Medium Voltage Distribution
MCset 17.5 kV
Air insulated switchboard
Withdrawable switchgear SF6 or vaccum technology
Installation instruction
January 2009
Contents
General
Glossary
Earthing switch control symbols
Moving part control symbols
Recommendations
Standard tightening torques
List of bags and accessories
Packaging
Dimensions and weights
6
9
10
10
Handling instructions
11
Installation and operation recommendation
13
Floor finishing and cubicle fastening
14
Surface condition
Floor quality
Description of irons and accessories
Placing and adjusting on non earthquake resistant
civil engineering works
Placing and adjusting on earthquake resistant
civil engineering works
11
11
11
12
12
14
14
14
14
16
Installation instructions
18
Installation of a FU equipped with
electromagnetic locking options
63
Steps to be taken for tests and inspection
65
Tests on site
66
Index
67
Unpacking cubicles
Placing cubicles in a switchboard
Coupling of cubicles
Plug-in check
Removing the mobile part transportation devices
Installing the main earth lead
Installing the electric connections of the busbars and MV cables
Installing busbars
Installing busbars between MTP and the MOTORPACT cubicle
Placing MV cables on AD cubicle
Placing MV cables on RHC cubicle
MV cable screen earthing
LV cable routing and connection
Placing the tunnel sheets
Placing the IPX1/IPX2 roofs or anti arc IPX1/IPX2
Placing the tunnel end sheets
Placing end sheets
Installing fans on versions 3600 A / 4000 A
Earthing switch with electromagnetic locking
Plug-in prevention with electromagnetic locking
Prior to installing the front panels
Power frequency dielectric test
Checking and cocking the internal arcing detector
version 05
2
2
3
3
4
4
5
AD, CL-GL, VT cubicles
RHB, RHC cubicles
Cubicle fitted with IPX1/IPX2 roofs
Transition Panel MTP
Land packaging
Ocean shipment packaging
Handling using a sling
Handling by rolling
Storage
07897301EN.indd
18
18
21
23
23
24
26
28
32
35
41
45
46
48
51
57
59
62
63
64
64
65
66
General
Glossary
Note: this document is available for all the units
ordered from the 2nd of April 2009.
UF
Functionnal Unit (cubicle + mobile part + Sepam)
AD
Incomming/outgoing cubicle
CL-GL
Withdrawable line coupling cubicle
TT
Measurement and busbar earthing cubicle
RHB
Connection from the top by bar
RHC
Connection from the top by bar cable
MTP
Connection duct between an MCset cubicle and a
MOTORPACT cubicle
DI
Fuse switch outgoing cubicle
TT
Voltage transformer
TC
Current transformer or current sensor
VPIS
Voltage Presence Indicating System
LV
Low voltage
MV
Voltage class, including levels 7.2 - 12 and 17.5 kV
SMALT
Earthing switch
Mobile part
LF
Withdrawable circuit-breaker with SF6 breaking which is
used in AD and CL cubicles
Rollarc 400
SF6 breaking withdrawable contactor equipping the AD1
cubicle
EVOLIS
Withdrawable circuit-breaker with vacuum breaking which
is used in AD and CL cubicles
CTV1
Vacuum breaking withdrawable contactor equipping
the AD1 cubicle
OED
Rack-in or rack-out and removal tool of the mobile parts
on the ground
Table
dextraction
Extraction or insertion table without the removal tool
of the mobile parts on the ground
Earthing switch control symbols
Plug-in prevention position.
Locking possible.
Plug-in or withdrawal position.
Operation position.
Open earthing switch mechanical indicator
light.
version 05
07897301EN.indd
General
Closed earthing switch mechanical
indicator light.
Position can be locked using paslocks.
Moving part control symbols
Operation position.
Plugged-in position.
Withdrawn position.
Insertion/extraction position.
Recommendations
Installation above the switchboard
All type of equipment installation such as lamp or light are forbidden.
Marking
It is compulsory forbidden to walk
on the parts bearing this marking.
It is compulsory forbidden to remove
the parts bearing this marking when
the equipment is energised.
07897301EN.indd
version 05
General
Standard tightening torques
(Non greased screws and bolts)
Screw
Torque in Nm
13
28
10
50
12
75
14
120
Application methods:
The elastic washers placed on the
external sides of the pads and busbars
ensure better distribution of stress
regarding screws tightened to the
recommended torques.
List of bags and accessories
Switchboard packaging
Package
Contenu
Switchboard end and fixing
- Switchboard end sheets
- Fixing columns
- Bag of screws and bolts
- Wiring collector external closure
Switchboard
- 2 cubicle operation cranks
- 10 mm2 wire
- 1 earth fishplate and seal
- Civil engineering guide
- Installation manual
- Operating manual
Civil engineering
- Cubicle fastening rails
- Expansion pins
- Bag of screws and bolts
Package (Optional)
Content
Tests and inspection
- Manual earthing kit
Spare parts
- Fuses
Optional accessories
- 1 busbar earthing carriage
- 1 phase balance testing device
- 1 I and U test lead
- 1 tunnel closure kit
- 1 mobile part extraction tool
(ERT or extraction table)
version 05
07897301EN.indd
General
Packaging
Content
Cubicle
packaging
Separate
packaging
- Busbar fastening
(1)
- Busbar shims
(1)
- Lock associated with the cubicle
- Lock unit
Screws and bolts for:
- Cubicle fastening on civil engineer. works
- Intercubicle fastening
- Coupling gaskets
Cable fastening (AD cubicle):
- Flange supports
- Flanges
Cable floor:
- Bottom plates
- Cable support sleeves
- Bag of screws and bolts
- Busbar 1250 A
- Cable connection brackets
- Busbar covers
- Zero frequence toroids
- Busbars 2500 A, 3150 A et plus
- Cable compartment
- Fan compartment (FU 3600 A/ 4000 A)
(1) in general.
(2) these parts can sometimes be dispatched in a separate package.
The tank installation drawings can be dispatched:
AD1 : AAV8094101
AD2 : AAV8900201
AD3 : BBV1456801.
07897301EN.indd
version 05
Dimensions and weights
AD, CL-GL, VT cubicles
Cubicles with 1 CT per phase, internal arcing withstand
and Gas Exhaust version (wall-mounted) or no internal arcing
Dimensions
AD1
AD2
AD3
CL1
(2500A)
(3150A)
(3600A)
(4000A)
CL2
CL3
(2500A)
TT1
(3150A)
TT2
DI2
(3600A)
(4000A)
Width (mm) L
570
700
900
900
900
570 x 2 700 x 2 900 x 2 900 x 2 900 x 2 570
700
700
Height** (mm) H
2300
2300
2300
2300
2445
2300
2300
2300
2300
2445
2300
2300
2300
Depth (mm) P
1550
1550
1550
1700
1700
1550
1550
1550
1700
1700
1550
1550
1550
Weight* (kg)
850
1000
1300
1700
1760
650 x 2 750 x 2 850 x 2 1250 x 2 1310 x 2 500
550
750
Weight (kg) of VT
compartment
120
130
130
130
130
120
130
130
130
130
130
130
120
* Maximum fully fitted weight.
** This dimension excludes cable flanges as well as any compartments placed under the cubicle.
version 05
07897301EN.indd
Dimensions and weights
AD, CL-GL, VT cubicles
Cubicles with 1 CT per phase, internal arcing withstand on 4 sides
Compartment for version
3600 A / 4000 A
Dimensions
AD1
AD2
AD3
CL1
(2500A)
(3150A)
(3600A)
(4000A)
CL2
CL3
(2500A)
TT1
(3150A)
TT2
DI2
(3600A)
(4000A)
Width (mm) L
570
700
900
900
900
570 x 2 700 x 2 900 x 2 900 x 2 900 x 2 570
700
700
Height** (mm) H
2300
2300
2300
2300
2445
2300
2300
2300
2300
2445
2300
2300
2300
Depth (mm) P
1725
1725
1725
1725
1725
1725
1725
1725
1725
1725
1725
1725
1725
Weight* (kg)
850
1000
1300
1700
1760
650 x 2 750 x 2 850 x 2 1250 x 2 1310 x 2 500
550
800
Weight (kg) of VT
compartment
120
130
130
130
130
120
130
130
130
130
130
130
120
* Maximum fully fitted weight.
