Creating Production Lines - SPD

A production line describes a unique set of operations departments, or manufacturing areas that produce one or more of your products. You can associate production lines with flow assemblies and discrete jobs.

Uploaded by

Larry Sherrod
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
61 views16 pages

Creating Production Lines - SPD

A production line describes a unique set of operations departments, or manufacturing areas that produce one or more of your products. You can associate production lines with flow assemblies and discrete jobs.

Uploaded by

Larry Sherrod
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 16

System Process Document

Creating Production Lines

Department
Responsibility/Role
File Name 27599141.doc
Revision
Document Generation Date 14/01/2010 14:03:00
Date Modified 1/14/2010 02:03:00 PM
Last Changed by
Status

Creating Production Lines


Trigger:

Concept
A production line describes a unique set of operations departments, or manufacturing areas that
produce one or more of your products. You can associate production lines with flow assemblies
and discrete jobs.

In this topic, you define manufacturing production lines in the Production Lines page.

Required Field(s) Comments

Output - Result(s) Comments

Additional Information

Last changed on: 1/14/2010 02:03:00 PM Page 1


System Process Document
Creating Production Lines

Procedure

Step Action
1. Begin by navigating to the Production Lines page.

Click the vertical scrollbar.

Page 2 Last changed on: 1/14/2010 02:03:00 PM


System Process Document
Creating Production Lines

Step Action
2. Click the Production Lines object.

Last changed on: 1/14/2010 02:03:00 PM Page 3


System Process Document
Creating Production Lines

Step Action
3. The Production Lines page is used to define a line that is a rate-based resource.
Production lines encompass a set of operations, departments, or manufacturing
areas. You can use ATP rules to determine capable to promise status of the line.

Step Action
4. Click in the Name field.

Page 4 Last changed on: 1/14/2010 02:03:00 PM


System Process Document
Creating Production Lines

Step Action
5. Enter the desired information into the Name field. Enter "Laptop1".

Last changed on: 1/14/2010 02:03:00 PM Page 5


System Process Document
Creating Production Lines

Step Action
6. Click in the Description field.

Step Action
7. Enter the desired information into the Description field. Enter "Laptop line".

Page 6 Last changed on: 1/14/2010 02:03:00 PM


System Process Document
Creating Production Lines

Step Action
8. Exception sets can help you identify capacity problems.

Click in the Exception Set field.

Last changed on: 1/14/2010 02:03:00 PM Page 7


System Process Document
Creating Production Lines

Step Action
9. Enter the desired information into the Exception Set field. Enter "Standard".

Step Action
10. The Minimum Hourly Rate represents the minimum number of assemblies the
line can produce per hour.

Click in the Minimum Hourly Rate field.

Page 8 Last changed on: 1/14/2010 02:03:00 PM


System Process Document
Creating Production Lines

Step Action
11. Enter the desired information into the Minimum Hourly Rate field. Enter "30".

Last changed on: 1/14/2010 02:03:00 PM Page 9


System Process Document
Creating Production Lines

Step Action
12. The Maximum Hourly Rate must be greater than or equal to the minimum rate.

Click in the Maximum Hourly Rate field.

Step Action
13. Enter the desired information into the Maximum Hourly Rate field. Enter "40".

Page 10 Last changed on: 1/14/2010 02:03:00 PM


System Process Document
Creating Production Lines

Step Action
14. Click in the Start Time field.

Last changed on: 1/14/2010 02:03:00 PM Page 11


System Process Document
Creating Production Lines

Step Action
15. Enter the desired information into the Start Time field. Enter "08:00:00".

Step Action
16. Click in the Stop Time field.

Page 12 Last changed on: 1/14/2010 02:03:00 PM


System Process Document
Creating Production Lines

Step Action
17. Enter the desired information into the Stop Time field. Enter "17:00:00".

Last changed on: 1/14/2010 02:03:00 PM Page 13


System Process Document
Creating Production Lines

Step Action
18. Click the Lead Time Basis option.

Step Action
19. Click the Routing-Based list item.

Page 14 Last changed on: 1/14/2010 02:03:00 PM


System Process Document
Creating Production Lines

Step Action
20. Click the Save button.

Last changed on: 1/14/2010 02:03:00 PM Page 15


System Process Document
Creating Production Lines

Step Action
21. You have completed the Creating Production Lines procedure.
End of Procedure.