
The construction of embankments is a responsibility to be assumed by the
Contractor in connection with the pay items enumerated in Sections 203
and 204, covering materials with which the embankments are constructed.
205
129
205.08-Basis of Payment. Embankments will not be paid for directly. The
contract unit prices for the materials with which embankments are
constructed shall be full compensation for all embankment construction that
has been performed in accordance with the Plans and Specifications.
206
130
SECTION 206-FINAL DRESSING
206.01-Description ..................................................................................131
206.02-Equipment ...................................................................................131
206.03-Method and Scope of Work.......................................................131
206
131
SECTION 206-FINAL DRESSING
206.01-Description. This work shall consist of dressing all slopes and
areas including borrow pit areas and embankments to within reasonably
close conformity to the lines, grades and cross section indicated on the
Plans or as directed by the Engineer, and generally preparing the project for
final inspection and acceptance. The costs thereof shall be included in
prices bid for other items of construction.
EQUIPMENT
206.02-Equipment. All equipment necessary for the satisfactory
performance of this construction shall be on the project and approved
before work will be permitted to begin.
CONSTRUCTION REQUIREMENTS
206.03-Method and Scope of Work. Final Dressing shall be performed by
hand work and machines to produce a uniform satisfactory finish to all parts
of the roadway and other components of the project. The roadbed,
shoulders, ditches and slopes shall be shaped within reasonably close
conformity to the specified lines, grades and cross sections. Spoil banks,
waste areas, etc. shall be dressed in a satisfactory manner. Rock cuts shall
be scaled of all loose fragments and left in a neat, safe and workmanlike
condition.
The entire rights-of-way shall be cleaned of all weeds, briars and
brushes unless otherwise specified on the Plans. All structures, both old
and new, shall be cleared and cleaned of all brush, drifts, heavy vegetation,
sediment, rubbish, obstructions and other objectionable material.
Final dressing shall be performed prior to sodding and seeding
operations when these construction items are included in the Contract.
Tracked machines used in the dressing of slopes shall be run up and
down slopes as opposed to longitudinally.
207
132
SECTION 207-SUBGRADE CONSTRUCTION AND
PREPARATION
207.01-Description ..................................................................................133
207.02-Equipment ...................................................................................133
207.03-Preparing Subgrade ...................................................................133
207.04-Compacting Subgrade................................................................133
207.05-Drainage and Protection ............................................................134
207.06-Checking Subgrade.....................................................................134
207.07-Disposal of Excess or Unsuitable Material ...............................134
207.08-Method of Measurement ............................................................134
207.09-Basis of Payment.........................................................................135
207
133
SECTION 207-SUBGRADE CONSTRUCTION AND
PREPARATION
207.01-Description. This work shall consist of the construction and
preparation of part or all of the roadbed to receive the immediate
construction of a base or pavement thereon.
EQUIPMENT
207.02-Equipment. All equipment necessary for the satisfactory
performance of Subgrade Construction and Preparation shall be on the
project and approved before work will be permitted to begin.
CONSTRUCTION REQUIREMENTS
207.03-Preparing Subgrade. The subgrade shall be prepared in
reasonably close conformity with the lines and grades as shown on the
Plans or as staked by the Engineer.
Excavation and Undercutting shall be performed in accordance with
the provisions of Section 203.
Where the roadbed is below grade, the Contractor shall haul, spread
and compact suitable material in sufficient quantity to correct the
deficiency. Spreading and compacting material shall be performed in
accordance with the pertinent provisions of Section 205.
Where the roadbed has been seeded for erosion protection or has
vegetative growth established, the Contractor shall clip the roadbed to
remove the deleterious material prior to placing the base or sub-base
material.
The Contractor shall haul, spread and compact suitable material in
sufficient quantity to correct deficiencies obtained by the removal of the
deleterious material. The work shall be in accordance with pertinent
provisions of Section 205.
Where sub-bases are to be constructed on the subgrade, the limits of
the subgrade preparation shall extend across the entire section upon which
the subbase course is to be applied, including the shoulders.
Where forms are required in the construction of base or pavement, the
subgrade as prepared shall be 12in. (30 cm) wider, on each side, than the
neat width of the base or pavement.
