Sample CM Contract
Sample CM Contract
PROJECT NO:
STATE MV DESIGNATION:
CONSTRUCTION MANAGER:
ARCHITECT-ENGINEER:
                                      Charlie Crist
                                       Governor
                                      Linda H. South
                                         Secretary
    CM Contract
                                             FORM OF AGREEMENT
                                   BETWEEN OWNER AND CONSTRUCTION MANAGER
 THIS AGREEMENT made this           day of        (month)        in the year Two Thousand Seven by and between Real
 Estate Development and Management, Department of Management Services, State of Florida, hereinafter called the Owner, and
                                                  ARTICLE 1
                               THE CONSTRUCTION TEAM AND EXTENT OF AGREEMENT
 The Construction Manager accepts the relationship of trust and confidence established between him and the Owner by this
 Agreement. He covenants with the Owner to furnish his best skill and judgment and to cooperate with the Architect-Engineer in
 furthering the interests of the Owner. He agrees to furnish efficient business administration and superintendence and use his best
 efforts to complete the project in the best and soundest way and in the most expeditious and economical manner consistent with the
 interest of the Owner.
 1.1        The Construction Team - The Construction Manager, the Owner and the Architect-Engineer, called the "Construction
            Team", shall work jointly during design and through final construction completion and shall be available thereafter
            should additional services be required. The Architect-Engineer will provide leadership during the Preconstruction
            Phase with support from the Construction Manager and the Construction Manager shall provide leadership to the
            Construction Team on all matters relating to construction.
The specific representatives of the Construction Team are shown in Exhibit A attached.
1.2         Extent of Agreement - This Agreement for "                              (Project Name/Number)                           ,"
            between the Owner and the Construction Manager supersedes any prior negotiations, representations or agreements.
            When drawings, specifications and other descriptive documents defining the work to be included under a construction
            authorization are substantially complete, they shall be identified in the construction authorization issued by the Project
            Director. When drawings, specifications and other descriptive documents defining the work to be included in the
            guaranteed maximum price (GMP) are sufficiently complete, an Amendment to the Agreement shall be signed by the
            Owner and Construction Manager, acknowledging the GMP amount and the drawings, specifications and other
            descriptive documents upon which the GMP is based. To expedite the preparation of this GMP Amendment by the
            Owner, the Construction Manager shall obtain three (3) sets of signed, sealed and dated drawings, specifications and
            other documents upon which the GMP is based from the Architect-Engineer, shall acknowledge on the face of each
            document of each set that it is the set upon which he based his GMP and shall send one set of the documents to the
            Owner's Contracts Administrator along with his GMP proposal, while keeping one set for himself and returning one set
            to the Architect-Engineer. The GMP Proposal shall include the following sections:
            This Agreement shall not be superseded by any provisions of the documents for construction and may be amended only
            by written instrument signed by both Owner and Construction Manager.
1.3 Definitions:
            Construction Authorization  The term Construction Authorization shall mean a written work order based on a defined
            scope of work excluding Construction Managers fees as specified in Article 8, prepared by the Project Director and
            issued to the Construction Manager. Construction Authorizations shall be used prior to the date of the GMP
            Amendment and all work performed pursuant to Construction Authorizations shall be included in the GMP
                                                                   1                                                          Rev. 9/07
           Construction Manager -             (Construction Manager Name/Address)
Estimate - The Construction Manager's latest estimate of probable project construction cost.
           Owner - The State of Florida, Department of Management Services, Real Estate Development and Management, acting
           through its Secretary or those persons designated by the Secretary to act in his behalf, as Agent for the (Agency)
           pursuant to the Client agreement dated      (Date)           . The entity that will occupy, use and own the project upon
           substantial completion is the Ownerentity. The funds with which the compensation of the architects, engineers,
           Construction Managers, etc. will be paid are under the control of the Ownerentity, based on approval of each
           payment by Real Estate Development and Management. All duties of Owner hereinafter shall be performed by Real
           Estate Development and Management.
Permitting Authority - The local authority with jurisdiction over the area in which the project is located.
           Project - The Project is the total work to be performed under this Agreement. The Project consists of permitting,
           construction and code inspection for "               (Project Name/Number)                         " necessary to
           build the component parts of the project identified in Exhibit B.
           Project Director - The person designated by the Owner to provide direct interface with the Construction Manager with
           respect to the Owner's responsibilities. (See Exhibit A)
1.4        Owner's Construction Budget: Owner's funds budgeted and requested for construction of the Project. The Owner's
           Construction Budget is   (Amount)       identified in Exhibit B, including all Construction Manager fees, costs of the
           work and the Owner's and Construction Manager's construction and interface contingencies as defined in Articles 8 and
           9. This acknowledgement of the Owner's budgeted funds is not to be construed as the Construction Manager's
           Guaranteed Maximum Price. A Guaranteed Maximum Price will be offered by separate documentation as outlined in
           Article 7.
                                                    ARTICLE 2
                                         CONSTRUCTION MANAGER'S SERVICES
The services which the Construction Manager shall provide include, but are not limited to, those described or specified herein. The
services described or specified shall not be deemed to constitute a comprehensive specification having the effect of excluding
services not specifically mentioned.
2.1.1 General:
           (1)    Commencing immediately after contract award, the Construction Manager shall implement and shall utilize
                  throughout the life of this Contract all subsystems of the Project Management Information System hereinafter
                  referred to as PMIS.
           (2)    The reports, documents, and data to be provided shall represent an accurate assessment of the current status of
                  the Project and of the work remaining to be accomplished and it shall provide a sound basis for identifying
                  variances and problems and for making management decisions. It shall be prepared and furnished to the Owner
                  and the Architect-Engineer monthly and shall accompany each pay request.
           (3)    If requested by the Project Director, the Construction Manager shall conduct a comprehensive workshop in
                  Tallahassee for participants designated by the Project Director and additional seminars as required to provide
                  instruction. This workshop and the seminars shall facilitate each participant's and the Owner's representatives'
                  use and understanding of PMIS; shall support, in-part, the function of organizing in concert with the Architect-
                  Engineer for the design and construction of the Project; and shall establish, with the full concurrence of the
                  Owner and the Architect-Engineer, procedures for accomplishing the management control aspect of the Project.
           (4)    The PMIS shall be described in terms of the following major subsystems:
                  (a) Narrative Reporting, on a monthly basis,
                  (b) Schedule Control, on a monthly basis,
                  (c) Cost Control, and estimating,
                  (d) Project Accounting,
                  (e) Accounting and Payment, and
                  (f) Action Reports.
                                                                    2                                                      Rev. 9/07
2.1.2   NARRATIVE REPORTING SUBSYSTEM
        (1)   The Construction Manager shall prepare written reports as described hereunder. No other PMIS narrative reports
              shall be required. All reports shall be in 8 1/2" X 11" format.
(2) The Narrative Reporting Subsystem shall include the following reports:
              (a) A Monthly Executive Summary which provides an overview of current issues and pending decisions, future
                  developments and expected achievements, and any problems or delays, including code violations found by
                  Permitting Authority.
(b) A Monthly Cost Narrative describing the current construction cost estimate status of the Project.
              (c) A Monthly Scheduling Narrative summarizing the current status of the overall project schedule. This report
                  shall include an analysis of the various project schedules, a description of the critical path, and other analyses
                  as necessary to compare planned performance with actual performance.
              (d) A Monthly Accounting Narrative describing the current cost and payment status of the entire project. This
                  report shall relate current encumbrances and expenditures to the budget allocations.
              (e) A Monthly Construction Progress Report during the construction phase summarizing the work of the various
                  subcontractors. This report shall include information from the weekly job site meetings as applicable such as
                  general conditions, long lead supplies, current deliveries, safety and labor relations programs permits,
                  construction problems and recommendations, and plans for the succeeding month.
(f) A Daily Construction Diary during the construction phase describing events and conditions on the site.
              (g) A monthly Minority Business Enterprise report during the construction phase summarizing the participation
                  of certified minority subcontractors/material suppliers for the current month, and project to date. The report
                  shall include the names, addresses, and dollar amount of each certified MBE participant.
              (h) A Contractors Minority Business Enterprises Status Report of Partial Payment form is attached to this
                  Agreement as Exhibit L and is to be completed and submitted with each pay request.
              (i) Construction Manager shall implement a direct tax savings purchase plan approved by the Department of
                  Revenue that, upon acceptance, will be part of the Construction Managers services.
        (3)   The reports outlined in subsection (2)(a) through (e) above shall be bound with applicable computer reports and
              submitted monthly during design and construction phases and shall be current through the end of the preceding
              month. Copies shall be transmitted to the Owner and the Architect-Engineer and others designated by the Project
              Director with the monthly pay requisition.
              Additional copies of the report outlined in subsection (2)(a) shall be bound separately and distributed monthly as
              directed by the Project Director.
        (4)   The report outlined in subsection (2)(f) above shall be maintained at the site available to the Owner and
              Architect-Engineer. A copy, bound, of the complete diary shall be submitted to the Owner at the conclusion of
              the project.
        (l)   Master Project Schedule - Upon award of this Contract, the Construction Team, shall submit a master project
              schedule covering the planning and design approvals, construction and Owner occupancy of the Project. This
              schedule will serve as the framework for the subsequent development of all detailed schedules. The master
              project schedule shall be produced and updated monthly throughout the project.
        (2)   Construction Schedule And Requirements For Overtime Work For Projects With Construction Costs In Excess of
              $5,000,000.00 Within thirty (30) days after the date of the Owner's issuance of a Notice to Proceed, the
              Construction Manager shall prepare and submit to the Architect-Engineer a construction schedule in
              quadruplicate graphically depicting the activities contemplated to occur as a necessary incident to performance of
              the work required to complete the project, showing the sequence in which the Construction Manager proposes for
              each such activity to occur and duration (dates of commencement and completion, respectively) of each such
              activity. An example of an acceptable form of such a construction schedule is contained in Appendix I of the
              Corps of Engineers' Regulation ER 1-1-11 entitled "Network Analysis System", a copy of which is available to
              the Construction Manager from the Architect-Engineer, upon request. Another form of construction schedule
                                                                3                                                           Rev. 9/07
              which provides the same kind of information and employs the same basic principles as illustrated in Appendix I
              of the Corps of Engineers' Regulation ER 1-1-11 will be acceptable to the Owner if used by the Construction
              Manager; provided, however, that the Architect-Engineer shall determine whether the construction schedule
              developed and submitted by the Construction Manager meets the requirements stated above and such
              determination shall be binding on the Construction Manager. Failure of the Construction Manager to develop
              and submit a construction schedule as aforesaid shall be sufficient grounds for the Architect-Engineer to find the
              Construction Manager in substantial default and certify to the Owner that sufficient cause exists to terminate the
              contract or to withhold any payment.
              Following development and submittal of the construction schedule as aforesaid, the Construction Manager shall,
              at the end of each calendar month occurring thereafter during the period of time required to finally complete the
              subject project, or at such earlier intervals as circumstances may require, update and/or revise the construction
              schedule to show the actual progress of the work performed and the occurrence of all events which have affected
              the progress of performance of the work already performed or will affect the progress of the performance of the
              work yet to be performed in contrast with the planned progress of performance of such work, as depicted on the
              original construction schedule and all updates and/or revisions thereto as reflected in the updated and/or revised
              construction schedule last submitted prior to submittal of each such monthly update and revision. Each such
              update and/or revision to the construction schedule shall be submitted to the Architect-Engineer in duplicate.
              Failure of the Construction Manager to update, revise, and submit the construction schedule as aforesaid shall be
              sufficient grounds for the Architect-Engineer to find the Construction Manager in substantial default and certify
              to the Owner that sufficient cause exists to terminate the Contract or to withhold payment to the Construction
              Manager until a schedule or schedule update acceptable to the Architect-Engineer is submitted.
        (3)   The Construction Manager shall prepare and incorporate into the schedule data base, at the required intervals, the
              following schedules:
              (a) Pre-Bid Schedules (Subnetworks) - The Construction Manager shall prepare a construction schedule for
                  work encompassed in each bid package. The schedule shall be sufficiently detailed as to be suitable for
                  inclusion in the bid package as a framework for contract completion by the successful bidder. It shall show
                  the interrelationships between the work of the successful bidder and that of other subcontractors, and shall
                  establish milestones keyed to the overall master schedule.
              (b) Subcontractor Construction Schedules (Subnetworks) - Upon the award of each sub-contract, the
                  Construction Manager shall jointly with the subcontractor, develop a schedule which is more detailed than
                  the pre-bid schedule included in the specifications, taking into account the work schedule of the other
                  subcontractors. The construction schedule shall include as many activities as necessary to make the schedule
                  an effective tool for construction planning and for monitoring the performance of the subcontractor. The
                  construction schedule shall also show pertinent activities for material purchase orders, manpower supply,
                  shop drawing schedules and material delivery schedules.
              (c) Occupancy Schedule - The Construction Manager shall jointly develop with the Architect-Engineer and
                  Owner a detailed plan, inclusive of punch lists pursuant to Section 255.077, Florida Statutes, final
                  inspections, maintenance training and turn-over procedures, to be used for ensuring accomplishment of a
                  smooth and phased transition from construction to Owner occupancy. The Occupancy Schedule shall be
                  produced and updated monthly from its inception through final Owner occupancy.
2.1.4   Cost Control Subsystem - The operation of this subsystem shall provide sufficient timely data and detail to permit the
        Construction Team to control and adjust the project requirements, needs, materials, equipment and systems by building
        and site elements so that construction will be completed at a cost which, together with all other project costs, will not
        exceed the maximum total project budget. Requirements of this subsystem include the following submissions at the
        following phases of the project:
Estimates
(a) At completion of Advanced Schematic Preconstruction Phase For Each Item Or Bid Package.
