Sr.No.
Description
Bulk Excavation
Concrete Finishing
Concrete Placement
Floor Finishes
Kerbs & Paving
Painting
Reinforcement Ratios
Roof Insulation
Screeding
10
Trench Excavation
11
Waterproofing
12
Basement Excavation'
13
Brickwork
14
Ceiling Finishes'
15
Concrete Mixing'
16
Grit Blasting'
17
Formwork
18
Plastering
19
Paintwork
20
Rule of Thumb
21
Wall Finishes
22
Tower Cranes
Remaks
Construction Wet Trades -Blockwork
Ref
Task / Description
Slow
Ave
Fast Units
630
Thermalite Blockwork, under 100mm thick
1.8
2.5
3.2 m2/hr
631
Thermalite Blockwork, under 100-150mm thick
1.4
1.9
2.5 m2/hr
632
Thermalite Blockwork, over 150mm thick
1.2
1.6
2.1 m2/hr
633
Lightweight Concrete Blockwork, under 100mm thick
1.5
2.2
2.9 m2/hr
634
Lightweight Concrete Blockwork, under 100-150mm thick
1.4
1.9
2.1 m2/hr
635
Lightweight Concrete Blockwork, over 150mm thick
1.2
1.6
2.0 m2/hr
636
Heavyweight Concrete Blockwork, under 100mm thick
1.4
2.1
2.9 m2/hr
637
Heavyweight Concrete Blockwork, under 100-150mm thick
1.2
1.6
2.1 m2/hr
638
Heavyweight Concrete Blockwork, over 150mm thick
1.1
1.4
1.8 m2/hr
639
Face Finish, Raked Out
71.4
- m2/hr
640
Face Finish, Bag Rubbed
29.4
- m2/hr
641
Face Finish, Flush Pointing
17.6
- m2/hr
Slow
Ave
Fast Units
Foundations and Excavation -Bulk Excavation
Ref
Task / Description
270
Excavation Bulking Factor, Sand/Soil
15.0
20.0 %
271
Excavation Bulking Factor, Gravel
33.0
- %
272
Excavation Bulking Factor, Clay/Chalk
40.0
- %
273
Excavation Bulking Factor, Boulder Clay
45.0
- %
274
Excavation Bulking Factor, Rock
60.0
275
Spoil Weight, Rock
2.5
- %
Tonnes/
- m3
Tonnes/
276
Spoil Weight, Concrete
2.4
277
Spoil Weight, Landfill/CDG
1.9
- m3
Tonnes/
- m3
Tonnes/
278
Spoil Weight, Sand
1.8
- m3
279
Rail Mounted Grab, 2.0m3 bucket 2.4min lift cycle
30.0
48.0
59.0 m3/hr
281
Crane Mounted Clamshell Grab, 2.0m3 bucket 2.9min lift
cycle
Crane Mounted Clamshell Grab, 2.5m3 bucket 2.9min lift
cycle
282
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil
6.9
8.7
10.2 m3/hr
283
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil
23.4
28.6
33.4 m3/hr
284
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil
45.5
50.0
58.0 m3/hr
285
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds
5.6
7.1
8.2 m3/hr
286
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds
20.5
25.0
29.0 m3/hr
287
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds
36.8
40.0
46.0 m3/hr
288
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk
5.6
7.1
8.3 m3/hr
289
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk
20.5
25.0
28.7 m3/hr
290
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk
37.0
40.0
46.0 m3/hr
291
Hydraulic Excavator, 0.3m3 bucket, Hard Ground
4.5
6.1
7.2 m3/hr
292
Hydraulic Excavator, 0.4m3 bucket, Hard Ground
17.9
22.2
25.0 m3/hr
293
Hydraulic Excavator, 0.5m3 bucket, Hard Ground
25.7
28.6
32.9 m3/hr
280
25.0
33.0
41.0 m3/hr
34.0
42.0
52.0 m3/hr
Concrete Works -Concrete Finishing
Ref
Task / Description
Slow
Ave
Fast Units
485
Surface Finishing, Steel Float By Hand
9.2
13.9
25.0 m2/hr
486
Surface Finishing, Wood Float By Hand
11.7
17.2
29.4 m2/hr
487
Surface Finishing, Power Float
13.9
20.8
37.0 m2/hr
488
Surface Finishing, Light Brush on Trowel
55.8
90.1
170.0 m2/hr
489
Surface Finishing, Brush on Trowel Margin
28.8
48.5
85.0 m2/hr
490
Surface Finishing, Sprayed By Pump, expose aggregate
65.0
95.0
145.0 m2/hr
491
Surface Finishing, Wire Brush, expose aggregate
15.0
25.0
30.0 m2/hr
492
