APQP
Advanced Product
Quality Planning
According to AIAGs (QS9000) APQP Manual
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 1, Printed 10/12/98
About This Course....
This course is not meant to be an
exercise in Sit and Listen.
If you have a question, speak up and
we can discuss your question or
comments.
Timing is approximate.
Breaks are scheduled to be long
enough for you to stay aware of What
Is Happening.
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 2, Printed 10/12/98
What Is APQP?
APQP is defined process for a product
development system for Ford, GM, Chrysler
and their suppliers.
APQP is an attempt to provide a common
path and synchronization of product
development activities.
APQP is an attempt to ensure communication
both within a company and between a
company and their customer.
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 3, Printed 10/12/98
What is the AIAGs APQP Reference Manual?
It Is General Information
It Does Not Address Specific
Manufacturer Information or
Requirements
It is NOT Auditable
It Does Attempt To Give Guidance
It Does NOT Address Any Specific
Industry or Manufacturer
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 4, Printed 10/12/98
Basics
Do NOT try to write a procedure just like
the APQP reference manual.
Look at what YOU are doing and relate
it to the APQP process described by the
reference manual.
Be ready to explain Equivalencies Where and How and What your system
does which fulfills APQP timeline
elements.
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 5, Printed 10/12/98
The Target & Goal
Continuous Improvement
Production
Pre-Launch
Prototype
LSL
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
USL
Advanced Product Quality Planning
Slide 6, Printed 10/12/98
Advanced Product Quality Planning
Concept
Initiation - Program
Approval Approval
Prototype
Planning
Design & Development
Planning
Pilot
Product
Process
Launch
Validation Product - Process
Production
Feedback Assessment & Corrective Action
Plan &
Define
Program
Product
Process Product &
Design & Design & Process
Dev.
Dev.
Validation
Verification Verification
AIAG APQP & Ctrl Plan Reference Guide, Page 5
A structured method of defining the steps (process) necessary to assure that a
product satisfies the customer
The goal of APQP is to facilitate communication with everyone involved to
ensure that all required steps are completed on time.
Effective APQP depends upon top management commitment and support to
assure that customer satisfaction is achieved
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 7, Printed 10/12/98
Fords Concept to Customer (CTC)
Initiated in 1984. Technically obsolete.
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 8, Printed 10/12/98
Simplicity
Do not make your system overly
complex
Dont try to copy the APQP manual, just
Meet the intent with your system
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 9, Printed 10/12/98
A Simple APQP Sequence
I
I
I
I
I
I
I
I
A
I
I
I
I
I
A
I
R
R
R
R
I
A
I
I
I
I
I
I
I
A
R
R
R
A
A
A
A
I
I
I
A
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
A
A
I
I
I
I
I
A
A
A
A
A
A
R
A
A
A
A
A
I
I
I
I
I
R
R
I
I
I
I
I
I
F
I
R
I
R
A
A
A
A
A
R
A
R
R
A
R
A
A
R
R
A
A
A
A
A
A
A
R
T
R
I
I
I
I
I
I
Customer
Sales
R
A
A
R
A
A
R
A
A
A
F
A
A
A
I
I
I
Quality Assurance
Purchasing
F
A
A
A
I
I
I
Program Manager
F
I
I
I
A
R
A
Production
R
I
R
R
R
I
R
A
R
A
I
Materials
Manufacturing Engineering
Design Engineering
Responsibility
Element
A
A
A
A
I
A
I
A
A
I
A
I
I
I
I
A
Market Research Information
Quality History Review
Engineering Research Data
Advanced Quality Planning Schedule
Preliminary Product/Process Design
Feasibility Analysis
Design FMEA
Process FMEA
Prototype Build and Verification
Significant Characteristics
Final Product and Process Design
Measurement and Test Equipment Needs & Costs
Process Control Plan
Process Flow Chart
Audit and QA Work Instructions
Order Production Tooling, Gages, Test Equipment
Select & Rate Suppliers
Train Quality Personnel
Supplier PSW Review & Sign-Off
Set-Up & De-Bug Production and Inspection Equipment
Preliminary Capability Studies For Production Processes
Process Optimization (Design Of Experiments)
Process Review (PFMEA Walk Through)
Product Training
Work Instructions (Manufacturing)
Measurment and Test Equipment Verification
Packaging
Part Sample Warrant
A = Assistance
I = Input
R = Responsibility
F = Sachs - Florence
T = Sachs - Troy
Advanced Product Quality Planning
Slide 10, Printed 10/12/98
QS 9000
APQP Involves:
4.1 Management Responsibility
4.2 Quality System
4.3 Contract Review
4.4 Design Control
4.5 Document and Data Control
4.9 Process Control
4.10 Receiving (Incoming)
4.11 Inspection, Measuring and Test Equipment
4.12 Inspection and Test Status
4.13 Control of Nonconforming Product
4.14 Corrective Action
4.15 Handling, Storage, Packaging and Delivery
4.16 Quality Records
4.18 Training
4.19 Servicing
4.20 Statistical Techniques
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 11, Printed 10/12/98
A Word About Design
If you design it in, its there to stay!
You will constantly be waiting for the next problem to surface!
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 12, Printed 10/12/98
PPAP
Sub-Set
APQP Launch Binders
PPAP Submission
The End Product of APQP!
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 13, Printed 10/12/98
Typical Automotive Trilogy Development
APQP Timeline
Process Flow Diagram
(Includes ALL Processes)
Process FMEA
(On ALL Processes)
Critical Characteristics
& Failure Effects Issues
Process Control Plan
Some Elements may
be Included On
(Critical Processes from FMEA)
Critical Characteristics
& Characteristic Control Issues
Design FMEA
(On Intended Use)
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 14, Printed 10/12/98
Automotive Documentation Development
Develop Process
Flow Listing
Check for Customer
Requirements.
Enter Every
Major Process
from Flow Listing
into FMEA Form
Give careful consideration
to what you consider a
Major process.
Develop FMEA(s)
Element for Every
Process
Give careful consideration
to defining Control Plan
stages:
Prototype
Pre-launch
Production
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Develop the
Control Plan with
Critical
characteristics
Use the appropriate RPN
numbers and
considerations of other
appropriate information /
data to determine Critical
Characteristics.
Develop control
mechanisms appropriate
for Critical
characteristics.
Advanced Product Quality Planning
Slide 15, Printed 10/12/98
APQP Design & Process Controls
Design Reviews
Design Verification
Design Validation
Process Validation
Design FMEA
Process FMEA
Prototype Validation
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 16, Printed 10/12/98
Product Quality Planning Responsibility Matrix
APQP Phases
Define the Scope
Plan and Define (Section 1.0)
Product Design and Development (Section 2.0)
Feasibility (Section 2.13)
Process Design & Development (Section 3.0)
Product and Process Validation (Section 4.0)
Feedback, Assessment and Corrective Action (Section 5.0)
Control Plan Methodology (Section 6.0)
Design
X
X
X
X
X
X
X
Manufacturing
X
Service Supplier
X
X
X
X
X
X
X
X
X
AIAG APQP & Ctrl Plan Reference Guide, Page 2
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 17, Printed 10/12/98
Product Quality Planning Checklists
Design FMEA
Design Information
New Equipment, Tooling and Test Equipment
Product/Process Quality
Flow Plan
Process Flow Chart
Process FMEA
Control Plan
Check Lists for these line items are in the
AIAGs APQP & Control Plan reference manual
contained as a group - Appendix A starting on
page 63. Use them!
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 18, Printed 10/12/98
Benefits of APQP
Ensures early planning takes place
Directs resources to the customer
Identifies required changes early in the
process
Provides quality product on time and at
lowest cost
Enables cross-functional inputs and outputs
Addresses potential problems early in
Design
Manufacturing
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 19, Printed 10/12/98
Each APQP is Unique
Because of product and program differences
Timing and sequence are dependent upon
customer needs and expectations
Product complexity
Stamping
Sub-assembly
New
Modification
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 20, Printed 10/12/98
Progressive Fundamentals
Organize a Cross-Functional TEAM
Define the scope
Team-to-team communications
Training
Simultaneous (concurrent) engineering
Control Plan Phases
KEY**
Prototype
Pre-Launch
Production
Concern resolution
Includes analytical techniques
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 21, Printed 10/12/98
QS 9000 Elements to Consider
4.6
4.10
4.11
What else do you think???
