Saep 383

Approving Third Party Laboratories, Geotechnical Offices and Batch Plants
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (3 votes)
8K views15 pages

Saep 383

Approving Third Party Laboratories, Geotechnical Offices and Batch Plants
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 15

Engineering Procedure

SAEP-383
5 December 2012
Approving Third Party Testing Laboratories,
Geotechnical Engineering Offices and Batch Plants
Document Responsibility: Inspection Engineering Standards Committee

Saudi Aramco DeskTop Standards


Table of Contents
1

Scope............................................................. 2

Conflicts and Deviations................................. 2

Purpose.......................................................... 2

Applicable Documents.................................... 3

Definitions and Acronyms............................... 4

Evaluation and Certification Procedures........ 5

Responsibility and Authority........................... 6

Approval, On-Hold and Withdrawal


of Approval Procedures.......................... 8

Appendix A: Third Party Testing Laboratory


Approval Process Permanent Basis.. 12
Appendix B: Third Party Testing Laboratory
Approval Process One-Time Basis.... 13
Appendix C: Batch Plant Approval Process Permanent Basis............. 14
Appendix D: Batch Plant Approval Process One-Time Basis........................................ 15

Previous Issue: New

Next Planned Update: 5 December 2017


Page 1 of 13

Primary contact: Albarillo, Rodolfo Celino at 966-3-8801496


CopyrightSaudi Aramco 2012. All rights reserved.

Document Responsibility: Inspection Engineering Standards Committee


SAEP-383
Issue Date: 5 December 2012
Approving Third Party Testing Laboratories,
Next Planned Update: 5 December 2017
Geotechnical Engineering Offices and Batch Plants

Scope
This procedure provides minimum requirements for the approval of companies that
intend to qualify as Saudi Aramco approved Third Party Testing Laboratories,
Geotechnical Engineering Offices and Batch Plants.
This procedure does not cover approval of agencies engaged in non-destructive testing
(NDT) as described in SAEP-1140 and related standards and procedures.
Commentary Note:
This procedure does not cover on-site pre-cast yards used for fabricating small
foundations and other similar non-prestressed pre-cast elements. Such pre-cast yards
are subject to the evaluation and approval of the respective Area Project Inspection
Units/Inspection Department.

Conflicts and Deviations


2.1

Conflicts
Any conflict between this SAEP and other applicable Mandatory Saudi Aramco
Engineering Requirements (MSAERs) shall be resolved in writing by the
Company through the Manager, Inspection Department and/or Consulting
Services Department of Saudi Aramco, Dhahran.

2.2

Deviations and Waivers


Any required deviation from the requirements of this procedure shall be
reviewed and approved by the Inspection Department Manager. Direct all
requests to deviate or waive the requirements of this Procedure in writing to the
Manager, Inspection Department, Dhahran, according to the internal company
procedure SAEP-302, Instructions for Obtaining a Waiver of a Mandatory Saudi
Aramco Engineering Requirement.

Purpose
The purpose of this SAEP is to specify the accreditation requirements of Saudi Aramco
and approval procedure of Third Party Testing Laboratories, Geotechnical Engineering
Offices and Batch Plants.
This procedure also clarifies the following processes:
3.1

Process of QMS/technical assessments

3.2

Process of putting an approved entity on On-Hold Status and,


Page 2 of 15

Document Responsibility: Inspection Engineering Standards Committee


SAEP-383
Issue Date: 5 December 2012
Approving Third Party Testing Laboratories,
Next Planned Update: 5 December 2017
Geotechnical Engineering Offices and Batch Plants

3.3
4

Process of withdrawing approvals from approved entities.

Applicable Documents
The latest edition of the following applicable references shall be applied:
4.1

Saudi Aramco References


Saudi Aramco Engineering Procedures
SAEP-301

Instruction for Establishing and Maintaining Saudi


Aramco Engineering Requirements

SAEP-302

Instructions for Obtaining a Waiver of a Mandatory


Saudi Aramco Engineering Requirement

SAEP-1150

Inspection Coverage on Projects

Saudi Aramco Engineering Standards


SAES-A-110

Surveying Coordinates and Datum

SAES-A-112

Meteorological and Seismic Design Data

SAES-A-113

Geotechnical Engineering Requirements

SAES-A-114

Excavation and Backfill

SAES-Q-001

Criteria for Design and Construction of Concrete


Structures

SAES-Q-005

Concrete Foundations

SAES-Q-006

Asphalt and Sulfur Extended Asphalt Concrete


Paving

SAES-Q-012

Criteria for Design and Construction of Precast and


Prestressed Concrete Structure

Saudi Aramco Materials System Specification


09-SAMSS-097

Ready-Mixed Portland Cement Concrete

Saudi Aramco General Instruction


GI-0400-001

Quality Management Roles and Responsibilities


Saudi Aramco Construction Safety Manual

PID Work Instruction


7.5-WI-PID-BP&CTU-01 Batch Plants and Civil Testing Laboratories
Inspection Coverage

