C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 1 of 10
Petroleum Development Oman L.L.C.
Schedule D - Unit Rates for Alterations & Day Works C-5
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 2 of 10
Unit Rates for Alterations & Dayworks
CIVIL WORKS
Ref.
No.
1.
DESCRIPTION
UNIT
Excavation
a)
Hand excavation in all types of soil except rock to reduce
levels, for pits, trenches, foundations, etc. including support
to sides of excavation all as per PDO-ERD-17-01.
b)
Ditto but rock excavation or breaking up existing reinforced
concrete.
c)
Mechanical excavation in all types of soil except rock.
d)
Mechanical rock excavation.
1.
Filling
a)
Backfilled into excavations and compacted in 200 mm layers
including removing surplus materials from the Site all as per
PDO-ERD-17-01.
a)
Selected excavated material
b)
Imported granular material
c)
Sand bedding for cable trench
d)
35 mm Gravel filling ( switchyard area )
e)
Cable warning tape
f)
Cable tile
No
2.
Plain Cement Concrete
a)
Supply and place plain concrete including any required
formwork.
b)
c)
d)
15 N/mm
25 N/mm
35 N/mm
2
2
2-
3.
Reinforced Cement Concrete
a)
Supply and fix reinforced concrete including any required
formwork.
a)
b)
c)
25 N/nm
35 N/nm
2
2
Extra over all concrete rates for sulphate resisting or
supersulphated cement
m
m
m
m
m
m
m
m
m
m
m
m
m
3
3
3
3
3
3
3
3
3
3
3
3
3
UNIT RATE
RO
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 3 of 10
CIVIL WORKS
Ref.
No.
DESCRIPTION
UNIT
4.
Reinforcement
a)
Supply and install high yield steel rod reinforcement of all
diameter bars to BS 4449.
kg.
b)
Supply and install A 142 fabric reinforcement to BS 4483.
c)
Supply and install A 193 fabric reinforcement to BS 4483.
d)
Supply and install A 252 fabric reinforcement to BS 4483.
5.
Foundation protection
a)
Supply and place 1000
concrete foundations.
b)
Foundation Protection including Protection of Concrete
surfaces in contact with soil (including top of blinding
concrete) up to 150mm above Grade Level by painting (DFT =
600 microns minimum) with NITOCOAT PE-135 or MASTER
SEAL-550 or equivalent product.
c)
Underside of Foundations to be protected with 1000 gauge
Polythene Sheet.
6.
Grouting
a)
Cement and sand (1:2) with non-shrinkable grout to
machinery bed plates, steel structure base plates and the like.
7.
Anchor Bolts
a)
Supply, install and cast anchor bolts as per standard drawing
STD-2-3950-01-A3-A, including cutting pocket and grouting.
8.
Block work
a)
200mm compound wall of load bearing hollow concrete block
work (10.5 N/mm2 at 28 days) in cement mortar (1:4).
b)
200mm hollow block internal wall in filled with Grade 15
concrete and T10Rebar
c)
350mm external cavity wall consisting of 100mm solid block
external skin, 200mm hollow block internal skin and 50mm
cavity filled with mineral wool like Polystyrene or rock fiber
insulation. In filled with Grade 15 concrete and T10Rebar
9.
Plastering
a)
Plastering / rendering of block wall and concrete surface using
CM 1:4 including providing galvanized corner heads, angle
beads and expanded metal lathes required etc complete.
b)
15mm thick external plaster
c)
15mm thick internal plaster
gauge
polythene
sheet below
m
m
m
m
m
2
2
2
2
2
item
m
m
3
3
3
2
2
UNIT RATE
RO
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 4 of 10
CIVIL WORKS
Ref.
No.
DESCRIPTION
UNIT
d)
13mm thick ceiling plaster
10.
Painting
a)
Prepare and apply one coat of primer and two coats of paint
of approved shade on concrete and plastered surfaces
b)
External and internal walls - washable and steam resistant
emulsion paint with matt finish (Refer ' W3'. Appendix D of
PDO-ERD-17-04)
c)
Ceiling - emulsion paint (Refer ' C2'. Appendix G of PDO-ERD17-04)
11.
Fencing
a)
Supply and erect chain link fencing all in accordance with
Specification and drawing No. STD 2 1601 01.
b)
Single gate (type 20) as described on drawing No. STD 2 1625
20.
No.
c)
Double gate (type 7) as described on drawing No. STD 2 1625
007.
No.
12.
Roads
a)
Shape and trim excavation onto falls.
b)
Naturally occurring rock and gravel compacted sub-base.
c)
300 mm road base of fine graded stone.
d)
50 mm thick bitumen, aggregate premix as bearing course.
e)
250 x 125 mm flush precast concrete kerb and including
concrete bed and launch.
13.
Steelworks
m
m
m
m
m
m
2
2
2
3
2
2
Supply, fabricate, galvanise and erect steelwork and
metalwork including all cutting, notching, drilling, bolting,
welding and fixing.
Applicable for Gantry, Cross arms and Cross bracing of OHL
structure, Stay blocks for OHL structure, Switchyard
Equipment support structure.
a)
Heavy steelwork weighing more than 22 kg/m
kg
b)
Light steelwork weighing up to 22kg/m.
kg
c)
Hand railing and balustrading.
kg
d)
Ladders and caged ladders.
kg.
14.
Preliminary excavation and backfilling for HRSG
UNIT RATE
RO
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 5 of 10
CIVIL WORKS
Ref.
No.
a)
DESCRIPTION
Unit adjustment rate for Civil Works associated with
preliminary excavation and backfilling for HRSG (See
Schedule B3)
UNIT
UNIT RATE
RO
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 6 of 10
PLANT
Ref.
No.
1.
