The document outlines labor production rates for various construction works including carpentry, masonry, and tinsmithing. It provides the man hours per quantity needed to complete each type of work at low, average, and high production levels. The rates are outlined in a table with over 20 categories of work and specific tasks within each category.

Uploaded by

Phatts Pontod
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
823 views4 pages

Labor Production Table (NHA)

The document outlines labor production rates for various construction works including carpentry, masonry, and tinsmithing. It provides the man hours per quantity needed to complete each type of work at low, average, and high production levels. The rates are outlined in a table with over 20 categories of work and specific tasks within each category.

Uploaded by

Phatts Pontod
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

LABOR PRODUCTION TABLE

MAN HOURS PER QUANTITY


W O R K D E S C R I P T I O N
LOW AVERAGE HIGH

I. TRADE: CARPENTRY WORKS

A. FORM WORKS INSTALLATION

1.0 WALL ON GROUND 4.00 MH/S.M. 2.00 MH/S.M. 1.60 MH/S.M.


2.0 WALL ABOVE GROUND 4.70 MH/S.M. 2.35 MH/S.M. 1.88 MH/S.M.
3.0 BEAMS 6.16 MH/S.M. 3.08 MH/S.M. 2.46 MH/S.M.
4.0 COLUMNS 4.70 MH/S.M. 2.35 MH/S.M. 1.88 MH/S.M.
5.0 SUSPENDED SLAB
0 TO 18" 3.34 MH/S.M. 1.67 MH/S.M. 1.34 MH/S.M.
18 TO 36" UP 6.66 MH/S.M. 3.33 MH/S.M. 2.66 MH/S.M.
6.0 ELEVATED and SHORED SLAB FORMING
6.01 FORMING ONLY 17.20 MH/S.M. 8.60 MH/S.M. 6.88 MH/S.M.
6.02 FORMING and SHORING 22.00 MH/S.M. 11.00 MH/S.M. 8.80 MH/S.M.
7.0 WOOD WALL and PARTITIONS 1.00 MH/S.M. 0.50 MH/S.M. 0.40 MH/S.M.

B. FORM WORKS FABRICATION 2.15 MH/S.M. 1.08 MH/S.M. 0.86 MH/S.M.

C. STRIPPING OF FORMWORKS

1.0 WALL ON GROUND 0.50 MH/S.M. 0.25 MH/S.M. 0.20 MH/S.M.


2.0 WALL ABOVE 10' 2.58 MH/S.M. 1.29 MH/S.M. 1.03 MH/S.M.
3.0 BEAMS 2.06 MH/S.M. 1.03 MH/S.M. 0.82 MH/S.M.
4.0 COLUMNS 1.70 MH/S.M. 0.85 MH/S.M. 0.68 MH/S.M.
5.0 SUSPENDED SLAB
0 TO 18" 1.67 MH/S.M. 0.84 MH/S.M. 0.67 MH/S.M.
18 TO 36" UP 2.16 MH/S.M. 1.08 MH/S.M. 0.86 MH/S.M.
6.0 ELEVATED and SHORED SLAB FORMING
STRIP OF FORMS 7.00 MH/S.M. 3.50 MH/S.M. 2.80 MH/S.M.
7.0 FLOOR SLAB AT GRADE - STRIP OF FORMS 5.60 MH/S.M. 2.80 MH/S.M. 2.24 MH/S.M.
LABOR PRODUCTION TABLE
MAN HOURS PER QUANTITY
W O R K D E S C R I P T I O N
LOW AVERAGE HIGH

