The document contains requests to make several changes to activity IDs and their relationships in a project schedule: 1) Update successors and predecessors for several activities 2) Add new activities to a group and link them to an existing activity 3) Correct original durations for activities in a group 4) Add a new activity, provide its duration, and define its successor 5) Provide reasoning for deleting activities and relink remaining activities 6) Reinstate several "finish-to-start" links between activities
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views2 pages

Comments

The document contains requests to make several changes to activity IDs and their relationships in a project schedule: 1) Update successors and predecessors for several activities 2) Add new activities to a group and link them to an existing activity 3) Correct original durations for activities in a group 4) Add a new activity, provide its duration, and define its successor 5) Provide reasoning for deleting activities and relink remaining activities 6) Reinstate several "finish-to-start" links between activities
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

A.

Activity ID 9 should actually have successor FS with the group activity for all Civil
Works no 48

B.

Activity ID 12 should have a successor FS with the activity 49

C.

Activity ID 49 should have a predecessor FF+10days with activity 14

D.

Add the following Activities ID into group ID71 and link them FS with activity ID 36
(Predessessor)
Cost Estimate Stock Pile Dust suppression system (Duration 44)
Cost Estimate MHE wash-down system (Duration 44)
Cost Estimate MHE Control System (Duration 44)
Cost Estimate Commodity Accounting System (Duration 44)

E.

Please correct the Original Durations for all activities within group ID71 (i.e ID
72,73,74,75,76,78) to Duration 44

F.

Please add a new activity within your group ID 3 Design Requirements


-

Onshore Building Utilities and Layout,


Please advise for the duration of this activity and link it (successor) FS with 59

G.

Please advise reasoning for the deletion of the following activities (from Schedule
18th of July)
From Cardno
1) Basis of Design UPS (Activity ID 109 18th July Schedule)
From Archirodon
1) Preliminary Design/Cost Estimate UPS (Activity ID 158 18 th of July Schedule) Relink
FS with the above Cardnos activity.
2) Preliminary Design/Cost Estimate Shore Protection (if required) (Activity ID 137
18th of July Schedule) Relink FS with 12
3) Preliminary Design/Cost Estimate Water Supply (Activity ID 140 18 th of July
Schedule) Relink FS with 32
4) Preliminary Design/Cost Estimate Poles & Fixtures (Activity ID 161 18 th of July
Schedule) Relink with FS 42
5) Preliminary Design / Cost Estimate - LAN System (Activity ID 172 18th of July
Schedule) Relink with 94SS+4 days and 45
6) Preliminary Design / Cost Estimate - Security System (Activity ID 173 18th of July
Schedule) Relink with SS with the above activity SS+4 and 44
7) Preliminary Design / Cost Estimate - Satcom System (Activity ID 174 18th of July
Schedule)
Relink with FS with 45

8) Preliminary Design / Cost Estimate - Marine Radar(Activity ID 175 18th of July


Schedule)
Relink with SS with the above activity SS+4 and 45
9) Preliminary Design / Cost Estimate - Vessel Docking System(Activity ID 176 18th of
July Schedule) Relink with SS with the above activity SS+4 and 45

H.

Please re-instate the following links

1) Activity ID 52FS with 51


2) Activity ID 53FS with 52
3) Activity ID 54FS with 53
4) Activity ID 55FS with 54
5) Activity ID 56FS with 55
6) Activity ID 58FS with 57
7) Activity ID 49FS with 14,12,5,9