207.04-Compacting Subgrade. On subgrades that require reworking, all
vegetation within the limits of the subgrade preparation described above
shall be removed and disposed of as directed by the Engineer prior to
beginning reworking and re-compacting operations. The density of the
finished subgrade shall be equal to not less than 100% of the maximum
density. The determination of optimum moisture, maximum density and
density of the soil in place shall be in accordance with the provisions of
Subsection 205.04. When field tests show failure to meet the density
requirement, the subgrade shall be loosened by disking, harrowing or other
207
134
approved methods to a depth of not less than 6 in. (15 cm), then reshaped
and re-compacted in conformity with the applicable requirements of
Subsection 205.04. The subgrade material shall be moistened or aerated as
necessary during mixing and compacting to provide optimum moisture
content in accordance with the provisions of Subsection 205.04.
All soft, yielding material which will not compact readily shall be
reworked or removed and replaced, and the replacement material
compacted in accordance with the pertinent provisions of Section 205.
207.05-Drainage and Protection. Grading of Subgrade shall be
performed in such a manner as to provide ready drainage of water from the
subgrade. Ditches and drains shall be maintained to provide proper
drainage during the construction.
The Contractor shall take all precautions necessary to protect the
subgrade from damage. Hauling over the finished subgrade shall be limited
to that which is essential for construction purposes.
All ruts or rough places that develop in a completed subgrade shall be
smoothed and the subgrade re-compacted.
207.06-Checking Subgrade. As determined by checking, the lines, cross
sections and grades of the subgrade as completed shall be in reasonably
close conformity with those shown on the Plans for the bottom of sub-base,
base, or pavement, or with those established by the direction of the
Engineer.
The subgrade shall be constructed to the grading line shown on the
Plans, with an allowable working tolerance of 1 in. (25 mm).
The subgrade shall be rechecked as stipulated in the respective sections
governing construction of the several types of base and pavement.
207.07-Disposal of Excess or Unsuitable Material. If grading has been
performed under a previous Contract, removal and disposal of unsuitable
material below subgrade elevation in both cut and fill sections will be
measured and paid for as Road and Drainage Excavation (Unclassified).
If grading is included in the Contract, removal and disposal of
unsuitable material below subgrade elevation in cut sections will be
measured and paid for as "Undercutting". In the subgrade of embankment
sections, no measurement for payment will be made for the removal and
disposal of excess or unsuitable material. The disposal of excess or
unsuitable material shall be performed in accordance with the provisions of
Subsection 203.07.
COMPENSATION
207.08-Method of Measurement. Measurement for Subgrade
Construction and Preparation will be made along the median center-line of
the project for divided sections, and along the center-line of the pavement
for 2-lane and other undivided sections, excluding bridges, by the station
(100 ft. (1,000 m)).
The volume of excess or additional material moved, or of unsuitable
material removed, to be measured for payment in accordance with the
207
135
provisions of Subsections 207.07 and 207.09 will be measured by the cross
section method, of if that method is unfeasible, by some other method
approved by the Engineer and computed in accordance with the provisions
of Section 109, Measurement and Payment.
Water required for compaction will be measured by the M.G. (1,000
gal.) (m
3
) by means of calibrated tanks or distributors, or by means of
accurate water meters.
207.09-Basis of Payment. Payment for Subgrade Construction and
Preparation per 100 ft. (1,000 m) station shall be full compensation for
shaping and compacting the roadbed, all ramps, service roads, approaches,
roadside rest areas, etc., as shown on the plans. It shall also include the
moving or furnishing of any additional material required, or the disposal of
excess material, provided the material to be placed or removed does not
exceed a depth of 3 in. (75 mm). Where a depth of 3 in. (75 mm) is
exceeded, the total quantity of material removed or placed will be paid for
at the appropriate price bid per cubic yard (cubic meter) for Borrow
Excavation (Unclassified) or Road and Drainage Excavation (Unclassified).
Where the Contract includes the construction of the combined grading,
drainage, and pavement structure, the construction and preparation of the
subgrade will be considered as an obligation in connection with the
construction and preparation of the road, and the material moved will be
classified and included in the computation of pay items provided in
Excavation and Undercutting, Section 203.
