0 ratings0% found this document useful (0 votes) 83 views26 pages1
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here.
Available Formats
Download as DOCX, PDF or read online on Scribd
EXAMPLE 11.6
The floor of a kitchen, measuring 3.20m X 3.001, is to be finished with
marble effect floor tiles each measuring 330 mm x 330mm. If there are
nine tiles ina pack, calculate the number of packs required. Allow 10%
for wastage.
Solution:
3.20 x 3.00 = 9.60 m?
330mm X 330mm
0.33 m X 0.33 m = 0.1089 m?
Area of the floor
Area of one tile
As there are nine tiles in a pack, each pack will cover 0.1089 x 9 or
0.98 m? of the floor.
Area of the floor
Number of p ——
Area of tiles in one pack
cks required =
Oo
0.98
Wastage = 10% of 9.8 = 9.8 x 1 = 0.98
Therefore, number of packs required (including 10% for wastage) =
9.8 + 0.98 = 10.78, say 11EXAMPLE 11.7
The floor of a room, measuring 6.0m X 4.2 m, is to be covered with lamin-
ate flooring. If one pack covers an area of 2.106 m2, calculate the number
of packs required, Consider wastage © 10%.
Solution:
Om x 4.2m
5.20 m?
Area of the floor
Floor area
Number of packs required = —_—fleor area_
f 4 Area covered by one pack
25.2
Wastage ® 10% = 5/100 x 11.97 = 0.6
Number of packs required = 11.97 + 0.6
= 12.57, say 13EXAMPLE 11.8
The 3D view of a room is shown in Figure 11.7. The internal wall and ceil-
ing surfaces require a coat of emulsion paint. Calculate their areas in m?.
Given: Size of the door = 2m x 1m wide
Height of the skirting board = 100mmSolution:
The area of each wall will be calculated separately and added later to find
the total wall area. The areas of the window, door and skirting board have
to be excluded.
Area of wall 1 (see Figure 11.8a) = Length x Height
= 4.0 * (2.9 - 0.1)
= 4.0% 2.8=11.2m?
4.0m
sl
4.0m
le
Wall 1
Wall 3
2.9m Door
2.0m
pot Skirting board roam |
¢
t 7
Figure 11.8Areas (1) 109
Area of wall 2 = Length x Height
5.0 X (2.9 — 0.1)
= 5.0 X 2.8 = 14.0m?
= Gross area of the wall — Area of the door ~ Area of the
skirting board
=4.0 X 2.9 — 2.0 x 1.0— (1.5 X 0.1 + 1.5 X 0.1)
(see Figure 1 1.8b)
= 11.6 — 2.0 - 0.3 = 9.3m?
The details of wall 4 are shown in Figure 11.9.
Area of wall 3
50m |
ware — | waaow | f
Aly 29m
am
2 ace
7
Figure 11.9
Area of wall 4 = Gross area of the wall — Area of the window — Area of
the skirting board
5.0 X (2.9 — 0.1) — 1.2 * 1.2
5.0 x (2.8) — 1.44
= 12.560
Total wall area = 11.2 + 14.0 + 9.3 + 12.56
47.06m*
1g = 5.0 X 4.0 = 20m!11.5.1 Cavity walls The cavity wall of a domestic building consists of brickwork as outer
leaf and blockwork as
iner leaf and the cavity between the Owo filled
with Rockwool. The outer leaf of brickwork is 103mm thick (also
called half brick thick wall). The inner leaf of concrete blocks is
100mm thick. The measurements of bricks and concrete blocks used in
area calculations are shown in Figure 11.10. The number of bricks and
concrete blocks per m? are 60 and 10 respectively.
EXAMPLE 11.9
A cavity wall 5.4 m long and 2.7 m high (Figure 11.10) is to be constructed
using facing bricks and aerated concrete blocks. Find the number of bricks
and blocks required. Allow 5% extra for wastage.
Briek work
cavity
Block work
27m
x
@
Bricks Asrated concrete blocks
‘215 mm long x 65mm high /440 mmm long © 215 mm high
40mm thick mortar
©) Joints
©
ure 11.10 Cavity wall construction,Solution:
Size of a brick without mortar joints = 215 x 102.5 x 65mm
Size of a brick with mortar joints = 225 X 102.5 x 75mm
Size of a block without mortar joints = 440 215 x 100mm
Size of a block with mortar joints = 450 x 225 x 100mm
Area of a brick = 225 x 75 = 16875mm?
