PERMOHONAN PELAN KERANA MENDIRIKAN SATU UNIT
RUMAH BANGLO 1 TINGKAT DI ATAS LOT NO : 13061 GM
4952, BUKIT TO BENG, MUKIM KUALA NERUS, DAERAH
KUALA NERUS, TERENGGANU DARUL IMAN.
RC DESIGN CALCULATION
PEMILIK
FATIMAH@MEK BINTI OMAR
I/C NO: 500731-11-5102
NO.126, KAMPUNG KESOM, MANIR,
21200 KUALA TERENGGANU,
TERENGGANU DARUL IMAN.
PERMOHONAN PELAN KERANA MENDIRIKAN SATU UNIT RUMAH
BANGLO 1 TINGKAT DI ATAS LOT NO : 13061 GM 4952, BUKIT TO
BENG, MUKIM KUALA NERUS, DAERAH KUALA NERUS,
TERENGGANU DARUL IMAN.
DESIGN DATA
1. Structural calculations in accordance to BS 8110 limit state design.
2. Brickwall
a. 4 thick on beam = 2.6kN/m2
3. Characteristic strength of material
a. Fy = 460 N/mm2 (HT bar)
b. Fy = 250 N/mm2 (MS bar)
c. Fcu = 25 N/mm2
4. Allowable soil bearing pressure = 100 kN/m2
5. Density of concrete = 24 kN/mm2
ROOF FLOOR
CALCULATION
Type in your company name here;
19-10-2016, Wednesday, 21:59:6
BEAM MARK: RB1
FULL PATHNAME: D:\FAIRUZ\2016\BANGLO\NAZROL oktober banglo fatimah b.tok
beng\rc\RB\RB1.oo1
DESIGN THE SUPPORT MOMENT FOR MOST CRITICAL LIVE LOAD PATTERN
DESIGN FOR SUB-FRAME BEAM
ALONG GRID : 2;/B-G;
Sub-frame Beam End Support Condition's Parameter is PIN, i.e. ZERO
MOMENT
CodeOfPractice
BS8110:1985
Span No
Span-m
RB1
RB1A
RB1B
RB1C
Support
No.
3.00
3.30
5.10
3.60
fys
460
0.00
0.00
0.00
0.00
0.00
Load Type
X2
fyv
250
cover
35
span
4
cantilever
Nil
Width-mm Depth-mm F-width F-depth
125
125
125
125
350
350
350
350
Upper column
Height-m Width-mm Depth-mm
B
C
D
F
G
Span
L.L.
No
m
fcu
25
0
0
0
0
0
0
0
0
0
0
125
125
125
125
0
0
0
0
Lower column
Height-m Width-mm Depth-mm
3.60
3.60
3.60
3.60
3.60
LoadingSource
225
125
225
125
225
D.L.
125
225
200
225
125
L.L.
kN;kN/m
1
1
udl
udl
SelfWeight
1: INPUT
1.05
3.00
0.00
0.75
2
2
udl
udl
SelfWeight
1: INPUT
1.05
3.00
0.00
0.75
3
3
udl
udl
SelfWeight
1: INPUT
1.05
3.00
0.00
0.75
4
4
udl
udl
SelfWeight
1: INPUT
1.05
3.00
0.00
0.75
X1
m
D.L.
kN;kN/m
========================================================================
DESIGN FOR DEAD LOAD AND LIVE LOAD:
Design for the following load factors:Dead Load = 1.40;
Live Load = 1.60
Wind Load = 0.00
1.40*DEAD LOAD & 1.60*LIVE LOAD FACTORED MOMENT-kNm
Span No Left
LFace
Span
RFace
Right
CutSpan
RB1
RB1A
RB1B
RB1C
-0.0
-6.7
-13.3
-13.9
-0.6
-5.5
-11.6
-12.2
5.7
3.1
10.0
6.6
-5.5
-10.5
-12.8
-0.6
Moment & Shear Curtailment, CutSpan is at
Design for Moment at support centre
-6.9
-11.8
-14.8
-0.0
-0.4
-4.2
-0.0
-3.7
25 percent of Span
1.40*DEAD LOAD & 1.60*LIVE LOAD FACTORED SHEAR-kN
Span No Left
LFace
CutSpan RFace
Right
RB1
8.9
RB1A
11.2
RB1B
17.7
RB1C
16.3
Design for Shear
Span
No.