When the Contract provides for the construction of a sub-base, base, or
pavement on a road that has been graded under a previous Contract, and the
Item for Subgrade Construction and Preparation is included in the Contract,
this Item will be paid for at the contract unit price per 100 ft. (1,000 m)
station for Subgrade Construction and Preparation. Payment for material
moved will be subject to the stipulations set out in the first paragraph of this
Subsection.
Unless designated by the Plans, the clipping of a roadbed that has been
seeded will not be paid directly but the costs shall be incidental to other
items of construction.
Water applied as ordered by the Engineer will be paid for at the
contract unit price per M.G. (1,000 gal. (m
3
)), as provided in Section 203.
208
136
SECTION 208-SHOULDERS AND DITCHES
208.01-Description ..................................................................................137
208.02-Materials......................................................................................137
208.03-Equipment ...................................................................................137
208.04-General ........................................................................................137
208.05-Final Cleanup..............................................................................137
208.06-Method of Measurement ............................................................137
208.07-Basis of Payment.........................................................................138
208
137
SECTION 208-SHOULDERS AND DITCHES
208.01-Description. This work shall consist of the construction of
shoulders and ditches adjacent to both sides of the base or pavement, to
obtain proper drainage, in accordance with these Specifications and in
reasonably close conformity with the lines, grades and typical cross sections
shown on the Plans, or as directed by the Engineer.
MATERIALS
208.02-Materials. Material for constructing shoulders may be obtained by
cleaning out side ditches, if approved by the Engineer. If additional
material is required, it shall be furnished by the Contractor from approved
sources.
EQUIPMENT
208.03-Equipment. All equipment necessary for the satisfactory
performance of this work shall be on the project and approved before work
will be permitted to begin. Compaction shall be accomplished by the use of
any type roller that will produce the required results.
CONSTRUCTION REQUIREMENTS
208.04-General. During construction of shoulders every precaution shall
be taken to protect the surface and edges of pavement. No shoulder work
shall be started until the pavement has developed effective resistance to
damage.
Shoulder construction shall be completed by blading, moistening as
may be necessary, and thoroughly compacting. After completion the
shoulders shall be maintained with respect to lines, grades and cross
sections until final acceptance of the project.
208.05-Final Cleanup. Final Dressing shall be performed in accordance
with the applicable provisions of Section 206.
Disposal of excess or unsuitable material shall be performed in
accordance with the provisions of Subsection 203.07.
Final cleanup shall be performed in accordance with the provisions of
Subsection 104.11.
COMPENSATION
208.06-Method of Measurement. Shoulder and ditch construction will be
measured by the mile (km) along each respective shoulder and/or ditch
constructed or reworked.
Material required in excess of that obtained by cleaning out side
ditches will be measured by cross sectioning the approved borrow pit or
pits before and after removal of the material.
Water will be measured by the M.G. (1,000 gal.) (m
3
) by means of
calibrated tanks or distributors, or by means of accurate water meters.
208
138
208.07-Basis of Payment. Shoulder and ditch construction will be paid for
at the contract unit price for Shoulders and Ditches per linear mile (km).
Material required in excess of that obtained by the cleaning outside ditches
will be paid for at the contract unit price per cubic yard (m
3
) for Borrow
Excavation (Unclassified). Water applied as ordered by the Engineer will
be paid for at the contract unit price per M.G. (1,000 gal.) (m
3
).
209
139
SECTION 209-PROJECT EROSION AND SILTATION
CONTROL
209.01-Description .................................................................................. 140
209.02-Classification............................................................................... 140
209.03-Equipment................................................................................... 142
209.04-Project Review............................................................................ 142
209.05-Preconstruction Conference ...................................................... 142
209.06-Construction Requirements....................................................... 142
209.07-Construction of Structures ........................................................ 143
209.08-Method of Measurement............................................................ 148
209.09-Basis of Payment......................................................................... 148
209
140
SECTION 209-PROJECT EROSION AND
SILTATION CONTROL
209.01-Description. This work shall consist of temporary and permanent
measures to control erosion and siltation through the use of fiber mats,
netting, mulches, grasses, slope drains, sediment basins, temporary silt
fences and other control devices.
The siltation control measures shall be performed so as to achieve
economical, effective and continuous erosion and siltation control in all
phases of construction per the approved Storm Water Pollution Prevention
Plan (SWPPP).