D. INSTALLATION OF CARPENTRY WORKS

1.0 PLYWOOD PARTITION 2.00 MH/PC 1.00 MH/PC 0.80 MH/PC


2.0 T and G FLOORING and SIDING 0.28 MH/B.F. 0.14 MH/B.F. 0.11 MH/B.F.
3.0 CEILING FRAME WORK 0.73 MH/B.F. 0.37 MH/B.F. 0.29 MH/B.F.
4.0 SIDING FRAME WORK 0.53 MH/B.F. 0.27 MH/B.F. 0.21 MH/B.F.
5.0 FLOORING FRAMING 1.94 MH/B.F. 0.97 MH/B.F. 0.78 MH/B.F.
6.0 WOODEN POST ERECTION 0.85 MH/B.F. 0.43 MH/B.F. 0.34 MH/B.F.
7.0 TRUSS FABRICATION 0.70 MH/B.F. 0.35 MH/B.F. 0.28 MH/B.F.
8.0 TRUSS INSTALLATION 1.60 MH/B.F. 0.80 MH/B.F. 0.64 MH/B.F.
9.0 GIRT INSTALLATION 0.43 MH/B.F. 0.22 MH/B.F. 0.17 MH/B.F.
10.0 PLATES INSTALLATION 0.27 MH/B.F. 0.14 MH/B.F. 0.11 MH/B.F.
11.0 PURLINS INSTALLATION 0.53 MH/B.F. 0.27 MH/B.F. 0.21 MH/B.F.
12.0 FACIA BOARD INSTALLATION 0.91 MH/B.F. 0.46 MH/B.F. 0.36 MH/B.F.
13.0 1/4" or 3/4" thk. PLYWOOD
- CUTTING BY MANUAL 2.00 MH/PC 1.00 MH/PC 0.80 MH/PC
- ASSEMBLY 0.83 MH/S.H. 0.42 MH/S.H. 0.33 MH/S.H.
14.0 CEILING
- FRAME INSTALLATION 2.66 MH/S.M. 1.33 MH/S.M. 1.06 MH/S.M.
- PLYWOOD INSTALLATION 2.00 MH/S.M. 1.00 MH/S.M. 0.80 MH/S.M.
15.0 CABINET BOARDING 0.26 MH/B.F. 0.13 MH/B.F. 0.10 MH/B.F.
16.0 CABINET FRAMING 0.36 MH/B.F. 0.18 MH/B.F. 0.14 MH/B.F.
17.0 WOOD WALL PARTITIONS 1.00 MH/S.M. 0.50 MH/S.M. 0.40 MH/S.M.
18.0 PANEL WALL 14.00 MH/S.M. 7.00 MH/S.M. 5.60 MH/S.M.
19.0 FORMING WEIGHT ANCHOR BOLTS 9.00 MH/S.M. 4.50 MH/S.M. 3.60 MH/S.M.
20.0 NET FORMING 7.00 MH/S.M. 3.50 MH/S.M. 2.80 MH/S.M.

E. DOORS and WINDOWS

1.0 W-PANEL INSTALLATION 0.80 MH/PC. 0.40 MH/PC. 0.32 MH/PC.


2.0 STEEL WINDOWS INSTALLATION 4.00 MH/PC. 2.00 MH/PC. 1.60 MH/PC.
3.0 LOUVER WINDOWS INSTALLATION
3.01 FIXED ASBESTOS 9.26 MH/S.M. 4.63 MH/S.M. 3.70 MH/S.M.
3.02 FIXED METAL LOUVERS 6.24 MH/S.M. 3.12 MH/S.M. 2.50 MH/S.M.
3.03 FIXED G.I. SHEET 9.26 MH/S.M. 4.63 MH/S.M. 3.70 MH/S.M.
3.04 FIXED GLASS 6.24 MH/S.M. 3.12 MH/S.M. 2.50 MH/S.M.
3.05 FIXED WOODEN 6.76 MH/S.M. 3.38 MH/S.M. 2.70 MH/S.M.
4.0 ALUMINUM FRAMED WINDOWS 20.00 MH/EACH 10.00 MH/EACH 8.00 MH/EACH
5.0 SLIDING GLASS DOOR 24.00 MH/EACH 12.00 MH/EACH 9.60 MH/EACH
6.0 HOLLOW METAL DOOR 20.00 MH/EACH 10.00 MH/EACH 8.00 MH/EACH
LABOR PRODUCTION TABLE
MAN HOURS PER QUANTITY
W O R K D E S C R I P T I O N
LOW AVERAGE HIGH
7.0 ROLLING DOORS 50.00 MH/EACH 25.00 MH/EACH 20.00 MH/EACH
8.0 FIXED WINDOW 0.63 MH/S.F. 0.32 MH/S.F. 0.25 MH/S.F.
9.0 DOOR LOCKSET 3.20 MH/SET 1.60 MH/SET 1.28 MH/SET
10.0 DOOR JAMB
FABRICATION 0.44 MH/B.F. 0.22 MH/B.F. 0.18 MH/B.F.
INSTALLATION 0.66 MH/B.F. 0.33 MH/B.F. 0.26 MH/B.F.
11.0 CYCLONE WIRE INSTALLATION 6.24 MH/B.F. 3.12 MH/B.F. 2.50 MH/B.F.

