6 Prime Movers of Energy: 6.1. PUMPS
6 Prime Movers of Energy: 6.1. PUMPS
1. Present operating conditions differ from the design conditions. This change often occurs after a
plant has undertaken a water conservation program.
2. Oversized pumps were specified and installed to allow for future increases in capacity.
3. Conservative design factors were used to ensure the pump would meet the required conditions.
4. Other design factors were chosen at the expense of pump efficiency when energy costs were lower.
171
Pump Survey
A survey of pumps should concentrate on the following conditions associated with inefficient
pump operation. These are discussed in order of decreasing potential for energy savings in existing
installations. For the survey to produce worthwhile savings, only pumps above a certain size, such as
25 horsepower, need be checked.
1.
a)
b)
c)
d)
2.
172
173
The energy requirements of the overall system can be reduced by the use of a booster pump to provide
the high-pressure flow to a selected user and allow the remainder of the system to operate at a lower
pressure and reduced power.
8. Change Pump Speed
Variable-speed drives yield the maximum savings in matching pump output to varying system
requirements. However, variable speed drives generally have a higher investment cost than other
methods of capacity control. Several types of variable-speed drives can be considered:
As an example of the savings from the use of a smaller pump, assume 300 tons of refrigeration
is required during the summer months but only 75 tons for the remaining nine months. One of two 700gpm chilled-water pumps, equipped with 40-horsepower motors, is operated during the winter, with
two thirds of the flow bypassed. A new 250-gpm pump designed for the same discharge head as the
original two units consumes only 10 horsepower. The electric savings from operating the small pump
during the winter is:
Annual Savings
174
Trimming and balancing an impeller usually cost less than $1,000, and payback, therefore, is less than
three months.
FEET
1. Determine the impeller diameter to reduce head from 164 feet to 140 feet while maintaining 2,750gpm flow. Apply the affinity laws and note that both the head and flow are reduced as the impeller
is trimmed.
NPSH
6'
8'
220
50 55
14 1/2
60 65
10'
12'
70
75
200
160
140
18'
22'
83 84
84 83
82
80
13
12 1/4
78
11 1/2
150
HP
120
100
100
HP
80
P
0H
20
TOTAL HEAD
180
13 3/4
14'
78 80 82
125
HP
75
HP
60
40
0
500
1000
Figure 6.1:
1500
2000
2500
3000
3500
4000
GPM
175
176
From Q1 and H1 above a new operating point 1 is determined. The important concept here is that point
1 is not the original system operating point (2,500 gpm, 236 ft.). Rather it is the one and only point on
the original pump curve that satisfies the affinity law equations at the new operating point 2 (2,500 gpm,
150 ft.). It must be determined before BHP 2 can be calculated from the affinity laws.
10" x 18" Radial Flow Pump
15 1/2" Diameter Impeller
1750 RPM
250
A
.
400
BHP
300
200
BHPA
175
200
TDH, ft.
225
100
150
Speed2 = ?
1000
2000
3000
4000
5000
6000
Flow, gpm
Figure 6.2:
177
System
Curve
Operating
Points
Flow (gpm)
Figure 6.3:
Pump Curve
Operating Points
System Curve
Throttled
System Curve
Open
Flow (gpm)
Figure 6.4:
178
Typical Pump and System Curves for Pump with Throttling Valve
25
Throttling
Method
20
Power
Savings
15
Adjustable
Speed
Method
10
40%
60%
80%
100%
Flow (%)
Figure 6.5:
179
pump which has to be maintained in order to avoid cavitation inside the pump. The net positive suction
head required accounts for pressure drop inside the pump. The pressure head at the inlet has to be
calculated for each installation. The conventional tools for pressure losses in pipes are commonly used
and adequate. Since the occurrence of bubble forming inside the housing of the pump is absolutely
forbidden the backpressure of the system is of the same importance as NPSH. The adequate
backpressure will prevent the formation and can be achieved, if not available by the nature of the
system, by installation of backpressure valve.
