Improvement of Overall Equipment Effectiveness (Oee) in Injection Moulding Process Industry
Improvement of Overall Equipment Effectiveness (Oee) in Injection Moulding Process Industry
ABSTRACT: Injection moulding is a plastic-forming process used in the production of most of the plastic parts
(about 70%) in automobile industries.The manufacturing industry has gone through significant changes in the
recent years. For a good manufacturing plant, the most recommended thing is quality, efficiency and operating
cost. These parameters depend on the function of the equipments used in the industry. Nowadays a remarkable
improvement has taken place in the maintenance management of the physical assets and productive systems to
reduce the wastage of energy and resources. Because of this, the organization should introduce a maintenance
system to improve and increase both the quality and productivity continuously.OEE is one of the performance
evaluation methods that are most common and popular in the production industries. In this work, the OEE of
the injection moulding process was increased from 61% to 81% through the implementation of availability,
better utilization of resources, high quality products and also raised employee morale and confidence.
Keywords:- Focused quality improvement , Major Losses, Maintenance, , Manufacturing performance, Overall
Equipment Effectiveness improvement, Planning, Training etc.,
I. INTRODUCTION
Management is the process of getting things done, effectively and efficiently, through and with other
people.
Objective: to attain the organizational goals.
Efficiency: doing things right.
Effectiveness: doing the right things!
In most of the automotive parts manufacturing units lack of higher rate of quality defects in produced
parts and minor stops due to workforce, planning and unskilled operators for their competitive. So that it is
required to keep proper observation for reducing product rejection and wastage, producing parts without defect,
proper training for workers and reducing equipments breakdown and down time. The term Total productive
maintenance (TPM) is originated in Japan in the year 1971 as a method for improved machine availability
through better utilization of maintenance and production resources. In most production settings the operator is
not viewed as a member of the maintenance team, in TPM. The machine operator is trained to perform many of
the day-to-day tasks of simple maintenance and fault-finding. Teams are created that include a technical expert
(often an engineer or maintenance technician) as well as operators [1]. The concept of overall equipment
effectiveness was originated from Japan in 1971.The Japan Institute of Plant Maintenance promoted the total
productive maintenance (TPM) which includes overall equipment efficiency. The OEE calculation is quite
general and can be applied to any manufacturing organization [2]. It is closely tied to JIT (Just in Time) and
TQM (Total Quality Management) and it is extension of PM (preventive maintenance), where the machines
work at high productivity and efficiency, and where the maintenance is all employee responsibility, and focus to
prevent the problem before it may occurs [3]. The aim of TPM to reduce the six major equipment losses, to zero,
has been recognized as necessary for corporate survival. TPM is a unique Japanese system of plant
management, developed from preventive maintenance concept. This approach emphasizes the role of team
work, small group activities, and the participation of all employees to accomplish equipment improvement
objectives [4]. It challenges a sense of joint responsibility between operators and maintenance workers, not only
to keep the machines running smoothly, but also to extend and optimize their overall performance [5] TPM is
intended to bring both functions (production and maintenance) together by a combination of good working
practices, team working and continuous improvement [6]. This work focus on improving the Overall Equipment
Effectiveness of the Injection Moulding machine through the implementation of availability, better utilization of
resources, high quality products and also raised employee morale and confidence.
Manufacturing Process
Pellets placed in hopper
Pellets fall into barrel through throat
Pellets packed to form solid bed. (air forced out through hopper)
Pellets melted by mechanical shear between barrel and screw
Melted plastic form shot in front of screw (screw moves back as plastic moves forward reciprocating
screw)
Screw moves forward to inject plastic into mould cavity
Part cooled and solidifies (next shot is made)
Mould opens
Ejection pins move forward to eject part
Mould closes and Process starts again
Note:-
o Injection Pressure typically 15,000 psi.(3000 ~ 40,000 psi)
o Hydraulic pressure is about 10x less
Injection moulding is a manufacture technique for making parts from plastic material. (polystyrene,
nylon, polypropylene and polythene)
Heated, fluid plastic is injected at high pressure into a mould, which is the inverse of the desired shape.
Injection moulding is used to create a variety of parts, like plastic milk cartons, containers, bottle caps,
automotive dashboards, pocket combs, and most other plastic products available today.
Injection moulding is extensively used in automobile manufacturing industry.
