A Detailed Overview of the
Contract for Construction
     Heather F. Shore, Esq.
      911 Main Street, Suite 2300
      Kansas City, MO 64105-5319
        Phone: 816-292-7000
          www.brlawkc.com
       Different Contract Types
1.   Lump sum contracts
2.   Unit price contracts
3.   Cost plus contracts
4.   Cost plus contracts with a guaranteed maximum
     price
5.   Design/Build contracts
6.   Construction management contracts
7.   Job order contracts (JOCs) (Indefinite supply
     contracts)
      Different Contract Types
Lump sum contracts:
   This is a contract for a fixed price.
   The contractor bears all the risk of loss for
    costs of completion within scope of work
    defined by the owner.
   Usually competitively bid but less flexibility to
    negotiate terms when the government sends
    out the contract for competitive bidding.
         Different Contract Types
Unit Price Contracts:
   This is a contract based on specified unit prices for
    quantities of work that are estimated.
   Usually involves easily measurable quantities of work.
      e.g., earth removal, rock removal, concrete placed
   Often done with different prices for different volumes of
    work anticipated to pass on discounts to owners and
    lower risk of loss to the contractor.
          Different Contract Types
Cost Plus Contracts:
   In a cost plus contract the owner pays for the actual cost of
    the contract plus a flat fee or percentage of the project costs.
   Some courts will impose a fiduciary relationship between
    the owner and contractor that forces the contractor to
    manage and control costs.
   This is a contract with limited use because the owner must
    generally have a large amount of control over the scope of
    the work and the labor, equipment and supplies to be used.
       The large management burden placed on the owner has caused a
        variation of the contract to become used.
         Different Contract Types
Cost Plus with a Guaranteed Maximum Price
 Contracts:
   This is a cost plus contract with a clause stating a maximum
    price that will be paid for the project.
   This eliminates the need to prove a breach of fiduciary duty
    for high project costs.
   Note: often there is a shared savings clause included
    wherein the parties split the benefit of projects lower than the
    maximum guaranteed price to incentivize the contractor to
    work to keep project costs low.
         Different Contract Types
Design/Build Contracts:
   This is a contract with one entity to both design and
    construct the project.
   This often reduces costs and responsibility as well as
    speeds up the project.
       The contractor may be able to furnish design services
        without worrying about designer licensing laws. See
        Strain-Japan R-16 School District v. Landmark Systems,
        Inc., 965 S.W.2d 278 (Mo. App. 1998)
         Different Contract Types
Construction Management Contracts:
    This contract allows the owner to retain a contractor,
     architect, engineer or other person to manage the project
     including reviewing plans and specifications, budgets and
     managing execution of the work.
    Two types of construction management contracts:
    1.   At-risk: The manager may contract directly with tradesman
         and suffers the risk of loss for costs associated with them.
    2.   Not-at-risk: The manager may take bids but the owner
         contracts directly and bears the risk of loss.
        Different Contract Types
Job Order Contracts:
   These are competitively bid contracts with a
    fixed price for an indefinite amount of work.
   Usually, they are used for bidding many small
    projects at one time.
   Generally used in the public setting as opposed
    to the private market.
     Standard Form Agreements
   Standard form agreements are recommended
    and have become generally well recognized and
    used in the industry.
   Available forms:
       American Institute of Architects (AIA)
       Engineering Joint Contract Documents Committee
        (EJCDC)
       Associated General Contractors (AGC)
   Remember to tailor them individually for each
    job.
The Ten Most Important Clauses of
 Construction Contracts (with two
  more to make an even dozen)
   Payment                  Delays and Extensions
   Contractors Design      Indemnification and
    Responsibility            Insurance
   Differing Site           Notice of Claim
    Conditions                Provisions
                             Termination
   Exculpatory
                             Incorporation by
   Alternative Dispute       Reference
    Resolution (ADR)
                             Flow Down
   Liquidated Damages
Documents, Provisions and Issues
            to Note
Payment Clauses and Issues
Types of Necessary Documents for Payment:
1.    Schedule of values
2.    Application for payment
3.    Supporting backup documents (e.g., lien waivers,
      certified payrolls, schedule updates and test
      results)
      Some lien waivers may be unenforceable.
         R.S.Mo.  429.005.
