Protection Schemes
Protection Schemes
Document                  Title                                                   No of
reference                                                                         pages
                          This cover page                                             1
                    C3.1 Employers Works Information                                 31
TABLE OF CONTENTS
PART C3: SCOPE OF WORK                                                        PAGE 2              C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                                                             CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
PART C3: SCOPE OF WORK                                                   PAGE 3             C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                          CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
LIST OF DEFINITIONS
LIST OF ABBREVIATIONS
AC Alternating Current
CT Current Transformer
DC Direct Current
LV Low Voltage
MV Medium Voltage
PART C3: SCOPE OF WORK                            PAGE 4   C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                            CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
VT Voltage Transformer
1 Reference Documents
   The Contractor Provide the Works in strict accordance with the contract, this Works
   Information. In addition to the requirements of this Works Information, the Works conform to the
   documents and drawings listed in section 11 and 12 of Part 3B of the Works Information, as
   well as other documents forming part of the references.
   The applicable revisions and amendments of the reference documents are the latest versions
   in force at the time of the contract award.
   Unless specifically stated in section 11 of Part 3B of the Works Information (Part 3B), the
   Contractor proposes the specifications required for the detail engineering, fabrication,
   installation   and    commissioning.   Such       specifications   are   supported   by   International
   specifications, standards; codes, practices and their use are accepted by the Project Manager.
2 Drawing Convention
   Where reference is made in this Works Information to the normal position of auxiliary contacts,
   the convention is such that the contacts are in the normal condition when:
3 General Requirements
   The Contractor provides all the protection devices and auxiliary equipment required to perform
   the functions defined for the different protection schemes. The main protection functions are
   implemented by the use of IEDs.
PART C3: SCOPE OF WORK                           PAGE 5        C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                            CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
   Other protection functions required, such as internal arc and bus zone protection are performed
   by separate IEDs. The Contractor designs a comprehensive protection scheme that defines the
   interfaces between all relays as well as the other related systems.
   The Contractor makes provision for the supervision and indication of the status of wiring and
   signals from all the tripping relays to the external trip coils.
   The design of the protection schemes are presented in the form of Protection & Control
   Functional & Interface Diagrams and detailed design drawings together with the related
   documentation describing the functions of the different devices used.
   Protection & Control Functional & Interface Block Diagrams for typical circuits defined in
   section 12 of Part 3B are submitted with the tender documentation for evaluation. All indicated
   optional functionalities are catered for and tendered for separately on an individual basis.
   Preliminary designs for the 4PA0100, 4PA0700, 4PA0800 and Buszone protection schemes
   are required.
   Although the Contractor is permitted to alter the designs of the circuits to suit their products, no
   functionality may be omitted after Design Freeze without the written consent of the Project
   Manager.
   All IEDs are pre-programmed with the respective logics that enable the protection scheme to
   comply with the specification as provided during the engineering phase. The programmable
   logics are also aligned with the relevant design drawings that define the functionality of the
   scheme. No logic programming is required after delivery of the equipment, but the application
   of conventional functional settings is necessary.
    The Contractor also supplies all IEDs for LV switchgear reticulation in accordance with
    Appendix 3 of part 3B of the Works Information as highlighted in Part 3A, and section 7 of Part
    3B of the Works Information. The supplied LV IEDs are free-issued to Others, for installation
    on the LV switchgear panels. Engineering, in the form of logic development and the
    programing of the IEDs in accordance to the LV switchgear philosophies is the responsibility of
    the Contractor. The Contractor is also responsible for testing and commissioning of the IEDs
    after installation by Others.
PART C3: SCOPE OF WORK                            PAGE 6       C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                       CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
   The Contractor supplies at least two licences for the software as a minimum for application of
   settings and for IED logics.
   All IEDs and auxiliary relays provided by the Contractor are type tested by an independent
   laboratory and these results are made available to the Project Manager for evaluation and
   acceptance. In addition to independent laboratory tests, the protection and associated
   equipment offered are evaluated, tested and approved by the Project Manager as per 240-
   56227589 and 32-333 prior to offer.
   All IEDs, auxiliary relays and their modules have a proven service record of at least five years
   and a combined effective service life of one hundred years. An international and national relay
   reference sales list is provided by the Contractor with tender submission.
   The Contractor provides the information regarding re-calibration of the electronic devices
   necessary to keep them in perfect working order or any other required intervention by the
   OEM, subsequent to the sale of equipment that has a financial impact on the Employer.
   All future upgrades and modifications of the electronic devices are communicated timeously to
   the Employer. Any malfunction of the same device experienced by other users or known to the
   Contractor is communicated to the Employer.