Area of a block = 450 x 225 = 101 250mm?
We must have compatible units of all components. Therefore, change the
length and the height of the wall into millimetres. 1 m = 1000mm
Length of the wall = 5.4m = 5400mm
Height of the wall = 2.7m = 2700mm
Area of the wall = 5400 x 2700 = 14580000 mm?
Area of the wall
Area of one brick
14 580 000
= eee = 864
16 875
Number of bricks required =
Areas (1)
Wastage @ 5% = 864 X 5/100 = 43.2, say 44
Total number of bricks = 864 + 44 = 908
Number of blocks required = eee 144
101250
Wastage @ 5% = 144 X 5/100 = 7.2, say 8
Total number of bricks = 144 + 8 = 152
12.3 Mass, volume The density of building materials is an important property that a struc
and density tural engineer has to consider for calculating the forces acting on a build-
The self-weight of building components is permanent and known as
the dead load. The live load on the other hand keeps on changing, andtypical examples are: weight of people using a building. wind force act-
ing on a building etc.:
Mass of a material/component = Density x Volume
EXAMPLE 12.6
A water storage cistern measuring 2.5m x 2.0m x 1.2m high is to be
provided in a building:
(a) Calculate the volume of water when the cistern is filled to 15. cm from
the top rim
(b) Use the volume of water calculated in part (a) to determine the mass
of water, The density of water is 1000 kg/m?
(Q Find the load |force) on the joists supporting the cistern. 1 kg =
9.8 newton (N)
Solution:
(a) Convert 15 cm into metres. To do this divide 15 by 100 as
tem = im
100
5 15
15cm = —2 m=0.15m
100
Depth of water in the cistem = 1.20 — 0.15 = 1.05m
Volume of water = wh
= 2.5 X 2.0 X 1.05 = 5.25m*
(b) Density of water = 1000 kg/m?
This means that 1 m? has a mass of 1000 kg
Mass of 5.25 m? = 5.25 x 1000 = 5250kg
(©) Load (or force) on the joists = 5250 x 9.0 = 51450N
12.4 Concrete mix Concrete is one of the important materials used in the construction of
and its constituents — buildings and civil engineering structures, The constituents of a con-
crete mix are cement, fine aggregates (sand), coarse aggregates (gravel,
blast-furnace slag ete.) and water. Water is added for the chemical reac~
tion between cement and water to take place and produce a solid con-
crete from a semi-fluid state. The amounts of these constituents may be
determined by considering either their volume or mass. If the propor-
tions of cement, sand and gravel are measured by volume, the concrete
mix is known as a nominal mix. Mixing by volume does not take into
account the moisture content of the aggregates, therefore nominal mixes
are used only for minor work. Typical examples of nominal mixes are1:2:4 concrete and 1:3:6 concrete. The 1:2:4 concrete means that it is
prepared by mixing I part cement, 2 parts fine aggregates and 4 parts
coarse aggregates. The volume of water is about 50-60% of the volume
of cement. In this section only nominal mixes are considered.
If we want to prepare 1m? of 1:2:4 concrete mix, the quantities of dry
materials may be calculated as shown below. The volume of cement in
a 25 kg bag is 0.0166 m’.
Assuming the volume of water to be 55% of the volume of cement,
the proportions of the concrete mix may be written as 1:2:4:0.55. The
total of these proportions is 7.55:
Volume of cement = — <1 = 0.132 mi
155
Volume of fine aggregates = oa X 2 = 0.265 m?
Volume of coarse aggregates = i: x 4 = 0.53 m
Volume of water = a X 0.55 = 0.073 mé or 73 litres
‘The coarse aggregates contain a lot of air voids which are filled by the
other ingredients when they are mixed. The final volume of the concrete
mix will be less than I m°, The volume of the dry materials must be
increased by 50% (approximately) to get the required quantity of con-
crete, The detailed calculations are given in Appendix 1.ALT
1:2:4 concrete
Appendix 1 Concrete mix
A concrete mix can be prepared by two methods: (a) mixing by volume
and (b) mixing by mass. In the latter method the mass of cement, fine
aggregates (sand) and coarse aggregates (gravel, crushed stone, crushed
bricks, blast-furnace slag ete.) are calculated for preparing the concrete
mix. In this section, only the former method is described,
If'we want to prepare Im’ of 1:2:4 concrete mix, the quantities of dry
materials may be calculated as shown below: The volume of cement in
a 25kg bag is 0.0166m',
Assuming the volume of water to be 55% of the volume of cement,
the proportions of the concrete mix may be written as 1:2:4:0.55. The
total of these proportions is 7.55:
Comentifine aggregatesicoarse aggregatesiwater
IL 2 4 0.55
Volume of cemer
Volume of fine aggregates = od 2 = 0.265 m?