209.02-Classification. Siltation and erosion control methods will be
classified and paid for under the following designations or as otherwise
specified.
(a) Temporary Berms.
A temporary berm is constructed of compacted soil, with or
without a shallow ditch to prevent excessive erosion until
permanent controls are installed or slopes stabilized.
(b) Temporary Slope Drains.
A temporary slope drain is a facility consisting of metal pipe,
plastic pipe, flexible rubber pipe or other material acceptable to the
Engineer that may be used to carry water down slopes to reduce
erosion.
(c) Sediment Structures.
Sediment basins, ponds, and traps, are prepared storage areas
constructed to trap and store sediment from erodible areas in order
to protect properties and stream channels below the construction
areas from excessive siltation.
(d) Check Dams.
Check dams are barriers composed of logs and poles, large
stones or other materials placed across a natural or constructed
drain way.
(e) Temporary Seeding and Mulching.
Temporary seeding and mulching are measures consisting of
seeding, mulching, fertilizing, and matting utilized to reduce
erosion. All cut and fill slopes including waste sites and borrow
pits shall be seeded when and where necessary to eliminate
erosion.
(f) Brush Barriers.
Brush barriers shall consist of brush, tree trimmings, shrubs,
plants, and other approved refuse from the clearing and grubbing
operation.
209
141
Brush barriers are placed on natural ground at the bottom of
fill slopes, where the most likely erodible areas are located to
restrain sedimentation particles.
(g) Baled Hay or Straw Checks.
Baled hay or straw erosion checks are temporary measures to
control erosion and prevent siltation. Bales shall be either hay or
straw containing 5 C.F. (0.15 m
3
) or more of material.
(h) Temporary Silt Fences and Filter Barriers
Silt fences and filter barriers are temporary measures utilizing
filter cloth and other materials as designated on the Plans. The
filter cloth shall meet the requirements of AASHTO M 288 for
Sediment Control fabrics.
(i) Temporary Sediment Filter Bags.
The sediment bags may be utilized either on slope drains, pipe
culverts, box bridges, or for pumping sediment from sediment
traps and sediment basins. This construction shall be performed as
shown on plans or as directed by the Engineer. The material shall
be a non-woven geotextile fabric bag resistant to rot, mildew,
puncture and tearing, with a minimum seam breaking strength of
200 lbs(90 kgs) The seams shall demonstrate less elongation and
deformation that the geotextile fabric.
GEOTEXTILE FABRIC SPECIFICATIONS
Properties Test Method
Weight 8.0 oz/yd. ASTM D 3776
Thickness 90-105 mils ASTM D 1777
Grab Tensile 240 lbs. ASTM D 4632
Grab Elongation at Break 50% ASTM D 4632
Puncture Resistance 115 lbs. ASTM D 4833
Trapezoidal Tear 100 lbs. ASTM D 4533
Mullen Burst 350 lbs. ASTM 3786
Water, Flow Rate 105 gpm/ft.2 ASTM D 4491
Permittivity 1.7 sec.-1 ASTM D 4491
UV Resistance 85% str. Ret. ASTM D 4355
Standard Bag Minimum Dimensions
14.5 x 1.5 x 6.5 ft. and 14.5 x 2 x 13.25 ft.
Maximum Flow Rate
14.5 x 6.5 ft. up to 500 gpm
14.5 x 13.25 ft. up to 2,000 gpm
A manufacturers label designating the maximum allowable flow rate of the
bag in gallons per minute shall be permanently attached to each bag.
209
142
EQUIPMENT
209.03-Equipment. All equipment necessary for the satisfactory
performance of this work shall be on the project and approved, before work
will be permitted to begin.
CONSTRUCTION REQUIREMENTS
209.04-Project Review. Prior to the preconstruction conference the
Contractor shall meet with the Engineer to discuss potential problems with
erosion and siltation control due to construction activities and actions to be
taken to prevent such problems. Pursuant to this discussion the Contractor
shall prepare a comprehensive erosion and siltation control plan in
accordance with Subsection 209.05 below and the approved SWPPP. The
plan shall be continuously implemented to effectively control erosion and
siltation during the term of the contract.
