Cost estimate of Oil & gas facilities
Welcome to this presentation.
It explains how the investment cost for an Oil & Gas facility is
estimated.
After a short introduction, the 3 common methods of cost
estimate are shown.
Common ratios, such as $/kg for equipment, pipe etc. are given.
Please download this file so that you can see my trainers notes in
the top left corner latest Acrobat Pro feature.
Herv
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Please download this file to access my notes in the top left corner
Place your
mouse over
here
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Please download this file to access my notes in the top left corner
Place your
mouse over
here
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Agenda
Introduction
The different estimation methods:
Capacity factored
Equipment factored
Analytical
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
What will be the
2013 Herv Baron
overall cost of
this facility?
HERVE
BARON
Cost estimate of Oil & gas facilities
Cost = Quantities * item costs
All items
How would you determine quantities?
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Quantities estimates:
Ratio from past projects
Material Take-Off
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Cost = Quantities * item costs
All items
How would you determine quantities?
What is an item cost made of?
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Item cost = Supply cost + installation cost
How would you each one?
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Item cost estimates:
Supply + installation
In-house data from
past projects
Inquiries
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Item cost estimates:
Supply + installation
In-house data from
past projects
Inquiries
Sensitivity to:
Raw materials
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Item cost estimates:
Supply + installation
In-house data from
past projects
Inquiries
Sensitivity to:
Raw materials
2013 Herv Baron
Steel, alloy steel, copper,
cement, iron
HERVE
BARON
Cost estimate of Oil & gas facilities
Item cost estimates:
Supply + installation
In-house data from
past projects
Inquiries
Sensitivity to:
Raw materials
2013 Herv Baron
Construction market
HERVE
BARON
Cost estimate of Oil & gas facilities
Sensitivity to:
Raw materials
2013 Herv Baron
Construction market
HERVE
BARON
Cost estimate of Oil & gas facilities
Purpose of estimate:
Concept screening
Study of feasibility
Decision to invest
Estimate type:
Capacity factored
Equipment factored
2013 Herv Baron
Analytical
HERVE
BARON
Cost estimate of Oil & gas facilities
Purpose of estimate:
Concept screening
Study of feasibility
Decision to invest
Estimate type:
Capacity factored
Equipment factored
2013 Herv Baron
Analytical
HERVE
BARON
Cost estimate of Oil & gas facilities
Capacity factored
C1/C2 = (P1/P2) e
e ~ 0.6
Ci: Cost of facility with production
capacity Pi
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Capacity factored
C1/C2 = (P1/P2) e
e ~ 0.6
Ci: Cost of facility with production
capacity Pi
2013 Herv Baron
Exercise: what is the increase in cost for +50% capacity increase?
HERVE
BARON
Cost estimate of Oil & gas facilities
Capacity factored
C1/C2 = (P1/P2) e
e ~ 0.6
Ci: Cost of facility with production
capacity Pi
2013 Herv Baron
Exercise: what is the increase in cost for +50% capacity increase?
In your opinion, what is the limit of such estimate?
HERVE
BARON
Cost estimate of Oil & gas facilities
Capacity factored
C1/C2 = (P1/P2) e
e ~ 0.6
Ci: Cost of facility with production
capacity Pi
2013 Herv Baron
Exercise: what is the increase in cost for +50% capacity increase?
In your opinion, what is the limit of such estimate? It takes into
account neither market conditions nor plant location (labour cost)
HERVE
BARON
Cost estimate of Oil & gas facilities
Equipment factored
C=fM
C: total installed cost of facility
M: cost of main equipment
f: factor
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Equipment factored
C=fM
C: total installed cost of facility
M: cost of main equipment
f: factor
2013 Herv Baron
Note: Typical figures for Petrochemical Plant
HERVE
BARON
Cost estimate of Oil & gas facilities
Equipment factored
C=fM
C: total installed cost of facility
M: cost of main equipment
f: factor
2013 Herv Baron
Whats the main equipment?
HERVE
BARON
Cost estimate of Oil & gas facilities
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
2013 Herv Baron
How is the cost of main
equipment evaluated?
