Substation Civil Design
Substation Civil Design
SUMMARY
Network Standard NS185 details the general requirements for various Construction,
Architectural, Civil and Structural engineering aspects to be considered and
included into the design of Major Substations.
ISSUE
For issue to all Ausgrid and Accredited Service Providers staff involved with the
design of Major Substations.
Ausgrid maintains a copy of this and other Network Standards together with updates
and amendments on www.ausgrid.com.au.
Where this standard is issued as a controlled document replacing an earlier edition,
remove and destroy the superseded document.
DISCLAIMER
As Ausgrids standards are subject to ongoing review, the information contained in
this document may be amended by Ausgrid at any time.
It is possible that conflict may exist between standard documents. In this event, the
most recent standard shall prevail.
This document has been developed using information available from field and other
sources and is suitable for most situations encountered in Ausgrid. Particular
conditions, projects or localities may require special or different practices. It is the
responsibility of the local manager, supervisor, assured quality contractor and the
individuals involved to ensure that a safe system of work is employed and that
statutory requirements are met.
Ausgrid disclaims any and all liability to any person or persons for any procedure,
process or any other thing done or not done, as a result of this Standard.
Note that compliance with this Network Standard does not automatically satisfy the
requirements of a Designer Safety Report. The designer must comply with the
provisions of the WHS Regulation 2011 (NSW - Part 6.2 Duties of designer of
structure and person who commissions construction work) which requires the
designer to provide a written safety report to the person who commissioned the
design. This report must be provided to Ausgrid in all instances, including where the
design was commissioned by or on behalf of a person who proposes to connect
premises to Ausgrids network, and will form part of the Designer Safety Report
which must also be presented to Ausgrid. Further information is provided in Network
Standard (NS) 212 Integrated Support Requirements for Ausgrid Network Assets.
INTERPRETATION
In the event that any user of this Standard considers that any of its provisions is
uncertain, ambiguous or otherwise in need of interpretation, the user should request
Ausgrid to clarify the provision. Ausgrids interpretation shall then apply as though it
was included in the Standard, and is final and binding. No correspondence will be
entered into with any person disputing the meaning of the provision published in the
Standard or the accuracy of Ausgrids interpretation.
Network Standard
NS185
Major Substations Building Design Standard
September 2013
CONTENTS
1
SCOPE ........................................................................................................................ 1
ASBESTOS.................................................................................................................. 1
DEFINITIONS .............................................................................................................. 2
REFERENCES ............................................................................................................ 4
4.1
4.2
4.3
General ......................................................................................................... 7
Design Standards.......................................................................................... 7
Design Life of Structural Components .......................................................... 7
100 year Design Life.......................................................................... 7
50 year Design Life............................................................................ 7
20 year Design Life............................................................................ 8
Replacement of Components ............................................................ 8
Design of the Components for Design Life ................................................... 8
Preliminary Maintenance Procedures and Operation
Schedules .................................................................................................... 9
5.6
Life Cycle Costing (LCC) .............................................................................. 9
5.6.1
LCC Assessment and Report ............................................................ 9
5.6.2
Mid-term Refurbishment Requirements and
Activities............................................................................................. 9
5.7
Ecologically Sustainable Development ......................................................... 9
General ....................................................................................................... 11
Designer Safety Reports ............................................................................. 12
Design Risk Assessment. ........................................................................... 12
Durability ..................................................................................................... 12
Noise and Vibration..................................................................................... 12
Ventilation, Air Quality and Temperature Control ....................................... 13
Site Investigation......................................................................................... 13
General ............................................................................................ 13
Site Investigation ............................................................................. 13
Sites in Flood Prone Areas ......................................................................... 14
Structures Below the Groundwater Table ................................................... 14
Discharge of Groundwater............................................................... 14
Collection and Management of Groundwater .................................. 15
7.4.4
Compressed Fibrous Concrete Sheeting ........................................ 17
7.4.5
Autoclave Aerated Concrete (AAC)................................................. 17
7.4.6
Calsil Bricks ..................................................................................... 17
7.4.7
Mud Brick and other Unfired Masonry ............................................. 17
7.4.8
Asbestos Based Products................................................................ 17
7.4.9
Other Materials ................................................................................ 17
7.5
Masonry ...................................................................................................... 17
7.5.1
Durability .......................................................................................... 17
7.5.2
Brick Growth .................................................................................... 18
7.5.3
Bed Joint Reinforcing....................................................................... 18
7.5.4
Control Joints................................................................................... 18
7.5.5
Alternative Materials ........................................................................ 18
10
11
11.3.4
Safe Egress and Adequate Working Space .................................... 29
11.3.5
Equipment Handling Plans .............................................................. 29
11.3.6
Cabling Marshalling Area Requirements ......................................... 29
11.3.7
General Circulation and Personnel Access ..................................... 30
11.3.8
Access for Telecommunication Carriers.......................................... 31
11.3.9
Access for People with Disablilites .................................................. 31
11.4
Amenities .................................................................................................... 31
11.4.1
Minimum Requirement..................................................................... 31
11.4.2
Additional Amenities ........................................................................ 31
11.4.3
Lighting ............................................................................................ 32
11.5
Emergency Facilities ................................................................................... 32
11.6
Security ....................................................................................................... 32
11.6.1
General Design Requirements ........................................................ 32
11.6.2
Doors, Locks and Keys................................................................... 32
11.6.3
Monitoring and Alarms..................................................................... 33
11.7
Power and Lighting ..................................................................................... 33
11.7.1
Emergency Lighting ......................................................................... 33
11.7.2
Task Lighting.................................................................................... 33
11.7.3
External Lighting .............................................................................. 33
11.7.4
General Power Outlets .................................................................... 33
11.7.5
Location of Switches, Cables and Lights......................................... 33
11.8
Data and Communications.......................................................................... 33
11.8.1
Standards......................................................................................... 33
11.8.2
Telecommunications Brief ............................................................... 34
11.8.3
Communications Cabinets............................................................... 34
11.8.4
Communication Installation works ................................................... 34
11.8.5
External Communications Conduits ................................................ 34
11.8.6
Internal Communications Conduits.................................................. 35
11.8.7
Cable Trenches and Trays .............................................................. 35
11.9
Future Expansion of Control Rooms........................................................... 36
11.10 Plant and Equipment Labelling ................................................................... 37
11.11 Building Signage ......................................................................................... 37
11.11.1
Compartment/Room Names ............................................................ 37
11.11.2
Standard Ausgrid Operational Signs ............................................... 37
11.11.3
Emergency Information Diagrams ................................................... 37
11.12 Building Design Documentation.................................................................. 38
11.12.1
Drawings and Specifications............................................................ 38
11.12.2
Room Data Sheet Proforma ............................................................ 38
11.12.3
Maintenance Procedures and Operating
Manuals ........................................................................................... 38
11.12.4
Design and Construction Certification ............................................. 39
September 2013
SCOPE
This Standard details the performance and design criteria for the architectural and
structural design of buildings for Major Substations with the voltages of 132kV,
66kV, 33kV and 11kV.