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 22, Printed 10/12/98
Team Organization
Cross-functional
Engineering (Typically the leader)
Quality Assurance
Purchasing
Manufacturing Engineering
Material Control
Sales/Marketing
Etc.
Participation appropriate for phase being conducted
Resources - Team defines Needs
*Should* involve customer or subcontractor
participation (not always feasible)
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 23, Printed 10/12/98
Define Scope
Select team members and functions
Define roles and responsibilities
Identify external customer needs, expectations and
requirements
Identify internal customer needs, expectations and
requirements
Complete preliminary feasibility study
Identify costs, timing and constraints
Identify documentation process and method
Develop program plan (if project is a go)
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 24, Printed 10/12/98
Team-to-Team Communication
Manage using the APQP process
Understanding of How We Work As A Team
Should have a Focus Person & Distributed Minutes
Customer teams
Internal teams
Supplier teams
Sub-Teams
Subcontractors should be encouraged to embrace
APQP and QS 9000
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 25, Printed 10/12/98
Materials
F
I
I
I
A
R
A
F
A
A
A
I
I
I
R
A
A
R
A
A
R
A
A
A
I
I
I
I
I
I
I
A
I
I
I
I
I
A
I
R
R
R
R
A
I
A
I
I
I
I
I
I
I
A
R
R
R
A
A
A
A
I
I
I
A
A
A
I
I
I
I
I
A
A
A
A
A
A
R
A
A
A
A
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
A
I
I
I
I
I
R
R
I
I
I
I
I
I
F
I
R
I
R
A
A
A
A
A
R
A
R
R
A
R
A
A
R
R
A
A
A
A
A
A
A
R
T
R
I
I
I
I
I
I
Customer
Sales
F
A
A
A
I
I
I
Quality Assurance
Purchasing
R
I
R
R
R
I
R
A
R
A
I
Production
Simple Responsibilities Matrix Example
Program Manager
Design Engineering
Manufacturing Engineering
Responsibility
Element
A
A
A
A
I
A
I
Market Research Information
Quality History Review
Engineering Research Data
Advanced Quality Planning Schedule
Preliminary Product/Process Design
Feasibility Analysis
Design FMEA
Process FMEA
A
Prototype Build and Verification
A
Significant Characteristics
I
Final Product and Process Design
Measurement and Test Equipment Needs & Costs
A
Process Control Plan
I
Process Flow Chart
Audit and QA Work Instructions
Order Production Tooling, Gages, Test Equipment
Select & Rate Suppliers
Train Quality Personnel
Supplier PSW Review & Sign-Off
Set-Up & De-Bug Production and Inspection Equipment
Preliminary Capability Studies For Production Processes
Process Optimization (Design Of Experiments)
I
Process Review (PFMEA Walk Through)
Product Training
I
Work Instructions (Manufacturing)
I
Measurment and Test Equipment Verification
I
Packaging
A
Part Sample Warrant
A = Assistance
I = Input
R = Responsibility
F = Site 1
Advanced Product Quality Planning
Slide 26, Printed 10/12/98
T = Site 2
Training
Customer needs and expectations
Working as a Team
Group process skills
Development skills
Requirements of APQP
FMEA
APQP
PPAP
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 27, Printed 10/12/98
Recommended Statistical Courses
Basic Business
Advanced
Business
Office, Staff, &
Management
Selected Staff, &
Management
Statistical
Process Control
Production Floor,
Production Staff &
Management,
All of Quality
& Engineering
Measurement
System Analysis
Design of
Experiment
Production Staff &
Management,
All of Quality
& Engineering
Specific Production
Staff,
Quality Engineers&
QA Manager
& Product
Engineering
*Your APQP Team should attend as many classes as time will allow
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 28, Printed 10/12/98
Customer and Supplier Involvement
Customer may initiate the planning
process
Supplier has the obligation to establish
cross-functional team to manage
process
Supplier should expect the same
performance from their subcontractors
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 29, Printed 10/12/98
Simultaneous (Concurrent) Engineering
Requires cross-functional team participation
Replaces prior system of sequential phases
and pass-off (old method)
APQP team ensures that other functions and
teams plan and execute support activities
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 30, Printed 10/12/98
Customer Requirements
Ways to Determine Customer Requirements
Print
Purchase Request or Request for Quotation
QFD - Quality Function Deployment
Service Engineers
Verbal Communications
Development Engineers
Product Check List
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 31, Printed 10/12/98
Base Documentation
Critical Characteristics Matrix
Process Flow Diagram
Design FMEA
Process FMEA
Control Plan
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 32, Printed 10/12/98
Chicken or Egg
Which is First? Second? Third?
Control Plan?
Process Flow Diagram?
Design FMEA?
Process FMEA?
Process Documentation (Work Instructions)?
Why Does it Matter?
Relationship to Product Planning
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 33, Printed 10/12/98
Typical Automotive Trilogy Development
APQP Timeline
Process Flow Diagram
(Includes ALL Processes)
Process FMEA
(On ALL Processes)
Critical Characteristics
& Failure Effects Issues
Process Control Plan
Some Elements may
be Included On
(Critical Processes from FMEA)
Critical Characteristics
& Characteristic Control Issues
Design FMEA
(On Intended Use)
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 34, Printed 10/12/98
The Links
Each Flow Chart element must have a
matching FMEA element. As a trilogy,
remember - the links must all match.
The trilogy documents must precisely
link to your process documentation
(work instructions or however your company
addresses this issue)
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 35, Printed 10/12/98
One Document? Or More?
Manufacturing Entity
Receiving
Machine
or Cell 2
Machine or
Cell 1
Machine
or Cell 3
Pack
& Ship
Internal or
External
Customer
Segmented = By machine or cell
Device, Technology or Family = a flow of a technology or a device
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Receiving
Pack
& Ship
Slide 36, Printed 10/12/98
The Control Plan
A Control Plan is a written description of systems for parts and processes
Process Dominated
Prototype *A Design Output
Used During Prototype Build
Dimensional Measurements
Material and Performance Tests
Pre-Launch
Update After Prototype and Before Production
Production
Comprehensive
Process Controls
Test and Measurement Systems Used
Reaction Plan
Sampling Plans
SPC Requirements
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 37, Printed 10/12/98
QS9000:1996 - FMEAs
4.2.3 - Quality Planning
Process Failure Mode and Effects
Analysis (Process FMEAs)
Process FMEAs shall consider all special
characteristics. Efforts shall be taken to improve
the process to achieve defect prevention rather
than defect detection. Certain customers have
FMEA review and approval requirements that shall
be met prior to production part approval (see
customer specific pages). Refer to the Potential
Failure Mode and Effects Analysis reference
manual.
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 38, Printed 10/12/98
QS9000:1996 - Control Plans
4.2.3 - Quality Planning
The Control Plan
Suppliers shall develop Control Plans at the system,
subsystem, component and/or material level, as appropriate
for the product supplied.
The Control Plan requirement encompasses processes
producing bulk material (e.g., steel, plastic resin, paint) as
well as those producing parts.
The output of the advanced quality planing process, beyond
the development of robust processes, is a Control Plan.
Control Plans may be based on existing plans (for mature
products and capable processes). New plans are required
when products or processes differ significantly from those in
current production.
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 39, Printed 10/12/98
QS9000:1996 - Control Plans
4.2.3 - Quality Planning
The Control Plan (continued)
The Control Plan shall cover three distinct phases as appropriate:
Prototype - a description of the dimensional measurements and
material and performance tests that will occur during Prototype build.
NOTE: Prototype control plans may not be required from all suppliers.
Pre-launch - a description of the dimensional measurements and
material and performance tests that will occur after Prototype and
before full Production.
Production - a comprehensive documentation of product/process
characteristics, process controls, tests, and measurement systems that
will occur during mass production.