AREA OF REBAR-mm2
Left Span Right
RB1
RB1A
RB1B
RB1C
Support
No.
B
C
D
F
G
Span
No
8.4
7.5
11.9
10.5
8.1
13.1
17.0
9.5
17.5
15.5
10.1
9.1
at support centre
REBAR ARRANGEMENT -Top/Bottom
Left
Span
Right
Ten/Com
%Steel
65
57
65
65
65
57
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1 0.15
2T12= 2x1 0.15
Bot
65
57
65
65
99
57
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1 0.23
2T12= 2x1 0.15
Bot
113
57
65
83
126
57
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1 0.29
2T12= 2x1 0.15
Bot
118
57
65
65
65
57
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1 0.27
2T12= 2x1 0.15
Bot
Column Moment-kNm
Upper
Lower
0.0
0.0
0.0
0.0
0.0
12.6
13.7
18.2
9.6
Stress-N/mm2
CutSpan R
0.3
0.8
2.1
1.5
0.6
Side
Bar
Support Reaction-kN
D.L.
L.L.
5.0
13.0
17.8
20.0
5.2
Vc-N/mm2
CutSpan R
1.1
2.9
3.7
3.8
1.3
Link
S
Defl'n
ratio
RB1
0.23 0.20 0.33
0.57 0.57 0.57 1R 6-200 1R 6-200 1R 6-200 6.24
RB1A
0.29 0.21 0.36
0.57 0.57 0.57 1R 6-200 1R 6-200 1R 6-200 5.67
RB1B
0.46 0.25 0.48
0.57 0.57 0.57 1R 6-200 1R 6-200 1R 6-200 3.67
RB1C
0.42 0.26 0.25
0.57 0.57 0.57 1R 6-200 1R 6-200 1R 6-200 5.20
========================================================================
Type in your company name here;
19-10-2016, Wednesday, 21:59:6
BEAM MARK: RB4
FULL PATHNAME: D:\FAIRUZ\2016\BANGLO\NAZROL oktober banglo fatimah b.tok
beng\rc\RB\RB4.oo1
DESIGN THE SUPPORT MOMENT FOR MOST CRITICAL LIVE LOAD PATTERN
DESIGN FOR SUB-FRAME BEAM
ALONG GRID : 5;/D-F;
Sub-frame Beam End Support Condition's Parameter is PIN, i.e. ZERO
MOMENT
CodeOfPractice
BS8110:1985
Span No
Span-m
RB4
RB4A
Support
No.
3.85
1.25
fys
460
fyv
250
cover
35
span
2
cantilever
Nil
Width-mm Depth-mm F-width F-depth
125
125
350
350
125
125
Upper column
Height-m Width-mm Depth-mm
D
E1
F
Span
L.L.
No
m
fcu
25
0.00
0.00
0.00
0
0
0
Load Type
X2
0
0
Lower column
Height-m Width-mm Depth-mm
0
0
0
3.60
3.60
0.00
LoadingSource
225
125
0
D.L.
200
225
0
L.L.
kN;kN/m
1
1
udl
udl
SelfWeight
4: INPUT
1.05
3.00
0.00
0.75
2
2
udl
udl
SelfWeight
4: INPUT
1.05
3.00
0.00
0.75
X1
m
D.L.
kN;kN/m
========================================================================
DESIGN FOR DEAD LOAD AND LIVE LOAD:
Design for the following load factors:Dead Load = 1.40;
Live Load = 1.60
Wind Load = 0.00
1.40*DEAD LOAD & 1.60*LIVE LOAD FACTORED MOMENT-kNm
Span No Left
LFace
Span
RFace
Right
CutSpan
RB4
RB4A
-0.0
-9.3
-1.0
-8.1
8.3
0.0
-8.5
-0.4
Moment & Shear Curtailment, CutSpan is at
Design for Moment at support centre
-10.2
-0.0
-0.0
-6.3
25 percent of Span
1.40*DEAD LOAD & 1.60*LIVE LOAD FACTORED SHEAR-kN
Span No Left
LFace
CutSpan RFace
Right
RB4
10.7
10.0
9.3
15.1
RB4A
11.8
11.0
9.6
3.6
Design for Shear at support centre
Span
No.
AREA OF REBAR-mm2
Left Span Right
RB4
RB4A
Support
No.