Making Good Walls, prepare, shutter, pour
5.5
8.6 m2/hr
493
Making Good Columns, prepare, shutter, pour
2.8
6.9 m2/hr
494
Making Good Sides of Beams, prepare, shutter, pour
2.8
7.0 m2/hr
495
Making Good Slab Soffits, prepare, shutter, pour
4.2
5.5 m2/hr
496
Making Good Bolt Holes, prepare, shutter, pour
14.8
16.8
497
Making Good Rubdown Precast Concrete, prepare, shutter, pour
18.0
498
Making Good Scabble 3 head brush hammer, prepare, shutter, pour
30.7
59.5
25.8 no/hr
- m2/hr
73.8 hrs/m2
Concrete Works -Concrete Placement
Ref
Task / Description
Slow
Ave
Fast Units
460
Placing concrete, lorry based pump
30.0
40.0
50.0 m3/hr
461
Hollorib Decking, concrete topping
85.0
100.0
120.0 m2/hr
462
Hollorib Decking, concrete topping, incl PowerFloat
40.0
50.0
70.0 m2/hr
463
Placing Concrete, By Wheelbarrow over 1-10m
2.1
2.3
2.5 m3/hr
464
Placing Concrete, By Wheelbarrow over 10-20m
1.5
1.8
2.1 m3/hr
465
Placing Concrete, By Wheelbarrow over 20-50m
0.8
1.1
1.5 m3/hr
466
Placing Direct From Readymix Lorry, Mass Fill
2.8
3.1
3.3 m3/hr
467
Placing Direct From Readymix Lorry, 50mm Blinding
1.3
1.6 m3/hr
468
Placing Direct From Readymix Lorry, Ground Beams
1.5
1.7 m3/hr
469
Placing Direct From Readymix Lorry, Pile Caps
1.0
1.5
2.3 m3/hr
470
Placing Direct From Readymix Lorry, Duct Walls
0.8
1.1 m3/hr
471
Placing Direct From Readymix Lorry, Stub Columns
0.4
0.6 m3/hr
472
Placing Direct From Readymix Lorry, Ground Slab
2.1
2.3
2.6 m3/hr
473
Placing Direct From Readymix Lorry,Drains Bed and Cover
0.9
1.0 m3/hr
474
Placing From Tower Crane, Pile Caps
475
Placing From Tower Crane, Mass Fill
4.0
4.5
5.5 m3/hr
476
Placing From Tower Crane, Slabs under 150mm thick
0.9
1.3
1.7 m3/hr
477
Placing From Tower Crane, Slabs over 150mm thick
1.2
1.5
1.8 m3/hr
478
Placing From Tower Crane, Trough/Coffered Slabs
0.9
1.1
1.2 m3/hr
479
Placing From Tower Crane, Stairs and Landings
0.6
0.7
0.9 m3/hr
480
Placing From Tower Crane, Blinding
0.8
1.0
1.1 m3/hr
481
Placing From Tower Crane, Beams under 150mm thick
0.5
0.6
0.8 m3/hr
482
Placing From Tower Crane, Beams over 150mm thick
0.6
0.8
1.0 m3/hr
483
Placing From Tower Crane, Walls
0.6
1.1
1.5 m3/hr
484
Placing From Tower Crane, Columns
0.4
0.5
0.6 m3/hr
1.2
The Phrase
All Word(s)
Any Word(s)
1.4
1.6
m3/hr
Architectural Builders Work and Finishes -Floor Finishes
Ref
Task / Description
Slow
Ave
Fast Units
691
Granolithic Flooring
3.1
- m2/hr
692
Terrazzo Flooring, in-situ
3.6
- m2/hr
693
Terrazzo Flooring, pre-cast
4.6
5.1 m2/hr
694
Mosaic Tiling, 0.045x0.045m
1.5
2.2 m2/hr
695
Clay, quarry Tiles, small areas, much cutting
0.8
1.1 m2/hr
696
Clay, quarry Tiles, large areas, little cutting
2.2
2.8 m2/hr
697
Raised Floor System
2.6
- m2/hr
698
Linolium/Thermo-Plastic Flooring
3.1
5.0 m2/hr
699
Thermo-Plastic Floor Tiles
3.3
5.6 m2/hr
700
Wood Block Flooring, lay blocks
1.5
2.1 m2/hr
701
Wood Block Flooring, sand and polish
3.1
- m2/hr
702
Carpeting, Underlay & Gripper
5.6
6.1 m2/hr
703
Carpeting, Adhesive Fixing
3.5
4.2 m2/hr
704
Carpeting, Fully Fitted
2.0
2.8 m2/hr
705
Hardboard Sheeting Coverings, small areas
706
Hardboard Sheeting Coverings, large areas
6.6
7.2 m2/hr
707
Floor Sheeting Coverings, Lay Lino
9.5
10.5 m2/hr
3.7
4.1
m2/hr
Roads & External Works -Kerbs & Paving
Ref
984
985
986
987
988
989
990
991
992
993
994
995
996
Task / Description
Concrete Slabs, laid on bedding, to slight falls
Concrete Slabs, laid on bedding, to steep falls
Concrete Slabs, laid in mortar, to slight falls
