15/04/2014
EEEN60301 Power System Modelling
Introduction to Power Systems
Monday 23 September 2013
Introduction to
Electrical Power Systems
Prof. Peter Crossley
p.crossley@manchester.ac.uk
Function of a Power System:
• Generate electrical energy economically and with
minimum ecological disturbance
• Transfer this energy over transmission lines and
distribution networks with maximum efficiency and
reliability
• Deliver electrical energy to consumers at virtually fixed
voltage & frequency
1
15/04/2014
Electrical Power Systems:
When compared with other man-made networks (e.g.
communications, gas, water, sewage) electrical power
systems are the most expensive in terms of capital invested,
most influential in terms of disruption to our mode of life in
case of breakdown, most visually intrusive in terms of
impact on the landscape and the most ecologically intrusive
in terms of thermal, chemical and potential radiological
pollution.
Structure of a Power System
2
15/04/2014
Boiler + turbines + Exhaust gases
generators Coal store
Cooling towers
Electrical substation
Coal fired power station
Generation:
• Large synchronous generator
driven by a steam turbine
produces three phase electrical
power at a typical voltage of
22kV line-line.
Q1. What is the output current per phase if a 500MW turbine +generator is
used and is operating at its rated output power ?
500MW/3 ÷ (22kV/√3) = 13kA at 22kV
Q2. Why is the generator operating at 22kV rather than 400kV or 400V ?
3
15/04/2014
Stator Winding of a 660MW Generator
Repairing a 200MW generator rotor
Stator of a hydro generator
4
15/04/2014
Future:- Thermal Power Station burning domestic waste,
river water cooling and gas/particle emission filtering
What is a Power System?
Load
Generator Load
Generator
5
15/04/2014
Transmission:
• Generator Voltage of 22kV is too low for 1960’s
transmission over long distance, hence 275kV
step up to 275kV or 400kV (UK) using transformer
transformers.
– 500MW = 13kA at 22kV = 1kA at 275kV
• At 275/400kV the power is transmitted via
an overhead line to a bulk power
substation for connection to the 400kV
transmission network.
Transmission, Sub-transmission & Distribution Network
transformer
Generating
6
15/04/2014
= circuit breaker
400kV Substation
= disconnector
= transformer
Transmission feeders
Substation:
interconnecting 4
transmission feeders
Miss July
Transmission
Pylon of the Month!
Mr
January
it was the wrong sort of snow!
7
15/04/2014
Transmission Line after a Hurricane (India)
= circuit breaker
Bulk Substation
= disconnector
= transformer
Transmission
network
Sub-transmission
network
8
15/04/2014
busbar
isolator
circuit breaker CT’s
Electrical Substation
Sub-transmission &
distribution line on
same tower (USA)
Mixed voltage lines not
used in UK
9
15/04/2014
Distribution Network
• In a UK distribution substation, the transmission or sub-transmission
voltage is reduced to 33kV or 11kV
• Large industrial consumers are supplied at 33kV or 11kV
• Large commercial are supplied at 11kV
• Generally 33kV is then reduced to 11kV
• Finally, 11kV is stepped down to 415V 3-phase supply
• 3-phase 415V supply consists of three phases plus neutral
• Most consumers supplied via underground cable and fed from one-phase
(line) and a neutral (plus an earth)
3.3kV feeder supplying 400V 3-phase load
10
15/04/2014
Conversion from overhead line to cable
Distribution substation
11
15/04/2014
11kV Radial rural distribution feeder with wind generator
11 kV overhead line
V1 V2 V3 SW3
33/11 kV
Transformer SW1 SW2 680V/11 kV
Transformer
680V wind generator
Load-1 Load-2
LV Distribution Network (400V)
• 3-phase 400V supply consists of three phases plus neutral
• Normally supplied by 4-core underground cable
• Most consumers connected to one-phase (line) and neutral
• An earth is supplied to consumers for protection purposes
• The earth is connected to the outer metal casing of electrical appliances, if an
insulation breakdown occurs, the casing becomes live, the fuse blows and the
consumer is protected.
• Fuses in a domestic distribution box are now being replaced by over-current
operated miniature circuit breakers (mcb’s). Operate at ten’s of amperes.
• Residual current tripping devices (RCD) are also used to protect consumers.
Operate when difference between line and neutral current is greater than 50mA
(reduces risk of electrocution).
12
15/04/2014
Domestic 240V electrical system
3-phase supply
kW & kWH meter
Domestic 240V single-phase supply
Electric Electric Water
shower cooker heater
Revision:- What is an electrical power system?
Sources of electrical energy:-
generators convert mechanical energy into electrical energy
mechanical energy derived from steam in thermal power station
mechanical energy also extracted from a wind-turbine or a gas-turbine.