Volume of coarse aggregates = —!_ x 4 = 053m)
735
Volume of water = —1 x 0,55 = 0,073 m* or 73 litres
755
The coarse aggregates contain a lot of air voids which are filled by
cement, water and fine aggregates when they are mixed.
The mass of each ingredient can be calculated by multiplying its
volume by density:
Mass of 0.132 m* of cement = 0.132 1506 = 198.8kg
Mass of 0.265 m" of sand = 0.265 X 1650 = 437.25kg
Mass of 0.53:m? of gravel = 0.53 1600 = $48 kg
Mass of 0.073 m’ of water = 0.073 1000 = 73 ke
Total = 1557 kgim*The density of fresh concrete is 2350kg/m'
The ratio in which the volumes of the dry materials should be inereased
is 23501557 or 1.5
The volumes of dry materials that will give 1m’ of concrete after
mixing are:
Volume of cement = 0.132 x 1.5 = 0.198m*
Volume of sand = 0.265 * 1.5 = 0.397m*
Volume of gravel = 0.53 x 1.5 = 0.8m"
Volume of water = 0,073 X 1.5 = 0,109m' or 109 litres
Cement:fine aggregates:coarse aggregates: water
13 6 0.55
Volume of cement = * 1 = 0.095 m*
10.55
1
in 5 = 3 = 0.284 m?
Volume of fine aggregates = 7-55
1
Volume of coarse aggregates = —— x 6 = 0.569m?
olume of coarse azerezates = T= m
Volume of water = * 0.55 = 0.052 m} or 52 litres
1
10.55
‘The mass of each ingre
volume by density
nt can be calculated by multiplying its
Mass of 0.095 m* of cement = 0.095 * 1506 = 143.1 kg.
Mass of 0,284 m? of sand = 0.284 X 1650 = 468,6kg
‘Mass of 0.569:m" of gravel = 0.569 X 1600 = 910.4kg,
Mass of 0.052 m' of water = 0.052 x 1000 = 52kg
Total = 1574 kgfm*
The density af fresh concrete is 2350kg/m’ (approx.)
The ratio in which the volumes of the dry materials should
is 2350/1574 or 1.49 (say 1.5)
‘The volumes of dry materials that will give Im! of concrete after
mixing are:
increased,
Volume of cement = 0.095 * 1,5 = 0.143 m*
Volume of sand = 0.284 1.5 = 0.426m*
Volume of gravel = 0.569 x 1.5 = 0.854m*
Volume of water = 0,052 x 1.5 = 0.078m’ or 78 litresEXAMPLE 12.7
A concrete drive to a garage is to be 10 m long, 3 m wide and 150 mm thick.
Calculate:
(a) The volume of concrete required to construct the drive
(b) The quantities of cement, sand and gravel required, if 1:2:4 concrete
is to be used
Solution:
(a) Convert 150mm into metres, as the units of all measurements should
be the same:
150 mm = 12° = 9.15 m
1000
The shape of the drive is a rectangular prism.
Volume of concrete required = lwh
10 X 3X 0.15
= 4.5m?
(b) The quantities of dry materials to make 1 m? are (from Appendix 1)
Cement = 0.198m’; sand = 0.397m’; gravel = 0.8m’; water =
109 litres
The quantities of the above materials to make 4.5 m? are:
Cement = 4.5 X 0.198 = 0.891 m?
Sand = 4.5 X 0.397 = 1.787m*
Gravel 5X08 = 3.60m'
Water = 4.5 X 109 = 491 litres
EXAMPLE 12.8
Figure 12.9 shows the plan of the proposed extension to a building.
Find:
(a) The volume of the earth to be excavated
(b) The volume of concrete required to construct the deep strip foundationPlen
m
8] Extension
Take down existing wall
0.260 m+} } 39m _,) |__2.sm_)
Existing building
(a)
260 mm 260 mm
7 J, oattywal SLY
a
| DPC
r 50mm
GL.
