Floating Drilling Training Guide
Floating Drilling Training Guide
1
Section
OBJECTIVES
Describe the two most commonly used methods to designate the severity of a design
environment.
Describe how wind, waves and current are measured/reported and how the direction
impacts floating drilling rigs.
List the equipment and methods used to compensate for rig motions.
Describe the equipment used on floating rigs to handle the BOPs, bulk material,
tubulars and deck material.
1-1
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
CONTENTS Page
1-2
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1.1 OVERVIEW
In the late 1950s and early 1960s, the search for petroleum began to extend to
unprotected offshore waters with depths deeper than could be drilled with bottom-
founded drilling rigs. The first floating rig operations were small, shipshape vessels
converted for seafloor coring and very shallow drilling in water depths of 300 to 1000 ft.
Promising exploration potential, Offshore California was one of the early drivers for
floating drilling rig development. Figure 1.1 shows progression of industry well water
depths vs. time.
Year
60
63
66
69
72
75
78
81
84
87
90
93
96
99
19
19
19
19
19
19
19
19
19
19
19
19
19
19
0
1000
2000
Wa ter Depth ft
3000
4000
5000
6000
7000
8000
9000
10000
Technology for bottom-founded drilling rigs could not be easily adapted to floating rigs
due to the motion of the rig (as compared to the seafloor). This characteristic generated
completely new methods for drilling which included subsea blowout preventers, drilling
risers and drillstring motion compensation. The earliest floating rigs used essentially long
bell nipples fabricated into joints with conventional bolted flanges. Riser tensioning
systems were a series of wirerope, sheaves and weights. There was no drillstring
compensation other than the use of bumper subs installed in the drillstring.
In the late 1960s most floating rigs were older vessels that were converted for drilling.
Several early drillships had shipshape hulls (Figure 1.2) and a few drillships had a barge
type hull. By the early 1970s many new vessels with shipshape hulls were being
constructed for drilling. About this time, a new type floating rig, the semisubmersible,
was being designed (Figure 1.3).
1-3
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Figure 1.3 - Early Semisubmersible Floating Rig, Bluewater II, 1975 Vintage
1-4
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
The new semisubmersible designs were basically upgrades on submersible barge rig
designs with larger pontoons. These rig designs were typically moored vessels.
Examples include the Sedco 135, early Odeco designs (Ocean Prospector, etc) and
Pentagone 80 series rigs. With the oil embargo and the crude price increases of the
early 1970s, the number and the different design types of floating rigs exploded.
Floating rigs which include both drillships and semisubmersibles are generally classified
into generations based on their design and characteristics. A description of the general
characteristics of the several generations of semisubmersible rigs can be found in
Appendix 1.1.
With new, large semisubmersible rig designs, the number of drillships declined after the
early 1980s. The much better motion characteristics of the semisubmersible made it the
favorite of the industry. Due to the shift in market demand, drilling contractors built no
drillships for the industry between 1983 and 1997. However, during this time frame, the
government of India did build two drillships for their own use. All the drillships with barge
type hulls were removed from the fleet by the mid 1980s.
Most of the early floating rigs were moored but dynamically positioning technology was
being developed in the 1960s for seafloor coring operations. By the early 1970s the first
dynamically positioned (DP) floating drilling rigs (shipshape) were being used in water
depths as deep as 6000 ft. Early DP vessels included the Sedco 445 (built in 1971) and
the Discoverer Seven Seas (built in1975).
By the mid 1980s the worldwide floating rig fleet was composed of about 170
semisubmersibles and 60 drillships (Figure 1.4). The number of floating rigs in the
world held fairly constant between 1985 and the early 1990s at about 160 to 225 units.
During this same time period, many of the first generation floating rigs were retired from
service as the result of the downturn in the industry. The number of floating rigs
declined to about 140 by the 1990s. By 1993 about 23 drillships existed.
1-5
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
250 Semisubmersibles
200 Drill ships
Number of rigs
150
100
50
0
1980 1985 1990 1995 2000
Year
In the late 1990s the price of oil increased, and many deepwater and ultra-deepwater
leases were purchased in the Gulf of Mexico and around the world. Deepwater is
generally considered in excess of 2000 ft and ultra-deepwater in excess of 5000 ft. To
drill the new leases there was an immediate need for deepwater and ultra-deepwater
floating rigs. However, engineering designs for large ultra-deepwater semisubmersibles
had languished during the industry downturn in the late 1980s and early 1990s. To fill
the need for ultra-deepwater, drillships became the optimum choice, due to existing hull
designs and the large variable load needed for the long and heavy drilling riser. About 15
ultra-deepwater shipshape drillships were built in the late 1990s and early 2000s. Many
of these rigs were capable of drilling in water depths as deep as 10,000 ft. In the early
2000s, semisubmersible designs for ultra-deepwater, i.e., high variable load capability,
became available and several very large semisubmersibles were built (i.e., Deepwater
Horizon, Bingo 9000, etc.). These new semisubmersibles had variable loads required for
drilling in up to 10,000 ft water depth, however these rigs do not have variable loads as
high as deepwater drillships.
Beginning in the late 1980s dynamically positioned and/or dynamically positioned
mooring assist semisubmersibles began to be designed and built. Today several
semisubmersible rigs are available that have the capability to be completely dynamically
positioned without a mooring system.
In 2000, forty drillships were in the world floating rig fleet. Thirty of these rigs were
equipped to operate in a fully dynamically positioned mode, and ten rigs had only
m o o rin g ca p a b ility. B y 2 0 0 0 , 2 3 o f th e w o rld s fle e t o f 1 7 0 se m isu b m e rsib le rig s h a d fu ll
DP capability, and the balance were moored.
1-6
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
With this world fleet available, the industry steadily increased the water depth and
number of wells drilled worldwide. Figure 1.5 illustrates that prior to 1980, only about
500 wells had been drilled worldwide in greater than 600 ft water depth. By 1990, more
than two thousand wells had been drilled in over 600 ft water depth and by the year
2000, the well count had increased to over 4400 wells. By the year 2000, only 140 wells
had been drilled worldwide in over 5000 ft water depth.
5000
Wells In Greater Water Depth
Before 1980
4000
Before 1990
3000 Before 2000
2000
1000
0
0 2000 4000 6000 8000 10000
Water Depth ft
Rig rates for floating rigs have always been very sensitive to demand and industry
activity. It has not been uncommon to see the rate for a deepwater rig to be as low as
$35-40k/day during industry slow downs, then during times of high industry demand, the
rate for these rigs can double or triple. Historically, offshore platform rig rates have had
very stable daywork rates that are reflective of capital employed to build the rig and rig
labor costs. Jack up rig rates have been a bit more sensitive to industry demand. A
general rule-of-thumb is that rig rates will be about $600 to $1000/day per million dollars
of new construction cost. For example, a new ultra-deepwater semisubmersible with a
cost near $300 M and would have a dayrate near $225k/day.
Prior to the fifth generation rigs built or converted in the late 1990s and early 2000s,
floating rigs were typically outfitted to drill to only about 20,000 to 25,000 ft. These rigs
typically had 2000 or 3000 Hp drawworks and one million-pound rated derricks. Most of
the fifth generation rigs have much higher rated depth capacity (25,000 to 35,000 ft) with
4000 Hp or larger drawworks and derricks rated to as much as two million pounds.
1-7
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1.2.1 DRILLSHIPS
Drillships have the primary advantage of very high variable load capability, and they can
move long distances in a short time. Many early drillships had variable load capacity for
well supplies that could allow drilling an entire well without re-stocking. Variable loads of
10,000 to 20,000 tons would permit transit to a remote location with all the casing,
cement, mud products and other supplies needed to drill an entire well. This was an
important factor in early offshore drilling operations as many areas of the world lacked
the necessary infrastructure to obtain well supplies. Today most areas of the world have
a developed infrastructure and the importance of a high variable load is not as important.
An old industry rule-of-thumb for floating rigs is the variable load required for well
operations is 1000 tons per 1000 ft of water depth.
A high variable deckload is still important in deepwater since the riser system can have
an air weight approaching four to five million pounds (2000 to 2500 tons) rather than
the one to two million pounds air weight of riser systems for 1500 to 2000 ft water depth.
The large riser system air weight made shipshape vessels a logical choice for early
ultra-deepwater rigs.
1-8
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
All drillships today have shipshape hulls and are self-propelled with open water transit
speed of about 10-12 knots. For example, the Jack Ryan drillship traveled almost 2100
nautical miles from Trinidad to the Gulf of Mexico at an average speed of just over 10
knots in the spring of 2001 (8.7 transit days).
A disadvantage of drillships is that they are very sensitive to weather (wind, waves and
current) impacting the rig anywhere other than the bow. If environmental loads are
placed on the side of a rig rather than on the bow, very high rig motion results and
stationkeeping problems are increased. A moored shipshape vessel cannot change
the rig heading more than about five degrees (by adjusting mooring line tension) after
it is moored and is thus very sensitive to environmental loads impacting the rig on the
beam (side).
In the late 1970s very few turret moored shipshape vessels were built. These rigs had
mooring systems and limited dynamic positioning capability. The mooring was located
a ro u n d th e rig s m o o n p o o l circu m fe re n ce a n d a llo w e d th e rig to ch a n g e rig h e a d in g
(turn). Turret moored rigs typically had relatively small mooring systems and were not
capable of full dynamic positioning. This would keep the prevailing environment on the
bow and reduce vessel motions when the environment impacted the rig from a
quartering or beam environment. Only two turret moored shipshape vessels exist in
2001 (Discoverer 511 and Discoverer I).
Dynamically positioned rigs change bow heading (sometimes slowly) to keep the bow
into the environment. This minimizes vessel motion and environmental loads on the rig.
If the environment is not collinear (wind, wave and current not from the same direction)
shipshape vessels can have significant rig motions which may slow or prevent rig
operations. In many areas of the world such as the North Sea, winter environment
conditions are so severe that a shipshape vessel cannot safely work due to excessive
ship motions.
A disadvantage of shipshape rigs is their increased motion sensitivity to the direction and
intensity of the environment. Early shipshape rigs were used only in low environmental
conditions or areas such as in the summer months in the North Sea and offshore
Norway due to this sensitivity. The fifth generation shipshape rigs have improved motion
responses to the environment because of their large size and displacement.
1-9
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1.2.2 SEMISUBMERSIBLES
The primary advantage of semisubmersible rigs is the reduced sensitivity of rig motion
as a result of environmental loading. Wind and wave loads on the columns and the rig
structure are much less than those generated on a shipshape vessel. Generally,
semisubmersible rigs are not as dependent on the direction from which the environment
impacts the rig. Rig heading changes to minimize environmental loads are not required.
This is important for moored operations. Many semisubmersible rigs have the drill floor
located very near the center of the rig to take advantage of the reduced vessel motion at
this location on the rig.
Early shallow water depth rated semisubmersible rigs had very low variable loads.
Common variable loads were 1500 to 2000 tons, which limited well supplies that could
be carried on the rig. Most rigs drill with a low air gap (to improve vessel stability) and
transit at a higher draft (to permit higher transit speeds). At the higher transit draft, the
variable load of a semisubmersible is generally significantly reduced as required to
maintain vessel stability. Most semisubmersible designs would permit transit with only
minimal casing, well supplies or drillstring left standing in the derrick. This characteristic
of a semisubmersible rig requires frequent restocking with necessary well supplies.
The ultra-deepwater semisubmersible designs of the late 1990s have variable loads
as high as 8,000 to 10,000 tons. The riser can be the largest user of variable load on a
ultra-deepwater rig and can consume as much as 25 to 30% of the available variable
load. The ultra-deepwater rigs have drilling risers with larger (heavier) choke and kill
lines, longer joints (reduced weight of connections) and often use long lengths of bare
riser. Today new materials and designs can reduce the top deck riser weight as much as
15 %. New floatation materials offer about 20% more buoyancy per unit volume over
conventional buoyancy materials; however, presently there is a substantial cost
premium. Building risers out of composite materials is an emerging technology that may
reduce on-deck weight of the riser by 40-50 % in the future.
1 - 10
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
80 Semi
70
Transit time days
60
50
40
30 Assumptions:
20 1. Drillship speed = 10 kt
10
2.Semi speed = 6 knot
0
1000 3000 5000 7000 9000 11000
Transit Distance Nautical Miles
1 - 11
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Many semisubmersible rigs are moved on transport ships when a long rig move is
required. With a semisubmersible on the deck of the ship (dry tow) (Figure 1.7) the rig
transport ship can make in excess of 10-knots transit speed. Only recently have transit
ships been large enough to carry more than second generation size semisubmersibles.
The larger semisubmersibles were simply too large and weighed too much to place on
the transport vessel. In the late 1990s larger transport ships have become available and
some of the larger semisubmersibles can be dry transported.
Many early drillships and semisubmersible rigs had both thrusters and/or self-propulsion.
For example, most of the Aker H-3 semisubmersible rigs had thrusters and all of the
Odeco Victory class semisubmersible rigs had a propeller in each pontoon for self-
propulsion. As these rigs have been updated and modified over the years, many of the
older semisubmersible rigs have had their thrusters and/or self-propulsion features
removed. This was generally done for economic reasons as a semisubmersible with
self-propulsion is usually required to have a marine crew (captain, able-bodied seamen,
etc.) on the rig all the time. Typically these rigs are towed by tugboats between rig
locations today.
1 - 12
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
In the past, dynamic positioning has proved less reliable than moored operations in
m a in ta in in g a rig s p o sitio n o ve r a su b se a w e llh e a d . In 1 9 9 3 a n d 1 9 9 4 , a jo in t in d u stry
study (Deepstar) performed a qualitative risk assessment of emergency disconnect
frequency with dynamically positioned rigs(1). The report concluded that on average,
loss of station occurred once every 175 operational rig days. The new more advanced
dynamically positioning systems used on rigs built after the 1990s should have
increased reliability over the dynamically positioning systems included in this study.
Generally moored rig stationkeeping has a very high reliability. North Sea experience
indicates the probability of a total mooring system failure is once every 200 rig years.
The reliability of moored stationkeeping in milder environments such as the Gulf of
Mexico should be better.
Many operators have been reluctant to production test or complete production wells with
dynamically positioned rigs. The reliability of stationkeeping with dynamically positioned
rigs is the primary concern. For many areas of the world, these operations require a
separate barge to capture produced fluids (flaring has regulatory restrictions) which
further increase risk of these dynamically positioned operations.
Many of the large ultra-deepwater rigs built after the late 1990s (for example the
Discoverer Enterprise) have the potential to hold large volumes of produced crude in the
ships hull. This capability has a high cost for inert gas blanket systems in crude storage
tanks, increased regulatory and safety requirements, etc. Many of these rigs were
constructed with this capability; however, the necessary equipment has never been
installed and would have an added cost of several million dollars.
Dynamically positioned rigs typically have large power plants installed and consume
large quantities of fuel. Large dynamically positioned drillships and semisubmersible rigs
can average consuming 300 to 350 bbls of diesel per day. A standard moored rig will
typically have much less installed horsepower and average only 75-100 bbl/day of diesel
consumption. The difference in fuel cost is at least partially offset by the cost of anchor
handling vessels and time required for mooring. Providing for very large anchor
handling vessels needed for deepwater mooring in remote locations can be very
expensive.
In some areas of the world, the quantity of air emissions is tightly regulated and the
increased air emissions of a dynamically positioned rig must be considered. DP systems
will be covered in section 5.0.
1 - 13
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1 - 14
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1.3 ENVIRONMENT
This section is intended to provide a general background on the offshore environmental
data needed for the assessment of operating conditions and risks associated with
floating rig operations.
Effective operations with floating type rigs strongly depend on the environment. Unique
to floating drilling is the movement of the rig with the environment as compared to the
well and mudline.
A meteorologist generally gathers environmental data. Generally they develop a
prediction of future meteorological conditions after studying past data on winds, waves
and currents. From these data, models are developed that will permit predicting how
severe the environment may be in the future.
A method used to evaluate past environmental conditions is called a hindcast or the
determination of the magnitude of storms, which occurred at the rig site historically. An
environmental hindcast for a given area is usually available. For example, a joint industry
hindcast known as GUMSHOE is available for the Gulf of Mexico. The hindcast should
cover at least a three-year period. After the hindcast data is gathered and modeled, a
forecast of future environmental conditions can be made. Figure 1.8 shows the results
of a forecast of environmental conditions for use in rig stationkeeping and riser analysis.
40
35 Fifty Year Return
30 Twenty Year Return
25
Five Year Return Ten Year Return
20
15 One Year Return
10
95% Non-exceedance
5
20 40 60 80 100
Wind Speed knots
1 - 15
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
There are two commonly used methods to designate the severity of a design
environment for a floating rig. These methods are:
The cumulative probability method which specifies the percentage of time
during the average time period (year) that the environment (winds, seas and
current) will not exceed a given level.
The return period method which specifies the average recurrence interval
between the occurrence of a given environment.
Extreme meteorological conditions are usually modeled with the return period method.
Fixed platform, floating production facilities and floating rigs operating next to (or above)
offshore facilities often use this design approach. For example wind, waves and current
for a 100-year return period are often specified as the design environment for fixed
platforms, floating production facilities, etc.
For short-term floating rig operations away from other offshore structures or facilities,
the risk of a stationkeeping failure is less severe, and a lower design environment is
warranted. For low to moderate design environments, the cumulative probability method
is often used.
Wind, waves and current for a 100-year design environment are not the most severe
storm, which occurs once every 100 years. It is the environment, which has a 1/100
probability of being exceeded in one random year. The probability that a 100 year
environment will be exceeded in 100 years is 1-(0.99) 100 or 0.63. The probability that a
100 year storm will be exceeded in 20 years is 1-(0.99)20 = 0.18.
Prior to the mid 1990s, most floating rig stationkeeping analysis used the cumulative
probability method to determine the design environment. Today, most stationkeeping
analysis for floaters uses the return period method, and often, both methods are used.
In general, there is no direct correlation between the return period method and the
cumulative probability method.
ExxonMobil typically will use both the cumulative probability and the return period
method when analyzing the stationkeeping capabilities of a floating rig.
1 - 16
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
200 95%
180 One yr return
160 M iss. Canyon Blk 509
Force on rig Kips
120
100
80
60
40
20
0
Wind Wave Current
Figure 1.9 illustrates the loads imparted to a floating rig during a typical operating
environment. A floating rig responds to loads imparted to it by three environmental
conditions: winds, waves and currents. Usually, winds are the most significant
environmental load that impacts a floating rig.
1 - 17
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1.3.1 WINDS
Since wind loads can have a powerful effect on a floating rig, a basic understanding of
the cause and nature of winds is important.
Winds are caused by differences in atmospheric pressure that occur from one
geographic location to another. Winds flow from geographic areas with high pressure to
areas that have low pressure. High and low pressure geographic areas around the world
are generally created by differences in temperature.
The wind speed at any one location is a function of the difference between high and low
pressure across that location. As winds move due to pressure gradient differences from
one location to another, Corollas force affects its motion due to the rotation of the earth
and centripetal force due to the curvature of streamlines. When mapping winds, lines of
constant atmospheric pressure are called isobars. When isobars are closely spaced, the
pressure gradient is very large and winds will have higher velocity than where isobars
are spaced further apart. In the Northern Hemisphere, the Corollas force results in winds
circulating counter-clockwise. In the Southern Hemisphere, this force causes winds to
circulate in a clockwise direction.
Wind is air in horizontal or nearly horizontal motion and is named in accordance with the
direction from which it blows, i.e.; an east wind is from the east. The freedom of air to
move is a function of the proximity and topography of the surface it flows over. As air
flows over land, it behaves in an irregular fashion.
Friction between the ground
and the air produces Typical Wind Speed vs. Elevation Correlation
eddies in the air, which one hour mean w ind speed
produce gusts and lulls. 150
Convection from local
temperature differences 130
Height Above Sealevel - meters
1 - 18
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
For floating rigs, wind speeds are generally referenced to a height of 32.8 ft or 10 meters
above sealevel. Wind speed is generally expressed in knots; one knot is equivalent to
1.15 miles per hour. Since a knot is a measure of speed, it is incorrect to express wind
speed in knots per hour. Distances in marine operations are usually expressed in
nautical miles, which are equal to 1.15 statute miles. Dividing nautical miles by speed in
knots results in time.
The surface of air is least turbulent over the open sea where friction is reduced to a
minimum. Generally, winds are steadier and have higher velocity over the sea than over
a land surface. Wind speeds constantly fluctuate (i.e., gusts). To account for changing
wind speeds, floating rig stationkeeping design is based on average wind speed over
specified intervals. Typical designs call for one-minute, 10-minute or one-hour average
wind speed. In general, the shorter the average time interval, the higher the average
wind speed. Often, it is possible to develop a relationship between the one-minute, 10-
minute and one-hour wind speed for a given geographic area. A common error is to
confuse or misunderstand the difference between these three wind speed design
averages.
Approximate conversio n s a re o fte n u se fu l, a n d th is ro u g h b a llp a rk ru le -of-thumb can
easily be remembered:
(1-minute average wind speed) x 0.85 = 1 hour average wind speed
(20 meter (65.6 ft) height wind speed) x 0.92 = 10 meter (33ft) wind speed.
For example, a 50-knot wind observed at a 66-ft rig height would be roughly equal to a
45-knot wind at a 10-meter elevation.
Once the design wind speed is determined, a way to calculate the force imparted to the
rig from that wind speed must be determined. Wind forces on a floating rig impact the
projected area exposed to the wind. The load from wind is a square root function of the
wind velocity, and this general equation relates wind speed to load imparted to a floating
rig:
2
Wind Force = (wind speed) x shape coefficient x projected area of all
surfaces exposed to the wind
In addition to using more exact equations than the above general equation, model tests
are usually used to better quantify wind loads on a rig, and a meteorologist develops
wind speeds.
The projected area exposed to the wind should include columns, deck members,
deckhouses, trusses, crane boom, derrick substructure, drilling derrick and the hull
above the waterline. The shape coefficient typically ranges from about 0.5 to 1.5
depending on the exposed area. Since wind speed increases with height above
sealevel, this equation requires the correct wind speed for the elevation of the exposed
area.
The calculated wind forces on a rig can be treated as constant or as a combination of
a steady component and a time varying component. Generally, the second method will
use a longer average wind speed than when wind is treated as a constant. The time
varying component is also known as low-frequency wind force. Low-frequency wind
forces are normally computed with an empirical numerical method. Low-frequency
wind forces typically induce low frequency rig motions.
1 - 19
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1.3.2 WAVES
For very extreme meteorological conditions, (i.e., winds and waves) waves can be the
largest environmental load imparted to a rig.
Waves are generated by winds acting on the surface of the ocean over a distance. This
distance is called fetch. There is a relationship between wave height, wind speed, fetch
and the length of time that a wind blows. For a fixed fetch distance, increasing wind
forms increasing height waves. As fetch distance increases, a given wind will produce
bigger waves.
Swells are a system of waves that have moved out of the generating area into a region
of weaker opposing winds (or calm). Swells decrease in height with travel and may be
difficult to distinguish from locally wind-generated waves. Swells usually have a well-
rounded profile, a greater wave length, and disturb the water to a greater depth. Swells
indicate that there may have been strong winds or a severe storm recently hundreds of
miles away. The swells come from the same direction as the wind which created them
and may indicate an approaching storm.
A simple or a regular wave is shown in Figure 1.11. The basic measure of wave height
is called significant wave height represented by Hs. Hs is equal to the average of the
highest one third of the waves passing a point. This method is used because it is roughly
equivalent to what a trained observer would estimate as the wave height for a given
series of waves.
C = L /T = W a ve C e le rity
Seafloor
Wave Period The time that elapses for a wave to traverse its length.
Wave Height Difference in elevation between the wave crest and the proceeding wave trough.
Amplitude The height of the elevation of the wave crest above the still water level.
Wave Length The horizontal distance between two successive wave crests.
Wave Celerity The propagational speed of the wave.
Frequency The number of wave cycles per second
Figure 1.11 Definition of Simple Wave
1 - 20
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
The significant wave height is not the maximum wave height. The maximum wave height
is larger than the significant wave height. A rule-of-thumb is that the maximum wave
height is estimated to be 1.9 to 2.2 times the significant wave height.
The period of a wave is the time that elapses for a wave to traverse its length. The
motions of a floating rig are very dependent on the period of a wave. In general, the
longer the period of the waves the more the vessel will respond (heave) to the wave.
For a short period wave, vessel motion response will be lower. Typically, waves have a
period of 8 to 14 seconds with swells having the longest period and producing the most
floating rig motion response. Longer period waves travel faster than short period waves.
The period, length, energy level and the depth of swells can be the major factor affecting
the motion of a rig. Local weather can be insignificant but a large swell can have a large
impact on floating rig motions. Areas of the world where swell often impact floating rig
operations are West Africa, Brazil and Australia.
Determining the force imparted to a floating rig by waves is a very complex problem.
Typically, model tests or analytical methods are used to relate wave characteristics to a
force imparted to the rig. The direction a wave impacts the rig must also be considered
for this calculation.
1 - 21
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1.3.3 CURRENT
Current is important to floating rigs since current can have a large impact on many
drilling operations. Some operations, which can be significantly impacted by current,
include operations prior to running the BOPs and riser (open-water work), Remote
Operated Vehicle (ROV) operations and rig stationkeeping. Generally, problems arise in
currents exceeding two knots because of high drag loads on the riser and drilling vessel.
Currents are caused by local or global winds that drive water around the oceans. Ocean
current can generate a significant load on floating rigs. Unlike wind and waves, currents
will result in loads imposed both on the floating rig, tubulars and other equipment below
the ocean surface such as mooring equipment. A good understanding and knowledge of
the impact of current on floating rigs is essential.
Similar to wind, current loading on a floating rig is a square root function of the current
velocity, and this general equation shows this relationship:
2
Current Force = (current speed) x drag (or current) coefficient x
projected area of all surfaces exposed to the current or the wetted
surface area (shipshape hull).
Drag or current coefficients are generally established from model testing.
There are three general types of currents that are often encountered offshore. The first is
currents associated with major ocean circulatory currents, such as the Gulf Stream
located off the US East Coast. The second is locally induced currents and the third is
periodic currents associated with tidal flow.
Figure
Figure 1.12
1.12 Major
Major Ocean
Ocean Currents
Currents of
of the
the World
World
1 - 22
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Globally generated ocean currents generally are found worldwide but are usually found
at continent margins. Typically, current along the eastern margin of a continent are
stronger than current along the western margin of a continent. Figure 1.12 shows major
cu rre n ts o f th e e a rth s o ce a n s. S u b su rfa ce cu rre n ts ca n a lso b e d u e to th e rm a l
variations in the water column or bathsymetry changes. These currents can occur for
long sections at any depth in the ocean. The GOM eddy and Loop current are globally
generated currents.
Locally generated currents are driven by the wind and/or swell and are usually limited to
a relatively shallow surface layer of the ocean. Since winds and/or swell cause these
currents, they are usually collinear with the generating wind direction and are confined to
a relatively shallow surface layer.
General correlation of wind speed with locally generated currents can be made. For
example, for water depths greater than 250 ft in the Gulf of Mexico, current speed may
be taken as 2.5% of the wind speed of return periods of 5 to 50 years and as 1.5% of the
wind speed for a one-year return period (current uniformly distributed over the top 250 ft
of the water column). Another correlation sometimes used is that wind induced current
is 1% of the wind velocity at 32.8 ft elevation. Formulas other than these for variation of
current velocity with ocean depth can be considered if shown to be appropriate for the
site condition.
Currents associated with tidal events often affect long lengths of the water column but
are usually not found in deeper water depths. These currents change in direction over a
period of time. As the tide rises, the flow will be in one direction, and as it falls, it will be
another direction.
There are a few special environmental events that can affect environmental loading,
these include Tsunamis and Solitons. Tsunamis are very large waves caused by an
earthquake or volcanic eruption either on the ocean floor or near the shoreline. Both
waves and current can intensify as they move into shallower water.
Solitons are found most often in the Far East and are formed by a combination of
thermal variations, lunar tidal changes and bathymetry. A Soliton is an underwater wave
that is usually periodic in nature.
In many areas of the world historical current data is very minimal. In these cases, it is
common to install current meters on a temporary oceanfloor-anchored mooring to gather
tidal and global current information. This data gathering process may take in excess
of a year.
1 - 23
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1.3.4 DIRECTIONALITY
It is necessary to understand the direction from which the wind, waves and current
impact a floating drilling rig, since this will have a large effect on total environmental
loading. Figure 1.13 shows the definition of wind and wave directions (relative to a
drilling rig) as is commonly used when performing stationkeeping analysis. For winds
and waves, it is common to assume these two environmental loads impact a rig
collinearly or from the same direction. Likewise, wind generated surface current is
usually assumed to act on a rig collinearly with wind and wave forces.
1 - 24
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Currents, especially tidal or global currents, will usually impact a rig at a different
heading than the heading from which wind and waves impact the rig. In cases with high
global or tidal current, the rig heading may be chosen to minimize environmental loading
from current rather than to minimize loading from the wind and waves.
Wind and wave generated (storm generated) currents generally occur in shallow ocean
depths where the structure (hull, pontoons, columns) of floating rigs are located. Wind
and wave generated loads can be added with tidal or global currents if both these
environments impact the rig from the same direction. It is also possible for wind and
wave generated surface current to impact a rig at 90o or 180o from tidal or global current
orientation. Obviously not only the magnitude of wind, wave and current environments
are important, but also the direction of these environmental loading forces.
1 - 25
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
-4 24
Lig ht Ic ing
-7 20
-9 16
-11 12
-13 8
g
Ic i n
e
-16 4
ra t
de
Mo
-18 0 -2 1
-
28 0
-20 -4 1
30
(oC) (oF) 2
32
3
4
34
6
36
38
7
8
40
ng 9
ur
42
i
)
Ic
( oC
t
44
ra
ng vy
pe
i
46
Ic a
He
(o 8
vy
4
Se F)
Te
a
He
a
ry
Ve
1 - 26
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Using this figure for a location with a 14oF air temperature, wind velocity of 30 knots and
a sea temperature of 32oF, it indicates that heavy icing could be expected. Table 1.2 can
be used to estimate the icing accumulation expected for these icing categories:
Category Accumulation
____________ ______________________
Light 0.4 in. to 1.4 in. in 24 hours
Moderate 1.4 in. to 2.6 in. in 24 hours
Heavy 2.6 in. to 5.7 in. in 24 hours
Very Heavy 5.7 in. + in 24 hours
Table 1.2 - Categories of Icing Conditions
Icing can impact the loading and stability conditions of a rig and should be considered in
wind-force calculations.
Steel components, i.e., pontoons, columns, drilling riser, etc., exposed to temperatures
below 4oF should be qualified for cold temperature applications. Such qualification may
require material testing and special steel formulations for cold service. The special steels
used in cold environments are not as susceptible as common steels to becoming brittle
and fracturing in very cold environments. The operating range of elastomeric materials
should also be consistent with cold weather operations.
Many years ago weather mapping used a Beaufort scale to describe wind and sea state.
For reference, Table 1.3 summarizes and defines the Beaufort scale.
Wind Speed U.S. Estimated wind speed WMO Code
Beaufort S eam an s Weather Effects observed at sea Effects observed on land Term and height Code
meters per km per
Number knots mph term Bureau of waves in feet
second hour
Term
0 Under 1 Under 1 0 .0 0 .2 Under 1 Calm Sea like mirror Calm; smoke rises vertically
Ripples with appearance of scales; Smoke drift indicates wind
Calm, glassy, 0 0
1 1-3 1-3 0 .3 1 .5 15 Light air no foam crests direction; vanes do not
Light
move
Small wavelets; crests of glassy Wind felt in face; leaves
2 4-5 4-7 1 .6 3 .3 6 11 Light breeze Rippled, 0-1 1
apperance, not breaking rustle; vanes begin to move
Large wavelets; crests begin to Leaves , small twigs in
Gentle
3 7-10 8-12 3 .4 5 .4 12 19 Gentle break; scattered whitecaps constant motion; light flags Smooth, 102 2
breeze
extended
Small waves, becoming longer; Dust, leaves, and loose
Moderate
4 11-16 13-18 5 .5 7 .9 20 28 Moderate numberous whitecaps paper reaised up; small Slight, 2-4 3
breeze
branches move
Moderate waves, taking longer form; Small trees in leaf begin to
5 17-21 19-24 8 .0 1 0 .7 29 38 Fresh breeze Fresh Moderate, 4-8 4
many whitecaps; some spray sway
Larger waves forming; whitecaps Larger branchges of trees in
Strong
6 22-27 25-31 1 0 .8 1 3 .8 39 49 everywhere; more spray motion; whistling heard in Rough, 8-13 5
breeze
wires
Strong
Sea heaps up;white foam from Whole trees in motion;
Moderate
7 28-33 32-38 1 3 .9 1 7 .1 50 61 breaking waves begins to be blown resistance felt in walking
gale
in streaks against wind
Moderate high waves of greater Twigs and small branches
length; edges of crests begin to broken off trees; progress
8 34-40 39-46 1 7 .2 2 0 .7 62 74 Fresh gale Very rough, 13-20 6
break into spindrift; foam is blown in generally iompeded
Gale well marked streaks
High waves; sea begins to roll; Slight structural damage
9 41-47 47-54 2 0 .8 2 4 .4 75 88 Strong gale denbse streaks of foam; spray may occurs; slate blown from
reduce visibility roofs
Very high waves with overhanging Seldom experienced on
crests; sea takes white apperance as land; trees broken or
10 48-55 55-63 2 4 .5 2 8 .4 89 102 Whole gale High, 20-30 7
foam is blown in very dense streaks; uprotted; considerable
Whole
rolling is heavy and visibility reduced structural damage occurs
gale
Exceptionally high waves; sea Very rarely experienced on
11 56-63 64-72 2 8 .5 3 2 .6 103 117 Storm covered with white foam patches; land; usually accompanied Very high, 30-45 8
visibility still more reduced by widespread damage
12 64-71 73-82 3 2 .7 3 6 .9 118133 Air filled with foam; sea completely
13 72-80 83-92 3 7 .0 4 1 .4 134149 white with driving spray; visibility
14 81-89 93-103 4 1 .5 4 6 .1 150166 greatly reduced Phenomenal, over
Hurricane Hurricane 9
15 90-99 104-114 4 6 .2 5 0 .9 167183 45
16 100-108 115-125 5 1 .0 5 6 .0 184201
17 109-115 126-136 5 6 .1 6 1 .2 202-220
1 - 27
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1 - 28
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
After the design environmental conditions of a rig are determined, resulting rig motions
must be determined. Typically, environmental loads impact a rig and produce two types
of motions, mean or steady-state vessel offset and low frequency motions about the
mean vessel offset. Wind and currents are generally considered to produce steady state
vessel motion. Waves can produce both steady state motions and low-frequency
motions
A primary motion of a rig is the vessel offset. This is important, as it will affect riser and
structural casing design and operability. Vessel offset is caused by the combination of
current, wind and wave forces. Typically the steady state and low-frequency rig motions
are combined to calculate a mean or average vessel offset and a maximum vessel offset
which would include low-frequency vessel motions.
Vessel offset is measured as a percent of water depth for floating rigs. Figure 1.16
shows how vessel offset is measured for floating rigs. Vessel offset depends on many
factors including water depth, environment, riser system and rig design. The offset limits
for a rig under the maximum design and operating limits should be determined by a riser
analysis in conjunction with a stationkeeping analysis.
Offset = 100 ft = 5%
2000 ft
W ater D ep th = 2000
1 - 29
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
There are some general rules-of-thumb for vessel offset. Generally, the two conditions
are maximum design (and operating) condition and the allowable mean offset. The
allowable mean offset is the offset produced by mean or average environmental forces.
Maximum allowable offset includes the mean offset and low-frequency vessel motions.
Generally, the allowable mean offset falls in a range of two to four percent of water
depth. The lower bound generally applies to deepwater and the larger range applies to
shallow water (less than 300 ft) operations. Maximum allowable offset for deepwater is
typically in the range of 8% to 12% of water depth. The lower bound generally applies to
deepwater and the upper bound applies to shallow water. Generally, when a rig exceeds
its specified maximum operating limit, the riser is disconnected from the BOPs to prevent
rig equipment damage. After the riser disconnect, much larger offsets are possible
before rig motions become a limiting factor.
When a new rig design is first constructed, a model test is generally performed in a wave
tank and/or a wind tunnel. Rig response to a full range of wave frequencies is measured
and a response amplitude operator (RAO) graph results. The RAO curve is often used to
compare the motion response expected for different rig designs.
E ve ry rig h a s a n O p e ra tin g M a n u a l w ith th e rig s o p e ra tin g lim its fo r rig m o tio n s a n d
offsets clearly identified. This manual should be consulted and used when determining
permitable vessel motions in different operating conditions. Table 1.4 is a summary of
typical vessel motion limits for several rig operations.
1 - 30
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Heave for a floating rig can be limiting criteria for operations in some areas, especially in
areas with large swells. Typically the riser slip joint telescoping length will limit maximum
heave. Most older floating rigs have slip joints and riser tensioner systems with
maximum 50 ft stroke. For routine conditions, riser pup joints are used to space-out the
riser slip joint to permit about equal downward travel (25 ft) and upward travel (25 ft). In
deeper water depths it is common to space out the riser to permit a bit more upward
travel since vessel offset in deepwater can be significant. Figure 1.17 illustrates the gain
in riser length (slip joint scope) as a result of offset in various water depths. Newer fifth
generation rigs have longer stroke riser slip joints and riser tensioner systems (as much
as 65 ft stroke).
Figure 1.17 Gain in Riser Length for Vessel Offset for Various Water Depths
1 - 31
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
The riser tensioner system is a vital part of the marine riser system. The riser tensioners
apply vertical force to the top of the marine riser. The marine riser system is designed
a n d to p te n sio n se le cte d b a se d o n th e rise rs re sp o n se to th e e n viro n m e n ta l a n d
hydrostatic loads, as well as the requirement that it properly perform its functions.
Among the marine riser system functional constraints are the angles at both the lower
flex joint and the upper ball joint. Other constraints include ensuring stress levels in the
riser are below the allowable stresses. In addition to stresses resulting from some
functional constraints, stresses in the riser are also caused by dynamic loads, loads from
hydrostatic pressures (burst and collapse) and stress loads required to prevent the riser
from buckling. Since the riser has seawater on. the outside and a heavier mud on the
inside, a minimum riser tension is required to prevent the riser from buckling which can
add bending stresses and lead to a functional failure.
Specialized computer programs are generally used to predict riser behavior under the
design conditions. The analysis includes calculating the required riser top tension,
maximum permissible rig offsets and maximum loads on riser components. Detailed
information on the design of the marine drilling riser system will be covered in Section 9.
The riser tensioner system applies a constant vertical force to the riser while the floating
vessel moves vertically and laterally in response to the environment (wind waves and
current). The riser tensioners generally use high-pressure air (typically to 2000 to 2400
psi) applied to a piston area to generate constant upward force on the riser. Oil is usually
maintained in the piston only for lubrication. By keeping the pressure constant, applied
tension to the riser is held constant as the rig moves with the environment. Figure 1.18
shows the basic components of a typical riser tensioner system.
1 - 32
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Fixed Orifice
Accumulator
Air-Oil Reservoir
25-40 psi
Cylinder
Multiple (usually six to ten) hydraulic cylinders with wireline sheaves and wirerope are
generally used. The wire rope is reeved around the sheaves and one end of the wire
rope is attached to the outer barrel of the slip joint (the outer barrel is attached to the
riser, BOPs and seafloor). The hydraulic cylinders are powered by air pressure stored in
numerous pressure vessels. The tension on the wire rope and the riser is directly
proportional to the pressure of the stored air which is controlled at a specific value by the
Driller.
Most early floating rigs had limited riser tensioner capacity (generally less than 1000 kip)
which is generally adequate for shallow to moderate water depths and mud weights.
Most fourth and fifth generation floating rigs are designed for deeper water depths and
have higher tensioner capability, typically 2 to 3.5 million pounds. Some fifth-generation
rigs have as much as 4.8 million pounds of riser tensioning capacity.
The most often encountered riser tensioner is the Shaffer 80 kip, 50 ft travel unit. This
u n it is o fte n still re fe re n ce d a s a R u cke r te n sio n e r. T h e se te n sio n e rs a re o fte n m o u n te d
in pairs and riser tensioner capacity of rigs is often a multiple of 80 kip. Other companies
manufacture 80 kip, 50 ft travel tensioners. Larger tensioner units are often encountered
on later generation rigs that have a capacity of 160 kip or 250 kip each. A few rigs have
100 kip, 125 kip and various other rated tensioners with travels of 50 to 55 ft. A few early
generation floating rigs have 60 kip tensioners with a 40 ft stroke. These companies
manufacture riser tensioners: Shaffer, Vetco, Western Gear, Brown Brothers, and
Maritime Hydraulics.
1 - 33
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Most riser tensioner systems include a method to limit the speed and/or distance they
will pull the riser in the event of a structural failure of a riser or a broken wirerope. For
rigs that are dynamically positioned, the riser tensioner system also includes a more
sophisticated method (know as a riser recoil system) to limit and manage riser tension
and travel when a DP system failure occurs resulting in an emergency disconnect of the
riser from the subsea BOPs.
In the late 1990s, a new type of riser tensioner system illustrated in Figure 1.19 was
introduced and is included on several fifth generation rigs. These tensioners are called
In -lin e te n sio n e rs a n d w e re d e ve lo p e d fo r in cre a se d rise r te n sio n s a sso cia te d w ith
ultra-deepwater. The system operates essentially the same as conventional riser
tensioners except the hydraulic cylinders are attached directly to the riser tension rig and
each tensioner is rated to 800 kip.
Padeye
Diverter
Ball & Socket
Ball Joint To APV &
Oil Accumulators
Six 40-65'
Cylinders
Slip 800 kip each
Joint
Tensioner
Power Line
3000 psi
1 - 34
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
By the end of 2001, six ultradeep rigs have this type of riser tensioner system installed
and at least two more planned rig upgrades will include this new type riser tensioner
syste m . T h e p rim a ry a d va n ta g e o f In -lin e rise r te n sio n e r syste m s o ve r tra d itio n a l
wireline systems include: lower initial cost, lower maintenance cost and lower weight
(located lower on the rig).
An o th e r a d va n ta g e o f th e N -lin e rise r te n sio n syste m is th e T rip S a ve r o p tio n . W ith
this option, the riser tensioner cylinders are mounted under the rig floor on sliding
beams. This makes it possible to slide a deployed riser and BOP from under the well
center to an alternate site in the moonpool. This permits performing work at the well
center (such as running subsea trees) without retrieving the riser and BOPs.
Many riser tensioners often have common piping to an opposite tensioner. When one
tensioner is out of service for maintenance, often an opposite tensioner will also be out
of service. This is one reason riser designs often assume only ~ 80% of the riser
tensioner rated pull be relied on for riser tension. The riser tensioner air system is
usually hard-piped from stainless materials and requires very special welding and
cleaning procedures if the system is modified.
It is important that a rig have adequate air compressors, air pressure vessel (APV)
volume and emergency/standby capacity.
Almost all rigs have some guideline tensioners. Typically these are just smaller versions
of the riser tensioner units with 16 kip tension and 40 ft strokes. Some early generation
floating rigs have 14 kip 30 ft stroke guideline tensioners and several 22 kip 40 ft stroke
guideline tensioners have been manufactured. These units are often used for BOP pod
recovery umbilicals as well.
1 - 35
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
A floating rig moves on the ocean surface as a result of environmental loading and the
well, subsea wellhead and drilling riser are attached to the ocean floor. To compensate
for the vertical motion between the top of the riser and a floating rig, a riser slip joint is
u se d . T h e rise r slip jo in t te le sco p e s to p e rm it th is ve rtica l m o tio n . A d d itio n a lly th e slip
joint has a low-pressure seal to permit mud in the riser to return to the rig and the
surface mud system.
Figure 1.20 is a drawing of a typical riser slip joint. The outer barrel is attached to the
riser, the inner barrel is attached to and moves with the rig. The riser tensioners are
attached to the outer barrel only, and riser tension should not be transmitted to the inner
slip joint barrel. For dynamically positioned rigs, the riser tensioner rig has the capability
to rotate when rig heading changes are made.
Rig Floor
Diverter Packer
Diverter Housing Diverter Insert
Load Ring
Outer Barrel
Gooseneck
Not To Scale
Flexiable Pipe
Riser Coupling
Marine
Riser Choke, Kill, Boost or
Hydraulic Power Line
1 - 36
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
The seal between the inner and outer slip joint barrel is usually a packing element, which
provides a low-pressure seal. The packing element is a rubber bladder (similar in
principal to a tire inner tube), and internal air pressure activates the seal between the
inner and outer barrel. On some rigs, the air pressure to the packer can be regulated at
th e D rille rs co n so le to p e rm it in cre a sin g th e p a cke r p re ssu re if a le a k o ccu rs d u rin g a
riser flow situation. Many rigs use the rig air supply (80 to 100 psi) to charge the packer
which can limit increasing the packer pressure to match well pressure if it exceeds the
rig air pressure limitation. Some rigs have switched from low-pressure rig air to a high-
pressure air source and use a regulator to adjust the pressure in the packer. This
permits using higher pressure in the slip joint packer. Most slip joints have two packing
elements for redundancy. Often the upper packer is actually two pieces and can be
changed-out with the slip-joint in service. Usually the lower slip joint packer is a single
piece unit and cannot be replaced while the slip joint is in service. Some rigs have one
slip joint packer operated by air and the second packer hydraulically operated for
redundancy. Slip joints on older rigs typically provide for 50 ft of total travel, however,
later generation floating rigs have longer slip joints.
On some early ship-shape rigs, the rig floor is only 40-50 ft above sealevel. On these
rigs, the riser tension ring can be under sealevel, and short p ig ta ils o f w ire ro p e a re
used to place a connection in the riser tensioner wireropes above sealevel (where divers
will not be required to slip and cut the wireropes). If the top of the outer barrel is below
sealevel, it is also possible to reduce the slip joint packer pressure and allow seawater to
flood into the riser very fast. This could be an asset if severe lost returns were
experienced.
Each drilling contractor has their own philosophy on cutting and slipping the wirerope
used with conventional tensioner systems. Some contractors keep up with the ton-miles
service of the wire rope and slip and cut wirerope at specified intervals. Large
semisubmersible rigs in mild environments often have a very limited heave and most
contractors will not have a formal cut-and-slip wire rope policy for riser tensioners.
At the top of the inner barrel and just under the diverter housing and flowline, a flex joint
or ball joint permits the rig to roll and pitch. On some rigs a second riser flex joint is
located just under the slip joint to provide for additional rig roll and pitch.
Located below the riser tensioner ring are the termination connections for the choke, kill,
hydraulic power line and riser boost line. Steel armored flexible lines are typically used
to accommodate the motion of the upper flex joint and the telescoping joint. More
information on flexible lines can be found in Section 10.
More information on slip joints including operational information, inspection guidelines
and associated equipment can be found in Section 9.
1 - 37
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Drilling risers are rated by the API for different tension limits. These API designations
are shown in Table 1.5.
Marine Risers
Coupling Tensile Load Rating
Class Rated load
1 - 38
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
The earliest floating rigs did not have drillstring motion compensators. These rigs used
bumper subs or shock subs in the drillstring to accommodate for vertical rig motion (as
compared to the well). The first drillstring motion compensators were introduced in the
late 1970s and were generally rated for 400 kips and had strokes of 15, 20 or 25 ft.
The drillstring compensator isolates the drillstring from environmentally induced vertical
rig motions. The first compensators were mounted between the traveling block and the
hook. A major advantage of the drillstring compensator was to minimize wear inside the
BOPs, marine riser and casing when drilling. While drilling with weight on the bit, the
drillstring does not move (in relative position with the well) with rig motions. The
compensator also permitted better control of weight on bit which is important when
directional drilling. A disadvantage is that a drillstring compensator mounted between the
block and the hook requires a substantial height which requires that the derrick be taller.
Also, rails in the derrick are generally installed to control swinging motion of the
compensator as a result of ship motion. The compensator can add over 40 kips weight
to the traveling assembly.
1 - 39
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
The system operates very similarly to riser motion compensators with air pressure air
(up to 2400 psi) acting on a piston area. Usually oil is kept in the piston for lubrication
purposes. As the rig heaves upward, the compensator cylinders are compressed and the
hook moves downward (relative to the drill floor) and the hook stays at a constant level
with the earth (well). The cylinder pistons compress the air through the hose into the
APVs to maintain the preset tension level. As the rig heaves downward, air from the APV
expands into the compensator cylinders and the hook move upward in relationship to the
rig floor. Operation of a drillstring motion compensator is shown in Figure 1.22. During
operation, the compensator works at approximately midstroke and the only movement
relative to the rig is the drillstring, hook and cylinder rod. The traveling block, hoses and
main frame remain motionless relative to the drilling vessel. The Driller can increase,
decrease or maintain drill bit weight by controlling the pressure applied to the
compensator.
1 - 40
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Adjusting the air pressure sets the compensator tension. The air pressure is increased
by transferring air from the standby APV to the power APV and is decreased by bleeding
air. The weight on the drill bit equals the drill string weight minus the compensator weight
(traveling block and compensator main frame weight). The crown block weight indicator
determines the drillstring weight.
As an example, if a drillstring has a 200 kip weight and the desired WOB is 25 kip, then
the hookload gauge should be set to the force required as 200 minus traveling block
weight minus compensator main frame weight minus weight on bit. For example a 15 kip
traveling block, a 35 kip main frame weight and a 25 kip WOB, the hookload gauge
should read 125 kip (200-15-35-25).
Most motion compensators ca n b e lo cke d to p re ve n t th e co m p e n sa to r fro m o p e ra tin g .
W h e n a n in -lin e co m p e n sa to r is in th e lo cke d p o sitio n , th e te n sile lo a d o f th e
compensator will increase substantially. For example, when locked, the 400 kip Shaffer
motion compensator has a one million pound hookload capacity but there will be no
motion compensation. Typically leaf chains are used instead of wire rope on the
compensator pistons. The adjustment and maintenance of the chains are very important.
Inspection and wear checks of the compensator chains should be made when rigs
receive the initial pre-work inspection and on a monthly schedule.
The compensator shown in Figure 1.22 is a p a ssive co m p e n sa to r in th a t it m a in ta in s a
constant weight on the bit as set by the Driller. When a bit or other suspended string is
off bottom (no weight on the bit), the string moves with the rig. In other words, a passive
compensator will not react to vessel motion if the load is freely suspended from the
floating rig. For later generation rigs, this type motion compensator has been increased
in working loads to 500, 600, 800 and 1000 kips. Most passive drillstring motion
compensators can control WOB to about 8-12 % of total load. For example, for a drill
string with a weight of 450,000 lbs., the hookload may vary as much as 50,000 lbs.
before the compensator will function correctly. Passive compensators are also very
sluggish when in use with light string weights (or mass loads)(2).
In the mid 1980s, significant changes in drillstring motion compensator designs
occurred. Several contractors introduced the top mounted drillstring compensator at this
time. Advantages of a top-mounted compensator are less hookload fluctuation. The
system works essentially like a conventional in-line compensator except the cylinders
are located between the crown block and the traveling block or at the very top of the
derrick (Figure 1.23). This eliminates the need for heavy duty guide rails in the derrick.
These units typically have 25 ft stroke and are rated (compensating) to 600 or 1000 kips.
1 - 41
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1 - 42
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Difficulty landing subsea trees in extreme environments such as the North Sea led to the
development of active h e a ve co m p e n sa to rs in th e m id 1 9 9 0 s. T h e te rm a ctive h e a ve
refers to the addition of sensors to monitor rig heave and compensator position which
are then input to a computer. The computer then controls an active hydraulic cylinder
installed in a passive compensator system. With active heave compensation, the bit will
stay at the same position in reference to the bottom of the well. While landing a subsea
tree, the tree will stay in the same position relative to the seabed (and subsea wellhead)
througho u t a ll o f th e flo a tin g d rillin g rig s h e a ve m o tio n . M o st rig s th a t o p e ra te in e xtre m e
environments have an active heave compensating system.
The heave motion and compensator position sensors provide increased control of
drillstring motions by actively applying force to the passive compensator system.
Active heave compensation can be installed on both conventional in-line and top-
mounted passive heave compensator systems. Many rigs have conventional passive
motion compensators that have been retrofitted with active heave systems. An active
heave compensator retro-fitte d to a rig s e xistin g e q u ip m e n t ca n h a ve a co st o f a b o u t
$1.0M. Most rigs have active heave compensator systems that permit active heave
compensation across the full spectrum of operations. However, a few early rigs and
systems may have limitations (software) that will only be able to operate active heave
compensation in BOP and completion landing.
1 - 43
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
This system has several advantages over conventional traveling block and crown
mounted compensators:
1. The unit will electronically sense the relative motion of the vessel and eliminate the
need for changes in weight or pressure to compensate for rig vertical movement.
2. The full-rated load of the traveling equipment can be utilized during compensation
because the system is an integral part of the drawworks.
3. The system eliminates a large mass located high in the derrick, and thus rig stability
is increased.
4. A shorter derrick can be utilized.
These advantages are important in deepwater when loads (risers, long casing strings,
etc.) approach the weight limits of the traveling equipment.
This system uses a computer to process input from multiple sensors located on the
travel block, dead-line and on the rig structure. Programmable logic controllers then
activate AC motors that provide power to the drawworks. As much as 7000 continuous
HP is required for the drawworks. Several of these active heave compensating
drawworks are installed on fifth generation floating rigs.
1 - 44
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Wireline operations on a floating rig may also be impacted by the rig heave and may
require the use of the motion compensator. Figure 1.26 shows how the motion
compensator can be configured to operate during wireline operations by attaching a
cable from the block (motion compensator) to the outer barrel of the slip joint (outer
barrel is fixed to the riser not compensated). Since the wireline is attached at two
points, the deck of the rig and the wellbore, the motion compensator cable should be
attached to the outer barrel of the slip joint and run through a sheave above the wireline
sheave and back to the deck. This is necessary to maintain a one-to-one travel between
the wireline and the compensator. Therefore the distance between the hook and outer
barrel of the slip joint does not change was the rig heaves up and down.
1 - 45
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
The riser slip joint permits the vertical motions and offset of a floating rig. Flex joints
allow for the rig to roll, pitch and offset and are located at the top and the bottom of the
riser. As noted, almost all floating rigs have a ball joint located between the diverter and
the riser slip joint. This ball joint permits the rig to move in relationship to the top of the
riser. Most upper ball joints have a 10o maximum angle.
Located just above the subsurface BOPs, all floating rigs have a device to permit
misalignment between the BOP stack and the marine riser. This misalignment is caused
when the rig is offset from the well. Most flex joints can accommodate up to 10 o (in each
direction) misalignment.
Early floating rigs used ball joints just above the BOP stack. Almost all of these have
been replaced by flexjoints. The early ball joints were pressure balanced to minimize
frictional resistance to bending. Most used hydraulic oil pressurized from the rig. When
lower ball joints were used, appreciable wear often occurred as the angle change
between the riser and the BOPs occurred very quickly and the drillstring often was in
contact with the ball joint, riser and BOP inside diameter.
There are many different types
of flexjoints (Figure 1.27). Some
flex joints (Vetco Uniflex, Oil
States FlexJoint) permit a less
rapid angle change between the
riser and the BOPs. Some
flexjoints can be ordered
equipped to permit installation of
a wear bushing. As flexjoints
bend, they develop a reactive
bending moment that also helps
create a longer smoother bend
that will help mitigate drillstring
wear in the riser and BOPs.
The manufacturers of flex joints
build units with different
pressure and tensile ratings for
different water depths and
operating conditions.
To accommodate the flexjoint
bending, the choke, kill and
power fluid lines must flex. Early Figure 1.27, Typical Drilling Riser Flexjoint
generation rigs used spiral steel
flex loops (either horizontal or vertical loops) and almost all rigs today use flexible hoses
to accommodate this motion. Information on flexible hoses is found in Section 10.
1 - 46
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1 - 47
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
All modern floating rigs have a pneumatic bulk storage system, which is used for
cement, barite and often, benonite. Early floating rigs use about 40 psi air pressure to
move bulk materials through steel lines to the point of delivery, i.e., cement mixing or
mud mixing areas. Later floating rigs use higher air pressure systems (about 60 psi).
Similar to rigs, newer workboats have 60 psi bulk air systems. Most rigs use a dedicated
air supply system rather than rig air system. It is important that the bulk air supply have
adequate air dryers to remove moisture from the air used to move bulk materials.
Storage of bulk materials is in pressurized tanks often called P-tanks. These tanks vary
in size from about 500 cubic ft to over 3000 cubic ft. Workboats have similar P-tanks
and air systems installed for transfer of bulk materials from the supply base (on land)
and the rig. Anytime that any type of solid particle is moved through a line, static charges
will build up. For this reason only steel piping is used, and ground wires around rubber
hose sections should be installed.
Most second-generation rigs have roughly 8,000 to 10,000 cubic ft of cement and bulk
mud material storage capacity. Later generation rigs have more storage capacity, as
much as 20,000 to 25,000 cubic ft. It is generally best if bulk storage tanks are located
near their end use; e.g., cement bulk storage tanks should be near the cementing unit.
Shipping bulk materials over long distances or to much higher elevations has been
troublesome for many floating rig operations in the past.
Some rigs store bulk barite and cement in separate storage systems. With this
arrangement, it is not possible to ship barite to the cement mixing area. As a
contingency, every rig should have the ability to ship barite to the cement unit if well
control operations require mixing and pumping a barite plug.
A primary concern with bulk systems is contamination. For example, visually it is very
difficult to tell the difference between some types of cement and barite. It is very easy to
become confused and mix cement and barite or contaminate barite with bentonite, etc. It
is recommended a dedicated offloading hose be used for each bulk material stored on
the rig.
Periodically, it is necessary to clean P-tanks, which requires placing personnel in the
tank. This procedure should be very closely supervised to ensure adequate breathing air
is available in the tank, and that all applicable safety precautions are taken, i.e., limited
working time due to heat, breathing apparatus, etc.
1 - 48
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Most second generation semisubmersible rigs and some drillships handle drillpipe very
much like jackup, platform and land rigs. Some of these rigs have Iron Roughnecks and
spinning tongs. Drillpipe is racked into finger boards in the derrick by a derrickman.
The derricks on these floating rigs are designed to accommodate dynamic loads
resulting from a drillstring stood-back (since the derrick moves with rig motions).
Since floating rigs can have substantial rig motions, manual pipe handling is often
replaced with more sophisticated racking systems. Safety and reduction in drillstring
handling time have driven the industry to the more advanced drillstring handling
systems.
Some second-generation semisubmersibles and drillships have automated pipe-racking
systems. Examples of early automated vertical pipe racking systems are the BJ type V,
Maritime Hydraulics 3-arm systems, and the Varco PHM systems. A derrickman
operates an automated racking system, which lifts and moves a stand of drillpipe into a
fin g e rb o a rd . O n so m e rig s a sta b b in g a rm is u se d to h e lp limit motions of the drillpipe
while it is being moved around in the derrick.
Most early drillships used horizontal pipe racker systems. Since early drillships had
substantial rig motions, dynamic loading of a drillstring standing back in the derrick is
a concern. The horizontal pipe racker eliminated the need to stand a drillstring in
the derrick.
Horizontal pipe rackers store drillpipe in stands horizontally (Figure 1.28). The drillstring
storage racks are located just outside the derrick. A stand of drill pipe is moved to the rig
flo o r o n a ska te . W h e n th e to o l jo in t is n e a r th e ro ta ry, th e to p o f th e sta n d is p icke d u p
to the vertical position inside the derrick. The stand is then made-up and added to the
d rill p ip e in th e h o le . U su a lly a sta b b in g a rm is u se d to h o ld th e b o tto m o f th e sta n d
when it is stabbed into the drillstring in the rotary. When pulling out of the hole, the
process is reversed and the drill pipe is stored in stands (horizontally) in the pipe racker
on trips. Usually only very limited amounts of special tools are stood-back in the derrick
on the early drillships. Horizontal drillstring handling systems are susceptible to
mechanical or hydraulic failures and manual handling of a drillstring cannot be used
if the racker is broken.
1 - 49
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1 - 50
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1 - 51
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1.5.3 CRANES
There are two basic types of cranes used on floating rigs, mechanical and hydraulic
cranes. Mechanical cranes can have very fast lift times but require substantial operator
skill and training. Hydraulic cranes typically have slower lift speeds but are simpler to
operate. Most cranes are powered by a dedicated diesel engine, but electrically powered
cranes are sometimes found on floating rigs.
Since floating rigs move with the environment, cranes on these rigs must be designed to
accommodate dynamic loading. The dynamic loads exerted on a crane may be 2-3
times the static loads of the material being lifted.
Most second-generation floating rigs have cranes rated for a maximum of about 40 to 60
to n s w ith 1 0 0 to 1 2 0 ft b o o m s. T h e cra n e s ra te d ca p a city is b a se d o n th e sm a lle st liftin g
ra d iu s. T h e cra n e s ca p a city a t th e m a xim u m b o o m ra d iu s is a s lo w a s 5 -10 tons.
Typically, the heaviest loads a floating rig will handle are the wireline logging unit or a
double BOP ram body. The long riser joints on many fifth generation floating rigs can
approach 50,000-lbs air weight.
S e ve ra l fifth g e n e ra tio n rig s (D isco ve re r E n te rp rise ) h a ve cra n e s w ith kn u ckle b o o m s
(Figure 1.30). The boom on these cranes are segmented and this permits more control
on the crane and its load when high rig motions are being experienced.
1 - 52
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Most drilling contractors will limit crane operations to certain environmental operating
conditions. The sea state is the primary concern for cranes, but crane operations are
also limited by wind speed. It is a common requirement that cranes cannot be operated
when wind speed exceeds about 40 to 45 knots. This can be an important consideration
when developing plans for rig operations prior to tropical storms.
Every crane must be equipped with a load-rating chart that defines the maximum load
carrying capacity. For floating rigs, capacity in dynamic loading conditions are also
specified. Limits on wind velocity, rig motions, sea states, etc., are included on each
crane load carrying capacity.
Personnel bypassing safety systems cause most problems with rig cranes. It is common
for one rig crew to disable a safety system and then fail to reinstate it. The next crew will
assume the safety system is functional and rely on the safety system to prevent an
overload. If all safety systems are not operational, serious accidents can occur.
Crane booms are designed for vertical lifts only. Marginal side loads on a crane boom
will cause a failure.
1 - 53
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Almost all floating rigs are equipped with a 18-3/4 in. BOP 15 ksi systems today. A BOP
stack can have an air weight of as much as 500 kip. Generally, the lower marine riser
package will weigh 125-150 kip with the balance of the stack weight included in the ram
preventer package.
Most second-generation rigs stored the BOPs at the surface in two pieces. The LMRP
is stored in one location and the BOP rams in a second location. This permits handling
the BOP with a short rig floor substructure. Typically, overhead trolley cranes were used
to move the BOP sections from their storage stumps to the moonpool. Since the BOP
sections are transported with an overhead crane, it is free to swing with vessel motions.
Rig motions often limit BOP running operations when overhead cranes are used to
transport BOP stacks. Once the two BOP sections are mated in the moonpool, they
must be pressure tested to ensure pressure integrity of the system.
Some second and many most third generation rigs have taller substructures and can
move the entire BOP stack as a unit with overhead cranes. This eliminates the need to
test the BOP in the moonpool during critical path rig operations.
Many third and later generation rigs have BOP transporter systems. The BOP
transporter is a hydraulically operated carrier, which also serves as the BOP stump
when the BOPs are not being used. A transporter typically handles the entire BOP stack
as a unit. Since the transporter holds the BOPs, vessel motions do not affect the ability
of the stack to be run and retrieved. Many BOP transporter assemblies have guide rails
to permit control of the BOP while it passes through the splash zone. A disadvantage of
transporter systems is that they are heavy and typically require a large moonpool. Since
the BOP stack is handled in the moonpool (or even partially below the moonpool), a
relatively short derrick substructure can offset the added weight of the transporter
system.
BOP equipment will be covered in detail in Section 9.
1 - 54
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1 - 55
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1 - 56
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Classification societies generally require that a drilling vessel undergo a limited structural
inspection at a given time interval, i.e., every two years, and every four years. The
inspection society records will usually serve at least as a partial basis for determining the
structural integrity and history of the rig.
Floating rig owners use one of these classification societies (listed in order of commonly
encountered floating rigs): American Bureau of Shipping (ABS), Det Norske Veritas
(D n V ), L lo yd s R e g istry o f S h ip p in g , a n d B u re a u V e rita s.
Maritime regulatory bodies are affiliated with a national government. They require that a
floating vessel registered in that country or drilling offshore of that country meets certain
minimum standards with regard to safety equipment, marine equipment and crew.
Maritime regulatory bodies include the United States Coast Guard, the Norwegian
Maritime Directorate, and the United Kingdom Department of Transport. Floating rigs
and offshore support vessels generally receive periodic inspections by the regulatory in
order to keep their agency certificates current.
Some governments also have a regulatory agency, which sets standards and
procedures for rigs, drilling operations, personnel training and safety. Examples include
the United States Minerals Management Service, the Norwegian Petroleum Directorate
(NPD), and the Canada Oil, Gas and Lands Administration (COGLA). These agencies
often set rules covering drilling equipment, pressure testing of equipment, crew training,
safety systems (including life saving equipment), drills and many other areas.
1 - 57
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1 - 58
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
In moderate environment areas, another type of support vessel is often used to transport
personnel and limited amounts of deck cargo. Sometimes called crewboats or
speedboats, these ships are typically constructed of aluminum and can travel at over 10
knots. While they can carry a substantial number of people, they are generally limited to
a fairly small deck cargo weight and do not carry bulk materials. Speedboats used in the
Gulf of Mexico typically are 120-160 ft in length and have roughly 6000 Hp installed and
three or four propellers. In recent years, larger aluminum speedboats have been
constructed which are very fast and can also carry more deck cargo.
In areas of the world with more extreme environmental conditions, such frequent supply
of a rig cannot be made. In these areas larger ships are used for rig supply. Some rig
operations drilled in remote areas also use larger workboats due to the cost to provide
multi-function workboats. Since the ship is larger, many of these ships also have the
capability to handle anchors and mooring operations.
Many later offshore support vessels have a thruster installed into the bow to assist
stationkeeping next to a rig while it is offloading. The more advanced support vessels
have azimuthing main screws, large bow thrusters and a dynamically positioning system.
1 - 59
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
Anchor handling vessels and tugs are used to tow but only anchor-handling vessels are
used to install and retrieve mooring systems and equipment. An important characteristic
o f th e se tw o typ e s o f sh ip s a re th e ir b o lla rd p u ll. B o lla rd p u ll is th e m a xim u m
continuous pulling force that the workboat can exert when pulling against a stationary
object at zero forward speed. The bollard pull of a particular ship is a function of the
horsepower available to the propellers, the hull design and the environment, etc (Figure
1.32). The rated bollard of a ship is determined experimentally by the ship pulling against
a stationary object (anchor on the seafloor, pile, etc) in a calm wind and seastate and
measuring the line tension. Factors, which can reduce bollard pull, are vessel heading
re la tive to th e p u ll, re d u ce d e fficie n cy o f th e p o w e r p la n t w ith u se a n d e n viro n m e n ta l
condition. Heavy seastate and winds can have a large impact on the bollard pull of an
anchor handling vessel or a tug. A general rule-of-thumb is that a bollard pull of 25
pounds per horsepower can be expected of newer ships with well-maintained and
efficient power and propeller systems.
19000
Advertis ed AHV Bollard
Total Installed Horsepower
17000
25 lbs per ins talled Hp
15000
13000
11000
9000
7000
5000
50 75 100 125 150 175 200
Bollard pull - Long Ton
Ships used for towing have on the stern deck two hydraulically o p e ra te d p in s. T h e p in s
provide directional control of a tow wire between the tow winch and the stern of the ship.
They, in effect, move the pivot point of the towline from the winch location (usually
forward of midship) to a point near the stern of the ship. This prevents the towline from
moving over either the port or starboard side of the ship, which can cause a stability
problem.
1 - 60
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
The motion of an offshore support vessel can have important impacts on the efficiency
and safety of floating rig operations. Support vessel motions vary with boat size and the
hull design. Some hull shapes result in reduced ship motions. Generally, the larger the
ship, the better the motion response. Also, the deeper the draft of the hull, the better the
sh ip s m o tio n re sp o nse. The water depth at land-based dock facilities can often be a
limiting factor on the maximum draft of a support vessel, which can be used at the dock.
Similar to floating rigs, offshore support vessels have many regulatory bodies to ensure
vessel seaworthiness. The same classification societies, government regulatory bodies
that have regulations for floating drilling rigs generally also regulate offshore support
vessels. In addition, the International Maritime Organization (IMO) has developed certain
recommendations regarding international standards of maritime vessels. The IMO is an
international organization with members from participating countries and offers only
recommendations and has no enforcement authority.
Stability of an offshore support vessel is an important concern. Stability is a measure of
a sh ip s a b ility to re m a in a flo a t a n d u p rig h t w h e n a cte d u p o n b y e n viro n m e n ta l fo rce s (o r
when damaged and flooded). Generally a regulatory body such as the US Coast guard
will supervise stability tests and issue a stability letter. It is the responsibility of the ship's
ca p ta in to e n su re th a t th e sh ip s lo a d in g is in co m p lia n ce w ith th e a p p ro ve d sta b ility
letter.
Anchor Handling boats have many requirements on their winch, bollard pull and mooring
equipment-handling systems. These requirements are covered in Section 6.
1 - 61
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1.9 REFERENCES
1. S w o rn , A .W .: Q u a n tita tive R isk A n a lysis o f D isco n n e ct F a ilu re D u rin g D yn a m ica lly
P o sitio n e d D rillin g , R e p o rt 1 9 9 3 -221593, DeepStar Ia Project, Feb. 2, 1995.
2. Bennett, P.: A ctive H e a ve T h e B e n e fits to O p e ra tio n s a s S e e n in th e N o rth S e a ,
SPE 37956.
3. G a d d y, D .E .: U ltra d e e p D rillsh ip W ill R e a ct T o H e a ve W ith E le ctric -Compensating
D ra w w o rks, O il a n d G a s Jo u rn a l, Ju ly 2 1 , 1 9 9 7 .
1 - 62
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1.10 APPENDICIES
APPENDIX I - SEMISUBMERSIBLE RIGS
General
There are about 165 worldwide semisubmersible units available today (2000). From
about 1990 to 2000, the semisubmersible fleet has averaged about 160-165 units.
Generally, semis can be divided into five generations determined by rig design and year
of delivery. These groups can be sorted as follows (Table 1.6):
% World
Originally Built Fleet
1st Generation Before 1973 2
2nd Generation 1973 - 1981 46
3rd Generation 1982 - 1985 31
4th Generation 1986 1993 10
5th Generation 1993 - 2001 11
1 - 63
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1 - 64
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1 - 65
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
FLOATING DRILLING VESSELS
1 - 66
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2
Section
OBJECTIVES
On completion of this lesson, you will be able to:
Explain how water depth and RKB elevation impact fracture gradient and pore
pressure.
Be able to adjust mud weights, LOTs, etc. of an offset well to a different water depth
and RKB elevation.
Calculate fracture gradients for wells drilled with floating drilling rigs.
List the factors which impact equivalent circulating density and know which factors
are manageable.
Describe the factors which must be considered when selecting a mud type for a well
drilled with a floating rig.
Describe how natural gas hydrates affect the mud selection process.
2-1
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
CONTENTS Page
2-2
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2.1 OVERVIEW
As water depth increases beyond the point where bottom founded rigs can drill, floating
rigs and techniques are used while drilling exploration and most appraisal and
development wells. The special equipment used when floating rigs drill has an impact on
well designs. As water depth increases many floating rig drilling techniques become
critical to well planning and efficient operations. It is important that the issues associated
with floating rig operations be included in well planning.
Pore pressure and fracture gradient predictions are the most important factors that affect
well planning in deeper water depths (Figure 2.1). As water depth increases, the margin
between pore pressure and fracture gradient typically reduces as well. The well design
and cost are therefore heavily impacted by these predictions.
Every drilling engineer should be familiar with methods and procedures to develop pore
pressure and fracture gradient predictions. While ExxonMobil has specialists who
develop pore pressure and fracture gradients, it is necessary for the drilling engineer to
understand the basis and the uncertainties in their estimates as well as to compare their
estimates with offset wells.
2-3
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
This equation defines the fracture pressure as a variable dependent on the overburden
pressure, the formation pore pressure and the horizontal to vertical effective stress ratio
(K). This general method is used in many methods to predict fracture pressures. The
difference in most predictive methods is how to estimate pore pressure, overburden
pressure and the vertical effective stress ratio K.
2-4
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2.2.1 OVERBURDEN
The overburden pressure at a given depth is the weight of everything above it. e.g.,
seawater, density of soil from the mud line to the depth of interest. All well depth
references are from the rotary Kelly bushing (RKB). The air gap can have a significant
impact on overburden (especially shallow overburden) and should be included in all
overburden calculations. The air gap on floating rigs can range from about 40 ft to as
much as 125 ft.
The gradient of a seawater column does change slightly with water depth. However, this
change is usually insignificant, and generally a seawater hydrostatic pressure of 8.55
ppg (roughly 3.5 WT% salt) is a good estimate (4).
To estimate overburden below the mud line, the well depth from the mud line to the
depth of interest is usually broken down into numerous intervals. The bulk density of
each interval is then estimated and the overburden pressure of that interval calculated. A
sum of the overburden pressure from the seawater and all intervals below the mud line
will result in the total overburden pressure at the depth of interest.
2.4
2.3
2.2
Bulk Density, gm/cc
2.1
2
Best Curve Fit
1.9
1.6
0 2000 4000 6000 8000 10000
Subsea Depth ft
2-5
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
For deeper wells, bulk densities from density logs can be integrated to the depth of
interest and will result in a good estimate of overburden pressure. Unfortunately, density
logs are seldom run in shallow hole sections of a well and getting an estimate of shallow
below mud line overburden pressure can be difficult. Soil boring data is available in
almost all areas of the world, and typically, soil borings will penetrate from a few feet to
as much as 2000 ft below the mud line. The submerged unit weight of soil can be
integrated to develop an overburden pressure for shallow formations. Figure 2.2 is an
example of a bulk density vs. depth below sea level plot for a GOM shelf well.
Overburden pressure is expressed in psi. An overburden gradient is measured in psi/ft
and is the normal method used in the industry to express overburden. The overburden
gradient for a well typically increases asymptotically with depth and should near a 1.0
psi/ft (19.2 ppg or a 2.3 SG) with depth. Figure 2.3 shows typical overburden gradient
curves from around the world.
1.0 psi/ft
2000
4000
6000
Depth Below Mudline - ft
8000
Offshoe California
12000
Gulf Coast - Fertl &
Timko
14000 MW Shelf, Australia
20000
13 14 15 16 17 18 19 20 21
Overburden pressure Gradient- lbs/gal
2-6
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2-7
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2-8
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
Overburden Gradient
Pore Pressure
9000 Eaton
Daines
Christman
Brennan & Annis
11000 Simmons & Rau
Barker & Woods
13000
Depth RKB, ft TVD
15000
17000
19000
21000
23000
25000
9 10 11 12 13 14 15 16 17
Stress Gradients, ppge
Figure 2.4 - Comparison of Different Fracture Gradient Prediction Methods
2-9
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
By far the most common method to estimate fracture gradients is the Eaton Technique
(8)
. T h is m e th o d re la te s th e e ffe ctive stre ss ra tio to P o isso n s ra tio . P o isso n s ra tio is
th e n co rre la te d w ith o ve rb u rd e n g ra d ie n t. B o th P o isso n s ra tio a n d o ve rb u rd e n a re
variable with depth. Table 2.1 summarizes many of the fracture gradient prediction
methods. The impact of tectonic effects on formation stress states is not directly
incorporated in these predictive techniques.
Eaton (1968) f(Poisson's, OB) yes yes Gulf Coast, Land, Shelf
Daines (1980 & 1982) f(Poisson's) yes yes f(first PIT) All, international
Beekels & Van Eekelan (1982) f(depth) no mo Offset PIT Land, worldwide
Brennan & Annis (1984) f(effective stress) yes yes GOM shelf
Simmons & Rau (1988) f(Poisson's) yes yes Deepwater, modified Eaton
Rocha & Bourgoyne (1984) f(depth, compaction) no yes Need computer & Brazil, deepwater worldwide
offset well info
2 - 10
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
In shallow water and on land, the pore pressure can have a significant impact on the
calculated fracture gradient. In deeper water, the pore pressure has a lesser impact on
the fracture gradient prediction. Figure 2.5 illustrates the sensitivity of calculated fracture
gradients to pore pressure with a fixed overburden gradient for a well in 7400 ft. water
depth.
2 - 11
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
Figure 2.6 illustrates that as water depth increases, the need for accurate predictions of
fracture gradient, overburden gradient and pore pressure increases. Many times
deepwater wells have a very small margin between fracture gradient and pore pressure
gradient. Small errors in either fracture gradient or pore pressure predictions can result
in a well not achieving its geologic objectives, or the achievable well depth being
constrained. In these cases, accurate prediction of casing setting depths is also very
difficult, and the well plan has a high degree of uncertainty. The very high cost of
deepwater operations further heightens the critical need for accurate predictions.
Shelf
Increasing
Water
Depth
Deepwater
2 - 12
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2 - 13
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
1000
WD 1 = 2000 ft
2000 WD 2 = 3500 ft
3000
Mudline
4000
3500 ft
5000
RKB 1 = 5548 ft PIT 1 = 13.2 ppg
6000
7000 PIT 2 = ?
RKB 2 = 7102 ft
8000
9000
10000
P IT 2 (p p g ) = P IT 1 x (R K B 1 / R K B 2 ) + 8 .5 5 x (W D 2 W D 1 /R K B 2 )
PIT2 = 12.1 ppg (Adjusted to proposed well water depth and RKB)
Figure 2.7 - Method to Correct Offset Well for Water Depth and RKB Elevation
2 - 14
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
Figures 2.8 and 2.9 illustrate how adjusting offset well PITs to a common reference
water depth and RKB elevation will help improve the mud weight prediction for a
new well.
13 305, 7073'
429-2, 6134'
12
Mud weight (ppg)
476, 6626'
11.5
520, 6738'
11
522, 6929'
10.5
606, 6294'
10
607, 6588'
9.5 657, 7520'
9 348, 7209'
8.5 Block WD
8
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
11000
12000
13000
14000
Depth below mud line, ft
2 - 15
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
12.0 429-2
11.5 476
11.0 520
10.5 522
10.0 606
607
9.5
657
9.0
348
8.5
8.0
1000
2000
3000
4000
5000
6000
7000
8000
9000
0
10000
11000
12000
13000
14000
Depth below mud line, ft
Figure 2.9 - Offset Well Mud Weight Adjusted to a Common WD and RKB
2 - 16
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
For most shelf and normal pressured wells, ECD is usually not a design issue. Common
casing sizes and low to moderate mud weights result in ECDs, which are relatively
small, typically 0.5 ppg or less. Also, for most of these wells, there is a large margin
between the pore pressure gradient and the fracture gradient, and a small ECD does not
have a significant effect on initial well design or operational procedures. In cases where
a large margin exists, ECD is less important. However there is an increasing number of
shelf wells and shallow water wells being drilled where ECD is a much higher concern
and constraint.
2 - 17
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
With increasing water depth and well depth, the number of casing strings required to
reach total depth often increases. These wells usually have a low margin between pore
pressure and fracture gradient, several tight clearance liner strings, small hole sizes,
higher mud weights and much higher ECDs. For example, a recent well drilled with a
floating rig in the GOM required nine casing strings to reach 23,000 ft total depth. Also, a
GOM well in 9687 ft. water depth required six casing strings to reach 20,500 ft rkb with a
final mud weight of only 11.1 ppg.
In many ultra-deep wells, ECDs of as much as 1.5 ppg are often encountered (17). Active
management of several drilling parameters, special well planning issues and special
procedures are required for these wells to ensure they reach their geologic objectives.
When drilling a well with a small margin between pore pressure and fracture gradient,
it is often difficult to maintain enough mud weight to overbalance pore pressure when
not circulating and keep ECD low enough to prevent lost returns when circulating
and drilling.
When the pore pressure to fracture gradient margin is small, determining where to set a
casing string can be very difficult. In some cases, increased formation integrity from
setting a casing string can be more than offset by the increased ECD resulting from
su b se q u e n t sm a lle r ca sin g , d rill p ip e a n d h o le size . T h e w e lls a ch ie va b le d e p th m a y b e
limited, and setting several additional casing strings may not significantly improve the
likelihood of achieving deeper well depths. Drilling with underbalanced mud weight is not
an option with many wells drilled with floating rigs as the formation lacks enough
strength and the wellbore becomes unstable. A large volume kick can result very quickly
when drilling into a high permeability, thick sand (high KH) when mud weight is even
slightly underbalanced. As a result there is a tendency to experience large volume
and/or large intensity formation influxes when drilling with large ECDs.
2 - 18
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
Figure 2.11 illustrates that, as well depth increases, ECD typically increases, and the
degree of underbalance can rapidly increase when the ECD is removed.
14000
16000
Min.
18000
Well Depth ft
20000
ECD = 1.5 ppg
Typical Range
22000
24000
ECD = 0.5 ppg Max.
26000
28000
ECD = 1.0 ppg
30000
0 500 1000 1500 2000 2500
BHP Change Due to ECD psi
ECDs can be managed by optimizing mud rheology, well geometry, mud circulation
rates, well angle and rate of penetration while drilling (18). Figure 2.12 illustrates how
ECD can be managed (reduced) by optimizing these factors.
2 - 19
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2 - 20
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2 - 21
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2 - 22
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2 - 23
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2 - 24
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
1.2
Actual Wells
1 Minimum
Margin PIT-MW, ppg
Average
0.8
0.6
0.4
0.2
0
25 20 15 10 5
Hole Size in.
2 - 25
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
After the optimum setting depth of the conductor casing is planned, selection of
subsequent casing string setting depths is straightforward. With the expected fracture
gradient and mud weight schedule known, the margin between ECD and the mud
weight below that string will determine the string setting depth. This process is shown
in Figure 2.14 for a generic deepwater well in 7400 ft. water depth.
7000
13000
Setting Depth 16" @ 12000'
15000
17000
19000
8 9 10 11 12 13 14 15 16
Mud Weight, PPG
2 - 26
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
This process is continued downhole until reaching the desired well depth or until there
are no longer any casing strings available. The final casing setting depths for the generic
well are shown in Figure 2.15.
7000
Barker FG
0.3 ppg Predicted Mud Weight.
9000
20" conductor @ 10,000'
PIT = 10.2 ppg
11000
16" @ 12000'
TVD Depth, rkb-ft
13-3/8" @ 14500'
PIT = 12.8 ppg
15000
0.4 ppg
9-5/8" @ 17200'
17000
PIT = 12.2 ppg
19000
8 9 10 11 12 13 14 15 16
Mud Weight, PPG
Figure 2.15 - Final Generic Well Casing Strings Setting Depth Design
2 - 27
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2 - 28
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2 - 29
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2 - 30
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2 - 31
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
36-in. 36-in.
Top of Cement
20-in. 20-in.
Top of Cement
Void
Mud
Cement
13 3/8-in. 13 3/8-in.
Figure 2.16 - Casing Annulus Options, Wells Drilled With a Floating Rig
BURST LOADING
The following guidelines are recommended for calculating annulus pressures for burst
design of casing strings when the strings are landed in a SSWH. The guidelines depend
on whether the casing annuli is sealed with cement at the last casing shoe.
The typical case found with casing strings set in wells with floating rigs is not to seal the
annulus with cement. This is also the preferred method of preventing excessive pressure
buildup in casing annuli. Figure 2.17 illustrates this design condition. Typically it is
possible to place casing strings so that primary cement will not seal the casing annulus
at the previous casing shoe.
2 - 32
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
With this case, fluids and pressures in the casing annulus change with time. Pressure at
the casing annulus seal assembly is assumed to balance the local formation pore
pressure below the last casing shoe. Depending on water depth, casing setting depth,
mud weight and exposed formation pore pressure, the mud left in the casing annulus
may or may not drop as shown in Figure 2.17.
36-in. 36-in.
Mud Drop
20-in. 20-in.
Void
Mud
Cement
13 3/8-in. 13 3/8-in.
Figure 2.17 - Casing Burst Design, Annulus Not Sealed With Cement
The recommended pressures to use in burst design when designing casing for floating
operations when the annulus is not sealed with cement are:
1. Assume that the mud in the casing annulus will drop below the seal assembly to
a depth that the setting mud weight will balance the local pore pressure at the
shoe, then use zero backup from the seal assembly to the top of the mud
column.
2. Next use setting mud weight gradient from the top of the mud to the previous
casing shoe.
3. Then use the local pore pressure gradient from the last casing shoe to the design
string setting depth.
Appendix 2 includes an example showing how this recommended method can be used
when designing for burst conditions.
2 - 33
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
The presence of shallow hydrocarbons can complicate the goal of leaving casing annuli
non-sealed. It is common practice to cover all hydrocarbon intervals with primary
cement, and this is a regulatory requirement in many areas such as the GOM.
When a hydrocarbon zone is near a previous casing shoe, it can be difficult to cover the
hydrocarbon interval with cement and still leave the shoe at the previous annulus open,
not sealed with cement. It may be necessary to use less than optimum casing setting
depths to leave casing annuli open after hydrocarbon zones are properly cemented.
In a few cases, it may be necessary to seal a casing annulus with cement creating a
trapped volume. When this condition exists, the hydrostatic pressure trapped below the
seal assembly cannot bleed-off to the formation. For this case, the recommended
pressures for use in burst design are:
1. Use zero psi burst backup pressure at the seal assembly.
2. Use setting mud weight from the seal assembly to the top of cement.
3. Use a 9.0 ppg gradient for the cement column (from top of cement to the outer
casing shoe depth).
4. Use local formation pressure gradient from the outer casing shoe depth to the
casing setting depth.
COLLAPSE DESIGN
For collapse design of strings landed in a subsea wellhead, it is recommended that the
external pressure be assumed to be the casing setting mud weight. Credit is not taken
for possible pressure reduction due to fluid loss to exposed formations below the outer
casing string (even if the annulus is not sealed with cement). The worst case assumption
is that permeable formations do not exist below the outer casing shoe.
2 - 34
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2 - 35
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
Most wells drilled with floating rigs will drill at least some very geologically young
formations. Typically, very young formations are very sensitive to water. When drilling
these intervals with non-inhibitive muds it is co m m o n to e xp e rie n ce so ca lle d g u m b o
problems. Gumbo can be a significant drilling problem and can limit drilling rates, plug
flowlines and result in oversize hole and formation evaluation problems. As a result,
many operators use inhibitive muds to drill shallow reactive formations. It is common to
drill with high sodium chloride muds, calcium chloride muds and even SBM to prevent
gumbo problems when drilling shallow formations.
2 - 36
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2 - 37
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2 - 38
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
The hydrate formation conditions can be altered by the addition of inhibitors and
promoters. Hydrate inhibitors include salts, alcohols and glycols that lower the threshold
temperature at which hydrates form. Alcohols such as methanol are the most effective
hydrate inhibitors, however addition of alcohols to the mud system has many detrimental
effects, and are generally not used by the industry. Salts including sodium chloride and
calcium chloride are the most often used hydrate inhibitor in drilling mud systems.
Glycols are essentially low-grade alcohols and include ethylene glycol and glycerol, and
they are commonly used in mud systems as hydrate inhibitors.
Other inhibitors function by slowing down rather than preventing the formation of gas
h yd ra te crysta ls. T h e d e ve lo p m e n t o f kin e tic in h ib ito rs has occurred recently, but they
have not been used in drilling fluid systems to date. A primary advantage of kinetic
inhibitors is they apparently function at very low concentrations. However, they are quite
expensive. Hydrate promoters include nitrogen, hydrogen sulfide, oxygen, carbon
dioxide and some other compounds such as lecithin (glyceryl esters).
The pressure at the BOPs is due to the hydrostatic head of the fluid in the well or choke
line plus any surface pressure. Figure 2.20 illustrates an example of subsea conditions
that could be expected with mud weights from 9 to 16 ppg mud with 1000 psi casing
pressure and temperatures at the mud line for the GOM.
16 ppg
1000' WD
9 ppg
500' WD
1000
30 35 40 45 50 55 60 65 70 75
Seafloor Temperature Deg. F
Experience has shown natural gas hydrates can form when water in the drilling mud
interfaces with natural gas in a wellbore (21). Natural gas in a wellbore can occur due to
formation influxes (kicks) and the process of circulating out a kick. Water in the wellbore
can also be a result of formation water that entered the wellbore during the kick.
2 - 39
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
The pressure and temperature conditions where hydrates begin to form is called the
equilibrium condition. The equilibrium hydrate formation conditions for several common
drilling muds are shown in Figure 2.21. The addition of inhibitors (salts or alcohols) to
the liquid phase of a water based mud will depress the P-T conditions where hydrates
can occur.
9 ppg 500' WD
Hydrates
Seawater M ud
23 wt%NaCl + 10%Glycol
Equilibrium charts such as Figure 2.21 do not take into account the kinetics of hydrate
formation. Laboratory testing has shown that the speed a hydrate requires to form
depends on many factors including the magnitude the actual P-T conditions are below
equilibrium condition (supercooling). Figure 2.22 illustrates a typical P-T curve as
hydrate forms and the equilibrium condition.
2 - 40
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
4000
Hydrates Forming
Cooling
3500
Hydrate
Pressure, psi
Formed
Equilibrium
3000 Condition
Hydrates Decomposing
2500 Heating
65 70 75 80 85 90 95
Temperature, Degrees F
Figure 2.23 is based on laboratory testing with 24-WT% sodium chloride mud and
illustrates that the risk of forming a hydrate increases with time when the P-T conditions
are less than the hydrate forming equilibrium conditions.
6.1%C2
9 ppg 500' WD
High Risk
No Hydrates in 24 hrs
No Risk of Hydrates
Low Risk
24-wt% NaCl M ud
Equilibrium
1000
30 35 40 45 50 55 60 65 70 75
Seafloor Temperature Deg. F
2 - 41
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
(22)
Figure 2.14 - Example Risk Analysis of a Hydrate Inhibitive Mud
2 - 42
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
Beginning in the mid-1980s, synthetic based drilling muds began to be used with floating
rig operations by some operators. These muds use refined base oil rather than diesel or
mineral oil to reduce the toxicity of the mud and permit cuttings discharges in some
areas. Hydrates can form in a synthetic base mud system. The hydrate inhibition
characteristic of an SBM is primarily a function of the inhibitor concentration in the
dispersed water. The base oil in an SBM can be thought of as an inert ingredient as far
as hydrate formation is concerned. Water in an SBM is generally dispersed in the oil
phase, and it typically has a very high inhibitor concentration (calcium chloride). Testing
of an SBM found that an SBM with 30% CaCl2 in the internal phase did not form
hydrates under extreme subcooling. However, hydrates did form when the concentration
of CaCl2 was reduced to 15-WT% (22). Unlike water based muds, gas is soluble in a
synthetic oil based mud system which can permit gas and the water (which is dispersed
in the oil phase) to come in contact. Research has found that an SBM without salt in the
water phase formed more hydrates faster than are formed in a partially hydrate inhibitive
water based mud system (22). Also, any formation water that occurs with a gas influx can
provide the free water required to form a hydrate in an SBM system.
It is possible to depress the hydrate formation conditions to about 30oF if water based
mud is nearly saturated with sodium chloride. Unfortunately, the minimum density of a
near saturation sodium chloride water based mud is near 10.4 ppg. In many cases, the
formation integrity at the conductor casing will not permit use of a mud with a density
over about 10 ppg. This could be a problem if a shallow gas sand were expected when
the maximum mud weight cannot allow adding sodium chloride to a high saturation in
the mud.
In this situation, either higher risk of hydrate formation must be accepted, or additional
alternate inhibitors must be used. For water based muds, it is typical to run the sodium
chloride concentration at 20 to 24-WT%. As the sodium chloride concentration
approaches saturation, the hydrate inhibition ability of a mud increases faster. As a
result a mud with 20-WT% sodium chloride will have much less hydrate inhibitive
capability than a mud with 24-WT% sodium chloride. Over about 26-WT% sodium
chloride, additional sodium chloride actually is detrimental to hydrate inhibition efforts.
Mixing salts, i.e., NaCl and CaCl2 in a mud system can have solubility problems and salt
precipitation can result. Table 2.2 can be used to convert the chloride ion concentration
of a mud to the WT%.
2 - 43
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
Additional hydrate depression with a water based mud (below what can be achieved with
salts) must be achieved with the addition of different inhibitors, usually low-grade
alcohols. Low-grade alcohols include glycerol and glycols. With the addition of these
inhibitors, a water based mud can be formulated to achieve a maximum of about 40oF
hydrate depression. Some operators use significantly under saturated water based
muds and rely on using pills with inhibitors such as ethylene glycol as a mitigator when a
potential hydrate condition exists.
Sodium Chloride is the most effective hydrate inhibitor (on a weight basis). Calcium
chloride is a very effective hydrate inhibitor, however calcium chloride muds can be toxic
to marine life and difficult to handle. The use of calcium chloride muds should be
carefully considered. Potassium chloride water based muds are fairly poor hydrate
inhibited systems.
In the late 1980s and early 1990s, the industry performed a great deal of testing on
various hydrate inhibitive mud systems (23). A consulting engineering company, Westport
Technology developed a computer program to calculate the hydrate equilibrium
conditions for many mud systems used by floating rigs. The computer program called
Whyp is used by many in the industry. The computer program only calculates equilibrium
conditions (pressure and temperature) and does not give any qualitative information on
the kinetics of hydrate formation in drilling muds.
2 - 44
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
Hydrates can also be encountered with floating rigs outside the wellbore. It is common to
observe gas bubbles outside the structural casing and even between the structural and
conductor casing strings. The gas bubbles often accumulate and form a hydrate on the
outside of the BOP stack, wellhead connector and the subsea wellhead. The wellhead
manufacturers have designed into their equipment precautions to prevent hydrates from
forming in critical locations.
For example most wellhead connectors have a seal to keep gas and hydrates out of the
gap between the wellhead connector and the subsea wellhead. Also newer wellhead
connectors usually have the ability for an ROV to inject chemicals into areas of the
connector that could become plugged with hydrates. It is also common to install a seal
between the subsea wellhead housing and the mud mat to help prevent gas migration.
The formation of natural gas hydrates has occurred many times during deepwater
operations, sometimes when not expected. For example, one operator was using a
water based mud system during P&A operations and allowed the sodium chloride
concentration of the mud to drop significantly (to lower mud density). The mud hydrate
equilibrium conditions were significantly under the conditions where hydrates are
calculated to occur. Unfortunately, natural gas was in a casing annulus below a wellhead
seal assembly. When the seal assembly was unset, the gas quickly formed a hydrate
plug with the drilling mud and plugged both choke and kill lines and the BOPs. Several
days were required to resolve this problem and complete abandonment operations on
the well.
2 - 45
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
REFERENCES:
1. H u b b e rt, M . K ., a n d W illis, C .G .: M e ch a n ics o f H yd ra u lic F ra ctu rin g , T ra n s. A IM E
(1957) 210.
2. C h ristm a n , S .A .: O ffsh o re F ra ctu re G ra d ie n ts, S P E 4 1 3 3 , JPT (Aug. 1973).
3. M a tth e w s, W .R . a n d K e lly, Jo h n ,: H o w to P re d ict F o rm a tion Pressure and Fracture
G ra d ie n t fro m E le ctric L o g s, Oil and Gas Journal ( Feb. 20, 1967) 92-116.
4. S m ith , R .C . a n d C a lve rt, D .G .: T h e u se o f S e a W a te r in W e ll C e m e n tin g , JPT,
(June 1975) 759-764.
5. E a to n , B .A .: T h e E q u a tio n fo r G e o p re ssu re P re d ictio n fro m W e ll L o g s, S o cie ty o f
Petroleum Engineers of AIME, SPE 5544.
6. B o w e rs, G .L .: P o re P re ssu re E stim a tio n F ro m V e lo city D a ta : A cco u n tin g fo r
O ve rp re ssu re M e ch a n ism s B e sid e s U n d e rco m p a ctio n , S P E 2 7 4 8 9 p re se n te d to th e
1984 IADC/SPE Drilling Conference in Dallas, Texas.
7. W a rp in ski, N .R . a n d S m ith , M ich a e l B e rry: R o ck m e ch a n ics a n d F ra ctu re
G e o m e try, R e ce n t A d va n ce s in H yd ra u lic F ra ctu rin g , S P E M o n o g ra p h (1 9 8 9 ), vo l.
12, pp57-80.
8. E a to n , B .A .: F ra ctu re G ra d ie n t P re d ictio n a n d its A p p lica tio n in O ilfie ld O p e ra tio n s,
JPT (Oct. 1969) 1353-1360.
9. B re n n a n , R .M . a n d A n n is, M .R .: A N e w F ra ctu re G ra d ie n t P re d ictio n T e ch n iq u e
th a t S h o w s G o o d R e su lts in th e G u lf o f M e xico , S P E 1 3 2 1 0 , 1 9 8 4 .
10. D a in e s, S .R .: P re d ictio n o f F ra ctu re P re ssu re s fo r W ild ca t W e lls, S P E 9 2 5 4 , 1980.
11. C o n sta n t, D .W . a n d B o u rg o yn e , A .T .: F ra ctu re -Gradient Prediction for Offshore
W e lls, SPE Drilling Engineering (June 1988) 136-140.
12. S im m o n s, E .L . a n d R a u , W .E .: P re d ictin g D e e p w a te r F ra ctu re P re ssu re s: A
P ro p o sa l, S P E 1 8 0 2 5 , p re se n te d a t th e 1 9 8 8 SPE Annual Technical Conference
and Exhibition, Houston, Oct. 2-5, 1988.
13. R o ch a , L .A . a n d B o u rg o yn e , A .T .: A N e w S im p le M e th o d o f E stim a te F ra ctu re
P re ssu re G ra d ie n t, S P E 2 8 7 1 0 , 1 9 9 4 .
14. B a rke r, J.W .: E stim a tin g S h a llo w B e lo w M u d lin e D e e p w a te r G O M F ra ctu re
G ra d ie n ts, p re se n te d a t th e 1 9 9 7 H o u sto n A A D E C h a p te r A n n u a l T e ch n ica l F o ru m .
15. E a to n , B .A . a n d E a to n , T .L .: F ra ctu re G ra d ie n t P re d ictio n fo r th e N e w G e n e ra tio n ,
World Oil (Oct. 1997), 93-100.
16. A a d n o y, B e rn t S .: G e o m e ch a n ica l A n a lysis fo r D e e p w a te r D rillin g , IA D C /S P E
39339, 1998.
2 - 46
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
2 - 47
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
APPENDICIES
SOLUTION
Eaton Technique for Deepwater (15):
Step 1: Using Figure 2.15, the overburden at the three desired well depths is:
Overburden Overburden
Depth, TVD-rkb-ft Gradient, psi/ft Pressure, psi/ppg
5100 0.58 2958/11.15
6700 0.68 4556/13.07
9050 0.75 6788/14.42
2 - 48
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
EATON EQUATIONS:
P o isso n s R a tio (v) for 0 to 4999.9 ft below the mud line:
CALCULATION RESULTS
Calc. Fracture Actual Fracture
Depth, TVD ft P o isso n s R a tio - v Gradient, psi/ft/ppg Pressure, psi/ft/ppg
5100 0.390 0.5380/10.35 0.5356/10.3
6700 0.440 0.6356/12.22 0.6344/12.2
9050 0.470 0.7393/14.21 0.7384/14.2
2 - 49
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
Figure 2.15 - E atons A verage O verburden D ensity Data For Various Water Depths
2 - 50
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
LOT,ppg = 2816/0.052/5100 ft
= 10.6 ppg
CALCULATION RESULTS
2 - 51
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
SOLUTION
Step 1, Calculate Annular Mud Drop
In this case there is no seal trapping a fixed volume outside the casing string. The mud
in the annulus can leak-off to the formation. Based on the surface casing setting depth of
3500 ft subsea, calculate the annular mud drop below the casing seal assembly to
balance the 12.5 ppg annular fluid with 9.0 ppg pore pressure (below the surface
casing).
This is the subsea depth to which the fluid level will drop. Therefore, plot zero backup
pressure from the seal assembly down to the top of the annular fluid at 980 ft. subsea.
Draw a straight line between this pressure and the zero pressure point at the top of the
annular fluid at 980 ft. subsea.
2 - 52
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
Step 2, Calculate the Formation Backup Pressure at the Protection Casing Shoe
While there is a transition from 9.0 to 12.5 ppg over the last 1000 ft of this hole section,
use 9.0 ppg for the hole section backup calculation.
Formation pressure at the protection casing shoe = 9.0 ppg x 0.052 x 8500 ft
= 3978 psi
Plot this pressure at the protective casing shoe at 8500 ft subsea and draw the 9.0 ppg
gradient line between this point and the pressure at the surface casing shoe.