Concrete Slabs, laid in mortar, to steep falls
Concrete Slabs, laid on sand, to slight falls
Concrete Slabs, laid on sand, to steep falls
Cobble Stones, laid in mortar, no patterns
Cobble Stones, laid in mortar, with patterns
Artificial Stone, laid on sand, with patterns
Brick Paviors, in mortar, straight joints
Brick Paviors, in mortar, herringbone pattern
Gravel Paths, including preparation of sub-base
Concrete Paths, 100mm thick, including preparation of sub-base
997
998
999
1000
1001
1002
1003
1004
1005
1006
1007
1008
Concrete Kerbs or Channels, laid straight
Concrete Kerbs or Channels, laid to 5m radius
Concrete Kerbs or Channels, laid to 10m radius
Concrete Kerbs or Channels, laid to 20m radius
Stone/Granite Kerbs or Channels, laid straight
Concrete Edging, laid straight
Concrete Edging, laid to 5m radius
Concrete Edging, laid to 10m radius
Concrete Edging, laid to 20m radius
Cutting and Fitting Ends, Concrete Kerbs
Cutting and Fitting Ends, Channels
Cutting and Fitting Ends, Concrete Edging
Slow
2.7
2.3
1.5
1.1
1.7
1.6
-
-
-
0.9
-
-
-
Ave
-
-
-
-
-
-
0.3
0.2
2.5
1.3
1.0
10.5
2.5
6.2
4.5
5.0
5.5
3.5
7.7
5.8
6.2
7.1
6.6
5.8
8.3
-
-
Fast
4.2
2.7
2.3
1.5
2.8
1.9
-
-
-
1.9
1.2
-
-
Units
m2/hr
m2/hr
m2/hr
m2/hr
m2/hr
m2/hr
m2/hr
m2/hr
m2/hr
m2/hr
m2/hr
m2/hr
m2/hr
- m/hr
-
m/hr
- m/hr
- m/hr
- m/hr
- m/hr
- m/hr
- m/hr
- m/hr
- no/hr
- no/hr
- no/hr
Architectural Builders Work and Finishes -Painting
Ref
Task / Description
Slow
Ave
Fast Units
841
Prepare Walls
14.2
- m2/hr
842
Prepare Doors
12.5
- m2/hr
843
Prepare Door Frames
25.0
- m/hr
844
Burn Off / Heat Strip Paintwork
1.1
- m2/hr
845
Internal Timber, 1 coat primer before fixing, generally
6.7
- m2/hr
846
Internal Timber, 1 coat primer before fixing, timber lengths
20.0
847
Internal Timber, knot, 1 primer, stop, 1 undercoat, 1 gloss
1.7
2.1 m2/hr
848
Internal Timber, touchup primer, 1 undercoat, 1 coat gloss
3.1
3.8 m2/hr
849
Internal Timber, polyurethane varnish, 2 coats
3.3
- m2/hr
850
Internal Timber, polyurethane varnish, 3 coats
2.2
- m2/hr
851
Internal Timber, linseed oil to hardwood, 2 coats
3.6
- m2/hr
852
External Timber, windows and frames
2.4
- m2/hr
853
External Timber, knot, 1 primer, 2 undercoats, 1 coat gloss,
1.5
- m2/hr
854
External Timber, touchup primer, 2 undercoats, 1 coat gloss,
2.0
- m2/hr
855
External Timber, 2 coats wood preservative
856
External Timber, 3 coats polyurethane varnish
2.0
- m2/hr
857
Internal Walls, 2 coats emulsion to plaster
8.0
- m2/hr
858
Internal Walls, 2 coats emulsion to brick/blockwork
6.0
- m2/hr
859
Internal Walls, 1 mist, 2 coats emulsion to plaster
6.0
- m2/hr
860
Internal Walls, 1 mist, 2 coats emulsion to brick/blockwork
4.5
- m2/hr
861
Internal Walls, 1 primer, 1 undercoat, 1 gloss to plaster
2.3
- m2/hr
862
Internal Walls, undercoat to door frame
20.0
- m/hr
863
Internal Walls, gloss to door frame
16.5
- m/hr
864
Internal Walls, undercoat to door
7.1
- m2/hr
865
Internal Walls, gloss to door
6.2
- m2/hr
866
External Walls, 2 coats sandtex to render/concrete
2.5
- m2/hr
4.0
- m/hr
m2/hr
867
External Walls, 2 coats sandtex to brick/blockwork
2.0
- m2/hr
868
External Walls, 1 sealer, 2 emulsion to render/concrete
2.0
- m2/hr
869
External Walls, 1 sealer, 2 emulsion to brick/blockwork
1.7
- m2/hr
870
Floors, epoxy paint
2.9
- m2/hr
871
Ceilings, emulsion paint, 2 coats
6.1
- m2/hr
872
Ceilings, emulsion paint, 3 coats
5.0
- m2/hr
873
Ceilings, textured paint
4.2
- m2/hr
874