4 Power Supplies
   Auxiliary power for the protection systems will be provided from an external DC power supply
   system provided by the Contractor in accordance with part 3D of the Works Information, except
   for the unitised (i.e. Unit 1 to 6) switchgear which will be provided by the Employer. The
   nominal rating of the voltage supply will be 220V DC.
   IEDs, auxiliary relays and other DC equipment are capable of operating continuously at
   extreme tolerances of the DC supply voltage, which is 220V DC  20%. The equipment is
PART C3: SCOPE OF WORK                        PAGE 7       C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                            CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
      therefore capable of operating at either 176V or 264V continuously without detriment to the
      protection system.
      All indications are non-volatile i.e. if the DC supply fails, then on restoration of the DC supply
      the indication resumes the status that it had before the supply failed.
5 Protection Devices
      The Contractor supplies protection devises that conforms to the requirement stated below in
      the following subsections.
         The Contractor designs and provide Protection schemes for all the power circuits (i.e.
         incomers, feeders and others) consisting of IEDs constructed as a 19 inch rack mountable
         unit or according to Contractor's standard arrangement. No terminals are provided on the
         19 inch rack. Where required, the tails are suitably ferruled with a minimum length of two
         meters.
         All IEDs are equipped with screen or display facility to allow for human interface. The
         contents are clearly visible from a distance of 2 m and at an angle of 30 from either side.
         This display is of the Liquid Crystal Display (LCD) with anti-glare and non-blinking
         properties. The IEDs display makes it possible for the mimic of the circuit protected by the
         device to be illustrated on the display. The mimic shows as a minimum the status of circuit
         breakers (ON or OFF), status of earth switches, position of circuit breaker (connected or
         disconnected) and electrical parameters (voltage, current, power, etc.) for a particular
         circuit. The mimic should also display an interlock on a device if present.
         Provision is made for the local control of the breakers to be performed from the associated
         IED using an integrated control pad for local test purposes during maintenance only.
         LEDs are required for indication of the operation of the alarm and protection functions
         within the IED and are an integral part of the device. The allocation of the LEDs to the
         different functionality is configurable to allow for flexibility during the engineering phase.
         Split face IEDs, whereby the digital display is mounted on the door of the LV compartment
         and connected to the main processing unit by means of fibre optic cable, are preferred.
PART C3: SCOPE OF WORK                             PAGE 8       C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                           CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
       The devices are equipped with ports to allow for access to information via a communication
       link. These ports have the capacity that matches the data transfer requirements for the
       associated communication bus.
       A label stating the firmware version is fixed to all IEDs. Information regarding the estimated
       data retention time of the storage medium used in the IEDs is provided to the Employer.
5.1.2 Functions
       The protection, control, indication and data capturing functionalities are provided by the
       IEDs. All functions, settings and internal logic are programmable through the IED software
       and a personal computer (PC), except where otherwise stated.
       The Contractor specifies and gives written details of protection functionalities that are
       inherently part of their IEDs but are not required by the performance specification.
       A single IED is able to provide all the required main and back-up protection functions for the
       scheme in question as a minimum. The control and indication functions are also
       incorporated in the IEDs.
       IEDs have measurement functions with analogue outputs as described under section 6 of
       Part 3B for each protection scheme. These analogue outputs are configurable by the user
       for ranges between 4 and 20mA. Response time for signals is 500msec for a step input of
       80%.
       The integration of the auxiliary functions such as the DC Fail and Trip Circuit Supervision
       (TCS) functions within the device is preferred. The IEDs have a self-monitoring function of
       both integral hardware and software that is done on a continuous basis. Any fault or
       irregularity is immediately alarmed to an output contact.
       The random switching of the DC auxiliary supplies at high rate does not affect the
       functionality of the IED. Where required, the internal battery requirements for numerical
       IEDs (i.e. battery lifetime, type of battery etc.) is stated on a label attached to the front of the
       numerical device.
PART C3: SCOPE OF WORK                           PAGE 9        C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                      CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
       Unless otherwise specified, all IED are provided with manual-reset operation indicators for
       each function of the IED. These do not operate until the IEDs have operated. Resetting is
       accomplished without opening the case.
       The IEDs have disturbance or event recording and data logging capability with the integral
       storage media. The information stored in the IED is accessible via the communication port.
       Information regarding the estimated data retention time of storage medium of the IEDs is
       provided to the Employer.
       All IEDs have the capability to perform control, indication or monitoring, interlocking and
       data transfer functions via a communication bus. The IEDs communication capability
       complies with IEC 61850 standard.
5.1.3 Software
       Software installed on the IEDs for event or disturbance recordings, data logging, settings
       and marshalling or configuration is accessible via a dedicated communication link using
       engineering tools. This software allows information to be downloaded in COMTRADE
       format in accordance with IEEE C37.111-1991. All software required to perform the
       marshalling and settings of the IEDs is contained in one package.