234 psi
Pressure psi
3000 3000
Surface 1638 psi
4000 3500 ft subsea 4000
3000 ft BML
Depth 5000 12.5 ppg 5000 Depth
ft Subsea 12.5 ppg setting MW gradient ft Subsea
6000 6000
Top of Cement
7000 7000
2 - 53
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
EXAMPLE 2
Annular mud drop does not fall below the subsea wellhead seal assembly
Given: Water depth = 4000 ft, protection casing will be set at 12,000 ft subsea (8000 ft
bml), Surface casing is set at 7000 ft subsea (3000 ft bml) in normal 9.0 ppg pore
pressure. Pore pressure of 9.0 ppf exists from the mud line to 11,000 ft subsea and then
a transition to 12.0 ppg pore pressure at 12,000 ft subsea. Cement will be brought above
the top of abnormal pressure but below the surface casing shoe. The final mud weight
the protective casing is set in is 12.5 ppg. See Figure 2.17 for the wellbore sketch.
SOLUTION
Step 1: Calculate Annular Mud Drop
In this case there is no cement seal at the surface casing shoe in the casing annulus.
Based on the surface casing setting depth of 7000 ft subsea, calculate the annular drop
required to balance the 12.5 ppg annular fluid with 9.0 ppg pore pressure.
Formation pressure at the surface casing shoe = 7000 ft x 9.0 ppg x 0.052
= 3276 psi
Because this depth is still above the mud line, the fluid level will not fall below the seal
assembly in the casing annulus. Plot the formation pressure at the surface casing shoe
at 7000 ft subsea.
Net pressure at the SSWH = 3276 psi 1950 psi = 1326 psi
Plot this pressure at the SSWH at 4000 ft. subsea and draw the 12.5 ppg gradient line
between this point and the pressure at the surface casing shoe.
2 - 54
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL DESIGN ISSUES
Plot this pressure at the protective casing shoe and draw the 9.0 ppg gradient line
between this point and the pressure at the surface casing shoe.
Pressure psi
1000 1000
2000 2000
Figure 2.17 - Example Problem #2, Casing Burst Back-up Pressure Example
2 - 55
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3
Section
3.0 STABILITY
OBJECTIVES
Define the symbols, definitions and theoretical relationships of the Small Angle (Initial)
Stability Theory.
Define the data collected and procedures used in a daily ballast control Variable Load
Form.
3-1
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
CONTENTS Page
3-2
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
When a vessel is floating, it must be able to resist the forces of the environment and
remain upright (Figure 3.1). Stability is a way of describing the ability of a rig to resist
th e se fo rce s. In ta ct sta b ility is th e rig s a b ility to re m a in u p rig h t w h e n th e re is n o d amage
or flooding, while damage stability is the stability of a rig after flooding has occurred.
Adequate stability is a requirement for safe operation. The design and operating goal is
to maintain the vessel in a condition where accidents do not lead to catastrophes.
Stability is achieved via the interaction of buoyancy and gravity acting on the vessel. The
buoyancy force is exactly equal and opposite to the gravity force. Buoyancy is provided by
the displacement of water. Archimedes determined that the weight of displaced water is
equal to the weight of the floating object. When a vessel is floating, the buoyancy force is
exactly equal and opposite to the gravity force. The buoyancy force acts through the center
of buoyancy. This point is generally referred to as B or CB. The location of B is a function of
the hull shape. Since we can't change the hull without taking the vessel into a yard, the
position of the CB is fixed for a given draft, trim and list. The distance from the keel to the
center of buoyancy is called KB (keel, K, to center of buoyancy, B).
3-3
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3-4
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
The center of gravity (G) is the geometric center of mass of the vessel (Figure 3.3). G can
also be defined as the center of the concentration of the weight of the vessel and all
weights on board, and is the point at which all the downward forces of weight can be
considered to act.
Keel (K) is the baseline or reference plane from which vertical measurements are taken.
3-5
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
K G is the ve rtical dista nce o f th e vessels gross center of gravity above the keel. KG is
measured in feet to the nearest hundredth. In general, a lower KG produces better stability.
Vertical center of gravity (VCG) is the distance the center of a weight is located above
the keel. VCG is measured in feet to the nearest hundredth.
The gravitational force acts through the center of gravity and is equal to the total weight
of the vessel, i.e., the sum of the lightship and the deadweight. By varying the
deadweight's location, we can manipulate the position of the center of gravity.
3-6
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
150.0L.T. 150.0L.T.
VCG
140.0 ft WL1
WL1 G1 WL1
WL1
WL
G WL WL G WL
new
KG G1
KG
new KG VCG
54.00 ft KG 12.00
53.50 ft
KG
100.0 L.T. K 100.0 L.T.
Figure 3.4 - Weight Added High Figure 3.5 - Weight Added Low
3-7
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
Shifting Weight Up
The center of gravity (G) will move parallel to, and in the same direction as a weight shifted.
If the weight is shifted up (Figure 3.7) from a lower VCG to a higher VCG, G will move up,
and in the same direction as the weight that was shifted creating a new KG, which is higher.
In general, a higher KG produces less stability. When shifting a weight, there is no change
in displacement or mean draft.
3-8
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
Figure 3.8 Removing Upper Weight Figure 3.9 Removing Lower Weight
3-9
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
The center of buoyancy (B) is located at the geometric center of the underwater portion of
the vessel. KB is the vertical distance in feet from the keel to the center of buoyancy. KB
cha nge s as the vessels m ea n d ra ft chan ges.
3 - 10
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
The center of gravity section discussed how the adding, removing or shifting of weights
would affect location of G. The center of buoyancy section discussed how lowering or
raising the draft would affect the location of B. However, during actual drilling operations,
the Ballast Control Operator (BCO) will maintain a constant draft for the drilling vessel.
Thus if a weight is added removed or shifted, the BCO will remove, add or shift ballast
water to compensate for the change in the weights to maintain the constant draft.
3 - 11
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3.1.6 INCLINATION
In initial stability theory, when the vessel is inclined to a small angle of about 10o, the center
of buoyancy (B) moves to the inclined (low) side/end. This movement is in the arc of a
circle until it reaches the new geometric center of the underwater portion of the rig. Since
the rig is three-dimensional, the location of G or B must be described in the vertical,
transverse and longitudinal planes.
WL WL
Figure 3.13 - Movement of B During Inclination Figure 3.14 First Dimension - Vertical
3 - 12
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3 - 13
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
Figure 3.17 - Longitudinal Center of Gravity Figure 3.18 Third Dimension - Longitudinal
3 - 14
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3.1.7 METACENTER
When a rig lists, the center of buoyancy swings in an arc. The origin point for the arc is
called the metacenter (M) (Figure 3.19). The M is located by the intersection of a vertical
line above the original center of buoyancy (B) when the vessel is level, and a vertical line
above the new center of buoyancy (B1) when the vessel is inclined to a small angle of about
10 degrees. The metacentric radius, BM, is the radius length of the arc that the center of
buoyancy swings along.
The height of the metacenter in Figure 3.20 above the keel (KM) is measured in feet and is
determined by the KB and the metacentric radius, BM. KM changes as mean draft
changes.
KM = KB + BM
KM = Height of the Metacenter, feet
KB = Height of the center of buoyancy, feet
BM = Metacentric Radius, feet
3 - 15
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
As displacement and mean draft increase in Figure 3.21, the volume of displacement
increases, which increases KB. If the waterplane area does not change, the net result is
that BM is reduced causing the metacenter to lower, creating a smaller KM.
Figure 3.21 - Increase in Volume of Displacement Figure 3.22 Decrease in Volume of Displacement
As displacement and mean draft decrease in Figure 3.22, the volume of displacement
decreases. If the waterplane area does not change, the net result is that BM increases,
causing the metacenter (M) to rise, creating a higher/larger KM.
3 - 16
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
As shown in Figure 3.23, metacentric height (GM) is the vertical distance in feet from
the center of gravity (G) to the metacenter (M). G must be lower than M (KG less than
KM) for the vessel to have positive stability.
G M is th e m easure o f a vesse ls initialsta bility. A s G M incre a ses, the vessels in itial stability
increases. As GM decreases, the vessels in itial stability d ecre ases.
For any particular mean draft, M will remain constant, and as such, only the movement of G
will affect GM. As displacement and mean draft change, GM will be affected both by the
movement of G and M.
GM
G
KM
KG
WL
B
3 - 17
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3 - 18
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
Righting arm (GZ) is the horizontal distance between the vertically downward force of
gravity (G) and the vertically upward force of buoyancy (B) after the vessel has been
inclined by an external force. GZ is a distance in feet measured along a line from the
center of gravity to a point (Z) perpendicular to a line representing the buoyancy force.
Righting moment (RM) is the amount of force available to right the vessel. R M is the
product of the displacement () and the righting arm (GZ). RM= x GZ.
As KG decreases in Figure 3.25, GM increases creating a longer righting arm (GZ) and
therefore a larger righting moment (RM).
Environmental Forces
Environmental Forces
Figure 3.25 Righting Arm (GZ) Increases Figure 3.26 Righting Arm (GZ) Decreases
As KG increases in Figure 3.26, GM decreases, creating a shorter righting arm (GZ) and
therefore a smaller righting moment (RM).
A rig s sta bility can be d e scribed a s p ositive , n eu tral or ne ga tive.
3 - 19
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
When the center of gravity is at the same vertical height as the metacenter, no righting arm
exists. If the vessel is inclined to a small angle by an external force, the vessel will remain
in the inclined position after the external force is removed. In neutral stability (Figure 3.28),
the KG equals the KM. The angle at which the vessel comes to rest with neutral stability is
called the angle of loll. This is its new initial position, and if further heeled by an external
force, will return to this position when that force is removed.
3 - 20
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3 - 21
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
7000
6000
Righting Moment
5000
4000
3000
2000
1000
0
0 5 10 15 20 25 30 35 40 45 50
Inclination (degrees)
3 - 22
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3 - 23
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3.2.1 KG CALCULATIONS
ADDING WEIGHT
Your present displacement is 14,000 long tons. KG at this displacement is 62.00 feet. 200
long tons of casing is loaded on your deck at a VCG of 130.00 feet. How will KG be
affected with the addition of the weight? To find the answer, follow these steps:
1. Multiply original displacement by
original KG. The result will be a vertical
moment of force in ft/tons. 14,000 LT 62.00 FT = 868,000 ft-tons
2. Multiply the loaded weight by its VCG. 200 LT 130.00 feet = 26,000 ft-tons
3. Add the load to original displacement 14,000 + 200 = 14,200 LT
and add the moments of force to get 868,000 + 26,000 = 894,000 ft-tons
4. Divide the total moments by the total
displacement. The result, expressed in
feet, is the new KG. 894,000 14,200 = New KG at 62.96 feet.
Because the weight was added above the original center of gravity, G moved up a total of
0.96 ft.
REMOVING WEIGHT
In order to determine the shift of KG when weights are removed, the only difference in the
process is that the weight and moments are subtracted from the original displacement and
moments. Suppose your original displacement was 18,500 long tons and your KG was
68.00 feet. If 210 long tons at a VCG of 115.00 feet were discharged, the computation
would be:
ORIGINAL DISPLACEMENT: 18,500 LT 68.00 FEET = 1,258,000 ft tons
Load removed: - 210 LT 115.00 feet = - 24,150 ft tons
New displacement: 18,290 long tons 1,233,850 ft tons
1,233,850 18,290 = New KG at 67.46 feet.
3 - 24
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
SHIFTING WEIGHT
Calculating the new KG when weights are shifted is actually a process of removing
(subtracting) a weight from its old VCG and then adding the same weight to its new VCG.
Example: The rig has a displacement of 21,000 long tons and a KG of 58.00 feet. A
weight of 180 long tons with a VCG of 110.00 feet is moved to a VCG of 167.00 feet.
WEIGHT KG\VCG VERTICAL MOMENTS
21,000 58.00 feet 1,218,000 ft-tons
-180 110.00 feet - 19,800 ft-tons
+180 167.00 feet + 30,060 ft-tons
21,000 1,228,260 ft-tons
1,228,260 21,000 = New KG at 58.49 feet.
The original displacement is multiplied by the original KG to obtain the vertical moments
before the weight is shifted. The shifted weight is assigned a minus (-) sign, placed in
the weight column and multiplied by its original VCG to determine a negative moment.
The shifted weight is then added back (assigned a plus (+) sign), placed in the weight
co lu m n a n d m u ltip lie d b y its n e w K G w h ich is p la ce d in th e m o m e n ts co lu m n . T h e
moments are then totaled and divided by the displacement (which will be the original
displacement as the weight was not added or removed from the rig).
3 - 25
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3 - 26
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
Sample Problem
A vessels displace m en t is 1 3,0 00 lo n g tons, flo ating in salt w a ter. T he vessels K G is
64.38 feet. A salt-water tank 50-ft in length and 30 ft in breadth has been added to the
vessel. If the tank were half full of seawater what would be the transverse and longitudinal
free surface corrections to KG?
3 - 27
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3 - 28
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
Metacentric height (GM) is a distance in feet measured from the center of gravity (G) to the
height of the metacenter (KM). As long as KG is numerically less than KM, the vessel
possesses positive initial stability, and GM is positive. Should KG be numerically greater
than KM, the vessel possesses negative initial stability (the vessel is in an unstable
con dition ), a nd G M w ou ld b e n eg ative. S ince m e tacentric he ight is a m e a sure o f a vessels
initial stability, GM must be calculated for any loaded condition.
The basic formula is: GM = KM - KG
Where:
GM = metacentric height, feet.
KM = heigh t o f th e m e tacen te r, fe et. F ou nd in the vesse ls h ydrostatic
tables/curves for a particular mean draft or displacement.
KG = height of the center of gravity, feet (based upon the known location
of all weights, and determined by calculation).
O nce the vessels K G has b ee n d ete rm ine d, the fre e su rface (F S ) co rrection m ust be
calculated. Since FS causes a virtual rise in th e vessels center of g ra vity and is d iffere nt in
both longitudinal and transverse directions there will be two corrected KGs; KGT and KGL.
Since there are two KGs, there are correspondingly two KMs, KMT and KML. Therefore
two GMs must be calculated, GMT and GML. KMT and KML are tabulated separately in the
vesse ls h yd rosta tic ta ble s fo r an y p articu la r m ea n dra ft o r displace m en t.
The Transverse Center of Gravity (TCG) and the Longitudinal Center of Gravity (LCG) are
determined in exactly the same manner as the vertical center of gravity.
The TCG of any particular load (logging skid, casing load, container, etc.) is its distance in
feet to port (-) or to starboard (+) o f th e vessels fore a nd a ft ce nte rline . A b oard a
semisubmersible drilling rig the LCG of a weight is its distance forward (-) or aft (+) of
amidships. For a drill-ship, LCG is measured in feet either aft of the forward perpendicular
or forward of the aft perpendicular.
The TCG and LCG for each item are first determined. The weight of the load is multiplied
by the respective TCG and LCG to determine the transverse moments (TM) and
longitudinal moments (LM).
The transverse and longitudinal moments for all loads are added and then divided by the
vesse ls disp lace m en t to determ in e th e rig 's T C G and L C G .
3 - 29
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
Trim is the difference between the drafts forward and aft. If the draft aft is greater than the
draft forward, the vessel is said to be trimmed (or down) by the stern. If the forward draft is
greater than the draft aft, the vessel is said to be trimmed (or down) by the bow.
List or heel is the difference in feet and inches between the port and starboard drafts. If the
port drafts are greater, the vessel is listed/heeled to port. If the starboard drafts are greater,
the vessel is listed/heeled to starboard.
Trim and list are calculated from the draft readings.
The most common means of referring to trim and list is in degrees. The control room
operator compensates for added, discharged and shifted weights by pumping ballast from
or into lower hull ballast tanks and from column tanks. The control room operator uses
transverse and longitudinal inclinometers measuring list and trim (respectively) in degrees
to accomplish this.
3 - 30
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
A vessels list/h eel a nd trim ca n be calcula te d usin g the T he ory of M o m e nts. A w eight
moved through a distance equals a moment. The total heel or trim moments are
calculated, and when divided by the MH1 or MT1, heel or trim is determined. MH1 or MT1
may be available on the hydrostatic curves or determined from formulae.
3 - 31
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
Figure 3.33
Figure 3.34
3 - 32
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
Sample Problem:
A semisubmersible drilling rig with a displacement of 14,566 long tons and KMT of 81.52
ft is preparing for an incline test. A weight of 40 long tons is moved a distance of 68 ft to
port. The plumb line length is 50 ft and deflection is 24 in.
1. W h a t is th e ve sse ls K G T ?
(A) in. 24 in.
TAN = (L) ft x 12 in. TAN = 50 ft x 12 in. TAN = 0.04
40 L. T. x 68 ft 2720
GM = 14566 L.T. x 0.04 GM = 582.64 GM (GMT) = 4.67 ft
KGT = KMT (-) GMT
KGT = 81.52 (-) 4.67
KGT = 76.85 ft
KG = KGT (-) FSCT
3 - 33
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
When a vessel heels beyond a small angle of about 10 degrees (Figure 3.35), the center of
buoyancy (B) continues to move to the inclined side and the metacenter (M) increases in
height due to an increase in waterplane area at the new waterline. The result is an
increase in stability as metacentric height and righting arm increase, providing that the
center of gravity does not increase in height, or shift to the inclined side.
WL
WL1
WL1
WL
The angle of inclination at which maximum righting arm is developed is the angle at which
the deck edge becomes immersed. This is called the downflooding angle (Figure 3.36). At
this angle the maximum wedge of buoyancy has been gained on the immersed side. The
maximum angle in degrees at deck edge immersion is governed by the amount of
freeboard. The larger the freeboard, the larger the maximum angle.
At deck edge immersion, maximum waterplane area will have been achieved; thus KM will
have reached its highest point. After deck edge immersion, the waterplane area will
decrease rapidly, causing a lowering of the metacenter and a rapid decrease in GM.
3 - 34
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
After the deck edge is immersed, no additional buoyancy can be gained. Any further
inclination, (heel) past deck edge immersion, causes the line of force through the center
of gravity to move closer to the line of force through the center of buoyancy creating a
decrease in righting arm. After deck edge immersion, seawater may be downflooded
into chain lockers, vents, hatches, and doors causing a further reduction in righting arm
due to a lateral shift in the center of gravity.
There are limits as to how much inclination a vessel can survive. The most common
limitation is the angle where compartments begin to flood (Figure 3.37). This angle is
the downflood inclination (downflooding through portholes, etc. may occur before deck
edge immersion). On an open boat, the downflood inclination is where the deck edge
goes under water. On MODUs, downflooding generally occurs through vent lines,
hawse pipes, or weathertight doors. In all cases, stability criteria focus on preventing
downflooding.
3 - 35
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
Our vessel needs to be stable in every operating condition. The International Maritime
Organization (IMO) publishes rules that detail required stability criteria for MODUs. The
IMO MODU Code addresses three types of criteria for the vessel:
Intact Stability -- Normal Operating Condition; limiting design wind speed is 70 knots.
Intact Stability -- Severe Storm (or Survival) Condition; limiting design wind speed is 100
knots.
Damage Stability limiting design wind speed is 50 knots.
These rules (or criteria) have been developed over time, taking into account research in
stability and lessons learned from stability-related accidents.
Often, individual nations (like Norway and the United States) will have their own stability
criteria, but they are generally similar to or based on the IMO Code.
It is important to understand that the criteria are not arbitrary restrictions. Their purpose
is to ensure that MODUs and other vessels are designed and operated safely. Failure to
satisfactorily meet the loading condition limits in the Trim and Stability book can lead to
capsize, loss of a vessel and loss of life.
3 - 36
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
8000
7000
6000
5000
Righting Moment
4000
g M om ent B
3000 A W in d H eelin
Downflood
2000
1000
0
0 5 10 15 20 25 30 35 40 45 50
Inclination (degrees)
Figure 3.38 - Righting Moment Curve with Wind Heeling Curve and
Downflooding Angle
We gauge the amount of stability by comparing the heeling moment curve against the
righting moment curve. At zero inclination, the wind heeling moment is greater than the
righting moment. The two curves cross at point A. This point is the static inclination
where the wind moment and righting moment are in equilibrium. The vessel would have
this amount of inclination in a steady wind. At some greater inclination, point B, the
righting moment curve crosses the wind-heeling curve a second time. This is called the
second intercept. If the inclination exceeds this angle, the righting moment becomes
less than the heeling moment and the wind will capsize the vessel.
Stability criteria considers the righting moment curve and the heeling moment curve from
the upright condition with zero degrees inclination to the downflooding inclination or the
second intercept inclination, whichever is less.
3 - 37
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
The area under the righting moment curve between two angles of inclination represents
the energy required to right the rig. Similarly, the area under the inclining moment curve
between two angles of inclination represents the energy provided by the wind to incline
the rig. In Figure 3.39, areas 1 and 2 correspond to the energy associated with the wind
overturning the vessel up to the downflood angle and areas 2 and 3 represent the
required energy to incline the vessel to this same angle. In all cases, we want areas 2
plus 3 to be greater than 1 plus 2. In other words, that the energy required to list the rig
to the downflooding angle is more than the energy provided by the wind.
8000
7000
6000
5000 3
Righting Moment
4000
3000
2000
1 2
1000
0
0 5 10 15 20 25 30 35 40 45 50
Inclination (degrees)
Figure 3.39 - Righting Moment and Wind Heeling Moment
Illustrating Areas Considered in Stability Criteria
3 - 38
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
The IMO intact stability criteria for MODUs require the righting energy to exceed the
overturning energy by a factor of 1.3 for semisubmersibles (area 2+3 >= 1.3 * {area
1+2}) or 1.4 for ships and barges (2+3 >= 1.4 * {1+2}). The factors of 1.3 or 1.4 provide
some margin for other forces such as waves and currents that act on the vessel and for
uncertainty in weight surveys performed on the rig. Semisubmersibles are not as
susceptible as ships to large roll angles, and thus have a lower factor (1.3 versus 1.4).
In the Normal Operating Condition, the wind heel curve is based on a 70-knot wind
speed, and for the Severe Storm (or Survival) Condition, a 100-knot wind speed must be
used. Since the wind force is proportional to the square of the wind velocity, the
overturning moments in the Severe Storm Condition are approximately double the
moments of the Normal Operating Condition. For the Severe Storm Condition, the
MODU may be deballasted, but removal or relocation of solid consumables or other
variable load is not allowed. Deballasting increases the freeboard, which increases the
reserve buoyancy and the downflooding angle, and usually also increases the righting
moment curve.
3 - 39
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
The righting moment curve may be adjusted to obtain the desired area ratio (1.3 or 1.4)
by vertically moving the center of gravity of the rig. Lowering KG increases the height of
the GZ curve, increases the area under the righting moment curve, and for the same
windforce, increases the area ratio. Conversely, increasing KG reduces the area ratio.
The corrected KG which provides the required design area ratio (1.3 for
semisubmersibles and 1.4 for drillships) for intact stability and provides an area ratio of
1.0 for damaged conditions is known at the Maximum Allowable KG (also called KG
Max). Of all the restrictions the marine crew must comply with while operating the rig in
the floating mode, this is the most important. Maintaining KG below the maximum
allowable KG (Figure 3.40) ensures that the stability will be positive.
ALLOWABLE KG (ft)
3 - 40
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
Operating with the rig KG below the maximum allowable KG will allow the rig to
withstand 70-knot winds at operating draft and 100 knot winds at survival draft. In a
damaged condition, the rig will be able to withstand 50-knot winds.
T h e m a xim u m a llo w a b le K G is d isp la ye d in th e rig s o p e ra tio n a l m a n u a l a s a cu rve
similar to figure 3.40. Note that for any draft there is a maximum allowable KG
depending on the wind. For winds greater than 70 knots, the rig must be operated below
the 100-knot wind curve. With winds less than 70 knots, the rig may be operated safely
below the 70-knot curve.
Changing the KG to meet wind limitations from 70 to 100 knots can be difficult. Material
may need to be offloaded from the rig or moved lower in the rig. The BCO must perform
d a ily ch e cks o f th e rig s sta b ility to e n su re th e rig ca n su rvive h ig h e r w in d sp e e d a n d
deballasting to survival draft. Contingency plans should be in place to address deck-
loading moves to meet survival conditions or higher wind speeds if necessary.
3 - 41
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
The IMO Code also includes stability criteria and related requirements for cases in which
the vessel is damaged.
Progressive Flooding:
All piping and ventilation within the damage zone is assumed to be damaged.
Positive means of closing off the damaged compartment and any damaged piping or
ventilation ducts must be provided so that the flooding can be stopped from spreading
to other compartments.
3 - 42
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
On semisubmersibles and newer jackups, these damage criteria result in designs that
have damage control bulkheads. Typically, the damage control bulkheads parallel
the shell at a distance inboard somewhat more than 1.5 meters (but only in the waterline
region where IMO allows damage). This results in relatively small compartments
(usually voids or seawater ballast tanks) at the exposed sides of the columns or hull that
limit the flooding should they be damaged. Figure 3.41 shows the typical
compartmentation of a semisubmersible column in the draft range subject to damage.
Drillships normally have adequate compartmentation and reserve stability to withstand
damage without needing damage control bulkheads or double-sides.
Column
Interior
Sea Water Ballast
Tanks
3 - 43
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
The IMO Code prescribes that the vessel must withstand the heel from a wind speed of
50 knots from any direction after damage has occurred. The final waterline must be
below any opening that could result in downflooding. For semisubmersibles, the
following additional requirements apply:
The angle of inclination after damage, and with wind, must be less than 17
All openings within 4 meters above the final waterline are required to be weathertight
The range of positive righting moment must be at least 7 (to the 2nd intercept or the
downflood point)
At some angle within the range of positive righting moment, the righting moment must
reach a value of twice the wind heeling moment.
Some nationalities prescribe an area requirement in the damage condition, similar to the
IMO intact criteria shown in the Figure 3.42. Typically, the area requirement is 1.0.
< 17 > 7
RM
WH
Downflood
At some angle in the
range of positive stability, Angle of
RM >= 2 x WH Inclination
Figure 3.42 - Righting Moment after Damage -- IMO Rules for Semisubmersibles
3 - 44
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
The vessel must not sink or capsize if any single compartment is flooded due to the
extent of damage noted previously. For semisubmersibles, in addition to damage within
the damage zones, flooding may include any compartment adjacent to the sea or any
compartment containing a potential source of a sea water leak, such as a pump room.
For semisubmersibles, the following requirements also apply:
The angle of inclination after flooding must be less than 25
The range of positive righting moment must be at least 7 (Figure 3.43).
Angle of
Inclination
Figure 3.43 - Righting Moment after Compartment Flooding, IMO Rules for Semisubmersibles
3 - 45
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3 - 46
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3 - 47
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
Subsea Equipment
The weight and location of subsea equipment carried onboard is determined by survey.
This survey extends to the BOP, BOP hoses, slip joint, flex joint and other subsea
equipment.
Stores
Manifests should be maintained for the various stores on board the vessel. These
stores may include the following:
Drilling stores
Engine room stores
Electrical stores
Paint locker
Subsea stores
G e n e ra l sh ip s sto re s
Food and provisions
The manifests should state the present weight of parts or supplies carried in each
storeroom.
Other Deck Equipment
A general survey should be preformed to identify other weights carried on board.
Mooring Equipment
The weight of deployed chain, wire, anchors, pendant lines and anchor buoys is
accounted for in the stability calculation. Usually these weights are considered to be
part of the vessel light ship, and the mooring equipment deployed is entered as a
d e d u cte d w e ig h t. T a b le s p ro vid e d in th e ve sse ls o p e ra tio n s o r sta b ility m a n u a l a re u se d
to translate deployed lengths of chain and wire into weights and VCGs.
Mooring and Riser Tension
Although not an actual weight, mooring and riser tension may have a significant effect on
the vessel displacement. Mooring and riser tension is typically entered as a weight with
an assigned VCG.
Although the BCO is responsible for the weight survey, other rig personnel including
the toolpusher, chief engineer, chief steward, store clerks and even the ExxonMobil
drilling supervisor may be responsible for providing the necessary weight information
to the BCO.
Ideally, an active record should be maintained by the BCO of all parts, equipment, or
supplies coming aboard or leaving the vessel. This will facilitate the weight survey and
stability calculations and ensure that accurate vessel weight records are maintained.
3 - 48
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
The weight estimates performed for the stability calculation can be checked relatively
easily. The check is performed by comparing the calculated vessel displacement with
the actual displacement determined from the vessel drafts.
The major errors in the stability calculations are usually due to one of the following
reasons:
Incorrect Tank Reading
Errors in tank gauge readings are a common source of error. A small error in a liquid
level can lead to a large error in the corresponding liquid weight estimate. This is
particularly true for semisubmersibles, which carry a large percentage of their total
displacement in ballast water and other liquids. Gauges can be checked by comparing
gauge readings against manual tank sounding. If the difference in the two tank
measurements is significant, the gauge should be recalibrated.
Incomplete Weight Survey
An incomplete weight survey of drilling equipment, spare parts, third party equipment
and supplies will often reflect an error in the total weight estimate. Therefore the weight
survey should be as complete and thorough as practical and should use the most
accurate item weight data available.
A major source of error is in estimating the weight of loose equipment and stores
distributed around the vessel. An up-to-date manifest of parts for all compartments will
help maintain a valid weight estimate for the stability calculation.
Old Lightship Estimate
As discussed earlier, the original lightship weight and VCG will change throughout the
life of a drilling vessel. For example a new welding shack may be added on deck, an
Iron Roughneck may be added to the drill floor, or an old emergency generator may be
changed out with a different unit. All these lightship changes should be noted and
recorded in the vessel operations manual so that an up-to-date lightship weight and
VCG can be maintained. If these changes to lightship are not recorded, the true vessel
lightship weight cannot be determined. In such cases, a new inclining experiment may
need to be performed for the vessel in order to obtain valid lightship properties.
Not all marine personnel are diligent in performing a valid stability calculation. A practice
not uncommon on many drilling vessels is to adjust the numbers of the ballast and other
liquid weights on the stability form in order to obtain agreement between the calculated
and actual vessel drafts. Often, liquid tanks on some drilling vessels are never sounded
even though liquid levels in these tanks may be suspect from gauge readings.
Another common practice is to forestall the routine of a daily stability calculation and to
perform these calculations on a weekly or even monthly basis.
These practices are unsafe because the true stability condition of the vessel cannot be
determined from such shortcuts in a detailed daily calculation.
3 - 49
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
The following is a recommended check for the ExxonMobil Drilling Supervisor to help
ensure the safe operation of the rig:
Review the stability calculation
Do results appear complete and accurate?
Is the correct value of lightship and center of gravity entered?
Does the worksheet contain both the calculated displacement and the
displacement determined from rig draft?
Any unknown weights entries?
Any unknown weights placed at the main deck level?
Is a calculation made to evaluate rig stability if the BOP stack must be
tripped for repair or maintenance?
Is a survival draft calculation made each time a daily stability calculation
is performed?
Check all hydraulic watertight door for proper operations: seals free of paint
Verify that weekly tank soundings are conducted and results are compared
with sensor readings
Are watertight doors and hatches kept closed
Compare daily stability calculations from multiple weeks and different BCOs
to determine trends or input errors
An example daily stability report is provided in Appendix 1.
3 - 50
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
Damage to a floating vessel can occur as a result of collision with another vessel or
obstruction, or due to structural damage/failure. Although damage-flooding
countermeasures are the same for either type of damage, damage due to collision is the
most severe due to the possibility of rapid flooding.
Damage from collision has the capability of being the most severe type. A vessel
displacing several thousand tons moving at a speed of 10-12 knots can inflict a great deal
of damage to an exposed column.
Immediate Objectives
A. Reduce list and/or trim.
B. Return vessel to near original mean draft.
C. Reduce mean draft.
Countermeasures
A. Sound the general alarm. Summon damage control team.
B. Identify where the damage is located by using the inclinometer and the King
gauges. (Note: King gauges are not always available to void spaces, chain
lockers etc.)
C. De-ballast adjacent ballast tank. Activate emergency de-ballast system if
available. (De-ballast damaged tank first, only if immediately controllable, such
as may be the case with minor damage.
D. Counter-flood ballast tank on the diametrically opposite side of the vessel if
response from de-ballasting adjacent tank is not quick enough.
E. Plug the vent to damaged tank or void space.
F. Consider other options: Transferring drill-water, using other ballast pumps if
available, dumping drill-water from the day tank, dumping mud from the mud
pits and slacking anchor chains on damaged side.
3 - 51
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
REMARKS
1. The drill floor should be notified so as to make preparations to disconnect from the
LMRP.
2. Deballasting the damaged tank first should only be attempted if it is known that the
damage is minor.
3. When de-ballasting the adjacent ballast tank, use two (2) ballast pumps. This
action will correct the list/trim faster and perhaps make counter-flooding
unnecessary. In the case of severe damage, de-ballasting with two pumps may be
necessary to keep the list/trim from increasing.
4. Plugging the vent to the damaged tank will assist in reducing list and/or trim by
slowing and perhaps stopping the influx of seawater. When the damage area is
brought above the water line, by decreasing the draft, the plug should be removed
to keep from further damaging the tank.
5. Counter-flooding assists in reducing list/trim by creating a powerful lever of added
weight on the opposite side of the vessel. When counter-flooding, however, mean
draft and, therefore, reserve buoyancy is being reduced., For this reason, counter-
flooding should only be done when necessary, and only as long as necessary.
6. Slacking anchor chains on the damaged side is also an effective means to assist in
reducing list/trim. A fairly large amount of weight can be removed quickly. This may
also be an extremely important countermeasure on a vessel with forward column
damage and aft pump rooms with no emergency de-ballast system. Due to the
various vessel designs, this procedure may not be effective in some situations.
7. Transferring drill water is an additional countermeasure, which may also be initiated
on the ballast panel. This countermeasure provides a righting lever by removing
weight from near the damaged area, and transferring it to the opposite side of the
unit without increasing mean draft. Due to different vessel designs and location of
drill water tanks this countermeasure may not be an option in some cases.
3 - 52
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
One of the first actions to take in the case of unexpected inclination is to determine the
cause. The inclination could be the result of open valves, a structural problem in a tank
bulkhead, dumping of mud pits, repositioning of large weights, or possibly, external damage
to the hull. In case of damage, the immediate objective should be to reduce the inclination
and return the vessel to an appropriate draft. If the damage assessment indicates that the
damaged area may be elevated out of the water, then corrective actions should include de-
ballasting.
Unexpected list or trim often falls into one of the following three categories in which vessel
inclination is:
1. increasing rapidly
2. increasing slowly
3. not increasing
The possible causes for unexpected list or trim are:
1. Flooding due to external causes
a. hull damage
b. failure of hull penetration (valve or piping)
2. Flooding due to internal causes
a. broken or corroded piping
b. open valve
c. failed check valve
d. ruptured tank bulkhead
3. Transfer of liquids
a. discharged liquid mud
b. inadvertent (personnel error)
c. equalizing between tanks
d. consumed liquids (fuel and drill water)
4. Shift of non-liquid loads
a. broken mooring line
b. consumed bulk materials
c. repositioning of heavy weights
5. Load form errors
a. mathematics
b. measurements
c. weight estimate
d. center of gravity estimates
6. Heel or trim due to environmental forces
Constant list or trim usually results from a miscalculation in the load form and could result
from a mathematical error, or using the wrong weight or location.
3 - 53
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
It could also be due to false tank soundings. An obvious solution is to recheck the load
form.
Other causes of constant list or trim could be the inadvertent transfer of a small quantity of
liquid, a load shift, or environmental forces. A corrective action would be to assess the
situation and, if required, level the rig through the transfer of liquids.
If extensive flooding occurs while in transit, due to damage or some other reason, such that
flooding cannot be controlled, the choice of tank from which to pump from will be
limited. Consider using both ballast pumps to pump from the damaged tank in order to
slow the inflow.
All openings and vents on the main deck, such as hatches, ventilators, tank vents, and
companionways are provided with a means of watertight closure. All watertight openings,
when not in use, should be secured.
Damage control countermeasures in general, would be the same as for collision damage,
modified to suit the specific damage situation.
3 - 54
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3.6 GLOSSARY
SYMBOL TERM DEFINITION
Displacement Weight of the vessel.
WT Weight Cargo/load weight.
K Keel Reference for measuring weight VCG or KG.
)(
Amidship symbol Geometric longitudinal center of vessel.
3 - 55
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
KMT Height of the transverse Measured in feet above the keel. Located in
metacenter hydrostatic tables.
KML Height of the longitudinal Measured in feet above the keel. Located in
metacenter hydrostatic tables.
GMT Transverse metacentric Measure of initial transverse stability of a vessel.
height Determined by subtracting KGT from KMT.
3 - 56
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3.7 REFERENCES
1. Diamond Offsh o re : In tro d u ctio n to S ta b ility a n d B a lla st C o n tro l co u rse m a n u a l,
October 1998
2. E xxo n P ro d u ctio n R e se a rch C o m p a n y; M a rin e O p e ra tio n s fo r O ffsh o re D rillin g
Volume I, Stability and Loadout, February 1992
3. M o b il D rillin g ; F lo a tin g D rillin g S ch o o l m a n u a l, Stability and Ballast Control
3 - 57
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3.8 APPENDIX
-444 Line Add. Wt. VCG V. Mom. LCG L. Mom. TCG T. Mom.
DESCRIPTION Out Lt. Ft LT*Ft Ft LT*Ft Ft LT*Ft
#1 1 0.00 27 0 -120 0 93 0
#2 1 0.00 27 0 -105 0 93 0
#3 1 0.00 27 0 105 0 93 0
#4 1 0.00 27 0 120 0 93 0
#5 1 0.00 27 0 120 0 -93 0
#6 1 0.00 27 0 105 0 -93 0
#7 1 0.00 27 0 -105 0 -93 0
#8 1 0.00 27 0 -120 0 -93 0
3 - 58
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
4146 TOTAL Fuel & F. 887.4 6.70 5947 -5.99 -5318 -29.55 -26221 1586 8276
water
3 - 59
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
Mud pit #1 326 52.59 123.10 6473 -91.20 -4796 9.00 473
Mud pit #2 358 57.68 123.40 7117 -106.30 -6131 9.00 519
Mud pit #3 221 41.34 123.50 5106 -103.70 -4287 -5.60 -232
Mud pit #4 224 42.00 123.50 5187 -103.70 -4355 -14.80 -622
Mud pit #5 250 40.31 123.50 4979 -76.78 -3095 9.20 371
3 - 60
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
BUL K TANK S
1FT=100 Wt. VCG V. Mom. LCG L. Mom. TCG T. Mom.
Type Factor Ft.-In. LT Ft LT* Ft LT* Ft 7 LT* Ft
GEL #1 STBD FWD GEL 1.6675 910 47.23 67.81 3202 -116.75 -5514 88.00 4156
GEL #2 STBD FWD GEL 1.6675 4010 3.53 51.31 181 -109.25 -386 88.00 311
#3 STBD AFT CMT 1.00 3510 16.58 53.93 894 109.25 1811 88.00 1459
#4 STBD AFT CMT 1.00 1604 59.67 64.14 3828 116.75 6967 88.00 5251
#1 PT FWD BARITE 0.7407 4300 0.00 50.00 0 -116.75 0 -88.00 0
#2 PT FWD BARITE 0.7407 3009 39.66 56.55 2243 -109.25 -4333 -88.00 -3490
#3 PT AFT CMT 1.00 2106 47.50 61.26 2910 109.25 5190 -88.00 -4180
#4 PT AFT CMT 1.00 4300 0.00 50.00 0 116.75 0 -88.00 0
Surge Tk. port GEL 6.00 125.00 750 -78.00 -468 -13.00 -78
Surge Tk. stbd BARITE 4.00 124.00 496 -78.00 -312 -5.00 -20
3 - 61
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3 - 62
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3 - 63
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
3 - 64
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
MOONPOOL LOADS
Actual Vert L. Mom T. Mom
ITEM Weight VCG Moment LCG LT-ft TCG LT-ft
LT Ft LT*Ft Ft - Fwd Ft - Port
51.93 LMRP 51.93 LT. 51.93 127.00 6595 -25.00 -1298 0.00 0
123.00 0 22.00 0 0.00 0
Support frame "DO NOT REMOVE" 6.89 115.00 792 -18.00 -124 0.00 0
Misc tools 4 123.00 492 0.00 0 0.00 0
SSTV 4 123.00 492 0.00 0 0.00 0
Subsea equip 4 123.00 492 0.00 0 0.00 0
82.00 BOP LOWER 82.59 LT. 82.59 128.00 10572 -18.00 -1487 0.00 0
TOTALS 153.41 126.69 19435 -18.96 -2909 0.00 0
3 - 65
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
VESSEL STABILITY
TOTAL DECK LOADS 1934.24 120.92 233889 4.39 8491 -0.40 -779
Variable Deck Load = 2166.3 s.t. Deck load margin = 714 s.t.
1934.2 l.t. 638 l.t.
VESSEL SUMMARY
Actual Vert Long Mom Tran Mom F.S. F.S.
-874 10 0 0
DAMAGE FLOODING
3 - 66
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4
Section
OBJECTIVES
Upon completion of this section, you will be able to:
List, describe and recognize potential marine related problems in offshore drilling
operations so they can be called to the attention of appropriate personnel and
corrected before they become serious problems.
List and describe the most common marine problems on offshore rigs today.
4-1
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
CONTENTS Page
4-3
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4.1 INTRODUCTION
The offshore drilling industry has experienced several major accidents involving high
loss of life. Following each accident, rig contractors and other industry groups took steps
to upgrade safety equipment, maintenance, and training of marine personnel. However,
since the last major accident in 1983, contractors have downsized/merged/ reorganized
to reduce costs and become more competitive. As a result, emphasis on marine safety
has suffered.
Today, there may be a perception throughout industry that compliance with
Classification Society Rules, Governmental Regulations, and Industry Guidelines )such
as the IMO MODU Code, Safety of Life at Sea (SOLAS) and API Recommended
Practices) adequately address marine safety systems and training so that Operators
only need to focus on the drilling equipment requirements for the operation. Although all
industry groups contribute to marine safety, no one group addresses everything.
Even though no major accidents involving high loss of life have occurred recently,
accidents resulting in loss of life still occur - accidents that are primarily due to lack of
equipment maintenance and/or lack of personnel training. Therefore, the risk of a major
accident remains if the right chain of events occurs. This risk can be reduced by
proactive efforts by Operator personnel.
Marine awareness starts with an understanding of the marine safety systems on
an offshore drilling rig. This section of the Floating Drilling School highlights key
requirements in the following critical areas:
Stability.
Ballast Control.
Abandonment/Survival Systems.
Fire Fighting System.
Emergency Power System.
Structural Integrity.
Personnel Qualification/Experience.
Emergency Response Training.
At the end of this section, you should be able to recognize potential problems that
exist on your rig so that they can be called to the attention of the appropriate contractor
and operator personnel before a potential problem becomes a real and serious
problem.
E xxo n M o b ils p rim a ry m a rin e sa fe ty sta n d a rd s a re co n ta in e d in th e Upstream Design
Guidance Manual Mobile Offshore Unit Marine Safety.
4-4
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4.2 STABILITY
S ta b ility is th e N a va l A rch ite cts w a y o f d e scrib in g th e a b ility of a rig to resist capsizing or
o ve rtu rn in g . In ta ct sta b ility re fe rs to th e rig s a b ility to re m a in u p rig h t w h e n th e re is n o
damage or flooding while damage stability refers to the stability of the rig after flooding in
one or more compartments has occurred. Loss of stability is one of the most serious
consequences that can happen to a vessel.
Stability theory is covered in another section of the Floating Drilling Manual. This section
addresses the practical application of stability theory in offshore drilling operations.
ACCURATE INPUT
Stability calculation results are only as accurate as the input.
Marine safety surveys have shown that errors often creep into the calculations -
sometimes intentionally and sometimes unintentionally. When this happens, the
results are meaningless and everyone on board is placed at risk.
Potential sources of errors found in stability calculation worksheets include:
SENSOR ERRORS
The ballast, fuel, potable water, drill water, and mud pit weights used in the stability
calculation are generally based on sensor input. The sensors measure the liquid level in
each tank, and charts in the Operating Manual are used to correlate the liquid level with
the weight of the liquid in each tank. If these sensors are not reading correctly, errors are
introduced into the calculations. The liquid weights on most rigs represent approximately
35-40% of the total rig displacement (rig weight). Therefore, if these sensors were reading
high by 1%, this would correspond to approximately 100-200 MT.
4-5
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
All rigs have sounding tubes that permit the liquid level in each tank to be manually
checked in order to verify the accuracy of the sensor input. The tank sounding
readings should be checked against the sensor readings weekly. On many rigs, the
sounding tubes are clogged (corroded) and tank soundings are not regularly conducted.
Operating in this mode introduces uncertainty in fluid levels, in weights, and hence
stability.
ASK: Ask the marine personnel how often they sound the tanks.
Results of rig surveys have shown that tank sensors can be in error by up to 0.5 M. In
most rigs, this would correspond to an error of approximately 5% of the total weight in the
tank. Occasionally, sensors short-out and indicate that a tank is pressed up (completely
full) when the tank is either empty or partially full.
Draft sensors should also be periodically checked against visual observations. Draft marks
are painted on each column for this purpose. Visual readings should correspond to sensor
readings within +/- 0.2 M.
4-6
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
Another error made by the BCOs was in accounting for weight of the mooring lines
deployed on location. The BCOs knew that the weight of the chain mooring lines was
included in lightship so they subtracted out the weight of the mooring lines deployed on
location (Note: there was a 30 MT difference in the calculation for weight of chain
outboard; this difference should have been resolved). This particular rig was designed and
equipped for operations in 1500-ft of water. When operations were extended into 1715-ft
of water, additional chain was added to each mooring line to permit operations to be
conducted in deeper water. The BCOs incorrectly deducted the entire mooring line weight
instead of only the mooring line weight included in lightship. This introduced a 250 MT
error.
4-7
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
On Day 40, the BCO made a 333 MT entry for Dummy Ballast (mystery name), which did
not appear on the other two worksheets. On Day 41, the BCO corrected this error and
entered 295 MT of extra chain that did not appear on the other two worksheets.
The results in this example were not being interpreted properly they were being
manipulated to provide a desired answer. When stability calculation results show that
the rig is trimmed/heeled and the inclinometers indicate that the rig is on an even keel, the
BCO should identify the problem and correct it instead of altering input.
ASK:
Ask the BCO if he has any guidelines on how much KG margin should exist.
The results should always indicate a KG margin of at least 3-ft. If you find yourself on a rig
where the KG margin is low (less than 3-ft), you are "at risk." Historically, these are the
same rigs that routinely keep watertight doors and hatches open so that they do not
interfere with normal operations. If the watertight doors/hatches are left open, uncontrolled
flooding can occur during storms, which leads to loss of stability and possibly loss of
the rig.
4-8
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
return the rig to an even keel and safe draft after flooding.
4-9
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
Ballast Pumps
The ballast system normally includes two independent pumps in each pontoon to permit
continuous operation of the system if one of the pumps is out of service for routine
maintenance or pump replacement. Newer rigs locate these pumps in separate
compartments so that if one pump room floods, both ballast pumps in that pontoon are not
lost.
Each ballast pump should be capable of taking suction on every ballast tank in the
pontoon. In addition, ballast pumps are typically selected to permit suction to be taken on
every tank with the rig inclined up to about 10 degrees (each rig will have slightly different
limits).
ASK: Ask the BCOs if they know the limiting angle for proper operation of the
ballast pumps. See if they need to go to equipment manuals to answer
your question.
Ballast Control Operators should be aware of the ballast system capabilities and
limitations so that timely and correct action can be taken during an emergency. Otherwise,
all personnel on board are "at risk."
There are no current industry standards for ballast pumps with the exception that the
ballast system should be capable of deballasting the rig from drilling draft to survival draft
in less than three hours. (The objective is to be able to secure operations and
deballast to survival draft in advance of a storm). Consequently, pumps are primarily
selected for suction.
ASK: Ask the BCOs if they know the length of time required to deballast from
drilling to survival draft.
If ballast piping suffers from scaling and/or pump impellers are excessively worn, the
three-hour objective may not be met.
Control Valves
The ballast system includes both manual and remotely operated valves. Manual valves
are generally installed to isolate various sections of the system during routine
maintenance, and remotely operated valves are installed for normal operations.
4 - 10
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
In the event of power failure, the ballast system must be secured to prevent
uncontrolled flooding. Some remotely operated valves are designed to fail in the closed
position while others are designed to fail in the current position. The valves may or may
not be designed to change position upon the reactivation of power. The mode of failure
depends upon the valve design and the control system arrangement:
Some valves are opened and closed electrically (worm or screw drive). Upon loss
of electrical power, these valves fail in the position at the time of failure. When
power is restored, the valve resumes its position or operation at the time of failure
(open, closed, or shifting position).
Other valves are fitted with air or hydraulic actuators. An electrical signal from the
control panel activates a solenoid, which opens a valve in the air or hydraulic
pressure line leading from an accumulator to the ballast valve. When pressure (air
or hydraulic) is applied to the ballast valve, the valve opens. When the electrical
signal to the solenoid valve is turned off, the solenoid in the air/hydraulic pressure
line is closed. Some control systems are designed so that pressure is
simultaneously bled off the ballast valve when the solenoid in the control pressure
line is closed. Other designs employ a shuttle valve so that an electrical signal is
required to shift the shuttle valve to bleed pressure off the ballast valve. In either
event, when pressure is bled off, a spring forces the ballast valve to shift to the
closed position.
If all remotely controlled valves fail in the closed position, the ballast system is
secure. If all remotely controlled valves fail in the current position, any tank open to the
sea at the time of power failure will flood unless rig personnel go to the pump room and
manually secure the valve.
ASK: Ask the BCOs if all ballast valves fail in the closed position.
If the valves are not designed to fail in the closed position, the Barge Engineer and Ballast
Control Operator must have contingency plans in place so that rig personnel go
immediately to the pump room and manually close all valves to each ballast tank. Ballast
valves should all be labeled to indicate the direction to close the valve (CW or CCW). Most
rigs are equipped with both CW and CCW close valves.
4 - 11
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
A manual and a remotely operated valve are located on the inlet (upstream) side of each
ballast pump. The valves shown on the discharge side (downstream) of the pumps are
manually operated. The discharge valve on pump #2 is shown to be normally open. The
discharge valve on pump #1 is shown to be normally closed. If the primary pump #2 fails,
the discharge valve on pump #1 must be manually opened.
ASK: Ask the BCOs if the ballast pumps have both a manual and a remotely
operated valve upstream and downstream of the pump.
Some rigs have both manual and remotely operated valves on the discharge side of the
ballast pump instead of just a manually operated valve as shown in Figure 4.1.
In order to pump ballast into a tank, remotely operated valves a, b, c and d must be open.
Valves e and f must be closed.
For deballasting operations, remotely operated valves d, f, b, and e should be open.
Valves a and c should be closed.
Upon loss of main power, valves a, b, c, d, e and f should be closed to prevent
uncontrolled flooding or cross flow between tanks.
The system is normally arranged so that only one tank in each pontoon can be handled
at a time.
4 - 12
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4 - 13
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4.3.6 APPENDIX I
Accident Report - Flooding of Starboard Pump Room
June 30, 1992
Summary:
June 6 Salt-water pump in starboard pump room failed.
June 10 Pump removed for inspection and repair.
Electrical and mechanical isolation permits issued.
Manual upstream valve closed.
Remote upstream valve in closed position; not manually closed (locked
out).
Parts placed on order.
June 30 Starboard pump room floods (completely fills with water).
Bilge alarms ignored.
Electrical equipment problems on starboard side (fans in
accommodation space start/shut down; 440v circuit breaker trips and
will not reset; elevator in starboard center column will not operate).
Flooded pump room confirmed 40 minutes after initial bilge alarms.
Pump room completely flooded and starboard fire pump, sprinkler
pump, fuel oil pump, cooling water pump, and drill water pump under
water.
Cause
The manual valve upstream of the salt-water pump was in fact not closed
on June 10 as thought. Some of the valves in the pump room were left-
hand close and some were right-hand close. The valve in question was a
left-hand close and was properly marked, but it was apparently opened
instead of being closed because left-hand close valves were unusual on
this rig. The pump room then flooded when someone inadvertently opened
the remotely controlled valve upstream of the pump.
Contributing Causes
The Marine Department did not sign off on the isolation permits.
A sign was not posted on the panel in the ballast control room
indicating that the pump was out of service.
Several BCOs were not informed that the pump was out of order.
Several maintenance personnel were not aware of the pump isolation.
Remote valve was not closed (locked out)
4 - 14
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4 - 15
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
Potential Problems
The rig was designed with one pump room and two thruster pump rooms in
each pontoon. The main pump room in each pontoon houses the fire, fuel
oil, sprinkler, cooling water, drill water, and salt-water pumps. The ballast
pumps, which also serve as emergency bilge pumps, are located in the
thruster pump rooms. In this particular situation, the rig maintained the
capability to deballast to survival draft, if necessary. In addition, the fire,
fuel, drill water pumps in the port pontoon provided the necessary capability
to continue operations without jeopardizing safety.
Many rigs are designed with only one pump room in each pontoon. If the
pump room floods on these rigs, all pumps on that side of the rig are lost.
To compensate, some rigs have cross piping connecting the two pontoons.
Otherwise, in the event of a storm, the rig would not have any capability to
deballast to survival draft.
4 - 16
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4.4 ABANDONMENT/SURVIVAL
Semisubmersibles are equipped with lifeboats or survival craft, life rafts, and life jackets for
use in an emergency. In some instances, exposure suits are also provided.
In most areas of the world, rig evacuation by helicopter is the preferred means for rig
abandonment. If abandonment by helicopter is not possible, rig evacuation by
lifeboat/survival craft offers a greater chance of survival than using life rafts or jumping
directly into the water, provided crews and rig personnel are properly trained and
equipment is maintained.
Marine safety surveys have found that lifeboat/survival craft maintenance and personnel
training are weak on some rigs. Surveys also have found that many rig personnel are
afraid to climb into a lifeboat/survival craft during a drill because they are concerned that
the lifeboat/survival craft may be prematurely released and fall into the water resulting in
in ju ry o r d e a th . In e ffe ct, e ve ryo n e o n b o a rd is p la ce d at-risk during rig abandonment
unless the contractor has handled his maintenance and personnel training properly.
In addition, many personnel are not aware of the serious consequences of entering cold
water without wearing an exposure (survival) suit. They may not have received necessary
training on how to quickly put on an exposure suit and properly seal all openings. They are
"at risk" if they do not properly don a suit and seal all openings before leaving the rig. An
exposure suit that leaks is not much better than no suit at all.
An Escape, Evacuation, and Rescue (EER) analysis that describes a safe and reliable
means to evacuate all personnel
Exposure suits for all personnel on board, if applicable typically if the water
temperature is below 60o to 68o F.
4 - 17
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
LIFEBOAT/CAPSULE
Lifeboats/survival craft should be designed and equipped as follows:
1. Totally Enclosed
2. Self-Righting
3. Motor-Propelled
4. On-load/Off-load Release Hooks
T h e se life b o a ts/su rviva l cra ft a re o fte n re fe rre d to a s to ta lly e n closed motor propelled
survival craft (TEMPSC).
The release hooks should be designed to release regardless of whether the falls
are under load. Commonly, the hooks are described as on-load release hooks with
off-load backup release capability or off-load release hooks with on-load backup
release capability.
Off-load Release Hooks - Off-load release hooks are designed to disengage after
the lifeboat/survival craft has been lowered and is floating on the water with no
load on the falls.
On-load Release Hooks - On-load release hooks are designed to release under
any load up to 1.1 times the fully loaded weight of the lifeboat on the falls. These
hooks will not release if the lifeboat/survival craft is floating on the water and
there is no load on the falls.
Note: An industry study conducted several years ago concluded that the design of
release hooks, particularly on-load release hooks, requires that certain
procedures be followed to prevent accidental or premature release. In a
number of accidents, the safety features failed because the release gear
malfunctioned or crew members failed to understand the system and, as a
consequence, did not properly reset the release hooks.
Lifeboats/survival craft should be launched quarterly.
5. Seating Capacity
Lifeboat/survival craft seating capacity requirements shall be established by an EER
analysis. It should provide at least one seat for everyone on board under the
emergency scenarios requiring evacuation. Consideration shall be given to injured
personnel, loss of a TEMPSC, and use of survival suits, where required. Normally, this
requires seating for 200% of personnel onboard 100% on bow and stern (semi) and
100% on port and starboard (drillship).
Lifeboat/survival craft seating capacity varies with manufacturer and model.
Lifeboat/survival craft installed on semisubmersibles usually have seating for about 50-
65 averag e people wearing life jackets. Exposure suits are bulkier than life jackets
a n d m o st o ffsh o re d rillin g p e rso n n e l a re b ig g e r th a n a n a ve ra g e 1 5 0 -lb person, so
the maximum seating capacity may be less than the rated capacity.
4 - 18
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
6. Equipment
Lifeboats/survival craft should be equipped with the following:
permanently installed VHF marine radio connected to a battery charger
emergency lighting
radar transponder or EPIRB (Emergency Position Indicating Radar Beacon)
first-aid kit
fire extinguisher
potable water
sprinkler system
signaling equipment
compass
breathing air
running lights
cold start capability, if required
back-up starting system
off load release hooks with on-load backup
external strobe lights
food (may be waived if justified by the EER analysis)
Note: Lifeboat/Survival Craft Inspection. Regular inspection by factory-trained
personnel is necessary to help ensure that the lifeboats and associated release
hooks are properly maintained and that rig personnel are familiar with
lifeboat/survival craft and release hook operation. Each lifeboat manufacturer has a
routine maintenance program for their equipment, and a copy of the program
should be available on the rig. Rig personnel should understand Lifeboat/survival
craft maintenance procedures.
Manufacturers also periodically issue service bulletins or service alerts, which
notify customers of accidents and/or identify recommended modifications. A copy
of all service bulletins should be maintained on the rig. These bulletins are
g e n e ra lly se n t to th e co n tra cto rs h o m e o ffice , a n d th e h o m e o ffice is re sp o n sib le
for forwarding copies to each rig. In some instances, the manufacturer's service
bulletins were lost when rigs were sold or contractors merged. Consequently,
there are still lifeboat/survival craft within industry that have not been modified to
correct problems.
Note: The practice of hanging dual-fall lifeboats by temporary support pendants (for
maintenance) introduces a safety hazard. Consequently, the maintenance
pendants should be inspected by the senior marine operations supervisor prior to
release from the falls.
4 - 19
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
LIFE RAFTS
The EER analysis should establish the number of davit-mounted life rafts. Normally, a rig
should be equipped with a sufficient number of float-free life rafts to accommodate 100%
of the rig compliment. The rafts should be located away from the lifeboat/survival craft
launch areas so that they are accessible even when the lifeboats are not.
LIFEJACKETS
Lifejackets should be provided for 150% of the maximum number of people permitted on
board. All lifejackets should be equipped with a light.
A lifejacket should be stored near each bunk (100%) and another 50% should be stored at
locations near the moonpool, spider deck, and abandonment stations.
LIFE RINGS
Life rings should be located in areas around the upper deck and the moonpool area and
other areas where there is a potential for a man to fall overboard. At least one life ring
located near each normally manned space should be equipped with a light and self-
activating smoke generator. In addition, at least one life ring should have a retrieving line.
ESCAPE ROUTES
Two escape routes should be available from every normally manned space.
Routes from the quarters to lifeboats should be clearly marked and free of obstructions.
4 - 20
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
EXPOSURE SUITS
The rig should be equipped with exposure suits for everyone onboard when operations are
conducted in areas where the daily mean water temperature is anticipated to be below
20oC (68oF) over 5% of the time during a month and rescue time exceeds survival time
without a suit.
Cold water can kill in a relatively short period of time. During the first few minutes after
entering cold water there is a high probability of death by drowning as a result of
respiratory and circulation shock responses. If the individual survives the initial shock of
entering the water, the body core temperature will gradually drop until it reaches 91o F
when voluntary movement ceases and drowning and/or heart failure occurs (hypothermia).
A person becomes unable to help themselves (i.e. grab a line long before this occurs).
The length of time between entering the water and losing all voluntary movement
(estimated survival time) is related to the weather, physical characteristics of the
individual, and the type of protective clothing. For example, the average survival time for
an individual in 50o F water wearing work clothing (no protective clothing) is
approximately 2 hours as shown in Figure. 4.2. The dotted lines above and below the
solid line indicate the range in survival times for different individuals. In 32oF water, the
average survival time is approximately one hour.
4 - 21
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
Survival time can be increased by use of protective clothing as shown in Figure 4.3.
Uninsulated helicopter suits increase the survival time to about 8 hours in 50o F
water. Insulated helicopter suits increase survival time to more than 14 hrs and
exposure suits provide almost unlimited survival time in 50o F water.
Uninsulated
Helicopter Suit
w/Heavy Clothing
Figure 4.3 Estimated In-Water Survival Time for Various Types of Protection
Most suits are one-piece with integral hood, boots and gloves. The suits have a fast and
efficient entry via a waterproof airtight front zipper. Air expulsion valves ensure instant
venting of excessive trapped suit air in water, without water ingress. Buoyancy and
thermal insulation is provided by internal-buoyant cell foam. The suits are designed to limit
the average drop in body temperature to 2o or less with water conditions between 32 and
37o F (0 and 3 deg C) after a 6 hr period in the water. Theoretically, body temperature
should not drop below 92o F in 18 hours if the individual is wearing a properly sealed
exposure suit.
Number: Suits should be provided for 150% of the maximum number of personnel
permitted on board.
Location: Stored in the quarters (one near each bunk) and at lifeboat/survival craft
stations
4 - 22
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
Personnel are not familiar with operation of the lifeboat release mechanism(s)
Personnel are not aware of the hazards associated with entering the sea
4 - 23
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4 - 24
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
Remotely operated valves in the fire system should fail in the open position.
Only services which are directly associated with fire fighting or washdown should be
connected to the fire main.
4 - 25
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
FIRE PUMPS
The rig should be equipped with at least two independently driven fire pumps installed in
separate locations so that an accident in one area will not disable all of the pumps. One of
the pumps should be dedicated to fire fighting service exclusively. The other pump(s) may
be used for sanitary, ballast, bilge or general service as long as they are manifolded into
the fire main.
Each pump should be capable of maintaining 50-psi pressure at the nozzle tip with any
two hydrants open and 19mm nozzles set on straight stream. In addition, where a foam
system is provided for protection of the helicopter deck, the pump should be capable of
maintaining 100 psi at the foam installation.
The fire pumps should automatically start upon loss of pressure in the fire main.
ASK: Ask fire team leaders if the fire pumps are wired for automatic operation.
If the pumps are not wired for automatic operation, remote start-up switches should be
located at strategic points around the rig. The pumps should also be set for local
operation.
Any pump connected to a fire main should be provided with a manually operated valve to
isolate the pump from the fire main for repairs and maintenance.
At least one pump, if electrically operated, should be connected directly to the
emergency switchboard.
FIRE MAIN
The fire main should be routed clear of hazardous areas. It should also contain isolation
valves so that any section of the main can be closed off and permit the remainder of the
main to be held at rated pressure as shown in Figure 4.5.
4 - 26
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
ASK: Ask the fire team leaders to show you the isolation valves.
FIRE STATIONS
Fire stations should be located at strategic places around the rig. Each station should
consist of:
a hydrant
HYDRANTS
The number and position of hydrants should be sufficient to permit at least two jets of
water from hoses attached to separate hydrants to be brought to bear in any part of the rig
where a fire may occur.
FIRE HOSES
Standard fire hoses are 50 to 60 ft. in length. Most hoses are 2 in. diameter, however
some stations are outfitted with 1 in. diameter hoses. Permanently connected hose reels
found in accommodation spaces usually have smaller diameter non-collapsible hoses.
NOZZLES
Standard nozzle sizes are 12 mm, 16 mm, and 19 mm.
Note: The 16 and 19 mm nozzles are generally used at outdoor fire stations, and the
12 mm nozzle is generally used in accommodation and service spaces.
FIREMAN'S EQUIPMENT
Every rig should have at least 4 sets of fireman's equipment. Each set should consist of
the following:
a protective outfit, including gloves, boots, a face mask or hood and a helmet
a self-contained breathing apparatus with at least 3 spare breathing air bottles
a portable battery-operated safety lamp capable of functioning efficiently for a
period of not less than 3 hrs
a fireman's axe
a safety harness and lifeline.
The equipment should be stored in pairs (2 sets/pair) at different locations.
4 - 27
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
FIRE EXTINGUISHERS
Sufficient fire extinguishers should be available so that at least one extinguisher is readily
accessible from any part of the rig. In addition, one portable fire extinguisher should be
located adjacent to every exit in the accommodation space.
Spaces equipped with fixed fire extinguishing systems such as machinery spaces should
also have fire extinguishers positioned at several locations in the space.
Portable extinguishers should be inspected quarterly. Checks should confirm the
proper charge - type (A, B, C) matched to potential class of fire; hoses and extinguishers
should appear to be in good condition; and the extinguishers should contain a current
inspection stamp with date.
HELIDECK
Fire fighting equipment for the helideck should consist of the following:
if the rig is equipped with refueling capability, a foam application system consisting
of monitors or foam-making branch pipes capable of delivering foam solution to all
parts of the helicopter deck.
4 - 28
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
FIRE DETECTION
Every rig should have a fire detection system.
Machinery Spaces. Two different types of detectors should be provided in machinery
spaces - Thermal, smoke, and fragile bulb type detectors are commonly used.
Smoke (flame) - Ultra violet flame detectors are generally used in open areas.
Fragile bulb - These sensors are generally set at approximately 30oC above the
normal ambient temperature. Most regulations also specify that the sensors need
not be set at temperatures less than 57oC.
Accommodation Spaces. A smoke detector should be installed in every personnel-
sleeping compartment.
4 - 30
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4.6.2 LOCATION
The emergency source of power and the emergency switchboard should be located:
4 - 31
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
Navigation/helideck lights .
Emergency lighting:
at every embarkation station on deck and over the side.
in all service and accommodation alleyways, stairways and exits.
in the machinery spaces and main generating stations.
in all control stations and in all machinery control rooms.
in the tool pusher's office and on the drill floor (all spaces where drilling
activities can be controlled.
at the stowage position(s) for firemen's outfits.
at the sprinkler pump, if any, at the fire pump, at the emergency bilge
pump, if any, and at their starting positions.
on the helicopter landing deck.
Ballast pump.
4 - 32
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
On semisubmersibles, each ballast pump should be capable of being supplied with power
from the emergency switchboard (only one of the pumps should be considered to be in
operation at any one time). The preferred arrangement is to have one of the pumps in
each hull connected directly to the main switchboard and the other pump connected
directly to the emergency switchboard. When sizing the emergency source of power, the
largest ballast pump should be assumed to be operating simultaneously with the other
critical loads noted above.
Personnel transfer cranes and elevators giving access to areas not accessible by
stairways.
Flooding alarms.
4 - 33
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
Note: The feeder should be protected against overload and short circuit at the main
switchboard. When the system is arranged for feedback operation, the feeder
should also be protected against short circuit at the emergency switchboard.
If the voltage level on the emergency switchboard falls to a pre-set level (normally 60% to
85% of normal), the bus-tie circuit breaker automatically opens and interrupts the supply of
electrical power from the main switchboard. When this occurs, power to the emergency
switchboard is then supplied by the emergency generator or accumulator battery source.
A short time delay is usually built into the system to delay opening of the bus-tie circuit
breaker after loss of main power in order to eliminate start-up of the emergency power
system when the main power system immediately recovers from a transient loss of power.
When main power is restored, the bus-tie circuit breaker is closed (either manually or
automatically), thereby restoring power from the main switchboard to the emergency
switchboard. The circuit breaker to the emergency power source is simultaneously opened
to break that circuit.
The arrangement shown in Figure 4.6 is typical of many rigs in operation today, but it
does not have the ballast pumps connected directly to the emergency switchboard. In
order to operate the ballast pump, the bus-tie circuit breaker must be closed and power
"back-fed" to the main switchboard. This approach is impractical if main power is lost
because of a fire in the main engine room.
The schematic in Figure 4.7 represents the preferred arrangement, which also complies
with current industry standards.
4 - 34
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
As shown, one ballast pump in each pontoon is connected directly to the emergency
switchboard in addition to the fire pump and other emergency equipment. This
arrangement permits all equipment to be operated during normal operations because
the bus-tie circuit breaker is closed and power from the main switchboard is delivered
to the emergency switchboard. When main power is lost, all critical equipment is
already connected to the emergency switchboard, and there is no reliance on the
main switchboard.
4 - 35
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
Design integrity
Fatigue life
DESIGN REVIEW
Prior to construction, Classification Society personnel review drawings and calculations
provided by the owner to confirm that the design is in accordance with the "Rules." Design
approval includes a review of stress analyses, fatigue analyses, and may include an
evaluation of member redundancy. In some instances, the Classification Society may
conduct independent analyses to evaluate new designs.
Stress Analysis: The stress analysis includes an evaluation of the stresses in individual
members and the stress levels at connections.
Fatigue Analysis: Offshore drilling rigs are generally designed for a minimum 20-year
fatigue life under an assumed set of environmental conditions. Since most drilling rigs
operate worldwide in a variety of environments, these fatigue analyses are useful in
identifying highly stressed areas ("hot spots"), but they are not very good at reliably
predicting actual rig service life.
Member Redundancy: Some of the newer rigs were designed with member
redundancy, which means that one of the lower structural members (horizontal or
diagonal) could fail and the remaining members would not be over stressed. This design
feature provides additional confidence that the rig should not experience a structural
problem that would lead to rig collapse and possibly high loss of life.
4 - 36
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
Computer analysis techniques used by both rig designers and Classification Society
personnel in their design reviews have improved significantly since the 1970s when the
first semisubmersibles entered the offshore fleet. As a result, the newer fourth and fifth
generation rigs should be better designed and should have fewer structural problems.
On the other hand, these same tools allow designers to design closer to the allowable
stress limits, thus perhaps removing conservatism that used to exist.
After a rig has been placed in service, an in-service inspection of critical joints
provides the best information about the condition of the rig itself and whether the
rig is fit for continued service. These inspections are particularly significant for
older rigs where cracking due to fatigue has occurred.
IN-SERVICE INSPECTION
Classification Societies require an inspection of selected critical connections every five
years. These particular inspections are called "Special Periodical Surveys (SPS). The
inspection program typically includes non-destructive testing of approximately 20-25% of
the major structural connections such as the column to pontoon, horizontal brace to
column, diagonal brace to column, K-joint, column to upper deck, diagonal to upper deck,
transverse girder and longitudinal girders. Loss of integrity in any of these joints could
cause adjacent members to be overstressed, which would ultimately lead to loss of the rig.
The inspection techniques vary from Society to Society and surveyor to surveyor. DnV
Rules specify magnetic particle inspection (MPI) or eddy current (EC) with limited use of
ultrasonics to inspect critical areas while ABS will accept visual inspection for most
connections.
These inspections also include a random sample of external attachments such as
hydrophone brackets, lifting padeyes and walkways. The remaining areas are inspected
visually. If significant defects are found, the Classification Society Surveyor will expand the
scope of the inspection.
DnVs program is much more structured and formalized than the ABS approach. Following
shipyard delivery, DnV issues an inspection plan which includes rig drawings showing
areas that are to be inspected, the inspection frequency, and the type of inspection
technique (visual, magnetic particle, x-ray, ultrasonic). ABSs approach is slightly different -
they ask the rig owner to submit a plan and then ABS will either approve or disapprove it.
Access to the lower structural members for inspection generally requires the rig be at
shallow draft in a protected area. Normally scaffolding must be erected on the pontoons to
permit access to the lower horizontal and diagonal connections to the columns. Access to
some of the upper connections also requires scaffolding. If MPI is used, the surface must
be repainted/recoated.
A typical structural inspection requires five to seven days, depending on weather and the
number of inspection crews.
The Classification Society surveyor is usually not present during the entire
inspection; instead he uses reports of third party inspectors hired by the rig owner to
determine suitability of the rig for continued operations.
4 - 37
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
When the inspection is completed and all repairs, if any, have been made, the
Classification Society surveyor will provide a temporary permit until a formal certificate is
issued approximately six months later by the Classification Society home office. A typical
example of the wording used in the formal certificate "...all areas were found or placed
in satisfactory condition" is shown in Appendix II. This certificate is intended to serve as
proof that the Classification Society surveyor witnessed the inspection, and he has
concluded that the rig is fit-for-purpose. This certificate is also needed by the rig owner
to maintain insurance. The Surveyor also issues a Special Periodic Survey report,
which contains the inspection program and results of the inspection. A copy of the
SPS report is required to be on the rig and another copy is provided to the
contractor for his office files.
REPORTING DAMAGE
If a collision occurs while the rig is in service, the Classification Society is to be informed
immediately. A surveyor will be sent to the rig to review the damage and make a
determination on whether temporary repairs will be adequate until the rig comes in for its
next SPS or whether the rig must come into the shipyard for immediate repairs.
REPAIRS
Any welding of structural members or any structural modifications to the rig must have
Classification Society approval. The repair and the welding procedures to be followed
should be approved by the Classification Society.
4 - 38
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
Figure 4.8 - Time required for a 1-mm surface crack to penetrate through a 25-mm
tubular member
Note: The curve in Figure 4.8 was based on DNV test results on a horizontal member to
column connection on a specific rig.
As an example, 5-6 M waves would produce a stress level of 5.6 ksi in the member. At this
stress level a 1-mm crack would work its way completely through the wall thickness in a
little more than 300 days. If the wave height was higher, the stress level would be greater
and the length of time to propagate through the member would be shorter. In the Northern
North Sea, waves exceeding 5-6 M occur between 5 - 40 days/year. Therefore, it is
possible to have a minor surface defect work its way completely through the member in
about 8 yrs if the defect was not detected and repaired.
4 - 39
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
The curve in Figure. 4.9 illustrates how rapidly the crack length increases after a
penetration occurs. As shown, the rate of propagation speeds up as the length of the crack
increases. Under the same 5-6-M waves, the crack length doubles every 20 days.
Note: The crack does not have to propagate all the way around the member before
failure occurs. As the crack propagates, the intact part of the member must carry
all of the load. Eventually, the load will exceed the strength of the remaining tubular
surface and the member will fail in tension.
The SPS surveys are intended to locate and repair such defects before they cause
structural failure.
4 - 40
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
Inspections rely too much on visual methods which miss significant defects.
ExxonMobil performs a structural assessment before mobilizing a rig. This assesses if the
S P S in sp e ctio n s m e e t E xxo n M o b ils e xp e cta tions. If not clear, a risk decision is made on
whether to perform an independent ExxonMobil inspection.
4 - 41
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4.7.5 APPENDIX II
American Bureau of Shipping
65 Broadway, New York, N.Y. 10006
Report No. AD2070 Aberdeen, U.K., 24th September 1985
Best Driller
THIS IS TO CERTIFY that the undersigned Surveyor to this Bureau, did, at the request of
the Owner's Representative attend the Column Stabilized Drilling Unit "Best Driller" of
London, U.K., on the 4th day of September, 1985 and subsequent dates as she lay afloat
on drilling location in the North Sea and at Invergordon, Scotland, in order to examine and
report upon Underwater Inspection in Lieu of Drydocking, Continuous Hull Survey and
Continuous Machinery Survey. For particulars see report as follows:
UNDERWATER INSPECTION IN LIEU OF DRYDOCKING
1. Selected areas of the Unit's underwater parts of the lower hulls were cleaned by
divers and the sea was sufficiently clear.
2. Exposed areas of the shell plating of the lower hulls and columns, above the
waterline, were examined and found or placed in satisfactory condition as noted
below:
(a) Shell plating and internals in way of column SC-2 were cropped and partly
renewed at this time. For details, refer to Report No. AD2076 dated 24th
September 1985.
(b) Shell plating and internals in way of columns CSC-1 and SC-1 were cropped
and partly renewed at this time. For details refer to Report No. AD2074 dated
24th September 1985.
3. The center hulls, below the waterline, including the welded butts, sea chest
strainers, external piping, kort nozzles and propellers were examined, as
recommended, by qualified divers using closed T.V. circuit with two-way
communication system and video-tape documentation supplemented by the diver's
report describing and attesting to the conditions found and considered in
satisfactory condition. The condition of the port kort nozzle, as reported in Report
No. AD1711 dated 17th May 1984, found not to have been aggravated and
it is recommended that the pittings in way of the port kort-nozzle be re-examined
at next drydocking survey.
4. The stern tube bearings were examined externally by the divers and no leakages
were noted. Due to configuration of the kort-nozzles, it was not possible for
clearances to be taken.
4 - 42
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
SEMINAR NOTE:
The bold emphasis in the text was added to illustrate the non-descriptive method
used by surveyors to state that the rig is in good condition.
This rig was 10 years old at the time of the inspection. The weld repairs indicated
above were due to either overstressing, poor weld repairs to correct earlier problems,
or poor welds at the time of shipyard delivery that had not been detected until this
inspection. In any case, these areas should be monitored.
4 - 43
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4.8 PERSONNEL
Personnel training and experience levels vary from contractor to contractor and from rig to
rig. At the present time, industry has not adopted any minimum marine requirements
fo r p e rso n n e l in ke y p o sitio n s su ch a s O ffsh o re In sta lla tio n M a nager (OIM), Barge
Engineer, Assistant Barge Engineer, and Ballast Control Operator. Some countries
(Norway, United States) have instituted formal requirements and now require licensing in
these key positions, however, there are still many areas of the world where personnel
performing these jobs have only received "on-the-job" training and little, if any, formal
training. Industry experience has shown that all personnel on board are "at risk" if
personnel assigned to these key positions are not adequately trained.
4 - 44
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
RESPONSIBILITIES
The Offshore Installation Manager (OIM) or Person in Charge is the senior person on
board and is responsible for:
The overall safety of the drilling rig.
The stability of the drilling rig.
The structural integrity of the drilling rig .
Training emergency crews (fire fighting, lifeboat crews, etc.).
EXPERIENCE
The Offshore Installation Manager (OIM) should have at least four years of employment
assigned to a MODU in a supervisory position (OIM, rig superintendent, toolpusher, driller,
barge engineer, or maintenance supervisor) and six months on board the specific MODU.
TRAINING
In order to properly carry out this responsibility, the OIM should have completed the
following training programs:
Advanced fire fighting.
Basic and advanced stability.
Ballast control (semisubmersibles only).
Survival at sea.
Basic first aid.
LICENSING
In order to be licensed, the rig OIM must successfully complete courses in the above
subjects, meet experience guidelines, and successfully pass an examination which
includes relevant questions on the following topics:
Watchkeeping.
Meteorology and Oceanography.
Stability.
Ballasting.
Damage Control.
Maneuvering and Handling.
Fire Prevention and Fire Fighting Appliances.
Lifesaving and Survival.
4 - 45
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
RESPONSIBILITIES
The Barge Engineer and Assistant Barge Engineer are typically responsible for:
The stability of the rig.
Ballasting operations.
Daily stability calculations.
Watertight integrity.
Inspection and maintenance of mooring and towing equipment.
Loading and placement of consumables such as casing, barite, cement, bentonite,
fuel and water.
Maintenance of emergency and other marine related equipment.
EXPERIENCE
T h e B a rg e E n g in e e r a n d th e A ssista n t B a rg e E n g in e e r sh o u ld h a ve a t le a st o n e ye a rs
experience on the specific semisubmersible as a barge engineer or ballast control
operator.
TRAINING
The Barge Engineer and Assistant. Barge Engineer should have completed the following
training programs:
Basic fire fighting.
Basic and advanced stability.
Ballast control (semisubmersibles only).
Survival at sea.
Marine Operations.
Basic First Aid.
4 - 46
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
LICENSING
In countries that license the barge engineer position, personnel must successfully
complete courses in the above subjects, meet experience guidelines, and successfully
pass an examination which includes relevant questions on the following topics:
Watchkeeping.
Meteorology and Oceanography.
Stability.
Ballasting.
Damage Control.
Maneuvering and Handling.
Fire Prevention and Fire Fighting Appliances.
Lifesaving and Survival.
4 - 47
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
RESPONSIBILITIES
The Ballast Control Room Operator (BCO) or watchstander is typically responsible for:
The stability of the rig.
The rig draft.
Maintaining the rig on an even keel.
The stability calculations (or assisting the Barge Engineer)..
The daily maintenance and operation of the control room and pump room.
EXPERIENCE
Semisubmersible ballast control operators should have at least six months experience in a
"trainee" position on a similar design semisubmersible constantly supervised by a qualified
BCO.
4 - 48
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
TRAINING
All BCOs should have completed the following training schools or programs:
Basic fire fighting.
Basic stability.
Ballast control.
Survival at sea.
Basic first aid.
LICENSING
Personnel licensed as a Ballast Control Operator must have successfully completed
courses in the above subjects, meet experience guidelines, and successfully pass an
examination that includes relevant questions on the following topics:
Meteorology and Oceanography.
Stability.
Ballasting.
Damage Control.
Fire Prevention and Fire Fighting Appliances.
Lifesaving and Survival..
4 - 49
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4.8.2.5 Resumes
The resumes of the OIM, Barge Engineer/Assistant Barge Engineer, and the BCOs should
be reviewed prior to awarding the contract, prior to initiation of operations if personnel
have changed, and during operations when new personnel are assigned to the rig. Most
resumes submitted to Operator personnel show the individual's name, current position,
date hired by the contractor and an abbreviated summary of the individual's oilfield
experience and training. Educational background is often not provided.
In order to obtain all of the data required to evaluate personnel in a timely manner, the
request for resumes should include a request for the following information:
Name.
Age.
Position.
Experience summary including dates, positions held, and employers.
Training summary including course name, school name, location, and dates
attended (self study courses should be indicated).
Education summary including college/university, location, dates attended,
degree awarded.
Many resumes do not include the location of the school or the duration of the
school, so it is difficult to assess whether the training was a one-day overview or a
more comprehensive five-day course.
4 - 50
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
Several typical examples for personnel in the key marine positions are described below:
Offshore Installation Manager. The resume shown in Table 4.2 describes an OIM on a
semisubmersible operating in the UK sector of the North Sea.
Name:
Position: OIM
Hired: 05/89
Experience School Dates of Training
OIM Survival Combined 04/20/90
Rig Alpha
03/90 - Present
OIM
Rig Beta
05/89 - 03/90
Harbor Pilot
Virgin Island Port
Authority
10/83-01/89
Chief Mate
Point Shipping Inc.
01/80 - 09/83
Table 4.2 - Example Resume - Offshore Installation Manager
As shown, the OIM did not have any prior experience on a semisubmersible or any other
drilling rig before being hired as OIM. Although this individual had been a Chief Mate and
Harbor Pilot, he had not received any formal training on semisubmersible operations
(ballast control and stability). The resume shows that he received survival and fire fighting
training but it does not indicate where the training was received or the duration of the
program. The resume does not provide any information on college/university education.
This individual would not meet the minimum requirements discussed earlier.
4 - 51
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
Barge Engineer. The resume shown in Table 4.3 is for a Barge Engineer on a
semisubmersible operating in the UK sector of the North Sea.
Name:
Position: Barge
Engineer
Hired: 12/79
This gentleman was hired in December 1979 as a Roustabout. Eight months later, he was
promoted to Ballast Control Operator. He completed a "self study" course for Barge
Engineers/Ballast Control Operators in June 1981, approximately one year after he
became a BCO. Five years later, he received formal training in stability. Although the
training shows a course in stability and damage control, it does not indicate where the
training was given or the duration of the course. The resume does not provide any
information on educational background.
Although this individual meets the experience and training requirements now, he
would not have been acceptable in the 1980-85 period.
4 - 52
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
The Barge Engineer described in Table 4.4 was working on a semisubmersible in the Gulf
of Mexico.
Name:
Position: Barge Engineer
Nationality: U.S.
Date of Birth: 12/28/35
Hired: 5/88
Experience Schools Dates of Training
Barge Engineer Master MODU,
Rig Kilo USCG License 1988
06/91 Present Master MODU 1988
Basic Buoyancy 1988
Barge Engineer and Stability
Rig Lima Ballast Control 1990
05/89 06/91 Simulator
Engineering 1989
Ballast Control Technology
Operator Certificate 1990
Rig Oscar OIM MODU, 1990
10/88 05/89 unrestricted, USCG
Marine Fire Fighting
Barge Engineer and Emer.
Rig Oscar Training
05/88 10/88 Combined Offshore
Survival, Fire
Barge Engineer Fighting and First
Rig Tango Aid
1986 1988 Offshore Survival
General Manager
Astilleros Corrientes
1981 1985
Manager Hydraulics
Houston Corp.
03/77 - 11/80
Table 4.4 - Example Resume - Barge Engineer
The resume only describes the schools attended since he went to work for the present
Contractor. The resume also indicates that this individual has an Engineering Technology
Certificate, but it does not state the college/university or the dates. This individual
satisfies the minimum requirements for his position.
4 - 53
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
Ballast Control Operator. The Ballast Control Operator described in Table 4.5 was also
working on a semisubmersible operating in the UK sector of the North Sea.
Name:
Position: Ballast Control
Oper.
Hired: 12/85
Experience School Dates of Training
Ballast Control RGIT Combined 02/21/86
Operator Survival 05/10/90
Rig Delta RGIT Combined
11/90 - Present survival Refresher 06/11/90
Module VIII (Barge
Roustabout Engr./BCO) 01/17/91
Rig Delta Basic Fire Course 06/03/91
09/89 - 11/90 Helicopter Landing 02/07/92
Officer
Floorman Stability Theory
Rig Zebra
09-88 - 11/88 (Quit)
Roustabout
Rig Zebra
02/86 - 09/88
This gentleman was hired in December 1985 as a roustabout. After holding various
assignments as a roustabout and floorman, he was promoted to Ballast Control Operator
in 1990; however, he did not receive any formal stability training until February 1992. He
did complete a "self study" course for Barge Engineer/Ballast Control Operator in June
1990 before assuming his first job as BCO. His resume indicates that he successfully
completed the Robert Gordon Institute of Technology (RGIT) survival and fire fighting
courses in 1986 and a refresher in 1990. The resume does not indicate if the stability
course was an in-house course or provided by outside sources. The resume does not list
any educational background. This individual would not have met our requirements at the
time he was promoted to the position of Ballast Control Operator.
4 - 54
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
The resume for the Ballast Control Operator described in Table 4.6 indicates that he
completed mandatory Survival at Sea training but there is no mention of any stability or
ballast control training. He does not meet the minimum requirements for this position.
Name:
Position: Ballast
Control Oper.
Hired: 10/88
Experience Schools Dates of Training
Ballast Control Survival Combined 03/30/90
Operator
Rig Alpha
05/89 - Present
Ballast Control
Operator
Rig Alpha Beta
10/88 - 04/89
Table 4.6 - Example Resume - Ballast Control Operator
Note: A review of BCO resumes indicates that many men are given a trial period of six to
nine months as a BCO before they receive any formal training in order to ensure that the
man will stay with the job. During this time, they usually receive "on-the-job" training by the
Barge Engineer while they are manning the control console on a full time basis. Very few
contractors have Ballast Control Operator trainee positions.
These resumes indicate that most of the men holding those positions were not
qualified at the time they assumed their jobs, and one is still not qualified. Although
there are many well qualified men holding OIM, Barge Engineer, and Ballast Control
Operator positions, there are also many unqualified men within industry. Personnel
working on rigs where unqualified men are employed are "at risk" every day.
4 - 55
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4 - 56
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4 - 57
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
"BEST DRILLER"
STATION BILL
SIGNALS
Fire and Emergency: Intermittent ringing of general alarm bells; sounding of whistle
for period of at least ten seconds
Abandon ship: Continuous ringing of general alarm bells
Man Overboard: Hail and pass the word "man overboard" to the bridge
All Clear: Ringing of general alarm bells three times
INSTRUCTIONS
1. All personnel reporting on board will immediately determine the location and duties of
their emergency station.
2. All personnel will be instructed in the performance of their special duties by their
immediate supervisor.
3. Each person participating in an abandon ship drill will be required to wear a properly
donned life preserver.
4. At the sounding of an emergency signal, emergency squads will assemble with
equipment at their designated station to await squad leader's instructions.
5. Any person discovering a fire will immediately notify the bridge and, if safe to do so,
extinguish the fire with available equipment.
6. At the sounding of the fire and emergency signal:
Start fire pumps.
Close all weathertight doors, hatches, and air shafts.
Stop all ventilator fans and blowers.
Lead out fire hose to affected area as directed by fire squad leader.
7. At the sounding of the man overboard signal, toss life ring buoy with smoke signal
overboard, keep man overboard in sight. Rescue boat crew will immediately clear
rescue boat for launching. Crane operator will stand by to launch rescue boat or lower
personnel basket as directed.
8. Helicopter emergencies:
motorman will immediately start foam pump
all personnel stay clear of the helicopter deck and await instructions
4 - 58
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4 - 59
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4 - 60
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
STATION BILL
Key requirements of a station bill:
It should be:
Clear and easy to understand
Written in languages understood by all of the crew
It should include:
The Chain of Command - alternatively, the Chain of Command should be
posted nearby (Table 4.8).
Emergency station assignments for everyone on the rig including visitors.
Chain of Command
Offshore Installation Manager
Sr. Tool Pusher
Night Tool Pusher
Barge Engineer
Table 4.8 - Chain of Command
The leader, backup leader, and the individual responsible for taking muster at
each emergency station
The emergency command center staff
Fire squads (two four-man teams minimum; leader, nozzle man and two hose
men)
Lifeboat crews (one crew for each lifeboat; commander, second-in-command,
radioman, mechanic)
The equipment to be brought to each station and the people who are to bring
the equipment.
Note: Every station should have a hand-held radio to communicate with the
command center.
Emergency signals
All emergency stations should be under the command of the Offshore
Installation Manager (OIM).
4 - 61
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
4 - 62
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MARINE SAFETY
The 1989 International Maritime Organization (IMO) MODU Code specifies detailed and
comprehensive requirements for drills and training. The same requirements are contained
in the MODU Code Consolidated Edition issued in 2001. While many countries in which
you operate require adherence to the IMO Code, the 1989 Code applies only to rigs
constructed beginning in May 1991. The previous 1979 Code hardly addresses drills and
training. This shows, once again, that you cannot necessarily rely on "the regulations" to
ensure an adequate level of marine safety.
E xxo n M o b ils G u id e lin e s o f C re w P ro ficie n cy D rills (w h ich in clu d e fire /a b a n d o n m e n t) a re
included in the Safety Management Program Manual (SMP).
4 - 63
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5
Section
Describe the basic operation of each of the position reference systems used by
deepwater drilling rigs.
List the different types of thrusters used by DP vessels and describe the differences
between each.
Understand the basic layout of a power distribution system onboard a DP vessel and
be familiar with the associated protection systems.
Interpret Drive-off/Drift-off results to determine the settings for the red and yellow
watch circles.
5-1
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
CONTENTS PAGE
5-2
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5-3
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5.1 INTRODUCTION
Dynamic Positioning (DP), like conventional mooring, is a means of maintaining a
floating vessel at a specified location with respect to a reference point and at a specified
heading using propellers and/or thrusters. For drilling, the reference point usually is the
wellhead on the seafloor.
Dynamic Positioning and its associated technology have evolved over the past forty
years. The control of a ve sse ls p o sitio n b y th e u se o f th ru ste rs, ra th e r th a n m o o rin g
lines and anchors, was originally conceived for positioning coring ships in deepwater
where deploying anchors was not possible. The Cuss I was the first ship to maintain its
station by dynamic positioning on 9 March 1961 in 948m water depth offshore La Jolla,
California. The ship was equipped with four 200 HP thrusters. Each individual thruster
was manually controlled to maintain the vessel's position and heading. The system
employed a surface radar receiving echoes from four buoys and a sonar interrogating
subsea beacons to provide a position reference. This arrangement was nowhere near
today's definition of Dynamic Positioning.
As one can imagine, maintaining an acceptable watch circle by simultaneous manual
control of a number of thrusters would be quite tedious. This gave rise to the need for
automatic control. The coring vessel Eureka, working for Shell Oil, also in 1961, was the
first to be fitted with analog controllers of a very basic nature. The system made use of
two steerable thrusters fore and aft along with her main propulsion to automatically
maintain the vessel's position and heading.
F u rth e r ve sse ls fo llo w e d su ch a s th e "C a ld rill", "G lo m a r C h a lle n g e r" a n d "T e re b e l. A ll
pioneers in the development of the dynamic positioning technology. The systems
employed were crude by today's standard, utilizing analog controllers with no
consideration given to system redundancy, but it was a start.
Today's systems are much more sophisticated and complicated but have also become
much more reliable. Modern Dynamic Positioning systems have taken advantage of the
tremendous advances made in computer technology over the past couple of decades.
Redundancy has become integral to the design of modern DP systems. This redundancy
includes every aspect of the DP system; the computers, the position reference inputs,
the vessel's power generation and electrical distribution systems, and the propulsion
systems. A modern DP vessel of the highest classification is capable of maintaining
station following the total loss of a single compartment.
5-4
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5-5
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
Advantages Disadvantages
Deepwater applications Higher power requirements
Self-propelled, no tugs required to move Higher fuel cost
from one location to another
Higher maintenance cost
No need to hire large expensive anchor
handling boats Need for specially trained personnel to
operate the sophisticated equipment
Rapid setup on location
More vulnerable to failures resulting in
Rapid move-off capability in storm or the need to emergency disconnect
iceberg conditions
Greater risk of riser/wellhead damage in
Ability to head into weather excessive offset/failure to disconnect
scenarios
Ability to start up in higher sea states
Higher day rate compared to moored rigs
Can easily work in areas where damage
to hardware on the seabed, such as
pipelines, is a concern
5-6
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
A significant disadvantage of a DP vessel is that the day rate is normally higher than for
an equivalent moored vessel - due to both greater capital expense and additional
operating cost. Sophisticated DP equipment and higher installed power on board result
in higher capital expenditure. Fuel consumption, equipment maintenance, and the need
for specially trained operating personnel all contribute to the increased operating cost.
Another, somewhat intangible, disadvantage is the higher engineering attention required.
The responsible engineer (i.e. Chief Engineer or Senior Maintenance Supervisor) on the
vessel should have a thorough understanding of the DP system to ensure its efficient
and safe operation. In addition, a fair amount of shakedown time is usually needed if the
DP system is new or has just gone through a major modification.
5-7
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
TRANSLATIONAL MOVEMENT
Surge - This is movement in the horizontal plane in the forward or aft direction.
Sway - This is movement in the horizontal plane in the transverse direction or
side-to-side.
Heave - This is the vertical movement in the up or down direction.
The DP system is concerned with controlling only three of these movements, surge,
sway, and yaw. The combination of surge and sway define the vessel's position while
5-8
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
yaw defines the vessel's heading. Even though the remaining three freedoms of
movement, pitch, roll and heave, are not controlled by the DP system, they are
measured as necessary inputs to correct the vessel position reference signals.
These motions are detected by the Vertical Reference Unit (VRU).
Both vessel position and heading are controlled about desired input values, known as
"se tp o in ts. In e a ch ca se the vessel's actual position and heading must be measured in
order to obtain "feedback" values. The vessel position at a given moment in time is
determined through a range of Position Reference Systems while the vessel heading is
provided by one or more gyro compasses. The difference between the desired
setpoints and the measured feedback is the error. The DP system, in turn, provides
thruster commands in attempt to reduce the error to zero.
5-9
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
WIND
WAVE
FORCES
CURRENT
FORCES
Once a rig is on location, external forces (Figure 5.2) act on the vessel structure to
move it from its desired position or heading. These forces include wind, wave and
current. To maintain the desired position or heading the DP system must then produce
equal and opposite forces via the thrusters. The difficult part is to be able to measure
these external forces accurately so that the system knows how much thruster force is
needed and which direction to apply it.
Wind can be measured directly using a wind sensor. Wind sensors can provide an
accurate and continuous measurement. This measurement is then fed into the computer
for immediate compensation. Wind compensation is further discussed in section 5.2.6.
An accurate method has not been developed to measure the current and wave forces
using sensors deployed from the vessel. This is because the vessel's structure and/or
thruster wash disturb the waters in the immediate which results in inaccurate
measurements. For this reason, this portion of the external force must be deduced over
a period of time by monitoring the rig's tendency to move off location or change heading.
All forces not attributable to direct measurement (i.e. wind) are combined together and
la b e le d a s "cu rre n t. T h e cu rre n t fo rce is a co m b in a tio n o f cu rre n t, w a ve , a n d sw e lls
along with any errors in the system.
5 - 10
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
DGPS
Portable 3-
Computers/ axis Joystick
Display
consoles
Thrusters
Wind Sensors
Operators
Uninterruptible
Power Supply
Tautwire/
Riser Angle
Sensors Motion
Gyrocompass
Reference
Sensors Acoustic Reference
System
COMPUTERS
For the most part, modern DP systems utilize off-the-shelf Pentium type computer
processors operating in a Windows environment. The computers may be arranged in a
single, dual or triple configuration, depending on the level of redundancy required. The
system communicates via an Ethernet or Local Area Network (LAN), which incorporates
many other vessel control functions.
5 - 11
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
DP vessels that meet the highest classification requirements (class 3) are triple
redundant consisting of three operator stations and three independent computers.
Communication between the three systems is via a dual high-speed data network. This
type of arrangement significantly increases the reliability of the system compared to a
single or even a dual system. The system is able to detect an error and isolate the faulty
data or component. The concept of majority voting is used to detect and isolate faults.
If a fault is detected in one of the computers or sensors, that computer or sensor is
isolated. The onus does not befall the DP Operator to determine which data or
component is correct, as is the case with dual redundant systems.
The term MMI or man-machine interface has been adopted for the control consoles.
Basically this is where all the input buttons, indicator lights, display screens and
maneuvering joystick are located. The control consoles are typically installed on the
bridge along with the other essential controls such as position reference control units,
thruster control console (Figure 5.4), communication suite, radar and vessel
management system console. In some semi-submersible vessels the DP consoles may
be located in a space other than the bridge. The location is not all that critical, but there
is definitely an advantage to having the operator located in a space that has a view of
the outside to provide some orientation during heading and position changes.
For vessels to satisfy the class 3 requirement, a backup computer and control console
must be provided in a separate location from the main system. This is so DP capability is
not lost in the event of a fire or flooding in the compartment housing the main system.
The DP system is protected against power failure by the inclusion of an Uninterruptible
Power Supply (UPS). This system provides a stabilized power supply not affected by
short-term interruptions or fluctuations of the ship's a.c. power supply. Power is supplied
to the computers, consoles, displays, alarms, position- and environment-reference
systems. In the event of an interruption to the main a.c., a bank of batteries will supply
power to all of these systems for a minimum of 30 minutes. Note: this emergency back
up applies only to the DP system electronics and not to the thrusters.
5 - 12
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
MATHEMATICAL MODELING
The DP computers carry out their positioning function by using a feedback control loop
as shown in Figure 5.5. The DP operator inputs the desired position for the vessel into
the controller. The actual position of the vessel is determined by the position reference
systems and is input into the computer.
Based on the position error (desired minus actual), the controller calculates the
commands to the thrusters which provide the necessary forces to counter the
environmental forces and maintain the vessel on location.
Critical to the reliability and performance of a DP vessel is the power generation,
distribution and management system as discussed in detail in Section 5.6.
ENVIRONMENTAL
MEASURED WIND FORCES
DESIRED MOTIONS
CONTROLLER THRUSTERS SHIP
POSITION Fc
POSITION
THRUSTER
ERRORS
COMMANDS
APPARENT POSITION
POSITION REFERENCE
5 - 13
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
There are three independent control loops, one each for the surge, sway and yaw axes
of the vessel. The three control axes are coupled by the thruster allocation logic in the
controller as shown in Figure 5.6.
WIND DRAG
TABLES
Fx T1
SURGE +
+
CONTROLLER
T2
VESSEL INDIVIDUAL
SWAY Fy THRUSTER
POSITION + THRUSTER
CONTROLLER + ALLOCATION
ERRORS T3 COMMANDS
LOGIC
YAW Mz T4
+
CONTROLLER +
Certain properties of the vessel, such as the displacement, added mass, hydrodynamic
and aerodynamic coefficients must be known in order to design the control system
software.
CONTROLLER
The controller of a DP system must perform the following main functions:
Process all data generated by the dynamic positioning sensors, discarding non-
significant or faulty signals, carry out the necessary filtering and computations, and
optimize stability of the implemented control algorithm.
Determine most probable true position (surge, sway and heading) and command
available thrusters, minimizing power consumption and complying with any other
requirements (e.g. that imposed by power management system).
Present the operator with up-to-date information on vessel location relative to the
reference point, status information about all equipment including alarms,
malfunctioning equipment, and adequate warnings about potential loss of position.
5 - 14
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
PID CONTROLLER
The earlier generation controllers calculated the thruster commands based on the
position error, the rate of change in position error and time integral of the position error.
This controller is commonly referred to as the PID (proportional-integral-derivative)
controller. The "proportional" control provides the thrust that is analogous to the spring
force generated by a mooring system when the vessel is offset from its equilibrium
position. The "derivative" control provides the controlled damping, and the "integral"
control is required to maintain a zero position error. If the integral term is not included,
a cumulative difference in the measured and reference variables must be tolerated so
that the controller, through the proportional term, can command the necessary steady-
state counterforce.