TTR SAY be 0.120.m
Concrete
750 mm
0.5m
Section aa Section b-b
Oo ©
Figure 12.9
Solution:
Figure 12.9 shows the sectional details of the deep strip foundation.
The foundation may be considered to be a rectangular prism; hence
its volume will be the product of the cross-sectional area and the depth.
The width of the trench will be equal to the width of the foundation,
i.e. 500 mm (or 0.5 m). The foundation plan, shown in Figure 12.10, has
been divided into parts A, B and C to simplify the calculations.0.260 + 3.74 + 0.260 + 0.120 = 4.380 m
3
260 mm
§ 500 mm wide foundation trench
260 mm.
‘sl
| -260 mm thick
500 mm wide cavity wall
foundation’ Extension
trench 500 mm
3.740 m
«120 mm
Existing building
Figure 12.10
The total cross-sectional area will be the sum of the areas of parts A, B
and C.
Area of part A = 2.88 X 0.5 = 1.44m?
Area of part B = 4.38 x 0.5 = 2.19m?
Area of part C = Area of part B = 1.44m?
Total area = 1.44 + 2.19 + 1.44 = 5.07 m?
Depth of the trench = 900 mm or 0.9m
Volume of earth = 5.07 X 0.9 = 4.563 m*
Depth of the foundation = 750mm = 0.75m
Volume of concrete = 5.07 X 0.75 = 3.803 m*15.1 Introduction
15.2 Foundations
15 Costing — materials and
labour
LEARNING OUTCOMES:
(2) Calculate the quantities af materials jar a range of construction activities
tb) Work out the cast of matertals
{e) Calculate the cos! of labour for 3 range of construction activities
‘One of the important branches of building technology is to prepare the
estimates of the cost involved in constructing a building. The overall
cost of a project determines its viability and enables the client to arrange
capital for financing the construction. The main components of the cost
‘of constructing a building are the cost of materials, labour, plant and con-
actor's profit
This chapter gives some examples on how to prepare approximate
estimates. The costs of materials and labour are never constant and they
also differ from one region to another. For latest information on the cost
‘of materials, labour and plant reference should be made to publications
which update this information at regular intervals.
‘Conerete is by far the most commenly used material in the construction
‘of foundations of buildings. For plain concrete 1:3:6 concrete mix is
usually used, but for reinforced concrete 1:2:4 of a stronger mix is used.
Asdescribed in Chapter 12, the quantities of cement and aggregates for
preparing a concrete mix may be determined by considering either their
volume or mass. In this section we will consider how to work out the
mass of the cement and the aggregates. This gives a better quality of
concrete as we can take into account the moisture content of the-aggre-
gates if they are not dry.172 Construction Mathematics
Consider a 1:3:6 concrete mix. The density of concrete is approxi-
mately 2400 kg/m’ or in other words, | m* of concrete has a mass of
2400kg. To prepare | m* of concrete the quantities of cement and the
aggregates are:
a % 2400 = 240kg (the quantity of cement
is | part out of 10)
= 720 kg
2 x 2400
10
Coarse aggregates 1440 kg
‘The amount of water depends on where the conerete is 10 be used. For
strip foundations the amount of water could be about 50% of the amount
of cement, giving a water cement ratio of 0.5.
EXAMPLE 15.1
Calculate the cost of materials and labour required to construct the 1:3:6
conerete strip foundation shown in Figure 15.1, given that:
Cost of materials
Cement = £3.60 per 25 kg bag
Fine aggregates = £32.00 per 850 kg jumbo bog,
Coarse aggregates = £32.00 per 850 kg jumbo bag
Labour
Approximate labour hours = 2 per m? for mixing and placing concrete
Hourly rate = £12.00
Solution:
Area of foundation = 2[17.3
776m
7.76 X 0.2
0.6 + 0.6) x 0.6 + (6.3 x 0.6i]
Volume of concrete 3.552 m3
The quantities of materials to prepare 1 m* of concrete are given in see-
tion 15.2, For preparing 3.552 m’ of concrete the quantities af material
and their costs are:
Material Mass
Cement 35% 25kg bags
Fine aggregates 720 ¥ 3.552 3 ¥ 850kg jumbo bags
Coarse aggregates 1440 * 3,552 6 x B50kg jumbo bagsCosting ~ materials and labour 173
ees
7 |
i cutee
@:
ooo
: screens
wo
soni
Figure 15.1
15.3 Cavity walls
Cost of cement = £3.60 x 35 = £126.00
Cost of fine aggregates = 3 = £96.00
Cost of coarse aggregates = £32 x 6 = £192.00
Total cost of materials = £414.00
Labour hours = 2 x 3.552 = 7.104
Labour cost = 7.104 X £12.00 = £85.25
Total cost (materials and labour) = £414.00 + £85.25 = £499.25
‘The cavity walls in dwelling houses consist of a 102.5mm, outer
leaf of bricks and a 100mm thick inner leaf of lightweight concrete174 Constuiction Mathematics
blocks, The space between the (wo leaves, called the cavity, is 50 10
75mm wide and provided with 50mm thick Rockwool or other insula-
tion material suitable for the purpose.