D
E1
F
Span
No
REBAR ARRANGEMENT -Top/Bottom
Left
Span
Right
Ten/Com
%Steel
65
57
65
68
85
57
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1 0.20
2T12= 2x1 0.15
Bot
78
57
65
65
65
57
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1 0.18
2T12= 2x1 0.15
Bot
Column Moment-kNm
Upper
Lower
0.0
0.0
0.0
15.9
-3.1
Stress-N/mm2
CutSpan R
2.2
0.9
0.0
Side
Bar
Support Reaction-kN
D.L.
L.L.
6.6
16.0
-1.8
Vc-N/mm2
CutSpan R
1.3
3.0
0.5
Link
S
Defl'n
ratio
RB4
0.28 0.24 0.42
0.57 0.57 0.57 1R 6-200 1R 6-200 1R 6-200 4.86
RB4A
0.31 0.25 0.09
0.57 0.57 0.57 1R 6-200 1R 6-200 1R 6-200 14.96
========================================================================
Type in your company name here;
19-10-2016, Wednesday, 21:59:6
BEAM MARK: RB12
FULL PATHNAME: D:\FAIRUZ\2016\BANGLO\NAZROL oktober banglo fatimah b.tok
beng\rc\RB\RB12.oo1
DESIGN THE SUPPORT MOMENT FOR MOST CRITICAL LIVE LOAD PATTERN
DESIGN FOR SUB-FRAME BEAM
ALONG GRID : C;/2-7;
Sub-frame Beam End Support Condition's Parameter is PIN, i.e. ZERO
MOMENT
CodeOfPractice
BS8110:1985
Span No
Span-m
RB12
RB12A
Support
No.
4.50
4.50
fys
460
fyv
250
cover
35
span
2
cantilever
Nil
Width-mm Depth-mm F-width F-depth
125
125
350
350
125
125
Upper column
Height-m Width-mm Depth-mm
2
4
7
Span
L.L.
No
m
fcu
25
0.00
0.00
0.00
0
0
0
Load Type
X2
0
0
0
0
0
Lower column
Height-m Width-mm Depth-mm
3.60
3.60
0.00
LoadingSource
225
225
0
D.L.
125
125
0
L.L.
X1
kN;kN/m
1
1
udl
udl
SelfWeight
12: INPUT
1.05
3.00
0.00
0.75
2
2
2
udl
udl
point load
SelfWeight
12: INPUT
Sec Bm
1.05
3.00
6.68
0.00
0.75
1.24
D.L.
kN;kN/m
1.50
========================================================================
DESIGN FOR DEAD LOAD AND LIVE LOAD:
Design for the following load factors:Dead Load = 1.40;
Live Load = 1.60
Wind Load = 0.00
1.40*DEAD LOAD & 1.60*LIVE LOAD FACTORED MOMENT-kNm
Span No Left
LFace
Span
RFace
Right
CutSpan
RB12
RB12A
-0.0
-22.4
-0.7
-20.7
10.1
16.4
-20.7
-0.9
Moment & Shear Curtailment, CutSpan is at
Design for Moment at support centre
-21.9
-0.0
-5.9
-0.0
25 percent of Span
1.40*DEAD LOAD & 1.60*LIVE LOAD FACTORED SHEAR-kN
Span No
RFace
Right
RB12
11.8
11.4
12.6
19.9
RB12A
28.0
27.6
20.3
14.6
Design for Shear at support centre
20.4
15.1
Span
No.
LFace
CutSpan
AREA OF REBAR-mm2
Left Span Right
RB12
RB12A
Support
No.
2
4
7
Span
No
Left
65
57
65
84
199
57
65
141
194
57
2T12= 2x1
2T12= 2x1
65
70
Stress-N/mm2
CutSpan R
2T12= 2x1
2T12= 2x1
Ten/Com
%Steel
2T12= 2x1 0.44
2T12= 2x1 0.15
Side
Bar
Bot
2T12= 2x1 2T12= 2x1 2T12= 2x1 0.46
2T12= 2x1 2T12= 2x1 2T12= 2x1 0.16 Bot
Column Moment-kNm
Upper
Lower
0.0
0.0
0.0
REBAR ARRANGEMENT -Top/Bottom
Left
Span
Right
1.1
0.9
0.0
Support Reaction-kN
D.L.