Suppliers shall establish cross-functional teams to develop Control Plans for
approval by the appropriate customer engineering and quality personnel
unless this approval requirement is waived by the customer. In some cases,
the customer will establish a cross-functional team to develop the Control
Plan.
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 40, Printed 10/12/98
Semiconductor Supplement
Quality Planning - 4.2.3.S
During the advanced quality planning processes, the supplier shall
include all processes from the incoming material through shipping
and warehousing
Failure Mode and Effects Analysis and Control Plan documents
shall include these processes.
The Intent:
The supplier shall *consider* all processes. But - does it mean that
all process shall be included in the FMEA and Control Plan?
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 41, Printed 10/12/98
APQP Manual : 1995
6.2 Overview
A control plan is a written description of the
system for controlling parts and processes
In effect, the Control Plan describes the actions
that are required at each phase of the process
including receiving, in-process, out-going, and
periodic requirements to assure that all process
outputs will be in a state of control
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 42, Printed 10/12/98
FMEA Manual : 1995
Process Potential FMEA
Is ...a summary of engineers/teams thoughts
(including an analysis of items that could go wrong
based upon experience and past concerns) as a
process is developed.
A process FMEA should begin with a flow chart/
risk assessment of the general process. This flow
chart should identify the product/c characteristics
associated with each operation.
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 43, Printed 10/12/98
Concern Resolution
Design or Process concerns
Responsibility matrix
Disciplined problem solving methods
Use analytical techniques (*as appropriate)
(See AIAGs APQP & Control Plan reference manual page 4 and appendix B, page 81)
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 44, Printed 10/12/98
Product Quality Planning Timing Chart
Concept
Initiation - Program
Approval Approval
Prototype
Planning
Design & Development
Planning
Pilot
Product
Process
Launch
Validation Product - Process
Production
Feedback Assessment & Corrective Action
Plan &
Define
Program
Product
Process Product &
Design & Design & Process
Dev.
Dev.
Validation
Verification Verification
AIAG APQP & Ctrl Plan Reference Guide, Page 5
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 45, Printed 10/12/98
Timing Plan
Depends upon
Product complexity
Customer expectations
Team plan for
Training
Event
Action
Do NOT Under Estimate the
Importance of Timing!
Framework for tracking
Basis for status reporting
Prepare a timing chart using available project or similar
software
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 46, Printed 10/12/98
Timing Plan Contents
Identify individual tasks
Track resources by task
Establishes dependencies between tasks
Determine critical path
Track specific tasks or groups of tasks
Status reports
ID
1
Task Name
Visit 1
Dur
5d
Start
4/28/97
Finish
5/2/97
April
May
June
July
August
September
Apr
May
Jun
Jul
Aug
Sep
Plant Tour and Gather Information
2d
4/28/97
4/29/97
100%
Meet with Teams
2d
4/28/97
4/29/97
100%
Feasibility Determination
2d
5/1/97
5/2/97
Initial Project Plan Developed
1d
5/2/97
5/2/97
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
100%
Advanced Product Quality Planning
Slide 47, Printed 10/12/98
Project Plan Elements
Mission
Scope
Objectives
How to measure
Consider this a laundry list for an
index.
Requirements
Definitions and specifications
Market analysis
Feasibility
Time
Resources
Plant space
Etc.
Each item does not, however, have
to reside in one book.
You should have (at least) an index
of the project plan with the
location and owner (responsibility)
of each element clearly identified.
Timeline
Control system
Team
Cost Estimate
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 48, Printed 10/12/98
Project Plan Definitions
Mission - Goal, customer and approach
Scope - What will and will not be included (with
consideration to available technology)
Objectives - Technical, profit, performance, quality, etc.
Requirements - Deliverables
Definition and specification - Criteria it must meet
Market analysis - Expected annual production volume,
length of run, start (delivery) target date, target price (Japan),
key sales points, key competitors, etc.
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 49, Printed 10/12/98
Project Plan Definitions (continued)
Preliminary Feasibility - Degree to which current tooling and
equipment can be used
Timeline - Major milestones and detail task schedule
Control system - Answers questions such as:
How will progress be measured?
Who will receive reports?
How are changes handled?
What limits are there on authority, responsibility, and
accountability?
Team - Who, from where and who is the team leader?
Beware of Turf Wars!
Cost estimate - Estimate with assumptions. Often all information is
not available.
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 50, Printed 10/12/98
Project Plan Summary Sheet
Broad
Project #
Title
Customer
Model/Year
Part #
Date
Project Mission
Project Scope
Project Objectives
Contractural Requirements
Product Definition & Spec.
Current Capability
Timeline
Control System
Team Definition
Specific
Prelim. Cost Estimate
Project vs D&D (Design & Development)
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 51, Printed 10/12/98
Analytical Techniques
Assembly Build Variation Analysis
Benchmarking
Cause & Effect Diagram
Characteristics Matrix
Critical Path Method
Design of Experiments (DOE)
Design for Manufacturability & Assembly (DFM & DFA)
Design Verification Plan & Report (DVP&R - Chrysler & Ford)
Dimensional (Dynamic) Control Plan (DCP)
Mistake Proofing (Poka-Yoke)
Process Flow Charting
Quality Function Deployment (QFD)
System Failure Mode & Effects Analysis (SFMEA)
See AIAGs APQP & Control Plan reference manual appendix B, pages 81 thru 85
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 52, Printed 10/12/98
APQP Phases
Phase 1: Plan & Define Program
Phase 2: Product Design & Development Verification
Phase 3: Process Design & Development Verification
Phase 4: Product & Process Validation
Phase 5: Feedback Assessment & Corrective Action
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 53, Printed 10/12/98
APQP Phase 1:
Plan and Define Program
Concept
Initiation - Program
Approval Approval
Planning
Planning
Design & Development
Product
Process
Validation Product - Process
Production
Feedback Assessment & Corrective Action
Plan &
Define
Program
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 54, Printed 10/12/98
Phase 1 Inputs
Voice of the Customer
Business Plan and Marketing Strategy
Product/Process Benchmark Data
Product/Process Assumptions
Product Reliability Studies
Customer Inputs
Service
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 55, Printed 10/12/98
Voice of the Customer
Market research
Historical warranty and quality information
Team experience
Complaints
Recommendations
Data and/or other information
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 56, Printed 10/12/98
Voice of the Customer
External and
Internal
Customers
Stated, Real and
Perceived
Needs
Cultural Needs
Unintended
Uses
Functional
Needs vs.
Technical
Features
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 57, Printed 10/12/98
Market Research
Customer
interviews
Customer
questionnaires
and surveys
Marketing test
and positioning
reports
New product
quality and
reliability studies
Competitive
product quality
studies
Things Gone
Right reports
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Things Gone Right
The following is a list of vehicle features. Please read the entire list and place
an X next to those features of your new vehicle that you Particularly Like.
Room & Comfort
Interior Appearance
Front Room
Seat Appearance
Front Seat Comfort
Instrument Panel
Entry & Exit from Front
Door Panels
Cargo Capacity
Carpeting
Cargo loading, unloading
Exterior Appearance
Front View
Side View
Rear View
Paint
Moldings
Advanced Product Quality Planning
Handling
Handling on Highway
Handling in City, Parking
Visibility in Rear
Steering
Brakes
Slide 58, Printed 10/12/98
Historical Warranty and Quality Information
Things Gone Wrong
Things gone
Tell us about any troubles you have had with the vehicle. Mark a X in each
Wrong reports
box next to any item you have had trouble with.
Warranty reports
Exterior Paint
Capability
Paint mist or soray over body finish
Chipped paint
indicators
Color difference between body panels
Scratched paint
Uneven color on one body panel
Sags, runs in paint
Supplier plant
Paint ot tape stripes coming off, missing
Dirt in paint
internal quality
Rust, corrosion
Body paint on moldings, ornaments
Other paint troubles. Please describe.
reports
Problem
Steering & Handling
resolution reports
Steering noisy
Steering requires high or uneven effort
Customer plant
Constant pull to one side
returns and
Vehicle vibrates at speeds
Below 45 MPH
Above 45 MPH
Steering wheel spokes not correctly positioned when front wheels streight
rejections
Other steering and handling problems. Please describe.