Ceilings, artex finish
4.1
- m2/hr
875
Internal Steelwork, 1 primer, 1 undercoat, 1 gloss
1.3
2.4
- m2/hr
876
External Steelwork, 1 primer, 2 undercoats, 1 gloss
0.9
1.7
- m2/hr
877
Guttering Steelwork, 1 coat primer, 2 undercoats, 1 gloss
2.5
- m/hr
Concrete Works -Reinforcement Ratios
Ref
Task / Description
Slow
Ave
Fast Units
442
Pile Cap, Concrete m3 x Ratio = Rebar Tonnes
14.8
- % ratio
443
Base Slab, Concrete m3 x Ratio = Rebar Tonnes
13.2
14.1 % ratio
444
Suspended Slab, Concrete m3 x Ratio = Rebar Tonnes
20.6
25.6 % ratio
445
Platform Slab, Concrete m3 x Ratio = Rebar Tonnes
15.6
- % ratio
446
Columns, Concrete m3 x Ratio = Rebar Tonnes
15.8
18.7
28.7 % ratio
447
Walls, Concrete m3 x Ratio = Rebar Tonnes
14.7
15.0
- % ratio
Roof Structures and Coverings -Roof Insulation
Ref
Task / Description
Slow
Ave
Fast Units
541
Polystyrene Boards
8.5
- m2/hr
542
Glass Fibre, low pitch
12.0
- m2/hr
543
Glass Fibre, steep pitch
19.0
- m2/hr
Construction Wet Trades -Screeding
Ref
Task / Description
Slow
Ave
Fast Units
642
Sand/Cement Floor Screed, 15-20mm thick
4.8
5.7 m2/hr
643
Sand/Cement Floor Screed, 20-30mm thick
4.6
5.5 m2/hr
644
Sand/Cement Floor Screed, 30-40mm thick
3.2
4.2
5.3 m2/hr
645
Sand/Cement Floor Screed, 40-50mm thick
2.0
3.8
5.2 m2/hr
646
Sand/Cement Floor Screed, 50-65mm thick
3.3
3.9 m2/hr
647
Sand/Cement Floor Screed, 65-100mm thick
3.0
3.6 m2/hr
648
Fix/Setout Screed Battens
10.0
- m/hr
Foundations and Excavation -Trench Excavation
Ref
Task / Description
Slow
Ave
Fast Units
306
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil
5.6
7.1
8.2 m3/hr
307
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds
4.8
6.1
7.3 m3/hr
308
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk
4.8
6.1
7.1 m3/hr
309
Hydraulic Excavator, 0.3m3 bucket, Hard Ground
9.7
5.4
6.4 m3/hr
310
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil
20.5
25.0
29.2 m3/hr
311
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds
18.2
22.2
26.0 m3/hr
312
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk
18.2
22.2
26.0 m3/hr
313
Hydraulic Excavator, 0.4m3 bucket, Hard Ground
17.0
20.0
23.4 m3/hr
314
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil
26.0
28.6
33.1 m3/hr
315
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds
26.3
28.6
33.2 m3/hr
316
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk
26.3
28.6
33.2 m3/hr
317
Hydraulic Excavator, 0.5m3 bucket, Hard Ground
22.7
25.0
28.8 m3/hr
318
Excavate and Board Trench, 0.5-1.5m deep, < 2.0m wide
3.3
4.5
6.8 m2/hr
319
Excavate and Board Trench, 1.5-3.0m deep, < 2.0m wide
3.0
4.2
6.5 m2/hr
320
Excavate and Board Trench, 3.0-4.5m deep, < 2.0m wide
2.7
4.0
6.0
m2/hr
321
Excavate and Board Trench, 0.5-1.5m deep, > 2.0m wide
6.6
7.1
8.8 m2/hr
322
Excavate and Board Trench, 1.5-3.0m deep, > 2.0m wide
6.2
6.7
9.2 m2/hr
323
Excavate and Board Trench, 3.0-4.5m deep, > 2.0m wide
5.8
6.2
10.5 m2/hr
Water Engineering -Waterproofing
Ref
Task / Description
Slow
Ave
Fast Units
1181
Asphalt coatings, horizontal surfaces
3.5
4.2
5.8 m2/hr
1182
Asphalt coatings, vertical surfaces
1.2
1.7
2.2 m2/hr
1183
Bituminous Brushed application, 2 coats
4.8
5.0
6.3 m2/hr
1184
Bituminous Brushed application, 3 coats
3.3
3.5
4.4 m2/hr
1185
Bituminous Sheets, horizontal surfaces
3.8
4.0
4.8 m2/hr
1186
Bituminous Sheets, vertical surfaces
3.3
3.5
4.2 m2/hr
1187
Polythene Sheets, horizontal surfaces
20.0
- m2/hr
1188
Bentonite Sheets, horizontal surfaces
18.7
25.0
31.3 m2/hr
1189