** This dimension excludes cable flanges as well as any compartments placed under the cubicle.
07897301EN.indd
version 05
Dimensions and weights
Cubicles with 2 CTs per phase, internal arcing withstand
and Gas Exhaust version (wall-mounted) or no internal arcing
Compartment for version
3600 A / 4000 A
AD3
Dimensions
AD1
AD2
(2500A)
(3150A)
(3600A/4000A)
Width (mm) L
570
700
900
900
900
Height** (mm) H
2300
2300
2300
2300
2445
Depth (mm) P
1700
1700
1700
2000 (RHB3) 2275 (RHC3) 1700
Weight* (kg)
900
1050
1350
1750
1810
130
130
130
130
Weight (kg) of VT compartment 120
* Maximum fully fitted weight.
** This dimension excludes cable flanges as well as any compartments placed under the cubicle.
Cubicles with 2 CTs per phase, internal arcing withstand on 4 sides
(installed in the middle of the room, no wall-mounting)
Compartment for version
3600 A / 4000 A
AD3
Dimensions
AD1
AD2
(2500A)
(3150A)
(3600A/4000A)
Width (mm) L
570
700
900
900
900
Height** (mm) H
2300
2300
2300
2300
2445
Depth (mm) P
1725
1725
1725
1725
1725
Weight* (kg)
950
1110
1400
1800
1800
Weight (kg) of VT compartment
120
130
130
130
130
* Maximum fully fitted weight.
** This dimension excludes cable flanges as well as any compartments placed under the cubicle.
version 05
07897301EN.indd
Dimensions and weights
RHB, RHC cubicles
Compartment for version
3600 A / 4000 A
Cubicles with 1 CT per phase, internal arcing withstand
on 4 sides (installation in the middle of the room, no wall-mounting)
Dimensions
RHB1
RHC1
2 cables max.
per phase
RHC1
3 to 4 cables
per phase
RHB2
RHC2
2 cables max.
per phase
RHC2
3 to 4 cables
per phase
RHB3 (2500A)
RHC3 (2500A) RHC3
2 cables max.
per phase
3 to 4 cables
per phase
RHB3 (3150A) RHB3
RHC3 (3150A)
2 cables max.
per phase
(3600A)
(4000A)
Width (mm) L
570
Height (mm) H
2300
570
700
700
900
900
900
900
2300
2300
2300
2300
2300
2300
2750
Depth (mm) P
2000
2275
2000
2275
2000
2275
2000 (RHB3)
2000
2275 (RHC3)
Weight* (kg)
950
950
1100
1100
1400
1400
1800
1820
Weight (kg) of VT compartment
120
120
130
130
130
130
130
130
* Maximum fully fitted weight.
Compartment for
version 3600 A / 4000 A
Cubicles with 2 CTs per phase, internal arcing withstand on 4 sides
(installation in the middle of the room, no wall-mounting)
Dimensions
RHB1
RHC1
RHC1
RHB2
RHC2
RHC2
RHB3 (2500A)
RHC3 (2500A) RHC3
2 cables max.
per phase
3 to 4 cables
per phase
RHB3 (3150A) RHB3
RHC3 (3150A)
2 cables max.
per phase
(3600A)
(4000A)
Width (mm) L
570
570
700
700
900
900
900
900
Height (mm) H
2300
2300
2300
2300
2300
2300
2300
2750
2 cables max.
per phase
3 to 4 cables
per phase
2 cables max.
per phase
3 to 4 cables
per phase
Depth (mm) P
2000
2275
2000
2275
2000
2275
2000 (RHB3)
2000
2275 (RHC3)
Weight* (kg)
1000
1000
1150
1150
1450
1450
1850
1820
Weight (kg) of VT compartment
120
120
130
130
130
130
130
130
* Maximum fully fitted weight.
07897301EN.indd
version 05
Dimensions and weights
Cubicle fitted with IPX1/IPX2 roofs
(e.g.: AD1 with internal arcing withstand
on 4 sides)
Dimensions
AD1 IPX1
AD1 IPX2
Width (mm) L
570
570
Height (mm) H
2732
2732
Depth (mm) P tunnel
1815
2485
Transition Panel MTP
(Motorpact, vacuum technology,
Transition Panel)
This duct is factory-mounted to the right or left
of an MCset cubicle (depends on switchboard
configuration).
See MOTORPACT civil engineering guide :
46032-700-07A.
Dimensions
10
MTP
1250 A
2500 A
3150 A
Width (mm) L
375
375
375
Height (mm) H
2300
2300
2300
Depth (mm) P
1550
1550
1550
Weight (kg)
240
275
310
version 05
07897301EN.indd
Handling instructions
Land packaging
Functional Unit
Ocean shipment packaging
Functional unit
Cubicles packed by threes
Handling using a sling
FU with circuit-breaker
07897301EN.indd
version 05
11
Handling instructions
Handling by rolling
Storage
Store the devices in their original
packaging, placed on dry ground or on
a material insulating it from humidity.
Prolonged storage
12
After prolonged storage, thoroughly clean insulating parts before operation.
version 05
07897301EN.indd
Installation and operation
recommendation
The switchgears resistance
to ageing in an MV substation
depends on 3 main factors:
1/ The necessity of correct
implementation of connections:
New cold retractable or slip-on
technology offers ease of installation
that favours resistance over time.
Their design allows them to used in
polluted environments with harsh
climatic conditions.
2/ Impact of the relative humidity
factor:
Installing a heating device is essential
in climates with high relative humidity
levels and major temperature
differences.
Ensure that draughts and/or thermal
shocks are avoided in all cubicle
compartments in order to avoid the
creation of dew points (sources of
partial discharges).
Operation and maintenance
In case of dismantling, the elastic
washers must be change and replace
by new ones supplied by Schneider
Electric.
Outside normal conditions of use,
(between -5C and 40C , absence
of dust, corrosive gas, etc.), it is
recommended to
examine, with our Schneider Electric
services centre, the steps to be
taken, in order to ensure correct
functioning of the installation.
Our service centre is at your
disposal at any time:
b to undergo an installation diagnostic,
b to offer you, if need be, suitable
maintenance operations,
b to offer you maintenance contracts,
b to offer you adaptations.
Version 3600 A / 4000 A:
We strongly recommend that you
clean the ventilation grids A and B
regularly (every 2 years):
A: standard grids
B: grids only on RHB version.
A fan monitoring system must be
installed with the cubicle control
and monitoring devices.
Permanent operation of the
following must be guaranteed:
Cubicles types
version 05
3/ Electrical room ventilation control:
Grid size must be suited to the power
dissipated in the substation. These
grids must be placed exclusively
in the vicinity of the transformer, in
order to avoid air circulation on the LV
switchboard.
It is strongly advised to periodically
carry out, (minimun every 2 years
approximately), a few operation
cycles on operating devices.
After 6 to 12 month operations, we
recommend you to check the busbars
and MV cable connection tightening.
It should be done with a calibrated
torque spanner, adjust to lower torque
compare to values indicated in page 4.
If no problems are detected and if the
busbars and cable connections havent
been modified, it will not necessary to
do again this check.
07897301EN.indd
The equipment must be installed
in conformity with the relevant IEC
standard.
Outside of these normal usage
conditions, we recommend contacting
Schneider Electric to determine the
operations to be carried out as well as
their frequency according to the actual
service conditions.
An MCset 17.5 kV Maintenance
and Services guide is available.
It gives practical information on:
b maintaining the equipment in good
operating order,
b ensuring that the equipment is safe
during all installation, repair and
servicing operations.
DEAI03EN/ART833121
DEAI03FR/ART833120
Fans quantity
3600 A
4000 A
AD3, CL3
RHB3
13
Floor finishing
and cubicle fastening
Surface condition
Floor evenness is such that a 2 meter ruler moved over all surfaces and in all
directions, does not display a difference of more than 5 mm.