Documents, Provisions and Issues
            to Note
Payment Timing:
   1.   Parties should establish their own
        deadlines for payment.
   2.   But be mindful of state and federal statutes
        governing payment (prompt payment acts in
        Kansas and Missouri).
        Essential Contract Terms
Statutes and Laws to ConsiderPublic
   Construction Contracts
   R.S.Mo.  34.057.1
       This statute requires the contractor to pay the subcontractor
        within a specified time of receiving payment from the owner.
   Kan. Stat. Ann.  16-1903
       Requires payment by the Owner to Contractor no later than 30
        days after the Owner receives a properly completed,
        undisputed payment application.
       Requires payment by the Contractor to Subcontractor within 7
        business days from receipt of payment from the Owner.
        Essential Contract Terms
Statutes and Laws to ConsiderPrivate
   Construction Contracts
   R.S.Mo.  431.180
       All persons who enter into a contract for private design or construction
        work shall make all scheduled payments pursuant to the terms of the
        contract.
   Kan. Stat. Ann.  16-1803
       Requires payment by the Owner to Contractor within 30 days from
        owners receipt of an undisputed payment application.
       Requires payment by the Contractor to Subcontractor within 7
        business days from Contractors receipt of payment from the Owner.
Documents, Provisions and Issues
            to Note
Retainage:
   Often the owner retains a percentage from the payments until the
    end of the project to incentivize the contractor to finish.
   Statutes will limit the amount that can be withheld.
       Private projects
           Missouri limits retainage to 10%, declares retainage to be trust
            funds, and allows retainage to be held for punch list items in an
            amount sufficient to protect owner.
           Kansas limits retainage to 10% and requires contractor to pay the
            subcontractor within 7 business days of receiving payment of
            retainage.
       Public projects
           Missouri caps retainage to 5% of the value of the contract unless
            the owner determines higher rate is needed; allows owner to hold
            retainage until completion of punch list items.
           Kansas limits retainage to 10% and trigger interest if retainage not
            timely paid.
Documents, Provisions and Issues
            to Note
Other Issues to Remember Regarding
 Payment:
   Third party roles:
       Remember issues dealing with the architects review of payment
        applications and the lenders requirement for lien waivers.
            Be mindful of endorsements on the back of checks!
   I nterest on late paym ents:
       R.S.Mo.  408.020 = 9% interest rate
       Kan. Stat. Ann.  16-201 = 10% interest rate
   P rovisions for billing disputed w ork :
       These provisions usually state the owner doesnt have to pay for
        disputed work or she can direct the work through a change directive
        with the amount to be paid determined later and the contractor can
        charge an agreed upon amount for this work.
    Essential Contract Terms
Payment Terms:
Three types of payment clauses are often
   seen in construction contracts between
   General Contractors and Subcontractors:
1. Payment by a Certain Date
2. Pay When Paid
3. Pay if Paid
       Essential Contract Terms
Paym ent by a Certain Date:
-   This is the payment clause seen most often in
    construction contracts between General
    Contractors and Subcontractors.
-   In this type of payment clause, the General
    Contractor must pay the Subcontractor by a
    specified date (often within 30 calendar days
    from the date of the Subcontractors invoices).
        Essential Contract Terms
Pay w hen Paid:
-   Under this payment arrangement, the date by which the
    General Contractor must pay the Subcontractor is
    calculated in reference to the date by which the Owner
    should have paid the General Contractor.
-   E.g. Payment is due within thirty (30) calendar days of
    the date when the General Contractor receives payment
    by the Owner.
-   Note: under this clause, the General Contractor must pay
    the Subcontractors regardless of whether the General
    actually does receive payment from the Owner.
       Essential Contract Terms
Pay if Paid:
-   Under this payment arrangement, the General
    Contractors payment obligation to the Subcontractor
    is conditioned on the Owner paying the General
    Contractor.
-   Language must clearly establish a pay if paid
    arrangement.
-   A pay if paid clause is no defense to a mechanics
    lien claim in Kansas or Missouri. But Kansas courts
    have held a surety is not liable to pay subcontractors
    if the bonded subcontract contains a pay if paid clause
    and the principal has not been paid.
         Essential Contract Terms
The Contractors Design Responsibility:
Design Review:
 Pay particular attention to design review clauses that may
  shift the responsibility of reviewing the designs for defects
  from the owner or architect to the contractor.