1.2 Polymers
Polymer (poly-many; mer-unit or parts) is defined as a substance composed or molecules characterized by
the multiple repetition or one or more species of atoms or groups or atoms linked to each other in amounts
sufficient to provide a set or properties that do not vary markedly with the addition or removal or one or a few or
the constitutional units. Oligomer is a substance composed or molecules containing a few or one or more species
or atoms or groups or atoms (constitutional units) repetitively linked to each other. Constitutional unit is a
species or atoms or group or atoms present in a chain or polymer or oligomer molecule. Monomer is a
compound consisting of molecules each or which can provide one or more constitutional units. When the
polymer is formed by polymerization of two or more than two types of monomers together the polymer is called
Copolymer. Polymerization is the process of converting a monomer or a mixture of monomers into a polymer.
Plastics: A polymeric material with the ability to flow into a desired shape when heat and pressure are
applied to it.
Polymeric material - A chemical compound formed by linking many monomer units to form larger
molecules that contain repeating structural units.
Recycling of Plastic
State and Federal Regulation
Codes for Plastics
OEE is essentially the ratio of Fully Productive Time to Planned Production Time. In practice, however, OEE is
calculated as the product of Availability, Performance and Quality.
1. Autonomous maintenance:
Fostering operator ownership.
Perform Mould cleaning water flow material flow adjustment inspection readjustment on
production equipment.
2. Focused improvement:
Systematic identification and elimination of 16 losses.
Working out loss structure and loss mitigation through.
Structured why-why analysis, FMEA (Failure Mode Effective Analysis).
Achieve improved system efficiency.
Improved OEE on production systems.
3. Planned maintenance:
Planning efficient and effective PM, PdM and TBM systems over equipment life cycle.
Establishing PM check sheets.
Improving Mean Time Between Failure (MTBR), Mean Time To Repair (MTTR).
4. Quality maintenance:
Achieving zero defects.
Tracking and addressing equipment problems and root causes.
Setting3M(machine/man/material) conditions.
5. Education and training:
Imparting technological, quality control, interpersonal skills.
Multi-skilling of employees.
Aligning employees to organizational goals.
Periodic skill evaluation and updating
6. Safety, health and environment:
Ensure safe working environment.
Provide appropriate work environment.
Eliminate incidents of injuries and accidents.
Provide standard operating procedures.
7. Office TPM:
Improve synergy between various business functions.
Remove procedural hassles.
Focus on addressing cost-related issues.
Apply 5S in office and working areas.
8. Development Management:
Minimal problems and running in time on new equipment
National Conference on Contemporary Approaches in Mechanical, 52 | Page
Automobile and Building sciences-2014
Karpaga Vinayaga College Of Engineering & Technology
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE)
e- ISSN: 2278-1684, p-ISSN : 2320334X
PP 47-60
www.iosrjournals.org
Utilize learning from existing systems to new systems Maintenance improvement initiatives
Maintenance Strategies:
Maintenance actions can be divided into four general categories or strategies. The maintenance plan for
a company's assets will be a combination of these four strategies (Fig.9), often they could all be used on the
same machine.
Break down losses: These are losses of quantity via defective products and losses of time due to
decreased productivity from equipment breakdowns.
Setup and adjustment losses: These losses stem from defective units and downtime that may be
incurred when equipment is adjusted to shift from producing one kind of product to another.
Idling and minor stoppage losses: Typically, these kinds of small losses are relatively frequent. They
result from brief periods of idleness when between units in a job or when easy to clear jams occur.
Reduced speed losses: These losses occur when equipment is run at less than its design speed.
Quality defects and rework: These are product related defects and corrections by malfunctioning
equipment.
Startup losses: These are yield losses incurred during early production, from machine startup to
steady state.
Table.1.Six Big Losses
OEE Loss OEE Loss Category
Six Big Loss Comment
Category Metric Examples
Equipment Failure
Unplanned
Downtime Losses
V. DATA ANALYSIS
Plant Operating Time = Fully Productive Time + Quality Losses + Speed Losses + Downtime Losses +
Planned Shutdown
Planned Shutdown = Tea Break + Lunch/Dinner/Supper Break
Down Time = Waiting Time for Operator + Setups & Changeover Time + Material Flow Shortage
Time + Failure or Breakdown Time + Meeting Time
Production Data:
Shift Length (Plant Operating Time)
Tea Breaks
Meals Break
Down Time
Idle(Design) Run Rate
Total number of Production Quantity
Total number of Rejected Quantity
Support Variable:
Planned Production Time = Shift Length Breaks
Operating Time = Planned Production Time Downtimes
Good Quantity = Total Production Quantity Total Rejected Quantity
Problem Statement
The bottle neck machines are selected for the implementation of TPM in the Injection Molding
Machine for the following reasons.