The design of all Ausgrid Major Substations shall comply with this Standard.
An associated Network Standard, NS186 Major Substations Civil Works Design
Standard, details the performance and design criteria for the civil works design of
Major Substations.
This standard should be read in conjunction with other Ausgrid standards relevant to
the requirements for ventilation, substation overpressure, active and passive fire
mitigation. Refer to Section 4 References for specific details.
Ausgrid may have some site specific design requirements which apply in addition to
those in this Standard. This Standard draws attention to the unique requirements of
substations to meet the Ausgrid performance expectations of the asset.
This document does not include detailed information for yard structures in
substations, nor does it include provisions or information for distribution substations,
kiosks or pole top equipment such as transformers, regulators or capacitors.
ASBESTOS
All materials and equipment used for construction of Ausgrids assets are to be free
from Asbestos and or Asbestos related products. Suppliers are expected to comply
with the Work Health Safety Act 2011 (NSW) together with the Work Health Safety
Regulation 2011 (NSW) and confirm in writing that all products supplied to Ausgrid
contain no Asbestos related materials.
If any asbestos is encountered during construction or maintenance activities then
safe work method statements and appropriate practices must be implemented.
Materials containing asbestos must be handled by a licensed contractor. This
material should be disposed of offsite to an appropriately licensed landfill.
All work must be in accordance with Ausgrids Be Safe Hazard Guideline 01:
Asbestos.
September 2013
DEFINITIONS
Active System
Access requirements
Requirements for openings, loading docks corridors and passages and for
supporting the weight of all equipment and personnel.
Approved
Requires written consent from Ausgrid. Such written approval may contain
authorised specific departures from the Standard.
BCA
Cage
Design
Designer
The Designer is the nominated party responsible for the layout and design
of the project under the overall direction of Ausgrid. The Designer may be
an internal group within Ausgrid, an Alliance Partner or an external party
appointed for the project.
Design Life
The timeframe in which the building can operate efficiently and be fit for
purpose without break down of the building fabric or structure.
Dolly
A device used to split the load from the transformer float to the prime
mover.
ENA
Equipment
Plan
Handling
A plan that clearly illustrates and shows consideration for the movement of
plant for equipping, replacement and maintenance/operation.
Equipping
Fire stopping
Measures that are adopted to prevent the spread of fire, smoke and acid
residues from one compartment to another.
GIS
High voltage
A voltage above 1,000 volts alternating current or 1,500 volts direct current.
Impact Resistance
Layout Drawings
Light weight
construction
ceiling
Low maintenance
Major Substation
Overpressure
Passive System
Describes a system of fire protection with no moving parts which does not
rely on other external controls in order to function as intended. Examples of
passive systems are: fire rated building elements such as fire barrier walls,
fire doors in the closed position etc.
September 2013
Self-cleaning
Uses natural weather conditions to remove dust, debris and other airborne
materials.
STS
Substation
In this Standard, the term substation refers only to Zone or Subtransmission substations. This includes substations with 132/11 kV, 66/11
kV, 33/11 kV, 132/66 kV and 132/33 kV. This may include temporary STS
or Zone substations as defined below.
Switch building
Switch room
Switchgear
Switching equipment
Switchyard
Temporary
Relates to substations with a design life of 20 years. Refer to Clause 5.3 for
a further explanation on the various substations.
Transformer
Transformer float
Turning circle
The area required for access by a transformer float to allow the replacement
of a transformer.
WELS
September 2013
REFERENCES
All work covered in this document shall conform to all relevant Legislation,
Standards, Codes of Practice and Network Standards including but not limited to:
4.1
NEG EP09 Intruder Resistant Fences for Zone & Subtransmission Substations
Maintainability
Standards
for
and
End
Electrical
of
Life
Network
September 2013
4.2
Australian Standards
AS/NZS ISO 14040:1 Environmental management - Life cycle assessment Principles and framework.
AS 2293.1 Emergency escape lighting and exit signs for buildings - System
design, installation and operation
4.3
September 2013
ANZECC & ARMCANZ Australian and New Zealand Guidelines for Fresh
and Marine Water Quality, October 2000
ESAA D(b)36-1990 Guide for Design of Substations in Cyclone and Other High
Wind Areas (For Information only)
IEC 60529 Ed. 2.1 Degrees of protection provided by enclosures (IP Code)
Work Health and Safety Act 2011 (NSW) and Regulation 2011 (NSW)
FUNCTIONAL REQUIREMENTS
5.1
General
September 2013
Substations are classified by the required Design Life which is based on issues
relevant to calculated load, system reliability and criticality as determined by
Ausgrid. Three classifications are used in the design for Major Substations:
5.2
Design Standards
Substation buildings shall be designed to comply with all relevant legislation,
Australian Standards, Codes of Practice and the Building Code of Australia (BCA),
relevant statutory and approving authorities and any other requirements as directed
by Ausgrid.
Ausgrid requirements are described in this Network Standard, other Network
Standards and/or Network Engineering Guidelines (NEG).
5.3
5.3.1
5.3.2
5.3.3
September 2013
5.3.4
Replacement of Components
For a Design Life of 100 years or 50 years, replacement of components is allowed
for accessible and replaceable non-structural elements. These may include, but are
not limited to, the following items;
External roof and wall sheeting materials.
Roof guttering and downpipes.
External architectural elements.
Exposed external metalwork such as handrails, ladders, louvres etc.
External doors and door frames.
Internal fittings and finishes such as doors, amenities, paintwork etc.