L.L.
6.4
28.4
8.5
Vc-N/mm2
CutSpan R
1.5
5.3
1.8
Link
S
Defl'n
ratio
RB12
0.31 0.33 0.53
0.57 0.57 0.57 1R 6-200 1R 6-200 1R 6-200 4.16
RB12A
0.73 0.53 0.39
0.57 0.57 0.57 1R 6-200 1R 6-200 1R 6-200 3.41
========================================================================
GROUND FLOOR
CALCULATION
Type in your company name here;
19-10-2016, Wednesday, 21:59:6
BEAM MARK: GB1
FULL PATHNAME: D:\FAIRUZ\2016\BANGLO\NAZROL oktober banglo fatimah b.tok
beng\rc\GB\GB1.oo1
DESIGN THE SUPPORT MOMENT FOR MOST CRITICAL LIVE LOAD PATTERN
DESIGN FOR SUB-FRAME BEAM
ALONG GRID : 2;/B-G;
Sub-frame Beam End Support Condition's Parameter is PIN, i.e. ZERO
MOMENT
CodeOfPractice
BS8110:1985
Span No
Span-m
GB1
GB1A
GB1B
GB1C
Support
No.
3.00
3.30
5.10
3.60
fys
460
3.60
3.60
3.60
3.60
3.60
Load Type
X2
fyv
250
cover
35
span
4
cantilever
Nil
Width-mm Depth-mm F-width F-depth
125
125
125
125
450
450
450
450
Upper column
Height-m Width-mm Depth-mm
B
C
D
F
G
Span
L.L.
No
m
fcu
25
225
125
225
125
225
125
225
200
225
125
125
125
125
125
0
0
0
0
Lower column
Height-m Width-mm Depth-mm
1.20
1.20
1.20
1.20
1.20
LoadingSource
225
125
225
125
225
D.L.
125
225
200
225
125
L.L.
kN;kN/m
1
1
udl
udl
SelfWeight
1: INPUT
1.35
8.45
0.00
0.00
2
2
udl
udl
SelfWeight
1: INPUT
1.35
8.45
0.00
0.00
3
3
udl
udl
SelfWeight
1: INPUT
1.35
8.45
0.00
0.00
4
4
udl
udl
SelfWeight
1: INPUT
1.35
8.45
0.00
0.00
X1
m
D.L.
kN;kN/m
========================================================================
DESIGN FOR DEAD LOAD AND LIVE LOAD:
Design for the following load factors:Dead Load = 1.40;
Live Load = 1.60
Wind Load = 0.00
1.40*DEAD LOAD & 1.60*LIVE LOAD FACTORED MOMENT-kNm
Span No Left
LFace
Span
RFace
Right
CutSpan
GB1
GB1A
GB1B
GB1C
-0.0
-12.5
-26.6
-26.8
-1.1
-10.2
-23.2
-23.3
10.6
5.2
18.6
12.4
-10.8
-19.1
-25.5
-1.1
Moment & Shear Curtailment, CutSpan is at
Design for Moment at support centre
-13.5
-21.6
-29.4
-0.0
-0.0
-6.1
-0.0
-5.4
25 percent of Span
1.40*DEAD LOAD & 1.60*LIVE LOAD FACTORED SHEAR-kN
Span No Left
LFace
CutSpan RFace
Right
GB1
17.1
GB1A
21.6
GB1B
35.0
GB1C
32.2
Design for Shear
Span
No.
AREA OF REBAR-mm2
Left Span Right
GB1
GB1A
GB1B
GB1C
Support
No.
B
C
D
F
G
Span
No
16.2
14.8
20.1
15.2
33.7
18.6
30.6
19.8
at support centre
25.1
26.5
36.1
18.5
REBAR ARRANGEMENT -Top/Bottom
Left
Span
Right
Ten/Com
%Steel
84
73
84
84
84
73
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1 0.15
2T12= 2x1 0.15
Bot
84
73
84
84
138
73
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1 0.25
2T12= 2x1 0.15
Bot
172
73
84
118
192
73
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1 0.34
2T12= 2x1 0.15
Bot
174
73
84
84
84
73
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1 0.31
2T12= 2x1 0.15
Bot
Column Moment-kNm
Upper
Lower
0.3
0.6
1.6
1.0
0.5
23.6
25.1
34.5
17.7
Stress-N/mm2
CutSpan R
0.9
1.7
4.7
3.1
1.5
Side
Bar
Support Reaction-kN
D.L.