OPERATING
SITUATION
HOURS OF
OPERATION
AVERAGE
kW USAGE
Constant Operation at
Full Capacity
Single Speed Fan
Cycling
Two Speed Fan
Cycling
Variable Control at
Constant Speed
Variable Speed
Control
1202.2
P = 16.2
B = 32.4
P = 16.2
B = 32.4
P = 4.3
B = 8.55
P = 2.72
B = 5.44
P = 1.99
B = 3.98
P = 765.3 (*)
B = 852.7
P = 1132 (*)
B = 1146
1202.2
1202.2
PROPELLER
FAN ENERGY
[kWh]
19475.6
BLOWER FAN
ENERGY
[kWh]
38951.2
12397.9
27627.5
4867.6
9798.3
3270
6540
2392.4
4704.8
(*) The propeller fan will operate slightly fewer hours in these modes because of the cross towers
cooling effect with the fan off.
Table 6.1.
6.2. FANS
Fans provide the necessary energy input to pump air from one location to another while they
overcome the various resistances created by the equipment and the duct distribution system. Fans have
been classified in a general way as either centrifugal fans or axial-flow fans, according to the direction of
airflow through the impeller. There are a number of subdivisions of each general type. Generally, the
subdivisions consist of different styles of impellers and the strength and arrangement of construction.
Because of the type of impeller dictates fan characteristics, it influences the amount of energy
(horsepower) the fan needs to transport the required volume of air. The centrifugal fan has four basic
types of impellers--airfoil, backward curved, radial, and forward-curved. Table 6.2 gives the nominal
efficiency of the various types of fans at normal operating conditions.
180
Type of Fan
Axial Fan
Centrifugal Fans
Airfoil Impeller
Backward-Curved Impeller
Radial Impeller
Forward-Curved Impeller
Table 6.2:
Efficiency
%
85-90
75-80
70-75
60-65
55-60
Reductions in exhaust airflows are usually obtained by adjustment of dampers in the duct.
Damper control is a simple and low-cost means of controlling airflow, but it adds resistance, which
causes an increase in fan horsepower. Accordingly, if fan output is heavily throttled or dampered, the
savings opportunity of alternate methods of volume control should be investigated.
More efficient methods of volume control are to:
1. Install inlet vane control.
2. Reduce the speed of the fan.
3. Provide variable-speed control.
Figure 6.6 shows the reduction in horsepower realized by reducing fan speed.
Before alternate methods of volume control are considered, the condition of the existing fan and
duct system should be checked. Some factors that can reduce fan efficiency are:
1. Excessive static-pressure losses through poor duct configuration or plugging.
2. Duct leakage from poor joints or flange connections, access doors left open, damage or corrosion,
etc.
3. An improperly installed inlet cone, which inadequately seals the fan inlet area and allows excessive
air recirculation.
4. Excessive fan horsepower caused by poor fan maintenance, such as bad bearings, shaft
misalignment, worn impeller blades, or corroded fan housing.
5. Dirt and dust accumulations on fan blades or housing.
6. Buildup of negative pressure.
Once the existing system operates as efficiently as possible, alternate methods to control flow can be
evaluated.
181
100
s
per
am
D
tlet
Ou
60
t
Inle
s
per
Dam
e
Van
Sp
ee
d
40
Va
ria
ble
Percent Horsepower
80
20
0
0
20
40
60
80
100
Percent Volume
Figure 6.6:
182
another alternative if the fan operates at low volume for a significant portion of the time but full capacity
is still required part-time.
As an example of the savings to be realized from a reduction in fan speed, assume the exhaust
airflow requirements have been reduced 50 percent on a 20-horsepower centrifugal fan. Reducing fan
rpm 50 percent by changing belt sheaves will halve fan output. Figure 6.6 shows a horsepower
comparison of various methods of centrifugal fan control for typical fans. A 50 percent reduction with
an outlet damper requires 80 percent of rated power; with a slower-speed motor, only 25 percent of
rated power is required. (Refer to the variable speed control curve on the figure.) Therefore:
Annual Savings = (20 hp x 80% - 20 hp x 25%) x 6,000 hrs/yr x $0.041/hp-hr
= $2,700
The reduction in fan output will result in operation of the electric motor at less than rated
capacity. If the horsepower required at the reduced flow is less than about one third of rated
horsepower, the potential savings for substitution of a smaller motor should also be investigated.