Field return
product analysis
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 59, Printed 10/12/98
Team Experience
Input from higher system level or past
QFD projects
Media commentary and analysis
Customer letters and suggestions
Things gone Right/Wrong reports
Dealer comments
Fleet operator comments
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 60, Printed 10/12/98
Team Experience (continued)
Field service reports
Problems and issues reported from Internal
customers
Internal evaluations using surrogate customers
Road trips (e.g.: Struts)
Management comments and/or direction
Government requirements and/or regulations
Contract review
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 61, Printed 10/12/98
Business Plan - Marketing Strategy
Framework for quality plan
May place constraints on timing, cost, investment, positioning,
R&D resources
Strategy defines target customer, key sales points, key
competitors
SWAT
Strengths
Weaknesses
Opportunities
Threats
Old vs. New
How deep and how far to go
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 62, Printed 10/12/98
Product - Process Benchmark Data
A requirement of QS 9000 para. 4.1
Provides inputs to establish performance targets
Must address key process(es)
Must be measurable
Methods for successful benchmarking:
Identify appropriate benchmark(s)
Find reason for gap between your status and benchmark
Develop a plan for closing gap, meeting or exceeding
benchmark
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 63, Printed 10/12/98
Product - Process Assumptions
Assumptions
Features
Design
Process concepts
Technical innovations
Advanced materials
Reliability assessments
New technology
Document assumptions as part of project plan
Utilize as inputs to plan
Consider alternate paths in case assumptions do not play out
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 64, Printed 10/12/98
Product Reliability Studies
Frequency of repairs or replacements within
designated time period(s)
Repair or Throw-away?
LRU Level (Line Replaceability Unit)
Long range reliability and/or durability tests
Studies can be VERY costly and lengthy
EDCTP (Environmental Design Criteria Test Plan)
Failures
Market
Share
Durability
MTBR = Mean Time Between Replacement
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
MTBO = Mean Time Between Overhaul
MTBF = Mean Time Between Failures
Advanced Product Quality Planning
Slide 65, Printed 10/12/98
Customer Inputs
Next users provide information about
needs and expectations
Possibility of previous conducted
reviews and studies
Used to develop measure of customer
satisfaction
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 66, Printed 10/12/98
Phase 1 Project Review
Project #
Model/Year
Title
Part #
Customer
Date
Our advanced quality planning team has considered the following questions in Phase 1
of our APQP process. The documents provided have been used as a basis for analyzing
the ability to meet all specified requirements. All 'NO' answers are supported with attached
comments identifying our concerns and/or proposed changes to enable us to meet
specified requirements.
Yes
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
No
Checklist Item
Has historical data and experience concerning customer needs been considered?
Has full consideration been given to the overall business plan and marketing strategy?
Have product/process benchmark data been considered?
Have the product/process assumptions been identified and challanged?
Have product reliability studies been conducted?
Have there ben appropriate customer inputs into the process?
Do the design goals reflect the data generated?
Do the quality and reliability goals reflect appropriate standards?
Is the preliminary bill of materials sufficiently thorough?
Does the preliminary process flow chart relate to the primary BOM and
product/process assumptions?
Are all special product and process characteristics lited?
Does the produxct assurance plan include and outline of program requirements, goals,
factors that may place the program at risk, FMEA, and preliminary enginering
standards requirements?
Feasible
Feasible
Not Feasible
Product can be produced as specified with no revisions.
Changes recommended (See attached)
Design revision required to produce product within specified requirements
Team Member/Title/Date
Team Member/Title/Date
Team Member/Title/Date
Team Member/Title/Date
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
This form is Slide
on course
disk 10/12/98
67, Printed
MIS
Materials
Maintenance
HR
Production
Sales
Laboratory
Quality
Engineering
Purchasing
Phase 1: Plan and Define Program
Management
Phase 1 Responsibility Matrix
Output
Design Goals
Reliability and Quality Goals
Preliminary BOM
Preliminary process flow chart
Preliminary list of special product and
process characteristics.
Product assurance plan
Management Support
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
This form is on course disk
Slide 68, Printed 10/12/98
APQP Phase 2:
Product Design and Development
Program
Approval
Prototype
Planning
Planning
Design & Development
Product
Process
Validation Product - Process
Production
Feedback Assessment & Corrective Action
Product
Design &
Dev.
Verification
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 69, Printed 10/12/98
Outputs by Design Responsible Activity
Design FMEA
DFM and DFA
Design for Manufacturability
Design for Assembly
Design Verification
Design Reviews
Prototype Build - Control Plan
Engineering Drawings (including Math data)
Engineering Specifications
Material Specifications
Drawing and Specification Changes
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 70, Printed 10/12/98
Additional Outputs by Design Responsible Activity
Updated special characteristics list
Prototype parts build
Make - Buy decisions
Parts inspection
Assembly of prototype(s)
Preferably manufacturing, not model shop
Inspection layout
Prototype validation testing
Redesign as required and design review
Update DFMEA (and System Level FMEA if appropriate)
Feasibility report
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 71, Printed 10/12/98
FMEAs
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 72, Printed 10/12/98
DFMEA
Disciplined analytical tool
Assess probability of failure
Effect of failure
Must be continually updated
Causes changes and/or additions to previously
selected special product and/or process
characteristics
If you do not have design control, you MUST (should)
have customer DFMEA
Check list (AIAG APQP Manual Appendix A-1)
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 73, Printed 10/12/98
Design, concept,
function and
sensitivity
(tolerancing) to
manufacturing
variation
Manufacturing
and/or assembly
process
Dimensional
tolerances
DFM and DFA
Performance
requirements
Number of
components
(complexity)
Process
adjustments
Material
handling
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 74, Printed 10/12/98
Design Verification
Inspection methods
Testing methods
Ensure that all design outputs meet
design input requirements
Alternate calculations
CAD/math data
Review design stage documents before release
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 75, Printed 10/12/98
Design Reviews - Evaluations
Design/functional requirement(s) and considerations
Formal reliability and confidence goals
Component/subsystem/system duty cycles
Computer simulation and bench test results
DFMEA(s)
Review of the DFM and DFA
Design of experiments (DOE) and assembly build
variation results
Test failures
Design verification progress
Max/Min builds
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 76, Printed 10/12/98
Design Review Tracking
Track verification progress using a
design verification plan and report (DVP&R
- Ford & Chrysler)
Product/process validation of
components
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 77, Printed 10/12/98
Process Flow Diagram Example
Process Flow Diagram
Inspect
Store
Move
Step
Fabrication
Part Number:
Part Description:
Prepared By:
Date: 4/5/93
Rev. : C
Approved By:
QA Manager
Operations Manager
Senior Advisor
QA Engineer
Operation Description
Item #Key Product Characteristic
Item #
Key Control Characteristic
Move "OK" Vinyl Material
From Storage Area and
Load Into Press.
1.0
Material Specs
1.0
Material Certification Tag
Auto Injection Mold Cover
In Tool #
2.0
Tearstrip In Cover
2.1
2.2
Tool Setup
Machine Setup
3.0
Hole Diameter In Cover
2.1
2.2
Tool Setup
Machine Setup
4.0
Flange Thickness In Cover
2.1
2.2
Tool Setup
Machine Setup
5.0
Pressure Control Protrusions
Height
2.1
2.2
Tool Setup
Machine Setup
6.0
Pressure Control Protrusions
Filled Out
2.1
2.2
Tool Setup
Machine Setup
7.0
Cover - Flash Free
8.0
Cover Filled Out
9.0
Free Of Foreign Material
2.1
2.2
2.1
2.2
2.2
Tool Setup
Machine Setup
Tool Setup
Machine Setup
Machine Setup
Visually Inspect Cover
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 78, Printed 10/12/98
PFMEA Example
Process Failure Mode And Effects Analysis
Process:
Low - High
Outside Suppliers Affected:
Engineer:
Primary Process Responsibility:
Model Year/Vehicle(s):
Part Number:
Other Div. Or People Involved:
Scheduled Production Released:
PFMEA Date:
Quality Assurance Manager
Quality Assurance Engineer
Take TPPE
Material Held In
Storage Area
Fragmented Container
Insufficient Supplier Control
Unpredictable Deployment
Improper Handling
Misidentified Material
Material Certification
18
10
90
Actions
Taken
RPN
Recommended
Actions And Status
Detection
Current Controls
Severity
Potential Cause Of Failure
RPN
Wrong Material
SIR
Container
Potential Effects Of Failure
Detection
Potential Failure
Mode
Severity
Process Function
Senior Advisor
Occured
Operations Manager
Part Name
Operation
Number
Rev.