       The Contractor supplies evidence, on request, in the form of reports from a mutually
       acceptable third party that an adequate formal specification for the software has been
       produced at no additional cost. The specification is based on a requirement document and
       comprehensive risk analysis. The software is formally verified to ensure that it matches its
       specification.
       All software purchased on this contract and subsequent software upgrades supports the
       latest Microsoft Windows operating system. The Contractor informs the Employer of any
       and all new releases. The latest software version is always compatible with the installed
       base of IEDs, which originally were compatible with the previous version of software that
       was compatible with the previous Microsoft Windows operating system. For example, if the
       existing software is only compatible with Windows 95, it is upgraded to Windows 7 (the
       latest Microsoft supported operating system).
PART C3: SCOPE OF WORK                        PAGE 10     C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                         CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
       All software and firmware are backward and forward compatible (i.e. the software on this
       contract is such that all future versions of software will be compatible with the installed base
       of IEDs).
       The current inputs of the devices are rated at 1A. Where required, the voltage inputs are
       rated at 110V AC, unless otherwise stated.
       The IED is also provided with the digital inputs for the control and indication functions as
       determined by the schemes described in section 6 of Part 3B.
       The configuration of the inputs is programmable. The minimum number of inputs required is
       provided in the C&I Interface Signals for MV Switchgear found in Appendix 4A of Part 3B.
       The Contractor designs all protection schemes such that all output contacts of the IEDs
       have self-resetting capabilities, except for those linked to master trip and lockout functions,
       which have manual-reset capabilities.
       Each protection scheme has at least two output contacts for tripping. The IED is also
       provided with the digital outputs for the control and indication functions as determined by
       the schemes described in section 6 of Part 3B.
       DC Fail and under voltage protection functions are facilitated by normally closed contacts.
       All other relays have normally open contacts.
PART C3: SCOPE OF WORK                         PAGE 11      C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                        CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
       The Contractor submits certificates and report stating that protection devices offered have
       been subjected to routine and type tests which cover at least the tests recommended in
       standard 32-333. The program of routine and type tests is submitted to the Project Manager
       for acceptance.
       Unless otherwise specified, all IEDs are provided with suitable test facilities for VT and CT
       circuits to enable tests carried out on the IEDs while in position inside the panel without
       disconnecting any wiring or links. Test facilities are provided in accordance with standard
       32-333.
       Two copies of all test certificates are submitted to the Project Manager for acceptance once
       the tests have been completed.
      Bus zone protection is implemented by utilising a numerical differential relay. These devices
      comply with the requirements of 32-333 standard as a minimum.
      Only a low impedance scheme is acceptable. The Contractor provides details of the CT
      requirements. CT selection methodology is required to be submitted to the Project Manager
      for acceptance.
      All devices are fitted with contacts which are self-resetting with exception of the tripping
      function.
      The devices are provided with hand-reset operation indicators for each of the functions. The
      indicators do not operate until the relays have closed their contacts. Re-setting is
      accomplished without opening the case.
      The protection schemes are provided with suitable test facilities to enable tests to be carried
      out on the device while in position on the panel without disconnecting any wiring.
      The bus zone protection equipment is housed in separate panels designed to accommodate
      482.6 mm (19 inch) type racks or the Contractors standard arrangement. The panels are
      constructed in accordance with Eskom Standard number 32-333.
PART C3: SCOPE OF WORK                         PAGE 12     C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                        CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
      Auxiliary power for the bus zone protection device will be provided at 220V DC nominal
      voltage rating from an external DC power supply system provided by the Contractor in
      accordance with part 3D of the Works Information, except for the unitised (Unit 1 to 6)
      switchgear which will be provided by the Employer. The AC power supply for the cubicle
      lighting will also be provided by the Employer.
      DC line filters are installed in the bus zone system such that it protects the electronic
      components against voltage spikes.
      The Contractor designs and supplies arc protection schemes that are integral part of the
      switchgear as described in part 3A of the Works Information.
      The arc detection system conforms to the requirement stated below in the following
      subsections.
       The arc protection function is provided by a device that accepts both light and current
       signals as input. These signals are detected simultaneously to initiate a trip and alarm.
       The arc protection relay performs the high speed tripping of the supply circuit breaker in the
       event of an arc fault when the current exceeds a pre-set reference value. The device have
       a maximum sensor detection function pulse delay time of less than 5 ms and subsequently
       issues a breaker trip pulse in a time of less than 10 ms from fault inception. The total
       (including breaker and arcing time) fault clearance time required is less than 100 ms from
       fault inception.
       All devices are fitted with contacts which are self-resetting with exception of the tripping
       function.
       DC line filters are installed in the arc detection system such that they protect the electronic
       components against voltage spikes.