183
This section includes demand-side management measures for increasing outside air usage,
reducing air leakage around valves and fittings in compressor air lines, recovering air compressor
cooling water, recovering air compressor waste heat, pressure reduction, adding screw compressor,
controls, compressor replacement, and adding low-pressure blowers.
6.3.2. Typical Performance Improvements
1. Use Outside Air For Compressor Intakes
If compressor power is measured:
ES = 3 V LFA H WR
HP FR LF C 2 H WR
EFF
k 1
FR =
Pdo kN
P 1
i
k 1
Pdm kN
P 1
i
LF = FL FTL + FU FTU
WR =
WI WO
WI
WR =
TI TO
TI + 460
OR
184
2.
Compressor Controls
ES =
3.
HP C H FR ( LFC LFP)
EFF
H C FR
EffL
EffS
4.
ES =
5.
(1 FR ) HP LF UF C H
EFF
k 1
k
P0 N
Pi C2 V f
N C4
1
P
k 1
L=
Ea Em
P
D
NL (Ti + 460) l C1 C2 C d
V=
Pi
C3 T + 460
185
P
k
Pi C 2 V f
N C3 0
k 1
P
i
PC =
Eac Emc
k 1
k N
k 1
k N
0
Pi C2 Q
N C3
1
Pi
k 1
PB =
Eab E mb
7.
ES =
Q C p C1 (Te Tr ) HH
EFF
Definitions
Use Factor - The fraction of the yearly hours that the compressor is used.
Applicability
Facility Type - Any facility that uses an air compressor and has a use for the waste heat.
Climate - Wherever space heating is required for a significant portion of the year.
Demand-Side Management Strategy - Strategic conservation.
For More Information
Varigas Research, Inc., Compressed Air Systems, A Guidebook on Energy and Cost Savings,
Timonium, MD, 1984.
Options
Waste Heat
Recovery
Installed Costs
($)2
2,098
Energy Savings
(MMBtu/yr)
676
Cost Savings
($/yr)3
2,786
Simple Payback
(yr)
0.8
1. Tabulated data were taken from the Industrial Assessment Center (IAC) data base. All values are averages
based on the database data. The implementation rate for this measure was 34%.
2. One example from the IAC data base to further clarify the costs is as follows: The waste heat from a 75 hp
screw compressor was used to heat the plant. The energy savings were 417 MMBtu/yr, the cost savings were
$2,594/yr, and the implementation cost was $1,530 - giving a simple payback of seven months.
The energy cost savings are based on proposed dollar savings as reported to IAC from the center, usually almost
identical to actual savings reported from the facility.
Definitions
187
Power Rating - The power indicated by the air compressor manufacturer-usually shown on the
nameplate.
Power Reduction Factor - The ratio of the proposed power consumption to the current power
consumption, based on operating pressure.
Inlet Pressure - The air pressure at the air intake to the compressor, usually local atmospheric pressure.
Applicability
Facility Type - Any facility that has an air compressor.
Climate - All.
Demand-Side Management Strategy - Strategic conservation.
For More Information
National Technical Information Service, Compressed Air Systems, A Guidebook on Energy and Cost
Savings, #DOE/CS/40520-T2, March 1984.
Options
Pressure
Reductions
Installed Costs
($)2
864
Energy Savings
(MMBtu/yr)
187
Cost savings
($/yr)3
2,730
Simple Payback
(yr)
1.0
1. Tabulated data were taken from the Industrial Assessment Center (IAC) database. All values are averages based
on the data base data. The implementation rate for this measure was 48%.
2. One example from the IAC data base to further clarify the costs is as follows: Reducing the air pressure control
setting on a 75 hp air compressor from 115 psig to 100 psig resulted in energy savings of 22,500 kWh and cost
savings of $1,180/yr. The implementation cost was $270, resulting in a simple payback of three months.
The energy cost savings are based on proposed dollar savings as reported to IAC from the center, usually almost
identical to actual savings reported from the facility.
188
Hole Diameter
[in]
3/8
1/8
1/16
1/32
Energy Wasted
Per Leak
[kWh/h]
29.9
14.2
3.4
0.9
0.2
Table 6.3:
Definitions
Gage Pressure - The system pressure supplied by the compressor.
