Harga Bahan & Upah Jember 2009

This document lists prices for various construction materials and labor in the Jember region. It provides prices for over 70 different items commonly used in construction, including types of sand, stone, cement, wood, tiles, pipes, electrical wiring, tools and other miscellaneous materials. The prices are given per unit (such as per cubic meter, kilogram, sheet or piece) making it a comprehensive price list for construction materials in the local area.

Uploaded by

Eka Mamonto
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
61 views39 pages

Harga Bahan & Upah Jember 2009

This document lists prices for various construction materials and labor in the Jember region. It provides prices for over 70 different items commonly used in construction, including types of sand, stone, cement, wood, tiles, pipes, electrical wiring, tools and other miscellaneous materials. The prices are given per unit (such as per cubic meter, kilogram, sheet or piece) making it a comprehensive price list for construction materials in the local area.

Uploaded by

Eka Mamonto
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 39

DAFTAR HARGA BAHAN DAN UPAH

Untuk Wilayah Jember

NO JENIS BAHAN SATUAN HARGA KETERANGAN

I BAHAN PASIR
1 Pasir Pasang m3 Rp 76,000.00
2 Pasir Urug/Sirtu m3 Rp 73,000.00
3 Pasir Cor m3 Rp 76,000.00
4 Batu Koral m3 Rp 93,000.00
5 Tanah Urug m3 Rp 51,000.00

II BAHAN BATU PECAH MANUAL


1 Batu Gunung/Batu Kali m3 Rp 138,000.00
9 Batu Merah biji Rp 350.00

IV BAHAN SEMEN
2 Semen 40 Kg zak Rp 48,000.00
3 Semen Putih 40 Kg zak Rp 85,000.00

V BAHAN KAPUR
1 Kapur Pasang m3 Rp 228,000.00
2 Kapur Pasang (20 Kg) zak Rp 12,000.00

VI BAHAN LANTAI DAN KERAMIK


5 Tegel Keramik 20 x 25 (polos) m2 Rp 42,900.00
6 Tegel Keramik 20 x 20 (polos) m2 Rp 42,900.00
11 Tempat Sabun buah Rp 22,000.00
12 Kloset Jongkok (setara INA) warna muda komplit buah Rp 220,000.00
16 Urinoir (komplit) buah Rp 825,000.00
18 Avour (KM/WC dan Bak Cuci) buah Rp 48,400.00

23 Roster Karang Pilang biji Rp 4,700.00

VIII BAHAN BESI


1 Besi Beton Polos kg Rp 13,500.00
2 Besi Beton Ulir kg Rp 14,500.00
6 Kawel / Baut ( bahan plat ) kg Rp 12,000.00
7 Kawel / Baut ( bahan besi ) kg Rp 13,000.00

XI ASBES GELOMBANG
2 Asbes Gelombang Kecil 270 x 105 x 4 mm lembar Rp 85,000.00
28 Eternit Polos m2 Rp 9,300.00
31 Pompa manual Merk Dragon Unit Rp 350,000.00
NO JENIS BAHAN SATUAN HARGA KETERANGAN

XII BAHAN PAKU


1 Paku Reng kg Rp 19,000.00
2 Paku Usuk kg Rp 18,000.00
3 Paku Triplek/Eternit kg Rp 21,000.00

XIII BAHAN KRAN


2 Kran Biasa 3/4" buah Rp 18,400.00
4 Stop Kran 3/4" buah Rp 52,500.00

XIV PIPA PVC CLASS AW


C PIPA + MOF ( SOCKET ) P. 6 M - S 10
2 PIPA PVC 2" ( MOF P = 6 M - 10 S ) lonjor Rp 105,200.00
5 PIPA PVC 4" ( MOF P = 6 M - 10 S ) lonjor Rp 323,200.00

XV BAHAN KAYU
7 Kayu Kamper Papan 2/20 ; 3/30 ; 4/20 m3 Rp 8,600,000.00
12 Kayu Meranti 8/12 ; 6/12 m3 Rp 4,650,000.00
13 Kayu Meranti Usuk 5/7 ; 4/6 m3 Rp 4,000,000.00
14 Kayu Meranti Papan 2/20 ; 3/30 ; 4/20 m3 Rp 4,650,000.00
15 Kayu Meranti Reng 2/3 ; 3/5 m3 Rp 4,000,000.00
17 Kayu Kruing 5/7 ; 6/12 ; 8/12 ; 8/15 m3 Rp 5,650,000.00
19 Kayu Sengon ( Bekisting ) m3 Rp 1,500,000.00
21 Kayu List 1/5 Meranti m' Rp 2,500.00

XVI BAHAN CAT KAYU DAN TEMBOK


1 Plamir Tembok kg Rp 9,600.00
2 Plamir Kayu kg Rp 16,500.00
4 Cat Tembok (Setara Cathilac) kg Rp 17,500.00
5 Minyak Cat liter Rp 15,000.00
6 Meni Kayu kg Rp 17,000.00
7 Cat Kayu (Setara Emco) kg Rp 43,500.00
9 Ter 1 Blek = 10 Liter blek Rp 63,000.00