(b) At Completion of Design Development Phase For Each Item Or Bid Package.
(c) At Completion of 100% Construction Documents Phase For Each Item Or Bid Package.
        (e)   Construction Documents Estimates - Prior to the bid of each bid package, when the working drawings and
              specifications are complete, the Construction Manager shall prepare and submit a cost estimate on the basis of a
              quantitative material take-off with current local cost for each bid group by subcontract package.
                                                               4                                                         Rev. 9/07
2.1.5   Project Accounting Subsystem - The operation of this subsystem shall enable the Construction Team to plan effectively
        and to monitor and control the funds available for the project, cash flow, costs, change orders, payments, and other
        major financial factors by comparison of budget, estimate, total commitment, amounts invoiced, and amounts payable.
        This subsystem will be produced and updated monthly and includes the following reports which together will serve as a
        basic accounting tool and an audit trail. The Construction Manager will retain all project files in a manner consistent
        with proper accounting procedures that would be sufficient for an audit by the Owner for a period of 5 years after final
        completion of the project. This report will also provide for accounting by building and site element.
        (a)   Costs Status Report presenting the budget, estimate, and base commitment (awarded contracts and purchase
              orders) for any given contract or budget line item. It shall show approved change orders for each contract which
              when added to the base commitment will become the total commitment. Pending change orders will also be
              shown to produce the total estimated probable cost to complete the work.
        (b)   A Payment Status Report showing the value in place (both current and cumulative), the amount invoiced (both
              current and cumulative), the retained, the amount payable (both current and cumulative), and the balance
              remaining. A summary of this report shall accompany each pay request.
        (c)   A Detailed Status Report showing the complete activity history of each item in the project accounting structure.
              It shall include the budget, estimate and base commitment figures for each contract. It shall give the change
              order history including change order numbers, description, proposed and approved dates, and the proposed and
              approved dollar amounts. It shall also show all pending or rejected change orders.
        (d)   A Cash Flow Spreadsheet showing the projected accumulation of cash payments against the project. Cash flow
              projections shall be generated for anticipated monthly payments as well as cumulative payments.
        (e)   A Detailed Schedule of Values shall be maintained as necessary to supplement the operation of the project
              accounting subsystem. The detailed schedule of values will be used to provide construction cost accountability
              for general conditions work, on-site reimbursable expenses, and costs requiring accounting needs.
        (1)   Upon award of contract the Construction Manager shall develop a draft comprehensive Project Manual
              describing the services set forth in this Contract. This shall provide a plan for the control, direction, coordination
              and evaluation of work performed throughout the project organization including identification of Key personnel,
              responsibilities of Construction Manager, Owner and Architect-Engineer; work flow diagrams; and strategy for
              bidding the work. The Project Manual shall be updated as necessary throughout the design, construction and
              Owner occupancy phases. Five copies of the Project Manual and any updates shall be submitted to the Owner
              and Architect-Engineer. In developing the Project Manual, the Construction Manager shall coordinate with the
              Owner and the Architect-Engineer.
        (2)   Contents of Project Manual - The Project Manual shall describe in detail the procedures for executing the work
              and the organizations participating. The Project Manual shall include as a minimum the following sections:
              (a) Project Definition - The known characteristics of the project or subprojects shall be described in general
                  terms which will provide the participants a basic understanding of the project or sub-projects.
(b) Project Goals - The schedule, budget, physical, technical and other objectives for the project shall be defined.
              (c) Project Strategy - A narrative description of the project delivery methods shall be utilized to accomplish the
                  project goals.
              (d) Project Work Plan - A matrix display of the program of work to be performed by the Construction Manager,
                  the Architect-Engineer and the Owner during each phase of the project.
              (e) Project Organization - A summary organization chart showing the interrelationships between the Owner, the
                  Construction Manager and the Architect-Engineer, and other supporting organizations and permitting review
                  agencies. Detailed charts, one each for the Construction Manager, the Architect-Engineer, the Client Agency
                  and Owner showing organizational elements participating in the project shall be included.
              (f) Responsibility Performance Chart - A detailed chart showing the specific responsibilities and
                  interrelationships of the Owner, the Architect-Engineer, and Construction Manager. The Responsibility
                  Performance Chart shall indicate major responsibility, and minor responsibility, for each specific task
                  required to deliver the project. The Construction Manager shall develop a similar chart for the personnel
                  within his own organization who are assigned to the project, and also for the personnel of the Owner and the
                                                                5                                                           Rev. 9/07
                Architect-Engineer from data supplied by each.
            (g) Flow Diagrams - These charts shall display the flow of information and the decision process for the review
                and approval of shop drawings and submittals, progress and change orders.
            (h) Written Procedures - The Construction Manager will provide written procedures for communications and
                coordination required between Construction Team members throughout the project. Procedures shall cover
                such items as correspondence, minutes, reports, inspections, team meetings, technical reviews, design
                reviews, and other necessary communications.
      (1)   Review and Recommendations and Warranty. - The Construction Manager shall familiarize himself thoroughly
            with the evolving architectural, civil, mechanical, plumbing, electrical, and structural plans and specifications
            and shall follow the development of design from Preliminaries through Working Drawings. He shall make
            recommendations with respect to the selection of systems and materials, and cost reducing alternatives including
            assistance to the Architect-Engineer, and Owner in evaluating alternative comparisons versus long term cost
            effects. The evaluation shall speak to the benefits of the speed of erection and early completion of the project.
            He shall furnish pertinent information as to the availability of materials and labor that will be required. He shall
            submit to the Owner, Permitting Authority and Architect-Engineer such comments as may be appropriate
            concerning construction feasibility and practicality. He shall call to the Project Director's and the Architect-
            Engineer's attention any apparent defects in the design, drawings and specifications or other documents. He shall
            prepare an estimate of the construction cost utilizing the unit quantity survey method.
      (2)   Review Reports and Warranty - Within 45 days after receiving the Construction Documents for each phase of the
            project, the Construction Manager shall perform a specific review thereof, focused upon factors of a nature
            encompassed in Paragraph (1) above and on factors set out in Paragraph (5). Promptly after completion of the
            review, he shall submit to the Project Director and Permitting Authority, with copies to the Architect-Engineer, a
            written report covering suggestions or recommendations previously submitted, additional suggestions or
            recommendations as he may deem appropriate, and all actions taken by the Architect-Engineer with respect to
            same, any comments he may deem to be appropriate with respect to separating the work into separate contracts,
            alternative materials, and all comments called for under Article 2.3(5).
            DISCLAIMER OF WARRANTY: - THE OWNER DISCLAIMS ANY WARRANTY THAT THE PLANS
            AND SPECIFICATIONS FOR THE PROJECT ARE ACCURATE, PRACTICAL, CONSISTENT OR
            CONSTRUCTIBLE.
      (3)   Long Lead Procurements - The Construction Manager shall review the design for the purpose of identifying long
            lead procurement items (machinery, equipment, materials and supplies). When each item is identified, the
            Construction Manager shall notify the subcontractors, the Project Director and the Architect-Engineer of the
            required procurement and schedule. Such information shall be included in the bid documents and made a part of
            all affected sub-contracts. As soon as the Architect-Engineer has completed drawings and technical
            specifications and the Construction Manager has obtained permitting approval, the Construction Manager shall
            prepare invitations for bids. The Construction Manager shall keep himself informed of the progress of the
            respective subcontractors or suppliers, manufacturing or fabricating such items and advise Project Director,
            Owner and Architect-Engineer of any problems or prospective delay in delivery.
      (4)   Separate Contracts Planning - The Construction Manager shall review the design with the Architect-Engineer
            and make recommendations to the Owner and to the Architect-Engineer with respect to dividing the work in such
            manner as will permit the Construction Manager to take bids and award separate construction sub-contracts on
            the current schedule while the design is being completed. He shall take into consideration such factors as natural
            and practical lines of severability, sequencing effectiveness, access and availability constraints, total time for
            completion, construction market conditions, availability of labor and materials, community relations and any
            other factors pertinent to saving time and cost by overlapping design and construction that are authorized by the
            Owner.
                                                             6                                                          Rev. 9/07
(5)   Interfacing
      (a) The Construction Manager shall take such measures as are appropriate to provide that all construction
          requirements will be covered in the separate subcontracts for procurement of long lead items, the separate
          construction subcontracts and the general conditions items performed without duplication or overlap,
          sequenced to maintain completion of all work on schedule. Particular attention shall be given to provide that
          each bid package clearly identifies the work included in that particular separate subcontract, its schedule for
          start and completion and its relationship to other separate Construction Managers.
      (b) Without assuming any Design responsibilities of the Architect-Engineer, the Construction Manager shall
          include in the reports required under Article 2.3(2) comments on overlap with any other separate
          subcontracts, omissions, lack of correlation between drawings, and any other deficiencies noted, in order that
          the Project Director and Architect-Engineer may arrange for necessary corrections.
(6)   Job-Site Facilities - The Construction Manager shall arrange for all job-site facilities necessary to enable the
      Construction Manager and the Owner's representatives and the Architect-Engineer to perform their respective
      duties in the management, inspection, and supervision of construction.
      Tangible personal property, otherwise referred to as Job-Site facilities, include but are not limited to such things
      as trailers, toilets, typewriters, computers and any other equipment necessary to carry on the project. The method
      of acquiring such job-site facilities which are planned to become the property of the owner at the conclusion of
      the project shall be evaluated based on cost over the life of the project. Owning versus leasing shall be
      considered by the Construction Manager obtaining at least two (2) proposals for leasing and at least two (2)
      proposals for purchasing and then analyzing which is least expensive over the usage life of the item. The
      Construction Manager shall present his evaluation with recommendation to the owner for approval.
      When the Construction Manager wishes to supply Job-Site Facilities from his own equipment pool, he shall first
      evaluate buy versus lease as discussed in the paragraph above. If leasing is found to be the least expensive
      approach, then he may lease such Job-Site Facilities from his own equipment pool at a price not greater than the
      lowest of the three (3) lease proposals obtained.
      For all such facilities purchased which may become the property of the owner at the conclusion of the project,
      the Construction Manager shall maintain ownership responsibilities of such facilities until the project conclusion.
       Reimbursement for cost of such equipment will be made at the conclusion of the project at the documented
      purchase price. At that time, the Construction Manager shall provide the owner with a complete inventory for
      each unit of equipment. The inventory shall describe the equipment and identify the purchase price, serial
      number, model number and condition. Where said equipment has a title, said title shall be properly transferred to
      the Owner or to his designee.
      The Construction Manager is responsible for proper care and maintenance of all equipment while in his control.
      At the time of transfer to the owner, the owner may refuse acceptance of the equipment if the owner determines
      in its sole discretion that the equipment has not been properly cared for by the Construction Manager or that such
      acquisition would not otherwise be in the best interest of the Owner. In such event, the Construction Manager
      will be reimbursed for such item in accordance with Article 9.2(4) hereof.
(7)   Weather Protection - The Construction Manager shall ascertain what temporary enclosures, if any, of building
      areas should be provided for and may be provided as a practical matter, in order to assure orderly progress of the
      work in periods when extreme weather conditions are likely to be experienced. He shall submit to the
      Construction Team his recommendations as to needed requirements of this nature and as to the contract or
      contracts in which they should be included.
      (a) The Construction Manager shall monitor conditions in the construction market to identify factors that will or
          may affect costs and time for completing the project; he shall make analysis as necessary to (l) determine and
          report on availability of labor, material, equipment, potential bidders, and possible impact of any shortages or
          surpluses of labor or material, and (2) in light of such determinations, make recommendations as may be
          appropriate with respect to long lead procurement, separation of construction into bid packages, sequencing
          of work, use of alternative materials, equipment or methods, other economics in design or construction, and
          other matters that will promote cost savings and completion within the scheduled time.
      (b) Within 30 days after receiving Notice to Proceed, the Construction Manager shall submit a written
          "Construction Market Analysis and Prospective Bidders Report" setting out recommendations and providing
          information as to prospective bidders. As various bid packages are prepared for bidding, the Construction
          Manager shall submit to the Project Director and the Architect-Engineer a list of potential bidders. The
                                                       7                                                          Rev. 9/07
                Construction Manager shall be responsible to stimulate bidder interest in the local market place and identify
                and encourage bidding competition.
            (c) The Construction Manager shall carry out an active program of stimulating interest of qualified Construction
                Managers in bidding on the work and of familiarizing those bidders with the requirements of this project.
      (1)   Construction Manager's Staff - The Construction Manager shall maintain sufficient off-site support staff, and
            competent full time staff at the Project site authorized to act on behalf of the Construction Manager to coordinate,
            inspect and provide general direction of the work and progress of the subcontractors and he shall provide no less
            than those personnel during the respective phases of construction that are set forth in Exhibit "C" to this
            agreement. He shall not change any of those persons named in Exhibit "C" unless mutually agreed to by the
            Owner and Construction Manager. In such case, the Owner shall have the right of approval of the qualifications
            of replacement personnel. Such approval will not be unreasonably withheld.
      (2)   Lines of Authority - The Construction Manager shall establish and maintain lines of authority for his personnel,
            and shall provide this definition to the Owner and all other affected parties such as the code inspectors of the
            Permitting Authority, the sub-contractors, the Architect-Engineer and the Owner's representatives, to provide
            general direction of the work and progress of the various phases and subcontractors. The Owner and Architect-
            Engineer may attend meetings between the Construction Manager and his Subcontractors, however, such
            attendance shall not diminish either the authority or responsibility of the Construction Manager to administer the
            subcontractor.
