All rights reserved
Natural Stone Headwall or Endwall: 
A wall built of natural stone at a pipe opening to support the road and protect it from the erosive forces 
of flowing water.  Walls built at the inlet of a pipe are called headwalls.  Walls built at the outlet of a 
pipe are called endwalls.    
Purposes 
Headwalls and endwalls are built to support the roadway at pipes and to prevent erosion around pipe 
installations.  Properly constructed headwalls significantly improve the flow capacity of the pipe.   
Benefits of Stone Headwalls and Endwalls 
 Low-cost, long-lasting solution to erosion problems at pipe openings.  
 Prevent flowing water from damaging the road structure. 
 Provide structural support for the road and prevent crushing of the pipe. 
 Increase the flow capacity of pipes by reducing turbulence and directing flow. 
 Visually identify pipe openings and protect them from traffic and maintenance equipment.  
How Stone Headwalls and Endwalls Work   
The strength of a rock wall comes from the weight of the interwoven stacked stones and friction 
between the rock surfaces.  Wall stability comes from tightly fitting the stones together and staggering 
the joints.   
Typical Requirements 
 Materials:  Rock of uniform thickness, flat on two or three sides that can be handled  
  by one person are ideal.  Native sandstone or limestone of any size and shape can be used, but 
construction will be easier and faster with stones that have some flat sides.  In areas where native 
stone is unavailable, headwalls are constructed of a variety of different materials.  Pre-fabricated 
and cast-in-place concrete, concrete blocks, and molded plastic are environmentally acceptable 
materials.  (Alternate construction techniques will be covered in a separate technical bulletin.)  
 Equipment: A pick, shovel, and sledgehammer or pry bar are the only required pieces of  
  equipment.  If large rock is available, a skilled operator can save time and labor by placing large 
stones with a backhoe.    
The publishers of this publication gratefully acknowledge the financial support of the Pennsylvania State 
Conservation Commission. For additional information or assistance, contact: Center for Dirt & Gravel 
Roads Studies, Penn State University, 207 Research Unit D, University Park, PA  16802  (Toll-Free 
Phone: 1-866-668-6683, Fax: 814-863-6787, Email: dirtandgravel@psu.edu).  Additional copies 
available on our website at: www.dirtandgravelroads.org  
Endwall at pipe outlet.  Headwall at pipe inlet. 
Technical  
Bulletin  
Natural Stone Headwalls 
Version 1.0  6/1/04 
All rights reserved                                            
Construction 
 Excavate on either side of the pipe to make room for 
the wall.  Typically walls need to extend 2-3 times the 
diameter of the pipe on each side of the pipe.  The 
base of the wall should be at least as low as the 
bottom of the pipe inlet. 
 Push a large flat rock(s) under the pipe opening.  This 
rock armors the erosion-prone earth at the pipe 
opening. 
 Start the base course with the largest available stones 
(see illustration a).  Use rocks with flat sides in the 
face of the wall taking care to stagger the joints.  
Irregularly shaped stones can be used to provide 
support behind the wall and to weave the wall 
together from front to back for structural integrity (see 
illustration b).  
 Backfill and compact the wall in layers as it is built 
with material that is damp enough for compaction and 
free of large roots and clumps of organic material. 
 Build the wall to the elevation of the top of the pipe. 
Place a large stone over the top of the pipe to bridge 
the two halves of the wall together and protect the 
pipe.  If a large stone is unavailable, continue to build 
the wall to the desired height, alternating the joints in 
the rock (see illustration c and elevation view).  
Important Considerations 
 The base of the wall carries the greatest load and 
should be the thickest part of the wall (see cross-
sectional view). As a general rule of thumb the wall 
should be as thick at its base as the projected height 
(e.g. a pipe with an outside diameter of 18 and 12 of 
cover requires a wall about 30 thick at its base).     
 Geotextile reinforcement of headwalls vastly 
increases the strength and durability of headwalls and 
can be especially useful when rock is scarce or 
rounded and difficult to stack. (See Technical Bulletin 
D-003b for details of geotextile reinforcement.) 
 Walls are typically canted back or sloped against the 
load they are holding.  Depending on the size and 
shape of stone, the height of the projected wall, and 
the potential load above the wall, wall builders will 
cant their walls back between  and 2 per foot of 
wall height.  Properly backfilled, the more a wall is 
canted back, the stronger it will be (see cross-
sectional view).      
This publication is available in alternative media upon request. The Pennsylvania State University is committed to the policy that all persons shall have equal access 
to programs, facilities, admission, and employment without regard to personal characteristics not related to ability, performance, or qualification as determined by 
University  policy  or  by  state  or federal  authorities.  The  Pennsylvania  State  University  does  not  discriminate  against  any  person  because  of  age,  ancestry,  color, 
disability or handicap, national origin, race, religious creed, sex, sexual orientation, or veteran status. Direct all affirmative action inquiries to the Affirmative Action 
Office, The Pennsylvania State University, 201 Willard Building, University Park, PA  16802-2801; tel. (814) 863-0471; TDD (814) 865-3175. U.Ed #RES-01-50. 
Headwall Construction Sequence:  
Plan or Birds Eye View 
Elevation or Turtles Eye View 
P
i
p
e 
a
c
P
i
p
e 
b
P
i
p
e 
Cross-Section or Cutaway View 
Pipe y
x 
backfill 
 to 2 
per 1 
Keys 2 Success 
- Cant the wall back         - Stagger joints for stability and strength 
- Backfill and compact as the wall is built     
- Set the base of the wall approximately equal to the projected height 
x =y