HERVE
BARON
Cost estimate of Oil & gas facilities
Process design
PFDs
H&M balance
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Equipment factored
C=fM
f: factor
f depends on
type of facility (petrochemical, refining, LNG, off-shore)
Size
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Equipment factored
C=fM
f: factor
f depends on
type of facility (petrochemical, refining, LNG, off-shore)
Size
2013 Herv Baron
Typical figures for a chemical plant
In your opinion, how can we refine the estimate?
HERVE
BARON
Cost estimate of Oil & gas facilities
Equipment factored
C = fi Mi
Mi Cost of all type i Main equipment
fi: factor
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Equipment factored
C = fi Mi
Mi Cost of all type i Main equipment
fi: factor
Why do you think justifies such an approach?
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Equipment factored
C = fi Mi
Mi Cost of all type i Main equipment
fi: factor
Why do you think justifies such an approach?
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Equipment factored
C = fi Mi
Mi Cost of all type I Main equipment
fi: factor
2013 Herv Baron
In your opinion, what is the limit of such estimate?
HERVE
BARON
Cost estimate of Oil & gas facilities
Analytical
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
2013 Herv Baron
Engineering & Project Management
Miscellaneous
HERVE
BARON
Cost estimate of Oil & gas facilities
Analytical
Establish the bill of quantities (BOQ) in each trade: equipment,
civil, piping, structural steel etc.
BOQ = Material Take-Off (what is measured from available
drawings at this stage) + allowances for design development +
allowances for what is not yet on drawings + contingencies
Apply ratios to get supply + installation cost
Installation cost = qty * manhours/ton ratio * labour cost
Labour cost is all in, i.e., includes construction equipment (crane,
scaffolding)
The ratio is based on standard manhours, i.e., home country,
Localization factor (productivity) to be applied, i.e., actual
2013 Herv Baron
installation manhours = ratio * productivity
Example: piping installation cost, ratio: 250 std h / ton
Western Europe, labour cost $100/hr yields $20k/ton
Middle East, labour cost $18/hr, productivity 2.5 yeilds $16k/ton
HERVE
BARON
Cost estimate of Oil & gas facilities
Analytical
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
2013 Herv Baron
Engineering & Project Management
Miscellaneous
HERVE
BARON
Cost estimate of Oil & gas facilities
Main equipment supply + install
Supply
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Main equipment supply + install
Supply: eqt list (dimensions) => weight
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Process design
PFDs
H&M balance
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Main equipment supply + install
Supply: eqt list (dimensions) => weight
Rate?
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Main equipment supply + install
Supply: eqt list (dimensions) => weight
Rate:
USD 4/kg for CS depends on eqt size: 4 (large) 10 (small)
USD12/kg for SS
2013 Herv Baron
USD 300-500 /m2 for Shell&Tube / Air-coolers
USD 1000/kW for pumps
Important note: the above ratios and the following ones - are the ones obtained by large EPC
Contractors ordering large quantities (USD 1bln jobs). Higher ratios must be used on smaller jobs!
HERVE
BARON
Cost estimate of Oil & gas facilities
Main equipment supply + install
Supply: eqt list, dimensions/capacity/weight
Installation
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Main equipment supply + install
Supply: eqt list, dimensions/capacity/weight
Installation ratios: % supply cost, typ. 8%
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Main equipment supply + install
Supply: eqt list, dimensions/capacity/weight
Installation ratios: % supply cost, typ. 8%
30 std manhours/ton (includes labour
2013 Herv Baron
and equipment)
HERVE
BARON
Cost estimate of Oil & gas facilities
Analytical
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
2013 Herv Baron
Engineering & Project Management
Miscellaneous
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: ratio (eqt weight), typ. 40%
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: ratio f (eqt number)
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: ratio f (eqt number)
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: ratio f (eqt number)
Remark: Unit vs Interconnection
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: ratio (eqt number, eqt weight)
MTO
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Process design
PFDs P&IDs
H&M balance
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Process design
PFDs P&IDs
H&M balance
Equipment list
Plot Plan
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping Layout
P&IDs
Plot Plan
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
For more information on Engineering, refer to:
A unique synthesis for the
busy Project professional
270 pages
300 illustrations
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
For more information on Engineering, refer to:
Table of Contents
2013 Herv Baron
HERVE The Oil & Gas Engineering Guide
BARON
2nd edition
Order direct on the publisher website:
http://www.editionstechnip.com/en/catalo
