Al Mussafah A Al Mussafah Ahalia Hospital Al Mussafah Ahalia Hospital

This document outlines the project benchmark dates and activities for the Al Mussafah Ahalia Hospital Project over a 27 month period. It includes key milestones such as commencement, completion of sub-structure and superstructure, MEP works, finishes, and project completion. It also lists the general works including mobilization, site preparation, technical submittals and approvals, and procurement activities. The original durations range from 0 to 389 days with many activities occurring concurrently over multiple months.

Uploaded by

Châu Tú
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
104 views4 pages

Al Mussafah A Al Mussafah Ahalia Hospital Al Mussafah Ahalia Hospital

This document outlines the project benchmark dates and activities for the Al Mussafah Ahalia Hospital Project over a 27 month period. It includes key milestones such as commencement, completion of sub-structure and superstructure, MEP works, finishes, and project completion. It also lists the general works including mobilization, site preparation, technical submittals and approvals, and procurement activities. The original durations range from 0 to 389 days with many activities occurring concurrently over multiple months.

Uploaded by

Châu Tú
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Activity ID Activity Name Original

Duration Month
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
AL MUSSAFAH AHALIA
A HOSPITAL
PROJECT BENCHMARK
BEN DATES
XXX-0000 Commencement Date/Site Possession 0 Commencement Date/Site Possession
XXX-0010 Receipt of Contract Documents & IFC Drawings 0 Receipt of Contract Documents & IFC Drawings
XXX-0020 Receipt of Building Permit 0 Receipt of Building Permit
XXX-0030 Completion of Sub-Structure 0 Completion of Sub-Structure
XXX-0040 Completion of Superstructure 0 Completion of Superstructure
XXX-0050 Completion of MEP Works 0 Completion of MEP Works
XXX-0060 Completion of Finishes 0 Completion of Finishes
XXX-0070 Project Completion 0 Project Completion
XXX-0080 Power On 0 Power On

GENERAL WO
WORKS
MOBILIZATION AN D P REPERATORY WORKS
PRE-0010 Mobilization 62 Mobilization
PRE-0020 Installation of Temp. Site O ffices and Facilities 55 Installation of Temp. Site O ffices and Facilities
PRE-0030 Pre-Construction Survey and Site Setting Out 5 Pre-Construction Survey and Site Setting Out
PRE-0040 Geotechnical Soil Investigation 18 Geotechnical Soil Investigation
PRE-0050 Demolish Existing Building and Site Clearance 31 Demolish Existing Building and Site Clearance
PRE-0060 Install Tower Cranes 27 Install Tower Cranes
TECHNICAL SUBMITTALS
SU & APPROVALS
SUBMITTALS
PRE-1010 Prepare and Submit QC/QC and Safety Plans 31 Prepare and Submit QC/QC and Safety Plans
PRE-1020 Prepare and Submit Construction Schedule 31 Prepare and Submit Construction Schedule
PRE-1030 Prepare and Submit Construction Methodologies 289 Prepare and Submit Construction Methodologies
PRE-1040 Prepare and Submit Civil/Structural Materials 304 Prepare and Submit Civil/Structural Materials
PRE-1050 Prepare and Submit MEP Materials and Equipment 304 Prepare and Submit MEP Materials and Equipment
PRE-1060 Prepare and Submit Conveying System 61 Prepare and Submit Conveying System
PRE-1070 Prepare and Submit Finishing Materials 151 Prepare and Submit Finishing Materials
PRE-1080 Prepare and Submit Shop Drawings 389 Prepare and Submit Shop Drawings
PRE-1090 Prepare and Submit As-Built Drawings 250 Prepare and Submit As-Built Drawings
REVIEW AND APPROVALS
A
PRE-2010 Review and Approval of QC/QC and Safety Plans 31 Review and Approval of QC/QC and Safety Plans
PRE-2020 Review and Approval of Construction Schedule 31 Review and Approval of Construction Schedule
PRE-2030 Review and Approval of Construction Methodologies 289 Review and Approval of Construction Methodologies
PRE-2040 Review and Approval of Civil/Structural Materials 304 Review and Approval of Civil/Structural Materials
PRE-2050 Review and Approval of MEP Materials and Equipment 304 Review and Approval of MEP Materials and Equipment
PRE-2060 Review and Approval of Conveying System 61 Review and Approval of Conveying System
PRE-2070 Review and Approval of Finishing Materials 151 Review and Approval of Finishing Materials
PRE-2080 Review and Approval of Shop Drawings 389 Review and Approval of Shop Drawings
PRE-2090 Review and Approval of As-built Drawings 250 Review and Approval of As-built Drawings
PROCUREMEN OF LONG LEAD ITEMS
PROCUREMENT
XXX-1020 Procurement of Conveying Systems 209 Procurement of Conveying Systems