PART C3: SCOPE OF WORK                         PAGE 13      C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                        CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
       Arc detection is performed with light sensitive type elements located in the respective
       switchgear chambers (including segregated busbars between panels). The elements are
       installed in such a way that they completely cover the space to be protected.
       The light sensors are not triggered by external light sources such as camera flashes or
       welding arcs.
       The sensor has the degree of protection to operate within the boards internal
       environmental conditions.
5.3.3 Monitoring
       The internal arc protection system has a self-diagnostic (self-monitoring) function that
       prevents the relays from operating if a system (i.e. devices and sensors) fault is detected. It
       clearly indicates by means of an alarm indicator the fault and the location thereof.
       The system gives an indication of the fault location (i.e. which compartment faulted) locally
       at the switchgear panel through an IED and remotely on the dedicated engineering station.
       The power supply modules are continuously monitored and should provide an alarm in the
       event of failure.
       Where required, the auxiliary relays are provided with the desired trip or indication function
       with the operation time of less than 50 ms. The auxiliary relays must comply with the
       requirements of 32-333.
       Unless otherwise specified, all the relays are provided with manual-reset operation
       indicator/s for the dedicated function. The indicator/s does not operate until the relay has
       operated. Resetting is accomplished without opening the case.
       Each relay has at least two output contacts for tripping and two output contacts for external
       alarms.
PART C3: SCOPE OF WORK                         PAGE 14      C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                               CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
6 Protection Schemes
      Description of circuit protection schemes to be supplied by the Contractor.
       The PA numbering is a numbering system dating back to the 1980's. The first numerical
       represents the protection technology, 4 signifying phase 4 (an Eskom description meaning
       an IED). PA stands for Protection Auxiliary. The last four numbers signify the type of circuit
       being protected.
       Protection scheme is provided for all feeders to the MV motors with power rating larger or
       equal to 1MW. Each scheme includes the following functions:
       In addition, the schemes have binary Input/output (I/O) facilities as well as analogue outputs.
       These input facilities are for external trip and close signals and to enable thermistors to
       decrease the tripping time of the overload elements. The trip outputs are latched.
       The protection elements have setting ranges as detailed in Schedule A in Appendix 2 of Part
       3B. The characteristic curves of IDMTL overcurrent and earth fault protection elements
       conform to IEC standards.
       Thermal overload protection monitors the current flowing into the motor. Based on these
       currents, it models the temperature inside the motor.
PART C3: SCOPE OF WORK                              PAGE 15       C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                        CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
      Negative phase sequence protection function is made available in the motor protection
      scheme. This function protects the motor against overheating caused by induced double
      frequency currents. The negative phase protection has an inverse and a definite time
      characteristics.
      Motor stall protection function is available in the motor protection scheme. This function is
      preferably an overcurrent protection element set below the locked rotor current and a time
      delay set to the stall capability time of the motor. The time delay is adjustable over the range
      specified in Schedule A in Appendix 2 of Part 3B.
      Three-phase definite time undervoltage protection function is made available in the motor
      protection scheme. This function does not operate for the loss of a single-phase VT supply
      but only operates for the loss of all three phases after a predetermined period. The
      undervoltage protection function trips the motors for a sustained under voltage condition. The
      protection elements are energized from voltage transformers with secondary of 110 V phase-
      to-phase and 63.5 V phase-to-neutral. The elements are adjustable to operate in the voltage
      ranges specified in Schedule A and have drop-off/pick-up ratios greater than 95%. Setting
      adjustment is preferably continuously variable, but if adjusted in steps, these do not exceed
      10%. The time delay is adjustable over the range specified in Schedule A in Appendix 2 of
      Part 3B.
      Other functions required in the motor protection scheme such as current interlock, long
      starting time, etc. are indicated in Schedule A in Appendix 2 of Part 3B.
      Provision is made for output analogue signals (i.e. current and power) from the IEDs. The
      Contractor provides separate measurement modules (i.e. transducers) for both current and
      power. Alternatively, the measurement modules are provided as an integral part of the
      protection IED. The Contractor also provides in the Rates Price Schedule both the take out
      price for having separate measurement modules, as well as the price for transducers
      provided as an integral part of the IED.
      Protection scheme is provided for all feeders to the MV motors with power rating smaller than
      1MW. Each scheme includes the following:
PART C3: SCOPE OF WORK                           PAGE 16    C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                         CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
     In addition, the schemes have binary I/O facilities as well as analogue outputs. These input
     facilities are for external trip and close signals and to enable thermistors to decrease the
     tripping time of the overload elements. The trip outputs are latched.
     Thermal overload protection monitors the current flowing into the motor. Based on these
     currents, it models the temperature inside the motor.
