Serene Resort Reconstruction Plan

The document outlines a 9 phase renovation and expansion plan for Serene Resort & Training Center in Janda Baik, Pahang Darul Makmur from March to December. Phase 1 involves reconstructing existing chalets and buildings, adding new outdoor activity equipment, redesigning the entrance, adding landscaping and lighting, and resort equipment. Phase 2 would extend the resort by securing additional land for new chalets, facilities, and infrastructure.

Uploaded by

Azhar Ahmad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
92 views1 page

Serene Resort Reconstruction Plan

The document outlines a 9 phase renovation and expansion plan for Serene Resort & Training Center in Janda Baik, Pahang Darul Makmur from March to December. Phase 1 involves reconstructing existing chalets and buildings, adding new outdoor activity equipment, redesigning the entrance, adding landscaping and lighting, and resort equipment. Phase 2 would extend the resort by securing additional land for new chalets, facilities, and infrastructure.

Uploaded by

Azhar Ahmad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

SERENE RESORT & TRAINING CENTER, JANDA BAIK, PAHANG DARUL MAKMUR

Duration Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Concept  Proposal
Award  of  Contract
Design  &  Planning
Mobilisation
Reconstruction  of  existing  26  chalets.
a.    Mock-­‐up  unit
b.    Approval  of  MUU
c.    25  units
Reconstruction  of  a  new  worker’s  accommodation
a.    Site  clearance  &  Demolition
b.    Construction
Reconstruction  of  a  reception  building
a.    Site  clearance  &  Demolition
b.    Construction
New  outdoor  activities  equipments  :
a. Flying  fox
b. Rock  climbing  tower
c. Abseiling
d. Canopy  walk
e. High  Ropes  Challenges
f. Jungle  trekking
g. Outdoor  exercise  gym  equipments
5. Redesign  and  construction  of  existing  entrance  structure.
a.    Site  clearance  &  Demolition
b.    Construction
6. Landscape  including  solar-­‐powered  street  lighting
7. Resort  equipments
a. 2  nos.  buggy
8.      Completion

9. 2nd  Phase  Extension  (upon  securing  land)


a. Chalets
b. Facilities
c. Landscape
d. infrastructure