Shift End Status: Particulars Unit-3 Unit-4

The document provides a status report for units 3 and 4 from a power plant. It summarizes key operational parameters like generation levels, coal and water consumption, mill operations, temperatures and tank levels for the two units. Generation was slightly higher for unit 4 compared to unit 3. Bottom ash hoppers and centrifuges were reported to be clear. Temperatures were within normal ranges for both units.

Uploaded by

venkateshbitra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views1 page

Shift End Status: Particulars Unit-3 Unit-4

The document provides a status report for units 3 and 4 from a power plant. It summarizes key operational parameters like generation levels, coal and water consumption, mill operations, temperatures and tank levels for the two units. Generation was slightly higher for unit 4 compared to unit 3. Bottom ash hoppers and centrifuges were reported to be clear. Temperatures were within normal ranges for both units.

Uploaded by

venkateshbitra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

SHIFT END STATUS 2/24/2018

Particulars Unit-3 Unit-4


1 Generation 3.222 3.408745
2 APC 0.1319 0.1581
3 Coal consumption 2059 2037
4 Oil consumption (LDO / HFO)
5 DM water consumption 120 72
6 Hydrogen consumption 1 0
7 Reason for low generation

BC 7.00 to 8.20 AD 09:40-11:00


8 Bottom ashing details
AD 11.30 to 12.45
9 Economiser hoppers status clear clear
10 Centrifuges bfp-b ptw mot PTW
11 APH soot blowing done done
12 Water wall soot blowing not done Feb-00
13 LRSB not done
14 Scheduled changeover not done
15 Emergency equipment available available

16 Load / MVAR 280/ -21 304/-34


17 Vacuum 0.085 0.086
18 Mills in service CDEFH C-G
19 Mills under permit nil K
20 Drum pr./Silica/PH/Cl 151/41/9.4/184 133/43/9.3/115

21 AG/DC (%)
22 CW forebay level 6.49
23 Fire water tank level 9.8/10.3
24 SH / RH temperatures 543/540 545/555
25 SH / RH attemperation 64/3 58/0
26 Max. SH Acromat temp. 594 618
27 Max. SH/RH metal temp. 555/558 554/572
28 AVG MS/RH temp

ABT Deviations : STAGE- II