For official use only
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
FORMATION REHABILITATION BY
BLANKETING USING C.C. CRIB/CUBE
& RAIL CLUSTER METHOD
Special Report No. GE-R- 67
DECEMBER-2004
Geotechnical Engineering Directorate
RESEARCH DESIGNS & STANDARDS ORGANISATION
1
LUCKNOW-226011
PREFACE
This report is prepared on the basis of IPWE technical
presentations & papers, site inspection and literature survey. The
views expressed are subject to modification from time to time in the
light of future developments on the subject. The views do not represent
the views of the Ministry of Railways (Railway Board), Government of
India.
This report is the property of RDSO and is meant essentially
for official use. It may not be loaned, reproduced in part or in full or
quoted as an authority without the permission of Director General,
RDSO.
(A.K.Singh) (Nand Kishore)
Director/GE Executive Director/GE
2
CONTENTS
S. No. Description Page No.
1. Introduction 1
2. Reference 1
3. Scope 1
4. Methods of rehabilitation tried in past 1
5. Rehabilitation practices over Indian Railways 2
6. CC crib method 2
7. Improvisations in CC crib method 4
8. Site visits 8
9. Observations & suggestions in CC cube method 10
10. Improvements in CC crib method 13
11. Conclusion 14
12. References 16
Annexures I to VIII 18 to 25
3
FORMATION REHABILITATION BY BLANKETING USING CC CRIB/CUBE
METHOD
1.0 INTRODUCTION:
Occurrence of unstable formation due to foreseen or unforeseen reasons is the bane
of all railways. Huge expenditure is involved in maintaining such unstable and
weak stretches on account of loss of ballast due to puncturing into formation and
additional tamping effort required due to frequent disturbance in track geometry.
With introduction of higher speed and heavier axle load, rehabilitation of unstable
formation has become very essential.
2.0 REFERENCE:
Vide letter no. 2002/CE-II/5 dated 27.07.2004, Railway Board instructed RDSO to
study the C.C. crib method, carry out site visits and standardize the procedure so
that the method could be adopted on various railways. This method was initially
devised by Shri S.P.S. Jain, the then PCE/S.E. Railway and was put to work in
field conditions.
3.0 SCOPE:
This report covers technical details of the C.C. crib/Cube method, compaction
aspects of blanket and suggests further improvements in the method.
4.0 METHODS OF REHABILITATION TRIED IN PAST:
Various methods, which have been tried in the past on Indian Railways to
rehabilitate unstable formations are as follows: -
i) Lime piling & L.S.P.I.
ii) Ballast piling
iii) Cement grouting
iv) Cationic bituminous emulsion
v) Vinyl drains
vi) Open cross drains filled with coarse grained material
vii) Sal balli/Sleeper/Rail piling
viii) Layer of laterite block
ix) Polyethylene and other similar impervious sheets
x) Geotextiles
xi) Geojute and sand layer
None of the above methods, tried over Indian Railways in the past, has been found
suitable for rehabilitation. Experience gained over a period suggests that
blanketing is the most practical, effective and economical method of rehabilitation.
A layer of coarse-grained material properly compacted is termed as a blanket layer.
Properly designed thickness of blanket reduces the stresses transferred to the sub
grade to safer levels, known has threshold stress.
4
5.0 REHABILITATION PRACTICES OVER INDIAN RAILWAYS:
Various methods for laying of blanket are as follows:-
i) With Aluminum Alloy Girder (RDSO Method)
ii) Track Dismantling Method
iii) With manually operated portals
iv) With C. C. Crib and rail clusters (S E Railway Method)
v) With rail clusters (Eastern Railway Method)
vi) Lifting of track with deep screening
vii) Fully mechanized methods tried over the world Railways.
The advantages & disadvantages of various methods have been detailed in RDSO
Report No. GE-39 issued in March-2003. This report focuses on C. C. crib and rail
cluster method only.