Bentonite Sheets, vertical surfaces
11.2
15.0
17.3 m2/hr
1190
Epoxy Based application, 1 coat
Epoxy Based application, 2 coat
-
-
75.0
38.0
- m2/hr
- m2/hr
1191
Foundations and Excavation -Basement Excavation
Ref
Task / Description
Slow
Ave
Fast Units
294
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil - Basement Works
6.4
8.0
9.4 m3/hr
295
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds - Basement Works
5.5
6.9
8.1 m3/hr
296
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk - Basement Works
5.2
6.5
7.9 m3/hr
297
Hydraulic Excavator, 0.3m3 bucket, Hard Ground - Basement Works
4.7
5.9
8.2 m3/hr
298
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil - Basement Works
12.6
15.4
18.9 m3/hr
299
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds - Basement Works
11.7
14.3
16.7 m3/hr
300
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk - Basement Works
10.9
13.3
15.6 m3/hr
301
Hydraulic Excavator, 0.4m3 bucket, Hard Ground - Basement Works
9.7
11.8
14.0 m3/hr
302
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil - Basement Works
18.2
20.0
23.0 m3/hr
303
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds - Basement Works
16.5
18.1
20.0 m3/hr
304
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk - Basement Works
15.4
16.7
19.3 m3/hr
305
Hydraulic Excavator, 0.5m3 bucket, Hard Ground - Basement Works
13.3
15.4
17.7 m3/hr
Construction Wet Trades -Brickwork
Ref
Task / Description
Slow
Ave
Fast Units
593
English Bond, 0.5 Brick thick
0.7
0.8
1.1 m2/hr
594
English Bond, 1.0 Brick thick
0.6
0.8
0.9 m2/hr
595
English Bond, 1.5 Brick thick
0.4
0.5
0.6 m2/hr
596
English Bond, 2.0 Brick thick
0.3
0.4
0.5 m2/hr
597
Flemish Bond, 0.5 Brick thick
0.8
0.9
1.2 m2/hr
598
Flemish Bond, 1.0 Brick thick
0.6
0.7
0.9 m2/hr
599
Flemish Bond, 1.5 Brick thick
0.3
0.8
1.0 m2/hr
600
Flemish Bond, 2.0 Brick thick
0.3
0.4
0.5 m2/hr
601
Flemish Garden Wall Bond, 0.5 Brick thick
0.8
1.2
1.4 m2/hr
602
English Garden Wall Bond, 0.5 Brick thick
0.8
1.0
1.3 m2/hr
603
Stretcher Bond, 0.5 Brick thick
1.0
1.3
1.6 m2/hr
604
Building in Metal Door Frame
0.5
0.5
0.3 hrs/no
605
Building in Metal Window
0.6
0.5
0.4 hrs/no
606
Building in Wood Door Frame
0.4
0.3
0.2 hrs/no
607
Building in Wood Window
608
Building Brick on Edge Coping
3.7
- hrs/m
609
Building Brick on Edge Canted Cills
1.8
- hrs/m
610
Pointing to Frames
12.4
15.4
17.8 hrs/m
611
Bitumen DPC, horizontal under 100mm wide
2.9
- m2/hr
612
Bitumen DPC, horizontal 100-255mm wide
9.1
- m2/hr
613
Bitumen DPC, horizontal over 255mm wide
14.3
- m2/hr
614
Bitumen DPC, vertical under 100mm wide
5.8
- m2/hr
615
Bitumen DPC, vertical100-225mm wide
7.8
- m2/hr
616
Bitumen DPC, vertical over 225mm wide
10.0
- m2/hr
617
Reinforcement ExMet, horizontal under 100mm wide
5.8
- m2/hr
618
Reinforcement ExMet, horizontal over 100mm wide
9.1
- m2/hr
0.6
0.5
0.4
hrs/no
Construction Wet Trades -Brickwork
619
Reinforcement ExMet, vertical under 100mm wide
3.8
- m2/hr
620
Reinforcement ExMet, vertical over 100mm wide
5.8
- m2/hr
621
Face Finish as work Proceeds, Raking Out
26.3
27.8
29.4 m2/hr
622
Face Finish as work Proceeds, Flush and Rubbed
4.2
4.3
4.5 m2/hr
623
Face Finish as work Proceeds, Struck Pointing
2.8
3.0
3.1 m2/hr
624
Face Finish as work Proceeds, Bag Rubbed
1.1
- m2/hr
625
Face Finish as work Proceeds, Bucket Handle
5.4
5.6
5.8 m2/hr
626
Face Finish as work Proceeds, Recessed 5-10mm
4.2
4.7
4.9 m2/hr
627
Face Finish after completion, Flush and Rubbed