     Negative phase sequence protection function is made available in the motor protection
     scheme. This function protects the motor against overheating caused by induced double
     frequency currents. The negative phase protection has an inverse and a definite time
     characteristics.
     Motor stall protection function is made available in the motor protection scheme. This
     function is preferably an overcurrent protection element set below the locked rotor current
     and a time delay set to the stall capability time of the motor. The time delay is adjustable over
     the range specified in Schedule A in Appendix 2 of Part 3B.
     Three-phase definite time under voltage protection function is made available in the motor
     protection scheme. This function trips the motors for a sustained under voltage condition and
     is provided for protection of MV motors. They are energised from voltage transformers with
     secondary of 110 volt phase-to-phase and 63.5 volt phase-to-neutral. The measuring
     elements are adjustable to operate in the voltage ranges specified in Schedule A and have
     drop-off/pick-up ratios greater than 95%. Setting adjustment are preferably continuously
PART C3: SCOPE OF WORK                         PAGE 17       C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                          CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
      variable, but if adjusted in steps, these do not exceed 10%. The time delay is adjustable over
      the range specified in Schedule A in Appendix 2 of Part 3B.
      Directional earth fault is required if the option of a zero sequence current balancing
      transformer is considered across the motor feeder cables since the MV system is resistive
      earthed with the MV motor neutral unearthed.
      Other functions required in the motor protection scheme such as current interlock, long
      starting time, etc. are indicated in Schedule A in Appendix 2 of Part 3B.
      Provision is made for output analogue signals (i.e. current and power) from the IEDs. The
      Contractor provides separate measurement modules (i.e. transducers) for both current and
      power. Alternatively, the measurement modules are provided as an integral part of the
      protection. The Contractor also provides in the Rates Price Schedule both the take out price
      for having separate measurement modules, as well as the price for transducers provided as
      an integral part of the IED.
      Protection scheme for the feeders of the transformer with the power rating larger or equal to
      10MVA includes the following functions:
      The IDMTL overcurrent and earth fault are set as back-up protection for the transformer
      differential protection as well as protection for downstream circuits.
      In addition, the IEDs have binary input facilities. These input facilities cater for external alarm
      and trip signals such as Buchholz, winding temperature, oil temperature and pressure relief
      protection. A minimum of eight binary inputs are required.
PART C3: SCOPE OF WORK                          PAGE 18       C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                         CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
      The protection elements have setting ranges as detailed in Technical Schedule A found in
      Appendix 2. The characteristic curves of IDMTL overcurrent and earth fault protection
      elements conform to IEC standards.
      The overcurrent and earth fault elements (i.e. IDMTL or definite time) are set as main
      protection for the interconnector and back-up protection for downstream circuits.
      The Contractor specifies and supplies the fibre optic or pilot wire cables, which are suitable
      for the cable differential protection, to be installed by Others. Fibre optic links are preferred
      for differential protection application.
      A synchronism check facility is provided for the changing of power supplies on a MV board,
      which is feeding from different sources. The synchronism check facility measures the three
      phase voltage quantities from the cable and busbar VTs. Once the three voltages are the
      same, in phase, magnitude, phase rotation and frequency, a closing signal is issued to the
      breaker of the normal supply and an open to the alternative supply after a period not
      exceeding 100 ms. This is done to ensure the make-before-break operation. Different set
      parameters are required.
      A typical switching or operating procedure for the power transfer is as follows: Close the unit
      supply breaker (with unit supply cable VT alive) to energize the busbar (busbar VT dead and
      station supply breaker opened with station supply breaker cable VT dead). Vice versa is also
      applicable. This is a Live line, dead bus charge.
      The protection elements have setting ranges as detailed in Technical Schedule A found in
      Appendix 2 of Part 3B. The characteristic curves of IDMTL overcurrent and earth fault
      protection elements conform to IEC standards.
PART C3: SCOPE OF WORK                           PAGE 19    C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                           CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
      The Contractor provides output analogue signals (i.e. current and voltage) from the IEDs.
      These measurement modules are an integral part of the protection IED. The Contractor also
      provides a take out price for having separate measurement modules (i.e. transducers) in the
      Rates Price Schedule.
      Protection scheme for the feeders of the transformer with the power rating smaller than
      10MVA includes the following functions:
      The IDMTL overcurrent and earth fault are set as main protection for the transformer / feeder
      and back-up protection for downstream circuits.
      In addition, the IEDs have binary input facilities. These input facilities cater for external alarm
      and trip signals such as Buchholz, winding temperature, oil temperature and pressure relief
      protection. A minimum of eight binary inputs are required.
      The protection elements have setting ranges as detailed in Technical Schedule A found in
      Appendix 2 of Part 3B. The characteristic curves of IDMTL overcurrent and earth fault
      protection elements conform to IEC standards.