Floor quality
For the rolling of mobile part extraction tools without degrading the floor, it must
have acompression withstand u 33 MPa.
Description of irons
and accessories
Cubicle fastening
Take this equipment from
the civil engineering package
of the switchboard packaging.
Standard civil engineering:
- 1 iron section A (length 2m)
- 4 expansion pins B
- 2 fastening shims C.
Earthquake resistant civil
engineering:
- 2 iron sections A (length 2m)
- 8 expansion pins B
- 4 fastening shims C.
Place and fix the irons to the floor using
the supplied expansion pins, screws
and washers.
Note: in the case of a switchboard with
only cubicles AD3-CL3 leave a 40 mm
space for natural ventilation.
Placing and adjusting on non
earthquake resistant civil
engineering works
Preparation
Drill a hole in the floor and irons.
Placing the irons
Cut the last iron to the required length.
14
version 05
07897301EN.indd
Floor finishing
and cubicle fastening
Tightening irons
Do not bend the iron on installation.
Longitudinal adjustment:
using a the water level and using shims before
tightening the screws.
Transversal adjustment:
using a the spirit level and using shims before
tightening the screws.
For the correct installation of
cubicles, it is advised to comply with
a tolerance of 0.2 cm/m and a max.
gap of 10 mm/10m on the length of
the switchboard.
07897301EN.indd
version 05
15
Floor finishing
and cubicle fastening
Placing and adjusting on
earthquake resistant civil
engineering works
Preparation
Drill a hole in the floor and irons.
Placing the irons
Place and fix the irons to the floor using the supplied
expansion pins, screws and washers.
Cut the last iron to the required length.
Note: in the case of a switchboard with
only cubicles AD3-CL3, leave a 40 mm
space for natural ventilation.
16
version 05
07897301EN.indd
Floor finishing
and cubicle fastening
Tightening irons
Do not bend the iron on installation.
Longitudinal adjustment:
using a the water level and using shims before
tightening the screws.
The irons must be very smooth,
because adjustment using actuators
is not possible.
Transversal adjustment:
using a the spirit level and using shims before
tightening the screws.
For the correct installation of
cubicles, it is advised to comply with
a tolerance of 0.2 cm/m and a max.
gap of 10 mm/10m on the length of
the switchboard.
07897301EN.indd
version 05
17
Installation instructions
Unpacking cubicles
The preparation of cubicles must be carried out
on the premises where they will be installed.
To avoid damaging the FU
front panel components,
leave the protection
foam in place until the
switchboard is in
the operation phase.
Remove the 4 handling lugs (1 and 2).
The circuit-breakers are delivered in cubicles in a
withdrawn position.
Unpack the functional unit by removing the wooden
columns (8 screws), then the plastic cover.
Remove the cubicle packaging.
Placing cubicles in a switchboard
Assembling, adjusting and fastening
Note: place switchboard cubicles
according to front panel drawings and
the single-line diagram.
Start by placing the cubicle located in
the middle of the switchboard (except in
the case of an extension of the existing
switchboard) then position the cubicles
on either side of it, according to the Civil
Engineering Guide indications.
Depending on the type of civil
engineering, take the following from
packages:
1 bag of non earthquake resistant
civil engineering screws and bolts
n 51236072F0:
Rear adjustment accessories:
A: 4 x HM12 nuts
B: 2 quick cage nuts
C: 5 flat washers
D: 4 x (HM12x70) screws
E: 2 support irons.
Front fastening accessories:
F: 2 hook head bolts
G: 2 fastening shims
H: rubber anti-vibration plate.
1 bag of earthquake resistant civil
engineering screws and bolts
n 51236075F0:
Cubicle X must not impede cubicle
X+1 and conversely with respect
to overall dimensions.
Depending on the load, if a cubicle
is found to be raised after the next
one is installed, there is a risk of
vibrations.
18
Rear fastening accessories:
H: 2 hook head bolts
K: 2 fastening shims.
Front fastening accessories:
H: 2 hook head bolts
J: 2 fastening shims.
version 05
07897301EN.indd
Installation instructions
Placing on maintenance space
Do not dismantle any part
of the cubicle.
Note: placing can be carried out by lifting or rolling.
Handling of the cubicle by rolling.
Adjusting cubicles on standard civil
engineering works
The operations described here after, must only be
carried out once the cubicle is positioned on civil
engineering works.
Position the support irons A and the
rubber anti-vibration plates B at the
rear of the cubicle by gaining access
through the maintenance space.
Place the 2 quick cage nuts C at the
rear of the cubicle, by gaining access
underneath the cubicle.
Screw the lock nut D on each actuator
E, place washer F, then screw the
actuators in the quick cage nuts C.
Lift the rear of the cubicle by screwing
the 2 actuators to level the cubicle
Cubicle X must not impede cubicle
X+1 and conversely with respect
to overall dimensions.
Depending on the load, if a cubicle
is found to be raised after the next
one is installed, there is a risk of
vibrations.
07897301EN.indd
version 05
19
Installation instructions
Fastening to the floor on standard civil
engineering works
Note: remove the front panel if the cubicle is fitted
with VT, it is first necessary to remove them, refer
to the operating manual (07897302), the chapter
on Instructions for access to the interior of a
cubicle.
To be retrieved from the bag of screws
and bolts.
Place the fastening screws at the front
of the cubicle and tighten them.
To be retrieved from the two bags of
screws and bolts H and K.
Place the fastening screws at the rear
of the cubicle and tighten them.
To be retrieved from the two bags of
screws and bolts J and H.
Place the fastening screws at the front
of the cubicle and tighten them.
Fastening to the floor one earthquake
resistant civil engineering works
Note: remove the front panel if the cubicle is fitted
with VT, it is first necessary to remove them, refer
to the operating manual (07897302), the chapter
on Instructions for access to the interior of a
cubicle.
Cubicle X must not impede cubicle
X+1 and conversely with respect
to overall dimensions.
Depending on the load, if a cubicle
is found to be raised after the next
one is installed, there is a risk of
vibrations.
20
version 05
07897301EN.indd
Installation instructions
Coupling of cubicles
Installing the inter cubicle gasket
Note: for a first generation switchboard extension,
consult the installation manual (07897302) First
generation switchboard extension.
Place the self-adhesive inter cubicle
gasket along the entire top part of the
right side of the cubicle, except on the
high end of the cubicle.
This operation is not necessary for
the cubicle on the far right side of the
switchboard.
Install the second cubicleby proceeding
in the same way as the first one and
tighten the actuators. Assemble the 2
cubicles together (10 fastening points).
Access to the fastening points:
- Refer to chapter on Instructions for
access to the interior of a cubicle in
the operating manual (07897302).
- See page 23 Removing the mobile
part transportation devices.
Assembling cubicles
The lifting rings and its nuts cages
associated must be removed.
A: assembly of HM8 x 30 screws + M8 washers
and HM8 nut.
B: assembly of HM8 x 16 screws + M8 washers
and M8 cage nuts.
C: assembly of HM6 x 16 screws + M6 washers and
HM6 nut + M6 washers.
Internal arc : 4 sides option.
For every square hole (nb : 6/side) on the side
of backplate, it shall be screwed to the one
located on its side with:
Screw : VAM HM8x30
Washer : Was. CS 8x18x1.4
Nut : HM8.
07897301EN.indd
version 05
21
Installation instructions
Assembling a MOTORPACT cubicle /
MTP transition panel
Left-hand fastening
Right-hand fastening
Implementation:
1: disassemble the transition panel (E) front and rear
panel sheets
2: open the front doors of the MOTORPACT top and
bottom compartments
3: disassemble the central front panel D of
MOTORPACT by withdrawing the 4 screws
4: disassemble the rear sheets of the MOTORPACT
compartments:
see manual (46032-700-08B), Installation guide
5: install screws (A), nuts (B) and washers (C) as
shown opposite.