Page 3 of 15

Document Responsibility: Inspection Engineering Standards Committee


SAEP-383
Issue Date: 5 December 2012
Approving Third Party Testing Laboratories,
Next Planned Update: 5 December 2017
Geotechnical Engineering Offices and Batch Plants

4.2

Industry Standards and Codes


Process Industry Practice
PIP CVS02010

Geotechnical Engineering Investigation Specification

International Standardization Organization


ISO/IEC 17025:2005

General Requirements for the Competence of


Testing and Calibration Laboratories

ISO 9001:2008

Quality Management Systems-Requirements

American Society for Testing and Materials

ASTM C94

Standard Specification for Ready Mix Concrete

ASTM C1077

Standard Practice for Laboratories Testing Concrete


and Concrete Aggregates for Use in Construction
and Criteria for Laboratory Evaluation

ASTM D2850

Test Method for Unconsolidated, Undrained


Compressive Strength of Cohesive Soils in
Triaxial Compression

ASTM D3666

Standard Specification for Minimum Requirements


for Agencies Testing and Inspecting Road and
Paving Materials

ASTM D3740

Practice for Minimum Requirement of Agencies


Engaged in the Testing of Soils and Rocks

ASTM D4428

Standard Test Method for Crosshole Seismic Testing

ASTM D5778

Standard Test Method for Electronic Friction Cone


and Piezocone Penetration Testing of Soil

ASTM E329

Standard Specifications for Agencies Engaged in


Construction Inspection and/or Testing

Definitions and Acronyms


Assessment: Systematic evaluation of the Saudi Aramco approved Third Party Testing
Laboratories, Geotechnical Engineering Offices and Batch Plants at planned frequencies
using the minimum guidelines of ISO 19011 or ISO/IEC 17025
Batch Plants: Ready-Mix Concrete Batch Plants, Precast Plants and Asphalt Batch
Plants
BP&CTU: Batch Plants and Civil Testing Unit Inspection Department (ID)
approving authority for Third Party Testing Laboratories and Batch Plants
Page 4 of 15

Document Responsibility: Inspection Engineering Standards Committee


SAEP-383
Issue Date: 5 December 2012
Approving Third Party Testing Laboratories,
Next Planned Update: 5 December 2017
Geotechnical Engineering Offices and Batch Plants

CEU: Civil Engineering Unit


CSD: Consulting Services Department
DPIS: Dhahran Projects Inspection Section
Geotechnical Engineering Office (GEO): A Saudi Aramco approved agency
performing geotechnical engineering calculations on Saudi Aramco projects
Geotechnical Third Party Testing Laboratory (GTPTL): A Saudi Aramco approved
Third Party Testing Laboratory with specific approval in the Geotechnical Category
IAU: Inspection Assessment Unit
ID: Inspection Department
ISSD: Inspection Support Services Division
P&SPD: Projects and Strategic Purchasing Department
PID: Projects Inspection Division
QMS: Quality Management System
Survey: Evaluation of compliance with Saudi Aramco requirements and vendors
quality management system of new Third Party Testing laboratories, Geotechnical
Engineering Offices and Batch Plants for Saudi Aramco approval
Third Party Testing Laboratory (TPTL): A Saudi Aramco approved service
provider to perform testing for Saudi Aramco projects
6

Evaluation and Certification Procedures


6.1

Third Party Testing Laboratories


In order to be qualified as a Saudi Aramco approved Third Party Testing
Laboratory (any material), an entity shall have ISO/IEC 17025 or
SASO/ISO 17025 accreditation. The approval of each laboratory shall be based
on the Test Standards listed in its ISO 17025 accreditation.
Commentary Note:
In situations where a test standard is not listed in the accreditation certificate of
any of the Saudi Aramco approved third party testing laboratory and if required by
a Saudi Aramco proponent, additional testing capabilities may be added on onetime basis only to its approval list based on recommendations from subjectmatter-experts (SME) or Responsible Standardization Agent (RSA) from either
Inspection Department or Consulting Services Department.