209.05-Preconstruction Conference. At the preconstruction conference
the Contractor shall submit for acceptance his plan for the staging of his
operations and for accomplishment of temporary and permanent erosion
and siltation control work for: (1) All areas within the rights-of-way as are
applicable for clearing and grubbing, grading, bridges and other structures
at water courses, paving and incidental construction and (2) Areas outside
the rights-of-way that will be disturbed by the construction such as borrow
areas, waste areas, haul roads and staging areas. The Contractor's plan for
erosion and siltation control work shall incorporate and supplement, as
applicable, the basic control devices shown in the plans to provide
acceptable temporary and permanent siltation controls during all stages of
construction. No work shall be started until the erosion control plan,
including the staging of temporary and permanent erosion control measures,
has been accepted by the Engineer. Rejection of all or part of the plan shall
not constitute a basis for an extension of contract time.
The erosion and siltation control plan shall be updated as work
progresses to show changes due to revisions in work schedules or sequence
of construction, or when directed by the Engineer.
209.06-Construction Requirements. Prior to or simultaneously with the
clearing and grubbing operations, the Contractor shall install siltation
control devices in accordance with the approved erosion control plan. Such
work may involve the construction of temporary berms, dikes, dams, silt
fences, sediment basins, lined channels, permanent cut-off ditches, slope
drains or other control devices as necessary to prevent and control erosion
and siltation. Water from cofferdams is not to be pumped directly into
streams, but is to be pumped into sediment ponds or traps. No grading shall
be performed until the erosion and siltation control devices are in place to
the satisfaction of the Engineer. Areas to be graded shall not be cleared and
grubbed more than 20 calendar days prior to beginning grading operations
in such areas. Stockpiled topsoil or fill material is to be treated so the
sediment runoff will not contaminate surrounding areas or enter nearby
209
143
streams. In order to reduce sediment in runoff, erosion control structures
shall be installed promptly during all construction phases.
The Contractor's operations shall be staged so that graded or otherwise
disturbed erodible surfaces are protected as the work progresses. Once the
Contractor begins grading for a roadway cut or embankment, he shall
maintain a continuous, viable operation to complete the cut or embankment
to subgrade elevation, unless otherwise approved in writing by the
Engineer. Exposed erodible cut or embankment slopes shall be final
dressed, topsoiled and protected with permanent seeding, sodding, matting
or other acceptable erosion and siltation control measures in vertical
increments not exceeding 25 ft. (7.5 m) as the work progresses; and no
portion of these slopes shall remain unprotected for more than 20 calendar
days unless the Engineer determines that weather conditions or other
special circumstances preclude current placement of permanent control
measures. Temporary erosion control measures shall be implemented as
directed by the Engineer.
Seeding, sodding, matting or other acceptable erosion and siltation
control operations shall be initiated within 48 hours after any one of the
following conditions occurs:
1. Each 25 ft. (7.5 m) vertical increment is graded or
2. Upon suspension or completion of grading operations in a specific
area.
The above requirements for progressive siltation control also apply to
graded areas off the rights-of-way such as waste areas, borrow areas and
haul roads.
The Contractor shall incorporate all permanent erosion and siltation
control features into the project at the earliest practicable time. Temporary
erosion and siltation control features shall be used to control erosive
conditions that warrant protection prior to installation of permanent control
features or that are needed to temporarily control erosion or siltation that
develops during construction but which is not associated with permanent
control features on the project.
Where construction activities cross or border areas of depression (ie.
Sinkholes without openings or open throats), erosion control measures shall
be installed and maintained as shown in the plans. When construction
activities encounter an open throated sinkhole (Class V Injection Well), the
Engineer shall be notified immediately and a minimum of a single row of
silt fence backed by hay or straw bales and shall be installed as detailed on
the Standard Drawings and Subsection 209.07 (g) of the Standard
Specifications or other measures prescribed in the approved SWPPP shall
be employed. The measures mentioned above shall encircle the sinkhole
opening so as not to allow any silt to enter the opening.
In the event of conflict between these requirements and erosion and
siltation control laws, rules or regulations of other Federal or State or local
agencies, the more restrictive laws, rules or regulations shall apply.
209.07-Construction of Structures
209
144
(a) Temporary Berms.