      The Contractor provides output analogue signals (i.e. current) from the IEDs. These
      measurement modules are an integral part of the protection IED. The Contractor also
      provides a take out price for having separate measurement modules (i.e. transducers) in the
      Rates Price Schedule.
PART C3: SCOPE OF WORK                           PAGE 20      C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                        CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
      The overcurrent and earth fault protection is utilised to provide the required current input for
      the arc detection interlock and also act as back-up protection for downstream circuits.
      A synchronism check facility is provided for the changing of power supplies on a MV board,
      which is feeding from different sources. The synchronism check facility measures the three
      phase voltage quantities from the cable and busbar VTs. Once the three voltages are the
      same in phase, magnitude, phase rotation and frequency, a closing signal is issued to the
      breaker of the normal supply and an open to the alternative supply after a period not
      exceeding 100 ms. This is done to ensure the make-before-break operation. Different set
      parameters are required.
      A typical switching or operating procedure for the power transfer is as follows: Close the unit
      supply breaker (with unit supply cable VT alive) to energize the busbar (busbar VT dead and
      station supply breaker opened with station supply breaker cable VT dead). Vice versa is also
      applicable. This is a Live line, dead bus charge.
      In addition, the IEDs have binary input and output facilities in accordance with the scheme
      requirements for external trip signals.
      The protection elements have setting ranges as detailed in Technical Schedule A found in
      Appendix 2 of Part 3B. The characteristic curves of IDMTL overcurrent and earth fault
      protection elements conform to IEC standards.
      The Contractor provides output analogue signals (i.e. current and voltage) from the IEDs.
      These measurement modules are an integral part of the protection IED. The Contractor also
      provides a take out price for having separate measurement modules (i.e. transducers) in the
      Rates Price Schedule.
6.8 Bus Section (4PA1400) and Maintenance Isolator (4PA1400A) Control Schemes
      The bus section and maintenance isolator schemes are used as control and indication
      device only without protection functions.
PART C3: SCOPE OF WORK                            PAGE 21   C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                           CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
      The details on the requirements of the scheme are given in Technical Schedule A in
      Appendix 2 of Part 3B.
      Protection scheme provided for an incomer from a 3.3 kV diesel generator includes the
      following functions:
      In addition, the scheme has binary I/O facilities as well as analogue outputs. These input
      facilities are for external trip and close signals. The trip outputs are latched.
      Negative phase sequence protection function is made available in the diesel generator
      protection scheme. This function protects the diesel generator against overheating caused
      by induced double frequency currents. The negative phase protection has an inverse and a
      definite time characteristics.
      Three-phase definite time undervoltage protection function is made available in the generator
      protection scheme. This function does not operate for the loss of a single-phase VT supply
      but only operates for the loss of all three phases after a predetermined period. The
      undervoltage protection function trips the generator for a sustained under voltage condition.
      The protection elements are energized from voltage transformers with secondary of 110 V
PART C3: SCOPE OF WORK                           PAGE 22      C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                          CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
     phase-to-phase and 63.5 V phase-to-neutral. The elements are adjustable to operate in the
     voltage ranges specified in Schedule A and have drop-off/pick-up ratios greater than 95%.
     Setting adjustment is preferably continuously variable, but if adjusted in steps, these do not
     exceed 10%. The time delay is adjustable over the range specified in Schedule A in
     Appendix 2 of Part 3B.
     Other functions required in the diesel generator protection scheme such as current interlock,
     long starting time, etc. are indicated in Schedule A in Appendix 2 of Part 3B.
       The system protects the segregated breaker, busbar and cable chamber respectively in the
       case of an internal arc fault for air insulated MV switchgear.
       The main protection device is mounted on the board incomer panels with the auxiliary
       devices in different panels as required.
       An overcurrent or earth fault signal is activated once the current on any one phase exceeds
       the reference values. This function has the capability to capture and display the three
       phase currents that caused the protection operation. The system is able to provide arc
       protection with low fault currents as well (i.e. smaller than 4 kA fault current).
PART C3: SCOPE OF WORK                            PAGE 23     C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                          CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
       The circuit breaker failure protection facility is provided by the arc protection system to trip
       the upstream feeder circuit breaker in case of an incomer breaker failure. A time delay of
       100 ms is allowed for the main circuit breaker to operate before the breaker fail protection
       operates the upstream circuit breaker. The total tripping time does not exceed the
       switchgear internal arc test time, Tt (as defined in IEC 62271-200).
       The function of this application is to detect and clear internal arc faults in the busbar
       chamber on a particular board. When any of the light sensors on the board detect an arc
       together with an overcurrent or earth fault current on the incomer feeder, it trips the incomer
       feeder, bus section breaker and all the feeder circuit breakers of the relevant zone.