Any proposal for replacement of components during the substation Design Life shall
be subject to a Life Cycle Cost assessment in accordance with Clause 5.6.
5.4
State the design has considered and is in accordance with relevant Codes and
Standards to achieve the Design Life specified by Ausgrid.
5.5
September 2013
5.6
5.6.1
5.6.2
5.7
10
September 2013
As part of the ESD process, EG 320 Major Substation Embodied Impacts Interim
Guidelines provides some guidance on the initiatives that may be applicable for
reducing embodied impacts associated with Major Substation projects.
11
6.1
General
September 2013
The substation building shall be of a low profile design where practicable. The
proposed external and internal colours and finishes shall be submitted to the
Ausgrid Representative for approval. The ceiling height shall accommodate all plant
and equipment including provision for arc fault venting as required.
The building shall have minimum rating of IP55 to IEC 60529, with a minimum
thermal insulation of R2.5 in the walls, floor and ceiling and shall accommodate the
following items of equipment:
Meal room facilities (where specified), complete with hot and cold potable
water supply;
Storage facilities for spare equipment, circuit breaker trolleys, blanking plates,
cover plates, signs, ladders, hanging rack for earth leads and operating sticks.
An ergonomically designed operators desk, plan table, chair, filing cabinet, notice
board and HMI complete with telephone shall be installed.
The design of all substations shall address the issues of aesthetics, the
environment, resource minimisation, energy usage and legal requirements. All
developments should be of appropriate quality to meet the Ausgrid design
requirements and shall comply with the following:
Make suitable provision for safe access to routine operating and visual
monitoring locations.
Make suitable allowance for safe work at heights with adequate space
provided around equipment to ensure that ladders, scaffolding, elevated work
platforms etc can be utilised when required.
12
September 2013
Enable access from ground level into the building for all major plant such as
circuit breaker trucks in accordance with the Work Health and Safety
Regulation 2011 (NSW).
6.2
6.3
6.4
Durability
Low maintenance materials which do not require applied finishes to be retouched or
re-coated for the life of the system are preferred. Where applied finishes are
required such finishes shall comply with the requirements in Appendix B and Clause
5.3.
All external finishes and fittings are to be self-cleaning where possible.
Refer to NS187 for material limitations with respect to fire performance.
6.5
13
September 2013
6.6
6.7
Site Investigation
6.7.1
General
The requirements for site inspection and investigation are described in NEG SM05
Site Assessment Process for Major Projects. The site investigations required are
divided into the following two stages:
6.7.2
Site Investigation
NEG SM05 shall form the basis of the required site inspection and investigation
requirements.
Ausgrid shall undertake the applicable Stage 1 Preliminary Site Assessment
activities during the site acquisition and concept design phase.
14
September 2013
The Designer shall undertake the applicable Stage 2 Detailed Site Assessment
activities during the detail design phase.
Site investigation work for the substation building shall consider site conditions
including both the previous and proposed land use. Investigations shall be carried
out to ensure compliance with all relevant standards and all other project specific
requirements.
Site investigations could include, but not be limited to, electric and magnetic fields,
noise and vibration, hydrology, geology, contamination, ecological, bush fire threat,
Aboriginal heritage, non-Aboriginal heritage, visual and aesthetics, and traffic and
access.
6.8
6.9
6.9.1
Discharge of Groundwater
Discharge of groundwater to local council or water authority stormwater
infrastructure shall only occur where a water quality assessment against the
NS185 + NSAs 1738 & 1766
15
September 2013
ANZECC Guidelines has been completed. The assessment shall confirm the
discharge water would not pose a risk of harm to the receiving water body.
All approved groundwater discharges shall be external to the substation building
using gravity drainage or an automatic pumping system, as required. Pumping
systems shall be installed in accordance with Clause 10.3.2.
6.9.2
16
MATERIALS IN SUBSTATION
STRUCTURES
7.1
Construction Materials
September 2013
7.2
Preferred Materials
Appropriately fire rated masonry including brick work, reinforced blockwork or
reinforced concrete are the preferred materials for the construction of substation
building walls.
Appropriately fire rated reinforced concrete is preferred for floors.
The use of lightweight construction for the walls, floors and roof that meets the
functional building requirements may also be acceptable subject to the approval of
Ausgrid. This approach could include a steel framed construction with suitable
cladding and an appropriate fire rated lining where required.
Other materials can be used except as detailed in the requirements in this Standard,
NS187, NS188 Design for Substation Overpressure and the Building Code Australia
(BCA).
7.3
Finishes
All finishes for substation building elements are included in Appendix B.
7.4
Material Limitations
Due to the performance requirements of substations, some standard construction
industry materials may not be permitted.
7.4.1
Timber
Due to the risk of ignition during a fire or substation overpressure, timber building
materials are generally not to be used in the construction of the substation. In
locations such as amenities areas, pilot isolation rooms, piles or landscaping the
limited use of timber may be acceptable where suitable alternatives are not
available, subject to the approval in writing of Ausgrid. Any wood composites shall
be specified as low formaldehyde or no formaldehyde.
Timber piles and timber landscaping shall be in accordance with the requirements of
NS186 Major Substations Civil Works Design Standard.
17
7.4.2
September 2013
Rubber
Rubber shall not be used in the substation building construction. Rubber is
adversely affected by ozone which may sometimes be present in substations.
7.4.3
Aluminium
Aluminium shall not be used for structural members in substations. Aluminium may
be used for trench covers where cable coating is adopted to mitigate the risk of fire
spread and the extent of damage to the cables.
7.4.4
7.4.5
7.4.6
Calsil Bricks
Calcium Silicate (Calsil) bricks may be used only in strict compliance with the
manufacturers requirements for laying. Calsil bricks shall be laid at the correct
dampness to ensure bond strength. On site testing may be required to verify the
bond strength achieved.
7.4.7
7.4.8
7.4.9
Other Materials
Products containing inhalable Man Made Mineral Fibre (MMMF) shall not be used.
This includes some sandwich panels, insulation batts, and some types of fire
stopping products.
Plastics and resins which are not fire resistant shall not be used in the construction
of any building.
7.5
Masonry
The use of unreinforced masonry shall be avoided due to the need to allow for the
effects of ductile failure. All masonry work shall comply with the following clauses.