XVII ALAT PENGGANTUNG DAN PENGUNCI


1 Kunci 2 x putar buah Rp 72,600.00
3 Engsel pintu nylon arch asli buah Rp 21,800.00
6 Grendel Tanam buah Rp 66,000.00
8 Kunci Bulat buah Rp 46,200.00

XVIII BAHAN LISTRIK


2 NYA 2,5 mm m' Rp 2,900.00
7 Kabel Turin NYA 3 x 4 mm ( NYM 3 x 4 ) m' Rp 15,750.00
8 Kabel NYY. LMK uk. 2 x 1 1/2" m' Rp 7,350.00
9 Kabel NYY. LMK uk.4 x 16 mm m' Rp 73,500.00
10 Kabel NYY. LMK uk.2 x 2,5" mm m' Rp 10,000.00
11 Kabel NYAF uk. 6 mm m' Rp 6,300.00
12 Kabel Tanah uk.3 x 6 mm m' Rp 22,600.00
13 Kabel NYY.LMK 2 x 4 mm m' Rp 15,750.00
14 Kabel NYY.LMK 2 x 6 mm m' Rp 19,000.00
15 Kabel NYMHY.LMK 2 x 4 mm m' Rp 10,000.00
16 Kabel NYA.LMK uk. 10 mm m' Rp 11,550.00
17 Kabel NYAF.LMK. Uk. 10 mm m' Rp 12,600.00
18 Kabel NYAF.LMK. Uk. 6 mm m' Rp 6,300.00
19 Kabel NYM 2 x 1,5/m m' Rp 5,250.00
20 Kabel NYM 2 x 2,5/m m' Rp 7,350.00
21 Kabel NYM 3 x 2,5/m m' Rp 9,450.00
22 Kabel T.C 3 x 3,5 + 1 x 35 m' Rp 22,050.00
23 Kabel T.C 4 x 25 m' Rp 16,800.00
33 Lampu Dop Pijar (merk setara Philip) 100 Watt buah Rp 4,600.00
37 Lampu PLC (merk setara Philip) 18 Watt buah Rp 28,350.00
50 Sakelar Tunggal (merk setara Brocco) buah Rp 16,000.00
51 Sakelar Ganda (merk setara Brocco) buah Rp 18,000.00
52 Stop Kontak (merk setara Brocco) buah Rp 17,000.00
53 Zekering buah Rp 8,500.00
54 Kap T.O 2 buah Rp 91,500.00
55 Kap Mercury Cobra Kecil buah Rp 315,000.00
56 Kap Mercury Cobra Besar buah Rp 325,500.00
57 Kap Terbuka E. 27 (hijau) buah Rp 25,500.00
58 Kap Taman Type Cristolite TO. 10 buah Rp 121,000.00
59 Time Switch buah Rp 342,000.00
60 Magnetic Contractor 220 V buah Rp 367,500.00
61 MCB 50 A ( Engkel ) buah Rp 210,000.00
62 MCB 50 A ( Dobel ) buah Rp 499,000.00
63 Suspension Clamp buah Rp 30,500.00
64 Sekering Kodok 1 Group buah Rp 79,000.00
65 Terminal buah Rp 30,500.00
66 Lidah Buaya set Rp 28,900.00
67 Perching Connector 1 B buah Rp 7,500.00
68 Kabel NYAF 16 mm m' Rp 16,500.00
69 Elemen + Kop + Sekring 63 A buah Rp 21,000.00
70 Elemen + Kop + Sekring 10 A buah Rp 6,000.00
71 Skoen 25 buah Rp 2,000.00
NO JENIS BAHAN SATUAN HARGA KETERANGAN

XIX BAHAN LAIN - LAIN


1 Spirtus liter Rp 12,000.00
3 Pewarna Plitur buah Rp 600.00
4 Amplas lembar Rp 7,200.00
5 Minyak Tanah liter Rp 3,500.00
6 Solar liter Rp 4,500.00
7 Bensin liter Rp 4,500.00
9 Pelumas / minyak bekisting liter Rp 28,800.00
10 Gemuk/Stempet kg Rp 21,600.00
21 Lem Kayu kg Rp 30,600.00
22 Dempul Kayu (untuk plitur) biji Rp 1,800.00
38 Elektroda 3,2 mm (2%) kg Rp 78,000.00
39 Chladianplast 100 x 80 lembar Rp 86,400.00
40 Chladianplast 210 x 80 lembar Rp 100,800.00
41 Chladianplast 240 x 80 lembar Rp 115,200.00
42 Chladianplast 300 x 80 lembar Rp 144,000.00
43 Pipa Besi Kotak 1,6 mm uk. 4 x 4 lonjor Rp 180,000.00
44 Pipa Besi Kotak 1,6 mm uk. 5 x 5 lonjor Rp 230,400.00
45 Kereta Dorong buah Rp 396,000.00
46 Timba buah Rp 5,800.00
NO JENIS BAHAN SATUAN HARGA KETERANGAN