L.L.
12.0
31.6
42.7
48.0
12.8
Vc-N/mm2
CutSpan R
0.0
0.0
0.0
0.0
0.0
Link
S
Defl'n
ratio
GB1
0.34 0.29 0.49
0.49 0.49 0.49 1R 6-200 1R 6-200 1R 6-200 8.00
GB1A
0.43 0.30 0.52
0.49 0.49 0.49 1R 6-200 1R 6-200 1R 6-200 7.28
GB1B
0.69 0.37 0.71
0.49 0.49 0.49 1R 6-200 1R 6-200 1R 6-200 4.71
GB1C
0.63 0.39 0.37
0.49 0.49 0.49 1R 6-200 1R 6-200 1R 6-200 6.67
========================================================================
Type in your company name here;
19-10-2016, Wednesday, 21:59:6
BEAM MARK: GB4
FULL PATHNAME: D:\FAIRUZ\2016\BANGLO\NAZROL oktober banglo fatimah b.tok
beng\rc\GB\GB4.oo1
DESIGN THE SUPPORT MOMENT FOR MOST CRITICAL LIVE LOAD PATTERN
DESIGN FOR SUB-FRAME BEAM
ALONG GRID : 5;/D-F;
Sub-frame Beam End Support Condition's Parameter is PIN, i.e. ZERO
MOMENT
CodeOfPractice
BS8110:1985
Span No
Span-m
GB4
GB4A
Support
No.
3.85
1.25
fys
460
125
125
3.60
3.60
0.00
fyv
250
cover
35
span
2
cantilever
Nil
Width-mm Depth-mm F-width F-depth
450
450
125
125
Upper column
Height-m Width-mm Depth-mm
D
E1
F
Span
L.L.
No
m
fcu
25
225
125
0
Load Type
X2
200
225
0
0
0
Lower column
Height-m Width-mm Depth-mm
1.20
1.20
0.00
LoadingSource
225
125
0
D.L.
200
225
0
L.L.
kN;kN/m
1
1
udl
udl
SelfWeight
4: INPUT
1.35
8.45
0.00
0.00
2
2
udl
udl
SelfWeight
4: INPUT
1.35
8.45
0.00
0.00
X1
m
D.L.
kN;kN/m
========================================================================
DESIGN FOR DEAD LOAD AND LIVE LOAD:
Design for the following load factors:Dead Load = 1.40;
Live Load = 1.60
Wind Load = 0.00
1.40*DEAD LOAD & 1.60*LIVE LOAD FACTORED MOMENT-kNm
Span No Left
LFace
Span
RFace
Right
CutSpan
GB4
GB4A
-0.0
-17.7
-2.0
-15.2
16.3
0.0
-17.2
-0.6
Moment & Shear Curtailment, CutSpan is at
Design for Moment at support centre
-20.6
-0.0
-0.0
-11.6
25 percent of Span
1.40*DEAD LOAD & 1.60*LIVE LOAD FACTORED SHEAR-kN
Span No Left
LFace
CutSpan RFace
Right
GB4
21.2
19.8
18.6
30.2
GB4A
22.7
21.2
18.4
6.4
Design for Shear at support centre
Span
No.
AREA OF REBAR-mm2
Left Span Right
GB4
GB4A
Support
No.
D
E1
F
Span
No
REBAR ARRANGEMENT -Top/Bottom
Left
Span
Right
Ten/Com
%Steel
84
73
84
102
131
73
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1 0.23
2T12= 2x1 0.15
Bot
111
73
84
84
84
73
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1
2T12= 2x1 0.20
2T12= 2x1 0.15
Bot
Column Moment-kNm
Upper
Lower
1.7
0.8
0.0
31.8
-5.5
Stress-N/mm2
CutSpan R
5.1
2.3
0.0
Side
Bar
Support Reaction-kN
D.L.
L.L.