7.5.1
Durability
The durability requirements for masonry construction shall be in accordance with AS
3700 and AS/NZS 2699 with the following additional requirements:
Wall ties and built-in components (other than lintels) shall satisfy the
requirements of durability class R4 for all locations. Use Grade 316 stainless
steel for all wall ties.
Lintels shall satisfy the requirements of durability class R3 for all locations. As
a minimum Ausgrid requires all lintels to be hot-dip galvanised steel with a
minimum coating mass of 600 g/m2.
18
September 2013
7.5.2
Brick Growth
When selecting clay bricks the representative expansion coefficient of the brick shall
be considered. Products with low expansion are preferred.
7.5.3
7.5.4
Control Joints
Walls shall have joints of sufficient size and spacing to provide for expansion due to
temperature change and brick growth. Control Joints shall also allow for contraction
and articulation caused by expansive soils, ground movement, mine subsidence or
specific site conditions.
Filler materials and sealants shall have proven long term characteristics for
softness, plasticity and flexibility to ensure the wall has sufficient space for
movement and/or cracking. Filler materials shall also have a fire resistance
commensurate with the fire resistance level required for the associated walls.
7.5.5
Alternative Materials
The use of non-conventional alternative materials shall be subject to approval in
writing by Ausgrid. Alternative materials shall have a well established track record
and codification by Standards Australia to confirm the performance of the material.
Independent test results on the performance of the alternative material may also be
considered.
Alternative materials shall perform at least as well as conventional materials and
satisfy all of the requirements of this Standard.
19
BCA PROVISIONS
8.1
Building Classification
September 2013
Substation buildings do not fit a particular class of building under the Building Code
of Australia (BCA) but are generally considered as Class 8 buildings.
All substations shall comply with the relevant provisions of the BCA noting that the
BCA may contain some provisions that are inappropriate for electricity substations.
Where compliance with the Deemed to Satisfy provisions of the BCA is considered
to be inappropriate or not possible, approval should be sought under the Alternative
Solution provisions of the BCA.
8.2
8.3
Egress
Ausgrid generally requires all rooms which contain electrical power equipment to
have at least two (2) exits, diagonally opposite where possible.
Basements that are used primarily as cable marshalling areas may be provided with
only one (1) exit provided that;
1.
The basement does not contain any other significant electrical power
equipment, and
2.
The basement complies with the BCA with regard to maximum floor area, exit
travel distances and any other requirements.
All designs which do not provide two (2) exits from any compartment shall comply
with the BCA, the relevant Australian Standards AND be approved by Ausgrid prior
to submission to the Local Approving Authority.
20
September 2013
9.1
Overpressure
The substation building shall be designed to withstand the overpressures that may
result from arcing by-products and from deflagrations, in accordance with the
manufacturers recommendations, Ausgrids NS188 Design for Substation
Overpressure, the BCA and relevant Australian Standards.
Facilities shall be installed in the switch room(s) to vent arcing by-products away
from all personnel access areas. The by-products of any arcing shall be either fully
contained or be vented outside the switch room(s) in accordance with the
switchboard manufacturers recommendations.
The applicable design requirements for ductile behaviour of building elements shall
be observed in accordance with the BCA and all relevant Australian Standards.
9.2
Mine Subsidence
If the proposed substation building is within or near a mine subsidence area the
design shall comply with the guidelines and requirements of the Mine Subsidence
Board and the Local Council or Approval Authority.
The Designer shall be responsible for obtaining approval of the design from the
Mine Subsidence Board and the Local Council or Approval Authority.
9.3
21
10
10.1
September 2013
10.2
10.2.1
Floors
General
The floor of the entire substation building shall be of suitable concrete construction
and treated in a manner approved by Ausgrid.
Post-tensioned or pre-stressed floors shall only be used where practicable and
approved by Ausgrid.
The locations of stressing tendons in post-tensioned slabs shall be clearly marked
on the soffit of the slab and the adjacent wall to clearly indicate the tendon location
from the top of the slab.
Pre-cast concrete floor systems which incorporate thin topping slabs shall not be
used in areas which are subject to concentrated floor loads, unless deflection
compatibility between panels is appropriately designed and detailed.
The finished floor surface in the high voltage switch room shall have a degree of
finish, hardness and flatness that meets the requirements of the switchgear
supplier. Refer to the relevant Ausgrid standard drawings for switch room floor
topping details and requirements.
Sufficient space should be provided in front of the switchgear to enable safe and
effective operation of the equipment by an operator standing in front of the
switchgear panel.
10.2.2
10.2.3
22
10.2.4
September 2013
Deflections
Switchgear rooms shall be designed for the specific deflections and vibration
limitations of the proposed equipment.
10.3
10.3.1
Walls
Architectural Detailing
All internal walls and the internal skin of external walls shall be of suitable material
to enable the fixing of wall anchors for support of equipment or cable trays.
Masonry or reinforced concrete walls shall be designed to minimise the extent of all
cracking. Joints shall be provided as necessary to control cracking. For reinforced
walls, horizontal reinforcing shall be proportioned to provide a high degree of crack
control.
Lightweight steel-framed walls may be acceptable and shall be subject to the
approval of Ausgrid. Lightweight walls shall not be used in load bearing situations in
substations other than for temporary substations.
10.3.2
10.4
10.4.1
Roofing System
General
The roofing system consists of roof cladding, roof drainage elements, roof space,
ceilings and associated support structures.
The roofing system of the substation building shall provide the specified Design Life
at a minimum Life Cycle Cost. Replacement is allowed for the outer or aesthetic roof
components (e.g. roof sheeting, guttering, downpipes and architectural elements) at
nominated intervals during the Design Life. Replacement during the Design Life
requires a Life Cycle Cost assessment in accordance with Clause 5.6 and shall be
subject to approval by Ausgrid.
23
September 2013
The area around the substation building, immediately under the roof eaves, shall be
sloped away from the building to prevent water ingress. Refer to NS 186 Major
Substations Civil Works Design Standard for details of personnel access paths and
other areas external to the building.
10.4.2
Weather Protection
To minimise the risk of water entering the building no penetrations are permitted
through the roof.
In addition, no penetrations (other than approved fixings) are permitted through any
impervious membranes or continuous building elements that sit below the main roof.