      (3)   Schedule and Project Manual Provisions - The Construction Manager shall provide subcontractors and the
            Owner, its representatives and the Architect-Engineer with copies of the Project Manual (total number of copies
            not to exceed 10) developed and updated as required by Article 2.2 expanded for the Construction Phase
            employing their respective milestones, beginning and finishing dates, their respective responsibilities for
            performance and the relationships of their work with respect to subcontractors and suppliers. He shall also
            continue to provide current scheduling information and provide direction and coordination regarding milestones,
            beginning and finishing dates, responsibilities for performance and the relationships of the Construction
            Manager's work to the work of his subcontractors and suppliers to enable them to perform their respective tasks
            so that the development of construction progresses in a smooth and efficient manner in conformance with the
            overall project schedule. The schedule shall include all phases of the construction work, material supplies, long
            lease procurement, approval of shop drawings, change orders in progress, schedules for change orders, and
            performance testing requirements. He shall advise the Owner, its representatives and the Architect-Engineer of
            their required participation in any meeting or inspection giving each at least one week notice unless such notice
            is made impossible by conditions beyond his control. He shall hold job-site meetings at least once each month
            with the Construction Team and at least once each week with the subcontractors and the Architect-Engineer's
            Field Representative, or more frequently as required by work progress, to review progress, discuss problems and
            their solutions and coordinate future work with all subcontractors.
            (a) Without assuming responsibilities of the Architect-Engineer, and unless waived in writing by the Owner, the
                Construction Manager shall prepare invitations for bids, or requests for proposal when applicable, for all
                procurements of long lead items, materials and services, and for Subcontractor contracts. Such invitations
                for bids shall be prepared in accordance with the following guidelines:
                1.    Contracts over $1,000 but not exceeding $10,000 may be entered into by the Construction Manager
                      with the firm which submits the lowest verbal quotation. The Construction Manager shall obtain a
                      minimum of two (2) verbal quotations. These quotations shall be entered on a bid tabulation sheet and
                      a copy of such tabulation sent to the Owner, Architect-Engineer and to each firm. The successful
                      quotation shall be confirmed by written contract or purchase order to the low bid firm defining the
                      scope and quality of work to be provided.
                2.    Contracts exceeding $10,000 but not exceeding $200,000 may be entered into by the Construction
                      Manager with the firm who is qualified and submits the lowest responsive proposal. The Construction
                      Manager shall request at least three (3) firms to submit sealed written proposals based on a written
                      drawings and/or specification. The written proposals shall all be opened publicly at the location, date
                      and time named by the Construction Manager in his request for proposal. A tabulation of the results
                      shall be furnished to the Owner, Architect-Engineer and to each firm.
                3.    Contracts exceeding $200,000 but not exceeding $500,000 may be entered into by the Construction
                      Manager with the firm who is qualified and submits the lowest responsive proposal. The Construction
                                                             8                                                          Rev. 9/07
               Manager shall advertise these projects at least once with the last advertisement appearing at least 21
               calendar days prior to the established bid opening date. These proposals shall be based on approved
               plans and specifications. Bids shall be received and opened publicly at the location, date and time
               established in the bid advertisement.
          4.   Contracts exceeding $500,000 shall be treated the same as described under 3 above except that the
               advertisement shall be run for at least 30 days prior to the established bid opening and at least 5 days
               prior to any scheduled pre-bid conference.
          5.   Individual purchases of materials or rentals or leases of equipment amounting to less than $1,000.00
               each may be made without bids or quotes when reasonably necessary to expedite work on the project,
               however, the Construction Manager shall not divide or separate a procurement in order to avoid the
               requirements set forth above.
6. Site utilities may be acquired at market rates from the entity(ies) providing such in the franchise area.
      (b) As part of such preparation, the Construction Manager shall review the specifications and drawings prepared
          by the Architect-Engineer. Ambiguities, conflicts or lack of clarity of language, use of illegally restrictive
          requirements, and any other defects in the specifications or in the drawings noted by the Construction
          Manager shall be brought to the attention of the Project Director and Architect-Engineer in written form.
      (c) For each separate construction contract exceeding $25,000, the Construction Manager shall, unless waived
          by Owner, conduct a pre-bid conference with prospective bidders, the Architect-Engineer and Project
          Director. In the event questions are raised which require an interpretation of the bidding documents or
          otherwise indicate a need for clarification or correction of the invitation, the Construction Manager shall
          transmit these to the Architect-Engineer and upon receiving clarification or correction in writing shall
          prepare an addendum to the bidding document, and issue same to all of the prospective bidders.
      (d) For all contracts exceeding $25,000, the Construction Manager shall establish a pre-qualification procedure
          for applicable subcontract trades.
(5)   Bonds - In accordance with the provisions of Section 255.05, Florida Statutes, the Construction Manager shall
      provide to the Owner, on forms furnished by the Owner, a 100% Performance Bond and a 100% Labor and
      Material Payment Bond each in an amount not less than the total construction cost as defined in Article 9 and
      inclusive of the Construction Manager's fees. To be acceptable to the Department of Management Services as
      Surety for Performance Bonds and Labor and Material Payment Bonds, a Surety Company shall comply with the
      following provisions:
      1. The Surety Company shall have a currently valid Certificate of Authority, issued by the State of Florida,
         Department of Financial Services, Office of Insurance Regulation, authorizing it to write surety bonds in the
         State of Florida.
      2. The Surety Company shall have currently valid Certificate of Authority issued by the United States
         Department of Treasury under Sections 9304 to 9308 of Title 31 of the United States Code.
3. The Surety Company shall be in full compliance with the provisions of the Florida Insurance Code.
      4. The Surety Company shall have at least twice the minimum surplus and capital required by the Florida
         Insurance Code at the time the invitation to bid is issued.
      5. If the Contract Award Amount exceeds $500,000, the Surety Company shall also comply with the following
         provisions:
          A.   The Surety Company shall have at least the following minimum ratings in the latest issue of Best's Key
               Rating Guide.
                                                            POLICYHOLDER'S                   REQUIRED
               CONTRACT AMOUNT                                  RATING                 FINANCIAL RATING
               $ 500,000 TO       1,000,000                          A-                        CLASS I
                1,000,000 TO      2,000,000                          A-                        CLASS II
                2,000,000 TO      5,000,000                          A-                        CLASS III
                5,000,000 TO 10,000,000                              A-                        CLASS IV
               10,000,000 TO 25,000,000                              A-                        CLASS V
               25,000,000 TO 50,000,000                              A-                        CLASS VI
               50,000,000 TO 100,000,000                             A-                        CLASS VII
               50,000,000 TO 100,000,000                             A-                        CLASS VII
                                                       9                                                           Rev. 9/07
            B.   The Surety Company shall not expose itself to any loss on any one risk in an amount exceeding ten
                 (10) percent of its surplus to policyholders, provided:
                 (a)   Any risk or portion of any risk being reinsured shall be deducted in determining the limitation of
                       the risk as prescribed in this section. These minimum requirements shall apply to the reinsuring
                       carrier providing authorization or approval by the State of Florida, Department of Financial
                       Services, Office of Insurance Regulation to do business in this state have been met.
                 (b)   In the case of the surety insurance company, in addition to the deduction for reinsurance, the
                       amount assumed by any co-surety, the value of any security deposited, pledged or held subject to
                       the consent of the surety and for the protection of the surety shall be deducted.
(6)   Quality Control - The Construction Manager shall develop and maintain a program, acceptable to the Owner and
      Architect-Engineer, to assure quality control of the construction. He shall supervise the work of all
      subcontractors providing instructions to each when their work does not conform to the requirements of the plans
      and specifications and he shall continue to exert his influence and control over each subcontractor to ensure that
      corrections are made in a timely manner so as to not affect the efficient progress of the work. Should
      disagreement occur between the Construction Manager, the Owner or the Architect-Engineer over acceptability
      of work and conformance with the requirements of the specifications and plans, the Owner shall be the final
      judge of performance and acceptability.
(7)   Subcontractor Interfacing - The Construction Manager shall be the single point of interface with all
      subcontractors for the Owner and all of its agents and representatives including the Architect-Engineer. He shall
      negotiate all change orders, field orders and request for proposals, with all affected subcontractors and shall
      review the costs of those proposals and advise the Owner and Architect-Engineer of their validity and
      reasonableness, acting in the Owner's best interest prior to requesting approval of each change order from the
      Owner. Before any work is begun on any change order, a written authorization from the Owner must be issued.
      However, when health and safety are threatened, the Construction Manager shall act immediately to remove the
      threat to health and safety. He shall also carefully review all shop drawings and then forward the same to the
      Architect-Engineer for review and actions. The Architect-Engineer will transmit them back to the Construction
      Manager who will then issue the shop drawings to the affected subcontractor for fabrication or revision. The
      Construction Manager shall maintain a suspense control system to promote expeditious handling. He shall
      request the Architect-Engineer to make interpretations of the drawings or specifications requested of him by the
      subcontractors and shall maintain a suspense control system to promote timely response. He shall advise the
      Project Director and Architect-Engineer when timely response is not occurring on any of the above.
(8)   Permits - The Construction Manager shall secure all necessary building permits from the Permitting Authority
      and all necessary utility connection permits, the cost of which will be considered a direct cost item.
      (a) The Construction Manager shall provide for each of the following activities as a part of his Construction
              Phase fee:
1. Maintain a log of daily activities, including manpower records, weather, delays, major decisions, etc.
2. Maintain a roster of companies on the project with names and telephone numbers of key personnel.
3. Establish and enforce job rules governing parking, clean-up, use of facilities and worker discipline.
            5.   Provide a safety program for the project to meet OSHA requirements. Monitor for subcontractor
                 compliance without relieving them of responsibilities to perform work in accordance with the best
                 acceptable practice.
            7.   Miscellaneous office supplies that support the construction efforts which are consumed by his own
                 forces.
8. Travel to and from his home office to the project site and Tallahassee as the project requires.
(b) The Construction Manager shall provide personnel and equipment or shall arrange for separate
                                                        10                                                         Rev. 9/07
                subcontracts to provide each of the following as a direct cost item:
           1.   Schedule the services of independent testing laboratories and provide the necessary testing of materials
                to ensure conformance to contract requirements.
           2.   The printing and distribution of all required bidding documents and shop drawings, including the sets
                required by the Permitting Authority's inspectors.
(10)   Job Site Administration - The Construction Manager shall provide as part of his construction phase fee, job site
       administrative functions during construction to assure proper documentation, including but not limited to such
       things as the following:
       (a) Job Meetings - Hold weekly progress and coordination meetings to provide for an easy flowing project.
           Implement procedures and assure timely submittals, expedite processing approvals and return of shop
           drawings, samples, etc. Coordinate and expedite critical ordering including direct tax saving purchases and
           delivery of materials, work sequences, inspection and testing, labor allocation, etc. Review and coordinate
           each subcontractor's work. Review and implement revisions to the Schedule. Monitor and promote safety
           requirements. In addition, regular project status meetings will be held between the architect, owner and
           Construction Manager either biweekly or monthly, whichever is designated by the Project Director.
           Use the job site meeting as a tool for preplanning of work and enforcing schedules and for establishing
           procedures, responsibilities, and identification of authority for all to clearly understand.
           Identify party or parties responsible for follow up on any problems, delay items or questions and record
           course for solution. Revisit each pending item at each subsequent meeting until resolution is achieved.
           Require all present to make any problems or delaying event known to those present for appropriate attention
           and resolution.
       (b) Shop Drawing Submittals/Approvals - Provide staff to check shop drawings and to implement procedures for
           submittal and transmittal to the Architect-Engineer of such drawings for action, and closely monitor their
           submittal and approval process.
       (c) Material and Equipment Expediting - Provide staff to closely monitor material and equipment deliveries,
           critically important checking and follow-up procedures on supplier commitments of all subcontractors.
       (d) Payments to subcontractors - Develop and implement a procedure for review, processing, and payment of
           applications by subcontractors for progress and final payments.
       (e) Document Interpretation - Refer all questions for interpretation of the documents prepared by the Architect-
           Engineer to the Architect-Engineer.
       (f) Reports and Project Site Documents - Record the progress of the project. Submit written progress reports to
           the Owner and the Architect-Engineer including information on the subcontractor's work, and the percentage
           of completion. Keep a daily log available to the Owner, the Architect-Engineer and the Permitting Authority
           inspectors.
       (g) Subcontractor's Progress - Prepare periodic punch lists for subcontractor's work including unsatisfactory or
           incomplete items and schedules for their completion.
       (h) Substantial Completion - Ascertain when the work or designated portions thereof are ready for the Architect-
           Engineer's substantial completion inspection. From the Architect-Engineer's list of incomplete or
           unsatisfactory items, prepare a schedule for their completion indicating completion dates for the Owner's
           review. If the Construction Manager wishes the Architect-Engineer to conduct a pre-substantial completion
           inspection in conjunction with his own forces, the Architect-Engineer will prepare the presubstantial punch
           list from which the Construction Manager will develop a completion schedule. The Architect-Engineer will
           issue a certificate of substantial completion when the work on his presubstantial punch list has been
           accomplished (See Exhibit D).
       (i) Final Completion - Monitor the Subcontractor's performance on the completion of the project and provide
           notice to the Owner and Architect-Engineer that the work is ready for final inspection. Secure and transmit
           to the Owner, through the Architect-Engineer, all required guarantees, affidavits, releases, bonds and
           waivers, manuals, record drawings, and maintenance books including the Final Completion form shown in
           Exhibit E.
(j) Start-Up - With the Owner's personnel, direct the checkout of utilities, operations, systems and equipment for
                                                       11                                                        Rev. 9/07
           readiness and assist in their initial start-up and testing by the trade Construction Managers.