KALMAN CONTROLLER
Another type of controller, more commonly used now, uses what is known as Kalman
filtering technology. Functionally these Kalman controllers are analogous to the PID
controllers - the manner in which the proportional, integral and derivative terms are
computed is different. Kalman controllers employ mathematical models and the thruster
commands no longer depend on the difference between required and measured values,
but between required values and values derived from models. The measured values
obtained from the position reference systems and other sensors are used to adjust the
models in real time. Use of the modeling method involves calculation of the forces acting
on the vessel and thus requires knowledge of the numerous hydrodynamic parameters
of the vessel. Nevertheless, the Kalman controller can provide a superior performance
relative to the PID controller, as it can include a much better position signal processing
logic, especially in situations where the position signals are constantly contaminated by
ambient noise. Another situation where the Kalman controller is superior is when the DP
system is in a "dead reckoning mode" following complete loss of all online position
sensors. Better dead reckoning performance allows the operating personnel more time
to deal with the situation.
Kalman filtering provides another system improvement. Ocean waves act on a floating
vessel in two ways. First, there is a high frequency component that physically lifts the
ship up and puts it back down in the same place, in an oscillatory and circular motion.
Because the high frequency forces involved are so large, and the thrusters so relatively
small, it would be futile to try and command the thrusters to counter these motions.
Second, there is a low frequency component where the ship drifts slowly off position due
to low frequency forces, called wave drift forces. This effect can be witnessed when
watching a seagull floating in waves; it moves around in a vertical circle in each wave
but only drifts along very slowly.
One of the controller requirements, therefore, is to remove the high frequency
component from the position measurements so as to prevent the control system, and
therefore the thrusters, reacting to it. Applying Kalman filtering and modeling techniques
to the processing of the error signal has achieved improved filtering of the wave
frequency motions without introducing a lag in the system, and thus has improved
controller performance.
5 - 15
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 16
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
In vessels where redundancy is necessary, two or three gyros are fitted. If only two
gyros are fitted, the problem still exists with determining which unit has failed. All the DP
system can do is to monitor the difference in heading readout between the two gyros,
and flag up a warning if that difference exceeds a certain value (e.g. 3 degrees, initiating
the warning "Gyro Difference Error"). This puts the ball firmly back into the DPOs court
regarding the selection of the correct gyro; it may be that the backup has failed. This
leaves a less than satisfactory situation for the DPO, as it may be impossible for him to
tell immediately which compass is giving problems. In vessels with two gyros, it is
strongly recommended that the DPO note the magnetic compass heading when the
vessel is set up on DP and settled. Note: it is not normal for the DP system to be
configured to accept input from magnetic compasses.
The gyrocompass is an extremely important input into the DP system. Without the
gyrocompass input, the DP system will not be capable of maintaining heading nor
position. It may be intuitively obvious why the system will not be able to maintain
heading, but perhaps not so much why the positioning capability is lost. This is because
the position setpoint is used to define the position of the moonpool center. The gyro
compass reading is used by the Position Reference Systems (PRS) to account for the
orientation of the sensors (antennas, transducers, & hydrophones) from the moonpool.
Without this orientation the PRS will not know its relation to the setpoint.
If three gyros are fitted, then the DP system may use Voting logic to detect a gyro failure,
and give an appropriate warning to the DPO. Three gyros are typically fitted in vessels
complying with Equipment Class 3, where triple modular redundancy is the norm in the
DP system.
5 - 17
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 18
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
One result of the environment is the roll, pitch and heave motions of the vessel. These
are three of the six freedoms of movement not controlled by the DP system. For the
purposes of DP we ignore heave
entirely, but it is necessary that the
DP system be provided with accurate
and instantaneous values of Roll and
Pitch. This is to allow compensation
values to be applied to the various
position reference sensor inputs to
the DP relating to angular
measurements. Some Position
Reference Systems rely on angle
measuring sensors, which are
located some distance from the
center of gravity of the vessel. This is
similar to the heading compensation
Figure 5.8 - Vertical Reference Units
described in the previous section.
For example the hydroacoustic PRS make calculation based on sensor inputs assuming
the vessel in vertical. Without this compensation errors would be introduced into this
positioning information. Instrumen-tation to measure these values is provided in the form
of a Vertical Reference Sensor (VRS) or Vertical Reference Unit (VRU). The terms VRS
and VRU are synonymous.
There are many types of vertical reference sensors. The pendulous mass type sensor is
the simplest and least expensive. Its performance, however, is only marginally
acceptable due to the effects of lateral accelerations. The measured angle includes both
the true angle of inclination and the error induced by the lateral acceleration of the
vessel.
Other types of sensors include vertical gyros and the combination of linear and angular
accelerometers which provide significant improvement over the pendulous mass type
sensor.
5 - 19
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 20
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
The detection of representative wind values is sometimes difficult, and is often a factor of
correct positioning of the wind sensors. In general they must be above and clear of any
structure that would provide windshadow. Windshadow may stem from masts or
structures such as the derrick. It is common to position wind sensors on either end of a
transverse yardarm or on opposite ends of the vessel.
In most DP systems, the DPO selects the in-use wind sensor, and it is up to him to
determine when that wind sensor input is no longer appropriate, and to select an
alternative. If both wind sensors are de-selected, the DP system will use the value of the
wind contained in the model, i.e. a constant value. Under these conditions there will be
no update of wind values, and feed-forward facility, so no direct compensation for
gusting conditions. The DPO must be aware of this. It may be that he has de-selected
both wind sensors for an impending helicopter visit, in order to prevent disruption of the
positioning due to draft from the helicopter's rotors affecting the wind sensors. If this is
the case, the DPO must also be aware of the hazards involved in the re-selection of the
wind sensor. If the value for the wind on re-selection is different to that contained in the
model, then the DP system will treat the apparent change as an instantaneous gust, and
the feed-forward may initiate a drive-off. Unless the change in windspeed during the
period of de-selection has been radical, the drive should not be particularly violent, but
it is something for which the DPO must be prepared.
5 - 21
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 22
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
The Navstar GPS consists of three segments: Space, Control and User.
5 - 23
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
SPACE
The space segment consists of 24 satellites in 6 orbital planes, including three in-orbit
spares. These orbit the earth in 12-hour orbits at an altitude of 20,200 kilometers.
CONTROL
The control segment consists of a Master Control station in Colorado Springs, with 5
monitor stations and 3 ground antennas located throughout the world. The monitor
stations track all the GPS satellites in view and collect ranging information from the
satellite broadcasts. These stations in turn relay this information to a Master Control
station where satellite orbital parameters or ephemeris data are computed (Figure 5.13).
This precise orbital data is injected back to the satellites by uplink every six hours via the
three upload stations. This orbital correction information is then incorporated into the
positioning information (L1 & L2 signals) broadcasted by the satellite.
5 - 24
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
SATELLITE SIGNAL
The GPS system operates at two frequencies; 1575.42 MHz (L1) and 1227.60 MHz (L2).
All satellites transmit both L1 and L2 frequencies. Since the frequency is the same for all
satellites, the modulation must contain characteristics making it possible to separate the
different satellite signals from each other. This is achieved by using codes on the
signals, called pseudo-random noise codes (PRN codes) (Figure5.14). There are two
types of pseudo-random noise codes used; a precise-code (p-code) and a Coarse
Acquisition code (C/A - code). The L1 transmission is modulated by the P-code and the
C/A-code, while the L2 frequency carries the P-code only. The P-code provides the
Precise Positioning Service (PPS) which provides an accuracy of 20 meters. This portion
of the GPS service was originally restricted for military use only. The US DoD injected a
deliberate degradation in the range accuracy of the C/A code known as Selective
Availability (S/A). The degradation is achieved by introducing "jittering" or "dither" to the
transmitted clock data, which gives a rapid rate of change to the pseudoranges. Further,
slow rate-of-change errors are introduced to the ephemeris data (orbital co-ordinates). In
combination these two effects reduce the overall accuracy to around 100 meters. Civilian
users were thus limited to the Standard Positioning Service (SPS) obtained from the
C/A-code signals transmitted on the L1 frequency.
As of May 1, 2000 Selective Availability was removed allowing civilian receivers to yield
the higher accuracy from the C/A code.
5 - 25
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
MEASUREMENT PRINCIPLE
Each satellite continuously broadcasts the time and its orbital position. A GPS receiver
must receive four or more of these signals at once to determine its position. The receiver
makes use of "Pseudo-Ranges" to calculate a position. The measurement is based on
the principle that both the satellite and the receiver are generating the same pseudo-
random codes at the exact time. By comparing how late the satellite's pseudo-random
code appears, compared to the receivers code, the travel time of the signal can be
determined. The travel time is then multiplied by the speed of light to get the distance.
These measurements are referred to as pseudo-ranges as they will be affected by
errors in the receiver clock. Since this error will be the same for all satellites in view,
provided that at least four satellites are in view, the clock offset can be determined by
use of simultaneous equation techniques. To compute the antenna position, the receiver
must resolve four unknowns: Cartesian co-ordinates x, y and z and clock error. The
spatial locations of the satellite are known quantities included in the coded satellite
messages. Three satellites can be used to compute a 2-dimensional fix if the height
above the terrestrial spheroid is known. This technique is known as fixed height and is
also used to enhance position computations with more than three satellites.
This method is known as height aiding.
SOURCES OF ERROR
Even without the deliberate degradation in range accuracy there are other sources of
error that influence the signal accuracy (Figure 5.15).
5 - 26
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
Ionosphere
The ionosphere is the layer of the atmosphere ranging in altitude from 50 to 500 km
and consists largely of ionized particles, which causes signal delays and refraction
(Figure 5.16).
Troposphere
The troposphere is the lower part of the atmosphere. This is where changes in
temperature, pressure and humidity associated with weather changes occur.
These factors cause varying degrees of delay and refraction to the signal.
Multipath Effects
These are caused by reflection signals from the surface near the receiver that can either
interfere with, or be mistaken for, the signal that follows the straight-line path from the
satellite. If the reflected signal is very strong, the GPS receiver might lose lock on the
satellite. Multipath is difficult to detect and sometimes hard to avoid (Figure 5.17).
5 - 27
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
Geometry Effects
Basic geometry can itself magnify other errors with a principle called Geometric Dilution
of Precision - GDOP. When the user is at a position where the lines drawn from the
satellites are nearly perpendicular to each other, the point of intersection is well defined.
The effects of geometry vary with time of day and number of satellites available. Poor
geometry can magnify small errors (Figure 5.18). The dilution of precision (DOP) is a
dimensionless number indicating how much geometry is magnifying the errors. DOP is
broken into four components (horizontal, vertical, geometric, & time), the most commonly
used value being the horizontal component, HDOP. The lower the HDOP value the
better the accuracy based on satellite geometry. Ideally, HDOP values should remain
below 3, if HDOP creeps above 5, then the position fixing becomes suspect.
5 - 28
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 29
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
The user in the vessel will apply the PRCs in one of two ways. Direct Injection involves
interfacing the PRCs directly to the GPS receiver so that the pseudo ranges can be
corrected, deriving a differentially corrected position. The second method is to supply
both pseudo-ranges from the GPS receiver, and the PRCs to a PC running DGPS
software which combines the two sets of data to derive the corrected position.
5 - 30
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
The use of differential techniques may potentially result in system accuracies superior to
those obtained from the p-code. Even when using the p-code, the GPS system will
exhibit inaccuracies associated with errors in satellite position within its orbit. Using the
C/A code with differential corrections, the effects of orbital errors are reduced.
The differential link used to transmit the corrections varies from HF and UHF short-range
radio links to communications satellite links providing longer range or even global
coverage. The type of differential link selected will depend on circumstances and
location but an essential requirement is a high update rate for the corrections. For DP
purposes, update rates of less than 5 seconds are necessary. Longer update intervals
will result in erratic positioning.
DIFFERENTIAL GPS DATA LINKS
There are several different types of PRC data link available from DGPS suppliers.
Typical systems and suppliers are shown in Table 5.2.
There are advantages and disadvantages to every type of link available. The UHF and
VHF links allow the fastest correction update rates and thus tend to provide the highest
accuracy, generally at the two meter level or better. They are however limited in range to
70 kilometers or less, and thus require reference stations to close in proximity to the
area of operation.
The medium and low frequency systems are more versatile, with ranges of up to 500 or
even 700 kilometers being available, but this extra coverage is generally at the expense
of update rate and hence accuracy and stability. These medium frequencies are also
more susceptible to interference caused by weather and dawn/dusk effects. The
Inmarsat and high frequency Systems are very much dependant on having line of sight
to the differential transmitter (i.e. the reference station or a communication satellite).
5 - 31
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
The communications satellites provide the most flexible DGPS link solution (Figure
5.22). Update rates are generally at the five second level or faster and thus there is little
degradation of accuracy. Most Inmarsat DGPS suppliers have now designed frequency
taps which can extract the correction data from the vessels own lnmarsat
Communications system without affecting its communications capabilities. The
availability of multiple reference stations also allows the computation of a network
position solution using more than one reference station. This produces a more robust
and stable position with effective and automatic redundancy of reference stations.
5 - 32
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
NETWORK DGPS
Some DPGS systems are able to accept multiple differential inputs obtained from widely
separated reference stations(Figure 5.23). The simplest method of deriving a position
using multiple differential signals is for the receiver to average a number of PRC values,
from different reference stations, weighting each by the distance to the reference
stations (highest weighting to the PRC values from the nearest reference station). A
more satisfactory solution involves a full least-squares computation using all PRCs
received. Both of these methods are referred to as decentralized systems. Another
method, the centralized system involves the computation of one set of PRCs ashore,
based on all the data from the reference stations, and this set of PRCs are then
transmitted to the user. This is the method used in the UDI Starfix Network package,
also the Sercel Veripos network, and the Racal Skyfix Network. In these systems,
reference station data is relayed to a Hub or network control center. Correction data is
then sent to the user in raw form; this is then processed on board to determine the best
solution, with the position of the vessel used to determine the optimum PRCs. Generally,
network DGPS systems provide greater stability and accuracy, and remove more of the
ionospheric error than single reference station systems. Also, Network systems are more
comprehensively monitored at the Hub stations, where user information or warning data
may be generated and sent out.
5 - 33
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
DGPS ACCURACY
The accuracy quoted for DGPS varies from one to five meters. Within a particular
constellation of satellites the accuracy varies between one and three meters, rising to
five meters during a constellation change.
PERFORMANCE AND PRACTICAL ASPECTS OF DGPS
Experience has shown that DGPS provides the best reliability when the vessel is in open
water. Degradation in the system may be experienced if the vessel is positioned
alongside a platform structure due to signal reflection (multi-path) or loss of signal line-
of-sight. Position jump may occur at changes in constellation configuration (picking up or
dropping of satellites). It is important that the receiving antenna for the satellite signals
be placed at the highest point in the vessel. This is impracticable in some vessels such
as crane barges with large mobile jib structures. Advanced receivers are able to mitigate
the effects of constellation change by adjusting the weighting of signals from newly
acquired satellites, ramping the weighting from zero when the satellite first rises above
the elevation mask, up to maximum when a few degrees above it. Reverse ramping is
applied as the setting satellite approaches the elevation mask.
One particular problem experienced by some operators has been system lock-up or
"G P S fre e ze . T h is is o fte n u n e xp la in e d , but GPS freeze can have catastrophic results
for the DP capability as the DP will consider the position data of high quality (e.g. very
stable) possibly rejecting other PRS in favor of the frozen GPS. If the vessel is slightly off
her set-position then continuous, apparently ineffective compensation from the thrusters
will result in drive-off.
Problems are occasionally reported of interference of DPGS signals caused by telex,
mobile phones, satcom kit or radar. This type of interference must be checked out on
installation.
5 - 34
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 35
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 36
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 37
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
TRANSPONDERS
A transponder (Figure 5.24) is similar to a transducer in that it also transmits and
receives acoustic signals. The difference being transponders are positioned on the
seafloor and transmit an acoustic signal in response to an interrogation signal sent from
the vessel. A variety of transponder types are used, depending on the particular
application. They operate in the 15 kHz - 32 kHz band. When using multiple
transponders each must operate at discrete frequencies, separated by a minimum of
500 Hz, in order to allow identification of the transponder sending the signal and to avoid
interference between multiple replies. The transponder itself is battery powered and may
have rechargeable or replaceable batteries. Battery life is obviously limited, and will
depend on type of battery, functions available, low or high power operation, and
interrogation rate. For this last reason, it is normal to reduce the ping rate to the lowest
rate commensurate with effective positioning, as the higher ping rates will deplete the
batteries more quickly.
5 - 38
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
Transponders are anchored to the seafloor using a sinker weight and 1 - 2 meters of
mooring chain (Figure 5.25). The amount of weight used can vary from 60 - 150 kg
depending on the water depth and environmental conditions. The transponders are fitted
with a float to keep the unit vertical and off the seafloor.
Transducer
Protection
Wire Rope to Surface
Float (Typically not
used in Drilling)
Float
(Divinycell)
Transponder
1 2 m Mooring Line
150 kg Sinker
Care must be taken when deploying transponders to ensure that the sinker weight is not
being lowered onto any seabed hardware, or into a location where there will be acoustic
shadowing. It is a good idea not to deploy transponders too close to ROV operations
where its umbilical can get fouled in the transponder's anchor chain and unwittingly drag
the transponder away in its travels. Perhaps the biggest source of interference is noise
and aeration from the vessel's thrusters and propellers. The DPO must consider the
acoustic path between Transducer and Transponder, and arrange to minimize the
amount of thruster wash that is directed into that path.
Retrieval of the transponders may either be done by a ROV or through remote release.
During remote release the transponder receives an acoustic release command from the
surface, the release hook at the base of the unit opens releasing the mooring tether to
the sinker weight. The transponder then floats to the surface carried by its fitted float.
5 - 39
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
LONG BASELINE
At a minimum the Long Baseline Acoustic Position Reference System (Figure 5.26)
consists of three transponders on the sea bottom and a transducer on the vessel. The
basic principle behind this system is that it measures the amount of time required for a
signal to travel from the transducer to the transponder and back. This travel time is then
multiplied by the speed of sound in water to get a round trip distance. Knowing the range
to each of the transponders a relative position of the vessel can be calculated by
triangulation. The entire process is started by the surface transducer producing an
interrogation signal which is received by the transponders. The transponders then reply
with a return signal. To avoid signal interference each transponder replies after a
predetermined delay and with a unique frequency. This fixed time lapse between the
reception of the interrogation signal, and the transmission of the reply, ensures that the
transponder replies do not arrive at the transducer simultaneously. The processor is
aware of the delay time programmed into each transponder and factors this into the
calculation.
Most advanced systems will utilize more than three transponders and perhaps even
more than one transducer on the vessel to receive the reply signals. This provides an
element of redundancy along with multiple positions which can be averaged together to
improve accuracy.
5 - 40
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
The long baseline system can provide very accurate positioning information. One
advantage of this system over the other acoustic system is the angle of incidence of the
return signal is not relevant. Thus a major source of error is eliminated; that of angular
distortion in reply signal paths due to ray bending or refraction. Errors in range
measurements caused by ray bending are less significant. The system may have a
sound velocity profile inserted to allow ray bending corrections to be applied. The
accuracy of the determined positions will depend on a number of factors, in particular the
accuracy of the sound velocity profile used, the number of ranges measured and the
geometrical angles of cut of the position circles.
Filtering takes place using a weighted least-squares analysis on the ranges measured.
Also since this system does not need to know the angle of incident of the return signal
there is no need for a VRS input, thus eliminating a potential failure point.
The position that is calculated is a relative position from the transponders and therefore
requires the location of the transponders to be known. This is performed through a
calibration process during system setup.
5 - 41
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
independent of water depth, and is better for higher than lower frequencies. Deeper
water requires lower frequencies in order to conserve transponder battery power. A
disadvantage of the LBL system is the lower update rates available in deeper water. It is
not possible to maintain the desired once-per-second data rate in waters deeper than
500m so it becomes necessary to reduce the update rate to 4 seconds or even longer.
For general DP position reference, USBL is a more versatile and flexible system,
providing adequate accuracy, and easily deployable anywhere. LBL systems are more
accurate over the specific area of the array, typically 0.1% water depth, but require
additional setup time.
SHORT BASELINE
The conventional short baseline system (Figure 5.27) uses an array of receiving
elements called hydrophones, which are mounted on the vessel. These hydrophones
make up an array and the distance between the hydrophones forms the baseline. Similar
to the long baseline system a minimum of three hydrophones are required, but the
baseline distance is much shorter since the array is mounted on the vessel verses the
seafloor. The system also utilizes a subsea beacon positioned on the seafloor to emit an
acoustic pulse. The time-of-arrival of this acoustic pulse is measured at each
hydrophone, and the differences in time-of-arrival are compared. Unlike the long
baseline system the actual distances of the beacon to the individual hydrophones are
not measured, but the distance differences are determined from the difference in time-of-
arrival. Knowing the geometry of the hydrophones the differences in time-of-arrival can
be used to compute the offset of the vessel to the beacon, and hence a relative position
of the vessel.
The subsea beacon can either be a pinger or a transponder. A pinger emits acoustic
pulses at a fixed ping rate, usually once per second. A transponder emits acoustic
5 - 42
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
pulses only when interrogated by an interrogator installed on the vessel. One distinct
difference between the pinger and the transponder is the data rate. In the case of the
pinger, the data rate is fixed and cannot be controlled from the surface once the beacon
is deployed. Some pinger designs can be switched on, off, or released from their
anchors by a series of acoustic codes emitted from the vessel. As for the transponder, it
has to be interrogated from the surface and the data rate is entirely surface controlled.
However, for deepwater applications, the minimum time required to complete a data
cycle for the transponder can be several seconds due to the round trip distance between
the interrogator on the vessel and the transponder on the sea bed, and the speed of
sound in water.
Short baseline systems are typically fitted with four or more hydrophones to improve
redundancy and system reliability. For instance some of the Nautronix systems use six
or eight hydrophones in combination with four transponders to develop multiple ranging
solutions. The system then performs a least squares fit based on ALL the valid position
measurements and reports a single SBL solution to the DP system. Hydrophones
exhibiting a reduced S/N ratio are eliminated automatically from the solution, thereby
achieving a high level of redundancy. This use of redundant hydrophones also allows
some of the hydrophones to suffer from acoustic masking from local noise sources and
still retain full accuracy.
Another type of SBL system uses ranging principles similar to the LBL system but
slightly reversed. Here one of the hydrophones in the hull array is replaced with a
transducer and the seabed beacon is a transponder. As in the LBL system, this system
uses the transducer to send out an interrogation pulse which is received and replied to
by the transponder. A range is then determined for each hydrophone based on the time
delay observed between the transmission of the interrogation pulse and the reception of
the reply signal. The result is a number of range measurements from which a position
can be determined. This position is, of course, relative to the location of the seabed
beacon or transponder.
A significant advantage of SBL systems, when compared with Ultra Short Baseline
(USBL) and LBL systems in deeper water, is the update rate. With free-running beacons
on the seabed there is no delay associated with the interrogation of transponders. Data
rates may be maintained at the once-per-second desirable for DP purposes irrespective
of water depth, although this will not be true for the systems wherein a transponder is
interrogated for reply. The SBL systems also show a greater accuracy in deeper water
compared with USBL systems due to the lower impact of water noise as well as the
longer baselines. The SBL system is capable of achieving accuracies within 0.1% to
0.2% of slant range.
With any SBL system, the co-ordinate system is attached to the vessel (the x/y co-
ordinates of the hydrophones or transducers) and as such will roll, pitch and yaw with
the vessel's movement. This necessitates the inclusion of VRU and gyro units into the
system in order to enable the effects of vessel movement to be extracted.
Once common in drill ships, SBL acoustic position reference systems have generally
been superseded by USBL/SSBL and LBL systems but are fast making a comeback due
to the advantages mentioned above relating to deepwater operations.
5 - 43
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 44
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 45
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
Spreading
Spreading of the acoustic energy is simply a function of distance. If an acoustic signal
originates at a position, and radiates from that position in a spherical pattern, there will
be a decrease in the signal intensity in proportion to the square of the distance. This is
because the energy within the signal will be spread over an increasing area, such that a
target (listening transponder) will intercept only a small proportion of the transmitted
energy.
Attenuation
Attenuation is a weakening of the acoustic signal, which is mostly caused by absorption
of the acoustic energy as it travels through the water. In this case, a proportion of the
acoustic energy will be converted to heat within the water. The amount of absorption
depends heavily on the frequency of the acoustic signal, and the temperature, salinity
and pressure of the water. Best results are obtained with signals of low frequency, within
the 10 - 30 kHz band. At higher frequencies than this the effective range reduces to
unacceptable levels. One system, the Nautronix ATS uses a multi-frequency "chirp" for
the interrogating pulse. If one frequency is masked or lost then the others should ensure
reception.
5 - 46
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 47
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
Noise Interference
Noise interference is a further hazard to effective acoustic operations. An adequate
signal-to-noise (s/n) ratio must be maintained to ensure secure communications. Noise
conditions vary with sea state and with noise from propellers and thrusters. Noise may
also emanate from underwater operational elements, e.g. from ROV and drilling. Noise
may also be emitted from supply vessels working alongside, or from such diverse factors
as rain falling on the sea surface. The higher the s/n ratio, the more accurate will be the
position measurements obtained.
5 - 48
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
KALMAN FILTERING
The mathematical technique of Kalman filtering provides a method of combining
measurements from different sources in a statistically optimum manner. The requirement
of combining two or more PRS inputs within a DP system is an example of the use of
Kalman filtering.
Earlier generations of DP systems, before Kalman filtering, used PID controllers to
provide thruster commands based on the position offset of the vessel from the setpoint.
Kalman controllers work on a different principle, employing mathematical models of the
ve sse ls p o sitio n . T h e m a th e m a tica l m o d e l is d e te rm in e d fro m kn o w le d g e o f th e p re vio u s
position and of the forces acting on the vessel. The system then combines the modeled
and measured positions to determine the best estimate of the vessel position. This
estimated position is then used to modify the model. The weighting within the Kalman
filter on model or measurement will depend on the expected performance of the PRS. If
the PRS in question is "noisy", i.e. the variance is large, then greater weight should be
placed on the model. If the PRS are accurate, then greater weighting can be allocated to
the measurement position. The design of the Kalman filter will determine the reactions of
the control system in response to vessel excursions and erratic position measurements.
5 - 49
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
VOTING
For redundant operation the DP vessel will usually (where possible) use three or more
PRS, allowing the DP system to apply Voting logic to the measurements. Voting will
involve taking the middle value, or Median of the three or more input values. For each
PRS input the offsets from the Median value are examined and checked against a
preset reject limit. The Median is used, not the average, since if averaging was adopted,
the inclusion of data from the erroneous system would pollute the average value, and
the good data would then show excessive offsets which might also result in their
being rejected.
5 - 50
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
A circle is shown for each PRS of the radius equal to the Innovation for that PRS (Figure
5.30). The Standard Deviation limit is shown centered on the display, which is the
predicted position.
Each PRS is assigned a Weighting value; this is inversely proportional to the Innovation
value, thus the weighting is based on the relative circle sizes.
The weighting values always total 1.0 regardless of how many PRS are enabled. Within
this, the larger the weighting, the smaller the Innovation or circle size. For all PRS the
measurements are filtered. Position reference inputs are sampled once per second. In
the above display the raw PRS data is shown as small crosses corresponding to each
PRS. This is unfiltered data so the crosses may exhibit significant movement. Filtering is
applied such that the new filtered measurement is equal to nine times the old filtered
measurements (Northings and Eastings) plus the new measurements, divided by ten.
This is the second stage of filtering. Filtered positions from this stage are displayed as
small circles on the display.
5 - 51
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
The third stage of filtering concerns the statistical mix of the two or more PRS enabled,
in order to provide the calculation of the vessel position. If, for example, three PRS are
engaged; then we look separately at Northings and Eastings. It may happen that the
HPR system is giving noisy returns and is close to the Variance Test reject limit. The
statistical mix calculation (for Northing only, for illustration) is as follows:
Thus, from Table 5.3, we can see that the noisy measurements from the HPR are not
affecting the final position, and that the position depends on measurements from both
DGPS inputs, with a bias toward the more accurate input.
When three or more PRS are deployed, a further rejection limit is set and displayed. This
is the Median Test Limit, and its radius is 6 meters. Its function is to generate rejection of
a jumping PRS measurement through majority voting, and is not affected by the Kalman
filtering.
If a single PRS is deployed then the first and second stage filtering will be carried out,
but all other noise in the measurements will be preserved in the positional calculation.
If two position references are deployed, one good and one poor, then it is possible for
the relative weightings to be 0.99 and 0.01. Under these circumstances the poor
reference will be frequently if not continually rejected. Another problem is that there is no
link between accuracy and reliability. It's possible that the "good" (reliable) PRS may
start to track-off giving inaccurate positioning information. At this point the DP system
knows only that the relative calibration is no longer correct, thus the system with the
lower weighting will be rejected in this case. Thus, with only two PRSs there is a danger
that an accurate PRS will be rejected while a poor or erroneous one will be retained and
used for positioning. This is a good argument for the use of three PRS in any operation
where positioning is vital or critical. It must be mentioned here that when using HPR
systems each system must be treated as a single PRS despite the number of
transponders used for redundancy purposes. This is because the system most likely
operates through a common transducer or transceivers. This will not be the case if two
separate and independent HPR systems are in use and there is no potential for a
common fault.
5 - 52
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
The DPO should use caution in his choice of position reference systems. For any
operations requiring system redundancy it is necessary to utilize three position
references. Two PRS are not adequate, since there will arise the question as to which
one has failed when contradictory reference data is received from the two systems.
Three systems will give more security against this possibility, especially if the DP system
is programmed to apply a PRS voting or median check.
Where three PRS are required, the DPO should choose systems which have differing
principles. This reduces the probability of Common-mode failure, where one event may
result in the failure of multiple references. Common-mode failure is more likely to occur
in situations where the choice of PRS has included two or more of the same type of
system.
5.4 THRUSTERS
Thrusters provide the forces and moments to counter the environment and hold the
vessel on station. Effective and reliable propulsion and thruster systems are central to
the efficient operation of DP vessels. One fundamental requirement in thruster design
and selection is to have minimal aeration and cavitation because these are major
sources of noise. Thruster noise can severely degrade the performance and reliability of
the acoustic position reference system. The thruster layout will vary ship-to-ship, and will
depend on many factors. The design and function of the vessel will affect the choice of
thruster type and layout, as will other factors such as draft, level of redundancy required,
type of power plant, and hull configuration.
Three types of thruster make up the majority of units found on DP vessels, with a small
selection of other types used in a minority of vessels.
The three types are:
Main propeller(s),
Tunnel thrusters, and
Azimuth thrusters.
A propeller generates thrust from the lift forces on the wing section of its blades. To
change the amount of thrust, one of two (or possibly both) variables can be altered,
either the pitch of the propeller or its speed. Controllable-Pitch (CP) propellers run at a
constant rotation speed (rpm) and vary their thruster output by changing the pitch of the
blades. Fixed-Pitch (FP) propellers on the other hand vary their thruster output by
changing their rotational speed. These two variations of thrust control can be applied to
any of the three thruster types mentioned above. Controllable-Pitch and Fixed-Pitch
systems will be discussed in further detail is sections 5.4.4 and 5.4.5 respectively.
5 - 53
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 54
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
One physical characteristic that must be kept in mind is that the effect of tunnel thrusters
is radically reduced if the vessel has more than about two knots headway or sternway.
The actual speed at which their efficiency is reduced varies from ship to ship. In some
vessels, it is possible to observe a slight but positive reverse thrust effect at certain
speeds. For this reason, vessels operating in a high current environment may
experience difficulties in maintaining heading control.
Effectiveness of tunnel thrusters also heavily depends on the length of the tunnel; the
longer the tunnel the less efficient the thruster. Tunnel thruster output may differ in each
direction. The design of a tunnel thruster will minimize this difference, but it is common to
find a tunnel thruster slightly more powerful in one direction than in the other.
5 - 55
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
Typically a DP drill ship, uses six azimuthing thrusters; three at the bow and three aft.
When underway on passage, these units provide the steering function, and are linked to
the autopilot.
5 - 56
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
In some semi-submersible rigs, azimuth thrusters may be fitted directly beneath the
pontoons; thus they are the deepest point of the vessel. This configuration is particularly
vulnerable to grounding damage, and every precaution must be taken to ensure this
does not occur. Some semi-submersible vessels have thrusters located on the upper
sides of the pontoons. This may be a safer arrangement when navigating in shallower
areas, but the thrusters are closer to the surface and therefore less effective due to the
greater potential for cavitation. In either configuration a semi-submersible will have a
minimum of four thrusters, one in each corner.
Another possible installation configuration is the canister-mounted thruster, in which the
whole unit including the drive motor, control units, shafts and propeller are built into a
cylindrical canister (Figure 5.34). The canister-mounted design provides the ability for
the canister to be retracted into the hull vertically or else pivoted into the hull in a
horizontal position. This facilitates repairs and servicing without the need for divers or
underwater work. The thrusters can also be retracted during transit mode to reduce
the amount of hydrodynamic drag on the hull.
5 - 57
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
It is normal for an azimuth thruster to have Ahead and Astern directions of operation.
The Ahead direction is the most efficient; the propeller blade design is optimized for this
direction, as is the nozzle design. This will also be the most advantageous direction
regarding the positioning of the propeller mountings and hub gearbox (these are
normally placed ahead of the propeller when operating in the "ahead" direction). When
operating in the reverse or "astern" direction the amount of thrust available drops off to
typically 60%. Thus it is normal for the DP system to operate these units in the "ahead"
direction at all times. However when maneuvering the vessel manually, the operator may
elect to reverse the direction of thrust for short periods as this is faster than rotating the
unit through 180. Some DP systems will force an azimuth thruster to rotate to operate in
the ahead mode. In others, if operating astern, when approx. 60% - 70% of reverse pitch
is reached, it will break away, rotate and operate in the ahead mode.
Note: This feature may be most disconcerting to the DPO if he is not expecting it!
DEAD ZONES
When multiple azimuth thrusters are fitted in close proximity to each other, it is
necessary to ensure that the exhaust wash from one thruster does not impinge on
another thruster. If this were to happen, the "downstream" thruster will become less
efficient and may overspeed and trip. In cases such as this the DP control software
must be programmed to prevent the thrusters from operating in these azimuth ranges
or dead zones.
5 - 58
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 59
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
C.P. propellers with an all-hydraulic hub, i.e. without spring loading, may fail in a number
of ways. The dynamic balance of the blades may allow them to remain at the set pitch
subsequent to a hydraulic failure, or the propeller may be specifically designed to fail "as
se t. D e p e n d in g o n th e sp e e d o f th e ve sse l a t th e tim e o f fa ilu re , th e p ro p e ller may well
return to zero pitch. DP vessels must have their C.P. propellers arranged to fail-safe to
zero pitch or as set upon loss of hydraulic pressure. This is not easily achieved, and this
failure mode is one that should be tested during the regular auditing of the vessel. Some
thruster manufacturers will arrange interlocks such that a hydraulic hub failure results in
an automatic trip or shutdown of that thruster.
Despite the above, it must be realized that C.P. propellers have a variety of failure
modes other than the result of a loss of hydraulic pressure. In view of this, the DPO
needs to monitor his propeller feedback closely, and if failure occurs, he must shut down
or trip that thruster immediately. It is possible for the wrong thruster to be shut down if
the DPO does not take extreme care in monitoring his instrumentation. An example of
what may happen is that, in a vessel with two bow tunnel thrusters, No 1 fails to full
pitch, thrusting to starboard. The DP system rapidly assesses the situation, including the
feedback thrust from No. 1, and correctly applies full thrust from No. 2, thrusting to port
in an attempt to compensate from the errant No. 1. The DPO looks at his system and
sees No. 1 thruster at maximum starboard thrust, and No. 2 at maximum port thrust. He
must carefully check his setpoint-feedback values on each of the two thrusters, together
with the alarms which have been generated, in order to come to the correct decision to
shut down No. 1 thruster.
5 - 60
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
Factor CPP VS
Drive Simple Complicated
Thrust 12.5T per 1000 hp 15T per 1000 hp
Acoustics Poor Good
Base Load 25% at zero pitch Zero at zero speed
Power Factor Poor at low load Good through range
Failure modes Difficult to totally prevent full Easier to prevent full thrust
pitch
CAPEX Least Most
OPEX Most Least
Table 5.4 Comparison of Thruster Types
Most DP systems working with azimuth thrusters will incorporate a Fixed Azimuth or
biasing function. In calm conditions, a DP vessel often hunts or oscillates continuously in
position. This is because the propulsion units are underutilized - having nothing to "push
a g a in st. In su ch circu m sta n ce s, it m a y b e p o ssib le to re d u ce th e n u m b e r o f th ru ste rs
enabled. A large semisubmersible may be configured with eight azimuth thrusters -
two at each corner, and in calm or light conditions may work with just four. Even so, it
may happen that these thrusters are azimuthing continuously, causing a lot of wear and
tear on the steering gear. Selecting Fixed Azimuth or setting up a bias will allow the
system to set one or more thrusters at a fixed azimuth so that the other thrusters can
work against this force while still compensating for environmental forces. This function
is also utilized to optimize the operation of the power generation plant and will be further
discussed in Section 5.
5 - 61
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 62
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 63
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 64
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 65
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 66
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
A simplified drawing of the power distribution system with some of the main loads are
shown in Figure 5.35.
DC Drilling DC Drilling
Motors Motors
480V Switchboard (aft) 480V Switchboard (aft) 480V Switchboard (aft) 480V Switchboard (aft)
EDG
Emergency
Aux Aux Aux Aux Aux Aux
Switchboard
Panel Panel Panel Panel Panel Panel
HPU1 Thruster HPU2 HPU1 Thruster HPU2 HPU1 Thruster HPU2 HPU1 Thruster HPU2 HPU1 Thruster HPU2 Thruster
#2 #1 #5 #4
HPU1 #6 HPU2
#3
5 - 67
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 68
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 69
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 70
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
In addition to controlling the number of generators online, the PMS also limits DP system
and Drilling power availability to prevent system overloads. The PMS calculates and
advises how much power may be consumed for drilling and stationkeeping. For these
calculations an additional safety factor is established by assuming the diesel generator
capacity to be 95% of the equipment design capacity. Thus, for these diesel generators
in question the "kW Available" will be calculated as if its actual capacity were 3975 kW,
providing a 200 kW cushion. For the Drilling SCRs the available power is calculated to
be the total online power capacity (95% Capacity Factor applied) less the vessel hotel
load, and less the thruster loads. The DP system is provided a power limit in a similar
fashion. It is allowed to use the total online power capacity (95% capacity factor applied)
less hotel load and a small reserve (normally 2MW) for drilling to use in an emergency.
This reserve power may be altered if deemed necessary. If additional power is
demanded beyond the calculated available power, the PMS will restrict this increase
until additional diesel generators have been brought online.
It is recognized that there may be instances where unexpected loss of an online
generator could cause the remaining generators to be loaded beyond their ability to
support the power system and therefore to trip off line, resulting in a blackout.
To preclude this result, the PMS system will take immediate actions in the event
of a generator loss:
1. Issue a signal to all the thruster drives on the affected bus to shut down for a
one second period, which is sufficient time for the DP system to respond to the
reduced power availability by throttling back the thruster commands to revised
DP power available levels.
2. Issue a start signal to another generator powering the same bus as the failed
generator, which will result in the available power being restored to its pre-fault
level in less than 60 seconds.
3. Reduce the DP and Drilling Power Available signals to reflect the reduced
online generating capacity.
The thrusters are equipped with a load ramp feature which minimizes the transient on
the electrical system following the one second shutdown of the thrusters. Power to the
effected thrusters will be gradually restored per a pre-set ramping function to prevent the
tripping of the remaining online diesel generators. The time used to bring the thrusters
back to existing levels gives the system the time needed to start and synchronize (place
online) a replacement generator.
There are four HV buses which can be connected together in a single bus configuration
or in a large number of ways, even to the point of having four independent power
systems on the vessel. The PMS should be designed to handle all these possible
configurations. To that end, the PMS function is on a per bus basis. Handling of faults
and power limiting is therefore separate for the four different buses. Accordingly, when
the Engineer separates a particular bus section for maintenance purposes it will still
have the same power protection as if it were part of the single bus configuration.
5 - 71
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
Note
Safe drilling operations will normally require the power generation
and distribution system to be operated in a split bus configuration.
This may result in additional main engines being online and may
result in increased fuel usage, but protects against a blackout
caused by catastrophic failure of a main switchboard.
5 - 72
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 73
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5.5.4 BLACKOUT
In order to prevent Blackouts, it is normal to split the switchboard system into two or
more parts, connected by means of bus tie switches. Blackouts may occur in two ways.
One way stems from the correct operation of the protection system on a faulty generator
causing this machine to trip. This causes the remaining healthy diesel generators to
operate in a transient fluctuating condition while attempting to return the system to
normal. These transient conditions may cause the healthy diesel generators to trip due
to operating conditions being outside acceptable limits.
The other cause of blackout conditions arises where the installed protection devices are
unable to discriminate, resulting in the trip of one or more healthy diesel generators
because of faults relating to a malfunctioning generator. In general, the greater the
amount of connected generating capacity, the lower is the risk of total blackout.
A major consideration is that of the open or closed status of the bus tie switches
A common failure mode occurs where a governor failure in one generator leads to a
disturbance in the load sharing. That machine takes an inordinate share of the total load,
and may lead to a reverse power situation arising with another generator. If there are
only two diesel generators onboard, a blackout situation may occur, as the generator
running on reverse power will shut down (if it is otherwise healthy) on reverse current
protection, while the generator suffering governor failure shuts down on overload.
Power shortages and blackout situations will result in severe consequences to the
operation. As discussed in the previous sections a number of lines of defenses exist to
ensure continuity of power supply to essential consumers. Without this backup it is
possible for a power problem to result in total loss of thrusters, with consequent drift-off
position. Subsequent to such a problem the vital factor is the time taken to restore power
to essential circuits and services. If this time is too great then a drift-off may escalate into
a major catastrophe. It is obvious that a total blackout is to be avoided, and a number of
measures are taken to ensure such an event does not occur. These measures include
the provision of redundancy into power systems where deemed necessary, and the
provision of power protection devices and power management systems.
5 - 74
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 75
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 76
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
The decision of whether to opt for Class 2 or Class 3 is a balanced decision based on
the cost of purchasing a system, plus the probability of having a physical failure and the
associated risks and potential costs. Generally, as the economic consequences of a loss
of position increases, so does the level of hardware redundancy installed. It should be
noted, however, that Class 3 involves much greater complexity and some question if it
really provides greater reliability. The majority of modern, new-build MODUS have Class
3 systems while the earlier generation vessels had Class 2 systems (Table 5.5).
5 - 77
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 78
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5.7 OPERATIONS
The need to rapidly disconnect the riser from the BOP stack also imposes some special
requirements.
1. In deepwater, a multiplex BOP control system is required to both reduce time
to execute necessary controls in an emergency and to avoid large umbilicals
that are difficult to handle.
2. the need for quick disconnect requires guidelineless operation and results in
modified designs for the guide base, lower marine riser package, and BOP
stack. Also, sophisticated acoustic systems and/or TV systems are required
for reentry operations.
A well designed data recording system is required to record all of the critical data
continuously and provide the relevant information for a post-event analysis. During an
emergency situation, the operating personnel would be very busy in handling the
emergency and in restoring control of the vessel. The operator would not have time to
accurately record the details of the event which are usually very important for the post-
event analysis. This analysis is necessary to diagnose the causes of the event so that
corrective actions can be taken. This data logging system can also provide a continuous
system performance monitoring capability which is very useful for the system
maintenance and during system performance evaluations.
Daily engineering records of all the critical parameters of the drilling operations, including
stationkeeping, are also useful for maintaining a close surveillance of the operating
conditions. This helps identify any degrading equipment or system performance under
certain operating conditions. These daily records are also useful for post-event analysis
as well as documentation of the drilling operation.
5 - 79
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
These plots are of great use operationally as well, and being theoretical plots, they are
modified in the light of actual experience. Modern DP control systems include some
form of online capability predictor for both present and future conditions. This allows
the operator to not only monitor the prevailing situation, but also investigate some
what if scenarios.
5 - 80
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 81
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 82
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 83
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 84
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5.8.3 ENVIRONMENT
Drive-off & Drift-off analyses will be performed by URC for both the 95%
non-exceedance and one year return period environment. Typically the
95% non-exceedance environment will provide larger operating circles yet
the probability of exceeding this environmental criteria is more likely. The one year
return period environment, on the other hand, is more conservative, yet in some
instances, the watch circles will be operationally too restrictive.
5.8.4 CRITERIA
As the rig moves off location, due to either a malfunction in the DP system (drive-off) or
a loss of power (drift-off), the riser will lean placing angles in the flex joints while the slip
joint & tensioners will stoke out to accommodate the longer distance between the rig and
the wellhead. The Drive-off/Drift-off Analysis determines how each of these components
will behave with vessel offset. The goal is to establish which of these components
reaches its operating limit first and at what corresponding vessel offset.
Table 5.6 lists the component limiting criteria used in the example.
Item Criteria
Lower Flex Joint Angle Degrees 8
Upper Flex Joint Angle Degrees 8
Slip Joint Stroke Ft (65-ft maximum stroke) 30
Riser Tensioner Stroke (65 ft Maximum stroke) 30
Table 5.6 Limiting Criteria for Glomar Jack Ryan
The limits are rig specific. The limits included in Table 5.6 where used for the Dynamine
well drilled in 3300 ft of water in Trinidad with the Glomar Jack Ryan drillship and are for
p u rp o se s o f illu stra tin g th e d rive o ff/d rift o ff m e th o d o lo g y.
5 - 85
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
5 - 86
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
15 0
Offset (%) & Angles (degrees)
10 15
Stroke (feet)
5 30
0 45
-5 60
0 50 100 150 200 250 300
Time (seconds)
5 - 87
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
15 0
Offset (%) & Angles (degrees)
10 15
Flex Joint Angle Limit
Stroke (feet)
5 30
0 45
Required
Disconnect
Time
-5 60
0 50 100 150 200 250 300
Time (seconds)
Figure 5.39 Drift Off Analysis Results with LFJ
Limit
The riser and LMRP should be lifting off of the BOP at or before the time when the lower
flex joint angle reaches its limit. This sets the required disconnect time. Failure to
disconnect at or before this time would result in damage to the LFJ or other riser
components. The emergency disconnect sequence typically requires 45-60 seconds to
complete a series of functions before the command is given to unlatch the LMRP
connector. This sequence of functions is discussed in more detail in Section 12.
5 - 88
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
DYNAMIC POSITIONING
As shown in Figure 5.40, the EDS is assumed to take 45 seconds, and this amount of
time is subtracted from the required disconnect time. Therefore the EDS must be
initiated no later than 200 seconds after the start of the drift-off incident. This
corresponds to a vessel offset of 7.9% WD, which establishes the maximum setting point
for the red watch circle.
The yellow watch circle is established by subtracting an additional 60 seconds which is
the time needed by the driller to hang-off the drill pipe before the EDS can be initiated.
As shown in Figure 5.40 the maximum setting for the "yellow" watch circle for the drift-
off case is 4.3% WD.
15 0
Offset (%) & Angles (degrees)
10 15
Stroke (feet)
5 30
0 45
Required
60 sec for 45 sec Disconnect
Driller hangoff for EDS Time
-5 60
0 50 100 150 200 250 300
Time (seconds)
5.9 REFERENCES
Dynamic Positioning, David Bray, Oilfield Publications Limited, April 2000
5 - 89
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6
Section
OBJECTIVES
On completion of this section, you will be able to:
State the major functions of a mooring system for a mobile offshore drilling unit.
State the advantages and disadvantages of all-wire, all-chain, and chain/wire rope
combinations.
State maximum line tension and approximate offset criteria for drilling and standby
conditions.
State the basis for establishing the anchor test pull tension.
6-1
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
CONTENTS PAGE
6-2
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6-3
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6.1 INTRODUCTION
Stationkeeping, or the ability of a vessel to hold position against the effects of the
environment, either using moorings or Dynamic Positioning (DP), is a critical part of the
drilling operation. The state-of-the-art in stationkeeping technology has advanced
considerably in recent years. Deepwater, ten years ago, was considered about 3,000 ft.
In 2001, exploration drilling was conducted from a DP vessel in nearly 10,000-ft of water and
from a moored vessel in 9,000 ft of water.
This chapter focuses on the basics of spread mooring systems. Topics include how a
mooring system works, mooring analysis, and information on mooring hardware. Mooring
system operation and installation will also be covered in this section.
6-4
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6-5
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Semisubmersibles spread moorings for up to about 5,000 ft water depth and either DP
or special preset moorings in greater water depths. All vessels used for long-term production
operations are moored, and the majority of vessels used for development drilling tend to
be moored.
For the purpose of this section, only multi-point non-weathervaning spread moorings are
addressed. DP systems are discussed in Section 5.0.
6-6
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6-7
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
A secondary mooring system function is to allow adjustment of the horizontal position of the
vessel, through manipulation of the mooring lines. Adjustment may be necessary to
counteract offsets due to weather and enable drilling, workover or well maintenance
operations to be continued (e.g., in loop current conditions). In certain applications, this
horizontal movement will also allow operations to be continued in extreme conditions.
Horizontal vessel movements are also used when handling heavy loads as a risk mitigation
should the load be dropped.
The offset limits specified for a particular vessel mooring will largely depend on the function it
will perform and/or the limiting weather conditions in which the function must be performed.
With vessels engaged in drilling, the drilling riser design generally governs how far the vessel
can offset before causing operational problems or overstressing the ball/flex joint. Design
offset limits are usually somewhere between 2% and 4% of water depth while drilling and
between 8% and 10% with the riser connected in a non-rotating mode.
Each mooring line exerts a horizontal and vertical load on the vessel. The sum of the
horizontal tensions counteracts the environmental loads on the vessel. The tension in each
mooring line is established through a combination of the horizontal forces (mean
environmental loads) to which the rig is being subjected and the mooring component weight
(chain and/wire) suspended off the seafloor plus any vertical forces at the seafloor (vertical
component). When a rig is first moored on location, an initial tension is imposed on the
mooring legs to set the anchors. This tension is known as the test load tension. After all the
anchors are test loaded, the tension in the mooring lines is reduced to an operating tension
or pretension. The greater the pretension, the more suspended line will be picked up off the
seafloor. Higher pretensions tend to make the mooring system stiffer, i.e. restoring forces
increase faster with offset.
Obviously, the tension on the windward mooring system legs (the legs facing toward the
direction of the prevailing environment) will be greater than that imposed on the leeward
legs (the legs directed away from the environment). The amount of tension in the windward
legs is also impacted by the tension in the leeward legs since tension in the windward legs
has to offset the tension in the leeward legs. This is why operating tensions in the leeward
mooring legs are often reduced in storm or high current conditions, plus slackening leeward
lines also reduce vessel offset. If a rig is abandoned due to the approach of a storm, tensions
are often reduced in all legs for the same reason.
The performance of a mooring system is impacted by the stiffness of each leg. Stiffness of a
mooring leg is a function of mooring line equipment, geometry, pretension, and mooring line
elasticity. Stiffness can be defined as the tangential slope of a restoring force curve at a given
rig offset. This curve is known as the Load Excursion Curve. An example of a Load
Excursion Curve is shown in Figure 6.3, showing the restoring force of a single mooring leg
(Line No. 5) with the environment directed toward the rig at 245 related to true North. It also
shows the restoring force of the combined mooring system (solid line). Figure 6.4 shows a
plan view of the mooring pattern for the particular rig in question explaining the location of line
No.5 and the direction of the environment (in the quartering direction).
Before a detailed look at the environmental loads on the mooring system can be made, a
description of the components of this system should be discussed. The following section
gives an overview of the elements that make up the mooring system.
6-8
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Load / Vessel Excursion
1000
Mooring Line #5
Total System Restoring Force
Stiffness: Slope of Tangent Line
800 Mooring Stiffness = 2200 lbs/ft
600
400
200
0
0 50 100 150 200 250 300 350
6-9
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Winch/Windlass
s
Waterline
Fairlead
Mooring Wire
Suspended Length
Anchor / Chain
Chain / Wire Connection
X-Over Connection
Grounded Chain
Mud Line
Chain Touchdown Point Drag Embedment Anchor
The basic elements can be split into two major categories, as follows:
6 - 10
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 11
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Drive Linkage to
second Windlass
Hydro Dynamic Brake
6 - 12
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
WINCH
A winch is designed to provide a means for spooling and storing line. Although the sizes and
types of winches vary, their basic design and function are similar. The winch drum can
support multiple sizes of wire rope. Therefore, if the wire rope is changed to an alternate size
than was originally used, the drum will not need to be modified. However, the level winding
sheave may need upgrading. The draw back to a single drum winch is that as the number of
wire wraps increases on the drum, the maximum line tension capability decreases (see
Figure 6.15). W ire rope sizes range from 2 to 3 -1/2. T he m aximum length is limited by the
drum size. The lengths range from 3,000 - 6,000-ft. The winch has a brake holding powers
from 830,000 - 300,000-lbs and a stall-pull of 700,000 - 320,000 lbs. Figures 6.9 and 6.10
illustrate the winch system.
6 - 13
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 14
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
COMBINATION WINCH/WINDLASS
On deepwater rigs, a combination dual drum traction winch with storage reels is often used.
The combination wire/chain system is built into a combined unit for each leg. Some of the
more modern rigs sometimes include wire winches and/or storage reels in the lower hull to
reduce deck load. The wire is directed from the lower hull location to the deck level, via
sheaves. Figures 6.11, 6.12, and 6.13 illustrate a dual traction winch/windlass combination,
notice that the two are coupled together with a single drive train. On the combination system,
the chain and wire sizes, wire length, and line pull capabilities are the same as the
conventional system. The traction winch can handle up to 3-7/5" wire rope and since it
utilizes a storage reel, lengths in excess of 10,000-ft are common. An another important
feature of the traction winch is its ability to provide constant pull since the wire is always on
the bottom wrap.
Wire or chain tension measuring devices generally employ strain gauges, load cells, or
amp/load conversion tables. Load cells or stain gauges are typically located under the
winch/windlass frame. The tension reading for the winch/windlass can be converted from the
amps applied the motor in order to initiate motion. See Figure 6.14. These systems should
be calibrated before running anchors.
Winch/Windlass #1
Winch/Windlass #2
Storage Reel #1
Storage Reel #2
6 - 15
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Drive Train
Storage Reel
Figure 6.12 - Close-up Picture of Combination System
6 - 16
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
800
500
Tension, Kips
400
300
200
100
0
0 200 400 600 800 1000 1200 1400 1600
AMPS
Figure 6.14 Figure 6.14 Load vs Amp Chart for Traction Winch
@ maximum torque
6 - 17
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Chain Lockers - These are chain storage compartments usually mounted within the lower
part of the columns or underdeck.
Chain Stoppers: Stopper is designed to Chain Windlass Pawl
take the full load of the mooring line and
thus direct the load off the windlass. The
stoppers are separate from the windlass
and are either a set of hydraulic rams or
steel plate. With the stopper engaged,
routine maintenance of the windlass can
be safely performed.
Pawl: The pawl is a mechanical break
that is part of the winch or windlass,
usually located on the outer rim of the
drum. The pawl is designed to take the
full load of the mooring line and is a
back up to the drum brake (Figures
6.16 and 6.17). Figure 6.16
P aw l U n en gaged
6 - 18
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
column
fairlead
angle
= 37
bolster
pontoon
Figure 6.19 - Chain Fairlead and Fairlead/Bolster Angle
6 - 19
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Permanent Chain Chasers (PCCs) - PCCs are devices used during anchor deployment and
recovery, normally stored or secured to the rig when the rig is moored. The PCC consists of a
chase collar, 10 to 20 ft of chain, and 90 to 100 ft of wire rope. The chain from the anchor
runs through the chase collar, therefore the ID of the collar should be large enough to pass
any connecting links or swivels (Figure 6.20).
Anchor Shank
Anchor Shackle
Pendant Lines: Pendant lines were used on the first moored MODUs to set and recover the
anchors. They were similar to the PPC device except that once the anchor had been set, the
pendant line would be connected to a buoy and left at the anchor location. This worked well
in shallow water. Currently, few rigs are outfitted with pendant lines, and most have gone to
the PCC instead.
6 - 20
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Tri-Link This connection is used in a wire/chain system and enables the last section of
chain to be connected to the first section of wire (Figure 6.21). The operational
procedure for making this crossover is in Section 6.8.2.
Windlass Winch
Winch Side
Windlass Side
Tri-Link
Crossover
Platform Chain / Wire Connector
Tri-Link
Fairlead
Figure 6.21
6 - 21
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Connectors: There are basically five types of connectors used in the mooring line:
1. Shackle: It consists of a bow, which is closed by a pin. A shackle is typically used to
connect the shank of the anchor to the mooring chain.
2. C o n n e ctin g lin k K e n te r typ e : T h e co n n e ctin g lin k ke n te r typ e is m o st co m m o n ly
used for the connection two pieces of chain mooring line, where the terminations of
the two pieces have the same dimensions (i.e. the 2 eyes of the link are the same
size). The kenter links have a shorter fatigue life that the chain.
3. C o n n e ctin g lin k C typ e : L ike th e ke n te r lin k, th e C lin k is u se d fo r th e co n n e c tion of
two pieces of mooring line with terminations that have the same dimensions. The
main difference between the kenter and C link is the way that the connector is
opened and closed. The C-link is also easier to disassemble than the Kenter link
4. Connectin g lin k P e a r sh a p e d : T h e p e a r sh a p e d lin k is u se d fo r th e co n n e ctio n o f tw o
pieces of mooring line with terminations that have different dimensions.
5. Swivels: A swivel is used to relieve the twist and torque that builds up in the mooring
line and is important in a chain/wire combination system due to the torque in the wire
under high tension. The swivel is often placed a few links from the anchor point
and/or between the chain-wire crossover point. Under heavy loads, conventional
swivels may not be able to rotate, thus allowing the torque to twist or knot the chain.
Newly designed swivels are able to function under heavy loads due to a special
bearing surfaces inside the swivel that reduces the friction.
Spring Buoy: Spring Buoys are surface or subsurface buoys that are connected to a
catenary mooring line. In deepwater, they help reduce the weight of the mooring lines.
They also reduce the effects of line dynamics in deepwater (dampen reactionary forces).
They can also be used to hold up the mooring line if it crosses over pipelines or other
subsea equipment.
Piggy-Back: Is the practice of using two or more anchors in order to obtain holding
power greater than can be achieved with one only. Typically, the PCC wire from the first
or lead anchor is used to set the second or outboard anchor.
The mooring leg components will be discussed in detail in the Section 7.
6 - 22
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Anchor Type Fluke area, fluke angle, fluke shape, anchor weight, tripping palms,
stabilizer bars, etc. Figure 6.22 shows components of a modern DEA.
Behavior During and After Deployment Opening of the flukes, penetration of the
flukes, depth of burial of the anchor, stability of the anchor during dragging, soil
behavior over the fluke.
6 - 23
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 24
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
D ue to the w ide variation of im pacting factors, the prediction of an anchors holding pow er is
difficult. Exact holding power can only be determined after the anchor is deployed and test
loaded.
Anchor performance data for the specific anchor type and soil condition should be obtained if
possible. In the absence of credible anchor performance data, Figure 6.26 and 6.27 may be
used to estimate the holding power of anchors commonly used to moor floating vessels.
Figures 6.26 and 6.27 are reproduced from Techdata sheet 83-08R except that the holding
capacity curves for the Moorfast (or Offdrill II) and Stevpris anchor were upgraded. The
upgrading of these two curves was based on model and field experience acquired in recent
years. The design curves presented in these two figures represents in general the lower
bounds of the test data. The tests used to develop the curves were performed at a limited
number of sites. As a result, the curves are for use in generic soil types such as soft clay and
sand. Recent studies indicate, however, that several parameters such as soil strength profile,
lead line type (wire rope versus chain), cyclic loading, and anchor soaking may significantly
influence anchor performance in soft clay. In addition, some high efficiency anchors have
demonstrated substantial resistance to vertical load in soft clay. Furthermore, there are new
version of high efficiency anchors that are not covered by these two figures. These issues are
addressed in Appendix B of API RP 2SK.
Note: The holding capacity curves in Figures 6.26 and 6.27 do not include a safety factor.
The allowable safety factors for anchor loads are substantially lower than those for line
tensions. The rationale is to have the anchor moved instead of the mooring line broken in the
event of mooring overload. Anchor movements of the most loaded lines would normally
cause favorable redistribution of the mooring loads among the mooring lines resulting in
lower line tensions and anchor loads for these lines. This would help the mooring system
survive storm environments exceeding the maximum design environment.
6 - 25
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
DEAs have been used as long as people have sailed the seas. Many types have existed over
the years. Today there are two categories used by vessels:
1. Fixed fluke types.
2. Adjustable fluke types.
Figure 6.25 overviews of the DEAs commonly manufactured until the 1980s. Several of
these are still in use, e.g. Moorfast, Offdrill II, Bruce TS, Flipper Delta. Fixed fluke types were
developed specifically for drilling and construction operations where ultra-high holding
capacity is important. Until about 1970, the majority of DEAs were constructed from cast
steel. Currently, the fixed fluke, twin shank types are all fabricated from plate steel, reducing
weight per fluke area and making the anchors much more efficient.
6 - 26
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 27
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 28
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Industry standards for the design of mooring systems (API RP 2SK) allow an angle of 5 at
the seafloor in the intact line condition and 10 in the damaged line condition for Deep
Embedment Anchors.
The majority of DEAs have the ability to adjust the fluke angle in different soil types. Figure
6.28 shows an explanation of fluke adjustment on the modern DEA (Bruce flat-fluke type).
6 - 29
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 30
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 31
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Figure 6.31 & 6.32 - Chain Manufacturing - Stud Insertion & Flash Butt Weld Grinding
6 - 32
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
CHAIN GRADES
Until the 1960s, studlink chain had been provided for ship anchor chain using Grade 1 and 2
steel bar stock, based on the amount of strength in the chain required. The U.S. Navy
required higher strength chain, and a Grade 3 was introduced. Baldt, a supplier of chain to
the U.S. Navy, also introduced a di-lock type that had higher strength than Grade 3. Offshore
drilling required chain with greater strength than Grade 3. Due to capacity problems at Baldt,
two chain manufacturers in Sweden (Ramnas and Lujsnes) were approached to make high
strength chain as an alternative to the di-lock. This heralded the introduction of Oil Rig Quality
(ORQ) chain that was specifically intended for use by MODUs. API introduced a standard for
the manufacture of the ORQ chain (API RP 2F). Other chain manufacturers (Vicinay,
Hamanka, Nippon) also developed the capability to make ORQ chain.
In the early 1980s, all the chain manufacturers developed a still higher strength chain initially
known as Grade 4 (or K4), which was about 25% stronger than ORQ chain. Due to
manufacturing problems (mostly during heat treatment), all the chain manufacturers
experienced K4 chain failures between 1982 and 1984. In 1985, the Norwegian Classification
Society, DNV, introduced a new chain specification (Specification for Offshore Chain C.N 2.6)
that dealt with the manufacturing and quality control aspects of high strength chain, including
bar stock supply. This specification introduced the NV K3 and NV K4 (rig) grades. The
American Bureau of Shipping (ABS) followed with their own specification (Guide for
Certification of Offshore Chain) that introduced RQ 3 and RQ 4 Grades (similar to NVK 3 and
NVK 4). In 1993, a new document was introduced by the International Association of
Classification Societies (IACS) known as W.22. This document, updated in 1999, is the main
guide for chain manufacture and quality control today. All the classification societies now
have similar documents.
Since the introduction of the NVK and RQ chain grades, there have been only a few failures
of the higher strength grades, mainly because of localized fatigue problems.
The breaking strength for various sizes and grades of mooring chain are listed in Table 6.1
6 - 33
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Diameter Dimensions Air Weight (lbs/ft) Water Weight (lbs/ft) B re a kin g T e st L o a d B T L (kip s)
(in) Length (in) Width (in) Stud Studless Stud Studless ORQ ORQ + 20% Grade 4
2 12.0 7.2 38 35 33.0 30.4 489 587 635
2 3/16 13.1 7.9 45 42 39.1 36.5 579 695 752
2 1/4 13.5 8.1 48 44 41.7 38.3 611 733 793
2 5/16 13.9 8.3 51 46 44.3 40.0 643 772 835
2 3/8 14.3 8.6 54 49 46.9 42.6 676 811 878
2 1/2 15.0 9.0 59 54 51.3 46.9 744 893 967
2 5/8 15.8 9.5 65 60 56.5 52.2 815 978 1,059
2 11/16 16.1 9.7 69 63 60.0 54.8 852 1,022 1,106
2 3/4 16.5 9.9 72 66 62.6 57.4 889 1,067 1,154
2 7/8 17.3 10.4 79 72 68.7 62.6 965 1,158 1,253
3 18.0 10.8 86 78 74.8 67.8 1,044 1,253 1,356
3 1/16 18.4 11.0 89 81 77.4 70.4 1,084 1,301 1,408
3 1/8 18.8 11.3 93 85 80.9 73.9 1,125 1,350 1,461
3 3/16 19.1 11.5 97 88 84.3 76.5 1,167 1,400 1,515
3 1/4 19.5 11.7 100 92 86.9 80.0 1,209 1,451 1,570
3 5/16 19.9 11.9 104 95 90.4 82.6 1,251 1,501 1,625
3 3/8 20.3 12.2 108 99 93.9 86.1 1,295 1,554 1,681
3 1/2 21.0 12.6 116 106 100.9 92.2 1,383 1,660 1,796
3 9/16 21.4 12.8 121 110 105.2 95.6 1,428 1,714 1,854
3 5/8 21.8 13.1 125 114 108.7 99.1 1,473 1,768 1,913
3 3/4 22.5 13.5 134 122 116.5 106.1 1,566 1,879 2,033
3 7/8 23.3 14.0 143 130 124.3 113.0 1,660 1,992 2,156
3 15/16 23.6 14.2 147 135 127.8 117.4 1,708 2,050 2,218
4 24.0 14.4 152 139 132.1 120.8 1,756 2,107 2,281
4 1/8 24.8 14.9 162 148 140.8 128.7 1,855 2,226 2,408
4 1/4 25.5 15.3 172 157 149.5 136.5 1,955 2,346 2,538
4 3/8 26.3 15.8 182 166 158.2 144.3 2,057 2,468 2,671
4 1/2 27.0 16.2 192 176 166.9 153.0 2,160 2,592 2,805
4 5/8 27.8 16.7 203 186 176.5 161.7 2,265 2,718 2,941
4 3/4 28.5 17.1 214 196 186.1 170.4 2,372 2,846 3,080
4 7/8 29.3 17.6 226 206 196.5 179.1 2,480 2,976 3,220
5 30.0 18.0 238 217 206.9 188.7 2,589 3,107 3,362
Note: In the absence of more accurate data, the following approximations can be used:
Let D = Nominal diameter of chain in inches
6 - 34
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
CHAIN FAILURE
A major problem with studlink chain is that the studs can work loose. If this happens, the
studs may fall out. With Chain Grades 1 to 3, it was common practice to weld the studs
during the manufacturing process (usually prior to heat treatment). With the higher strength
chains, stud welding has been found to cause premature cracking and fatigue failures at the
weld zones. A new type of oversized stud was introduced that eliminated the need for stud
welding (see Figure 6.30). Drilling contractors did not like the unwelded studs since it was
necessary for the chain to be periodically sent back to the factory to hydraulically re-affix the
studs (with the associated cost and operating problems). For this reason, a chain grade was
specified by some drilling contractors that fell somewhere between ORQ and K4 in strength
(ORQ +10% and ORQ +20%). The theoretical reason for these new grades was to allow the
studs to be welded while still utilizing a higher strength material. This approach has not been
totally accepted by the classification societies. At least one chain manufacturer (Ramnas) has
developed an asymmetrical stud and a means to insert these studs into the chain link under
tension to minimize the extent of chain stud loosening.
Another issue with mooring operations using chain, especially where combination wire/chain
systems are specified, is the question of torque. Six-strand wire commonly used in floating
drilling rig mooring operations (see Section 5.5.6) generates substantial torque under tension
changes. Chain has a natural tendency to freely rotate (about 3 a link) without any
resistance at all (acting very much like a free swivel). Once all the free rotation has been
taken up, the chain acts very much like a bar of steel and resists further rotation. Further
enforced rotation will cause the chain to knot and tangle. For this reason, swivels are used
between the chain/anchor and chain/wire connections.
6 - 35
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 36
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Like chain, wire rope is fabricated from steel with different grades based on required tensile
strengths. The most commonly used grades in the offshore drilling industry are Extra
Improved Plow Steel (EIPS) and Extra Extra Improved Plow Steel (EEIPS). Another issue
concerning wire rope for floating drilling rig operations is that the type of lubricant Wire ropes
used in MODU mooring systems is usually changed out every five to eight years, depending
on usage, the type of mooring equipment and the amount of wear and tear. For MODU
operations, no elaborate lubricants are used (generally petroleum based only) and only
standard galvanization is employed for corrosion protection.
All types of six strand wire rope generate torque when placed under tension. As the tension in
the wire changes, so do the torque characteristics. When used in combination with chain, a
swivel is often placed between the connection of the chain and wire to minimize the amount
of twisting transferred into the chain. While the swivel will alleviate some of the twist transfer
problems, over time, its use has been found to cause the wire rope to unlay and reduce the
fatigue life of the wire rope. The whole question of torque and the design and use of swivels
used in this application is not completely understood at present, therefore, it is not discussed
further in this section, but an overview of swivels is given in Section 6.5.7.
Spiral strand wire rope is often used for floating production applications. In these applications,
longevity is more critical than easy handling, since the rope will only be handled during the
initial installation. Spiral strand is similar to a bridge strand parallel lay construction with a
slight helix angle introduced into the strands. Spiral strand can be manufactured to be torque
balanced so that it does not introduce any torque when tensioned. Therefore, it can be
connected to chain with no twisting problems. Spiral strand has a longer fatigue life than six
strand wire, but it has to be handled very carefully to prevent damage during installation. It
can never be used in conjunction with or while connected to six strand wire or it will be
severely damaged. Generally speaking, spiral strand is not used around fairleads, unless a
very large diameter sheave or roller is used in the fairlead or a large radius bending shoe is
employed.
The breaking strength for various sizes and grades of wire rope are listed in Table 6.2.
6 - 37
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Note: In the absence of more accurate data, the following approximations can be used:
Let D = Nominal diameter of wire in inches
6 - 38
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 39
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 40
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 41
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 42
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 43
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Figure 6.41 - Comparison of Socket Designs for Spiral Strand & 6 Strand Wire Rope
6 - 44
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
To put a spelter socket on the end of a wire rope, the wire is inserted through a hole in the
base of the socket, unwound, and carefully cleaned. Either lead, lead/zinc alloy, or resin is
applied to seal and affix the opened w ires w ithin the socket body. T his form s a plug that
essentially prevents the wire from being pulled. The socketing process for MODUs can be
performed in the field by experienced personnel. For large permanent moorings, the process
is complicated and should be performed in a controlled environment (Figure 6.42).
Figure 6.42 - Proper Method to Clean Wire Strands for Resin Socket
Sockets can be either open or closed in configuration (Figure 6.45). Their length and size will
largely depend on the type of wire and application for which it is being used (e.g., permanent
or temporary moorings). The ratio of socketed wire section length and wire diameter is about
6.8 for 6 strand wire rope. Note that the spiral strand socket is considerable longer than the 6
strand socket. Due to the lower flexibility of the wire, the socket used for spiral strand is
normally fitted with an additional flex relief boot to minimize stress concentrations at the
wire/socket interface.
6 - 45
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Forged, closed spelter sockets are the preferred choice for MODU moorings. Currently
practically all contractors use an extra-heavy duty type (often referred to P eew ee or
G oldnose). Figure 6.43 shows a close-up photo of this socket type. The preferred method
for connecting to sections of mooring w ire is to em ploy either a K enter or C connecting link
as noted in Figure 6.44. The main reason for the chain connecting link being used in this
application is to minimize or prevent damage to the mooring wires when the connection is
spooled on AHV winch drums during installation and recovery. If the wire is spooled on top of
a connection that uses other hardware types, the sharp edges will damage and cut the wire.
Wires are also sometimes connected using a closed socket with the bow fed directly into an
open socket (Figure 6.45). This type connection is mainly used with tow wires, rather than
with MODU mooring systems.
Figure 6.43 - Examples of Lowery "Peewee" Extra Heavy Duty Closed Socket Being Used in the Field
6 - 46
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Figure 6.44 - Spelter Heavy Duty "Peewee" Socket connected using "C" Connecting Link
6 - 47
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
D C O N N E C T IN G S H A C K LES
V arious D connecting shackles are available for use as connectors in mooring systems.
Figure 6.46 shows examples of bolt-type shackles (used when connecting mooring
sections). The means for securing the shackle pins varies with the application. Some
examples of securing mechanisms include a threaded pin and nut (with stainless steel
cotter securing pin), a stainless steel locking taper pin, a bolted horseshoe clip, or even
tack welding. If welding is used, the effect of the heat on the shackle base metal has
to be considered.
6 - 48
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
W ide body shackles (Figure 6.47) are sometimes used during mooring installations where
soft eye installation slings or grommets are required during the release of a mooring line over
the stern roller of an AHV.
6 - 49
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
SWIVELS
Swivels are often used to connect a chain and anchor or with combination wire/chain
systems between the wire and chain sections. Conventional 6-strand wire rope construction
produces high torque under tension, and the swivels are designed to minimize the transfer of
torque from the wire into the chain. Examples of swivels commonly used in mooring systems
are shown in Figure 6.48. The photo in Figure 6.49 shows the attachment of a swivel to an
anchor. It should be noted that the sw ivelis connected through a D shackle in this case,
which eliminates side loading on the ears of the swivel.
Figure 6.48 - Example of a Mooring Swivel Connected to Anchor with "D" Shackle
6 - 50
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Figure 6.49 - Photo of Mooring Swivel Connected to Anchor with a "D" Shackle
6 - 51
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
API Spec. 2F
6 - 52
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Requirements and specifications of synthetic ropes, such as nylon and polyester, should
be determined by a mooring analysis. They should not be used in operations that require
frequent deployment and retrieval of the rope.
PCC or Pendant lines should consist of chain, wire rope, and connecting hardware.
Synthetic ropes are not acceptable.
Buoys should be constructed from steel or synthetic material. Surface buoys (pendant or
mid-line) should be sized for no more than 40% submerged. They should incorporate
measures such as compartmentalizing or foam filling to minimize the risk of sinking in
case of buoy damage. Sub-surface mid-line buoys should be rated for use at the
required depth of operation identified in the mooring analysis.
Sufficient mooring line should be left on the mobile offshore unit to permit moving the
unit 300 ft off-station in any direction in case of emergency.
6 - 53
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 54
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 55
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Table 6.3 - Mooring System Applications And Pertinent Factors Of The Systems.
As you can see from Table 6.3, mooring systems can be divided into three categories:
All wire rope systems
All chain systems
And a chain/wire rope combinations (this would include inserts like polyester)
The advantages and limitation of each system are discussed below.
6 - 56
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
In this system, the chain is outboard between the anchor and the wire rope. By proper
selection of the lengths of chain and wire rope, a combination system offers the advantages
of low operating tension requirements, high restoring force, added anchor holding capacity,
and good resistance to bottom abrasion. These advantages make it the best system for
deepwater operations. Anchor deployment and retrieval are generally more time consuming
with a combination system since a crossover must be made to connect the chain to wire.
Combination line systems can either use a combination winch/windlass or the chain/wire can
be inserted into the mooring leg via the AHV. For instance if a rig only has an all wire system
and winch, the AHV can insert chain between the anchor and the outboard end of the wire
rope. If a rig only has a chain and windlass system, the AHV can insert wire rope into the
mooring leg somewhere in the suspended section of chain. The wire would cross back over
to chain on the outboard side of the fairleader. See Section 6.12.2 for more explanation of the
wire insert process.
6 - 57
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 58
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 59
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Tension at
winch / windlass
6 - 60
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
d = (Th / W) (Cosh(WX/Th)-1)
S = (Th / W) Sinh(WX/Th)
6 - 61
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 62
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
In the US, according to accepted industry standards (API RP 2SK Recommended Practice
for Design and Analysis of Stationkeeping Systems for Floating Structures), the design
criteria selected for a permanent mooring system in survival conditions is recommended to be
a 100 year return period storm. For a MODU, a five-year return period storm can be used if
the vessel is to be moored away from other structures, and a ten-year storm should be used
if it will be moored close to other structures. To understand the magnitude of load difference,
Table 6.4 shows a comparison of environmental loads for the fifth generation MODU Ocean
Confidence. This rig was chosen because it represents the type of vessel that might be
employed for deepwater drilling, as well as production operations.
6 - 63
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Another major difference between the two mooring types is the method used in analyzing and
designing the systems. For a temporary drilling mooring, API RP 2SK recommends a quasi-
static analysis since the effects of line dynamics are accommodated through the use of
relatively conservative safety factors. The document also recommends a more rigorous
dynamic analysis be used for the final design of a permanent mooring system, while safety
factors may be relaxed to reflect that some uncertainty in line tension prediction is removed.
The more stringent design criteria results in components of a permanent mooring being
considerably larger than a temporary mooring. For instance, the required chain size for the
Ocean Confidence, when engaged in exploration drilling, is three inch K4 Grade, with a
weight per ft in air of 90 lbs. For a permanent mooring the required chain size would be in
excess of five inch K4 grade, with a weight per foot in air of 238 lbs. All other mooring
component sizes are increased as well; meaning the overall component weight in a
permanent mooring system will be more than double that of a temporary system.
The impact on the method and cost of the installation of a production vessel mooring
system will be considerable.
A different philosophy exists between permanent and temporary moorings with regard to
mooring component inspection and maintenance. Mooring components for drilling and
construction operations can be readily inspected after being recovered between wells when
they are out of the water. It is important to replace components in these temporary systems
on a regular schedule as necessary. On production vessels, it is not normally practical to
inspect mooring components out of the water. Subsea inspection techniques of these
components are complicated, expensive, and only partially effective at best. Therefore, these
components are typically designed or selected to last the life of the field.
The remainder of the sections only deal with temporary mooring systems.
6 - 64
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Analysis by URC is required unless already conducted for similar water depth, in
same area, with the same rig.
Otherwise, the drilling and/or third party contractor, or the DrillMoor Quasi-Static
Mooring Analysis can be used.
If the drilling engineer conducts the analysis, it should be calibrated against prior URC
w o rk. N o m a tte r w h o co n d u cts th e a n a lysis, it w ill b e th e d rillin g e n g in e e rs re sp o n sib ility
to develop the deployment and retrieval procedures.
It is essential to have a good design basis at the start of the mooring design cycle. The
design basis should reflect the current industry guidelines and standards. In addition, it should
include information on any operations that may be unique or require special attention. These
may include offset limitations during drilling, details of seafloor obstructions, and the distance
between well locations within or near the mooring spread.
6 - 65
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 66
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
CURRENT FORCES
Data for the magnitude, direction, and seasonal variation of surface currents should be
obtained for the area of operations.
Current forces are due to viscous drag on the submerged portion of the vessel hull and scale
with the square of the current velocity:
Fcurrent Ccurrent Vcurrent
2
where the drag coefficient Ccurrent depends on the current heading with respect to the vessel.
For semisubmersible vessels, current forces are higher at operating draft than at survival
draft and are higher from the beam than from the bow (sometimes significantly so).
Current force coefficients are the scaling factors used to determine the load on the vessel in
different areas. The two methods for estimating current force coefficients are numerical
calculations based on the projected areas of the underwater surfaces per API RP 2SK
guidelines and wind tunnel testing. Current forces are calculated for bow, quartering and
beam attack angles.
It should be noted that current is typically higher at the surface than further down the water
colum n, but it generally does not vary significantly over a vessels draft. G enerally use the
surface current value when calculating the current force on the vessel.
Figure 6.54 shows an example of a comparison of current force calculations based on drag
coefficients derived from model testing and numerical calculations from API RP 2SK. Notice
that force or current load is greater in the operating draft.
6 - 67
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
2
API RP 2SK = 59.2 kips/knot
400
300
200
100
0
0 0.5 1 1.5 2 2.5 3 3.5
Current Speed, knots
6 - 68
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
WIND FORCES
Wind forces are due to viscous drag on the exposed portion of the vessel hull, superstructure,
and scale with the square of the wind velocity.
Fwind Cwind Vwind
2
where drag coefficient Cwind depends on the wind heading with respect to the vessel.
For semisubmersibles, wind forces are higher at survival draft than at operating draft,
and there is some variation in overall force due to change in heading.
Wind force coefficients are the scaling factors used to determine the load on the vessel in
different areas. The two methods for estimating wind force coefficients are numerical
calculations based on the projected areas of the exposed surfaces per API RP 2SK
guidelines and wind tunnel testing. Wind forces are reported for bow, quarter and beam
attack angles.
See Figure 6.55 for an example comparison of drag coefficients derived from wind model
testing and numerical calculations from API RP 2SK. Note: Force or wind load is greater in
the survival draft.
300
200
100
0
0 10 20 30 40 50 60 70
Wind Speed, knots
6 - 69
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
The design wind speed for use in the mooring analysis should be selected in accordance
with the following criteria:
1. The maximum wind speed averaged over a one-minute interval should be used in
Quasi-Static analysis. Other time-varying speeds are often reported by URC and
others. You will sometimes see 10-minute or 1-hour average velocities, these are
known as low-frequency wind forces. In order to adjust the wind velocities of various
average time intervals the following equation can be used:
Vt = Vhr
Where:
Vt = wind velocity for the average time interval t.
= Time factor from Table 6.5
Vhr = 1 hour average wind velocity
2. The wind speed should be based on an elevation of 33-ft (10-m) above still
water level.
3. The design wind speed should be selected for the most severe season during
which operations are to be conducted at a given site.
WAVE FORCES
Wave forces are made up of three components:
1. Mean Wave Drift Force.
2. First Order or High Frequency Motion (independent of the mooring system, it is the
vessels response to the waves).
3. Second Order or Low Frequency Motion (a function of stiffness & dampening, it is the
resonance of the mooring system) .
6 - 70
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Wave drift force coefficients are the scaling factors used to determine the load on the vessel.
The two methods for estimating wave drift force coefficients are numerical calculations
through radiation/diffraction hydrodynamic models and scale model testing in a wave tank.
They are reported for bow, quarter and beam attack angles.
The basic measure of wave height is called significant wave height represented by Hs. Hs is
equal to the average of the highest 1/3 of the waves passing a point. This method is used
because it is roughly equivalent to what a trained observer would estimate as the wave height
for a given series of waves.
The maximum wave height is larger than the significant wave height. A rule of thumb is that
the maximum wave height is estimated to be 1.9 to 2.2 times the significant wave height. The
design wave height should be determined based on the statistical wave height distribution for
the design case environment. Figure 6.56 offers a comparison of wave drift forces at the
survival and operating draft. Notice that the difference in force or wave load is minimal
between the survival and the operating draft, but the difference in the beam and bow
directions are significant.
FIRST ORDER (HIGH FREQUENCY) MOTIONS
First order, or high frequency, motions are determined using vessel Response Amplitude
Operators (RAOs), complex scaling factors describing the vessel motions response to waves.
RAOs are typically listed as amplitude and phase combinations at selected wave periods for
each of the six degrees of freedom - surge, sway, heave, roll, pitch, and yaw, at various wave
headings relative to bow. Like the wave-drift force coefficients, RAOs can be calculated either
160
120
Wave Force, Kips
100
80
60
40
20
Note: On this particual rig, the wave loads on the Beam and Bow are the same.
0
0 5 10 15 20 25 30 35 40 45
6 - 71
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Rotational RAOs - These are given any number of ways, such as deg/ft, deg/m,
rad/ft, rad/m or, more rarely, dimensionless (referenced to the wave slope as /
rather than wave amplitude).
Phase Angles for RAOs The units of the phase angles are in either degrees or
radians (and are obvious if not explicitly stated). The phase angles may be either
lagging or leading and referenced to the wave crest, trough or null point.
Figure 6.58 shows a typical first order motion at the fairlead.
10
6
Amplitude of Motion (ft)
2
Surge
0 Sway
Heave
-2
-4
-6
-8
-10
0 4 8 12 16 20 24 28 32 36
Time (sec)
Figure 6.58 - High Frequency Motion at Fairlead
6 - 72
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
80
60
40
amplitude of motion (ft)
20
Surge
0 Sway
Heave
-20
-40
-60
-80
0 40 80 120 160 200 240 280 320 360
time (sec)
Note: The motions illustrated in Figures 6.58 and 6.59 are for regular waves.
Generally, seas have random waves, and the motions would be more complex.
6 - 73
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 74
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
For this particular rig and environmental condition, the following conclusions can be
made:
Of the three environmental forces, the wind force imparts the largest load.
The wind force imparts the largest load in the quartering direction.
The wave force imparts the largest load in the bow and beam direction (equivalent
loads).
The current force imparts the largest load in the beam direction.
The following section describes various methods for conducting a mooring analysis.
6 - 75
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
STATIC ANALYSIS
Single mooring line Static Analysis is the first step in the design. This type of analysis
provides the following information:
QUASI-STATIC ANALYSIS
Quasi-Static Analysis: In this approach, the dynamic wave loads are taken into account by
statically offsetting the vessel by an appropriately defined wave induced motion. Vertical
fairlead motions and dynamic wave effects associated with mass, damping, and fluid
acceleration are neglected. Research in mooring line dynamics has shown that the reliability
of the mooring designs base on this method can vary widely depending on the vessel type,
water depth, and line configuration. Nevertheless, because of the conservative factors of
safety that are introduced with this method, it is appropriate for temporary mooring systems.
The following steps outline the Quasi-Static analysis:
A vessel heading and the mooring spread pattern that maximizes the operating time
while still meeting safety factor requirements is selected.
The environmental criteria (wind, wave, and current) data is entered for the maximum
operating, maximum design, and any other desired condition.
A mooring response graph is generated, as shown in Figures 6.62b & 6.63. (This
particular graph is for the Marine 700 in 4600-ft of water with a chain/wire combination
system and a quartering environment)
The designer analyzes the maximum operating condition to verify the pretension selected
keeps the maximum offset to within 3% of water depth. For each attack angle (beam,
bow, and quartering), calculations determine the environmental loads, the maximum
vessel offset, and the tension in the mooring lines and anchors.
6 - 76
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Next, the designer analyzes the maximum design condition. For each attack angle
(beam, bow, and quartering), calculations determine the environmental loads, the
maximum vessel offset, and the tension in the mooring lines and anchors.
If the rig is equipped with thruster-assist, it may be used in the operating condition to
reduce the line and anchor tensions. However, caution should be exercised in assuming
thrusters are available at 100% efficiency in the maximum design case.
1. A graph of the mean environmental forces (wind, current, mean drift force) verses the
restoring force is generated. See Figure 6.62a. The environmental force (180 kips in
this example) is resisted by the mooring system. The two opposing forces reach
equilibrium (static condition) at an offset of 54-ft or 1.2% of water depth.
2. The effects of the High Frequency and Low Frequency motions (called "surge" in
DrillMoor) are added to the mean offset. See Figure 6.62b. The combined HF and LF
motions add an additional 11-ft of offset which also increases the line and anchor
tensions. Therefore, the total or maximum offset (65-ft in this example) is equal to the
sum of the mean offset and the surge.
480
420
Environmental Load, kips
360
300
240
Environmental Load = 180 kips
180
120
60
Mean Offset = 54 ft
0
0 10 20 30 40 50 60 70
Offset, ft 54 ft = 1.2% WD
Figure 6.62a - Mooring Response Graph
6 - 77
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Mooring Response Curves
95% Non-Exceedance
600
Restoring Force
540 Maximum Anchor Load
Maximum Line Load
480
Line Load of 435 kips = 30% Capacity
420
Load / Tension, kips
360
300
180
Environmental Load = 180 kips
120
60
Mean Offset = 54ft 11ft Surge Max Offset = 65ft
0
0 10 20 30 40 50 60 70 80
Offset, ft 65 ft = 1.4% of WD
1050
Environmental Load = 939 kips
Load / Tension, kips
900
Line Load of 765 kips = 53% Capacity
750
600
Anchor Load of 632 kips = 77% Capacity
450
300
Surge = 29ft
150
Mean Offset = 262ft Max Offset = 291ft
0
0 50 100 150 200 250 300 350
Offset, ft 291 ft = 6.3% of WD
6 - 78
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
This procedure is called quasi-static analysis because, although there is some estimate of the
vessel motions, all calculations are performed as if the vessel is stationary in its maximum
offset position. Quasi-static analysis is performed for various attack angles (typically bow,
beam, and quartering) for both intact and damaged mooring conditions.
Figures 6.62b and 6.63 also illustrate typical mooring response graphs for the 95% non-
exceedance and 10-year environments. The three curves represented in the graphs are
the total system restoring force, maximum loaded line, and maximum loaded anchor.
The graph also includes the mean and maximum vessel offsets. These curves are used
to evaluate the response of the mooring system and ensure the design standards are
meet. During the analysis, the following mooring components are modified in order to
optimize the design:
Chain length
Wire length
Operating or Pre-Tensions
Rig heading
Mooring pattern
Line management (slackening leeward lines) is also a method used to ensure the design
standards are met. See Section 6.12.3 for more information on line management.
C. DYNAMIC ANALYSIS
Only a general overview of the Dynamic analysis will be covered in this section since the
depth of the topic is beyond the scope of the manual. More information on the subject
can be found in the API RP 2SK.
Dynamic analysis accounts for the time varying effects due to mass, damping, and fluid
accelerations. In this approach, the time-varying fairlead motions are calculated from the
ve sse ls su rg e , sw a y, h e a ve , p itch , ro ll a n d ya w m o tio n s. G e n e ra lly it is su fficie n t to
account for only the vertical and horizontal fairlead motions in the plane of the mooring
line. Dynamic models are used to predict mooring line responses to the fairlead motions.
The majority of the mooring analysis conducted for MODUs will be with Quasi-Static
method. The Dynamic method is used if the Quasi-Static results do not meet the design
criteria. The Dynamic method is more accurate and thus the design safety factors are
lower. Table 6.8 compares Quasi-Static and Dynamic safety factors.
6 - 79
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 80
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
5-Year Environment
Special attention should be given to operations in an area of tropical cyclones such as
the Gulf of Mexico (hurricane) and South China Sea offshore China (typhoon). These
areas are characterized by generally mild environment combined with severe storms
during the cyclone season. For operations out of the cyclone season, the 5-year
environment can be determined using the environmental data excluding tropical
cyclones. For operations during the cyclone season, the tropical cyclone data should be
included, and the design wind speed should not be lower than 60 knots (one-minute
average at 10-m/33-ft elevation).
The return period can be reduced for certain operations during the tropical cyclone
season provided the following conditions are met:
A risk analysis is conducted to evaluate the consequences of a
mooring failure.
Operations personnel evacuation or move the vessel is planned
and executed before arrival of a tropical cyclone.
A weather forecast system with local environmental feedback is
available to provide accurate forecasting.
There is no other structure within five miles of the operation.
The reduced return period in this case should be determined by the risk analysis, but it
should not be less than one year.
10-Year Environment
When a vessel is operating in an area within five-miles of other offshore facilities or
equipment, a minimum of a 10-year return period should be used in the analysis. In a
tropical cyclone area, for operations out of the cyclone season, the 10-year environment
can be determined using the environmental data excluding tropical cyclones. For
operations during the cyclone season, the tropical cyclone data should be included,
and the design wind speed should not be lower than 70 knots (1-minute average
at 10-m/33-ft elevation).
6 - 81
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 82
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
ANALYSIS CONDITIONS
For the mooring analysis, several conditions should be examined. These include the
mooring line condition (wire and/or chain), tensions (line and anchor), and vessel offset.
Other criteria such as clearance requirements should be examined where mooring lines
cross over pipelines or other subsea equipment.
Line Condition: Intact, Damaged, Transient
Intact condition refers to the condition in which all mooring lines are intact. Damage
condition refers to the condition in which the vessel settles at a new equilibrium position
after a mooring line breakage. Transient condition refers to the condition in which the
vessel is subjected to transient motions (overshooting) after a mooring line breakage
before it settles at the new equilibrium position. The conditions to be analyzed are in
Table 6.7:
6 - 83
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Line Tension
Tension limits and equivalent factors of safety for various conditions and analysis
methods are provided below. These criteria apply to the maximum design condition. No
checking is required for the line tension under the maximum operating condition and the
maximum connected condition for the drilling riser. The different analysis criteria are
located in Table 6.8.
The maximum line angle at the mudline under the Maximum Design Environment
is less than 10o for the damage condition, and less than 5o for the intact condition.
Most drag embedment anchors have adjustable flukes/shanks. The amount of
adjustment will be anchor specific, but generally, the setting is either wide open (50
degrees) or closed (30 degrees). In soils such as sand and medium to hard clay, an
anchor with a fluke/shank angle of 30 degrees will give the highest holding power. If
used in soft clay or mud a 50 degrees fluke/shank angle is appropriate. The
manufacturer will have hold capacity charts for various anchor weights and soil
condition. This data should be compared to the anchor holding capacity charts in the API
RP 2SK (See Figures 6.25 & 6.26).
6 - 84
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
CLEARANCE REQUIREMENTS
The clearances between the floating vessel or its mooring components and other marine
installations should be determined. Clearance requirements are provided below.
Where a mooring line crosses a pipeline within the elevated part of its catenary, a
minimum vertical clearance of 30 feet under the intact condition should be maintained.
A mooring line can contact a protected pipeline provided this contact remains throughout
the full range of predicted intact line tensions. The contact point must not occur in the
"thrashing zone" i.e. the catenary touch down point.
Where two mooring lines cross, a minimum vertical clearance of 30 feet is required
for the intact condition.
If a marine installation lies in the dragging path between the anchor and the mobile
offshore unit, the anchor should be at least 1000 feet from the marine installation.
Otherwise, the anchor should be at least 300 feet from the marine installation.
INSTALLATION
The mooring installation is also evaluated in order to ensure that both the MODU and the
anchor-handling vessel (AHV) can safely handle the loads and determine the AHV
requirements. The DrillMoor program can be used to evaluate the associated loads during
the running/retrieving of the anchors and to develop procedures.
6 - 85
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
The Mobil Units database will be available on the intranet in the coming months.
6 - 86
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
scan sonar records, soil strength data should be obtained for the analysis. A survey
contractor like Racal, Fugro, or John Chance can provide field maps with subsea
obstructions.
A simple Excel spreadsheet can be developed to evaluate several mooring patters and
rig headings. This data should include any subsea equipment or obstructions and can be
plotted in the X & Y coordinate system. See Figure 6.64.
9830000
9825000
8
1
Rig Heading 20 Deg.
7
9820000
Northing, ft
2
9815000
6
Pipe Line
9810000
3
5
9805000
Pipe Line 4
Pipe Line
9800000
1015000 1020000 1025000 1030000 1035000 1040000 1045000 1050000
Easting, ft
6 - 87
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
ENVIRONMENTAL DATA
Environmental data is usually obtained from ExxonMobil Upstream Research Company
(URC) and can be a long lead-time item. Depending on the location, the environmental
data that is available may be limited and is usually analyzed over the entire year. For
short-term operations, this data may be conservative unless the operations are to be
conducted during the months of extreme weather.
ENVIRONMENTAL CRITERIA
The industry recognizes two classifications of environmental conditions when evaluating
mooring systems: maximum design condition and maximum operating condition. The
crite ria to b e u se d w ill b e d e te rm in e d b a se d o n th e rig s p ro xim ity to o th e r o ffsh o re
installations/subsea equipment. For rigs operating near other offshore installations,
where the consequence of a mooring failure would be higher, a 10-year return period is
used. A further explanation of determining the environmental criteria is provided in
Section 6.8.5.
6 - 88
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
ANCHORS 1 2 3 4 5 6 7 8
Type
Weight (kips)
Fluke Setting
(degrees)
Bolster Angle
(degrees)
CHAIN
Size (in)
Weight in air
(lbs/ft)
Grade
Usable Length
(ft)
Breaking Strength
B T L (kip s)
WIRE ROPE
Size (in)
Usable Length
(ft)
Breaking Strength
C T B (kip s)
Weight in air
(lbs/ft)
Winch / Windlass / Winch Type
Tension Capacities Drum / Traction
Stall (kips)
1 2 3 4 5 6 7 8
Water Depth at
radius 2 x WD , ft
Water Depth at Seafloor Type Well Location X&Y / Grid (ft)
Well Location (ft) (clay / Sand) X: Y:
Thruster Output Seafloor Obstruction Well Location Lat / Long
(kips) (attach Plat)
Thruster Yes / No (Yes / No) Lat: Long:
Azumuthing
Desired Rig
Heading
(degrees grid)
6 - 90
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 91
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
There are numerous AHV sizes and manufacturers, but for this summary, they will be
divided into 3 classes (small, medium, and large).
Small: > 6000 BHP or 80-90 Tons Bollard Pull.
Medium: 6000 12000 BHP or 90-165 Tons Bollard Pull.
Large: > 12,000 BHP or 165 200 Tons Bollard Pull.
The following equation converts break horse power to bollard pull:
(BHP x 27.5 )/1000 = Bollard pull (kips)
AHVs are equipped with multiple winches of various sizes and tensioning capabilities.
Currently the largest conventional wire wrap winch is capable of 1,000,000 lbs of pull
(bare drum). Keep in mind that, as the layers increase on the winch drum, the tension
capacity decreases. There are a few AHVs that are equipped with traction winches.
These winches have the maximum pull always available.
Anchor handing vessels should be equipped with a stern roller and a shark jaw or
equivalent remote controlled pendant holding device. They should have sufficient
bollard pull and winch pull for the intended operation. These needs can be assessed
with DrillMoor.
6 - 92
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
The shark jaw, is a hydraulically operated mechanical stop that can support the weight
of line outboard of the vessel while connections are made. The pop up pin (or guide) is
a set of hydraulic operated alignment rollers (vertical) that keep the mooring line/work
wire centered on vessel. The stern roller is a heavy-duty cylinder made into the stern of
the vessel that will turn/roll, as the line is dragged across. This reduces wear on the
mooring components and to the stern of the AHV (Figure 6.66).
The water depth and associated line loads will generally dictate the AHV size
requirements. For instance, in shallow water the mooring line may be all chain and the
suspended load minimal. Therefore, the winch capacity of the AHV will not be as critical
as the bollard pull. The bollard pull on the other hand will be critical since the AHV must
drag the chain across the seafloor during the stretch out. In deepwater both the winch
size and bollard pull are important.
Figures 6.67 and 6.68 illustrate a medium size AHV.
6 - 93
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Figure 56
6 - 94
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Rig Heading
8
1
7
Breast Anchors
Point
6 (main) 3
Anchors
5 4
The normal convention is to run out the point anchors first followed by the breast
anchors. Once the first point anchor is set, the next anchor would be the one on the
opposite side of first anchor deployed. For instance if the number four anchor is ran first,
the next anchor would be the number eight (for a eight line mooring system). Then the
next set of opposing point anchors would be run. The reason for running the anchors in
such a manor is to have the first anchors maintain station as soon as possible. Weather
conditions and subsea equipment will also drive which set of anchors is set first.
The following is a summary for setting anchors in 1000 ft to 5000 ft of water with drag
embedment anchors and a chain/wire combination system.
6 - 95
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 96
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Figure 6.70
6 - 97
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
another 1 to 2 feet of chain and the load is transferred to the winch. The chain from the
windlass can then be disconnected at the Tri-Link and the deployment process
continues via the wire/winch (See Figure 6.71).
Figure 6.71
6 - 98
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
The amount of work wire used during deployment is critical to ensuring the anchors are
set and holding. The rule-of-thumb for the work wire length during deployment is 1.3
times the water depth. The AHV will have an electronic depth finder on board, but it is
important to include the estimated depth at each anchor location in the deployment
procedure to expedite the process. After the rig has deployed the designed length of
chain/wire and the AHV has deployed 1.3 times the water depth of work wire, the anchor
will be just past the setting location. The winch operator on the rig will read a tension
approximately equal to weight of the mooring chain/wire paid out (assuming all the line is
suspended). To stretch out the mooring leg, the AHV will increase power until bollard
power and the winch tension will approximately equal the weight of the work wire, PCC
w ire , a n d th e a n ch o r. T h is is ca lle d stre tch in g o u t. T h e A H V w ill re m a in a t th is p o w e r
setting until forward movement of the AHV stops. If the job is designed correctly, the
anchor will be 100ft 200ft off bottom (See Figure 6.72)
Rig has
all mooring line paid out, rig winches are secured
AHV pays out workwire until 1.3 x WD
AHV increases bollard power to stretch line until clear of seafloor
stre tch o u t o r u n til b o lla rd p u ll o f ve sse l p ro vid e s m a xim u m
achievable tension on mooring line.