16.4
37.6
-3.9
Vc-N/mm2
CutSpan R
0.0
0.0
0.0
Link
S
Defl'n
ratio
GB4
0.42 0.37 0.63
0.49 0.49 0.49 1R 6-200 1R 6-200 1R 6-200 6.24
GB4A
0.45 0.36 0.11
0.49 0.49 0.49 1R 6-200 1R 6-200 1R 6-200 19.21
========================================================================
Type in your company name here;
19-10-2016, Wednesday, 21:59:6
BEAM MARK: GB12
FULL PATHNAME: D:\FAIRUZ\2016\BANGLO\NAZROL oktober banglo fatimah b.tok
beng\rc\GB\GB12.oo1
DESIGN THE SUPPORT MOMENT FOR MOST CRITICAL LIVE LOAD PATTERN
DESIGN FOR SUB-FRAME BEAM
ALONG GRID : C;/2-7;
Sub-frame Beam End Support Condition's Parameter is PIN, i.e. ZERO
MOMENT
CodeOfPractice
BS8110:1985
Span No
Span-m
GB12
GB12A
Support
No.
4.50
4.50
fys
460
125
125
3.60
3.60
0.00
fyv
250
cover
35
span
2
cantilever
Nil
Width-mm Depth-mm F-width F-depth
450
450
125
125
Upper column
Height-m Width-mm Depth-mm
2
4
7
Span
L.L.
No
m
fcu
25
225
225
0
Load Type
X2
125
125
0
0
0
Lower column
Height-m Width-mm Depth-mm
1.20
1.20
0.00
LoadingSource
225
225
0
D.L.
125
125
0
L.L.
X1
kN;kN/m
1
1
udl
udl
SelfWeight
12: INPUT
1.35
8.45
0.00
0.00
2
2
2
udl
udl
point load
SelfWeight
12: INPUT
Sec Bm
1.35
8.45
16.17
0.00
0.00
0.00
D.L.
kN;kN/m
1.50
========================================================================
DESIGN FOR DEAD LOAD AND LIVE LOAD:
Design for the following load factors:Dead Load = 1.40;
Live Load = 1.60
Wind Load = 0.00
1.40*DEAD LOAD & 1.60*LIVE LOAD FACTORED MOMENT-kNm
Span No Left
LFace
Span
RFace
Right
CutSpan
GB12
GB12A
-0.0
-45.1
-1.4
-41.7
18.9
31.4
-40.8
-1.8
Moment & Shear Curtailment, CutSpan is at
Design for Moment at support centre
-43.3
-0.0
-9.8
-0.0
25 percent of Span
1.40*DEAD LOAD & 1.60*LIVE LOAD FACTORED SHEAR-kN
Span No
RFace
Right
GB12
22.8
22.0
25.1
39.7
GB12A
56.0
55.2
40.6
28.6
Design for Shear at support centre
40.5
29.4
Span
No.
Left
CutSpan
AREA OF REBAR-mm2
Left Span Right
GB12
GB12A
Support
No.
2
4
7
Span
No
LFace
84
120
306
73
2T12= 2x1
2T12= 2x1
321
73
84
206
84
103
3T12= 2x2 2T12= 2x1 2T12= 2x1 0.57
2T12= 2x1 2T12= 2x1 2T12= 2x1 0.18 Bot
Column Moment-kNm
Upper
Lower
Stress-N/mm2
CutSpan R
2.8
2.1
0.0
2T12= 2x1
2T12= 2x1
Ten/Com
%Steel
84
73
0.9
0.7
0.0
REBAR ARRANGEMENT -Top/Bottom
Left
Span
Right
3T12= 2x2 0.54
2T12= 2x1 0.15
Side
Bar
Bot
Support Reaction-kN
D.L.
L.L.
15.8
68.4
20.3
Vc-N/mm2
CutSpan R
0.0
0.0
0.0
Link
S
Defl'n
ratio
GB12
0.45 0.49 0.82
0.49 0.49 0.56 1R 6-200 1R 6-200 1R 6-200 5.34
GB12A
1.13 0.80 0.58
0.56 0.49 0.49 1R 6-150 1R 6-200 1R 6-200 3.45
========================================================================
COLUMN
CALCULATION
Type in your company name here;
19-10-2016, Wednesday, 21:59:38
FLOOR PATHNAME : D:\FAIRUZ\2016\BANGLO\NAZROL oktober banglo fatimah b.tok
beng\rc\RB\RB.cln
CODE OF PRACTICE USED IS BS8110:1985
Design for Braced Column in X-direction
Design for Braced Column in Y-direction
Floor D.L.
RB 1.40
L.L.