22
version 05
07897301EN.indd
Installation instructions
Plug-in check
Each time a cubicle is coupled, check,
using the mobile part, that plug-in and
locking is correctly carried out at the
end of travel.
Removing the mobile part
transportation devices
To extract the mobile part and door closure, refer to operating manual
in the chapter on Operating instructions.
The operations described here after, must only be carried out once the cubicle
has been positioned on civil engineering works.
For the insertion and plug-in of the
mobile part as well as door closure,
refer to the operating manual
(07897302) in the chapter on
Operating instructions.
Do not handle the mobile parts before removing the wedges.
On circuit-breaker LF
1: remove the 2 transportation reinforcements
(3 screws per reinforcement)
2: place the 4 front plate fastening screws and spur
washers, contained in the bag of screws and bolts.
Tightening torque: 8.5 Nm.
3: on the first operation, remove the label:
On a ROLLARC/ CTV1 contactor
1: Remove the 2 transportation reinforcements
(3 screws per reinforcement)
2: place the 4 front plate fastening screws and spur
washers, contained in the bag of screws and bolts.
Tightening torque: 8.5 Nm.
3: on the first operation, remove the label:
On an EVOLIS circuit-breaker
1: remove the front panel screws
2: extract the circuit-breaker (out of the cubicle)
3: remove the top wedge with access
via the LV compartment
4: remove the wedge positioned on the circuit-breaker.
Tightening torque: 8.5 Nm.
5: on the first operation, remove the label:
07897301EN.indd
version 05
23
Installation instructions
On an EVOLIS LF circuit-breaker
1: remove the 3 transportation reinforcements
(3 screws for the lower reinforcement and 3 screws
for the upper reinforcement)
2: place the 6 front plate fastening screws and spur
washers, contained in the bag of screws and bolts.
Tightening torque: 8.5 Nm.
3: on the first operation, remove the label:
Installing the main earth lead
From the switchboard to the buildings
earth
Note: when the end sheets are placed, remove the
punch-outs from the sheets.
For a switchboard with a MOTORPACT cubicle at the
end, refer to MOTORPACT installation manual ref.
46032-700-08.
Connect the earth bar to the buildings earth at the end of the switchboard, on the
right and on the left, place the special fishplate by positioning the oblong hole on
the inside of the cubicle.
Tighten with a torque of 28 Nm (the fishplates for the end of the switchboard are
in the switchboard package)
24
version 05
07897301EN.indd
Installation instructions
Inter-cubicles MCset - MCset
and MCset - Transition Panel MTP
Note: this connection can be done during the
installation of each cubicle or at the end of
switchboard assembly.
The connection is located at the base of
the cubicle
Retrieve the self-adhesive seal in the
bag of screws and bolts.
Position this seal around the fishplate.
Install the fishplate by sliding it from
cubicle 2 to cubicle 1.
Put back and lock in place the fastening
screws. Use only screws HM8x30.
28 Nm tightening torque.
Stick the seal onto the cubicle sheet as
shown in A.
Inter-cubicles
Transition Panel MTP - Motorpact
The connection is located in the middle of the cubicle.
The MTP duct earth bar fish plate is installed at the factory.
When coupling it to the Motorpact, simply screw the MTP duct fish plate onto
the earth bar inside the Motorpact.
07897301EN.indd
version 05
25
Installation instructions
Installing the electric connections
of the busbars and MV cables
General information
Assemblies with bolts for MV and LV
internal equipment.
Screws and bolts to be used:
Class 8.8 according to standard
NF E 27 005, i.e. an elastic limit,
Re 630 Nm / mm.
Connection maintenance:
During downtime, check clamping of
connections with a torque wrench.
In the case of dismantling, change the
elastic washers.
Note: to carry out the following
preliminary switchboard operations see
chapter Instructions for access to
the interior of a cubicle.
Cubicle AD and CL without VT
Preliminary operations
to be carried out
Placing
busbars
Placing MV
cables
Extraction of the mobile part
(Optional)
Close the earthing switch
Remove the front panel
protective cover plates
Remove the separation plate
from between the switchgear
compartment (moving part)
and the cable compartment.
(Optional)
Remove the busbar access sheet
Remove the manhole sheet
Cubicle AD and CL with fixed VT
Placing
busbars
Preliminary operations
to be carried out
Placing MV
cables
Extraction of the mobile part
(Optional)
Close the earthing switch
Remove the front panel protective
cover plates
Remove the fixed VTs
Remove the separation plate
from between the switchgear
compartment (moving part)
and the cable compartment.
(Optional)
Remove the busbar access sheet
Remove the manhole sheet
26
version 05
07897301EN.indd
Installation instructions
Cubicle AD and CL with withdrawable VT
Preliminary operations
to be carried out
Placing
busbars
Placing MV
cables
Extraction of the mobile par
(Optional)
Withdraw the VT fuses
Close the earthing switch
Remove the front panel protective
cover plates
Remove the withdrawable VTs
Remove the separation plate
from between the switchgear
compartment (moving part)
and the cable compartment.
(Optional)
Remove the busbar access sheet
Remove the manhole sheet
TT cubicle with fixed VTs
Preliminary operations
to be carried out
Placing
busbars
Placing MV
cables
Remove the front panel
protective cover plates
Remove the fixed VTs
Remove the separation plate
from between the switchgear
compartment (moving part)
and the cable compartment.
(Optional)
Remove the busbar access sheet
Remove the manhole sheet
TT cubicle with withdrawable VT
Preliminary operations
to be carried out
Placing
busbars
Placing MV
cables
Withdraw VT fuses
Close the earthing switch
Remove the front panel
protective cover plates
Remove withdrawable VTs
Remove the separation plate
from between the switchgear
compartment (moving part)
and the cable compartment.
(Optional)
Remove the busbar access sheet
Remove the manhole sheet
07897301EN.indd
version 05
27
Installation instructions
Installing busbars
This connection is done during
the installation of each cubicle.
Access the busbars through the cubicle
side.
Retrieve;
- In package of the cubicle packaging,
the busbars
- In package of the cubicle packaging,
any busbar shims (if they exist).
If this is not possible, access through
the interior of the cubicle (refer to
chapter on Instructions for access to
the interior of a cubicle).
Place the busbar between the 2
previously assembled cubicles
(refer to chapter on Principle of
assembling busbars).
Block the fastening screws by
tightening on the side of the screw
heads.
50 Nm tightening torque.
Repeat these operations each time a
switchboard cubicle is placed.
Principle of assembling busbars
1250 A busbars
Bag of 1250 A busbars: 03407033F0.
A: top view of busbars
B: 1 x (100 x 8) bar per phase
C: nut
D: fan type lock washer
E: flat washer
F: M10 x 40 screws.
28
version 05
07897301EN.indd
Installation instructions
Evolis HP 2500 A busbars
A: top view of busbarss
B: 3 riser busbars
C: 2 x (100 x 8) per phase
D: nut
E: an type lock washer
F: flat washer
G: M10 x 55 screws
H: 3 hole shim.
A: top view of busbarss
B: 2 x (100 x 8) per phase
C: nut
D: fan type lock washer
E: flat washer
F: M10 x 55 screws
G: 3 hole shim
H: 6 hole shim.
2500 A busbars
Bag of 2500 A busbars: 03407034F0.
07897301EN.indd
version 05
29
Installation instructions
Evolis HP 3150 A busbars
A: top view of busbarss
B: 4 riser busbars
C: 3 x (100 x 8) per phase
D: nut
E: an type lock washer
F: flat washer
G: M10 x 55 screws.
A: top view of busbarss
B: 3 x (100 x 8) per phase
C: nut
D: fan type lock washer
E: flat washer
F: M10 x 70 screws
G: 3 hole shim
H: 6 hole shim.
3150 A busbars
Bag of 3150 A busbars: 03407035F0.
30
version 05
07897301EN.indd
Installation instructions
Evolis HP 4000 A busbars
A: top view of busbarss
B: 4 riser busbars
C: 4 x (100 x 8) per phase
D: nut
E: an type lock washer
F: flat washer
G: M10 x 55 screws.