Figure 15.2 shows a brick and a block as they are laid in the con-
struction of walls. The dimensions shown are without the mortar joints,
With 10mm thick mortar joints their dimensions are:
Bricks: 225 > 102.5 x 75mm
Concrete blocks: 450. 100 2 225 mm
i
(@) Brick
215 mm
(8) Concrete block
Figure 15.2
Surface area of | brick = 0.225 x 0.075m = 0.0169 m?
I
Number of bricks per m: = 59.2 say 60)
0.0169
Surface area of | concrete block = 0.450 * 0.225 m = 0,10125m™
L
Number of concrete blocks per m® =
= 9.88 say 10
0.10125Costing ~ materials and labour 175
‘The quantity of mortar required for Im? of brickwork is 0.026 m' and
for Lm’ of blockwork is 0.012m',
EXAMPLE 15.2
Calculate the number of bricks and 100 mm thick aerated concrete blocks,
and the quantities of cement and sand, tw construct a 4,0 m % 2.8m high
cavity wall with a 2.0 m * 1.2 m high window. Allow for 5% extra bricks
and blocks and 10% extra mortar
Labourrates are: £15,00/m? for brickwork and £1 1.30/m? for blockwork
Solution:
Area of the wall = 4.0 X 2.8 — (2X 1.3)
8.8 x 60 = 528
Number of bricks with 5% extra allowance
Number of blocks = 88 X 10 = 88
Number of blocks with 5% extra allowance = 88 % 1.05
Mortar required for brickwork = 0.026 % 8.8 = 0.2288m?
Quantity of mortar with 10% extra allowance = 1.1 X 0.2288 = 0.252 m?
Mortar requited for blockwork = 0.012 x 88 = 0.1056m'
Quantity of mortarwith 10% extra allowance = 1.1% 0.1056 = 0.116 m?
BX 105 = 555
3
Brickwork
Assume the density of 1:3 cement/sand mortar to be 2300 kgim3
Mass of 0.252 m! of mortar = 0.252 x 2300 = 579.6kg
‘Mass of cement = tx 579.6 = 144.9 kg
Mass of sand = + 579.6 = 434.7 kg
Blockwork:
300 kgimn?
116 % 2300 = 266.8kg
Assume the density of 1:6 cement/sand mortar to be
‘Mass of 0.116 m? of mortar
1
Mass of cement = 2X 266.8 = 38,1Tkg,
Mass uf sand =
X 266.8 = 228.69 kg
Total quantity of coment = 144.9 + 38.11 = 183.01kg
Total quantity of sand = 434.7 + 228.69 = 663.39kg,
Cost of labour
Brickwork
15,00 X 8.8 = £132.00
£11.50 X 8.8 = £101.20
Blockworke176 Consuuction Mathematics
15.4 Flooring Softwood boards and chipboard sheets are used as floor covering mater-
ials in dwelling houses. The thickness of these materials depends on the
spacing between the floor joists. For a spacing of 400mm between the
joists, 18mm thick floorboards and chipboard sheets are satisfactory.
‘The coverage provided by tongued and geooved floor boards/chipboard
is slightly Tess than their actual surface area as the tongue of
one board fits into the groove of the next one. A floorboard measuring
2400 x 121 x 18mm provides coverage of 0.272 n°, Figure 15.3 shows
the joists and floorboards of an upper floor.
