Project: Mid end- Residential Building
Zone: R2
Lot: 192.15 SQ. M
Total Floor Area
Ground Floor Floor area(m2)
Garage 30.7
Porch 10.9
Living room &Foyer & Dining room 71.9
Kitchen with nook 26.08
Dirty kitchen 7.66
Laundry area and utilities 9.64
Powder rooom 3.68
Maids room with t&b 10.52
Hallways 21.07
Total 192.15
2nd Floor Floor area(m2)
Master bedroom with t&b 42.54
Girl's room/ Boy's room 48.32
toilet & bath 3.24
family room 25.3
balcony 10.9
Hallways 15.06
Stairs 5.19
Total 150.55
EXCAVATION WORKS
PARTS DIMENSIOHEIGHT(m)NUMBER TOTAL VOLUME(m3)
FOOTINGS
F1 1.5X1.5 1.7 17 65.025
F2 1.2X1.2 1.7 4 9.792
F3 1.0X1.0 1.7 7 11.9
CONCRETE WORKS
PARTS DIMENSIONTHICKNESS NUMBER TOTAL VOLUME(m3)
FOOTINGS
F1 1.5X1.5 0.3 17 11.475
F2 1.2X1.2 0.3 4 1.728
F3 1.0X1.0 0.3 7 2.1
COLUMNS 0.2x0.4 5.5 28 15.456
TERMINATED 0.2x0.4 9 2.952
TOTAL 12.504
2ND FLOOR BEAMS 0.2x0.4 0.4 10.686
ROOF BEAMS 0.2x0.3
SLAB
SUSPENDED SLAB 150.655 0.1 1 15.0655
SLAB OR FILL 181.25 0.1 1 18.125
CF1 (17)
TILE QUANTITY VOLUME: 1.5x1.5x0.3=0.6
PORTLAND CEMENT: 5.06
GROUND FLOOR QUANTITY WHITESAND: 0.3375x17=
PORCH 117 GRAVEL: 0.675x17=11.47
DINING FOYER AND LIVING ROOM 190
KITCHEN 96 CF2 (4)
DIRTY KITCHEN 72 VOLUME: 1.2X1.2X0.3=0.
MAIDS ROOM 75 PORTLAND CEMENT: 3.24
TOILET AND BATHROOM 71 WHITE SAND: 0.216X4=0
T&B WALL 220 GRAVEL: 0.432X4=1.728 C
POWDER ROOM 77
2ND FLOOR CF3 (7)
BEDROOMS 117 VOLUME: 1X1X0.3
HALLWAY AND FAMILY ROOM 103 PORTLAND CEMENT: 2.25
MASTER'S BEDROOM 89 WHITESAND: 0.15X7=1.0
MASTER'S T&B 202 GRAVEL: 0.3X7=2.1 CU. M
MASTER'S T&B WALL 265
T&B 80 COLUMNS
t&B WALL 225 VOLUME: 12.504 CU.M
BALCONY 112 PORTLAND CEMENT: 113
WHITESAND: 6.252 CU.M
GRAVEL: 12.504 CU.M
2ND FLOOR BEAMS
VOLUME: 10.686 CU.M
PORTLAND CEMENT: 97 B
WHITESAND: 5.343 CU.M
GRAVEL: 10.686 CU.M
ROOFBEAMS
VOLUME: 10.398 CU.M
PORTLAND CEMENT: 94 B
WHITESAND: 5.199 CU.M
GRAVEL: 10.398 CU.M
SUSPENDED SLAB
VOLUME: 13.255 CU.M
PORTLAND CEMENT: 120
WHITESAND: 6.6275 CU.M
GRAVEL: 13.255 CU.M
SLAB OR FILL
VOLUME: 18.125 CU.M
PORTLAND CEMENT: 164
WHITESAND: 9.0625 CU.M
GRAVEL: 18.125 CU.M
VOLUME: 1.5x1.5x0.3=0.675
PORTLAND CEMENT: 5.0625x17=87bags
WHITESAND: 0.3375x17=5.73 cu.m
GRAVEL: 0.675x17=11.475 cu.m
VOLUME: 1.2X1.2X0.3=0.432 CU.M
PORTLAND CEMENT: 3.24X4=13 BAGS
WHITE SAND: 0.216X4=0.864 CU.M
GRAVEL: 0.432X4=1.728 CU.M
VOLUME: 1X1X0.3
PORTLAND CEMENT: 2.25X7=16 BAGS
WHITESAND: 0.15X7=1.05 CU.M
GRAVEL: 0.3X7=2.1 CU. M
COLUMNS
VOLUME: 12.504 CU.M
PORTLAND CEMENT: 113 BAGS
WHITESAND: 6.252 CU.M
GRAVEL: 12.504 CU.M
2ND FLOOR BEAMS
VOLUME: 10.686 CU.M
PORTLAND CEMENT: 97 BAGS
WHITESAND: 5.343 CU.M
GRAVEL: 10.686 CU.M
ROOFBEAMS
VOLUME: 10.398 CU.M
PORTLAND CEMENT: 94 BAGS
WHITESAND: 5.199 CU.M
GRAVEL: 10.398 CU.M
SUSPENDED SLAB
VOLUME: 13.255 CU.M
PORTLAND CEMENT: 120 BAGS
WHITESAND: 6.6275 CU.M
GRAVEL: 13.255 CU.M
SLAB OR FILL
VOLUME: 18.125 CU.M
PORTLAND CEMENT: 164 BAGS
WHITESAND: 9.0625 CU.M
GRAVEL: 18.125 CU.M