Tank Inspection Checklist

This 3 sentence summary provides the key details from the inspection report: The report documents an inspection of tanks at OKI Pulp & Paper, listing the supplier, manufacturer, contractor, and inspection items checked such as identification, cleaning, material conformity, welding, painting, piping, supports and a hydrostatic test. Upon completion of the inspection, the equipment was released for commissioning contingent on any noted defects being addressed.

Uploaded by

Indra Harapan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
167 views1 page

Tank Inspection Checklist

This 3 sentence summary provides the key details from the inspection report: The report documents an inspection of tanks at OKI Pulp & Paper, listing the supplier, manufacturer, contractor, and inspection items checked such as identification, cleaning, material conformity, welding, painting, piping, supports and a hydrostatic test. Upon completion of the inspection, the equipment was released for commissioning contingent on any noted defects being addressed.

Uploaded by

Indra Harapan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

OKI PULP & PAPER - INSPECTION REPORT - TANKS

Start-Up Group No: Name:

Equipment Pos No: Name:

Supplier: Manufacture: MEI-Contractor:


_____________________ Pipe Line Data

Flow Substance:

Design Pressure (m3):

Material:

Insulation:
Check by Verified by
Notes in Defect List
Check List n/a Date Supplier Contractor Purchaser Mills
1 Identification (name plate/tagging)
2 Overall cleaning
3 Conformity with specifications and drawings
4 Material Conformity
5 Grouting inspection
6 Inside inspection and polishing
7 Welding
8 Welding records (X-ray, ultrasonic, etc)
9 Finishing
10 Lining
11 Painting
12 Piping
13 Flange Parallelism
14 Support Ladder, Platform installation
15 Agitator Installation (Separate inspection Report)
16 Earthing Connection
17 Hydrostatic Test
18 Thermal insulation
19 Authorities' Inspection reports and approvals
Note: Defect List must be always enclosec
The referred equipment has been inspected and is hereby released for commissioning.
Date Sign Contractor
S ign Supplier Sign OKI