       (k) Record Drawings - During the progress of the work, the Construction Manager shall require the plumbing,
           air conditioning, heating, ventilating, elevator, and electrical subcontractors to record on their field sets of
           drawings the exact locations, as installed, of all conduit, pipe and duct lines whether concealed or exposed
           which were not installed exactly as shown on the contract drawings. The Construction Manager shall also
           record all drawing revisions that have been authorized by change order that effect wall or partition locations,
           door and window locations and other template changes. The exact routing of conduit runs shall be shown on
           these drawings.
           Each drawing shall be noted "As Built" and shall bear the date and name of the subcontractors that
           performed the work. Where the work was installed exactly as shown on the contract drawings the sheets
           shall not be disturbed except as noted above.
           The Construction Manager shall review the completed As-Built drawings and ascertain that all data
           furnished on the drawings are accurate and truly represent the work as actually installed. When manholes,
           boxes, underground conduits, plumbing, hot or chilled water lines, inverts, etc. are involved as part of the
           work, the Construction Manager shall furnish true elevations and locations, all properly referenced by using
           the original bench mark used for the institution or for this project
(11)   Administrative Records - The Construction Manager will maintain at the job site, unless agreed to otherwise by
       the Project Director, on a current basis, files and records such as, but not limited to the following:
The project records shall be available at all times to the Owner and Architect-Engineer for reference or review.
(12)   Owner Occupancy - The Construction Manager shall provide services during the design and construction phases,
       which will provide a smooth and successful Owner occupancy of the project. He shall provide consultation and
       project management to facilitate Owner occupancy and provide transitional services to get the work, as
                                                        12                                                         Rev. 9/07
             completed by the Construction Managers, "on line" in such conditions as will satisfy Owner operational
             requirements.
             He shall conduct the Construction Manager's preliminary punch list inspection and coordinate the completion of
             all punch list work to be done with Owner occupancy requirements in mind.
             He shall secure required guarantees and warranties, assemble and deliver same to the Owner in a manner that
             will facilitate their maximum enforcement and assure their meaningful implementation.
             He shall continuously review "As-Built" Drawings and mark up progress prints to provide as much accuracy as
             possible.
             The Owner will not occupy or take control of the project until the above items discussed in this paragraph have
             been completed and the "Substantial Completion", "Start-Up", "Record Drawing", and "Warranty" requirements
             specified in paragraphs 2.4(10)h, 2.4(10)j, 2.4(10)k, and 2.4(13) have been completed to the Owner's satisfaction
             excluding the requirements for a warranty inspection nine months after Owner Occupancy.
      (13)   Warranty - Where any work is performed by the Construction Manager's own forces or by subcontractors under
             contract with the Construction Manager, the Construction Manager shall warrant that all materials and equipment
             included in such Work will be new except where indicated otherwise in Contract Documents, and that such Work
             will be of good quality, free from improper workmanship and defective materials and in conformance with the
             Drawings and specifications. With respect to the same Work, the Construction Manager further agrees to correct
             all work found by the Owner to be defective in material and workmanship or not in conformance with the
             Drawings and Specifications for a period of one year from the Date of Substantial Completion or for such longer
             periods of time as may be set forth with respect to specific warranties contained in the trade sections of the
             Specifications. The Construction Manager shall collect and deliver to the Owner any specific written warranties
             given by others as required by the Contract Documents. Also, the Construction Manager shall conduct, jointly
             with the Owner and the Architect-Engineer, a warranty inspection nine (9) months after the date of Owner
             Occupancy.
                                                  ARTICLE 3
                                           OWNER'S RESPONSIBILITIES
3.1 Owner's Information - The Owner shall provide full information regarding his requirements for the project.
3.2   Owner's Representative - The Owner shall designate a representative who shall be fully acquainted with the project and
      shall define the lines of Owner authority to approve Project Construction Budgets, and changes in Project. He shall
      render decisions promptly and furnish information expeditiously.
3.3   Architect and Engineer's Agreement - The Owner shall retain an Architect-Engineer for design and to prepare
      construction documents for the project. The Architect-Engineer's services, duties and responsibilities are described in
      the Agreement between the Owner and the Architect-Engineer, a copy of which will be furnished to the Construction
      Manager. The Agreement between the Owner and the Architect-Engineer shall not be modified without written
      notification to the Construction Manager.
3.4   Site Survey and Reports - The Owner shall provide for the furnishing for the site of the project all surveys describing
      the physical characteristics, soil reports, and subsurface investigations, legal limitations, utility locations, and a legal
      description.
3.5   Approvals and Easements - The Owner shall pay for necessary approvals, easements, assessments and charges required
      for the construction, use or occupancy of permanent structures or for permanent changes in existing facilities.
3.6   Legal Services - The Owner shall furnish such legal services as may be necessary for providing the items set forth in
      Article 3.5 and such auditing services as he may require.
3.7   Drawings and Specifications - The Construction Manager will be furnished a reproducible set of all copies of Drawings
      and Specifications reasonably necessary and ready for printing.
3.8   Cost of Surveys & Reports - The services, information, surveys and reports required by the above paragraphs shall be
      furnished with reasonable promptness in accordance with the approved schedule at the Owner's expense, and the
      Construction Manager shall be entitled to rely upon the accuracy and completeness thereof.
                                                              13                                                          Rev. 9/07
3.9       Project Fault Defects - If the Owner becomes aware of any fault or defect in the Project or non-conformance with the
          drawings and specifications, he shall give prompt written notice thereof to the Construction Manager and Architect-
          Engineer.
3.10      Funding - The Owner shall furnish in accordance with the established schedule, reasonable evidence satisfactory to the
          Construction Manager that sufficient funds will be available and committed for the cost of each part of the Project. The
          Construction Manager shall not commence any work, unless authorized in writing by the Owner.
3.11      Lines of Communication - The Owner and Architect-Engineer shall communicate with the subcontractors or suppliers
          only through the Construction Manager while such method of communication is effective in maintaining project
          schedules and quality.
3.12      Lines of Authority - The Owner shall establish and maintain lines of authority for his personnel and shall provide this
          definition to the Construction Manager and all other affected parties.
3.13      Permitting & Code Inspections - The Owner recognizes and coordinates with the Permitting Authority and expects the
          Construction Manager to do the same.
                                                        ARTICLE 4
                                                PERMITTING AND INSPECTION
Before Construction can begin, it is necessary by statute for the Construction Manager to obtain a Building Permit. In addition,
construction will be inspected for code compliance, compliance with drawings and specifications, and quality by inspectors
working for the Permitting Authority. The building permitting and code inspection requirements shall be as described in Articles
4.1 through 4.2 hereinafter.
4.1       Building Permits - The contractor is obligated to obtain and pay for a building permit from the local authority for
          construction of this State facility.
          In the case of plumbing, electrical, other internal system permits and connection permits, the Contractor is obligated to
          obtain such permits and pay such fees.
          The Contractor shall determine the permits and fees required by any entity having jurisdiction over any part of the project
          and shall include the cost of all such permits in his bid proposal.
4.2       Code Inspections - All projects will require detailed code compliance inspections by the local authorities with jurisdiction
          over the area in which the project is located. The disciplines normally include, but are not necessarily limited to, structural,
          mechanical, electrical, plumbing and general building. The contractor shall make all permits, drawings, specifications,
          previous inspection reports, and change documents available to Code Inspectors. The contractor shall provide a copy of
          each inspection report to the Architect/Engineer in a timely fashion.
                                                          ARTICLE 5
                                                        SUBCONTRACTS
5.1       Definition. - A subcontractor is a person or organization who has a direct contract with the Construction Manager to
          perform any of the work at the site. Nothing contained in the Contract Document shall create any contractual relation
          between the Owner or Architect-Engineer and any subcontractor.
5.2       Proposals. - Subject to Article 9 and, in accordance with Article 2.4(4), the Construction Manager shall request and
          receive proposals from subcontractors and suppliers and will award those contracts to the qualified low bidder after he
          has reviewed each proposal and is satisfied that the subcontractor is qualified to perform the work.
5.3.1     Subcontractual Relations - By an appropriate written agreement, the Construction Manager shall require each
          subcontractor to the extent of the work to be performed by the subcontractor, to be bound to the Construction Manager
          by the terms of the Contract Documents, and to assume toward the Construction Manager all the obligations and
          responsibilities which the Construction Manager by these Documents, assumes toward the Owner and the Architect-
          Engineer. Said agreements shall preserve and protect the rights of the Owner and Architect-Engineer under the
          Contract Documents with respect to the Work to be performed by the subcontractor so that the subcontracting thereof
          will not prejudice such rights. Where appropriate, the Construction Manager shall require each Subcontractor to enter
          into similar agreements with his Sub-subcontractor.
                                                                    14                                                            Rev. 9/07
        The Construction Manager shall make available to each proposed Subcontractor, prior to the execution of the
        Subcontract, copies of the Contract Documents to which the Subcontractor will be bound by this Article 5.3 and identify
        to the Subcontractor any terms and conditions of the proposed Subcontract which may be at variance with the Contract
        Documents. Each Subcontractor shall similarly make copies of such Documents available to his Sub-subcontractors.
        (1) On all subcontracts where the bid exceeds $100,000, the Construction Manager may require subcontractors to
        provide a 100% performance bond and a 100% labor and material payment bond from a surety company authorized to
        do business in the State of Florida by the Department of Financial Services, Office of Insurance Regulation. If the
        Construction Manager wishes to award subcontracts to Subcontractors unable to supply this bonding, he may request
        special authorization to do so. Upon providing justifiable background information, such authorization shall not be
        withheld unreasonably.
        (2) On all subcontracts where the bid exceeds $200,000.00, each subcontractor must submit a completed experience
        questionnaire and financial statement on the form entitled "Experience Questionnaire and Construction Manager's
        Financial Statement" Form #DBC-5085, incorporated herein by reference or equivalent form supplied by Construction
        Manager. The subcontractors financial condition must demonstrate that adequate fixed and liquid assets and equipment
        are available to properly perform the subcontract.
        (3) Workforce - The subcontractor must agree to perform no less than 15% of the project construction work utilizing its
        own employees.
        (4) Subcontractor experience - The subcontractor must have successfully completed no less than two projects of similar
        size and complexity within the last five years.
        (5) Supervision - The subcontractor must agree to provide field (on-site) supervision through a named superintendent
        for each trade (general concrete forming and placement, masonry, mechanical, plumbing, electrical and roofing)
        included in the subcontract. In addition, the subcontractor shall assign and name a qualified employee for scheduling
        direction for its work. The supervisory employees of the subcontractor (including field superintendent, foreman and
        schedulers at all levels) must have been employed in a supervisory (leadership) capacity of substantially equivalent
        level on a similar project for at least two years within the last five years. The subcontractor shall include a resume of
        experience for each employee identified by him to supervise and schedule his work.
              In the event of a change in the work the subcontractor's claim for adjustments in the contract sum are limited
              exclusively to its actual costs for such changes plus no more than 15% for overhead and profit and bond costs.
              Each subcontract shall require the subcontractor to expressly agree that the foregoing constitute the sole and
              exclusive remedies for delays and changes in the work and thus eliminate any other remedies for claim for
              increase in the contract price, damages, losses or additional compensation.
              b. Each subcontract shall require that any claims by subcontractor for delay or additional cost must be submitted
              to Construction Manager within the time and in the manner in which the Construction Manager must submit such
              claims to the Owner, and that failure to comply with the conditions for giving notice and submitting claims shall
              result in the waiver of such claims.
5.4     Responsibilities for Acts and Omissions - The Construction Manager shall be responsible to the Owner for the acts and
        omissions of his employees and agents and his subcontractors, their agents and employees, and all other persons
        performing any of the work or supplying materials under a contract to the Construction Manager.
5.5     Subcontracts to be provided. The Construction Manager shall include a copy of each subcontract, including the general
        supplementary conditions, in the project manual.
                                          ARTICLE 6
                 SCHEDULE, TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
6.1 At the time a Guaranteed Maximum Price (GMP) is established, as provided for in Article 7, a project substantial
                                                               15                                                        Rev. 9/07
        completion date, a project final completion date and an Owner Occupancy date for completion of the project in
        accordance with the master project schedule, shall also be established by the Construction Team. The Construction
        Manager agrees to complete the construction in accordance with the agreed upon substantial completion date, final
        completion date and Owner Occupancy date. The Construction Manager acknowledges that failure to complete the
        project within the construction time set forth in the approved schedule may result in substantial damages to the Owner,
        for all of which damages the Construction Manager shall be liable.
6.2     The date of Owner Occupancy shall occur as described in Article 2.4(12) hereinabove. Warranties called for by this
        Agreement or by the Drawings and Specifications shall commence on the Date of Owner Occupancy of the project.
                                              ARTICLE 7
                              GUARANTEED MAXIMUM PRICE FOR CONSTRUCTION
7.1     When the Design Development Documents are sufficiently complete to establish the scope of work for the project or
        any portion thereof, as generally defined by a design document listing to be provided by the Architect-Engineer and
        Construction Manager upon execution of this Agreement, which is to be used only as a guide in developing the
        specifications and plan data necessary to establish a Guaranteed Maximum Price, or at such time thereafter designated
        by the Owner, the Construction Manager will establish and submit in writing to the Owner for his approval a
        Guaranteed Maximum Price, guaranteeing the maximum price to the Owner, for the construction cost of the project or
        designated part thereof. Such Guaranteed Maximum Price will be subject to modification for changes in the project as
        provided in Article 10. However, the actual price paid for the work by the Owner shall be the actual cost of all work
        subcontracts, supply contracts, direct labor costs, direct supervision costs, and direct job costs as defined under Article
        9, plus the Construction Manager's fees or the GMP, whichever is less when the work is complete.
7.2     The GMP will only include those taxes in the cost of the project which are legally enacted at the time the GMP is
        established.