Water Depth
not to scale
Figure 6.72
6 - 99
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Once the mooring line has been stretched out, the AHV will quickly reduce bollard power
to 10-20%. The weight of the mooring line will drag the AHV backwards as the
anchor/line fall to the seafloor. As the anchor is falling, the catenary shape of the
mooring line will also pull the anchor toward the rig. The AHV will communicate to the rig
that the anchor is on bottom, and the coordinates of the rig and AHV should be noted.
If all went well, the anchor will embed in the seafloor and the rig winch will still have
tension. An estimate of the final anchor location should be made to within + or -100 ft.
This is done by taking the horizontal distance from the rig to the AHV and subtracting
out the distance the AHV is from the anchor (See Figure 6.73). The DrillMoor program
can be used to make this calculation. This information will be critical in recovering
the anchors.
Figure 6.73
Once the anchor is on bottom, the AHV will then chase the PCC wire back to rig. It is a
good practice to tension up with the rig winch to load the anchor to a value at least equal
to its weight while the AHV isCONVENTIONAL
chasing in. CATENARY ANCHOR MOORING
This is to ensure that the anchor is set correctly
before the AHV moves to the next anchor. The DrillMoor program can be used to
determine the appropriate winch tension and the resulting anchor tension (line weight,
anchor weight, and seafloor drag must be taken into account).
For deepwater mooring operations, it is necessary to ensure that the chase wire is tight
on the drum before deploying each anchor. If the wire is not tight on the drum, the weight
of the mooring leg may cause the wire to become entangled on the drum or to slip during
later high load payout. If needed, to tighten the wire on the drum, the AHV will redeploy
the wire after taking the PCC for the next anchor and re-spool the wire while maintaining
sufficient bollard pull to tighten the wire.
6 - 100
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Anchor #4
550
Anchor #5
Anchor #6
500 Anchor #7
Anchor #8
Winch Tension, Kips
450
400
Anchor #8 Slipping
350
300
6 - 101
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 102
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 103
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 104
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 105
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Safe Zone
Figure 6.75 - Safe Zone Established for Multiple Well Drill Site
6 - 106
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
In 2002, a MODU was moored up with suction piles/polyester inserts in 9000-ft of water
in the GOM.
6 - 107
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 108
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6.12.6 SEPLA
The Suction Embedded Plate Anchor or SEPLA is a newly developed anchor system that
uses a suction follower (similar to a suction pile) to embed a plate anchor. The suction
follower is immediately retracted once the plate anchor is brought to design soil depth and
can be reused to install additional plate anchors.
The SEPLA consists of a rectangular fluke with a full-length keying flap running along its top
edge (Figure 6.79). The keying flap is mounted with an offset hinge such that soil pressure
along its top edge will force the flap to rotate with respect to the fluke, effectively quadrupling
the vertical end bearing area and preventing it from moving back up its installation track when
tensioned. The mooring line is attached to the fluke by means of twin plate steel shanks.
For installation, the SEPLA is mounted in slots at the bottom of the follower and retained by
the mooring line and recovery bridle (Figure 6.80). The mooring line is connected to the
SEPLA and the top of the suction follower during the deployment and is spooled off a winch
installed on either the SEPLA installation vessel or a separate AHV (Figure 6.81). The
suction follower, with the SEPLA slotted into its base, is lowered to the seafloor, allowed to
self-penetrate and then suction embedded in a manner similar to a suction pile. Once the
SEPLA has reached its design penetration depth, the mooring line and retrieval bridle that
hold the SEPLA secure in the bottom of the follower are released by the installation ROV.
The pump flow direction is then revered and water is pumped back into the follower. The
follower moves upward, leaving the SEPLA in place (Figure 6.82). Tension in the follower
recovery wire, in combination with the positive pressure provided by the pump, will extract
the follower from the seafloor. The follower is then recovered to the installation vessel for
deployment of the next SEPLA.
At this time, the mooring line is tensioned by the installation vessel in the direction that the
S E P LA is to be loaded. T his keying tension w ill:
Pull the initially vertical mooring line through the soil so that it forms the classic
inverse catenary shape from the mudline to the anchor shackle.
Start rotation of the SEPLA fluke to an orientation perpendicular to the direction of the
mooring line at the end.
Set the keying flap to prevent further loss of penetration beyond that which is
necessary to set he keying flap.
The SEPLA is now ready to develop its full pullout capacity. Regardless of the initial
orientation of the fluke to the mooring line, the SEPLA with its long, rigid shank will rotate to
present the maximum projected area to the direction of pull ensuring ultimate pullout capacity,
based on the anchors penetration depth and soil properties, is achieved.
Full scale offshore testing of the SEPLA in 1999 resulted in a successful test of 543 kips
tension at the anchor.
In a recent survey of venders (01/01/02) the cost associated with the SEPLA system is
as follows:
To buy system is $80k to $90k per anchor, no rental information was available.
In 2001, a MODU was moored up with SEPLA anchors/polyester inserts in 6200-ft of
water in the GOM.
6 - 109
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 110
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
Figure 6.81 - SEPLA system lowered over AHV stern roller (notice A-frame)
6 - 111
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 112
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 113
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
6 - 114
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
The synthetic fiber rope is either rented in a long-term contract (four to five years) or
purchased from the supplier.
In a recent survey of venders (01/01/02), the costs associated with synthetic systems
are as follows:
6 - 115
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
MOORING DESIGN AND OPERATIONS
REFERENCES
Exxon Upstream Design Guidance Manual, Section III Mobil Offshore Unit Mooring
Systems, located on the LAN: I:\EMDC\Drilling\Technical\Tech
Library\Manuals\Design Guidance\Mooring.PDF
API Spec 2F, Specification for Mooring Chain, Sixth Edition, June 1, 1997.
The Inspection and Discard of Wire Mooring Lines, Supplement for Participants in a
JIP on an Appraisal of Discarded Mooring Ropes, Noble Denton & Associates,
London, December 1992.
Guide for the Certification of Offshore Mooring Chain, American Bureau of Shipping,
1999.
Certification of Offshore Mooring Chain, DnV Certification Notes No. 2.6, August
1995.
Dunnavant, T. W., and Kwan, C-T. T., Centrifuge Modeling and Parametric Analyses
of Drag Anchor Behavior, OTC Paper 7202, Houston, May 1993.
6 - 116
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
7
OPEN WATER OPERATIONS
Section
OBJECTIVES
On completion of this lesson, you will be able to:
List the typical scope of work for an ROV supporting drill rig operations.
List the types of guidance systems used for floating drilling operations and the
advantages of each.
List the two methods for spudding a subsea well and describe the differences.
List forces involved on structural casing and design requirements for structural
casing.
7-1
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
CONTENTS Page
7-2
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7-3
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7.1.1 INTRODUCTION
When performing open water operations from a floating drilling rig, operations are
typically assisted by an ROV installed on the drilling rig. An ROV, as illustrated in Figure
7.1, is an unmanned, remotely controlled, tethered vehicle with video cameras for
observing subsea operations and one or more manipulator arms for performing work
around the drilling location. ROVs are built in many different sizes and forms depending
on the tasks required and can be as simple as a video eyeball to a heavy multi-functional
work vehicle which can have the dexterity of divers and can operate in water depths up
to 10,000 ft. The operational advantages of an ROV over a diver is that they have
unlimited endurance at subsea conditions and can perform in hazardous conditions
where the liability of putting a man in the water would not be allowed.
A typical ROV is deployed using an umbilical that supplies both the control/video signal
and electrical power. The typical ROV will use electrical power to operate hydraulic
pumps to power the thrusters and manipulator arms. To provide maneuverability of the
vehicle subsea, most ROVs are equipped with a tether that connects the vehicle back to
the umbilical. To improve communication and video signals, the ROV umbilical for
deepwater ROVs is typically equipped with fiber optic conductor within the umbilical.
7-4
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
For support during drilling operations, the ROV is typically only used to provide video
pictures back to the rig floor and to assist guidance of tools into the wellbore. Listed
below is a summary of tasks where an ROV may be used during drilling and completion
operations.
Perform bottom surveys when moving onto location. This survey confirms that no
obstructions are on the seafloor when the well is spudded.
Place acoustic beacons for DP rigs.
Visually monitor jetting structural casing.
Assist stab-in of drilling assemblies into the wellbore.
Monitor returns at the seafloor with the sonar while drilling the structural or
conductor hole riserless to detect shallow gas.
Visually monitor conductor casing running and cementing operations.
Retrieve cement samples to confirm cement returns to the mud line.
Visually monitor the alignment and installation of the BOP stack onto the
wellhead.
Inspect/monitor the riser, BOPs, and slope indicators.
Inject glycol/methanol to prevent or remove hydrates from subsea connectors.
Jet/remove hydrates from BOP wellhead connector.
Actuate hydraulic functions on the BOP stack or subsea tree with hot stabs.
Actuate and verify valve status on subsea trees.
Replace ring gaskets.
Cutt/reestablishing guidelines.
Provide video when inspecting subsea equipment for pressure or control
system leaks.
Assist in recovery of dropped objects.
7-5
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Provide video and assist stabbing tools in the wellhead during P&A operations.
Install and/or remove wellhead corrosion caps.
Inject corrosion inhibitor into the wellhead during abandonment operations.
Assist in recovering lost mooring equipment.
Replace/recover acoustic beacons.
Place explosives during P&A operations.
Perform video and sonar bottom survey to meet regulatory compliance.
As ROVs developed over the years, they have increased in their functionality and are
now an integral part of most floating drilling operations. As an example of functionality, a
string of 22 in. casing that was stuck +/- 600 ft off bottom on a GOM ultra-deepwater well
in 2001 was cut by the ROV to allow the stuck section of casing to be recovered and the
well reentered. This operation was conducted utilizing the manipulator arms and a
hydraulic grinder attached to the ROV.
Pure Observation Systems - the smallest systems and are typically only
equipped with a video camera. These systems are small, relatively inexpensive
and can be mobilized and setup quickly while occupying a minimum amount of
deck space.
Work Systems typically tethered, equipped with multiple cameras and at least
one manipulator arm. These systems are typically installed on the rig for the
duration of a project and utilize a deck mounted a-frame system for deployment.
Work systems are frequently used for drill rig support with the most common
systems types being the Scorpio, Recon, and Hydra (Figure 7.2). Water depth
rating for these systems typically range up to 1500 meters.
7-6
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Special Purpose Systems designed and built for special and unique jobs such
as cable laying operations, seafloor salvage operations, and heavy support
operations. These systems (Figures 7.2, 7.3 and 7.4) may be used on ultra-
deepwater operations but are typically only used for drill rig support during
subsea completion and/or template operations.
Buoyancy material
Manipulator Arms
Figure 7.4 Scorpio ROV
The selection of the ROV is typically made prior to mobilization and installed on the rig
for use during the term of the rig contract. The selection of the ROV is typically based on
the following factors:
Water depth.
Operating Environment High Current.
Planned scope of work (i.e. drilling support, operating subsea trees, and
connecting jumpers or umbilical for subsea equipment).
Cost of work system.
Complexity of engineering interface (e.g. drilling support only or subsea Xmas
tree/template completion included).
Typically, water depth and planned work scope drive ROV work system selection.
If the system is to only provide minimal tasks to support-drilling operations, the most
cost-effective system that can operate in the environment is usually selected. If
multiple complex operations are to be performed such as supporting and installing
subsea trees, then the system capabilities and tooling would be included as
important selection criteria.
7-7
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
High technology titanium manipulators are not usually required for drilling rig support
work. The best manipulators are robust, rig repairable and weldable, and possess
sufficient dexterity to perform the required work scope. Manipulators that provide fine
motor skills in excess of that required by anticipated work scope are a false economy.
Field reliability is typically more valuable than unnecessary dexterity.
The most cost effective ROV system is one that can consistently do the work required
in a timely manner. When an ROV has to be consistently recovered to make tooling
adjustments, changes or repairs, the rig time cost incurred will easily offset a low cost
ROV operating or standby day rate.
7-8
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
ROV Handling
System
deploying ROV
over the side
of a drilling
vessel.
7-9
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
The ROV uses electrical power to drive hydraulic pumps, which in turn power hydraulic
motors, which drive the thrusters on the vehicle. Controls for the ROV are typically
electro-hydraulic, and the telemetry is normally all electronic. Newest generation ROVs
for deepwater are sometimes powered with all electric motors. Onboard sonar permits
the ROV to determine the location of other objects when optical visibility does not exist.
Sonar can also be used to identify gas bubbles within drilling spoil plumes as well as
determine vehicle location by ranging distances and compass azimuths from other
objects on the seafloor, whose location is known.
Every effort must be made to do ROV work out of critical path. However, if the ROV
experiences difficulty in performing a particular task, the resulting delay can place the
ROV work in the critical path. By its nature, ROV intervention work can be slow and
tedious. When done in the critical path, it is very costly in rig time.
The Company should always plan its ROV work with the ROV crews 24 to 48 hours in
advance, to ensure that the vehicle and required tooling are working and ready for use.
The ROV crew should develop a table of required end effectors, number of
required turns, and required torque for all Xmas tree and template valves.
ROV Company should have 100% redundancy for all mission critical tooling.
ROV crew should have a seafloor photograph file of all subsea components
requiring ROV intervention.
Once competent ROV crews are familiar with rig operations and subsea
equipment, ROV personnel changes should be avoided.
ROV maintenance should be performed during long drilling periods and rig moves,
so that the ROV will always be ready to work when required. The ROV will always be
heavily used during the spud and finish of a well. Any day the ROV is not in use, it
should be a day of preventative maintenance for the ROV crew. ROV maintenance and
downtime should always be documented on the ROV daily work log.
7 - 10
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Paint equipment or items (e.g., casing, drill pipe, guide lines, BOP funnels,
connector indicators) that need to be viewed with the video camera a white or
yellow color.
Paint indicator rings or contrasting colors around small items that need to be
identified subsea (e.g., ring gaskets, indicator rods).
Provide handles at locations (e.g. BOP hot stabs, guidebase, actuator panel on
subsea tree) where the ROV is to perform work or standby to provide video for
an extended time.
Utilize floats or sonar reflectors to assist in locating the wellbore and/or
equipment placed on the seafloor.
7 - 11
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7 - 12
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7 - 13
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Permanent Guidebase (PGB) The PGB illustrated in Figure 7.8 is a guide frame that
latches to an external profile at the top of the low pressure wellhead and is equipped
with four guidepost that are used to guide the BOP stack over the high pressure
wellhead. For the Vetco MS-700 wellhead system, the lower section of the PGB is also
used with the GRA assembly when the guideposts are removed and the GRA frame
installed. PGBs can be retrieved from the wellhead during a plug and abandonment with
a special retrieval tool.
Guideposts
with guidelines
Low pressure installed
wellhead housing
PGB
7 - 14
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Low Pressure
Wellhead Housing
Conductor Casing
Structural Casing
7 - 15
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7 - 16
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Fixed Orifice
Air-Oil Reservoir
25 40 psi
Cylinder
Tension is maintained by adjusting the high-pressure air that supplies pressure to oil
beneath the tensioner piston. Tensioners are typically double sheaved to allow a piston
stroke of 12.5 ft to provide 50 ft of heave compensation.
While maintaining guideline tension with only the TGB in place, a compromise must
sometimes be made to provide adequate tension to guide the tools into the wellbore, but
minimized enough to prevent lifting the guidebase from the seafloor.
After the BOP stack has been run, the riser establishes the path to the well. The
guidelines remain in place to provide guidance after the BOP stack is recovered at the
end of the well. When using a straight hydraulic BOP control system, the guidelines are
also used to guide the BOP control pod during deployment and retrieval. This process
allows the control pod to be retrieved independently of the LMRP when repair of a
control pod is required.
If the structural casing is jetted into location, the well location would be established when
the casing tags bottom with the guidelines attached to the PGB installed at the top of the
structural casing. After the structural casing is jetted in place, the guidelines would be
used to guide tools into the wellbore and the BOP stack over the wellhead after the
conductor casing is in place. If a guideline is broken after installation, the broken
guideline can be cut away and re-established with either ROV assistance or with tugger
wire conveyed tools supplied by the wellhead manufacturer.
7 - 17
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Stack Connector
(Up-funnel)
Down
Funnel
Slope Indicators
Mud Mat
Figure 7.12 Guidelineless Reentry System Figure 7.13 Down Funnel Guidelineless System
When operating in deepwater, a well is typically spudded, by jetting the structural casing
into place. The structural casing location is determined by surveying the rig on location
at the surface and the casing is jetted into place to establish the well location. If the BOP
stack is not equipped with a down funnel, a Guidelineless Reentry Adapter (GRA) shown
in Figure 7 will be installed on the low-pressure housing which is welded to the top joint
of structural casing. The GRA is essentially an up funnel sized to received the wellhead
connector and align it over the wellhead. Drilling assemblies and the conductor casing
are also stabbed into the structural casing using the GRA with assistance from the ROV
and by repositioning the rig with the D/P system or the anchor winches.
7 - 18
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
If the BOP stack is equipped with a down funnel, the structural casing will be installed
without a guidance system. The drilling assembly for the conductor casing and the
conductor casing are stabbed into the structural casing with assistance from the ROV
and by re-positioning the rig either by the D/P system or the anchor winches. After the
conductor casing is installed, the BOP stack is stabbed onto the high pressure housing
by repositioning the rig and final alignment is achieved by the down funnel installed on
the bottom of the stack.
The clearance for the down funnel between the wellheads, guide frames, slope indicator
b ra cke ts, a n d va lve o u tle ts is critica l sin ce th e rig s B O P sta ck m u st b e a b le to
sufficiently swallow the high-pressure wellhead housing and land out without any
obstructions. If the wellhead and funnel are from the same manufacturer, this is typically
not a problem. When using equipment from different manufacturers or when working on
a previously installed wellhead system, detailed drawing and dimensions should always
be used to verify that the stack and funnel can align over the wellhead without
interference.
As illustrated in Figure 7.14, the guidelineless system can also be used when the hole
for the structural casing is drilled and the casing is cemented into place. In this scenario,
clear seafloor visibility is necessary for the ROV to locate the pre-drilled hole and
coordinate the rig movement required, to stab the casing into the wellbore.
After the casing is landed and cemented, the drilling assemblies and/or BOP stack are
stabbed into the structural casing with assistance from the ROV and by re-positioning
the rig either by the D/P system or the anchor winches as noted above.
Although either system can be used on a moored rig regardless of water depth, the
guideline system is typically used when water depths are less than 3000 ft, but they
have been used in water depths up to 5000 ft. As the industry moved into the ultra-
deepwater in the mid 1990s, more and more moored rigs began to operate guidelineless
due to the problems associated with guideline entanglement and the additional time
required to deploy and retrieve the lines. Guidelines can be especially difficult to manage
in ultra-deepwater when operating in a high current environment.
7 - 19
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7 - 20
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7.3.1 INTRODUCTION
Structural casing is the first casing installed on subsea wells and is designed to provide
the support foundation for the accumulated weight of the subsequent casing strings. The
structural casing is also designed to provide the foundation for supporting the weight of
the BOP stack and resistance to all environmental bending moments that will be
encountered. During design of the structural casing, loading between the inner string of
casing is ignored and the structural casing is designed without considering the strength
of any inner casing strings.
Additionally, the structural casing provides sufficient hole integrity while drilling the hole
for the conductor casing. The capability of the structural casing to withstand these loads
is a function of the following:
The two most common sizes for structural casing are 30 in. and 36 in. with a 1.5 in. wall
thickness. Other common sizes for structural casing depending on bending strength
requirements, are:
7 - 21
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
To ensure transfer of the load between the 18 in. high-pressure wellhead to the to
structural casing, the 18 in. wellhead housing can be rigidly locked down onto the low-
pressure wellhead housing after the conductor casing string is landed. Successful rigid
lock down causes the two wellheads to act as one component preventing cyclic
movement, which could cause fatigue failure in the conductor casing below the
wellhead. Rigid lock down provides increased fatigue resistance, but not increased
bending capacity.
To ensure that the wellbore can withstand the bending and axial loads imposed while
drilling; the structural casing is designed considering no load sharing between the
structural and conductor casing. This approach is necessary since load sharing between
the two strings may not be achieved due to the possibility of uncemented annulus. In
addition, the bending moment contribution of the conductor string is relatively small since
it is a function of the fourth power of the diameter.
7 - 22
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Bending loading
factors:
Lateral loading at
flex joint due to
riser loads.
Wellhead and
BOP stickup
above the mud
line.
Soil strength
below the mud
line.
BOP and wellhead
angle (affects both
vertical loading
and bending).
FLEX JOINT
Axial loading
factors:
Vertical loading at
flex joint due to
riser loads.
BOP weight
(buoyed).
Wellhead and
casing weight
(buoyed) of all Figure 7.15 Loads and Bending Moments
subsequent
casing strings.
Design for bending is generally calculated assuming that the structural casing is not
fixed at the mud line and that some degree of deflection in the casing occurs for some
distance below the mud line due to the soil strength. This deflection will move the fixed
point of the casing below the mud line and cause a longer moment arm.
When coupled with the resistance from the soil strength, the required bending strength
of the casing will be less since it will be assisted by the strength of the soil and
distributed over a longer interval.
7 - 23
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
For areas where soil strength data is unavailable or when a comprehensive analysis will
not be performed, a conservative calculation would be to design the casing assuming a
fixed point at the component mud line. This approach though will generally result in an
over design with larger casing and wellheads than required.
LATERAL LOADING
To keep the riser straight and prevent it from buckling, a large vertical load is applied to
the riser with the riser tensioners. The amount of riser tension that must be applied is
equal to the buoyed weight of the riser, the differential weight of the mud in the riser and
seawater, and an amount of overpull to place the neutral plane down into the BOP stack.
For DP rigs, the amount of riser tension should also be sufficient (typically 50 100 kips
of additional tension is required) to provide confident emergency LMRP and riser
disconnect, with manageable recoil.
The axial overpull of the riser tension at the top of the BOP stack is transmitted
through the flex joint and the LMRP at the top of the BOP stack. In a perfect case,
this overpull would have no horizontal component. However, the reality of floating
drilling is that the wellhead and BOP stack will never be completely vertical and there
will always be some horizontal loading resulting from how far off vertical the structural
casing was set or rig offset.
7 - 24
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
The typical BOP stack is about 50 ft tall and results in a 60 to 62 ft total moment arm
from the flex joint to the visible mud line. Thus any deviation from vertical by the
structural casing and the low-pressure wellhead will impart a bending moment to the
LMRP connector, affecting its ability to disconnect and reconnect.
If soil at the mud line were strong such as granite, the stickup height distance would be
all that is needed to calculate the bending stress in the structural casing at the mud line.
However, soil strengths can be very weak and tend to decrease with water depth. The
soil strength for a given area will usually be known from offset well data or compressive
strength analysis of core samples. A bit set down test can be run to check these soil
strength estimates. Usually a 26 in. bit with 5 kips set down weight and no pumps will
stop penetrating at 150-p si co m p re ssive so il stre n g th . T h is d e fin e s th e co m p e te n t m u d
lin e ve rsu s th e visib le m u d lin e o r m u rk lin e . S e a flo o r m u d a b o ve th e co m p e te n t m u d
line does not contribute to structural casing bending resistance.
Since soft clays are generally found near the mud line, the structural casing will deflect
as it is laterally loaded until the soil develops more resistance and the pipe increases its
bending stress. As the pipe deflects, a cavity will be formed along the pipe from the
cyclic loading as the pipe moves back and forth. If excessive defection occurs, wear
and/or failure of the casing just below the mud line may occur.
Soil strength can also be used to determine whether or not structural casing can be
jetted in, and if so, how many joints or whether the structural casing must be cemented
in a drilled hole. Typical depths for structural casing are three to four joints or about 100
ft of casing below the visible mud line if an oversize hole is drilled and the structural
casing cemented. If the structural casing is jetted, the typical setting depths are normally
five to seven joints or about 200 to 300 ft of casing below the visible mud line, depending
on soil strength, potential loads, and experience in the area.
Soil strength, casing OD, wall thickness, casing connector bending strength, and
anticipated lateral loading will also determine whether an unexpected excessive stick up
height will be acceptable for a given location.
7 - 25
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Pull out is where the planned or excessive riser tension pulls the structural casing out
of the seafloor. Sinking is where the structural casing and wellhead might subside
below the visible mud line. Since the hole for the conductor casing is normally drilled
riserless, and riser tension is not applied until after the BOP stack is in place, pull out
is not an issue.
Sinking of the structural casing can always potentially be a problem. Selecting the proper
setting depth, whether the hole is drilled and the casing cemented or the structural
casing jetted, is critical in preventing the casing from sinking. Typical soil strengths for
the Gulf of Mexico and West Africa require around 120 ft of casing when drilled and
cemented and 240 to 300 ft when the casing is jetted to prevent sinking. Guidelines for
ca lcu la tin g m in im u m ca sin g le n g th s fo r va rio u s so il stre n g th s a re a va ila b le in th e IA D C
D e e p w a te r W e ll C o n tro l G u id e lin e s.
In addition to proper casing setting depth, prudent operational procedures such as:
operating with reduced pump rates when drilling directly below the structural
casing shoe to prevent wash out.
avoiding excess pipe reciprocation while jetting and allowing sufficient time
for skin tension to develop after the casing is in place before releasing the
running tool.
conductor casing cementing procedures that restrict set down of the
conductor casing string onto the structural casing to 50 kips until the
conductor casing is cemented.
Additionally, a mud mat may be run on the low-pressure wellhead assembly, to reduce
the possibility of the structural casing sinking. This is frequently done in deepwater due
to the reduced seafloor soil strength present from the lack of overburden pressure.
For a 16 ft x 16 ft square mud mat, about 150 kips of axial load is provided to support the
stru ctu ra l ca sin g a fte r it is p la ce d o r p ro vid e a n o g o sto p in d ica to r d u rin g je ttin g
operations. The additional axial load-bearing capability of the mud mat may also allow
earlier release of the running tool, thus decreasing the soak time required to for the skin
friction of the soil to develop.
In practice, a pull out/sinking analysis is not done during the design of the structural
casing.
7 - 26
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
The casing extension joint that is welded to the low-pressure wellhead and the next
one/two intermediate joints will typically have a greater wall thickness (e.g., 1.5 in.
instead of 1.0 in.) to provide sufficient design-bending strength. This ensures that the
higher bending strength 1.5 in. wall pipe extends b e lo w th e co m p e te n t m u d lin e .
Normally, the larger, higher bending strength pipe is only required for the upper 80 ft
and a pipe with less wall thickness can be used for the remainder of the string.
Due to the normal 30 or 36 in. OD size for typical structural casing used, the API
Specification for Line Pipe is used for specification of wall thickness and grade. Weld-on
connectors, either threaded or squinch type are normally used, and information on
tensile and bending should be obtained from the manufa ctu re rs ca ta lo g .
7 - 27
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
In general, quick stab or squinch type connectors have looser manufacturing tolerances
than do threaded connectors of the same size, wall thickness, and grade. Typically, this
means that threaded type connectors have more bending strength and pressure rating
than quick stab connectors of the same size, weight, and grade. All structural casing
welds on connectors use an o-ring seal for pressure containment.
The quick stab connectors all use a pin up by box down approach, where a
load-bearing snap ring inside the box latches into a load bearing profile on the base of
the pin. Common quick stab connectors are the Vetco ALT-2 (Figure 7.16) and Drill-
Quip HD-90.
Threaded structural casing connectors typically use an easy to stab, pin up by box down,
aggressive fast pitch thread that can make-up with as little as - turn. Common
threaded connectors used are the Vetco RL-1 (Figure 7.17), RL-4, and Drill-Quip H-90
MT/QT.
Generally speaking, quick stab connectors are only used when structural casing will be
cemented in a predrilled hole. This is because of the large cross sectional area
presented by the quick stab connector makes casing difficult to jet and may limit the
number of joints that can be jetted, increasing the risk of insufficient structural pipe being
set or excessive stick up.
Structural casing that is used for jetting operations is typically equipped with threaded
connectors that are more streamlined and have less cross sectional shoulder to impede
the casing as it is jetted. Connectors flush on the outside diameter are also available.
7 - 28
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Jet the structural casing directly into the seafloor (Figure 7.18) using an internal
jetting string, or
Drill the hole (Figure 7.19) for the structural casing tailored in-depth to accept the
planned structural casing string, leaving the necessary stick up above the mud
line while placing the casing float shoe on bottom.
If the structural casing can be jetted, typical rig economics will dictate jetting as the most
cost efficient technique to use. Structural casing with near flush joint weld on connectors
are typically used.
Bottom conditions and seafloor soil strength determine if the structural casing can be
jetted in. If the structural casing cannot be jetted, a hole will be drilled and the casing run
and cemented. Bottom conditions that typically prohibit jetting are a hard sandy bottom,
coral, and boulders or glacial debris.
Returns through
running tools
Mud Mat
Structural Casing
Returns to TGB
seafloor
Seafloor
Figure 7.18 Jetting Structural Casing Figure 7.19 Drilling Hole for
into Place Structural Casing
7 - 29
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
During jetting operations, a pilot hole is drilled by a bit powered by a mud motor. As the
casing forces itself into the formation under its own weight, it not only wedges additional
formation into the bit where it is drilled up by the bit but also forms a continuous seal.
Cuttings are then carried up the internal annulus and ejected through ports in the
running tool.
The weight of the casing assembly is slacked off from an initial start weight of
approximately 10,000 pounds, gradually increasing with penetration to nearly 80% of
total available weight at full depth. The controlled light starting weight aids in setting the
casing at or near vertical while the 80% maximum weight provides a safety margin to
keep the neutral weight point below the running tool.
The washing out of the formation inside the structural casing eliminates the internal
friction, leaving only the external soil friction which then lets the casing force itself into
the formation by its own weight. However, as the casing penetrates the formation, side
frictional forces absorb ever-increasing portions of applied weight until very little,
if any, remains for penetration of the casing into the soil. The string is worked until
drag (overpull) is lowered to an acceptable level that allows an effective ROP
within WOB guidelines.
The casing jetting is usually done with at 9 5/8 in. mud motor with a medium to low
torque range. The important factor is to ensure that the motor provides a flow rate of
1000 1200 gpm. If the motor is unable to provide this flow rate, a jet sub is typically
included in the jetting assembly to increase the flow and assist in cleaning the inside
diameter of the casing.
The most common bit for jetting 30 or 36 in. casing is a 26 in. soft formation rock bit.
Other bit sizes that can be used are 20, 24, 28 or 31.5 in. bits. The 38 and 31.5 in. bits
are typically special order bits. The space out of the bit is important to hole enlargement
ahead of the bit and to allow the bit to drill hard streaks that may be encountered. The
recommended space out for the bit is 6 in. (+/- 3 in.) below the bottom of the casing. For
a typical 26 in. bit, the nozzles will be approximately 8 in. inside the casing when the
bottom of the cones extend 6 in. outside the casing.
7 - 30
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7 - 31
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
When tallying the internal jetting string components, items such as the wellhead running
tool should be split to provide measurements of the tool length above and below the top
of the wellhead as illustrated in Figure 7.21. The structural casing and jetting string
should be tallied to provide approximately 6 in. of bit stick out (+/- 3 in.) below the casing
as illustrated in Figure 7.22. If required, the jet shoe joint may be cut and beveled to
match the jet string and provide the proper stick out. If the bevel joint is cut, caution
should be taken to ensure that the joint is cut straight since an uneven cut may cause
the casing to build angle as it is jetted.
Figure 7.21 Running Tool Measurement Points Figure 7.22 Recommended Bit Stickout
The jetting assembly and cam actuated running tool (CART) are made and stood back in
the derrick prior to running the structural casing to minimize the time casing remains
suspended from the rig in open water.
Prior to running the structural casing, components such as the mud mat, PGB or GRA
must be installed in the moon pool to allow the casing to be run through the opening.
7 - 32
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7 - 33
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
After makeup of the wellhead housing, it is important to record the weight of the casing
for use in determining the neutral weight required to release the running tool after the
casing is in place.
Note: Since the weight of the structural casing can be quite large, the capacity of the
spider beams or BOP transporter should be verified to ensure that adequate capacity is
available.
Slope Indicators
Cement Ports
7 - 34
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
26 in. bit.
9-5/8 in. low torque mud motor with 0o
bend and stabilizer sleeve. If the drill
ahead tool is used, the near bit
stabilizer may be omitted to prevent
angle build while drilling ahead.
Float sub with solid float. A solid float
is used to prevent U-tubing up the drill
string on connections and to prevent
flow up the drill string if a kick is taken.
If a jet sub is used, the float should be
installed above the jet sub.
Jet sub (required only if the flow
capacity of the mud motor is less than
the flow rate required 1000 gpm)
String stabilizer.
Drill collars, space out subs, and
crossovers as required.
If a drill-ahead tool is being used, the
BHA should include needed MWD
Figure 7.25 Installation
tools.
Of Jetting Assembly With
Structural Casing
Suspended In Moon Pool.
7 - 35
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Note: If using Vetco MS 700 retrievable guidebase (RGB), ensure the running tool has
a hold-down mechanism to prevent early release of RGB.
Bull plugs
7 - 36
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
To allow circulation while jetting in the casing, bull plugs are removed from the top of the
running tool. Prior to running the assembly subsea, the weight of the casing and jetting
string should be recorded to use in determining the neutral weight required to release
the running tool after jetting the casing into place.
After stabbing the running tool into the wellhead, the ROV should verify the bit stick out
below the casing (Figure 7.27) and the weight of the jetting string should be recorded.
Since depth perception is difficult when viewing equipment with the ROV (Note bit
extension photo), a reference mark can be painted on the bit indicating the desired
extension distance (six inches) to assist in determining the proper bit extension.
Figure 7.27 Bit Stickout As Observed By ROV After Making Up Wellhead Running
Tool.
7 - 37
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7 - 38
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Have ROV check guidebase and guideline orientation to ensure that casing has
not rotated. ROV should also check running tool to ensure that it has not rotated
and record the position of each of the slope indicators.
Test the mud motor and ensure that pumps, valves, seawater and gel sweeps
are aligned and ready to use.
Calculate footage for last stand to be jetted to ensure that at least 30 ft will
remain when casing is at TD. If needed, singles should be added or removed
from the landing string.
Release boats that may be tied to the rig to prevent excessive rig movement.
ROV should then be positioned up current to monitor the jetting operations. When the
ROV is in position, the casing should be slacked off to tag the mud line and the depth
recorded as the murk line depth. It should be noted that depth will off by the stretch of
the drill pipe due the weight of the casing and landing string.
Re-check PGB
slope indicator
for change with
ROV and orientation
of PGB. Note any changes
in PGB inclination or orientation, so any required Figure 7.30 Tagging
corrections can be made. bottom with jetting assembly
and establishing location.
7 - 39
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
After recording the slope indicator reading, the ROV should then be repositioned at the
mud line to monitor jetting operations. If an MWD is in the inner jetting string, it can be
used to verify plumb of jetting string.
During jetting operations, a pilot hole is drilled by a bit powered by a mud motor and the
casing forces itself into the formation under its own weight. As the casing slides down
the hole, it wedges additional formation into the
bit where it is drilled up by the bit allowing the
casing to form a continuous seal with the
formation. Cuttings drilled by the bit are carried
up the internal annulus and ejected through ports
in the running tool (Figure 7.33).
7 - 40
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
After jetting +/- 50 ft below the mud line, the pumps should be increased to 1000 to 1200
gpm while monitoring the outside of the casing for broaching. During jetting operations,
the pump rate should be kept constant to allow the mud motor differential pressure to be
monitored.
To assist hole cleaning, high viscosity sweeps should be pumped at mid-stand and
before each connection. The pipe should also be reciprocated the full length and worked
until the drag frees up before making each connection.
7 - 41
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Since set down weight can be as much as 100 kips less due to WOB when the casing
reaches TD, it can be difficult to determine if the casing is at the correct depth from pipe
measurements at the surface. If the water is too cloudy for the ROV to see reference
marks on the casing, the following procedure (Figure 7.35) can be used to determine
the distance remaining to be jetted:
Mark the drill pipe at the rotary and record the string weight with current WOB.
Shut down pumps and work casing up quickly to bring the dirt line mark on the
casing above the plume.
Using the ROV, record the distance from the dirt mark to the desired location on
the reference marks painted on the casing. This the distance remaining that needs
to be jetted.
Slack the casing back to the mark place on the drill pipe prior to picking up the
casing and measure in the remaining distance to be jetted. Typical stickup for the
structural casing is 7 10 ft.
At TD, a high viscosity pill is typically pumped and casing allowed to soak while
supporting the landing string with the compensator to allow wall friction to secure the
casing in place. After shutting down the pumps and allowing visibility to clear, the angle
from the slope indicators should be checked with the ROV.
7 - 42
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
If a drill-ahead tool is used, the running tool and inner stem are released allowing the drill
string to be slacked off. After releasing the running tool, the first 15 to 20 ft should be
drilled without pipe rotation and with reduced pump rate to prevent damage to the
running tool and wash out below the structural casing. On the trip out of the hole after
drilling the hole for the conductor casing, the stem is pulled up into the wellhead running
tool and the running tool retrieved to the surface.
Note: Before tripping in the hole with the casing and jetting assembly, the single above
the running tool should be painted white to provide an indicator of the stem location so
that the running tool is not pulled out of the wellhead on a wiper trip.
7 - 43
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
A common method is to establish the maximum weight-per-ft using that, which equals
the casing and BHA weight below the mud line. A simpler method is dividing the casing
and BHA weight by the length and rounding down to a convenient weight.
The applied weight maximum assures the majority of compression in the casing is below
the mud line where it is supported and limits bending forces above the mud line. It also
establishes a weight that should be reached before reciprocation is considered to
prevent overworking of the soil.
Applied weight must never exceed the total available weight (casing, BHA, guidebase),
as the landing string will be put into compression and quickly bend. A 20% safety margin
should be used under normal conditions.
Another weight that is critical is the weight that places the neutral weight point at
the running tool. If this condition is reached, it puts the running tool in a condition
where the stem could turn and possibly release the tool or over-torque the tool to
the latched position.
7 - 44
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Failure to work the string in an effective and timely manner is one of the chief causes of
casing being set too high. Excess weight application can cause the angle to deviate from
vertical and staying in one spot too long encourages soil erosion, which can weaken the
so ils a b ility to h o ld th e ca sin g , which will require additional soak time.
When the rate of penetration slows significantly with a constant applied weight, either the
weight must be increased within the limits for the current depth or the string must be
re cip ro ca te d to le sse n th e so ils grip on the casing.
The frequency of working cannot be predetermined and can vary with each well with soil
conditions dictating the frequency that the pipe must be worked. Using the WOB
guidelines helpd prevent over or under working the casing.
Monitor initial pick up for excess overpull and then work at normal rate.
Work the pipe at a fast pace (>1 ft/sec) to liquefy soil and reduce the friction.
Work at a constant pace as the rate influences weight indicator reading.
Work at a consistent pace to enable comparisons to be made at different depths.
Work until overpull has been reduced to an acceptable level relative to hole
depth.
Overpull in upper section is reduced to less than 10,000 pounds
Overpull is allowed to slowly build in lower sections as conditions warrant.
Overpull should be only be reduced slightly as setting depth is neared.
Work before each connection to near zero overpull.
Return to bottom and gradually bring rate and weight back up, do not spud
bottom.
The string must also be worked to near zero drag before connecting, as the string will be
stationary for the time required for makeup. This is the main reason that planning should
be done to eliminate a connection in the last 30 ft.
7 - 45
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Mud motors may impart reactive torque to the left as the bit turns to the right. This
problem may be more pronounced with higher torque mud motors. During jetting
operations, many casing strings turn to the left, but a substantial number also turn to the
right. Other causes of this rotation include the formations and torque which is trapped
during connection make up and worked up the string. On the typical job, the rotation of
the guidebase is not such that it needs correcting.
If necessary, the guidebase rotation can be corrected and should be done with the string
as high as possible. This is another reason that adjustments should be made to the drill
string before beginning to allow a long run to bottom on the last stand (i.e., pick up or
layout singles to ensure connection will not be made during last 30 ft). This allows the
most pick up distance.
The turning of structural casing must be done with caution or not at all. The major
concern is the possibility of turning or releasing the running tool. The string should only
be turned in small increments and only with close monitoring. Turning the string works
because of two factors, the tool is difficult to turn when it is not at neutral weight and the
friction has a limited amount of force that it can apply to hold the casing in place. When
the casing is moved upward, friction attempts to hold the casing (tensional force),
leaving little if any friction to counteract the torque force. Torque virtually disappears
when the string is moved vertically and, for this reason, the string can be turned at or
near full depth if required.
Assure each step will be done with caution while monitoring or do not do it.
Make sure the running tool is not at neutral weight point.
Pre-load 2000 to 5000 ft/pounds of torque in the top drive keeping below level
that affect running tool or drill string connections.
Have Driller turn string in small increments of 90 degrees of less while checking
the running tool.
Return to bottom and check to see if turn was achieved. Check running tool.
Repeat procedure until desired effects are achieved, monitoring during the entire
operation.
If turn achieved, release top drive brake to eliminate any trapped torque.
Also, some PGBs, like the Vetco SG-5 may be unpinned and rotated to the correct
guideline orientation and then pinned back by the ROV.
7 - 46
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
A TGB is typically not used in water depths greater than 2000 ft or when jetting in
structural casing. If a TGB is not used, the ROV will normally place marker buoys next to
the structural casing hole to assist in locating the hole when stabbing tools or casing
(Figure 7.36).
7 - 47
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
The hole for the structural casing is typically drilled with a pilot bit
and hole opener (Figure 7.37). For 30 in. casing a 26 in. bit x 36 in.
hole opener assembly is used and for 36 in. casing, a 26 in. bit x 42
in. hole opener assembly is typically used. To prevent bit darting, a
full gauge stabilizer or tandem hole opener assembly is run. The
pilot bit can be thread locked, to prevent inadvertent downhole back-
off of bit.
To guide the assembly into the TGB, Four in. (hemp) guide ropes are typically
installed about 10 ft above bit, centering the assembly between the guidelines. As the
assembly is stabbed into the TGB, the four guide ropes will break free and allow the
assembly to enter the wellbore. For areas with high environmental loads, a second set of
guide ropes may be required and will be typically installed 10 to 15 ft above the first set
of guide ropes.
7 - 48
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
After stabbing into the TGB, the hole will typically be jetted or drilled with a very slow
rotary until the hole openers and/or stabilizers are below the TGB. In addition, for the
first 40 ft the hole is typically drilled with a reduced flow rate and minimal weight and
rotary to ensure that the assembly does not become entangled in the TGB or guidelines
and to prevent washing out below the TGB. After the first 30 to 40 ft are drilled the flow
rate is typically increased to 1000 to 1200 gpm and the interval drilled with seawater and
high viscosity sweeps to clean the hole. At TD, the depth is confirmed and the indicator
mark on the BHA at the top of the TGB funnel is confirmed as the primary reference
mark for TD. RKB pipe measurements are also confirmed, taking into account tide
changes adjusted from guideline tide gauge measurements or tide charts.
At TD, the hole will typically be swept with a high viscosity sweep and a wiper trip made
to the mud line. After the wiper trip, the hole will typically be filled with high viscosity mud
to assist keeping the hole open while running the casing.
Since the angle of the BOP stack will be reflected by the structural casing, a survey
should be taken at TD to determine the hole angle. Hole angles less than 1.5o are
preferred. If operating in an area with deep currents, hole angle may be affect by the
offset of the BHA when it initially tags the bottom. On a 3300 ft water depth well, drilled
offshore of Trinidad in 2000, with a 2.0 knot current extending down to 2000 ft, the BHA
had an initial angle of 5+ degrees when surveyed with the MWD tool at 30 ft below the
mud line. To correct for this angle, the rig was repositioned over the wellbore after a
location had been established and an additional survey taken to confirm the angle was
within acceptable tolerance. Drilling in open water with high current may also require the
use of a mud motor to minimize drill pipe fatigue potentially caused by the offset and
bow in the drill string.
7 - 49
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7 - 50
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
If TGB was run, connect the 4 guide ropes about 10 ft above bottom of float shoe to the
guidelines. Guide ropes are typically attached to the casing by welding an attachment
(e.g., chain link, large nut, flat bar ring) at 90 degree intervals around the casing with the
guide ropes attached using the same
technique as with 36 in. drilling BHA. After
the casing enters the water, it should be
filled with seawater until the ROV verifies
that the water is flowing out of the shoe
joint.
7 - 51
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7 - 52
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
While tripping to the seafloor with the casing, the 4 guide ropes, guidelines, CART
should be monitored with the ROV, and the drill crew should ensure that the running
string is not allowed to rotate. Prior to entering the wellbore (approximately 20 ft above
seafloor), the motion compensator should be opened and pressured to support the entire
weight of the drill string.
While monitoring with the subsea TV or ROV, the float shoe should be stabbed in the
wellbore. During stab-in, the set down weight should be limited to 5 kips to prevent
buckling of the structural casing. If the casing is being stabbed into a TGB, the
guidelines and slope indicator should be monitored to determine if the casing is
tagging/hitting the as it enters the wellbore. If necessary, the guideline tension may
be adjusted to reposition or change the angle of the TGB.
Continue to run in the hole with the casing limiting the set down weight, to a maximum of
80% of the buoyed casing weight below the mud line. Tag bottom with the casing and
confirm proper stickup and slope indicator readings with the ROV. If the angle from slope
indicators is excessive, the rig may be repositioned to align the casing vertically.
If the casing extends too deep, or if the wellbore is unable to support the casing, the
casing is typically supported with the motion compensator during cementing and until the
cement can support the weight of the casing. If this is down, the driller needs to monitor
and adjust weight down as required to keep incoming tide from picking up on both
conductor and structural casing.
Prior to landing out the casing, the cementing manifold that is stood back in the derrick is
made up to the landing string. The typical cementing manifold typically consists of a drill
pipe double, safety valve, side door pump-in sub or top drive cement head, safety valve,
and a pup joint for proper space out. The cementing stand is typically spaced out such
that when the casing is landed out, the lower safety valve is about 12 to 15 ft above the
rig floor at maximum tide and heave.
7 - 53
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Cementing the structural casing is similar to most cement jobs except that returns must
be monitored subsea with the ROV. Listed below is a summary of the typical steps for
cementing the structural casing:
7 - 54
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
If the slope indicator changes when the string is slacked off to neutral weight, the casing
weight is picked back up and the casing is held in place until the cement surface
samples harden.
7 - 55
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
CONDUCTOR CASING
In floating drilling, the next string of casing to be set after structural casing is conductor
casing. The most common size for conductor casing is 20 in., 133 pounds/ft or 169
pounds/ft. The purpose of this casing string is to provide sufficient hole integrity to drill
the surface hole. This casing string will include the 18-3/4 in. high-pressure wellhead
housing and will typically be set to a minimum of 1000 ft below the mud line (BML) and
commonly set around 2000 ft BML. The BOP stack will be installed onto the high-
pressure wellhead after the conductor casing is set to provide a well control barrier for
the remainder of the well.
Bending/Buckling.
Burst.
Collapse.
Connector selection:
Make-up.
Bending strength.
7 - 56
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7.4.2 BENDING/BUCKLING
Since the structural casing is designed to accommodate all bending loads, the main
buckling and bending risk for 20 in. conductor casing occurs when it is run. This is
because it is always run in open water where there is no lateral support. The following
causes bending and buckling loads imposed on the conductor casing:
Vessel motion can place large bending loads on the casing when it is sitting in
the slips. This problem is mainly associated with the older smaller drill ships and
semisubmersibles that experience excessive roll. Excessive vessel motion can
cause the bending moment on the casing at the rotary where the casing is fixed
in the slips. This problem is exaggerated as the casing weight increases and the
pipe becomes more fixed (unable to rock) in the slips.
Deep currents and currents greater than 2 knots can place large bending loads
on conductor casing while it is being run. Anytime current can push the 20 in.
casing against the side of the moon pool; bending failure of the casing is a real
risk. High currents can also cause vortex-induced vibration, which can cause
fatigue failure.
The most common buckling risk to conductor casing is excessive set down
weight from tagging a bridge when running the casing. This can be mitigated by
good running procedures and practices; and by always running 20 in. casing in a
clean hole with sufficiently dense spotting mud in the hole. Unsupported casing
can be difficult to detect when working in open water since the weight indicator
typically does not change as the pipe bends in open water.
The largest buckling load in designing 20 in. casing is the weight of all
subsequent casing strings, the weight of the inner cementing string, and the
weight of the BOP stack, assuming top 800 ft of casing unsupported by cement
and no load sharing with the structural casing string.
7 - 57
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Current Speed
Current Speed
7 - 58
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7.4.3 BURST
The 20 in. conductor casing should provide sufficient burst resistance so that the
formation will always fail before the casing. Typically, 20 in. 133 ppf X-56 or 20 in.
169 ppf X-56 casing is used as conductor casing on floating rigs. This casing has an
API burst of 3060 psi/4500 psi.
This burst capability of the conductor casing is important because the well will be shut-in
if a kick occurs and not diverted. In practice, the BOPs, not the diverter, will always be
the preferred immediate response to a kick taken while drilling below conductor casing.
When 20 in. is set 1000 ft or deeper below the mud line, the potential weaknesses of the
Regan type diverter used on floating rigs and the slip joint inner barrel packing typically
make shut-in the safest option.
7.4.4 COLLAPSE
The most likely threat of collapse to the 20 in. conductor casing string is human error in
not filling the casing and/or landing string as the casing is run. One common mistake that
has caused the collapse of 20 in. casing is failure to consider the hydrostatic exerted by
the fluid column in the landing string. In deepwater, this can be the majority of the
collapse pressure exerted on the casing. The additional pressure exerted by heavy pad
mud spotted in the conductor hole and/or cement in the annulus should also be
considered when verifying the collapse resistance of the casing.
Using heavier pipe such as 133-ppf versus 94-ppf can give roughly three times more
collapse resistance. However, procedures and practices must still be used to ensure that
every joint of casing is filled and all of the air is displaced from beneath the running tool
as the casing is run.
Typical connectors used for conductor casing are the Vetco RL-4S, RL-1 or Dril-Quip H-
90 connector in box up by pin down mode for this casing string.
7 - 59
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
If the well kicks on a shallow water location, the resulting gas boil will typically push
the rig off to one side of it. As the brakes are released on the down-wind anchor
winches, the potential energy of the mooring system moves the rig off location.
Increasing water depth mitigates the risk of fire and loss of water buoyancy
from a kick at the seafloor.
As grave as having the well kick at the seafloor beneath the rig is, it is less
risky than having a riser in place. The riser provides a large capacity conduit
to take the kicking well flow to the rig floor, where the diverter system may be
inadequate to handle the flow.
Drilling the conductor hole with a pin connector and bringing mud returns to the rig
can be beneficial when working in shallow water. But, it would most likely cause lost
returns when used in water depths greater than 1000 ft due to the increased column
height above the structural casing shoe.
7 - 60
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
A pilot hole is used to assist in well killing since the smaller annulus provides additional
ECD and less volume to be filled with mud. A typical pilot hole size is 9 7/8 in. and is
drilled with 8 in. drill collars and seawater. Pilot holes are generally used in one of the
two following formats:
Position the rig off location 300 to 500 ft and drill the pilot hole to the proposed
conductor casing setting depth. This option allows shallow reservoirs to be explored
and the final conductor hole depth to be adjusted based on shallow hazards
encountered. The disadvantage to this option is that it may provide a broaching path
to the seafloor from the final wellbore location and it can be difficult to plug and
abandon the pilot hole.
Set the conductor casing and drill the pilot hole to conductor casing setting depth
beneath the structural casing. This method also provides the smaller hole for well-kill
operations and can be more economical since it does not require the pilot hole to be
plugged. The disadvantage of this method is that after drilling into a shallow hazard,
the hazard must be isolated to allow the hole to be opened to full bore. Loss of the
pilot wellbore due a shallow flow could also cause the structural casing and other
wellbore to the lost.
After drilling the pilot hole, it is typically opened in one pass with stacked hole openers
(15 by 26 in.).
If prior experience in a given area indicates this hole can be drilled with seawater and
shallow seismic indicates no hazards, then the conductor hole section can be drilled with
a full size bit. The conductor hole is typically drilled with seawater using high viscosity
gel sweeps and wiper trips to clean the hole. For deepwater locations, drilling is usually
performed with a rotary assembly, but precautions must be taken to ensure the drill
string remains in tension in the open water section. It is not uncommon to find bent joints
of drill pipe or heavy weight drill pipe after completing the open water section on a
deepwater location. If the location is prone to high currents, it may be necessary to drill
the open water section with a mud motor to minimize the fatigue on the pipe as it is
rotated in open water.
7 - 61
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
When drilling the conductor hole interval, it is typical to maintain a volume (400 to 500
bbls) of weighted kill mud (12.0 to 14.0 ppg). The actual volume and weight of this fluid
is usually determined by the dynamic kill analysis, rig storage capacity, and the
perceived risk of encountering shallow gas. If a pilot hole is drilled, this mud would be
used to perform the dynamic kill and provide overbalance on the formation. If a full
gauge hole is drilled, the volume of weighted mud would be available to spot in the hole
after reaching TD and to stabilize the well if small water or gas sands were encountered.
In the GOM, shallow water flows (SWF) are common in some deepwater regions and
are routinely drilled with a weighted mud while allowing returns to exit at the seafloor.
This method provides the necessary hydrostatic below the mud line to control the SWF
and allows the interval to be drilled and isolated with casing. Depending on the interval
to be drilled, this method can require 10,000 15,000 barrels of weighted mud to
successfully drill the interval.
7 - 62
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Since the conductor casing does not provide the bending strength required to support
the wellhead free standing above the mud line, it is critical that the 20 in. casing go all
the way to planned setting depth to properly land out onto the low pressure wellhead.
Since pup joints are not used with the conductor casing, the casing is typically measured
beforehand and the hole depth drilled to match the casing length to ensure that sufficient
rat hole remains for fill as the casing is run. Rat hole lengths typically range from 30 to
50 ft depending on hole conditions and experience in the area.
To minimize the time that the hole is open, the following items are typically preformed
out of critical path:
Prepare the 18 3/4 in. high-pressure wellhead joint either on the wiper trip or prior to
drilling the conductor hole by:
Painting white indicator rings around the joint every 5 ft from the landing shoulder
of the high-pressure housing down and one-ft indicators between the rings.
These would be used to measure unexpected premature stick up.
Measure weld on centralizer ribs to ensure that they will go into the low-pressure
wellhead housing.
Inspect all sealing areas in 18-3/4 in. wellhead housing for scoring.
To provide for easy make up of the 18-3/4 in. high-pressure wellhead joint, an easy
to stab, non threaded connector may be used to compensate for the top heavy hard
to stab wellhead. This is especially important on rigs that are sensitive to rig motion.
If guidelines are being used, four chain links are welded onto the 20 in. shoe joint at
360o, 90o, 180o, and 270o above the float shoe to provide an anchor point for the
rope guides. Distance from shoe for placement of the links is determined by the
height of the guidepost to ensure that shoe stabs into structural casing before the
guide ropes break. A typical distance is post length plus five ft.
Also, a rotating ring can be installed on the casing between stop collars and rope
guidelines connected to it at 360o, 90o, 180o, and 270o.
Paint depth marks on the shoe joint at five-ft intervals to assist the ROV video.
Clean connectors, install o-rings, and replace protectors. Visually inspect conductor
casing for foreign material that may plug the float shoe.
7 - 63
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Since the landing string requires rotation to release the wellhead running tool, the casing
is typically landed with the landing string made up into the top drive. Prior to beginning
casing operations, a cement stand consisting of either a top drive cement head of a side
door pump-in sub with safety valves located above and below is made up into a stand of
pipe and placed in the derrick. To allow for proper space out of the cement head above
the floor, singles may need to be added or removed from the landing string as the casing
is run in the hole. If changes to the landing string are required, it should be made during
the first couple of stands to prevent the long delays after the casing enters open hole. A
typical space out for the cement head is 15 ft above the floor to provide contingency for
rig offset and heave.
As the casing is made up, the float shoe joint should be filled with seawater and the
observed in the moon pool to ensure that the water can drain freely. If guidelines are
used, the guide ropes are connected to the chain links welded to the shoe joint and
attached to the guidelines. Guide ropes are usually attached to the guidelines (Figure
7.42) by either looping a short section of chain around the line that can fall away when
the rope breaks from the chain or by attaching small shackles around the guidelines. If
shackles are used, they will remain on top of the guideposts and could cause
interference for other guidance equipment.
7 - 64
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Since the connectors that are typically used on conductor casing are quick stab (Figure
7.43), it is important to ensure that the proper torque is applied to all connections and the
locking tabs are installed. Quick stab connections can back-out with as little as 1/4 turn,
especially with weight suspended below. After making up the first joint into the shoe
joint, it is typical to energize all locking tabs to provide added resistance to prevent
backing off the joint while drilling the cement and float shoe. For the remainder of the
casing, only two locking tabs are typically used to allow the two remaining tabs to be
used as backup should the casing need to the laid down and rerun. During makeup, any
joints that do not align properly to allow the tabs to be energized should be rejected and
replaced. If the wellhead joint is equipped with a quick stab connector, all tabs should be
energized to prevent the connection from backing out during P&A cutting operations.
To assist the ROV in identifying the movement of the casing with video camera, white
reference lines are typically painted at each connection. This indicator line enhances the
video and provides a reference as the pipe moves into the wellbore.
7 - 65
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Depending on testing requirements after the BOP is installed, the nominal seat protector
(NSP) may or may not be installed in the wellhead before it is run. For information on the
NSP, refer to Section 8.
7 - 66
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
The cement stinger is run by installing a false rotary type C-plate on top of wellhead
(Figures 7.44 and 7.45) and using a small set of bowl and slips used to secure the drill
pipe. If a small set of bowl and slips are not available, two sets of drill pipe elevators can
be used to install the cement stinger.
7 - 67
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
After the cement stinger is installed, the 18 in. wellhead running tool is made up to the
stinger and the running tool secured to the wellhead by wellhead technician. To provide
a reference for alignment of the running tool alignment key and rotation of the tool stem,
a vertical anti-rotation mark should be painted on the 18 in. CART and the key slot
location. These paint marks will be used to visually confirm proper make up of the 18
in. CART into the wellhead as the casing is run and proper release of the 18 in. CART
after the cement job.
While running the cement stinger and working around the top of the wellhead, it is
important that the sealing area on the wellhead be protected and that the maximum
recommended torque be applied to the drill pipe-cementing stinger.
For wells where the water depth is less than the casing length, it will be necessary to
stab the casing into the wellbore and makeup the cement stinger while the casing is
stationary in open hole. To minimize the possibility of sticking the casing, operations
should be planned to minimize the time that the casing is stationary.
Located on the top of the 18 in. wellhead running tool are bleed ports that are used to
vent the air that is trapped beneath running tool after it is installed. To vent this trapped
air, the wellhead must be lowered to the waterline and seawater circulated through the
cement stinger to fill the void area and vent the trapped air (Figure 7.46). After the air is
vented, the wellhead is raised above the splash zone to allow the wellhead technician to
be lowered on
a riding belt to
close the
bleed ports.
Note: A void
filled with air
is caused by
the inability
to fill the
casing on
the inside
above the
height of the
sealevel on
the outside.
If the casing
is already
stabbed into
the wellbore Figure 7.46 Air Trapped in Casing
when the
running tool is installed, the wellhead is sometimes lowered below the waterline to allow
the void to gravity fill with seawater. This is necessary since circulation through the
landing string and cement stinger could also displace some of the pad mud from the
open hole.
7 - 68
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7 - 69
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
As the casing is stabbed into the wellhead, the guide ropes will land on the top of the
guideposts and break away as the casing is lowered. If currents or other environmental
forces have offset the casing to where the guide ropes do not properly align the casing,
the following are typically used to align the casing:
If casing will not go down at maximum set down weight or if the casing is not moving
subsea to coincide with the movement of the casing at the surface, the top drive is
typically made-up and mud or seawater circulated and washed through obstructions.
If weighted mud was spotted in the hole and circulation is required, it is important to
remember that the seawater inside the casing will be circulated into the open hole and
will result in a reduction of hydrostatic pressure. If circulation is required and hydrostatic
pressure must be maintained, weighted fluid should be displaced into the casing before
it enters the wellbore, and a volume of mud should be available to use to wash the
casing to bottom, if required.
If extreme hole conditions exist, where heavy mud must be spotted in the open hole, and
high set down weights are required to get the casing in the hole; a stab-in float collar can
be used to allow the cement stinger to be stabbed in and sealed to the float collar. In this
configuration, the annulus between the stinger and the casing can be filled with weighted
mud to provide additional casing weight, and the volume of seawater that must be
circulated from the casing is minimized.
Another change that will be noted if weighted mud was spotted in the wellbore will be a
loss in casing weight as the casing enters the wellbore. This loss in weight is caused by
the buoyed effect of the casing since the weighted mud will be on the outside with
seawater on the inside of the casing. This reduction in weight must be considered when
determining the available casing weight below the mud line to prevent buckling the
casing in open water. This loss in weight is sometimes mistaken for an increase in drag
as the casing is lowered. To determine if the loss of weight is drag or from the buoyed
effect (casing floating), the pick up weight can be used for a comparison.
7 - 70
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
When the casing reaches total depth, a cementing stand from the derrick is typically
made up to the top drive and used to wash down the casing, if required, and land-out the
casing. When the last stand is made up from the derrick, the motion compensator should
be opened and aligned to land-out the casing on the wellhead and support the casing
and landing during cementing operations.
With the assistance of the ROV, the 18 in. wellhead is landed on the low pressure
wellhead with a set-down weight of 50 kips to allow the 18 in. wellhead to latch into the
low-pressure wellhead housing. After the weight is set down, the slope indicators should
be checked with the ROV to determine if the additional weight caused movement in the
wellhead housing. To confirm a proper latch into the wellhead, a 50 kips overpull test
above buoyed weight of casing, landing string, and air weight of blocks is performed.
After a successful overpull test, slack back to the original set-down weight and hold until
after the cement job.
Figure 7.47 High Pressure Wellhead Landed in Low Pressure Wellhead Housing
7 - 71
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Typically, the lead slurry will be an extended (prehydrated bentonite or sodium silicate)
lighter weight slurry (11.0 to 11.5 ppg) designed to bring cement to the seafloor, without
losing returns. The tail cement will typically cover 500 ft above the shoe and consist of
N e a t ce m e n t m ixe d fro m 1 5 .6 to 1 6 .2 p p g d e p e n d in g o n th e cla ss o f ce m e n t u se d .
Verify collapse resistance of 20 in. casing is sufficient for height of tail cement planned.
If required, reduce height of tail.
Slurry volumes for conductor casing are typically calculated using 100% excess of open
hole annular volume. Caliper logs or volumes calculated from mud circulation is typically
not available for this hole section. Cement tests should be performed for all slurries
using actual material samples, mix water from rig and under shallow formation
conditions (e.g. low temperature if operating in deepwater).
7 - 72
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Cementing operations for the conductor casing are typically very large and can take up
to three hours to mix, pump and displace. Mix and pump rates for the lead slurry can
range up to seven to eight bpm and with the tail slurry typically mixed at rates of four to
six bpm. High pump rates are beneficial in helping ensure good displacement due to the
large annular volume.
Since the cement stinger is +/-100 ft from the float shoe and the displacement volume
will be relatively small, the cement unit is used to displace the cement with seawater at
rates of six to eight bpm. During displacement, the pump rate is typically reduced to two
to three bpm prior to the cement exiting the cement stinger with the cement displaced to
50-70 ft of the shoe. When displacing the cement for the conductor casing it is important
to ensure that adequate cement remains in the casing to provide a casing test.
After displacing cement, the pressure is bled off to verify that the float shoe is holding.
If float is not holding, pump back the amount bled off and hold pressure until surface
samples are hard. If float is holding, slack off remaining 20 in. casing weight onto the
structural casing and check slope indicators with the ROV for change from vertical.
If no change in the slope indicator and the wellhead shows no sign of sinking, the
18 in. CART tool may be released.
If the slope indicator does change, hold casing weight with motion compensator for at
least four hours or until surface samples are hard. After the cement samples are set,
attempt to slack off 20 in. casing weight onto structural casing and recheck the slope
indicators.
7 - 73
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Once the conductor casing weight can be fully transferred to structural casing with
PGB slope indicator reading acceptable angle, release 18 in. CART and retrieve the
running tool and cement stinger. Caution should be taken as the cement stinger is pulled
from the wellhead to prevent damage to the sealing area within the wellhead and the
ring gasket area. When pulling out with the cement stinger, space out so that a
connection is not made with the end of the drill pipe stinger at the 18-3/4 in. wellhead.
7 - 74
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
-100
-200
Knots
-300 0.25 black dotted
0.50 cyan dotted
0.75 blue dotted
-400 1.00 green
Depth (m) 1.25 red
1.50 yellow
-500 1.75 magenta
2.00 black
-600 2.25 cyan
2.50 blue
-700
-800
-900
-1000
2/10 2/11 2/12 2/13 2/14 2/15 2/16 2/17 2/18 2/19 2/20 2/21
Date(2001)
7 - 75
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
When spudding a well in an area where high currents are expected, a profile should be
obtained prior to beginning operations so that equipment can be designed and/or
modified. Listed below are some of the potential problems and solutions that have been
used when performing open water operations in this environment.
Drill strings or casing may be subjected to vortex induced vibration (VIV) that could
cause failure of the casing or drill pipe. For conductor casing, strakes have been
installed to reduce VIV.
When initially spudding the bottom and establishing location with either a bit or
casing jetting assembly, the wellbore can be offset 200 to 300 ft from the surveyed
position at the surface. Even if the offset location is within the location tolerance, the
well will mostly likely to spudded with an unacceptable angle
When running large bore tubulars in the high current environments, drag from the
current may offset the pipe such that it will not safely pass through the rotary without
unacceptable drag. Options to work around this have been to, provide a slight list to
the vessel to coincide with the angle of the pipe, when working with a DP rig, move
the rig up current and allow the rig to drift with the current as the pipe is run, or use
stab-in float equipment and fill the casing with heavy mud to decrease the angle.
Unacceptable bending loads on the pipe or casing. High bending loads typically
occur at the slip area where the stiff bending moment arm exists. Work around for
this problem has been to use a centering device in the moon pool or to secure the
pipe on the rotary in a set of tapered elevators instead of slips. The elevators allow
the pipe to rotate on the tool joint taper and minimize the bending moment.
If the current is only high at the surface, the angle will decrease as the pipe is run and
additional weight is placed below the current. If the current runs deep as shown in
Figure 7.50, the offset will tend to get worse as long as the same size pipe is being
deployed. When running casing on the landing string, the angle will tend to decrease as
the landing string is run since a smaller cross sectional is exposed to the higher surface
current with the heavier weight suspended below.
7 - 76
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
7 - 77
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
The mud weight used is typically the maximum that can be used and still keep a
0.3 ppg margin between mud weight and formation fracture.
Where confidence of SWF sand depth prediction is high, the hole section can be
drilled with seawater and prehydrated gel sweeps until about 75 to 50 ft above
shallowest predicted SWF sand, and then use weighted mud.
Drill 1000 ft section of 26 in. hole blind at about 100 ft per hour, with a circulation rate of
800 1000 gpm. This requires a larger amount of mud than the rig can normally carry.
Thus, the rig would build a large volume of 16.0 ppg mud and then water back the
weight with seawater to that required (10.5 to 12.5 ppg) in the suction pit just before it is
pumped downhole.
When the required hole depth and rat hole are made, the well is displaced to
required mud weight with a low fluid loss mud, with low flat gel strength
(YP ~ 10 and PV ~ 15) to facilitate cementing. Density of spotting mud should be
sufficient to kill the SWF, but not so heavy as to fracture weak zones or balloon.
The ROV should monitor returns for SWF from the time the conductor hole is started
until surface casing is successfully cemented.
7 - 78
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
CONCEPT
Conductor casing by open hole annuli with SWF zones exposed must be successfully
cemented to provide a seal to eliminate SWF and to structurally support the conductor
casing. The current best practice for this is to use a fast-setting nitrogen foam cement.
The nitrogen reduces the density of the cement slurry to below the formation fracture
weight. The special fine grind of the cement causes the cement to have a right angle set
item, with no transition. This should preclude the SWF zone from flowing once the
cement starts to set. A typical inner cementing stinger will be run inside the conductor
casing to about 150 ft above the float shoe. Activities after mixing and displacing cement
are the same as would follow any conductor casing cement displacement. These would
include monitoring for wellhead subsidence while slacking off conductor casing weight
onto low-pressure wellhead housing and rigidly locking the 18-3/4 in. high-pressure
wellhead onto the low-pressure wellhead.
Circulating and conditioning mud to cement: Once the conductor casing is landed
out with 50 kips down, the cement job will begin. Except for the 50 bbl lead spacer
ahead that is 0.2 ppg heavier than the kill mud, the well will not be circulated prior to
cementing. The ROV will have jetting tool ready to use and stand by to observe open
cement ports on low-pressure wellhead housing. If there is any question that the cement
ports might be plugged, the ROV should clean them out.
Cement slurry design: Cement slurries planned to isolate SWF consist of a large
foamed lead slurry and small unfoamed neat cement tail slurry. A 50-bbl spacer
weighing 0.2 ppg more than kill mud left in hole, should be pumped ahead of the
lead slurry.
Lead slurry:
Slurry volume includes 200% casing by open hole excess.
Lead slurry is designed fast set after about five hours thickening time.
Nitrogen is staged into cement going downhole to maintain density at
0.5 ppg > than mud weight left in hole.
Slurry is mixed and pumped at four to six bpm.
7 - 79
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
OPEN WATER OPERATIONS
Tail slurry:
Slurry volume includes 100% casing by open hole excess.
Tail slurry is designed to fast set after about 3-3/4 hours thickening time.
Lead slurry density 15.2 ppg.
Lead slurry is not foamed with nitrogen.
Slurry is mixed and pumped at four bpm.
Displacement:
Cement will be displaced at eight to twelve bpm with seawater.
Slow down displacement rate to three bpm for the last 20 bbls of displacement.
Displace cement to leave about 100 ft cement sump inside conductor casing.
Displace cement with cementing pump only.
Have ROV close all cement port ball valves immediately after displacement pumped.
Check float valve and continue per normal conductor casing cement job.
Safety:
Hold JSA meeting before rigging up and starting nitrogen foam cement job.
Ensure that all Chiksan connections and swivels are properly hobbled with
competent safety chains and clamps.
Pressure test nitrogen lines with water, not nitrogen.
Use hand held radios to ensure good communication between nitrogen pump,
cementing unit, rig floor, and cement bulk tanks.
7 - 80
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
8
CASING/CEMENTING OPERATIONS Section
OBJECTIVES
The intent of the material in this section is to cover the differences in wellhead and
casing/cementing operations conducted from a floating rig and the same operations
conducted from a rig with surface wellhead equipment. A basic understanding of
surface wellhead equipment and casing/cementing operations is required. Special
situations that may arise during these types of operations on a floating rigs are also
covered.
Describe the major differences between surface and subsea wellhead equipment.
List the number and size of casing strings that are run on a typical well drilled from a
floating rig.
Describe the two primary methods for actuating casing hanger seal assemblies and
two types of sealing elements.
Describe the major differences between subsea release wiper plugs and similar
equipment used during cementing operations with surface wellhead equipment.
State the procedure to take if a casing hanger seal assembly fails to test.
Describe the corrective action that must be taken if casing becomes stuck off bottom
on a well drilled from a floating rig.
8-1
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
CONTENTS Page
8-2
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8.1.1 INTRODUCTION
Wellheads, casing hangers and seal assemblies used at either the surface or subsea
must be designed to meet the following requirements:
1. The wellhead must have enough strength and stiffness to support the blowout
preventers during drilling/completion operations and Christmas tree equipment if the
well is produced.
2. The wellhead and casing hangers must be capable of supporting the weight of the
casing strings suspended from the wellhead.
3. The wellhead must provide a housing and sealing surface that, along with suitable
seals, is capable of containing fluids and pressures up to the rated working pressure.
It is difficult to meet these requirements at the surface and even more difficult subsea. In
addition, the subsea wellhead must be capable of resisting the bending moments
im p o se d b y th e flo a tin g d rillin g ve sse ls m o ve m e n t o ff lo ca tio n a n d , a lo n g w ith the
structural casings strings, the forces exerted by a tensioned riser. The first subsea
wellheads used for floating drilling rigs were adaptations of surface wellhead equipment
and were manufactured by CIW. Vetco and National Oilwell entered the subsea
wellhead market in the early 1970s. Many early floating rigs used low pressure (~ 5k
psi) two stack wellhead systems (typically 21-1/4 in. & 13-5/8 in.) that were bulky and
inefficient. After the mid-1970s, the Industry standardized on 18-3/4 in. 10k psi BOP
equipment with a few 16-3/4 in. systems used in special applications such as
dynamically positioned (DP) drillships. Beginning around the mid-1980s, most new
floating rigs and rig upgrades were equipped with 18-3/4 in. 15k psi BOP equipment
due to Industry demands. Deeper water and higher pressures required the development
of 18-3/4 in. 15k psi subsea wellhead systems with metal-to-metal seal assemblies.
Further challenges are pushing the Industry to develop 20k psi BOP and subsea
wellhead systems.
Refer to EMDC Drilling OIMS Manual, Element 3, Drilling Design Standards for a list of
acceptable subsea wellhead systems (based on successful ExxonMobil field
experience). At the time of this writing, the list includes systems from ABB Vetco Gray,
DrilQuip, Cameron, FMC and Kvaerner National. Vetco is currently providing about 40
to 50% of the subsea wellhead equipment used by the entire Industry. The remainder of
the market is divided among DrilQuip, Cameron and FMC, with National providing < 5%.
F o r sim p licity a n d d u e to th e a m o u n t o f e q u ip m e n t th a t is ru n w o rld w id e , V e tco s M S -700
system will be used for discussion and illustration. This is not meant to imply that this is
the best system or the only system to consider, but rather that it is representative of the
typical equipment that will be encountered. Actual selection should be based on specific
requirements, current experience, cost, availability, etc. The manufacturer must provide
detailed information on equipment specifications, running tools and procedures for the
equipment that is selected.
8-3
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
Typical subsea wellhead equipment is shown in Figure 8.1. Similar equipment with a
retrievable Permanent Guidebase (PGB) used with moored floating rigs is shown in
Figure 8.2. Figure 8.3 shows a Guidelineless Re-entry Assembly (GRA) that is used
with Dynamically Positioned (DP) rigs. The low pressure wellhead housing is run on the
structural casing (typically 30 in. to 36 in.) which can either be drilled and cemented or
jetted-in. The 18-3/4 in. high pressure wellhead housing is run on the conductor casing
(typically 20 in. to 22 in.) and lands-out and latches into the low pressure housing. The
18-3/4 in. high pressure housing provides a means to connect to the subsea BOP stack
(or subsea Christmas tree if the well is produced) and suspend casing strings that are
run below the conductor casing. Most subsea wellhead manufacturers allow their BOP
connector profile to be cut on other manufacturers wellheads to avoid the need to
change out the hydraulic BOP wellhead connector each time a different subsea wellhead
system is used. Operationally, the conductor casing and high pressure wellhead are run
on drill pipe or landing string. The high pressure wellhead is landed and latched into the
low pressure wellhead, and the conductor casing is cemented to the mudline. The
subsea BOP stack and riser are then run, and the BOP hydraulic connector is clamped
to the top of the high pressure wellhead. Drilling is then ready to proceed for
subsequent casing strings.
8-4
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
18-3 /4 H ig h P re ssu re
Wellhead Housing
7 C a sin g H a n g e r 3 0 .9 1
& Annulus Seal
9-5 /8 C a sin g H a n g e r
& Annulus Seal 5 4 .8 3
Low Pressure
Wellhead Housing
13-3 /8 C a sin g H a n g e r
& Annulus Seal
8-5
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8-6
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
Each string of casing that is run below the conductor is remotely landed and sealed in
the 18-3/4 in. high pressure housing, as shown in Figure 8.3.
Note: The casing hanger and seal assemblies (commonly called pack-offs) stack one on
top of the other inside high pressure housing. 13-3/8 in. casing is typically the first string
run, landed and packed-off inside the high pressure wellhead. After running the 13-3/8
in. casing, each subsequent string has its own hanger and seal assembly that land on
top of the previous seal assembly. In this example, 9-5/8 in. casing and 7 in. casing
have been run below the 13-3/8 in. casing.
Note: If the seal assemblies run inside the high pressure wellhead leak, pressure is also
applied to the outer and inner casing strings and shallower formations. This could cause
the outer casing to burst, cause an underground blowout or collapse the inner casing
string if the leak occurs during pressure testing. Unlike surface wellhead equipment,
subsea wellhead equipment does not have a means for monitoring or for relieving
pressure build-up in the casing annuli below each seal assembly. This is a major
difference between surface and subsea wellhead equipment. Great care must be taken
in running and testing the seal assemblies on subsea wellhead equipment. Procedures
for running, testing and repairing/replacing seal assemblies will be discussed later in this
section. Also related to the pressure build-up in the casing annuli is a phenomenon
known as Annular Pressure Build-up (APB), which is extremely critical on high
pressure/high temperature (HP/HT) subsea production wells or subsea wells that are
tied-back to surface structure. APB has resulted in the failure of several non-EM
operated wells in the US GOM. APB will be discussed further under Cementing
Operations.
8-7
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
Subsea wellhead equipment is designated by the inner diameter (ID) and pressure rating
of the high pressure wellhead housing. The required ID depends on the size of the BOP
stack that the floating rig is equipped with. Systems are available in 18-3/4 in. and 16-
3/4 in. sizes and 10k and 15k psi pressure ratings. Very few 16-3/4 in. systems are
currently manufactured, as their use is generally limited to the few remaining older
drillships that are still equipped with 16-3/4 in. BOP stacks. API Specification 17D (Spec
17D) covers subsea wellhead equipment. Standard subsea wellhead systems are
typically rated between 2.5 and 3.0 million ft-lbs bending and 6.0 to 7.0 million lbs load
capacity.
Bending load ratings are typically governed by the wall thickness of the high pressure
wellhead housings and how the high and low pressure wellheads interact together.
Standard subsea wellhead systems will generally have a high pressure housing outer
diameter (OD) of about 27 in. To obtain a higher bending rating, the high pressure
housing OD is increased (to as much as 30 in.), the high pressure to low pressure
wellhead housing interface is strengthened, and a special high strength wellhead
connector is required. The wellhead load capacity is the sum of the maximum combined
casing loads plus the test pressure load at the full rated working pressure. For an 18-3/4
in. inner diameter (ID), 15k psi working pressure wellhead, the test pressure load is
equivalent to 4.1 million (M) lb. Table 8.1 lists ratings for various manufacturers 18-3/4
in., 15k psi subsea wellhead systems that the student is most likely to encounter.
8-8
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
Most manufacturers offer both three-hanger and four-hanger high pressure wellhead
housings, although four-hanger housings are becoming less popular. A typical casing
program for the three-hanger housing is 36 or 30 in. x 20 in. x 13-3/8 in. x 9-5/8 in. x 7
in., with the three casings strings in bold type landed in the high pressure wellhead. For
the 4-hanger housing it is 36 or 30 in. x 20 in. x 16 in. x 13-3/8 in. x 9-5/8 in. x 7 in.,
again with the four casing strings in bold type landed in the high pressure wellhead.
With most four-hanger systems wellhead housings, a dummy 16 in. hanger must be run
if the 16 in. casing is not needed. If 16 in. protective casing is required, the current trend
is to run a three-hanger wellhead housing with a 16 in. low pressure (typically 5,000 psi
rating) hanger profile sub welded into the 20 in. casing below the high pressure
wellhead. This effectively converts the three-hanger wellhead into a four-hanger
wellhead and does not require a dummy 16 in. hanger if the 16 in. liner is not run.
8-9
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
Note: The hanger profile sub can be run directly below the 18-3/4 in. high pressure
housing (leaves none of the 20 in. casing exposed) or can be run deeper in the string
(requires higher burst rating for the 20 in. casing that is left exposed after running the 16
in. liner). The former option is desirable if there is concern with leaking 20 in. casing
connections whereas the latter option should be considered if there is a high potential for
sticking the 16 in. liner off bottom. The student should consult with experienced
individuals and local practice.
For deepwater applications where shallow water flow is a problem, most wellhead
manufacturers also provide a low pressure hanger profile sub below the low pressure
wellhead housing that allows running an additional string of 26 in. or 24 in. casing below
the structural casing. With the addition of an 11-3/4 in. liner hung off the bottom of the
13-3/8 in. casing, this brings the total number of available casings strings to eight:
36 in. x 26 in. or 24 in. x 20 in. x 16 in. liner x 13-3/8 in. x 11-3/4 in. liner x 9-5/8 in. x 7 in.
Several manufacturers (Vetco and DrilQuip) now offer large bore wellhead systems with
an additional 18 in. low pressure hanger profile sub run in the 22 in. casing below the
18-3/4 in. high pressure wellhead. This increases the total number of available casing
strings to nine: 36 in. x 26 in. x 22 in. x 18 in. liner x 16 in. liner x 13-3/8 in. x 11-3/4 in.
liner x 9-5/8 in. x 7 in.. Large bore wellhead systems will be discussed further under
Special Situations at the end of this section.
The subsea wellhead housing is subjected to the same bending forces as the structural
casing and must be able to resist these forces without failing or sustaining damage.
Although subsea wellhead housings are generally thick wall construction and made of
moderate to high yield material, bending ratings are especially important in deeper water
and for wells drilled from dynamically positioned (DP) rigs. Bending ratings for various
subsea wellhead systems are listed in Table 8.1. These ratings and the strength of the
structural and conductor casing must be designed to exceed the expected loads that will
be encountered during the life of the well.
Note: Most subsea wellhead manufacturers now offer an improved method to reduce
bending fatigue whereby the low and high pressure wellhead housings are rigidly locked
together. The rigid lockdown feature causes the two wellheads to act as one
component, preventing cyclic movement which could cause fatigue failure in the
conductor casing below the wellhead. Rigid lockdown should be considered for
production wells or any well drilled in a high current environment. Wellhead
manufacturers should be consulted for exact ratings, options and recommendations. For
critical and/or deepwater wells, it is also recommended that EM URC conduct a bending
analysis which includes both the wellhead and the structural and conductor casing
strings.
8 - 10
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8 - 11
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8 - 12
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
The high pressure housing will have a running profile for either threaded or cam-
actuated running tools. In addition to size, pressure rating and number of hanger
positions, the high pressure wellhead system must be specified for the expected service
conditions. Additional specifications include sweet or sour service (per NACE MR-01-
75), standard latch or rigid lockdown, bending moments and combined load ratings.
Subsea wellhead systems are available with up to 7.0M ft-lb bending moment and
7.1 M lb combined load ratings.
Note: The combined load consists of casing weight plus test pressure (e.g., MS-700
combined load rating of 7.1 M lb corresponds to 3.0 M lb casing weight + 15k psi full
bore test pressure). Also note that the higher bending moment ratings generally
required the use of 36 in. (or larger) structural casing. Refer back to Table 8.1 for
additional info on ratings for various subsea wellhead systems.
CASING HANGERS
Casing Hangers are used to run and land additional
strings of casing in the high pressure housing. All casing
hangers used with subsea wellhead equipment are
mandrel-type as compared to slip-type hangers that are
common with surface wellhead equipment). The hangers
are supported either by a shoulder in the high pressure
housing or by the seal assembly and casing hanger for
the previous set casing string. Space-out is extremely
critical for mandrel-type casing hangers. The remedial
procedure for casing stuck off bottom is to use a casing
patch tool, which is discussed under Special Situations at
the end of this section. In addition to providing support to
hang casing and reacting to pressure test loads, the
casing hanger also allows return flow from the annulus
during cementing, provides external seal surfaces for an
annulus pack-off and internal seal surfaces for tools,
tubing hanger and tieback sealing. Casing hangers have
an internal profile for either threaded or cam-actuated
running tools. The bottom of the hanger is threaded with
a casing box connection and has a tong neck to facilitate
thread make-up. A pin x pin casing handling pup is
generally bucked onto the bottom of casing hanger prior
to sending it out to the rig.
The standard casing program for a three-hanger
wellhead system includes 13-3/8 in., 9-5/8 in. and 7 in.
Figure 8.6 13-
casing hangers (Figure 8.6), but other sizes are also
3 /8 , 9 -5 /8 and 7
available. The hangers stack on top of each other as
Casing Hangers
subsequent casing strings are run.
8 - 13
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
Because of the large diameter and high working pressures, large downward loads are
imposed on the wellhead landing shoulder where the 13-3/8 in. casing hanger lands.
This shoulder must support the weight of all casings strings set in the wellhead plus the
force caused by test or wellbore pressure. Wellhead manufacturers use various
methods of dealing with this problem. As an example, Vetco uses a high strength insert
load ring in the 18-3/4 in. MS-700 high pressure housing and an integral passive (no
moving parts) load ring permanently attached to the 13-3/8 in. casing hanger to provide
7.1 M lb combined load rating.
SEAL ASSEMBLIES
Seal Assemblies, also referred to as casing pack-offs
(Figure 8.7), are used to seal the annulus between the
casing hanger and the wellhead housing and must
provide a pressure tight seal up to the rated working
pressure of the system. The seal is formed by an
elastomer and/or metal-to-metal seal. Seal assemblies
are further categorized by the method by which they
Figure 8.7 MS-1
are set: weight set or torque set. Most wellhead
Seal Assembly
syste m s u se a u n ive rsa l size se a l a sse m b ly th a t w ill
(Casing Pack-off)
work with any of the casing hangers that are run in the
high pressure wellhead housing.
Seal assemblies are installed around the upper portion of the casing hanger and are
generally run via sin g le trip w h e re th e y a re ru n w ith th e ca sin g h a n g e r a n d e n e rg ize d
after the cement job is completed. The single trip method has gained much favor due to
rig time and cost savings. Seal assemblies can also be run and set on a separate trip
after the casing has been cemented. This option generally allows more flow-by area
during cementing, which may be desirable if Equivalent Circulating Density (ECD) is a
problem and cement placement is critical. Because seal assemblies are such a critical
component of the subsea wellhead system, they will be discussed in more detail later in
this section.
8 - 14
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8 - 15
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
If high bending loads or fatigue are anticipated, the 18-3/4 in. wellhead housing can be
rigidly locked down using the Bootstrap Tool (Figure 8.10). The Bootstrap Tool is run as
an integral part of the 18-3/4 in. CART and allows preloading of the high pressure
wellhead to the low pressure housing with up to 1.0 M lbs. The Bootstrap Tool uses 12
hydraulic cylinders to multiply 80 kips of drill string overpull into 1.0 M lb setting force.
Other variations of this tool use mechanical levers(vs. hydraulic pistons) to achieve
similar preload forces.
8 - 16
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8 - 17
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8 - 18
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8 - 19
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
Figure 8.15 Nominal Seat Protector, Wear Bushings and Retrieving Tool
8 - 20
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8 - 21
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8 - 22
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
casing that lands in the high pressure housing. Seal assemblies are further categorized
by the method by which they are energized: weight set or torque set.
WEIGHT SET
Weight set is the preferred method for all deepwater applications, with systems available
fro m a ll five o f th e le a d in g w e llh e a d m a n u fa ctu re rs. V e tco s MS-700 and DrilQuip SS-15
are the most common examples of weight set seal assemblies. Operational procedure
for running a weight set seal assembly is included later in this section.
TORQUE SET
Torque set is mostly limited to older design equipment, but still has its place in shallower
w a te r w h e re a va ila b le w e ig h t is lim ite d b y th e le n g th o f th e ru n n in g strin g . V e tco s S G -5
wellhead system is the most common example of torque set seal assemblies. Torque is
delivered to drive nut of the seal assembly via the running tool, which is rotated to the
right by the landing string.
Seal assemblies are installed around the upper portion of the casing hanger and are
g e n e ra lly ru n via sin g le trip w h e re th e y a re ru n w ith th e ca sin g h a n g e r a n d e n e rg ize d
after the cement job is completed or they can be run on a separate trip (generally less
desirable due to additional rig time and cost, unless more flow-by area during cementing
is re q u ire d ). M o st w e llh e a d syste m s u se a u n ive rsa l size se a l a sse m b ly fo r th e 1 3 -3/8
in. and smaller casing hangers. Refer to Figure 8.7 for a weight set, metal-to-metal seal
MS-1 seal assembly that is used with the Vetco MS-700 wellhead system. The MS-1
seal is an all metal-to-metal (no elastomer components or back-up seal) and is rated for
sour service up to 15,000 psi.
The seal is relatively simple and consists of four main parts:
1) A n e n e rg izin g rin g o r E rin g .
2) th e U se a l.
3) a lower support ring.
4) an assembly nut.
8 - 23
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
The mating surfaces for the seal are wicker profiles cut into the circumference of the
w e llh e a d h o u sin g a n d ca sin g h a n g e rs. T h e w icke rs a re o f a h a rd e r m a te ria l th a n th e U
seal. The MS-1 se a l is a tta in e d b y e n g a g in g th e E rin g in to th e U se a l, w h ich sp re a d s
a n d d e fo rm s th e so fte r U in to th e p a ra lle l w icke rs (Figure 8.20). Each wicker seal
interface provides an effective seal. The five to seven wickers engaged provide five to
seven separate seals.
In addition to sealing, the Before Setting After Setting
b itin g o f th e U se a l b y th e
wickers provides a
mechanical lock between the
casing hanger, MS-1 seal
assembly and wellhead
housing. The angle of the
wickers was designed to
provide an optimum balance
between sealing and locking.
Note: Many of the other Wickers
wellhead manufacturers use a
lock ring (as compared to
V e tco s w icke rs) to lo ckd o w n
the seal assembly and casing
hanger to the wellhead
housing. On expendable
wells, the common practice is
to leave the lock rings off Figure 8.20 MS-1 Seal Engagement
seal assemblies (if so
equipped) to allow easier removal of the casing hangers during well abandonment.
If the primary seal assembly cannot be correctly set or fails to pressure test, subsea
wellhead manufacturers provide an Emergency seal assembly that can often be used
to correct the problem.
EMERGENCY SEALS
The two primary types of emergency seals are:
1) Elastomer only.
2) A combination of metal-lip seals and elastomer pack-off.
The elastomer only seal is generally limited to a maximum pressure of 10,000 psi
whereas the combination of metal-lip seal and elastomer pack-off are rated to a full
15,000 psi. Other variations of emergency seal assemblies use a lead seal or
combination of lead and elastomer, but these are much less common today. Most
emergency seal assemblies are generally shorter (by 1 to 2 inches) and may have more
taper or relief on the nose area than the standard seal assemblies they replace. These
features allow them to set slightly higher and still not interfere with the next casing
hanger and also to be more junk tolerant. Most wellhead manufacturers have
emergency seal assemblies available for sour service up to the rated working pressure
8 - 24
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
Wellhead Housing
Wickers
Metal-lip Seals
Casing Hanger
Elastomer pack-off
8 - 25
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8 - 26
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
Note: if it is required to test the blind/shear rams (BSR) after drilling out casing, a means
must be provided for backing off of the test plug so that the BSR can be closed.
Although this was once an MMS requirement, most current regulations do not require
re-testing the BSR until after the next string of casing has been set. If BSR testing is
required after drill out, special tools must be obtained from the wellhead manufacturer
(e.g., DrilQuip Drill Pipe Release and Test Sub).
Note: a leaking casing hanger seal assembly can pose a very serious problem on a well
drilled from a floating rig. If the annulus below the seal assembly is closed, a leak could
result in either a burst outer casing string or collapse of the inner casing string. Because
of this, it is often desirable to leave the annulus between the inner and outer string open
(i.e., leave TOC below previous casing shoe) to act as a relief valve. However, if
hydrocarbon bearing zones are present below the previous shoe, regulations may
require sealing the annulus by bringing TOC a sufficient distance above the shoe.
If the annulus is closed, extreme caution should be taken during testing of the seal
assembly. The recommended method is to pump at a low, controlled rate and maintain
a pressure-volume plot. A leak can often be identified sooner from the plot than from a
pressure drop on a gauge. Early identification can prevent bursting or collapsing a
casing string. Additional information on leaking seal assemblies is included under
Special Situations, Section 8.4.1, Leaking Seal Assemblies.
8 - 27
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8.2.1 INTRODUCTION
Casing running from floating rigs requires additional procedures and precautions
compared to land and platform drilling operations due to vessel motion and use of
subsea wellhead equipment. General guidelines and precautions for running casing
from a floating rig are discussed in this section. Checklists for casing equipment and
running operations should be completed prior to the start any job. Refer to ExxonMobil
Standard Operations Manual Floating Drilling, Section 9 for a copy of the checklists.
Note: casing must be designed per basic standard specified in EMDC Drilling OIMS
Manual, Element 3. At the time of this writing, the basic standard is the ExxonMobil
Bridging Document for Interim Well Casing and Tubing Design (EMLRFD).
DRILLING REQUIREMENTS
Include pre-job, during-job and post-job guidelines and precautions that are specific to or
of special importance for casing operations on floating rigs.
8 - 28
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8 - 29
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8 - 30
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
EQUIPMENT MAKE-UP
Make-up torque will be specified in the drilling program or supplemental procedure and
is based on connection type, grade and weight of pipe, plating on the threads and type
of thread compound to be used. Refer to ExxonMobil Bridging Document for Interim
Well Casing and Tubing Design (EMLRFD), Section 7.6 for information on connection
make-up requirements and recommended thread compounds. Unless specified
otherwise, consideration should be given to using an environmentally friendly thread
compound such as Bestolife 2000. Float equipment is to be made-up with thread
locking compound.
A standard torque gauge can be used to make-up most casing connections. However,
critical strings such as production casing or tubing should be monitored with a torque-
tu rn syste m su ch a s W e a th e rfo rd s JA M o r e q u iva le n t.
8 - 31
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
LANDING STRING
For floating drilling operations, all casing is landed using drill pipe as the landing string.
If the casing weight exceeds the tensile rating of normal drill pipe, heavier weight and/or
higher strength drill pipe is typically used (e.g., for 5 in. drill pipe landing string, use 25.6
ppf S-135 versus 19.5 ppf X-95 or G-105). Hevi-Wate drill pipe (HWDP) could also be
substituted, but is seldom used. Casing can also be used as the landing string using a
full bore casing hanger running tool (refer to Figure 8.13), but this takes significantly
longer to run and the casing landing string must be laid down at the end of the job.
There is also a higher potential for sticking the casing off bottom.
Deeper well depths and deepwater operations have driven the Industry to develop high
tensile strength landing strings. The use of special heavy wall (0.75 in), high strength
(S-135 and higher) drill pipe landing strings with high strength connections is becoming
common on ultra-deepwater new generation rigs. Tensile ratings for the special heavy
wall 5 in. OD landing strings is in excess of 1,300 kips and for 6-5/8 in. OD is in excess
of 1,600 kips (without safety factors). Grant Prideco has recently manufactured integral
joint (no welding) 5-1/2 in. and 6-5/8 in. with extra heavy wall (1.338 in.) and 125 ksi
grade (including tool joints) that are rated at 2,000 kips (without safety factor).
Because slip crushing is a serious limitation above about 1,500 kips, these landing
strings require a second tool joint knot below the box end to allow using bottle-neck
elevators in lieu of slips (LAST Landing and Slipless Technology). At the time of this
writing, the integral joint slipless landing string has not been used. Note that due to the
high cost of any of the special landing strings, this equipment is not used for drilling (i.e.,
use is dedicated to landing casing).
To reduce th e la n d in g strin g te n sile ra tin g , it is a lso p o ssib le to flo a t in a p o rtio n th e
string. The upper portion of the casing string is not filled with mud, which increases the
buoyancy and reduces the load. This technique has been used successfully in the past,
but is limited by casing collapse and differential pressure across the float equipment. If
the float equipment fails, the full casing load will be placed on the landing string. Due to
the availability of higher strength landing strings and the risks involved, this method is
seldom used.
SPACEOUT
A standard precaution is to spaceout the landing string so that a connection does not
have to be made while the casing hanger or seal assembly is in the BOP stack. This is
to reduce the possibility of damage due to vessel heave. The spaceout is accomplished
by using drill pipe pup joints of the appropriate length. Another precaution is to spaceout
the landing string at the surface to avoid interference with the cement head due to vessel
heave or tidal fluctuations. In some areas, tidal variations as much as 30 ft exist. The
same effect can also be caused by vessel offset in deepwater.
8 - 32
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8 - 33
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
PROCEDURE
(example is for a Vetco MS-700 system which uses weight set seal assemblies)
Ensure the Nominal Seat Protector (NSP) or wear bushing has been removed and
that the wellhead and BOP have been jetted clean.
Make-up DPRT (or PADPRT) with the cement wiper plug launching assembly (out of
critical path if possible).
Thread the seal assembly onto the DPRT (out of critical path if possible).
Lower the DPRT and stab it into the casing
hanger until it shoulders out
(Figure 8.24). Rotate the stem on the tool
four RH turns to lock the tool to the
casing hanger (out of critical path if
possible).
Run the casing to the last joint.
Make-up the DPRT to the last joint
suspended in the casing slips. Lift the
assembly and run the casing hanger to the
subsea wellhead on the landing string.
Check measurements to ensure hanger is
at the proper depth in the wellhead. Set
down all casing weight and 15 - 20 kips
landing string weight. The weight indicator
reading should be the same as when the
wear bushing was retrieved. Do not move
or pick-up the casing after it has landed out.
Circulate and cement the casing as per
program. Do not reciprocate the casing.
Figure 8.24 Installing DPRT
Rotate the landing string four RH turns to into Casing hanger
release the DPRT/PADPRT stem from the
lower body (tool remains locked to the
casing hanger).
Begin lowering the landing string, allowing
the stem to move downward approximately 48 in..
Slack off 20 kips landing string weight to fully energize the seal assembly.
8 - 34
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
Line up to circulate down the choke or kill line and break circulation. A good method
to ensure you are lined up properly is to leave the failsafe choke of kill line valve
closed and apply 50 100 psi, then open the valve and check to see if the
pressure drops.
Note: In deepwater, the volume in a choke or kill line can exceed 100 bbls. This will
result in having to pump several bbls of the fluid to build pressure. It is
recommended that a volume versus pressure plot be used to determine the minimum
volume required to achieve the desired pressure.
Close pipe ram or annular and pressure up through a choke or kill outlet to test the
casing hanger to wellhead seal. Pump at a low, controlled rate and carefully monitor
the volume pumped. Generally to bbl above the volume required to pressure up
the line is the maximum volume necessary to achieve a successful test if the seal is
not leaking. Use extreme caution as a leaking seal assembly can result in casing
failure during testing. After a successful test, vent off pressure and open preventer.
Measure the volume of fluid bled back.
Lift the landing string approximately 35 in. until the stem piston shoulders out.
Rotate landing string four (4) RH turns to release the tool from the casing hanger.
Retrieve tool. Approximately 50 kips of overpull is required to release the seal
assembly from the DPRT setting sleeve.
Pull the tool back to the surface and inspect the lead impression blocks to determine
whether or not the seal has been properly energized.
Run in the hole and set the wear bushing. For the Vetco MS-700 system, overpull
about 30 kips to ensure the wear bushing is latched to the casing hanger. With
neutral weight on the running tool, use RH rotation to un-jay and release the running
tool. POOH with running tool.
8 - 35
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8 - 36
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8.3.1 INTRODUCTION
Cementing operations on floating drilling rigs are similar in most aspects to land or
platform rig operations. However, there are several significant differences: 1) type of
cement head that is used, 2) wiper plug releasing system and 3) lack of casing
movement while cementing. The casing is not rotated or reciprocated for the following
reasons:
Possibility of sticking the casing hanger above the desired setting point in the
wellhead housing.
Possibility of detaching the casing running tool from the casing string prematurely.
Possibility of damaging the seal assembly or the sealing surfaces in the wellhead
housing.
Casing movement during cementing is known to improve mud displacement and the
integrity of the cement job, but it is not done on floating rigs. Because of this, other
methods and precautions must be taken to improve cementing success. These include,
but are not limited to, using an inhibitive mud system to minimize hole washout,
conditioning the mud and hole properly, using a pre-flush spacer, mixing cement
uniformly, and pumping at maximum possible rates. A cementing checklist should be
completed and all equipment thoroughly checked out prior to starting any job. Refer to
ExxonMobil Standard Operations Manual Floating Drilling, Section 10 for a copy of a
cementing checklist.
Note: The top of cement (TOC) for casing strings other than structural and conductor
should be well thought out.
The current trend is to leave as many of the annuli open as possible and not to bring
cement back into the previous casing shoe, thereby creating a downhole relief valve.
This avoids pressure build-up and potential for casing failure due to a leaking seal
assembly and a phenomena known as Annular Pressure Build-up (APB). Problems with
casing failures during seal assembly testing is relevant to all wells whereas APB pertains
to HP/HT (high pressure/high temperature) subsea production wells or subsea wells that
are tied-back and produced from a surface structure. APB has resulted in the failure of
several non-EM operated wells in the US GOM. At high production rates, heat from the
produced fluids can increase the pressure in trapped annuli and can result in burst outer
casing strings and/or collapsed inner strings.