II. TRADE: MASONRY WORKS

1.0 GROUTING and TOL PLASTERING 3.34 MH/S.M. 1.67 MH/S.M. 1.34 MH/S.M.
2.0 PEBBLE FINISHED 2.86 MH/S.M. 1.43 MH/S.M. 1.14 MH/S.M.
3.0 MARBLE INSTALLATION 4.00 MH/S.M. 2.00 MH/S.M. 1.60 MH/S.M.
4.0 1/4" x 2 x 8 RED BRICKS 10.00 MH/S.M. 5.00 MH/S.M. 4.00 MH/S.M.
5.0 GLAZED TILES 21.06 MH/S.M. 10.53 MH/S.M. 8.42 MH/S.M.
6.0 UNGLAZED TILES 8.70 MH/S.M. 4.35 MH/S.M. 3.48 MH/S.M.
7.0 GLAZED TILE WALL 6.00 MH/S.M. 3.00 MH/S.M. 2.40 MH/S.M.
8.0 CONC. BLOCK EXT. WALL 9.00 MH/S.M. 4.50 MH/S.M. 3.60 MH/S.M.
9.0 CONC. BLOCK INT. WALL 9.00 MH/S.M. 4.50 MH/S.M. 3.60 MH/S.M.
10.0 BRICKWORK 1.00 MH/S.M. 0.50 MH/S.M. 0.40 MH/S.M.
11.0 PLASTER WALL and CEILING 6.00 MH/S.M. 3.00 MH/S.M. 2.40 MH/S.M.
12.0 HOLLOW TILE WALL 4.00 MH/S.M. 2.00 MH/S.M. 1.60 MH/S.M.
13.0 ACOUSTIC CEILING 2.40 MH/S.M. 1.20 MH/S.M. 0.96 MH/S.M.
14.0 VINYL FLOOR TILE 3.60 MH/S.M. 1.80 MH/S.M. 1.44 MH/S.M.
15.0 UNGLAZED OR MOSAIC FLOOR TILE 17.00 MH/S.M. 8.50 MH/S.M. 6.80 MH/S.M.
16.0 LAYING OF CHB and ADOBE 2.28 MH/S.M. 1.14 MH/S.M. 0.91 MH/S.M.
17.0 CEMENT FINISH 1.43 MH/S.M. 0.72 MH/S.M. 0.57 MH/S.M.
18.0 CONC. HOLLOW BLOCKS LAYING
18.01 6" CHB 3.20 MH/S.M. 1.60 MH/S.M. 1.28 MH/S.M.
18.02 4" CHB 2.66 MH/S.M. 1.33 MH/S.M. 1.06 MH/S.M.
18.03 8" CHB 4.00 MH/S.M. 2.00 MH/S.M. 1.60 MH/S.M.
19.0 VIT. TILES - FLOOR 10.66 MH/S.M. 5.33 MH/S.M. 4.26 MH/S.M.
20.0 VIT. TILES - WALL 11.94 MH/S.M. 5.97 MH/S.M. 4.78 MH/S.M.