Page 5 of 15

Document Responsibility: Inspection Engineering Standards Committee


SAEP-383
Issue Date: 5 December 2012
Approving Third Party Testing Laboratories,
Next Planned Update: 5 December 2017
Geotechnical Engineering Offices and Batch Plants

6.2

Geotechnical Third Party Testing Laboratories


In order to be qualified as a Saudi Aramco approved Geotechnical Third Party
Testing Laboratory, an entity shall have ISO/IEC 17025 accreditation showing
under the scope of accreditation the standards listed below, including the tests
required to support these standards.

6.3

ASTM D 2850

Test Method for Unconsolidated, Undrained


Compressive Strength of Cohesive Soils in Triaxial
Compression

ASTM D 4428

Standard Test Method for Crosshole Seismic Testing

ASTM D5778

Standard Test Method for Electronic Friction Cone


and Piezocone Penetration Testing of Soil

Geotechnical Engineering Offices


In order to qualify as Saudi Aramco approved Geotechnical Engineering Office,
an entity shall be ISO 9001:2008 certified. The GEO shall utilize only a Saudi
Aramco-approved Geotechnical Third Party Testing Laboratory for obtaining
field data and other soil engineering properties.

6.4

Batch Plants
Batch Plants shall be ISO 9001:2008 accredited in order to be considered as
Saudi Aramco approved entity. Furthermore, all aggregate stockpiles or other
ingredients and plant equipment inside the perimeter fence of a Saudi Aramco
approved Batch Plant shall be in compliance with Saudi Aramco requirements
or Saudi Aramco equivalent Industry Standards.

6.5

Re-assessment and Renewal of Accreditation

Re-survey
Re-survey every two years shall be carried out by ID for TPTLs, GTPTLs &
BPs and by CSD for GEOs to confirm that the quality system and technical
capabilities remain in compliance with the accreditation requirements.

Responsibility and Authority


7.1

Third Party Testing Laboratories


The following are Inspection Department (ID) responsibilities:
7.1.1

Survey and approve/disapprove Third Party Testing Laboratories based


on Section 6.1.
Page 6 of 15

Document Responsibility: Inspection Engineering Standards Committee


SAEP-383
Issue Date: 5 December 2012
Approving Third Party Testing Laboratories,
Next Planned Update: 5 December 2017
Geotechnical Engineering Offices and Batch Plants

7.2

7.1.2

Spot check Technical and QMS implementation.

7.1.3

Administer issuance and withdrawal of Civil Testing Technician


Approval card.

7.1.4

Conduct unannounced focus assessments.

Geotechnical Third Party Testing Laboratories


7.2.1

The following are Consulting Services Department (CSD) responsibilities:


7.2.1.1

Provide technical assistance/consultancy services during field


and laboratory processes, as requested by a Saudi Aramco
organization.

7.2.1.2

Perform basic site and/or laboratory evaluation on non-routine


geotechnical tests, as requested by a Saudi Aramco organization.
Commentary Note:
This evaluation may be limited to reviewing and observing test
procedures, calibration certificates and general condition of the
testing equipment.

7.2.1.3
7.2.2

7.3

Research on current equipment or tools that could be added to


upgrade field testing.

The following are Inspection Department (ID) responsibilities:


7.2.2.1

Survey and approve/disapprove Geotechnical Third Party


Testing Laboratories based on Section 6.2.

7.2.2.2

Monitor technical and QMS implementation.

7.2.2.3

Conduct unannounced focus assessments.

Geotechnical Engineering Offices


7.3.1

The following are Consulting Services Department (CSD)


responsibilities:
7.3.1.1

Evaluate, survey and approve/disapprove Geotechnical


Engineering Offices (GEO).

7.3.1.2

Verify internal quality assurance system in report preparations.

7.3.1.3

Review and approve organizational charts and manpower levels


to ensure compliance with PIP CVS02010 and SAES-A-113.
Page 7 of 15

Document Responsibility: Inspection Engineering Standards Committee


SAEP-383
Issue Date: 5 December 2012
Approving Third Party Testing Laboratories,
Next Planned Update: 5 December 2017
Geotechnical Engineering Offices and Batch Plants

7.3.2

7.4

7.3.1.4

Review CVs and approve geotechnical/design personnel to


ensure compliance with PIP CVS02010 and SAES-A-113.

7.3.1.5

Review and evaluate geotechnical analyses tools (software),


geotechnical engineering references and codes.

7.3.1.6

Review and evaluate geotechnical reports to determine


geotechnical office capability to produce a geotechnical report
in compliance with PIP CVS02010 and SAES-A-113.

The following are Inspection Department (ID) responsibilities:


7.3.2.1

Verify compliance with ISO 17025/ISO 9001:2008 or


SASO/ISO 17025 accreditation.

7.3.2.2

Monitor compliance with ISO 17025/ISO 9001:2008 or


SASO/ISO 17025 QMS implementation.