Occured
Approvals:
1 - 10
Responsible
Activity
Required With Each
Shipment
Release Verification
Out Of Spec
Material
Contaminated
Fragmented Container
Supplier Material
Visual Inspection
63
Fragmented Container
Engineering Change
Release Verification
10
70
Unpredictable Deployment
Supplier Change
Fragmentation
Untrained LTO
10
50
10
30
Unpredictable Deployment
Material
Change
2
Move To
Unreleased
Periodic Audit Of
Open Boxes
Fragmented Container
Material
Composition
Supplier Process Control
Unpredictable Deployment
Green "OK" Tag
Customer Notification
Approved
Untrained Personnel
Storage
Check For Green "OK"
Tag At Press
Trace Card
Check List
Training
Hold In Approved
Storage Until
Contamination
Fragmentation
Open Containers
Process Problems
Housekeeping
Needed
Area Maintenance
Boxes Kept In Sealed
Storage Area Until
Needed
Boxes Lined With
Plastic
Liner On Pallets
Inside Storage
P. M. Facility
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 79, Printed 10/12/98
Prototype Build Control Plan
A description of the dimensional
measurements
Material tests
Functional tests that will occur during prototype
build
Depending upon product complexity, several
prototype builds may be necessary and may
require updates to the control plan
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 80, Printed 10/12/98
Standard Control Plan Example
Control Plan Number
Key Contact / Phone
Date (Orig.)
Part No./ Latest Change No.
Core Team
Customer Engineering Approval/Date
Part Name/Description
Supplier/Plant Apoproval/Date
Customer Quality Approval/Date
Other Approval/date (If Req'd)
Other Approval/date (If Req'd)
Supplier/Plant
Supplier Code
Characteristics
Process Name/
Part/
Process
Operation
Number
Description
Machine,
Device,
Jig, Tools
for Mfg.
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
No.
Product
Process
Date (Rev.)
Methods
Special
Char.
Class
Product/
Process
Spec/
Tolerance
Evaluation
Measurement
Technique
Size
Advanced Product Quality Planning
Frequency
Control
Method
Reaction
Plan
This form is onSlide
course
81,disk
Printed 10/12/98
Fords Dimensional Control Plan (DCP)
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 82, Printed 10/12/98
Control Plan Example (GM)
Process Control Plan
Supplier Name:
Supplier Rep.:
Supplier Code:
Telephone:
Title:
Part Number:
Part Description:
Date: 4/5/93
Key Product Control Characteristics
Engineering Change Letter:
Process Plan Effective Date: 4/5/93
Process Capability
Process Performance
(Short Term Capability)
(Long Term Capability)
[1]
[2]
[3]
[4]
[5]
[6]
[7]
[8]
[9]
[10]
[11]
[12]
[13]
[14]
[15]
Item Key Product Key Control Operation
Gage
Attr./ Last R&R % Gage Process
% Process
Cpk or Dev Process % ProcessCpk or Dev Type Of
Characteristic/CharacteristicsDescription Operation Variable
Date
R&R Capability
Capability
From
Perform. Perform
From
Control
Spec
Date
Target/Nom. Date
Target/Nom. Method
1.0
Vinyl Material
Spec
2.0
Tear Strip
(Cover)
1 = 0.41mm
.+/- 0.11mm
Gage Study
Auto
Injection
Mold
Cover
In TL#
2-7 = 0.685mm
.+/- 0.135mm
[7]
2.1
2.2
3.0
[1]
[2]
[3]
[4]
[5]
[6]
[7]
[1]
[2]
[3]
[4]
[5]
[6]
[7]
Tool Setup
Machine
Setup
Hole Diameter
(Cover)
4.60mm
.+/- 0.25mm
Auto
Injection
Mold Cover
TL#
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
[1]
[2]
[3]
[4]
[5]
[6]
[1]
[2]
[3]
[4]
[5]
[6]
Advanced Product Quality Planning
Controls
[16]
Freq. Of
Inspect.
Check
Every
Vendor
Box
Cert(s).
X bar and Start Of
R Charts Each Run
And Each
SQC
Shift
Database
Verify To
Spec
Sheet
X bar and 5 Pieces
R Charts Every 6
Months
SQC
Database
[17]
[18]
Operator
Process
Set-Up
Audit
Gage
Method
Instruction
and
(Proced. #) Frequency
Green "OK"
Release,
Each Box
3.607
3.609
This form is on course disk
Slide 83, Printed 10/12/98
Prototype Build
Make -buy decisions
Part inspections
Assemble prototypes
Perform layout inspection
Validation testing (Who will do testing?)
Redesign as required
Update DFMEA and SFMEA if required
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 84, Printed 10/12/98
Customer or Supplier Engineering Drawings
(including math data)
Review for special and/or critical characteristics
Review controlling drawings when engineering drawings
are nonexistent
Review drawings for:
Dimensions for form, fit, function, durability, government S&R
Control or datum surfaces/locators for function gages and
equipment
Feasibility/compatibility with industry standards
Compatibility of math data with two-way communications
(Written waivers acceptable)
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 85, Printed 10/12/98
Customer or Supplier Engineering Specifications
Review and understand controlling specifications
Identify functional, durability and appearance
requirements
Should define:
Sample size
Frequency
Acceptance criteria
Otherwise, determined by supplier and included in
control plan
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 86, Printed 10/12/98
Material Specifications
Review material specifications for
special characteristics
Physical properties
Performance
Environmental
Handling
Storage
Include in Control Plan
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 87, Printed 10/12/98
Drawing and Specifications Changes
Change control requirement applies
Ensure proper communication
QS 9000 Element 4.5 Document and data
Control applies (requires a Change Control system)
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 88, Printed 10/12/98
APQP Team Outputs
New equipment, tooling and facilities
requirements
Special product and process characteristics
Gage and testing equipment requirements
Team feasibility commitment and management
support
Subcontractor build
Supplier build
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 89, Printed 10/12/98
New Equipment, Tooling and Facilities Requirements
Preliminary identification of new equipment, tooling
and facilities
Address these items on the timing chart
Address capability requirements
Establish delivery times
Complete check list in AIAG APQP & Control Plan reference manual
Appendix A-3
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 90, Printed 10/12/98
Special Product and Process
Characteristics List
Upgrade preliminary list started in Phase 1 from
information gathered through review and
development of design features
Additional sources
DFMEA
SFMEA if applicable
PFMEA
Previous history
These may overlap
Must be on control plans for prototype, pre-launch
and production
Listing should be a team consensus
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 91, Printed 10/12/98
Gage and Testing Equipment Requirements
Preliminary identification of inspection, test and
measurement equipment
Requirements on timing chart
Complete in time to conduct measurement
systems analysis
Equipment builder
Pilot build
Production trial run
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 92, Printed 10/12/98
Team Feasibility, Commitment and Management Support
Team feasibility commitment
Complete program review check list, including:
Design feasibility
Can be manufactured, assembled, tested and packaged
Can be delivered in the right quantities on schedule at acceptable cost
Review design information check list in AIAG APQP Reference manual Appendix A-2 as part of
feasibility inputs
Open issues that require resolution with assigned responsibility and
timing.