Absolute Pressure - The sum of the gage pressure and the atmospheric pressure. The gage and the
absolute pressures are used in calculating the amount of air lost due to air leaks.
Applicability
Facility Type - Any facility that has an air compressor.
Climate - All.
Demand-Side Management Strategy - Strategic conservation and peak clipping.
For More Information
American Consulting Engineers Council, Industrial Market and Energy Management Guide, SIC 32
Stone, Clay and Glass Products Industry, Washington, DC, 1987, P. III-30.
Turner, et. al., Energy Management Handbook, John Wiley and Sons, New York, NY, 1982, pp. 424425.
189
Options
Leakage
Reduction
Installed Costs
($)2
934
Energy Savings
(MMBtu/yr)
230
Cost Savings
($/yr)3
3,540
Simple Payback
(yr)
0.3
1. Tabulated data were taken from the Industrial Assessment Center (IAC) data base. All values are averages
based on the data base data. The implementation rate for this measure was 79%.
2. One example from the IAC data base to further clarify the costs is as follows: Repairing air leaks in a
compressed air system having air compressors of 150 hp, 60 hp and 25 hp-all operating at 110 psig-resulted in energy
savings of 35,750kWh and cost savings of $2,760/yr. The implementation cost was $500.
3. The energy cost savings are based on proposed dollar savings as re ported to IAC from the center, usually
almost identical to actual savings reported from the facility.
Case Study
Estimated Energy Savings = 408.0 MMBtu/yr
Estimated Cost Savings = $5,730/yr
Estimated Implementation Cost = $460
Simple Payback = 1 month
Recommended Action
Leaks in compressed air lines should be repaired on a regular basis.
Background
The cost of compressed air leaks is the energy cost to compress the volume of lost air from
atmospheric pressure to the compressor operating pressure. The amount of lost air depends on the line
pressure, the compressed air temperature at the point of the leak, the air temperature at the compressor
inlet, and the estimated area of the leak. The leak area is based mainly upon sound and feeling the
airflow from the leak. The detailed equations are included at the end of the AR. An alternative method
to determine total losses due to air leaks is to measure the time between compressor cycles when all air
operated equipment is shut off.
The plant utilizes one 75hp compressor that operates 8,520 hrs/yr. Measurements taken during
the site visit showed the compressor to continuously draw 77.7 hp. Approximately 24% of this load is
lost to air leaks in the plant. The majority of the air leaks are due to open, unused lines. There are
several plant locations where pneumatic machinery could be connected to the primary air line, but at the
time of the site visit, no machines were connected. These open lines were typically found on or near Ibeams. The terms I-beam #1, #2, and #3 are used in the tables of this AR to label the leaks. In
190
order to allow for correct location of these open lines, a list of the terms and their approximate locations
follow:
191
Terms
Description
I-Beam #1
I-Beam #2
I-Beam #3
Anticipated Savings
Values for all factors affecting the cost of compressed air leaks were determined during the site
visit, and are listed in the following tables. Because of long piping runs to the equipment, the
compressed air temperature is estimated to be the same as room temperature.
92
14.7
115
72
115
75
91.5%
Screw
1
8,520
$14.05
Using these values, the volumetric flow rate, power lost due to leaks, energy lost and cost for
leaks of various sizes were calculated specifically for the conditions at this plant. The results are shown
in the following table.
As the table shows, the cost of compressed air leaks increases exponentially as the size of the
leak increases. As part of a continuing program to find and repair compressed air leaks, the table or
graph can be referenced to estimate the cost of any leaks that might be found.