47 Cangkul buah Rp 36,000.00


48 Gancu buah Rp 57,600.00
49 Sekrop buah Rp 45,000.00
50 Kuas 3 " buah Rp 6,500.00
51 Kuas 4 " buah Rp 13,200.00
54 Poly Carbonat ( P= 12 m, Tbl= 6 mm ) lembar Rp 528,000.00
55 Kalsiplank uk. 8 mm x 20 cm x 3 m lembar Rp 39,600.00
56 Kalsiplank uk. 8 mm x 30 cm x 3 m lembar Rp 56,400.00
57 Kalsiplank uk. 12 mm x 20 cm x 3 m lembar Rp 56,400.00
58 Kalsiplank uk. 12 mm x 20 cm x 3 m lembar Rp 82,800.00
59 Kalsibot lembar Rp 51,000.00
60 Air liter Rp 25.00
61 Sewa alat pengelasan jam Rp 250,000.00
62 Wall paper m2 Rp 350,000.00
63 Ijuk Aren Kg Rp 19,300.00

XX TENAGA
1 Mandor org/hari Rp 50,000.00
2 Kepala Tukang org/hari Rp 48,000.00
3 Tukang Kayu org/hari Rp 45,000.00
4 Tukang Batu org/hari Rp 45,000.00
5 Tukang Besi org/hari Rp 45,000.00
6 Tukang Cat org/hari Rp 40,000.00
7 Tukang Plitur org/hari Rp 40,000.00
8 Pekerja org/hari Rp 35,000.00
9 Juru Ukur org/hari Rp 75,000.00
10 Mekanik org/hari Rp 50,000.00
11 Pembantu Mekanik org/hari Rp 40,000.00
12 Operator Terampil org/hari Rp 50,000.00
13 Pembantu Operator org/hari Rp 40,000.00
14 Sopir Terampil org/hari Rp 50,000.00
15 Pembantu Sopir org/hari Rp 40,000.00
16 Penjaga org/hari Rp 35,000.00
17 Buruh Terampil org/hari Rp 45,000.00
18 Penganyam org/hari Rp 45,000.00
19 Pekerja Pengisi org/hari Rp 35,000.00
20 Pekerja Penganyam org/hari Rp 35,000.00
REKAPITULASI RENCANA ANGGARAN BIAYA
EE ( ENGINEER ESTIMATE )

KEGIATAN : PEMBANGUNAN TEMPAT MANDI, CUCI DAN KAKUS ( MCK )


LOKASI : DESA PAOWAN KECAMATAN PANARUKAN
WILAYAH : SITUBONDO KOTA
TAHUN : 2009

NO URAIAN PEKERJAAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN Rp 1,107,850.00


II PEKERJAAN TANAH & URUGAN Rp 371,445.67
III PEKERJAAN PASANGAN Rp 4,900,123.44
IV PEKERJAAN BETON Rp 7,166,731.29
V PEKERJAAN PLESTERAN/BENANGAN Rp 2,503,818.24
VI PEKERJAAN PINTU DAN ROSTER Rp 660,777.60
VII PEKERJAAN KERAMIK Rp 5,095,141.93
VIII PEKERJAAN RANGKA ATAP Rp 3,261,592.60
IX PEKERJAAN PENUTUP ATAP Rp 4,926,993.67
X PEKERJAAN PLAFOND Rp 3,115,450.52
XI PEKERJAAN PENGECATAN Rp 1,808,803.77
XII PEKERJAAN INSTALASI LISTRIK Rp 415,675.00
XIII PEKERJAAN SANITAIR Rp 5,472,238.20

JUMLAH PER- UNIT Rp 40,806,641.93


PPN 10% Rp 4,080,664.19
JUMLAH TOTAL Rp 44,887,306.12
DIBULATKAN Rp 44,887,000.00
Terbilang : Empat Puluh Empat Juta Delapan Ratus Ribu Delapan Puluh Tujuh Ribu Rupiah
LAPORAN KEMAJUAN FISIK

KEGIATAN : PEMBANGUNAN TEMPAT MANDI, CUCI DAN KAKUS ( MCK ) Minggu ke : 1 ( satu )
LOKASI : DESA PAOWAN KECAMATAN PANARUKAN Tanggal : 1 s/d 6 Nopember
WILAYAH : SITUBONDO KOTA
TAHUN : 2010