Management Support
Report project status to management
Recommend continue or drop project depending on feasibility
Cover open issues and concerns
Management support as required
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 93, Printed 10/12/98
Subcontractor Pilot Build
Supplier participated, if appropriate
Sample quantity required
Check that it is according to:
Work instructions
Control plan
Where to be produced
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 94, Printed 10/12/98
Supplier Pilot Sample Build
Parts availability
Tooling and equipment availability
Measurement equipment availability
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 95, Printed 10/12/98
MIS
Materials
Maintenance
HR
Production
Sales
Laboratory
Quality
Engineering
Purchasing
Phase 2: Product Design and Development
Management
Phase 2 Responsibility Matrix
Output
DFMEA
DFM / DFA
Design Verification
Design Reviews
Prototype Build
Engineering Drawings (inc. math data)
Engineering Specifications
Material Specifications
Drawing / Specification Changes
New Equipment, Tooling, Facilities Requirements
Special Product & Process Characteristics
Prototype Control Plan
Gages / Testing Equipment Requirements
Team Feasibility Committment
Management Support
Subcontractor Built
Supplier Build
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
This form is on course disk
Advanced Product Quality Planning
Slide 96, Printed 10/12/98
Phase 2 Project Review
Project #
Model/Year
Title
Part #
Customer
Date
Our advanced quality planning team has considered the following questions in Phase 2
of our APQP process. The documents provided have been used as a basis for analyzing
the ability to meet all specified requirements. All 'NO' answers are supported with attached
comments identifying our concerns and/or proposed changes to enable us to meet
specified requirements.
Yes
1.
2.
3.
4.
5.
6.
6a
6b
6c
7.
8.
8a
8b
No
Checklist Item
Is the product adequately defined (application requiremetns, etc.) to enable
feasibility evaluation?
Can engineering performance specifications be met as written?
Can product be manufactured to tolerances specified on the drawing?
Can product be manufactured with Cpks which meet requirements?
Is there adequate capacity to produce product?
Can the product be manufactured without incurring any unusual:
Costs for tooling?
Costs for capital equipment?
Alturnate manufacturing methods?
Is Statistical Process Control required on the product?
Where Statistical Process Control is used on similar product?
Are the processes in control and stable?
Are Cpks greater than 1.33?
Feasible
Feasible
Not Feasible
Product can be produced as specified with no revisions.
Changes recommended (See attached)
Design revision required to produce product within specified requirements
Team Member/Title/Date
Team Member/Title/Date
Team Member/Title/Date
Team Member/Title/Date
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
This form is on course disk
Advanced Product Quality Planning
Slide 97, Printed 10/12/98
APQP Phase 3:
Process Design and Development
Prototype
Planning
Design & Development
Pilot
Planning
Product
Process
Validation Product - Process
Production
Feedback Assessment & Corrective Action
Process
Design &
Dev.
Verification
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 98, Printed 10/12/98
Typical Design Responsibility Outputs
DFMCA
DFM/DFA
DV
Design Reviews
Prototype Build
Engineering Drawings
Engineering Specifications
Material Specifications
Drawing and Specification Changes
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 99, Printed 10/12/98
Typical APQP Team Outputs
New Equipment
Facilities
Etc.
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 100, Printed 10/12/98
Process Design and Development Outputs
Packaging standards
Product and process quality system review
Process flow chart
Floor plan layout
Characteristics matrix
PFMEA
Pre-launch control plan
Process instructions
Measurement systems analysis plan
Preliminary process capability study plan (Typically 100 Parts)
Management support
Additional Outputs
Update tooling, equipment and facilities list
Update process flow chart
Update PFMEA
Quote in-house gages, tooling and equipment
Order gages, tooling and equipment
Delivery of gages in time for MSA plan
Delivery of equipment
Must consider approval at equipment subcontractor, in-house installation, debugging and process potential studies (runoff)
Subcontractor pilot build
Supplier pilot build
Salable units?
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 101, Printed 10/12/98
Packaging Standards
From customer
Developed during prototype or prelaunch runs
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 102, Printed 10/12/98
Product and Process Quality System Review
Team must review existing quality systems manual to
ensure that changes resulting from APQP (if any) are
reflected
Must comply with QS 9000
Changes must be reflected in control plan
Reference AIAG APQP Reference manual Appendix A-4 check list
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 103, Printed 10/12/98
Process Flow Chart
Update process flow chart
(Example in AIAG APQP Reference manual Appendix A-6)
Describes current or proposed process flow
Used to analyze sources of variation
Helps analyze total process
Needed for process FMEA, characteristics matrix and control
plan
Reference AIAG APQP Reference manual Appendix A-6 check list
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 104, Printed 10/12/98
Process Flow Diagram Example
Process Flow Diagram
Inspect
Store
Move
Step
Fabrication
Part Number:
Part Description:
Prepared By:
Date: 4/5/93
Rev. : C
Approved By:
QA Manager
Operations Manager
Senior Advisor
QA Engineer
Operation Description
Item #Key Product Characteristic
Item #
Key Control Characteristic
Move "OK" Vinyl Material
From Storage Area and
Load Into Press.
1.0
Material Specs
1.0
Material Certification Tag
Auto Injection Mold Cover
In Tool #
2.0
Tearstrip In Cover
2.1
2.2
Tool Setup
Machine Setup
3.0
Hole Diameter In Cover
2.1
2.2
Tool Setup
Machine Setup
4.0
Flange Thickness In Cover
2.1
2.2
Tool Setup
Machine Setup
5.0
Pressure Control Protrusions
Height
2.1
2.2
Tool Setup
Machine Setup
6.0
Pressure Control Protrusions
Filled Out
2.1
2.2
Tool Setup
Machine Setup
7.0
Cover - Flash Free
8.0
Cover Filled Out
9.0
Free Of Foreign Material
2.1
2.2
2.1
2.2
2.2
Tool Setup
Machine Setup
Tool Setup
Machine Setup
Machine Setup
Visually Inspect Cover
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 105, Printed 10/12/98
Floor Plan Layout
Determine acceptability of inspection and test points
Control chart location(s)
Visual aides
Interim repair stations
(rework)
Nonconforming material storage
Keyed to material flow and control plan
Reference AIAG APQP Reference manual Appendix A-5
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 106, Printed 10/12/98
Characteristics Matrix
Displays relationship between:
Process parameter
Manufacturing stations
Reference AIAG APQP Reference manual Appendix B, page 82
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 107, Printed 10/12/98
Process FMEA
To the extent possible, potential failure modes
have been considered and addressed
May be started after design FMEA in Phase 2
Needs to be updated regularly
Must be done prior to committing new tools and
equipment
Living document
Typically started too late!
Reference AIAG APQP Reference manual Appendix A-7
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 108, Printed 10/12/98
Automotive Process FMEA
Process Failure Mode And Effects Analysis
Process:
Low - High
Outside Suppliers Affected:
Engineer:
Primary Process Responsibility:
Model Year/Vehicle(s):
Part Number:
Other Div. Or People Involved:
Scheduled Production Released:
PFMEA Date:
Quality Assurance Manager
Quality Assurance Engineer
Take TPPE
Material Held In
Storage Area
Fragmented Container
Insufficient Supplier Control
Unpredictable Deployment
Improper Handling
Misidentified Material
Material Certification
18
10
90
Actions
Taken
RPN
Recommended
Actions And Status
Detection
Current Controls
Severity
Potential Cause Of Failure
RPN
Wrong Material
SIR
Container
Potential Effects Of Failure
Detection
Potential Failure
Mode
Severity
Process Function
Senior Advisor
Occured
Operations Manager
Part Name
Operation
Number
Rev.
Occured
Approvals:
1 - 10
Responsible
Activity
Required With Each
Shipment
Release Verification
Out Of Spec
Material
Contaminated
Fragmented Container
Supplier Material
Visual Inspection
63
Fragmented Container
Engineering Change
Release Verification
10
70
Unpredictable Deployment
Supplier Change
Fragmentation
Untrained LTO
10
50
10
30
Unpredictable Deployment
Material
Change
2
Move To
Unreleased
Periodic Audit Of
Open Boxes
Fragmented Container
Material
Composition
Supplier Process Control
Unpredictable Deployment
Green "OK" Tag
Customer Notification
Approved
Untrained Personnel
Storage
Check For Green "OK"
Tag At Press
Trace Card
Check List
Training
Hold In Approved
Storage Until
Contamination
Fragmentation
Open Containers
Process Problems
Housekeeping
Needed
Area Maintenance
Boxes Kept In Sealed
Storage Area Until
Needed
Boxes Lined With
Plastic
Liner On Pallets
Inside Storage
P. M. Facility
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 109, Printed 10/12/98
Pre-launch Control Plan
Description of dimensional measurements, materials
and functional tests
Adds additional product and/or process controls
Purpose is to contain potential nonconformities
utilizing:
More frequent inspections and/or tests
More in-process and final inspection and/or check points
Statistical evaluations
Increased audits
Reference AIAG APQP Reference manual Appendix A-8 check list
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 110, Printed 10/12/98
Automotive Control Plan
Control Plan Number
Key Contact / Phone
Date (Orig.)