6.0 C.C.CRIB METHOD:
A technical paper on this method titled as, “Sand blanketing of bad formation by
using C. C. Crib and rail clusters” was presented in IPWE seminar, 2002 by Shri
S.P.S. Jain, the then PCE of S.E. Railway. The details are reproduced below:
i) Components of the equipment : Mainly there are 2 components, which are
used in this method. The first one is a pair of CC Crib and the second part is
one set of 2 clusters, each of 3 x 90R rails 10 ft. long, and a few wooden
sleepers and steel bolts etc.
ii) Assembly : The 2 CC cribs are bolted together by means of high tensile nuts
and bolts and covered all-round by thin steel sheets, except in the back side
and at the bottom, where thicker plates of 3mm and 5 mm are provided for
better load bearing characteristics.
The rail clusters of 3 x 90R rails 10 ft. long is a standard CE’s drawing and can
be adopted upto a span of 10 ft. on B.G. with 20 kmph speed restriction.
iii) Principle : The principle behind the method is that rail cluster is used to
relieve the small patch of track. One end of the rail cluster is supported on
single layer of 12 ft. long CC Crib, and the other end is supported on wooden
sleepers put across the track. At first stage, the formation below the rail cluster
and just in front of CC Crib is worked upon. The CC Crib as well as rail
cluster move forward very akin to cutter machine, leaving behind a gap in the
formation, which is immediately filled by blanketing material.
iv) Step-by-step method :
5
(a) First of all a suitable block of 30-45 minutes is taken and in this block,
ballast is removed and formation is cut to desired depth and size to
accommodate the pair of CC Crib.
(b) Thereafter, the block is cancelled after supporting the track properly over
the CC Crib.
(c) Now the rail cluster is inserted below the sleeper kept on top of the CC
Crib and the other end on the wooden sleepers.
(d) Speed restriction of 20 kmph shall be imposed immediately thereafter and
traffic allowed to pass.
(e) The work will proceed against the direction of traffic.
(f) After the ballast in between sleeper is removed, the formation in front of
CC crib and below the rail cluster is dug for 2 ft. depth and 2 ft. width for
a length of 12 ft across the track i.e. 6 ft. on either side of center of track.
(e) Now the CC crib is pushed forward by one ft. by means of ropes,
manually. This will leave a gap of 1 ft. behind the CC Crib.
(f) Before laying the blanket, geo-textile is spread in the gap as shown in the
figure. The geo-textile shall form a layer of separation between the
blanketing material and parent formation. (Fig. 1)
Fig. 1 Blanket laying with CC crib and rail clusters
(g) The blanket material is kept ready in gunny bags by the side of track so as
not to delay its pouring in the formation void behind the CC Crib.
(h) This gap then is filled by proper blanket material duly approved for
quality laid down by the RDSO.
(i) The blanket material is topped upto sleeper level where it is left for
compaction under traffic.
(j) While this process is going on, a further cut in the formation in front of
the CC Crib is made and room is made for further movement of CC Crib
forward.
(k) The process is repeated in a cyclic manner.
(l) The rail cluster is shifted forward by means of rope at suitable interval
by incremental method so as to execute the work under traffic block
and without jeopardizing track safety.
6
At a time, 5-6 sets of such rail cluster and CC Crib are inserted so as to execute
the work simultaneously at number of locations on one particular site.
(v) Disadvantages of CC crib method
During execution, following disadvantages have been experienced:
a) At a time, very short length of blanketing - about one foot is possible.
b) CC crib is very heavy - about 300 kg and difficult to shift manually or with wire
ropes.
c) Work can not be done on metal sleepered track.
d) Output of work is very low about 1.5 m to 2 m per day.
e) CC crib penetrates into soil and it becomes difficult to lift and move forward
even with the help of dip lorry.
f) Uneven settlement takes place at the two ends of CC crib after passage of traffic
leading to unsafe conditions at times.
g) Sometimes see-saw conditions in rail cluster is generated due to
improper support at the ballast end for the rail cluster.