7.3     When the project is bid and 100% of the Trade Contracts have been executed, the contingency within the GMP may be
        decreased in proportion to the percent of the work completed. In other words, if 10% of the work has been completed
        and the Owner requests that the contingency within the GMP be adjusted, then 10% of the contingency within the GMP
        will be removed from the GMP by change order.
7.4     At the time of submission of a Guaranteed Maximum Price, the Construction Manager will verify the time schedule for
        activities and work which were adopted by the Construction Team and used to determine the Construction Manager's
        cost of work. In addition to the cost of work, a GMP will include an agreed upon sum as the construction contingency
        which is included for the purpose of defraying the expenses due to unforeseen circumstances relating to construction.
        The Construction Manager will be required to furnish documentation evidencing expenditures charged to this
        contingency prior to the release of funds by the Owner. Documentation for use of the Contingency shall be determined
        by the Construction Team, included in the Project Manual and displayed monthly in the PMIS. The Architect-Engineer
        shall verify the actual costs. If bids are received below the applicable line items in the GMP, the surplus will be added
        to the contingency.
        If bids are received above the applicable line item in the GMP the deficiency will be taken from the contingency,
        however such events shall not be cause to increase the GMP.
        If bids are not received for a portion of the work at or below the applicable line item amount in the GMP, the
        Construction Manager reserves the right to perform that portion of the work as acknowledged by the Owner or negotiate
        for its performance for the specified line item lump sum amount or less.
                                                  ARTICLE 8
                                          CONSTRUCTION MANAGER'S FEE
8.1     In consideration of the performance of the contract, the Owner agrees to pay the Construction Manager as compensation
        for his services, fees as set forth in Subparagraphs 8.1.1, 8.1.2 and 8.1.3.
8.1.1   Preconstruction Phase Fee - For the performance of the services set forth under paragraphs 2.1.3(l), 2.1.4(a)(b)(c)(d),
        2.3(1) and 2.3(2) and for profit and overhead related to these services, a total fee of (Amount) . The Preconstruction
        Phase Fees are based on constructability review, value engineering and estimates of probably cost and shall be paid as
        follows:
        The Construction Manager's personnel to be assigned during this phase and their duties and responsibilities to this
        project and the duration of their assignments is shown on Exhibit F.
                                                                16                                                         Rev. 9/07
8.1.2   Construction Phase Fee - Prior to commencement of the Construction Phase, the Owner will direct the Construction
        Manager in writing to proceed into the Construction Phase. The Construction Manager's compensation for work or
        services performed during the Construction Phase shall be a fee of (Amount). (However, the Owner retains the right
        to review the need and effectiveness of any employee or employees assigned by the Construction Manager, should the
        Project Director question the need for the employee or employees). The Construction Phase Fee shall be invoiced and
        paid in     (No. months)      monthly payments of (Amount) each and one final monthly payment of         (Amount) .
        The first monthly payment shall become due thirty days following the issuance of the first Construction Authorization
        by the Project Director and the final monthly payment shall be paid only when construction of the project is finally
        completed and occupancy of the project accepted by the Owner. If construction is authorized only for a part of the
        project, the fee paid shall be proportionate to the amount of work authorized by the Owner.
        (1)   Adjustments in Fee - For changes in the project as provided in Article 10, the construction phase fee shall be
              adjusted as follows:
              (a)    The Construction Manager shall be paid an additional fee subject to negotiation if the Construction
                     Manager is placed in charge of reconstruction of an insured or uninsured loss excluding any condition that
                     may have been caused from negligent acts by the Construction Manager.
              (b)    Should the duration of the construction stipulated herein for Final Completion extend beyond (Number)
                     months after the Notice-To-Proceed, receipt of final drawings and specifications, or receipt of all
                     necessary permits, whichever is later, due to no fault of the Construction Manager, the Construction
                     Manager's Additional Construction Phase Fee will be (Amount) per working day, for each day or
                     portion thereof. The Construction Manager's staff during such time extensions shall be that shown in
                     Exhibit G.
              (c)    The Construction Manager will not be due any additional Overhead and Profit on increases in the
                     Guaranteed Maximum Price (GMP) that do not exceed          (Amount)        . Should the GMP be increased
                     by more than        (Amount)           under the terms of Article 10 hereinafter due to no fault of the
                     Construction Manager, the Construction Manager's additional Overhead and Profit for the Construction
                     Phase will be (Percen)t of that portion of the accumulative increases in the GMP that exceed the GMP by
                     more than (Amount)           .
                     Construction Manager's Exclusive Remedy: In the event the construction Substantial or Final Completion
                     date is extended, regardless of whether delay is caused by any act or neglect of the Owner or the
                     Architect-Engineer, or is attributable to the Owner or the Architect-Engineer, the Construction Manager's
                     sole and exclusive remedy is an extension of the construction completion date and payment of additional
                     Construction Phase fees and Overhead and Profit for Construction Phase as provided above.
        (2)   Costs and Expenses Included in Fee - The following are included in the Construction Manager's fee for services
              during the Construction Phase:
              (a)    Salaries or other compensation of the Construction Manager's employees at his principal office and branch
                     offices.
                     The Construction Manager's personnel to be assigned during the construction phase, their duties and
                     responsibilities to this project and the duration of their assignments are shown on Exhibits H and I.
              (b)    General operating expenses related to this project of the Construction Manager's principal and branch
                     offices.
              (d)    Salaries or other compensation of the Construction Manager's employees at the job site. The Construction
                     Manager's personnel to be assigned to the site during the Construction Phase under the job site
                     management and supervision fee, their duties and responsibilities and the duration of their assignment are
                     shown on Exhibit I.
              (e)    General operating expenses incurred in the management and supervision of the project, except as
                     expressly included in Article 9.
              (g)    Job office supplies - includes paper, pencils, paper clips, file folders, staples, etc., and janitorial supplies
                     (photo copy or blue print paper not included).
                                                                17                                                           Rev. 9/07
               (h)   Direct tax saving purchase program.
8.1.3   Overhead And Profit For Construction Phase - For overhead, profit and general expenses of any kind, except as may be
        expressly included in Article 9, for services provided during and related to the construction phase, the fee shall be
          (Amount)        and shall be paid proportionally to the ratio of the cost of the work in place, and less retainage (see
        Article 12.1), as it bears on the latest estimate of the total construction cost or to the GMP or to the Owner's
        Construction Budget, whichever is less. The balance of the fee shall be paid when construction of the project is finally
        completed and occupancy of the project accepted by the Owner. If construction is authorized only for a part of the
        project, the fee paid shall be proportionate to the amount of work authorized by the Owner. The Construction
        Manager's exclusive remedy for any adjustments in the Overhead and Profit for construction phase fee is provided in
        Article 8.1.2(1).
                                                     ARTICLE 9
                                                COST OF THE PROJECT
9.1     Definition - The term Cost of the Project shall mean costs necessarily incurred in the Project during the Construction
        Phase for Construction services and paid by the Construction Manager which are not included in Article 8. Such costs
        shall include the items set forth below in this Article.
        The Owner agrees to pay the Construction Manager for the Cost of the Project as defined in Article 9. Such payment
        shall be in addition to the Construction Manager's fees stipulated in Article 8.
        (1)    Wages paid for labor (as opposed to wages paid to management or supervisory personnel) in the direct employ of
               the Construction Manager in the performance of his work under Agreement, times a multiple of (Percent) to
               cover fringe benefits.
        (2)    Cost of all materials, supplies and equipment incorporated in the Project, including costs of transportation and
               storage thereof.
        (3)    Payments due to subcontractors from the Construction Manager or made by the Construction Manager to
               subcontractors for their work performed pursuant to contract under this Agreement.
        (4)    Cost including transportation and maintenance of all materials, supplies, equipment, temporary facilities and
               hand tools not owned by the workmen, which are employed or consumed in the performance of the work, cost on
               such items used but not consumed which may be turned over to the Owner at the end of the project and cost less
               salvage value on such items used but not consumed which remain the property of the Construction Manager. For
               those items to be turned over to the Owner at the end of the project, Article 2.3(6) shall apply.
        (5)    Rental charges on all necessary machinery and equipment, exclusive of hand tools used at the site of the Project,
               whether rented from the Construction Manager or other, including installation, repairs and replacements,
               dismantling, removal, costs of lubrication, transportation and delivery costs thereof, which are used in the
               support of a sub-contractor or the Construction Manager's own forces in the performance of the work, at rental
               charges consistent with those prevailing in the area.
        (6)    Cost of the premiums for all insurance and cost of premiums for all bonds which the Construction Manager is
               required to procure by this Agreement specifically for the construction project. This includes any sub-contractor
               bonds the Construction Manager deems appropriate.
        (7)    Sales, use, gross receipts or similar taxes related to allowable direct costs of the Project imposed by any
               governmental authority, and for which the Construction Manager is liable.
        (8)    The cost of corrective work subject, however, to the GMP and except for any corrective work made necessary
               because of defective workmanship or other causes contributed to by the Construction Manager or his
               subcontractors or suppliers.
               No costs shall be paid by the Owner to the Construction Manager for any expenses made necessary to correct
               defective workmanship or to correct any work not in conformance with the Plans and Specifications or to correct
               any deficiency or damage caused by negligent acts by the Construction Manager.
        (9)    Minor expenses at the site, such as telegrams, long distance telephone calls, telephone service, expressage,
               postage, and similar petty cash items in connection with the Project to be billed at cost.
(10) Costs for trash and debris control and removal from the site.
                                                                18                                                       Rev. 9/07
         (11)   Cost incurred due to an emergency affecting the safety of persons and property.
         (12)   Legal costs reasonably and properly resulting from prosecution of the Project for the Owner, including handling
                claims for changes by Subcontractors and Vendors, subject to the following limitations:
(a) The Owner approved incurring such costs in advance, which approval shall not be unreasonably denied; and
(b) The legal costs were not incurred as result of the Construction Manager's own negligence or default.
                This paragraph does not provide for payment of legal costs incurred in preparing or asserting claim or requests,
                by Construction Manager itself, for change orders or in enforcing the obligations of this contract.
         (13)   All costs directly incurred in the performance of the Project for the benefit of the Project and not included in the
                Construction Manager's fees as set forth in Article 8.
         (14)   If requested by the Owner, the Construction Manager will perform all or a portion of any item in Article 9 for the
                cost of the work.
         (15)   If approved by the Owner, the Construction Manager, when qualified, may perform all or a portion of the work
                for any item listed on the estimate or GMP breakdown where it is deemed advantageous due to schedule or
                economic benefit for the direct cost of the work.
         (16)   Transportation greater than 100 miles from the site for those personnel employed directly for the project. Such
                transportation must be approved in advance by the Owner, and may be in accordance with the Construction
                Manager's standard personnel policy but not exceeding the limits established by Florida Statutes 112.061.
         (17)   Costs of all reproductions used for bidding or information purposes required by the project to directly benefit the
                project.
(18) Costs for watchman and security services for the project.
         (19)   Costs for efficient logistical control of the site, including horizontal and vertical transportation of materials and
                personnel. Also, costs for adequate storage and parking space.
         (20)   Costs for such temporary facilities during construction, as approved by the Owner, including temporary water,
                heat, power, sanitary facilities, telephones, radios and computers with software.
         (21)   Costs for any job site items not referenced herein, not normally provided by the subcontractors, which will be
                provided by the Construction Manager as required to complete the work.
         (22)   Cost of utilizing a computer aided design and drafting application (CADD) for record drawings as described in
                Article 2.4(10)(k). Upon completion of the work, the Construction Manager shall obtain two (2) paper copies
                and two (2) sets of disk files from the Architect-Engineer and record to scale all as-built conditions. The disk
                shall be submitted to the Architect-Engineer when completed, together with two sets of blue line or black line
                prints for certification and forwarding to the Owner/ Client Agency, at the time of final completion.
                For those Construction Managers who do not have CADD capabilities, the as-built marked-up drawings will be
                submitted to the Architect-Engineer. The Architect-Engineer will make the electronic updates and provide two
                (2) paper copies and two (2) sets of CADD disk files and return them to the Construction Manager for
                development of the close-out documents.
                                                     ARTICLE 10
                                                CHANGE IN THE PROJECT
10.1     Change Orders - The Owner, without invalidating this Agreement, may order Changes in the Project within the general
         scope of this Agreement consisting of additions, deletions or other revisions, the GMP, and the Construction
         Completion Date, being adjusted accordingly. All changes in the Project not covered by an authorized contingency
         shall be authorized by Change Order signed by the Owner before the change is implemented.
10.1.1   A Change Order is a written order to the Construction Manager signed by the Owner issued after the execution of this
         Agreement, authorizing a Change in the Project, the Construction Manager's fee, or the Construction Completion date.
         Each adjustment in the GMP resulting from a change order shall clearly separate the amount attributable to the Cost of
         the Project.
                                                                 19                                                          Rev. 9/07
10.1.2   The increase or decrease in the Guaranteed Maximum Price resulting from a change in the Project shall be determined
         in one or more of the following ways:
         (1)    by mutual acceptance of a lump sum properly itemized and supported by sufficient substantiating data to permit
                evaluation by the Architect-Engineer and Owner;
(3) by cost as defined in Article 9 and a mutually acceptable fixed or percentage fee; or
10.1.3   If none of the methods set forth in Clause 10.1.2 is agreed upon, the Construction Manager, provided he receives a
         written order signed by the Owner, shall promptly proceed with the work involved. The cost of such work shall then be
         determined on the basis of the reasonable expenditures and savings of those performing the work attributed to the
         change. However, in the event a Change Order is issued under these conditions, the Architect-Engineer will establish
         an estimated cost of the work and the Construction Manager shall not perform any work whose cost exceeds that
         estimate without prior written approval by the Owner. In such case, and also under Article 10.1.2 above, the
         Construction Manager shall keep and present, in such form as the Owner may prescribe, an itemized accounting
         together with appropriate supporting data of the increase in the Cost of the Project as outlined in Article 9. The amount
         of decrease in the Guaranteed Maximum Price to be allowed by the Construction Manager to the Owner for any deletion
         or change which results in a net decrease in cost will be the amount of the actual net decrease.