1.9
2.0
2.1 m2/hr
628
Face Finish after completion, Struck Pointing
1.3
1.2 m2/hr
629
Face Finish after completion, Bucket Handle
2.5
2.7
2.9 m2/hr
Architectural Builders Work and Finishes -Ceiling Finishes
Ref
Task / Description
Slow
Ave
Fast Units
722
Suspended Ceilings, office situations
2.6
3.5 m2/hr
723
Suspended Ceilings, First Fix
0.7
- m2/hr
724
Suspended Ceilings, Second Fix
1.2
- m2/hr
Concrete Works -Concrete Mixing
Ref
Task / Description
Slow
Ave
Fast Units
448
Concrete Weight, 1m3
2.4
- Tonnes
449
Readymix Lorry, Length
8.3
- m
450
Readymix Lorry, Width
2.5
- m
451
Readymix Lorry, Height
3.7
- m
452
Readymix Lorry, Length
24.4
- Tonnes
453
Readymix Lorry, Turning Circle
16.4
- m
454
Readymix Lorry, Allowable Access Ramp Gradient
17.0
455
Mixing Concrete, By Hand
0.3
- m3/hr
456
Mixing Concrete, Single Drum Paddle Mixer
158.0
180.0
210.0 m3/hr
457
Mixing Concrete, Double Drum Paddle Mixer
315.0
370.0
420.0 m3/hr
458
Mixing Concrete, Single Drum Plant Pan Mixer
120.0
- m3/hr
459
Mixing Concrete, Dry Mix Plant
90.0
- m3/hr
20.0 degrees
Bridge Works -Finishes
Ref
968
Task / Description
Simple Universal Beam Steel Bridge, bridge
lighting, handrails etc
Slow
Ave
17.0
Fast Units
- m/day
Structural Frames -Finishes
Ref
Task / Description
Slow
Ave
1236
Grit Blasting to structural steel frames, standard
to SA2.5
60.0
80.0
Fast Units
100.0 m2/12hours
Bridge Works -Formwork
Ref
963
Task / Description
Shaft Slip Forming
Slow
Ave
300.0
Slow
Ave
Fast Units
500.0 mm/hr
Concrete Works -Formwork
Ref
Task / Description
Fast Units
350
Pilecaps, < 0.7m2
0.9
1.6
2.0 m2/hr
351
Pilecaps, 0.7-2.5m2
1.6
2.0
2.3 m2/hr
352
Pilecaps, 2.5-3.0m2
2.0
2.3
2.5 m2/hr
353
Pilecaps, > 3.0m2
2.3
2.5
3.1 m2/hr
354
Ground Beams, < 0.7m2
1.1
1.7
1.8 m2/hr
355
Ground Beams, 0.7-1.5m2
1.7
1.8
2.5 m2/hr
356
Ground Beams, 1.5-3.0m2
1.8
2.5
2.6 m2/hr
357
Ground Beams, 3.0-5.0m2
2.5
2.6
3.5 m2/hr
358
Elevated Plain Slab Soffit
0.6
0.8
1.2 m2/hr
359
Beams, on erected falsework, width 100-200mm
0.9
1.0
1.1 m2/hr
360
Beams, on erected falsework, width 200-300mm
1.0
1.1
1.3 m2/hr
361
Beams, on erected falsework, width 300-500mm
1.2
1.3
1.5 m2/hr
362
Beams, on erected falsework, width 500-750mm
1.5
1.6
1.8 m2/hr
363
Beams, on erected falsework, width over 750mm
1.4
1.5
1.7 m2/hr
364
Walls, Construct Kickers
5.3
7.1
10.0 m2/hr
365
Walls, Fully Framed Formwork/Struts, 1.0-2.0m2
0.9
1.8
1.9 m2/hr
366
Walls, Fully Framed Formwork/Struts, 2.0-5.0m2
1.0
2.2
2.5 m2/hr
367
Walls, Fully Framed Formwork/Struts, over 5.0m2
1.2
2.5
2.9 m2/hr
368
Walls, StoriForm Shutters, 1.0-3.0m2
1.0
1.4
2.0 m2/hr
369
Walls, StoriForm Shutters, 3.0-5.0m2
1.9
2.3
3.3 m2/hr
Concrete Works -Formwork
370
Walls, StoriForm Shutters, 5.0-10.0m2
2.3
2.8
3.5 m2/hr
371
Walls, StoriForm Shutters, 10.0-15.0m2
3.2
4.5
4.0 m2/hr
372
Walls, StoriForm Shutters, over 15.0m2
3.8
4.8
5.4 m2/hr
373
Ground Slabs
1.0
1.5
1.8 m2/hr
374
Columns, Construct Kickers, direct to slab
3.2
4.1
5.4 no/hr
375
Columns, Construct Kickers, suspended from soffit slab
1.2
2.8
3.2 no/hr
376
Columns,
Columns, Square
Square Sides,
Sides, Timber
Timber Clamp/Prop,
Clamp/Prop, csa
csa
0.4m2
Columns, Square Sides, Timber Clamp/Prop, csa
0.4m2
Columns, Square Sides, Steel Forms, 1.5 x 1.5 x
<
0.1m2
0.1-
1.3
1.6
1.8 m2/hr
over
1.8
2.1
2.4 m2/hr
9.0m
2.0
2.3
2.5 m2/hr
7.9
9.5
10.3 m2/hr
6.9
7.5
8.3 m2/hr
381
high
Columns, Square Sides, Steel Forms, 2.0 x 2.0 x 9.0m
high