Bobot Realisasi Fisik


Terhadap Terhadap Terhadap
NO URAIAN PEKERJAAN Vol Sat Total Volume Total
Pekerjaan Pekerjaan
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 24.00 M2 0.334 100% 0.334
2 Pengukuran & Pasang Bouwplank 15.00 M' 1.310 100% 1.310
3 Papan Nama Proyek 1.00 Bh 0.929 100% 0.929
2.573 2.573
II PEKERJAAN TANAH & URUGAN
1 Galian Tanah Pondasi 7.87 M3 0.503 100% 0.503
2 Urugan Pasir Bawah Pondasi 1.31 M3 0.300 100% 0.300
3 Urugan Pasir Bawah Lantai 0.08 M3 0.018 - -
4 Urugan Tanah Kembali 1.96 M3 0.042 - -
0.863 0.803
III PEKERJAAN PASANGAN
1 Pas. Pondasi Batu Kali 1 : 8 11.07 M3 10.613 65% 6.898
2 Pas. Bt. Merah 1 : 4 5.72 M3 0.768 - -
11.381 6.898
IV PEKERJAAN BETON
1 Pas. Beton Sloof 15/15 0.46 M3 4.773 - -
2 Pas. Beton Kolom 15/15 0.62 M3 6.433 - -
3 Pas. Ring Balk 15/15 0.43 M3 4.462 - -
4 Rabat Beton t = 7 Cm 0.64 M3 0.978 - -
16.646 -
V PEKERJAAN PLESTERAN
1 Plesteran Dinding 1 : 4 89.32 M2 5.815 - -
5.815
VI PEKERJAAN PINTU DAN ROSTER
1 Pas. Pintu PVC 2.00 Bh 1.277 - -
2 Pas. Roster 0.64 M2 0.257 - -
1.534 -
VII PEKERJAAN KERAMIK
1 Pas. Keramik Lantai 20/20 15.00 M2 3.665 - -
2 Pas. Keramik Dinding 20/25 31.21 M2 8.388 - -
12.053 -
VIII PEKERJAAN RANGKA ATAP
1 Pas. Gording Kayu Kruing 6/12 0.35 M3 5.619 - -
2 Pas. Usuk Kayu Meranti 4/6 0.16 M3 0.014 - -
3 Pas. Listplank 3/30 Kayu Meranti 0.14 M3 0.016 - -
4 Pas. Konsol Kayu Kruing 6/12 0.12 M3 1.927 - -
7.576 -
IX PEKERJAAN PENUTUP ATAP
1 Pas. Asbes Gelombang Kecil 44.33 M2 7.686 - -
2 Pas. Bubungan Asbes 8.21 M2 3.758 - -
11.444 -
X PEKERJAAN PLAFOND
1 Pas. Rangka plafond ky.meranti 4/6 29.47 M2 6.197 - -
2 Pas. Plafond Asbes Semen 29.47 M2 1.039 - -
7.236 -
1 2 3 4 5 6 7
XI PEKERJAAN PENGECATAN
1 Pengecatan Dinding Baru 89.32 M2 2.263 - -
2 Meni Kayu 69.30 M2 0.805 - -
3 Pengecatan Kayu 12.25 M2 0.791 - -
4 Pengecatan Plafond 13.52 M2 0.343 - -
4.202 -
XII PEKERJAAN INSTALASI LISTRIK
1 Pas. Titik Lampu 3.00 Bh 0.588 - -
2 Pas. Lampu PLC 18 watt ( merk setara Philip ) 3.00 Bh 0.198 - -
3 Pas. Saklar Ganda ( Setara Broco ) 1.00 Bh 0.042 - -
4 Pas. Saklar Tunggal ( Setara Broco ) 1.00 Bh 0.037 - -
5 Overspaneng 15.00 M' 0.101 - -
0.966 -
XIII PEKERJAAN SANITAIR
1 Pas. Avour 3.00 Bh 0.337 - -
2 Pas. Penguras 3.00 Bh 0.337 - -
3 Pas. Tempat Sabun 2.00 Bh 0.102 - -
4 Pas. Closet 2.00 Bh 1.826 - -
5 Pas. Tempat Bak Mandi & Tempat Closet/cuci 3.00 Bh 1.742 - -
6 Pas. Pipa PVC Ø 2" Kamar Mandi 3.00 M' 0.198 - -
7 Pas. Pipa PVC Ø 4" Kamar Mandi 10.00 M' 1.553 - -
8 Pas. Pipa PVC Ø 4" Air Kotor 5.00 M' 0.776 - -
9 Septictank 1.00 Bh 4.148 - -
10 Resapan 1.00 Bh 4.719 - -
11 Pengeboran Sumur Pompa Komplit dan 1.00 Ttk 1.161 - -
pipa PVC Ø 1½" L = 10 M
12 Pompa manual Merk Dragon 1.00 Unit 0.813 - -
17.712 -