Transmission network:-
overhead lines are used across the country and cables in urban areas
generated power = consumed power, demand increases must be matched by increases in generation
system frequency (50Hz) increases if generated power > demanded power
system frequency (50Hz) decreases if generated power < demanded power
system frequency is controlled to be 50Hz.
Distribution network:-
transfer power from transmission network to regions, towns and homes
discuss reasons for different voltage levels.
Environmental impact:-
impact of fossil fuels on air quality, CO2, SOX, NOX emissions
advantages/disadvantages of renewable energy sources and nuclear
Economic cost of different sources of energy and need for reliability
13
15/04/2014
Revision
• Why 50Hz or 60Hz?
– lower frequencies cannot be used due to flicker in filament lamps
– iron losses increase in proportion to frequency
– leakage reactances increase in proportion to frequency
– capacitive reactance between lines reduce with freq.
– interference with telephone lines increase with freq.
– higher frequencies enable smaller motors, generators and
transformers.
• Remember electrical networks were first designed in the
1890’s:- hence 50 or 60Hz was sensible choice.
Revision
• Why 3-phase?
– Increases the rating of a.c. generators
– a.c. allows conversion of electrical to mechanical energy
– Comparative capacity of machines operating with different phases:
• 1-phase = two connecting wires = 1.00 capacity
• 2-phase = three connecting wires = 1.41 capacity
• 3-phase = three connecting wires = 1.50 capacity
• 4-phase = four connecting wires = 1.53 capacity
• -phase = connecting wires = 1.57 capacity
– Hence power gains beyond 3-phase are small,
– 3-phase only needs three wires and
– polyphase systems = balanced rotating magnetic field in machines
14
15/04/2014
Revision
• Why such a variety of voltages?
– Power received by the load is: P = V.I.cos
– Percentage transmission loss is Ploss = I2R x 100% / P
– For efficient transmission Ploss should be minimised.
– Hence reducing I reduces power loss, but if P is to be held
constant V must be increased proportionally
– Implies high transmission voltage is desirable
– Problem:- higher voltages = taller towers + longer insulator strings
+ broader rights of way + more expensive plant & construction
costs
– Compromise between rising capital costs as voltage increases
and greater losses as voltage reduces.
What is distributed, dispersed or embedded generation?
Generation connected to a circuit from which other customers are
supplied directly.
(2 kW – 100MW connected at 415 V - 132 kV)
e.g. Combined Heat & Power
Co-generation: Diesel generators, micro-turbines (gas)
Wind turbines/Biomass/Photovoltaics
Fuel cells /Storage
CIGRE definition of Dispersed Generation: not centrally planned
not centrally dispatched and connected to distribution network
15
15/04/2014
Diesel Generators:
Wind, Photo-Voltaic & Tidal
16
15/04/2014
Power
company
Photo Voltaic Wind power Hydraulic Fuel cell
Gas
company Measure
ment
Information
network
Buildings,
hospitals, Hydrogen
schools, etc. Control Supply side
system
Sewage Biomass
Co-generationDemand side treatment power
Electricity
Heat
Residential Public Energy storage
load Refuse power
load (NAS battery)
Features of distributed generation
• Renewable - resource led:
– technology = induction generator, electronic interface (AC-DC-AC, DC-
AC), DFIG (double fed induction generator).
• CHP - heat led:
– technology = synchronous generator
• Widely varying output and technical characteristics
• Many owners and operators
• Output does not usually respond to network conditions
17
15/04/2014
Biomass バイオマスプラント
牛糞尿 plant (Night soil)
PV power
太陽光発電 Bio Gas
Gen
← Engine
Load Generation system
発電設備
Load
負荷
Historical perspective
• Before the construction of the UK National Grid all generation was
embedded in distribution networks
• Objective of the CEGB was to generate and transmit electricity in the
most economic manner (statement true in most countries)
• Some countries (e.g. Sweden) maintained town and city authorities and
constructed CHP plants (provides district heating & local electricity generation)
• Objective of CHP:- minimise heating and electricity costs
18
15/04/2014
Distributed Generation
Coal, gas, oil, nuclear stations
Central
Generators
Interconnected
Transmission Network
Distribution
Network
Loads CHP Loads
19
15/04/2014
Could we replace coal
stations with wind
Past generators?
Future ??
