DECOMMISSIONING Work Methd

This work method statement outlines the decommissioning of a fire detection system in a main warehouse. It involves shutting down the control panel by removing the fuse and battery terminal, removing all fire detection and alarm system devices, pulling out the existing cables along with the devices, pausing work, and conducting housekeeping such as site restoration and removal of debris. The statement was prepared by a representative and approved by an SPDC representative.

Uploaded by

martins73
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
110 views1 page

DECOMMISSIONING Work Methd

This work method statement outlines the decommissioning of a fire detection system in a main warehouse. It involves shutting down the control panel by removing the fuse and battery terminal, removing all fire detection and alarm system devices, pulling out the existing cables along with the devices, pausing work, and conducting housekeeping such as site restoration and removal of debris. The statement was prepared by a representative and approved by an SPDC representative.

Uploaded by

martins73
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 1

WORK METHOD STATEMENT

Introduction:

Work method statement for Decommissioning of fire detection systems in Main Warehouse

Scope of work:

This method statement covers all decommissioning activities.

S/N TASK STEPS STEPS DESCRIPTION REMARK


1 Shutting down of The panel will be shut down by

panel removing the fuse from the panel

and the battery terminal.


2 Removal of all FDAS All existing FDAS devices will be

devices removed
3 Removal of existing All FDAS cables and pipes will be

cables pulled out along side with the

devices.
4 Pause Pause
5 housekeeping Site restoration will be done and

all dirty moved out of the site

Prepared by: ______________________ sign: _________________