7. IMPROVISATION IN C. C. CRIB METHOD:
Though C. C. crib method, is very simple and economical for formation
rehabilitation but due to constraints as mentioned above, a need for improvement
was felt while executing work with this method. To overcome the few of these
constraints, S.E. railway had effected certain changes in the CC crib method. The
method which has been detailed in IPWE paper titled as, “Formation rehabilitation
in Amarda-Jaleswar: Using CC cribs, rail clusters and further improvisation” in
2004 by Sr. DEN/South/Kharagpur. This method, hereafter referred to as ‘CC
cubes’ is reproduced below:
7.1 Arrangements
To tide over the limitations of the earlier method, the following arrangements are
made :-
(i) The C.C. crib is cut into three parts. Both the outer one thirds parts with
star stiffeners are retained, termed as C.C. cubes, and the middle part is
discarded. Outer truncated parts size is 60 x 60 x 60 cm.
(ii) The C.C. cube is encased in a 5 mm thick steel plate leaving one out of the
six faces open.
(iii) A 12 m long rail clusters of three 52 kg rails is used instead of 3 m long
rail clusters of three 90 R rails.
iv) The 12 m long rail cluster is supported at every 3 m on the C.C cubes.
(cross-section of supporting arrangements shown in fig. 2)
7
Fig. 2 Cross-section of supporting arrangements
The open face of CC Cube is kept vertical facing away from the track.
7.2 Activities
(i) Imposition of 20 kmph speed restriction.
(ii) Insertion of rail clusters under traffic block of about 2 hrs (fig.3)
Three rail clusters
Fig. 3 Insertion of rail clusters from side of sleepers
(iii) Excavation of 900 mm wide and 900 mm deep (below sleeper bottom)
trench across the track @ 3000 mm c/c (Fig. 4)
8
Rail cluster
trenches
Fig. 4 Excavation of trenches across the track
(iv) Lowering of CC cubes in trenches and supporting rail clusters on CC
cubes (Fig. 5)
CC cubes
Fig. 5 Lowering of CC cubes in trenches
v) Excavation of caked ballast/ Earth in between the trenches upto 900 mm
below the sleeper bottom (Fig.6)
9
Existing soil/caked ballast
Fig. 6 Excavation of existing formation/caked ballast between CC cubes
vi) Filling of blanket material without removal of CC cubes and rail clusters
(Fig. 7)
Blanket material
Fig. 7 Filling of blanket material between CC cubes
vii) Lifting of track with jack and pulling forward the rail clusters by turfer at the
leading end
viii) Removal of CC cubes and filling the balance cavity with blanketing material
upto bottom of sleeper
Fig. 8 Pulling of rail cluster, cubes and blanketing
ix) Insertion of the released C.C. cubes under the rail clusters at 3 m from the
leading set of C.C. cubes by lowering in the trench excavated in advance.
7.3 Progress: 18 m per day per set, due to ease in handling of C. C. cubes, with a
batch of 110 men.
7.4 Advantages:
10
(i) Due to light weight & small size, C.C. cubes are easier to handle vis-à-vis
C.C. crib .
(ii) Once the rail cluster is in position, the C.C. cubes can be inserted from the
sides without traffic block.
(iii) Part filling of cavity is possible because C.C. cubes do not span
continuously across the track.
(iv) Better output & utilization of man power due to excavation in the leading
3 m spans of the rail cluster and blanketing in rear portion simultaneously.
7.5 Constraints:
i) The track is still to be lifted for pulling forward the rail clusters and the
work is to be done under 20 kmph speed restriction.
ii) The required depth of excavation has to be ensured at site since the CC
cubes do not ensure it fully by default.
7.6 Precautions:
(i) Work to be executed only under the personal supervision of at least a
J.E/P. Way.