Where penetrations are not avoidable, a suitable sealing system shall be proposed
for review and approval by Ausgrid.
Architectural roof elements are to minimise dust entry into the building as this may
affect the operation of indoor switchgear and control equipment.
10.4.3
Roof Sheeting/Cladding
Roof sheeting shall have a minimum slope of 5 degrees unless the design ensures
the roof sheeting cannot permanently deform, or otherwise allow water ponding to
occur, under the expected maintenance or construction loading. All roof
sheeting/cladding shall be specified to minimise reflectivity.
Unless approved, all roof sheeting shall utilise concealed fasteners which do not
require the roof sheeting to be perforated. Cyclone fasteners are preferred and
should be used for all types of roof sheeting. Alternative fastener types shall be
subject to the approval of Ausgrid and, in all cases, shall meet or exceed the wind
loading requirements of Clause 10.7.
Roof coatings shall be of a light colour to reflect heat and decrease heat load on the
building wherever possible.
10.4.4
Roof Drainage
The use of external roof gutters is to be minimised subject to the drainage
requirements of the local Council.
Where roof gutters are omitted, each external doorway shall be provided with
waterfall protection as a minimum requirement for diverting run-off from the roof. In
addition, suitable provisions should be made around the building perimeter to collect
and divert roof run-off and to provide suitable erosion control.
Where external roof gutters are provided they shall be of large, oversize, design to
minimise blockages and reduce the need for access and maintenance.
Downpipes shall be oversized and provided with a gap at the base (minimum 75mm
above ground level) to allow collected leaves and debris to be removed before
entering the underground stormwater system. At ground level, the associated
stormwater sumps and grates shall be appropriately sized and detailed so as to
minimise roof water overflowing onto the adjoining ground or pavements.
The underground stormwater system shall be completely external to the substation
building unless otherwise approved in writing by Ausgrid.
10.4.5
24
September 2013
that it can be used for appropriate fall restraint techniques with minimal fall
distances and pendulum effects.
A roof access system that relies on the roof sheeting for structural support is not
preferred and shall be referred to Ausgrid for approval.
10.5
10.6
10.7
Wind Loads
Wind Loads applicable to the substation buildings shall be in accordance with
AS/NZS 1170.2 - 2002 and shall not be less than the value derived from the
following:
Note:
Substation Category
100 year
50 year
20 year
For structures covered by the BCA, AS/NZS 1170.0 - 2002 requires the design
loads to comply with the annual probability of exceedance as given in the BCA. For
these structures the relevant requirements of the BCA shall apply where they are
more severe than the values given in the table above.
25
10.8
September 2013
Earthquake Loads
Earthquake loads shall be obtained from AS/NZS 1170.4 and AS/NZS 1170.0.
The ENA guidelines Seismic Security of Power Systems ND/S/-01 (ESAA, ESC158
January 1994) and Substation Seismic Design Application Guide ND/S/-02 (ESAA,
ESC156 September 1994) should also be referenced for information purposes.
The annual probability of exceedance and the probability factor (kp) for earthquake
loading shall not be less than that shown in the table below:
Note:
Substation
Category
Annual Probability of
Exceedance
Probability Factor
(kp)
100 year
50 year
20 year
1/2500
1/2500
1/1000
For structures covered by the BCA, AS/NZS 1170.0 - 2002 requires the design
loads to comply with the annual probability of exceedance as given in the BCA. For
these structures the relevant requirements of the BCA shall apply where they are
more severe than the values given in the table above.
10.9
Structural Redundancy
Substation buildings shall be designed to prevent progressive collapse following a
substation fire or an overpressure event. This requirement shall apply only at the
locations, and to the extent, that these events are required to be sustained by the
building structure. Refer to Clauses 9.1 and 9.3.
26
September 2013
prevent flyrock from entering the site and/or damaging associated overhead
transmission lines.
10.13.1
All conduits shall be graded away from the building where possible.
All bell mouths are to be installed in line with Ausgrid requirements to minimise
water ingress to the building. See Ausgrid Drawing No. 177332.
All conduits shall be located to ensure cabling is not exposed to any sharp
edges or misaligned joints which may damage the cable.
27
11
ARCHITECTURAL DESIGN
REQUIREMENTS
11.1
Vermin Proofing
September 2013
All building elements shall be animal and vermin proof. Animals and vermin include
birds, possums, cats, rats, mice, snakes, foxes and termites. Where external ledges
or potential bird roosting places cannot be eliminated by the Designer, the need for
'bird-spikes' or similar systems to deter roosting, shall be considered.
11.2
Termite Protection
11.2.1
Specifications
Ausgrid buildings should generally be designed to avoid the use of timber or
cellulose based products that may be subject to termite attack.
At locations where the use of timber or cellulose based products are deemed to be
necessary, suitable precautions as indicated below shall be adopted to detect
and/or protect against termite attack:
The buildings shall have suitable design detailing of floors, walls and joints to
deter termite entry and allow for visual detection of any termite activity.
By limiting the use of materials that are subject to termite attack and adopting the
precautions as indicated above, the further installation of physical termite protection
systems within a substation will generally not be required.
Where additional termite protection, including physical termite protection, is
proposed at a specific location, it shall be subject to the written approval of Ausgrid.
Chemical systems for termite protection are not acceptable and will not be
approved.
Specifications for concrete work are to include provisions regarding the use of pegs
in concrete and screeding activities. All pegs used for activities such as, but not
limited to, height levelling of slabs or indicators of wet areas for screeding at a lower
level are to be removed and all holes properly filled and compacted to avoid
cracking or holes which may allow the ingress of termites.
11.2.2
11.3
11.3.1
28
11.3.2
Amenities
Emergency facilities
Security
September 2013
Battery Accommodation
Substation batteries are to be located in suitable metal cabinet-type accommodation
within the control room / switch room. Separate battery rooms are not required
unless requested and approved by Ausgrid.
The battery cabinet-type accommodation can be either free-standing or wall
mounted as required.
Where multiple battery groups are provided in a substation, the batteries shall be
located with sufficient separation to enable maintenance or similar activities on one
battery to not adversely affect operation of the other.
Refer also to NS191 Batteries & Battery Chargers in Major Substations for specific
battery accommodation requirements.