8 - 37
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
Note: There are circumstances where the annuli cannot be left open. If hydrocarbon
bearing zones are present below the previous shoe, regulations generally require
sealing the annulus by bringing TOC a sufficient distance above the shoe. Also, annuli
that were initially left open may become sealed at a later time due to barite settling of the
mud.
Because of this, the following mitigation measures should be considered for wells that
have the potential for APB:
Installation of burst disks in casing couplings of outer casing strings (not applicable to
production casing).
Foam modules applied to the outer surface of the inner casing string (requires
sufficient annular clearance).
Foamed spacers pumped during cement job that are trapped below the seal
assembly (questionable value).
Consideration to run more casing strings as liners, thereby eliminating an annulus
(typically requires higher strength/grade/weight for casing string liner is hung from).
High pressure wellhead housing with side outlets for active B & C annuli bleed and
monitoring (conceptual design exists, but no equipment has been built at the time of
this writing).
8 - 38
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
CEMENT HEAD
Special cement heads similar to those
used for liner cementing jobs are
required for floating drilling casing
PICK UP SUB WITH
cement jobs. This is due to the casing NC50 (4-1/2" IF) BOX
8 - 39
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
Plug Mandrel
A drill pipe dart is released from the cement head behind the cement. The drill pipe dart
wipes the cement from the landing string and latches into and releases the top plug.
SSR wiper plugs larger than 13-3/8 in. are also available in double plug sets, but
generally only a top plug is run. Most cementing service companies have SSR wiper
plugs that are PDC bit drillable and some have a non-rotating feature that is designed to
reduce the amount of time to drill out the wiper plugs. Normal practice is to make-up the
SSR wiper plug set, casing hanger running tool (DPRT or PADPRT) and casing hanger
and stand it back in the derrick prior to running casing. Of utmost importance, the
landing string must be drifted to ensure there is sufficient clearance for the ball and dart.
It is also recommended that no component of the landing string have sharp internal
shoulders that may damage or cause the dart to become hung up.
8 - 40
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
OPERATIONAL SUMMARY
Operational Summary for running and releasing SSR wiper plugs is as follows.
Pressures listed are approximate and vary depending on wiper plug size. Consult
manufacturer for pressure range for the equipment that is used.
Ensure SSR wiper plug set and mandrel with equalizing sub (Figure 8.27) are
made-up to the bottom of the casing hanger running tool.
Ensure proper size releasing ball and dart are loaded in the SSR cementing head.
Landing string, casing hanger running tool, equalizing sub, etc. must be drifted to
ensure there is sufficient clearance for the ball and dart.
Run casing and land hanger in subsea wellhead housing as per program. The
casing string is normally landed with the SSR cementing head stand.
Install SSR cementing head and break circulation. Circulate at least one casing
volume or annulus volume (whichever is greater). Pump preflush spacer as per
program.
When ready to cement, drop the setting ball and pump at low rates until the ball
lands in the ball seat of the bottom wiper plug and the pressure starts to build up.
Application of 1,200 to 1,600 psi differential pressure is required to release the
bottom wiper plug.
Note: The pressure increase to release the bottom plug is often difficult to see. The
bottom plug will move down the casing wiping ahead of the cement until it hits the
float collar. Approximately 300 psi is required to shear the pins on the bottom plug
ball seat, which moves downward to expose circulating ports. This allows cement to
be pumped through the bottom plug.
Mix and pump cement as per program.
After pumping the cement, a drill pipe dart is released from the SSR cementing head
and is followed with the postflush spacer (if required). The drill pipe dart should be
pumped at a slow rate until it lands and latches in the top wiper plug and pressure
starts to build up. Application of 1,700 to 3,100 psi differential pressure is required to
release the top wiper plug. The drill pipe dart and top wiper plug then move down
the casing together and wipe cement until they land out on top of the bottom plug
and shut off circulation.
After launching the top wiper plug, the rig pumps are generally used to displace
cement on floating rigs. It is recommended not to over-displace the cement.
However, it is common practice to over-displace by as much as 50% of the volume of
the float joints if a clear indication of the top wiper plug shear release was seen.
Note: It is generally easier to drill cement than to repair a wet shoe.
Bleed casing pressure to zero and check to ensure floats are holding.
Procedure for setting and testing the seal assembly was covered under casing
operations.
8 - 41
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8 - 42
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
8 - 43
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
A leaking casing hanger seal assembly can pose a very serious problem on a well drilled
from a floating rig. If the annulus below the seal assembly is closed, a leak could result
in either a burst outer casing string or collapse of the inner casing string. Because of
this, it is often desirable to leave the annulus between the outer string open (i.e., leave
TOC below previous casing shoe) to act as a relief valve. However, if hydrocarbon
bearing zones are present below the previous shoe, regulations may require sealing the
annulus by bringing TOC a sufficient distance above the shoe. If the annulus is closed,
extreme caution should be taken during testing of the seal assembly. Generally to
bbl is the maximum volume necessary to achieve a successful test if the seal is not
leaking. The recommended method is to pump at a low, controlled rate (~ BPM) and
maintain a pressure-volume plot. A leak can often be identified sooner from the plot
than from a pressure drop on a gauge. Early identification can prevent bursting or
collapsing a casing string.
If a leaking seal assembly is suspected during initial pressure testing, it recommended
that the test be stopped and efforts made to determine the source of the leak. Other
possible locations of the leak besides the seal assembly are:
1) Surface equipment leak.
2) BOP pipe rams.
3) choke or kill line.
4) test plug.
5) BOP stack to wellhead connector.
Some leaks may be simple to diagnose: a leak past the BOP rams may be detected
by returns up the riser; a leaking wellhead connector may be detected with the subsea
TV or ROV and a leaking test plug is indicated by returns up the drill pipe. However,
even simple diagnostics can be very difficult on a floating rig: heave can cause bbl or
more fluctuation when monitoring returns up the riser, and it is often difficult to see leaks
with subsea TV or ROV without adding dye to the fluid. Other leaks may only be found
by trial and error. If no other leaks can be found, it is probable that the seal assembly is
leaking. Sometimes repeating the seal assembly setting procedure will solve the
problem. Increased weight, pressure or torque may be effective depending on the type
o f se a l th a t is u se d . W e llh e a d m a n u fa ctu re rs re co m m e n d a tio n sh o u ld b e fo llo w e d .
8 - 44
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
If these attempts fail to correct the leak, the seal assembly should be pulled and carefully
inspected to determine the cause of the problem. Junk, trash or shale may have lodged
under the seal assembly and prevented it from being properly set and energized. The
Seal Retrieval Tool (refer to Figure 8.14) is used to retrieve the seal assembly. Before
rerunning the seal assembly, the Clean & Flush Tool (refer to Figure 8.18) should be
run to remove debris and flush the area between the casing hanger and wellhead
housing. The Clean & Flush Tool should be painted white prior to running. Lead
indicators on the tool and marks on the paint can be used to determine the distance the
tool has engaged into the annulus. The condition of the seal assembly that was pulled
and any other available indicators will be used to decide what type of seal assembly to
run. If junk marks are present, it may be desirable to run an emergency seal assembly
(refer to Figure 8.29) that has metal lip seal with an elastomer pack-off.
The Vetco SG-TPR emergency seal assembly is designed to set and seal with hanger
offsets up to 0.35 and junk marks up to 0.100 inch depth and still provides 15k psi
pressure integrity. If no indication of junk, a new MS-1 seal assembly may be run. Used
seal assemblies are generally not re-run or refurbished. The DPRT (refer to Figure
8.12) or the PADPRT (refer to Figure 8.12) can be used to run, set and test either type
of seal assembly.
If these efforts fail to correct
the leak, the well may require a
Bridging Seal (refer to Figure
8.29). The bridging seal is
designed to land and seal in
previous casing hanger and
lock and seal in the wellhead
housing bore. Implied by its
name, bridging seals allow
bridging above damage in the
wellhead housing up to an area
that is not damaged. They are
available for 13-3/8 and 9-5/8
in. casing hangers and are run
with either an MS-1 or SG-TPR
emergency seal assembly.
The bridging seal stack up Figure 8.29 Bridging Seal (shown without seal assembly)
height is identical to that of a
casing hanger and assumes the next available hanger position in the wellhead housing.
The DPRT (refer to Figure 8.11) is used to run, set and test the bridging seal.
Note: This option may preclude running and landing the remaining casing strings in the
wellhead. Depending on the situation, subsequent casing may have to be run as a liner
if there are no slots left in the wellhead after running a bridging seal.
8 - 45
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
Stuck casing can be a very serious problem for wells drilled from floating drilling rigs.
Standard precautions (such as providing sufficient rat hole to allow for fill on bottom and
having the hole in as good of shape as possible) sometimes are not enough. Since
subsea wellhead systems require the use of mandrel casing hangers, casing stuck off
bottom generally results in the casing extending above the subsea wellhead and into or
above the BOP stack. If efforts to run the
casing to bottom or pull it from the well are
unsuccessful, the solution requires the use
of an overshot-type casing patch (Figure
8.30). Special casing patches for this
application are available from various service
companies (Bowen, A-Z, etc.) and have an
internal slip assembly and packer (elastomer
and/or lead seals) that provide a pressure
tight assembly. The Operational Summary
for installing the casing patch is as follows:
Cement the casing as per procedure.
Consider reducing amount of cement
pumped to ensure TOC is safely below
wellhead and BOP (typically not a
problem as casing annuli are either left
open or cement only brought 200 ft
inside previous casing shoe on floater
wells). Release casing hanger running
tool and POOH with landing string.
Using a casing cutter, cut the casing one
or more joints below the wellhead.
Retrieve the cut end. To ensure a
precision cut, it is often recommended
that a second cut be made with the
assistance of a marine swivel landed out
in the wellhead housing. Retrieve the cut
end.
Dress off the top of the cut with a mill to
Figure 8.28 Overshot-type Casing Patch prevent damaging the seals on the inside
of the casing patch.
Run the casing patch and casing hanger spaced out with casing and/or pup joints to
provide the desired space-out. Slight rotation should allow the casing patch to
swallow the casing stub in the wellbore. The casing patch has an extension sub that
allows sufficient swallow to allow the casing hanger to be landed in the wellhead
housing.
Set and energize the seal assembly to lock the casing hanger to the wellhead.
POOH with casing hanger running tool.
8 - 46
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
To put the casing string in tension, a releasing spear is run into the casing below the
casing patch and used to pull the casing stub further into the extension sub of the
casing patch. Slips inside the casing patch hold the casing in tension. Release
spear and POOH.
Pressure test casing string and resume operations.
8 - 47
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
OVERVIEW
Special situations, mostly related to deepwater drilling, have driven the Industry to
develop large bore subsea wellhead systems. Large Bore systems are somewhat more
complicated than standard subsea wellhead equipment and their use is
warranted/required only if one or more of the following conditions is present:
8 - 48
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
ANNULAR TOLERANCES
The concern with large bore wellhead systems is the extremely tight tolerances between
the wellhead equipment and the casing strings that are run. As an example, the
clearance between the 18-3/4 in. high pressure wellhead housing and the 18 in. casing
hanger is only 0.0620 in., less than one tenth of an inch! The 18 in. casing hanger is
only about 3 ft tall, but this is no small feat considering the harsh environment and
remoteness on the bottom of the seafloor where the equipment is run. Use of flush joint
18 in. and 16 in. is mandatory, but this still affords very little annular clearance over the
entire length of the casing strings. Based on a pure flush (no external upset) 18 in.
casing connection, the total clearance between the 18-3/4 in. wellhead and the casing is
only 0.437 in., which equates to less than one quarter of an inch radial clearance over
the entire length of the 18 in. casing string. In addition to the close tolerances in and
below the wellhead, standard 21 in. OD drilling risers have IDs of approximately 19 in..
This results in about 0.5 in. radial clearance between the 18 in. casing and the riser.
Proper rig stationkeeping and riser tension must be maintained while the 18 in. casing is
run. Weather conditions should also be considered and may result in WOW downtime
until sea states are calmer.
Although tight annular tolerances are a major concern with large bore wellhead systems,
note that they have been successfully run in the US GOM and Caspian Sea. Without
this specialized equipment, it is probable that some of these wells may not have been
able to reach TD. Additional planning and extra precautions are recommended when
large bore subsea wellhead equipment is used. It is essential that all casing and
wellhead equipment be drifted, calipered and checked for damage.
8 - 49
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
DrilQuip has developed a system that will perform a cement top job outside of the 30 in.
structural casing without having to trip the landing string. The TITUS system has
become fairly popular in the North Sea where structural casing typically must be drilled
and cemented in place. Due to strong environmental forces in the North Sea (wind,
waves and current), the structural casing on many wells drilled from floating rigs will lose
its bond with the formation near the mudline. When this occurs, the wellhead and
subsea BOP stack generally develop cyclical movements that form a crater around the
wellbore.
Prior to the advent of TITUS, the typical remedial action was to run a bent joint of tubing
on drill pipe down one of the guidelines and pump a cement top job or puddle job to fill
the crater. This was difficult and often required the assistance of a ROV to guide the
tubing around the BOP stack and into the crater. After pumping the remedial cement
job, additional riser tension would be pulled in an effort to minimize wellhead movement
until the cement had set. The remedial action was not always successful and often
required more than one attempt.
TITUS equipment consists of a two inch (2 in.) steel pipe that is connected to the outside
of the 30 in. low pressure wellhead housing extension joint that terminates into a cement
distribution ring located above the bottom connector (Figure 8.31). Flexible lines with
quick connects are used to connect the 2 in. steel pipe to the permanent guidebase
(PGB) and on up to a swivel sub that is run on top of the Cam Actuated Running Tool
(CART). A special drill pipe dart is launched behind the primary cement job and seals
off the main bore of the swivel sub. The landing string is pressured up to about 500 psi
to shear out and open the side-outlet on the swivel sub. The cement top job is then
pumped down the landing string to a depth of approximately 33 ft (10 meters) below the
mud line and is distributed around the outside of the structural casing. A ROV is
required to disconnect the flexible line from the PGB prior to releasing the CART and
POOH with the landing string. TITUS equipment has been used successfully on
ExxonMobil operated wells in the North Sea and should be considered for future wells
drilled in this area or where similar problems exist.
8 - 50
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA WELLHEADS &
CASING/CEMENTING OPERATIONS
ROV operated 30 CA RT
Grout Latch
PGB
Low Pressure
Wellhead Housing and
3 0 E xtension J t.
seafloor
2 steel pipe
8 - 51
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
9
BLOWOUT PREVENTER EQUIPMENT Section
OBJECTIVES
The intent of the material in this section is to only cover the differences in BOP
equipment used either in a subsea BOP stack or on a floating drilling rig. This section
provides a brief summary on the equipment and is intended only as reference material
for the Floating Drilling School. A basic understanding of BOP and well control
equipment is required. Additional detailed information on Subsea BOP Equipment can
b e fo u n d in th e F lo a tin g D rillin g B lo w o u t P re ve n tio n a n d W e ll C o n tro l E q u ip m e n t
manual.
On completion of this lesson, you will be able to:
List the differences between the rams, annulars, and choke/kill valves used in
subsea BOPs and surface stack BOPs.
Describe the basic sequence required to operate a function (e.g. open a ram
preventer) when using a subsea hydraulic control system.
Describe how a multiplex BOP control provides redundancy for the electronics.
Describe the basic sequence required to operate a function (e.g. closing an annular
preventer) when using a multiplex BOP control system.
List the available backups for the control systems and describe the major functions
of each.
9-1
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
CONTENTS Page
9-2
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9-3
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9.1 INTRODUCTION
This chapter provides information on well control equipment used on a floating drilling
units focusing on the differences between that equipment and the equipment used on
land, platform or jack-up rigs. The "subsea" system places the BOP equipment and
wellhead on the seabed and is tied back to the surface by the marine riser, similar to a
long "bell nipple". The primary purpose of the system is to close in the well and to
provide flexible and redundant methods for safely removing an influx. In addition, the
system must also allow for rig motion, temporary suspension of the drill string, and
temporary abandonment of the location. Deepwater operations may also impose
additional requirements such as fast response times for the closing system
and high
bending
loads.
Flex Joint
LMRP
Connector
Annulars
Choke/Kill
Vales Ram
Wellhead
Connector
9-4
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
The typical subsea BOP stack (Figure 9.1) consists of two annular preventers, four ram
preventers, and three or four choke and kill line outlets. S in ce a flo a tin g rig s B O P s a re
located just above the mudline, replacing a damaged ram or installing casing rams
requires that the entire BOP stack must be brought to the surface. This is one of the
main reasons why two annular-type preventers are common for floating rigs. A general
subsea stack arrangement is shown in Figure 9.2 with a sequence of arrangements that
provide a
progressive
amount of well
control capability.
For DP
operations, it is
absolutely
necessary that
the BOP be
capable of
supporting each
main size of pipe
for hang-off and
that the stack has
shearing and
Figure 9.2 Various Subsea Stack Arrangements sealing capability.
9-5
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
Cam Ring
Lock Dogs
LOCK
Hydraulic
Piston
UNLOCK
9-6
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
When pressure is applied to the unlock ports, fluid enters the cylinders below the
pistons. The pistons and the cam ring are forced upward, thus allowing the dog-segment
to move radially outward through the action of the springs located between the dog
segments. There is a 45o taper on the wellhead grooves and the dog segments. When
the connector is picked up, the dog segments are forced radially outward by this taper.
The connector utilizes a VX gasket and is equipped with an indicator rod, which makes it
possible to monitor the locking and releasing function either on the surface or subsea
(with the aid of a ROV).
Vetco H-4 Connector Types
DHD H-4 E H-4 ExF H-4 HD H-4 SHD H-4 ExF HAR
H-4
Bending Load 2.5 MM 2 MM 3.1 MM 4.0 MM 7.0 MM 3.1 MM
Capacity @ 2/3
Yield (ft/lbs)
Preload (lbs) 5.0 MM 2.10 MM 2.51 MM 6.25 MM 7.5 MM 2.51 MM
Hydraulic Circuits 10 10 12 10 10 12
Max. Service 15,000 10,000 15,000 15,000 15,000 15,000
Pressure (psi)
Hydraulic Pressure 1,500 1500 1500 3,000 3,000 3,000
(psi)
The available H-4 connector styles are summarized in Table 9.1. The HD-H4 and SHD-
H4 are heavy-duty high preload connectors, suitable for high bending loads at 15,000 psi
service pressure. The HAR-
H4 (Figure 9.5) is a high
angle release connector used
primarily on LMRPs. The
connector has a much
reduced swallow over the
mandrel and allows release at
higher rig offsets.
9-7
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
Indicator Rod
Gasket
Retainer Pins
Primary
Actuator Unlock
Ring
Secondary
Unlock
Locking
Segment
Lock
MODEL 70 CONNECTOR
The Model 70-collet connector normally has six to nine cylinders with all cylinders being
used for unlocking and 4-6 cylinders used for locking. Hydraulic closing fluid pulls an
actuator ring down which, by leverage and tapered surfaces, forces pivoted locking
segments under the hub. Opening pressure causes the actuator ring to push upward
and the locking segments rock open to release the connector. All the cylinders are
attached to the actuator ring to unlock the connector, but only four to six of the cylinders
are attached to the bottom plate of the connector to provide locking force. When
unlocking, all cylinders will push upward on the actuator ring to unlock the connector. To
monitor the actuation of the connector, indicating rods can be monitored by subsea TV
or ROV to verify the locked or unlocked position of the actuator ring. Due to the short
swallow of the connector over the wellhead, Cameron advertises that the connection can
be released and pulled away from the wellhead hub at angles
up to 30 o.
An AX type ring gasket is used on the collet connector with spring loaded gasket
retainers to simplify ring gasket replacement. The Model 70 connector (Figure 9.6) is
available in 10 ksi and less working pressure.
9-8
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9-9
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9.2.3
CONNECTOR RING GASKETS
Connector manufacturers use different varieties of type AX, NX, CX, DX, or VX ring
gaskets (non-API) to provide a metal-to-metal seal against the wellhead or connected
component. These gaskets are made from a variety of materials including low yield
carbon steel and a variety of resilient materials used as a backup for the metal-to-metal
seal.
If the BOP-to-wellhead ring gasket fails to test or develops a leak when the stack is
subsea, the gasket can usually be replaced with a ROV. With the connector on the
wellhead, retainer screws/hydraulic pins can be retracted allowing the release of the ring
gasket. After picking up the connector the seal ring will remain on the wellhead where it
can be retrieved by the ROV. A new seal ring can then be placed on the wellhead and
the connector lowered onto the wellhead.
For the Vetco VX gasket (Figure 9.9), cadmium plated carbon steel or stainless steel
ring gaskets can be used in 10,000-psi equipment. Only stainless steel ring gaskets
should be used for 15,000-psi service.
VX Gasket Standard VGX Gasket. Rated for VT Profile Gasket A ABB Vetco Gray H-4
carbon steel, cadmium 15,000 psi at temperatures
plated metal-to-metal seal
secondary metal-to-metal connectors, MS-700 and
up to 350 F. seal. The secondary VT SG subsea wellhead
for 10,000 psi MWP. Geometrically
Stainless steel rated for sealing surface is used systems are
interchangeable with the
15,000 psi MWP. VX gasket. Ideally suited
when impact, corrosion or manufactured with the
for high-pressure, high- washout has damaged the dual taper VXNT gasket
temperature applications primary VX sealing profile with two
and critical service surface in the wellhead or independent sealing
applications connector. surfaces
9 - 10
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
Gas Hydrate
9 - 11
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
Hydraulically
Actuated Ram Locks
9 - 12
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
For deepwater applications and DP vessels it is extremely important that the bending
strength of the body and flanges throughout the BOP stack be considered and the
bending moments calculated to ensure that the integrity remains sound during high
offsets. When high strength bolts are used to provide for the increased bending loads,
hydrogen embrittlement of the bolts has been observed in the bolts due to the subsea
environment and the sacrificial anodes on the BOP stack. To reduce the potential for
hydrogen embrittlement, a hardness check should be performed prior to installing the
b o lts to e n su re th a t th e R o ckw e ll C va lu e is in a ra n g e o f 3 4 -35.
In addition, for DP vessels that rotate to weather vane into the environment, the torque
that is generated from the rigs rotation must be dissipated through the tensioner ring on
the riser to prevent damage to the BOP stack and or wellhead.
9 - 13
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
When drill pipe is hung off on a subsea stack, the pipe ram blocks typically support the
weight of the drill string with the tool joint supported on the contoured edge of the ram
block face. To support the weight of the drill string without damaging the ram block, ram
blocks used in subsea BOP stacks should have a hardened area around the lip of the
ram block. If Variable Bore Rams (VBR) are used, the amount of pipe that can be hung-
off should be determined by the largest size of the VBR range (i.e. 5 pipe for 3 - 5
VBR) so that the weight will be supported by the ram block and not the VBR packer. If
a smaller size pipe must be hung off in the VBR, the hang-off weight should be limited to
prevent damage to the ram packer.
The limiting or maximum hang-off weights will vary according to the preventer
type/manufacturer and should be verified from the manufacturer's catalog.
9.3.2 RAM LOCKS
To maintain wellbore integrity when hydraulic closing pressure is removed from a
preventer, all ram preventers are required to have a locking mechanism to lock the ram
closed and maintain a seal against full rated wellbore pressure. The two basic types of
locking mechanisms that are incorporated by the manufacturers are:
automatic locking mechanisms that are integral to the ram operating system
independent lock that functions independently of the ram operating system
On the Hydril MPL lock (Figure 9.12), a mechanical lock is set each time the ram is
closed. A unidirectional clutch mechanism and a lock nut control locking and unlocking
of the MPL. The unidirectional clutch mechanism maintains the nut and ram in a locked
position until the clutch is disengaged by applying opening pressure to the ram.
9 - 14
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
Locking
Wedge
Tail Rod
ST Lock Port
and Piston
9 - 15
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
Shear Ram Type 5 S-135 (19.5 lb/ft) 5 S-135 (24.7 9 5/ 8 K -55 (47
lb/ft) lb/ft)
C IW 18 15k T o r T L - SBR
C IW 18 15k T o r T L DVS 2480 1990 N/A
C IW 18 15k T o r T L - SSR 1650 1320 980
H yd ril 18 15k L W (19 o p erato r) <2800 <2800 <2800
Shaffer T-72 (14 o p erato rs) 3100 3850 N/A
Shaffer V-SH R (14 o p erato r) 2100 2600 N/A
9 - 16
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
To provide the necessary shear force, shear rams are sometimes equipped with bonnets
that provide either a larger piston (19 in. versus 15 in. for Hydril rams) or a tandem
piston that provides a second piston on tail rod to the close side of the shear rams.
This additional closing area will reduce the required closing pressure for a given tubular
size and weight by 40 50% (i.e. Shaffer 18 in., 15k ram with 14 in. by 16 in.
tandem piston shear pressure for 5 in., 32.7 lb/ft drill pipe is reduced from 2600 psi
to 1175 psi).
DP rigs are subject to drift/drive off from the well site, and consequently, there is a higher
probability of shear-ram usage. To provide greater assurance that the well will be
isolated on a disconnect, some DP rigs are equipped with two sets of shear rams. The
lower shear ram is functioned first to provide the initial shear and seal and the upper
shear ram is actuated afterwards as a backup shear/seal or to provide a seal should the
lower shear be damaged and unable to provide a seal after shearing the pipe. BOP
stacks on DP rigs will typically either be equipped with two sets of shear rams or shear
rams with larger or tandem pistons as described above.
Several new ultra-d e e p w a te r rig s h a ve a lso a d d e d a S u p e r S h e a r ra m th a t h a s th e
capability to shear some drill collars and larger sizes/weights of drill pipe and casing.
These rams are designed to shear only and do not provide a seal, thus requiring the
blind shear ram to be closed afterwards to secure the wellbore.
9 - 17
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 18
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
Shaffer Spherical
18 5 K
Figure 9.16 Annular Closing Pressure for Various Water Depths & Mud Weights
9 - 19
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
Another circumstance where additional closing pressure may be required for an annular
preventer is when closing the annular against wellbore pressure. The wellbore pressure
effect is generally of no consequence when closing a single annular or the upper annular
since the wellbore pressure is typically low when the annular is actuated. However,
when a lower annular is exposed to high wellbore pressure before being closed, the
normal closing pressure to the lower preventer may not be sufficient to close it and
establish a seal. This closing pressure limitation occurs where the closing ratio of the
annular preventer is relatively small. Although closing the lower annular against high
wellbore pressure may be an infrequent event; the possible wellbore pressure effect on
the lower annular should be considered. An alternative to using the lower annular could
be to close a lower pipe ram and hang off.
9 - 20
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 21
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9.5.1 GENERAL
Choke and kill valves required on surface BOP stacks must also be installed on subsea
stacks. Since the stack is subsea, the valves must be hydraulically operated rather than
manually operated. Two valves with hydraulic operators are required on each choke and
kill line outlet from the BOPs, and the valves should be positioned as close to the BOP
stack as possible with a minimum of connections between the stack and the valves.
The type of choke and kill valves used on floating rigs differs by manufacturer, gate/fluid
flow sealing design and actuation design. The selection of a particular valve/actuation
combination will depend on
peculiarities of the installation
geometry, water depth application and
other considerations including cost,
working pressure, maintenance costs,
repair part availability, and closing
pressure requirements, etc.
When opening a gate valve,
movement of the gate causes a hole in
the gate to line up with the flow
passage through the valve body
(Figure 9.17). The flow passage
through the gate is located near the
stem end for fail closed valves.
Retracting the gate toward the
operator causes the valve to close.
The gate seals against the
downstream seat assembly with a
metal-to-metal seal. Most choke and
kill valves are bi-directional in that they
will hold pressure from either direction. Figure 9.17 Typical Subsea Choke/Kill Gate Valve
To operate the valve, a stem is used to connect the valve gate to the valve actuator. On
some valves, the bottom side of the gate will also have a stem that is exposed to
seawater hydrostatic to balance forces across the gate. Seawater hydrostatic pressure
on the exposed end area of the lower stem will translate into a force to close the valve
offsetting force to open the valve. When forces across the gate are balanced by a lower
stem causing the valve to be almost water-depth insensitive, the valve is known as a
balanced valve (Figure 9.18).
Actuators typically use combinations of spring force, hydrostatic force of the column of
co n tro l flu id o r se a w a te r h yd ro sta tic a ctin g o n th e o p e n sid e o f th e a ctu a to r, a n d
se a w a te r h yd ro sta tic o r co n tro l flu id h yd ro sta tic a ctin g o n th e clo se sid e o f th e a ctu a to r.
Some actuators have a single opening fluid inlet. When this type actuation is used, force
to close the valve is generated by a spring in the actuator, and seawater hydrostatic
acting on the actuator. Pressure inside the valve (in-line) is used to assist closing on
9 - 22
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
some unbalanced valves. Other actuators have a pressure-assist close port. Valves
used for deepwater (>2000 ft) typically have a pressure assist circuit.
F o r m a n y ye a rs, ch o ke a n d kill va lve s w e re a d ve rtise d a s b e in g F a il-sa fe w h ich w a s
sometimes abbrevia te d F S . T h is te rm is g e n e ra lly d e fin e d a s th e a b ility o f a va lve to
close in the absence of any hydraulic control pressure from the surface control system, a
pre-loaded spring forces the gate to close whenever the opening control pressure is
zero. At high in-line differential pressure across the gate, seat friction may prevent fail-
safe closure. High in-line differential pressure across the gate could occur if a valve were
closed on a high-pressure flowing stream. Beginning in the late 1980s most
manufacturers would not guarantee fail-safe closure of their valves in all service
conditions. To provide for fail-safe operations, a pressure-assist close circuit was added
to the choke and kill valves subsea to provide this feature. This circuit is placed subsea
at the valve to ensure pressure assist close is available should hydraulics not be
available from the surface.
9 - 23
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 24
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 25
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
Flexible Choke,
Kill, and Rigid
Conduit Jumper
Hoses
Flex
Joint
ROV
Intervention
Panel
Choke/Kill
Test Valve
9 - 26
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
On DP rigs, the connection between the LMRP and the BOP stack will have a guide
funnel, either up (on BOP) or down funnel (on LMRP), and orientation pins to stab and
realign the LMRP onto the BOP stack. The alignment system is needed to land and latch
the LMRP onto the BOP stack subsea after a disconnect. Figure 9.22 shows the up
funnel alignment system used on the Discoverer Seven Seas and a generic down funnel
system is show in Figure 9.23.
9 - 27
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9.8.1 OVERVIEW
The function of a BOP control system is to direct hydraulic fluid to the appropriate side of
the operating piston and to provide the means for the fluid on the other side of the piston
to be vented. There are two basic classifications of control systems used in floating
drilling operations, the hydraulic and the Electro-hydraulic multiplex-control system.
The most common is the hydraulic control system, which is primarily found on moored
floating rigs. The E/H multiplex control system is primarily used on DP and ultra-
deepwater moored floating drilling vessels. The multiplex design provides the necessary
response times required on DP rigs for an emergency disconnect during a possible drive
off or drift off. Some of the manufacturers of control systems are Cameron Iron Works
(now a part of Cooper Oil Tools), Shaffer, ABB, and the Valvcon Division of Hydril.
9.8.2 HYDRAULIC CONTROL SYSTEM
Fluid used to operate the functions on the BOP stack is delivered from the hydraulic
control manifold (closing unit) through the hose reel, hydraulic hose bundle to the
subsea control pods. The pods contain control valves, which direct power fluid to the
various BOP stack functions on command from the surface. The control valves are
operated by pilot fluid supplied through small, individual pilot hoses, which connect the
valves to the hydraulic control manifold located at the surface. These small hoses are
contained in the hose bundle with the power fluid hose. The surface hydraulic control
manifold contains the panel valves, which direct pilot fluid pressure to the pod valves.
These panel valves are generally equipped with solenoid actuated cylinders which allow
co n tro l o f th e p a n e l va lve s fro m th e D rille rs p a n e l a n d m in i re m o te p a n e l. T o p ro vid e
complete redundancy for the subsea portion of the control system, two independent
hose reels, hose bundles, and pods are used.
The preceding discussion oversimplifies the hydraulic control system to a great extent.
To provide more detail, the following system description begins at the surface control
system and concludes with the subsea BOP pod. Keep in mind that the primary function
of each item on the system is to get fluid to the selected equipment at the desired
pressure in the minimum amount of time.
9 - 28
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 29
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 30
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 31
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 32
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 33
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
To allow the pods to be retrieved subsea from the LMRP, retractable stingers with
elastomers seals are used to provide fluid passage from the pods to the control hose for
each function. Each pod is equipped with a stack stinger and a LMRP stinger. The
stingers extend and retract into female receptacles on the stack and LMRP respectively
and are hydraulically energized to provide a pressure seal. Fluid ports in the stingers
align with ports in the female receptacles where control hoses attach the female
receptacle to the shuttle valve at the preventer.
9 - 34
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
Connected to
Function
Connected to
Connected to Yellow Pod
Blue Pod
9 - 35
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 36
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9.11.1 INTRODUCTION
The intent of a multiplex (MUX) system is the same as the hydraulic control system, to
provide for the remote operation of subsea blowout preventers and/or other well control
va lve (s). T h e te rm m u ltip le x sim p ly m e a n s th a t th e co m m u n ica tio n s syste m fro m th e
su rfa ce to th e se a flo o r ca rrie s co m m a n d s a n d /o r d a ta fro m th e su rfa ce to th e su b se a
electronic components via a single medium (cable) using a method for continuously
sharing the transmission medium.
Multiplexed communications links and electrical power links are provided to decrease
the time required to function a BOP or subsea valve. Experience has proved that an
a ll h yd ra u lic co n tro l syste m ca n n o t p ro d u ce e ffe ctive re sp o n se tim e s in u ltra -
deepwater. Time is a particularly significant factor in the operation of a system on a
dynamically positioned (DP) vessel when an emergency disconnect is required. Total
actuation times must be measured in seconds or a disconnect from the seafloor may
become impossible before the vessel drags the BOP over, causing damage to subsea
equipment, wellhead and BOP, possibly leaving the well unprotected.
In the early 1980s with the introduction of computer control devices, the basic format of a
m u ltip le x co n tro l syste m b e g a n to m ig ra te to th e co n ce p t o f a "C e n tra l C o n tro l U n it.
Probably this format was suggested by the basic "Hub" design where a computer can
accept both input signals and at the same time generate output signals. Since a single
computer negates the concept of redundancy, it wasn't long before two computers were
employed running parallel communication paths.
Current Multiplex systems are also driven by the convenience of modern computers to
the extent that many of the independent and redundant features of the original dedicated
and separate control panels and pods are now unobtainable. Instead, triple-redundant
computers and multiple parallel communications paths are offered as security against
electrical and communications failure.
9 - 37
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 38
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 39
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 40
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 41
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 42
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
control system is equipped with a minimum of two mux cables, a blue and yellow system
cable. The cables are stored on storage reels that are equipped with air or hydraulic
motors, a level winding system, and a slip ring to allow circuitry to be maintained while to
the reel rotates.
The mux cable is an armor-covered cable that typically has four power supply wires and
six to ten communication conductors. The power conductors are typically 8 AWG size
conductors and provide 440 volts for the solenoid supply. The wires used for
communications are typically 20 AWG and can be either single or multi conductors.
The overall cable is usually around 1.5 in. in diameter with a breaking strength of
30,000 pounds.
9 - 43
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 44
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
Solenoid valves are equipped with dual coils powered from each pod for redundancy
with the status continuously monitored providing an alarm to the surface panel for any
open circuits. To minimize leaks at the low volume sliding sleeve solenoid valves, 20-
micron filters are installed in each pod to maintain a clean solenoid supply fluid.
Another important part of a multiplex control pod is the accumulators in the pod used to
store and maintain solenoid supply (pilot) pressure. Solenoid supply pressure is required
to be available at all times so that pod startup can be accomplished.
During operations, one pod is always "active" (pressurized) and the second or redundant
pod is updated and actuated electrically so that on selection, it assumes the status of the
active pod.
9 - 45
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 46
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 47
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
The additional volume of nitrogen to provide the 890 psi precharge pressure in the
example above is necessary to overcome the hydrostatic pressure acting on the
opposing side of the operating piston that is vented to the sea when a function is
actuated. Since the accumulator is filled with an additional volume of nitrogen to
counteract the equivalent hydrostatic pressure, the available volume remaining in the
accumulator for fluid will be less. The example below using Boyles Law of gases
illustrates that the available fluid in a 10 gallon accumulator decreases from 6.0 gallons
on the surface to 3.76 gallons when used at 4000ft water depth.
System Operating Pressure = 3000 psi
Surface Precharge Pressure = 1200 psi
Total fluid in a 10 gal accumulator on surface = 60% or 6.0 gals
Subsea Precharge pressure for 2000ft WD = 2090 psi
Total fluid in a 10 gal accumulator subsea = 51.2% or 5.12 gals
Subsea Precharge for 4000ft WD = 2980 psi
Total fluid in a 10 gal accumulator subsea = 37.6% or 3.76 gals
When the temperature change from surface to subsea and the compressibility of
nitrogen is added to the equation, the available fluid from a subsea accumulator
becomes even less, making them impractical for use as a way to decrease closing times
due to the number of bottles that would be required. For this reason, large diameter
conduit lines are the preferred means to reduce closing times as water depth increases.
On some ultra-deepwater rigs, helium has been substituted for nitrogen for subsea
bottles (primarily used for the deadman system). The smaller molecule of helium makes
it more compressible at the higher pressure needed for pre-charging deepwater subsea
accumulators. The higher compressability of the helium provides more usable fluid per
accumulator than nitrogen, thus requiring fewer bottles to be mounted on the BOP stack.
A disadvantage to using helium as a precharge gas for accumulators bottles is that it
tends to leak at a higher rate than nitrogen, is less readily available and costs about
400% more than nitrogen. Accumulator bottles equipped with a piston type float have
proven less resistant to helium loss than conventional bladder or float accumulator
bottles used with nitrogen.
Subsea accumulator bottles used as surge bottles with annular preventers should
typically be pre-charged to 500 psi, plus the hydrostatic pressure gradient for the given
seawater depth. Subsea accumulator bottles used in conjunction with emergency
backup subsea acoustic systems should be precharged, and adjusted for water depth in
the same manner as other subsea bottles to ram preventers.
9 - 48
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9.13.1 ACOUSTIC
An acoustic system can be installed on the blowout preventer stack to actuate selected
functions when the primary control system is lost. An acoustic control system can
operate in water depths down to 6000 feet and up to a one mile offset from the wellbore
depending on the model. Acoustic systems manufactured by Raytheon Company and
Cameron Iron Works are the most common. Acoustic signals may be emitted on location
from the rig or off location from the deck of a boat. Acoustic signals are sent through the
water to hydrophones located on the blowout preventer stack. Through a subsea battery
powered electronics system mounted on the stack, the acoustic signals are converted to
electrical signals, which in turn actuate solenoid pilot valves located in a dedicated mini
pod dedicated to the acoustic system. The solenoid pilot valves send a hydraulic signal
to actuate a control valve in the acoustic mini-pod. This allows fluid from a stack
mounted acoustic accumulator bank to function the selected preventer. The acoustic
system hydraulics are connected to the preventer through a second shuttle valve
mounted at the function. Selected functions may include shear rams close, hangoff pipe
ram close, wedgelock (if equipped), and connector unlatch.
Typically, the capacity of the subsea acoustic bottle is 1.5 times the volume required to
function the selected components. The subsea accumulator bottles for the acoustic
system are the same as surface bottles plus an adjustment for seawater hydrostatic
pressure at the given location. The subsea acoustic bottle pressure is not regulated
down and the full 3000-psi bottle pressure is delivered to the selected function.
If installed, the acoustic system should be tested by actuation of a BOP function
1. when the BOP stack is initially run to verify competence of the system.
2. before retrieving the stack at the completion of the well to provide data for
possible maintenance.
9 - 49
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9.13.2 DEADMAN
T h e M U X syste m m a y in clu d e a fe a tu re ca lle d D e a d m a n w h ich ca n b e tu rn e d on
(armed) or off (disarmed) as desired by the operator. When armed, the shear rams will
be closed and other selected functions will actuate should there be a loss of all
hydraulic power, communications, and all electrical power subsea. The energy provided
to activate the shear rams and other functions is in the form of hydraulic energy stored
in subsea accumulators attached to the BOP stack. A combination of the following
conditions must simultaneously exist for the deadman function to trigger. They are:
1. loss of electrical power to the Yellow pod.
2. loss of electrical power to the blue pod.
3. loss of hydraulic pressure from the hot-line(s).
4. loss of hydraulic pressure in the rigid conduit line(s) coming down the riser.
T h e d e a d m a n se q u e n ce is u se r d e fin e d . O n th e Glomar Jack Ryan, the sequence is
programmed to rapidly increase the BOP manifold pressure, shear pipe, lock the ST-
Locks on the shear ram, close all choke and kill line valves, and unlatch the choke and
kill line connectors on each pod. Lithium batteries in each pod provide the necessary
electrical power to fire the solenoids and run the PLC processor that controls the
sequence. Fluid power is from four (4) dedicated 175-gallon accumulator bottles on the
lower BOP stack. These bottles are independent and isolated from the surface
accumulators except when being charged.
9 - 50
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9.13.4 ELECTRO-HYDRAULIC
An electro-hydraulic system is sometimes used for a backup to the multiplex BOP
control system. The electro-hydraulic system provides a direct electric signal to the
solenoid valves bypassing the multiplex logic. The system uses dedicated wires in the
MUX cable connected directly to the solenoid valves. This system requires the normal
hydraulic circuit to be operational and is setup to only operate dedicated emergency
functions.
9 - 51
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 52
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 53
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9.15.1 INTRODUCTION
The basic function of the diverter system on a floating rig is similar to that for rigs with a
surface BOP stack, to allow uncontrolled flow to be safely directed away from the drilling
rig. Figure 9.37 shows a typical diverter system.
The general purpose associated with diverter systems is to divert shallow flow from the
wellbore when insufficient integrity is available at the casing shoe to allow the well to be
shut-in and the influx circulated out with the BOPs. In floating drilling, the industry has
moved away from using the diverter system to handle a shallow gas kick at the surface
due to the higher peak pressures seen during riser unloading, and the reliability of the
diverter equipment. The dynamic peak pressure condition is not solely a floating drilling
condition but takes on added significance with floating rigs because of the larger
hole/riser volumes, equivalent higher formation pressures, more diverter equipment seal
arrangements, and the tortuous diverter flow path.
The primary use of the diverter systems today on floating rigs is to handle gas in
the riser. In this event, the diverter system is not exposed to as prolonged a pressure
situation because the source of uncontrolled flow has been shut off by the closed BOP.
The trapped energy of the gas migrating in the riser, however, will still have to be
handled by the surface diverter but for a shorter duration than a non-shut-in situation.
9 - 54
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 55
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
In areas where the water depth is less than 500 feet, a pin connector (Figure 9.38) may
be used if a zone with a high potential for shallow gas must be drilled in the conductor
hole section. The need for the pin connector is based on the fact that diverting subsea
could allow the gas to surface directly beneath the rig. The shorter riser length in this
water depth also provides less gas expansion/storage volume before it reaches the
surface making the diverter system a more reliable option. Pin connectors are very rarely
used in floating drilling operations today.
The best well control practice for shallow gas is prevention practices, i.e., controlled
penetration rates, seawater hydrostatic and dynamic kill procedures.
9 - 56
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 57
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
Diverter housing - anchors the diverter system and provides side outlets for
return flowline, diverter lines.and trip tank/fill-up lines. Diverter housing is
permanently mounted to the rig floor substructure.
Discharge lines and valves - routes fluids overboard or to the shale shaker.
Valves are also included to isolate all auxiliary lines for the trip tank and fill up
lines. Valves and lines are permanent installations on floating rigs.
Upper ball/flex joint provides angular movement of the riser/slip joint caused
by rig motion on floating rigs.
Slip joint - provides a dynamic seal between the riser and the rig while
permitting vertical motion of the rig.
Riser provides a conduit from the seafloor to the surface.
Diverter control system provides control to sequentially function the
necessary diverter components so the well is not shut in at the surface.
Riser Mud Gas Separator System (optional) provides a means to circulate
the mud from the riser through a mud gas separator before returning to the
shakers/mud pits.
9 - 58
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
Bladder
Diverter housing
lockdown dogs
Flowline Outlets
Diverter Housing
welded to substructure
On the KFDS diverter system it is important to ensure that the diverter close function is
never actuated unless the diverter packer is installed. Actuating the diverter packer
9 - 59
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
without the packer installed could cause the bladder to rupture causing injury to
personnel. To ensure that the diverter close function cannot be actuated unless the
packer is installed, an interlock is typically installed to block packer close fluid unless the
diverter lock down dogs are energized. A review of this system is typically required
during rig acceptance to ensure that an interlock system is included.
A CSO (Complete Shut-Off) diverter unit (Figure 9.41), that incorporates an annular-
type packing element is also used and found on rigs built or upgraded since the mid
1990s. This system has a full through-bore internal diameter equal to the riser and is
typically rated for 1000-psi wellbore pressure on 5-inch pipe and 500 psi wellbore
pressure on open hole. The full bore internal diameter allows the diverter packer to
remain installed while handling large OD tools thus reducing handling time for BHAs and
large downhole tools.
Opening Chamber
Closing Chamber
Closing the CSO type diverter is accomplished by applying pressure below the piston
that forces the element up and in around the pipe. The CSO diverter is opened by
venting closing pressure and applying opening pressure to the top of the piston. As the
piston moves down, the elasticity of the element forces the element to the open position.
The volume to close the CSO type diverter is substantially greater than the KFDS
diverter and can require up to 20 seconds to operate.
9 - 60
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 61
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
Ball Valve
Guillotine Knife
Valve
9 - 62
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
Ball valves are preferred in the flowline, and the diverter lines and are typically found on
floating rigs built or upgrades after the mid 1990s. The ball valve is preferred because it
provides a full open, non-restricted flow path with a quarter-turn actuation and can easily
be fitted with failsafe hydraulic actuators. Hydraulic actuators for ball valves are typically
designed for 1500 psi operating pressure and are preferred due to their reliability and
quick response. The hydraulic valve actuator for the ball valve is also generally smaller
than the pneumatic actuator on knife valves since it operates at a higher supply pressure
and does not require the piston travel. The BOP accumulator system is normally used to
provide the hydraulics to the actuators via independent pressure regulators for the
diverter system.
The guillotine knife-type valve was installed quite extensively on third generation and
earlier rigs and is still common on floating rigs today. The working pressure of the
guillotine knife-type valves is typically 150 psi and is acceptable for use, but not
preferred because of the low-pressure seal mechanism, the exposed gate feature and
the split-body design.
The split-body design may allow the fluid to leak external to the valve body. The knife
valve is also generally equipped with a low-pressure pneumatic actuator that may not
provide the force required to actuate the valves with high differential pressure. Air
actuators are normally designed for 80 to 120 psi operating pressure and are generally
much larger and require more maintenance than hydraulic actuators. If rig air pressure
drops below the minimum air pressure requirement to the actuator, the actuator torque
could be reduced and the valve may be slow opening or not fully opened. Pneumatic
actuators for guillotine knife valves typically do not have a failsafe feature to ensure that
the valve fails to the correct position should control pressure be lost.
Actuators should be sized to operate the ball and knife valves with the minimum rated
working pressure of the system applied across the valve. For example, if the diverter
system is rated as a 300-psi system, the actuators should be capable of operating the
valves against 300-psi pressure.
Butterfly valves are not acceptable in diverter installations since they are not full
opening. API gate valves are acceptable but are seldom used because of their costs,
large size and the large space necessary for installation and repair.
The shaker (flowline) valve should be installed upstream of all low-pressure equipment
such as flo sho, in-line gas sensor, mud bucket return line, and mudlog equipment to
protect the equipment during a diverting operation.
9 - 63
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 64
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9.15.10 RISERS
The drilling riser acts as the primary conduit between the drilling vessel and the well,
with the diameter of the riser sized to be compatible with the desired BOP/wellhead
system. The most common drilling riser size contains a nominal tube OD of 21 in. and a
0.625 in. wall. Riser sizes vary with in size and yield from wall thickness of 0.50 to 1.125
in. with pipe outside diameter from 20 in. to 22 in. and yield up 80 ksi.
For additional information on Risers and Slip Joints, see Section 10.
9 - 65
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 66
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
9 - 67
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
BLOWOUT PREVENTER EQUIPMENT
REFERENCES
1. IADC Deepwater Well Control Guidelines: First Edition, October 1998
2. E xxo n C o m p a n y In te rn a tio n a l F lo a tin g D rillin g B lo w o u t P re ve n tio n a n d W e ll C o n tro l
E q u ip m e n t M a n u a l; R e visio n 1 , 1 9 9 7
3. W e st D e e p w a te r C h a lle n g e s S e m in a r M a n u a l; Ju ly 2 7 -28, 2000
4. C a m e ro n C o n tro ls B a sic O p e ra tio n M a n u a l fo r th e M a rin e 7 0 0 D rillin g R ig ;
Volumes 1, 2 and 6, Revision B01, July 2001
9 - 68
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10
Section
RISER SYSTEMS
OBJECTIVES
On completion of this lesson, you will be able to:
State the maximum allowable ball/flex joint angles for drilling and
non-drilling conditions
Identify the major components of the diverter system and describe how it
operates
10 - 1
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
CONTENTS Page
10 - 2
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 3
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
RISER JOINTS
Individual riser joints are run from the lower flex joint through the water column. Riser
joints are equipped with choke and kill lines and may also be equipped with a hydraulic
conduit and/or mud boost line. Some riser joints may be equipped with buoyancy to
reduce the overall in-water weight of the riser.
PUP JOINTS
Shorter versions of the riser joints, pup joints allow the riser to be precisely spaced out for
the water depth at the well location. Pup joints are not equipped with buoyancy.
FILL-UP VALVE
The fill-up valve allows the riser to be rapidly filled with seawater to prevent riser collapse
if the drilling fluid begins to evacuate the riser (generally not recommended for use in
ExxonMobil operations).
10 - 4
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
TELESCOPIC JOINT
Often referred to as a Slip Joint, it attaches the upper-most riser joint to the rig. The
Telescopic Joint compensates for riser length variation due to vessel heave and offset.
The Telescopic Joint is composed of an inner barrel (upper section) and an outer barrel
(lower section). Riser tensioners on the rig are attached to the outer barrel and allow the
riser to be supported in tension to prevent buckling. The inner barrel is attached directly
to the rig at the upper flex/ball joint, and strokes in and out of the outer barrel as the rig
moves.
TENSIONER RING
A solid circumferential support ring called the Tensioner Ring has all of the tensioner
cables pre-attached and is stored beneath the diverter. The riser is run through the
support ring, and the ring is latched to the slip joint prior to landing the BOP stack.
The tensioner ring can be nonrotating or rotating for use with a D/P rig.
RISER TENSIONERS
Riser tensioners allow constant tension to be applied to the riser while allowing for rig
heave.
DIVERTER
The diverter housing allows the drilling fluid returns to be directed to the mud pits. It also
has an element that allows the top of the riser to be closed so that gas/mud returns can be
safely diverted overboard through large diameter vent lines in the event gas is allowed to
enter the riser.
Each of the components above the BOP is an integral part of the drilling riser system.
The various drilling riser system components are described in more detail below.
Sketches of major components or subassemblies are provided.
10 - 5
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 6
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
A typical drilling riser joint consists of the following components (Figure 10.3):
riser main tube
connectors
auxiliary lines (choke, kill, mud boost, hydraulic conduit)
buoyancy
Since the BOP isolates wellbore pressure, the riser is not generally considered as a high-
pressure containment component. However, pressure integrity is important since the
hydrostatic pressure of the mud in the riser is greater than the seawater pressure outside
the riser. This pressure differential becomes pronounced as illustrated in the Table 10.1
for varying water depth and mud weight increases.
Loss of pressure integrity in the riser can cause the wellbore to be underbalanced since
the riser may contain a significant amount of the total hydrostatic pressure.
10 - 7
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
The lower half of the connector also forms a landing shoulder for hang-off of the drilling
riser system during installation and retrieval of the BOP stack. This hang-off provision is
im p o rta n t in d e e p w a te r w ith la rg e B O P s sin ce th e rise rs h a n g in g w e ig h t a n d th e re su ltin g
dynamic loading can be significant, and the support shoulder must be able to handle
such conditions.
10 - 8
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
Generally, riser end connections are preloaded designs. Methods to achieve preloaded
conditions vary between different suppliers. A preloaded connection is one in which the
co n n e ctio n s m e ch a n ica l fo rce s, o n p ro p e r m a ke -up, exceed the range of anticipated
bending, tension, and pressure separating loads. Proper preload prevents large cyclic
stresses in the connection and its premature fatigue failure.
Tensile capacity for riser coupling is defined by API Spec 16R in Table 10.2:
A seal subassembly or seal sub located between the flanges provides pressure integrity.
By using a separate seal sub, rather than an integral seal, change-out of a leaking riser
joint is quick and easy during running operations without having to replace an entire joint.
This is usually a field-replaceable insert equipped with elastomeric seals, however metal-
to-metal seals are also available. In addition, if a seal pocket within a flange is damaged,
then special seal subs are usually on-hand utilizing elastomeric seals in different locations
to bridge the damaged area(s) within the seal pocket.
The most common connector for a deepwater application is a flange connection like that
shown in Figure 10.6. Makeup of flange connections typically requires the use of large
bolts to ensure proper connection preload. Preloading ensures pressure and structural
integrity, and fatigue resistance. Most designs of this type have replaceable bolts and
nuts so that damage to threads can be quickly and easily handled at the rig floor.
Seal Sub
10 - 9
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
Another common type of riser connector is the dog type, shown in Figure 10.7. Bolts or
screws are used to drive dogs on the box end of the coupling into a profile on the pin end.
Within this design, individual segments are radially preloaded into a mandrel profile on the
other half of the connection. Angled faces on the segments and the mandrel profile
convert this radial loading into axial preloading forces within the connection. Proper
torque applied to each segment actuating screw creates the desired preloaded condition.
As with the flange connectors, this preloaded mechanical connector also creates sufficient
force to resist the separating force of the radial positioned auxiliary lines around the
circumference of the riser string tubular. In some designs, the actuating section of the
connector can be readily removed and replaced at the rig floor should the actuating
mechanism become damaged, thereby allowing running or retrieval operations to
continue.
During makeup of the riser joints, all auxiliary lines (choke, kill, mud boost, rigid conduit)
are configured on the riser joints to align and stab when each riser connection is made up.
Auxiliary lines are typically secured to the joint at the riser flange and do not have their
own locking connection. Since the lines do not lock together, all loads from the riser and
BOP stack are supported by the riser flange. In addition, the load that is generated while
pressure testing the auxiliary lines (Table 10.3) is also transmitted to the flange and can
be substantial for large bore choke/kill line systems
10 - 10
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10.6 BUOYANCY
Riser joints may also be equipped with buoyancy to help offset the riser system's
submerged weight. The closer the riser is to neutral buoyancy, the less top-tension is
needed to maintain a vertical position. There are two methods of providing buoyancy,
syntactic foam and air cans.
Syntactic foam has an in-air weight of 24-to-32-lb/cu ft, is simple, rugged, and finding
wider use for both drilling and permanent production riser installations. Syntactic foam
can be used in deeper applications and does not require air compression equipment that
air cans require. However, the density of the foam to withstand the increased hydrostatic
pressure increases overall weight and deck load.
Syntactic foam is more reliable than air cans and does not require air compression
equipment that air cans require. However, since it provides less buoyancy than the same
volume of air, foam usually results in greater outside diameters and longer coverage
lengths versus the air can approach. The buoyant force generated by the foam must not
exceed the submerged weight of the riser system since the riser string must remain
negatively buoyant to prevent compression when the LMRP is disconnected from the
BOP stack.
10 - 11
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
Generally the foam should be run in the corresponding water depth range to minimize the
top tension required and to prevent water ingress into the foam if it is run too deep.
During the riser analysis, it is essential that amount and location of each type of foam
buoyancy is known so that the correct riser tension curves can be calculated.
10 - 12
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 13
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 14
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 15
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 16
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 17
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 18
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 19
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
An upper flex/ball joint, like the lower one, accommodates lateral movement of the drilling
vessel and prevents bending failure at the upper end of the riser. Like the lower flex/ball
joint, the upper one provides rotational motion while maintaining wellbore access and mud
column containment. These are also usually ball or flex joints providing up to 10-degrees
of freedom. The functional requirements and design features of this joint are similar to
those mentioned for the lower flex/ball joint, but the upper joint is not required to
withstand a large pressure differential, therefore pressure compensation is not
necessary. Figure 10.16 shows an upper ball joint.
10 - 20
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 21
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
During normal drilling operations, the diverter, shown in Figure 10.17 and 10.18, directs
drilling fluid from the telescop in g jo in t to th e m u d p its. In th e ve rtica l b o re s o p e n p o sitio n ,
the fluid exits through lateral ports (flowline) that are piped to the mud pits. If there is an
unexpected abrupt mud or gas flow into the drilling riser, the diverter system [diverter,
flowline valve(s), and overboard diverter line valve(s)] redirects the flow to the overboard
line and closing in around the drill pipe. The diverter usually contains multiple large
diameter (12 to 16 in.) lines for handling large volumes of mud flowing up the drilling riser.
If an unexpected flow takes place, these lines are isolated and other lines that lead to
overboard are opened.
During a well control situation, an annular-like element closes the vertical opening in the
diverter, thereby isolating the rig floor and protecting rig personnel. This annular element
allows the diverter to close on a wide range of tubular sizes. The diverter is not intended
to a ct a s a b lo w o u t p re ve n te r, b u t a s a m e a n s o f re d ire ctin g th e flu id s ve rtica l flo w fo r sa fe
discharge. To prevent significant pressurization, diverter systems are designed such that
activation causes the vent lines to open. At the same time, the bag element and flowline
are closed. The diverter sits in a diverter housing that is a structural part of the drilling rig
directly beneath the rotary table.
Diverter Seals
Trip Tank Pump Inlet
10 - 22
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10.11.1 GENERAL
The riser is subjected to various forces that cause it to deviate from vertical and since it
essentially gains all of its structural integrity from tension, the single most important
parameter in operation of the system is top tension. Insufficient top tension can result in
operational problems associated with riser curvature, large flex joint angles, or even
buckling. Tensioning the riser will reduce the curvature and flex joint angle, however too
much tension produces high stresses in the riser that can result in reduced fatigue life and
increased maintenance to the riser and the tensioning system.
To determine the proper tension for the various mud weights during the well, a riser
analysis is performed based on the following parameters:
Water depth.
Mud weight.
Wave and current environment.
Riser properties.
Vessel Offset.
Prior to the riser analysis, detailed specifications of the riser components should be
obtained from the Contractor or Manufacturer to provide buoyancy and in-water weights.
Table 10.4 low is an example of riser specifications for the Glomar Jack Ryan riser.
10 - 23
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
With the riser information listed above and the water depth at the location, a riser joint
arrangement can be prepared to establish the weights for the required riser configuration.
A number of comprehensive computer programs have been developed to model riser
behavior and determine the riser angles and stresses associated with a prescribed set of
parameters or operating conditions. These angles and stresses are compared to a set of
empirically based limits, or criteria on the stresses and angles, and are used to establish
the recommended riser tension using an iterative analysis that requires vessel offset as an
input. A mooring analysis or station-keeping analysis is required to determine the
appropriate vessel offsets to input to the riser analysis.
In areas with a severe environment, deepwater, or when operating with a D/P rig, a
co u p le d a n a lysis may be performed to include bending loads throughout the entire riser
system including the BOP stack, wellhead, and structural/conductor casing. This analysis
accounts for bending from the BOP stack down through the conductor casing taking into
account soil strengths, whereas the normal riser analysis assumes the BOP stack is a
fixed point.
10 - 24
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
WAVE
FORCES
C
BOUYANCY TENSION PULLED
U F
R O ON RISER BY VESSEL
R R
E C VESSEL OFFSET
NTES
WEIGHT OF MUD,
RISER AND DRILLSTRING
IN RISER (IF ANY)
Figure
Figure 10.18
10.19 RiserLoads
Riser Loads During
During Drilling
DrillingOperations
Operations
10 - 25
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
It is essential that upper and lower joint angles remain below specified values to prevent
damage to the riser, LMRP, BOP and casing strings. Damage to these items can result in
loss of pressure integrity and subsequently well control. To maintain riser integrity and
ensure safe operations, API recommends maximum design and operating guidelines
including a calculation for Minimum Required Top Tension as represented in Table 10.5.
10 - 26
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
where TSR min is the minimum slip ring tension; N the number of tensioners; n the number
of tensioners subject to sudden failure; and R f the fleet angle and mechanical efficiency
factor. For a typical rig with 8 tensioners N = 8, two of which are subject to sudden
failure n = 2, and a fleet angle and mechanical efficiency factor R f = 0.90 then:
Note: If the tensioners are connected and operated in pairs, then two tensioners should
be considered for sudden failure. If the tensioners have individual controls and separate
piping, then one tensioner can be considered for sudden failure.
10 - 27
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 28
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
COLLAPSE
The riser is not generally designed to resist hydrostatic collapse, but this situation can
occur if the riser is evacuated by a large gas influx or by a severe loss of mud (either to
the ocean or downhole). Riser can withstand from 1000 to 4000 ft of evacuation
depending on the wall thickness, diameter and yield strength. The DRILLRISER program
in the standard PC load can be used to determine the void depth at which collapse occurs
for a specific riser and top tension. The OIMS manual requires that riser collapse be
checked against the following criteria:
Unloaded by gas: 50% evacuated (but maximum evacuation of 1500 ft)
with 9 ppg mud below
Hole in riser at bottom: the heavy mud in riser equalizes with seawater
and leaves the upper section of the riser void,
void depth = water depth x (1.0 8.5/max. mud density)
BURST
The riser is subject to burst loads imposed by the pressure differential between the
internal mud and external seawater. Although burst should be checked, particularly in
deepwater, these loads are usually well within the burst capacity of the riser pipe.
VIV ANALYSIS
In high current situations, analysis for VIV should be performed by URC. This analysis will
determine if VIV is likely to occur and what the expected fatigue life of the riser will be. If
VIV damage potential is too high, it is possible to run VIV suppression devices. See
Section 10.16 for VIV suppression devices.
HANG-OFF ANALYSIS
The particular hang-off configuration for a rig should be modeled to determine if the rig
and riser motion could cause significant dynamic effects, or bucking at the top of the riser.
If problems are indicated, there may be preventive measures available such as altering
the suspended weight of the riser (e.g. trapping mud in the riser on disconnect).
10 - 29
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
DEEPWATER DRILLING
In d e e p w a te r, th e rise r w ill n e e d b u o ya n cy a n d th e rig s te n sio n in g ca p a city w ill h a ve to b e
high, especially with high mud weights. The high tension may result in high stress and
necessitate the use of the Method B for the stress evaluation. Riser collapse is also more
of a concern in deepwater.
HIGH CURRENTS
High currents increase the upper and lower riser angles and vessel offset must be more
carefully controlled. Higher riser tension is required to keep the riser angles low.
SEVERE ENVIRONMENTS
Severe wind and wave conditions increase vessel offsets and usually cause the lower
riser angle to be the governing criterion. In some cases the static and dynamic stresses
will cause the stress limit to be exceeded. The stress criterion rarely governs except in
severe seas or situations where the riser is not suitable for the water depth, mud weight,
and environment.
10 - 30
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
2500
Riser Vertical Tension (kips)
2000
1500
1000
Since the Glomar Jack Ryan is a D/P vessel and subject to an emergency disconnect of
the LMRP, the minimum riser tension in the example above is constant for mud weights
from 8.55 ppg (seawater) to 11.5 ppg. The governing factor for the tension from 8.55 ppg
to 11.5 ppg is minimum tension to ensure lift off of the LMRP from the BOP stack, not riser
stability. For mud weights over 11.5 ppg, tension increases to offset the additional mud
density in the riser.
10 - 31
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
Required Data:
A 12.0 ppg Mud Weight
B 50 feet Height of mud column above mean water line
C 75 feet Length of standard riser joints
D 6 each Number of standard riser joints without buoyancy
E 10/21 each Number of standard riser joints with buoyancy each type 1 and 2
F 30975 lbs In-water weight of a standard riser joint without buoyancy (0.87 x air weight)
G 3975/645 In-water weight of a standard buoyed riser joint weight for each type 1 & 2
lbs/each jt.
H 60 feet Total length of riser pup joint(s)
I 35000 lbs Total in-water weight of riser pup joints
J 105544 lbs Total weight of outer barrel (of the telescopic joint) above water, tensioner ring,
and middle flex joint
K 75 feet Length of outer barrel below water
L 3.0 in. C&K line ID
M 60750 lbs In-water weight of outer barrel (air wgt. X .87)
N 19.75 inches Inside diameter of standard riser joint
P 2959 feet Distance from mean water line to bottom of lowest riser joint
Q 8 Number of tensioners
TWW Total weight of the riser string in water (w/o mud), KIPS (1000 pounds)
DMW Differential mud weight (riser and C&K lines) , KIPS (1000 pounds)
MTT Minimum Top Tension, KIPS (1000 pounds)
MTS Minimum Tensioner Setting, KIPS (1000 pounds)
The objective of the calculation is to estimate the suspended weight of the riser and the
differential mud weight. The buoyed weight of the various riser joints and the telescopic
joint can be obtained from the rig contractor. These weights are usually recorded when
the riser is run and the contractor will have data from previous installations that will allow
the weights to be verified.
10 - 32
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
CALCULATION
1. TWW = [(D x F) + (E x G for type 1) + ( E X G for type 2) + I + J + M]/1000
= [(6 x 30975) + (10 x 3975) + (21 x 645) + 35000 + 105544 + 60750]/1000
= [185850 + 39750 + 13545 + 35000 + 105544 + 60750]/1000
= 440 KIPS
2. DMW = {0.052 x x [(A-8.55) x N2 x P + A x N2 x B + (A-8.55) x L2 x P]}/1000
4
= 0.052 x .785 x [(12.0 8.55) x 19.52 x 2959) + 12.0 x 19.52 x 50 + (12.0 8.55) x 32 x 2959
1000
= {0.052 x .785 x [(3.45 X 390.0 X 2959) + (12.0 x 390.0 x 50)]}/1000
= {0.052 x .785 x [3981334 + 234000]}/1000
= 172 KIPS
3. MTT = TWW + DMW
= 440 + 172 = 612 KIPS
4. MTS = MTT x [ Q/( Q tensioner pair failed ) ]/(efficiency due to fleet angle and mechanical)
= 612 x [ 8/(8 2) ]/0.9
= 612 x 1.48
= 906 KIPS
10 - 33
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
The goal of the space out calculation is to determine the number of riser joints and pup
joints that will be required (Table 10.7). Consideration is given to the possible tidal
variations, maximum heave motions and lengthening of the slip joint due to vessel offset.
A desired mean slip joint stroke position is established based on these factors. Generally,
a rig will space out so that the slip joint is one-half to two-thirds closed. This allows for rig
heave and tidal variation to further collapse the slip joint, and maximizes the length
available slip joint to stroke out as the vessel offsets from the location.
10 - 34
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 35
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
A riser running tool (see Figure 10.22) is used to lift individual riser joints into the derrick
and to raise or lower the entire riser string. The lower end of the riser running tool
engages the riser connector on the top of the riser joint. The make-up of the riser running
tool can be manual or hydraulic. The upper end of the riser running tool will directly fit into
the bails suspended from the hook, or it will have a sub that fits into large elevators in the
bails.
Dog Type Riser Running Tool Flange Type Riser Hydraulic Flange Type Riser Mechanical
Vetco MR-6D Running Tool Vetco HMF Type Running Tool Vetco HMF
The BOP and LMRP are the first components of the riser system that are run. The BOP
and LMRP should be thoroughly inspected and function tested on the rig prior to being
deployed. This preparation can be completed out of the critical path if the LMRP and BOP
are stored together as a single unit and the pod hoses can be installed. On some rigs, the
BOP and LMRP must be mated in the moonpool as they are run, which necessitates
function testing of the stack in the critical path to ensure that the control pods are correctly
configured and engaged.
10 - 36
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
The following points should be considered when reviewing the contractors procedure for
running the BOP, LMRP, and riser:
Ensure that a new steel ring gasket is installed in the wellhead connector.
If the stack was split from the LMRP prior to being mated in the moonpool,
then a function test should be performed to test all pod seals between the
LMRP and BOP.
Pull off the location 75 ft or more prior to running the riser. Move the rig back over
the well when preparing to run the telescopic joint.
Minimize the time that the BOP and LMRP spend in the wave zone. This can be
accomplished by making up two joints of riser together before connecting them to
the LMRP.
Test the choke and kill lines every five to ten joints to the maximum test pressure
that will be required throughout the well. Ensure that sufficient spare riser seals
are available at the rig.
Ensure that the riser running tools and handling equipment have current inspection
certification.
Ensure that there is proper equipment and a reliable procedure for checking the
torque and make-up position of the riser connections.
Record the weight of the riser every joint as it is deployed. An accurate
measurement of the buoyed weight is required to ensure that sufficient tension is
applied to the top of the riser. The final hanging weight should be compared to the
value used in the riser analysis.
Verify that the riser buoyancy rating is sufficient for the planned deployment depth.
After lowering the BOP and LMRP below the splash zone, all auxiliary lines are typically
pressures tested to ensure pressure integrity in each line. Auxiliary lines should be tested
to the maximum BOP test pressure that will be encountered during the well and at regular
interval while running the remaining riser. The control umbilicals or mux cables are
spooled out and run with the riser.
When running the BOP stack in a high current environment, the current may cause the
BOP stack and riser to deflect and be offset from the rig (Figure 10.23). This offset can
cause high bending loads at the riser flange, restrict operations due to contact between
the riser and the diverter housing, and require the rig to be offset from the location to
position the BOP stack over the wellhead before landing the stack. On a D/P rig, the rig
may even be placed up current and allowed to drift with the current to minimize the angle
in the rotary while deploying the riser.
10 - 37
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
On deepwater riser deployment operations, relatively small vessel heave can cause high
loads on the riser and surface equipment due to the different frequencies of the riser and
vessel motions. Due to the large mass of the riser, the motion of the riser can get out of
sync with the vessel as it heaves up and down. This difference in frequency may cause
extremely high loads if the riser is still traveling down and rig starts an upwards motion.
Hookloads of 2 to 2.5 million pounds have been reported during these episodes. During
the opposite cycle, the riser may go into compression if the rig heaves down while the
riser is still on the up stroke, which may cause the riser to buckle, then develops high
sn a p a n d je rk lo a d in g a s to re tu rn s to te n sio n .
10 - 38
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
CONSIDERATIONS
The telescopic joint is more commonly landed fully collapsed and locked as described
above. Some rigs land the stack with the telescopic joint fully extended like a bumper
sub. The disadvantage to this procedure is that the landing shoulder on the bottom of
the inner barrel is rarely inspected and several BOP stacks have been dropped from
this failure.
The riser tensioners are usually rigged up prior to landing the stack. This allows a
large portion of the load to be carried by the tensioners as the stack is landed. At
least enough tension to prevent buckling of the riser is usually transferred to the
tensioners, with the remaining load carried by the block.
10 - 39
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
The BOP stack should be directly over the wellhead before it is lowered. This
prevents damage to the wellhead or the guidelines (if used). Guidelines can easily be
severed as the stack swallows the guideposts. Landing of the stack is monitored with
a Remotely Operated Vehicle (ROV) or a stack mounted camera.
Once the stack is positioned over the well it should be lowered firmly to swallow the
wellhead connector.
10 - 40
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 41
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 42
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
When reviewing the rig procedure for hanging off the riser, some issues to consider are as
follows:
The riser must be pulled up far enough to ensure that the LMRP remains clear of the
BOP stack.
If the riser is hung off in the spider, rig movement may cause the riser to rock within
the spider, or rock the entire spider. Gimbaled spiders may help prevent this.
If the riser is suspended on the riser running tool and/or tensioners, the dynamic load
caused by relative motion between the riser and the rig can be very large. The reason
that the loads can be very large is that they depend on the acceleration and
deceleration of the total mass of the riser, not just the relatively low buoyed weight.
An indicator of this dynamic effect is a fluctuating load.
Interference between the riser and the diverter housing, moonpool or hull should be
considered. If the riser is left suspended through the diverter housing it is probably
better to position a bare joint in the diverter.
If the rig is abandoned with the riser suspended from the tensioners, it is important to
overpressure the tensioners so that they remain stroked out and the riser load is
evenly distributed among the tensioners even if some of the air bleeds off. If the
tensioners stroke in and bottom out the load will be unevenly distributed among the
tensioners, possibly overloading some of the lines.
10 - 43
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 44
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10 - 45
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
RISER SYSTEMS
10.17 REFERENCES
IADC Deepwater Well Control Guidelines: First Edition October 1998
E xxo n C o m p a n y In te rn a tio n a l F lo a tin g D rillin g B lo w o u t P re ve n tio n a n d W e ll C o n tro l
E q u ip m e n t M a n u a l; R e visio n 1 , 1 9 9 7
API Recommended Practice 16Q First Edition, November 1, 1993
Atlantic Margin Joint Industry Group, Deepwater Drilling Riser Integrity Management
Guidelines, Revision 2, March 2000
10 - 46
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11
Section
OBJECTIVES
The intent of the material in this section is to only cover the differences in well control
operations conducted from a floating rig and the same operations conducted from a rig
with a surface BOP stack. A basic understanding of well control operations and
principles is required.
On completion of this section, you will be able to:
Describe the complications in abnormal pressure detection and kick detection when
drilling from a floating rig.
List the considerations for selecting a pump rate when circulating out an influx with a
subsea stack.
Describe a method to compensate for choke line friction when initiating circulation
when circulating out an influx on a floating vessel.
11 - 1
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
CONTENTS Page
11 - 2
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11.1 GENERAL
The major difference in floating well control is the location of the BOP stack on the ocean
floor. The well control complications resulting from the BOP stack being located on the
seafloor include:
Effects of long large risers, and long small diameter choke/kill lines.
As the water depth increases, the BOPs are moved further from the rig and can actually
be closer to the bit than to the rig for most of the well. This, along with the large volume
of the drilling riser, complicates early detection of kicks and makes quick reliable shut-in
methods more complex. The long choke and kill lines also complicate and hinder
successful well control operations due to their high friction losses.
Unlike surface BOP well control operations, the BOPs are installed on the conductor
casing, and the diverter system remains ready for use anytime the BOP stack is run.
Diverter systems on floating rigs are also subject to more frequent and rigorous service
conditions than those encountered with surface BOP operations since they remain in
place throughout the well.
Causes of kicks and the equipment/procedures for kick detection are not necessarily all
unique in a floating drilling operation.
11 - 3
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 4
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
In floating drilling operations, the integrity of the formation should be tested after setting
each casing string. Prior to the PIT, the mud should be circulated to ensure that it is
clean and that there is a uniform mud density throughout the wellbore. If there is
sufficient heave to cause movement of the pipe through the annular preventer, the pipe
should be hung off on the pipe ram to prevent surges and fluctuations in the pressure
during the test. Since the surface pressures are typically low, especially for shallow
casing string, a low pressure gauge or digital gauge should be used to record the test
pressures. Pump rates during the test may vary from to 1 bpm depending on the open
hole size and hole volume. To provide sufficient data points, pressures during the test
should be recorded and plotted every bbl regardless of the pump rate. To determine
the fracture closure pressure, the final shut-in pressure should be held a minimum of 10
minutes. The results of the PIT should be calculated and posted on the rig floor to assist
in planning for well control operations.
When conducting PITs with non-aqueous fluids (NAF), the operation is much more
critical since fractures caused by an NAF are much more difficult to close and less likely
to regain their original fracture resistance strength. For this reason, caution should be
taken when performing the PIT with an NAF to ensure that initial leakoff is detected
before excessive fracturing occurs.
If a computerized cement unit is used, the pressures should be recorded by the
computer at the unit so that additional data points can be provided. The real time plotting
feature of this system can be beneficial in identifying the initial leakoff to the formation.
When using a Pressure While Drilling (PWD) sub, the pressures recorded by the PWD
during the PIT should be downloaded and compared to the surface test pressures to
confirm the results.
The mud density to control the well is distributed throughout the open hole, casing and
riser. In deepwater locations, the hydrostatic in the riser may be providing anywhere
from 25 to 50% of the overall hydrostatic pressure for the wellbore. When operating in
shallow water (<1000 ft), a common practice was to maintain a mud weight that would
provide an overbalance on the wellbore during the loss of hydrostatic from the riser. In
deepwater locations where sufficient mud weight to provide an overbalance for loss of
hydrostatic in the riser cannot be maintained while drilling, procedures must be in place
and equipment must be tested to ensure that the well can be secured prior to the loss of
the riser.
The compressibility effects associated with NAF are a function of both pressure and
temperature. The density at the bottom of the wellbore can be 0.3 to 0.5 ppg heavier
than measured at the surface due to the hydrostatic pressures exerted on the fluid.
Conversely, the density at the bottom of the wellbore on a high temperature well can be
0.3 to 0.5 ppg lighter than measured at the surface due to the expansion of the fluid. On
most deepwater wells, the bottom hole temperatures will be low, therefore the pressure
effects will dominate. Even if a NAF is used during the PIT, it typically will not cause a
problem since the relative difference between the mud weight and the PIT pressure is
the same.
11 - 5
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
Another characteristic of the NAF is a higher friction loss while circulating resulting in a
high Equivalent Circulating Density (ECD). ECDs from NAF will typically run between 0.3
and 0.6 ppg and are especially high when drilling 8 in. hole below 9 5/8 in. casing due
to the smaller annular clearance. When drilling with NAF, the use of a PWD tool can be
especially useful in determining the actual downhole pressure.
Due to the thin margin between the pore pressure and the overburden pressure, mud
losses on deepwater wells are common and difficult to prevent. Once the fracture is
opened, it can be difficult to stop. Since shallow formations in deepwater do not develop
matrix strength, fracture propagation may also be difficult to stop. The use of an NAF will
also compound this problem due to the heavier density from the compressibility of the
mud. The higher ECD pressures while circulating and the increased difficulty for the
formation to heal since the NAF penetrates the fracture tip more readily is also a
problem. The following drilling practices are commonly used to prevent exceeding the
fracture gradient:
Control drilling to limit cutting loading and increasing the ECD.
Limiting tripping speeds and pipe movement to prevent surges.
Use of PWD tools to measure downhole ECDs while drilling.
Better training and kick detection by rig crew and monitoring equipment.
11 - 6
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 7
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
With substantial heave, the flowline rate will change in response to this vertical motion,
making it difficult to detect a small influx. Other rig motions, such as substantial roll and
pitch, will affect the liquid level of the mud pits and make it difficult to accurately measure
the active pit volumes and the changes in their levels. During heavy sea conditions,
PVTs can fluctuate +/-20 bbls and the flo-sho can deviate 10 to 15%. This problem can
be even greater when operating from a drillship due to increased motion.
As water depth increases, the importance of detecting a kick early also increases in
response to the rapid increase in gas volume allowed to expand freely as the influx is
moving up the hole. For very shallow water locations, the rapid volume increase is
detected by increasing flow or pit volume, and the BOPs are closed well before the gas
reaches the BOPs or the surface. For deepwater wells, an influx may be above the BOP
stack before a significant change in pit volume and increased flow is noticeable at the
surface.
A second reason for early influx detection is the limited differential between mud weight
and fracture pressure typically found in deepwater wells. The likelihood of a kick causing
lost returns is significantly increased when the mud weight fracture pressure tolerance is
small.
PVT SENSORS
When a rig is experiencing substantial motion, kick detection can be improved in a
number of ways. Frequent flow checks by the driller is the simplest method. The well can
also be flow checked to the trip tank to determine if a small flow is occurring. Pit Volume
Totalizer (PVT) sensors can be installed to minimize pit volume deviations due to the
rig s p itch a n d ro ll. L o ca tin g th e P V T se n so rs in o p p o site co rn e rs o f a n a ctive p it a n d
a ve ra g in g re su lts w ill n e u tra lize th e rig s m o tio n .
Another factor that increases the difficulty in detecting an influx is the use of synthetic
base mud (NAF). While drilling, the flow properties of NAF can add up to 0.6 ppg of
ECD and provide sufficient overbalance to prevent a formation from flowing until the
interval has been drilled and the pumps are shut down. The disadvantage to this
situation is that since a larger amount of the high permeability, high porosity formation
has been drilled, larger influxes can be taken in a shorter time period. The highly
compressible nature of the fluid also makes it more difficult to flow check the well since
the natural expansion of the mud will cause the well to flow longer on connections and
flow checks.
D u rin g d rillin g , a p h e n o m e n o n ca lle d b a llo o n in g ca n o ccu r w h e re flu id is lo st w h ile
circulating and flows back into the wellbore when the pumps are turned off. This
phenomenon is caused by the opening and closing of induced or in-situ micro fractures.
When the bottom hole pressure (ECD) exceeds or equals the fracture propagation
pressure, a stable radial fracture is propagated. When the pumps are turned off and the
ECD falls below the fracture propagation pressure, the fracture closes and pushes the
mud back into the wellbore. Flow back from a ballooning formation can be 50 to 75 bbls
and take up to 30 minutes to stop flowing on connections.
11 - 8
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
To provide for kick detection, the well is flow checked to the trip tank with the flow rate
recorded (e.g. volume recorded each minute) and compared to previous flow checks. A
decreasing flow rate while flow checking would typically indicate a ballooning formation,
whereas a constant or increasing flow rate would indicate an influx from the formation.
Trending successive flow checks is key to identifying ballooning
When the ECD exceeds the fracture propagation pressure significantly, the fracture
propagation becomes unstable and results in massive mud losses.
11 - 9
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 10
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
Whenever the mud weight is changed substantially, the choke line friction can be
corrected by use of this equation:
11 - 11
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 12
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
In addition to the typical diverter system used to divert the fluid overboard, some rigs
are now equipped to allow returns from the riser to be routed through a gas separator
where the gas can be vented and mud returned to the active system. This system is
beneficial in keeping the gas off the rig floor and out of the mud processing room, but
they are not designed to handle a riser unload should the gas reach its critical expansion
point. In addition, the riser degasser systems may not allow indicators such as flo-sho
and return gas to be monitored since they could be bypassed.
If trapped gas is released into the riser (above the BOPs), field-testing has shown that it
is important to allow the gas to migrate to the surface without pumping. This will tend to
strin g -o u t a n d ke e p th e g a s in sm a ll b u b b le s w h ile in th e rise r. S m a lle r g a s b u b b le s ca n
be handled safely because they surface slowly and do not displace mud from the riser
(small bubbles slip by mud in the riser). After given adequate time for gas to migrate to
the surface, the riser must be circulated to remove any residual gas. As a precaution,
this circulation should be performed at a very slow rate.
11 - 13
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
SPACEOUT AND SHUT-IN 1. Pick-up and position tool joint to shut-in the well.
2. Shut down pumps.
For this reason, precise instruc- 3. Check for flow.
11 - 14
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 15
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
To allow for a fast sh u t-in , the first valve downstream of the choke should be in
the closed position with the choke half open during drilling and tripping operations
(Figure 11.3).
First Valve
Downstream of Choke
Open Valve
Closed Valve
Figure 11.3 Shut-in Arrangement for Typical Choke Manifold for Subsea BOPs
11 - 16
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 17
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 18
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11.7.1 GENERAL
T h e D rille rs co n so le sh o u ld b e e q u ip p e d w ith an accurate gauge to monitor the drill pipe
pressure and a display showing the pump rate in strokes per minute and the cumulative
number of pump strokes. The display should also provide a control to zero the
cumulative stroke counter.
The control panel for the remotely adjustable chokes should provide gauges to register
drillpipe pressure and casing pressure immediately upstream from the choke that is used
to control the well. The panel also contains the choke controls, a gauge indicating choke
position, meters to read pump rate in strokes per minute and cumulative pump strokes,
and a control to zero the cumulative pump stroke counter.
In addition to the previously described equipment, an additional gauge should be
provided at the choke console to monitor the casing pressure on the circulating line that
will not be used (inactive line) to circulate the influx from the wellbore. This inactive
circulating line gauge is used:
To simplify the measurement of choke line friction pressures.
To allow the choke operator to automatically exclude most, if not all of the choke
line friction from drill pipe pressure when the initial drill pipe circulating pressure
is established.
To signal the invasion of the active choke line by gas.
In addition, some rigs with multiplex BOP control systems have pressure and
temperature sensors installed on the BOP and/or LMRP for monitoring the pressure and
temperature at subsea. If the BOP is equipped with a pressure sensor, it can be used to
compensate for CLFP when initiating circulation and to signal when the influx enters the
BOP stack. The use of the sensor is especially useful since it:
Provides a gauge to compensate for CLFP when using both lines to circulate.
Allows the inactive line to remain closed for use as a backup line.
Provides a subsea sensor to measure the annulus pressure when the fluid in the
choke/kill line is too viscous to transmit a pressure to the surface.
11 - 19
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 20
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
When using two lines for circulation, the BOP stack may act as a gas/mud separator
assuming the mud and gas are in two phases. The effect of this is that the majority of the
gas will exit through the upper choke/kill line, causing the friction to be less, thus
allowing a greater proportion of the total influx flow through the upper line. The net effect
is that there is less of a chance for mud/gas swap over in the choke/kill line and less
fluctuation in surface pressures.
11 - 21
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 22
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
TYPE OF INFLUX
A gas influx produces a higher casing pressure than any other type of influx of the same
volume. This is due to the ability of gas to expand as it nears the surface and force mud
from the annulus, thereby further reducing the hydrostatic pressure. Any influx should be
assumed to be gas as it represents the worse condition. Even a water or oil kick will
contain associated gas.
KICK INTENSITY
Kick intensity refers to the additional mud weight in pounds per gallon required to kill the
kick, i.e. a one-pound kick, a two-pound kick, etc. It is equal to shut-in drill pipe pressure
divided by the depth of the kicking formation and the 0.052 conversion factor. Kick
intensity primarily affects the rate of influx feed-in rather than the maximum surface
pressure reached during circulation. That is, a two-pound kick will feed in at a faster rate
than a one pound kick. The pressure levels of kicks of different intensity are appreciably
different throughout a large portion of the circulation. However, when the gas reaches
the surface, these pressures differ by very little. Therefore, for the same volume of
feed-in, the maximum casing pressure is relatively insensitive to the kick intensity;
however, since the rate of feed-in is governed by the pressure differential into the
wellbore (as well as other factors such as formation permeability), a 1.5 pound per gallon
kick would have to be detected much quicker than a 0.4 pound per gallon kick for the
volume of feed-in to be the same. If the same time elapses in both cases before the
kicks are detected and the well shut-in, the volume of feed-in would be much greater
with the 1.5 pound per gallon kick.
11 - 23
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 24
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 25
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
CASING BURST
The maximum allowable surface pressure on the casing should be calculated for each
change in casing type in a casing string with different weights and grades, and the
lowest value used. The weak point in the casing is usually at the bottom of the lowest
grade and weight of pipe in the string. The lower of the two values for the casing or the
casing shoe will determine the estimated surface pressure for downhole failure. Usually
the casing shoe will govern.
For casing strings with extensive drilling or tripping hours, additional consideration
for casing wear should be considered in the burst calculation. Misalignment in
particular may be a problem on deepwater wells due to the possible wellhead
angle or rig offset. Casing wear is also caused from deviated holes, doglegs,
coarse hardbanding, and corrosion.
11 - 26
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 27
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
OVERBALANCE
MUD WEIGHT
In some circumstances, where sufficient integrity at the casing shoe is available, the well
may be circulated by adding a couple of additional points of mud weight to provide the
overbalance kill mud weight. This method would remove the influx and add the
overbalance pressure needed to trip and operate during the first circulation. Caution
should be taken if this method is selected, the additional u-tube pressure added could
cause formation breakdown. This method should not be selected solely on the fact that a
quicker well kill will occur. Field experience has proved that more than one circulation is
generally necessary to remove all of the gas from the annulus.
11 - 28
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 29
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 30
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
With the pump running at the desired constant speed and the casing pressure
stabilized on the inactive line pressure gauge at the desired value, read the drill pipe
pressure.
Note: The drill pipe pressure read at this point is that pressure necessary to
maintain a constant bottom-hole pressure.
The difference between the shut-in and pumping drill pipe pressure is the pressure
required to circulate the drilling fluid at the desired rate. While maintaining the casing
pressure constant on the inactive line pressure gauge, the casing pressure on the active
line pressure gauge will decrease by an amount equal to the choke line friction pressure.
Note: Changes in pressure due to choke manipulation require approximately two
seconds per 1,000 ft of drill string to register on the stand pipe gauge; however, this lag
in response time can be longer if a large gas kick is present.
Keep the stabilized drill pipe pumping pressure constant by manipulating the annulus
choke while continuing to maintain the same CONSTANT pump rate.
Any change in bottom-hole pressure will be seen as a change in drill pipe pressure and
can be corrected by manipulating the annulus choke, since the mud density remains
constant in the drill pipe.
11 - 31
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 32
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
Concurrently open the annulus choke on the active circulating line and slowly bring the
pump up to selected speed (kill rate).
1. While bringing the pump up to speed, adjust choke to hold the casing pressure at
285-psi (SICP - CLFP) on the active line pressure gauge (Figure 11.8). This will
essentially maintain a constant bottom-hole pressure.
2. With the pump running at the desired contact speed and the casing pressure
stabilized at 285 psi on the active line pressure gauge, read the drill pipe pressure.
The drill pipe pressure read at this point is that pressure necessary to maintain
a constant bottom-hole pressure. The difference between the shut-in and pumping
drill pipe pressure is the pressure required to circulate the drilling fluid at the desired
rate, the initial drill pipe circulating pressure.
11 - 33
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 34
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
Calculations
1) IFP = IDPCP - SIDPP = 330 - 210 = 120 psi
2) FDPCP = IFP X (KMW/OMW) = (120)(11.0/10.0) = 132 psi
3) FDPFP = IDPCP - FDPCP = 330 - 132 = 200 psi
4) PSI decrease per increment = FDPFP/10 = 20 psi
IDPCP = Initial Drill Pipe Circulating Pressure
SIDPP = Shut-in Drill Pipe Pressure
IFP = Initial Friction Pressure
KMW = Kill Mud Weight
OMW = Original Mud Weight
FDPCP = Final Drill Pipe Circulating Pressure
FDPFP = Final Drill Pipe Friction Pressure
Next the stroke per increment is calculated for the pressure reduction.
Drill String Capacity = 171 bbls
Pump Output = 0.120 bbls/stk
Strokes to Displace Drill Pipe = 171/0.120 = 1425 stks
Strokes per Division = 1425/10 = 142
A schedule is then prepared showing a 20 psi decrease in the drill pipe circulating
pressure every 142 strokes.
11 - 35
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
As the kill weight mud is pumped from the surface to the bit, downward adjustments are
made to the drill pipe pressure based on the schedule above. When the balance weight
mud reaches the bit, the final pressure of 132 psi will be held until the annulus is
displaced with balance weight fluid (Figure 11.11).
As the annulus is displaced with balance weight fluid, the casing pressure will decrease
to zero psi. As the casing pressure becomes less than the CLFP, the choke will be
completely open and the choke operator will not be able to compensate for the CLFP
(Figure 11.12). The drill pipe and bottom hole pressure will increase by 154 psi, an
amount equal to the CLFP adjusted for the new mud weight.
11 - 36
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 37
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 38
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
Field studies indicate that a 300-psi differential from the mud filled riser to the fluid in the
choke line would cause displacement of the remaining trapped gas into the choke line.
Displacement of the gas at lower differential pressure is untested, however displacement
efficiency will probably decline with declining pressure differential. With shallow water or
low mud weight, obtaining a large pressure difference may not be possible especially if
the rig does not have a riser boost line to displace the riser with kill fluid before opening
the annular.
Since the potential for forming hydrates when displacing trapped gas with freshwater is
likely, a hydrate-inhibited fluid should be used. If gas does enter the riser above the
BOPs, field-testing has shown that it is important to allow the gas to migrate to the
surface without pump in g . T h is w ill te n d to strin g o u t th e g a s a n d ke e p it in sm a ll
bubbles in the riser. Small bubbles can be handled safely because they surface slowly
and do not displace mud from the riser (mud slips by small bubbles in the riser).
After allowing adequate time for gas to migrate to the surface, the riser must be
circulated to remove any residual gas. This circulation should be performed at a very
slow rate. The time required for gas bubbles to migrate to the surface will depend on
several factors including mud properties, water depth, and gas bubble characteristics
(number, size, and initial pressure). Field testing in equivalent 1350-ft. water depth
indicated gas bubbles would require at least 30 minutes to migrate to the surface.
A minimum of a 30-minute waiting period should be used for comparable water depths.
In general, a longer waiting time should be used for deeper water depth.
Included at the end of this section is an example of a rig specific (choke/kill line
configuration specific) procedure to remove trapped gas.
11 - 39
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
Note: Choice of rams is dictated by need to circulate between choke and kill lines,
above closed rams.
4. Open both upper kill-line valves. At this point, both valves on each of the upper
choke-and kill lines (above the closed rams) are open. Rig up to take choke line
returns through choke manifold and mud gas separator.
5. Rig up cement pump to kill line.
6. With cement pump, circulate unweighted mud at 2 bpm down kill line, across stack,
and up choke line (Figure 11.16). Hold backpressure on choke line as calculated in
Step 1. Continue to circulate until both choke-and-kill lines are filled with unweighted
mud.
Note: Unweighted mud or a gel pill should be used to displace weighted kill mud
from lines to avoid barite settling when water is pumped. This step also ensures a
clear flow path across the stack.
11 - 40
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
Note: If the cement unit has been previously targeted to pump down the choke line,
the procedure can be varied as follows: pump water down choke line to stack taking
mud returns out kill line. Hold backpressure on kill line. Do not overdisplace choke
line. After displacement, shut-in choke and kill lines at surface.
Note: If a riser boost line is available, raise riser mud weight to kill mud weight.
8. Close both upper kill line subsea valves. All valves should now be closed except for
upper choke line valves, which should be open. Bleed off pressure on kill line.
11 - 41
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 42
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
Caution: Gas may become trapped in stack any time gas is circulated from wellbore
below a closed annular BOP. Repeat trapped gas procedure any time gas is
circulated from wellbore.
36. Observe well to be sure kill is completed. Open #1 annular, and then close both
upper choke line valves. Proceed with normal post-kick operations.
11 - 43
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11 - 44
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
Figure 11.22
11 - 45
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL CONTROL OPERATIONS
11.12 REFERENCES
IADC Deepwater Well Control Guidelines: First Edition October 1998
Exxon Company International, Floating Drilling Blowout Prevention and Well Control
Manual: Revision 1, 1997
11 - 46
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12
Section
OBJECTIVES
On completion of this lesson, you will be able to:
Use a graph from a drive off/drift off analysis to determine the alarm setting for an
emergency disconnect.
List the hourly checks that must be made between the Driller and the DP Operator to
confirm that the emergency disconnect alarms are operational.
Calculate drill pipe spaceout for hanging off the drill pipe.
List the emergency disconnect procedures that are typically used for non-routine
operations.
List the important items to confirm during emergency disconnect and hang-off drills.
List the steps to re-enter the well after the drill pipe has been hung off and sheared.
Describe a typical fishing assembly used to fish the sheared drill pipe from the BOP
stack.
12 - 1
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
CONTENTS Page
12 - 2
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12.1 INTRODUCTION
When operating from a dynamically positioned rig, systems and procedures to secure
the wellbore and disconnect the LMRP from the BOP stack are required to protect the
well and equipment should the rig drive off or drift off from location. This section will
provide information on the systems and procedures used to perform an emergency
disconnect and re-entry of the wellbore afterwards.
12 - 3
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
Listed in Table 12.1 are the typical items that are normally included in a EDS, but this list
will vary immensely depending on the BOP stack and control system.
12 - 4
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
Listed in Table 12.2.1 through 12.2.2 is an actual disconnect sequence, for the Glomar
Ja ck R ya n , u se d d u rin g th e n o rm a l d isco n n e ct w h e n sh e a ra b le ite m s a re a cro ss th e
BOP stack.
Note that actuation times are sequenced for critical functions to allow them to fully
actuate before the next critical function is actuated (e.g. shear ram vent is 28 seconds
after shear ram close).
Table 12.2.1 N orm al E m ergency D isconnect S equence from Glomar Jack Ryan
Elapsed Function Action Comment
Time, sec
0 Start Emergency Disconnect Initiated on control surface panel.
0 Rapid BOP Regulator Increase Increase Increases BOP manifold pressure to 3000 psi
0 Enable Deadman Enables DM Enables the deadman system electrically
0 Blind Shear Close Close Blind Shearing Rams
0 Choke Line Connector Vent Vents "latch" side of kill line connector
0 Kill Line Connector Vent Vents "latch" side of choke line connector
0 Riser Connector Vent Vents "latch" side of riser connector
0 Blind Shear ST Lock Lock Locks ST-Locks on Blind Shearing Ram. Sequence valves inside
bonnets prevent locking until rams close
0 MPR ST Lock Lock Same as above - this is precautionary, only needed if Driller fails
to manually lock ST locks after closing rams.
0 Lower Inner Choke Valve Close Closes lower inner choke valve
0 Lower Outer Choke Valve Close Closes lower outer choke valve
0 Upper Inner Choke Valve Close Closes upper inner choke valve
0 Upper Outer Choke Valve Close Closes upper inner choke valve
10 Lower Inner Kill Valve Close Closes lower inner kill valve
10 Lower Outer Kill Valve Close Closes lower outer kill valve
10 Upper Inner Kill Valve Close Closes upper inner kill valve
10 Upper Outer Kill Valve Close Closes upper outer kill valve
10 Lower Annular Vent Vents pressure from opening & closing sides
10 Upper Annular Vent Vents pressure from opening & closing sides
10 Casing Shear Vent Vents pressure from opening & closing sides
10 Upper Pipe Ram Vent Vents pressure from opening & closing sides
10 Middle Pipe Ram Vent Vents pressure from opening & closing sides
10 Lower Pipe Ram Vent Vents pressure from opening & closing sides
20 Kill Line Connector Unlatch Unlatches kill line connector
20 Choke Line Connector Unlatch Unlatches choke line connector
20 Lower Inner Choke Valve Vent Vents lower inner choke valve closing pressure
20 Lower Outer Choke Valve Vent Vents lower outer choke valve closing pressure
20 Upper Inner Choke Valve Vent Vents upper inner choke valve closing pressure
12 - 5
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
20 Upper Outer Choke Valve Vent Vents upper outer choke valve closing pressure
20 Lower Inner Kill Valve Vent Vents lower inner kill valve closing pressure
20 Lower Outer Kill Valve Vent Vents lower outer kill valve closing pressure
20 Upper Inner Kill Valve Vent Vents upper inner kill valve closing pressure
20 Upper Outer Kill Valve Vent Vents upper outer kill valve closing pressure
28 Blind Shear Ram Vent Vents closing pressure from blind shear ram
28 Blind Shear Ram ST-Lock Vent Vents closing pressure from blind shear ram ST-Lock
28 Subsea Accumulator Vent Vents deadman fluid supply line between bottles & pods
30 Stack Stinger Seals De-energize De-energizes stack stinger seals.
36 LPR - ST Lock Vent Vents pressure rams and locks could be closed
36 MPR - ST Lock Vent Vents pressure rams and locks could be closed
36 UPR - ST Lock Vent Vents pressure rams and locks could be closed
36 Riser Recoil Fire Initiates Riser Recoil System controlling surface tensioners
42 Riser Connector Unlatch Unlatches Riser Connector (primary unlatch)
42 Riser Connector Secondary Unlatch Unlatches Riser Connector (secondary unlatch)
44 Upper Annular Open Opens annular to ensure lift off with tensioners should annular
not open by previously venting.
Table 12.2.2 N orm al E m ergency D isconnect S equence from G lom ar J ack R yan
Early generation multiplex control systems were limited to a single EDS. Newer BOP
multiplex control systems that are software driven offer the capability to have multiple
disconnect sequences that can be selected for various operating conditions. A common
co n fig u ra tio n o n th e n e w e r syste m s is to h a ve tw o E D S se le ctio n s, o n e N o rm a l se ttin g
th a t se cu re s th e w e llb o re w ith th e b lin d sh e a r ra m s a n d a se co n d C a sin g E D S
se le ctio n . T h e C a sin g E D S is u se d w h e n th e B O P sta ck is e q u ip p e d w ith a ca sin g
shear ram (shear only, does not seal) that is used to cut large tubulars and the blind
shear is closed afterwards to seal the wellbore.