4000 A busbars
Bag of 4000 A busbars: 51237530F0.
A: top view of busbars
B: 4 x (100 x 8) per phase
C: nut
D: fan type lock washer
E: flat washer
F: M10 x 85 screws (special)
G: 3 hole shim
H: 6 hole shim.
07897301EN.indd
version 05
31
Installation instructions
Cover mounting principle
(depending on needs)
Mounting the covers with clips
Retrieve: from package of the cubicle packaging, the covers.
Note: for mounting the covers with rings,
see page 34.
Position the half-covers on the
connection pads.
Close the covers on the bars.
MOTORPACT
to the right
MOTORPACT
to the left
Installing busbars between MTP
and the MOTORPACT cubicle
1250 A busbars
A: nut
B: contact washer
C: flat washer
D: M10 x 40 screws
E: 1 x (76 x 9,5) per phase
F: 2 holes shim
G: M10 x 60 screws
H: 1 hole shim.
Note: for phase 3, the connection bar on the transition
panel side is fastened to an insulator support.
32
version 05
07897301EN.indd
Installation instructions
2500 A busbars
MOTORPACT
to the right
MOTORPACT
to the left
MOTORPACT
to the right
MOTORPACT
to the left
A: nut
B: contact washer
C: flat washer
D: M10 x 55 screws
E: 2 x (76 x 9,5) per phase
F: 1 hole shim
G: M10 x 70 screws.
Note: for phase 3, the connection bar on the transition
panel side is fastened to an insulator support.
3150 A busbars
A: nut
B: contact washer
C: flat washer
D: M10 x 70 screws
E: 3 x (76 x 9,5) per phase
F: 1 hole shim
G: M10 x 80 screws.
Note: for phase 3, the connection bar on the transition
panel side is fastened to an insulator support.
07897301EN.indd
version 05
33
Installation instructions
Optional insulated busbars
MTP - Top views
Mounting the covers:
A: install a ring around the busbar, inside the cover
(allow to clamp the cover in position)
B: close the cover with rings
C: close the cover with clips
D: fit the entire cover assembly with clips.
For cover mounting, refer to the chapter Cover
mounting principle.
Mounting the covers with rings
Position the half-covers on the
connection pads.
34
version 05
Close the covers on the bars by
tightening the rings in the notches.
07897301EN.indd
Installation instructions
Placing MV cables on AD cubicle
General information
An explanation is given for all types of cables.
Retrieve: from package of the cubicle packaging,
back plates, flanges and fastenings.
A: 3 single-pole cables
B: 1 three-pole cable.
To access the interior of a cubicle (refer to the
operating manual chapter on Instructions for
access to the interior of a cubicle )
Cut cable bushings according
to the number and diameter of cables.
Install them on the cables.
Position the cable and its grommet
correctly between the sheets (A).
Fix and press the flange support
against the cable under the cubicle
floor.
To produce cable ends, refer to
accessories for manufacturer
instructions.
MV cable maintenance on AD cubicle
Successively assemble, after having installed a row
of cables:
- Flange support
- Flanges
- Back plates.
Fix the flange support under the floor,
after placing the cables vertical to
their attachment bracket.
Block the cables with half-flanges.
Reassemble bottom plates.
Fill in the openings that have not been
used with uncut cable bushing.
07897301EN.indd
version 05
35
Installation instructions
Height of cable insulation replacement
Type of cubicle
Configuration
AD1 - AD2
630 A
LV toroids
621
1 set of 3 CTs
454
2 sets of 3 CTs
438
LV toroids
621
1 set of 3 CTs
454
2 sets of 3 CTs
438
1 set of 3 CTs
477
2 sets of 3 CTs
459
1 set of 3 CTs
428
2 sets of 3 CTs
428
3150 A
1 set of 3 CTs
404
3600 A/ 4000 A
1 set of 3 CTs
653
1250 A
AD3
H (mm)
1250 A
2500 A
Surge arrester
Removing
In the case of an AD1 or AD2 cubicle
fitted with a surge arrester, access to
the cable compartment through the front
requires removal of the surge arrester
assembly.
1: remove the busbar surge arrester connection
2: remove the insulator support.
Placing
To place back into operation, carry out the operations
in the reverse order of removal.
Tightening torque
B: 50 Nm
E: 20 Nm.
36
version 05
07897301EN.indd
Installation instructions
Single-pole or three-pole cable without
toroid TC
Drill a hole in bracket A according
to the cable head to be connected.
Place and fix bracket A.
AD1 and AD2, 1, 2 or 3 cables per phase
An explanation is given for a phase.
Do the same for the two other phases.
Retrieve: in package of the cubicle packaging,
the bracket and the screws and bolts.
Connect the cables.
Standard tightening torque corresponding to
of the bolts.
B: 50 Nm tightening torque.
Note: how the bracket fastening screws
are assembled:
1: M10 x 30 screws
2: M10 washer
After having installed a row of cables, then assemble
the support flange (see chapter on MV cable
maintenance on AD cubicle).
3: M10 nuts.
Dielectric tests must be carried out before
connecting the surge arresters.
For the connection of surge arresters, refer to chapter
on Surge arresters.
Place and fix brackets A, C and D.
B: 50 Nm tightening torque.
Connect the cables.
Standard tightening torque corresponding to of
the bolts.
After having installed a row of cables, then assemble
the support flange (see chapter on MV cable
maintenance on AD cubicle).
Dielectric tests must be carried out before
connecting the surge arresters.
For the connection of surge arresters, refer to chapter
on Surge arresters.
AD3, 1 to 4 cables per phase
Remove the bars.
07897301EN.indd
version 05
Drill a hole in the bars according to the
cable heads to be connected.
37
Installation instructions
Put back the bars with new washers.
Installing ever the lug inside the
support and place the screw head
outside the support.
Standard tightening torque
corresponding to of the screws.
A: screw
B: washer
C: nut
D: lug.
Dielectric tests must be carried
out before connecting the surge
arresters.
Fix the surge arrester connections if
they exist.
Tightening torque:
B: 50 Nm
E: 20 Nm.
AD3 3150 A/ 4000 A up to 8 cables
per phase
38
Remove the bars.
Drill a hole in the bars according to the
cable heads to be connected.
Put back the bars with new washers.
Installing ever the lug inside the
support and place the screw head
outside the support.
Standard tightening torque
corresponding to of the screws.
Dielectric tests must be carried
out before connecting the surge
arresters.
A: screw
B: washer
C: nut
D: lug.
Tightening torque:
B: 50 Nm
E: 20 Nm.
version 05
Fix the surge arrester connections if
they exist.
07897301EN.indd
Installation instructions
Single-pole cable with toroid CT
on cubicle AD1 and AD2
AD1 and AD2, 1 or 2 cables per phase
The explanation is given for one phase.
Do the same for the two other phases.
Retrieve: in package of the cubicle packaging,
pads A and screws and bolts.
Drill a hole in pads A according to the
cable head to be connected.
Place and fix pads A.
50 Nm tightening torque.
Note: how the fastening screws
of the pads are assembled:
1: M10 x 30 screws
2: M10 washers
3: M10 nuts.
AD1 1 cable per phase
Place phase 2 cable in the toroid.
The explanation is given for one phase.
Do the same for the two other phases.
Note: how the cable head fastening screws are
assembled:
1: M10 x 30 screws
2: M10 washers
3: M10 nuts.
Standard tightening torque
corresponding to of the bolts.
After having installed a row of cables,
then assemble the support flange (see
chapter on MV cable maintenance on
AD cubicle).
AD2 1 cable per phase
07897301EN.indd
Connect the cables on the pads.
Place the cables in the toroids.
version 05
39
Installation instructions
Note: how the cable head fastening screws are
assembled:
1: M10 x 30 screws
2: M10 washer
3: M10 nuts.
Connect the cables.
Standard tightening torque
corresponding to of the bolts.
Dielectric tests must be carried
out before connecting the surge
arresters.
