DISCIPLINE:
WORK CLEARANCE
Date:
Project Name : ISFB Industrial Support Facility / EPC-6
Location of Installation
Applicable Installation
References Specification :
SATIP / SAIC:
Drawing No:
Others:
Description of Installation:
Installation executed and completed by: Installation Inspected by:
CONSTRUCTION AY C QC
Comment:
Installation ACKNOWLEDGED by:
SAPMT
NOTE:
This CLEARANCE is an internal document of AYC - ISFB Project. It does not represent or replace an RFI.
Any inspections that needs PID inspections and release, must be raised by an RFI which can support to this
Page 1 of
CLEARANCE. This does not constitute PID acceptance 4 release or as a SAIC replacement.
and
DISCIPLINE:
WORK CLEARANCE MECHANICAL
Date:
Project Name : ISFB Industrial Support Facility / EPC-6
Location of Installation
Applicable Installation
References Specification :
SATIP / SAIC:
Drawing No:
Others:
Description of Installation:
Installation executed and completed by: Installation Inspected by:
AYC Site Engineer - MECHANICAL AYC QC - MECHANICAL
Comment:
Installation ACKNOWLEDGED by:
SAPMT
NOTE:
This CLEARANCE is an internal document of AYC - ISFB Project. It does not represent or replace an RFI.
Any inspections that needs PID inspections and release, must be raised by an RFI which can support to this
Page 2 of
CLEARANCE. This does not constitute PID acceptance 4 release or as a SAIC replacement.
and
DISCIPLINE:
WORK CLEARANCE TELECOM
Date:
Project Name : ISFB Industrial Support Facility / EPC-6
Location of Installation
Applicable Installation
References Specification :
SATIP / SAIC:
Drawing No:
Others:
Description of Installation:
Installation executed and completed by: Installation Inspected by:
AYC Site Engineer - TELECOM AYC QC - TELECOM
Comment:
Installation ACKNOWLEDGED by:
SAPMT
NOTE:
This CLEARANCE is an internal document of AYC - ISFB Project. It does not represent or replace an RFI.
Any inspections that needs PID inspections and release, must be raised by an RFI which can support to this
Page 3 of
CLEARANCE. This does not constitute PID acceptance 4 release or as a SAIC replacement.
and
DISCIPLINE:
WORK CLEARANCE PLUMBING
Date:
Project Name : ISFB Industrial Support Facility / EPC-6
Location of Installation
Applicable Installation
References Specification :
SATIP / SAIC:
Drawing No:
Others:
Description of Installation:
Installation executed and completed by: Installation Inspected by:
AYC Site Engineer - PLUMBING AYC QC - PLUMBING
Comment:
Installation ACKNOWLEDGED by:
SAPMT
NOTE:
This CLEARANCE is an internal document of AYC - ISFB Project. It does not represent or replace an RFI.
Any inspections that needs PID inspections and release, must be raised by an RFI which can support to this
Page 4 of
CLEARANCE. This does not constitute PID acceptance 4 release or as a SAIC replacement.
and