J U M LAH 100.000 10.274


LAPORAN KEMAJUAN FISIK

KEGIATAN : PEMBANGUNAN TEMPAT MANDI, CUCI DAN KAKUS ( MCK ) Minggu ke : 2 ( dua )
LOKASI : DESA PAOWAN KECAMATAN PANARUKAN Tanggal : 7 s/d 12 Nopember
WILAYAH : SITUBONDO KOTA
TAHUN : 2010

Bobot Realisasi Fisik


Terhadap Terhadap Terhadap
NO URAIAN PEKERJAAN Vol Sat Total Volume Total
Pekerjaan Pekerjaan
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 24.00 M2 0.334 100% 0.334
2 Pengukuran & Pasang Bouwplank 15.00 M' 1.310 100% 1.310
3 Papan Nama Proyek 1.00 Bh 0.929 100% 0.929
2.573 2.573
II PEKERJAAN TANAH & URUGAN
1 Galian Tanah Pondasi 7.87 M3 0.503 100% 0.503
2 Urugan Pasir Bawah Pondasi 1.31 M3 0.300 100% 0.300
3 Urugan Pasir Bawah Lantai 0.08 M3 0.018 100% 0.018
4 Urugan Tanah Kembali 1.96 M3 0.042 100% 0.042
0.863 0.863
III PEKERJAAN PASANGAN
1 Pas. Pondasi Batu Kali 1 : 8 11.07 M3 10.613 100% 10.613
2 Pas. Bt. Merah 1 : 4 5.72 M3 0.768 60% 0.461
11.381 11.074
IV PEKERJAAN BETON
1 Pas. Beton Sloof 15/15 0.46 M3 4.773 100% 4.773
2 Pas. Beton Kolom 15/15 0.62 M3 6.433 100% 6.433
3 Pas. Ring Balk 15/15 0.43 M3 4.462 50% 2.231
4 Rabat Beton t = 7 Cm 0.64 M3 0.978 - -
16.646 13.437
V PEKERJAAN PLESTERAN
1 Plesteran Dinding 1 : 4 89.32 M2 5.815 - -
5.815
VI PEKERJAAN PINTU DAN ROSTER
1 Pas. Pintu PVC 2.00 Bh 1.277 100% 1.277
2 Pas. Roster 0.64 M2 0.257 100% 0.257
1.534 1.534
VII PEKERJAAN KERAMIK
1 Pas. Keramik Lantai 20/20 15.00 M2 3.665 - -
2 Pas. Keramik Dinding 20/25 31.21 M2 8.388 - -
12.053 -
VIII PEKERJAAN RANGKA ATAP
1 Pas. Gording Kayu Kruing 6/12 0.35 M3 5.619 - -
2 Pas. Usuk Kayu Meranti 4/6 0.16 M3 0.014 - -
3 Pas. Listplank 3/30 Kayu Meranti 0.14 M3 0.016 - -
4 Pas. Konsol Kayu Kruing 6/12 0.12 M3 1.927 - -
7.576 -
IX PEKERJAAN PENUTUP ATAP
1 Pas. Asbes Gelombang Kecil 44.33 M2 7.686 - -
2 Pas. Bubungan Asbes 8.21 M2 3.758 - -
11.444 -
X PEKERJAAN PLAFOND
1 Pas. Rangka plafond ky.meranti 4/6 29.47 M2 6.197 - -
2 Pas. Plafond Asbes Semen 29.47 M2 1.039 - -
7.236 -

1 2 3 4 5 6 7
XI PEKERJAAN PENGECATAN
1 Pengecatan Dinding Baru 89.32 M2 2.263 - -
2 Meni Kayu 69.30 M2 0.805 - -
3 Pengecatan Kayu 12.25 M2 0.791 - -
4 Pengecatan Plafond 13.52 M2 0.343 - -
4.202 -
XII PEKERJAAN INSTALASI LISTRIK
1 Pas. Titik Lampu 3.00 Bh 0.588 - -
2 Pas. Lampu PLC 18 watt ( merk setara Philip ) 3.00 Bh 0.198 - -
3 Pas. Saklar Ganda ( Setara Broco ) 1.00 Bh 0.042 - -
4 Pas. Saklar Tunggal ( Setara Broco ) 1.00 Bh 0.037 - -
5 Overspaneng 15.00 M' 0.101 - -
0.966 -
XIII PEKERJAAN SANITAIR
1 Pas. Avour 3.00 Bh 0.337 - -
2 Pas. Penguras 3.00 Bh 0.337 - -
3 Pas. Tempat Sabun 2.00 Bh 0.102 - -
4 Pas. Closet 2.00 Bh 1.826 - -
5 Pas. Tempat Bak Mandi & Tempat Closet/cuci 3.00 Bh 1.742 100% 1.742
6 Pas. Pipa PVC Ø 2" Kamar Mandi 3.00 M' 0.198 100% 0.198
7 Pas. Pipa PVC Ø 4" Kamar Mandi 10.00 M' 1.553 - -
8 Pas. Pipa PVC Ø 4" Air Kotor 5.00 M' 0.776 - -
9 Septictank 1.00 Bh 4.148 - -
10 Resapan 1.00 Bh 4.719 - -
11 Pengeboran Sumur Pompa Komplit dan 1.00 Ttk 1.161 - -
pipa PVC Ø 1½" L = 10 M
12 Pompa manual Merk Dragon 1.00 Unit 0.813 - -
17.712 1.940