After having installed a row of cables,
then assemble the support flange (see
chapter on MV cable maintenance on
AD cubicle).
AD2 2 cables per phase
AD3 2 cables per phase
Place the cables in the toroids.
Note: how the cable head fastening screws are
assembled:
1: M10 x 30 screws
2: M10 washer
3: M10 nuts.
Connect the cables.
Standard tightening torque
corresponding to of the bolts.
Dielectric tests must be carried
out before connecting the surge
arresters.
After having installed a row of cables,
then assemble the support flange (see
chapter on MV cable maintenance on
AD cubicle).
40
version 05
07897301EN.indd
Installation instructions
Placing MV cables on RHC cubicle
General information
An explanation is given for all types of cables.
Retrieve: from package of the cubicle packaging,
back plates, flanges and fastenings.
A: 3 single-pole cables
B: 1 single-pole cable.
To access the interior of a cubicle (refer to the
operating manual chapter on Instructions for
access to the interior of a cubicle )
Cut cable bushings according
to the number and diameter of cables.
Install them on the cables.
To produce cable ends, refer to
accessories for manufacturer
instructions.
MV cable maintenance on RHC cubicle
Successively assemble, after having installed a row
of cables:
- Flange support
- Flanges
- Cables bushing plates.
Fix the flange support onto the cables
bushing plates, after placing
the cables vertical to their attachment
bracket.
07897301EN.indd
version 05
See chapter on MV cable maintenance on AD cubicle) for installation
instructions.
41
Installation instructions
Single-pole or three-pole cable without
toroid TC
RHC3 1250 A, RHC1 and RHC2 1, 2 or 3
cables per phase
Drill a hole in bracket A according
to the cable head to be connected.
Place and fix bracket A.
An explanation is given for a phase.
Do the same for the two other phases.
Retrieve: in package of the cubicle packaging,
the bracket and the screws and bolts.
Place and fix brackets A and C.
B: 50 Nm tightening torque.
Note: how the bracket fastening screws
are assembled:
1: M10 x 30 screws
Connect the cables.
Standard tightening torque corresponding to of
the bolts.
2: M10 washer
3: M10 nuts.
After having installed a row of cables, then assemble
the support flange (see chapter on MV cable
maintenance on RHC cubicle).
Dielectric tests must be carried out before
connecting the surge arresters.
For the connection of surge arresters, refer to chapter
on Surge arresters.
RHC3 1250 A and RHC2 4 cables per
phase
Drill a hole in bracket A according
to the cable head to be connected.
Place and fix bracket A.
An explanation is given for a phase.
Do the same for the two other phases.
Retrieve: in package of the cubicle packaging,
the bracket and the screws and bolts.
Place and fix brackets A.
B: 50 Nm tightening torque.
Note: how the bracket fastening screws
are assembled:
1: M10 x 30 screws
2: M10 washer
3: M10 nuts.
Connect the cables.
Standard tightening torque corresponding to of
the bolts.
After having installed a row of cables, then assemble
the support flange (see chapter on MV cable
maintenance on RHC cubicle).
Dielectric tests must be carried out before
connecting the surge arresters.
For the connection of surge arresters, refer to chapter
on Surge arresters.
42
version 05
07897301EN.indd
Installation instructions
RHC3 2500 A 4 cables per phase
Remove the bars.
Drill a hole in the bars according to the
cable heads to be connected.
Put back the bars with new washers.
Installing ever the lug inside the
support and place the screw head
outside the support.
Standard tightening torque
corresponding to of the screws.
A: screw
B: washer
C: nut
D: lug.
RHC3 3150 A up to 8 cables per phase
Remove the bars.
Drill a hole in the bars according to the
cable heads to be connected.
Put back the bars with new washers.
Installing ever the lug inside the
support and place the screw head
outside the support.
Standard tightening torque
corresponding to of the screws.
A: screw
B: washer
C: nut
D: lug.
07897301EN.indd
version 05
43
Installation instructions
Single-pole cable with toroid TC
RHC1 1or 2 cables per phase
Drill a hole in bracket A according
to the cable head to be connected.
An explanation is given for a phase.
Place and fix bracket A.
Do the same for the two other phases.
Retrieve: in package of the cubicle packaging,
the bracket and the screws and bolts.
Note: how the bracket fastening screws
are assembled:
1: M10 x 30 screws
Place and fix brackets A.
B: 50 Nm tightening torque.
2: M10 washer
3: M10 nuts.
Connect the cables.
Standard tightening torque corresponding to of
the bolts.
After having installed a row of cables, then assemble
the support flange (see chapter on MV cable
maintenance on RHC cubicle).
There are three ways of installing the toroids
(according to the width of the cubicles):
1: 1 single-pole cable
2: 1 single-pole cable
3: 2 single-pole cables.
Dielectric tests must be carried out before
connecting the surge arresters.
For the connection of surge arresters, refer to chapter
on Surge arresters.
44
version 05
07897301EN.indd
Installation instructions
MV cable screen earthing
On single-pole or two-pole toroid CT
The braid connection is done under the
cubicle.
In all cases, the insulated MV cable
screen braids must pass through
the toroids before connection to the
switchboard main earth lead.
In all cases, the MV cable screen braids
must be insulated and pass through the
zero frequence toroid before connection
to the switchboards earth.
The braid connection is done on
the switchboard earth bars in the
maintenance space.
Example: one cable per phase, 3 braids
to be connected. Two cables per phase,
6 braids to be connected.
On zero frequence toroid
Example of cable leadthrough:
A: 1 three-pole cable
1 cable per phase
3 earthing braids
B: 2 three-pole cables
2 cables per phase
6 earthing braids
C: 3 single-pole cables
1 cable per phase
3 earthing braids
D: 6 single-pole cables
2 cables per phase
6 earthing braids.
07897301EN.indd
version 05
45
Installation instructions
LV cable routing and connection
Incoming cables at the end
of the switchboard
Remove the roofing sheet on each
cubicle (6 screws).
Remove the cubicle cable troughs.
Place the strand and the feed wires.
Conduct the wiring cubicle by cubicle,
by passing wires through the cable
bushing of the cable troughs.
Reassemble the cable troughs.
Carry out connections to the terminal
blocks.
Remove the cable leadthrough sheet
located on the roofs of the cubicles (4
screws), as well as the roofing sheets(6
screws).
Cut the cable leadthrough sheets
according to the wires to be installed.
Reassemble the roofing sheets
(6 screws per sheet).
Incoming cables through the top,
cubicle by cubicle
46
version 05
Install the glands on these sheets and
pass the wires through.
07897301EN.indd
Installation instructions
Replace the sheet (4 screws).
Connect the wires to the terminal blocks
and fix the roofing sheet (6 screws).
Incoming cables from below,
cubicle by cubicle
Remove the cable trough.
Cut according to the number and the
diameter of the cables.
(maximum 5 diameters 20 mm) at the
base of the cable trough.
Remove the roofing sheets,and any
the cable leadthroughsheets (6 and 4
screws).
Thread the wiring as well as feeder
cables up to the cubicle roof.
Place the cable trough.
Place the wires on the terminal blocks,
then connect them.
Reassemble the roofing sheets (6 and
4 screws per sheet).
07897301EN.indd
version 05
47
Installation instructions
Placing the tunnel sheets
Wall-mounted anti arc tunnel
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
1/ First fit the angle bracket (2) on the wall using
two screws.
2/ Fit the sheet (1) onto the cubicle using four screws
(B) for MCset 1 and 6 screws (B) for MCset 2 and
MCset 3.
3/ Attach the roof (3) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (3) on the angle bracket (2) using
two screws (C).
4 side anti arc tunnel
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
1/ First fit the sheet (1) onto the cubicle using four
screws (B) for MCset 1 and 6 screws (B) for
MCset 2 and MCset 3.
2/ Attach the roof (2) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
48
version 05
07897301EN.indd
Installation instructions
Wall-mounted anti arc tunnel for
versions 3600 A / 4000 A
Wall-mounted anti arc tunnel
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
1/ First fit the angle bracket (2) on the wall using
two screws.