CONSTRUCTION
CONSTRUCTIO
STRUCTURAL WORKS
SUB-0000 Start Structural Works 0 Start Structural Works
SUB-0005 Finish Structural Works 0 Finish Structural Works
SUBSTRUCTURE
SUBSTRUCTU
PILING WORKS
WOR
SUB-0010 Exacavate to Platform Level for Bored Piling Operation 12 Exacavate to Platform Level for Bored Piling Operation
SUB-0015 Mobilization of Drilling Rigs (by Sub-Contractor. 12 Mobilization of Drilling Rigs (by Sub-Contractor.
SUB-0020 Bored Piling Operation and Pile Test 60 Bored Piling Operation and Pile Test
SUB-0030 Excavate up to Bottom of Pile Caps 30 Excavate up to Bottom of Pile Caps
SUB-0040 Trimming and Treatment of Pile Heads 30 Trimming and Treatment of Pile Heads
SUB-0050 Fill/Compact Working Platform for Secant Piling Operation 12 Fill/Compact Working Platform for Secant Piling Operation
SUB-0060 Secant Pile Retaining Walls 40 Secant Pile Retaining Walls
SUB-0070 Construct Capping Beam for Secant Pile Retaining Walls 40 Construct Capping Beam for Secant Pile Retaining Walls
SUB-0080 Parking Area - Install Suitable De-watering System (If Required) 16 Parking Area - Install Suitable De-watering System (If Required)

CAR PARKING AREA - BASEMENT 2


SUB-1010 Excavation Inside Cofferdam 26 Excavation Inside Cofferdam
SUB-1020 Spray Gunite on Secant Pile Retaining Wall Surfaces 20 Spray Gunite on Secant Pile Retaining Wall Surfaces
SUB-1030 Blinding and Waterproofing under Base Slab 12 Blinding and Waterproofing under Base Slab
SUB-1040 Water proofing on Retainin g Walls 16 Water proofing on Retaining Walls
SUB-1050 Construct Base Slab 20 Construct Base Slab
SUB-1051 Construct Base Slab (Part 1) 7 Construct Base Slab (Part 1)
SUB-1052 Construct Base Slab (Part 2) 7 Construct Base Slab (Part 2)
SUB-1053 Construct Base Slab (Part 3) 7 Construct Base Slab (Part 3)
SUB-1054 Construct Base Slab (Part 4) 7 Construct Base Slab (Part 4)
SUB-1060 Construct Perimeter Walls, Inter nal Walls and Columns 20 Construct Perimeter Walls, Inter nal Walls and Columns
SUB-1070 Construct Water Tank Walls and Columns (1st Lift) 10 Construct Water Tank Walls and Columns (1st Lift)
SUB-1080 Construct Water Tank Walls and Columns (2nd Lift) 12 Construct Water Tank Walls and Columns (2nd Lift)