J U M LAH 100.000 31.421


LAPORAN KEMAJUAN FISIK

KEGIATAN : PEMBANGUNAN TEMPAT MANDI, CUCI DAN KAKUS ( MCK ) Minggu ke : 3 ( tiga )
LOKASI : DESA PAOWAN KECAMATAN PANARUKAN Tanggal : 13 s/d 18 Nopember
WILAYAH : SITUBONDO KOTA
TAHUN : 2010

Bobot Realisasi Fisik


Terhadap Terhadap Terhadap
NO URAIAN PEKERJAAN Vol Sat Total Volume Total
Pekerjaan Pekerjaan
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 24.00 M2 0.334 100% 0.334
2 Pengukuran & Pasang Bouwplank 15.00 M' 1.310 100% 1.310
3 Papan Nama Proyek 1.00 Bh 0.929 100% 0.929
2.573 2.573
II PEKERJAAN TANAH & URUGAN
1 Galian Tanah Pondasi 7.87 M3 0.503 100% 0.503
2 Urugan Pasir Bawah Pondasi 1.31 M3 0.300 100% 0.300
3 Urugan Pasir Bawah Lantai 0.08 M3 0.018 100% 0.018
4 Urugan Tanah Kembali 1.96 M3 0.042 100% 0.042
0.863 0.863
III PEKERJAAN PASANGAN
1 Pas. Pondasi Batu Kali 1 : 8 11.07 M3 10.613 100% 10.613
2 Pas. Bt. Merah 1 : 4 5.72 M3 0.768 100% 0.768
11.381 11.381
IV PEKERJAAN BETON
1 Pas. Beton Sloof 15/15 0.46 M3 4.773 100% 4.773
2 Pas. Beton Kolom 15/15 0.62 M3 6.433 100% 6.433
3 Pas. Ring Balk 15/15 0.43 M3 4.462 100% 4.462
4 Rabat Beton t = 7 Cm 0.64 M3 0.978 100% 0.978
16.646 16.646
V PEKERJAAN PLESTERAN
1 Plesteran Dinding 1 : 4 89.32 M2 5.815 100% 5.815
5.815 5.815
VI PEKERJAAN PINTU DAN ROSTER
1 Pas. Pintu PVC 2.00 Bh 1.277 100% 1.277
2 Pas. Roster 0.64 M2 0.257 100% 0.257
1.534 1.534
VII PEKERJAAN KERAMIK
1 Pas. Keramik Lantai 20/20 15.00 M2 3.665 32% 1.173
2 Pas. Keramik Dinding 20/25 31.21 M2 8.388 - -
12.053 1.173
VIII PEKERJAAN RANGKA ATAP
1 Pas. Gording Kayu Kruing 6/12 0.35 M3 5.619 100% 5.619
2 Pas. Usuk Kayu Meranti 4/6 0.16 M3 0.014 100% 0.014
3 Pas. Listplank 3/30 Kayu Meranti 0.14 M3 0.016 100% 0.016
4 Pas. Konsol Kayu Kruing 6/12 0.12 M3 1.927 100% 1.927
7.576 7.576
IX PEKERJAAN PENUTUP ATAP
1 Pas. Asbes Gelombang Kecil 44.33 M2 7.686 100% 7.686
2 Pas. Bubungan Asbes 8.21 M2 3.758 100% 3.758
11.444 11.444
X PEKERJAAN PLAFOND
1 Pas. Rangka plafond ky.meranti 4/6 29.47 M2 6.197 50% 3.099
2 Pas. Plafond Asbes Semen 29.47 M2 1.039 50% 0.520
7.236 3.618