Batch Plants
The following are Inspection Department (ID) responsibilities:

7.4.1

Survey and approve/disapprove Batch Plants.

7.4.2

Spot check technical and QMS implementation.

7.4.3

Conduct periodic technical and quality assessments.

7.4.4

Administer issuance and withdrawal of Batch Plant Internal QC


Technician Approval Card.

Approval, On-Hold and Withdrawal of Approval Procedures


8.1

Approval
8.1.1

Third Party Testing Laboratory (TPTL) Workflow Chart


8.1.1.1

Workflow chart in Appendix A shall be followed for Third


Party Testing Laboratory Approval Process - Permanent Basis
approval.

8.1.1.2

Workflow chart in Appendix B shall be followed for Third


Party Testing Laboratory Approval Process - One-Time Basis
approval.

Page 8 of 15

Document Responsibility: Inspection Engineering Standards Committee


SAEP-383
Issue Date: 5 December 2012
Approving Third Party Testing Laboratories,
Next Planned Update: 5 December 2017
Geotechnical Engineering Offices and Batch Plants

8.1.2

Third Party Testing Laboratory (TPTL) Evaluation Report


BP&CTU shall issue evaluation report to TPTL management. The report
shall be approved by the Sr. Supervisor/DAPIS.

8.1.3

Geotechnical Third Party Testing Laboratory (GTPTL) Evaluation Report


BP&CTU, in coordination with CSD shall issue evaluation report to
GTPTL management. The report shall be approved by the
Sr. Supervisor/DAPIS.

8.1.4

Geotechnical Engineering Office (GEO) Evaluation Report


CSD, in coordination with BP&CTU shall issue evaluation report to
GEO management. The report shall be approved by CSD/Civil
Engineering Unit Supervisor.

8.1.5

8.1.6

Batch Plant Workflow Chart


8.1.5.1

Workflow chart in Appendix C shall be followed for Batch


Plant Approval Process - Permanent Basis approval.

8.1.5.2

Workflow chart in Appendix D shall be followed for Batch


Plant Approval Process - One-Time Basis approval.

Batch Plant Overall Evaluation/Approval


BP&CTU, in coordination with IAU is responsible for the overall
evaluation/approval of Batch Plants. BP&CTU shall evaluate the
technical aspects while IAU shall evaluate quality management systems.
BP&CTU shall issue Batch Plant evaluation report through P&SPD.
The report shall be approved by responsible Project Inspection Division
Head.

8.1.7

ID/SHAREK Update
Responsibility for the update of the List of Approved TPTLs, GTPTLs,
Batch Plants and GEOs in the ID/SHAREK web page shall be as follows:
8.1.7.1

ID is responsible for the update of the List of Approved


TPTLs, GTPTLs and Batch Plants
(http://sharek.aramco.com.sa/orgs/30003279/Shared%20Docm
ents/Forms/AllItems.aspx).

8.1.7.2

CSD is responsible for the update of the List of Approved GEOs


(http://sharek/orgs/30003036/30012126/SitePages/SA%20Approved
%20Geotechnical%20Offices.aspx).
Page 9 of 15

Document Responsibility: Inspection Engineering Standards Committee


SAEP-383
Issue Date: 5 December 2012
Approving Third Party Testing Laboratories,
Next Planned Update: 5 December 2017
Geotechnical Engineering Offices and Batch Plants

8.1.8

One-Time Basis Approval


8.1.8.1

Remote Locations (TPTLs and GEOs)


Approval by ID and/or CSD as described in sections 6.1 to 6.3,
may be granted in locations where there are insufficient Saudi
Aramco approved TPTLs and GEOs.
In such cases, a letter from permanently approved entities
confirming they cannot be accommodated shall be secured by
Contractor.

8.1.8.2

Remote Locations (Batch Plants)


One-Time Basis Approvals for Batch Plants in remote areas
shall be as per 09-SAMSS-097 Section 12.

8.1.8.3

On-site TPTL Branch


For On-site TPTL branch, only those with Saudi Aramco
permanently approved TPTLs shall be considered for one-time
basis approval.

8.2

On-Hold and Withdrawal of Approval Procedures


8.2.1

8.2.2

Grounds for Putting On-Hold and Withdrawal of Approval


8.2.1.1

TPTLs, GTPTLs, GEOs and Batch Plants shall be subjected to


be put On-Hold or approval removed, due to, but not limited
to violations with potential severe impact to product/service.

8.2.1.2

For committing serious violations such as unethical business


action, Health, Safety and Environmental violations, etc.,
immediate On- Hold status shall be implemented.