Actual Work Critical Milestone AMAH-1 Date Revision Checked Approved


30-Nov-11 ISSUED FOR TENDER
Remaining Work
AL MUSSAFAH AHALIA HOSPITAL
Critical Remaining Work PRELIMINARY SCHEDULE
Milestone
Actual Milestone 1 of 4
Activity ID Activity Name Original
Duration Month
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
SUB-1090 Construct Beams and Deck Slab @ -2.55 Level 18 Construct Beams and Deck Slab @ -2.55 Level
SUB-1091 Construct Beams and Deck Slab @ -2.55 Level (Part 1) 10 Construct Beams and Deck Slab @ -2.55 Level (Part 1)
SUB-1092 Construct Beams and Deck Slab @ -2.55 Level (Part 2) 10 Construct Beams and Deck Slab @ -2.55 Level (Part 2)
SUB-1100 Construct Stairways and Ramp (from -5.55 to -2.55 Level) 10 Construct Stairways and Ramp (from -5.55 to -2.55 Level)
CAR PARKING AREA - BASEMENT 1
SUB-2010 Water proofing on Retainin g Walls 10 Water proofing on Retainin g Walls
SUB-2020 Construct Perimeter Walls, Inter nal Walls and Columns 16 Construct Perimeter Walls, Inter nal Walls and Columns
SUB-2030 Construct Beams and Deck Slab @ +0.55 Level 16 Construct Beams and Deck Slab @ +0.55 Level
SUB-2031 Construct Beams and Deck Slab @ +0.55 Level (Part 1) 10 Construct Beams and Deck Slab @ +0.55 Level (Part 1)
SUB-2032 Construct Beams and Deck Slab @ +0.55 Level (Part 2) 10 Construct Beams and Deck Slab @ +0.55 Level (Part 2)
SUB-2040 Construct Water Tank Roof Slab @ +0.55 Level 8 Construct Water Tank Roof Slab @ +0.55 Level
SUB-2050 Construct Stairways and Ramp (from -2.55 to +0.55 Level) 10 Construct Stairways and Ramp (from -2.55 to +0.55 Level)
SUB-2060 Water Pr oofin g to Water Tank External and Internal Surfaces 20 Water Pr oofing to Water Tank External and Internal Surfaces
SUB-2070 Backfilling & Compaction Around Parking Aea to Finish Level 28 Backfilling & Compaction Around Parking Aea to Finish Level
MAIN BUILDI
BUILDING - BASEMENT FLOOR
SUB-3010 Blinding and Waterproofing under Pile Caps 15 Blinding and Waterproofing under Pile Caps
SUB-3020 Construct Pile Caps 30 Construct Pile Caps
SUB-3030 Water Pr oofin g at the Sides of Pile Caps 22 Water Pr oofing at the Sid es of Pile Caps
SUB-3040 Backfilling upto Bottom of Floor Slab 22 Backfilling upto Bottom of Floor Slab
SUB-3050 Blinding and Waterproofing under F loor Slab 15 Blinding and Waterproofing under F loor Slab
SUB-3060 Construct Basement Floor Slab 18 Construct Basement Floor Slab
SUB-3070 Construct Perimeter Walls, Inter nal Walls and Columns 18 Construct Perimeter Walls, Inter nal Walls and Columns
SUB-3080 Construct Beams and Deck Slab @ +0.60 F.F.L. 16 Construct Beams and Deck Slab @ +0.60 F.F.L.
SUB-3081 Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 1) 10 Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 1)
SUB-3082 Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 2) 10 Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 2)
SUB-3083 Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 3) 8 Construct Beams and Deck Slab @ +0.60 F.F.L. (Part 3)
SUB-3090 Water Pr oofin g at External Surfaces of Perimeter Walls 20 Water Pr oofin g at External Surfaces of Perimeter Walls
SUB-3100 Backfilling & Compaction Around Basement Floor to Finish Level 28 Backfilling & Compaction Around Basement Floor to Finish Level
SUB-3110 Construct Stairways and Ramp (from -3.25 to +0.60 Level) 24 Construct Stairways and Ramp (from -3.25 to +0.60 Level)
SUPERSTRUCTURE
SUPERSTRUC
CAR PARKING AREA - GROUND FLOOR
SUP-0010 Construct Lift Shaft, Pump Room and Medical Gas Room 30 Construct Lift Shaft, Pump Room and Medical Gas Room