(ii) During progress of work and after passage of train, track parameters are
required to be monitored and track needs to be attended as required.
(iii) Proper track protection to be ensured at all times.
iv) A railway watchman is required to be provided round the clock.
8.0 SITE INVESTIGATION BY RDSO
For studying and suggesting improvements in the method, site near Balasore was
visited by RDSO team twice. First in Sep’2004 by Shri S.K.Awasthi, ARE/GE &
Shri S.K.Ojha, SRE/GE alongwith Shri A.K.Sahu, ADEN/BLS when
rehabilitation work was going on between Balasore & Nilgiri road stations,
Balashore-Bhadrak section, Kharagpur division, S.E.Rly. Second inspection was
carried out in Dec’2004 by Shri A.K.Singh, Director/GE, Shri S.K.Awasthi,
ARE/GE & Shri S.K.Ojha, SRE/GE alongwith Shri A.K.Sahu, ADEN/BLS when
rehabilitation work was going on between Amarda road & Jaleswar stations,
Balasore-Kharagpur section, Kharagpur division, S.E.Rly
This is a double line section on Group ‘B’ Howrah-Chennai route (partly
electrified). On this section, approximately 33 to 35 trains ply daily & traffic
density on UP line is 10 GMT and on DN line is 11 GMT. The sectional speed of
this section is 105 kmph.
8.1 Balasore –Nilgiri road stations:
11
At this stretch, permanent speed restriction of 60 kmph was continuing on
account of weak formation. The track is LWR with PSC sleeper at sleeper
density of 1665 per km.
At the time of first inspection in September 2004, formation rehabilitation
work with blanketing using CC cube and rail cluster method was in
progress at km 240/14-16 (UP line). In this stretch, work was started in June
2004 and total length where rehabilitation work is to be carried out in this
stretch is 715 m on UP line between km 240/7-33. As reported by the
railway officials at site, an average progress of 10 to 12 m per day had been
achieved so far with manpower of 60 to 80. However, on the day of
inspection, only 6 m progress could be achieved with 60 manpower.
When this stretch was again visited in December 2004, no rehabilitation
work was going on. Progress achieved so far is 300 m. The zone of
permanent speed restriction, though reduced to few TP lengths, is still
continuing in the stretch where rehabilitation work has not been done.
AEN/Balasore reported that in the stretch where rehabilitation work was
over, no track maintenance problem is being faced. Prior to execution of
blanketing work, cross level variation was noticed to the tune of 30 mm,
specially in summer and rainy season. At km 240/11-13, ballast cushion
was found varying from 8 to 10 inches below bottom of sleeper after
execution of work. The quarry dust has been used as blanket material and it
was got tested by railways from S. M. Consultants, Balasore. As per testing,
the material has the following properties:
%age of fines 9.5%
Cu 1.67
Cc 0.68
The material being used does not conform to the specification of blanket
material as per the ‘Guidelines for Earthwork in Railway Formation, July
2003. The values of Cu and Cc are less than the specified values. This will
result in poorly graded material and lead to low density. Wooden mallets
were used for compaction of blanket material and no water was added to
quarry dust to get optimum moisture content for maximum compaction.
Turfers of 3 tonne capacity were used for pulling the rail clusters.
8.2 Amarda –Jaleswar stations:
At this stretch, permanent speed restriction of 60 kmph had been imposed
on account of weak formation. At the time of first inspection, no blanketing
was going on in this stretch, however when the section was again visited in
December 2004, formation rehabilitation work was in progress between
12
196/4-6 (DN line). Initially, work was started with CC crib method in 60 m
stretch but due to field problems faced in executing work with this method,
remaining blanketing work was planned with CC cube method after
incorporating improvements in the CC crib method.