Columns, Square Sides, Steel Forms, 2.0 x 4.0 x 9.0m
high
Columns, Round Sides, Sacrificial Plastic Mould, 3.0-4.0m
8.5
10.2
12.0 m2/hr
382
dia
3.5
4.5
6.0 m2/hr
383
Columns, Round Sides, Steel Mould, 3.0-4.0m dia
5.2
6.5
7.5 m2/hr
384
Columns, Sloping Column Heads, extra over rate
2.5
3.5 hrs/no
385
Staircases, Stair Soffit, Sloping
0.7
0.8
1.0 m2/hr
386
Staircases, Stair Soffit, Flat Landing
0.8
0.9
1.2 m2/hr
387
Staircases, Wall Strings
0.4
0.6
- m2/hr
388
Staircases, Open Strings
0.7
0.8
- m2/hr
389
Staircases, Riser Boards fixed to strings
2.5
2.8 m2/hr
390
Staircases, Risers fixed to Strings
2.3
2.6 m2/hr
391
Waffle Flooring, 2.4m grid
1.1
1.4
1.8 m2/hr
392
Shaft Slip Forming
300.0
393
Table Form, Aluminum System, 400m2 bays
2.1
3.2
377
378
379
380
500.0 mm/hr
3.8 m2/hr
Concrete Works -Formwork
394
Table Form, H-Frame Steel Falsework, 400m2 bays
1.9
3.0
3.5 m2/hr
395
Tunnel Forms, Wall and Slab poured as one
15.6
17.5 m2/hr
396
Hollorib Decking, lay deck
43.5
47.5 m2/hr
397
Hollorib Decking, shear connecting studs
29.3
31.2 m2/hr
398
Stop Ends, no perforations
2.8
3.5
4.2 m2/hr
399
Stop Ends, minor perforations
1.2
1.5
1.9 m2/hr
400
Stop Ends, dense perforations
0.9
1.1
1.4 m2/hr
401
Box Outs, 0.01-0.05m2
7.6
8.2
9.1 no/hr
402
Box Outs, over 0.05m2
3.1
3.9
4.5 no/hr
403
Dummy Frames, under 3.0m2
4.5
6.2
7.1 no/hr
404
Dummy Frames, over 3.0m2
3.1
3.7
4.5 no/hr
Construction Wet Trades -Plastering
Ref
Task / Description
Slow
Ave
Fast Units
654
Browning (undercoat), Internal Walls under 2.5m
high
2.2
2.8
3.1 m2/hr
655
Browning (undercoat), Internal Walls over 2.5m
high
2.1
2.6
2.8 m2/hr
656
Browning (undercoat), Reveals and Columns less
than 100mm wide
9.9
10.0
10.1 m2/hr
657
Browning (undercoat), Reveals and Columns 100200mm wide
5.2
5.4
6.4 m2/hr
658
Browning (undercoat), Reveals and Columns 200300mm wide
3.3
3.6
3.9 m2/hr
659
Covings
5.0
- m/hr
660
Skimming (topcoat), Internal Walls under 2.5m high
6.1
6.7
7.3 m2/hr
661
Skimming (topcoat), Internal Walls over 2.5m high
5.5
6.1
6.7 m2/hr
662
Skimming (topcoat), Reveals and Columns less than
100mm wide
12.6
13.8
15.4 m2/hr
663
Skimming (topcoat), Reveals and Columns 100200mm wide
7.7
8.3
9.8 m2/hr
664
Skimming (topcoat), Reveals and Columns 200300mm wide
4.5
5.0
5.5 m2/hr
665
Plaster Board to Ceilings
3.2
4.5
5.5 m2/hr
666
Plastering Ceilings, 1 Bonding, 1 Skimming
1.1
1.7
2.4 m2/hr
667
Plastering Ceilings, Topcoat Skimming
2.7
3.2
5.4 m2/hr
Bridge Works -Paintwork
Ref
Task / Description
Simple Universal Beam Steel Bridge, paintwork
### to all steel
Slow Ave Fast Units
-
6.9
- m/day
Concrete Works -Reinforcement
Ref
Task / Description
Slow
Ave
Fast
Units
405
Slabs/Foundations, steelfixing, 6mm
40.3
38.4
36.5 hrs/tonne
406
Slabs/Foundations, steelfixing, 8mm
28.2
26.9
25.8 hrs/tonne
407
Slabs/Foundations, steelfixing, 10mm
22.5
20.6
20.1 hrs/tonne
408
Slabs/Foundations, steelfixing, 12mm
16.9
16.3
15.4 hrs/tonne
409
Slabs/Foundations, steelfixing, 16mm
12.0
11.5
10.9 hrs/tonne
410
Slabs/Foundations, steelfixing, 20mm
9.2
8.6
8.2 hrs/tonne
411
Slabs/Foundations, steelfixing, 25mm
6.9
6.7
6.5 hrs/tonne
412
Slabs/Foundations, steelfixing, 32mm
5.7
5.5
5.2 hrs/tonne
413
Slabs/Foundations, steelfixing, 40mm
5.3
5.1
4.9 hrs/tonne
414
Slabs/Foundations, steelfixing, 50mm
5.2
4.9
4.6 hrs/tonne
415
Beams/Columns, steelfixing, 6mm
55.4
52.8
50.6 hrs/tonne
416
Beams/Columns, steelfixing, 8mm
38.8
37.0
35.1 hrs/tonne
417
Beams/Columns, steelfixing, 10mm
29.5
28.4
26.9 hrs/tonne
418