12 - 6
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12 - 7
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
Table 12.3.1 C asing E m ergency D isconnect S equence from G lom ar J ack R yan
Time Function Action Comment
sec
0 Start Casing EDS Initiated on control surface panel. Requires that pods be
engaged and remain functional during EDS
0 Rapid BOP Regulator Increase Increase Increases BOP manifold pressure to 3000 psi
0 Enable Deadman Enables DM Enables the deadman system electrically
0 Casing Shear Rams Vent Vents opening and closing sides of casing shear ram
0 HP Casing Shear Rams Close Closing high pressure casing shear rams with DM bottles
0 Choke Line Connector Vent Vents "latch" side of kill line connector
0 Kill Line Connector Vent Vents "latch" side of choke line connector
0 Riser Connector Vent Vents "latch" side of riser connector
0 Wellhead Connector Vent Vents "latch" side of wellhead connector
0 Lower Inner Choke Valve Close Closes lower inner choke valve
0 Lower Outer Choke Valve Close Closes lower outer choke valve
0 Upper Inner Choke Valve Close Closes upper inner choke valve
0 Upper Outer Choke Valve Close Closes upper inner choke valve - 10 second delay
10 Upper Annular Vent Vents opening and closing sides upper annular BOP
10 Lower Annular Vent Vents pressure from opening & closing sides
10 Upper Pipe Ram Vent Vents pressure from opening & closing sides
10 Middle Pipe Ram Vent Vents pressure from opening & closing sides
10 Lower Pipe Ram Vent Vents pressure from opening & closing sides
10 Lower Inner Kill Valve Close Closes lower inner kill valve
10 Lower Outer Kill Valve Close Closes lower outer kill valve
10 Upper Inner Kill Valve Close Closes upper inner kill valve
10 Upper Outer Kill Valve Close Closes upper outer kill valve - 13 second delay
23 Lower Inner Choke Valve Vent Vents lower inner choke valve closing pressure
23 Lower Outer Choke Valve Vent Vents lower outer choke valve closing pressure
23 Upper Inner Choke Valve Vent Vents upper inner choke valve closing pressure
23 Upper Outer Choke Valve Vent Vents upper outer choke valve closing pressure
23 Lower Inner Kill Valve Vent Vents lower inner kill valve closing pressure
23 Lower Outer Kill Valve Vent Vents lower outer kill valve closing pressure
23 Upper Inner Kill Valve Vent Vents upper inner kill valve closing pressure
23 Upper Outer Kill Valve Vent Vents upper outer kill valve closing pressure
23 Blind Shear Ram Close Closes Blind Shear Ram above Casing Shear Ram
23 Blind Shear Ram ST-Lock Lock Locks Blind Shear Ram with ST-Locks. Sequence valves
inside bonnets ensure lock occurs only after rams close
23 Kill Line Connector Unlatch Unlatches kill line connector
12 - 8
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
Table 12.3.2 C asing E m ergency D isconnect S equence from G lom ar J ack R yan
12 - 9
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12.3 ALARMS
Along with developing an EDS, a drive off/drift analysis is performed to determine the
vessel offset with the maximum mud weight and environmental (wind, waves, current)
conditions for the proposed location. The EDS times are then combined with the drive
off/drift off analysis to determine the setpoint for the dynamic position (DP) alarms. The
alarm setting is then input to the DP computers as watch circles with an alarm typically
initiated based on vessel offset. Some rigs also have the capability to initiate alarms
based on the upper/lower flex/ball joint angles and/or tensioner stroke, but most just
correlate back to the calculated offset at a particular flex joint angle or tensioner/slip joint
stroke and use the offset position.
T h e m o st co m m o n d e sig n a tio n fo r D P a la rm s is Y e llo w a n d R e d . T h e se a la rm s a re
typically set based on a preselected criteria for vessel offset, thruster output, power
output, wind, seas, current, flex joint angle/tensioner stroke, or loss of DP redundancy.
When the criteria of any of the conditions is reached, the alarm is initiated. An example
of the criteria for each of the conditions used on the Glomar Jack Ryan is listed below in
Table 12.4.
Yellow given when a preselected limiting criteria is reached and requires the Driller to
position and hang-off the drill pipe in preparation for securing the well with the blind
shear rams. For operations when drill pipe is not in the wellbore, other preparations are
to be made by the Driller as discussed in Section 12.5.
Red given when a preselected limiting criteria has been reached that requires the
Driller to actuate the EDS that closes the blind shear ram and unlatches the LMRP
connector.
In a d d itio n , a B lu e A d viso ry is a lso u se d so m e tim e s to sig n ify a d e g ra d e d situ a tio n
where operations may be suspended or systems and/or personnel are positioned for an
enhanced operating environment.
As illustrated in Table 12.4, specific operating criteria for each condition (i.e. red, yellow,
blue) are typically developed for each well location and agreed by ExxonMobil and the
Contractor. This table is then used as a decision tree when problems occur with the DP
system.
12 - 10
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
Table 12.4.1 Example - Well Specific Operating Criteria from Glomar Jack Ryan
THRUSTER Thruster output with all Thruster output with all Thruster output Thruster output with all
OUTPUT available units on line, available units on line, (excluding bias), with available units on line,
(excluding bias) does not (excluding bias) does all available thrusters exceeds 80% of total
exceed 50% of total not exceed 50% of total on line exceeds 65% available thruster power or at
available thruster power for available thruster power of total available the order of the OIM.
more than brief or isolated for more than brief or thruster power
periods. isolated periods.
POWER With all available With all available With all available With all available generators
OUTPUT generators online, generators online, generators online, online generator steady load
generator steady load does generator steady load generator steady load exceeds 80% of total
not exceed 50% of total does not exceed 50% does not exceed 65% available power for more than
available power for more of total available power of total available brief and isolated periods or
than brief or isolated for more than brief or power for more than at the order of the OIM.
periods. isolated periods. Less brief or isolated
than two engines on periods. On blackout, at the order of
one main buss. the OIM. On blackouts, wind
speeds>40 knots,
immediately Hang-off, Shear
Pipe and Disconnect.
WIND Steady speed < 40 knots, Steady speed < 40 Steady speed greater Speed greater than 70 knots
knots, than 60 knots or at the order of the OIM. On
Gusts < 45 knots blackout, windspeeds >40
Gusts < 45 knots knots, immediately Shear
Pipe and Disconnect.
SEAS Combined seas 15 ft or less Combined seas > 15 ft Combined seas > 20- Combined seas > 30 ft or at
25 ft the order of the OIM.
SURFACE < 2 Knots > 2 knots > 3.0 knots - POOH For surface currents above 4
CURRENT above the BOPs. knots at the order of the OIM.
Stand By until Yellow Pipe to stay above the BOP.
Alert resolved or
deteriorates into a Red
Alert
SLIPJOINT Up to 4 ft of stroke Over 6 ft of stroke due The tensioner stroke The maximum allowable
STROKEOUT to excursion off of criteria limits have tensioner stroke has
location reached the calculated occurred.
yellow alert angle due
to excursion off 11 ft.
location - >8 ft.
FLEXJOINT LMRP< 1.0 degrees Flexjoint angle at the Flexjoint angle at the Flexjoint angle at the LMRP
ANGLE LMRP is more than 1 LMRP has reached has reached the calculated
degree from setpoint the calculated yellow RED alert angle, 3 degrees
due to excursion off alert angle, >1.5 from setpoint due to
12 - 11
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
Note: The DPO and Driller have in conjunction with each other, when the OIM is not immediately available,
the authority to hang off and disconnect under an emergency condition if the situation such warrants.
The DPO and the Driller should utilize the Mate on Watch and A.D. respectively, to help them in the
notification process, as required.
Table 12.4.2 Example Well Specific Operating Criteria from Glomar Jack Ryan
12 - 12
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
A typical drift off analysis is illustrated below with hang-off and EDS times added to
determine the alarm setting for vessel offset.
15 0
Offset
LFJ Angle
Offset (%) & Angles (degrees)
Stroke (feet)
5 30
0 45
50 sec
60 sec for
Upper Ball Joint Angle Driller hang- for EDS
off
-5 60
0 50 100 150 200 250 300
Time (seconds)
In the illustration above, the disconnect criteria is based on the lower flex joint angle
(LFJA) of 8o since it is the first to reach its limiting criteria. In the example, the LFJA limit
of 8 degrees is reached at 240 seconds after the drift off begins. Based on the EDS in
Figure 12.2, 50 seconds (42 seconds at LMRP unlatch and 8 additional seconds for the
connector to unlatch plus contingency) is required from the time the Driller initiates the
EDS until the LMRP connector unlatches and lifts off the BOP stack. This means that the
red alarm will occur at 190 seconds or 7.3% of water depth offset.
To provide time for the Driller to hang-off the drill pipe, the yellow alarm is set 60
seconds prior to the red alarm at 130 seconds or 3.8% of water depth offset.
The alarm setting and watch circles described above are the maximum settings that
would be used for the drift off analysis and EDS listed above. In addition to the drift off
analysis, a drive off analysis is also performed and the analysis that reaches the limiting
criteria first is used to set the alarms.
12 - 13
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
Although the operating conditions will normally be less than those used in the analysis
and may provide additional time, the actual watch circles (alarms) that are used will
typically be set at a more conservative limit. As an example, the yellow alarm setting
may be set at 2% (67 ft offset) and the red alarm set at 5% (270 ft) for the 3381 ft water
depth well above to provide additional time for the Driller to hang-off the drill string and
for the EDS sequence to actuate. This conservative approach typically does not cause
unrequired hang-offs or disconnects since a DP system normally keeps the rig within 20
ft of the well location. Offsets outside of this 20-ft window usually only occur when a
major mishap has occurred, and the rig will continue to the upper limits anyway.
Actual communication of the alarms between the DP control room and the Driller is
accomplished by the following:
Red and yellow fla sh in g lig h ts a t th e D rille rs sta tio n .
Aud io a la rm s a t th e D rille rs sta tio n .
Clear call talk back system to allow the DP Operator and Driller to
simultaneously communicate.
Each tour after the BOP stack is installed, the DP Operator and Driller will test each of
the alarms and communication systems to verify each system is operational.
F o r h ig h e xp o su re o p e ra tio n s su ch a s w e ll te stin g o r w h e n th e C a sin g d isco n n e ct
sequence is to be used, special alarm settings will be substituted for the normal alarms.
For a well test operation where the pipe is already correctly positioned with the subsea
test tree (SSTT) landed in the wellhead, the yellow alarm setting may be reduced to
provide additional time to allow the well to be shut in downhole, the SSTT to be closed,
tubing pressure vented and the test string raised above the shear rams.
For rigs equipped with casing shear rams, the additional function of shearing the casing
with casing shear ram prior to closing the bind shear ram can add 20 to 30 seconds of
additional time to the EDS. In the example above, if the casing EDS required 70
seconds, the red alarm would need to be set at 170 seconds or 6% offset to achieve
unlatch prior to the LFJA of 8 degrees. If the disconnect criteria was not adjusted and the
red alarm was initiated at 7.3% offset (190 seconds), then disconnect would not occur
until 260 seconds when the LFJA had reached 9 degrees and the slip joint/tensioner
stroke out was at 30 ft.
12 - 14
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12 - 15
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
It is important that the tool joint remain on the ram block and not be picked up as the rig
moves off location to ensure that the tool joint is in the proper location when the pipe is
sheared. During an emergency disconnect in the Gulf of Mexico in 2001, the Driller
correctly positioned and hung off the pipe, but as the rig moved off location and tool joint
came closer to the rotary, the pipe was picked up to place the tool joint in its original
position causing the pipe to be sheared below the tool joint. This action caused the pipe
to be dropped and nearly placed the tool joint across the blind shear ram when they
were actuated. Closure of the blind shear rams on the tool joint would have left the well
open since the blind shear ram did not have the capability to shear the tool joint.
12 - 16
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
The motion compensator is also used to position the drill string during a drift off when
power is unavailable to the drawworks. For this reason, the motion compensator on DP
rigs should always be correctly pressured and ready for use even during operations such
as tripping when the compensator is not normally required. If the unlock function to the
compensator is electrically operated, this function should be on the emergency
generator or powered by an uninterrupted power supply.
Another important step that must be performed when the drill pipe is hung-off is
actuation of the ram locks. The ram locks are required to mechanically hold the rams
closed after the hydraulic pressure is removed during the EDS. If the ram locks are not
actuated, the rams may be allowed to open during the EDS, and the pipe will be
dropped. Some ram type preventers are equipped with locks that actuate automatically
when the rams are closed, but others require a separate function. Specific information
on ram locks can be found in Section 9.
12 - 17
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12 - 18
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12.5.1 PERSONNEL
RIG FLOOR
While operating with the BOP latched to the wellhead, the Driller or a qualified person
re lie vin g th e D rille r m u st b e in th e D rille rs h o u se a t a ll tim e s. S in ce th e E D S ca n d e p e n d
o n se co n d s to co m p le te th e a ctu a tio n in tim e , it is e sse n tia l th a t th e D rille rs sta tio n b e
attended at all times. This requirement prevents the Driller from assisting rig up on the
flo o r o r a tte n d in g p re jo b sa fe ty m e e tin g s u n le ss th e y a re h e ld in th e D rille rs h o u se . In
addition, a second person qualified to assist and perform an EDS is typically required to
be on the rig floor at all times to assist the Driller during an EDS. Typically the Driller will
be relieved by the Toolpusher or an experienced Assistant Driller and the second person
on the floor may be either the Toolpusher, Assistant Driller, or Derrickman.
DP CONTROL ROOM
The DP control room should be attended by at least one operator qualified to operate the
DP system on the rig at all times. A typical DP control room manning would be to have
four qualified operators onboard at all times with two operators per shift. To provide
adequate overlap during shift changes, it is typical to stagger the shift change for the
operators six hours apart. This configuration provides two operators in the control room
at all times and allows the operators to have sufficient overlap. During a twelve-hour
tour, the operators would rotate two hours on and two hours off watching the DP control
panel. This allows the operator not on the panel to man the radios, maintain the log
books and keep up other administrative duties while still allowing one person to maintain
100% of their attention at the control panel.
ENGINE CONTROL ROOM AND ENGINE ROOM(S)
The engine control room would typically be manned continuously with at least one
qualified person along with at least one additional person in the engine room.
12 - 19
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12.5.2 DRILLS
After the installation of the BOP stack, space-out and hang-off drills are typically
performed at each casing point and during the weekly fire and abandonment drills.
These drills will typically start at a point w h e re th e D rille r w o u ld re ce ive th e ye llo w
a la rm a n d e n d a t th e re d a la rm p o in t w h e re th e E D S w o u ld b e a ctu a te d .
The actuation of the EDS controls for the BOP stack is confirmed prior to deploying the
stack with the actuation of each function verified. Complete actuation of the EDS is
rarely performed subsea after the initial sea-trials for the rig and BOP control systems.
This is because an additional pressure test would be required for the LMRP seals.
Unlatching can also cause major damage to equipment due to riser recoil and could
require pulling the LMRP to replace pod seals. Re-latching can also be difficult.
During the hang-off drills, the following items are typically practiced and confirmed:
Pipe spaceout.
D rille rs kn o w le d g e o f th e ste p s to h a ng-off the drill pipe and lock the
hang off rams.
D rille rs kn o w le d g e o f m o tio n co m p e n sa to r syste m a n d h o w it w o u ld b e
used to support the drill pipe during rig offset.
D rille rs a b ility to h a n g -off the drill pipe using the motion compensator
without the use of the drawworks.
D rille rs a b ility to h a n g -off the drill pipe in the minimum time programmed
between the yellow and red alarm.
Since actual offset conditions are not present during these drills, it is important to
simulate various conditions (i.e. loss of drawworks power, loss of a communication
system to the DP control room) and quiz the Drill Crew on actions and conditions that
may occur during an actual disconnect.
12 - 20
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
Following the disconnect, the following list of items may be required and should be
considered:
1. Closing the annular on the sheared pipe and displacing the mud from the riser
utilizing the riser boost line.
2. Do the riser tensioners need to be adjusted to minimize the effects of riser and rig
from heaving at different frequencies? When operating in ultra-deepwater and in an
environment where the vessel has substantial heave, the frequency of the vessel
heave and riser heave can get out of sync allowing for possible compression of the
riser or extremely high tension loads.
3. Pull the drill pipe from the riser and recover the sheared section of drill pipe from the
string. This will be necessary to rig up the riser-landing joint or tension tool needed to
re-latch the LMRP to the BOP stack.
12 - 22
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12 - 23
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12 - 24
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
After the items listed above are confirmed, the rig floor is configured to re-land the LMRP
with a landing joint or riser tension tool using the drawworks and the motion
compensator. The drawworks must be used to land the LMRP instead of the riser
tensioners since the drawworks can provide the ability to pickup and slack off quickly.
Additionally, the drawworks have the sensitivity required to land out the LMRP on the
stack without damaging any stabs, seals or alignment pins. After the rig floor is
configured, the rig is positioned adjacent to the BOP stack and new gaskets are installed
for the choke/kill and LMRP connectors if required. During the re-latching of the LMRP,
the rig heading is adjusted to minimize rig motions and to align the LMRP to mate up
with the BOP stack. On some rigs, the outer barrel of the slip joint and the riser can be
rotated to allow the rig heading to be positioned into favorable weather while aligning the
LMRP to the BOP stack. Figure 12.4 illustrates an LMRP alignment with a BOP stack
during a reconnect.
Using the ROV to confirm
alignment from two
directions 90 degrees
apart, the LMRP is
lowered over the BOP
and final alignment is
completed by the
alignment pins on the
BOP. After the BOP stack
is landed, the LMRP
connector is latched and
the following items are Helical Slot and Alignment Pin
confirmed: Require for Orientation
Final Alignment Pins
Pod
stingers
extended
and tested.
Choke and kill
lines tested.
BOP functioned.
Pressure test
of the LMRP
connector. Figure 12.4 Re-connecting LMRP to BOP stack after a disconnect
After confirming the pressure integrity of the stack and control system, the riser would
then normally be displaced with weighted drilling fluid in preparation of opening the well
and recovering the sheared drill string.
12 - 25
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
Upper
Choke Upper
Upper Choke
Kill Upper
Kill
Lower
Choke Lower
Lower Choke
Kill Lower
Kill
Figure 12.5 BOP Stack After Re- Figure 12.6 Circulating The Wellbore With
Latching The LMRP With Sheared Drill The Sheared Drill Pipe Hung-Off In The BOP
Pipe Hung-Off On Middle Pipe Ram Stack After Re-Latching The LMRP Connector
12 - 26
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
To circulate the wellbore with the BOP stack in Figure 12.6, the upper kill and upper
choke line valves are opened and fluid is circulated down the kill line, across the BOP
stack through the sheared off joint of drill pipe and down the drill string. Returns are
taken though the lower choke line to the choke manifold. After the well has been
circulated and the wellbore is static, the blind shear rams are opened and the
recovery process to fish the sheared joint of pipe can begin.fishing assembly
After confirming that the wellbore is static and the blind shear ram is opened, the top of
the sheared joint of drill pipe (Figure 12.7) will need to be dressed off and the pipe
recovered with an overshot and grapple (Figure 12.8).
While milling off the top of the sheared drill pipe in the BOP stack, it is critical that the
mill not be dressed with any milling material on the outside to prevent damage to the
BOP stack. The most common method to fish for sheared drill pipe is to run a one-trip
system that includes a milling assembly with a grapple and pack-off. On a re-entry after
a disconnect in the GOM in 2001, the fish was dressed off with this assembly in less
than 30 minutes.
12 - 27
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
After dressing off the fish, the overshot is latched onto the fish and the wellbore can be
circulated through the drill string to confirm that the well is free of hydrocarbons below
the closed hang-off ram. After the well is circulated, the hang-off rams are opened and
the wellbore circulated and conditioned prior to removing the drill string and sheared joint
from the wellbore.
12 - 28
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12.9 APPENDICES
12 - 29
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
OPERATING STATUS
NORMAL CONDITION
The ship is defined as being in "NORMAL" operating status when ALL of the following
conditions apply:
1. Ship's desired position remains within the Blue watch circle for all but brief or isolated
periods.
2. Flex joint angle at the LMRP is within the agreed allowable offset limit for the water depth.
3. Ship is under DP control and the DP system is operating normally. All appropriate back
up (redundant) systems are available.
4. Thruster output, excluding bias, not exceeding 50% of total available thruster power for
more than brief or isolated periods.
5. Generator steady load is not exceeding 60% of total available power for more than brief
or isolated periods.
6. Upper riser angle is less than 2 degrees (Provided the Intermediate Flex Joint has been
run).
7. Steady wind speed is less than 40 knots, gusts are less than 45 knots.
8. Combined seas are 15 ft or less.
12 - 30
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
BLUE CONDITION
The ship is defined as being in "BLUE" operating status when any one of the following conditions
apply:
1. Ship's position has entered the Blue Alert "watch circle" for more than brief or isolated
periods.
2. Flex joint angle at the LMRP is more than the agreed allowable offset limit for the water
depth
3. Ship is under DP control but there has been a failure in a sub system which has left the
DP system in an operational state but without appropriate back-up (redundant) systems.
4. Thruster output, excluding bias, is exceeding 50% of total available thruster power for
more than brief or isolated periods.
5. Generator steady load exceeds 60% of total available power for more than brief or
isolated periods.
6. Upper riser angle is more than 2 degrees (provided the Intermediate Flex Joint has been
run).
7. Steady wind speed is greater than 40 knots, gusts are greater than 45 knots.
8. Combined seas are greater than 15 ft.
9. Surface currents measured by the current meter are greater than 2.5 knots.
When one of the following conditions occurs, the DPO must inform the Driller that a degraded
condition has been reached. This must be done both verbally and by activation of the Blue Alert
light. The DPO should also inform the ECR and OIM.
The Driller or Assistant Driller will immediately notify the Rig Superintendent, Company
Representative, Toolpusher, and Subsea Engineer. OIM, Rig Superintendent, Company
Representative and Toolpusher will review the conditions and decide which operations are
acceptable under the circumstances and whether or not to proceed with the operations.
YELLOW CONDITION
The ship is defined as being in "YELLOW" operating status when any one of the following
conditions occur:
1. Ship's indicated position has crossed into the yellow "watch circle" for more than brief or
isolated periods
2. Flex joint angle at the LMRP and/or slip joint/tensioner stroke criteria limits has reached
the calculated yellow alert angle.
3. DP system or Power Plant failure results in inability to maintain positioning control even if
the vessel is remaining within the watch circle (i.e; deadreckoning and/or joystick control)
4. Thruster output, excluding bias, exceeding 65% of total available thruster power.
5. Generator steady load exceeds 75% of total available power.
6. Due to loss of reference system, the DP system has no redundant back-up system.
When any of the above conditions occur the DPO must inform the Driller, ECR, and OIM that
Yellow Alert Status has been reached, both verbally and by activation of the Yellow alert light (if
not activated by the automatic system). The Driller will immediately and without hesitation take
steps to hang off the drill string (if applicable) and secure the well. The Assistant Driller will
immediately notify the OIM, Rig Superintendent, Company Representative, Toolpusher, and
Subsea Engineer. More detailed procedures covering specific operations are detailed within the
Glomar JACK RYAN Emergency Disconnect Procedures.
The ship is defined as being in "RED" operating status when any one of the following conditions
occur:
12 - 31
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
RED CONDITION
1. Ship's indicated position has crossed the calculated RED alert circle.
2. Flex joint angle at the LMRP has reached the calculated Red alert angle and/or the
maximum allowable tensioner stroke has occurred.
When any of the above conditions occur, the DPO must immediately verbally acknowledge, with
the Driller, the validity that the Red Alarm status has been reached.
At RED ALERT status the Driller must initiate Disconnect Procedures. He will immediately and
without hesitation activate the EDS. He will then confirm proper functions are operating by
observing the BOP panel on the Drillers console. More detailed procedures covering specific
operations are detailed within the Glomar JACK RYAN Emergency Disconnect Procedures.
12 - 32
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12 - 33
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
CONDITION YELLOW
1. The situation may arise where the Yellow alert will not be preceded by a Blue. In this
situation carry out all the steps listed at the condition Blue stage as well as the steps
listed within the condition Yellow.
2. Clear moonpool and rig floor of all personnel.
3. If drilling, pick up off bottom and shut off pumps.
4. If 5 1/2 in. drill pipe is in BOP stack, close MPR and ST locks.
5. If 3 1/2 in., 5 in. or 6 5/8 in. drill pipe is in BOP stack, close UPR and ST locks.
6. Slack off until tool joint lands out on MPR.
7. Adjust CMC for string weight above BOP plus 20kip
8. If no drawworks power is available, space out using CMC.
CONDITION RED
DRILLER:
1. Verbally authenticate Red Alert with DPO.
2. Driller to immediately, without question, activate EDS.
3. Unlock CMC, if not already unlocked and adjust air to lift string in riser plus 20 kips.
4. Verify unlatch and notify DPO of same.
5. Pick up on drill string to ensure sheared pipe end is well within the riser.
SUBSEA ENGINEER
1. Check MRT status. Using standby air boost MRT as required to collapse slip joint.
12 - 34
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12 - 35
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
CONDITION YELLOW
DRILLER
1. The situation may arise where the Yellow alert will not be preceded by a Blue. If this
situation occurs, carry out all the steps listed at the condition Blue stage as the steps
listed within the condition.
4. Clear rig floor and moonpool of all personnel.
5. If possible clear BOP of BHA by pulling or running current stand.
6. If BHA tubular can be cut by Blind Shear or Super Shear rams and be hung-off on rams
a. Open CMC while confirming space out.
b. Close MPR and ST lock if appropriate. Slack off until tool joint lands out on MPR.
c. Set CMC for string weight above BOP plus sufficient overpull.
d. If no drawworks power is available, space out using the CMC.
7. If BHA tubular can be cut by Blind Shear or Super Shear rams, but not hung-off on rams
a) Position tubular so tool joint is not across shear.
b) Set CMC for string weight above BOP plus sufficient overpull.
8. If BHA tubular cannot be cut by Super shear rams and pipe rams cannot be then attempt
to drop the string.
SUBSEA ENGINEER
1. Report to rig floor.
2. Verify Control System and MRT system are aligned as required
CONDITION RED:
DRILLER
1. Verbally authenticate Red alert with DPO.
2. Driller to immediately, without question, activate EDS.
3. Unlock CMC, if not already unlocked and adjust air to lift string in riser plus 20 kips.
4. Verify unlatch and notify DPO of same.
5. Pick up on drill string to ensure sheared pipe end is well within the riser.
SUBSEA ENGINEER
1. Check MRT status. Using standby air boost MRT as required to collapse slip joint.
12 - 36
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12 - 37
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
CONDITION YELLOW
DRILLER
1. The situation may arise where the Yellow alert will not be preceded by a Blue. In this
situation carry out all the steps listed at the condition Blue stage as well as the steps
listed within the condition Yellow.
2. Notify Cementer to stop cementing and displace cement from the drill pipe if possible.
a) If cement is not displaced from landing string, shut down operations and close MPR
and ST locks.
b) If cement is displaced from landing string, stop pumping and release casing hanger-
running tool by rotating landing string to the right. P/U landing string to clear running
tool above shear ram.
3. Clear moonpool and rig floor of all personnel.
4. Unlock CMC and adjust for string weight above BOP plus 20kip (unless string weight is
less than 20k)
SUBSEA ENGINEER
1. Report to rig floor.
2. Verify Control System and MRT system are aligned as required.
CONDITION RED
DRILLER
1. Verbally authenticate Red alert with DPO.
2. Driller to immediately, without question, activate EDS.
3. Notify Cementer that EDS has been initiated and shut down displacing.
4. Verify unlatch and notify DPO of same.
5. Pick up on landing string to ensure sheared pipe end is well within the riser.
SUBSHEA ENGINEER
1. Check MRT status. Using standby air boost MRT as required to collapse slip joint.
12 - 38
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
CONDITION BLUE
1. DPO to open direct line of communication with the Driller and notify the OIM and ECR.
2. The Driller or Assistant Driller will immediately notify the Rig Superintendent, Co. Rep,
Toolpusher and Subsea Engineer. The OIM, Rig Superintendent, Company
Representative, and Toolpusher will review the conditions and decide which operations
are acceptable under the circumstances and whether or not to proceed with operations.
3. If above BOP, stop and await further instruction.
12 - 39
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
CONDITION YELLOW
DRILLER
1. The situation may arise where the Yellow alert will not be preceded by a Blue. In this
situation carry out all the steps listed at the condition Blue stage as well as the steps
listed within the condition Yellow.
2. Clear rig floor and moonpool of all personnel.
3. If above the BOP stop. If casing is across BOP, space out casing collar to clear Shear
Blind rams or Super Shear rams.
4. Unlock CMC and set CMC for string weight above BOP plus sufficient overpull.
5. If no drawworks power is available, space out using the CMC.
SUBSEA ENGINEER
1. Report to rig floor.
2. Verify Control System and MRT system are aligned as required.
3. Assist Driller as required.
CONDITION RED
DRILLER
1. Verbally authenticate Red Alert with ______.
2. Driller to immediately, without question, activate EDS.
3. Unlock CMC, if not already unlocked and adjust air to lift string in riser 20 kips.
4. Verify unlatch and notify DPO of same.
5. Pick up on casing string to ensure sheared pipe is well within the riser.
SUBSEA ENGINEER
1. Check MRT status. Using standby air boost MST as required to collapse slip joint.
12 - 40
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12 - 41
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12 - 42
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
CONDITION YELLOW
DRILLER
1. The situation may arise where the Yellow alert will not be preceded by a Blue. In this
situation carry out all the steps listed at the condition Blue stage as well as the steps
listed within the condition Yellow.
2. Clear rig floor and moonpool of all personnel.
3. Close ST locks on well test rams.
4. Inform Well Test Supervisor to bleed annulus pressure to close downhole test valve.
5. Inform Well Test Supervisor to bleed tubing pressure.
6. Inform Well Test Supervisor to disconnect subsea test tree.
7. Pickup to remove upper section of test assembly from BOP stack.
8. Set CMC for string weight above BOP plus 20 kips overpull.
9. If no drawworks power is available, space out using the CMC.
SUBSEA ENGINEER
1. Report to rig floor.
2. Verify Control System and MRT system are aligned as required.
CONDITION RED
DRILLER
1. Once the Red Alarm has been verified, Driller to immediately, without question, activate
EDS
2. Unlock CMC, if not already unlocked and adjust air to lift string in riser plus 20 kips.
3. Driller must remain vigilant during EDS in case CMC requires further standby air or
drawworks are required to pull sheared tubular clear.
4. On tubular being sheared it is imperative that the tubular is pulled as far as possible clear
of the BOP and into the riser.
5. Verify unlatch and notify DPO of same.
SUBSEA ENGINEER
1. Check MRT status using standby air boost MRT as required to collapse slip joint
2. Lock inner and outer barrel of slip joint.
12 - 43
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12 - 44
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
CONDITION YELLOW
DRILLER
1. The situation may arise where the Yellow alert will not be preceded by a Blue.
2. In this situation, carry out all the steps listed at the condition Blue stage as well as the
steps listed within the condition Yellow.
a) Notify Cementer of current alarm status and stop cementing program and start
displacing cement.
b) Space out and displace cement with predetermined fluid to clear drill pipe of cement.
c) If cement is across BOPs attempt to circulate until cleared.
d) Clear moonpool and rig floor of all personnel.
e) If 5 1/2 in. drill pipe is in BOP stack, close MPR and ST locks.
f) If 3 1/2 in., 5 in. or 6 5/8 in. drill pipe is in BOP stack, close UPR and ST locks.
g) Hang-off tool joint.
h) Unlock CMC and adjust for string weight above BOP plus 20kip (unless string weight
is less than 20k)
i) If no drawworks power is available, space out using CMC
SUBSEA ENGINEER
1. Report to rig floor.
2. Verify Control System and MRT system are aligned as required.
CONDITION RED
DRILLER
1. Verbally authenticate Red Alert with DPO.
2. Driller to immediately, without question, activate EDS
3. Unlock CMC, if not already unlocked and adjust air to lift string in riser plus 20 kips.
4. Verify unlatch and notify DPO of same.
5. Pick up on drill string to ensure sheared pipe end is well within the riser.
SUBSEA ENGINEER
1. Check MRT status.
2. Using standby air, boost MRT as required to collapse slip joint.
12 - 45
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
CONDITION YELLOW
1. The situation may arise where the Yellow alert will not be preceded by a Blue. In this
situation carry out all the steps listed at the condition Blue
2. Clear rig floor and moonpool of all personnel.
3. If circulating, stop pumps.
4. If 5 1/2 in. drill pipe is in BOP stack, close MPR and ST locks.
5. If 3 1/2 in., 5 in. or 6 5/8 in. drill pipe is in BOP stack, close UPR and ST locks.
6. Set CMC for string weight above BOP plus 20.
12 - 46
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
CONDITION RED
DRILLER
1. Verbally authenticate Red Alert with DPO.
2. Driller to immediately, without question, activate EDS.
3. Unlock CMC, if not already unlocked, and adjust air to lift string in riser plus 20 kips.
4. Verify unlatch and notify DPO.
5. Pick up on drill string to ensure sheared pipe end is well within the riser.
SUBSEA ENGINEER
1. Check MRT status. Using standby air, boost MRT as required to collapse slip joint.
12 - 47
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
PROCEDURE
NOTE: The special BOP test joint is 1.125 in. wall thickness and will require the Super
Shear Rams when shearing.
CMC POSITIONING
1. When testing the BOP certain practices must be followed to maintain optimum
preparedness for a potential EDS situation.
2. Standby bottles for the HP air system must be kept fully charged at all times.
3. In the event of complete power loss it may be necessary to utilize the CMC for positioning
the string across the hang-off ram.
4. Ensure adequate APV pressure is available to lift the estimated total string weight from
the BOP to the floor plus 20kip.
CONDITION BLUE
1. DPO to open direct line of communication with the Driller and notify the OIM.
2. The Driller or Assistant Driller will immediately notify the Rig Superintendent, Company.
Representative,Toolpusher and Subsea Engineer.
3. The OIM, the Rig Superintendent, Company. Representative andToolpusher will review
the conditions and decide which operations are acceptable under the circumstances and
whether or not to proceed with operations.
4. Verify pipe figures for hanging off on the MPR.
5. If time permits: Stop test. Bleed off all pressure. Open all preventers. Pull tool clear of
BOP using Drawworks.
12 - 48
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
CONDITION YELLOW
DRILLER
1. The situation may arise where the Yellow alert will not be preceded by a Blue.
In this situation carry out all the steps listed at the condition Blue stage as well as the
steps listed within the condition Yellow.
2. Clear rig floor and moonpool of all personnel.
3. If 5 1/2 in. drill pipe is in BOP stack, close MPR, close ST locks.
4. If 3 1/2 in., 5 in. drill pipe is in BOP stack, close MPR, close ST locks.
5. Set CMC for string weight above BOP plus 20 kips.
6. If no drawworks power is available, space out using the CMC.
SUBSEA ENGINEER
1. Report to rig floor.
2. Verify Control System and MRT system are aligned as required.
CONDITION RED
DRILLER
1. Once the Red Alarm has been verified,
2. Driller to immediately, without question, activate EDS.
3. Unlock CMC, if not already unlocked and adjust air to lift string in riser plus 20 kips.
4. Driller must remain vigilant during EDS in case CMC requires further standby air or
drawworks are required to pull sheared tubular clear.
5. On tubular being sheared it is imperative that the tubular is pulled as far as possible clear
of the BOP and into the riser.
6. Verify unlatch and notify DPO of same.
SUBSEA ENGINEER
1. Check MRT status. Using standby air boost MRT as required to collapse slip joint.
2. Lock inner and outer barrel of slip joint.
Note: There will always be two stands of shearable drill pipe below the test tool if it is weight
set type and HWDP or DCs are hung below for testing.
12 - 49
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
12 - 50
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
EMERGENCY DISCONNECT
CONDITION YELLOW
DRILLER
1. The situation may arise where the Yellow alert will not be preceded by a Blue.
In this situation carry out all the steps listed at the condition Blue stage as well as the
steps listed within the condition Yellow. Clear moonpool of all personnel.
2. Clear rig floor and moonpool of all personnel.
3. Stop circulating.
4. Record all pressures and close all BOP mounted failsafe valves.
5. If 5 1/2 in. drill pipe is in BOP stack, close MPR and ST locks.
6. If 3 1/2 in.or 5 in. drill pipe is in BOP stack, close and ST locks.
7. Bleed pressure from choke and kill lines.
8. If annular is closed, open sweep valves and bleed any pressure through kill line.
Note: EDS includes opening upper annular which will allow any gas trapped beneath to
be vented subsea as the LMRP disconnects.
SUBSEA ENGINEER
1. Report to rig floor.
2. Verify Control System and MRT system are aligned as required.
3. Assist Driller as required.
CONDITION RED
DRILLER
1. Verbally authenticate Red Alert with DPO.
2. Driller, to immediately, without question, activate EDS.
3. Unlock CMC, if not already unlocked and adjust air to lift string in riser plus 20 kips.
4. Verify unlatch and notify DPO of same.
5. Pick up on drill string to ensure sheared pipe end is well within the riser.
SUBSEA ENGINEER
1. Check MRT status. Using standby air boost MRT as required to collapse slip joint.
12 - 51
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13
Section
OBJECTIVES
On completion of this section, you will be able to:
13 - 1
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
CONTENTS Page
13 - 2
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 3
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 4
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 5
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13.1 INTRODUCTION
Production testing is sometimes called p ressu re tran sien t testin g . This is because
m e a su rin g th e p ro file o f th e p re ssu re tra n sie n ts re tu rn to the well bore, during the
shut-in period after production, is a crucial and integral part of most production tests.
Assuring the generation and capture of high-quality pressure transient data can be easily
overlooked in designing and operating well tests. In the design, equipment, and
operations sections that follow, we will emphasize what needs to be done to get good
pressure transient data. Running a production test without good pressure transient data
is like doing a seismic survey with geophones.
13 - 6
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Initial Flow
6025
6000
5975
Main Flow Main Shut-in
5950
Pressure, PSIA
5925
5900
5875
Initial Shut-in
5850
5825
Figure 13.1 Idealized Flow Test
5800
0 12 24 36 48 60 72 84 96 108 120
Time (hours)
Figure 13.1 Idealized Flow Test
Such a test is often called the dual-flow, dual shut-in test (DFDS test). Figure 13.1
shows a typical bottomhole pressure response generated over the duration of this test.
W h e n w e u se th e te rm w e ll te st o r te st in th is te xt, it w ill re fe r to a p ro d u ctio n test of
the DFDS type, executed from a floating drilling rig, unless noted otherwise.
13 - 7
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 8
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 9
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
More on Objective 7
Test Economics: Objective 7 may add two or three days to the flow time, and three to
five days to the buildup time perhaps $2 to $3M to the test cost. But a point to keep in
mind regarding longer tests and the high cost is that, for a very short exploration well
test, approximately 8 0 % o f th e co st is fixe d . T h is fixe d co st in clu d e s co m p le tio n , rig u p ,
rig down, equipment standby, rig and design costs. Thus, as shown in Figure. 13.2, a
DEEPWATER
test with three timesESTIMATED
the flow and shut-in
WELL
periodsPER
TEST
costs about 40% more and will produce
TIME & EXPENSE PHASE
significantly more reliable and useful information. Three times the reservoir volume will
be investigated and up to three times the reserves can be proved up with a 40%
additional expense.
Information Gained From Test
6 days, 1.8 M $
12 days and 3.6 M $ 6 days, 1.8 M $
13 - 10
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
So an aggressive test objective for proving up commercial reservoir size may not have a
high chance of approval or success. Once into the main flow period, flow interruptions,
especially one requiring a disconnect sequence in which the well is killed, are fatal to the
pressure transient analyses for Objectives 5 and 7.
Typically production tests from floating rigs will involve flows from 24 hours to 3 days,
with pressure buildups of one to two times the duration of the flow periods. The shorter
flow period tests will definitely be light on Objective 7. However, even if the list of test
o b je ctive s d o e sn t in clu d e a T yp e 7 o b je ctive , th e b u ild u p fo r a n e xp lo ra tio n w e ll te st
should always be conducted and analyzed as if it did. As mentioned above in reference
to Objective 6, there may be bad but very valuable news in the buildup data, like the fact
that a very small reservoir sand was tested and significantly depleted by the test.
It is important that a consensus on the objectives, and their relative priorities, be reached
and documented. Priorities highly depend on specific circumstances. But generally,
lower priority objectives are often easily attained incidental to pursuit of larger objectives,
with no additional costs, when the test design is appropriate. Less often, because of
unforeseen developments or difficulties, certain objectives previously agreed to may
become mutually exclusive. This is the reason for pre-agreed, iron clad priorities.
Of course, things do change.
13 - 11
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13.3.1 INTRODUCTION
A well test design is the overall plan to be followed to attain the well test objectives.
It should include contingency plans for diagnosing unexpected poor well performance
and other problems and for correcting them, if possible.
The initial stage of the design, the conceptual stage, will require information on the test
objectives, estimated reservoir and fluid properties, and the application of pressure
transient principles. The latter usually takes the form of using well test or reservoir
simulators to determine flow times, and estimated rates and pressures. In some
cases, these will be gross estimates.
The second stage of the test design involves the specification of general types of
hardware, capacities, pressure ratings, design of the completion, and selection and
placement of instrumentation downhole. This will be discussed in the following topic
entitled Well Test Design Stage 2 Decisions on Basic Procedures and Hardware.
The third stage of well test design, which involves a step-by-step plan to execute the
test, is actually known as the Well Test Procedure. It may be subdivided into several
main parts covering such operations as the makeup of the test string, perforating and
completion operations, pressure testing equipment, flowing the well, on through to
abandonment. Before the procedures can be written, all test equipment must have been
specified/selected. Since procedures are at the finest level of detail, significant parts of
them are equipment specific.
The test design process seems like a formidable one, and it is. But in reality, hardly ever
does a test have to be designed from the ground up. Past experiences with the rig, the
equipment, and procedures are invaluable in streamlining the latter two stages of the
n e w te st d e sig n . O n ce th e te st o b je ctive s a n d th e re se rvo irs co n d itio n a n d flu id
properties are known, the conceptual test design can be quickly completed.
Then, past experiences with equipment and procedures can be drawn upon.
This stage is usually the responsibility of the well test engineer or test specialist. The
starting point is the collection of all available formation evaluation data (logs, cores,
wireline tester data, etc.) and a decision on the objectives of the test.
13 - 12
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Any typical set of test objectives requires use of the DFDS test. This test consists of the
following four events, always in the sequence below:
1. A (normally short) initial flow period.
2. An initial pressure buildup period, five to ten times longer than initial flow,
usually one hour minimum.
3. Then the main flow period, length to be discussed the major part of test design.
4. Then the main pressure buildup period, usually one to two times the main
flow period.
Why are pressure buildups needed in production testing? On the surface, it seems like a
waste of time and money to sit around doing nothing for several days after the flow test.
Figure 13.3 illustrates that the flow periods or pressure draw-down phases of the
DF/DSI test sequence are usually quite noisy. This is because the flow period is affected
by rate changes, completion cleanup, plugging and other changes in the flow path.
Initial Flow
6025
6000
5975
Main Flow Main Shut-in
Pressure, PSIA
5950
5925
5900
5875
Initial Shut-in
5850
5825
Figure
5800 13.3 - Real Flow Test
0 12 24 36 48 60 72 84 96 108 120
Time (hours)
13 - 13
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
As a result, the flow test (called the draw-down) only tells us what the well actually did in
the test - what we can see at the surface - a measured flow rate at a measured (overall)
p re ssu re d ro p . It d o e sn t h e lp to so rt o u t th e va rio u s co m p o n e n ts o f flo w resistance.
In theory, the draw-down pressure transient should be able to do more (see past
d a m a g e d co m p le tio n s, fa u lts, o r d e p le tio n ), b u t in p ra ctice , it ca n t.
We need this information, and only the buildup portion of the test can tell us what the
we lls p o te n tia l is (is p ro d u ctio n h a m p e re d b y a p o o r co m p le tio n ? ). A n d if d e sig n e d to d o
so, the buildup can give us some information about reservoir size and shape. We cannot
sort out any reservoir size or quality change effects from the draw-down. Pressure
buildups are required for any sort of reservoir description
The buildup can do this because it provides clean, noiseless, and focussed pressure
tra n sie n t d a ta fo r a n a lysis a n d m o d e lin g . B u t th is p re ssu re tra n sie n t d a ta is ve ry
d e lica te a n d su b tle . S o m e estimated but typical magnitudes of pressure disturbances
ca u se d b y flo w th ro u g h va rio u s e le m e n ts o f th e re se rvo ir syste m a re liste d b e lo w .
Many of the objectives of a production test analysis depend on sorting out these
elements from the pressure buildup data.
From Table 13.1, it is easy to see that most of the pressure drop occurs across the
completion. The additional pressure disturbances due to possible faults,
heterogeneities, or depletion would typically be only an extremely small percentage
of the total pressure drop observed at the completion. Looking at Figures 13.1 and
13.3, this is apparent. Ninety five percent of the pressure buildup occurs in the first
hour of shut-in. This is the recovery of the pressure drop across the completion and
near-wellbore region.
In addition to production rates, reservoir size is of critical importance. Reservoir size
(at least the minimum size proved up by the test) can be inferred by anomalies in the
pressure buildup caused by faults, heterogeneities, and depletion. These are subtle,
and occur gradually over days in the latter stages of the main pressure buildup,
so m e tim e s ca lle d th e la te tim e re g io n .
13 - 14
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Figure 13.4 illustrates some simulated pressure buildup results for a typical well test that
produced 4000 BOPD for 36 hours from a 400 md, 100-ft thick formation. The well is
considered to be in five different reservoir situations. The reservoir initial pressure is
6000 psia.
1. An infinite reservoir.
2. A single fault 1000 ft from the well.
3. We ll is ce n te re d in a 2 0 0 0 w id e ch a n n e l.
4. Well is centered in a 92 acre square closed reservoir, 2000 x 2000 ft
5. Well has pressure support on two opposite sides, each 1000 ft away.
6000
Pressure, PSIA
5975
5950
Infinite Reservoir
Fault @1000ft
5925
Channel 2000' west
92 Acres Closed
Nearby Pressure Support
There are several things to note on Figure 13.4. All the buildups recover most of the
pressure drawdown quickly, in the first half-hour or less. The pressure recovery in the 92
acre closed reservoir is noticeably incomplete, lining out at about 5967 psia. All the
other cases are approaching the initial pressure of 6000 psia, but from different
pressure levels.
13 - 15
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Note: The differences in pressure buildup levels are only two to six psi for these quite
different reservoir geometries. Also note that shape of the buildup curve is just as
important in pressure buildup analysis as the pre ssu re le ve l. S h a p e d iffe re n ce s a re n t
readily apparent here. To get a better definition of the shape, this data would be
tra n sfo rm e d (tim e sca le d isto rte d ) to m a ke a H o rn e r p lo t. F u rth e r d e fin itio n fo r
diagnostic work would result from a log-log derivative transform. These techniques are
very helpful but put a premium on getting excellent, distortion-free pressure buildup data.
To summarize, the diagnostic pressure transients resulting from reservoir quality
boundaries of depletion are overwhelmed by the n o ise in th e d ra w d o w n p re ssu re
disturbance due to even minute, undetectable rate fluctuations. And although the drilling
engineer does not need to interpret the buildup data, he will be required to ensure the
test objectives are meeting safety standards with no environmental incidents.
13 - 16
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
With the well shut-in for a pressure buildup, the rate is zero and constant (hopefully with
only some initial, brief and slight exceptions, to be discussed). Having thus eliminated
the influence of the very large pressure transients at the completion, due to production
rate fluctuations, well cleanup, etc., the resultant buildup pressure transient should
clearly show the effects of completion efficiency, reservoir quality, nearby boundaries,
and apparent depletion, if any.
The buildup time is normally required to be one to two times the flow time to get all of the
information available from the pressure transients generated by the flow period.
However, under certain conditions the buildup period can be cut to the flow period
length. These conditions are not often satisfied, but will be stated here.
The purpose of the Initial Flow Period is to relieve the formation fluids near the wellbore
of any supercharged pressure due to drilling or completion operations. It does so by
taking a small amount of flow into the wellbore, and drawing the pressure below the
static reservoir pressure. With a bottomhole shut-in valve (now normally recommended
practice in floating well test strings), the produced amount may be as low as two to six
barrels of flow, depending on the bottom hole volumetrics, and geometry between the
pressure gauge and the completion.
The initial flow should also clean the perforation area of much of the debris and mud
solids lodged there, establishing good communication between the formation and the
bottom of the test string (Bottom Hole Assembly or BHA). A well-designed initial flow
volume will shut the well in before this debris gets into the production screen or screens
(in-line screens), allowing it to fall harmlessly down into the bottom of the rathole,
hopefully never to be seen again.
Without a bottomhole shut-in valve, it would normally be necessary to clean up the well
(including the production test string) during the initial flow period. Otherwise, phase
segregation might wipe out the pressure buildup for initial pressure. In this case, the
initial flow period could last more than six hours even in a productive well. The initial
buildup would be suspect in most cases, due to up-hole disturbances in the tubing, even
if it lasted many hours.
13 - 17
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 18
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
More specifically, the production time Tp (in hours) required to reach a radius of Ri
(in feet) is given by:
Tp = (Ri * Ri) /(4)
Where = 2.637*10-4 * K/( c)
K = permeability in md
= porosity (fractional)
c = compressibility, sips
= viscosity (cp)
T o g e t a fe e l fo r th e m a g n itu d e o f th e n u m b e rs th a t g o in to th is e q u a tio n , le ts se t so m e
input parameters:
K = 800 md, = .7 cp, = 28%, c = 1.2*10-5
= 2.637*10-4 * 800 md /(0.28*1.2*10-5*0.7)
= .21096/(2.352*10-6) = 89.694*10-3
For a 2500-ft radius of investigation the required production time would be:
Tp = 2500*2500/(4*89.694*10+3) = 17.42 hours for transient to reach a point
2500 ft from the wellbore.
Please note that this equation only gives the time for the first part of the pressure
transient to reach a point 2500-ft from the wellbore. As a practical matter, the bulk of the
transient (or peak of the ripple) must reach this point. Furthermore, if there is a reservoir
h e te ro g e n e ity a t 2 5 0 0 ft, th e p re ssu re tra n sie n t h ittin g it m u st re tu rn its e ch o to th e
wellbore during the flow period for this feature to be detected and properly characterized
as a heterogeneity in the pressure buildup. Otherwise, there will be interference between
the echo from the heterogeneity at 2500 ft and the shut-in.
What this all means is that the flow time given by this equation needs to be multiplied by
a factor of about three. This assumes a valid initial pressure is obtained on the same
pressure gauge as used in the main buildup. Thus, to properly investigate the fault at
2500 ft in our example, a 52-hour flow time would be required, and a 78-hour buildup.
Or about 5.5 days of major flow and buildup time.
Also note that for a given formation (constant rock and fluid properties), the flow time
required for the pressure transient to reach a given radius is proportional to the square of
that radius - called the radius of investigation. Since, for a constant thickness
reservoir, the amount of volume investigated is also proportional to the square of the
radius of investigation, the volume investigated is proportional to the flow time.
The purpose of the Main Shut-in period is to initiate the pressure recovery and record
the pressure buildup of the reservoir at the wellbore, beginning at the instant of shut-in
and continuing until the buildup has lasted for one to two times the main flow. It should
only be shortened if there are no type 6 Test Objectives whatsoever. Please note that
this situation is not advisable in an exploration or delineation well test, because you
should always want to know the minimum test proved-up reservoir size, no matter how
short the flow, and how small minimum is. Otherwise, you might be testing a small sand
lens, and not know it.
13 - 19
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Bottomhole pressures are the key data collected in pressure transient testing. As will be
d iscu sse d in S e ctio n 7 , to d a ys e le ctro n ic p re ssu re g a u g e s a re e xtre m e ly p re cise , h a ve
quite good accuracy, and are temperature compensated, reliable, robust, and have
sufficient memory to store the pressure data generated over months of test time.
So, what are the complications?
There are two separate problems that can largely be solved by a good test design. They
b o th ca u se n o ise o r d isto rtio n s in th e m e a su re d b o tto m h o le p re ssu re so th a t th e g a u g e
is not measuring what is required for meaningful analysis. Unfortunately, there are no
re a l m e a n s o f filte rin g th is n o ise o u t to g e t w h a t is n e e d e d . A n d fin a lly, th e n o ise ca n
obscure or wipe out the features in the pressure transient response that must be seen
and analyzed to reach test objectives.
Recall that pressure buildup analysis theory requires that the pressure transient data
re p re se n t th e p re ssu re a t th e sa n d fa ce o f th e re se rvo ir, u n d e r no flow or shut-in
conditions. There are two separate problems here, and neither is the fault of the gauges
themselves, but one solution helps solve both problems.
13 - 20
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
GAUGE LOCATION
13 - 21
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The potential for problems with unknown and/or changing hydrostatic corrections to the
bottomhole pressure gauge is minimized by:
1. Using a bottomhole tester valve.
2. Putting gauges as close to completion as possible.
3. Design of BHA (e.g., put gauge below fluid entry point in tailpipe, not in some dead
end space up under packer).
4. Well-designed Initial Flow procedure, with produced volumes conducive to giving
hydrostatic correction at end of IPBU.
13.3.11 N O F L O W C O N D IT IO N VIOLATIONS
Pressure buildup analysis theory requires that the pressure transient data represent the
p re ssu re a t th e sa n d fa ce u n d e r no flow or shut-in conditions.
There are two real world complications to the no flow condition being satisfied during
the PBU.
1. Afterflow refers to the fact that fluid flows through the perforations some time after
the well is shut-in. This flow must occur to equalize the pressures in the wellbore and
in the reservoir at the perforations. The reservoir pressure is initially recharging very
rapidly near the completion at start of shut-in.
A similar effect may be seen when tests are run with strings that employ ESP pumps
and no bottomhole tester valve, or effective check valve. When the pump and well
are shut d o w n , th e p re ssu re b o o st su p p lie d b y th e p u m p ca u se s th e w e ll to g o o n
injection for a time, until the pressure in the test string equalizes with the reservoir
sand face pressure.
13 - 22
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The bottomhole shut-in valve will, for all practical purposes, eliminate afterflow and
phase humping problems, and reduce problems associated with the changing
hydrostatic correction (Figure 13.5).
Volatile Oil
Gas Phase Humping & Falling Liquid Level
K = 190.59 md
S = 300.06
P = 5004.31 psia
Gas humping
13 - 23
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The effect of tidal cycles can be seen in the latter stages of the PBU of offshore tests in
many cases. Even when reservoirs are abnormally pressured, tidal cycle oscillations are
observed in the latter stages of the buildup data, although at greatly reduced
magnitudes. This means that the added hydrostatic pressure due to sea height increase
is being transmitted down to reservoir depth by slight flexure of the rock.
Tidal fluctuations are well behaved and recognizable on the buildup. The best approach
to deal with this unwanted distortion of the pressure data is to filter it out of the data.
Using actual tidal data in the area while testing make this a much more reliable process.
One means to get this data is to affix a pressure gauge to the riser below the slip joint.
We have covered the basics of the conceptual test design and what it encompasses
the DFDS test method, pressure transients, radius of investigation, flow and buildup
times, and practical considerations in getting representative bottomhole pressures.
The next section will deal with phase 2 of test design, the specification of general types
of hardware, capacities, pressure ratings, design of the completion, and basic
procedures.
13 - 24
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
In the next stage of the test design, key decisions must be made regarding the
completion, basic test string components, the subsea safety system, and surface
equipment. Then test procedures can be outlined. And as this process of reducing the
conceptual test design to practice plays out, some compromises involving the
completion, equipment, and even some test objectives may be necessary. For example,
there may be equipment-related restrictions on the maximum production rate or
regulatory restrictions on the duration or total volume of production.
Good communication among the key decision-makers is essential to reaching these
compromises to minimize negative effects on the test objectives. Excellent coordination
between the test specialist or engineer, the drilling engineers, drilling operations and the
various service companies must be in place from very soon after the beginning of
planning until the test is over. And of course, there should be prompt feedback to the
clients if any of the test objectives have to be sacrificed, or tradeoffs made.
O f co u rse , fa cto rs b e yo n d a n yo n e s co n tro l m a y a d ve rse ly im p a ct th e ch a n ce s o f
attaining a given set of well test objectives. This may occur in spite of the effort made to
employ the best pressure gauges, downhole tools, completion techniques, and test
procedures. Weather, reservoir complexity, operational difficulties, poor well condition,
malfunctioning equipment, and human error are some examples of these factors. It is
important, therefore, to develop an understanding of what can go wrong beforehand, and
have contingency plans in place. Some tests that have failed to reach their objectives
had test designs without plans to handle unexpected events or conditions.
Once stage 2 is completed as per this section, equipment can be selected and the third
sta g e o f th e T e st D e sig n ca n th e n b e co m p le te d . T h is sta g e is u su a lly ca lle d th e T e st
P ro ce d u re sta g e . It co n sists o f w ritin g d e ta ile d , ste p -by-step, nuts and bolts procedures
for the various parts of the test. In practice, procedures are usually not started from
scratch, but some or many parts are adapted from previous test procedures.
13 - 25
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Safety, operational integrity, and concern for the environment are of paramount
importance in any testing operation. They cannot be compromised. A well test cannot
be considered successful without an operation whose planners and participants are
all totally committed in each of these areas.
After the groundwork has been laid, specific technical requirements must be met to
conduct a successful well test:
1. The well must be mechanically sound, in good pressure communication with and
only with the interval to be tested. That is to say an efficient completion with no
cement channels or leaks.
2. A valid initial pressure buildup should recorded on the main test gauge(s), with
the information and means to accurately correct gauge readings to a reservoir
datum depth.
3. A significant pressure drawdown must be induced in the reservoir by flowing the
well at a stable rate for the time period required as noted in the well test design.
4. Recorded bottomhole pressure buildup that measures only the reservoir pressure
recovery, and free of wellbore effects. Bottomhole pressures during the flow
period, as well as static and flowing temperatures, are also desired.
5. Accurate surface measurements made on all flow rates at the separator, and
temperatures and pressures at the wellhead, choke manifold, heater, and
separator.
6. Capture of fluid samples representative of those in the reservoir, and the correct
recombination parameters if the samples are not single phase (e.g., separator
samples).
7. Compositions (especially for toxic contaminants such as H2S) of produced
hydrocarbons from real time field analysis, and later from laboratory pressure-
volume-temperature (PVT) measurements.
8. A record of chloride (and possibly calcium, sodium, or other diagnostic cations)
concentrations in the completion fluid and produced water, and a complete set of
samples of these fluids for more thorough analysis later. Must employ necessary
techniques to distinguish between formation, mud filtrate, cushion, and
completion fluid.
9. A plan for mitigating hydrate formation and/or or wax deposition in the production
test string, and on the surface, in order to ensure safe, unrestricted production.
10. A complete chronological record of all significant events during the test period (to
be covered in Personnel Responsibilities and Information Retrieval).
13 - 26
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
These are the basic requirements and most seem quite straightforward and simple.
However, there are possible complications and qualifications, particularly in regard to
basic requirements 2, 3, and 4. These requirements can best be met by carefully
designing the test to provide these features:
A completion that is efficient, and does not absorb most of the pressure
drawdown. This allows a strong drawdown pressure transient to enter the
reservoir.
An unrestricted flow path through the test string and surface facilities that permit
flo w ra te s h ig h e n o u g h to te st th e fo rm a tio n .
13 - 27
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
1. Drilling engineer.
2. Test specialist or test engineer.
3. Completions engineer.
4. Operations Geologist.
5. Appropriate service company.
6. Regulatory Compliance.
13 - 28
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
ITEM 3: PERFORATION
Generally, balanced or over-balanced tubing conveyed perforation is used in deepwater
well tests. It typically produces more effective perforations (than wireline guns), can
handle long intervals without multiple trips, and does not require wireline runs and
equipment. The perforation guns are run on the test string itself, or on a completion
string, if in-place gravel packing is planned. In this case, of course, the test string is run
after the perforation and gravel-packing string(s) is (are) tripped in and out.
The effective underbalance used is usually quite moderate if formation integrity is a
concern, and in many cases the initial flowback volume is usually limited to several
barrels. This is to avoid getting perforation, cement, and formation debris into the
test tools or inline screens, if used. Use of too much initial underbalance with
unlimited flow may stick the perforation guns and totally plug the test tools, and
damage in-line screens. There are no proven benefits to taking a high
underbalance, high rate, and a large flow volume at perforation time with most
formations encountered in deepwater wells.
Initial pressure data is obtained after shut-in. If a full column liquid cushion is used
(see discussion on Item 11, below), with a well shut-in at the surface, perforation
underbalance can be made self-controlling by using a high initial underbalance.
Wellhead pressure is set at zero or low level before shots fired. This falls off to zero
after a few barrels of flow due to the low compressibility of the totally liquid cushion.
In this case, the well could be opened on a small choke immediately after the initial
low-volume surge for more cleanup. If an in-place gravel pack is planned, the perforation
procedure might differ from what was just described, with possibly a higher shot density,
more underbalance and more initial flow volume to clean out the perforation tunnels
more quickly and completely.
Note that perforation guns can be dropped down into the rathole automatically after
firing. This would permit running in production logs or pressure gauges by wireline
across the perforations, if the rathole is sufficiently deep.
ITEM 4: SAND CONTROL
The decision to employ sand control methods should be based on:
First hand company experience in the area.
Experience of other operators.
Core recovery and inspection.
Acoustic log interpretation.
Recommendations of rock strength experts, and service companies.
Whether the completion is expendable may also have some bearing on the type of sand
control chosen.
13 - 29
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
When deemed necessary, two types of sand control are typically used. These are in-line
screens and in-place gravel packs. In-line screens (e.g., excluder screens) are run as an
integral part of the test string, with the screens placed above the perforation guns and
below the packer. Excluder screens are applied when little or no sand production is
e xp e cte d . T h e scre e n s a ct a s a n in su ra n ce p o licy to ke e p sa n d p ro d u ctio n o u t o f th e
tubing and surface equipment. Obviously inline screens should not be run when
anticipated sand production would be great enough to cause formation collapse.
In this case, sand loss must be stopped at the perforations by other means.
A test procedure with in-lin e scre e n s is sim ila r to th e n o rm a l o n e -trip perforate and flo w
test string, except as follows:
With the inline screens, extra care should be taken to limit the initial flow after
perforation to several barrels (depending on bottom hole geometry, volumes) to
avoid pushing perforation, completion, and formation debris into the screens.
During the initial pressure buildup, most of this debris material should settle out
into the rathole.
The bottom hole gauges should be set up to record pressures external to and
inside the screens. This will sort out the apparent co m p le tio n d a m a g e in to tw o
parts - that from the actual damage in reservoir in the near wellbore vicinity and
that from the flow resistance of the screens.
This information is needed to diagnose screen plugging, even if it is only available after
the string is pulled. If necessary, inline screens could be back-flowed with a mud acid
mix if they are so severely plugged that meaningful rates cannot be reached, but this is
seldom required if precautions are taken to limit the initial flow, and let the debris settle
into the rathole.
With in-place gravel packs, two or three pipe trips are involved. In the three-trip case,
they are as follows:
1. The perforation.
2. The screen run and sand pack trip.
3. The final main test string run.
In the two-trip case (e.g., PerfPack), the perforation, screen run and sand pack trips are
combined into one, typically saving about two to three days of rig time. However,
ExxonMobil's worldwide experience to date (year-end 2001) with the two-trip process
has been mixed. One unsuccessful experience can easily cancel out several successful
ones. Most of the problems have been with the packer system they sometimes set too
so o n , w o n t se t, o r w o n t re le a se . In th e fu tu re , p ro b le m s su re ly w ill b e w o rke d o u t, a n d
the two step process will be improved enough to make it reliable.
There is much incentive for this system to work besides the two to three days saved in
rig time up front in the overall gravel packing process. More time might be saved in the
cleanup portion of the main flow test itself. This is because the two step process cuts
completion fluid loss between the gravel packing and the setting of the test string.
Recovery of large volumes of completion fluid losses can add days to getting the well
kicked-off and cleaned up.
13 - 30
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The in-place gravel pack procedure makes the measurement of initial pressure more
difficult, and introduces more uncertainty into its true value. More detailed discussion can
be found in section 13.8 - Instrumentation, Measurement and Sampling Equipment.
Gauge precision (essentially repeatability) is much greater than gauge accuracy. This is
w h y w e ca n t u se fo rm a tio n te ste r p re ssu re fo r in itia l p re ssu re , fo r e xa m p le , w ith o u t
introducing a 5 to 15 psi uncertainty right off the bat. Even if the same gauge is used, it
loses some precision when it is tripped in or out, primarily due to temperature hysteresis.
This is the rationale for Basic Technical requirement 2, already discussed.
There is no easy solution to this problem but we should try to get another initial
pressure once the main test string is in place. It should take an extra two hours to go
through the initial flow and buildup sequence again. Once again, there may be difficulty
characterizing the fluid column between the gauge and the perforations after initial flow.
The best data may be obtained after the test string is stabbed through the packer. This is
definitely true if the two-trip procedure is employed, as the first trip leaves an isolation
flapper valve in place above the gravel pack.
After this is done, the wellbore pressure needs a day or so to fall to formation pressure.
This clearly illustrates that developing a procedure for getting a good initial pressure and
executing it can be quite involved. The initial best pressure procedure is specific to the
completion procedure, and results are sometimes fraught with uncertainties.
ITEM 9: COMPLETION FLUID
The make up of the completion fluid used depends primarily on the density required, but
other properties are important. The test string that we will be discussing in some detail in
the next section has several key tools in it that are operated by manipulating pressure in
the tubing-to-casing annulus chamber formed between the packer and the BOP. A
cle a r, filte re d co m p le tio n flu id w ith n o so lid s is m u ch preferred to ensure that there are
no pressure communication problems between the surface and these bottomhole tools.
But be aware that service companies do state that their tools will operate in a high solids
mud environment, within limits.
A completion fluid that has no environmental or human exposure risks is preferred, but
this may not be possible if testing highly over-pressure wells. Of course, the completion
fluid should be compatible with the formation itself, causing no precipitation, and be gas
h yd ra te p ro o f. C o m p le tio n flu id s co n ta in in g h ig h co n ce n tra tio n s o f N a C l o r C a C l2 h e lp
suppress gas hydrate-formation under most conditions. CaBr2 and ZnBr2 completion
fluids are also used. Brines which are near saturation at surface conditions may
precipitate salt at the pressure/temperature conditions at the mudline. This has been
known to completely plug tubulars and the BOP choke/kill lines.
13 - 31
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
ITEM 10:
If production logging is planned or likely in the well testing program, then the completion
program and the bottomhole area of the wellbore should be designed to accommodate
production logging. Obviously, production logging across the completion interval is ruled
out if an excluder screen technique is employed. The production logging experts at URC
should be consulted early on, as rathole extension (or preservation) plans need to be
proposed early on.
ITEM 11: CUSHION DESIGN
The term cushion is used to describe the fluid placed in the test string (above the
bottomhole test valve) prior to perforation and/or starting flow. It is placed in the test
string by circulating, reverse circulating, or filling while RIH. The cushion true vertical
height and density determines the minimum pressure (i.e., its hydrostatic pressure) the
cushion column initially exerts on the formation. It also determines the minimum
pressure on the bottom side of the packer, and in the tubing. Obviously, the cushion
hydrostatic backpressure must be significantly less than the formation pressure to initiate
flow, and this difference would be the limiting or maximum initial drawdown pressure.
The cushion in the test string should permit a suitable range of drawdown pressures
while accommodating the expected volume of re-entry of completion fluid and mud
filtrate re-entry without the well dying. The cushion hydrostatic backpressure and any
restriction at the surface choke limit the drawdown, thus protecting the test string,
packer, and completion from excessive drawdown while it remains in the test string. A
liquid cushion design that gives about a 500 psi initial underbalance with a 500 psi
w e llh e a d p re ssu re is typ ica lly w h a ts id e a l. A g a s cu sh io n w ill h a ve a m u ch h ig h e r
wellhead pressure because the hydrostatic component of its backpressure is very low
(about 0.05 to 0.10 psi/ft, depending on pressure).
13 - 32
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
In normal to abnormal pressured wells, the best cushion is usually a liquid. A liquid
cushion provides better flow control immediately after perforation, due to its low
compressibility. However, it does not permit the widest range for pressure drawdown, or
accommodate large amounts of kill weight fluid entry that a nitrogen gas cushion does.
In almost all deepwater cases, the reservoir pressure is high enough to use some type
of liquid hydrocarbon cushion, such as diesel oil or base oil (oil based mud carrier).
In significantly over pressured wells, especially gas wells, an aqueous cushion can be
used. However, it must be heavily inhibitive against gas hydrate formation (see Section
12 - Special Situations, Gas Hydrates), and usually is with NaCl or CaCl2, for example.
The resulting weight is usually well above 9.5 ppg. So, in most cases cushions are liquid,
and usually base oil or diesel.
ITEM 12: PRELIMINARY TEST STRING DESIGN
The test tools that make up the test string will be covered in detail in the following
section. At this stage, the general test conditions, test design and the functions that
must be performed by the test string need to be outlined for discussion with the
downhole tool service company.
EXAMPLE:
Expected P and T.
water depth.
well location.
type of rig.
underbalanced perforation.
R/A tag(s).
bottom hole tester valve.
type of packer used.
packer depth.
test interval depth.
pressure gauge location.
possible surface readout on bottomhole gauges.
multiple cycles of reverse out and cushion re-establishment.
spotting acid.
13 - 33
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The production testing requirements are listed in the Drilling OIMS Manual (3-10):
Each program will contain the following sections, as applicable:
1. Cover page with review and approval signatures.
2. Distribution list.
3. Table of Contents.
4. General discussion: generalized test program outline.
5. Testing strategy & objectives.
6. Reservoir data.
7. Test intervals (by zones).
8. Perforating techniques.
9. Test rates and expected flowing temperatures.
10. Data acquisition requirements.
11. BOP stack/wellhead configuration and pressure test plan.
12. Sampling program (only mercury free sampling systems).
13. Environmental management (list of required onsite absorption material, etc.).
The next steps involve specific equipment selection. Before most of the step-by-step test
procedures can be detailed and finalized, specific equipment must be selected. The next
four sections cover downhole, surface, measurement, and production disposal
equipment, respectively.
13 - 34
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The test equipment system for deepwater testing must provide a secure flow path from
the completion to disposal, while providing safe and clean emergency disconnect at the
seafloor. To fulfill the test objectives, the equipment system must also accommodate the
measurement of pressures, temperatures, and flow rates at points along that path. This
all must be done in an environmentally friendly manner, and at a production rate and for
a time period adequate to reach the test objectives. It must then provide for a positive
shut-in of the well following production to measure reservoir pressure recovery.
Discussion of well test equipment will be divided into four areas:
1. Downhole equipment or the test string (made up of the lower test string and
u p p e r te st strin g , A K A th e te st strin g a n d la n d in g strin g , re sp e ctive ly).
2. Surface Equipment (vessels, piping, and safety).
3. Instrumentation, Measurement, Sampling, and Data Acquisition.
4. Production Disposal Equipment.
The lead-time or notice well testing service companies require (what they would like to
have to do best job) depends on the complexity of the job, the water depth, and
downhole and BOP environment (pressure, temperature, and H2S or CO2) under test
rates. It may be even more dependent on the degree of equipment tear-down, inspection
and testing required by the client and the job location. The critical class of equipment is
usually the subsea safety equipment, swivel and flowhead (part of the landing string, to
follow), and to some extent, the lower test string tools. Be aware that these times are
guidelines that might not apply in a specific case.
For the generic GOM oilwell test, a notice of about three months is desired. This
includes two months to do special equipment procurement and testing, to out logistics
and manning, and one month to set aside, assemble, and transport equipment. If the
test is similar to one done or planned recently, and then perhaps lead-time can be cut
d u e to re d u ce d p la n n in g a n d p ro cu re m e n t tim e . In th e fo rtu n a te ly ra re su rp rise - w e re
g o in g to te st it circu m sta n ce , th is tim e h a s b e e n cu t to le ss th a n a month. Below are
some atypical situations:
13 - 35
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
For overseas areas, the rule-of-thumb is to add about a month to GOM lead-times.
13 - 36
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
This section will describe various components that make up the test string run from
floating rigs. This test string is made up of two major sections. The lower test string
starts at the completion (Figure 13.7), includes the packer, major test tools, and extends
up to the BOP stack at the seafloor. It is supported at its top by the fluted hanger resting
in the wellhead wear bushing (Figure 13.6), and by the packer at the bottom. This two-
point support can only be only guaranteed if slip joints are used in the lower test string.
Slip joints will be discussed shortly.
T h e u p p e r p o rtio n o f th e strin g , e xte n d in g fro m th e B O P to a b o ve th e rig s flo o r, is called
the landing string. The landing string will be discussed last, but it should be said now
that landing string functions are essentially distinct and independent from the those of
the lower test string, and its makeup is usually independent of the lower test string
components below it (the exception may be submudline injection equipment). Most of its
w e ig h t is su p p o rte d a t its to p b y th e rig s m o tio n co m p e n sa to r, a n d th e b a la n ce a t th e
bottom by the fluted hanger seated in the wellhead.
13 - 37
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
In the broadest spectrum of production testing, three types of test strings are
encountered:
1. The Open Hole Drillstem Test String (OH-DST).
2. The Production Test String (PTS).
3. The Cased Hole Drillstem Test String (CH-DST) or Annnular Pressure Operated
(APO) test string.
OH - DST
ExxonMobil does not conduct OH-DSTs from floating rigs so they will not be discussed.
T h e b a re fo o t te st m ig h t b e re g a rd e d a s a p o ssib le e xce p tio n to th is ru le . In th is te st, th e
casing shoe is set just above the formation of interest, and the packer and the pressure
operated test tools are in the casing. The discussion
to follow on cased-h o le d rillste m o r A P O te st to o ls w ill a p p ly to th is e xce p tio n .
Subsea BOP Normal Operations
SSTT Connected
Choke Line
Kill Line
13 - 38
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
PTS Tubing
The Production Test String (PTS) consists of production tubing
and a packer, and perhaps a series of nipples in the tailpipe for a
Slip Joints
plug or downhole pressure gauge, as found in a typical producing
well. This test string is simple and very economical, and has no
m o vin g p a rts m a kin g it q u ite re lia b le . H o wever, this type of Drill Collars
string is not conducive to getting good pressure data, because
there is no tester valve to minimize afterflow or to isolate the Redundant
pressure gauges from wellbore, phase humping, etc. Also, this Circulating Valve
type of string has little operational flexibility a n d ca n t e a sily
accommodate the remedial measures sometimes required to
reach test objectives. Primary
CH-D S T Nomenclature Outdated: Prefer Using A P O T est Circulating Valve
String RA Tag
T h e u se o f th e te rm d rillste m in th e d e scrip tio n ca se d h o le
d rillste m te st is o f h isto rical origin, and has been inappropriate
for some time since production tubing, not drill pipe, is used in
Surface Readout
this test string. But the name stuck because the OH-DST and
CH-DST employ an array of test tools with similar functions, even
though they usually operate on quite different principles. Downhole Valve
A more appropriate name for the CH-DST is the annular pressure Hydrostatic
operated (APO) test string. We will now officially dispense with Reference Tool
the CH-DST terminology. APO is preferred because it describes
how most of its tool-components are operated, and correctly Pressure Recorder
implies that the string is operated in a cased hole sealed by BOP
rams and a packer so that annular pressure can be manipulated. Hydraulic Jar
Safety Joint
Packer
Slotted Tailpipe
Debris Sub
Tubing
Firing Head
Safety Spacer
Figure 13.7Perforating
- Test String
Guns
13 - 39
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
From here on, the focus will be entirely on the APO test string. APO tools are ideal for
testing from floating rigs because no pipe reciprocation or rotation is required to operate
the APO tools once the string is set. The string is securely sealed in the BOP stack and
at the packer. This makes for a safer test, and the failsafe shut-in feature of the bottom
hole tester valve reinforces the quick shut-in and disconnect capability afforded by the
subsea test tree.
Since the late 1980s, the APO test string has been firmly establishing a history of
reliability. ExxonMobil has been using the APO test string exclusively for floating rig tests
domestically (GOM and West coast, Alaskan coast) since about 1988, and overseas
since about 1995. Due to the almost universal use of the APO test string, the descriptive
te rm a n n u la r p re ssure operated bottomhole shut-in va lve h a s b e e n sim p lifie d to te ste r
va lve o r te st va lve . T h e u se o f e ith e r o f th e se tw o te rm s h e re w ill a lw a ys m e a n a n
annular pressure operated bottomhole shut-in valve.
The combination of the tester valve and pressure operated multiple-cycle reversing
valves provides test design and operational flexibility. More specifically, the APO
string can:
1. Accommodate a wide range of perforation and sand control options.
2. Be used with retrievable or permanent packers, and while the string is sealed off
by packer:
a) Establish and re-establish fluid cushions.
b) Reverse out produced fluids.
c) Circulate while set in packer.
d) Spot fluids or treatments.
e) Stimulate the well.
3. Prevent hydrate formation in deepwater pressure buildup tests by allowing
pressure to be bled off in from the test string without affecting the buildup below
the closed tester valve.
4. Accommodate wireline operations through the fullbore string (e.g., production
logging, sampling, add-on perforations, etc.).
5. Provide the only sure way to get good quality pressure data and meet typical
objectives when the testing time is limited, or when the reservoir fluid is neither
dry gas nor dead oil.
13 - 40
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The APO test string is always run through a BOP stack on the wellhead. The lower test
string is supported at its top by a fluted hanger carefully spaced out in the test string.
When the string is in place, the fluted hanger rests in the wear bushing in the wellhead.
A slick jo in t is p la ce d in th e te st strin g above the fluted hanger so that specific (usually
the middle pipe) BOP rams can be closed on it. ExxonMobil operations usually strive to
have dual ram closure on the slick joint (i.e. LPR and MPR). The APO test string must
always be used in conjunction with a packer, either permanent or retrievable, seated in
the casing. The slick joint, in the pipe rams in the BOP stack, and the packer seal the top
and bottom of the tubing-casing annular volume.
When a retrievable packer is used, slip joints are a mechanical necessity in testing
from a floating rig. Drill collars are used below slip joints to automatically keep the
required weight on the retrievable packer. A slip joint is a fullbore, integral part of the test
string that is essentially a joint of production tubing in two major pieces, one of which
slid e s a xia lly o r te le sco p e s a n d o n e se a ls w ith in th e o th e r. T h e tw o p ie ce s a re sp lin e d
internally so that they will transmit rotational torque. A slip joint 23 feet in length
(collapsed) will telescope five feet. Typically, three slip joints are used for wells of
average depth, but there is no practical limit. Deeper high-temperature wells might
require more. The slip joints are designed to be pressure compensated so that neither
internal nor external pressure affects axial forces.
Slip joints simplify the space out of the test string length required to properly seat the
fluted hanger in the BOP, while simultaneously seated at the packer. The slip joints also
take up any expansion/contraction of the test string due to pressure or temperature
changes, without changing the weight on the packer, or any other stress loading.
When a permanent packer is used, it is not an absolute mechanical necessity to use
slip joints, as the variable position of the seal assembly in the seal bore provides for
some uncertainty in the space out, and for some string expansion/contraction. In the
past, slip joints were sometimes avoided when possible (e.g. with permanent packer
applications) because they were thought to be a likely and unnecessary source of leaks.
But experience has shown slip joints to be very reliable, and they are now sometimes
used in APO test strings with permanent packers.
Drill collars must also be used below the slip joints in permanent packer applications
also to avoid pumping the string out of the seal bore (Note that this requires additional
cro sso ve rs to m a ke u p a n d re su lts in to o l jo in t co n n e ctio n s in th e te st strin g , w h ich a re
not gas tight). From a mechanical standpoint, simple is always preferable. Hence if the
slip joints can be eliminated from the test string they should be.
13 - 41
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Of course, there are several operational advantages to using slip joints with the
permanent packer, such as more accommodation of string expansion and contraction,
and easing the space out operation. But pressure data quality may make the best case
for using slip joints with a permanent packer. It should be kept in mind that any pressure
gauges set in nipples in the production string will also move if the seal assembly moves
with thermal contraction/expansion. In a test string without slip joints, the gauge height
above the perforations will probably be changing as long as the string is free-floating in
the seal bore assembly. It follows that the hydrostatic offset of the gauges will be
changing, with no means of quantifying the correction required to remove this distortion.
On the other hand, if the seal locator assembly is seated on the packer when the string
tries to expand, it corkscrews. Stresses are added to the string and any pressure gauges
above the seal assembly can be affected. However, gauges in a tailpipe assembly free
hanging below the packer would not be stressed.
In summary, with a permanent packer application and no slip joints, either the pressure
gauges move or the string corkscrews and stresses any gauges above the packer. If slip
jo in ts ca n t b e u se d , th e g a u g e s sh o u ld b e lo ca te d in th e ta ilp ip e b e lo w th e p a cke r to
reduce stress changes. Regardless, such a gauge location will give better pressure data,
but this will be subject will be covered later.
13 - 42
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Most APO major tools are simple in their operation, in that they are opened with
increased annular pressure, and closed when the pressure is bled off. This cycle can
occur numerous times. Other tools, such as single shot reversing valves, and string
pressure test valves, are actuated by one application of annular pressure, and then
permanently disabled - opened, or closed, respectively.
There is a third general classification of pressure operated test tools, which we shall
la b e l in d e xe d to o ls T h e te rm in d e xe d is in te n d e d to d e scrib e h o w o n /o ff cycle s o f
pressu re (e ith e r a n n u la r o r tu b in g ) ra tch e t th e to o l th ro u g h a fixe d se rie s o r cycle o f
pre-defined steps. Each step or index position controls the tool configuration. One cycle
o f p re ssu re m o ve s th e to o l to th e n e xt in d e xe d p o sitio n o r ste p .
Some index positio n s m a y b e n u ll w h ich in d ica te s th e re is n o ch a n g e in to o l
configuration from the previous configuration. Null index positions serve as safety nets
against inadvertent pressure cycles, and enhance compatibility with other pressure-
operated tools in the string. A tool cycle will normally consist of about 8 to 20 steps or
index positions, and a majority of these may be null positions, strategically placed
b e tw e e n g o to n e w co n fig u ra tio n p o sitio n s. O p e ra tio n o f a to o l strin g w ith m u ltip le
indexing tools can get quite complicated. It is possible to get in an untenable position if
ca re is n o t e xe rcise d . F o r th is re a so n , m o re re ce n tly d e ve lo p e d to o ls u tilize p u lse
technology.
13 - 43
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 44
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The bottomhole shut-in or tester valve is a fullbore (std. 2.25 in. ID) ball valve placed
near the bottom of the test string, but above the packer. It is the main valve used to shut-
in the well, and can be shut almost instantly on a well flowing at its maximum rate. The
most common types are actuated and powered by raising annular pressure levels to 800
to 1800 psi above hydrostatic. The number of operating cycles is theoretically
Ball Valve unlimited
for tester valves powered by annular pressure,
e xclu d in g p u lse typ e like the IRIS valve. It is
fa ilsa fe sh u t, u n le ss th e va lve is in th e H o ld -O p e n
Annulus Pres.
co n fig u ra tio n . H o ld O p e n m e a n s th e va lve sta ys
open with no applied annular pressure (e.g., while Control
GIH). Although manufacturers claim these valves Mandrel
13 - 45
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The PCT is a ball valve operated by changing annular pressure levels by pumping
annular fluid into the choke line from the rig floor to the BOP section below the pipe rams
sealed on the slick joint. It is fullbore opening, and the standard 5 in. OD tool size has a
straight through opening of 2.25 in. bore. The PCT will pass standard wireline tools, logs,
and perforating guns. It is run above the packer and standard memory gauges, but
below any reversing valves. The PCT will generally cut standard wireline, but will not cut
through wireline tools. Thus wireline operations on DP rigs are often limited to staying
above the PCT.
OPERATING PRINCIPLES
A pressure-driven, double-acting power piston operate s th e va lve b a ll. T h e p o w e r sid e
of the piston is continually exposed to the current bottomhole annulus pressure. On the
o p p o site sid e , th e re fe re n ce sid e , th e p isto n is h yd ra u lica lly co n n e cte d to a n itro g e n
ch a m b e r co n ta in in g a ca p tu re d re fe re n ce p ressure. This pressure is the bottomhole
annulus pressure when the BOP choke line on the rig floor has no pressure applied.
A strong coiled spring on this same reference side of the piston pushes the piston to the
b a ll clo se d p o sitio n w h e n th e re is n o or a small net fluid pressure difference across the
piston. Thus, with zero surface pressure imposed on the annulus, the ball is closed and
the valve is shut. Almost failsafe, but not exactly.
When the upper side of the power piston, which is exposed to the current bottomhole
annular pressure, senses enough annular pressure rise above the normal annular
p re ssu re to o ve rco m e th e sp rin g s fo rce , it w ill m o ve to ro ta te th e b a ll va lve o p e n .
The surface annular pressure at which the ball opens is selected by choice of coiled
spring when the tool is set up. The PCT opens at a surface annulus pressure of 800 to
1800 psi with typical setup.
FAILSAFE CLOSURE
T h e to o l w ill clo se w h e n th e re is a lo ss o f a n n u la r p re ssu re , m a kin g it a fa ilsa fe clo se d
valve. In practice, the valve never fails to close, unless something substantial is lodged
in the ball opening that mechanically prevents it from rotating and closing, or the annulus
pressure ports are completely plugged. It is conceivable, though, that an emergency
condition may occur in which annular pressure cannot be bled to zero, such as a high-
pressure leak from the tubing into the annulus. In anticipation of this possibility, the PCT
ca n b e co n fig u re d w ith a sh e a r sh u t d isc, w h ich ca n b e se t-up to fail at some pressure
level above that required to operate any other APO tools in the string. Once this disc
fails, the hydraulic chambers on each side of the power piston will be connected, and the
sp rin g s fo rce w ill ke e p th e b a ll va lve clo se d , re g a rd le ss o f th e a n n u la r pressure levels.
This feature used to be standard, but is now only used for gas well tests.
13 - 46
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Annulus Pres.
Seals
RELIABILITY
13 - 47
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 48
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
With the HOOP indexed Figure 13.11 - Hold Open Module (HOOP)
to the hold-open
position, an annular
pressure rise followed
by an annular pressure
bleed-off is required to
close the tool. For this
reason, you should
never be in a HOOP
lock-open cycle, or one
short of a lock-open cycle, in the major flow period of a test sequence, especially when
testing on a DP rig where you are counting on the PCT to close in the event of an
emergency disconnect. Obviously, when using this tool, an accurate history of PCT
valve cycles must be kept at all times.
Circumstances that might cause inadvertent PCT closings are very rare during test flow
periods, and when they do occur, something is usually wrong that would require
shutting-in the well anyway. Thus, HOOP should not be used as a means of avoiding
having to control and monitor annular pressure under normal circumstances.
13 - 49
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Independently
Operated
Circ. Valve
Tester valve
Sensor
Microprocessor
13 - 50
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The pattern is converted into an electronic signature and compared with a set of stored
signatures, each of which triggers a distinct valve operation or sequence of operations.
Thus, more complicated operational sequences are feasible than with the standard APO
tester valve, possibly without imposing a higher pressure on the casing (or on open
completions in other applications). Standard APO test tools are compatible with IRDV,
because conventional pressure level changes meant for APO test tools have little effect
on IRDV operation, and vice-versa. Power to operate the valves is provided by the
differential pressure between hydrostatic and an atmospheric chamber within the tool.
As the valve is functioned, a portion of the hydraulic fluid used to move the piston is bled
into the atmospheric chamber. After about 12 cycles, the chamber is full, and the tool is
now powerless. A booster chamber attachment is being tested to increase the number
of open/close cycles to 24.
The IRDV responds to four types of commands:
1. The direct or independent commands operate on both the tester and circulation
valves. They are stand-alone commands, not part of a sequence, used to open or
close both valves. An intelligent controller prevents both being opened
simultaneously.
2. Sequential commands are used only for the tester valve
3. Nitrogen commands are used for the circulating valve alone. They open and close
the circulating valve with a gas in the tubing so that gas cushions can be safely and
accurately spotted.
4. Preset commands are programmed into the tool before GIH with the string. Preset
commands can be used to close the circulating valve at a prescribed depth (actually,
hydrostatic pressure) when GIH. Preset commands are used with the IRDV valve in
the single trip perforate-gravel pack (PERFPAC) operation.
ExxonMobil has used the IRDV valve in offshore gravel packing operations and in the
main test string with very good success. However, there is some resistance to using it in
the main flow test string as it currently (Jan. 2002) has a limited number of valve cycles
due to its internal atmospheric chamber. There have been instances in which multiple
diesel cushions had to be re-established to get a well kicked-off, overall requiring 15 to
25 valve cycles. One particular well took a lot of completion fluid during gravel packing.
The PCT was used, and the current IRDV would not have had enough cycles to
complete the job. However, as mentioned above, Schlumberger is now testing a booster
module to supply power for 24 IRDV valve cycles.
13 - 51
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
H allib u rto n s L P R -N(R) APO tester Valve has been the main Halliburton APO TEST
downhole tester valve. It is an indexed tool. It is a fullbore (2.25-in. ID) ball valve
operated by annular pressure cycles. The valve is always in one of four configurations,
a s d icta te d b y th e h isto ry o f a n n u la r p re ssu re ch a n g e s a n d th e va lve s in d e xin g :
13 - 52
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
H allib u rto n s S elect T ester V alve is the latest fullbore APO tester valve offered by
Halliburton. ExxonMobil used the valve extensively in the 1998 Sakhalin Island
campaign on jackup rigs, and on one offshore West Africa test. It is offered in two sizes:
5-in. OD, 2.28-in. ID, and 7-in. OD, 3.5-in. ID The valve operating mechanism is different
from the existing Halliburton and Schlumberger APO tester valves. It does not use a
fixed indexing cycle, nor does it require that an annular pressure reference be captured
up front. It can be run in the hole open, so no bypass is required, and it does not require
capture of an annulus reference pressure.
The Select Tester valve has four main sections:
Ball valve section.
Upper hydraulic section.
Lower hydraulic section.
Nitrogen chamber section.
The operating sequence is as follows. To open the ball valve, annular pressure is
applied. Both the upper and lower hydraulic sections are ported to the annulus. The
increased annular pressure acts immediately on the upper hydraulic chamber, whereas
the annular pressure is metered slowly into the lower chamber. This delay causes a
temporary pressure imbalance that forces the ball valve open. After an additional short
delay, the metering cartridge in the lower hydraulic section closes, capturing the raised
annular pressure in the nitrogen chamber of the lower hydraulic section. The ball will
remain open until the annular pressure is bled off. This causes the resulting pressure
imbalance to force the ball valve to close. After a short delay after closing, the lower
hydraulic section nitrogen pressure chamber is metered back to the normal (zero
surface) annular pressure.
The hold-open feature is activated by:
1. Opening the valve with applied annular pressure.
2. Raising the annular pressure to a higher level about 1300 psi surface pressure.
This disconnects the ball closing mechanism, locking the ball valve open. It will remain
open until another 1300 psi of annular pressure is applied, which re-engages the ball
closing mechanism. Then, release of annular pressure closes the ball valve.
Note: With this valve, the next type operation is always optional and is not pre-ordained
by the indexing of the tool, as with the LPR-N valve. Moreover, the tool is failsafe shut,
as only an annular pressure bleed-off is required to close the valve if it is not locked
open. Recall that with the LPR-N valve, it takes an annular pressure increase followed
by bleed-off to shut the valve in some of the index positions.
13 - 53
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Multiple cycle reversing valves are extremely useful in well testing operations, simply
because the are multi-cycle. They add a lot of flexibility and capability for establishing
cushions, spotting acid, reverse circulating, and re-establishing cushions. They are
always used with APO test strings. They are operated by a number of methods, as will
be discussed. In general, th e y ca n b e se n sitive to d e b ris, ru st, e tc., a n d th e y d o n t m ix
well with drill pipe or dirty drill collars. This because they are sliding sleeve-over slot type
valves.
S ch lu m b erg ers
Multi-Cycle Circulating
Valve (MCCV), (Figure
13.13), is a fullbore (2.25-in.
ID) circulating valve that
operates on tubing side
pressure and flow reversals Index
(tubing-to-annulus and System
annulus-to-tubing). It is
placed above the tester Fluid
Flow
valve - as much as several Operating
hundred feet above it if Mandrel
13 - 54
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 55
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 56
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Most single shot reversing valves are annular pressure operated, but tubing pressure
operated tools are also available. As the name implies, they are single action tools that
permanently open one or more ports between the annulus and tubing. They may not be
sh o t o r o p e n e d u n d e r n o rm a l circu m sta n ce s if a m u lti-cycle circulation valve is in the
string and operating properly, but if they are, it is only after the test is over and the test
valve is closed. Thus, their activation pressure should be set considerably higher than
those of the tester valve, the samplers and the multi-cycle circulation valves.
T h e sim p le st o f th e se to o ls is S ch lu m b e rg e rs S in g le S h o t H yd ro sta tic O ve rp re ssu re
Reversing Tool (SHORT). It is permanently opened by one shot of annulus
o ve rp re ssu re . A n o th e r ve rsio n , S ch lu m b e rg e rs S in g le S h o t A n n u la r R e ve rsin g V a lve
(SSARV) has two safety features to prevent premature operation:
1. Two cycles of annular overpressure are required, and
2. The second cycle of overpressure must be completely bled off before the
reversing valve will open.
In Halliburton's line, the APO TEST single shot reversing valve is called the Rupture Disk
Safety Circulating Valve.
S ch lu m b e rg e rs tu b in g p re ssu re o p e ra te d to o l is ca lle d th e S in g le S h o t O ve rp re ssu re
Reverse Tool Internal/External (SORTIE). It can be operated by tubing or annular
overpressure. Halliburton offers the Internal Pressure Operated (IPO) circulating valve.
Raising tubing pressure to a set level above annular pressure operates it. This pressure
difference can be from 500 psi to 10,000 psi. Once activated, the tool is permanently
locked open.
All of these single shot reversing valves, as well as any multiple cycle reversing valves,
are usually placed atop the drill collar section if drill collars are used. If debris or sand
production is likely they are placed a minimum of several hundred feet above the main
tester valve to prevent debris that may settle on top of the tester valve from stacking high
enough to plug the circulation ports in the circulation/reversing valves.
While the most important tool in the APO TEST string is the bottomhole shut-in valve,
other components are essential to conducting a successful test by way of providing
flexibility in cushion replacement, remedial work, and dealing with unexpected events.
This subsection briefly describes these tools.
13 - 57
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
This is simply a short tubing sub that contains an insert of radioactive material that gives
a strong response on the GR-CCL log. It can be helpful when placed in any of the strings
connected with packer setting, completion and testing. It is most helpful when used in
conjunction with RA markers in the casing, as this greatly simplifies and strengthens the
depth correlation and verification process for setting the CHAMP or retrievable packer,
positioning the perforation guns, etc. at a specified depth relative to the test interval.
These two RA tags can be invaluable when the natural formation gamma ray signal
is weak, and further attenuated by the casing and tubing string. Their use is highly
recommended in both casing and tubing strings.
TEST STRING PRESSURE TEST VALVES
The test string pressure test valve is placed in the test string to facilitate pressure testing
of sections of the string as it is assembled and run in the hole. The flapper seals
intermittently for multiple pressure tests top down while GIH. In order for the string to be
filled from the annulus GIH, the main tester valve must be in the locked open position.
Increasing annular pressure to rupture a disc disables the tool. At this point, the tool
locks open full-bore and acts as a piece of tubing.
TUBING FILL VALVE
A close cousin to the test string pressure test valve is the tubing fill/test valve. The
difference is it has its own bypass ports, in addition to the flapper valve, which combine
to a llo w fillin g w h ile G IH w ith th e te ste r va lve in its d e fa u lt clo se d p o sitio n . T h e fla p p e r
valve seals intermittently for multiple pressure tests top down while GIH. This valve is
also permanently retired by increasing annular pressure.
SAFETY JOINTS AND HYDRAULIC JARS
A safety joint and jar sub, if run, would be placed on the bottom portion of the tubing
immediately above the permanent or retrievable packer. Their function is to help free the
string if it becomes stuck. In most cases, it is the retrievable packer that gets stuck. If the
packer does not release, any retrievable gauges are first pulled, and the jar sub is used
to attempt to knock the packer loose. If this fails, then the safety joint is parted using
left-hand torque.
SAFETY VALVES
Safety valves, when operated, seal off the test string to flow from below. Although the
main tester valve is primarily a failsafe shut-in device, there are conditions under which it
will not operate as such.
13 - 58
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
SAMPLING VALVES
APO test samplers discussed below are in-line fullbore tools, and there are three
basic types:
1. The dual-ball sampling valve, called the Dual Ball Safe ty V a lve in S ch lu m b e rg e rs
line.
2. The flow-through annular sampling valve, called the Fullbore Annular Sampling
Chamber (FASC) by Schlumberger, and the FUL-FLO sampler by Halliburton.
3. The bundled mono-phasic sampler (e.g., OIL-P H A S E typ e S C A R , o rig in a te d as a
wireline type of bottom hole sampler, but now mounted in bundle carrier run with the
test string).
Dual-Ball Sampling Valve is basically two in-line full-bore ball valves mounted in a
mandrel-carrier. The distance between the ball valves determines the sample volume,
so very large samples can be captured. This type of sampler can only capture a sample
at the end of the test, because when the two ball valves close simultaneously, capturing
a sample, they close off the test string permanently. These valves are normally activated
by an annular pressure that is significantly higher than that required to operate the main
tester valve, but below that required to operate single-shot reversing valves. This type of
sampling valve can also serve as a safety valve.
Flow-Through Annular Sampling Chamber (FASC), the well stream flows through the
central bore of the fullbore tool before and after sampling. An annular chamber in the
tool wall serves as the sampling chamber, which can be sealed to capture the sample at
any time in the test, with the well flowing or not. Sample volume is typically from 600 to
1200 cc. This sampling tool is also activated by an annular pressure well above that
required to operate the main tester valve, but well below that required to operate single
shot reversing valves or any other APO test tool that ends the test when it is activated.
Several annular sampling valves can be stacked, and each can be set up to trigger at a
different annular pressure. This permits capturing samples at different times in the test.
In practice, the flow-thru annular sampling chamber has been prone to leaks, and
requires special efforts to transfer a sample correctly (under single-phase conditions) at
the surface. Because they are APO test tools, they must be above the packer, which
means they sample at a lower pressure than wireline bottomhole samplers do. This is a
serious limitation for saturated or near-saturated systems.
Note: T h e a n n u la r sa m p le ch a m b e r in th is to o l is n o t a flo w th ro u g h ch a m b e r, b u t is
filled by drawing in a sample from the flow path. Thus, in a two-phase situation, it is less
likely to capture a representative sample than a dual ball sampler, which captures the full
flow stream.
13 - 59
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
ExxonMobil may run these two types of tools as backups to wireline bottomhole
sampling devices in certain situations. For example, in a deepwater test, wireline
bottomhole samplers are thought necessary to get a reservoir sample before any
possible wax or asphaltene deposition in the very cold upper test string. Inline samplers
are run in case there are problems with hydrates that could prevent wireline operations.
Bundled Mono-Phasic Sampler This type of sampler was adapted from the highly-
developed wireline sampler (e.g., OIL-PHASE in the case of Schlumberger), it is fairly
small in O.D, and is carried in a bundle carrier that can accommodate more samplers of
the same type or even gauges (ported to tubing or annulus). The sampler uses a
pressure-balanced, metered piston system to slowly sample from the flow stream at very
low-pressure drawdown. This is to avoid flashing additional gas off in the sampling
process, and thus getting an unrepresentative sample. Once the sample is taken, a high
back-pressure is placed on the sample chamber piston to keep the sample in the
m o n o -p h a sic co n d itio n .
Like the annular sample chambers, sampling does not affect well flow or terminate the
test per se. In Schlumberger colors, the bundled mono-phasic sampler is triggered by
annular pressure. Thus, it must be placed above the packer. In other colors, pressure or
acoustic signals can trigger the bundled mono-phasic sampler. Of course, the use of
timers in APO test string applications is unworkable, whereas this is the primary means
of triggering sampling in slip line applications of this sampler.
These bundle-mounted mono-phasic samplers overcome many of the disadvantages of
the inline ball valve and annular samplers (namely, leakage, sampling ends testing,
possible gas flashing during and after sampling). However, they still cannot offer what
wireline bottomhole sampling can and that is getting samples closer to the perforations,
a n d re trie vin g a n d Q C in g sa m p le s, a n d G IH fo r m o re w ith o u t p u llin g th e te st strin g .
However, they benefit by saving rig time required to run wireline samples, eliminating
lu b rica to rs a n d risk o f b ird -n e stin g w ire , a n d h a ve p ro ve d ve ry re lia b le .
In summary, bottom hole samples are of limited use for PVT work unless the flow stream
being sampled is one phase. However, there are situations in which wireline runs are not
advised, one being in an extremely hydrate-prone well. In these cases, the bundled
mono-phasic sampler nicely fills a niche, and the annular chambered sampler can serve
as a backup sampler.
Comments on SRO Pressure Readout
Surface readout (SRO) pressure measurement systems will be discussed in the
Measurement and Sampling section. Real time readout of bottomhole pressures or
batch-type readout of memorized bottomhole pressures can be very helpful in
conducting a successful test, and can p ro ve in d isp e n sa b le in d ifficu lt w e ll te sts.