1.60
fcu
25
fy
460
cover
35
L.L. x-kNm
Load incre.
10
Grid
Column X-Ht
Steel% LLReduction
Y-Ht
D.L.
y-kNm
Area
Rebar
2-A 150
2.0%
0%
150
9600
9600
452
4T12
4-A 150
2.0%
0%
150
9600
9600
452
4T12
7-A 150
2.0%
0%
150
9600
9600
452
4T12
2-B 125
1.6%
0%
225
2700
2700
15
452
4T12
4-B 125
1.6%
0%
225
2700
2700
30
452
4T12
7-B 125
1.6%
0%
225
2700
2700
12
452
4T12
7-B1 125
1.6%
0%
225
2700
2700
19
452
4T12
8-B1 125
1.6%
0%
225
2700
2700
452
4T12
1-C 150
2.0%
0%
150
9600
9600
452
4T12
2-C 225
1.6%
0%
125
2700
2700
22
452
4T12
4-C 225
1.6%
0%
125
2700
2700
37
452
4T12
7-C1 125
1.6%
0%
225
2700
2700
18
452
4T12
8-C1 125
1.6%
0%
225
2700
2700
452
4T12
1-D 150
2.0%
0%
150
9600
9600
452
4T12
2-D 200
1.0%
0%
225
2700
2700
34
452
4T12
5-D 200
1.0%
0%
225
2700
2700
48
452
4T12
7-D 225
1.6%
0%
125
2700
2700
19
452
4T12
7-E 125
1.6%
0%
225
2700
2700
18
452
4T12
8-E 125
1.6%
0%
225
2700
2700
452
4T12
5-E1 225
1.6%
0%
125
2700
2700
26
452
4T12
1-F 150
2.0%
0%
150
9600
9600
452
4T12
2-F 225
1.6%
0%
125
2700
2700
27
452
4T12
3-F 225
1.6%
0%
125
2700
2700
24
452
4T12
6-F 225
1.6%
0%
125
2700
2700
13
452
4T12
7-F 125
1.6%
0%
225
2700
2700
23
452
4T12
8-F 125
1.6%
0%
225
2700
2700
452
4T12
2-G 125
1.6%
0%
225
2700
2700
12
452
4T12
3-G 125
1.6%
0%
225
2700
2700
23
452
4T12
6-G 125
1.6%
0%
225
2700
2700
23
452
4T12
7-G 125
1.6%
0%
225
2700
2700
13
452
4T12
-----------------------------------------------------------------------------------------------SUM OF THE ABOVE TABLE:
498
84 ( I.E. CURRENT AND ABOVE FLOORS
SITTING ON THE ABOVE COLUMN)
SUM OF KEY PLAN LOADING:
498
84 ( I.E. CURRENT FLOOR SITTING ON THE
ABOVE COLUMN)
------------------------------------------------------------------------------------------------
SUMMARY OF TOTAL LOADING WITHOUT LOAD ALLOWANCE OF 10 PERCENT:
Total number of Columnn Section for Analysis
= 30
Total number of Columnn Section being Analysed = 30
Total Dead Load on Column in key plan,
Total Dead Load on Wall in key plan,
DLc =
DLw =
425 kN
0 kN
Total Dead Load in key plan,
DLp = DLc + DLw =
Total Column Selfweight,
Total Dead Load in floor(without wall selfwt),
425 kN *
SWc =
73 kN
DLpSWc = DLp + SWc =
498
kN
Total Live Load on Column in the floor,
LLc =
Total Live Load on Wall in key plan,
LLw =
Total Live Load in key plan,
LLp = LLc + LLw =
84 kN
0 kN
84 kN *
=============================================================================
====================
Total Dead Load in the floor & floors above (all included) =
Total Live Load in the floor & floors above (all included) =
498 kN
84 kN
=============================================================================
====================
THE FOLLOWING LOAD REACTION IS TAKEN AT THE FLOOR ALL THE WAY FROM ROOF:
Total Column Dead Load Reaction by Conventional Design
498
Total Column Live Load Reaction by Conventional Design
84
Total Wall
Dead Load Reaction by 3-D Finite Element Analysis =
Total Wall
Live Load Reaction by 3-D Finite Element Analysis =
kN
kN
kN
kN
Total Column+Wall Dead Load Reaction, TDLp = 498 + 0 = 498 kN
Total Column+Wall Live Load Reaction, TLLp = 84 + 0 = 84 kN
=============================================================================
====================
PAD FOOTING
CALCULATION
Type in your company name here;
19-10-2016, Wednesday, 21:59:41
FILE PATHNAME : D:\FAIRUZ\2016\BANGLO\NAZROL oktober banglo fatimah b.tok
beng\rc\rc.FTP;
CODE OF PRACTICE USED IS BS8110:1985
D.L/L.L-kN
kN/m2
1.4
1.6
fcu
fy
cover
Load incre.