Beams/Columns, steelfixing, 12mm
23.4
22.4
21.9 hrs/tonne
419
Beams/Columns, steelfixing, 16mm
16.6
15.8
15.1 hrs/tonne
420
Beams/Columns, steelfixing, 20mm
12.4
11.9
11.3 hrs/tonne
421
Beams/Columns, steelfixing, 25mm
9.9
9.2
8.7 hrs/tonne
422
Beams/Columns, steelfixing, 32mm
6.8
6.6
6.2 hrs/tonne
423
Beams/Columns, steelfixing, 40mm
6.1
5.9
5.6 hrs/tonne
424
Beams/Columns, steelfixing, 50mm
6.1
5.9
5.6 hrs/tonne
425
Walls, steelfixing, 6mm
41.2
40.8
39.1 hrs/tonne
Concrete Works -Reinforcement
426
Walls, steelfixing, 8mm
29.2
28.6
27.4 hrs/tonne
427
Walls, steelfixing, 10mm
22.7
22.0
21.2 hrs/tonne
428
Walls, steelfixing, 12mm
17.6
17.3
16.9 hrs/tonne
429
Walls, steelfixing, 16mm
12.4
12.2
11.8 hrs/tonne
430
Walls, steelfixing, 20mm
9.4
9.2
8.7 hrs/tonne
431
Walls, steelfixing, 25mm
7.4
7.2
7.0 hrs/tonne
432
Walls, steelfixing, 32mm
7.0
6.8
6.4 hrs/tonne
433
Walls, steelfixing, 40mm
6.4
6.1
5.9 hrs/tonne
434
Walls, steelfixing, 50mm
5.3
5.1
4.8 hrs/tonne
435
Staircases, steelfixing, 6mm
48.9
48.0
45.5 hrs/tonne
436
Staircases, steelfixing, 8mm
34.4
33.6
31.9 hrs/tonne
437
Staircases, steelfixing, 10mm
26.6
25.8
24.3 hrs/tonne
438
Staircases, steelfixing, 12mm
20.9
20.4
19.5 hrs/tonne
439
Staircases, steelfixing, 16mm
14.6
14.4
13.8 hrs/tonne
440
Staircases, steelfixing, 20mm
11.3
10.8
10.5 hrs/tonne
441
Staircases, steelfixing, 25mm
8.6
8.4
8.2 hrs/tonne
Quick Reference -Rule of Thumb
Ref
1
Task / Description
Slow
Ave
5.0
4.0
50.0
10.0
8.0
Fast Units
Site
Investigation
Pre
Drilling
Ground
Excavation,
Hydraulic
Backhoe
3.0 days/no
Bored Piling, 25-70m deep
Formwork Fixing
12.0
Reinforcement Fixing
0.7
Concrete Placement
16.0
- m3/day
Scaffold Erection, Steel Falsework
140.0
- m3/day
Blockwork Laying
7.0
- m2/day
Plastering and Rendering
12.0
- m2/day
7.0
12.0
17.5 m2/day
- m3/day
6.0 days/no
2
- m
/day
Tonnes/da
- y
10
Blockwork Laying
11
Stonework Cladding
5.1
- m2/day
12
Window Glazing
1.5
- m2/hr
13
Granolithic Flooring
4.5
- m2/hr
14
Floor Screeding
4.5
- m2/hr
15
Floor Screeding
60.0
16
Ceramic Wall Tiling
1.5
- m2/day
- m2/hr
Architectural Builders Work and Finishes -Wall Finishes
Ref
Task / Description
Slow
Ave
Fast Units
708
Mosaic Tiling, 0.045x0.045m
1.1
1.5 no/hr
709
Clay, quarry Tiles, Window Cills,
setout and level
55.5
- m/hr
710
Clay, quarry Tiles, Window Cills, fix,
grout and clean
1.5
711
Ceramic Tiles 150x150mm,
Ledges/Upstands
20.4
27.1
712
Ceramic Tiles 150x150mm, Areas
under 1.5m2 per room
0.9
1.0
1.2 m2/hr
713
Ceramic Tiles 150x150mm, Areas of
1.5-2.5m2 per room
1.4
1.6
1.9 m2/hr
714
Ceramic Tiles 150x150mm, Areas
over 2.5m2 per room
1.5
1.7
2.1 m2/hr
715
Ceramic Tiles 150x150mm, Extra
Over for Cutting
41.6
- no/hr
716
Ceramic Tiles 108x108mm,
Ledges/Upstands
62.5
- no/hr
717
Ceramic Tiles 108x108mm, Areas
under 1.5m2 per room
1.0
1.3
1.5 m2/hr
718
Ceramic Tiles 108x108mm, Areas of
1.5-2.5m2 per room
1.6
1.8
2.1 m2/hr
719
Ceramic Tiles 108x108mm, Areas
over 2.5m2 per room
1.7
1.9
2.2 m2/hr
- m2/hr
32.0 no/hr
720
Ceramic Tiles 108x108mm, Extra
Over for Cutting
721
Ceramic Tiles, Grouting Works
125.0
2.2
2.5
- no/hr
2.6 m2/hr
Scaffolds and Crainage -Tower Cranes
Ref
Task / Description
Slow
Ave
Fast Units
345
Erect and Setup 50m gib
11.0
7.5 days
346
Dismantle 50m gib
10.0
- days
347
Lifting, Reinforcement Bins and
Cages, 1st 15m lift
3.2
- mins/lift
348
Lifting, Reinforcement Bins and
Cages, above 1st 15m lift
0.5
- mins/15m
349
Lifting, Crane Tracking Time
3.3
seconds/
- m