gue-detail/1111/oil-gas-engineering-guide-
the.html
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: MTO
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: MTO
Item count: P&IDs
Lengths: Piping Layout
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: MTO
Item count: P&IDs
Lengths: Piping Layout
Both Process & Utility lines
Both Above Ground & Underground lines, Fire water
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: MTO
Item count: P&IDs
Lengths: Piping Layout
Both Process & Utility lines
Both Above Ground & Underground lines, Fire water
Allowances added for:
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: MTO
Item count: P&IDs
Lengths: Piping Layout
Both Process & Utility lines
Both Above Ground & Underground lines
Allowances added for:
what is not taken-off, e.g., small diameter and design
development (P&ID completion) to obtain quantities
to erect
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: MTO
Item count: P&IDs
Lengths: Piping Layout
Both Process & Utility lines
Both Above Ground & Underground lines
Allowances added for:
what is not taken-off, e.g., small diameter and design
development (P&ID completion) to obtain quantities
to erect
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: MTO
Item count: P&IDs
Lengths: Piping Layout
Both Process & Utility lines
Both Above Ground & Underground lines
Allowances added for:
what is not taken-off, e.g., small diameter and design
development (P&ID completion) to obtain quantities
to erect
2013 Herv Baron
cut and losses to obtain quantities to be supplied
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: ratio (eqt number, eqt weight)
MTO
Rate Supply
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: ratio (eqt number, eqt weight)
MTO
Rate Supply $ /kg, typ. USD 3 /kg for CS
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: ratio (eqt number, eqt weight)
MTO
Rate Supply $ /kg, typ. USD 3 /kg for CS
Install
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Piping supply + install
Qty: ratio (eqt number, eqt weight)
MTO
Rate Supply $ /kg, typ. USD 3 /kg for CS
Install std mhrs/ton, typ. 200-250 in unit,
100 on interconnecting pipe-racks,
2013 Herv Baron
applied to the total piping weight,
including fittings & valves.
HERVE
BARON
Cost estimate of Oil & gas facilities
Electrical supply + install
Price ratio % Main equipment, typ. 15-20%
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Electrical supply + install
Price ratio % Main equipment, typ. 15-20%
Quantities: Consumers list
2013 Herv Baron
Rate (supply+install): USD 50k / consumer (w/o
generation) USD 520 / installed kW
HERVE
BARON
Cost estimate of Oil & gas facilities
Consumers list
Single Line Diagram
Plot Plan
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Consumers list
Single Line Diagram
Plot Plan
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Instrumentation & Control system supply + install
Price ratio % Main equipment, range: 40-120%
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Instrumentation & Control system supply + install
Price ratio % Main equipment, range: 40-120%
Qties
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Instrumentation & Control system supply + install
Price ratio % Main equipment, range: 40-120%
Qties nb equiv. loops (CV, 0.5 ON/OFF, Analyser)
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Instrumentation & Control system supply + install
Price ratio % Main equipment, range: 40-120%
Qties nb equiv. loops (CV, 0.5 ON/OFF, Analyser)
2013 Herv Baron
Rate
HERVE
BARON
Cost estimate of Oil & gas facilities
Instrumentation & Control system supply + install
Price ratio % Main equipment, range: 40-120%
Qties nb equiv. loops (CV, 0.5 ON/OFF, Analyser)
2013 Herv Baron
Rate supply: $ /equivalent control loops, typ. 90k
install: hrs / equivalent control loops, typ. 750
HERVE
BARON
Cost estimate of Oil & gas facilities
Instrumentation & Control system supply + install
Price ratio % Main equipment, range: 40-120%
Qties Instrument list
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Instrumentation & Control system supply + install
Price ratio % Main equipment, range: 40-120%
Qties Instrument list
2013 Herv Baron
Rate Supply+install: $ / I/O, typ. 1000
HERVE
BARON
Cost estimate of Oil & gas facilities
Civil Works
Price Ratio % Main equipment cost, typ. 15-20%
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Civil Works
Price Ratio % Main equipment cost, typ. 15-20%
Qty
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Civil Works
Price Ratio % Main equipment cost, typ. 15-20%
Qty Dimensions/Weight of equipment &
structure => size of foundations (m3)
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Civil Works
Price Ratio % Main equipment cost, typ. 15-20%
Qty Dimensions/Weight of equipment &
structure => size of foundations (m3)
Rate
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Civil Works
Price Ratio % Main equipment cost, typ. 15-20%
Qty Dimensions/Weight of equipment &
structure => size of foundations (m3)
Rate all-in (materials & labour) rate $/m3, typ. 1000
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Civil Works
Price Ratio % Main equipment cost, typ. 15-20%
Qty MTO: excavation, formwork, rebar, etc.