10.1.4   If unit prices are stated in the Agreement or subsequently agreed upon, and if the quantities originally contemplated are
         so changed in a proposed Change Order that application of the agreed unit prices to the quantities of work proposed will
         cause substantial inequity to the Owner or the Construction Manager, the applicable unit prices and Guaranteed
         Maximum Price shall be equitably adjusted.
10.1.5   Should concealed conditions encountered in the performance of the work below the surface of the ground or should
         concealed or unknown conditions in an existing structure be at variance with the conditions indicated by the Drawings,
         Specifications, or Owner furnished information or should unknown physical conditions below the surface of the ground
         or should concealed or unknown conditions in an existing structure of an unusual nature, differing materially from those
         ordinarily encountered and generally recognized as inherent in work of the character provided for in this Agreement, be
         encountered, the Guaranteed Maximum Price and the Construction Completion date shall be equitably adjusted by
         Change Order upon a request for Change Order in accordance with Article 10.2.
All claims for additional cost or time shall be made by request for a change order submitted as provided in Article 16.
         If the Construction Manager is delayed at any time in the progress of the work by any act or neglect of the Owner or the
         Architect or of any employee of either or by any separate Construction Manager employed by the Owner or by any
         changes ordered in the work by labor disputes, fire, or unusual delay in transportation, unavoidable casualties or any
         causes beyond the Construction Manager's control or by delay authorized by the owner pending resolution of disputes,
         and such delay extends the completion date, the Substantial Completion shall be extended by Change Order for such
         reasonable time as the Construction Team may determine.
         Only delays which are determined to extend the critical path for the schedule for constructing the project will result in a
         time extension. Neither the Owner nor the Construction Manager shall be considered to own the schedule float time.
         The Architect-Engineer will have authority to order minor changes in the Project not involving an adjustment in the
         Guaranteed Maximum Price or an extension of the Construction Completion Date and not inconsistent with the intent of
         the Drawings and Specifications. Such changes shall be effected by written order. Documentation of changes shall be
         determined by the Construction Team, included in the Project Manual and displayed monthly in the PMIS. Changes
         shall be approved by the Project Director, Architect-Engineer.
10.4 Emergencies
         In any emergency affecting the safety of persons or property, the Construction Manager shall act at his discretion, to
         prevent threatened damage, injury or loss. Any increase in the Guaranteed Maximum Price or extension of time
         claimed by the Construction Manager on account of emergency work shall be determined as provided in Article 10.
                                                                 20                                                         Rev. 9/07
                                                  ARTICLE 11
                                            DISCOUNTS AND PENALTIES
11.1   All discounts for prompt payment shall accrue to the Owner to the extent the Cost of the project is paid directly by the
       Owner or from a fund made available by the Owner to the Construction Manager for such payments. To the extent the
       Cost of the Project is paid with funds of the Construction Manager, all cash discounts shall accrue to the Construction
       Manager. All trade discounts, rebates and refunds, and all returns from sale of surplus materials and equipment, shall be
       credited to the Cost of the Project. All penalties incurred due to fault of the Construction Manager for late payment of
       cost of the project will be paid by the Construction Manager.
                                              ARTICLE 12
                                PAYMENTS TO THE CONSTRUCTION MANAGER
12.1   Monthly Statements - The Construction Manager shall submit to the Owner a statement, sworn to if required, along with
       the cost reports required under Article 2.1.5, showing in detail all monies paid out, cost accumulated or costs incurred
       on account of the Cost of the Project during the previous period and the amount of the Construction Manager's fees due
       as provided in Article 8. Ten percent (10%) retainage shall be held on all payments until the contract is fifty percent
       (50%) complete, except when approved by the Owner certain suppliers and subcontractors may be paid the entire
       amount due when such payment is generally the practice of the industry. In such cases, if the Owner makes any
       payment of retainage to the Construction Manager which is attributable to the labor, services, or materials supplied by
       one or more subcontractors or suppliers, the Construction Manager shall timely remit payment of such retainage to those
       subcontractors and suppliers. Unless otherwise stated herein, the term 50% completion refers to the point at which the
       Owner has expended 50 percent of the total cost of the construction services purchased as identified in the contract
       together with all costs associated with existing change orders and other additions or modifications to the construction
       services provided for in this agreement. At 50% completion, the Owner must reduce the retainage from 10% to 5%
       Retainage shall not be withheld on services or fees set forth in Article 8. Pursuant to Section 255.078(4), Florida
       Statutes, after 50% completion of the construction services purchased pursuant to this Agreement, the Construction
       Manager may present to the Owner a payment request for up to one-half of the retainage held by the Owner. The Owner
       shall promptly make payment to the Construction Manager, unless the Owner has grounds, pursuant to Section
       255.078(6), Florida Statutes for withholding the payment of retainage. If the Owner makes payment of retainage to the
       Construction Manager which is attributable to the labor, services, or materials supplied by one or more subcontractors
       or suppliers, the Construction Manager shall timely remit payment of such retainage to those subcontractors and
       suppliers.
       The Construction Managers Design Phase Fee, Construction Phase Fee and Overhead & Profit shall be shown as
       separate line items on the Schedule of Contract Values. Payment of the Construction Managers Overhead and Profit
       shall be calculated based on the Construction Budget Balance or the GMP Balance whichever is applicable. The
       Construction Budget Balance or GMP Balance is established by subtracting the Design Phase Fee, Construction Phase
       Fee and Overhead & Profit from the latest estimate of the total construction cost or to the GMP or to the Owners
       Construction Budget, whichever is less. The billable Overhead and Profit is calculated by multiplying the percent
       complete of the Construction Budget Balance or the GMP Balance as applicable. This data shall be attached to the
       Partial Pay Request form shown in Exhibit J. Payments by the Owner to the Construction Manager shall be made as
       described in Article 17.6 hereinafter.
12.2   Final Payment - Final payment constituting the unpaid balance of the Cost of the Project and the Construction
       Manager's fee, shall be due and payable as described in Article 17.6 after the Owner has accepted occupancy of the
       project, provided that the Project be then finally completed, that the Construction Manager has verified by his signature
       that he has completed all items specified on the attached K, and that this Agreement has been finally performed.
       However, if there should remain work to be completed, the Construction Manager and the Architect-Engineer shall list
       those items prior to receiving final payment and the Owner may retain a sum equal to 150% of the estimated cost of
       completing any unfinished work and portion of the Construction Manager's retainage, provided that said unfinished
       items are listed separately and the estimated cost of completing any unfinished items are likewise listed separately.
       Thereafter, Owner shall pay to Construction Manager, monthly, the amount retained for each incomplete item after each
       of said items is completed.
12.3   Payments to Subcontractors - The Construction Manager shall promptly, within 10 days after receipt of payment from
       the Owner, pay all the amount due subcontractors and suppliers less a retainage of ten percent (10%) until the project is
       fifty percent (50%) complete After the project is fifty percent (50%) complete, the Construction Manager may elect to
       withhold retainage from payments to its subcontractors at a rate higher than 5 percent (5%). The specific amount to be
       withheld must be determined on a case-by-case basis and must be based on the contractors assessment of the
       subcontractors past performance, the likelihood that such performance will continue, and the Construction Managers
       ability to rely on other safeguards. The Construction Manager shall notify the subcontractor, in writing, of its
       determination to withhold more than 5% of the progress payments and the reasons for making that determination, and
       the Construction Manager may not request the release of such retained funds from the Owner. If there should remain
                                                              21                                                        Rev. 9/07
       items to be completed, the Construction Manager and Architect-Engineer shall list those items required for completion
       and the Construction Manager shall require the retainage of a sum equal to 150% of the estimated cost of completing
       any unfinished items, provided that said unfinished items are listed separately and the estimated cost of completing any
       unfinished items likewise listed separately. Thereafter, the Construction Manager shall pay to the subcontractors,
       monthly, the amount retained for each incomplete item after each of said items is completed. Before issuance of final
       payment without any retainage, the subcontractor shall submit satisfactory evidence that all payrolls, material bills and
       other indebtedness connected with the Project have been paid or otherwise satisfied, warranty information is complete,
       as-built markups have been submitted and instruction for the Owner's operating and maintenance personnel is complete.
       Final payment may be made to certain select subcontractors whose work is satisfactorily completed prior to the total
       completion of the Project but only upon approval of the Owner.
12.4   Delayed Payments by Owner - The Owner shall submit a payment request for all undisputed amounts to the Chief
       Financial Officer for payment no more than twenty (20) days after receipt of an approvable payment request. If the
       Owner should fail to pay the Construction Manager within thirty (30) days after the receipt of an approvable payment
       request from the Construction Manager, then the Construction Manager may, upon seven (7) additional days written
       notice to the Owner and the Architect-Engineer stop the Project until payment of the Amount owing has been received.
12.5   Payments for Materials and Equipment - Payments will be made for material and equipment not incorporated in the
       work but delivered and suitably stored at the site or another location subject to prior approval and acceptance by the
       Owner on each occasion.
12.6   Withholding Payments To Subcontractors - The Construction Manager shall not withhold payments to subcontractors if
       such payments have been made to the Construction Manager. Should this occur for any reason, the Construction
       Manager shall immediately return such monies to the Owners, adjusting pay requests and project bookkeeping as
       required.
                                             ARTICLE 13
                          INSURANCE, INDEMNITY AND WAIVER OF SUBROGATION
13.1 Indemnity
       (1)   The Construction Manager agrees to indemnify and hold the Owner and Architect-Engineer harmless from all
             claims for bodily injury and property damage (other than the work itself and other property insured under
             Paragraph 13.2(3)) that may arise from the Construction Manager's operations under this Agreement.
       (2)   The Owner shall cause any other Construction Manager who may have a contract with the Owner to perform
             construction or installation work in the area where work will be performed under this Agreement, to agree to
             indemnify the Owner and the Construction Manager and hold them harmless from all claims for bodily injury
             and property damage (other than property insured under Paragraph 13.2(3)) that may arise from the Construction
             Manager's operations. Such provisions shall be in a form satisfactory to the Construction Manager.
       (1)   The Construction Manager shall not commence any construction work in connection with this Agreement until
             he has obtained all of the following types of insurance and such insurance has been approved by the Owner, nor
             shall the Construction Manager allow any subcontractor to commence work on his subcontract until all similar
             insurance required of the subcontractor has been so obtained and approved. All insurance policies shall be with
             insurers qualified and doing business in Florida.
       (2)   Worker's Compensation Insurance - The Construction Manager shall take out and maintain during the life of this
             Agreement Worker's Compensation Insurance for all his employees connected with the work of this Project and,
             in case any work is sublet, the Construction Manager shall require the subcontractor similarly to provide
             Worker's Compensation Insurance for all of the latter's employees unless such employees are covered by the
             protection afforded by the Construction Manager. Such insurance shall comply with the Florida Worker's
             Compensation Law. In case any class of employees engaged in hazardous work under this contract at the site of
             the Project is not protected under the Worker's Compensation statute, the Construction Manager shall provide
             adequate insurance, satisfactory to the Owner, for the protection of employees not otherwise protected.
       (3)   Construction Manager's Public Liability and Property Damage Insurance-The Construction Manager shall take
             out and maintain during the life of this Agreement Comprehensive General Liability and Comprehensive
             Automobile Liability Insurance as shall protect him from claims for damage for personal injury, including
             accidental death, as well as claims for property damages which may arise from operating under this Agreement
             whether such operations are by himself or by anyone directly or indirectly employed by him, and the amount of
             such insurance shall be minimum limits as follows:
                                                              22                                                        Rev. 9/07
      (a) Construction Manager's Comprehensive General Liability                $500,000 Each Occurrence,
          Coverages, Bodily Injury & Property Damage                            Combined Single Limit
      Insurance clause for both BODILY INJURY AND PROPERTY DAMAGE shall be amended to provide
      coverage on an occurrence basis.
(4)   Subcontractor's Public Liability and Property Damage Insurance - The Construction Manager shall require each
      of his subcontractors to procure and maintain during the life of this subcontract, insurance of the type specified
      above or insure the activities of his subcontractors in his policy, as specified above.
(5)   Owner's and Construction Manager's Protective Liability Insurance - The Construction Manager shall procure as
      a cost of the project and furnish an Owner's and Construction Manager's Protective Liability Insurance Policy
      with the following minimum limits:
(6)   "XCU" (Explosion, Collapse, Underground Damage - The Construction Manager's Liability Policy shall provide
      "XCU" coverage for those classifications in which they are excluded.
(7)   Broad Form Property Damage Coverage, Products & Completed Operations Coverages -The Construction
      Manager's Liability Policy shall include Broad Form Property Damage Coverage, Products and Completed
      Operations Coverages.
(8)   Contractual Liability Work Contracts - The Construction Manager's Liability Policy shall include Contractual
      Liability Coverage designed to protect the Construction Manager for contractual liabilities assumed by the
      Construction Manager in the performance of this Agreement.
      (a) To cover to the fullest extent permitted by law, the Construction Manager shall indemnify and hold harmless
          the Owner and the Architect-Engineer and their agents and employees from and against all claims, damages,
          losses and expenses, including but not limited to attorney's fees, arising out of or resulting from the
          performance of the Work, provided that any such claim, damage, loss or expense (1) is attributable to bodily
          injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work
          itself) including the loss of use resulting therefrom, and (2) is caused in whole or in part by any negligent act
          or omission of the Construction Manager, any subcontractor, anyone directly or indirectly employed by any
          of them or anyone for whose acts any of them may be liable, regardless of whether or not it is caused in part
          by a party indemnified hereunder. Such obligation shall not be construed to negate, abridge, or otherwise
          reduce any other right to obligation of indemnity which would otherwise exist as to any party or person
          described in this Article.