Total quantum of rehabilitation work in this stretch is about 5 km – roughly
from km 192 to km 197. Work was started in Oct 2002 from km 197/6 and
stopped at km 194/6 in June.04. Again, work was started on 9.12.2004 from
km 194/6. On the day of inspection, work was going on between km 194/4-
6. After resumption of work, total 54 m was executed in span of 5 days
amounting to average daily progress of 11m. During this period, the number
of labourers employed varied from 60 to 80. The quarry dust which is
being used as blanket material was got tested by railways from S. M.
Consultants, Balasore. As per testing report, quarry dust has the following
properties:
Percentage of fines 0.25
Cu 4.33
Cc 2.56
Wooden mallets were being used for compaction and no water was being
added to quarry dust. As a result, lot of quarry dust was flying around at the
time of dumping it into track. Capacity of turfer used for pulling of rail
clusters was 3 tonne.
9.0 OBSERVATIONS & SUGGESTIONS IN CC CUBE METHOD BY RDSO
i) Presently, 3 tonne turfer is being utilized in pulling the rail clusters, and
both the clusters can be pulled at the same time by employing separate
turfer for each cluster. It was observed that it is possible to pull rail
cluster by 2.5 m in 6 to 8 minutes time by turfer being employed now.
However, at the time of observation, rail cluster was clear of ballast,
which might otherwise hinder this operation. The time taken is not much
and appears to be quite reasonable. However, if this operation is to be
further expedited, turfer of higher capacity say 5 tonne or more should be
used for pulling the rail clusters.
The ballast particles rolled down close to rail cluster offer high resistance
to pulling effort and hence regular removal of ballast from the side of rail
cluster should be done. Small size rollers/pipes can also be used on CC
cubes/wooden blocks for quick shifting of rail clusters. These rollers can
be lubricated with grease.
ii) Excavation - At present, excavation is being done manually. Survey of
excavators available in market was done as well as meetings were held
with representatives of leading manufacturers of excavators. It was
revealed that excavators which can dig out earth from beneath the sleeper
13
under running traffic conditions are simply not available. JCBs with
small size bucket are available but they also suffer from the handicap of
limited boom length, due to which it may not be possible for JCB operator
to watch the various maneuvers of the machine - a prerequisite for safe
working of machine. Moreover, the boom of JCB will infringe the
running track. In view of this, possibility of mechanization of excavation
is ruled out under the present circumstances.
iii) Dumping of blanket material - At present, blanket material is being
dumped manually into track from the location where it is stacked. It is
first put into pan with the help of shovel, then the pan is carried on head
and material is dumped into track. To save on time and to expedite
progress, blanket material can be kept at site in gunny bags which can be
dumped at site when required.
iv) Compaction of blanket material was being carried out with wooden mallets,
this may not give sufficient compactive effort and as a result,
Blanket may not have desired density. Later on, track may exhibit
settlement due to poor compaction of blanket. Also, there was no
watering arrangement for compacting the material near OMC. In absence
of water, lot of dust was flying around, with the result that progress of
work was being hampered as workers had to wait for dust to settle down
in order to have clear visibility. Blanket material is in general are coarse
in nature and they are amenable to compaction only with the help of
vibratory energy. Adequate importance and time should be given to
compaction activity. For exploring use of vibratory compactors, market
survey was carried out. Survey revealed that there a number of
companies which are manufacturing vibratory plate compactors with
small plate sizes which can easily be inserted in between the two adjacent
PRC sleepers and compact the blanket material. Details of few of these
models are given below:-
S. Name Model Weight Plate Size Compacting Remarks
No (Make) No (kg) (mmx mm) thickness
(mm)
1. Plate PRO-40 52 498X330 - Annexure- I
Compactor
(Fuji)
2 Tamping FR-75 72 330X280 - Annexure- II
rammer,
(Fuji)
3 Vibratory BT60/4 62&68 350X735 550 & 650 Annexure- III
tamper &
(BOMAG) BT65/4
4 Vibratory BP8/34 54 545 x 340 - Annexure - IV
plate
14
5 Vibratory GX160K 90 480 x 585 300 Annexure - V
Plate 1
compactor
(Ingersoll-
Rand)
6 Upright GX120A 71 270 x 330 530 mm Annexure - VI
rammer R
(Ingersoll-
Rand)
7 Vibratory CPT140 80 490 x 440 - Annexure - VII
Plate B
compactor
( L & T)
8 Vibratory MARK - 730 x 570 254 Annexure - VIII
Plate VC-20
compactor
(Continental)
In view of availability of these small plate size compactors, there is no reason
why they should not be used. However, the effect of these compactors on
progress of work can only be adjudged after introduction of same in field.