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Civil Works
Price Ratio % Main equipment cost, typ. 15-20%
Qty MTO: excavation, formwork, rebar, etc.
Rate Mhrs/operation + labour cost
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Steel structures
Price Ratio % Main equipment cost, typ. 10-30%
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Steel structures
Price Ratio % Main equipment cost, typ. 10-30%
Qty Ratio
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Steel structures
Price Ratio % Main equipment cost, typ. 10-30%
Qty Ratio pipe-racks: 90% of piping weight
2013 Herv Baron
platforms: 10% of equipment weight
HERVE
BARON
Cost estimate of Oil & gas facilities
Steel structures
Price Ratio % Main equipment cost, typ. 10-30%
Qty Ratio pipe-racks: 90% of piping weight
2013 Herv Baron
platforms: 10% of equipment weight
Rate
HERVE
BARON
Cost estimate of Oil & gas facilities
Steel structures
Price Ratio % Main equipment cost, typ. 10-30%
Qty Ratio pipe-racks: 90% of piping weight
2013 Herv Baron
platforms: 10% of equipment weight
Rate Supply USD 2/kg
Erection 20 std manhours/t
HERVE
BARON
Cost estimate of Oil & gas facilities
Analytical
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Painting, Insulation
Price ratio % eqt, piping, str cost, typ. 5% each
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Painting, Insulation
Price ratio % eqt, piping, str cost, typ. 5% each
Qty MTO
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Painting, Insulation
Price ratio % eqt, piping, str cost, typ. 5% each
Qty MTO
Rate supply + install h / m2
2013 Herv Baron
typ. 0,5 for painting 1,5 for (hot) insul.
HERVE
BARON
Cost estimate of Oil & gas facilities
Analytical
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
2013 Herv Baron
Engineering & Project Management
Miscellaneous
HERVE
BARON
Cost estimate of Oil & gas facilities
Temporary Construction facilities
2013 Herv Baron
Ratio % total cost, typ. 5% for new site
Detailed
HERVE
BARON
Cost estimate of Oil & gas facilities
Analytical
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
2013 Herv Baron
Engineering & Project Management
Miscellaneous
HERVE
BARON
Cost estimate of Oil & gas facilities
Engineering & Project Management = all Project services
Price ratio % total cost, typ. 15%
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Engineering & Project Management = all Project
services
2013 Herv Baron
Price ratio % total cost, typ. 15%
Qty ratio
HERVE
BARON
Cost estimate of Oil & gas facilities
Engineering & Project Management = all Project
services
2013 Herv Baron
Price ratio % total cost, typ. 15%
Qty ratio hrs / eqt item, typ. 1800 for Refining,
2500 for gas, 4000 for LNG
HERVE
BARON
Cost estimate of Oil & gas facilities
Engineering & Project Management = all Project
services
2013 Herv Baron
Price ratio % total cost, typ. 15%
Qty
HERVE
BARON
Cost estimate of Oil & gas facilities
Engineering & Project Management = all Project
services
2013 Herv Baron
Price ratio % total cost, typ. 15%
Qty home office: tasks list + std manhours
field supervision: ratio to labour, typ. 1/7
HERVE
BARON
Cost estimate of Oil & gas facilities
Analytical
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
Engineering & Project Management
2013 Herv Baron
Miscellaneous
Contractors cost
HERVE
BARON
Cost estimate of Oil & gas facilities
Miscellaneous
Earthworks: always specific
Special foundations
Infrastructures: roads, buildings
Spare parts, typ. 5% main equipment cost
First fill (catalyst, lubes, chemicals)
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Analytical
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
Engineering & Project Management
2013 Herv Baron
Miscellaneous
Contractors cost
HERVE
BARON
Cost estimate of Oil & gas facilities
Contractors cost
profit,
risks,
sales cost,
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Contractors cost
profit, typ. 7%
risks,
sales cost,
typ. 10-15%
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system
supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
Engineering & Project Management
Miscellaneous: catalysts etc.
