Our end- to- end development expertise is
Town Planning
tailored to your needs to enhance your design
Architectural Design and build experience.
Project Management
CONSTRUCTION SEQUENCING GUIDE
Building design and construction is no small undertaking at any scale and every project comes with their own challenges having an
understanding of what might occur throughout the construction of your project can provide ease of mind and enable to you to be aware of
imminent issues before your project is delay. Effective project management through the construction stage mitigates construction cost risks and
ensures effective communication with consultants and the builder at every stage of project delivery.
TYPICAL CONSTRUCTION PROCESS
Each construction process is unique and will be influenced by different construction methods, builder and project manager preferences, project
scale, design requirement and site conditions. However a typical building sequence will be similar to the following:
Excavate site platform
Set-out the footings, excavate and pour
Form up and pour the floor slab
Set-out and construct house frame (timber, brick, block, steel)
Erect the roof framing/trusses
Fix roof cladding
Install external windows, plumbing and electrical (rough in)
Finish internal and external walls
Internal fit out, including services
Landscaping
NOTIFY CERTIFIER
Construction should always begin with the consultation of your certifier (this is done to ensure timeframes for the application process,
inspections are mutually understood to mitigate any issues that may hinder the progress of your project)
CLEAR SITE
Remove unwanted vegetation from the site
Level the site as per specifications (excavator may be required)
Erosion and sediment control devices installed
TEMPORARY POWER AND WATER
Prior to construction you will need temporary electricity, water supply and ablution facilities
SET OUT
Can be done by a surveyor, concretor, carpenter, bricklayer (accuracy is necessary to avoid expensive mistakes)
Accuracy with distances from boundaries to the building are crucial (these will be checked for compliance with building regulations by the
certifier)
EXCAVATION OF FOOTINGS
Site to be excavated for footings
Steel for the foundations is fixed into position
The engineer, certifier or both will inspect the footings prior to concrete being poured
FOOTING INSPECTION
Give notice (usually 24 to 48 hours) to the certifier
If used, the engineer, will also require notice
SYDNEY
26 Carinya Avenue
aaddesign.com.au Brighton-Le-Sands, NSW
(02) 9599 6912
Our end- to- end development expertise is
Town Planning
tailored to your needs to enhance your design
Architectural Design and build experience.
Project Management
CONSTRUCTION SEQUENCING GUIDE
UNDER FLOOR DRAINAGE SERVICES
Before footings are poured drainer is required to install pipework going under the floor (i.e. wastewater drains or water supply)
POURING THE FOOTINGS
Concrete for footings poured as soon as possible after inspection
UNDER FLOOR DRAINAGE INSPECTION
Underfloor drainage will need to be inspection prior to covering the pipes with slab or floors with low clearance (less than standing)
Give notice (usually 24 to 48 hours) to the local government plumbing inspector.
Drainer usually gives notice, clarify this with drainer
MAIN DRAINS
The sewerage and stormwater is usually installed around the time of the slab pour or sub-floor is construction
The sewerage and stormwater can also be installed after all the brickwork and/or cladding and internal linings are complete
MAIN DRAIN INSPECTION
Give notice (usually 24 to 48 hours) to the local government plumbing inspector prior to backfilling trenches
ELECTRICAL SERVICES
Electrical services may need to put in or under the slab or behind brickwork
A licensed electrician is required
PREPARATION OF SLAB
Base walls or fully braced edge boards are placed to form the perimeter of the slab.
Under slab area is built up with compacted fill
Termite treatment system is put in place
Under floor services are positioned to plan (generally only drainage pipe work)
The waterproof membrane placed in position
Any edge boards for recesses or step-downs are positioned and braced.
Service penetrations through the waterproof membrane are sealed
TERMITE TREATMENT
Approved termite mesh, reticulated delivery system for chemical poison or other acceptable form of treatment is required.
Retain the treatment certificate for future reference.