Tongued and groowed
Figure 15.3. Tongued ane grocved softwood flooring.‘Costing ~ materials and labour 17
EXAMPLE 15,3
Find the cost of providing and fixing:
{a) sofnwoud floorboards in a room measuring 4.5m x 3.9m
{b) chipboard flooring in a raom measuring 5.0m % 4.2m
Floorboards measuring 3000 ¥ 121 X 18mm thick cust £16.99 for
@ pack of five, One pack covers an area of 1,71, Cost of labour is
£9.00hm",
Qne sheet of chipboard mezsuring 2400 * 600 x 18mm thick costs
£5.30, One sheet covers an area of 1.44 m?, Labour cost is £4.50 fm!
Allow wastage @ 10%.
Solution:
fal Area of the floor =
Number of packs of floorboards =
Wastage © 10% = 10.26 x 22 = 1.026
100,
Tolal number of packs required = 10.26 + 1.026 = 11.286 or 12
Cost of material = £16.99 % 12 = £203.88
Labour cost = £9.00 X 17.55 = £157.95
Total cost = £203.88 + £157.95 = £361.83
tb) Area of the room = 3.0% 4.2 = 210m?
‘Area of 1 sheet of chipboard = 2.4 x 0.6 = 1.4m?
Number of sheets required a 14.58
Wastage @ 10% = 14.58 x 14 = 1.458
: Too
Total number of chipboard sheets = 1
Cost of material = £5.30 x 16 = £84.80
Labour cost = 21% £4.50 = £94.50
Total cust = £84.80 + £94.50 = £179.30
+ 1.458 = 16.038 or 16
15.5 Painting, Painting is necessary to give doors, windows, walls ete. a finish that
enhances their appearance and provides protection from dust, dirt and
‘other harmful substances. In this section only the external surfaces of178 Constuetion Mathematics
Walls are considered, Some of the main factors that affect the amount of
paint required are the type of surface, the number of caats and the type
‘of paint.
EXAMPLE 15.4
The front wall of a house, shown in Figure 15.4, s tinished with roughcast
rendering and needs (wo coats of masunry paint, The spreading rale of
paint is 3m? per litre, Find the cost of paint and labour if one 3 litre can
‘of masonry pain{ costs £15.89, and the labour cost is £4.30 per m?
,- 8,
zo, |
g at
BI | 8
g} of “ dpe
3 |
7
000
(All imensions in mm}
Figure 15.4 Front elevation,
Solution:
The net area of the wall is calculated by subtracting the atea of the deor
and window from the total wal! area;
Area of roughest finish on the wall
9.0 x (3.0 = 0.15) = 20% 1.2 = 21% 10
= 25.65 — 2.42.1 =21.15m?
Area of wall
Volume of paint required = — ————__
Paint req Spreading rate of paint
= 2115 — 7.05 bites
3
Two cuats of paint require 2% 7.05 of 14,1 litres of paint
14a
Number of 5 litre cans
82 say 3Costing
materials and labour 179
Cost of paint = £15.89 x 3 = £47.67
Labour cost = 2 (ovals) X 21.15 X £4.30.
Total cost = £47.67 + £181.89 = £229.56
181.89
EXERCISE 15.1
‘The answers to Exercise 15.1 can be found in Appendix 2
For exercises 1 to 4 refer to the relevant example for material
and labour costs
1. Caleulate the cost of materials and labour required to
construct the 13:6 concrete strip foundation shown in
Figure 15.5
50 e600 3
I
(Allimensions in mma)
(@) Foundation plan
750
Deep strip foundation
|/- deer sta
{All dimensions to mim)
(0) Section,
Figure 15.5180)
Construction Mathomatcs
Brickwork
450m wide deop stp foundation
Figure 15.5. (Contimed)
2. Calculate the number of bricks and 100mm thick aerated
concrete blocks, and the quantities of cement and sand, to
construct @ 5.51% 2.7m high cavity wall with Ow
1.801m x 1.2m high windows, Allow for 5% extra bricks
and blocks and 10% extra mortar
2. Find the cost of providing and fixing
{a) Softwood flocrboards in a rourn measuring 5.0m x
42am
{} Chipboard flooringin a room measuring 4.3m X 3.9m
Allow wastage @ 10%
4 The walls of a house, shown in Figure 15.6, ate finished
with rougheast rendering and need lwo coals of masonry
aint, The spreading rate of paint is 3m? per lie. Find the
‘cox of paint and labour if ene 5 litre can of masonry paint
‘cons £15.89, and the labour cus is £4.30 per a”