Reasons for Distributed Generation
• Reduce environmental impact of generation
– harness dispersed renewable energy resources
– increase overall energy efficiencies (Combined Heat & Power)
– reduce need for bulk fossil fuel generators
(closure of “old” coal-fired stations)
• Future
– DG provides system reinforcement
(i.e. local real & reactive support)
– DG provides fuel security (depends on energy source)
20
15/04/2014
Issues:
• Conventional energy sources:
• coal, oil, gas, hydro, nuclear, impact on environment and society
• Future of conventional energy sources:
• clean coal, combined cycle gas turbines, fission, fusion, C0 2 storage
• Renewable energy sources:
• renewable fuels, wind, wave & tidal power, PV, energy networks
• Energy storage
• bulk and domestic mechanical, chemical, water and heat storage
• Energy flexibility and conservation
• domestic, vehicles, commercial, industry, shops, public attitude etc
• Education of society & strategies for sustainability
• acceptance of need for change, revision of planning laws, true costs etc
• energy usage, subsidies and taxation, energy audits, efficiency
Sustainable Energy Sources:-
• Operating life:- energy produced > energy consumed
• High conversion efficiency
• Low energy construction
• Low environmental impact
• Economic and ergonomically acceptable designs
• Integration into existing energy networks
• Public & political acceptance
• Expansion of UK manufacturing base = employment
• Decommissioning:- Recovery of energy in materials
21
15/04/2014
Diversified energy networks
• Replacement of large fossil fuelled power stations with multitude of small
renewable sources
• Requires radical re-think of how energy network operates
• Immediate:- conventional generation/storage technology
• Future:- fuel-cells, micro-generators, electronic interfaces, superconductors,
chemical storage etc
• Loosely controlled hierarchy of generation, storage, load management
• Complex, active distribution networks with non-deterministic sources of
economical low carbon energy
S Tr. S Tr.
Main Centralized
Generation Plant
TL TL
Transmission System
DSS DSS
Gas Turbine
Fuel Cell
DSS Micro Turbine
DSS
PV Gas Turbine
Flywheel
Batteries
Commercial Load Industrial Load
Fuel Cell
Distribution System
Residential Loads
Distribution Network Is No More Vertically Operated
22
15/04/2014
Passive Distribution Network
P,Q P,Q
Load
Dispersed Generation
P,Q? P,Q?
P,-Q
pv
P+/-Q
P,+/-Q
CHP S
23
15/04/2014
Benefits of DG:- Economics
a) Save world’s fuels reservoirs
b) Save T&D Expansions Costs
c) Increase the electric power equipment lifetime
d) Can Be Installed incrementally
e) Provide Combined Heat and Power (CHP)
f) Not Restricted by Geographically Limitations
g) Reduce wholesale power price (Location Margin Pricing)
Benefits of DG:- Operation
• Positive Impact on Network Voltage profile
• Reduce System’s Power Losses
• Satisfy the Thermal Constraints of T&D feeders
• Help for “Peak Load Shaving”
• Maintain System’s Continuity, Stability & Reliability
• Provide Local Reliability (in case of emergency & main source outage as standby generation)
• Maintain System’s Security and reinforce the Critical Electric Power
Infrastructure (Islanding)
• Positive Impact on Environment & eliminate/reduce emissions
24
15/04/2014
new-build estates with micro-generators, PV & storage
Power
Load curve
Supply from the
utility grid
(constant)
0
Charge Charge
energy DG output energy
storage storage
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
hour
Fuel cell
Hydrogen
Sewage treatment Biomass power
25
15/04/2014
CIRED Data
Dispersed generation/Total installed generating capacity
EnergieNed Data
CIGRE Data
45
40
35
30
25
%
20
15
10
5
0
Netherlands
Germany
Ireland
Belgium
Italy
Denmark
Finland
Poland
Sweden
Australia
Portugal
Greece
Austria
France
Spain
UK
Distributed generation & consumption in
Denmark (source Eltra)
7000
6000
5000
Consumption
4000
MW
Offshore wind
3000 CHP
Onshore wind
2000
1000
0
1990 1998 2005 2015
26
15/04/2014
Q & A:- Options for Electrical Energy in 2020
• Starting point:- generation in 2006
– Peak demand = 60,000MW, minimum demand = 18,000MW, average =
35,000MW.
– Gas = 43%, coal = 30%, nuclear = 18%, wind = 4%, water = 2%, oil = 2%,
other = 1%.
• Will average demand in 2020 reduce, increase or stay constant?
• Estimate 2020 average demand?
• What will cause the change?
• Should the UK build new nuclear power stations? (remember if no nuclear station built,
nuclear contribution by 2020 = approx 5%)
• Should we build more gas fired power stations? (uses imported gas)
• Should we build more wind-generators? (remember wind is not continuous, average
output from a 3MW machine is 1MW)
• Should we build more conventional coal stations? (what about Kyoto)
• Will we have the technology to build economic clean coal power stations?
• Estimate the average output in MW from gas, coal, nuclear, wind, water, oil and other
power stations by 2020?
Q&A
Prof. Peter Crossley
p.crossley@manchester.ac.uk
27