       The internal arc detection devices are applied to overlap in the bus section chamber, thus
       tripping only the faulty zone for an internal arc fault in the bus section chamber.
       The function of this application is to detect and clear internal arc faults in the circuit breaker
       chamber. Where multiple tripping is required the arc sensing devices detect an arc together
       with an overcurrent or earth fault current from the incomer feeder, it trips the incomer
       feeder, bus section breaker and all the feeder circuit breakers of the relevant zone.
6.10.6.1 Feeders
            The function of this application is to detect and clear internal arc faults in the feeder
            cable chamber. Where multiple tripping is required the arc sensing devices detect an
            arc together with an over current or earth fault current from the incomer feeder it trips
            the incomer feeder, bus section breaker and all the feeder circuit breakers of the
            relevant zone.
6.10.6.2 Incomers
            The function of this application is to detect and clear internal arc faults in the incomer
            cable chamber. Where multiple tripping is required the arc sensing devices detect an
PART C3: SCOPE OF WORK                          PAGE 24      C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                        CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
           arc together with an over current from the upstream feeder it trips the upstream feeder
           circuit breaker.
     The bus zone protection scheme is designed to protect the breaker, busbar and cable
     chamber respectively in the case of a three phase bolted fault for air insulated MV
     switchgear. The protection scheme is based on basic operation principles of low impedance
     differential current measuring system.
     The function of the bus zone protection system is to perform fast clearance of phase to
     phase and phase to earth faults. The supply breaker and all feeder breakers are tripped in
     the event of a fault and current exceeding a pre-set reference value.
     A check feature such as integral circuit supervision is included to prevent tripping of bus-
     zone protection if any of the current transformer circuits become disconnected during normal
     load conditions. Alarm contacts operate under these conditions to initiate a remote alarm.
     A testing system, consisting of current isolation and measuring facilities at the input from
     each current transformer, and facilities for short-circuiting the current transformer circuits,
     when they are isolated from the protection system, is included.
     The detailed system description (i.e. specification, layouts and circuit diagrams) and test
     procedures for the bus-zone protection system is provided in the tender documents.
     The Project Manager may request the Contractor to check whether the bus zone protection
     is stable under external fault conditions.
     The protection CT core is fed onto standard switchgear terminals and then to the CT test
     block and protection device measuring elements with overlapping of the bus section CT
     cores.
     The boards requiring single or double zone tripping are indicated in the Appendix 3 of Part
     3B.
PART C3: SCOPE OF WORK                            PAGE 25   C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                        CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
     DC Fail function is provided to monitor the DC supplies of all the protection schemes at the
     last supply point. This functionality can either be incorporated in the IED, if a separate power
     supply is available, or a dedicated auxiliary relay.
     The function allows for operating on loss of DC voltage. Alarm output signal is also
     transmitted to the DCS system and indicated on the IED, if separate suppliers are used.
    In addition to IEDs provided for MV Switchgear, the Contractor supplies the IEC 61850
    compliant IEDs for incomer and bus section circuits of the following LV Switchgear Boards:
    Generic technical requirements of these IEDs are as per section 3 and 5.1 of this Works
    Information (Part 3B). However the design functionality, descriptions, schematic drawings and
    protection settings for the specific circuits are provided by Others. The Contractor uses the
    information provided by Others to design, program and configure IEDs in such a manner that
    they function according to the design. The Contractor also configures the IEDs to interface
    with SAS network. Physical installation of these IEDs into the LV Switchgear panels is the
    responsibility of Others. The configuration of the IED, FAT, SAT, routing and termination of
    SAS fibre optic cables are the responsibility of the Contractor.
PART C3: SCOPE OF WORK                         PAGE 26      C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                         CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
    The standard circuit design facilitates the integration of signals from the CTs and VTs and the
    interface with circuit breakers to perform various functions such as protection, control, alarm
    and monitoring.      The IED that can perform at least control, indication and protection
    functionalities is used. The IED is also linked to the circuit breakers and earth switches for
    inter-tripping and interlocking functions where required.
    The control circuit design for the different types of feeders is described by Typical Schematic
    Diagrams listed in section 12 of Part 3B. The typical design includes functions for Supply
    Point, Control Trip, Control Close and Indication and DCF as shown in Figure 1 below.
The 220V DC control circuit design has the following functions as a minimum:
    The control circuit is protected as per proven Eskom practice. The Contractor ensures that
    there is adequate co-ordination grading between the mcbs in the control circuit and also the
    feeder from the DC supply. Example of the graded system of the mcbs used for the protection
    of the control circuit is as follows (as shown in Figure 1):
PART C3: SCOPE OF WORK                          PAGE 27      C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                          CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
    The designs of the components in the circuit breaker control circuits takes into account the
    control philosophies for closing and tripping the individual devices. The circuit is typically
    supplied from a 32 A power supply fed from the 220V DC external supply.