III. TRADE: TINSMITHING WORK

1.0 CORR. G.I. SHEET


1.01 LIFTING 2.16 MH/S.M. 1.08 MH/S.M. 0.86 MH/S.M.
1.02 INSTALLATION 6.12 MH/S.M. 3.06 MH/S.M. 2.45 MH/S.M.
2.0 INSTALLATION OF ASBESTOS ROOFING 2.00 MH/SHT. 1.00 MH/SHT. 0.80 MH/SHT.
3.0 INSTALLATION OF ALUMINUM OR G.I. SHT. 1.60 MH/SHT. 0.80 MH/SHT. 0.64 MH/SHT.
LABOR PRODUCTION TABLE
MAN HOURS PER QUANTITY
W O R K D E S C R I P T I O N
LOW AVERAGE HIGH
4.0 COPPER CLADDING ROOF DECK 1.01 MH/L.M. 0.51 MH/L.M. 0.40 MH/L.M.
5.0 FAB. OF G.I. GUTTER 6.94 MH/SHT. 3.47 MH/SHT. 2.78 MH/SHT.
6.0 G.I. SHEET ROOFING 1.64 MH/S.M. 0.82 MH/S.M. 0.66 MH/S.M.
7.0 FAB. OF G.I. GUTTER 1.05 MH/L.M. 0.53 MH/L.M. 0.42 MH/L.M.
8.0 FAB. OF DOWNSPOUT 1.94 MH/L.M. 0.97 MH/L.M. 0.78 MH/L.M.
9.0 GUTTER CUT and SHAPE 0.32 MH/L.M. 0.16 MH/L.M. 0.13 MH/L.M.
10.0 INST. OF GUTTER 1.78 MH/L.M. 0.89 MH/L.M. 0.71 MH/L.M.
11.0 DOWNSPOUT CUT and SHAPE 0.59 MH/L.M. 0.30 MH/L.M. 0.24 MH/L.M.
12.0 DOWNSPOUT INSTALLATION 0.27 MH/L.M. 0.14 MH/L.M. 0.11 MH/L.M.
13.0 CORR. G.I. ROOFING 3.60 MH/S.M. 1.80 MH/S.M. 1.44 MH/S.M.
14.0 CORR. ALUMINUM ROOFING 3.60 MH/S.M. 1.80 MH/S.M. 1.44 MH/S.M.
15.0 BUILT-UP ROOFING 4-PLY 17.00 MH/S.M. 8.50 MH/S.M. 6.80 MH/S.M.
16.0 PROTECTED METAL 4.00 MH/S.M. 2.00 MH/S.M. 1.60 MH/S.M.
17.0 CORR. ASBESTOS INST., LIFTING, HAULING 3.40 MH/S.M. 1.70 MH/S.M. 1.36 MH/S.M.
18.0 LEADERS and GUTTERS 1.20 MH/S.M. 0.60 MH/S.M. 0.48 MH/S.M.

IV. TRADE: CONCRETE WORKS

1.0 PLACING CONC.


1.01 SLAB ON FILL 10.00 MH/C.M. 5.00 MH/C.M. 4.00 MH/C.M.
1.02 SLIP FORM 50.00 MH/C.M. 25.00 MH/C.M. 20.00 MH/C.M.
1.03 FLR. FINISH UNHARDENED 2.00 MH/S.M. 1.00 MH/S.M. 0.80 MH/S.M.
1.04 CONC. FINISH HARDENED 2.86 MH/S.M. 1.43 MH/S.M. 1.14 MH/S.M.
2.0 REBAR WORKS
2.01 GROUND FLR. INSTALLATION 0.14 MH/Kg. 0.07 MH/Kg. 0.06 MH/Kg.
2.02 UPPER FLR. INSTALLATION 0.16 MH/Kg. 0.08 MH/Kg. 0.06 MH/Kg.
2.03 FABRICATION 0.2 MH/Kg. 0.10 MH/Kg. 0.08 MH/Kg.
3.0 MIXING MANUAL 32.00 MH/C.M. 16.00 MH/C.M. 12.80 MH/C.M.
4.0 MIXING MACHINE 3.60 MH/C.M. 1.80 MH/C.M. 1.44 MH/C.M.