1 2 3 4 5 6 7
XI PEKERJAAN PENGECATAN
1 Pengecatan Dinding Baru 89.32 M2 2.263 - -
2 Meni Kayu 69.30 M2 0.805 - -
3 Pengecatan Kayu 12.25 M2 0.791 - -
4 Pengecatan Plafond 13.52 M2 0.343 - -
4.202 -
XII PEKERJAAN INSTALASI LISTRIK
1 Pas. Titik Lampu 3.00 Bh 0.588 100% 0.588
2 Pas. Lampu PLC 18 watt ( merk setara Philip ) 3.00 Bh 0.198 100% 0.198
3 Pas. Saklar Ganda ( Setara Broco ) 1.00 Bh 0.042 100% 0.042
4 Pas. Saklar Tunggal ( Setara Broco ) 1.00 Bh 0.037 100% 0.037
5 Overspaneng 15.00 M' 0.101 100% 0.101
0.966 0.966
XIII PEKERJAAN SANITAIR
1 Pas. Avour 3.00 Bh 0.337 100% 0.337
2 Pas. Penguras 3.00 Bh 0.337 100% 0.337
3 Pas. Tempat Sabun 2.00 Bh 0.102 100% 0.102
4 Pas. Closet 2.00 Bh 1.826 100% 1.826
5 Pas. Tempat Bak Mandi & Tempat Closet/cuci 3.00 Bh 1.742 100% 1.742
6 Pas. Pipa PVC Ø 2" Kamar Mandi 3.00 M' 0.198 100% 0.198
7 Pas. Pipa PVC Ø 4" Kamar Mandi 10.00 M' 1.553 100% 1.553
8 Pas. Pipa PVC Ø 4" Air Kotor 5.00 M' 0.776 - -
9 Septictank 1.00 Bh 4.148 - -
10 Resapan 1.00 Bh 4.719 - -
11 Pengeboran Sumur Pompa Komplit dan 1.00 Ttk 1.161 - -
pipa PVC Ø 1½" L = 10 M
12 Pompa manual Merk Dragon 1.00 Unit 0.813 - -
17.712 6.095

J U M LAH 100.000 69.684


LAPORAN KEMAJUAN FISIK

KEGIATAN : PEMBANGUNAN TEMPAT MANDI, CUCI DAN KAKUS ( MCK ) Minggu ke : 4 ( empat )
LOKASI : DESA PAOWAN KECAMATAN PANARUKAN Tanggal : 19 s/d 26 Nopember
WILAYAH : SITUBONDO KOTA
TAHUN : 2010

Bobot Realisasi Fisik


Terhadap Terhadap Terhadap
NO URAIAN PEKERJAAN Vol Sat Total Volume Total
Pekerjaan Pekerjaan
1 2 3 4 5 6 7
I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 24.00 M2 0.334 100% 0.334
2 Pengukuran & Pasang Bouwplank 15.00 M' 1.310 100% 1.310
3 Papan Nama Proyek 1.00 Bh 0.929 100% 0.929
2.573 2.573
II PEKERJAAN TANAH & URUGAN
1 Galian Tanah Pondasi 7.87 M3 0.503 100% 0.503
2 Urugan Pasir Bawah Pondasi 1.31 M3 0.300 100% 0.300
3 Urugan Pasir Bawah Lantai 0.08 M3 0.018 100% 0.018
4 Urugan Tanah Kembali 1.96 M3 0.042 100% 0.042
0.863 0.863
III PEKERJAAN PASANGAN
1 Pas. Pondasi Batu Kali 1 : 8 11.07 M3 10.613 100% 10.613
2 Pas. Bt. Merah 1 : 4 5.72 M3 0.768 100% 0.768
11.381 11.381
IV PEKERJAAN BETON
1 Pas. Beton Sloof 15/15 0.46 M3 4.773 100% 4.773
2 Pas. Beton Kolom 15/15 0.62 M3 6.433 100% 6.433
3 Pas. Ring Balk 15/15 0.43 M3 4.462 100% 4.462
4 Rabat Beton t = 7 Cm 0.64 M3 0.978 100% 0.978
16.646 16.646
V PEKERJAAN PLESTERAN
1 Plesteran Dinding 1 : 4 89.32 M2 5.815 100% 5.815
5.815 5.815
VI PEKERJAAN PINTU DAN ROSTER
1 Pas. Pintu PVC 2.00 Bh 1.277 100% 1.277
2 Pas. Roster 0.64 M2 0.257 100% 0.257
1.534 1.534
VII PEKERJAAN KERAMIK
1 Pas. Keramik Lantai 20/20 15.00 M2 3.665 100% 3.665
2 Pas. Keramik Dinding 20/25 31.21 M2 8.388 100% 8.388
12.053 12.053
VIII PEKERJAAN RANGKA ATAP
1 Pas. Gording Kayu Kruing 6/12 0.35 M3 5.619 100% 5.619
2 Pas. Usuk Kayu Meranti 4/6 0.16 M3 0.014 100% 0.014
3 Pas. Listplank 3/30 Kayu Meranti 0.14 M3 0.016 100% 0.016
4 Pas. Konsol Kayu Kruing 6/12 0.12 M3 1.927 100% 1.927
7.576 7.576
IX PEKERJAAN PENUTUP ATAP
1 Pas. Asbes Gelombang Kecil 44.33 M2 7.686 100% 7.686
2 Pas. Bubungan Asbes 8.21 M2 3.758 100% 3.758
11.444 11.444
X PEKERJAAN PLAFOND
1 Pas. Rangka plafond ky.meranti 4/6 29.47 M2 6.197 100% 6.197
2 Pas. Plafond Asbes Semen 29.47 M2 1.039 100% 1.039
7.236 7.236