11.3.3
AFLC Accommodation
Audio Frequency Load Control (AFLC) equipment, where provided, shall be located
in suitable accommodation within the substation. The type of AFLC accommodation
adopted will depend on site location, substation layout, available space, equipment
type and other factors.
The requirements for AFLC accommodation shall be as follows:
1. Outdoor Equipment The first preference, where the site allows, is for an
outdoor kiosk type accommodation separate from the main substation buildings.
2. Indoor Equipment Where outdoor equipment cannot be used, all AFLC indoor
equipment shall be contained either inside one (1) room within a substation
building or in separate enclosures as indicated below.
3. Separate Enclosures Indoor AFLC equipment can be accommodated within
one or more separate buildings / enclosures located away from the main
substation building.
4. Alternative Use The AFLC room within a building / enclosure shall be
designed for an alternative future use (storeroom etc) following removal of the
AFLC equipment.
5. Overpressure No provision for overpressure due to deflagration is required for
the AFLC accommodation. Provision for arc fault overpressure may be required
depending on design and equipment selection.
6. Noise Suitable provisions shall be made to mitigate the noise impacts on
sensitive receivers due to AFLC equipment operation. Refer to Clause 6.5.
7. Ventilation The AFLC accommodation shall be externally vented with suitable
measures taken to address noise and contamination issues as required.
NS185 + NSAs 1738 & 1766
29
September 2013
8. Design Life The AFLC accommodation can be designed for a 20 year design
life in accordance with Clause 5.3.3 where appropriate. Prefabricated or
modular type construction that satisfies the design requirements may be
acceptable for this purpose.
The Designer shall prepare proposed designs for the AFLC accommodation and
submit these to Ausgrid for review and approval.
11.3.4
Exposed conductors
Position of permanent
switchgear etc
Egress paths shall not be near exposed live conductors including low voltage
Fall arrest
electrical
equipment
particularly
transformers,
Access into substations which contain areas which may be classified as confined
spaces shall comply with the provisions of AS 2865 and the WHS Regulation, 2011
(NSW).
11.3.5
11.3.6
30
11.3.6.1
September 2013
Safe Egress
All personnel entering and working within cabling marshalling areas are trained and
inducted. On this basis, all personnel are aware of the site-specific safety risks and
are familiar with the location of emergency egress points.
Emergency egress paths shall be maintained unobstructed.
In cable basements the egress paths shall have a minimum height of 2.0 m. In
establishing this, consideration shall be given to overhead cable trays and other
equipment or services supported from ceilings, beams or walls and cables located
at low level above the floor. Cables that are located on the floor can be excluded
from the minimum height calculation provided that:
sufficient space is provided to step over (or between) the cables; and
suitable emergency lighting is provided at, or near, each cable crossing of the
defined egress paths.
11.3.6.2
Internal cable trenches within a building shall allow for a suitable bending radius to
be provided for cables and other services installed in the trench. In particular,
suitable provision shall be made for the installation of fibre optic cables which may
have larger bending radii than other services within the cable trench. Refer to
Clause 11.8.
Suitable measures shall be taken to ensure that internal cable trenches do not have
exposed sharp edges or corners which may cause damage to cables during
installation works.
11.3.7
11.3.7.1
Corridors and passageways are to meet minimum BCA and AS 1657 requirements,
site specific and ultimate equipment handling dimensions including equipment
installation and maintenance requirements.
Refer to the Equipment Handling Plan to ensure all corridors and passageways are
adequate for all equipment movement.
Door sizes shall meet the requirements of the BCA and the Equipment Handling
Plan.
11.3.7.2
Lifts
Where lifts are required in substations they shall be designed for the transport of
personnel, equipment and ambulance or emergency stretchers which may be
required in an emergency.
Lifts shall satisfy the following requirements:
Minimum internal lift car sizes are: 2000 mm long x 1500 mm wide.
Minimum clear lift door sizes are: 2400 mm high x 1300 mm wide.
The Equipment Handling Plan: to ensure sufficient space to utilise lifts for the
installation and replacement of equipment.
NS185 + NSAs 1738 & 1766
31
11.3.8
September 2013
11.3.9
11.4
Amenities
The Designer shall incorporate the following amenities into substation building
designs.
11.4.1
Minimum Requirement
The minimum level of amenities at Major Substations which are determined by
Ausgrid as requiring amenities shall comprise a toilet, wash basin and wall mounted
hose tap.
Where possible, access to the toilet is to be provided such that a lower level security
key can be used to access the toilet without providing access to the general
switchyard / control room area.
11.4.2
Additional Amenities
Depending on location and frequency of use and as determined by Ausgrid further
amenities may be specified including some items as listed below. The provision and
extent of any additional amenities at a Major Substation shall be requested in writing
by Ausgrid.
11.4.2.1
Meal Room
A table and chairs with sufficient capacity for 4 persons. Additional seating
capacity, where required, will be subject to approval by Ausgrid.
A sink and cupboard unit connected to a domestic hot and cold water service.
All taps are to be WELS minimum 5 star (maximum 7.5 L/min) tap.
An instantaneous boiling water unit over the sink with automatic cut-out when
not in immediate use.
11.4.2.2
Toilet/shower
The cistern shall provide low water use and have full and half flush functions.
The rating shall be WELS minimum 4 star (maximum 4.5/3 L/min).
An enclosed shower tiled full height with attached change area including a
bench seat and (4) four clothes hanging hooks.
The shower head shall be a water saving type which complies with Sydney
Water requirements and guidelines.
A large wash basin with moveable spout. All taps are to be WELS minimum 5
star (maximum 7.5 L/min) tap.
All other water fixtures should achieve a minimum 5 star WELS rating.
32
11.4.3
September 2013
All amenities to be contained within one area with privacy locks on the entry
door, the shower cubicle and the toilet.
Lighting
All lighting in staff amenities shall be motion activated to ensure the energy levels
are kept to a minimum. Refer to Clause 11.7 for specific lighting requirements.
11.5
Emergency Facilities
One (1) emergency eyewash and safety shower facility shall be provided for the
substation to meet WorkCover and Ausgrid requirements. Any additional emergency
facilities shall be subject to the approval of Ausgrid.
The emergency facility shall be located near the area considered to be of highest
personnel risk. Generally, this will be a location that is external to, and as near as
possible to, a switch room door. Where practicable, the emergency facility should
also be in the vicinity of the battery enclosure location.
