The document provides maintenance guidelines for various electrical equipment: - Air circuit breakers, vacuum circuit breakers, and oil circuit breakers should be cleaned and have their contacts and mechanisms inspected. Gaps and alignments should be checked. - Low voltage panels should also be cleaned and have busbars, contacts, hardware, and auxiliary devices inspected. Insulation resistance tests are recommended. - Control wiring maintenance includes inspecting devices like contactors, relays, switches, and ensuring tight terminals and connections.

Uploaded by

ssvasavaongc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
174 views9 pages

Air Circuit Breaker-2

The document provides maintenance guidelines for various electrical equipment: - Air circuit breakers, vacuum circuit breakers, and oil circuit breakers should be cleaned and have their contacts and mechanisms inspected. Gaps and alignments should be checked. - Low voltage panels should also be cleaned and have busbars, contacts, hardware, and auxiliary devices inspected. Insulation resistance tests are recommended. - Control wiring maintenance includes inspecting devices like contactors, relays, switches, and ensuring tight terminals and connections.

Uploaded by

ssvasavaongc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 9

Electrical Breaker – Preventing Maintenance

Air Circuit Breaker (ACB)

 Cleaning of breaker with CRC-226

 Removal of old Grease and re-greasing the same with recommended grease

 Check condition of arcing contact and gap between fixed and moving arcing contracts shall be checked.

 Check condition of arcing contact and gap between fixed and moving arcing contracts shall be checked.

 Checking the reset mechanism, tripping of breaker through push button.

 Checking the reset mechanism, tripping of breaker through push button.

 Checking tripping of ACB through protection release.

 Checking presence and proper tightening of hardware.

 Checking presence of all cir clips.


 Checking condition and alignment of jaw contract with cradle terminals

 Checking condition of ACB wiring and replace if required.

 Checking and adjusting gap between hylam sheet and side plate.

 Checking proper closing of all poles together.

 Checking working of anti pumping device in case of EDO ACB.

 Checking alignment of SIC and its operation.

 Checking scrapping earth alignment.

 Checking condition of arc chutes.

 Checking U/V release pickup and drop off.

 Checking ACB tripping through Shunt release.

 Checking motor operation in case of EDO ACB.

 Checking closing coil operation in case of EDO ACB.


 Checking continuity and proper changeover of aux contract block.

 Checking IR between phases – phase (ACB Closed condition).

 Checking IR between phases – earth (ACB closed Condition).

 Checking IR between phases – earth (ACB in open condition).

 Setting of release as per the load.

Note - After the inspection, the ACB shall be checked for proper termination by mv drop Test

Vacuum Circuit Breaker (VCB):

 Cleaning of Vacuum Circuit Breaker with CRC-226

 Removal of old grease and re-greasing the same with recommended grease

 Check condition of SIC Contacts

 Checking condition and alignment of jaw Contact

 Checking and proper tightening of hardware


 Checking proper closing of all poles together

 Checking of breaker tripping through push button

 Checking and adjusting gap between hylam sheet and side plate

 Checking motor operation in case of EDO.

 Checking of auxiliary contacts continuity proper change over

 Checking presence of all circlips

 Checking IR between phase – phase (VCB closed condition)

 Checking IR between phase – earth (VCB closed condition)

 Checking IR between phase – earth (VCB in Open condition)

 Any faculty spare replace by new one, which will be charged extra.

Oil Circuit Breaker (OCB)

 Cleaning of Oil Circuit Breaker with CRC-226


 Removal of old grease and re-greasing the same with recommended grease

 Check condition of SIC Contacts

 Checking condition and alignment of jaw Contact

 Checking and proper tightening of hardware

 Checking proper closing of all poles together

 Checking of breaker tripping through push button

 Checking and adjusting gap between hylam sheet and side plate

 Checking motor operation in case of EDO.

 Checking of auxiliary contacts continuity proper change over

 Checking presence of all circlips

 Checking IR between phase – phase (OCB closed condition)

 Checking IR between phase – earth (OCB closed condition)


 Checking IR between phase – earth (OCB in Open condition)

 Any faculty spare replace by new one, which will be charged extra

LT Panel (during regular maintenance of LT Panel)

 Cleaning of Panel Breaker with CRC-226

 Check condition of Bus bars

 Checking condition and alignment of jaw Contact

 Checking and proper tightening of hardwares

 Checking of breaker tripping through push button

 Checking motor operation in case of EDO.

 Checking of auxiliary contacts continuity proper change overs

 Checking presence of all circlips

 Checking IR between phase – phase (ACB closed condition)


 Checking IR between phase – earth (ACB closed condition)

 Checking IR between phase – earth (ACB in Open condition)

 Checking of Contactor NO NC Point

 Checking of ad on block NO NC Point

 Checking of Control Wiring

 Checking of Thimble Tightness

 Checking of MCCB

 Checking o MCB

 Any faculty spare replace by new one, which will be charged extra.

Control Wiring (during regular maintenance of Control Wiring)

 Checking of All Control Wiring

 Checking of Contactor in NO/NC Point


 Checking of Glass Relay in NO/NC Point

 Checking of MCB Terminals

 Checking of RCCB Terminals

 Checking of Contactor Coil Resistance

 Checking of auxiliary Contact

 Checking of thimble of Terminals

 Checking of indicator of Panel

 Checking selectors switch in NO/NC Point

 Checking of TNC Switch in NO/NC Point

 Checking of Fuse Link Terminals

 Checking of Timer Relay Terminals

 Checking of Amp Meter Tightening at Terminals


 Checking of voltage meter Tightening at Terminals