SUP-0020 Construct Columns at Service Block Area 12 Construct Columns at Service Block Area
SUP-0030 Construct Roof Slab at Sevice Block Area 18 Construct Roof Slab at Sevice Block Area
SUP-0040 Construct Roof Parapet Wall s at Sevice Block Area 10 Construct Roof Parapet Wall s at Sevice Block Area
MAIN BUILDI
BUILDING - GROUND FLOOR
SUP-1010 Construct Internal Walls and Columns 18 Construct Internal Walls and Columns
SUP-1020 Construct Beams and Deck Slab @ +5.40 Level 18 Construct Beams and Deck Slab @ +5.40 Level
SUP-1021 Construct Beams and Deck Slab @ +5.40 Level (Part 1) 10 Construct Beams and Deck Slab @ +5.40 Level (Part 1)
SUP-1022 Construct Beams and Deck Slab @ +5.40 Level (Part 2) 10 Construct Beams and Deck Slab @ +5.40 Level (Part 2)
SUP-1023 Construct Beams and Deck Slab @ +5.40 Level (Part 3) 8 Construct Beams and Deck Slab @ +5.40 Level (Part 3)
SUP-1030 Construct Stairways 14 Construct Stairways
MAIN BUILDI
BUILDING - 1ST FLOOR
SUP-2010 Construct Internal Walls and Columns 18 Construct Internal Walls and Columns
SUP-2020 Construct Beams and Deck Slab @ +9.60 Level 18 Construct Beams and Deck Slab @ +9.60 Level
SUP-2021 Construct Beams and Deck Slab @ +9.60 Level (Part 1) 10 Construct Beams and Deck Slab @ +9.60 Level (Part 1)
SUP-2022 Construct Beams and Deck Slab @ +9.60 Level (Part 2) 10 Construct Beams and Deck Slab @ +9.60 Level (Part 2)
SUP-2023 Construct Beams and Deck Slab @ +5.40 Level (Part 3) 8 Construct Beams and Deck Slab @ +5.40 Level (Part 3)
SUP-2030 Construct Stairways 14 Construct Stairways
MAIN BUILDI
BUILDING - 2ND FLOOR
SUP-3010 Construct Internal Walls and Columns 18 Construct Internal Walls and Columns
SUP-3020 Construct Beams and Deck Slab @ +13.80 Level 18 Construct Beams and Deck Slab @ +13.80 Level
SUP-3021 Construct Beams and Deck Slab @ +13.80 Level (Part 1) 10 Construct Beams and Deck Slab @ +13.80 Level (Part 1)
SUP-3022 Construct Beams and Deck Slab @ +13.80 Level (Part 2) 10 Construct Beams and Deck Slab @ +13.80 Level (Part 2)
SUP-3023 Construct Beams and Deck Slab @ +13.80 Level (Part 3) 8 Construct Beams and Deck Slab @ +13.80 Level (Part 3)
SUP-3030 Construct Stairways 14 Construct Stairways
MAIN BUILDI
BUILDING - 3RD FLOOR
SUP-4010 Construct Internal Walls and Columns 18 Construct Internal Walls and Columns
SUP-4020 Construct Beams and Deck Slab @ +18.00 Level 18 Construct Beams and Deck Slab @ +18.00 Level
SUP-4021 Construct Beams and Deck Slab @ +18.00 Level (Part 1) 10 Construct Beams and Deck Slab @ +18.00 Level (Part 1)
SUP-4022 Construct Beams and Deck Slab @ +18.00 Level (Part 2) 10 Construct Beams and Deck Slab @ +18.00 Level (Part 2)
SUP-4023 Construct Beams and Deck Slab @ +18.00 Level (Part 3) 8 Construct Beams and Deck Slab @ +18.00 Level (Part 3)
SUP-4030 Construct Stairways 14 Construct Stairways
MAIN BUILDI
BUILDING - 4TH FLOOR
SUP-5010 Construct Internal Walls and Columns 18 Construct Internal Walls and Columns
SUP-5020 Construct Beams and Deck Slab @ +22.20 Level 18 Construct Beams and Deck Slab @ +22.20 Level
SUP-5021 Construct Beams and Deck Slab @ +22.20 Level (Part 1) 10 Construct Beams and Deck Slab @ +22.20 Level (Part 1)
SUP-5022 Construct Beams and Deck Slab @ +22.20 Level (Part 2) 10 Construct Beams and Deck Slab @ +22.20 Level (Part 2)
SUP-5023 Construct Beams and Deck Slab @ +22.20 Level (Part 3) 8 Construct Beams and Deck Slab @ +22.20 Level (Part 3)
SUP-5030 Construct Stairways 14 Construct Stairways
MAIN BUILDI
BUILDING - 5TH FLOOR
SUP-6010 Construct Internal Walls and Columns 18 Construct Internal Walls and Columns