    The control trip is the most important function of the control circuit and is supplied first,
    protected with a 16A protection device.            Should a fault downstream in the close or
    indication and DC fail function appear, the protection would protect the control trip from
    losing power. Typical trip coil inrush current is 2.8A (maximum), which will give a safety factor
    of 5 on the 16A circuit protection rating.
    The control close is more important than the indication and should a downstream fault in the
    indication and DC fail function appear the protection would protect the control close from
    losing power. Typical close coil inrush current is 2.8A (maximum), which will give a safety
    factor of 2 on the 6A circuit protection rating.
    The indication and DC fail have the lowest protection rating.         Should any upstream mcb
    operate, the DC fail operates and a DC fail alarm is activated but no operation of any
    protection function should take place.
    The control circuits is designed to make allowance for the alarm signals to be sent to the C&I
    system in accordance with the requirements described by the C&I Interface Signals for MV
    Switchgear in Appendix 4A of Part 3B.
    External 220V DC power supply is provided for the switchgear control circuit. This is used to
    provide power to the protection devices as well as the spring re-charge motors.
    The design of the switchgear is such that a failure and restoration of the 220V DC control
    supply voltage would not cause the complete isolation of the switchgear. It is required that two
    trip coils are used on each of the Unit Transformer Incomer Breaker and other panels as
    indicated in the Switchgear Schedules in Part 3A Appendix 3 of this Works Information.
PART C3: SCOPE OF WORK                           PAGE 28      C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                        CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
    Application of surge suppression units for control circuits, where required, is in accordance
    with 240-56227573.
    The Contractor provides a detailed description including formulas and diagrams of the
    algorithms used to perform the protection functions to the Project Manager. This information is
    treated as strictly confidential. This information is provided for all protection scheme
    developments.
    The Contractor provides a comprehensive set of blank forms and example setting details to
    cover all user settable configurations/functions in the module to the Employer.
    The IED marshalling is seen as part of the scheme as it is imperative that it is in accordance
    with the scheme design in order for the scheme to function correctly. All settings/marshalling
    related to the different protection schemes is pre-programmed at the factory and all IEDs are
    delivered pre-programmed in accordance with the scheme design.
    The final protection settings for the relays will be provided by the Employer for the Contractor
    to implement. In case the settings are not available at the time of Factory Acceptance Tests
    (FATs), the Contractor develops the preliminary settings for the purpose of testing. These
    settings are accepted by the Project Manager.
    The settings/marshalling are seen as integral parts of the scheme documentation. They are
    provided as part of the documentation as well as in software format in the file type as required
    by the associated IED.
    The different operating conditions (i.e. normal and abnormal) that are monitored by the
    protection schemes initiate different alarms. These alarms are communicated between IEDs,
    SAS and DCS via dedicated hardwired and communication bus links. The description of the
    concept proposed for the communication network is described on Part 3C of this Works
    Information.
PART C3: SCOPE OF WORK                        PAGE 29      C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                       CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
    The interface between the IEDs on the switchgear and the operating and engineering stations
    are facilitated by an Ethernet based Local Area Network (LAN) using IEC 61850 protocol as
    described in Part 3C of this Works Information.
    Data transfer between IEDs and DCS is done using hard wiring method and in accordance
    with C&I Interface Signals for MV Switchgear spreadsheet provided in Appendix 4A of Part
    3B. The signal descriptions can be found in Appendix 4B of Part 3B.
    Safety trip signals (e.g. Boiler trip, conveyor trip, etc.) issued from the DCS are done via
    interposing relays with potential free contacts. The operating voltage of the interposing relays
    is 24V DC. The interposing relays are designed to withstand the rated current of the closing
    coil for two times the longest possible closing time. SIL 3 rating interposing relays in
    accordance with the requirements of IEC 61511 are required. The interposing relay is also
    designed to withstand the making of the closing coil current at maximum system voltage
    rating.
PART C3: SCOPE OF WORK                        PAGE 30     C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                      CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
    The Contractor complies with all standards, specifications and regulations as part of 240-
    56227573 and the following standards as highlighted within this Works Information:
PART C3: SCOPE OF WORK                          PAGE 31   C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                       CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
12 List of Drawings
PART C3: SCOPE OF WORK                        PAGE 32      C3.2 ECC3 CONTRACTORS WORKS INFORMATION
ESKOM HOLDINGS SOC LIMITED                                     CONTRACT NUMBER: __________________
PART 3B: TUTUKA PS MV SWITCHGEAR REPLACEMENT PROJECT
13 List of Appendices
PART C3: SCOPE OF WORK PAGE 33 C3.2 ECC3 CONTRACTORS WORKS INFORMATION