MOHAMMED AL - OJAIMI ESTABLISHMENT EST.
Method Statement for Painting Works
1. Title
Method Statement for Painting Works
2. Purpose and scope
The purpose of this method is to describe the measures and ways of proper application of paint. Works
shall be carried out in compliance with the drawings, project specifications and materials.
3. Work procedure
1. Mock-up
o Mock up sample would be made for selection and approval of the Engineer prior to commencement
of the works.
2. Surface Preparation
o Hardware materials which are already fixed and not to be painted shall be removed. Removal if not
possible, it shall be covered/protected appropriately before surface preparation and painting will
commence.
o Clean and prepare concrete or Block wall surfaces to be painted. Efflorescence, chalk, dust, dirt,
grease and oils shall be removed.
o The surface of the area to be painted would be prepared by removing loose particles, blemishes and
deleterious materials by way of sanding.
3. Paint Application for inside walls
o After the surface is being prepared Latex primer, latex primer will be applied to check the undulations
in the wall and also for better bonding with the filler. After completion of Primer two coats of
filler/putty will be applied once the primer is dry.
o Next sanding would be done for cleaning and removing of splattered, blemishes and stains on the
painted surface.
MOHAMMED AL - OJAIMI ESTABLISHMENT EST.
Method Statement for Painting Works
o Two coats of Emulsion paint will be applied after completion of putty/Filler as per the approved RAL
number.
o For working at height, fixed and movable scaffolding would be erected as per area requirements.
Scaffolding when erected shall be inspected with Safety officer prior to usage. Operatives will be
inductive before working at site. Pre-start meeting would be conducted before the start of
painting activities and tool box meeting would be regularly conducted by safety officer for all concern
operatives.
o Inspection Request to be submitted for checking and approval of the Engineer.
4. Safety
1. All works shall comply with safety procedure or instruction set out in project safety plan and
Municipality rules and regulations.
2. Basic PPE to be worn by all staff or laborers.
3. All operatives involve in this work shall be inducted before entering the site.
4. Tool box talk shall be conducted regularly.
5. Equipments and tools
1. Wheel borrow
2. Drip tray
3. Drill machine
4. Pail
5. Sand paper
6. Rug cloth
6. Materials and references
1. Approved paints
2. Scope of works or specification
3. Approved drawing