Actual Work Critical Milestone AMAH-1 Date Revision Checked Approved


30-Nov-11 ISSUED FOR TENDER
Remaining Work
AL MUSSAFAH AHALIA HOSPITAL
Critical Remaining Work PRELIMINARY SCHEDULE
Milestone
Actual Milestone 2 of 4
Activity ID Activity Name Original
Duration Month
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
SUP-6020 Construct Beams and Deck Slab @ +26.40 Level 18 Construct Beams and Deck Slab @ +26.40 Level
SUP-6021 Construct Beams and Deck Slab @ +26.40 Level (Part 1) 10 Construct Beams and Deck Slab @ +26.40 Level (Part 1)
SUP-6022 Construct Beams and Deck Slab @ +26.40 Level (Part 2) 10 Construct Beams and Deck Slab @ +26.40 Level (Part 2)
SUP-6023 Construct Beams and Deck Slab @ +26.40 Level (Part 3) 8 Construct Beams and Deck Slab @ +26.40 Level (Part 3)
SUP-6030 Construct Stairways 14 Construct Stairways
MAIN BUILDI
BUILDING - 6TH FLOOR
SUP-7010 Construct Internal Walls and Columns 18 Construct Internal Walls and Columns
SUP-7020 Construct Beams and Deck Slab @ +30.60 Level 18 Construct Beams and Deck Slab @ +30.60 Level
SUP-7021 Construct Beams and Deck Slab @ +30.60 Level (Part 1) 10 Construct Beams and Deck Slab @ +30.60 Level (Part 1)
SUP-7022 Construct Beams and Deck Slab @ +30.60 Level (Part 2) 10 Construct Beams and Deck Slab @ +30.60 Level (Part 2)
SUP-7023 Construct Beams and Deck Slab @ +30.60 Level (Part 3) 8 Construct Beams and Deck Slab @ +30.60 Level (Part 3)
SUP-7030 Construct Stairways 14 Construct Stairways
MAIN BUILDI
BUILDING - 7TH FLOOR
SUP-8010 Construct Internal Walls and Columns 18 Construct Internal Walls and Columns
SUP-8020 Construct Beams and Deck Slab @ +34.80 Level 18 Construct Beams and Deck Slab @ +34.80 Level
SUP-8021 Construct Beams and Deck Slab @ +34.80 Level (Part 1) 10 Construct Beams and Deck Slab @ +34.80 Level (Part 1)
SUP-8022 Construct Beams and Deck Slab @ +34.80 Level (Part 2) 10 Construct Beams and Deck Slab @ +34.80 Level (Part 2)
SUP-8023 Construct Beams and Deck Slab @ +34.80 Level (Part 3) 8 Construct Beams and Deck Slab @ +34.80 Level (Part 3)
SUP-8030 Construct Stairways 14 Construct Stairways
MAIN BUILDING
BUILDI - ROOF AND TOP ROOF FLOOR
SUP-8040 Construct Internal Walls and Columns 8 Construct Internal Walls and Columns
SUP-8050 Construct Beams and Deck Slab @ +38.30 Level 9 Construct Beams and Deck Slab @ +38.30 Level
SUP-8060 Construct Stairways 8 Construct Stairways
CIVIL/ARCHITE
CIVIL/ARCHITECTURAL WORKS
CIV-0000 Start Civil/Architectural Works 0 Start Civil/Architectural Works
CIV-0005 Finish Civil/Architectural Works 0 Finish Civil/Architectural Works