A temporary berm shall be constructed of compacted soil,
with a minimum width of 24 in. (60 cm) at the top and a minimum
height of 12 in. (30 cm) with or without a shallow ditch,
constructed at the top of fill slopes or transverse to center one on
fills. Temporary berms shall be graded so as to drain to a
compacted outlet at a slope drain. The area adjacent to the
temporary berm in the vicinity of the slope drain must be properly
graded to enable this inlet to function efficiently and with
minimum ponding in this area. All transverse berms required on
the downstream side of a slope drain shall extend across the grade
to the highest point at approximately a 10 degree angle with a
perpendicular to center line. The top width of these berms may be
wider and the side slope flatter on transverse berms to allow
equipment to pass over these berms with minimal disruptions.
When practical and until final roadway elevations are approached,
embankments should be constructed with a gradual slope to one
side of the embankment to permit the placement of temporary
berms and slope drains on only one side of the embankment.
(b) Temporary Slope Drains.
Temporary slope drains shall consist of metal pipe, plastic
pipe, flexible rubber pipe, or other materials which can be used as
temporary measures to carry water accumulating in the cuts and on
the fills down the slopes prior to installation of permanent facilities
or growth of adequate ground cover on the slopes.
All temporary slope drains shall be adequately anchored to the
slope to prevent disruption by the force of the water flowing in the
drains. The base for temporary slope drain shall be compacted and
concavely formed to channel the water or hold the slope drain in
place. The inlet end shall be properly constructed to channel water
into the temporary slope drain. Energy dissipaters, sediment
basins or other approved devices shall be constructed at the outlet
end of the slope drains to reduce erosion downstream. An ideal
dissipater would be rip rap or a small sediment basin which would
slow the water as well as pick up some sediment. All temporary
slope drains shall be removed when no longer necessary and the
site restored to match the surroundings.
(c) Sediment Structures.
Sediment structures shall be utilized to control sediment at the
foot of embankments where slope drains outlet; at the bottom as
well as in the ditchlines atop waste sites; in the ditchlines or
borrow pits. Sediment structures may be used in most drainage
situations to prevent excessive siltation of pipe structures.
Sediment structures shall be constructed in accordance with sizes
shown on the Plans or as approved by the Engineer.
When use of temporary sediment structures is to be
discontinued, all sediment accumulation shall be removed, and all
209
145
excavation backfilled and properly compacted. The existing
ground shall be restored to its natural or intended condition.
(d) Check Dams.
Check dams shall be utilized to retard stream flow and catch
small sediment loads. Materials utilized to construct check dams
are varied and should be clearly illustrated or explained in the
Contractor's erosion control plan. All check dams shall be keyed
into the sides and bottom of the channel a minimum depth of 2 ft.
(60 cm). A design is not needed for check dams but some typical
designs are shown in the standard plans. Stone check dams should
generally not be utilized where the drainage area exceeds 50 acres
(20 hectares). Log and pole structures should generally not be
used where the drainage area exceeds 5 acres (2 hectares).
(e) Temporary Seeding and Mulching.
Seeding and Mulching shall be performed in accordance with
Section 801-Seeding. Mulching may be required on areas that
have not been seeded, in which case the rate of application of
asphalt binder is to be approximately 6 gal. per unit (1,000 sq. ft.)
(25 liters per 100 m
2
).
Fertilizer and agricultural limestone shall be applied as
specified in Subsection 801.05 for permanent seeding.
(f) Brush Barriers.
Brush Barriers shall consist of brush, tree trimmings, shrubs,
plants and other approved refuse from the clearing and grubbing
operation. The brush barriers shall be constructed approximately
parallel to original ground contour. The top of the brush barrier
shall be at least 5 ft. (1.5 m) below the finished roadway. The
brush barrier shall be compressed to an approximate height of 3 to
5 ft. (1 to 1.5 m) and approximate width of 5 to 10 ft. (1.5 to 3 m).
The embankment shall not be supported by the construction of
brush barriers.
(g) Baled Hay or Straw Erosion Checks.
Hay or Straw Erosion Checks shall be embedded in the
ground a minimum of 4 in. (10 cm) to prevent water flowing under
them. The bales shall also be anchored securely to the ground by
wooden stakes driven through the bales into the ground. Bales can
remain in place until they rot, or be removed after they have served
their purpose, as determined by the Engineer. The Contractor shall
keep the checks in good condition by replacing broken or damaged
bales immediately after damage occurs. Normal debris clean-out
will be considered routine maintenance.