      (b) In any and all claims against the Owner or the Architect-Engineer or any of their agents or employees by any
          employee of the Construction Manager, any subcontractor, anyone directly or indirectly employed by any of
          them or anyone for whose acts any of them may be liable, the indemnification obligations under this
          Paragraph shall not be limited in any way by any limitation on the amount or type of damages, compensation
          or benefits payable by or for the Construction Manager or any subcontractor under workers' or workmen's
          compensation acts, disability benefit acts or other employee benefit acts.
      (c) The obligations of the Construction Manager under this Article 13.2(9) shall not extend to the liability of
          Architect-Engineer, his agents or employees, arising out of (1) the preparation or approval of maps,
          drawings, opinions, reports, surveys, change orders, designs or specifications, or (2) the giving of or the
          failure to give directions or instruction by Architect-Engineer, his agents or employees providing such giving
          or failure to give is the primary cause of the injury or damage.
      (d) The Construction Manager hereby acknowledges receipt of one hundred dollars and other good and valuable
          consideration as part of his fee in exchange for giving the Owner and Architect-Engineer, respectively, the
          indemnification provided above in Article 13.2(9). The limit of such indemnification shall be $1,000,000.00
          per occurrence.
                                                       23                                                          Rev. 9/07
         (10)   Builder's Risk Coverage - The Construction Manager shall take out and maintain during the life of this
                Agreement a "Builder's Risk Policy" completed value form as a cost of the Project, issued to provide coverages
                on an "all risk" basis including theft. This coverage shall not be lapsed or cancelled because of partial occupancy
                by the Owner prior to final acceptance of the Project.
(11) Certificate of Insurance - The Owner shall be furnished proof of coverage of Insurance as follows:
                Certificate of Insurance form will be furnished to the Owner along with the Contract Documents. These shall be
                completed and signed by the authorized Florida Resident Agent, and returned to the office of Real Estate
                Development and Management. This Certificate shall be dated and show:
                (a) The name of the insured Construction Manager, the specific job by name and job number, the name of the
                    insurer, the number of the policy, its effective date, and its termination date.
                (b) Statement that the Insurer will mail notice to the Owner and a copy to the Architect-Engineer at least fifteen
                    (15) days prior to any material changes in provisions or cancellation of the policy.
                (c) Certificate of Insurance shall be in the form as approved by Insurance Standards Office (ISO) and such
                    Certificate shall clearly state all the coverages required in this Section commencing at 13.2 and ending with
                    13.3.4.
(d) Certificate of Insurance shall state that the Owner is listed as additional insured on all appropriate policies.
(e) Copy of the endorsement or additional insured rider to the General Liability Policy.
13.3.1   The Owner and the Construction Manager waive all rights against each other, for damages caused by perils covered by
         insurance provided under Article 13.2 to the extent covered by such insurance except such rights as they may have to
         the proceeds of such insurance held by the Owner and Construction Manager as trustees. The Construction Manager
         shall require similar waivers from all subcontractors and their sub-subcontractors.
13.3.2   The Owner and Construction Manager waive all rights against each other for loss or damage to any equipment used in
         connection with the Project and covered by any property insurance. The Construction Manager shall require similar
         waivers from all subcontractors and their sub-subcontractors.
13.3.3   The Owner waives subrogation against the Construction Manager on all property and consequential loss policies carried
         by the Owner on adjacent properties and under property and consequential loss policies purchased for the Project after
         its completion.
13.3.4   If the policies of insurance referred to in this Article require an endorsement to provide for continued coverage where
         there is a waiver of subrogation, the Owner of such policies will cause them to be so endorsed, failure to obtain proper
         endorsement nullifies the waiver of subrogation.
                                      ARTICLE 14
   TERMINATION OF THE AGREEMENT AND OWNER'S RIGHT TO PERFORM CONSTRUCTION MANAGER'S
                                      OBLIGATION
14.1     Termination by the Construction Manager - If the Project is stopped for a period of thirty (30) days under an order of
         any court or other public authority having jurisdiction or as a result of an act of government, such as a declaration of a
         national emergency making materials unavailable, through no act or fault of the Construction Manager, or if the Project
         should be stopped for a period of sixty (60) days by the Construction Manager, for the Owner's failure to make
         payments thereon, then the Construction Manager may, upon seven days written notice to the Owner, request payment
         for all work executed, the Construction Manager's fees earned to date, and for any proven loss sustained upon any
         materials, equipment, tools, construction equipment, and machinery, including reasonable profit, damages and terminal
         expenses incurred by the Construction Manager.
14.2 Owner's Right to Perform Construction Manager's Obligations and Termination by Owner for Cause.
         (1)    If the Construction Manager fails to perform any of his obligations under this Agreement including any
                obligation he assumes to perform work with his own forces, the Owner may, after seven (7) days written notice
                during which period the Construction Manager fails to commence correction of such obligation, make good such
                                                                  24                                                           Rev. 9/07
             deficiencies. The GMP, or the actual cost of the Project, whichever is less, shall be reduced by the cost to the
             Owner of making good such deficiencies and the Construction Manager's Construction Phase Fee shall be
             reduced by an amount required to manage the making good of such deficiencies.
       (2)   If the Construction Manager is adjudged a bankrupt, or if he makes a general assignment for the benefit of his
             creditors, or if a receiver is appointed on account of his insolvency, or if he persistently or repeatedly refuses or
             fails, except in case for which extension of time is provided, to supply enough properly skilled workmen or
             proper materials and fails to maintain an established schedule (failure to maintain schedule shall be defined as
             any activity on the critical path that falls 45 days or more behind schedule) which has been adopted by the
             Construction Team, or if he fails to make prompt payment to subcontractors for materials or labor, or persistently
             disregards laws, rules, ordinances, regulations, or orders of any public authority having jurisdiction, or otherwise
             is guilty of a substantial violation of a provision of the Agreement, then the Owner may, without prejudice to any
             right or remedy and after giving the Construction Manager and his surety, if any, seven (7) days written notice,
             during which period Construction Manager fails to commence correction of the violation, terminate the
             employment of the Construction Manager and take possession of the site and of all materials, equipment, tools,
             construction equipment and machinery thereon owned by the Construction Manager, and may finish the Project
             by whatever method he may deem expedient. In such case, the Construction Manager shall not be entitled to
             receive any further payment until the Project is finished nor shall he be relieved from his obligations assumed
             under Article 7. Reasonable terminal expenses incurred by the Owner may be deducted from any payments left
             owing the Construction Manager (excluding monies owed the Construction Manager for subcontract work).
       (3)   If the Construction Manager refuses to allow public access to all documents, papers, letters, or other material
             subject to the provisions of Chapter 119, Florida Statutes, and made or received by the Construction Manager in
             conjunction with this Agreement, then the Owner may, without prejudice to any right or remedy and after giving
             the Construction Manager and his surety, if any, seven (7) days written notice, during which period Construction
             Manager still fails to allow access, terminate the employment of the Construction Manager and take possession
             of the site and of all materials, equipment, tools, construction equipment and machinery thereon, owned by the
             Construction Manager, and may finish the project by whatever method he may deem expedient. In such case, the
             Construction Manager shall not be entitled to receive any further payment until the Project is finished nor shall
             he be relieved from his obligations assumed under Article 7. Reasonable terminal expenses incurred by the
             Owner may be deducted from any payments left owing the Construction Manager (excluding monies owed the
             Construction Manager for subcontract work).
       (1)   If the Owner terminates this Agreement other than pursuant to Article 14.2(2) or Article 14.2(3), he shall
             reimburse the Construction Manager for any unpaid Cost of the Project due him under Article 9, plus that part of
             the unpaid balance of the Construction Phase Fee in an amount as will increase the payment on account of his fee
             to a sum which bears the same ratio to the Construction Phase Fee as the Cost of the Project at the time of
             termination bears to the Guaranteed Maximum Price, if established, otherwise to the Owner's Construction
             Budget. The Owner shall also pay to the Construction Manager fair compensation, either by purchase or rental at
             the election of the Owner, for any equipment retained. In case of such termination of Agreement the Owner shall
             further assume and become liable for obligations, commitments and unsettled contractual claims that the
             Construction Manager has previously undertaken or incurred in good faith in connection with said Project. The
             Construction Manager shall, as a condition of receiving the payments referred to in this Article 14, execute and
             deliver all such papers and take all such steps including the legal assignment of his contractual rights, as the
             Owner may require for the purpose of fully vesting in him the rights and benefits of the Construction Manager
             under such obligations or commitments.
       (2)   After the establishment of the Guaranteed Maximum Price or at the completion of the Preconstruction Phase, if
             the final cost estimates or lack of legislative funding make the Project no longer feasible from the standpoint of
             the Owner, the Owner may terminate this Agreement and pay the Construction Manager his proportionate fee
             due in accordance with Article 8.1 plus any costs incurred pursuant to Articles 9 and 10.
                                                ARTICLE 15
                                       ASSIGNMENT AND GOVERNING LAW
15.1   Neither the Owner nor the Construction Manager shall assign his interest in this Agreement without the written consent
       of the other except as to the assignment of proceeds.
15.2 This Agreement shall be governed by the Laws of the State of Florida.
                                                              25                                                          Rev. 9/07
                                           ARTICLE 16
                  NOTICE OF CLAIM: WAIVER OF REMEDIES; NO DAMAGES FOR DELAY
16.1   The Owner's liability to Construction Manager for any claims arising out of or related to the subject matter of this
       contract, whether in contract or tort, including, but not limited to, claims for extension of construction time, for payment
       by the Owner of the costs, damages or losses because of changed conditions under which the work is to be performed,
       or for additional work, shall be governed by the following provisions:
(a) All claims must be submitted as a Request for Change Order in the manner as provided herein;
       (b)    The Construction Manager must submit a Notice of Claim to Owner and to the Architect-Engineer within 20
              days of when the Construction Manager was or should have been aware of the occurrence of the event giving rise
              to the claim; and
       (c)    Within 10 days of submitting its Notice of Claim, the Construction Manager shall submit to the Owner its
              Request for Change Order, which shall include a written statement of all details of the claim, including a
              description of the work affected.
              The Construction Manager agrees that the Owner shall not be liable for any claim that the Construction Manager
              fails to submit as a Request for Change Order as provided in this paragraph.
16.2   After receipt of a Request for Change Order, the Owner, in consultation with the Architect-Engineer, shall deliver to the
       Construction Manager its written determination of the claim. As to matters subject to the determination by final agency
       action (not actions for breach of contract or tort) the Owner's written decision shall be final agency action unless the
       Construction Manager requests an administrative proceeding pursuant to Section 120.57, Florida Statutes, by filing a
       petition in compliance with Rule Chapter 28-106, F.A.C. within twenty-one (21) days of the Construction Manager's
       receipt of the Owner's determination.
       The venue for all civil and administrative actions against the department shall be in Leon County, unless otherwise
       agreed by the parties.
16.3   For work the Construction Manager performs with its own forces, and in addition to the adjustments provided for in
       Article 8, the Construction Manager's exclusive remedy for delays in performance of the construction caused by events
       beyond its control, including delays claimed to be caused by or attributable to the Owner or the Architect-Engineer,
       including claims based on breach of contract or negligence, shall be a claim submitted in compliance with 16.1 above,
       for an extension of the scheduled construction time. In the event of a change in such work, the Construction Manager's
       claim for adjustments in the contract sum are limited exclusively to its actual costs for such changes plus (Percent)
       for profit. The Construction Manager expressly agrees that the foregoing constitute its sole and exclusive remedies for
       delays and changes in such work, and eliminate any other remedies for claim for increase in the contract price, delays,
       changes in the work, damages, losses or additional compensation.
                                                       ARTICLE 17
                                                    MISCELLANEOUS
17.1   Harmony - Construction Manager is advised and hereby agrees that he will exert every reasonable and diligent effort to
       assure that all labor employed by Construction Manager and his Subcontractors for work on the project shall work in
       harmony with and be compatible with all other labor being used by building and construction Managers now or
       hereafter on the site of the project.
       Construction Manager further agrees that this provision will be included in all subcontracts of the Subcontractors as
       well as the Construction Manager's own contract; provided, however, that this provision shall not be interpreted or
       enforced so as to deny or abridge, on account of membership or non-membership in any labor union or labor
       organization, the right of any person to work as guaranteed by Article 1, Section 6 of the Florida Constitution.
17.2   Apprentices - If the Construction Manager employs apprentices on the project, the behavior of the Construction
       Manager and the Owner shall be governed by the provisions of Chapter 446, Florida Statutes, and by applicable
       standards and policies governing apprentice programs and agreements established by the Division of Labor of the State
       of Florida Department of Labor and Employment Security. The Construction Manager will include a provision similar
       to the foregoing sentence in each subcontract.
17.3   Invoices - Invoices shall be submitted in detail sufficient for a proper preaudit and postaudit thereof. Invoices for any
       travel expenses shall be submitted in accordance with procedures specified in Section 112.061 of the Florida Statutes
       governing payments by the State for travel expenses.
                                                               26                                                          Rev. 9/07
17.4   Construction Manager's Project Records - The Construction Manager's Project Records shall be maintained as
       prescribed hereinabove in accordance with the State of Florida General Records Schedule for State Agencies A-1 and
       shall be made available to the Owner or his authorized representative at mutually convenient times.
