Create a disclaimer relative to the acceptance of the facility clearly identifying the items that are not
acceptable or does not have proper result documentation forwarded by the party turning over the site.
Disclaimer: All items not listed will not be accepted without proper documents and test results and
shall not be held liable. This is the minimum requirement and in the event that the building guidelines is
strictly enforced this shall be govern.
Make a standard turnover acceptance document/form for all trades, that will include the following:
Kick-off and turn-over of documents (Internal)
External Kick-off meeting
Mobilization
Safety Orientation
Inspection of deliveries in accordance to specifications (done each time there are deliveries
from sub-con)
General Implementation of works
Site Survey
Prior to installing any fire detection system, the contractor shall survey the site
to determine job conditions will not impose any obstructions that would
interfere with the safe and satisfactory placement of the system. The
arrangements to remove any obstructions with the Project Manager need to be
determined at that time.
Roughing-In piping Works
All piping installations shall run parallel/perpendicular to building grid lines. No
diagonal runs shall be allowed and all bends and offsets shall be avoided as
much as possible.
Pipe supports shall have a minimum of 1.5 meter between supports (GI wires
and similar to this shall not accepted)
QUALITY GUIDELINES AND
METHODOLOGY
Document No
W-QAG-SC01
Effectivity
Date
ACCESS CONTROL
Issue
02-Jan-13
Rev
Page
Total
No
No
Pages
No conduits shall be used in any system smaller than 20mm diameter electric
trade size, nor shall have more than (4) 90 degree bends in any one run and
where necessary, pull boxes shall be provided as directed.
Clamps shall be attached to the masonry walls by means of expansion shield or
masonry screw. Approved beam clamps or equivalent should be used to attach
conduits to exposed steel works.
For cutting pipes, pipe cutter or hacksaw can be used to cut pipes to desired
lengths. Ensure that cuts are made perpendicular to the pipe length, keeping
the cuts square. Debris and shavings from cuts must be removed in order to
keep sampling ports free of obstruction.
Wiring / Cabling Works
Proper splicing of wires
Splicing of wires shall be done only on pull boxes
Proper insulation of electrical tapes and rubber tape on required and
exposed feeder termination/splicing.
As per design wire size should be installed.
Applicable terminal lugs and eye lugs should be mounted well & tightened to
eliminate loose contact.
Installation of Smoke detector, FACP and Annunciator
Shall be implemented as per design instruction, for construction plans and
noted in general notes.
For peaked or sloped ceilings, install the alarm within 3 feet of the peak but not
within the apex of the peak.
Wall mounted alarms should not be placed more than 12 inches from the
ceiling
Smoke detectors should be installed at least 10 feet from any cooking
appliances.
Smooth ceiling spacing shall not exceed 30 feet (9 m).
QUALITY GUIDELINES AND
METHODOLOGY
Document No
W-QAG-SC01
Effectivity
ACCESS CONTROL
Date
02-Jan-13
Issue
Rev
Page
Total
No
No
Pages
Fire-Alarm Control Unit: Surface mounted, with tops of cabinets not more than
72 inches (1830 mm) above the finished floor.
Annunciator: Install with top of panel not more than 72 inches (1830 mm)
above the finished floor.
Functionality Test
Conventional Alarm System
Remove cover of each smoke detector and proceed to disconnect one
wire from the device
The fire alarm panel should annunciate a trouble condition on the
signal circuit
If the annunciator confirms the signal, the device can be reconnected
and remounted to the wall or ceiling.
Repeat the process to each conventional device.
Interfacing
Upon completion of the installation, the system shall be subjected to
complete functional and operational test in place of each detector.
Upon actuation of any smoke detectors an audible alarm shall sound
the FACP continuously; a tone generated alarm with pre-recorded
message shall sound at the floor level in alarm condition. The LCD
display at the FACP shall indicate the area in alarm Connecting
Hardware Reports