(h) Temporary Silt Fence and Filter Barriers.
Temporary Silt Fences and Filter Barriers shall be placed on
the natural ground, at the bottom of fill slopes, in ditches, or other
areas where siltation is an issue. Silt fences and filter barriers shall
209
146
be placed with the filter cloth material on the upper grade side of
the fence and anchored into the soil. (See standard drawings)
The Contractor shall be required to maintain the silt fence and
filter barriers in a satisfactory condition for the duration of the
project or until its removal is requested by the Engineer. The silt
accumulation at the fence may be left in place and seeded,
removed, etc. as directed by the Engineer. Unless otherwise
directed by the Engineer, all silt fence or filter barrier shall be
removed prior to completion of the project and shall become the
property of the Contractor.
(i) Temporary Sediment Filter Bags.
The sediment bags shall be placed on a road pad and
surrounded by silt fence as shown on the plans and per Standard
Drawings for Erosion Control and Landscaping.
Pumping From Sediment Traps. Place sediment filtering bag
on a level stabilized area over dense vegetation, straw, or as
detailed in plans. The pump utilized shall have a rating in
gallons(liters) per minute of not more than the maximum flow
rate of the bag. Insert the discharge hose into the corner of the bag
and double clamp. Do not allow hose to extend into bag any more
than 6 in. (15 cm). Monitor and evaluate the entire pumping
operation to assure the bag and connection are functioning
properly. A regulator to control flow rate should be attached to
pump or hose. At the beginning of the pumping operation the
pumping rate should be reduced to approximately to its
maximum rate for a period of 10 to 15 minutes, allowing the water
to evenly spread over the bottom of bag before the maximum
pumping rate begins. Bags may rupture when overfilled.
Therefore the Contractor shall monitor regularly when filling and
when the contained silt reduces the bags flow to approximately
the rate of initial discharge, the bag must be replaced.
Placement upon Temporary Drains or Pipe Culverts. Place
the bag a minimum of 6 in. (15 cm) upon the pipe and double
clamp. Replace the bag when approximately full of sediment.
Remove and dispose of the sediment in a manner satisfactory to
the Engineer by removing the bag with sediment from
environmentally sensitive areas or natural waterways. At a
suitable disposal site, silt bag, remove sediment from the bag and
smoothly grade into existing topography.
The Contractor shall install and maintain all temporary erosion and
siltation control features until no longer needed or permanent control
measures are installed. Any materials removed shall become the property
of the Contractor. In order to insure erosion and siltation control structures
work properly, it is imperative the sediment be removed; therefore,
inspection and maintenance of structures is to be performed on a regular
basis. During sediment removal, the Contractor shall take care to insure
that structural components of erosion and siltation control structures are
not damaged and thus made ineffective. If damage does occur, the
209
147
Contractor shall repair the structures at his own expense. Upon complete
removal of sediment traps, special ditches, etc., the area where they were
constructed is to be topsoiled, seeded and mulched.
In the event that temporary erosion and siltation control measures are
required due to the Contractor's negligence, carelessness, or failure to install
permanent controls as a part of work as scheduled, and are ordered by the
Engineer, such work shall be performed by the Contractor at his own
expense. (See special provisions 107F and 107P if applicable)
Where temporary erosion and siltation control work is acceptably
performed and failure of all or any part of the system occurs but is not
attributed to the Contractor's negligence, carelessness, or failure to install
permanent controls and falls within the specifications for a work item that
has a contract price, the units of work will be paid for at the proper contract
prices except as noted below. Should the temporary erosion and siltation
control work not be comparable to the project work under the applicable
contract items, the Contractor shall be ordered to perform the work on a
force account basis, or by agreed unit prices in compliance with Subsection
109.04.
Except as noted below, payment also may be made for replacement of
temporary erosion and siltation control devices installed according to the
plans or as approved by the Engineer provided such devices are no longer
effective because of deterioration or functional incapacity, except that no
payment shall be made for replacement of erosion and siltation control
devices ineffective due to improper installation, lack of reasonable
maintenance or because of failure of the Contractor to pursue timely
installation of permanent erosion and siltation control devices in accordance
with the Plans and Specifications or as directed by the Engineer.
