BRIDGE & ROOF CO.(I) LTD.
HPCL
( A GOVERNMENT OF INDIA OWNER:
ENTERPRISES)
PROJECT : FOUNDATION DESIGN FOR HPCL, VIZAG
ORDER NO.: D4003 REV : 0 PREP BY : CHEKD BY: APRVD BY:
A.K - 10.09.2017 J.R - 10.09.2017 J.R - 10.09.2017
NH
R
A
GENERAL LAYOUT OF WALKWAY
A = MINIMUM OFFSET FROM THE CIRCULAR TANK + RADIUS OF THE TANK
A=O + R
H= TOTAL LENGTH OF THE POLYGONAL PART OF WALKWAY
NH = LENGTH OF THE NON- POLYGONAL PART OF WALKWAY
= (180 - 360/n) x 0.5
WHERE n = NO OF SIDES OF THE POLYGON
B= WIDTH OF A SIDE OF THE POLYGON
MATHEMATICALLY:-
B= 2A / TAN
H= n x B
L= TOTAL LENGTH OF THE WALKWAY
L= NH+H
INPUT:-
n= 8
= 67.5 0
= 1.1780972 radians
RADIUS MINIMU
TANK OF THE M
NH (IN
TANK NO. FARM TANK OFFSET A (IN M) B (IN M) H (IN M) L (IN M)
M)
NO. ( R ) (IN (O) (IN
M) M)
701-T-102A TF-01 33 5.575 38.575 31.957 255.656 27.33 282.986
701-T-102B TF-01 33 5.875 38.875 32.205 257.64 27.03 284.67
701-T-101A TF-02 24 4.64 28.64 23.726 189.808 27.836 217.644
701-T-101B TF-02 24 4.652 28.652 23.736 189.888 27.836 217.724
701-T-101C TF-03 24 4.64 28.64 23.726 189.808 27.836 217.644
701-T-101D TF-03 24 4.64 28.64 23.726 189.808 27.836 217.644
701-T-101E TF-03 24 4.64 28.64 23.726 189.808 27.836 217.644
701-T-103A TF-04 24 4.64 28.64 23.726 189.808 27.836 217.644
701-T-103B TF-04 24 4.64 28.64 23.726 189.808 27.836 217.644
701-T-103C TF-04 24 4.64 28.64 23.726 189.808 27.836 217.644
701-T-105A TF-05 20.5 4.366 24.866 20.6 164.8 15.5 180.3
701-T-105B TF-05 20.5 4.366 24.866 20.6 164.8 15.5 180.3
701-T-104A TF-06 20.5 4.366 24.866 20.6 164.8 15.5 180.3
701-T-104B TF-06 20.5 4.366 24.866 20.6 164.8 15.5 180.3
701-T-104C TF-06 20.5 4.366 24.866 20.6 164.8 15.5 180.3
HENCE, THE LENGTH OF THE WALKWAY OF DIFFERENT TANK FARM CAN BE TABULATED AS
FOLLOWS:-
TANK FARM LENGTH OF
NO. WALKWAY (IN M)
TF-01 567.656
TF-02 435.368
TF-03 652.932
TF-04 652.932
TF-05 360.6
TF-06 540.9