The preferred location of the emergency facility is external to the building where
possible, and positioned near to the area(s) considered to be of highest personnel
risk. Where an emergency facility is required internally (e.g. a CBD substation)
suitable measures shall be taken to ensure that the splash zone does not impact on
electrical and other services such as power, lighting, switchboards, fire indicator
panels etc.
Emergency facilities are used infrequently and hence, for external locations, specific
drainage provisions for the discharge are not essential. However, for internal
locations provision for drainage should be included unless a specific path for the
discharge is provided that avoids hazardous conditions arising within the building.
A self contained emergency facility without fixed plumbing may be acceptable
subject to compliance with WorkCover requirements and relevant Australian
Standards. A Life Cycle Cost assessment shall be provided for these types of
facilities to balance the initial capital savings against future operation and
maintenance costs.
11.6
11.6.1
Security
General Design Requirements
The perimeter of live switchyards and the substation building shall be secured to
minimise the risk of unauthorised entry.
If a wall of a substation building faces a public space, there should be no external
recesses in the facade capable of offering a concealed place or climb point.
No storage rooms or areas other than those required for approved substation
equipment shall be allowed within substations.
Note:
11.6.2
33
11.6.3
September 2013
11.7
11.7.1
Emergency Lighting
Self contained emergency exit lights only shall be installed. The emergency exit
lighting system shall be checked and maintained in accordance with BCA
requirements. A separate battery and emergency DC lighting is not required.
11.7.2
Task Lighting
Task lighting shall be based on the type of equipment and the work to be carried out
in the compartment. The use of portable lighting to supplement task specific work is
allowed where adequate permanent task lighting is impracticable or not cost
effective.
Task lighting shall be in accordance with NEG SM04.21, AS/NZS 1680.1 and
1680.2.4.
11.7.3
External Lighting
Type and layout of fittings shall conform to Ausgrid NEG SM04.21. Refer to the
intrusive lighting provisions of AS 4282 and the general lighting provisions of AS/NZ
1158.
11.7.4
11.7.5
11.8
11.8.1
34
11.8.2
September 2013
Telecommunications Brief
A Telecommunications Brief indicating the specific project requirements shall be
issued by Ausgrid / Communications for all Major Substation projects. This Brief will
detail communications related work at the substation, and also other works required
to ensure the site is integrated into the communications network.
11.8.3
Communications Cabinets
Communications cabinets shall be designed, supplied and installed in accordance
with NS208 series of standards. The NS208 series provides details dealing with, but
not limited to, the following aspects:
11.8.4
connection of SCADA,
All external copper telephone lines shall be run to the Telephone Isolation Cabinet,
and shall be isolated from the building and any non-approved termination
equipment.
11.8.5
One (1) white 50mm conduit is required to be run from the Telephone Isolation
Cabinet (TIC) to outside of the substation boundary. Where the conduit transits
via the cable marshalling area, provision shall be made to enable the conduit to
be earth isolated from other cables.
The placement of the communications pit outside the substation boundary
should be such that it minimises the civil works required by the incumbent
National carrier (Telstra).
2.
One (1) white 50mm conduit is required to a communications pit outside the
boundary of the substation. The placement of the pit outside the substation
boundary should be such that it minimises the civil works by a competitive
National carrier (non-Telstra).
3.
One (1) orange 50mm conduit is to be run with each 11kV bank of conduits to
the cable marshalling area. Conduits are to be capped outside of the substation
boundary, unless otherwise specified in the Telecommunications Brief.
4.
A minimum of one (1) orange 63mm conduit for Protection Fibre is to be run
with each 33kV or higher voltage bank of conduits to the vicinity of the nearest
35
September 2013
joint bay. These conduits do NOT to enter the joint bay, but rather enter an
adjacent communications specific pit.
5.
11.8.6
Conduit depths shall align with NEG TC28 Installation of Optical Fibre
Infrastructure within Substations to ensure minimum disruption to the conduits
due to normal substation works.
2.
A minimum of two (2) orange 80mm diverse conduit routes are required
between all buildings. This may be facilitated in a ladder or ring
arrangement. Contact Ausgrid Communications for assistance in route
planning.
For most substations, a bank of control and protection conduits will typically be
constructed between buildings. The required internal communication conduits can
be run together with these conduits.
11.8.7
Maintain minimum bend requirements. For fibre optic cables the minimum bend
radius for cables is typically twenty one (21) times the outer diameter of the
cable. This usually translates to approximately 300mm minimum bend radius.
2.
Ensure all cables are contained in conduits, whether on cable trays or in cable
trenches. This will minimise exposure and the risk of mechanical damage when
run within a substation area.
3.
Saddle the cable conduits to the side wall of any cable trenches when running
conduits through an external switchyard.
4.
Minimise the risk of outage to redundant diverse cables by not using common
cable paths or common mechanical fixings where possible (i.e. booker rod
supporting dual cable trays).
5.
36
6.
11.9
September 2013
Label all conduits with the cable number at all substation transition (entry/exits)
points. Should the conduit run be significant, label also every 10 metres of
conduit.
Restrict panel dimensions (width and depth) to within a nominated range for
improved layout efficiency.
Distribute spare panel space appropriately throughout the room and amongst
each of the various functional groupings.
37
September 2013
Make suitable allowances for segregation and redundant paths for future
cables where appropriate.
Ensure that all allocations of future panel space are controlled and coordinated
solely by the Designer and variations are approved by Ausgrid.
Ensure that the future expansion provisions are clearly indicated on the design
drawings together with the approved nominal allocations.
Most designs for Major Substations will allow for some spare panel space within the
total allocated space to cater for known or reasonably expected future additions and
for panel upgrades and replacement. This provision may increase where there is a
level of uncertainty regarding future requirements. The amount of space provided
for future expansion will vary from site to site and as new technologies emerge.
Substations in CBD locations have specific requirements and may require additional
considerations to those that are indicated above.
11.11.1
Compartment/Room Names
Identification signs shall be provided in accordance with Ausgrid Drawing No.
167191.
Earth lead storage rooms shall not be labelled when the access doors are on the
external walls or are visible from outside the switchyard.