Poor performance among other machines
Material Refilling Problem
Oil leakage and Temperature problem
Machine Relay and Thermocouple Problem
Ejection and Clamping problems
Internal Parts Damages
Poor Housekeeping
Heater Zone problem
Quality Problems (Part Shrinkage, Catching, etc., )
Bottleneck Machine
A bottleneck is a phenomenon, where the performance or capacity of an entire system is limited by a
single or limited number of components or resources. In engineering, a bottleneck is a phenomenon by which
the performance or capacity of an entire system is severely limited by a single component. Formally, a
bottleneck lies on a system's critical path and provides the lowest throughput. A bottleneck in project
management is one process in a chain of processes, such that its limited capacity reduces the capacity of the
whole chain. The bottle neck machine is due to which productivity is going down most of the time and this plant
was selected as equipment for OEE calculation.
Table.2. List of Bottleneck Machines
Sl.No Capacity Machine Number No. of Machine Remarks
1 40 T IMM-01, IMM-07 2 Hydraulic Cylinder
OEE Calculation
Production Data
Plant Operating Time
= Shift length x 60 min
= 24 x 60 = 1440 min/day
Working days in a month
= 25 x 1440 = 36000 min/month
Planned Down Time
= Cleaning+ Break+ Meeting Time
= 30 +150 + 15 = 195 min/day
Table.3. Shift Times
Shift Timing Planned Downtime Remarks
Lunch- 12.30 ~ 01.00
I 08.00 am to 04.30 pm Tea Break- 10.30 ~ 10.40 & Downtime : 50 min
02.30 ~ 02.40
Dinner- 08.00 ~ 08.30
II 04.30 pm to 01.00 am Tea break- 06.20 ~ 06.30 & Downtime : 50 min
10.40 ~ 10.50
Supper- 04.30 ~ 5.00
III 01.00 am to 08.00 am Tea Break- 02.30 ~ 02.40 & Downtime : 50 min
0630 ~ 06.40
A sample calculation for the bottleneck machine IMM-06 is given below and for all other
machines; the values were directly mentioned in the tabular column given below (Refer Table.4).
IMM-06 Machine:
Planned Down Time = Setup & Mould Change Time + Break Time
= 300 min + 195 min = 495 min/day
= 495 min x 25 = 12375 min/month
Unplanned Down Time = Mechanical Breakdown + Electrical Breakdown + Electrical/Safety device
Breakdown
= 52.40 Hrs + 18.40 Hrs + 19.40 Hrs
= 90.20 x 60 = 5412 min/month
Total Production Parts= 1,95,500 Nos.
Total Rejection Parts = 21,600 Nos.
Good Parts = Total Production Parts Total Rejection Parts
= 1,95,500 21,600 = 1,73,900 Nos.
Ideal Run Rate = 12 parts/min
Planned Production Time = Plant Operating Time Planned Down Time
= 36000 12375 = 23625 min
Operating Time = Planned Production Time Unplanned Down Time
= 23625 5412 = 18213 min
OEE Factors
Availability = (23625 / 18213) x 100 = 77.09%
Performance = (195500 / 18213) /12 x 100 = 89.45%
Quality = (173900 / 195500) x 100 = 88.95%
OEE=77.09x 89.45x 88.95 = 61.34%
VII. METHODOLOGY
The methodology for OEE is based on the study of the steps used in the implementation of TPM in an
organization. This method is divided into various steps, whose aims are bring forth improved maintenance
policies of the mechanical equipment. Also, the continuous and through inspection of the production process is
achieved through measurements of the overall equipment effectiveness (OEE). The goal of developing this
methodology is to bring the competitive advantages, such as increasing the productivity, improving the quality
of the products and this project gives an idea about the outcomes of the industry such as productivity, quality,
profit etc., by introducing the new framework.
5S: 5S is the foundation program for TPM. It is a Japanese Nomenclature used for the implementation of TPM.
Seiri Sort / Organisation
Seiton Systematise / Tidiness
Seiso Sweep / Clean
Seiketsu Standardise
Shitsuke Self Discipline
It is a systematic process of housekeeping to identify and rectify the problems. If the 5S process is not
done in a systematic order, then it leads to more problem in production and quality. In this work the 5S audit
was done and it was finalized with few modifications. Such as, the rejection parts if found, it has to be separated
at the spot itself and sent to rework process. All the moulds and machines should be cleaned before starting the
production in every shift, etc.