DESCRIPTION
Unit
6.6kV Cabling
a)
6.6kV 400 Amps three phase cable, supply, direct buried, test
and commission.
b)
6.6kV 300 Amps three phase cable, supply, install direct
buried, test and commission.
c)
6.6kV termination, supply, install, test and commission
each
d)
6.6kV straight joint, supply, install, test and commission
each
2.
33kV Cabling
a)
33kV 400 Amp three phase cable, supply, install direct buried,
test and commission.
b)
33kV termination, supply, install, test and commission
each
c)
33kV straight joint supply, install, test and commission
each
d)
33kV Outdoor single phase sealing end, supply install, test
and commission.
each
3.
Concrete cable trench
a)
Concrete cable trench, with covers, 2000mm wide 1000mm
deep.
b)
Concrete cable trench, with covers, 2000mm wide 1000mm
deep suitable for vehicle road crossing.
UNIT RATE
RO
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 7 of 10
ENGINEERING & DESIGN
Ref.
No.
DESCRIPTION
Unit
Design Engineer
Hr.
Lead Discipline Engineer
Hr.
Protection Engineer
Hr.
Electrical Engineer substation
Hr.
Electrical Engineer OHL transmission
Hr.
Civil Engineer substation
Hr.
Civil Engineer OHL transmission
Hr.
Commissioning Engineer
Hr.
QA/QC Engineer
Hr.
10
Designer
Hr.
11
Draughtsman
Hr.
12
Technical Assistant
Hr.
14
Telecom Site Supervisor / Engineer
Hr
UNIT
RATE RO
OVERTIME
UNIT
RATE RO
UNIT
RATE RO
OVERTIME
UNIT
RATE RO
23
SITE LABOUR
Ref.
No.
DESCRIPTION
Unit
Mechanical
1
Foreman
Hr.
Welder
Hr.
Pipe Fitter / Fabricator
Hr.
Millwright
Hr.
Rigger
Hr.
Plant Fitter
Hr.
A/C Mechanic
Hr.
Instrument Pipe Fitter
Hr.
Electrical and Instrumentation
9
Foreman
Hr.
10
Electrician
Hr.
11
Cable Jointer
Hr.
12
Telecom Technician
Hr.
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 8 of 10
SITE LABOUR
Ref.
No.
DESCRIPTION
Unit
UNIT
RATE RO
OVERTIME
UNIT
RATE RO
Civil and Miscellaneous
13
Foreman
Hr.
14
Mason
Hr.
15
Concrete Labourer
Hr.
16
Unskilled
Hr.
17
Painter
Hr.
18
Steel Fixers
Hr.
19
Steel Erectors
Hr.
20
Plasterers
Hr.
21
Plant Operator
Hr.
22
Light Duty Driver
Hr.
Plant
Ref.
No.
DESCRIPTION
Unit
Portable compressor, 4.6 m3/min (complete with
air dryer with -20 oC water dewpoint capability)
Hr.
including tools and hoses.
2
Compressor, hoses and breaker to 10 m3/m
Hr.
Dumper, 0.53 m3 capacity
Hr.
Dumper, 1.00 m3 capacity
Hr.
Excavator, 0.50 m3 capacity
Hr.
Tipper truck, 7/10 ton
Hr.
Mobile crane, 15 ton
Hr.
Concrete mixer, reversing drum with hopper
(0.20/0.15)
Hr.
Concrete mixer, reversing drum with hopper,
weigher and feed shovel (0.40/0.28)
Hr.
10
Vibrator poker type
Hr.
11
Water Bowser 5000 litres
Hr.
12
Front end loader
Hr.
13
Tipper truck of 20T/24T
Hr.
14
Gas cutting gear
Hr.
UNIT
RATE RO
OVERTIME
UNIT
RATE RO
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 9 of 10
15
Backhoe 1.0 cubic meters capacity
Hr.
16
JCB 3c or equivalent
Hr.
17
Pick-up truck
Hr.
18
Truck 5T
Hr.
19
50T Crane
Hr.
20
15T Crane
Hr.
21
5T Crane
Hr.
22
Water bowser 5 m3 capacity
Hr.
23
Generator 10 - 25 KW
Hr.
24
Generator 100 - 15 KW
Hr.
25
Generator 150 - 240 KW
Hr.
26
Temporary Generator 5 MVA 11kV
26
Diesel welding set (400 A)
Hr.
27
Electrical welding set (400A)
Hr.
28
Air compressor 250 CFM (including air dryer with
-20oC water dewpoint capability)
Hr.
29
Ditto 600 CFM
Hr.
30
Fill pump 1000 GPM including hoses etc.
Hr.
31
High pressure test pump including hoses etc.
Hr.
32
Blast unit,
personnel
Hr.
33
Bucket Truck
fully
operational
Per Day
with
operating
Hr
PERCENTAGE ADJUSTMENT FOR OVERHEADS
MATERIALS PROCUREMENT
FOR
ADDITIONAL SERVICES
AND
(Refer Section C5, Schedule A Preambles paragraph 4)
Ref.
a
Applicable Schedule
% Adjustment
ADDITIONAL SERVICES Adjustment to the net cost of additional services for
costs of handling, administration, financing, overheads,
profit and all other costs related to the procurement of
such additional services.
+/- 3%
ON COSTS ON IMPORTED MATERIALS
+/- 3%
Adjustment to the net cost of Materials procured locally
or GCC countries, for costs of handling, administration,
financing, overheads, profit and all other costs related
to such procurement.
C311333
Amal HRSG -1 Project
Section C5 Schedule D - Page 10 of 10
IMPORTED MATERIALS
Adjustment to the net cost of Materials procured from
outside of the GCC countries for costs of handling,
administration, financing, overheads, profit, all other
costs related to such procurement.
+/- 3%