Priority Issues (Package Wise) : 1 AHS Package (Unit 2 COD and Continues Operation)
Priority Issues (Package Wise) : 1 AHS Package (Unit 2 COD and Continues Operation)
a Fire fighting system to be completed(Only hydrant system available in power house area. But, a
yet completed)
b Completion of ETP system. No manpower and some matirials yet to be received at site
c Manpower to be increased in fire fighting and ETP system
ge wise)
up to 80 Nos to complete the job.
be received at site
Daily Progre
Project: Bhavna
2x250 MW LIGNITE B
Boiler unit-2
Sr No DESCRIPTION
1 Structure
2 Pressure Parts
3 APH
4 Non Pressure Parts
5 Refractory Weight (NPP)
6 NPP ( 48 Group)
7 Rotary Parts
8 Piping
9 Insulation
10 Bed Material
11 ESP
Remarks: Insulation and platform work is in progress
Daily Progress Report of Boiler unit-2
Project: Bhavnagar Energy Company Limited
2x250 MW LIGNITE BASED TPP AT PADVA, BHAVNAGAR
Boiler unit-2
ERECTION (MT)
Total Scope (MT)
Up to 31-01-2017 2/1/2017 Cumm
8733 8734.86 0 8734.86
4302 4303.95 0 4303.95
721 720.49 0 720.49
3629 3575.76 0 3575.76
238 238.00 0 238.00
2404 2342.20 0 2342.20
493 490.56 0 490.56
1775 1800.16 0 1800.16
1625 1482.28 0 1482.28
1250 1535.00 0 1535.00
3560 3439.00 0 3439.00
work is in progress
GAR
Date- 01/02/2017
ALIGNMENT & WELDING (MT)
Up to 31-01-2017 2/1/2017 Cumm
8446.38 0 8446.38
4270.89 0 4270.89
720.49 0 720.49
3491.42 0 3491.42
238 0 238
2236 0 2236
489.56 0 489.56
1520.65 0 1520.65
1086.12 0 1086.12
1122 0 1122
3402 0 3402
Mechanical Erection Daily Progress Report for Chimney System as
Scope Completed Today
Sr No. Area Description
(MT) Quantity Progress
1 Bed Ash Hopper and Supporting Structure 320.000 315.500 0.000 4.500 240.600 0.000 79.400
2 a. BAISH 243.420 234.004 0.000 9.416 234.004 0.000 9.416
b. FAISH 191.990 166.000 0.000 25.990 155.000 0.000 36.990
3 Pipe Rack
a. Inter. Surge to Silo 205.000 207.000 0.000 -2.000 204.000 0.000 1.000
b. ESP to Surge Hopper 283.000 230.000 0.000 53.000 195.000 0.000 88.000
4 Misc. Work. 286.220 229.000 0.000 57.220 166.000 0.000 120.220
Total Scope in MT. 1529.630 1381.504 0.000 148.126 1194.604 0.000 335.026
Mechanical Erection Daily Progress Report for Ash Handling System as on dated 31.01.2017
ALIGNMENT,WELDING/BO
Balance PLACEMENT/ ERECTION
G AND GROUTING
Received. QTY. to be
Sl.No DESCRIPTION TOTAL QTY UOM
QTY received at TODAY
site TODAY 'S PREVIOU
CUMULATIVE 'S
TOTAL S
TOTAL
Remarks : Structure Part is not updated because DPR is not sent by MBCEL
Remarks
ALIGNMENT,WELDING/BOLTIN
G AND GROUTING
Remarks
PREVIO
Cumulative
US
2 2
4 4
4 4
4 4
4 4
4 4
2 2
4 4
2 2
112 112
3 3
12 12
0 0
12 12
18 18
2996 2996
147 147
2 2
20 20
9 9
9 9
8 8
336 336
1754 1754
2104 2104
6 6
129 129
110 110
116 116
104 104
41 41
76 76
5 5
3 3
410 410
435 435
1832 1832
200 200
30 30
5 5
11 11
3 3
3 3
3 3
11 11
1 1
2 2
1 1
0 0
0 0
2 2
8 8
0 0
8 8
8 8
1 1
6 6
1 1
3112 3112
390 390
262 262
5 5
80 80
8 8
6 6
0 0
3 3
0 0
0 0
0 0
2 2
0 0
0 0
6135 6153
2367 2379
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
PRIORITY#1
151 151 148 148
149 149 149 149
60 60 60 60
441 441 425 425
665 665 655 655
1014 1014 1014 0 1014
35 35 35 35
PRIORITY#2
31 0.000 31
6 0 6
26 26
659 0.00 659 634 0 634
109 109 102 102
ME STONE
8556 32 8588 7538 0 7538
INDURE PVT LTD
Project: Bhavnagar Energy Company Limited
2x250 MW LIGNITE BASED TPP AT PADVA, BHAVNAGAR
Structural Steel Works (LLHS)
IDLERS PLUMBER
Sr No DESCRIPTION PULLEYS
(ROLLER) BLOCKS
SCOPE ERECTION SCOPE ERECTION SCOPE ERECTION
1 CRUSHER HOUSE
2 BCN 8B 673 673 13 13 26 26
3 BCN 11A & 11B 921 921 20 20 40 40
4 BCN 15A & 15B 677 338 12 6 24 12
5 BCN 26A & 26B 1640 1640 14 14 28 28
6 BCN 28A & 28B 246 246 12 12 24 24
7 BCN 29A & 29B 244 244 12 12 24 24
8 BCN 4A & 4B 692 16 32 0
9 BCN 6A & 6B 210 14 28 0
10 BCN 7A & 7B 154 14 28 0
11 BCN 10A & 10B 147 14 28 0
12 BCN 8A 672 13 26 0
13 BCN 19A & 19B 1520 12 24 0
14 BCN 25A & 25B 1425 12 24 0
15 BCN LS 2A & 2B 700 10 20 0
16 BCN LS 3A & 3B 400 20 40 0
17 BCN LS 4A & 4B 900 14 28 0
18 BCN LS 5A & 5B 150 12 24 0
19 SFD - 2A & 2B 44 6 12
20 SFD - 3A & 3B 32 4 8
21 SFD - 6A1 & 6B1 42 6 12
22 SFD - 9A & 9B 56 6 12
23 RSFD - 16A & 16B 96 6 12
PRIORITY#1
26 26 65 65 2 2
40 40 110 95 2 1
24 12 45 28 2 1
28 28 136 136 4 3
24 24 15 15 2 2
24 24 14 14 2 2
32 40 2