SLAB INSPECTION
Give notice (usually 24 to 48 hours) to the certifier
POURING SLAB
If you allow the concretor to supply their own material ensure they keep all dockets also ask for concrete test results
WALLS AND FLOOR FRAMING
For a timber or brick veneer house you will require a carpenter
For a block or cavity brick house you will require a bricklayer
If your project has block or cavity brick walls and a timber framed floor you will require both
SYDNEY
26 Carinya Avenue
aaddesign.com.au Brighton-Le-Sands, NSW
(02) 9599 6912
Our end- to- end development expertise is
Town Planning
tailored to your needs to enhance your design
Architectural Design and build experience.
Project Management
CONSTRUCTION SEQUENCING GUIDE
ROOF FRAMING
FRAME INSPECTION
Give notice (usually 24 to 48 hours) to the certifier
GUTTERING AND DOWNPIPES
the fascia and barges and gutters are fixed after wall and roof framing is complete
Fall gutters to the correct downpipe positions.
Ensure gutters are in place before any roofing goes on.
Connect downpipe droppers to temporary downpipes and pipe any rainwater away from the footings
ROOF
Install roof sarking prior to fixing roof battens.
Fix roof battens
Fix roofing
WINDOWS AND EXTERNAL DOORS
Windows are to be fixed as soon as possible after roofing
Ensure flashings are used where required
Fix external door frames
SERVICES
Before fixing any wall sheeting is fixed or cavity brick or block walls go up it will be necessary engage the following contractors:
A plumber and drainer to fix pipes into walls, connect up to the mains, and test for leaks
An electrician to wire for the power, lighting systems and fire detectors required
Wiring should also be done for communication and data now
Ducting is to be installed for mechanical systems
PLUMBING ROUGH-IN AND ELEVATED DRAIN INSPECTION
Give notice (usually 24 to 48 hours) to the local government plumbing inspector
BRICKWORK - EXTERNAL WALLS
Fix sarking to external walls
Build veneer to outside
INTERNAL LININGS
Internal linings fitted by a plasterer (ensure that all plumbing and electrical work is correct first)
JOINERY
Fix all internal doors, skirtings, architraves, shelving, kitchen cupboards, vanities and other cupboards
WET AREA FLASHINGS
After the walls are sheeted, an accredited waterproofing system must be used to seal the walls and floors of shower recesses
A copy of the waterproofing certificate must go to the building certifier.
SYDNEY
26 Carinya Avenue
aaddesign.com.au Brighton-Le-Sands, NSW
(02) 9599 6912
Our end- to- end development expertise is
Town Planning
tailored to your needs to enhance your design
Architectural Design and build experience.
Project Management
CONSTRUCTION SEQUENCING GUIDE
FLOOR AND WALL COVERS
Tile all floors (when tiling the floors in wet areas, be sure that the floor is sloping to the floor waste)
Cover floors in chosen finish
PAINTING, INTERNAL AND EXTERNAL
An experienced painter will finish the internal and external surfaces and rectify minor imperfections in the finished surface (ensure that the
painter leaves paint to use for touch-ups, or include in the contract a requirement for the Painter to come back to do the touch-ups after all
trades have been through)
SHOWER SCREENS, MIRRORS AND ROBE DOORS
After the painter and tiler are finished the shower screens, mirrors and aluminium framed sliding robe doors can be fitted
FINAL FIT-OUT FOR PLUMBING
Fit all wastes and taps to sinks and tubs, and install toilets and the hot water service
Check the sewage has been connected and ensure all stormwater drainage is in place
FINAL PLUMBING AND DRAINAGE INSPECTION
Give notice (usually 24 to 48 hours) to the local government plumbing inspector
FINAL FIT-OUT FOR ELECTRICAL
Electrician to fit all switches, power points and wire up all electrical fittings
PERIMETER TERMITE TREATMENT
A durable notice describing chosen termite treatment system and maintenance requirements must be permanently fixed to the building
Perimeter treatments will need to be redoing if soil beside or adjacent to the building, or the concrete cap, is disturbed
FINAL INSPECTION
Give notice (usually 24 to 48 hours) to the certifier
Disconnect temporary services.
SYDNEY
26 Carinya Avenue
aaddesign.com.au Brighton-Le-Sands, NSW
(02) 9599 6912