v) It was observed that for taking out CC cubes, its open end is pulled out by
labourers while the opposite side is pushed out with the help of crow bar. It is felt
that the open side of CC cube can also be welded with a 5 mm thick plate as
provided on other sides and handles can be provided on any two opposite sides at
convenient locations. This will not only help in moving CC cubes from one
location to other but also reinforce the CC cube.
vi) For taking out CC cubes, track is to be lifted with the help of jacks. After removal
of cubes, space vacated is filled up with blanket material and thereafter, ballast is
put over blanket and packing is carried out. This operation requires 30 to 40
minutes. As CC cubes constitute support system for track, removal thereof
without block protection may endanger safety. At site, this operation is presently
being carried out by monitoring train position but without block. To avoid unsafe
conditions for passage of traffic specially on busy routes, clear block of required
duration should be arranged for shifting of CC cubes and rail cluster.
vii) At present, partial blanketing is being done as the formation is being dug out in
5.5 m width. Due to existence of original soil by the side of blanket, drainage is
impaired. To facilitate drainage, boulder cross drains of size 1.5 m X 0.6 m
extending from inner end of excavation to outer side of formation are being
provided @ 12 m c/c. It is felt that over a period of time, these drains may get
choked as the formation soil can enter into pore space of boulders easily. To
prevent such possibility, boulder can be wrapped around in geo-textile at sides
and bottom of cross drains where it comes in touch with soil. Other problem with
these drains, as pointed out by section DEN Shri V. K. Chaudhary that at the
15
point immediately above these boulder drains, track sags a little bit,
resulting in unevenness over boulder drains. The stretch where these drains
have been provided was trolleyed and unevenness was measured at a number
of locations, however, there was nothing unusual about the pattern of
unevenness in this stretch vis-à-vis the stretch where boulder drains have not
been provided. One plausible reason for this could be that the track has been
machine tamped in recent past.
However, boulder drains can be completely done away with if full formation
width blanketing is carried out. The extra work in the outer portion beyond
sleeper end can be carried out easily.
viii) As of now, wooden sleepers are being used on the side of excavated portion
at the end of day to stop falling of ballast, blanket & bank soil. At the time
of dumping of blanket material, extraction of these sleepers becomes
difficult. If three steel plates of adequate size and thickness with handles on
top -one for space between two rails and two for side portions are used in
place of wooden sleepers, this operation may take less time as steel plates
can be taken out while standing on the track.
ix) Work should always be executed in presence of railway officials and
sufficient safety measures should be adopted during blanketing and after
initial passage of traffic and monitoring of track parameters.
10. SUGGETIONS FOR IMPROVEMENTS IN CC CUBE METHOD
The present method can be further improved by incorporating following items:
i) Sufficient water should be sprinkled on blanket during compaction so as to
bring the water content near OMC. This will not only help in achieving
maximum dry density but also reduce dust nuisance during execution of
work.
ii) For effective compaction of blanket material should be compacted in layers
using vibratory plate compactors.
iii) To retain formation soil, blanket and ballast, steel plates of adequate size and
thickness with handles on top should be used in place of wooden sleepers.
iv) One open side of CC cube can be welded with a 5 mm thick plate as provided
on other sides and handles can be provided on any two opposite sides at
convenient locations which will not only help in moving CC cubes from one
location to other but also add to the stability of the CC cube.
v) Turfer of higher capacity say 5 tonne or more should be used for pulling the
rail clusters. Small size rollers/pipes preferably lubricated with grease can
also be used on CC cubes/wooden blocks for quick shifting of rail clusters.
