Time Table
Gantt Chart
    Activity              July-August               September               October-             December           January                 February                March
                                                                            November
                    1st    2nd   3rd    4th   1st   2nd   3rd   4th   1st    2nd 3rd 4th        1st     2nd   1st   2nd   3rd   4th   1st   2nd   3rd   4th   1st   2nd   3rd   4th
   Drafting of
    Research
    Proposal
    Buying of
    Materials
Preparation and
Experimentation
of Lignosulfonate
    Testing
  Final Draft
 Application in
   Concrete
 (Slump Test)
   Revision
  Completion