192
193
Hole
Diameter
_______
Flow
Rate
Cfm
_______
Power
Loss
hp
______
Energy
Lost
MMBtu/yr
________
Energy
Cost
per year
________
1/64
1/32
1/16
1/8
3/16
1/4
3/8
0.5
1.8
7.2
29.0
65.2
115.8
260.6
0.1
0.4
1.7
6.9
15.4
27.4
61.7
0.2
8.7
36.9
149.7
334.1
594.4
1,334.8
$31
$122
$518
$2,103
$4,694
$8,351
$18,805
The estimated energy savings and corresponding cost savings for the air leaks found during the
site visit are listed in the table below:
Summary of Savings
Machine
TOTALS
Leak
Diameter
In
Power
Loss
hp
Energy
Savings
MMBtu/yr
Cost
Savings
per year
1/16
1/16
1/16
1/8
1/16
1/16
1/16
1/16
1.7
1.7
1.7
6.9
1.7
1.7
1.7
1.7
36.9
36.9
36.9
149.7
36.9
36.9
36.9
36.9
$518
$518
$518
$2,103
$518
$518
$518
$518
18.8
408.0
$5,729
From the table above, the total estimated energy savings from repairing the air leaks are 408.0
MMBtu./yr and the total cost savings are $5,730/yr.
194
Implementation Costs
In general, implementation of this AR involves any or all of the following:
1) replacement of couplings and/or hoses;
2) replacement of seals around filters;
3) shutting off air flow during lunch or break periods; and
4) repairing breaks in lines, etc.
Specific repairs and implementation costs for the leaks found during the site visit are given in the table
below.
Implementation Costs
Machine
____________________
Cardboard Boxes Area
Cardboard Boxes Area
Hand Dye
Straight Knife
Web
I-beam #1
I-beam #2
I-beam #3
____________________
Repair Needed
_________________
_
install shut-off valve
install shut-off valve
install shut-off valve
replace coupling
change 0.5 tube
install shut-off valve
install shut-off valve
replace coupling
_________________
_
TOTALS
Parts
_____
_
$50
$50
$50
$2
$9
$50
$50
$2
_____
$263
Labor
_____
_
$25
$25
$25
$25
$25
$25
$25
$25
_____
_
$200
Total Cost
_________
_
$75
$75
$75
$27
$34
$75
$75
$27
_________
_
$463
Assuming that this work can be done by facility maintenance personnel, these leaks can be eliminated
for approximately $460. Thus, the cost savings of $5,730 would pay for the implementation cost of
$460 in about 1 month.
NL (Ti + 460)
Vf =
Pl
D 2
C 4 C5 Cd
Pi
4
C 6 Tl + 460
195
where
Vf
NL
Ti
Pl
Pi
C4
C5
Cd
D
Cb
Tl
h a g o r e a n
c o n s t a n t ,
3 . 1 4 1 6
The power loss from leaks is estimated as the power required to compress the volume of air lost from
atmospheric pressure, Pi, to the compressor discharge pressure, P, as follows2:
P
k
Pi C6 V f
N C 7 0
Pi
k 1
L=
Ea Em
k 1
kN
Where
L
k
N
C7
Po
Ea
Ea
Ea
Ea
Ea
Ea
Ea
Ea
1. A.H. Shapiro, The Dynamics and Thermodynamics of Compressible Fluid Flow, Vol 1, Ronald Press, NY,
1953, p. 100.
2. Compressed Air and Gas Institute, Compressed Air and Gas Handbook, Fifth Edition, New Jersey, 1989, Chapters
10 and 11.
3. Pneumatic Handbook, 7th ed., Anthony Barber, Trade and Technical Press, 1989, p. 49.
196
Ea
Em
197
198
This procedure, along with a couple of other common projects is covered in two publications:
Darin W. Nutter, Angela J. Britton, and Warren M. Heffington, Five Common Energy Conservation
Projects in Small- and Medium-Sized Industrial Plants, 15th National Industrial Energy Technology
Conference, Houston, TX, March 1993, pp. 112-120.
The same article was rewritten for Chemical Engineering. The reference is:
Conserve Energy to Cut Operating Costs, Chemical Engineering, September 1993, pp. 126-137
Options
Waste Water
Heat Recovery
Installed Costs
($)2
16,171
Energy savings
(MMBtu/yr)
3,306
Cost Savings
($/yr)3
14,676
Simple Payback
(yr)
1.1
199
1. Tabulated data were taken from the Industrial Assessment Center (IAC) data base and represent HOT waste
water IN GENERAL, not just cooling water. All values are averages based on the data base data. The
implementation rate for this measure was 41%.