Shop Drawing Review:
 Understand the clauses that address the scope of the
  architects or engineers responsibilities in reviewing shop
  drawings.
   Look for clauses that address the speed at which the shop drawing
    process must occur.
       Keep good records of any delays by the design professionals in
        reviewing your shop drawings.
          Essential Contract Terms
Differing Site Conditions:
-   A differing site conditions clause deals with estimating costs of
    unanticipated physical site conditions such as unknown underground
    conditions.
     -   Differing site conditions do not usually render a contract null and void
         nor do they provide a basis for claiming a lack of a meeting of minds.
-   Two Types of Differing Site Conditions Claims:
     -   Type I  subsurface or otherwise concealed physical conditions which
         differ materially from those indicated in the Contract Documents, or
     -   Type II  unknown physical conditions of an unusual nature, which
         differ materially from those ordinarily found to exist and generally
         recognized as inherent in construction activities of the character
         provided for in the Contract Documents.
       Essential Contract Terms
Exculpatory Clauses:
Pre-bid inspection:
   A pre-bid inspection clause usually requires that
    any condition that should have been seen during
    pre-bid inspection by the contractor is deemed
    disclosed and not a subject of the claim.
   This shifts some of the risk from the owner to the
    contractor.
        Essential Contract Terms
Exculpatory Clauses:
Duty to Discover Obvious Errors:
   A duty to discover obvious errors clause requires the
    contractor to discover any patent or obvious errors in the
    contract documents or to notify the owner of conflicting
    provisions or ambiguities so they can be clarified before
    opening the bids.
   This also shifts some of the risk from the owner to the
    contractor.
         Essential Contract Terms
   Exculpatory Clauses:
   No Damages for Delay clauses
       Addresses whether the contractor has a right to adjust the
        contract price after encountering delays at the projects, under
        various conditions and as a result of one or more potential
        causes.
       Missouri: In the private construction setting no damages for
        delay clauses have been ruled enforceable. But in the public
        setting the law provides that they are void as against public
        policy, except for contracts with the Missouri Department of
        Transportation (public works projects).
       Kansas: No damages for delay clauses are now prohibited.
        Essential Contract Terms
   No Damages for Delay clause
       Sample clause:
            In the event the Contractor is delayed in the
             prosecution of its work by any act, or omission to act,
             of the Owner or its representatives, the Contractor
             agrees to make no claim for damages for delay in the
             performance of the Contract, and agrees that any such
             claim shall be fully compensated for by an extension of
             time to complete performance.
        Essential Contract Terms
   No Damages for Delay clauses
       Exclusions:
            Delays caused by active Interference by Owner.
            Delays not within the contemplation of the parties.
            Delays so unreasonable that they constitute
             abandonment of the Contract.
            Delays resulting from breach of a fundamental
             obligation of the Owner.
        Essential Contract Terms
   Handling Changed Conditions
       Pay careful attention to existing drawings
       Note errors and ambiguities in the plans,
        drawings or specifications
       Inspect the site!
       Essential Contract Terms
Alternative Dispute Resolution (ADR):
     An ADR clause establishes a pre-agreed procedure to
      resolve disputes and claims on the project.
     Types:
          Negotiation
          Early neutral evaluation
          Mediation
          Moderated settlement conference
          Arbitration
          Mini trial
          Summary jury trial
          Rent a Judge
       Essential Contract Terms
Alternative Dispute Resolution (ADR):
When ADR is most valuable:
- Smaller disputes.
-   When opposing party is amenable to negotiations.
-   When the dispute involves complex legal or factual
    matters.
        Essential Contract Terms
Alternative Dispute Resolution (ADR):
Example ADR Clause:
      Mediation. The parties agree to first try in good faith to settle
       any claims, disputes and other matters in question arising out of,
       or relating to this Agreement or the breach thereof, by
       mediation in accordance with the Construction Industry
       Mediation Rules of the American Arbitration Association (AAA).
       If any party commences arbitration or litigation of a dispute
       without first attempting to resolve the matter through mediation
       (other than the recordation of a mechanics lien and/or a lawsuit
       to foreclose on said mechanics lien, which is specifically exempt
       from this Article), or if either party refuses to cooperate in the
       scheduling or conduct of mediation proceedings, then in the sole
       discretion of the arbitrator or judge, that party shall not be
       entitled to recover its attorneys fees and costs even if they
       would otherwise have been available to that party.