Part No./ Latest Change No.
Core Team
Customer Engineering Approval/Date
Part Name/Description
Supplier/Plant Apoproval/Date
Customer Quality Approval/Date
Other Approval/date (If Req'd)
Other Approval/date (If Req'd)
Supplier/Plant
Supplier Code
Characteristics
Process Name/
Part/
Process
Operation
Number
Description
Machine,
Device,
Jig, Tools
for Mfg.
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
No.
Product
Process
Date (Rev.)
Methods
Special
Char.
Class
Product/
Process
Spec/
Tolerance
Evaluation
Measurement
Technique
Size
Advanced Product Quality Planning
Frequency
Control
Method
Reaction
Plan
Slide 111, Printed 10/12/98
Process Instructions
Work instructions for operating personnel
Sources:
FMEAs
Control plans
Engineering drawings and specifications
Material specifications
Visual standards
Industry standards
Process flow chart
Floor plan layout
Characteristic matrix
Packaging standards
Process parameters
Producer expertise
Handling requirements
Operators of process
Accessible operators
Include set-up parameters
Reference QS 9000 Element 4.9 Process Control
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 112, Printed 10/12/98
Measurement Systems Analysis Plan Ensures Gage:
Linearity
Accuracy
Repeatability
Reproducibility
Correlation for duplicate gages
Gages may be needed prior to gage sign-off at subcontractor plant or any inhouse pilot runs
Material
Inspector
Sample
Collection
Methods
Test Method
Training
Sample
Preparation
Workmanship
Parallax
Practice
Samples
Reproducibility
Ergonomics
Standards
Measurement
Discrimination
Vibration
Bias
Repeatability
Calibration
Linearity
Instrument
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Temperature
Lighting
Humidity
Environment
These are some of the variables in a
measurement system. What others can
you think of?
Advanced Product Quality Planning
Slide 113, Printed 10/12/98
Measurement Precision
Indicates
Poor
Precision
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 114, Printed 10/12/98
Measurement Bias & Repeatability
Precise
Imprecise
Accurate
Inaccurate
Bias
You can correct for Bias
You can NOT correct for Imprecision
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 115, Printed 10/12/98
Preliminary Process Capability Study Plan
Must include characteristics identified in control
plan
Few characteristics for simple component
Many characteristics for complex product with
many parts
Reference AIAG Fundamental SPC Reference Manual
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 116, Printed 10/12/98
Packaging Specifications
For individual products
Customer packaging
Generic standards where appropriate
Must ensure delivery quality
Compatible with all material handling
equipment used
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 117, Printed 10/12/98
Additional Phase 3 Outputs
Updated equipment, tools and facility lists
Updated process flow chart, PFMEA and control plan
Quotes for in-house tooling, equipment and gages
Selection of potential new subcontractors
Quote and delivery of gages in time for MSA plan
Equipment build and runoffs
Generation of a subcontractor pilot build
Generation of a supplier pilot build
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 118, Printed 10/12/98
Updated Tool, Equipment and Facilities Lists
Information from PFMEA and other sources
Address on timing chart
Address capability requirements
Reference AIAG APQP Reference manual Appendix A-3 check list
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 119, Printed 10/12/98
Quoting In-House Tooling, Equipment and Gages
Delivery timing for pilot build or production trial run
Include capability requirements
Include trial run/runoff/prove-out requirements
Gage delivery for MSA plan and runoff
Reference AIAG APQP Reference manual Appendix A-3
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 120, Printed 10/12/98
Selecting Potential New Subcontractors
Responsible for planning, tracking and
follow-up for subcontracted work
Provide technical resources for tool and
gage design, fabrication and full
dimensional inspection
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 121, Printed 10/12/98
Subcontractor Pilot Sample Build
Supplier participation, if appropriate
Build sample quantity required
Machine trial runs
Pilot run(s)
In accordance with appropriate work
instructions
In accordance with control plan
Production tooling and equipment, if possible
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 122, Printed 10/12/98
Supplier Pilot Build
Provide for customer participation, if
specified
have process instructions in place
Have control plan in place
Provide required quantity
Complete MSA
Generate required documentation as
planned
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 123, Printed 10/12/98
Project Review III
Include in control plan
Manufacturing locations quality system
manual should be reviewed
Procedures and control plans to be
updated to reflect changes
Last chance to eliminate problems
before ramp-up
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 124, Printed 10/12/98
MIS
Materials
Maintenance
HR
Production
Sales
Laboratory
Quality
Engineering
Purchasing
Phase 3: Process Design & Development
Management
Phase 3 Responsibility Matrix
Output
Packaging Standards
Product/Process Quality System Review
Process Flow Chart
Floor Plan Layout
Characteristics Matrix
PFMEA
Pre-Launch Control Plan
Process Instructions
Measurement Systems Analysis Plan
Preliminary Process Capability Study Plan
Packaging Specifications
Management Support
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
This form is on course disk
Advanced Product Quality Planning
Slide 125, Printed 10/12/98
Phase 3 Project Review
Project #
Model/Year
Title
Part #
Customer
Date
Our advanced quality planning team has considered the following questions in Phase 3
of our APQP process. The documents provided have been used as a basis for analyzing
the ability to meet all specified requirements. All 'NO' answers are supported with attached
comments identifying our concerns and/or proposed changes to enable us to meet
specified requirements.
Yes
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
No
Checklist Item
Does packaging design ensure product integrity at point of use and meet customer specs?
Is the product process quality checklist completed for the system review?
Does the process flow chart indicate any problems with the process?
Does the floor plan checklist indicate any problems with the aceptability of inspection
points, control chart locations, applicability of visual aids, interim repair stations, and
storage area to contain defective materials?
Is a characteristics matrix appropriate and has one been constructed?
Does the process FMEA check list indicate any problems and is there a system for
periodic review of the PFMEA?
Does the control plan check list indicate that all dimensional requirements, material, and
functional tests that will occur after the prototype, and before full production, are included?
Are clear process instructions in appropriate detail and are they cross-referenced to all
appropriate sources?
Does the measurement systems analysis plan include responsibility to ensure gage linearity,
accuracy, repeatrability, reproducability, and correlation for duplicate gages?
Has the preliminary process capability study plan been completed?
Do the packaging specifications resulting from the packaging design assure that product
performance and characteristics will remain unchanged during packing, transit, unpacking,
and will it have compatability with all material handling equipment, including robots?
Feasible
Feasible
Not Feasible
Product can be produced as specified with no revisions.