MASONRY WORKS
WO
CIV-0010 Blockworks and Plastering Works 201 Blockworks and Plastering Works
CIV-0020 Boundary Walls 61 Boundary Walls
CIV-0030 Installation External Curb Stone and Paving Blocks 31 Installation External Curb Stone and Paving Blocks
THERMAL AND MOISTURE PROTECTION
CIV-1010 Water proofing Works to Wet Areas (i.e. Kitchen, Toilet, etc..) 231 Water proofing Works to Wet Areas (i.e. Kitchen, Toilet, etc..)
CIV-1020 Water proofing Works to External Surfaces 234 Water proofing Works to External Surfaces
CIV-1030 Water proofing Works to Roof Areas 61 Water proofing Works to Roof Areas
FINISHING WORKS
WO
CIV-2010 Install Curtain Walls (C omposite Aluminum Section and Glazing) 214 Install Curtain Walls (Composite Aluminum Section and Glazing)
CIV-2020 Wall Finishes 214 Wall Finishes
CIV-2030 Ceiling Finishes 214 Ceiling Finishes
CIV-2040 Floor Finishes 214 Floor Finishes
CIV-2050 Painting Works 214 Painting Works
CIV-2060 Install Sanitary Fittings (Sanitary ware and Tapware) 153 Install Sanitary Fittings (Sanitary ware and Tapware)
CIV-2070 Other External Finishing Works 132 Other External Finishing Works
DOORS AN D W
WIN DOWS
CIV-3010 Install Powder Coated Aluminun Doors 214 Install Powder Coated Aluminun Doors
CIV-3020 Install Fire Rated Wooden Doors 214 Install Fire Rated Wooden Doors
CIV-3030 Install Powder Coated Aluminum Windows 214 Install Powder Coated Aluminum Windows
CIV-3040 Install Aluminum Louver Doors 138 Install Aluminum Louver Doors
CIV-3050 Install Electrically Operated Sliding Doors 107 Install Electrically Operated Sliding Doors
CIV-3060 Instal Door Ironmongery 91 Instal Door Ironmongery
MISCELANEUO
MISCELANEUOUS METAL WORKS
CIV-4010 Install Epoxy Coated Aluminum Pipe Handrails 214 Install Epoxy Coated Aluminum Pipe Handrails
CIV-4020 Install Aluminum Powder Coated Ramp Railing 31 Install Aluminum Powder Coated Ramp Railing
CIV-4030 Install Aluminum Ladder Stair for Basement Floor 30 Install Aluminum Ladder Stair for Basement Floor
CIV-4040 Install Galvanized Ladder Stair from Roof to Top Roof 31 Install Galvanized Ladder Stair from Roof to Top Roof
CIV-4050 Install Access Panel for Services Type SD1 and SD2 123 Install Access Panel for Services Type SD1 and SD2
CIV-4060 Install Aluminum Kitchen Cabinet 122 Install Aluminum Kitchen Cabinet
CIV-4070 Install Epoxy Coated Wrought Iron for External Fence 61 Install Epoxy Coated Wrought Iron for External Fence
CIV-4080 Install Barrier for External Access to Basement Electrical Operator 30 Install Barrier for External Access to Basement Electrical Operator