       Essential Contract Terms
Liquidated Damages:
-   A liquidated damages contract provision imposes payment of
    a certain fixed amount in the event of a breach of a contract
    provision.
-   Under Missouri law, liquidated damage provisions are
    generally enforceable unless they are so disproportionate to
    the amount of any such damage reasonably to be
    contemplated as to be oppressive. Wilt v. Waterfield, 273
    S.W.2d 290, 295 (Mo. 1954).
-   See more recent cases cited in materials re penalties.
       Essential Contract Terms
Liquidated Damages:
Example of Liquidated Damages Clause:
- The Contractor understands and agrees that the completion of the
  entire Project within the time provided is an essential feature of this
  Agreement and that the Owner will sustain substantial damages, the
  amount of which is not possible to accurately determine at this time,
  if the work is not so complete. The Contractor, therefore, agrees to
  proceed with due diligence, taking all precautions and making the
  necessary arrangements to insure the completion of the work within
  the prescribed time. The Contractor further agrees that its failure to
  finally and fully complete the work within the time allowed shall be
  considered a breach of the Agreement and shall entitle the Owner
  to collect liquidated damages from the Contractor and/or the
  Contractors surety in the amount of $1,000.00 per calendar day for
  each day the Contractor is late in completing the Project.
       Essential Contract Terms
Delays and Extensions:
   A delays and extensions clause identifies
    which party is responsible for any delays and
    whether the delay entitles the contractor to
    more time or to reimbursement of costs
    incurred.
      Essential Contract Terms
Delays and Extensions:
Four types of delays and extensions clauses are often
    seen in construction contracts:
1.  Nonexcusable Delayswithin contractor or
    subcontractors control = no extra time or money
    given by owner.
2.   Excusable Delaysoutside of either partys control =
     give the contractor extra time to finish or money to
     finish at the original time.
       Essential Contract Terms
Delays and Extensions:
3.   Compensable Delaysowner bears responsibility = both
     extra time and money typically given to contractor.
4.   Concurrent Delayswhen two of the above delays overlap
     and would cause the project to be delayed for similar or the
     same time periods = responsibilities apportioned between
     the owner and contract, and extra time or money is
     awarded accordingly.
     Note: a compensable delay coupled with a non-excusable
     delay becomes classified as an excusable delay.
        Essential Contract Terms
Delay Damages Clause:
ExampleAIA A201 - 2007:
-   8.3.1 If the Contractor is delayed at any time in the commencement
    or progress of the Work by an act or neglect of the Owner or
    Architect, or of an employee of either, or of a separate contractor
    employed by the Owner, or by changes ordered in the Work, or by
    labor disputes unrelated to the Project, fire, delay in deliveries
    beyond the Contractors control, unavoidable casualties, other causes
    beyond the Contractors control, or by causes which the Architect
    determines may justify a delay, then the Contractor Time shall be
    extended by Change Order for such reasonable time as the Architect
    may determine.
-   8.3.3 This Section 8.3 does not preclude recovery of damages for
    delay by either party under provisions of the Contract Documents.
         (For pricing of these damages refer to Section 7.3)
       Essential Contract Terms
Indemnification:
- Under an indemnification provision, a
  party is obligated to either directly pay or
  reimburse the financial losses of another
  party.
-   Indemnification clauses usually contain
    the words defend, indemnify and hold
    harmless.
     Essential Contract Terms
Indemnification:
 It is against public policy in Kansas and Missouri
  to include a contractual provision requiring the
  indemnitor to indemnify the indemnitee for the
  indemnitees own negligence or intentional acts.
  R.S.Mo. 434.100; K.S.A.16-121.
 Insurance fills gaps left by indemnity and
  incentivizes the indemnitor to assume indemnity
  obligations.
       Essential Contract Terms
Indemnification:
Example Indemnification Clause:
- Subcontractor shall hold the Owner and the Contractor
   harmless from any and all claims, loss, demands for bodily
   injury, death or property damage incurred by any person or
   entity, including employees of the Subcontractor, as a result
   of any negligence, breach of contract, or failure to provide a
   safe place to work by the Subcontractor, its officers, directors,
   agents, employees or independent contractors in connection
   with any work performed under the Master Contract, or as a
   result either directly or indirectly, from the failure of the
   Subcontractor to faithfully carry out any provision of this
   Subcontract and/or the Master Contract.