Duration of On-Hold Penalty


The duration of On-Hold penalty shall be determined by the
Sr. Supervisor, DPIS for TPTLs, GTPLs, & Batch Plants and by the
Supervisor, CEU/CSD for GEOs.

8.2.3

Removal from Saudi Aramco ID/CSD webpage/SHAREK Approval List


Any TPTL, GTPTL, GEO or Batch Plant that have been put ON-HOLD
for more than six (6) months without any corrective action on violations
mentioned above after the Hold period had elapsed, shall be removed

Page 10 of 15

Document Responsibility: Inspection Engineering Standards Committee


SAEP-383
Issue Date: 5 December 2012
Approving Third Party Testing Laboratories,
Next Planned Update: 5 December 2017
Geotechnical Engineering Offices and Batch Plants

from the Saudi Aramco list of approved TPTLs, GTPTLs, GEOs or


Batch Plants in the ID/CSD webpage/SHAREK.
A letter for withdrawal of approval notification shall be sent by the
Supervisor of CEU/CSD for GEOs and by the Sr. Supervisor of DPIS for
the other service providers under this Procedure.

5 December 2012

Revision Summary
New Saudi Aramco Engineering Procedure.

Page 11 of 15

Document Responsibility: Inspection Engineering Standards Committee


SAEP-383
Issue Date: 5 December 2012
Approving Third Party Testing Laboratories,
Next Planned Update: 5 December 2017
Geotechnical Engineering Offices and Batch Plants

Appendix A: Third Party Testing Laboratory Approval Process Permanent Basis


Third Party Testing
Laboratory

Contracting

Secure Vendor Number


from Contracting Dept

Issue Vendor Number

BP&CTU

Submits Required
Documentation Package for
Approval

Yes

Civil Testing Lab?

Evaluate
Documentation
Package
(Civil Testing Lab)

No

Evaluate
Documentation
Package
(Other Testing Lab)

No

ISO 17025
Compliant?
Yes

Rectify Corrective
Action

ISO 17025
Compliant?

Yes

Conduct
Lab Survey
No

Issue Corrective
Action

No

Compliant?

Yes

Approves 3rd Party


Laboratory / Agency

Update ID
Website & Issue
Lab Approval

Page 12 of 15

Document Responsibility: Inspection Engineering Standards Committee


SAEP-383
Issue Date: 5 December 2012
Approving Third Party Testing Laboratories,
Next Planned Update: 5 December 2017
Geotechnical Engineering Offices and Batch Plants

Appendix B: Third Party Testing Laboratory Approval Process One-Time Basis


Third Party Testing
Laboratory

SAPMT

Responsible Project
Inspection Section

BP&CTU

Page 13 of 15

Document Responsibility: Inspection Engineering Standards Committee


SAEP-383
Issue Date: 5 December 2012
Approving Third Party Testing Laboratories,
Next Planned Update: 5 December 2017
Geotechnical Engineering Offices and Batch Plants

Appendix C: Batch Plant Approval Process Permanent Basis

Vendor

Submit
REQUEST FOR PLANT
APPROVAL

P&SPD (Purchasing)

BP&CTU

Process REQUEST
FOR PLANT
APPROVAL

Evaluates REQUEST
FOR PLANT
APPROVAL

REQUEST FOR
PLANT APPROVAL
acceptable?

No

Yes

Conducts Site / Plant


Evaluation / Survey

Site / Plant Evaluation /


Survey Acceptable?

Yes
No

Rectify Corrective
Action

Plant Approved

Notify Vendor of
Corrective Action
Required

Notify Vendor of
Approval

Issue Corrective
Action

Update ID Website &


Issue
Plant Approval

Page 14 of 15

Document Responsibility: Inspection Engineering Standards Committee


SAEP-383
Issue Date: 5 December 2012
Approving Third Party Testing Laboratories,
Next Planned Update: 5 December 2017
Geotechnical Engineering Offices and Batch Plants

Appendix D: Batch Plant Approval Process One-Time Basis


Contractor

Conduct Initial
Plant Survey

SAPMT

Process Request
for Approval

Responsible Project
Inspection Section

BP&CTU

Evaluate
Package

Review Package

Submit Request
for Approval
Yes

Comply with
requirements?

Complete?
No

Yes

Conducts Plant
Survey /
Evaluation

No

Compliance

No
Yes
Rectify Corrective
Action

Plant Approved

Notify Contractor
of Corrective
Action Required

Notify SAPMT of
Corrective Action
Required

Issue Corrective
Action

Notify Contractor
of Plant Approval

Notify SAPMT of
Plant Approval

Update ID
Website & Issue
Plant Approval

Page 15 of 15