This access to downhole data with string still in place can be used to quickly diagnose
and correct many types of problems, monitor the progress of the test, and make an
educated decision to end the pressure buildup. But it is quite expensive. It is the sort of
option that may pay for itself five times over in rig timesaving once every three to eight
applications. Its use in a development well where there is lots of prior experience to draw
on may not be economically justifiable. But for now, we will confine the discussion to
memory gauge carriers.
13 - 60
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The standard way to run standard memory pressure gauges in an APO test to use a
fullbore bundle carrier below the tester valve. The typical fullbore bundle carrier has a
2.25-in. ID and a 5 to 6-in. OD. In most cases, though not always, the carrier is
straight-through, which means the axis of the bore of the bundle carrier is not offset from
the main axis of the test string. It can normally carry four gauges, but bundle carriers can
be stacked to get more gauges downhole.
If a permanent packer is used, the bundle carrier will have to be placed above the seal
locator sub if it cannot pass through the seal bore assembly. This limits how close the
g a u g e s ca n b e p la ce d to th e p e rfo ra tio n s. T o o ve rco m e th is, a ta ilp ip e o r stin g e r ca n
be run below the seal (of smaller OD than the seal bore) to house gauges mounted on
the test string bore axis, below the perforated or slotted flow entry sub. Usually gauges
run in this manner can be pulled and replaced with wireline. A more detailed discussion
o n m o u n tin g g a u g e s in ta ilp ip e s w ill b e p ro vid e d in th e se ctio n M e a su re m e n t a n d
S a m p lin g .
When running an APO test string with a retrievable packer, it is possible to place the
bundle carrier below the packer, because seal bore clearance is not a factor. In many
cases, however, TCP perforation is employed with APO test strings having retrievable
packers, and bundle carriers are not usually run directly on top of or near to the TCP gun
firing head. Nonetheless, with improvements in gauge mechanical integrity and shock
absorbing subs, it is possible to get the gauges closer to the guns than in the past.
If this is not close enough, or if the risks to gauges are not acceptable, then with
pre-planning it is possible to run additional gauges via wireline after the TCP guns have
been fired and dropped. The additional gauges could be set in a stinger extension sub.
This requires a fullbore APO test string. Such a gauge assembly was run in the
Diana-3 test, as previously described.
13 - 61
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13.6.1 INTRODUCTION
The major purposes and functions of the landing string are as follows:
1. To complete the full bore flow path from the top of the lower test string in the
BOP up through the sea and riser to the rig floor, where it is supported by the
rig s m o tio n co m p e n sa to r.
2. To employ the subsea test tree (SSTT) to provide a quick, safe, pollution free
disconnect from the lower test string and withdrawal from the BOP stack in case
of an emergency, such as loss of rig position, etc., by:
Shutting the well in immediately below the disconnect point.
Shearing any wireline or coiled tubing at the disconnect point.
Sealing the bottom of the landing string to prevent hydrocarbon pollution,or
large volumes of gas escaping into the riser.
3. To employ the fluted hanger as a hang-off point in the subsea wellhead (high
pressure housing) to support the test string weight down to the slip joints, support
part of the landing string weight, and to position the slick joint (not to be confused
with the slip joint) opposite the appropriate rams in the BOP and the shear joint
opposite the blind/shear ram.
4. Provide a smooth, uniform cylindrical surface for the BOP rams to seal on.
5. Provide support and protection for the various external control lines, and
chemical injection lines.
13 - 62
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The components of the landing string will now be considered, beginning at the BOP at
the seafloor and working upward to the rig floor. Figures 13.15 and 13.16 show the
BOP stack in more detail.
13 - 63
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The subsea BOP stack is the key piece of well control equipment in deepwater drilling
operations. In deepwater testing operations, the BOP stack performs some additional
test specific functions. It also houses the pipe ram(s) that seal off on the slick jo in t in
the test string, making the casing-tubing annulus a pressure chamber to control the test
tools. It also provides the manifolding necessary to pass choke or kill line fluids and
pressure from the rig floor around the BOP rams to operate the test tools. The subsea
test tree assembly, and shear joint, must be spaced out across the BOP stack such that
the blind/shear rams willSubsea shear the BOP Production
shear joint in the event of Testan emergency disconnect.
And finally, the BOP houses specialAfter subsea Disconnect
safety tools that are positioned near the
b o tto m o f th e la n d in g strin g . T h e se to o ls a re cla ssifie d a s su b se a te st tre e e q u ip m e n t
and will be discussed next.
Choke Line
Kill Line
Fluted Hanger
13 - 64
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The fluted hanger is the bottommost special-purpose tool in the landing string. Shown in
Figures 13.15 and 13.16, it is a round, tapered collar (like a truncated cone) affixed to a
threaded mandrel joint. When the string is positioned in the packer, the fluted hanger
rests in a tapered seat in the bottom of the BOP stack. The hanger supports the weight
of the string below it down to the slip joints. If there are no slip joints (permanent packer
application), the entire string is hanging or is in some degree of compression. Whether
or not slip joints are used, neither the lower test string nor the landing string moves
vertically with the heave of a floating rig. Both are stationary at the seafloor via the fluted
hanger seated on the wear bushing in the wellhead.
The fluted hanger is threaded onto the special mandrel sub, which permits easy
adju stm e n t o f th e co lla rs d ista n ce fro m th e e n d o f th e su b to sim p lify sp a ce o u t. O n ce
adjusted, it is then locked into place to fine-tune the position of the slick joint above it
relative to the appropriate BOP rams, the shear joint across the blind/shear rams, and/or
to fine tune the space out of the string. The fluted hanger has passageways for fluid to
pass through the choke line, lower chambers of the BOP, and into the annular space
below the hanger. This is necessary to operate the APO tools in lower test string.
A slick joint (as opposed to slip joint) is a smooth cylindrical section of pipe with no
external upsets at the joints so that a uniform sealing surface is provided for the pipe
rams of the BOP. For well testing on floating rigs, usually dual ram closer is strived for,
but this may require fabrication of special-length slick joints (depending on BOP ram
spacing in relationship to the fluted land-out point). A special variety of slick joint, called
th e p o rte d slick jo in t, is required if sub-mudline chemical injection into the test string is
required. The ported slick joint has a small passage drilled along the length of it in the
slick joint wall, parallel to its axis. The passage runs almost the length of the slick joint,
up to its threaded ends, where it connects to external ports. The ported slick joint is used
to pump chemicals past the closed BOP rams, and theoretically to any depth short of the
packer. Its use is mandatory if hydrate inhibitor (methanol) is required below the mudline
(typical of gas tests in deepwater).
In some circumstances, two slick joints might be spaced out to give sealing at two test
string positions. For instance, it might be desirable to conduct some temporary operation
with the test string pulled up, but while the annulus is sealed. For instance, checking on
gas under the packer after killing a well while pulled up out of the permanent packer. In
this instance, the second slick joint would be below the fluted hanger.
13 - 65
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 66
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The primary purpose of the SSTT is to provide a safe, clean way to disconnect the string
in a hurry. To do this, it must:
Cut any coiled tubing or wireline in the string with the lower ball valve.
Shut-in the well at the seafloor.
Disconnect the test string immediately beneath the shear rams after the retainer
valve has sealed off the upper disconnected end.
Provide for full reconnect with all functions restored, including chemical injection.
Provide pump-in capability to kill the well in case of a system failure.
Comment [NKM1]: Page: 46
If the SSTT fails to disconnect, first hydraulically, and then after attempting mechanical Is this 37 or 38 or something else? Your number is
backup measures, the shear rams immediately above the SSTT are closed on special 35, but you have a ref. to Figure 1 at the start of the
shear subs in the string. Obviously, this is a last resort. SSTT section.
Note: Many older floating rigs have blind/shear rams that are incapable of shearing
standard shear joints provided by the testing companies. The dimensional and material
properties of the shear joint should be provided to the BOP manufacturer in order to
ensure shear-ability. Special-order or turned-down shear joints are frequently required.
13 - 67
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 68
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The spanner joint rests on the retainer valve and provides the sealing surface opposite
the annular BOP, while protecting control lines, if it becomes necessary to close the
annular. With this tool, annular pressure can be used to open the retainer valve for
reverse-out after disconnects if the control hoses are lost. The spanner joint also
contains a hydraulic manifold to sequence the timing of the SSTT shut-in and disconnect
operations.
Three hydraulic lines control the standard subsea test tree. In the normal configuration:
Line A is pressured and must be kept pressured to keep the lower main ball valve open.
This valve is failsafe closed.
Lines B and C are kept at normal riser hydrostatic pressure.
In an emergency disconnect, the following sequence is followed:
1. The pressure is bled off Line A, and the lower SSTT ball and retainer valve close
or attempt to close if wireline or coiled tubing is in the SSTT.
2. Line B is pressurized, giving a strong boost to the ball valve closing mechanism
so that it cuts any wireline or coiled tubing. Both the ball valve and the retainer
valve should close, sealing off upper and lower sections of the test string.
3. Line C is pressurized, disconnecting the upper section of the SSTT from the
lower SSTT section. The upper test string is picked up and pulled clear of the
BOP. If pressurizing Line C fails to achieve a disconnect, the SSTT can be
disconnected mechanically by a rotary motion.
4. Close the blind rams above the lower portion of the SSTT left in the stack. If the
SSTT and upper test string remain connected, the blind rams will shear the shear
joint and umbilical, thereby closing the SSTT valves and sealing the wellbore.
5. Pull out of the hole with the upper test string and begin pulling the riser if the
situation permits.
Note: For DP rigs timing for these steps is critical. It may be determined that insufficient
time exists for attempted disconnect, and reliance on the blind/shear rams to shear the
shear joint may be the disconnect option of choice (certain situations).
13 - 69
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The earliest SSTT systems were totally hydraulically powered, and this power was
generated at the rig floor with pumps and transmitted through small, flexible, high-
pressure lines. However, as water depths increased, the control length, volume, and
pressure drop increased to the point that disconnect times became unworkable for an
emergency. The first technique to shorten response times was to employ a downhole
hydraulic accumulator. This is a source of nitrogen-charged hydraulic energy stored just
above the retainer valve, within several feet of the SSTT. In the Schlumberger line, it is
called the hydraulic accumulator pod. It can be recharged from the surface, if necessary,
but this would not normally be required or desirable. This deepwater accumulator pod is
triggered by a hydraulic relay system, which is controlled from the surface in the manner
of the original SSTT control system. So this is a hydraulic relay system, with the power
source located where it is needed.
Because only very small volumes of hydraulic fluid from the rig floor are required to
control the relay system that actuates the valves, the response time is shortened
considerably. However, the response time with this system may still not be short
enough. In 5000 ft of water, the hydraulic relay system takes 30 seconds to disconnect
S ch lu m b e rg e rs th re e -inch 10K SSTT. This is considered too long for some dynamically
positioned rigs. And for sure in deeper water, a faster system was needed.
An electro-h yd ra u lic syste m is re q u ire d fo r fa ste r d isco n n e cts. S ch lu m b e rg e rs S E N -
TREE-3 e le ctro -hydraulic system uses electronics from the rig floor and an electric relay
instead of a hydraulic one to activate the hydraulic accumulator pod at the seafloor.
These systems can effect a complete shut-in and disconnect in about 20 seconds,
regardless of water depth. The SSTT must be shut-in, must unlatch, and the landing
string must be pulled up clear of the riser connector - all in less than 37 seconds. This
pushes the 20-second response of the electro-hydraulic SSTT. A hydraulically actuated
system could not meet this requirement.
13 - 70
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
For deepwater tests in new areas, it may be helpful to collect flow stream temperature
data near the seafloor during a well test at all flow conditions for modeling heat loss and
flowstream temperatures for the design of the production gathering system. Or it may be
necessary for gas hydrate mitigation design on the low temperature side, or assuring
that the temperature limits on elastomer seals in the BOP are not exceeded on the
high side.
A subsea pressure and temperature carrier can be used to record temperatures and
pressures, and (optionally) pass them up to the rig for real time monitoring (SRO).
Although this carrier uses the same standard temperature/pressure gauges that are
used bottomhole; the carrier has a special temperature probe to measure as close to the
flowstream as possible.
Typical pressure gauge bundle carriers are not suitable for the measurement of flow
stream temperature, because the temperature-sensing device in the gauge measures
the temperature of the pressure sensing crystal in the gauge (for compensation
purposes), not of the actual flow stream.
Schlumberger offers a real-time SRO temperature measurement from a probe as
described above. It is normally run atop the spanner joint. The probe is very close to the
flow stream wall, insulated from riser fluids, and should provide a representative flow
stream temperature measurement. While this temperature measurement might not be in
the ideal location for temperature data for design of subsea facilities, production risers,
and so forth, it is much better than can be obtained with a standard pressure gauge and
bundle carrier. Halliburton has temperature and pressure probes that are integral to
their electro-hydraulic SSTT package that communicate the data to the surface via the
control line bundle.
This is a fullbore, hydraulically-actuated ball valve that is placed in the landing string
about 50 to 100 feet below the rig floor (not always actually subsea). Lines from a
hydraulic pump system on the rig floor supply actuating power. The valve is balanced in
such a way that it remains in its last position in case of hydraulic failure. It can withstand
high differential pressure in both directions. To open, pressures across the ball valve are
automatically equalized by means of an internal valve. This minimizes the violent surge
and seal wear that would occur otherwise.
The primary purpose of the lubricator valve is to permit longer sections of wireline tools
to be introduced to a pressurized test string without the need for a full-length wireline
lubricator suspended above the surface flow head. In many cases, this would be
impossible or dangerous to do. The lubricator valve also helps to isolate the test string
for purposes of pressure testing.
13 - 71
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The riser sealing mandrel is a recently offered (circa 2000) safety device that facilitates
sealing the landing string at the BOP-diverter just below the rig floor. At increased water
depths, a gas leak in the landing string near the seafloor will expand into a much larger
volume as it comes up the riser to the rig floor. The riser sealing mandrel will contain this
volume, allowing the BOP diverter system to handle it safely.
The riser sealing mandrel is a full bore in-line section of pipe with an offset 9.5 in. OD,
the thicker face of which is scalloped to provide a protective recess for the SSTT control
and injection lines. A half-cylindrical section protective plate is bolted over the lines while
internally it compresses seals around the various lines. Now the diverter BOP has a
uniform cylindrical surface to seal on, the riser can be sealed, and all of the hydraulic
(electric too, if used) lines are protected.
Stiff joints are rigid, thick-walled sections of tubing that are used immediately below the
surface flow head (or surface test tree), extending below the rotary table on the rig floor.
Their purpose is to provide structural integrity and an additional safety factor into the top
of the landing string. Stiff joints prevent the high weight of the flow head (with perhaps a
lubricator on top of it) from causing the string to bend over or whip around, especially in
heavy heave conditions when the motion compensator is not supporting the landing
string from above.
The lower master valve is an additional, optional safety valve. Its position in the upper
part of the landing string. If there is a leak in the flowhead this valve (and the lubricator
valve, if present) could be closed to isolate the surface test tree for repair or
replacement.
The swivel joint is immediately above the lower master valve and below the flow head.
Its sole function is to allow the landing string below it to rotate with respect to the string
above it, without limit, under full operating pressure and flowing conditions. This ability to
rotate while flow testing is an absolute requirement for drilling vessels such as
dynamically positioned drill ships, because they must change their heading with
changing wind direction and sea conditions. Moreover, there are other situations in
which a rotational capability is needed. After all the surface flowlines have been rigged to
the flow head, a swivel joint would make it possible to quickly disconnect at a safety joint
or at the SSTT, if it fails to disconnect hydraulically, by means of string rotation while the
flow head remains stationary.
13 - 72
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Handling Sub
13.6.19 FLOW HEAD
13 - 73
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The master valve can be used to shut the well in if there is no wireline in the well. As
discussed, there may be an optional master valve below it and below the swivel joint.
There may also be a lubricator valve below deck that can be used to shut-in the well if
wireline tools are being loaded into the lubricator atop the flow head.
The swab or crown valve is on top of the flow head and isolates a straight through, full
bore entry port into the top of the test string. This valve and port is fitted to accommodate
a wireline BOP and lubricator to be attached to the top of the flow head so that wireline
tools can be introduced into and withdrawn from the pressurized test string.
The kill side wing valve isolates another entry port to the top of the test string. This valve
and line off the side of the flow head is usually connected to the rig pumps so that the
well string can be circulated, pressurized to operate certain tools, or pumped full of kill
weight completion fluid in a hurry to kill the well.
The flowline side wing valve isolates the exit port where the flow stream exits the test
string and flows through a flexible flowline to the surface production equipment. An
emergency shut down (ESD) valve is always placed on the flowline immediately
downstream of the flowline side wing valve or it may be attached to the flow head itself.
This is a failsafe-shut safety valve with a control system set up such that the flow stream
can be reliably shut off in seconds from any one of multiple strategically located stations
on the rig. This important piece of equipment is discussed in detail in section on surface
equipment, to follow.
13 - 74
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The test string is fixed with respect to earth in one or possibly two places: at the packer,
and via the fluted hanger in the wellhead, and possibly at the packer. When seas cause
the floating drilling rig to heave, yaw, pitch, and roll, the rig floor will move with respect
to the top of the test string. Some type of dynamic tensioner or motion compensation
system is required to support the landing string.
There are two requirements for a motion compensation system:
1. It must maintain a reasonably constant vertical tension on the test landing string,
regardless of rig motion. A tension somewhat less that the total landing string
weight is normally applied, so that the SSTT is not in tension in the BOP.
2. It must provide sufficient clearance for whatever is to be mounted atop the flow
head during the course of the test, normally the wireline BOP and lubricator.
In most cases, the drill string motion compensator on the travelling block will suffice, but
there has been at least one rig whose compensator did not adequately support the
landin g strin g . A m o tio n co m p e n sa to r b o o ste r ca n b e u se d in su ch ca se s.
Note: All the equipment on top of the STT must clear the travelling block and other rig
fixtures. In this adaptation, pulleys are used to increase the effective speed and travel of
the tra ve llin g b lo cks co m p e n sa to r.
Note: The STT must by spaced out in relation to the rig floor so as to always remain
above the rig floor. Hence, rig heave, tides and a safety margin will determine how high
the bottom of the STT should be above the rig floor. Should the STT bottom out on the
rig floor:
1. The landing string could pick up the test string, shifting the SSTT across the blind
shear rams and making an emergency disconnect impractical.
2. The rams sealing on the slick joint could be damaged by the fluted hanger
upward movement.
3. The packer seals may unseat.
The subsea hydraulic control console is the rig floor control station for the SSTT. It
contains the pumps, valving, gauges, and piping to supply and control hydraulic
pressure to the SSTT, and to bleed these pressures off quickly. It typically will contain
four separate systems:
1. A p re ssu rize d a ir co n tro l syste m to o p e ra te th e syste m s p n e u m a tic p u m p s.
2. A circuit to control the pressurized hydraulic fluid used to operate the SSTT.
3. A separate hydraulic fluid circuit to trigger the downhole hydraulic relay, which in
turn triggers the hydraulic accumulator pods to unlatch the SSTT.
4. A chemical injection system.
13 - 75
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Subsea control lines are kept in the form of flexible hose bundles on large skid-mounted
reels. They connect the subsea hydraulic control console to the various landing string
valves. When the various valves are placed in the landing string, the appropriate
hydraulic hose connections are made. At this point the valves in the landing string can
be operated, even as the string is being lowered into the riser.
As the landing string assembly continues, and as it is lowered into the riser, the control
line bundles are played off these reels and affixed to the landing string. Protector clamps
are usually used to secure the lines to the landing string. In many cases, a strong
waterproof plastic tape is used to bind the control line bundle to the string.
Hydrate inhibitor injection is usually required downhole, at least as low as the SSTT, in
deepwater gas wells, and in most deepwater oil wells (see section entitled, Special
Situations, Gas Hydrates). Additional lines, surface pneumatic pumps, and injection subs
will be required. Methanol is normally the inhibitor of choice, and 0.25-in. minimum ID
lines will be required. In the past, line crushing and subsequent leakage has been a
major problem, especially below the BOP. Now an armored line is used that is much
stronger and resistant to crushing. One example of this improved line looks like Romex
electric wire, but about five times the size. It is more or less flat in shape, and each edge
is embedded with a cable. The flowline is in the center.
13 - 76
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The purpose of this equipment is to provide pressure control so that wireline or slickline
runs can be made on a live well under pressure. Wireline or slickline work is not always
required when testing with the APO test string, but such capability adds to the versatility
of the test string, and certain test objectives may require its use. Since the APO test
string is typically fullbore opened to 2.25 in. ID, it easily accommodates wireline work.
Wireline work may be required to run gauges, run production logs, add perforations, or
provide surface readout of bottomhole gauge data. Slickline runs may be required to pull
or set plugs or pressure gauges, run bottomhole samplers, etc.
The typical lubricator is adaptable to housing different types of pressure sealing
components. A grease injection head must be used to make the seal around a conductor
cable (i.e., stranded wireline), whereas a simpler stuffing box is used to accomplish this
for slickline. The lubricator will have extension pieces to give it the length required to
load the wireline/slickline tools and weights into the lubricator barrel before it is secured
to the crown valve at the top of the flowhead.
Note: The lubricator/BOP can be quite tall, especially in high wellhead pressure cases.
Its height might interfere with the travelling block or complicate safe support of the
la n d in g strin g w ith th e rig s m o tio n co m p e n sa to r. T h e o p tio n a l su b se a lu b rica to r va lve ,
described a few pages earlier, is designed to prevent this situation. It effectively extends
th e lu b rica to rs le n g th d o w n th ro u g h th e cro w n a n d m a ste r va lve s to th e su b se a
lubricator valve, a hundred feet or so below the rig floor. Long bails (typically 40-ft)
sh a ckle d to th e rig s b a ils sh o u ld p ro vide the clearance needed to thread the wireline
tools into the STT above a closed lubricator valve.
13 - 77
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13.7.1 INTRODUCTION
Fluids produced in a well test must be processed, separated and measured through a
train of surface equipment on the rig deck(s). Normally this equipment is part of a
temporary, modular installation, piped together with hammer unions. Larger pieces are
skid mounted in protective frames for easy hoisting and protection during transport.
Produced fluid properties, rates and flow conditions are usually not known prior to
exploration well testing. Thus, surface test equipment must be designed to operate
safely and reliably under a much wider range of conditions than production equipment
in permanent facilities. However, all of the equipment will have pressure, temperature,
rate, and H2S (and CO2) partial pressure design limits. The test design specifications
furnished to the service company must provide expected upper limits for these
parameters.
Most pieces of surface equipment used in deepwater well tests are fairly standard and
are proceeding in the direction of flow: the emergency shutdown (ESD) system, data
header, choke manifold, heater, three-phase separator, surge tank, transfer pump,
booms and burner.
A discussion of the functions and operating characteristics of the major pieces of surface
equipment follows. Details on separator instrumentation and measurements will be given
in the following section, Measurement Equipment. The section after that, Crude
Disposal, will detail oil burners, and the equipment required to off-load produced liquids
to barges.
We will now pickup the well test flow where we left off in the previous section, at the
flowhead. Since the landing string is stationary at the seafloor with the fluted hanger
landed in the wear bushing, there is relative movement between it and the rig-floor of the
floating rig as it heaves. COFLEXIP-type flexible hose is run from the wing valve
actuator on the flowhead down to the rig deck in most deepwater tests. This hose is
usually three to four in. ID It is a heavily reinforced, armored hose of composite material,
available in 15,000 psi rating. It will accommodate the motion of the rig relative to the
flowhead.
Often rigs will have permanent piping installed from the rig floor to the well test area.
Occasionally, pipe sections with swivel joints are used to accommodate rig motion.
13 - 78
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The emergency shutdown (ESD) system controls the flowline valve actuator on the
process side wing valve of the flowhead. Another safety valve may be added, the
surface safety valve. It is installed on the deck floor between the flexible piping coming
down from the flowhead and the choke manifold. Both of these valves are failsafe
closed, hydraulic pressure is required to keep them open. The ESD system does not
control any of the SSTT functions.
ESD stations are usually located at the heater or steam exchanger, separator, surge
tank, on the drill floor, along the primary escape route and near the main entrance to
living quarters. The ESD is activated manually at any of the several stations by pushing
a clearly marked large red pushbutton-plunger, which bleeds pressure out of a looped
low-pressure circuit. This, in turn, actuates a control valve that bleeds off the hydraulic
pressure to the safety valves, closing them. This low-pressure line is usually of some
composite polymer or plastic material that can be cut with an axe or pocketknife, or
would melt in a fire anywhere along the loop to shut the valve(s).
The ESD system is flexible and can also be configured to shut-in automatically. High/low
pressure pilot sensors and erosion probes can be placed along the flow path to trigger
the ESD system in case of plugging, leaks, ruptures or sand erosion.
The final ESD design depends on the testing equipment and how it is laid out on the rig,
as well as safety requirements. But in any case, any person authorized to be on the
rig outside the living quarters should also be authorized to push the red ESD button
in an emergency.
13 - 79
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The data header is a manifold immediately upstream of the choke manifold. It is used for
accessing the flowstream for field sampling, injecting inhibitor, or sand production
measurement, in addition to monitoring the temperature and pressure of the flowstream
Figure 13.20. It a lso p ro vid e s a cce ss fo r w e llh e a d p re ssu re (e ve n w ith ch o ke m a n ifo ld
closed) and temperature sensors used in computerized data acquisition.
Sandec probe
Thermo well
Flow
Figure 13.20 - Data Header with Sandec Probe
13 - 80
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 81
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13.7.6 HEATERS
Production heaters are used to raise the temperature of the well effluent after it moves
through the choke manifold, just before entering the separator. Natural gases contain
water vapor. Serious problems can occur if freezing occurs in the surface equipment.
Furthermore, gas hydrates can form at temperatures of about 60 to 70F at pressures
commonly encountered upstream and sometimes downstream of the choke. Hydrates
and ice can also form when testing oil wells that have a significant
gas-oil ratio and free water. Following are conditions requiring the use of a heater, and
these conditions are likely to be more severe in deepwater tests because of the much
cooler flow stream:
1. H yd ra te s a re d iscu sse d in m o re d e ta il in th e se ctio n o n S p e cia l S itu a tio n s.
2. An emulsion or foam is being produced in the separator (made worse by cold
fluid temperatures).
3. High viscosity oil difficult to atomize in burner nozzle separator (made worse by
cold fluid temperatures).
4. Wax deposition may occur inside flow lines and vessels. Heating the oil will
minimize this deposition downstream.
TYPES OF HEATERS
For safety reasons, steam heat exchangers are used exclusively in deepwater well
testing operations. Their use permits the heat generating source (normally a diesel fired
auxiliary steam boiler, or the rig boiler) to be remote, not only from the wellhead - which
is a universal safety requirement, but also from the vicinity of the process flow lines.
A steam heat exchanger is similar in construction to a typical process heat exchanger,
with the well flowstream passing through the tube side and the steam on the shell side.
Steam from the boiler is passed to the exchanger through heavy duty, reinforced high-
pressure rubber hoses (3 to 4 in. OD, somewhat insulated), where it transfers heat to the
well stream in the coils. The steam condenses to water, which is normally recycled to the
boiler in a similar hose. This type of heater is very efficient, easier to operate and safer
than the diesel-fired indirect heater. The boiler and its required full-time operator is
normally supplied by a third party.
Heaters are currently available with working pressures as high as 20,000 psig for H2S
service. For well testing operations, heaters with 3 or 4 in. coils are normally used.
Heaters are rated in British Thermal Units (BTU) and vary in capacity from 0.5 to 6
MMBTU/hr. Special purpose heaters are available with 5 in. coils and have heating
capacities up to 12 MMBTU/hr.
On natural gas wells (and other flow streams prone to hydrates), the heater choke
(located at the midpoint of the heater coil system) is used to take some or most of the
pressure drop normally taken at the choke manifold. This keeps expansion cooling from
taking place until the flow stream is partially heated. If the choke manifold is used to take
all of the pressure drop, the line between the choke manifold and heater could freeze or
hydrate up.
13 - 82
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13.7.7 SEPARATOR
13 - 83
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
CAPACITIES OF SEPARATORS
Flow capacities of separators are stated in terms of BL/D for liquids or SCF/D for gas,
but these maximum rate capacities are somewhat exclusive of one another, and they are
not totally independent of operating pressure either. For example, a 14,400 BL/D liquid
rate capacity may be stated in the specifications. However, for this rate to be reached,
the separator liquid level control must be set to the upper level range. This is required to
give the liquid more separator volume, and increases liquid residence volume at the
expense of gas residence volume. The small table below illustrates the two endpoint
settings for the standard duty separator.
High Liq.Lv. Cntl Max. Liq. Rate 14,400 BL/D Max Gas Rate 25 MMSCF/D
Low Liq.Lv. Cntl. Max. Liq. Rate 6650 BL/D Max Gas Rate 60 MMSCF/D
Even so, these numbers may be optimistic as they are for the higher operating pressure
range, and well-behaved systems. Actual separator capacity is also dependent on flow
stre a m p ro p e rtie s a n d th e se tu p o r tu n e a n d co n d itio n o f th e se p a ra to rs co n tro l
system. So if predicted (test design) rates even approach these numbers, it would be
best to specify a larger, premium separator. It would have capacities about 15% higher
for the liquids and 50% higher for the gas.
OPERATING PROBLEMS
Sand or other solids can be very troublesome in separators. They can cause cutout of
valve trim, plugging of separator internals, and accumulation in the bottom. Hardened
trim can minimize effects of sand on the valves. For this reason, it may be best to
bypass the separator until the well has cleaned up some, perhaps employing the surge
tanks (discussion follows) as a cleanup vessel.
Emulsions cause separator operating problems. Emulsions adversely affect the liquid
level control and decrease the effective oil or water retention time in the separator,
thereby decreasing water-oil separation efficiency. Emulsion breaking chemicals and
heat are the best solution.
Liquid carryover and blow-by are additional operating problems. Carryover occurs when
liquid escapes with the gas phase. It is symptomatic of a high liquid level, damage to
vessel internals, foam, improper sizing, or plugged liquid outlets. It will adversely affect
gas orifice rate measurements in two ways: by distorting and amplifying the pressure
drops across the orifice plate as liquid driBbles through it, and by building up liquid in the
manometer legs, measuring the pressure drop across the orifice plate.
Blow-by occurs when free gas escapes with the liquid phase, and can be an indication of
low liquid level, vortexing, or level control failure and may be amplified by rig motions.
It will affect the liquid turbine meter accuracy.
13 - 84
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The surge tank is a low pressure but closed vessel that usually has a 50 to 75 psi
working pressure. Surge tanks are available with working pressures up to 175 psi. It is a
single or double-compartment vessel with an automatic pressure control valve on the
gas outlet line to maintain a backpressure that can be set to any pressure up to 45 psi.
The process objective is to keep the necessary backpressure on the surge tanks to feed
the (transfer pump fo r) p ro d u ctio n d isp o sa l syste m s, a t th e sa m e tim e a llo w in g o n lin e
calibration of the liquid flow meter on the separator via coordinated liquid level readings
from the surge tank. This backpressure alone is usually sufficient to offload production to
a barge, in most cases. It is not sufficient to push oil through high efficiency burner
nozzles, though. Consequently, the surge tank is not in the flow path most of the time
when burning, but only for intermittent calibration periods.
Sight glasses allow the change of volume of liquids in the tank to be measured. Tank
capacity is usually 50 or 100 barrels. Safety features include a safety relief valve for
accidental over-pressuring. The surge tank was originally designed as a secondary
stage of separation bu t n o w se rve s p rim a rily a s a sa fe g a u g e ta n k o n o ffsh o re te sts.
Surge tanks come in both vertical and horizontal configurations. Vertical tanks are
definitely preferred on drill ships to minimize liquid level sloshing.
13 - 85
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13.7.11 PIPING
Pipework selection is based on anticipated service pressure, flow rate, and layout of
equipment. The pressure specification is determined by the highest pressure expected
at a particular section in the well test flow stream. Thus a 15,000 psi rating might be
required between the flow head and the choke manifold, whereas only 5000 psi to the
heater, and 2000 psi to the separator.
The predicted flow rate is used to determine the pipe size. The service company will
design the system, and give predicted pressures along the entire flow path for a range of
oil rates and GORs. Service pipe diameter is usually 2 to 3 in. upstream of the choke
and 3 in. downstream. 4 in. piping is sometimes used downstream of the separator for
high-rate gas tests.
Pipework typically comprises straight lengths of 5 to 10 ft Pipe connections are
manufactured for standard or H2S service. All pipe, connections, and assemblies should
comply with ANSI B31.3 and API-6A. For sour service, compliance with NACE MR-OI-75
is necessary. Piping is usually connected w ith W e co typ e wing unions.
13 - 86
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Pressure gauges use sensing elements that convert fluid pressure into a physical
displacement or deformation. In mechanical gauges, this displacement or deformation is
recorded or displayed directly.
13 - 87
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The Bourdon type gauge is still in use today for very high temperature applications due
to the temperature limitations (about 350 to 400F, circa 2002) of the batteries that must
be used with electronic gauge. Its mechanism is a tube formed into a helix anchored at
one end and free to rotate at the other. The tube uncoils with increased pressure.
In the BHP application, w h e re it is kn o w n a s th e A m e ra d a g a u g e , a drum is rotated by
a mechanical clock, and a stylus attached to the free end of the coil scratches a fine line
on a coated, very thin metal sheet wrapped around the timed drum. The Bourdon tube is
also the mechanical heart of the dial display type of pressure gauge commonly seen on
all types of surface equipment.
ELECTRONIC GAUGES
13 - 88
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Vibrating Crystal Gauge: The third type of common transducer is the vibrating crystal.
Quartz or sapphire crystals are typically used, but quartz is the choice for most oilfield
applications. Quartz has excellent elastic properties, long-term stability, and is sensitive
to stress. When external stress is applied to the crystal, the resonant frequency of the
crystal shifts in proportion to the stress. Unfortunately, the resonant frequencies of
quartz crystals are also quite sensitive to temperature.
Therefore quartz gauges must be compensated for temperature effects. The standard
quartz gauge will use a calibration algorithm to reduce temperature effects. But the best
quartz gauges use direct temperature compensation. This is accomplished by adding
another identical quartz resonator exposed to the same temperature as the primary
pressure crystal, but kept in vacuum. The second crystal provides the reference to back
out temperature effects. The advantages of the vibrating quartz transducer are its
excellent accuracy, resolution, and long-term stability. The disadvantages are its
sensitivity to temperature and high cost. The compensated quartz crystal gauge has
only the disadvantage of relatively high cost.
13 - 89
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Errors in pressure measurements are rarely discussed in well test reports. Pressures
tend to be regarded as if they have no accuracy limitations. But this is never true for any
typ e o f p re ssu re g a u g e . E ve n if a g a u g e is ca lib ra te d p e rfe ctly a t n u m e ro u s p re ssu re
points, there will be an average error across the range of calibration. This is because of
th e n o n lin e a rity o f th e re sp o n se o f th e g a u g e s se nsor. The calibration is stored as a
p o lyn o m ia l b e st fit cu rve , w h ich ca n n o t e xa ctly re p re se n t p re ssu re a t e ve ry p o ssib le
pressure in the range. The Unigage CQG (compensated quartz gauge) pressure gauge
has a pressure accuracy of 1 to 2.5 psi. This is the absolute best accuracy for this
g a u g e in p e rfe ct ca lib ra tio n a n d o p e ra tin g co n d itio n .
The minimum error specified for the (uncompensated) Unigage Quartz gauge is 3.2 psi.
The error beyond that of the compensated gauge is due to the use of an algorithm for
temperature correction, rather than direct compensation with the second quartz crystal.
The Unigage H-Sapphire pressure gauge has a higher operating temperature limit of
375F, but more error at that range, 10 psi. Below 350F, the accuracy is 5 psi. It is
only used in very high temperature applications.
W e ve b e e n citin g e rro rs in p re ssu re m e a su re m e n t fo r a p e rfe ctly ca lib ra te d g a u g e .
Additional errors in pressure measurement will result from calibration mistakes, shock,
hysteresis from extreme pressure and temperature cycles, aging components, prolonged
service, and so forth. These are impossible to quantify, and can only be detected and
minimized by frequent calibration. Gauge errors accumulating due to expired calibration
or gauge wear and tea r a re n o t se rvice co m p a n ie s fa vo rite to p ic o f co n ve rsa tio n .
The service company may claim that these errors can be neglected because they may
be systematic, and the pressure trend is more important than the absolute value.
There is an element of truth to this, if use is subject to some very restricted conditions.
Three major ones are:
1. The same gauge that is used to measure initial pressure must be used for the
main flow and final buildup.
2. This gauge is not tripped in and out of the hole between the initial pressure and
the final buildup.
3. This gauge data is never, in any application, combined with data from another
gauge, be it BHP data from another test, wireline formation tester data, etc. to
reach an interpretation without mention of the probable errors compounded
between gauges (e.g., 5 to maximum of probably 15 psi).
Obviously these restrictions are rarely met or recognized, and are unacceptable for a
service costing $10K to $25K/day.
13 - 90
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
So the best absolute value of the pressure measurement, and the accuracy of that
absolute value, needs to be known for the best analysis of a well test, and for its use in
other applications. Any pressure measurement, especially including pressure
measurements with wireline formation testers, should routinely specify the estimated
associated error and quote the calibration history.
Pressure gauges on wireline formation testers seem to be infrequently calibrated and put
through lots of rough treatment. They provide the good resolution required for pressure
gradient work, but their absolute accuracy for pressures is not as good as test gauges,
generally.
When pressure data from different gauges, perhaps different trips into the well bore, are
mixed, serious interpretation errors can occur, especially if the gauges are not in
well-calibrated condition. For example, making a pressure gradient plot by including
pressure(s) from a well test with pressure(s) from a wireline formation tester run is not
good practice. There could easily be a 10 to 15 psi difference from different gauges
reading the same pressure.
The same logic applies to why a serious attempt should be made to get the initial
pressure buildup and the main pressure buildup on the same (well-calibrated) gauge.
A n d w h y fo rm a tio n te ste r p re ssu re s sh o u ld n t b e u se d for initial pressure in a well test
interpretation.
13 - 91
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
When speaking of high quality accurate pressure data, one must be reminded that all
pressure measurement instruments, except for two types, measure pressure indirectly.
The two direct measurements are made with the dead weight tester and the manometer.
The manometer can only measure low pressures or low differences in pressure.
The dead weight tester is the mechanical embodiment of the definition of pressure,
Force/Area. A horizontal plate that can be loaded with an assortment of weights rests
atop a cylindrical piston of specified cross-sectional area. The total weight of this
a sse m b ly, in a kn o w n g ra vity fie ld , d ivid e d b y th e p isto n s cro ss se ctio n a l a re a , p rovides
the force per unit area, or pressure. The sliding piston is free to move in an absolutely
vertical cylinder, which forms a closed hydraulic chamber with the piston. The hydraulic
fluid in the chamber will be under a pressure equal to the weight of the piston divided by
the cross sectional area of the piston, any static friction between the piston and
cylinder.
To be accurate a deadweight tester must have very low friction between the piston and
the cylinder, and be in a stable, motionless environment, and the axis of the cylinder
must be absolutely vertical. Elaborate versions of the simple mechanism just described,
housed in controlled high temp environments, and employing methods to minimize
piston friction, are used to calibrate the most scientifically advanced pressure gauges,
regardless of type. This is the standard.
C a lib ra tio n o f S ch lu m b e rg e r g a u g e s o n d e a d w e ig h t te ste rs is d o n e p e rio d ica lly a t o n e
of 20 locations worldwide. Every gauge should come with a calibration document that
provides the calibration coefficients and other key information obtained during the
calibration procedure. The pressure calibration curve for the compensated quartz gauge
makes use of 16 coefficients for the fit of pressure versus sensor response.
13 - 92
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
This will be a brief review of specifications for the downhole pressure gauges needed for
a well test:
Gauge resolution.
Gauge backup.
Battery options.
Gauge programming.
There will also be a more detailed discussion of surface readout of bottomhole pressure
systems and use of surface readout gauges. It must be mentioned that a successful test
requires good pressure gauges, calibrated, set up, and programmed appropriately by a
good, experienced gauge technician.
The first step in specifying a pressure gauge for a planned well test is to determine the
required gauge resolution. To accomplish this, it is necessary to predict the pressure
response of the reservoir. For a buildup test, the slope of pressure-time data plotted on
semi-log paper is given.
A pressure gauge should be chosen with adequate sensitivity to detect the expected
pressure change during the buildup period. The high range of the pressure gauge must
be chosen to be higher than the maximum expected operating pressures. Stimulation,
well killing procedures, DST circulating and hydrostatic pressures are often substantially
higher than reservoir pressures. Allowing a pressure gauge to see pressures out of its
range may ruin the gauge, or at the minimum, its calibration.
The Schlumberger WTQR quartz gauge is widely used. This gauge is calibrated over
the range of 1000 to 16,000 psi and has a resolution of 0.01 psi. This resolution is
more than adequate for deepwater Dual Flow-Dual Shut-in Tests. This is not
accuracy, but resolution, which means it can detect and record a pressure change
as small as 0.01 psi.
GAUGE REDUNDANCY
13 - 93
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
BATTERY OPTIONS
Verify that the Service Company is using batteries with a sufficiently long life and
adequate temperature rating for the planned well test. In deepwater wells, keep in mind
that the maximum recorded temperature (from W/L logs) may be as much as 20 to 35F
lower than the temperature seen in flow. This is dependent on water depth, total depth
and circulating history. As of 2002, the best batteries available for downhole gauges are
lithium batteries; they are good to 350F and will last an average of 27 days. Doubling up
on batteries can increase the useful recording life of the gauge.
PROGRAMMING THE SAMPLING FREQUENCY
The timing of most well test events is unpredictable. It is difficult to predict exactly how
long it will take to run the test string, space it out, pressure test it and get everything
ready to perforate and test. Furthermore, the duration of the flow and shut-in periods
may be adjusted during the test because of long cleanup times, well performance, the
need to stimulate, and other operational considerations. Programming the memory
pressure gauges prior to placing them in the test gauges is an important consideration in
designing a well test. Gauge programming involves setting the sampling rate (and
perhaps a series of time windows with different sampling rates) before putting the
gauges in the bundle carrier in the test string. The gauge technician will always ask the
test specialist or engineer for instructions on programming the gauges.
Fortunately electronic gauges have large memories. And well tests from floating rigs
are usually fairly short operations, requiring that the test string be in the hole an average
of six to ten days. What this means is that simple gauge programming will usually
be adequate.
Nonetheless, a number of options are available to vary the sampling rate to reduce the
number of non-useful data points, and to free more space in the memory chip for
denser data sampling over the region of interest. Furthermore, practically all gauges
w ill h a ve d e la ye d sta rt fe a tu re s. Ju st a s e ffe ctive a s d e la ye d sta rt a n d sa fe r is a
method that takes a pressure/temperature reading at very sparse intervals (say every 5
to 20 minutes).
For varying the sampling rate in the heart of test data collection, there are three methods
in use:
1. Data reduction algorithms reduce the amount of memory required to store the
data. An example is storing pressure differences from an automatically chosen
reference pressure.
2. S m a rt S a m p lin g sa m p le s ra p id ly when pressures are changing rapidly, and
slowly when pressures are stable. But this reduces gauge resolution, and
weights data collection most heavily on the drawdown. Improperly set, it can
easily skimp on data collection in a critical area, the late time region, which
re sp o n d s su b tly to re se rvo ir b o u n d a rie s, e tc. A lso , to b e sm a rt, it m u st u se
m o re b a tte ry p o w e r. O u tsm a rt S a m p lin g co m e s to m in d .
13 - 94
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
3. And finally, manually setting time windows with a constant sampling rate within
each window. This method has no inherent flaws when used sparingly, but its
flexibility does tempt one to overwork the problem. For example, trying to guess
exactly when the main buildup will start, a high sample rate is specified to
capture the rapid rise in pressure to get dense d a ta fo r a p re tty p lo t. A ctu a lly,
the data during this momentary change of pressure levels is not used at all in the
pressure analysis. But the main disadvantage is that an otherwise harmless
electrical glitch in the gauge could cause a sampling window to be skipped. So
an unintended and inappropriate sampling rate window is used. If this happens,
the situation is definitely much worse than if the feature had not been used.
GAUGE PROGRAMMING GUIDELINES
Current electronic gauge memories can store 100,000 to 400,000 readings (one
pressure-temperature-time set). For example, a gauge with a memory capacity of
100,000 readings, programmed to make one reading every 10 seconds, has a life of
100,000 x 10 = 1,000,000 seconds or about 11.6 days. A recording time delay of 1.5
days would extend the total time under the rig floor to 13 days.
This may be a little longer than the average test string will be below the rig floor, but a
100% safety factor is usually advised. A uniform 15 to 20 seconds per sample with a 1.5
day delay should give an adequate safety factor and adequate data density. A total test
time span of about 19 to 24.5 days would be covered. Going to a gauge with a memory
capacity of 400,000 readings would permit a constant sampling interval of 5 seconds.
This is probably overkill for typical DFDS tests from floating rigs. But such capacities will
surely be standard in the near future.
Remember, total test duration includes all operations: RIH, space out, pressure testing,
perforation, cleanup, stimulation, flow/buildup and time to run in and pull out of the hole.
T h e o th e r fa cto r th a t m a y co m e in to p la y is b a tte ry life . T h is is a so fte r n u m b e r th a n
memory capacity, so battery life limits should not be pushed. If necessary, batteries can
usually be d o u b le d u p to e xte n d th e g a u g e s o p e ra tin g life tim e . A ve ry h ig h sa m p lin g
rate may unnecessarily reduce battery life.
Three bottomhole gauges are recommended for recording the primary BHP data
collection. All of the gauges can be programmed the same way, conservatively, to cover
the longest possible test. Or one or two of the gauges can be programmed with no or
different delays GIH. Delays should be conservatively short. It is usually advisable to
specify a very long sampling interval (2 to 5 minutes) inste a d o f a d e la y. Y o u d o n t w a n t
to risk being set and ready to perforate with the gauges in wait state.
The manual selection of sampling rate windows should be used sparingly. A maximum
of 2 to 3 windows are recommended, and the programming should consider the
consequences of a skipped window on data collection.
13 - 95
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The gauge components (battery, memory, sensor, and pressure transmitting bellows)
are contained in sections of stainless steel housings, cylinders about 1.2 in. OD and
about 6 feet long made up.
BUNDLE CARRIERS
In TCP applications with retrievable packers, the BHP gauges are usually run in with the
test string on a full bore, in-line bundle carrier. The bundle carrier holds 4 gauges, which
are secured in deep cut scallops cut in the wall along the exterior length of the carrier.
Individual gauges can be ported to the interior or exterior. A typical fullbore bundle
carrier has a minimum OD of about 5.5 in. The bundle carrier is usually run below the
packer, with a shock sub between it and the TCP guns. If SRO is used, there will usually
be another special gauge carrier placed just above the packer, below the tester valve, to
carry the SRO gauges.
TAILPIPES OR STINGERS
With permanent packer applications in smaller holes, the bundle carrier may have to be
ru n a b o ve th e se a l a sse m b ly, a s it w o n t cle a r th e se a l b o re . It m ig h t b e a lo n g d ista n ce
above the perforations. But in these small to medium hole applications with permanent
packers, the gauges can be run inside tail pipes or stingers. The gauges are stacked
end to end in these instances. The tailpipes are usually blanked off (preferably with
weep holes), and the gauges are protected (but not isolated) from the flowstream.
There are methods to isolate gauges carried in this manner from perforation shock.
This method is also commonly used with excluder type completions.
It is possible to latch the gauges into nipples in the tailpipe so that they can be pulled to
surface and replaced by wireline. This is one area where the tailpipe method of running
gauges has an advantage over the bundle carrier method. But the full bundle carrier
does permit wireline activities without pulling anything. Remember, the closer to the
perforations the better the chance for good pressure data.
13 - 96
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Because of the high rig costs in deepwater testing environments, real-time monitoring of
bottom-hole pressure is often justified. Specialized, surface readout (SRO) equipment is
available for this purpose. It is specialized mainly because it must somehow transmit
bottomhole pressures past a shut tester valve.
SRO of gauge data can be invaluable if operational problems occur as it provides
diagnostic pressure data without disturbing the test string. It also allows real time
analysis to adjust flow and buildup periods to meet site-specific objectives. For example,
to lengthen the buildup in tight or layered zones or to shorten the buildup if the data
trend shows infinite reservoir behavior, meaning that the data trend has a constant
Horner slope and extrapolates exactly to a good initial pressure on the same gauge. The
advantages must be weighed against the additional operational time involved with
rigging up and running these gauges. A wireline lubricator has to be used on top of the
flowhead.
BASIC TYPES OF SRO
There are two types of SRO systems compatible with bottomhole shut-in valves in wide
u se to d a y T h e m o st w id e ly e m p lo ye d is S ch lu m b e rg e rs D a ta la tch syste m , w h ich u se s a
porting system to directly transmit bottomhole pressure past the PCT (or IRDV) to
gauges above. M e tro l T e ch n o lo g ys T .R .I.C .S . S R O syste m employs acoustic data
transmission across the shut-in va lve , u sin g a ta lkin g g a u g e b e lo w th e va lve , a n d a
liste n in g g a u g e a b o ve .
DATA-LATCH
13 - 97
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The LINC running and pickup tool is run in on electric line when:
1. SRO data is required in real time.
2. It is necessary to download the memory gauges.
3. It is necessary to reprogram the memory gauges.
The LINC pickup tool reads the induction signal put out by the downhole LINC coupler.
It requires no hydraulic or electrical wet-connection. The pickup tool is usually
mechanically latched into the LINC housing and coupler section, though this is
not a requirement.
Data-Latch is fullbore straight-through open (2.25 in. ID) when the LINC pickup tool is
not being used. When the LINC pickup tool is in the well, there is no fullbore opening,
but the cross-sectional area for flow is not reduced. Exxon has used this system, in most
of its deepwater exploration well tests in the GOM since its debut in 1989. It has been
very reliable.
Normally, the LINC pickup tool is not placed in the well when flowing. But when the well
is shut-in, LINC is run, and pressure gauge data from the prior flow period(s) are
dumped from the gauge memories, and the real time buildup data is transmitted.
In a recent GOM oilwell test, the well was flowed at about 4800 STB/D with the LINC
pickup tool latched into the string. The only effect was that the wireline noticeably
increased the frictional pressure drop in the string.
Data-Latch requires a lubricator and one or two additional personnel and is quite
expensive. It could save some rig time with diagnostic pressure information in instances
of plugging, damaged completion, uncertainty if guns fired, etc. More likely it will improve
the quality of the test by facilitating real time computer analysis of the pressure data.
However, the DGA-mounted gauges may be up to several hundred feet above the
completion. It is recommended, therefore, that additional memory gauges be placed
much lower in the test string, as close to the completion as possible. The final analysis
of the data would normally be done using data from the lowest gauges in the string,
other factors (such as gauge quality) being equal.
METROL TECHNOLOGY T.R.I.C.S.
13 - 98
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
HALLIBURTON SRO-E
H a llib u rto n s S R O -E surface pressure readout system is much less expensive and
le ss co m p lica te d th a n S ch lu m b e rg e rs D a ta -Latch SRO system. The SRO-E system
comprises a pressure gauge lowered via electric line and latched into a sleeved
hydraulic connection housed on top of the LPR-N valve.
Unfortunately, the SRO-E has several disadvantages inherent in its design:
The gauge and wireline must be in the hole to get data.
Only that pressure data generated while the complete system is in the hole is
captured.
No previously recorded data (from another gauge) can be accessed. Thus, to get
flowing bottomhole pressure data for skin damage analysis, the SRO electric line
and gauge must be in the hole prior to end of the flow period.
HALLIBURTON RT-91
H a llib u rto n s R T -91 surface pressure readout system did not see commercial use before
it was withdrawn from the market. The RT-91 was very similar to the Data-Latch system,
so much so that anticipated legal and patent problems contributed to its demise. This
tool is mentioned for completeness and to offer an explanation as to why Halliburton
offers no state of the art SRO system of its own.
The effect of tidal cycles can be seen in the latter stages of the PBU of many offshore
tests. Even when reservoirs are abnormally pressured, influences from tidal cycles are
observed in the latter stages of the buildup data, although at greatly reduced
magnitudes. This means that the added hydrostatic pressure due to sea height
increase is being transmitted down to reservoir depth by slight flexure of the rock.
Tidal fluctuations are well behaved and recognizable on the buildup. But they need to be
removed from the pressure data to properly analyze and interpret the late time buildup
data. Using actual tidal data collected in the area while testing makes this a
straightforward and reliable process. The normal procedure to get the basic tidal data is
to affix an electronic pressure gauge to the riser somewhere below the slip joint. The
gauge will record hydrostatic pressure on it, and the changes in this value with time will
reflect the tidal influence.
13 - 99
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Orifice meters have traditionally been used for determining gas flow rates in most
applications where high gas rates must be measured. If conditions are controlled, the
meter, manometer runs, and orifice plate areas kept free of liquids or trash, the
measurements are very accurate if the correction factors are applied. Gas is measured
for sales at the commercial distribution level by orifice meters. For well testing, gas
orifice meters are the only practical way to get accurate gas rate measurements.
The basic measurement in an orifice meter is the pressure drop (differential pressure)
across a constriction (orifice) in the meter run. A typical meter system consists of a
concentric, square-edged orifice plate, a fitting that holds the orifice plate centered in the
meter run, taps in the meter run for differential pressure measurement and a pressure
measuring/recording device.
For well testing applications, the most common of the plate-type orifices are thin sharp-
edged concentric orifice plates. The fitting that holds the orifice plate and provides
p re ssu re ta p lo ca tio n s is kn o w n a s a se n io r o rifice fittin g . T h is a cts like a
decompression chamber and allows the orifice plate to be changed under pressure, with
only a momentary flow disruption. The plate can be cranked into the upper chamber,
which is external and sealed from the meter run by a sliding valve. This capability for
ch a n g in g th e o rifice p la te o n -the-fly is im p o rta n t in w e ll te stin g a p p lica tio n s b e ca u se th e
test gas rate is not known in advance. Therefore, the plate orifice size will need to be
ch a n g e d to ke e p th e d iffe re n tia l p re ssu re in th e m e te rs m o st a ccu ra te w o rkin g ra n g e .
There are two basic types of pressure taps for sensing differential pressure the flange
tap and the pipe tap, and they are located in different positions upstream and
downstream of the orifice plate. It is important to know what type of pressure tap is used,
because that will dictate the correction factor used for taps.
The orifice meter is generally equipped with a two-pen recorder for continuous recording
of both static and differential pressure on a circular chart. The paper chart has a
pressure scale on it to enable direct reading of the measured pressures. Static pressure
is generally measured in psia with a Bourdon tube that moves the pen on the chart.
Differential pressure is measured in inches of water using a bellows meter. Any change
of differential pressure between two chambers in the bellows causes a movement of the
bellows to a new position of equilibrium, which moves the pen-arm shaft that records the
differential pressure on a chart. These pressures, along with meter temperature, will also
be recorded with transducers if a computerized data acquisition system is used.
The gas flow rate across an orifice plate in well testing applications is calculated using a
short form of the equation used for commercial gas sales. The short form includes four
correction factors. The long commercial form includes eleven correction factors.
These seven additional terms entail corrections of less than one percent and are
neglected in testing applications.
Without getting into the correction factors and absolute values, the gas flow rate, at
standard conditions, is proportional to the square root of (differential pressure * absolute
pressure/gas gravity). The gas gravity should be available from field lab measurements.
If not, a temporary value of gas gravity, very well documented, must be used for the
calculations. The rates will have to be adjusted later when the gas gravity is available.
13 - 100
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Prior to any production testing on the rig, all orifice plates should be examined for
obvious defects. The plate should be flat, and the edge of the orifice edge should be
clean, without nicks. The static and differential pressure recorders should be checked
and calibrated against a precision pressure gauge. An orifice plate should be installed
that will result in a differential between 40% and 80% of full scale during operation, to get
recordings into the range with the best sensitivity. This should be done only after the
rates have stabilized. The charts can be examined visually (i.e., to ensure that there are
no gaps in data, that the pen is tracing a measurable deflection, etc.) to verify that the
correct orifice size is being used. In making rate calculations, the differential and static
values should be averaged over the period between calculations.
Gas metering problems can be caused by:
Liquid carryover to the orifice plate and tap connections.
Trash and obstructions in the orifice run, plate, taps and lines.
Liquid accumulation in the bottom of a horizontal pipe run, in pipe sags or in the
meter body.
Flow disturbances (pulsing and slugging) caused by rig motion, insufficient
provision for flow stabilization or by irregularities in the pipe.
Differences or changes in prevailing operating conditions from those used for
calculation purposes.
Orifice plate eroded or not sized correctly.
Bellows out of calibration.
Incorrect zero adjustment of the meter.
Bent pen on the recording chart.
Wrong factors used in the orifice equation, Especially Gas Gravity.
Orifice plate size not as documented.
Formation of hydrates in the meter piping or body.
Sour gas.
13 - 101
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
One would think that liquid rate measurements are straightforward and accurate. The
most direct way to measure liquid rates is by taking liquid level measurements in a
calibrated low-pressure surge tank. In some cases, this is possible, and when it is, it is
preferred. It is extra work for the surface equipment and not highly welcomed. When the
oil is produced to a barge, low-pressure surge tanks are alternately in the flow stream
and essentially continuous strapping of the tanks is recommended.
However, when the oil is being pumped to burners, the low-pressure surge tanks are
not normally in the flow stream circuit because the burners require high-pressure oil to
operate efficiently. The surge tanks are used to calibrate the oil flow meter on the
separator, and the calibrated flow meter readings are used to calculate the oil rate.
Water and oil rates flowing through a separator are typically measured with turbine
meters, and much less frequently, with positive displacement meters. The rotary vane
type of positive displacement flow meter is usually a special order item in well testing
separators. They have fairly tight clearances and do not hold up well to well test
applications, where debris may find its way to the separator.
Turbine meters are used to measure liquid flow rates. The turbine meter measures flow
rate (instantaneous or cumulative) by converting liquid velocity into rotational velocity.
A turbine or propeller-like device rotates on a shaft. The speed of the turbine is
proportional to the linear velocity or flow rate of the fluid moving through the meter.
The rotation of the turbine is counted and accumulated to give the cumulative flow rate.
Normally there are two liquid flowmeter legs manifolded on the oil line. The 1 in. size is
typically suited for rates of 200 to 2000 BOPD. The 3 in. meter can handle rates in the
2000 to 25,000 BOPD range.
Turbine meters have a stated accuracy of 1% of reading with 0.05% flow rate
repeatability. Rangeability is generally 10:1. But these numbers are for ideal conditions,
with the meter carefully calibrated under the exact application conditions. When turbine
type flowmeters are installed in industrial applications, basic requirements are stipulated.
For example, strainers, vapor traps and dependable pressure and flow controllers must
be in place.
13 - 102
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Continuous flow is said to be preferred over intermittent dumping. The latter is more
common in well test applications. If all these factors are considered, plus a flow
stream that may contain debris, spent acid, etc., we can begin to understand why it is
rare to see a flowmeter calibration that hold constant to 5%. In fact, changes of 15%
have been witnessed in tests while flow conditions were apparently lined out and
constant. BHP, WHP and gas rate were constant, but liquid rate as per the flowmeter
jumped 15%.
It is important to realize that in well testing, the turbine flowmeter on the oil leg should be
used only as an indicator of flow rate if at all possible. Tank straps should be relied on
for volume calculations. If this is not possible (e.g., high pressure oil supply required for
burners), then the flowmeter should be calibrated at actual separator main flow
conditions several times during the main flow period. When the oil is burned, there
is no final validation available for meter measured oil rates.
W h e n su rg e ta n k stra p s a re m a d e o n p ro d u ce d o il, th e re su ltin g m e te r fa cto r is a ctu a lly
a lumped meter and shrinkage factor. This should be mutually understood so there is no
inadvertent double dipping with the shrinkage part of the overall factor. This sometimes
happens because the well-testing service company data sheets and computer program
break out the overall meter factor into a mechanical and a shrinkage component.
A mechanical component can be derived by calibrating the meter with water
(overall = mechanical because there is no water shrinkage). But all flowmeter references
say the mechanical factor component changes with the fluid and the conditions. So there
is really no way to measure the applicable mechanical factor without the shrinkage,
without a surge tank that will operate at separator conditions.
Even so, before the well test starts, both the oil and water meters on the separator
should be given a preliminary calibration. Flowing a known volume of water through both
meters at a steady rate is the technique used. This procedure will identify major metering
problems before the test starts. A meter will have to be replaced if it is found grossly
inaccurate in this calibration procedure.
13 - 103
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The following checklist should be followed for the best wellsite metering of liquids
and gas.
1. Verify that meters are clean and functioning correctly, and that the orifice place
differential pressure bellows are calibrated.
2. Document and validate all factors used by service companies in their onsite
calculations. The factors do not have to be the final numbers (e.g., gas gravity
may not be available) but they must always be documented.
3. There must be clear agreement on what the liquid meter factor means and
how to calculate separator oil rates for the correct PVT recombination ratio.
Is sh rin ka g e in clu d e d in a co m p o site fa cto r, o r is o n ly a tru e m e ch a n ica l fa cto r
reported? There should be no double dipping on shrinkage.
4. Require and observe strapping of tanks.
5. Always check calculations if rates take an unexplained jump or if
unusually steady.
6. Observe the shrinkage measurement process and verify that all pressure
and temperature measurements are taken at the correct locations.
7. Furnish any subsequent adjustments to rates to the PVT laboratory, and in some
instances, a shrinkage tester is installed downstream of the separator to correct
oil rates (measured at separator conditions) to stock tank (14.7 psia, 6F)
conditions. Oil is measured through a flow meter at separator pressure and
temperature. This oil rate is not at stock tank conditions, as some gas will evolve
when the oil passes from the separator to the surge tank and/or gauge tank
(described below). The shrinkage tester isolates a known volume of separator oil
and then allows the oil to shrink at atmospheric conditions outside the separator.
Because of the small volume of the shrinkage tester, it is not recommended to
calculate shrinkage factor in this manner. The recommended method is to flow
the oil to an atmospheric test tank and correlate the measured volume in the tank
with the separator oil meter reading. The correlation (known variously as the
meter factor or shrinkage factor) then incorporates both a meter factor and oil
volume correction.
13 - 104
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
SHRINKAGE FACTOR
13 - 105
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 106
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The data gathered from sensors mounted at measurement points along the flow stream
is collected through several interfaces and is routed to co m m a n d ce n tra l. T h is is a
controlled environment (positive pressure, w/ AC/Heat) data acquisition cabin with office
workspace, several computers and plotter/printers. Here the raw data can be displayed
real time on monitors for validation and well test control. Note: that The SRO system
usually uses the real time display of its own, usually in the wireline logging unit.
The cabin may also house a separate controlled environment module, which is used as
a field laboratory, to be discussed shortly.
COMPUTER CALCULATIONS, REPORTS, AND SPREADSHEETS
Gas rate calculations are made from the orifice meter data on the separator, employing
the five most significant orifice meter correction factors. Gas gravity drives one of the
more important correction factors, but it may not be available at the time. So an estimate
must be used, with adjustments to be made later. This adjustment can be easily handled
later, but only if the original estimate used in the calculations is well documented.
Liquid flowmeter rates are calculated from raw turbine meter data and manually
determined correction factors.
Even though a computerized acquisition system is used, some data must be determined
manually and entered into the system. Manually entered data will include physical
property data (e.g. gas gravity) and calibration data.
Excel -typ e co m p u te r g e n e ra te d sp re a d sh e e ts, ve ry sim ila r to th e D se rie s o f h a rd
copy forms used by ExxonMobil in past years, are used to report the surface data. The
data is reported in three stages of preparation once full measurements begin after the
flow stream is routed through the separator in the main flow period:
1. Raw data.
2. Intermediate results.
3. Final numbers for clie n t co n su m p tio n , in clu d in g flo w ra te s in sta n d a rd u n its.
13 - 107
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
These sheets will contain data displayed at time intervals normally ranging from
15 minutes to hourly, depending on length into the main flow and its stability. Field lab
results will be included in the display that includes water chlorides and sp.gr., oil API
gravity, gas gravity (actual or temporary values used in meter calculations), and gas H2S
and CO2 content.
At the beginning of the main flow, during cleanup, flow rates are not normally available
b e ca u se th e se p a ra to r is b yp a sse d . A se p a ra te sp re a d sh e e t fo rm ca lle d th e cle a n u p
sh e e t is u se d to d isp la y d a ta . It w ill re co rd te m p e ra tu re s a n d p re ssu re s a lo n g th e flo w
path, and a cumulative volume of liquids produced, if this is available for surge tank or
gauge tank measurements, or (last resort, estimated from P across the choke).
The importance of the information on the cleanup sheet is that it is used to track water
and cushion volumes and properties (ppg, chlorides) and gas content (especially H2S
and CO2). Most of this information is recorded manually from field personnel tally books
o r o n E xxo n M o b il typ e D fo rm s fro m o b se rva tio n s a n d fie ld la b re su lts, a n d th e
computer-produced cleanup sheet is mainly for the records. It typically includes no
calculations.
T h e re is a n o th e r ve ry im p o rta n t e ve n t o r ch ro n o lo g ica l re co rd ke p t o f a ll sig n ifica n t
events during the overall test period, from test personnel arrival on deck to departure.
This record is kept on the computer data acquisition system, but all entries are manual.
E xxo n M o b il p e rso n n e l a re u rg e d to ke e p th e ir o w n te st d ia rie s, b u t sh o u ld a lso h e lp
the service company with suggested entries or times of events as appropriate.
There are several ways to categorize the types of sampling of well test fluids:
What is sampled.
Where it is sampled.
How it is sampled.
The purpose of the sample.
13 - 108
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
PURPOSES OF SAMPLING
Liquid field samples are usually taken downstream of the choke manifold, through a
needle valve for fine control. At this point in the flow stream, the shearing forces
encountered passing through the choke will mix oil and water components. The liquid
mixture is decanted into a centrifuge test tube, where it is heated and spun in a
centrifuge to separate the oil and water phases. Water cut is noted, and the water is
analyzed for chlorides and other components by pre-arrangement. The mud engineer or
mud logger, in addition to the test service company, can provide this analysis. Oil
analysis in the field is usually minimal; API gravity is usually sufficient.
Gas field samples can be taken into an evacuated or purged cylinder or balloon for
chromatographic analysis. For toxic gas detection by Draeger or sniffer tube type
apparatus, the best results are obtained by using a plastic soft drink or milk bottle to
catch a consistent pre-sample for Draeger tube use.
13 - 109
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
These samples fall into two broad categories. The first is PVT quality samples, which are
the highest quality, taken under carefully controlled and recorded conditions. These
strin g e n t co n d itio n s a re n e ce ssa ry if th e se sa m p le s a re to b e u se d a s re se rvo ir
representative sa m p le s in P V T la b o ra to ry stu d ie s.
PVT Samples Taken at Surface Separator: PVT samples must be taken under
single-phase conditions. Since well flow streams, at least at the surface, are usually
multi-phase, surface PVT samples must be taken at the separator. The samples should
be taken at stable separator conditions when both oil and gas rates can be measured
accurately. Oil samples are taken from the oil outlet line of the separator, into 600 to
1200 cc evacuated sample cylinders. The sampling flow line is designed to sample
directly off the oil flow stream, with a minimum of dead space. The throttling of the
sample stream should take place as close to the sample bottle as possible. The sample
should be taken at a controlled, uniform slow rate so there is no flashing upstream of the
throttling, filling the cylinder over a 10 20 min. period.
Gas samples are taken from sampling ports on the gas outlet line of the separator.
Gas sample bottles should be evacuated, but purging with gas may be an acceptable
second choice if there is no liquid carry-over into the gas outlet line. The sampling port
should be arranged so as to minimize picking up liquid carry-over. If the separator
temperature is greater than ambient temperature, it may be necessary to heat the
sampling line to avoid condensation in the line and non-representative gas samples.
Gas sample cylinders come in 10 to 20 liter sizes. Enough gas sample must be taken to
recombine with the oil sample to restore it to reservoir composition. If the GOR is
high and the separator pressure is low, several gas samples may be required for
recombination with one oil sample.
Determining the recombination parameters for separator samples is crucial to getting
PVT quality lab samples. The relative rates of oil and gas must be known at the time of
sampling, and the parameters (shrinkage factors) for converting these rates to rates at
separator conditions must be supplied to the PVT lab with the samples. This has been
discussed at the end of the Liquid Rate Measurement section.
PVT Samples Taken at the Bottom of the Well: There is another location where the
flow stream may be single phase and PVT sampling can be done. That is near the
bottom of the well, just above the completion.
Bottomhole sampling is normally used only to sample under-saturated oil reservoirs.
It is never used for gas condensate reservoirs. The bottomhole sampling tool (or a linked
string of tools) is run in the hole on slickline or wireline, (so a wireline BOP and lubricator
is required) or can be run with the test string (operated by annulus pressure). An SRO
pressure and temperature gauge may be added to the bottomhole sampler string if it is
run in on wireline.
When the samplers are triggered (by a timer if on slickline), a pressure-balanced,
metered piston is withdrawn to slowly sample from the flow stream at very low-pressure
drawdown. This is to avoid flashing additional gas off in the sampling process, and thus
getting an unrepresentative sample. Once the sample is taken, a high backpressure is
p la ce d o n th e sa m p le ch a m b e r p isto n to ke e p th e sa m p le in m o n o -p h a sic co n d itio n .
13 - 110
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Sampling is normally done after the well is cleaned up, but before the well is drawn down
below its saturation pressure. Sometimes this is not possible if the well is initially near its
saturation pressure, and it must be drawn down below the buBble point to clean it up. In
this case it is best to employ the bottom hole sampler in the cleaned up well after it has
been shut-in for a period of several days.
Immediately prior to bottomhole sampling, the well is flowed at a very low drawdown and
rate for several hours. Hopefully, the sampler will see oil at its original condition of
saturation. Remember that the bottom hole sampler must be in a single-phase
environment if the samples are to be used for PVT studies.
A major advantage of bottom hole samples is that they require no recombination, and
better yet, no recombination recipe th e sa m p le s a re tra n sfe rre d to th e la b s P V T
equipment as is.
The field lab may be contained within the Data Acquisition Lab structure, but as a
separate module. It will have a controlled environment (positive pressure, with AC/Heat)
with several stainless steel workbenches and sinks. The field lab will contain the
equipment to perform basic analysis of the formation, cushion and completion fluids.
These properties include gas and liquid specific gravities, H2S and CO2 content of
gases, water cuts, BS&W, water salinity, etc. A centrifuge to speed oil-water separation
is always supplied.
Gas chromatography capability is not standard in service company field labs, but is
available through the mud loggers. However, the lab should house an instrument that
measures gas gravity from the separator outlet on a semi-continuous online basis.
This instrument is generically known as the Ranarex but it may be of another
manufacturer. Lab fluid analysis instruments, kits and other tools will vary depending
on local requirements. The default equipment may not always be adequate, so th e la b s
capabilities need to be verified in the planning stage, and again when the lab module
arrives at the well.
13 - 111
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13.9.1 INTRODUCTION
Only the largest exploration drilling rigs can accommodate the tankage required to store
the produced liquids from the typical oil or rich gas-condensate well test. Some of the
newest drillships have dedicated onboard tankage for up to 100,000 Bbls of test fluid
storage. As a practical limit on older/smaller floating rigs, such onboard tankage would
be limited to about 500 to 1000 barrels, due to deck space, and perhaps weight limits.
Special arrangements could perhaps be made for more storage, but capacities would
still limit the typical test length for a productive well.
Furthermore, even if sufficient storage were possible, safety considerations would not
fa vo r th e sto ra g e o f th e la rg e a m o u n ts o f live cru d e o r co n d e n sa te (e .g ., 1 0 K to 3 0 K
barrels) in temporary tankage on the rig. A specially designed venting system, at the
minimum, would be required. Note: There are special purpose vessels with adequate
crude stabilization facilities, and built-in tankage with closed venting system, but such
systems are only available on a few of the newest drilling rigs. So, the decision for oil
disposal comes down to two possibilities - either burn it, or offload it to a
storage/transport vessel.
In the GOM (and other offshore U.S. areas) there is no practical leeway for a decision -
oil cannot be burned. MMS regulations prior to 1996 allowed burning oil, in theory, as
lo n g a s th e re w a s n o sh e e n w h a tso e ve r visib le o n th e w a te rs su rfa ce . A s a p ra ctica l
matter, this meant only gas condensate and very light oils could be burned with any
confidence, and very carefully at that. Current MMS regulations do not allow burning of
liq u id h yd ro ca rb o n s u n le ss th e a m o u n ts to b e b u rn e d w o u ld b e m in im a l o r th a t th e
alternatives to burning are infeasible or pose a significant risk to offshore personnel or
th e e n viro n m e n t. A p p lica tio n s fo r e xce p tio n s u n d e r th e in fe a sib le o r sig n ifica n t risk to
p e rso n n e l o r e n viro n m e n t cla u se h a ve b e e n su b m itte d a n d re je cte d . T h u s, in e ffe ct,
the current MMS regulations forbid premeditated burning of liquid hydrocarbons.
Burning oil or condensate is permitted only in emergencies.
Consequently, since 1988, Exxon and operating partners have employed barges to take
the oil produced during well tests from floating rigs. Heretofore, these have been
anchored (moored) rigs.
Before proceeding to discuss barging and burning separately, it should be noted that
both methods of disposal are subject to unexpected disruptions. Thus, some on-board
tankage should be kept in reserve to take the production necessary to keep the well
flowing at a stable rate if brief upsets occur with the burners, or the barge has a
temporary problem.
13 - 112
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Oil burners are used to dispose of produced oil during well tests in most other parts of
the world. Recent technical advances have been made towards developing clean and
efficient burner nozzles for most but the heaviest crude oils. Figure 13.22 shows
S ch lu m b e rgNozzle
e rs E ve rG re e n b u rn e r h e a d . M o st se rvice co m p a n ie s n o w g u a ra n te e a
cle a n b u rn ca p a b ility o ve r a sp e cifie d flo w ra te ra n g e w ith m in im a l fa llo u t.
Pilot
Ignito
r
Propane line
Oil inlet
Figure 13.22 - S chlum bergers E verG reen B urner H ead
13 - 113
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Air compressors are additional critical pieces of equipment in the oil burning system, and
should have some backup. If a compressor goes down, there may be a very limited
amount of time (i.e., backup storage) to get the burners back to clean burn status.
Furthermore, if sufficient flow stream pressure (about 350 to 450 psi) is not available at
the separator outlet for efficient burning, then transfer pumps will need to be used to
boost the pressure to the nozzles. Note: When oil is burned, the normal flow path is
straight from the process separator to take advantage of the higher pressure and more
dissolved gas in the oil, both of which enhance burning.
Two burners are normally used for offshore tests to allow continuous testing, regardless
of wind direction, or for backup if wind is neutral. A valved manifold allows selection of
either port or starboard burners on the fly.
Burner capacities up to 20,000 STB/D can be achieved through stacking of multi-nozzled
burner heads. The maximum capacity for the single head 12-nozzle burner shown in
Figure 13.22 is 12,000 BOPD. These are maximum physical throughput capacities,
irrespective of the surroundings being able to handle resulting radiant heat loads. Recall
that about 8000 scf/min of air compression would be required to burn 12,000 BOPD.
Where oil flow is insufficient for efficient atomization and combustion, the number of
burning heads or individual nozzles can be reduced. The supply manifolds permit this
flexibility.
If the backpressure at the burner is too high for the separator to operate properly, larger
piping could be used, additional burner heads could be used, the separator control
pressure could be raised, or the transfer pumps could be used. In some instances, if all
these measures fail, then the well needs to be choked back accordingly. This is a last
resort, of course.
Burner booms are the extension arms and platforms for the burners, designed to keep
the burners well away from the rig, but secure and accessible. They comprise two or
three sections pinned together and supported by wire rope cables attached to a
stationary kingpost, which is rigidly attached to the deck. The booms have walkways for
access to the burner head, and carry a bundle of piping to supply produced oil and gas
for burning, compressed air line, pilot flare fuel, and water for spray shields and/or for
injecting into the flame for cleaner combustion.
Booms typically come in lengths of 45 to 90 ft However, they are available in shorter or
longer lengths. Some rigs have booms permanently attached. Boom length requirements
depend on their location and oil and gas rates all of which go into determining the
radiant heat flux expected on various rig surfaces. Spray shields are usually mounted on
each burner boom. Gas flares (no burner head necessary here) are included in the
booms. They will flare up to about 80 Mscf/D of gas. Wear you ear protectors!
13 - 114
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The service company supplying the surface equipment will make radiant heat flux
calculations based on the estimated flow rates in the test design. If the radiant heat flux
is expected to be very high, or if the burners will be close to heat sensitive equipment in
the rig (e.g., helicopter fuel tanks, landing pad, etc.) or some combination of these, some
form of additional heat protection is needed. Usually, this will take the form of water
spray curtains mounted along the rig deck perimeter, or in some cases, surface
inundation with cascades. Companies that specialize in this service can be employed, or
effective water shields can beset up by rig crew and operations personnel. Often one of
the rigs mud pumps can be lined up to provide additional water curtains. Auxiliary fire
fighting type pumps or rig centrifugal pumps and seawater are used, so after a long test,
there may be quite a bit of salt remaining on deck.
13 - 115
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13.9.6 BARGES
Seagoing flat-bottomed barges have been used by Exxon and its operating partners
approximately half-dozen times to offload oil produced in production tests from floating
rigs. Typically, the barge was moored to the rig, but held off about 200 feet from the rig
by two sea going tugs (Figures 13.23 and 13.24).
200 H aw ser L in es
3 P ro d u ctio n h o se
13 - 116
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
These barges are sea going and typically range in capacity from 12,000 to 40,000
barrels. Regardless of capacity, they have multiple separate compartments so
completion fluid, spent acid, diesel cushions, dirty and clean produced oil can all be
stored on a segregated basis. The contents are stored at atmospheric pressure. The
compartments are vented to the atmosphere through a common manifolded system,
terminating through a flame arrestor.
13 - 117
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
These barges were designed and approved for transport of stock tank type oil and not
specifically for production test oil. The important distinction here is that production test oil
w o n t b e sta b ilize d , a n d w ill still b e d e g a ssin g fo r so m e tim e a fte r it e n te rs th e b a rg e . In
fact, in deepwater wells, the flowstream comes to rig floor quite cool, and gets downright
cold after expanding across the choke. Heater capacity onboard is limited, and may not
be sufficient to get the flow stream up to ambient (i.e., barge) temperature.
When the cool, slightly pressurized oil moves into the barge it will be depressured, will
probably be warmed, and thus will evolve significant dissolved gas which will be coming
out of the vent line. Fortunately, the vent line is situated near the stern of the barge and
is normally downwind of the tending tug alongside the barge and the rig. Normal wind
conditions should disperse the gas with no trouble. However, the barge crew needs to
be apprised that there will be much more gas vented than when they fill their barge with
oil from a field stock tank where the gas has already been weathered at atmospheric
conditions for days, most probably.
These potential problems could be more acute with gas condensate being much more
volatile. On one well, in 1989, barging of gas condensate was the backup to burning.
Fortunately, the condensate burned as clean as a whistle without a drop spilled for five
days. With current MMS rules, ExxonMobil would have to barge this condensate in
the GOM.
H2S, even a small amount, would probably make barging as discussed above, unsafe
and unworkable. A closed vent system would have to be devised that returned all gases
vented from the barge to the rig, where it would be compressed, perhaps stripped of
H2S, but then vented to flare.
13.9.8 COSTS
Recent (1997) GOM tests used a barge and two tugs, and total costs averaged about
$20K per day. An additional $25K was charged to clean the barge after it was offloaded.
Typically, the oil recovered is sold at the end of the test but it cannot be credited back to
the drilling AFE due to royalty issues. But accounting issues aside for the moment, using
the barging option for a successful GOM test will normally more than pay for itself.
13 - 118
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The barge is moored to the rig with two 200-foot hawser lines, bow to the rig. Each of the
lines, at both the rig end and the barge end, is connected to the vessels through a
pelican hook arrangement, as shown in Figure 13.25. The pelican hook enables quick
remote disconnecting of the lines when a release line to it is pulled. To further facilitate
release on the rig end, the release line, in the form of a looped sling, is suspended from
the rig crane for a strong, quick pull.
The barge bow is held about 200 feet off the rig by a tug maintaining tension on a
1500 ft tow cable affixed to the stern of the barge. A second tug is positioned alongside
the barge to act as backup in keeping the barge in position, and as means of relief and
housing for the barge tankermen.
During loading, the barge is manned continuously by the barge tankerman, who is in
constant two-way radio contact with the rig tankerman. The rig tankerman keeps the
barge tankerman advised of any changes in flow stream content, quality and anticipated
volumes and rates. In this manner, the various liquids can be segregated, and the clean
oil volumes can be maximized for sale.
13 - 119
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 120
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
A flexible reinforced (rubber) transfer hose, usually about 3 in. ID, is used to move the oil
from the rig to the barge. The hose has dry quick-disconnects at each end, so no oil will
be spilled on emergency disconnect. The transfer hose is loosely looped about a support
line running from the rig to the barge that it is under no tension load, save its own weight.
But should the hose come under tension, the hose connections are designed to unlatch
before the hose ruptures. Total hose volume over water is about two to three barrels.
Note: The normal process flow path for oil barging is different than that for oil burning,
The oil exiting the separator is directed to a low pressure surge tank, where more gas
flashes from the oil. The normal range of surge tank operating pressures is 30 to 70
psig, and this is usually sufficient pressure to push the oil to the barge via the 3 in. ID
hose. If this is not satisfactory, surge tank pressures can be raised or transfer pumps
can be used.
13 - 121
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The overall responsibility for conducting a safe and successful test rests with the
company Drilling Superintendent. The Drilling Superintendent will work closely with the
tool pushers, the company drilling and testing engineers, the testing service company
personnel and all other contractors involved to ensure that safe practices and approved
procedures are followed. The test engineer must keep the drilling engineer and drilling
superintendent apprised on the progress towards meeting the test objectives. Likewise,
the drilling superintendent and drilling engineer should keep the test engineer informed
of any events that could impact reaching those objectives.
On a more detailed level, guidelines for specific responsibility assignments for a typical
floating rig well test are listed below. An example personnel responsibilities sheet can
also be found in Appendix A. All tests, procedures and rigs are different, so some
additions or shifts of responsibility may be necessary.
13 - 122
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 123
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
1. Set test objectives and priorities with input and approval from client organization.
2. Gather all pertinent formation evaluation and fluid property data.
3. Consult with Drilling Engineer on estimated maximum pressure drawdown
allowed.
4. Develop Conceptual Test Design giving flow and shut-in times, estimated rate
and formation pressure drawdown, wellhead pressures, water cuts, salinities, etc.
5. M a ke sp e cia l e q u ip m e n t re co m m e n d a tio n s (a s p e r 2 , 3 a b o ve , D rillin g E n g in e e rs
section).
6. Design sampling program: to include type, number, location sampled, sample
handling, and shipping information.
7. Write procedures for initial pressure, bringing well on for main flow, reaching
stable rate, and sampling.
8. Consult with drilling engineer on cushion design.
9. Specify an unloading curve to start the main flow, giving the minimum wellhead
pressure permitted as a function of produced cushion.
10. A ssu re th a t se rvice co m p a n ys co m p u te rize d te st d a ta fo rm s m e e t E xxo n M o b ils
standards and requirements.
11. Coordinate data gathering activities.
12. Make sure that calibration standards are met, especially for all liquid and gas
meters on separator. Witness calibrations.
13. Supervise initial flow, and buildup.
14. Supervise unloading and clean up of well with drilling engineer.
15. Reach decision on maximum sustainable test rate with drilling engineer, drilling
superintendent, surface equipment supervisor and captain.
16. Monitor test parameters in Data Acquisition Lab, gather data reports at selected
intervals.*
17. Verify constants, calculations and sensors used in Data Acquisition system by
occasional visual check of pressures and temperatures measured conventionally,
and by using hand calculations.
18. Supervise all surface sampling and entire bottomhole sampling operation, with
assistance from drilling engineer.
19. Continually advise the drilling engineer and drilling superintendent regarding
test progress towards objectives, problems and any anticipated test schedule
changes.
20. Evaluate test data onsite for completeness and accuracy; communicate test
progress and results to clients during and after the test.
21. If SRO is being used, instruct bottomhole gauge technician as to when SRO
pickup wireline is to be RIH, and how/when data is to be transmitted to test
specialist for analysis.
13 - 124
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
22. Analyze PBU in real time if SRO of bottomhole pressure is available. Compare
results to predictions, simulations to decide if buildup time is adequate.
Determine if PBU extrapolates to initial pressure.
23. If SRO of bottomhole pressure data is not used, analyze bottomhole pressure
data after the test string is pulled, verify data will meet test objectives, notify
drilling superintendent and clients.
24. Do follow up on test equipment and service company personnel performance
with drilling engineer.
25. Back onshore, collect all data, sample analysis, PVT studies, complete
interpretation, and write report.
13 - 125
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 126
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 127
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 128
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
MUD LOGGER
1. Take periodic samples of gas at the choke manifold during flow periods as
directed by test engineer and analyze samples with chromatograph.
2. Use gas detectors to determine presence of H2S or CO2 from choke manifold
samples and on the rig floor.
3. Assist with chloride analysis and resistivity measurements on water samples
as directed.
CEMENTER
TOOLPUSHER
1. Ensure that well killing equipment is ready and coordinate the well killing
operations.
2. Oversee running of test string and rigging up of surface control equipment.
3. Participate in the space out procedure.
4. Review the test string make up procedure with the drillers.
5. Consult with the APO tool service company personnel to ensure the necessary
valves on the drillfloor are properly configured for annulus pressure control.
Pass how this will be handled to the drillers and assistant drillers.
6. Help coordinate various steps of the production test sequence as pertains
to the downhole equipment, rig up of the flowhead and lines, wireline
BOP/lubricator, the ESD system, and the emergency disconnect procedure.
DRILLER
13 - 129
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
ASSISTANT DRILLER
CAPTAIN
1. Monitor weather forecast and outlook, and report anything of potential danger to
the Operations Supervisor and Rig Superintendent.
2. Oversee operation of the production barge and the tending tugs.
3. Enforce all safety regulations and coordinate any evacuation proceedings.
SUBSEA ENGINEER
1. Under company supervision, conduct pressure and function test on BOP stack
prior to beginning the production testing operations. Ensure that the BOP rams
are appropriate for the subsea safety assembly (SSTT) of the test string.
2. Work with downhole tool personnel, SSTT operator and Drilling Engineer to
ensure that the fluted hanger space out and the SSTT makeup is such that the
tool string alignment with the rams in the BOP stack is correct.
3. Monitor status of BOP stack and control system.
4. Watch for gas flow and hydrate buildups on the BOP stack , especially the
LMR area.
13 - 130
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The purpose of the production test is to generate high quality data and samples
sufficient to meet the test objectives. Proper recording of these test data and samples,
and the conditions under which they were obtained is very important.
O ve r th e ye a rs a se t o f 1 6 d a ta fo rm s, kn o w n a s th e D -forms, was developed by the
predecessor of ExxonMobil URC to help organize and facilitate the laborious task of
collecting and standardizing the recording of data from all types of well tests.
About 12 of these forms are applicable to well tests from floating rigs using downhole
electronic gauges. They are contained in Ref. 1, Section 11. Fortunately, since that time,
computerized data acquisition of surface data and electronic downhole memory gauges
have simplified this task and reduced the labor required to do it properly. But the
fundamentals of required data collection have not changed, nor has the ultimate
responsibility of seeing that it is done completely and correctly. The test specialist or
engineer has this responsibility.
There is a multitude of ways to categorize well test data, and all have their shortcomings.
The most general starts with two classifications, surface data and bottomhole data.
Surface data has many ways to sub-classify, but here is one way.
With computerized data acquisition, Excel formatted printed reports and data sets have
supplanted some of these key forms (D-05, D-06, D-07). These forms contain the largest
surface data sets, the complete raw surface data, calculated intermediate rate results,
and final data for the main flow period. Some of the data, such as choke size or orifice
plate hole diameter, and event descriptions, are entered manually when changes occur.
But the basic data is usually reported at 10 minute to one-hour time intervals. A
typical test will produce a 12 to 30 page surface data report, legal size landscape
Excel -type format.
As a part of pre-te st p la n n in g , th e te st e n g in e e r sh o u ld b rin g a se t o f D fo rm s o r o th e r
examples of what is wanted to a meeting with the service company so they can present
the required data in the desired format. Usually the standard format offered by the
service company is suitable, perhaps requiring a change or two. This change will usually
involve presenting some auxiliary data not integral to the basic calculations, such as field
sampling results, methanol injection rates, or oil pressure at the burners.
E ve n th o u g h re p la ce d , th e se D fo rm s a re a lso ve ry h e lp fu l in u n d e rsta n d in g th e d a ta
collection process, and the flow in the calculations. They are also helpful to manually
record data for occasional checks on the computerized data acquisition system. This is
highly recommended and helps one to become familiar with the computerized data
acquisition system's processing software logic.
13 - 131
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
This data can be of any type, except bottomhole data. But certain types of data must
always be manually recorded or entered. These types would include static descriptive
data of all kinds, significant events in the test, choke and orifice plate sizes, and field
analysis results for water cut, oil, gas and water properties. The well clean up process is
also described with manual data entries prior to the well stream being put through the
separator. The description of sampling conditions, techniques, and containers is all via
manual recording of data on the sampling forms (D-8, D-9, D-14, and D-15).
The advent of electronic memory gauges has totally automated the recording and
reporting of bottomhole pressure and temperature data. The gauge technician will
generate summary reports of the data, and PC computer readable diskettes or CDs
onsite for the test engineer as soon as the gauges are retrieved from the string and
dumped to the service company computer.
If SRO is used, the gauges are read real time, but normally dumped to diskettes in (4 to
12 hour) batches. The test engineer will incrementally add these data to a data set that
is re-analyzed to extend the buildup analysis. In this way, a decision can be made as
soon as practically possible that sufficient buildup data has been obtained. For the final
analysis and report, the deepest bottomhole gauge data are normally used. These are
usually not the SRO gauges.
13 - 132
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
D-1 contains a very brief summary of the test objectives, the roles of key personnel, and
contact information. It is best used as a rough guide for statement of objectives. The test
design document (Sect. 13-3) is a more comprehensive source for information on test
objectives. Test specialist is responsible for information.
D-2 is an essential form that contains a thorough description of the completion. This
data must be gathered from a number of sources. It contains information on depths,
bottomhole dimensions, mud, completion, and cushion fluid properties, pressure gauge
sensor port depths, etc. Drilling and/or completion engineer is responsible.
D-3 PERFORATION DATA
D-3 is partially obsolete in that it is set-up for multi-run wireline perforating. But most of
the information requested is applicable to any method of perforating. Some of the data
recorded manually will be available from the electronic memory gauges when they are
pulled. Test engineer or test specialist is responsible.
D-4 INITIAL FLOW PERIOD DATA
The D-4 form may be partially obsolete because it assumes that formation fluids will
su rfa ce d u rin g th e in itia l flo w p e rio d , w h ich isn t u su a lly tru e w h e n a b o tto m h o le te ste r
valve is employed. But most of the requested data is pertinent, such as underbalance,
flowing wellhead pressure, choke size, volumes and times. Test engineer or test
specialist is responsible.
13 - 133
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The D-5 form is where the heart of the surface data and the calculated rates from the
main flow period are recorded. Recording intervals typically range from 5 to 15 minutes
(first several hours of main flow) to 30 minutes to 2 hours (for the last part of very stable
production).
The data form contains flow rates and cumulative production volumes for gas, oil, and
water from the main flow period. Wellhead pressure and temperature, choke size, casing
pressure, and field-measured properties of the gas, oil, and water are also recorded.
These are usually gas gravity, API oil gravity, and chlorides (or resistivity), respectively.
If any H2S or CO2 is present, these concentrations are measured and entered on (a
slig h tly m o d ifie d ve rsio n o f) th e fo rm . T h e W e ll T e st R e p o rt sh e e t p ro d u ce d b y th e
Schlumberger computer system is an expanded equivalent of the D-5 form. But it may
be too large for faxing, and the manually filled D-5 form or an Excel version may be used
for daily reports to Drilling offices and the clients.
While the test engineer or test specialist is ultimately responsible for this data, most
of it is actually gathered and processed by the surface facilities crew and/or the
computerized data acquisition system. In any case, the test and drilling engineers should
use this form and the two that follow (D-6 and D-7) to manually record data to verify the
readings and calculations made by the surface facilities crew or the computer.
The D-6 form is used to record the raw liquid flowmeter data for oil and water from the
separator, to make meter factor, shrinkage and temperature corrections. It also contains
water BS&W, and API gravity of the oil. This form does not fully accommodate the
frequent calibration recommended for the oil flow meters. The test engineer or test
specialist is ultimately responsible that calibrations be made as frequently as possible at
actual separator operating conditions (See Section 13.8 - Volumetric Flow Rate
Measurement of Liquids).
The D-7 form is used to record the gas meter orifice diameter, the various correction
factors, gas gravity (from field measurements, or assumed) temperature, static pressure,
differential pressure, and the calculated gas rate for the main flow period. The test
engineer or test specialist is ultimately responsible for checking the condition of the
orifice meter, and use of the correct parameters. Of prime interest is use of the correct
g a s g ra vity (if a va ila b le ), o r d o cu m e n tin g w h a t g a s g ra vity is u se d a s a te m p o ra ry
p la ce h o ld e r. M e te r re a d in g s are made by the surface facilities crew and/or the
co m p u te rize d d a ta a cq u isitio n syste m . T h e in p u t sh e e t fo rm g e n e ra te d b y
Schlumberger is the equivalent of the D-6 and D-7 forms combined.
13 - 134
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The D-8 form is handy for keeping track of field liquid sample results, such as those
taken from the choke manifold during well clean up. Field samples are taken to monitor
test progress and are analyzed onsite. Typical analysis results include those from
sh a ke o u t fo r B S & W , oil gravity, water salinity, resistivity, pH and measurement
temperature.
Once clean up is complete and the well stabilizes, the emphasis shifts to obtaining
samples for offsite lab study, and field samples will be taken less frequently. The test
engineer is responsible for overseeing the sampling, determining frequency, monitoring
the analysis techniques and interpreting the results with respect to the progress of the
w e lls cle a n u p .
D-9 GAS SAMPLE FIELD ANALYSIS RECORD
The D-9 form is the gas equivalent of the D-8 form. Field gas samples are taken from
the choke manifold initially and later from the separator. Analysis results should always
include H2S and CO2. If a chromatograph is available, C1 through C5+ compositional
analysis can be obtained and recorded. Gas gravity as determined for the online
Ranarex , if available, can be entered on this form. But the primary utility of this form is
that it offers a gas sampling record for H2S and CO2. The test engineer is responsible
for overseeing the sampling and monitoring the analysis techniques. But if H2S shows
up, the test engineer and the drilling engineers should be made aware of this even
before it hits the form!
The following D forms are seldom used in deepwater exploration well tests, as explained
below their headings.
This form is a holdover from the mechanical gauge days and will not be used as the
primary bottomhole pressure medium is computer readable, from which listings can be
made at the desired time and sampling intervals.
This form is used to record milestone data, and is a step-by-step guide to a manual
Horner analysis. It can be used if requested, and is valuable if PC software is not
13 - 135
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
available for onsite computer analysis. But normally PC computer analysis is preferred
for speed in handling the massive amounts of data, reports and plots of results.
13 - 136
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
This is only used if the well has a significant amount of afterflow. If the bottomhole tester
valve is used, this technique and form are not used. These last three forms are generally
applicable, as noted.
This data form is used to record the time, conditions, and method under which separator
gas and liquid samples were taken. These conditions encompass the flow path from the
completion through the separator and include gas and oil rates, and water cuts. The
container ID numbers and volumes are described, as well as any special instructions or
contacts for the destination laboratory. The sampling technician will have a similar form.
The test or drilling engineer should check this form prior to the sampling operation to see
if it m e e ts E xxo n M o b ils n e e d s.
This data form is analogous to the D-14 form, but for downhole samplers. There is much
less data on flowstream conditions because conditions uphole are not critical. WHP is of
some interest, and rate could be important. Sampling depth, pressure, temperature, flow
rate, time, and sampler description are recorded.
Also important are the conditions of the sample transfer to shippable containers back at
the surface, including pressure and temperature, measured buBble point pressure, and
sample volumes. The container ID numbers and volumes are described, as well as any
special instructions or contacts for the destination laboratory. Again, the bottom hole
sampling service technicians will have their own forms, which will include most of this
information and probably more. The test or drilling engineer should check this form prior
to th e sa m p lin g o p e ra tio n to se e if it m e e ts E xxo n M o b ils n e e d s.
This form contains no new data but is a compact and useful summary of the important
test parameters and analysis results. The test engineer usually completes it before
leaving the well site. However the analysis results that are entered on this form are very
preliminary, by necessity, because some of the calculations are made with physical
properties that are estimated, pending onshore lab results. The D-16 form gives such a
handy synopsis of the test that it is widely circulated, and the preliminary nature of the
analysis is sometimes overlooked.
13 - 137
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
A very important, and usually tedious, part of the overall sampling process is getting the
samples to the onshore lab or client in a safe, secure, expeditious, and totally legal
manner. Shipping hazardous materials is impacted by the regulations and practices of a
number of company departments and governmental agencies, domestic and
international. This is a matter where experts experienced in the geographic area
should be consulted.
Even with such expert assistance, the test or drilling engineer is going to be responsible
for several items in connection with sample handling. The sample cylinders must have
an indelible label firmly affixed that lists the well, company, contact, date, place and
time taken.
Sometime the well test service company or the sampling contractor will handle the
samp le sh ip m e n t. T h is w ill b e m o re like ly if th e sa m p le s a re g o in g to th e co n tra cto rs
lab for the PVT studies, etc.
13 - 138
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
There are several types of reports that are typically written at the well site by the test
engineer for several audiences:
Regulatory reporting requirements should be determined before the test gets underway.
Reports of rates and cumulative volumes of oil, gas, and water may be required as the
test progresses, depending on jurisdictional area. The D-5 forms may be requested. The
to ta l cu m u la tive vo lu m e s o f p ro d u ctio n w ill b e re q u ire d a t te st e n d . A co m p le te d D -1 6
form (below) or a similar regulatory agency form may be required at the end of the test.
T h e D -1 6 fo rm is co m p le te d b y th e te st e n g in e e r a t th e e n d o f th e te st, u su a lly b e fo re
leaving the rig. It includes a preliminary analysis of the bottomhole pressure data.
It is widely circulated, and becomes a permanent part of the well file.
If SRO is used, the bottomhole gauges can be read in real time. More commonly, the
data are dumped to diskettes in 2 to 6 hour batches and given to the test specialist.
The specialist will add these data to the previous pressures and re-analyze the updated
pressures to extend the buildup analysis. In this way, a decision can be made as soon
as practically possible that sufficient buildup data has been obtained. For the final
analysis and report, the deepest bottomhole gauge data are normally used. These are
usually not the SRO gauges.
13 - 139
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
At the earliest opportunity, the ram configuration in the BOP stack must be reviewed
and, if necessary, be refitted with the proper type and size of rams to seal on the slick
joint and to accommodate the subsea test tree (SSTT) assembly.
The BOP slick joint is spaced out such that, with the fluted hanger landed in the
wellhead, the lower pipe rams (LPR) and the middle pipe rams (MPR) can be closed on
the slick joint to seal off the tubing annulus. The casing pressure is controlled at surface
through the kill line.
If an emergency disconnect is required due to excessive vessel offset or other adverse
conditions, the blind/shear rams can be closed on the shear joint. If sufficient time is
available, the SSTT can be disconnected and pulled well above the shear rams. The
shear rams can then be closed above the remaining portion of the SSTT and the Lower
Marine Riser Package (LMRP) can be disconnected from the BOP stack.
Note: Many older floating rigs have blind/shear rams that are incapable of shearing
standard shear joints provided by the testing companies. The dimensional and material
properties of the shear joint should be provided to the BOP manufacturer in order to
ensure shearability. Special-order or turned-down shear joints are frequently required.
13 - 140
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Deck Space and Loads: The variable deck load capacity or available deck space of
some of the smaller floating rigs (especially drillships) may require that some materials
be offloaded onto supply vessels or sent to shore before production testing equipment
ca n b e p la ce d o n th e rig . T h e rig s va ria b le d e ck lo a d is d e te rm in e d d a ily by stability
calculations, and the weight to be off loaded in order that test equipment can be brought
on board is thereby determined.
Radiant Heat Flux Loads from Burners: Short burner booms or confined spaces on
smaller rigs may result in excessive radiant heat flux loads on rig equipment when the
well is under test at design rates. Given the rate data from the Test Design Document,
the burner locations, and the rig layout, the surface equipment service company can
assist the drilling engineer with these calculations. Obviously, any oil and jet fuel tanks,
lifeboats, and composite helicopter pad surfaces cannot tolerate high radiant heat flux
loads, and will
have to be protected with water curtains, sprays, or cascades.