2. One example from the IAC data base to further clarify the costs is as follows: Installing a heat exchanger to
recover heat from waste water to heat incoming city water resulted in energy savings of 145 MMBtu/yr, cost savings
of $777/yr, and an imp lementation cost of $2,600, giving a simple payback of 3.4 years.
3. The energy cost savings are based on proposed dollar savings as reported to IAC from the center, usually almost
identical to actual savings reported from the facility.
Compressor Controls
Description
Screw compressors may consume up to 80% of their rated power output when they are running
at less than full capacity. This is because many screw compressors are controlled by closing a valve; the
inlet throttling valve on a typical throttled-inlet, screw-type compressor is partially closed in response to
a reduced air system demand. The pressure rise across the compression portion of the unit does not
decrease to zero, and thus power is still required by the unit. Accordingly, an older unit will continue to
operate at 80% to 90% and a new unit at 40% to 60% of its full load capacity horsepower. When
several screw-type air compressor are being used, it is more efficient to shut off the units based on
decreasing load than to allow the units to idle, being careful not to exceed the maximum recommended
starts/hour for the compressor. Modular systems that conserve energy by operating several small
compressors that are brought on line as needed instead of operating one large compressor continuously
are often found in retrofit and new installations.
Definitions
None.
Applicability
Facility Type - Any facility that has screw-type air compressors.
Climate - All.
Demand-Side Management Strategy - Strategic conservation.
Options
Screw
Compressor
Controls
200
Installed Costs
($)2
Energy Savings
(MMBtu/yr)
Cost Savings
($/yr)3
Simple Payback
(yr)
3,463
342
5,074
0.7
1. Tabulated data were taken from the Industrial Assessment Center (IAC) data base. All values are averages
based on the data base data. The implementation rate for this measure was 48%.
2. One example from the IAC data base to further clarify the costs is as follows: Installing controls on a 100 hp
compressor resulted in energy savings of 128,600 kWh and a cost savings of $6,750/yr, at an implementation cost of
$1,500.
3. The energy cost savings are based on proposed dollar savings as reported to IAC from the center, usually
almost identical to actual savings reported from the facility.
Definitions
Rated Load - The power usage indicated by the air compressor manufacturer; usually shown on the
nameplate.
Load Factor - The average fraction of the rated load at which the compressor operates.
Applicability
Facility Type - Any facility that uses compressed air in its operations. The savings increase as the size
of the compressor and the hours of use increase for both types of compressors.
Climate - Any climate in which the average outdoor air temperature is less than the air temperature in
the compressor room.
Demand-Side Management Strategy - Strategic conservation and peak clipping.
Modern Industrial Assessments
201
Options
Outside Air
Usage
Installed Costs
($)2
593
Energy Savings
(MMBtu/yr)
82
Cost Savings
($/yr)3
1,246
Simple Payback
(yr)
0.5
1. Tabulated data were taken from the Industrial Assessment Center (IAC) data base. All values are averages
based on the data base data. The implementation rate for this measure was 52%.
2. One example from the IAC data base to further clarify the costs is as follows: Supplying outside air to the
intakes of three air compressors (100 hp, 75 hp, and 50 hp) resulted in energy and cost savings of 10,050 kWh and
$490/yr. The implementation cost was $780.
3. The energy cost savings are based on proposed dollar savings as reported to IAC from the center, usually
almost identical to actual savings reported from the facility.
Compressor Replacement
Description
It is often advantageous to install a smaller compressor to more closely match the compressed
air requirements normally met by oversized or large compressors, for processes that have periods of
low compressed air usage. A smaller compressor will reduce energy usage and associated costs
because the smaller compressor will operate at a better efficiency than the larger compressor when air
requirements are low. Generally pre-1975 stationary screw-type compressors, if oversized for the
load, will run unloaded much of the time when the load is low. They are unloaded by closing the inlet
valve and hence are referred to as modulating inlet type compressors. Based on manufacturers data,
these compressors can consume as much as 85% of the full load horsepower when running unloaded.