Contractors cost
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Main features:
Different level of Cost estimate accuracy
Feasibility study +/-30% accuracy
Final Investment Decision (FID) +/- 10%
Which of the methods we have seen would you use for
each case?
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
Main concepts:
Different level of Cost estimate accuracy
Factored / Detailed
Qty estimate: allowances for design development
Rates:
In-house historical data similar Plant
Cost estimate: Contingencies for cost escalation
Inquiries + provisions for cost adders (supplies),
additional works/re-works (construction)
2013 Herv Baron
Direct costs / Indirect costs
HERVE
BARON
Cost estimate of Oil & gas facilities
Historical evolution:
+ Increased instrumentation & control costs
- Engineering low cost centers
- Low cost sourcing 20% cheaper
- Increase in productivity (3D model)
+ Additional requirements: safety, environment
2013 Herv Baron
HERVE
BARON
Cost estimate of Oil & gas facilities
For more information on Engineering, refer to:
A unique synthesis for the
busy Project professional
270 pages
300 illustrations
2013 Herv Baron
HERVE The Oil & Gas Engineering Guide - 2nd edition
BARON
Table of Contents
Discipline presentation:
activities and deliverables
The overall process
Methods & tools
HERVE The Oil & Gas Engineering Guide - 2nd edition
BARON
Table of Contents
Discipline presentation:
activities and deliverables
HERVE
BARON
The work of each
Engineering discipline is
described
HERVE
BARON
Design activities are
explained, e.g., Plant
Equipment layout
HERVE
BARON
Complex activities, such as
QRA, are explained
through a practical
example.
HERVE
BARON
How are materials of
construction selected ?
HERVE
BARON
How and when are Piping
Materials ordered?
HERVE
BARON
A sample of all common
Engineering documents is
included
HERVE
BARON
A sample of all common
Engineering documents is
included
Use this to specify what
you want to your
Engineering supplier !
HERVE
BARON
Verify the contents of
engineering documents
with check lists.
HERVE
BARON
Difference between
Engineering and Shop
drawings
HERVE
BARON
Understand the main
technical aspects, e.g.,
DCS vs ESD
HERVE
BARON
The common 2 types of
package control
HERVE
BARON
The different Plant
drainage systems
HERVE
BARON
The dynamic forces to
which an Off-Shore
Plant is subject
HERVE The Oil & Gas Engineering Guide - 2nd edition
BARON
Table of Contents
The overall process
HERVE
BARON
Use this as standard,
question deviations.
HERVE
BARON
Understand the new
3D-model centered
engineering process
HERVE
BARON
Know the interfaces
between disciplines...
and with Vendors
HERVE
BARON
Understand what
drives the Project
schedule
HERVE The Oil & Gas Engineering Guide - 2nd edition
BARON
Table of Contents
Methods & tools
HERVE
BARON
Use these methods as
standard, question
deviations.
HERVE
BARON
Implement powerful
procedures
HERVE
BARON
Request meaningful
progress reports
HERVE
BARON
Implement effective
Project Control
HERVE The Oil & Gas Engineering Guide - 2nd edition
BARON
This book is destined to both:
Oil & Gas companies Project execution personnel
Oil & Gas contractors Project execution personnel
HERVE The Oil & Gas Engineering Guide
BARON
2nd edition
If your are on the Client side, i.e., contracting Engineering
services, this book will help you to:
Specify to an Engineering supplier what you want: what
deliverables and with what contents,
Set a standard in Engineering execution that you and your
supplier can adhere to: design stages/gates, methods to be
used, etc.
Specify the progress report you want, with the meaningful
indicators,
Ask the right questions to assess the true progress,
HERVE The Oil & Gas Engineering Guide
BARON
2nd edition
If your are on the Contractor side, i.e., performing Engineering
activities, this book will help you to:
Understand the work of each discipline and the overall
picture,
Challenge what one discipline tells you,
Understand the critical areas,
Put in place the right methods to be successful,