Changes recommended (See attached)
Design revision required to produce product within specified requirements
Team Member/Title/Date
Team Member/Title/Date
Team Member/Title/Date
Team Member/Title/Date
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
This form is on course disk
Advanced Product Quality Planning
Slide 126, Printed 10/12/98
APQP Phase 4:
Product and Process Validation
Planning
Design & Development
Planning
Pilot
Product
Launch
Process
Validation Product - Process
Production
Feedback Assessment & Corrective Action
Product &
Process
Validation
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 127, Printed 10/12/98
Phase 4 Outputs
Production trial run
Measurement system evaluation (complete)
Preliminary process capability study
Production part approval
Production validation testing
Packaging evaluation
Production control plan
Quality planning sign-off and management support
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 128, Printed 10/12/98
Production Trial Run
Production tooling, equipment,
environment, facilities and cycle time
Process instructions and control plans
Minimum quantity set by customer
(Can be increased by team)
Generally 300 parts
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 129, Printed 10/12/98
Production Trial Run Product Used For:
Preliminary process capability studies
MSA (if not completed earlier)
Final feasibility
Process review
Production validation testing
PPAP
Packaging evaluation
First time capability
Quality planning sign-off
Design changes (if required)
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 130, Printed 10/12/98
Measurement Systems Analysis (MSA)
Complete studies as defined in the MSA
plan
Minimum are those identified in the
control plan
Subjected to evaluation prior to or
during production trial
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 131, Printed 10/12/98
Preliminary Process Capability Studies
Characteristics identified in the control plan
Usually 100 pieces minimum
May be 30 if run is less
Ppk 1.67 is acceptable unless otherwise specified
Ppk 1.67 requires action plan unless otherwise
specified
Reference AIAG Fundamental SPC Reference Manual
1.0 at spec limit
+-3 sigma = 1.67
Allows flop within spec limit
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 132, Printed 10/12/98
PPAP Scope
Production parts - generally 300 pieces
Service subcontractors - fulfill requirements
Bulk material
Includes internal and external sources for
information
Submission required prior to first production
shipment
Section II When submission is required for
guidance
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 133, Printed 10/12/98
Production Part Approval Process (PPAP)
Production Part Approval Process
Parts produced at production site using:
Production tooling
Production gages
Process
Operators
Environment
Process settings
Feeds
Speeds
Cycle times
Pressures
Temperatures
Intent is to validate (prove) that products made using production equipment meet
engineering requirements
If submission level is not known, contact customer
Default level is 3
Customer approval is required prior to quantity production
Reference AIAG Production Part Approval Process reference manual
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 134, Printed 10/12/98
Production Validation Testing
Engineering tests validate products manufactured
with:
Production tools
Production processes
Production operators
Performed under end-use operating conditions
Multiple validations for multiple intended uses
Reference QS 9000 Element 4.4.8
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 135, Printed 10/12/98
Packaging Evaluation
Packaging must conform to specifications
developed by customer or supplier
Assess protection of product
Customer specified packaging must be
evaluated by team
Pilot or production trial run parts usually
used in evaluation
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 136, Printed 10/12/98
Production Control Plan
Update pre-launch control plan (living document)
Add:
Sampling plans
Control method
SPC, inspection, attribute data and mistake-proofing
Reaction plan
Nonconformances clearly identified, quarantined and
disposition made
Requires customer approval unless otherwise
specified
Reference AIAG APQP Reference manual Appendix A-8, B and G
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 137, Printed 10/12/98
Review and Sign-Off
Process instructions in place and followed
Flow charts in place and followed
GR&R plans exist and are followed
Publish final feasibility report
Obtain formal sigh-off
Schedule and conduct management review
Obtain management commitment to assist in
open issues
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 138, Printed 10/12/98
Phase 4 Project Review
Project #
Model/Year
Title
Part #
Customer
Date
Our advanced quality planning team has considered the following questions in Phase 4
of our APQP process. The documents provided have been used as a basis for analyzing
the ability to meet all specified requirements. All 'NO' answers are supported with attached
comments identifying our concerns and/or proposed changes to enable us to meet
specified requirements.
Yes
1.
2.
3.
4.
5.
6.
7.
No
Checklist Item
Has the production trial run been conducted and does it indicate the need for any change?
Does the evaluation of the measurement systems indicate any need to modify the
control plan characteristics?
Does the preliminary process capability study indicate any potential problems?
Has the production part been approved?
Has the production validation testing indicated any problems?
Has rthe evaluation of the packaging of test shipments, where feasible, and test methods
indicated any difficulty?
Has the control plan methodology check list indicated any problems with that document?
Feasible
Feasible
Not Feasible
Product can be produced as specified with no revisions.
Changes recommended (See attached)
Design revision required to produce product within specified requirements
Team Member/Title/Date
Team Member/Title/Date
Team Member/Title/Date
Team Member/Title/Date
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
This form is on course disk
Slide 139, Printed 10/12/98
MIS
Materials
Maintenance
HR
Production
Sales
Laboratory
Quality
Engineering
Purchasing
Phase 4: Product and Process Validation
Management
Phase 4 Responsibility Matrix
Output
Production Trial Run
Measurement Systems Evaluation
Preliminary Process Capability Study
Production Part Approval
Production Validation Testing
Packaging Evaluation
Production Control Plan
Quality Planning Sign-Off
Management Support
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
This form is on course disk
Slide 140, Printed 10/12/98
APQP Phase 5:
Feedback, Assessment and Corrective Action
Planning
Planning
Design & Development
Product
Process
Launch
Validation Product - Process
Production
Feedback Assessment & Corrective Action
Feedback
Assessment &
Corrective Action
The results of continuing production are evaluated for common
or special causes of variation during this phase to ensure that
the products satisfy customer satisfaction requirements
The effectiveness of the quality process should be evaluated
during this process step
Includes continual improvement efforts
Includes delivery and service performance
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 141, Printed 10/12/98
Continuing Production
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 142, Printed 10/12/98
Phase 5 Outputs
Reduced variation
Customer satisfaction
Delivery and service
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 143, Printed 10/12/98
Reducing Variation
Identify process variation
take corrective action to reduce
variation
Develop proposal for customer review
Gain customer decision to implement,
negotiate or change design
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 144, Printed 10/12/98
Customer Satisfaction
Product or service must perform in
customers environment
Supplier must participate
Supplier and customer must be partners
Reference QS 9000 Element 4.1.6
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 145, Printed 10/12/98
Customer Satisfaction Metrics
Warranty
Labour claims
Concerns reports
Nonconforming material reports
Corrective actions
On time delivery
Tech calls
Customer rating
Returns
PPM
Response time
On-site representative
Market share
Cost control (total cost)
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 146, Printed 10/12/98
Delivery and Service
Continues the supplier - customer partnership
in problem solving and continuous
improvement
Replacement parts and services are
important
Leads to possible price reduction from:
Inventory cost reduction
Process cost reduction
Cost of quality reduction
Reference QS 9000 Element 4.15
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 147, Printed 10/12/98
MIS
Materials
Maintenance
HR
Production
Sales
Laboratory
Quality
Engineering
Purchasing
Phase 5: Feedback, Assessment and Corrective Action
Management
Phase 5 Responsibility Matrix
Output
Reduced Variation
Customer Satisfaction
Delivery and Service
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
This form is on course disk
Slide 148, Printed 10/12/98
Phase 5 Project Review
Project #
Model/Year
Title
Part #
Customer
Date
Our advanced quality planning team has considered the following questions in Phase 5
of our APQP process. The documents provided have been used as a basis for analyzing
the ability to meet all specified requirements. All 'NO' answers are supported with attached
comments identifying our concerns and/or proposed changes to enable us to meet
specified requirements.
Yes
1.
2.
3.
No
Checklist Item
Has a system for reducing future variation been developed and is it in place?
Is there a system for ensuring continuing customer satisfaction?
Is there a process in place for monitoring delivery and service so that it continues
to met customer needs?
Feasible
Feasible
Not Feasible
Product can be produced as specified with no revisions.
Changes recommended (See attached)
Design revision required to produce product within specified requirements
Team Member/Title/Date
Team Member/Title/Date
Team Member/Title/Date
Team Member/Title/Date
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
This form is on course disk
Slide 149, Printed 10/12/98
Control Plan Methodology
Aids in the manufacturing of products according to
customer requirements
Provide structured approaches
Contain a written summary of the system used in
minimizing process and product variation
Forms provided in the AIAG handbook are examples
of how to document
Alternate formats can be used if they contain
necessary information
Must be maintained and used throughout the product
life cycle
Cayman Systems 1998 - Revision Q 980812
(513) 777-3394 www.qs9000.com
Advanced Product Quality Planning
Slide 150, Printed 10/12/98
Control Plan Use
Initial: To document and communicate
initial process control
Next: Guidance in controlling processes
and to ensure product quality
Last: A living document reflecting
current methods of control and
measurement systems used
Cayman Systems 1998 - Revision Q 980812