Some pre- and post-1975 compressor manufacturers have developed systems that close the inlet valve
but also release the oil reservoir pressure and reduce oil flow to the compressor. Other strategies have
also been developed but are not usually found on older (pre-1975) screw-type compressors. The
unloaded horsepower for screw compressors operating with these types of systems typically ranges
from 80% to 90% of the full load horsepower for older compressors and from 40% to 60% for newer
202
compressors, depending on the particular design and conditions. In any event, if the compresses air
requirements are reduced during particular periods (such as a third shift), but are not eliminated entirely,
then installing a smaller compressor to provide the air requirements during these periods can be costeffective.
Definitions
None.
Applicability
Facility Type - Any facility that has a screw compressors and in which there are time periods during
which the compressed air requirements are low.
Climate - All.
Demand-Side Management Strategy - Strategic conservation.
Optimum Sized Equipment: Costs and Benefits 1
Options
Compressor Replacement
Installed Costs
($)2
11,826
Energy Savings
(MMBtu/yr)
975
Cost Savings
($/yr)3
9,828
Simple Payback
(yr)
1.2
1. Tabulated data were taken from the Industrial Assessment Center (IAC) data base. All values are averages
based on the data base data. The implementation rate for this measure was 39%.
2. One example from the IAC data base to further clarify the costs is as follows: A manufacturer of computer
peripheral equipment replaced a 200 hp air compressor with a 75 hp air compressor. The energy savings were $61,850
kWh and the cost
savings were $2,725. The implementation costs were $4,000.
3. The energy cost savings are based on proposed dollar savings as reported to IAC from the center, usually
almost identical to actual savings reported from the facility.
Low-Pressure Blowers
Description
Compressed air is sometimes used to provide agitation of liquids, to control vibration units for
material handling (as air lances), and for other low-pressure pneumatic mechanisms. For such
purposes, it is more efficient to use a blower to provide the required low-pressure air stream. Use of
low-pressure air from the blower would reduce energy consumption by eliminating the practice of
compressing air and then expanding it back to low pressure for use.
Definitions
Plating Tanks - Tanks containing chemicals used in plating operations, such as chrome plating.
Applicability
Facility Type - Any facility having plating tanks.
Climate - All.
203
Options
Low-Pressure Blowers
Installed Costs
($)2
3,023
Energy Savings
(MMBtu/yr)
404
Cost Savings
($/yr)3
5,677
Simple Payback
(yr)
0.5
1. Tabulated data were taken from the Industrial Assessment Center (IAC) data base. All values are averages
based on the data base data. The implementation rate for this measure was 54%.
2. One example from the IAC data base to further clarify the costs is as follows: A plating facility added a low
pressure blower. The energy savings were $41,000 kWh/yr and the cost savings were $3,200/yr. The implementation
cost was
$5,000.
3. The energy cost savings are based on proposed dollar savings as reported to IAC from the center, usually
almost identical to actual savings reported from the facility.
Case Study
Estimated Energy Savings = 428.7 MMBtu/yr
Estimated Cost Savings = $5,720/yr
Estimated Implementation Cost = $8,500
Simple Payback = 18 months
Recommended Action
A low pressure blower should be installed to provide agitation air for 3 plating tanks. Use of
low pressure air from a blower, as compared to use of compressed air, would reduce electrical
consumption by eliminating the current practice of compressing air and the expanding it back to the
lower pressure.
Background
A 100 hp compressor is currently in use at this facility, and a significant amount of the power
consumed by the compressor (31%) is used to provide air to agitate 3 plating tanks. This compressor
produces compressed air at 117 psig, but less pressure is actually needed to provide effective agitation.
The pressure and flow rate requirements for effective agitation are calculated from the following
equations:
Q = AF F
and
Pa = (0.43 SD SG ) + 0.75
204
where
Q
AF
A
Pa
SD
SG
For agitation tanks containing water, the agitation factor is 1.0 cfm/sq. ft.1 The effective surface area of
the tanks is 63.5 sq. ft. Thus, the flow rate required for agitation is calculated as follows:
Q = 1..0 63.5 = 63.5cfm
1.
Because the difference between the pressure delivered by the compressor and the pressure required for
effective tank agitation, the compressor is doing a large amount of unnecessary work. By implementing
a blower that has a pressure output more closely matched to the agitation requirement, significant energy
savings can be realized.