CIV-4090 Install Automatic Barrier and Electrical Operated Steel Gates 61 Install Automatic Barrier and Electrical Operated Steel Gates
CIV-4100 Install External Galvanized Flag Pipe 20 Install External Galvanized Flag Pipe
WOOD WORKS
CIV-5010 Install Bumper Guards and Corner Protection 78 Install Bumper Guards and Corner Protection
CIV-5020 Install Counters for Reception and Nurse Station 200 Install Counters for Reception and Nurse Station
CIV-5030 Install Corridor Handrail 153 Install Corridor Handrail
MEP WORKS
MEP-0000 Start MEP Works 0 Start MEP Works
AIR-CONTIONI
AIR-CONTIONING AND VEN TILATION SYSTEM
MEP-0010 Chilled Water and Air Distribution System 242 Chilled Water and Air Distribution System
MEP-0020 Install Galvanized Steel Sheet Rectangular Duct Works. 242 Install Galvanized Steel Sheet Rectangular Duct Works.
MEP-0030 Install Ventillation System 242 Install Ventillation System
MEP-0040 Install Building Managemenrt System (BMS) 214 Install Building Managemenrt System (BMS)

Actual Work Critical Milestone AMAH-1 Date Revision Checked Approved


30-Nov-11 ISSUED FOR TENDER
Remaining Work
AL MUSSAFAH AHALIA HOSPITAL
Critical Remaining Work PRELIMINARY SCHEDULE
Milestone
Actual Milestone 3 of 4
Activity ID Activity Name Original
Duration Month
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
MEP-0050 Install Air-Cooled Water Chillers and Pumps 92 Install Air-Cooled Water Chillers and Pumps
MEP-0060 Install Fresh Air Handlling Units 61 Install Fresh Air Handlling Units
MEP-0070 Roof Mounted Exhaust Fans 61 Roof Mounted Exhaust Fans
MEP-0080 Motor Control and Supply Distribution Panel 61 Motor Control and Supply Distribution Panel
DRAINAGE AND
AN PLUMB ING WORKS
MEP-1010 Installation of Internal Cold Water Pipes, F ittings and Valves 242 Installation of Internal Cold Water Pipes, F it tings and Valves
MEP-1020 Installation of Internal Hot Water Pipes, F ittings and Valves 242 Installation of Internal Hot Water Pipes, F it tings and Valves
MEP-1030 Installation of Internal Drainage Pipes and Fittings 242 Installation of Internal Drainage Pipes and Fittings
MEP-1040 Installation of Drain Water Pipes and Manholes 137 Installation of Drain Water Pipes and Manholes
MEP-1050 Install CWS Transfer Pump Set 92 Install CWS Transfer Pump Set
MEP-1060 Install of Electric Water Heaters 92 Install of Electric Water Heaters
MEP-1070 Install HWS Circulation Pump Set & CWS Booster Pump Set 92 Install HWS Circulation Pump Set & CWS Booster Pump Set
MEP-1080 Install Central Water F ilter in cl. Pipes, Filter Pumps Automatic Control Panel 92 Install Central Water F il ter incl. Pipes, Filter Pumps Automatic Control Panel