2/ Fit the sheet (1) onto the ventilation compartment
using four screws (B) for MCset 1 and 6 screws (B)
for MCset 2 and MCset 3.
3/ Attach the roof (3) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (3) on the angle bracket (2) using
two screws (C).
4 side anti arc tunnel for versions
3600 A / 4000 A
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
1/ First fit the sheet (1) onto the ventilation
compartment using four screws (B) for MCset 1
and 6 screws (B) for MCset 2 and MCset 3.
2/ Attach the roof (2) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
07897301EN.indd
version 05
49
Installation instructions
Installing a tunnel on a MTP transition
panel
The sheets are fitting by HM6 screws + M6 washers
and HM6 nuts combination (A):
1/ Mount the support sheets (1) first.
2/ Mount the side panel (2).
3/ Mount the roof (3).
4/ Mount the tunnel closing sheets to the front
and rear (4).
5/ Fasten the support sheets of each cubicle to one
another.
6/ Fasten the tunnels of each cubicle to one another.
50
version 05
07897301EN.indd
Installation instructions
Placing the IPX1/IPX2 roofs
or anti arc IPX1/IPX2
Wall-mounted cubicle IPX1 roof
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the angle bracket (2) on the wall using
two screws.
2/ Fit the sheet (1) onto the cubicle using four screws
(B) for MCset 1 and 6 screws (B) for MCset 2 and
MCset 3.
3/ Attach the roof (3) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (3) on the angle bracket (2) using
two screws (C).
5/ Fit the tunnel with each other using 5 screws
according to the vue (D).
Non wall-mounted cubicle IPX1 roof
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the sheets (1) onto the cubicle using four
screws (B) for MCset 1 and six screws (B) for
MCset 2 and MCset 3 for each sheet.
2/ Attach the roof (2) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
3/ Fit the tunnel with each other using 5 screws
according to the vue (D).
07897301EN.indd
version 05
51
Installation instructions
Wall-mounted cubicle IPX1 roof for
versions 3600 A / 4000 A
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the angle bracket (2) on the wall using
two screws.
2/ Fit the sheet (1) onto the ventilation compartment
using four screws (B) for MCset 1 and 6 screws (B)
for MCset 2 and MCset 3.
3/ Attach the roof (3) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (3) on the angle bracket (2) using
two screws (C).
5/ Fit the tunnel with each other using 5 screws
according to the vue (D).
Non wall-mounted cubicle IPX1 roof
for versions 3600 A / 4000 A
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the sheets (1) onto the ventilation
compartment using four screws (B) for MCset 1
and six screws (B) for MCset 2 and MCset 3
for each sheet.
2/ Attach the roof (2) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
3/ Fit the tunnel with each other using 5 screws
according to the vue (D).
52
version 05
07897301EN.indd
Installation instructions
IPX1 roof on a MTP transition panel
The sheets are fitting by HM6 screws + M6 washers
and HM6 nuts combination (A):
1/ Mount the support sheets (1) first.
2/ Mount the side panel (2).
3/ Mount the roof (3).
4/ Mount the tunnel closing sheets to the front
and rear (4).
5/ Fasten the support sheets of each cubicle to one
another.
6/ Fasten the tunnels of each cubicle to one another.
Wall-mounted cubicle IPX2 roof
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the angle bracket (2) on the wall using
two screws.
2/ Fit the sheet (1) onto the cubicle using four screws
(B) for MCset 1 and 6 screws (B) for MCset 2 and
MCset 3.
3/ Fit the feet (4) onto the cubicle using two screws
(B).
4/ Attach the roof (3) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (3) on the feet (4) using two screws
(C) and on the angle bracket (2) using two screws
(C).
6/ Fit the tunnel with each other using 5 screws
according to the vue (D).
07897301EN.indd
version 05
53
Installation instructions
Non wall-mounted cubicle IPX2 roof
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the sheets (1) onto the cubicle using four
screws (B) for MCset 1 and six screws (B) for
MCset 2 and MCset 3 for each sheet.
2/ Fit the feet (4) onto the cubicle using two screws
(B).
3/ Attach the roof (2) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (2) on the feet (4) using two screws
(C).
5/ Fit the tunnel with each other using 5 screws
according to the vue (D).
Wall-mounted cubicle IPX2 roof for
versions 3600 A / 4000 A
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the angle bracket (2) on the wall using
two screws.
2/ Fit the sheet (1) onto the ventilation compartment
using four screws (B) for MCset 1 and 6 screws (B)
for MCset 2 and MCset 3.
3/ Fit the feet (4) onto the cubicle using two screws
(B).
3/ Attach the roof (3) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (3) on the feet (4) using two screws
(C) and on the angle bracket (2) using two screws
(C).
5/ Fit the tunnel with each other using 5 screws
according to the vue (D).
54
version 05
07897301EN.indd
Installation instructions
Non wall-mounted cubicle IPX2 roof
for versions 3600 A / 4000 A
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
D: HM6 screws + M6 sealing washers and HM6 nuts
combination.
1/ First fit the sheets (1) onto the ventilation
compartment using four screws (B) for MCset 1
and six screws (B) for MCset 2 and MCset 3
for each sheet.
2/ Fit the feet (3) onto the cubicle using two screws
(B).
3/ Attach the roof (2) onto the sheet (1) using two
screws (C) for MCset 1 and three screws (C) for
MCset 2 and MCset 3.
4/ Attach the roof (2) on the feet (4) using two screws
(C).
5/ Fit the tunnel with each other using 5 screws
according to the vue (D).
IPX2 roof on a MTP transition panel
The sheets are fitting by HM6 screws + M6 washers
and HM6 nuts combination (A):
1/ Mount the support sheets (1) first and the feet (5).
2/ Mount the side panel (2).
3/ Mount the roof (3).
4/ Mount the tunnel closing sheets to the front
and rear (4).
5/ Fasten the support sheets of each cubicle to one
another.
6/ Fasten the tunnels of each cubicle to one another.
07897301EN.indd
version 05
55
Installation instructions
Tunnel sheets or IPX1/IPX2 roofs
for RHB cubicle
1/ Mount first the support sheets (1) furthest to the
rear of the cubicle continuing up to those positioned
at the front and the feet (3c)
2/ Mount the sheets (2) on the RHB duct part
3/ Mount the tunnel roof (3a) or the IPX1 roof (3b)
or the IPX2 roof (3c).
4/ Position the sheets of the adjacent cubicles,
installing the components in the order described
above.
5/ Fasten the support sheets of the two cubicles
to one another.
6/ Fasten the roofs of the two cubicles to one another.
* Ventilation compartments for version 3600 A / 4000 A.
Tunnel sheets or IPX1/IPX2 roofs
for RHC cubicle
1/ Mount first the support sheets (1) furthest to the
rear of the cubicle continuing up to those positioned
at the front and the feet (3c)
2/ Mount the access sheets (4).
3/ Mount the tunnel roof (3a) or the IPX1 roof (3b)
or the IPX2 roof (3c).
4/ Position the sheets of the adjacent cubicles,
installing the components in the order described
above.
5/ Fasten the support sheets of the two cubicles
to one another.
6/ Fasten the roofs of the two cubicles to one another.
56
version 05
07897301EN.indd
Installation instructions
Placing the tunnel end sheets
On anti arc tunnel
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
1/ First fit the sheet (1) onto the cubicle with
the screws (C)
2/ Fit the sheet (1) onto the tunnel with the screws (C).
On anti arc tunnel for version
3600 A/ 4000 A
A: front of the cubicle
B: HM6 screws
C: HM6 screws + M6 washers and HM6 nuts
combination.
1/ First fit the sheet (1) onto the cubicle with
the screws (C)
2/ Fit the sheet (1) onto the tunnel with the screws (C).
07897301EN.indd
version 05
57
Installation instructions
On IPX2 tunnel
A: front of the cubicle
B: rear of the cubicle
The sheets are fitting by HM6 screws + M6 washers
and HM6 nuts combination.