Anticipated Savings
Energy savings due to use of air at reduced pressure, ES, are estimated as follows1:
ES = (PC PB) H C1
where
PC
PB
H
C1
The volume of free air used for agitation Vf at this plant as obtained from the plant personnel is 130 cfm.
The power PC that is required to compress the volume of free air Vf needed for agitation from
atmospheric pressure Pi to the compressor discharge pressure Po can be calculated as follows2:
205
P
k
Pi C 2 V f
N C3 0
k 1
P
i
PC =
E ac E mc
k 1
kN
where
P
C2
Vf
k
_________________________________________________
1.
2. Compressed Air and Gas Handbook, Fifth Edition, Compressed Air and Gas Institute, New Jersey, 1989, Chapters
10 and 11.
N
C3
Po
Eac
Eac
Eac
Eac
Eac
Eac
Eac
Emc
Thus, the power that is currently consumed by the compressor to provide air for tank agitation is
calculated as follows:
0 .4
1. 41
1 .4
131
.
7
14.7
0 .4
PC =
0.82 0.92
206
Similarly the power required by the blower to provide the same amount of air for agitation, PB, can be
calculated as follows:
P
k
Pi C 2 Q
N C3 b
k 1
P
i
PB =
E ab E mb
k 1
k
where
Pb
Eab
Eab
Eab
Emb
= pressure at the blower outlet, 17.7 psia (3 psig). This value accounts for Pa plus
losses in the air lines.
= blower isentropic (adiabatic) efficiency, 60%
= 0.70 for turbo blowers
= 0.62 for Roots blowers1
= compressor motor efficiency, 92% for a 100 hp motor
Thus, the power that would be consumed by the blower to provide air for tank agitation is estimated as
follows:
_______________________________________
1. Anthony Barber, Pneumatic Handbook, 7th ed., Trade and Technical Press, 1989, p.49
0 .4
1 .4
1 .4
17
.
7
0 .4
PB =
0.60 0.80
For this facility, the energy savings, ES, that can be realized by installing a blower to provide agitation air
for the three tanks are estimated as follows:
ES = (33.7 1.6) 5746 0.746 = 137,597
kWh
MMBtu
= 469.7
yr
yr
207
MMBtu $13.34
CS = 469.7
= $6,265 / yr
yr MMBtu
Implementation Cost
Implementation of this AR involves purchase and installation of a low pressure blower and
corresponding controls. The purchase price for a blower that will provide a 3 psig air at a flow of 63.5
cfm, including controls, is estimated as $7,500. The installation cost is estimated as $1,000, including
modifications to tanks described below, giving a total implementation cost of $8,500. Thus, the cost
savings of $5,720/yr would have a simple payback of about 18 months.
In order for a 3 psig blower to deliver 63.5 cfm of air, the size of the air outlets in the tanks may
have to be modified. Assuming that there are 12 total outlets (4 outlets per tank), the required outlet
diameter is calculated from the equation for unchoked flow (less than the speed of sound) as follows:
D=
4 Q Tl + 460
P
NL C5 C 6 C 7 C db (Ti + 460 ) l
Pi
2 (k l )
k
P
l
Pi
(k 1)
k
where
T
NL
C5
C6
C7
Cbd
Ti
Pl
208
4 63.5 75 + 460
D=
1
17.7
12 60
109.61 0.6 (101 + 460 )
144
14.7
2 0 .4
1. 4
0 .4
17.7 1. 4
14.7
D = 0.20 inches
Therefore, if the current diameter of the air outlets is not equal to 0.20 inches, the outlets should be
enlarged.
REFERENCES
1.
209
2.
White, F.G., Industrial Air Compressors, Foulis, 1967
3.
Janna, W.S., Introduction to Fluid Mechanics, PWS Publishing Company, 1993
4.
Wolanski, W., Negoshian, J., and Henke, R., Fundamentals of Fluid Power, Houghton
Miffin, 1977
5.
Anderson B., The Analysis and Design of Pneumatic Systems, John Wiley and Sons, 1967
6.
Fluid Power Handbook and Directory, Hydraulics And Pneumatics, 1994
7.
Marks Standard Handbook for Mechanical Engineers, McGraw-Hill, 1987
8.
Vacuum and Pressure Systems Handbook, Gast Manufacturing Corporation, 1986
210