16
11. CONCLUSIONS:
Comparative position of CC crib vis-à-vis CC cube and suggested improvements
by RDSO, in the light of discussion above, is as follows:
S. Item CC crib CC cube
No Existing Improvements
suggested by RDSO
1 CC Crib 2ft X 2ft X 6 Ft 2ft X 2ft X 2 Ft -Same size
size & No. - two no. -10 nos. -All faces may be
(All faces covered by (All faces covered covered with 5 mm
plates) with plates except one thick plates and provide
face) handles on two opposite
sides.
2 Rail cluster - Length: 3m -Length: 12m No change
-rail section: 90 R -rail section: 90 R
- No. of rail cluster : 2 - No. of rail cluster: 2
- No. of rails in each - No. of rails in each
cluster: 3 cluster: 3
3 Traffic Initially 30-45 minutes Initially 2 hrs block No change
block block for removal of for removal of ballast
ballast & excavation and insertion of rail
for insertion of cc crib cluster
4 Excavation Manually Manually No change
5 Filling/ Dumped from gunny Manually with Manually but blanket
dumping of bags shovels & pans. material may be dumped
blanket from gunny bags already
material stored.
6 Compaction By train vibrations Wooden mallets & by Compaction should be
train vibrations done with small size
vibratory plate
compactors/ upright
rammers.
7 Pulling of Manually by wire ropes By turfer of 3.0 Pulling may be done
rail cluster tonnes capacity with turfer of 5.0 tonnes
capacity and small size
roller/ pipes lubricated
with grease should be
used for quick and easy
shifting of rail cluster.
8 Shifting of Manually pulled with Manually by lifting No change
CC wire ropes
Crib/Cube
17
9 Block for No block No block 30-45 minutes block
shifting of ( S.R. 20 kmph) ( S.R. 20 kmph) may be required on busy
CC crib/ routes.
cube &
remaining
blanketing
and
ballasting
10 Supporting Wooden sleeper Wooden sleeper Steel plates of adequate
arrangement provided on sides of size & thickness with
for retention excavated portion. handles on top may be
of used to retain
soil/blanket soil/blanket from sides.
material
11 Drainage No mention Cross drains of 1.5m Cross drains may
arrangement x 60 cm boulder wrapped with geo-
(when full filled provided @ 15 synthetics or full width
width of m c/c blanket should be
blanket is adopted.
not
envisaged/
planned)
12 Progress 1.5 m –2 m 9 m 12 m Progress may be
per day per day increased with more
number of sites tackled
simultaneously (say
about 50 m per day with
executing the work at 4
locations).
Railway may consider the suggestions & improvements given in para 9.0 & 10.0. After
receiving feedback from railways, the points shall be suitably incorporated and the
method shall be finalised.
18
12. REFERENCES:
1. Railway Board’s letter no. 2002/CE-II/5 dated 27.07.2004
2. Report on various methods of formation rehabilitation on railways. Report
no. GE-39, March’ 2003.
3. Special Report no. GE-27, FEB-1999.
4. Technical papers presented on IPWE’s seminar in January’2002 &
January’ 2004.
************
19
OFFICERS AND STAFF ASSOCIATED WITH PREPARATION OF REPORT
This report has been prepared by Shri A. K. Singh, Director/ GE, under the guidance of
Shri Nand Kishore, Executive Director/ GE. Valuable assistance has been rendered by
S/Shri S K Awasthi, ARE
“ S. K. Ojha, SRE,
“ Yeshwant Rao Tirpude, SE( Design)
The research base created by Shri S.P.S. Jain, Member Engineering, is gratefully
acknowledged.
********
20