25
460
50
10
Soil pressure100
COLUMN FOUNDATION DESIGN:
Grid
D.L. L.L. W.L. Mxy-kNm/m
Footing,B,L,H
Area,mm2
Rebar
1-C
350
350
250
750
750
T12-150
T12-150
1-D
350
350
250
750
750
T12-150
T12-150
1-F
350
350
250
750
750
T12-150
T12-150
2-A
350
350
250
750
750
T12-150
T12-150
2-B
52
750
750
250
750
750
T12-150
T12-150
2-C
81
14
14
950
950
250
750
750
T12-150
T12-150
2-D
133
23
23
1200
1200
250
750
750
T12-150
T12-150
2-F
102
18
18
1050
1050
250
750
750
T12-150
T12-150
2-G
44
700
700
250
750
750
T12-150
T12-150
3-F
91
16
16
1000
1000
250
750
750
T12-150
T12-150
3-G
83
15
15
950
950
250
750
750
T12-150
T12-150
4-A
350
350
250
750
750
T12-150
T12-150
4-B
113
20
20
1100
1100
250
750
750
T12-150
T12-150
4-C
143
25
25
1250
1250
250
750
750
T12-150
T12-150
5-D
197
33
33
1450
1450
250
785
785
T12-125
T12-125
5-E1
96
17
17
1050
1050
250
750
750
T12-150
T12-150
6-F
46
700
700
250
750
750
T12-150
T12-150
6-G
83
15
15
950
950
250
750
750
T12-150
T12-150
7-A
350
350
250
750
750
T12-150
T12-150
7-B
41
700
700
250
750
750
T12-150
T12-150
7-B1
71
12
12
900
900
250
750
750
T12-150
T12-150
7-C1
67
12
12
850
850
250
750
750
T12-150
T12-150
7-D
70
13
13
900
900
250
750
750
T12-150
T12-150
7-E
67
12
12
850
850
250
750
750
T12-150
T12-150
7-F
85
15
15
950
950
250
750
750
T12-150
T12-150
7-G
46
700
700
250
750
750
T12-150
T12-150
8-B1
30
600
600
250
750
750
T12-150
T12-150
8-C1
30
600
600
250
750
750
T12-150
T12-150
8-E
31
600
600
250
750
750
T12-150
T12-150
8-F
31
600
600
250
750
750
T12-150
T12-150
---------------------------------------------------------------------------1849; 93; SUM OF THE ABOVE: With Load Allowance of 10 percent,
1681; 84; SUM OF THE ABOVE: Without Load Allowance
----------------------------------------------------------------------------
SUMMARY OF COLUMN LOADING WITHOUT LOAD ALLOWANCE OF 10 PERCENT:
Total
Total
kN
Total
Total
kN
Footing SelfWeight
= 92 kN
Column Dead Load Reaction by Convention Design Method,
DLcd = 1589
Column Live Load Reaction by Convention Design Method,
Column Dead Load Reaction with Footing SelfWeight,
LLcd = 84 kN
TDLcd = 1681
SUMMARY OF COLUMN LOADING WITH LOAD ALLOWANCE OF 10 PERCENT:
Total Dead Load (with SelfWeight) = 1848.84 kN
Total Live Load from floors above = 92.83 kN
----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
SUMMARY OF TOTAL LOADING WITHOUT LOAD ALLOWANCE OF 10 PERCENT:
Total Footing SelfWeight of Whole Keyplan = 92 kN
Total Dead & Live Load of Whole Keyplan
= 1765 kN
Total Dead Load Reaction from Stump and Wall = 1681 + 0 = 1681 kN
Total Live Load Reaction from Stump and Wall = 84 + 0 = 84 kN
-------------------------------------------------------------------------------------------------------------------------------------------------------
DRAWING