17.5   Construction Manager's Payment Rights - Construction Managers providing goods and services to the Owner should be
       aware of the following time frames. Upon receipt, the Owner has thirty (30) days to inspect and approve the goods and
       services. The Owner has twenty (20) days to deliver a request for payment (voucher) to the Department of Banking and
       Finance. The 20 days area measured from the latter of the date the Pay Request is received or the goods or services are
       received, inspected and approved.
       If payment is not available to the Owner for transmittal to the Construction Manager within 30 days, a separate interest
       penalty set by the Comptroller pursuant to Section 55.03, Florida Statutes, will be due and payable in addition to the
       invoice amount. To obtain the applicable interest rate, please contact the agencys Fiscal Section at (850) 487-9891.
       The 30 days are also measured from the latter of the date the invoice is received or the goods or services are received,
       inspected and approved. Interest penalties of less than one (1) dollar will not be enforced unless the Construction
       Manager requests payment. Pay Requests which have to be returned to a Construction Manager because of
       Construction Manager preparation errors will result in a delay in the payment. The Pay Requests payment requirements
       do not start until a properly completed Pay Request is provided to the Owner.
       A Vendor Ombudsman has been established within the Department of Banking and Finance. The duties of this
       individual include acting as an advocate for vendors who may be experiencing problems in obtaining timely payment(s)
       from a state agency. The Vendor Ombudsman may be contacted at (850) 410-9354 or by calling the State Comptroller's
       Hotline, 1-800-848-3792.
17.6   Public Entity Crime Information Statement - "A person or affiliate who has been placed on the convicted vendor list
       following a conviction for a public entity crime may not submit a bid on a contract to provide any goods or services to a
       public entity, may not submit a bid on a contract with a public entity for the construction or repair of a public building
       or public work, may not submit bids on leases of real property to a public entity, may not be awarded or perform work
       as a Construction Manager, supplier, subcontractor, or consultant under a contract with any public entity, and may not
       transact business with any public entity in excess of the threshold amount provided in Section 287.017, for
       CATEGORY TWO for a period of 36 months from the date of being placed on the convicted vendor list."
17.7   Criminal Background Checks-Criminal History Background Checks shall be obtained for all employees and agents of
       the Contractor and his subcontractors, their agents and employees, and all other persons performing any of the work
       under a contract to the Contractor working within buildings or facilities either owned or managed by the Department of
       Management Services. The Contractor may also be required to perform Criminal History Background Checks for all
       employees and agents of the Contractor and his subcontractors, their agents and employees, and all other persons
       performing any of the work under a contract to the Contractor working within buildings or facilities owned or managed
       by other State Agencies.
       The Contractor is obligated to obtain and pay for each Criminal History Background Report (Report), which may be
       obtained by accessing the Florida Department of Law Enforcement online at http://www.fdle.state.fl.us/criminalhistory
       This Report can be obtained within minutes via the Internet. The cost per individual check is $23 and can be paid for by
       major credit card. For assistance, the FDLE help desk is 850-410-8109.
       The Contractor must supply FDLE with the employees complete social security number to allow FDLE to run the
       Report. However, there is no need for either the Inspector General or DMS office to have this number in its entirety.
       Therefore, prior to sending reports to DMS, and to maintain confidentiality, the Contractor must blacken out all but the
       last four digits of the individuals social security number.
       The Contractor shall forward the Report to the Regional Superintendent. The Office of Inspector General will make a
       recommendation regarding whether or not to allow entry/occupation of the buildings/facilities. If the Inspector
       Generals office denies an individual access to the facilities, additional information will be required in order to re-
       consider an individual for access. The Office of the Inspector General shall keep the records on file for a minimum of
       three years.
17.8   Discrimination; Denial Or Revocation For The Right To Transact Business With Public Entities - An entity or affiliate who
       has been placed on the discriminatory vendor list may not submit a bid on a contract to provide any goods or services to a
       public entity, may not submit a bid on a contract with a public entity for the construction or repair of a public building or
       public work, may not submit bids on leases of real property to a public entity, may not be awarded or perform work as a
       contractor, supplier, subcontractor, or consultant under a contract with any public entity, and may not transact business with
       any public entity.
17.9 Unauthorized Aliens - The Department shall consider the employment by any Construction Manager of unauthorized
                                                                27                                                           Rev. 9/07
          aliens a violation of section 274A(e) of the Immigration and Nationalization Act. Such violation shall be cause for
          unilateral cancellation of this contract.
17.10     Electronic Mail Capabilities - The Construction Manager must have electronic mail capabilities through the World
          Wide Web. It is the intention of the Department of Management Services to use electronic communication for all
          projects whenever possible. The Construction Manager shall provide their electronic mail address and the name of a
          contact person responsible for their electronic communications.
17.11     Assignment - For and in recognition of good and valuable consideration, receipt of which is hereby acknowledged, the
          Construction Manager hereby conveys, sells, assigns and transfers to the State of Florida all rights, title and interest in
          and to all causes to action it may now or hereafter acquire under the antitrust laws of the United States and the State of
          Florida for price fixing, relating to the particular goods or services purchased or acquired by the State of Florida
          pursuant to this Agreement.
17.12   Contingency Statement - The State of Floridas performance and obligation to pay under this contract is contingent upon an
        annual appropriation by the Legislature.
                                                                  28                                                         Rev. 9/07
IN WITNESS WHEREOF, the parties hereto have executed this Agreement the day and year first written above.
(CONTRACTORS NAME)
Attest: APPROVED:
By XXXXXXXXXXXXXXXXXXXXXXXXXXXX                                    ByXXXXXXXXXXXXXXXXXXXXXXXXXXXX
Corporate Secretary                                                Corporate President
As Witnessed:
By XXXXXXXXXXXXXXXXXXXXXXXXXXXX                                    ByXXXXXXXXXXXXXXXXXXXXXXXXXXXX
Mary Lynn Shearer, Administrator                                   Office of General Counsel,        Date
Contracts Section                                                  Department of Management Services
As Witnessed: APPROVED:
ByXXXXXXXXXXXXXXXXXXXXXXXXXXXX                                     ByXXXXXXXXXXXXXXXXXXXXXXXXXXXX
                                                                   Dean M. Izzo, Director                 Date
                                                                   Real Estate Development and Management
                                                             29                                              Rev. 9/07
                                              EXHIBIT A
Owner
                                   Project Director
Mary Lynn Shearer                  Contracts Administrator
Dean M. Izzo                       Director
Client
Project Director
Architect-Engineer
(Names) (Titles)
Construction Manager
(Names) (Titles)
                                                  30                Rev. 9/07
                                                                    EXHIBIT B
                                                                            31                                                 Rev. 9/07
                         EXHIBIT C
Individual Title
(Names) (Titles)
Individual Title
(Names) (Titles)
                              32                 Rev. 9/07
                                                                              EXHIBIT D
PROJECT NAME:
PROJECT NUMBER:                                                                                          CONTRACT FOR:
OWNER: Department of Management Services                                                                 CONTRACT DATE:
                             Attention:                                                                  DATE OF ISSUANCE:
ARCHITECT/ENGINEER:                                                                                      CONTRACTOR:
ADDRESS:                                                                                                 ADDRESS:
CITY, STATE, ZIP:                                                                                        CITY, STATE, ZIP:
PHONE & FAX:                                                                                             PHONE & FAX:
                                                                                                         BUILDING PERMIT
CERTIFICATE OF OCCUPANCY ISSUED:                                                                         JURISDICTION:
                                                                     (Date and Attach Document)
STATE FIRE MARSHALL APPROVAL ISSUED:
                                                                                                       (Date and Attach Document)
PROJECT OR DESIGNATED PORTION SHALL INCLUDE:
The work performed under this Contract has been reviewed and found to be substantially complete. The Date of Substantial Completion
of the project or portion thereof designated above is hereby established as                                                                 which is also the date of
commencement of applicable warranties required by the Contract Documents, except as stated below.
A list of items to be completed or corrected is attached hereto. The failure to include any items on such list does not alter the responsibility of the Contractor to
complete all work in accordance with the Contract Documents. The date of commencement o
The Contractor will complete or correct the work on the list of items attached hereto within the time prescribed in the contract from the
above Date of Substantial Completion.
The Owner accepts the work or designated portion thereof as substantially complete.
Distribution to: DMS Contracts Administrator, DMS Project Director, Architect/Engineer, Contractor, Client Agency
                                                                                    33                                                                    Rev. 9/07
                                                              EXHIBIT E
AGENCY:
PROJECT:
CONTRACTOR:
CONTRACT FOR:
CONTRACT DATE:
CONTRACT AMOUNT:
CONTRACTOR'S AFFIDAVIT
I solemnly swear and affirm: That the work under the above named contract and all amendments thereto have been completed in
accordance with the requirements of said contract; that all costs incurred for equipment, materials, labor, and services against the
project have been paid; that no liens have been attached against the project; that no suits are pending by reason of work on the project
under the contract; that all Workmen's Compensation claims are covered by Workmen's Compensation insurance as required by law;
that all public liability claims are adequately covered by insurance, and that the Contractor shall save, protect, defend, indemnify, and
hold the Owners harmless from and against any and all claims which arise as a direct or indirect result of any transaction, event or
occurrence related to performance of the work contemplated under said contract.
By:
STATE OF
COUNTY OF
Notary Signature:
                                                                                               [Notary Stamp or Seal]
Name typed printed or stamped:
                                                                     34                                                               Rev. 9/07
                                                                   EXHIBIT E (CONT'D)
PROJECT NO.:
PROJECT TITLE:
CONTRACTOR:
CERTIFICATE OF ARCHITECT/ENGINEER
I CERTIFY: That the work under the above contract has been satisfactorily completed on the date set forth in accordance with the terms of the contract; that the
contractor has submitted his sworn affidavit as evidence that he has paid all labor, material
                                                                                      35                                                                     Rev. 9/07
                             EXHIBIT F
                                                            Percentage
                                                Duration     of Time
Individual        Title                         In Months   Available
                                  36                                     Rev. 9/07
                                     EXHIBIT G
                                                              Percentage
                                                              of Time
Individual                Title                                Available
                                         37                                Rev. 9/07
                             EXHIBIT H
                                                             Percentage
                                                 Duration     of Time
Individual        Title                          In Months   Available
                                 38                                       Rev. 9/07
                             EXHIBIT I
                                                            Percentage
                                                Duration     of Time
Individual        Title                         In Months   Available
                                  39                                     Rev. 9/07
                                                                                                 EXHIBIT J
CERTIFICATION BY THE CONTRACTOR: According to the best of my knowledge and belief, I certify that all items and amounts shown on the face of this Application are correct,
that all work has been performed and material supplied in full accordance with the terms and conditions of the Contract, and that all materialmen, laborers and subcontractors, as
defined in Chapter 713.01, Florida Statutes, have been paid the amounts due them out of any previous payments made to the contractor by the Owner. Further, I agree to promptly
pay each materialmen, laborer and subcontractor, as defined in Chapter 713.01, Florida Statutes, upon receipt of payment from the Owner, out of the amount paid to me on,
account of such materialman's laborer's or subcontractor's work, the amount to which said materialman, laborer and subcontractor is entitled, reflecting the percentage actually
retained, if any, from payments to myself on account of such materialman's, laborer's and subcontractor's work.
CONTRACTOR By:
STATE OF
COUNTY OF                                            The foregoing instrument was acknowledged before me this
                                                                                                                                                              (date)
by                                                                                    of
                                                                                                                              (name of corporation
                   (name of officer or agent , title of officer or agent)                                                        acknowledging)
(Title or Vendor)
CERTIFICATION BY THE ARCHITECT- ENGINEER: I certify that I have checked and verified this Progress Payment Application; that to the best of my knowledge and belief, the
above application is a true statement of the value of the work performed and the materials suitable stored on the site; that all work and materials included in this Certificate have
been inspected by me or by my authorized assistants; that all work has been performed and material supplied in full accordance with the terms of this Contract; and I approved for
payment the amount noted above.
                                                                                                           Date:
Architect-Engineer
REVIEWED AND RECOMMENDED FOR PAYMENT:
                                                                                                           Date:
Owner's Project Director
APPROVED FOR SERVICES, PERFORMED AS STATED BY:
                                                                                                           Date:
DMS Form CM03 Revised 3/07
                                                                                                  40                                                                            Rev. 9/07
                                                    EXHIBIT K
ITEMS TO BE SUBMITTED WITH GENERAL CONSTRUCTION MANAGER'S REQUEST FOR FINAL PAYMENT
______ 2. Pay Request (4 copies with original signatures and original seals, noted as Final)
______ 5.     Power of Attorney from Surety for Release of Final Payment (Signed and sealed and dated same as
              Consent of Surety)
______ 7.     Satisfactory Conclusion or Release of Lien from all subcontractors or laborers who have filed Intent to
              Liens or have indicated non-payment from the general Construction Manager (especially if attorneys
              are involved)
______ 8.      Construction Manager's Guarantee of Construction for one year from the date of substantial
              completion
______ 9.     Copy of the approval by the Architect-Engineer and the transmittal to the using agency of manuals,
              shop drawings, as-builts (two sets of disk files and two sets of blue line or black line prints),
              brochures, warranties, and List of Subcontractors, with telephone numbers and addresses
______ 10.    Verification that Using Agency personnel have been trained in the operation of their new equipment
              (per system: HVAC, controls, fire alarm, etc.), attendance lists and preferred
______ 11. Fully executed Roof Warranty (if applicable) in the name of the Using Agency
______ 12. Other special warranties as required by specifications, in the name of the Using Agency
NOTE: The Project Director shall verify the math of all Pay Requests prior to signing Final Pay Request to assure
correct payment.
Project Number:
                                                        41                                                  Rev. 9/07
                                                                                                   Exhibit L
TOTALS:
42 Rev. 9/07