Jishu Hozen: Jishu Hozen also called autonomous maintenance is a team based approach to maintenance
activities. The goal of autonomous maintenance is to prepare operators to do some equipment care
independently of the maintenance staff. Jishu Hozen implementation lays the foundation for other maintenance
activities by establishing the basic condition for a machines operation.
Kaizen: Kai means change, and zen means good (for the better). Kaizen refers to continuous improvements
in the production process to achieve better quality. Here the continuous improvement was done in 5M (Man,
Machine, Mould, Method, Material).
The workers are provided additional training and awareness program. Based on the tonnage, the
moulds and machines are listed and separated accordingly. Some required modifications in the mould to achieve
the parts in proper shape and clean surface is done. The raw material grades are varied and some improved
properties in less cost was obtained. Optimization of process parameters were done by trial and error method.
By doing these works, the 5 evils such as defects, mistakes, delay, wastage and accidents can be
avoided or neglected. After successful implementation of TPM, it is found that OEE is increased (Refer Table.6)
upto 20%.
Classification of Abnormalities: After setting up of standards for all machines, abnormalities are found in all
machine, which is noted during the initial cleanup. It is systematic method to organize, order, clean and
standardize a work place and keep it that way. In this activity
Table.6.Abnormalities in IMM
Sl.No M/c No. Problem Corrective Action Benefits
1 5&8 Nozzle Heater Problem Heater replaced 6%
2 7,8 & 10 Oil Leakage Problem in Pump side New Hydraulic Hose replaced 8%
3 1,4,5 & 9 Nozzle Temp. variation New Thermocouple replaced 16%
4 3,8 & 7 Zone-01 Heater problem New Heater replaced 6%
5 11 Machine SMPS Problem New one replaced 12%
6 9 Ejection Cylinder Problem Serviced 21%
Production Data
Plant Operating Time
= Shift length x 60 min
= 24 x 60 = 1440 min/day
Working days in a month
= 25 x 1440 = 36000 min/month
Planned Down Time
= Cleaning+ Break+ Meeting Tim
= 30 + 70 + 15 = 105 min/day
VIII. CONCLUSION
It is essential for a company to improve the production rate and quality of the products. In order to
achieve this, the Overall Equipment Effectiveness was improved with low machine breakdown, less idling and
minor stops time, less quality defects, reduced accident in plants, increased the productivity rate, optimised
process parameters, worker involvement, improved profits through cost saving method, increased customer
satisfaction and increasing sales. The Overall Equipment Effectiveness of the Injection Moulding machine was
increased from 61% to 81% through the implementation of availability, better utilization of resources, high
quality products and also raised employee morale and confidence.
REFERENCES
[1] Abhishek Jain, Rajbir Bhatti, Harwinder Singh Deep and hiv kumar Sharma, Implementation of TPM
for Enhancing OEE of Small Scale Industry, International Journal of IT, Engineering and Applied
Science Research, 2012, Volume 1 No 1.
[2] Philip Godfrey, Overall Equipment Effectiveness Manufacturing Engineering, 2002, Vol, 81(3), 109-
112.
[3] Islam H. Afefy Implementation of Total Productive Maintenance and Overall Equipment Effectiveness
Evaluation, International Journal of Mechanical & Mechatronics Engineering, 2013, Vol:13.
[4] Bulent Dal, Phil Tugwell, and Richard Greatbanks, Overall equipment effectiveness as a measure of
operational improvement A practical analysis, International Journal of Operations & Production
Management, 2000, 20(12), 1488-1502.
[5] Debadyuti Das. Total Productive maintenance (TPM): A comprehensive tool for achieving excellence in
operations system A case study, Industrial Engineering Journal 2001, 30 (10), 15.
[6] Cooke, F. L., Implementing TPM in plant maintenance: some organizational barriers, International
Journal of Quality and Reliability Management, 2000,17(9), 1003-1016.
[7] Thomas R. Pomorski, Total Productive Maintenance (TPM) Concepts and Literature Review, Brooks
Automation, Inc.2004.
[8] Melesse Worknesh Wakjira, Ajit Pal Singh Total Productive Maintenance: A Case Study in
Manufacturing Global Journal of Researches in Engineering Industrial Engineering, 2012, Volume 12.
[9] Amit Kumar Gupta, R.K.Garg OEE Improvement by TPM Implementation: A Case Study,
International Journal of IT, Engineering and Applied Sciences Research, 2012, Volume 1.
[10] Gaurav Gera, Gurpreet Saini, Rajender Kumar, S.K.Gupta Improvement of Operational Efficiency of
Equipment through TPM: A Case Study, International Journal of Industrial Engineering Research and
Development, 2012, Volume 3.