Balance Civil works Completion Schedule for Juaymah 380 kv BSP project
S.No
Item Description
Date : 30.04.2016
Start date
Finish date
Status as on 02.04.2016
1
1.1
1.2
Walkway around buildings
380kV GIS building - 94% completed and balance
230kV GIS building - 88% completed and balance
work is in progress
work is in progress
31.03.2016
31.03.2016
96% Completed.
95% Completed.
1.3
Control room buiding - 85% completed and balance
work is in progress
07.04.2016
85% Completed.
Communication duct bank and CMH/ CHH - 95% completed.
2.1
Duct bank between CMH 1 to CMH 3 - 85 % Completed.
30.03.2016
100% Completed.
2.2
Duct bank between CMH 2 to Guard house
07.04.2016
Yet to start
05.04.2016
65% completed.
3
3.1
Fire Hydrant trench - 1100 RM
Fire hydrant trench - Raft concrete - 65% Completed.
work is in progress
1000 RM raft concrete completed out of 1100 RM
3.2
Fire hydrant trench - Wall concrete - 55% Completed.
90% completed
work is in progress
20.04.2016
800 RM wall concrete completed out of 1100 RM
55% Completed.
75% completed
MV and LV duvt bank - 90% completed and balance
work is in progress
07.04.2016
90% Completed.
Pump house - room readiness.
work is in progress
20.04.2016
65% completed.
SSD 1 fence system.
work is in progress
30.04.2016
Corner 3 to 4 beam concrete 20% completed
Corner 3 to 4 post fixing work 100% completed
Corner 1 to 4 wire mesh fixing work 75% completed
Corner 1 to 2 wire mesh fixing work 15% completed
Corner 1 to 2 post fixing work 60% completed
Corner 2 to 3 beam lean preparation work in progress(Part-1)
8
Crash Barrier.
work is in progress
30.04.2016
Work is in progress
10.05.2016
207 nos completed out of 274
9
40% completed. Balance
is in progress.
75% completed. Balance
is in progress.
Base coarse laying and compaction
Base coarse laying and compaction 100% completed at part
1,2&3 area
Base coarse laying and compaction 50% completed at part 4
area
40% completed
Base coarse laying and compaction 25% completed at part 10
area
Select fill compaction in progress at part 5 area
10
Asphalt pavement for substation yard area
11
Slope protection concrete
Work is in progress
01.06.2016
22.05.2016
01% completed
30.06.2016.
0% completed