Unless provided for on the plans, no direct payment will be made for
temporary and permanent erosion and siltation control measures in
disturbed areas outside the rights-of-way such as borrow areas, waste areas
and haul roads unless the borrow areas or waste areas are provided for by
the Department, and except for permanent Seeding (with Mulch) on borrow
areas and waste areas within the limitations prescribed in Subsection
203.04 and Subsection 203.07, respectively. Where the plans show
separate quantities for erosion and siltation control items to be used outside
the rights-of-way in connection with waste areas, borrow areas or other
project related construction, payment will be made for these items used and
accepted to the extent of these separately listed plans quantities; but the cost
of any overruns in these items, or the cost of any additional items required
for erosion and siltation control off the rights-of-way, shall be borne by the
Contractor unless prior approval in writing is received from the Engineer.
In case of failure of the Contractor to control project related erosion or
siltation, either on or off the rights-of-way, the Engineer may withhold
payment of future progress estimates until the Contractor has satisfactorily
performed the necessary corrective measures. If deemed necessary, the
Engineer may employ outside assistance or use his own forces to provide
the needed protective measures, with all incurred direct costs plus project
engineering costs being charged to the Contractor by appropriate
deductions from the Contractor's monthly progress estimate.
209
148
COMPENSATION
209.08-Method of Measurement. Temporary berms utilized on a daily
basis will be considered as a necessary part of the unit price for road and
drainage excavation and shall not be measured separately for payment.
The quantity of slope drains to be paid for shall be determined by the
linear foot (meter) constructed and measured.
Excavation for the construction of sediment structures will be
measured in accordance with the appropriate provisions of Subsection
203.09.
Sediment removal and disposal for cleaning of the sediment structures
will be measured by the cubic yard (cubic meter).
Rock used for inlet and outlet control on sediment structures will be
measured by the C.Y. (m
3
) in place in accordance with the appropriate
provisions of Subsection 109.01.
Pipe used in the construction of sediment structures will be measured
in accordance with the appropriate provisions of Subsection 607.12.
Concrete used in the construction of spillways or other structures
pertaining to sediment structures will be measured in accordance with the
appropriate provisions of Section 703.
Baled hay or straw erosion checks will be measured by the bale.
Check dams will be measured longitudinally across the top of the dam
and on a vertical plane down to the contour of the bottom of the ditch and
the number of S.F.(m
2
) calculated.
Brush barriers will be measured by the linear foot (meter) constructed
and accepted.
Temporary silt fences and filter barriers will be measured by the linear
foot(meter) constructed and accepted.
Temporary seeding and mulching operations will be measured in
accordance with the appropriate provisions of Subsection 801.09.
Temporary Sediment Bags shall be measured per each for the size bag
used per Subsection 209.02 (i).
209.09-Basis of Payment. Accepted quantities of Temporary Slope
Drains, and Brush Barriers will be paid for at the contract unit price per
linear foot (meter).
Check Dams will be paid for at the contract unit price per S.F.(m
2
).
Sediment Removal, will be paid for at the unit price per C.Y. (m
3
).
Baled Hay or Straw Erosion Checks will be paid for at the contract unit
price per bale.
Temporary Silt Fence and filter barriers will be paid for at the contract
unit price per linear foot (meter) which price shall be full compensation for
construction, maintenance, and removal.
The accepted quantities of Road and Drainage Excavation will be paid
for at the contract unit price per C.Y. (m
3
).
Concrete used in the construction of spillways or other structures
pertaining to sediment structures will be paid for in accordance with the
appropriate provisions of Section 703.
209
149
Seeding (with Mulch), Seeding (without Mulch), Temporary Seeding
(with Mulch) and Mulch items will be paid for in accordance with the
appropriate provisions of Subsection 801.10.
Water used in preparation of the seed bed and for maintenance will
paid for at the contract unit price per M.G. (1,000 gal.) ( m
3
) of water.
The Temporary Sediment Bags will be paid for at the contract price bid
per each for the size bag used which includes installation and/or
replacement along with all materials, equipment, tools, labor, and
incidentals to complete the work. Payment for removal and disposal of
material from bag shall be made by the C.Y. (m
3
) at contract price for
sediment removal.