1/ Fit the sheet (1) onto the cubicle and onto
the tunnel
2/ Fit the sheet (2) onto the tunnel feet on the front
face
3/ Fit the sheet (3) onto the cubicle, the tunnel
and the sheet (1)
4/ Fit the sheet (4) onto the sheet (1).
58
version 05
07897301EN.indd
Installation instructions
Placing end sheets
On the left end cubicle, place the cage nuts on the
sides.
Note: operations are identical for the right or left ends
of the switchboard.
Make sure that the busbar end cover
is assembled before mounting
the switchboards end covers.
On the left and right end cubicles, place and screw
(M8 screw) the 4 fastening columns of the end sheets
(right and left end of the switchboard).
Assembling cover panels of cubicle ends
Remove the punch-outsat the bottom of panels
to allow the main earth lead to pass through
(1 per panel).
07897301EN.indd
version 05
59
Installation instructions
On the right end cubicle, place the cage nuts on the
sides.
Assemble the end cover panels 1 and 2 (right and left
end of the switchboard).
A: HM8 screws+ M8 washers
B: HM6 screws+ M6 washers
D: assembly of HM8 x 30 screws + M8 washers
and HM8 nut + M8 washers.
60
version 05
07897301EN.indd
Installation instructions
Note: panel 3 is only assembled in the case
of a wall-mounted switchboard.
D: assembly of HM8 x 30 screws + M8 washers
and HM8 nut + M8 washers.
Place the cable sheet 4.
Place the two screws for fitting the cable sheet.
Store the cranks in the front end panel
07897301EN.indd
version 05
61
Installation instructions
Installing fans on versions
3600 A / 4000 A
Top view
Fasten the box using 10 screws A.
Connect the wiring in compartment B of the cubicle.
RHB
Maintenance procedures for vents and insulating
materials in the MCset 17.5 kV Maintenance and
Services Guide now available DEAI03F/ART833120.
62
version 05
07897301EN.indd
Installation of a FU equipped with
electromagnetic locking options
Earthing switch with
electromagnetic locking
For circuit-breaker plug-in and draw-out
operations, the earthing switch must be
operated.
FU delivered with the earthing switch
closed
As electromagnetic locking is not
supplied on installation of the FU, it
must be manually released in order to
operate the earthing switch.
Initial status:
- The earthing switch is closed,
- Selector 4 is in the locked closed
position.
Opening the earthing switch
without auxiliary supply
07897301EN.indd
version 05
Disassemble the VPIS without
disconnecting the wiring.
Insert a screwdriver via the box hole.
Push back and hold in place
the electromagnet (A) using the
screwdriver, then pull towards you
and turn the selector to the right in the
operation position.
Open the earthing switch, inserting
the crank in reference 5 until the
mechanical indicator light changes
status.
Position selector 4 in the locked open
position.
Put back the VPIS.
63
Installation of a FU equipped with
electromagnetic locking options
Plug-in prevention with
electromagnetic locking
Initial status:
- The circuit-breaker is in the withdrawn position.
- The earthing switch is closed.
- The front panel is disassembled to access cable
connections.
To access the cable connection compartment, circuit-breaker plug-in must be
prevented.
As electromagnetic locking is not supplied on installation of the FU, it must be
manually released in order to position the front panel when the operations are
complete.
The locking system is accessible as per the arrow in
the drawing opposite.
Prior to installing the front panels
If lever (A) is positioned as per figure 1, locking is
active and prevents installation of the front panel.
To deactivate the locking, insert a tool (screwdriver)
into the hole placed under the box support and push
the electromagnet rod (B).
Push the lever (A) to position it as per figure 2.
The system is released and the front panel can then
be put back.
Figure 1
Figure 2
64
version 05
07897301EN.indd
Steps to be taken
for tests and inspection
Power frequency dielectric test
This test must be performed by
authorised people.
This test can be carried out in one
single operation.
This preparation requires locking to be
forced.
All circuit-breakers must be plugged-in,
closed, with FU doors open.
It is essential to follow the sequences
here after.
All the TTs must be disconnected during
this test.
The insulation level of the switchgear
can be tested on site. The test voltage
shall be 80 % of the rated shortduration power-frequency withstand
voltage of the switchgear as specified
in clause 7.105 of IEC 62271-1.
More over, one of the outgoing FUs
must have its lower panel open for the
test cable
connection to the injection pin.
Locking forced
Carry out the circuit-breaker plugin operation (refer to the operating
manual).
On FUs not connected to the generator
Remove the shim.
Place the circuit-breaker in the test position,
with the door open.
Raise and block the door lock rod using
a 55 mm U shim.
Surge arrester connection
Press the pushbutton I to close the
circuit-breaker
This operation must only be carried out after dielectric tests,
and before the connection of medium voltage cables to the FU.
Place and fix the connection of each surge arrester.
Refer to the chapter on MV cable connection.
07897301EN.indd
version 05
65
Tests on site
Checking and cocking the
internal arcing detector(1)
This operation has to be made during assembly of the
tunnels (option) or during operation on the roof of the
cubicle.
The internal arcing detector is located
on the roof of the cubicle.
To be operational, it must be in cocking
position.
(1) The internal arcing detector is mounted according
to the internal arcing withstand characteristics of the
cubicle.
Cocking the internal arcing detector:
- Push the metal rod (1) in direction of
the bottom of the cubicle,
- Hang up the rod (1) on the support (2).
1: metal rod,
2: support.
66
version 05
07897301EN.indd
Index
AD, CL-GL, VT cubicles
C
Checking and cocking the internal arcing detector
Coupling of cubicles
Cubicle fitted with IPX1/IPX2 roofs
66
21
10
Description of irons and accessories
Earthing switch control symbols
Earthing switch with electromagnetic locking
Floor quality
Glossary
Handling by rolling
Handling using a sling
Installing busbars
Installing busbars between MTP and the MOTORPACT cubicle
Installing fans on versions 3600 A / 4000 A
Installing the main earth lead
Installing the electric connections of the busbars and MV cables
Land packaging
List of bags and accessories
LV cable routing and connection
Moving part control symbols
MV cable screen earthing
Ocean shipment packaging
Packaging
Placing and adjusting on non earthquake resistant civil engineering works
Placing and adjusting on earthquake resistant civil engineering works
Placing cubicles in a switchboard
Placing end sheets
Placing MV cables on AD cubicle
Placing MV cables on RHC cubicle
Placing the tunnel sheets
Placing the IPX1/IPX2 roofs or anti arc IPX1/IPX2
Placing the tunnel end sheets
Plug-in check
Plug-in prevention with electromagnetic locking
Power frequency dielectric test
Prior to installing the front panels
Recommendations
Removing the mobile part transportation devices
RHB, RHC cubicles
Standard tightening torques
Storage
Surface condition
Transition Panel MTP
Unpacking cubicles
07897301EN.indd
version 05
14
2
63
14
2
12
11
28
32
62
24
26
11
4
46
3
45
11
5
14
16
18
59
35
41
48
51
57
23
64
65
64
3
23
9
4
12
14
10
18
67
68
version 05
07897301EN.indd
Schneider Electric group service centers are there to provide:
- engineering and technical assistance,
- commissioning,
- training,
- preventive and corrective maintenance,
- adaptation work,
- spare parts.
07897301EN - REV. 05 a Schneider Electric Industries SAS All rights reserved.
Call your sales representative who will put you in touch with your nearest
Schneider Electric group service center or directly call the following telephone
number: +33 (0)4 76 57 60 60 Grenoble France.
Schneider Electric Industries S.A.S
As standards, specifications and designs change from time to time, please ask for confirmation
of the information given in this publication.
This document has been printed
on ecological paper.
954 503 439 RCS Nanterre
Capital social : 896 313 776
Publishing: Schneider Electric Industries SAS.
Design: Profil.
Printing:
35 rue Joseph Monier
CS 30323
92506 Rueil Malmaison Cedex
www.schneider-electric.com
07897301EN - REV. 05
01/2009