Offloading Oil Production to Barge (see 13.9).
Gas Hydrate Inhibitor Injection System (see 13.13, Special Situations).
PRE-TEST CONFERENCE
A pre-test conference (or several if needed) should be held with company personnel and
the Rig Superintendent, toolpushers, drillers, Rig Captain and other supervisory
personnel involved with the test. This is not the general safety meeting as it is for the
personnel who will run and supervise the test, but safety will be discussed. During the
pre-test meeting, the following items should be reviewed and discussed:
Test objectives and associated requirements.
Test equipment and hook-up.
Test procedures overview.
Personnel responsibilities.
Special Situations (H2S, offloading production to barges).
Safety procedures.
Emergency procedures and drills.
Supervisory personnel will discuss all pertinent pre-test meeting topics with their
respective personnel. Supervisors must ensure that the responsibilities of all personnel
associated with the test are clearly assigned and understood. The Operations
Supervisor will inform the supply vessel captains of their role in the impending test.
13 - 141
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
SAFETY CONSIDERATIONS
Any operation, which brings explosive, flammable, and potentially toxic materials to the
surface under high-pressure in proximity to a large number of personnel poses a
potentially hazardous situation. Safety and emergency planning for such an operation on
a deepwater well test is made more complex because it has to include all aspects of
general marine safety and emergency disconnects.
A safe well test must be built around a thoughtfully designed process to control and
dispose of these fluids. Hydrocarbons are produced, often at high pressures and rates,
through a temporary system. Plans must include handling disruptions, and must
recognize that some of the rig crew may be unfamiliar with equipment and procedures
used during production testing.
After the detailed well test design is completed, and the, process to control and dispose
of these fluids is laid out, a safety meeting should be conducted for the wellsite
supervisory and technical personnel. Some general safety connected topics are
listed below:
Safety procedures during testing.
Procedures for recognition and mitigation of H2S.
Procedures for handling emergencies, including disconnect and shear
deformations.
Descriptions of test string components (including working pressure and
temperature ratings).
Procedures for pressure testing of surface equipment.
Data on surface equipment throughput capacities, working pressure, and
temperature rating.
Schematic of surface test equipment layout and location.
Procedures for monitoring and control of testing operations.
Diagrams for process and instrumentation, with key parameters to watch.
Diagrams for overpressure alarms, shut down systems, vent lines.
Description of emergency shutdown system.
13 - 142
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The ExxonMobil supervisor in charge should conduct a safety meeting for everyone
onboard before the well is perforated. A second safety meeting should be held before
the well is opened for flow to the surface if an intervening (e.g., gravel packing) operation
occurs between perforation and production. All personnel on location must attend,
including supply boat captains for offshore tests, and barge tug captain, if applicable.
The following topics should be discussed at the first meeting and reviewed at
subsequent meetings, as appropriate:
Job responsibilities of each person during test operations, with emphasis on
safety aspects.
Special safety rules in effect.
Emergency contingency plans.
Warning alarms or signals, and actions that should be taken in response.
Hazards of hydrogen sulfide (see 13.13, Special Situations)
The ExxonMobil supervisor in charge is responsible for the following:
1. Decisions regarding weather conditions that may warrant killing the well and
securing it so that the riser can be pulled if necessary.
2. Ordering the shutdown of all radios and ignition-type internal combustion
engines for the duration of well perforating operations.
3. Making sure that H2S detectors are located around the rig floor and test
equipment.
4. Ensuring that portable H2S detectors are provided and used, if permanent
detectors are not installed around the well and production equipment.
5. Preparing and implementing a toxic gas contingency plan.
T h e sh ip s cap tain should:
1. Hold abandon-ship drills prior to the first well test and regularly once the test
commences
2. Check fire-fighting equipment and assign personnel to be responsible for
using the equipment
3. Organize and hold separate H2S drills, if H2S production is possible.
13 - 143
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The following general rules should be observed during well perforating and for the
duration of the production test:
1. No smoking ANYWHERE except in designated areas in living quarters.
No smoking in mud loggers lab, data acquisition lab, etc.
2. Close portholes and watertight doors.
3. N o w e ld in g , b u rn in g , ch ip p in g , o r g rin d in g w ith o u t th e E xxo n M o b il su p e rviso rs
permission.
4. D o n o t u se cra n e s e xce p t w ith th e E xxo n M o b il su p e rviso rs p e rm issio n .
5. Turn out unnecessary lights in the derrick, on the rig floor, and around the
separator.
6. Clear helicopter landings while the well is flowing with the ExxonMobil supervisor,
or decide in advance whether landings will be permitted while the well is flowing.
7. Have supply vessels stand off (not anchored) a reasonable distance while the
well is flowing.
8. Under no conditions should a well be perforated, produced or kept alive unless a
standby vessel is nearby to help in emergencies.
9. Start a flow test only during daylight and if the well will surface formation fluids
during daylight.
10. Personnel not required for the test or maintenance must remain in the living
quarters.
11. Limit personnel onboard to those required for testing and essential rig operations.
12. In all matters regarding the safety of the crew and ship, the captain has the final
authority.
A fire and boat drill should be conducted well in advance of the initiation of flow. If
there is a possibility of H2S in the produced fluids, a separate H2S drill should also
be conducted.
13 - 144
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
SHIPMENT CHECKS
Equipment sent to the rig for the production test should, as much as possible, be
pressure tested onshore before being sent out. Test string components are delivered to
the rig in metal cargo containers or tool baskets. Using a readiness checklist (see
Appendix B), the Drilling Engineer can verify that all of the required test tools, along with
an adequate supply of spares, are available on the rig. The compatibility of all test tool
connections should be checked.
Most of the surface equipment layout will probably be a near duplicate of that from
previous jobs on the same rig by the same service company. However, there may be
differences in layout of lines, location and capacity of storage tanks, etc.
All high-pressure lines should be firmly anchored to rig deck. Lines should be clearly
marked and stepways should be constructed over line clusters crossing walkways.
Test surface equipment and calibrate as follows:
1. After swinging out the burner booms, install all necessary connections between
the boom, separator, heater, transfer pump, gauge tank and rig floor.
2. Fill up the separator, burner lines, and gas flare line with water by using the
cementing unit.
3. Close the valves on the burner and gas flare lines and pressure test the
separator and lines.
4. Calibrate gas orifice meter differential pressure gauge.
Test burner function as follows:
1. Flush water and oil lines from the separator to the burner with water using
cementing unit or rig pump.
2. Test propane pilot lighters and water shields on both burners. Pump water
through the shields at a pressure of 120 to 150 psi or as recommended by
serviceman.
3. Vent the burner air line to clean out debris.
4. Conduct a burner test by pumping about 50 barrels of diesel from the gauge
tank, through the transfer pump, to the burner.
13 - 145
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 146
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
1. Driller runs bit and scraper in casing, swaps in completion fluid for mud and
circulates the well clean.
2. Service company runs wireline gauge ring and junk basket.
3. Service company runs CCL- Gamma Ray.
13 - 147
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
This sounds more complicated that it is the purpose of this is to simply record where
the rig was in the tidal cycle when the landing string space out mark was made on the
tubing at RKB.
Once the landing string is spaced out, stands are marked, tallied, and kept segregated
for the several reruns that are required. Normally the subsea safety equipment (SSTT,
retainer valve) is not placed in the initial landing string, but its length is represented with
d u m m y tu b in g .
The lower test string space out is a little more complicated and time consuming, as the
final length adjustments indicated by the space out can only be made after the pipe
immediately below the fluted hanger position has been pulled up to the rig floor. But
lower string depth control and space out is much easier to understand if you remember
that the space out in the string below the stack must be directly referenced to the top of
the interval to be tested as shown on the master log. This is done after the hole is cased
with a CCL-GR logging run that is depth correlated to the master log by means of tying it
to a GR characteristic feature above the test interval that is shown on both the openhole
and cased hole log.
In determining the test string length required to span the distance between the fluted
hanger and the top of the interval to be tested (the top shot), the correct space out must
be confirmed or determined by an actual trial fitting. Absolute measurements will not
work. Logging cables stretch with load and higher temperatures, and may also slip a little
in the calibrated cable-measuring wheel. So subsequent log runs are always depth
a d ju ste d to th e m a ste r lo g ru n . A lso , th e lo w e r te st strin g le n g th w ill va ry w ith
temperature and tensile load. This all goes to explain some or most of the differences
typically seen between logging depth and drillers d e p th s.
The master depth reference for locating the bottom of the lower test string for perforating
must be the top of the interval to be tested, as shown on the master reference master
log. Everything to follow must be tied to th e ch a ra cte ristic fe a tu re o n th e m a ste r lo g th a t
delineates the top of the interval.
The procedure to be followed for the lower test string space out will depend on what type
of packer is used, and how this packer is run.
13 - 148
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
If the packer is a retrievable packer, then the space out operation is conducted with the
test string, made up to its estimated required length below the fluted hanger, hanging
from the fluted hanger seated in the wellhead wear bushing. An RA tagged pup joint is
placed in the test string a few hundred feet up from the bottom. The required depth
control and space out adjustments are determined at the same time by CCL-GR
logging and noting the depth differences between the RA pip mark in the test
string and a GR feature chosen from the first GR-CCL log run after casing was set.
This feature should be about 200 to 400 ft above the top of the zone to be tested.
The CCL (Casing Collar Log)-GR log is examined to make sure that the packer will not
span a casing collar when it is set at correct depth. If it will, the string length below the
packer is changed. The string length between the packer and the top shot is measured.
Note: We are going to have to equate test string increment lengths to wireline measured
depth differences of a hundred feet or so, but any measurement discrepancies will be
relatively small numbers, in the several inches range, as opposed to errors of 10 to 20 ft
that can build over 10,000 to 20,000 ft if measurements are referenced to the surface.
A ll d e p th s a re re fe re n ce d to th o se o n th e m a ste r lo g g in g ru n , in th is ca se th e A IT lo g ,
which should be qualified by date and run number. The top of the zone is at 6356 ft AIT
depth and the top perforation should be at that depth.
1. There is a strong GR feature at 6090 ft AIT depth, on the open hole AIT log. It is
in a convenient position of 266 ft above the top of the zone to be tested.
2. This GR feature at 6090 ft will be used as the benchmark to tie in the depths of
the cased hole CCL-GR log run. The CCL-GR log also responds to this strong
GR, and it is easily recognized. Now the Casing Collar log is also depth
re g iste re d to th e m a ste r d e p th o n th e o p e n h o le lo g .
3. The test string is strapped from the top perforation shot to the RA tag placed in
the test string. In this example, that distance is measured to be 371.3 ft
4. When the test string is at correct depth, the top perforation will be at 6356 ft AIT
depth, and the RA tag will then be (371.3 to 266 ft) or 105.3 ft above the
benchmark GR feature.
5. The string is run to approximate depth without setting the packer. The string is
logged hanging in tension with CCL-GR and the difference in depths between the
RA tag and the benchmark GR feature is noted.
6. The amount the string below the fluted hanger has to be adjusted for the top shot
to be on depth is calculated, including adjustments for desired slip joint
compression (about half extension available and seen in this logging run), jar
compression, and packer stroke.
7. Check CCL and space-out before GIH to make sure that the retrievable packer
will not be set in a casing collar when on correct depth. Adjust packer setting
depth or string length between TCP guns and packer as required.
8. Insert or remove joints and pups as necessary. Run string, re-run CCL-GR log as
double check if necessary, set packer, lower string to rest on fluted hanger.
13 - 149
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Note: In this example there was a strong, distinct GR feature conveniently located about
250 ft above the interval to be tested. This is not always the case, and if the GR log
signals are fairly weak and not particularly distinctive, there might be some ambiguity in
the depth registration process for the test string. This is because the detected response
from the GR log is attenuated through casing, and gets even weaker when logged from
inside the test string.
A solution to this problem, and a great help in any case, is putting an RA tag in the
casing itself. The first CCL-GR log run in open casing is used to tie the RA casing tag
in to th e m a ste r d e p th o f th e re fe re n ce lo g . O n ce th is is d o n e , fu tu re lo g s n e e d o n ly to
see the strong casing RA pip mark for positive tie ins. Another RA tag is still placed in
the test string. The approximate depths of the casing and test string RA tags should be
coordinated so that they are about 100 to 200 feet apart when string is on depth so that
there is no mistaking which RA pip mark is on top.
When a permanent packer or gravel pack sump packer is employed, depth control and
the test string space out are two separate operations. The permanent or sump packer is
normally run in on wireline and set at the required depth using the CCL-GR log. Once
the permanent or sump packer is set, all subsequent space-outs (and perforating) are
performed from that packer depth.
With the retrievable packer, the depth registration is done with the GR-CCL log as with
the retrievable packer example just discussed. But picking the feature to depth correlate
to is probably more clear cut since the CCL-GR log should be essentially identical to the
original CCL-GR log, as both are run in open casing. Given the strapped distance from
the CCL-GR reference point on the logging tool to the top of the packer, setting the
packer at specified distance above the top of the interval to be tested is straightforward,
once the GR-CCL log is depth correlated to the original GR-CCL log.
The space out of the test string is different than for the retrievable packer case in that the
packer is already set at the correct depth. The lower string for space out is essentially
the same as will be run for the test, except that it has no fluted hanger.
The test string is made up, and a painted stand or two of tubing is placed in the string at
the position estimated to be where the pipe ram in the BOP stack will seal on the string
swhen it is fully seated in the permanent packer. Normally a white oil-based paint is used
and it is applied when running through the rotary, so that it is still soft enough to hold the
mark of the rams. To properly space out to determine the correct position of the fluted
hanger, the seal locator assembly in the lower test string is fully seated on the packer, as
determined by string weight loss. The MPR are then closed on the painted joint and
simultaneously the tubing is marked at the rig floor, using the index line (for the landing
string space-out discussed previously). Once the string is pulled up past the painted
stand, the exact location for the fluted hanger can be determined from the ram marks
and the internal dimensions of the BOP stack.
The fluted hanger is placed in the string in the proper position using pup joints. For a
typical floating test, 15 to 20 pup joints (minimum) of varying lengths are required. Some
w ill b e u se d fo r h a n d lin g p u p s (o n th e va rio u s te st to o ls), b u t m o st a re n e e d e d to
ensure proper subsea and landing string space-out.
13 - 150
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Once the final fluted hanger position has been determined by space out, the key
co m p o n e n ts o f th e la n d in g strin g a re in se rte d in to th e strin g , re p la cin g d u m m y
components used for space out. The subsea safety equipment (SSTT, retainer valve
and lubricator valve) is inserted as the string is RIH. The control lines for the subsea
safety equipment and any injection lines are run with the landing string at this time. The
seal assembly is stabbed in the bore, the string lowered until the fluted hanger is seated
on the wear bushing. If slip joints are utilized, the space out should allow them to be one-
half to two-thirds extended.
If in-place gravel packing is to be employed, then perforation will take place well before
the final test string is in place, and it will usually be done overbalanced with no flow to
surface. However, some of the main issues are the same for perforate-and-pack as the
perforate-and-flow operations. These are:
1. Type of gun, charge, shot density and phasing pattern.
2. How guns are to be fired.
3. If and when guns are to be dropped.
4. Type and location of bottomhole pressure gauges to run (if any).
5. Underbalance for perforation.
6. Type of cushion.
7. Well open at surface or closed at perforation.
8. Amount of flow desired immediately after perforation.
13 - 151
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
PERFORATING PROCEDURE
13 - 152
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 153
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
15. Mark tubing at rig floor using the index line, and note position of rig in tidal cycle.
Mark white painted stand in BOP stack by shutting VBR pipe rams on it.
16. Pull string up to painted stand and determine fluted hanger position.
17. P/U pre-assembled section consisting of crossover, fluted hanger, slick joint,
SSTT, shear sub, retainer valve.
18. Attach methanol injection lines. Attach control line bundle.
19. Function test SSTT tools, noting time to complete the disconnect via the control
hose umbilical. Note: The disconnect time will be the critical component of
emergency disconnect procedures, especially for dynamically positioned rigs.
20. RIH with rest of landing string, feeding control bundle and injection lines, affixing
to landing string with protective fixtures. Dual slips or special spiders made for
running umbilicals should be used.
21. P/U pre-assembled lubricator valve section, M/U, add control lines. Pressure test
assembly against tubing tester valve.
22. Add stiff joint(s) and space out flowhead with the bottom connection on the
surface test tree, spaced out such that it will remain at least 10 ft above the rig
floor at high tide and with rig heave.
13 - 154
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
23. Attach 40 to 45 ft long bails to support flowhead. M/U Coflex hose to wing valve
of flowhead and to the kill side of the flowhead (connected to cement unit).
24. Stab seals in GP packer. Observe weight while travelling additional distance prior
to seating the fluted hanger on wear bushing. Adjust motion compensator to
slack of the weight of the string below the fluted hanger. Lower master valve
should be at least 10 ft above the rig floor at high tide and upward rig heave.
25. Close middle VBR rams and test packer seals .
26. R/U Coflex hoses (kill side to cementing unit, flow side to choke manifold).
Close master and swab valves, open Manumatic valve, and flush across
flowhead, filling lines to choke manifold with completion fluid.
27. Close choke manifold, and pressure test equipment and connections from the
lubricator valve up through the surface spread and cementing unit. Close
Manumatic, bleed off pressure through choke manifold.
28. Close lower VBR rams and pressure annulus to unlock PCT from HOOP cycle
and disable the tubing tester valve. Bleed off to close PCT. Perfs are now
isolated by packer and closed PCT.
29. Cycle the circulating/reversing valve open with tubing pressure, and load the
tubing string with cushion fluid (base oil or diesel), being careful to not pump any
base oil into the annulus.
30. Cycle circulating/reversing valve closed. Note: The first hydrocarbon to surface
should occur only during daylight. Hence the PCT should remain closed until
ready to initiate flow.
31. Equalize pressure across the PCT valve by pressuring up on the tubing from the
cementing unit.
32. Line up choke manifold. Open PCT with annulus pressure.
33. Flow well as per the well test protocol.
13 - 155
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
1. Shut the well in at the PCT by bleeding the annular pressure to zero.
2. Keep the surface lines and choke manifold open and allow the test string
to depressure to 100 to 200 psi (monitor PCT for leaks). Then shut-in at
choke manifold.
3. R/U W/L lubricator, R/U Link SRO tool, pull up into lubricator barrel.
4. Isolate flowhead at wing (Manumatic) and kill line valves, close lubricator valve
below rig floor.
5. Pressure test W/L lubricator to lubricator valve with glycol-water mixture,
pressure test to 5000 psi. Bleed off pressure to equalize across lubricator valve
below rig floor, and open lubricator valve.
6. RIH with Link SRO tool and latch into DataLatch assembly, download memorized
data, monitor and record pressure buildup data real time at surface pressure.
7. Download data to external media every 4 hours or as requested by test engineer
or specialist.
8. When buildup is ended, POOH with Link SRO tool.
9. Bleed tubing pressure to zero and fill with diesel or base oil, close lubricator
valve, and P/U the BHS string into W/L lubricator barrel. Pressure test lubricator
using base oil (to prevent completion brine from contacting gas and forming
hydrates).
10. Pressure annulus to open PCT, cycle to hold open position. Note that on DP rigs,
wireline sampling is normally restricted to staying above the PCT valve, and the
PCT valve should never be cycled to hold open unit pulling out of the hole
following the test.
11. Load tubing with base oil, and pressure up flowhead to equalize pressures
across lubricator valve. Open valve, and RIH with BHS string.
12. Once samplers are in place, open well on small choke (#8 est.) and flow well at a
low rate as instructed by the EMEC testing specialist.
13. POOH with BHS string, close lubricator valve, and bleed off pressure above
lubricator valve. R/D BHS string from lubricator, check samples for validity
(buBble point pressure check).
14. When bottomhole samples are validated, R/D W/L lubricator, cycle PCT out
of hold open cycle to closed position with annular pressure cycles.
15. Reverse Out Test String.
16. Open upper master valve on flowhead and equalize pressures across
lubricator valve.
13 - 156
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
17. Open lubricator valve and apply tubing pressure cycles to open the MIRV.
18. Open Manumatic to surface equipment. Reverse circulate completion fluid, one
tubing volume above the MIRV. Stop when tubing is full of completion fluid.
19. Flush the surface lines.
20. Circulate completion fluid down tubing at 2 BPM to ensure MIRV open, increase
rate to 4 BPM, shut down pump when MIRV closes.
21. With tubing down to MIRV full of 10.3 ppg completion fluid, differential pressure
across PCT should be about 200 to 300 psi top down. This is OK to function
PCT, but check with last buildup pressure from SRO Data Latch.
22. Cycle annular pressure to lock PCT into hold open position. Well will probably
take fluid due to overbalance.
23. Bullhead 90 Bbls. of 10.3 ppg completion fluid into perfs, monitor well to
ensure dead.
24. Open lower VBR rams and pull seal assembly out of GP packer bore.
Reverse circulate two tubing volumes.
25. Open ram used for conventional reverse circulation and circulate bottoms up
conventionally.
26. POOH and lay down landing string and test string.
27. RIH with GP plug and sting into GP packer. Dump 20 ft of sand on plug.
28. Circulate inhibited kill wt. Completion fluid into the wellbore, POOH.
29. RIH and set cement retainer 150 ft below the mudline. Put 100 ft balanced
cement plug on top. POOH.
30. Pull BOP stack while laying down the riser.
31. RIH with corrosion cap, place on subsea wellhead, POOH.
32. Perform seafloor site survey with ROV.
13 - 157
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Pollution control is critical in offshore well testing. In most areas outside of USA,
produced hydrocarbons can be burned, and very little or no oil pollution or sheening
results. But regardless of the method of disposal, pollution control equipment should
be on hand in the event of an incidental oil loss.
When reversing out the tubing contents, take whatever precautions are required to
prevent mixing any oil contaminated completion or cushion fluid in with the completion
brine in the pits or annulus.
Do not discharge any completion fluid overboard prior to confirming that the fluid will
meet the requisite discharge criteria for the country in which you are operating.
One potential method of disposing of oil contaminated brine is to reinject it.
Make use of drip pans under major surface equipment and leak prone junctions.
Ensure that drip pans do not overflow.
Use absorbent pads under leak or spill prone areas where drip pans are not feasible.
If an uncontained spill does occur, make every effort to clean up with absorbent pads,
etc. Do not wash overboard and take care to ensure it does not enter drains.
Corrective action should be taken to contain any leaks or spills on the rig and clean them
u p , w ith o u t a n y o il re a ch in g th e w a te rs su rfa ce . O il sh e e n s ca u se d b y a ccid e n ta l sp ills
should be treated with dispersant. Dispersant will normally be applied by boom-mounted
systems temporarily mounted to a supply vessel or by portable eductor systems
o p e ra tin g w ith p re ssu re su p p lie d b y th e ve sse ls fire m a in . T h e fo llo w in g co rre ctive
actions will normally be followed in the event of an oil spill:
Supplies of dispersant will be maintained on a supply or support vessel.
Oil spill contingency plans are usually included in the operations manual and
addressed in the risk assessment.
Use workboat propellers to cause turbulence to promote mixing the dispersant
with the oil film.
Dispersant will be applied to oil films away from the rig using booms aboard
the workboat.
13 - 158
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
FIRE ON BOARD
Listed below is a general procedure example for securing the surface facilities and well
if a fire occurs during the test. Circumstances make the sequence of steps in this
procedure inappropriate, depending on the source, size and location of the fire.
1. Trigger the surface ESD system which will shut-in the well at the flow line
isolation valve (if present), and the Manumatic valve on the flowhead.
2. Activate the portion of the subsea safety system, which closes the ball valve on
the SSTT. Close the downhole shut-in valve (i.e. PCT).
3. Close the master valve and the crown valve.
4. With the cementing unit, pump water through the surface lines, separator and
burner to flush all hydrocarbons from surface equipment. Do not do this if fire
is being fed by leak in surface equipment.
5. Kill the well by bull heading and/or reverse circulating the well. Note: Be ready
to disconnect the subsea test tree at the hydraulic (or mechanical) latch and
the riser at the hydraulic connector in case the drilling vessel has to be moved
off location.
BAD WEATHER
Weather, such as high wind and waves and strong currents threatening to push a rig
off-station can necessitate an emergency disconnect. Emergency disconnect may also
be necessary because of a drive-off/drift-off, loss of mooring lines, the failure of
equipment or well control problems.
1. If there is a predictable, reasonable probability of losing station in the near future,
end the test and kill the well as follows:
a) Stop test by shutting well in at bottomhole tester valve. If wireline is in test string
POOH. Close master and swab valves.
b) Kill the well by displacing the tubing and the casing below the packer to the
bottom perforation with 10 barrels of base oil followed by kill weight completion
fluid. Over displace perforations by 5 barrels.
c) Monitor tubing and annulus pressure.
13 - 159
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 160
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
PRE-FLOW CHECKLIST
All surface equipment is pressure and function tested with the well open from tester
valve through to choke manifold, which is closed. Pressure is balanced across tester
valve. Downstream surface equipment is open. Separator is bypassed to surge tank.
Burner pilots are lit.
Barge, if used, is moored in position with flow line hooked up, tankermen (on rig and
barge) are in communication.
The main flow is not to begin in darkness, and not to begin if reservoir fluids will not
surface in daylight.
13 - 161
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
UNLOADING CURVE
An unloading curve should be prepared in advance (by the EMEC testing specialist)
using bottom hole pressure data and maximum pressure drawdown limits. It should be
used to help keep the bottomhole pressure drawdown within predetermined, acceptable
limits. It uses the simplifying assumptions that
1. No water is being produced from the zone.
2. Piston displacement of the load fluid occurs.
3. That frictional pressure drops are negligible.
These all combine to make this curve conservative. However, it should be honored until
we are reasonably certain that honoring it will kill the well. Recovery of completion fluids
lost to the formation, water influx, gravel pack failure (or screen plugging) or no effective
permeability will be the cause.
UNLOADING PRECAUTIONS
T h e o p e ra tive p h ra se h e re is E a sy d o e s it. N o th in g is g a in e d b y g e ttin g ro u g h with a
new well early on and irreparable damage can result. So usually the choke manifold is
configured with a No. 8 (1/8 in.) positive choke on one side, and the variable choke on
the other. Opening the well on a small choke initially ensures that either:
1. There is communication to the reservoir.
2. Or, there is a problem.
If there is a problem, opening the well on a large choke can aggravate the problem.
Note, however that the well should be brought on at a fast enough rate to ensure brine is
unloading from the wellbore.
13 - 162
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
After about 5 minutes of observing normal wellhead pressure behavior on the No.8 fixed
choke, the flowstream should be diverted to the variable choke side of the manifold to
proceed with the unloading. The flowing wellhead pressure should be controlled with the
variable choke to honor the unloading curve.
The well unloading should proceed honoring the unloading curve, which relates
minimum permissible flowing wellhead pressure to the cumulative volume of the cushion
produced. Because the flowstream is not normally routed through the separator at this
stage, some sort of gauging or a surge tank must be used to measure the cumulative
volume of cushion liquid produced. As well unloading progresses, the variable choke is
opened further as permitted by the unloading curve.
Normally a good well left on an appropriate choke setting will pretty much follow the
flowing wellhead pressure versus load water produced curve. In other words, a good
well will usually unload itself properly if it is properly choked back. However, sometimes
th e w e ll w o n t u n lo a d , a n d th e u n lo a ding curve can act as guide to help determine what
is going on.
13 - 163
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 164
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 165
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 166
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
SURGE TANK
If surge tanks are used, keep records of temperatures and pressures. These will be
needed to make adjustments to the separator shrinkage factor just measured.
HYDRATES
Follow the downhole methanol injection program until produced water rates, salinities,
wellhead pressure and temperature indicate adjustments should be made.
Watch for line frosting and monitor temperatures of surface equipment. Methanol
injection at surface may be required to supplement downhole injection.
13 - 167
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13.12.7 SAMPLING
Usually, three to four sets of surface separator samples are taken during the main flow
period. The first set is taken soon after flow has been routed through the separator,
water cuts are stable, and the separator rates and operating conditions are all stable.
This is a contingen cy sa m p le se t, a n d p ro b a b ly w o n t b e u se d if th e m a in flo w p ro ce e d s
successfully as scheduled.
The remaining three sets of separator samples should be taken under stable separator
conditions. If possible, the separator oil flow meter should be re-calibrated just prior
to sampling. A separator shrinkage measurement should be taken at this time.
Separator and surge tank temperatures and pressures should be recorded on the
appropriate forms.
The second set of separator samples is taken about midway through the main flow
period. The last two sets are normally taken right before the end of the main flow period.
Field samples are continued through the main flow. Sampling for H2S and CO2 should
continue through the test, even if none has been found so far. Trace amounts may show
late in the flow period. It is important to document where all of these routine samples are
obtained, and get these locations standardized among the service company personnel,
on all the shifts. Otherwise, results may be confusing.
13 - 168
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 169
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 170
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
PRODUCTION LOGGING
If the tested interval is not gravel packed, is thick, and appears to be layered or
non-uniform, production logging may be advised. Preparation for this operation is the
same as for bottom hole sampling via wireline, and the limitations for DP rigs are also
the same. Production logging may involve flowing the well at several rates with
intervening shut-in periods. Pay special attention to the possibility of hydrates forming.
If low salinity water is being produced in any quantity, wireline activities are not
recommended without a very carefully planned mitigation study.
13 - 171
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13.12.12 WRAP-UP
DATA COLLECTION
Before leaving the rig, the Test Specialist should obtain and check the pressure gauge
data from the bottommost gauges (non-SRO) after the test string is pulled. All surface
data and downhole pressure data should be collected as per Section 13.9.
PRELIMINARY REPORTING
The Test Specialist should complete preliminary buildup analysis before leaving the rig,
if p o ssib le . T h e P ro d u ctio n T e st S u m m a ry fo rm D -16 should be completed, and
distributed. It should be clearly noted that the results are preliminary. A preliminary draft
of a summary analysis of the overall testing operation what went well and what needs
improving, and any recommendations should be circulated to Drilling and
clients/partners as soon a practical.
Completion of the final report on the well test must await receipt of the PVT laboratory
analysis results on the samples.
13 - 172
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Two situations which require special planning and heightened precautions during the
execution of a deepwater production test are the possible presence of hydrogen
sulfide in the produced fluids and the likelihood of gas hydrate formation.
Unexpected, hazardous levels of H2S in the produced fluids can be extremely
dangerous and will probably require the test be terminated. The possibility of H2S in
deepwater well tests commands special attention due to the number of personnel on
the rig in a relatively confined situation.
Hydrate formation can restrict flow and prevent the passage of wireline tools, or even
completely plug the well flow path and bring the test to an abrupt halt. Dealing with the
aftermath of a complete plug-off and high trapped pressures in the test string is a
delicate and dangerous operation, not to mention time consuming. Deepwater wells are
much more prone to hydrate, especially near the mudline, than other wells. Hydrate
formation must be prevented through proper planning, use of inhibitive fluids and a
proper inhibition program.
Flow back testing is discussed at the end of this section only because it is a special
situation under production testing, not because it has any special connection to H2S or
gas hydrates.
13 - 173
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Hydrogen sulfide (H2S) is a corrosive and extremely toxic gas, ranking just beneath
hydrogen cyanide in the toxicity table. It is colorless, collects in low areas because it is
heavier than air, and is explosive over a very wide range of concentrations in air.
Fortunately H2S has an extremely offensive and penetrating odor at concentrations
well below lethal and even harmful concentrations. Unfortunately, after a short exposure
to m ild ly h a za rd o u s le ve ls o f H 2 S o n e s se n se o f sm e ll is to ta lly d e a d e n e d b y it.
The presence of H2S in the production stream requires special procedures for
conducting the well test and testing equipment that has metallurgical properties
compatible with the H2S environment. Most test equipment from leading suppliers
patronized by ExxonMobil will be specified to tolerate H2S at the very low maximum
levels generally considered safe from a deepwater operations perspective. However,
this should not be assumed across the board.
B u t te st e q u ip m e n t is u su a lly n o t th e w e a k lin k, e xce p t in h ig h te m p e ra tu re , h ig h
pressure H2S applications. Here, elastomer, seal and metallurgical technology may be
the weak link. H2S causes sulfide stress cracking or embrittlement of steels, depending
on steel composition, hardness, and presence of water. These hostile conditions
always require special engineering studies and equipment testing programs, as well
as safety programs.
DECISION TO PLAN FOR H2S
The potential for encountering H2S while well testing must be addressed during the well
test planning and design stages using all available pertinent data. Later, during drilling or
wireline formation testing, there will usually be some indication of H2S, if moderate to
high concentrations are present in the reservoir fluids, but not always. Moreover,
reservoirs with only trace to low concentrations of H2S (less than 10 to 20 ppm) may
not show measurable H2S content prior to flowing, even during the first several hours
o f flo w in g . T h is d e la y is ca u se d b y th e strip p in g a ctio n o f th e m u d filtra te (e sp e cia lly in
water-based muds) and to a lesser extent, the adsorption of H2S on steel surfaces
inside the test string. H2S is extremely soluble in water and quite soluble in oil. Water
can physically contain dissolved H2S in concentrations up to 29,000 ppm. So areas
where produced water or oil is vented to or open to the atmosphere may collect lethal
concentrations of H2S.
The decision to make special preparations for H2S usually hinges on the expectation
that H2S concentrations will exceed 10 ppm in the produced fluids. This is a safe, very
conservative H2S level guideline from the standpoint of toxicity to humans, because
10 ppm of H2S is considered harmless for 8 hours of continuous exposure, day in, day
out. There is another condition imposed by equipment considerations. It is that the
p a rtia l p re ssu re o f H 2 S m u st b e le ss th a n 0 .0 5 p si. T h is is e xp la in e d in H 2 S a n d
E q u ip m e n t b e lo w .
13 - 174
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 175
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 176
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The following safety procedures should be observed on all well tests where H2S is
known or expected.
1. Prior to beginning the well test, all personnel are briefed on the hazards of
hydrogen sulfide. A gas mask drill is held.
2. Each person on the rig floor, the testing crew and any associated support
personnel should have completed a certified H2S training program.
3. The test string should be of modified N-80 or lower yield strength. All sub-surface
test equipment must have a Rockwell C value of 22 or less.
4. Packers, seal assemblies, and BOP rubbers should be free from cuts and
scratches and made of H2S resistant material.
5. The rig floor and choke manifold, separator, and surge tank areas should be well
ventilated before the well is opened. Gauge tank areas for produced water, and
other areas where produced water is released to atmospheric pressure must be
very well ventilated and closely monitored.
6. Each individual who will be on the rig floor or working with the hydrocarbon
processing equipment (separator, burners, etc.) must have a self-contained
breathing apparatus suitable for hydrogen sulfide gas exposure.
7. Prior to formation fluid surfacing, the burners must be lit and operating on
supplemental fuel in a manner to ensure against flameouts.
8. Beginning at first gas to surface or when formation liquid surfaces, and at 15
minute intervals thereafter, the sour gas sniffer or Draeger tubes should be used
to determine if any H2S is present in samples bled off the choke manifold very
carefully through a very restrictive needle valve. If the gas has 20 ppm H2S or
more, all the following precautions will be observed:
a) All non-essential personnel will remain in the quarters and be prepared in the
event that transfer to the standby boat is necessary.
b) All personnel remaining on the drill floor and in the test equipment area will
wear continuous H2S monitors.
c) At 15 minute intervals, the sour gas sniffers, Draeger tubes or monitors
will be used to determine H2S concentrations throughout the vessel,
including the rig floor, separator area, accessible sunken areas (enter
closed areas only with breathing apparatus), other working areas, and the
living quarters area.
d) If the concentration in the air in any area exceeds 25 ppm, the well will be
shut-in and killed, and the test will be terminated until satisfactory corrective
action can be taken.
13 - 177
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
e) If H2S concentration reaches 50 ppm in the air in any area, in addition to the
well being shut-in, all test personnel not required for H2S control will be
alerted and assembled on the windward end of the vessel until acceptable
concentrations are attained.
f) The well will be shut-in at the bottomhole tester valve rather than the surface
valve, unless conditions warrant otherwise.
g) The separators will not be operated at pressures exceeding 75% of the
working pressure.
h) Sampling from the flow stream to the atmosphere, while necessary, should
be through restrictive needle valves, if possible, and into a semi-closed
co n ta in e r fo r sn iffin g w ith D ra e g e r tu b e s. T h is sa m p lin g sh o u ld b e o n ly
done when another person is observing.
i) H2S is extremely soluble in water and quite soluble in oil at high pressures,
but less so at low pressures. So areas where produced water or oil is
depressurized and vented could contain a hazardous buildup of H2S. Avoid
these areas if possible, entering only as required to make measurements,
with proper safety devices (Scott air packs) and observing partner. As a
practice, atmospheric tanks should not be used to store produced water if the
well contains H2S. Oil should not be stored in atmospheric tanks on the rig
regardless, and should not be barged without closed venting and H2S
removal systems.
j) The test string will be completely reverse circulated at least twice prior to
pulling out of the hole. If reverse circulation cannot be completed, the
operations office should be notified so that special preparations for pulling
the tubing wet can be made.
k) Under no circumstances should any person enter an area that has an H2S
concentration of 250 ppm or more unless wearing a self-contained fresh air
breathing apparatus.
l) Prior to the start of a production test, the chain of command should be clearly
identified so that someo n e is a va ila b le to a ssu m e e a ch p e rso n s
responsibilities should they become incapacitated.
13 - 178
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 179
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 180
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The possibility of gas hydrate formation in the flowstream is dictated by four factors:
1. The composition of the gas or gas/oil system.
2. The pressure.
3. The temperature.
4. The presence of water, and the amount of impurities (salt, CaCl2, inhibitor, etc)
in that water.
When all of the above factors are present, then it is said that hydrate formation is
th e rm o d yn a m ica lly fa vo re d . T h is m e a n s th a t h yd ra te fo rm a tion is possible, and any
formed will be stable at these conditions. In gas wells, with no oil present, hydrates will
fo rm ra p id ly w h e n e ve r fa vo re d , a n d ca u se p ro b le m s if fo rm e d in su fficie n t q u a n tity.
The maximum amount of hydrate that can be formed in most well testing situations will
be limited by the amount of water present. However, even small amounts of hydrates
may begin to stick at ID upsets or elbows, then collect, build up, and eventually form a
plug, stopping flow.
The basic parameter determinin g a p a rticu la r in h ib ito rs e ffe ctive n e ss is th e
concentration of the inhibitor in the water. The amount of total inhibitor required will be
proportional to water production, all other things being equal.
13 - 181
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The amount of produced water expected and its dissolved solids content are two of the
critical and basic input parameters used to design a hydrate inhibition program. More
needs to be said about them, because some past program designs have been based on
unrealistic assumptions regarding water salinity and rates.
Gas wells always produce a small amount of water vapor, some of which may condense
out somewhere in the well flow stream. This water existed in the gas phase with the
hydrocarbon gas in the reservoir, and so it contains no salt or other dissolved solids.
This water, whether in vapor or liquid phase, will readily form hydrates with light
hydrocarbon gasses under the conditions shown in Figure 13.26 (based on the
gas-condensed water system).
10000
Hydrates Possible
Pressure (PSI)
1000
No Hydrates
100
40 45 Figure
50 13.26 -55
Hydrate Formation
60 Graph
65 70 75 80
Temperature (Deg. F)
The good news here is that the gas in the reservoir can only carry a very limited amount
of water vapor with it, but if it condenses it is fresh water, which form hydrates very
easily in the deepwater environment. The exact amount depends on reservoir
temperature and pressure (it can be calculated), but it will vary from about 0.6 Bbl
to 2.5 Bbl of water per MMscf of gas.
13 - 182
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
It should be noted here that this 0.6 to 2.5 Bbl water might never condense out in the
separator. It may go out with the gas outlet to the flare line. Even though liquid water is
never measured in the separator, the flow stream may need to be inhibited.
Gas above a GOC or with no GWC may contain no water vapor at all. But for purposes
of designing the hydrate control program, it should be assumed that the gas may contain
water vapor, but certainly limited to the amounts just discussed (0.6 to 2.5 Bbls/MMscf).
Of course, if the gas well is
completed near a GWC, or the
formation evaluation is not clear
cut for mobile water saturations,
the completion may produce
formation water along with the
gas. If it were produced, this
formation water would likely be
produced in much greater
quantities than the gas-associated
water vapor discussed above.
However, this water will likely
contain varying amounts of salt,
which is a natural hydrate
inhibitor, as shown in
Figure 13.27. This figure shows
the effect of salt on hydrate
suppression parallels its effect on
freezing point suppression. A salt
concentration of 10% (or 100,000
ppm) by weight in water will
reduce the hydration temperature Figure 13.27 - Hydrate Depression Curve
by about 10F.
This water salinity of 10% is in the
ball park or low for most
deepwater reservoirs. The actual salinity of the formation water should be well known to
the project log analyst, as this parameter is a cornerstone for determining hydrocarbon
saturations in the reservoir. This information must be used to properly design the hydrate
inhibition program. For a rank wildcat, salinity information may be completely unknown.
Hydrate inhibition programs in the past were designed assuming that large amounts of
formation water might be produced with the gas, and that it would have no salinity. But
available salinity data should be taken into account. Those setting up the case study for
th e h yd ra te p re ve n tio n p ro g ra m n e e d to a sk th e te st c lie n ts fo r th e b e st e stim a te s o f
water salinity, and how much water production would be tolerated before the test is
terminated. The best available answers to these two questions should reduce excessive
predictions of methanol requirements.
13 - 183
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 184
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 185
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Figure 13.28 shows the results of flow stream temperature predictions at the wellhead
and mudline versus time prediction for a specific reservoir at one flow rate. The upper
curve represents the flow stream temperature response at the mudline. The simulation
shows that the well is in danger of hydrating below the mudline (i.e., below 71F) during
the first hour of flow, at the far-left side of the plot, therefore inhibition is required below
the mudline at test startup.
This is a good case to illustrate some real world complications that are difficult to
replicate in the model. The first is that there will actually be a 6 to 12 hour period in
which the rate is slowly ramped up during cleanup to the 25 MMscf/d in the case study.
The others are that the well may be loaded with a naturally inhibited cushion (base oil or
diesel), and later produce completion fluid, also inhibited. So the decision to go with
sub-mudline inhibitor injection is not clear cut.
90
80
Temperature (Deg F)
70
1 hour at risk: Mudline
Mudline Temperature
60 Surface Temperature
Hydrate Temperature = 71 F
50
40
30
20
Figure
0 13.28
5 - Flow
10 Stream
15 Temperature
20 Prediction
25 30 35 40 45 50
Time (hours)
T h e tie b re a ke r h e re is th a t if th e re is a n y p o in t in th e te st strin g w h e re yo u d o n t w a n t
hydrates to be formed, sticking and building up, its in the SSTT area. Hence, for gas
well tests in deepwater, it is most prudent to utilize sub-mudline injection equipment
(especially with DP rigs, where the chance for emergency disconnect is higher than
for a moored rig).
13 - 186
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
WELL FLOWING
Once the well starts flowing, the flow stream carries the deeper geothermal heat up to
the mudline, as shown in Figure 13.28, and in this simulation, the hydrate zone below
the mudline disappears within the hour. Caution is in order here. When kicking off the
well, often completion brine will be produced with the oil/gas mixture, flow rates will be
relatively low (little warming effects), temperatures at/near the mudline will be low, and
mudline pressures will be high. All these factors combine to make hydrate formation
very likely.
Once the mudline is reached, flowing well stream will start cooling quite dramatically in
deepwater well test, even at high flow rates. There is usually little or no effective
insulation from the very cold seawater, having a temperature of 30 to 35F. As a result,
flow stream temperatures at the rig floor in water depths over 4000 ft have been as low
as 55F for oil wells, and 50F for gas wells at high flow rates.
Note: The model predicts a wellhead temperature of 75 to 80F after warm up, whereas
the observed values are usually about 15 to 20F lower. This discrepancy may be due to
the fact that the model does not consider Joule Thompson cooling effects of the
expanding gas, or the heat transfer coefficients in the sea leg are too low. In this case,
the hydrate injection program must be adjusted to honor actual observed conditions of
temperature and pressure at the wellhead.
Another observation with deepwater tests has been that the flow stream temperatures at
the surface dropped with increasing production rates for both oil wells and gas wells.
At first thought, this is the opposite of what is expected! But for oil wells at least, this is a
sure indication that the flow stream cooled rapidly to a minimum temperature, lower than
the sea surface temperature, and was actually being re-warmed by the near surface
waters.
As a result, inhibitor injection at the SSTT in the BOP stack will be necessary in all
deepwater gas wells and sub-mudline injection is highly likely. The inhibitor volume
requirements will usually be higher than for injection below the mudline, because of the
much lower temperatures in the landing string. So two injection systems are necessary
unless the lower line can handle the total requirements. Even then, a second line may be
desired for backup.
Also, the warming trend with time shown for the wellhead temperature in Figure 13.28
was not observed on deepwater tests. Again, evidence that the sea has excess cooling
capacity, and does not heat up appreciably, even in the riser. So, inhibitor injection at the
SSTT in the BOP stack will usually be continued throughout the test in all deepwater gas
wells, unless there is no water production. The need for inhibitor injection below the
mudline may fade when the well warms there.
13 - 187
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 188
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
In deepwater gas wells hydrate inhibitor injection is usually required downhole, at least
as low as the BOP stack, and in some cases, below the BOP. Additional lines, surface
pneumatic pumps and injection subs will be required. The inhibitor injection line is run
with the SSTT control lines on the landing string.
Of course, injection below the BOP will require that a specially ported slick joint be
employed to get the inhibitor past the sealing pipe rams in the BOP. This slick joint has a
p o rt b o re d in its w a ll lo n g itu d in a lly to a cco m p lish th is. T h e in je ctio n lin e e n te rs th e
p o rte d slick jo in t a t th e to p , a b o ve th e se a lin g ra m s, a n d e xits a t th e b o tto m , b e lo w th e
sealing rams. Also, the SSTT is specially ported to handle the injection lines, so a
disconnect and reconnect can be done, and injection capability be re-established without
a trip of the landing string. Methanol is normally the inhibitor of choice, and 0.25-in.
minimum ID lines will be the minimum required. Early on, line crushing and subsequent
leakage has been a major problem, especially below the BOP. More recently, an
armored line is used that is much stronger and resistant to crushing. One example of this
improved line looks like Romex electric wire, but about five times the size. It is more or
less flat in shape, and each edge is embedded with a cable. The flow line is in the
center, protected in all dimensions.
Surface pumping equipment usually consists of low-rate high-pressure pumps, capable
of delivering several gal/min at 10,000 psi. For higher methanol injection needs, highly
specialized pumps and larger diameter (or special) umbilicals would be deployed.
This is generally a long lead-time item, and often has to be manufactured (including the
sub-mudline injection equipment and ported fluted hanger).
TOO MUCH INHIBITOR CAN CAUSE PROBLEMS
In the case of a gas well producing only condensed water vapor, an excess of inhibitor
causes no problems beyond waste, contaminating samples needlessly, and perhaps
inhibitor-water mixture disposal problems.
However, for any case in which moderate to high salinity water is being produced, care
must be taken because the common inhibitors (methanol and glycol) reduce the
solubility of salt in water. If sufficient inhibitor is injected into a flowstream containing
formation water with moderate to high salinity, salt will precipitate out in the tubing, and
possibly plug or restrict it. Again, a good hydrate prevention plan will incorporate the
best formation water salinity data available, and provide techniques for checking
methanol and salt concentrations in the produced water to verify that inhibition is
adequate. When producing a reservoir bounded by a salt dome, expect high salinity
water if any is produced.
INHIBITORS ARE NOT RECOVERED
Inhibitors that are injected into the flow stream are not recoverable. Methanol will be
distributed mainly in any water in the flow stream, then oil. A slight amount may be in the
gas. Methanol in the small quantities normally used should not cause any disposal (or
sales, in the case of oil) problems as it mixes and burns well. Large quantities of
methanol will dissolve water in oil.
13 - 189
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Methanol (or any other inhibitor) will contaminate any samples taken downstream of the
injection point. The amount of methanol used should be trimmed back as conditions
permit. Well before the test, in the program planning stage, it would be advisable to get
an opinion from the in-house and laboratory PVT experts on how much methanol can be
tolerated in the samples.
In some cases, such as the water cut falling to zero in an oil well after cleanup, injection
can be stopped. In other cases, it can be stopped for a short time before sampling if
hydrate indicators are watched carefully, and resumed after sampling. But time must be
allowed for the separator to flush out, and perhaps drain out the water leg. Methanol in
dry gas samples may not be a big problem.
13 - 190
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
The short answer is yes. The same conditions that determine formation in gas wells
apply to oil wells. But normally hydrates are not as big a problem as in gas wells. If the
o il is 1 0 0 % d ry, th e n h yd ra te s ca n t fo rm . B u t th is u su a lly isn t kn o w n p rio r to te stin g .
Other hydrate problems can be self-induced. Gas/brine mixtures usually occur during
initial clean up. In addition, water/brine knowingly or inadvertently introduced into the
tubing has caused serious hydrate problems (i.e. water used to test the wireline
lubricator flowed down to the mudline after the lubricator valve was opened, completely
plugging the tubing with hydrates).
Most oil flow streams will contain dissolved gas (methane, ethane, possibly CO2, H2S,
etc.). Most oil flow streams will contain at least some mix of formation and completion
water during cleanup, and small amounts afterwards for a day or so. So, at first glance,
all the factors are there for hydrate formation.
While laboratory studies have shown us that gas hydrates can indeed form in oil, they
fo rm q u ite slo w ly, re q u irin g fro m a n h o u r to a d a y o r so . M a ss tra n sfe r lim its th e ra te o f
hydrate formation in oil. This means that the hydrate forming components, methane and
water have to diffuse through the liquid oil phase to the mutual hydrate nucleation sites,
and this slows the formation. Once they do form in the oil phase, the hydrate crystals
tend to form as isolated flakes, or a loose mush or slurry, rather than a sticky,
mechanically competent mass capable of complete plugging. Another factor contributing
to making hydrates less of a problem in oil wells is that water produced with oil is a mix
of cushion fluid, completion fluid and water formation water and will usually have
inhibiting properties due to its salt or CaCl2 or other dissolved solids content.
Past conservative approaches to gas hydrate prevention in deepwater oilwell tests have
treated oil wells like gas wells. Subsea injection of methanol (up to several thousand feet
below the BOP in some cases) was employed if the hydrate formation map and tubing
pressure and temperature so indicated. But experience has borne out the observations
in the preceding paragraph. They explain why sub-mudline injection of inhibitor in oil
wells has not been necessary under conditions encountered to date.
Once above the mudline, the flow stream will get much cooler, and stay that way for a
relatively long time, so injection of inhibitor at the SSTT may be indicated in an oil well.
Therefore, sub-mudline injection of inhibitor in oil wells seems unnecessary because:
1. The load fluid is usually an inhibitor (or at least dry, in case of base oil cushion).
2. Produced water may be inhibited (dissolved salts).
3. Hydrates form slowly in oil, and will move above the SSTT injection point before
they can form prlblems.
4. The well will warm up below the mudline.
13 - 191
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 192
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Ideally, this study would model the entire well test (all flow and shut-in periods).
13 - 193
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Comments: The flow stream pressure and temperature profiles will probably be
calculated with WELLTEMP, perhaps with NODAL as a backup. The water rate is
usually given a wide range to URC. This is OK, if salinity is high, but water rates higher
than those or low salinities would cause drilling to call for the test to be ended. These
causes must be considered, as the drilling engineer must know the parameters that
could cause the test to be halted.
3. Find all of the hydrate prone areas in the test string as a function of time using
the hydrate map and the temperature and pressure profiles generated in Step 2,
above.
4. Design a subsurface hydrate inhibition system, the critical elements of the design
being:
a) The location(s) of injection of inhibitor.
b) The maximum rate of inhibitor, giving due consideration to fact that com-
pletion and cushion fluids are normally good hydrate inhibitors at start up.
Comments: The KEY decision to be reached here is whether or not inhibitor injection is
needed below the mudline. Sub-mudline injection complicates the system significantly.
Usually, this is not a close call for oil wells (because well heats sooner, hydrates form
more slowly, less likely to plug). For most deepwater gas wells, sub-mudline inhibitor
has been recommended to prevent hydrates in the near mudline (and critical
SSTT) area, especially during well startup. This is the worst possible place to have
a hydrate problem.
Sub-mudline injection requires a special ported slick joint to convey the inhibitor through
the BOP, as well as high-strength lines, and added pump capacity. Special protection
and precautions need to be taken to prevent the line being crushed in the annulus when
the APO tools are being operated. The injection sub, located perhaps 500 to 1500 ft
below the mudline, is often specially manufactured and not readily available.
5. From the modeling results, develop a rule-of-thumb on how the effectiveness and
need to adjust the methanol injection program can judged using field observable
parameters, such as:
a) WH temperatures and pressures.
b) Water cut, methanol content and salinity.
c) Signs of plugging, hydrate formation, such as:
- Quick drop in WHP and especially WHT.
- Loud, banging noises when a partial plug breaks loose.
d) Flow rate and elapsed time
6. In practice, we are limited by injection rate capacity (line size, pump pressure),
and may have less capacity than required for the high water rate case (which
URC usually includes). These high water rates are sometimes higher than drilling
would tolerate. Thus, we pump what we can, coordinate methanol injection with
water rates, consider salinities (we do not want to precipitate salt), monitor WHP
and WHT and remain alert for signs of hydrates.
13 - 194
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
Comments: When water rate goes down, we can reduce methanol injection rate, but
normally maintain a rate sufficient to keep about 30-35 volume % methanol (another
rule-of-thumb) in the water, unless water has salinity. Then we can back off some,
how much depends on salinity.
7. Remember, there will usually be water vapor in a gas well flow stream, so even if
the separator is not making liquid water some methanol is probably needed, but
only approximately 0.25 to 2 Bbl. Per MMscf of gas. The exact maximum amount
of water vapor that the gas can carry can be calculated from reservoir
temperature and pressure. Note that this water is essentially fresh, and is the
best type for forming hydrates. Formation water is another matter that must be
considered.
GENERAL OBSERVATIONS
1. Hydrate calculations are based on thermodynamic equilibrium, which does not
consider rate of formation.
2. Hydrate formation rate in gas is quite rapid, so kinetics are simpleco n sid e r
th e m fo rm e d .
3. Hydrate formation rate in gas dissolved in oil is much slower, sometimes taking
several hours to a day to form.
4. H yd ra te s fo rm e d in flo w in g o il d o n t stick a n d p lu g re a d ily, b u t te n d to flo a t a lo n g
as isolated crystals, or at worst, fo rm m u sh , w h ich d o e s flo w b u t w ith so m e
added resistance. The Blackback well, offshore Australia (circa 1995)
demonstrated this.
5. Because hydrates require water, and form slowly in oil, they usually are not a
problem in shut-in oil wells, except in the gas cap at the subsea wellhead area.
There usually is a gas cap there. So the well must be treated like a shut-in gas
well. Examples are Tierra del Fuego Salmon, circa 1970 (W/L entry blocked
after shut-in), and Xikomba-1 in Angola, circa 1999 (wireline samples stuck due
to hydrates in wellhead caused by water use to test the lubricator).
6. To mitigate hydrate formation problem in shut-in wells, we normally shut-in at
bottom and bleed off pressure above the tester valve, then pump a barrel or two
of methanol at the SSTT.
7. Observations may indicate the oil flow stream reaches its minimum temperature
quickly after it reaches the mudline, and is slowly warmed as it approaches
the rig by the near surface waters. Therefore, minimum depth for injection should
be at the SSTT.
13 - 195
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 196
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
PERSONNEL RESPONSIBILITIES
13 - 197
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
PURPOSE: The purpose of this document is to provide a query-style checklist for test
equipment to ensure a safe and successful operation. It is divided into 2 sections:
Items performed in the shop prior to load-out and items performed on the rig prior to
RIH. By writing directly on this list, complete each section of the checklist, sign/date it,
and provide a copy of Section 1 to ESSO representative on completion of the loadout,
and Section 2 on completion of RIH. If a particular item does not apply to the test at
h a n d (i.e g ra ve l p a ck vs. e xclu d e r), p le a se w rite N /A b e sid e th is ite m .
13 - 198
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
PERFORATING GUNS
1. Have sufficient guns been loaded out to accommodate the planned perforation
Interval?
2. Are the charge types in accordance with the program?
3. Have the perforation performance sheets been provided to the ESSO Engineer?
4. Has a preliminary detonation pressure for hydraulic firing heads been calculated
independently by Schlumberger and Esso and compared?
5. Is an adequate selection of rupture disks available and have rupture disk
calculations been performed and provided to the Esso Engineer?
6. Has the length from the lubricator sub landing point to the top shot been
measured? _____________
13 - 199
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 200
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
JARS
1. Prior to loadout, were the primary and backup tools fully function tested?
2. Are the primary and backup tools identical, or are they different types or models?
If different, explain.
3. What is the force needed to stroke the jars both up and down (both primary and
backup tools)?
4. What is the stroke of the jars (primary and backup)?
5. Were the tool joints inspected?
6. Prior to loadout, were the primary and backup tool bodies pressure tested (both
high and low) in the shop?
13 - 201
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
FLUTED HANGER
1. Is a backup fluted hanger available and has it been loaded out?
2. Are both the profile on the primary and backup fluted hangers identical to the
profile?
3. On the dummy hanger?
4. Is the fluted hanger compatible with the 10-3/4 in. wear bushing in the hole?
5. Will we make a dummy run with the same fluted hanger that will be run during
the well test?
6. Have the tools joints been inspected?
13 - 202
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
19. Have the ram sizes been checked to determine if they will seal on the slick joint?
20. Is the thickness of the ram blocks known and is it shown on the space out check?
21. Will the space out allow dual or single ram closure?
22. Is the SSTT pump through capable and has been function tested in the shop
prior to loadout?
RETAINER VALVE
1. Is a primary and backup tool available and have both been loaded out?
2. Are the primary and backup tools identical, or are they different types or models?
If different explain:
3. Is the retainer valve fail open or fail closed
4. Has the tool been serviced since the last job (ie: has the tool been broken down,
all seals been checked/changed, ball valve checked for scoring, metal sealing
surfaces checked for pitting/scoring)?
5. Has the retainer valve been function tested in the shop through the hose reel?
Time to close valve __________. Time to open valve ___________.
6. Was the body of the Retainer Valve pressure tested (LP and HP) in the shop
prior loadout?
7. Was the body of the Retainer Valve pressure tested (LP and HP) from above in
the shop prior loadout?
8. If used in conjunction with a bleed-off valve, has the bleeder valve been
function tested?
9. Have the tool joints been inspected?
10. If type RETV-DA is used (primary or BU), is the space out such that the spanner
joint is correctly located across an annular preventer? Are umbilical jumpers
available to reach from the RETV-DA to the SSTT?
LUBRICATOR VALVE
1. Is a primary and backup tool available and have both been loaded out?
2. Are the primary and backup tools identical, or are they different types or models?
If different explain.
3. What is the length of the control hoses that were loaded out, and is this sufficient
considering the placement of the valve in relation to the rig floor?
4. Has the tool been serviced since the last job (i.e. has the tool been broken down,
all seals been broken down, all seals been checked/changed, ball valve checked
for scoring, metal sealing surfaces checked for pitting/scoring)?
5. Have the lubricator valves been function and pressure tested (LP and LP) from
both directions prior to loadout?
6. Has the pump-through capability of the valve been tested in the shop? At what
pressure and flow rate?
7. Is the injection port open or plugged?
13 - 203
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
DATALATCH SYSTEM
1. Is the equipment needed to provide SRO of pressure below the SI valve?
2. Is the OD of the Powerline running tool small enough to allow it pass through all
then DST string components to reach the LCDA?
3. Do you have the needed equipment to splice the running tool onto the wireline
(including back- ups)?
4. Have you tested the SRO surface computer interface to ensure it is working
properly?
13 - 204
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
GENERAL INFORMATION
1. Are Lifting devices onsite for all of the downhole test tools?
2. Were all DST tools drifted to 2.125 in. on the rig prior to RIH?
3. Were all tools calipered and measured, on the rig prior to RIH?
4. If any of the dimensions differed from those on the DST stack-up sketches, were
the new dimensions provided to Esso representative so that space out
corrections could be made?
5. Were all tools function and pressure tested on the rig prior to RIH?
6. Were emergency procedures (yellow and red alarms) reviewed and understood
between Driver and the SSTT operator(s)?
TUBING TESTER VALVE (TFTV)
Unless otherwise indicated, provide information regarding the Primary tool.
1. Was the tool body pressure tested (both low and high) on the rig prior to RIH?
2. Was the flapper pressure tested (both high and low) from above prior to RIH?
3. Were all of the valve functions tested and verified to be in correct position for
RIH?
4. Are auto-fill ports open and functioning or are they plugged?
5. Has the rupture disk value been checked and agreed on by Esso and
Schlumberger?
6. What is the status of the backup tool?
13 - 205
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
FLUTED HANGER
Unless otherwise indicated, provide information regarding the Primary tool.
1. Did Esso, Schlumberger and the rig contractor all agree on the final SSTT/BOP
space out?
2. Was the fluted hanger set on the threaded mandrel in accordance with the
dimensions that all parties agreed to?
3. Was the SSTT /FLUTED hanger assembly measured immediately prior to RIH to
ensure consistency with requirements?
13 - 206
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
RETAINER VALVE
Unless otherwise indicated, provide information regarding the Primary tool.
1. Was the Retainer Valve function and pressure (LP and HP) tested on the rig
through the hose reel? Time to close valve ____________________
2. What is the status of the backup tool?
3. If type RETV-DA, is the space out such that the spanner joint is correctly located
across an annular preventer?
13 - 207
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
LUBRICATOR VALVE
Unless otherwise indicated, provide information regarding the Primary tool.
1. Was the Lubricator valve function and pressure tested (LP and HP) from both
directions on the rig prior to picking it up?
2. What is the status of the backup tool?
13 - 208
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
13 - 209
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
WELL TESTING OPERATIONS
REFERENCES
Chorneyko, David M., Simmons, A. Barlow, Patel, Harshad N., and Vela, Saul, The
ExxonMobil Exploration Company Well Testing Operations Manual, C o p yrig h t 2 0 0 0 ,
Chapter 11, pages 11-3 through 11-16), available on CD-ROM from EMEC Technology,
Formation Evaluation Group
C ra w fo rd , G a ry E ., P ie rce , A a ro n E ., E xp lo ra tio n W e ll T e stin g M a n u a l, Exxon
Production Research Company, July 1997, Section 11, Data Forms.
ExxonMobil Development Drilling, Drilling OIMS Manual, Second Edition, Section 3-10,
January 2002.
13 - 210
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14
Section
OBJECTIVES
This section will focus on some of the major attributes of subsea completion that differ
from typical offshore platform operations with the goal to gain a basic understanding of
the critical systems. The most significant differences between land or platform based
completion operations and subsea completion operations involve:
Describe the difference between single concentric and dual bore eccentric Vertical
Trees.
14 - 1
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
List the different types of subsea control systems and the application for
each system.
14 - 2
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
CONTENTS Page
14.0 SUBSEA COMPLETIONS .................................................................................................... 1
OBJECTIVES ........................................................................................................................ 1
14.1 OVERVIEW OF A SUBSEA COMPLETION ......................................................................... 4
14.1.1 PLANNING.............................................................................................................. 4
14.2 TREE SELECTION - HORIZONTAL VS. VERTICAL TREE ................................................. 6
14.2.1 SUBSEA TREE SELECTION ................................................................................. 6
14.2.1 VERTICAL TREES ................................................................................................. 7
14.2.3 E C C E N T R IC D U A L B O R E V E R T IC A L T R E E .................................................... 8
14.2.4 C O N C E N T R IC M O N O B O R E V E R T IC A L T R E E .............................................. 10
14.2.5 HORIZONTAL TREES .......................................................................................... 14
14.2.6 PARTIAL DRILLING HORIZONTAL TREE .......................................................... 15
14.2.7 FULL DRILLING HORIZONTAL TREE. ............................................................... 17
14.2.8 TREE SELECTION SUMMARY ............................................................................ 21
14.3 TUBING HANGER INSTALLATION ................................................................................... 23
14.3.1 TUBING HANGER ORIENTATION. ..................................................................... 23
14.3.2 ACTIVE HANGER ORIENTATION ....................................................................... 23
14.3.3 PASSIVE HANGER ORIENTATION..................................................................... 25
14.4 COMPLETION RISER ......................................................................................................... 26
14.4.1 DUAL BORE COMPLETION/WORKOVER RISER FOR
ECCENTRIC VERTICAL TREES ......................................................................... 26
14.4.2 ECCENTRIC VERTICAL TREE BARRIERS ........................................................ 29
14.4.3 MONO-BORE COMPLETION RISER FOR CONCENTRIC VERTICAL TREE .... 30
14.4.4 MONO-BORE COMPLETION RISER FOR HORIZONTAL TREES ..................... 30
14.4.5 LIFT FRAME ......................................................................................................... 31
14.4.6 RISER SUMMARY ................................................................................................ 33
14.5 SUBSEA TEST TREE CONTROLLED DISCONNECT ...................................................... 35
14.6 SUBSEA TREE CONTROL SYSTEMS .............................................................................. 38
14.7 SUBSEA TREE PREFERENCES ....................................................................................... 41
14.7.1 CASE STUDY TREE SELECTION FOR DEEPWATER GOM PROJECT ........ 42
14.8 REFERENCES .................................................................................................................... 44
14.9 WELL FLOWBACK SCHEMATIC FOR HORIZONTAL TREE............................................................ 45
14.10 BATCH SUBSEA TREE INSTALLATION ...................................................................................... 46
14 - 3
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14.1.1 PLANNING
Due to complexity and required operational features of the total subsea development
project, preplanning must start prior to procurement of the subsea tree and its related
equipment. It is important to ensure that all operational features of the tree and its
control system are identified and specified as early as possible. These must include:
All interfaces between the landing string, tubing hanger, subsea tree and control
system, and production tubing string must be evaluated. These may also include
control line requirements for the safety valve and chemical injection systems,
encapsulated conductors for downhole pressure/temperature monitoring
systems, intelligent completion components, and provisions for annular well
access and monitoring.
Rig related issues such as deck space, load capacity and equipment lay-out
plans need to be addressed as early as possible (oftentimes, even before the rig
is selected). This is mainly to ensure enough rig capacity and flexibility to perform
safe and efficient subsea operations under all anticipated environmental
conditions.
Operational envelopes for heave, pitch and roll and riser alignment for all critical
drilling and completion phases.
Prior to initiating offshore installation operations, a Systems Integration Test (SIT)
will generally be conducted. The functionality and operability of all related subsea
systems will be thoroughly tested at this time.
Batch Setting Plans (also reference appendix B)
Batch setting is an operational technique where multiple horizontal trees are run and set
at a given drill center to take advantage of operational efficiencies. Implementation of
this technique requires pre-investment in an extra conductor, referred to as a parking
14 - 4
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
stump. Additionally, all trees must be completed and delivered upon commencement of
drilling operations versus commencement of completion operations. As such, batch
setting requires substantial acceleration of the tree delivery schedule, therefore,
coordination among the Drilling and the Subsea Teams procuring trees is essential.
Batch setting benefits from learning curve acceleration because a procedure is repeated
many times over a short time frame and saves BOP trip time. The savings become more
and more significant as water depth increases.
Conductors are batch set on all wells at the subsea drill center plus one additional
parking stump. Trees are then run on drill pipe and landed on all conductors except the
conductor that is the initial drilling site. The BOP stack is then run, and drilling
commences. At the appropriate time for tree installation, the stack is disconnected from
the drill well and latched onto the tree from the adjacent conductor (the location of the
next drill well). The tree is then landed on the drill well to be completed. The process
eliminates a BOP round trip. This technique was used on the Diana, Marshall and Mica
developments. Estimated savings were approximately $1.2M per well.
14 - 5
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14 - 6
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14 - 7
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14.2.3 E C C E N T R IC D U A L B O R E V E R T IC A L T R E E
T h is tre e co n ce p t, a lso kn o w n a s a d u a l b o re V T , h a s tw o ve rtica l b o re s th ro u g h th e
tree body and tubing hanger as illustrated in Figure 14.2. In the Eccentric Vertical Tree
concept, the dual bore tubing hanger is eccentric and lands in the subsea wellhead
body. The eccentric design requires accurate orientation of the tubing hanger (TH) and
the tree. A detailed discussion of the TH orientation can be found in section 14.3.1.
The larger bore in the TH is for the production tubing which is suspended below the
hanger, and the smaller bore allows access to the production casing annulus. The
eccentric design does limit the production bore through the tubing hanger (typically a
5-1/2 in. x 2-3/8 in. bore when run in conjunction with 10-3/4 in. production casing).
Note: Some regulatory agencies require an annulus safety valve when dual bore trees
are utilized.
The annulus bore provides access to the production casing annulus and facilitates fluid
circulation and well control during tubing running or pulling operations when there are no
downhole mechanical barriers. The tubing hanger lands and seals in the subsea
wellhead body. This makes the tubing hanger independent from the VT itself.
The Eccentric Vertical Tree concept has a minimum of two subsea tree valves
(e.g. master and swab valves) located vertically above each bore (e.g., the production
tubing bore and production casing annulus bore). It is also common for the tubing
hanger spool to have a crossover connection between the production and annulus bore,
separated by an X-over valve (XOV).
This design provides vertical access through the vertical tree body to run or pull wireline
plugs that land into dedicated profiles in the dual bore tubing hanger. These wireline
plugs provide mechanical isolation to the tubing and production casing annulus for well
control. This becomes important during BOP removal/tree installation and during
workover operations. The Eccentric Vertical Tree concept has the production wing valve
outlet in the tree body at 90o to the production bore above the master valve. This diverts
the production flow stream horizontally, through the choke and mated connector to the
subsea flowline system.
14 - 8
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
SUMMARY OF ECCENTRIC VT
Two eccentric vertical bores through tubing hanger.
Tubing hanger lands in subsea wellhead (active alignment).
Flow diverted horizontally after master valve.
Tree installed with dual bore completion riser (open water).
Through tubing workovers no plugs to pull.
The typical steps to run the tubing and Eccentric VT are as follows:
1. Production tubing/TH is run via a dual bore completion riser and landed in the
subsea wellhead. This system will be run through the drilling riser/BOP.
2. Flow barriers (wire line plugs) are run and set in the tubing hanger. The
completion riser and drilling riser/BOP are pulled.
3. The VT is run via a dual bore completion riser/BOP.
4. The flow barriers are removed, and either the well is allowed to flow back to
surface via the completion riser, or the tree cap is run and the well flows through
the subsea manifold/pipeline.
14 - 9
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
4.2.4 C O N C E N T R IC M O N O B O R E V E R T IC A L T R E E
The Concentric VT concept uses a mono bore tubing hanger that is concentric and sets
in a tubing hanger spool landed above the subsea wellhead. The concentric design does
not limit the production bore through the tubing hanger, therefore a larger tubing string
can be used. For this tree concept, the flowpath for the production casing annulus is
around the concentric tubing hanger through side outlets machined in the tubing hanger
spool below and above the hanger as shown in Figure 14.3. The tubing hanger lands
and seals in the subsea wellhead body. This makes the tubing hanger independent from
the VT itself.
The Concentric Vertical Tree concept has a minimum of two subsea tree valves
(e.g. master and swab valves) for both the production tubing and casing.
This design provides vertical access through the vertical tree body to run or pull wireline
plugs that land into dedicated profiles in the mono bore tubing hanger. These wireline
plugs provide mechanical isolation to the production tubing only. The production casing
is isolated with a valve in the tubing spool body. This becomes important during BOP
removal/tree installation and during workover operations. The Concentric Vertical Tree
concept has the production wing valve outlet in the tree body at 90 degrees to the
production bore above the master valve. This diverts the production flow stream
horizontally, through the choke and mated connector to the subsea flowline system.
14 - 10
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
SUMMARY OF CONCENTRIC VT
Single concentric bore through tubing hanger.
Tubing hanger lands in tubing hanger spool (passive alignment).
Flowbase design allows tree retrieval without pulling jumper.
Tree installed with mono bore completion riser (open water).
Additional permanent leak path (tree/tubing hanger spool).
The typical steps to run the tubing and Concentric VT are as follows:
1. Flow barriers (wire line plugs) are run and set in the production casing.
2. The drilling riser/BOP is pulled.
3. The tubing hanger spool is run with DP.
4. Once the spool is landed the DP is pulled.
5. The drilling riser/BOP is run and the flow barriers are removed.
6. Production tubing/TH is run via a mono bore completion riser and landed in the
tubing spool. This system will be run through the drilling riser/BOP.
7. Flow barriers (wire line plugs) are run and set in the tubing hanger.
8. The completion riser and drilling riser/BOP are pulled.
9. The VT is run via the mono bore completion riser/BOP with a hose or small string
of tubing to maintain access to the production annuals.
10. The flow barriers are removed and either the well is allowed to flow back to
surface via the completion riser or the tree cap is ran and the well flows through
the subsea manifold/pipeline.
14 - 11
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14 - 12
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
VT Body
Manifold/Template
Connection
Tubing
Hanger
Tubing Hanger
Manifold Spool
Connection
Flow Base
18 3/4" Subsea Wellhead
Tubing Hanger
14 - 13
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14 - 14
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14 - 15
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
The Partial Drilling HT concept was used for the following projects:
Diana, Marshall, Madison (ExxonMobil GOM)
Mica (ExxonMobil GOM) (Figure 14.4)
Kizomba (ExxonMobil Angola)
14 - 16
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14 - 17
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
The Full Drilling HT concept was used for the following projects:
Dalia (Total Fina Elf Block 17 Offshore Angola)
Ross (Talisman Energy North Sea UK)
14 - 18
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14 - 19
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
Permanent
Wireline Plug
Manifold
Connection
Production Outlet
18 3/4" HP Wellhead
9-5/8 C asin g H an g er
Figure 14.5 Partial Drilling HT
HT Body
Production Casing Access
Permanent
Wireline Plug
Manifold
Connection
Production Outlet
14 - 20
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14 - 21
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
For deepwater operations, horizontal trees provide a number of key advantages over
vertical trees.
When cleaning up and testing a subsea well to a Mobile Offshore Drilling Unit
(MODU), two independent well control systems are fully functional. First, the
subsea test tree with shut-in and disconnect functions, provides the primary well
control system. Second, the rig blowout prevention stack (BOP) provides
shearing and disconnect capabilities in the event of a subsea test tree failure.
As a result, well control risk is substantially reduced.
Horizontal trees can be batch set on the subsea wellhead before
commencement of completion operations; thus reducing overall installation
times, equipment costs and complexities of vertical trees.
T o d a te , in d u stry h a s p rim a rily u tilize d th e P a rtia l D rillin g H T co n ce p t. H isto rica lly, th e
"Full Drilling" HT concept has only been used for slim hole casing programs in single,
subsea well developments. This is because much of the savings potential of the full
drilling horizontal (elimination of stack pulling operations) is quickly offset by the
efficiencies gained by batch drilling and setting the trees at a particular drill center.
The following sections focus on the tubing hanger installation and the completion riser.
14 - 22
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14 - 23
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
The TH is automatically rotated to the correct position when the orientation pin is
engaged into the Alignment Helix. Once in the correct position, the orientation pin will
drop into a vertical slot in the THRT body. Indication of correct position of the pin is
monitored using an ROV. Once oriented and landed, the TH integrity can be pressure
tested through kill/choke line, with the annular preventer closed against the THRT body.
Minimizing riser ball joint angle is important during this installation due to the tight
clearances between the marine riser/BOP and THRT/TH. Typically, the maximum
allowable riser ball joint angle is1.5. Rig heave is also important and should be limited
to ~1.5 m (5 ft). During landing and orientation operations, the heave compensation
system should be engaged.
Due to interface and alignment issues between the subsea wellhead, tubing hanger and
subsea tree, operators typically select the same vendor to provide the subsea wellhead
a n d su b se a tre e w h e n u sin g th e E cce n tric V e rtica l T re e o r d u a l b o re co n ce p t.
Examples are the Zinc, Balder, and Blackback projects. ExxonMobil and its affiliates
have mixed subsea wellhead and tree vendors successfully with the Eccentric Vertical
Tree concept on the Zafiro project in Equatorial Guinea, but not without additional cost
and time to develop and approve the orientation system.
Tubing Hanger
THRT
Tubing
Slips
Figure 14.8 - Tubing Hanger and THRT for the Zinc Eccentric Vertical
Tree
14 - 24
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
Stack-Up Test
d ry ru n
THRT
THRT
Quad
Penetraters
Tubing Hanger
Tubing
Hanger
False
Rotary
Figure 14.9 - Tubing Hanger and THRT for Mica Partial Drilling Horizontal Tree
14 - 25
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14 - 26
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
The riser has a separate stress joint installed on the bottom of the string, as well as
tension joint and protected landing joint used at surface. The landing joint needs to be
properly spaced out to allow heave related rig movements. A separate riser tensioning
system is connected to the tension joint.
For production testing purposes, a dual bore surface tree is also required. This tree is
equipped with top lubricator connectors for wireline access through either bore
(Figure 14.11).
Lift Frame
Annular Wing Valve
Swab Valves
X-Over Valve
Prod. Wing Valve
Rotary Table
Riser Connection
Umbilical
EDP
Swab Valves
LMRP
X-Over Valve
Sheer Rams
Gripper Rams
WH Connector
Manifold/Template
Connection
Tubing
Hanger
14 - 27
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
This same dual bore completion/workover riser system is used to run the Eccentric
Vertical Tree body after pulling the 18-3/4 in. BOP stack. The significant components of
the completion/workover system are the Lower Marine Riser Package (LMRP) and the
Emergency Disconnect Package (EDP). The LMRP includes a small bore workover BOP
stack providing coil tubing and wireline shear rams, a master valve and a crossover
valve. See Figure 14.12.
When perforating or gravel packing a subsea well having a vertical tree, operators
typically run an additional downhole barrier prior to running the tubing hanger assembly
and pulling the BOP stack to install the vertical tree. The three common methods used
are:
1. Installation of another production packer with an isolation string across the
completion interval,
2. Some type of downhole tubing plug, or
3. A full bore isolation valve.
14 - 28
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
ANN
ANN.
Shear Sub
SHEAR/
Flapper Valve SEAL
VBR
Sen Tree 7
Lower Ball Valve PIPE
Slick Joint
VBR
THRT
Tubing Hanger
14 - 29
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
Typically, well clean-up is performed after the production tree has been installed.
Primary well control at the seafloor is provided by the LMRP, a small bore workover
BOP installed on top of the vertical tree body. Additionally, the two master and two swab
valves in the vertical tree body for the production tubing and production casing annulus
can provide additional barriers.
One of the concerns with the eccentric vertical tree system is that during operations
when hydrocarbons are surfaced, drilling operations personnel will be relying on a
completion riser system that they may have little experience with. Therefore, it is
important to train the drilling operations personnel for these vertical tree installations.
Another concern with this concept is that these completion/workover systems may suffer
from lack of maintenance after the initial installation operations are completed. Proper
maintenance and inspection of the riser system and its connectors is essential.
14 - 30
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14 - 31
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
Schlumberger
7-3/8 10k Flowhead
1 0 -3 /4 H and lin g
Sub
Hydraulic Operated
Coflex Swab Valve
Support
Failsafe
Actuator Failsafe Actuator
Production
Kill Line Line #1
Dynamic Swivel
Hydraulic Operated
Master Valve
14 - 32
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14 - 33
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
Production Tubing
(landing string)
ANNULAR
Emergency
ANNULAR
Disconnect
Emergency Package
Disconnect BLIND SHEAR
Package
BLIND SHEAR
SUPER SHEAR
4 Ram 18-3/4 B O P
PIPE PIPE
3-Ram BSR
Workover BOP PR
VBR PIPE
Subsea Test Tree
PSR
VBR PIPE
THRT
VT Body
Tubing
Spool HT Body
14 - 34
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14 - 35
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
Packoff Sub
Retainer Valve
Shear Joint
Latch Connector
Flapper Valve
Ball Valve
Slick Joint
Tubing Hanger
Running Tool
14 - 36
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
The design of the subsea completion and test tree centers on the ability to perform a
controlled disconnect. To ensure hydrocarbon fluid isolation, the subsea test tree valves
operate in a very specific order:
1. The lower ball valve and then the flapper valve close shutting off the flow from
the wellbore.
2. The retainer valve above the latch closes to contain fluid in the landing string.
3. The small amount of fluid trapped between the flapper and retainer valve is bled
off into the drilling riser.
4. The latch disconnects allowing the upper section to be pulled clear of the BOP
stack.
5. If the drilling riser is also going to be disconnected, the BOP blind rams will then
close and the drilling riser disconnected.
6. The vessel can then move off location leaving the well fully controlled.
For subsea tree concepts that utilize a 21 in. drilling riser during well clean-up
operations, a key well control issue is a connection leak where gas escapes from the
landing string into the riser. Diverter operations would be required in water depths where
the gas could expand significantly as it rises to the surface. This risk can be mitigated by
using new production tubing with premium connectors for the landing string of each
subsea well or by conducting a thorough inspection between wells. The tubing selected
must be specifically qualified for service as a mono-bore completion riser. Vendor
provided mono-bore risers can also considered, but since the connections would need to
be designed for use on multiple wells and have a longer useable life, the cost of this
option may not be economically justified.
14 - 37
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14 - 38
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
Gooseneck
IW O C S (3 .3 5 O D )
being clamped to the
tubing landing string.
Figure 14.19 - S chlum bergers S enT ree 7 T est T ree A nd C om m ander H ydraulic C ontrol System
Provides 120 Second Response Time
14 - 39
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
SenTree 7
Accumulator Module
Figure 14.20 Sen Tree 7 test tree and Commander telemetry control system providing a 15
second response time.
14 - 40
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
The subsea tree is only one part of a larger subsea system as shown in Figure 14.21
that includes subsea templates or manifolds, subsea flowlines and pipelines, as well as
subsea control systems. The budget for design and procurement of subsea trees is
usually part of the overall budget for the subsea system, which is managed by the
subsea or facilities group within a project team. The budget for installing the subsea
trees is usually part of the drilling and completion budget. Consequently, the focus of the
drilling and completion group has been to install the subsea tree and related equipment
safely and efficiently.
14 - 41
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
Additionally, the future availability of the leased completion/workover riser system for
workovers was identified as a concern. Purchase of a dual bore completion/workover
riser system for the small number of wells in the development could not be justified. The
analysis suggested that selection of the Horizontal Tree would result in an average
savings of about $800k/well.
Even though the horizontal tree concept had not previously been used at the required
water depth (~4,650 feet of water), the drilling organization supported the HT
recommendation, since it appeared that it had greater potential to reduce completion
installation time and costs.
14 - 42
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
Use of the Eccentric Vertical Tree concept and dual bore completion/workover riser
system could expose operations to potential weather delays if offloading of the drilling
riser was required due to deck space limitations on MODU. Drilling estimated that
weather delays offloading or loading riser could add $1.0M per well if sufficient boats
were not available to conduct these operations out of critical path.
Actual installation times for horizontal trees installed at the Diana field were compared to
the vertical trees installed at the Zinc field. This comparison showed an average savings
of 6.7 days per well for horizontal trees using a single derrick MODU. Minimizing tripping
of the BOP stack and batch installation operations were key drivers to this savings in
time achieved at Diana. Additionally, the elimination of the completion/workover riser
system by using the MODUs drilling riser increased available deck space for other
completion equipment and decreased overall cost.
The HT concept provided future flexibility by being able to use existing drilling risers from
many different MODUs. Assumptions for well intervention can also contribute to the
subsea tree selection decision. The ability to sidetrack and re-drill through the HT further
reduces costs since sidetracks can be performed without pulling the HT. One sidetrack
re-drill through the horizontal tree has already been performed at Diana, and the
development plan anticipates future sidetrack re-drill opportunities. Drilling operations
personnel also preferred the SSTT system and the MODU BOP stack for well control
instead of a specialized completion/workover riser system that included a workover BOP
and EDP. The decision to use the production tubing as the landing string also provided
additional cost savings to the project.
Marshall-Madison:
3 T rees, 4600 W D
2000 / 2001
14 - 43
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14.8 REFERENCES
1. Towns, T. K., Deeken, D. G., Derby, L. M.,ExxonMobilDevelopment Company,
D ia n a S u b se a T re e S e le ctio n a n d In sta lla tio n R e su lts in 4 ,6 5 3 F e e t o f W a te r D e e p
Offshore Technology held in Rio de Janeiro, Brazil, October 17-19, 2001.
2. Moyer, M.C., Barry, M.D., Tears, N.C., "Hoover-Diana Deepwater Drilling and
Completions", OTC 13081, Offshore Technology Conference, Houston, Tx, May
2001.
3. S e n T R E E S u b se a W e ll C o n tro l S e rvice s S ch lu m b e rg e r, A p ril 2 0 0 1
4. S u b se a S o lu tio n s, S ch lu m b e rg e r, W in te r 1 9 9 9 /2 0 0 0
14 - 44
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
14 - 45
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
SUBSEA COMPLETIONS
U ncle J ohn
Figure S upport
14.25 V essel
Uncle Subsea
John SupportTree Batch
Vessel Installation
Subsea LayoutInstallation Layout
Tree Batch
14 - 46
EXXONMOBIL FLOATING DRILLING SCHOOL 2002 EDITION
ABANDONMENT OPERATIONS
15
Section
OBJECTIVES
On completion of this section, you will be able to:
Describe the differences between abandonment operations from a floating rig and
fixed structure.
Describe the process required to handle trapped gas when retrieving a seal
assembly from the wellhead.
Describe the various methods to cur and retrieve the structural and conductor casing
strings, wellheads, and guidebases.
15-1
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
CONTENTS Page
15-2
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
15.1 INTRODUCTION
Offshore exploration and many appraisal type wells are normally plugged and
abandoned following a formation evaluation program. The abandonment is necessary to
permanently isolate all hydrocarbon and permeable abnormally pressured water zones
to prevent communication between zones. The abandonment also prevents potential
migration of wellbore fluids to the seafloor and escaping into the ocean. All
abandonments should be conducted under the assumption that ExxonMobil will remain
re sp o n sib le fo r th e w e lls co n d itio n long after the abandonment and terms of the lease
expire. Methods to either temporarily or permanently abandon a wellbore will be dictated
b y lo ca l g o ve rn m e n ta l re g u la to ry a g e n cie s, b u t in g e n e ra l te rm s, E xxo n M o b ils g o a l is to
ensure that the wellbore is securely plugged and isolated.
15-3
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
15-4
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
15-5
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
15-6
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
15-7
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
3 0 L o w P re ssu re
To isolate the shoe with a balanced cement plug, Wellhead
the stinger is placed at depth in the open hole, and
drilling fluid is circulated to ensure that mud
densities within the wellbore are balanced prior to Structural Casing
cementing. If required, a high viscosity mud spacer
may be spotted in the open hole to support the
cement plug. 2 0 C a sin g
Figure 15.3
Isolating Casing Shoe
15-8
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
Fixed Length
Heave
15-9
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
When cementing through a retainer, the cement is typically circulated into drill string with
the retainer setting tool/stinger unstung from the retainer. While circulating the cement
into the drill string, sufficient backpressure must be held on the annulus to prevent the
cement from U-tubing out of the drill string and up into the annulus. On floating rigs, this
is typically done with the annular preventer closed while taking returns through a
choke/kill line to the choke manifold. The backpressure to prevent U-tubing is maintained
by adjusting a choke on the choke manifold. Due to the friction pressure in the long
choke/kill lines, the actual pressure held on the annulus will be increased by an amount
equal to the Choke Line Friction Pressure (CLFP).
15-10
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
Figure 15.5
Isolating Liner Tops
15-11
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
15-12
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
During the P&A process, each annular space between casing strings within the wellhead
should be tested for communications with the open hole. Any annulus in communication
with the open hole should be sealed with a mechanical plug and/or cement and tested.
In most cases, this will mean cutting and pulling an inner string of casing to get access to
the annulus. Removal of the casing will also allow access to the outer casing that will
also need to be cut and recovered. Figure 15.6 depicts a wellbore where the 9-5/8 in.
casing has been cut and removed and the annulus sealed with cement. Since the
9-5/8 in. and 13-3/8 in. annulus are both unsealed, each casing annulus must be
plugged and abandoned separately.
18-3 /4 1 0 K o r 1 5 K W e llh e a d
3 0 L o w P re ssu re W e llh e a d
Structural Casing
2 0 C a sin g
9-5 /8 C a sin g
7 L in e r
Hydrocarbon Zone
Figure 15.6
Plugging Annular Spaces
15-13
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
Seal Assembly
Released Position
Seal Assembly
Latched to wellhead Casing Hanger
Figure 15.7 Vetco Seal Assembly Retrieval Tool Latched into seal and pulling seal free
15-14
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
In either case, the seal assembly can be retrieved either before or after the casing has
been cut. The advantage to retrieving the seal assembly before cutting the casing is that
trapped gas, if present, can be handled separately and not be a concern while cutting
the casing.
The process to remove the seal assembly is complicated by the possibility that trapped
gas may have built up under the seal assembly over time. To prevent release of the
trapped gas into the riser, removal of the seal assembly must be done very carefully,
taking into account well control and the possibility of hydrates forming in the BOP stack.
To retrieve the seal assembly, a seal assembly retrieval tool is run to the wellhead on
drill pipe, and a BOP is closed to prevent accidental release of any trapped gas into the
riser as the seal is pulled free. Typically, an annular preventer is used during the seal
removal to simplify stripping the drill pipe up through the BOPs. If a side outlet is not
directly below the annular, a pipe ram should be considered to minimize the volume of
gas that may be trapped in the BOP stack afterwards. Since a BOP will need to be
closed while the seal assembly is retrieved, drill pipe should always be placed
immediately above the retrieval tool so that drill pipe will be across the BOP stack
during the retrieval.
After latching the retrieval tool into the seal assembly Figure 15.8, valves to the choke
and kill line outlets below the closed preventer on the stack are opened to monitor for
pressure and circulate across the stack. This removes any trapped gas that may have
be released. After the seal is pulled free Figure 15.9, the stack should be swept by
pumping down one line, across the stack, and up the other line to the gas buster. After
sweeping the stack, the preventer is opened, and the riser is circulated to remove any
residual trapped gas in the stack or that may be released into the riser. After circulating
the riser, the seal assembly can be recovered to the surface.
To minimize the possibility of hydrates forming in the BOP stack or choke/kill lines when
the seal is released, an inhibited fluid should be considered to sweep the BOP after the
seal is released. If using a water-base mud, a concentration of mud and glycol can be
mixed to sweep the BOP stack.
15-15
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
Annular Closed
Figure 15.8 Seal Retrieval Tool Figure 15.9 Seal Assembly Pull Free with
Latched into Seal Assembly Annular Closed. Circulating Across BOP
Stack
15-16
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
ONE-TRIP SYSTEM
O n th e o n e -trip syste m , th e ca sin g cu tte r is sp a ce d o u t b e lo w th e spear to place the
cutter at the cut point when the spear lands in the hanger. The advantage of this system
is that the cut can be confirmed immediately after it is made, and the additional trip to
ru n th e sp e a r is sa ve d . T h e d isa d va n ta g e to th e o n e -trip system is that a packoff
cannot be run with the spear since it would prevent circulation while cutting the casing.
The use of a packoff with the spear allows the casing-by-casing annulus to be circulated
to free the casing or remove contaminated mud. When pulling out of the hole with the
one-trip system, the casing is landed in the rotary and the cutting assembly is pulled
from the casing while working with a false rotary. Tripping pipe with a false rotary can
add several hours to the normal trip time required to pull the cutting assembly from
the wellbore.
TWO-TRIP SYSTEM
O n a tw o -trip syste m , th e ca sin g cu tte r is ru n o n th e first trip to cu t th e ca sin g , a n d th e
spear is made-up and run to the wellhead on the second trip to recover the casing. The
advantage of this system is that a packoff can be run with the spear to allow the casing
annulus to be circulated to remove contaminated mud and assist in freeing the casing.
The disadvantage to this system is that an additional trip is required to spear the casing,
and the cut cannot be confirmed until the second trip with the spear. If well control is a
concern while recovering the casing, the two-trip method offers the most protection since
a packoff can be run and a double string (drill pipe inside casing) of pipe is not across
the BOP stack.
In w a te r d e p th s le ss th a n 1 ,0 0 0 ft, th e tw o -trip syste m m a y b e p re fe rre d sin ce th e trip
times to the wellhead are relatively short and quick and outweigh the additional handling
time required to make-u p th e o n e -trip system, and also outweigh the additional time
required to simultaneously pull out of the hole with the cutting assembly and casing.
15-17
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
CASING CUTTER
Depending on the size of casing to be cut, a casing cutter body is selected that will
provide the necessary sweep of the blades to cut the casing. Table 15.1 shows cutter
arm lengths for various casing sizes. Blades Figure 15.10 are dressed with tungsten
carbide on the cutting surfaces. When cutting casing that is 16 in. or smaller, the motion
compensator on most rigs can adequately compensate for rig heave. If the motion
compensator cannot adequately keep the pipe stationary, a marine swivel can be run
and landed out in the wellhead.
Cutter Body Casing Size Length of Max. Cutter Pump Est. Time to
O.D. (inches) (inches) Cutter Arms Diameter Pressure (psi) Make Cut
(inches) (inches) (minutes)
8 3 /8 9 5 /8 3 12 1200 5
8 3 /8 10 6 18 1200 5
8 3 /8 11 6 18 1200 10
11 1 3 3 /8 7 19 100 200 15
11 16 7 19 100 200 15
11 20 15 36 200 400 20
11 30 23 52 400 600 30
11 36 23 52 400 600 45
11 48 31 69 600 120
11 60 31 69 600 180
15-18
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
Figure 15.11 details the major components of a casing mill cutter. The casing cutter is a
simple hydraulic tool with a piston that is forced downward by pump pressure that
extends a set of knives outward against the casing. The top drive is engaged, and a slow
rotary speed is set for maximum torque to be maintained until the casing is cut, usually
only a few minutes Figure 15.12 for casing sizes 13 3/8 in. and smaller. Once the casing
is cut through, it is important that the fluid level in the hole be maintained for losses, in
the event there is a void behind the casing.
In our example of removing a string of 9-5/8 in. casing, an 8-1/4 in. body casing cutter is
used dressed with knives to open wide enough to assure that the casing is cut cleanly as
shown in Figure 15.9.
9 5 /8 C asing
13 3 /8 C asing
Casing Cutter
15-19
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
CASING SPEAR
The casing spear used for P&A operations on a floating rig is the same as that used on a
rig with a surface BOP stack. The casing spear is typically run with a spear stop and set
in the casing hanger. A sp ear sto p is important when operating from a floating rig
since rig heave could reset the spear deeper in the casing with each upward heave.
To provide a seal inside the casing at the spear, a pack-off can be run to allow
circulation up the backside of the casing. Circulation may be required to free stuck
casing or prevent swabbing while retrieving casing with a small annulus clearance.
W h e n a o n e -trip cu t a n d p u ll syste m is u se d , th e p a cko ff ca n n o t b e ru n w ith th e sp e a r
since it would prevent circulation while cutting the casing.
When retrieving the casing hanger/spear up through the BOP stack, the motion
compensator should be unlocked and overpressured to prevent severe overpull on the
drill pipe should the casing hanger hang up in a ram cavity. The retrieval of the casing
hanger with a spear leaves the flat shoulder on the casing hanger exposed and prone to
falling into a ram cavity. The casing hanger is also prone to hanging up on the bottom of
the inner barrel of the slip joint when tripping out of the hole and requires the use of the
motion compensator to prevent over-tensioning the drill string.
A spear should be selected that is beveled on the top side to minimize the possibility of
the spear hanging up in the BOP stack.
Spear Stop
13 3 /8 C aing
15-20
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
TESTING PLUG(S)
These plugs shall be tagged and/or pressure tested to at least 500 psi in excess of the
formation leak-off pressure, or to the working limit of the weakest exposed casing string,
whichever is less (ExxonMobil guideline).
15-21
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
15-22
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
15-23
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
15-24
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
15-25
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
When performing a multiple cut, it is critical to ensure that the knives are stationary and
not affected by rig heave. Since the cuts on the wellheads will be performed in open
water after the BOP stack has been retrieved, a landout point in the wellhead is required
to provide a passive point of resistance for the motion compensator. Removing the
heave component from the drill string while cutting the casing ensures that the space-out
from the wellhead to the cut remains the same, thereby reducing the window that is
being cut and the time required to make the cut, and reducing the possibility of
damaging the cutter knives.
The marine swivel Figure 15.18, when used is positioned
in the cutting assembly to land-out in the wellhead and Rotating Stem
position the casing cutter at the proper cut location. When
the marine swivel seats in the wellhead, it provides
passive resistance for the motion compensator to act
against to provide heave compensation.
Thrust Bearing
Marine swivels are equipped with a support ring to land-
out in the wellhead and a thrust bearing that allows
rotation of the inner stem and the drill string. Typical tool
sizes are from 10.5 in. to 14.0 in. with support rings from
12.0 in. to 35.0 in.. Bearing Stationary Sleeve
capacity ranges from 45 to 250 kips.
With the marine swivel landed-out in the wellhead, the
casing can be cut with either the rotary/top drive or with a
mud motor using a large casing cutter equipped with extra
long knives. After cutting the casing, the cutting assembly
would be tripped and a casing spear or wellhead running
tool used to retrieve the casing, wellheads and
assemblies.
If the wellhead running tool is used, it will require make-up into the wellhead with
left-h a n d ro ta tio n . B e fo re ru n n in g th e w e llh e a d ru n n in g to o l, a ll o rin g se a ls sh ould be
removed to facilitate stab-in and make-up. During make-up of the running tool into the
wellhead, the torque limit switch to the top drive should be set to a minimum and surface
rotation should be matched with drill string rotation at the tool with the ROV. When high
overpull or jarring is required to free the wellheads and casing from the mud line, the
wellhead-running tool will provide a more secure catch than the large spear or the
external catch tool (Weatherford MOST tool).
A Marine swivel can also be used when cutting smaller casing with the BOP and
riser in place.
15-26
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
As depicted in Figure 15.19, a downhole mud motor is placed above cutter allowing the
casing to be cut without pipe rotation. Without the support of the drilling riser, it is
preferable to use a mud motor to prevent the necessity of having to rotate the drill string
in open water, particularly at deeper water depths.
Once the MOST tool is set onto the wellhead, circulation is begun and the pressure
forces a piston down, opening the knife blades against the casing, and the cutting is
begun. An increase in pump pressure will indicate that the cut has been made.
15-27
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
The pumps are shut down, and the MOST tool is picked-up to engage the wellhead, and
a pull is taken to determine if the conductor casing, structural casing and PGB/mud mat
are free. Figure 15.20. If so, then the entire assembly is pulled to the surface and laid
down.
Prior to cutting the conductor and structural casing, the exact location of the casing
connectors should be determined and the cutters spaced out to avoid cutting the casing
across a connector. It is also preferable to cut above any connections on the conductor
pipe since the rotation and torque of the cutter knives may back off the connection above
the cut. When running the conductor casing, all locking tabs/devices should be utilized
on any connections that may be above the cut location. If the casing is cut below a
connection and the joint backs off, rotation of the joint will prevent the knives from
continuing to cut/mill the conductor casing which will prevent the knives from reaching
the opening width required to cut the structural casing.
When attempting to pull the casing, wellheads and mud mat free from the mud line, it is
essential that the casing be completely cut. If only a small section on one side of the
casing remains uncut, it is nearly impossible to pull apart the uncut section. In addition,
when the casing parts, the sudden loss in tension can cause the MOST tool to release
from the wellhead and leave the wellheads leaning at an angle that makes it difficult to
re-latch the tool.
The wellheads and casing can also be difficult to pull free from the mud line due to the
cuttings and cement accumulation on top of the mud mat and/or guidebase(s). The
15-28
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
cuttings and cement accumulate on the mud mat and guidebase while the conductor
hole is drilled and as a result of the excess conductor casing cement.
In Figure 15.21, the MOST tool is landed on the wellhead with the casing cutter spaced
at the desired location to cut the conductor and structural casing. In Figure 15.22, the
conductor and structural casing have been cut, the MOST tool latched onto the wellhead
and the casing and wellhead are being lifted from the seafloor.
The MOST tool is a highly reliable system whose grapples are available to retrieve
various manufactured wellheads, including Vetco, Cameron, National, and Dril-Quip
Figure 15.21 Cutting Conductor & Figure 15.22 Wellheads & Conductor/
Structural Casing with MOST Tool Structural Casing being Retrieved with MOST
Tool
15-29
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
CABLES OR CHAINS
CONNECTED BY
ROV AT TIME OF P&A
15-30
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
15-31
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
15-32
ExxonMobil Floating Drilling School 2002 Edition
ABANDONMENT OPERATIONS
15.15 REFERENCES
E xxo n P ro d u ctio n R e se a rch C o m p a n y; S u b se a W e llh e a d R e m o va l E P R .1 8 P R .8 4 ,
February 1984
15-33
ExxonMobil Floating Drilling School 2002 Edition