        Essential Contract Terms
   AIA Indemnification clause ( 3.18)
       The Contractor shall indemnify the Owner,
        Architect, Architects consultants, and agents
        and employees of any of them for negligent
        acts or omissions of the Contractor,
        Subcontractor, or anyone directly or indirectly
        employed by them.
       No limitation on the amount or type of
        damages.
       Essential Contract Terms
Notice of Claim Provisions:
-   A notice of claim provision provides that failure
    to give timely notice of any claim constitutes a
    waiver of that claim.
-   In Missouri, notice of claim provisions are
    generally enforceable. Gillioz v. State Highway
    Commn, 153 S.W.2d 18 (Mo. 1941).
       Essential Contract Terms
Notice of Claim Provisions:
Benefits and reasons to include these provisions:
1.   They give the recipient a chance to gather
     information about a claim before the information is
     lost.
2.   They allow for easier settlement opportunities
     avoiding further claims and litigation.
3.   They may help determine if a claim is legitimate.
4.   They aid the recipients in managing and budgeting
     the project by divulging necessary information at an
     early stage.
      Essential Contract Terms
Notice of Claim Provisions:
Example Notice of Claim Provision:
- Owner shall, no later than 60 days before initiating an
  action against Contractor, provide written notice of claim
  to Contractor. The notice of claim shall state that the
  Owner asserts a construction defect claim and is
  providing notice of the claim pursuant to the Contract.
  The notice of the claim shall describe the claim in detail
  sufficient enough to explain the nature of the alleged
  construction defect and the result of the defect. In
  addition, the Owner shall provide the Contractor with
  any evidence in possession of the Owner that depicts the
  nature and cause of the construction defect.
         Essential Contract Terms
Termination:
-   A termination clause calls for the termination of the
    contract under an enumerated set of circumstances.
-   Three types of Termination Clauses:
    -   Termination for Convenience:
         -   Allows an owner (or contractor) to terminate a contract for any reason
             (including convenience) or even for no reason.
    -   Termination for Cause:
         -   Allows an owner (or contractor) to terminate a contract under a
             specified set of circumstances that usually arise because of the fault of
             the contractor (or owner, as the case may be).
      Essential Contract Terms
Termination:
Example Termination for Convenience Clause:
- This Contract may be terminated, in whole or in part,
  from time to time, when such action is deemed by the
  Owner, in its sole discretion, to be in its best interest.
  Termination of the Work hereunder shall be effected by
  notice of termination to the Contractor specifying the
  extent to which performance of the Work is terminated
  and the date upon which such termination becomes
  effective. The date upon which such termination
  becomes effective shall be no less than ten (10) days
  after the notice is sent.
      Essential Contract Terms
Termination:
Example Termination for Cause Clause:
- If the Work is stopped for a period of thirty (30) days
  through no fault of the Contractor or because the Owner has
  not made payments thereon as provided in the Contract, then
  the Contractor may without prejudice to any other remedy
  the Contractor may have, upon seven days written notice to
  the Owner, terminate the Contract and recover from the
  Owner payment for all work executed and for any loss which
  Contractor can substantiate through documentation or
  otherwise resulting from the stoppage of the Work, including
  reasonable overhead, profit and damages.
         Essential Contract Terms
Incorporation by Reference Clauses:
   Incorporation by reference clauses usually provide for various
    other documents and writings referred to in the contract to be
    incorporated in full into the contract and become part of the
    terms and provisions of the contract.
   The incorporated documents do not have to be attached to
    the contract being signed, nor do they even have to exist at
    that time. Wasson v. Schubert, 964 S.W.2d 520 (Mo. App.
    1998).
       E.g., plans that have not been fully developed or distributed but that
        are otherwise identifiable.
        Essential Contract Terms
Flow Down Clauses:
   Flow down clauses typically provide that the subcontractor
    shall assume to the general contractor certain obligations that
    the general contractor assumes to the owner regarding the
    subcontractors scope of work.
   If there is conflict between the provisions of the general
    contract and subcontract, courts will generally hold the more
    specific previsions of the subcontract prevail over the general
    provisions of the contract or its documents incorporated by
    reference.