11.11.2
11.11.3
11.11.3.1
Emergency information diagrams shall comply with the Department of Planning &
Infrastructure Hazardous Industry Planning Advisory Paper No 1 Emergency
Planning, AS 3745 and relevant sections of AS 1319.
Emergency information diagrams, including emergency drainage diagrams, shall be
prepared for the entire substation area including the completed substation building.
They shall be prepared and installed prior to commissioning of the substation.
All emergency information diagrams shall be updated when any modifications are
undertaken. Additionally, the diagrams shall be inspected for relevancy and
accuracy at least annually during routine substation inspections. Any deficiency in
the emergency diagrams shall be reported to Ausgrid / Network Development.
38
September 2013
11.12.2
11.12.3
Ensure the specified Design Life to comply with Life Cycle Costing
requirements.
Include all items added to the project due to revised construction, design,
security or organisational issues encountered in the design and construction
phases.
39
September 2013
11.12.4
40
September 2013
Space Name
Access Notes
Equipment
Roof
Type
Finish/colour
Thermal Rating
Design Life
Slope
Fasteners
Guttering
Downpipes
Anchor Points
Floor
Type
Finish
Traffic
Loadings / Point Loading
Tolerances
Inserts / Penetrations
Min. Fire Rating
Overpressure
Wall
Type (Internal/External)
Acoustic rating
Finishes (Internal/External)
Viewing Panels
Fixtures (Internal/External)
Min. Fire Rating
Overpressure
Venting type and area
Doors
Min. Clear Opening
Hob height.
Type / Min. Fire Rating
Electronic Security
Keying
Min Fire rating
Overpressure
Ceiling/slab soffit
Type
Finish
Acoustic Rating
Min. Fire Rating
Overpressure
Venting
NS185 + NSAs 1738 & 1766
Fixtures
Furniture
41
September 2013
42
September 2013
Ceiling
Walls
Floors
11 and 33kV
Switch room
Unpainted unless
otherwise
specified P1
Unpainted unless
otherwise specified
P2
132kV
Switch room
Unpainted unless
otherwise
specified P1
Unpainted unless
otherwise specified
P2
Control Room
Unpainted unless
otherwise
specified P1
Unpainted unless
otherwise specified
P2
Cable Basements
Marshalling
galleries, jointing
and other areas
where mass cables
are found
Battery Rooms
(where provided)
Unpainted
Unpainted
Unpainted
unless otherwise
specified P1
Unpainted unless
otherwise specified
P2
Communications
Room
Unpainted
unless otherwise
specified P1
Unpainted unless
otherwise
specified P1
Unpainted unless
otherwise
specified P1
Unpainted unless
otherwise specified
P2
Unpainted unless
otherwise specified
P2
Unpainted unless
otherwise specified
P2
Sprinkler Valve
and Pump Room
AFLC Rooms
Steel Trowel
Monolithic slab
Concrete Sealer P8
Steel Trowel Monolithic slab
Concrete Sealer P8
Steel Trowel Monolithic Slab with
Concrete Sealer P8
Steel Trowel Monolithic Slab with epoxy
paint P6
43
September 2013
Room/Area
Ceiling
Walls
Floors
Lunch Room
Painted P1.
Painted P2
Toilets / Showers
Painted P1.
Capacitor Rooms
Unpainted unless
otherwise
specified P1
Unpainted unless
otherwise
specified P1
Unpainted
Painted P2
Ceramic tiles to
wet areas
Unpainted unless
otherwise specified
P2
Unpainted unless
otherwise specified
P2
Unpainted
Stairs
Cable risers
Lifts
Transformer Bays
(Internal)
Transformer
Roadway
(Internal)
Loading Docks
Entry Foyers and
general circulation
areas
B2
Finished stainless
steel (Rigidtex
5WL Patterned
SS)
Unpainted off-form
concrete or
masonry.
Unpainted
Unpainted unless
otherwise
specified P1
Unpainted unless
otherwise
specified P1
Unpainted unless
otherwise specified
P2
Unpainted unless
otherwise specified
P2
B3
Type
Internal Finish
External Finish
Class 2
Class 3
Class 2
Class 4
Painting
The following paint systems and colours are only to be provided at the locations that are
specified by Ausgrid. Proposed alternative paint systems and colours will require the
written approval of Ausgrid.
Table 3: Paint Finishes
Code Surface
P1
Ceilings
P2
Internal Walls
Typical
Substrate
Paint system
Concrete or
Fyrechek
Concrete or
masonry with
render
Colour
reference
Colour name
White
Wattyl 25A-3P Antique Ivory
44
Code Surface
September 2013
Typical
Substrate
Paint system
Colour
reference
Colour name
Internal
Handrails,
Balustrades
Doors, Door
Frames
Metal
Semi-gloss
solvent borne
Dulux
70BB 08/064
Dark Grey
Semi-gloss
solvent borne
P5
Floor
Concrete
Oil resistant,
concrete sealant
Clear
Clear
P6
Floors and
Walls
Durafloor N
(Novolac)
Clear
Clear
Clear
Clear
Clear
As Specified
As Specified
P3
P4
P7
P8
P9
Note:
Concrete,
Alkaline resistant
concrete block epoxy coating
system
Full height
External Walls Concrete,
Non-Sacrificial
Masonry and Teflon
ceramic tiles
Graffiti Barrier
Floors
Concrete
Concrete sealer
to prevent dusting
Roofs
Metal
Manufacturers
Standard
All painting shall comprise a sealer coat, primer coat and two finish coats of
paint as specified above.
45
September 2013
General Principles
Ecologically sustainable development (ESD) can
implementation of the following principles and programs:
be
achieved
through
the
In the application of the precautionary principle, public and private decisions should
be guided by:
-
Polluter pays - that is, those who generate pollution and waste should bear
the cost of containment, avoidance or abatement.
The users of goods and services should pay prices based on the full life
cycle of costs of providing goods and services, including the use of natural
resources and assets and the ultimate disposal of any waste.
Ausgrid.
This document must not be reproduced in whole or
in part or converted to machine readable form or
stored in a computer or imaging system without the
written permission of Ausgrid.
Revision History
Initial Issue:
December 2004
Second Issue:
April 2008
Current Issue:
September 2013
Document Control
Authorised By: Terry Lampard
Document Number:
NS185