MEP-1090 Install Water Tanks Including Related Piping Works 92 Install Water Tanks Including Related Piping Works
MEP-1100 Install Drainage Pump Set 92 Install Drainage Pump Set
FIRE FIGHTING SYSTEM
MEP-2010 Install Fire Sprinkler System 242 Install Fire Sprinkler System
MEP-2020 Install Fire Alarm and Fire Detection System 242 Install Fire Alarm and Fire Detection System
MEP-2030 Install FM-200 Clean Agent System 92 Install FM-200 Clean Agent System
MEP-2040 Install Fire Water Pumps and Control Panels 76 Install Fire Water Pumps and Control Panels
MEP-2050 Install Portable Fire Extinguishers 76 Install Portable Fire Extinguishers
MEDICAL GASES
GAS
MEP-3010 Installation Medical Gases 242 Installation Medical Gases
ELECTRICAL W
WORKS
MEP-4010 Install Power/Lighting Cables, Supports & Trays 242 Install Power/Lighting Cables, Supports & Trays
MEP-4011 Install Electrical Service to Mechanical Works 242 Install Electrical Service to Mechanical Works
MEP-4020 Install Main and Sub Distribution Boards including MCC 245 Install Main and Sub Distribution Boards including MCC
MEP-4030 Install 1500KVA Dr y Type Transformer 92 Install 1500KVA Dr y Type Transformer
MEP-4031 Install Stand by Generator 92 Install Stand by Generator
MEP-4040 Install Final Sub-Circuit, Fixtures and Accessories 199 Install Final Sub-Circuit, Fixtures and Accessories
MEP-4060 Install Lighting Fixtures 199 Install Lighting Fixtures
MEP-4070 Install Public Address & Voice Evacuation System 242 Install Public Address & Voice Evacuation System
MEP-4080 Install SMATV System 242 Install SMATV System
MEP-4090 Telephone, Data (Structure Cabling) and CATV System 242 Telephone, Data (Structure Cabling) and CATV System
MEP-4100 Install Uninterruptable Power Supply (UPS) 242 Install Uninterruptable Power Supply (UPS)
MEP-4110 Install Earthing System 242 Install Earthing System
MEP-4120 Install Lightning Ptotection 90 Install Lightning Ptotection
MEP-4140 Install Nurse Call System 184 Install Nurse Call System
MEP-4150 Install IPTV System and Audio System 184 Install IPTV System and Audio System
MEP-4160 Install CCTV System and Access Control System 184 Install CCTV System and Access Control System
CONVEYING SYSTEM
SY
CON-0000 Start Installation of Conveying System 0 Start Installation of Conveying System
CON-0010 Install Parking Lift Type (L3) 60 Install Parking Lift Type (L3)
CON-0020 Install Bed Lifts Type (L1) 183 Install Bed Lifts Type (L1)
CON-0030 Install Passenger Lifts Type (L2) 183 Install Passenger Lifts Type (L2)
CON-0040 Install Service Lifts Type (L4) 183 Install Service Lifts Type (L4)
SPECIAL CONSTRUCTION
CONS
SPC-0010 Install Car park Shade from Steel Pipe & Polypropylene Cover 101 Install Car park Shade from Steel Pipe & Polypropylene Cover
PROVISIONAL ITEMS - INDICATIVE ONLY
SPC-0015 Install Swimming Pool System in 7th Floor 150 Install Swimming Pool System in 7th Floor
SPC-0020 Install Window Washing System 101 Install Window Washing System
SPC-0030 Install Kitchen Equipment with Freezer, Fridge and Oven 101 Install Kitchen Equipment with Freezer, Fridge and Oven
SPC-0040 Install Laundry Equipment incl. Shelves, Racks and Free Standing Washing 101 Install Laundry Equipment incl. Shelves, Racks and Free Standing Washing Machin e
Machine
SPC-0060 Install Stainless Steel Design Space Frame for Building Facade' 71 Install Stainless Steel Design Space Frame for Building Facade'
TESTING, COM
COMMISSIONING AND POWER ON
TST-0000 Install Temporary Power & Water Supply 20 Install Temporary Power & Water Supply
TST-0010 Testing and Commissioning 24 Testing and Commissioning
TST-0020 Inspection/Snags and Approvals 14 Inspection/Snags and Approvals
TST-0030 Temporary Power ON 0 Temporary Power ON
TST-0040 Final Inspection and Approval 6 Final Inspection and Approval
TST-0050 Connection to Main Services (by Statutory) 6 Connection to Main Services (by Statutory)
TST-0060 Building Completion Certificate 6 Building Completion Certificate

Actual Work Critical Milestone AMAH-1 Date Revision Checked Approved


30-Nov-11 ISSUED FOR TENDER
Remaining Work
AL MUSSAFAH AHALIA HOSPITAL
Critical Remaining Work PRELIMINARY SCHEDULE
Milestone
Actual Milestone 4 of 4