1 2 3 4 5 6 7
XI PEKERJAAN PENGECATAN
1 Pengecatan Dinding Baru 89.32 M2 2.263 100% 2.263
2 Meni Kayu 69.30 M2 0.805 100% 0.805
3 Pengecatan Kayu 12.25 M2 0.791 100% 0.791
4 Pengecatan Plafond 13.52 M2 0.343 100% 0.343
4.202 4.202
XII PEKERJAAN INSTALASI LISTRIK
1 Pas. Titik Lampu 3.00 Bh 0.588 100% 0.588
2 Pas. Lampu PLC 18 watt ( merk setara Philip ) 3.00 Bh 0.198 100% 0.198
3 Pas. Saklar Ganda ( Setara Broco ) 1.00 Bh 0.042 100% 0.042
4 Pas. Saklar Tunggal ( Setara Broco ) 1.00 Bh 0.037 100% 0.037
5 Overspaneng 15.00 M' 0.101 100% 0.101
0.966 0.966
XIII PEKERJAAN SANITAIR
1 Pas. Avour 3.00 Bh 0.337 100% 0.337
2 Pas. Penguras 3.00 Bh 0.337 100% 0.337
3 Pas. Tempat Sabun 2.00 Bh 0.102 100% 0.102
4 Pas. Closet 2.00 Bh 1.826 100% 1.826
5 Pas. Tempat Bak Mandi & Tempat Closet/cuci 3.00 Bh 1.742 100% 1.742
6 Pas. Pipa PVC Ø 2" Kamar Mandi 3.00 M' 0.198 100% 0.198
7 Pas. Pipa PVC Ø 4" Kamar Mandi 10.00 M' 1.553 100% 1.553
8 Pas. Pipa PVC Ø 4" Air Kotor 5.00 M' 0.776 100% 0.776
9 Septictank 1.00 Bh 4.148 100% 4.148
10 Resapan 1.00 Bh 4.719 100% 4.719
11 Pengeboran Sumur Pompa Komplit dan
1.00 Ttk 1.161 100% 1.161
pipa PVC Ø 1½" L = 10 M
12 Pompa manual Merk Dragon 1.00 Unit 0.813 100% 0.813
17.712 17.712

J U M LAH 100.000 100.000


ANALISA HARGA SATUAN BAHAN DAN UPAH

KEGIATAN : PEMBANGUNAN TEMPAT MANDI, CUCI DAN KAKUS ( MCK )


LOKASI : DESA PANGI KECAMATAN SANG TOMBOLANG
KABUPATEN : BOLAANG MONGONDOW
TAHUN : 2017

JENIS PEKERJAAN SAT INDEKS HARGA SATUAN JUMLAH HARGA

Pekerjaan Persiapan
Pembersihan lokasi M2
Upah Pekerja org/hari 0.10000 Rp 90,000.00 Rp 9,000.00
Mandor org/hari 0.05000 Rp 110,000.00 Rp 5,500.00
Jumlah Rp 14,500.00
Pekerjaan Tanah dan Urugan
Galian Tanah Pondasi M3
Upah Pekerja org/hari 0.75000 Rp 90,000.00 Rp 67,500.00
Mandor org/hari 0.02500 Rp 110,000.00 Rp 2,750.00
Jumlah Rp 70,250.00
Urugan Pasir Bawah Pondasi M3
Bahan Pasir Urug/Sirtu m3 1.20000 Rp 150,000.00 Rp 180,000.00
Upah Pekerja org/hari 0.30000 Rp 90,000.00 Rp 27,000.00
Mandor org/hari 0.01000 Rp 110,000.00 Rp 1,100.00
Jumlah Rp 208,100.00
Urugan Pasir Bawah Lantai M3
Bahan Pasir Urug/Sirtu m3 1.20000 Rp 150,000.00 Rp 180,000.00
Upah Pekerja org/hari 0.30000 Rp 90,000.00 Rp 27,000.00
Mandor org/hari 0.01000 Rp 110,000.00 Rp 1,100.00
Jumlah Rp 208,100.00
Urugan Tanah M3
Bahan Tanah Urug m3 1.20000 Rp 150,000.00 Rp 180,000.00
Upah Pekerja org/hari 0.30000 Rp 90,000.00 Rp 27,000.00
Mandor org/hari 0.01000 Rp 110,000.00 Rp 1,100.00
Jumlah Rp 208,100.00
Meratakan kembali M2
Upah Pekerja org/hari 0.25000 Rp 90,000.00 Rp 22,500.00
Mandor org/hari 0.00833 Rp 110,000.00 Rp 916.67
Jumlah Rp 23,416.67

JENIS PEKERJAAN SAT INDEKS HARGA SATUAN JUMLAH HARGA

Pekerjaan Pasangan
Pondasi Bt. Kali 1 : 5 M3
Bahan Batu Gunung/Batu Kali m3 1.00000 Rp 200,000.00 Rp 200,000.00
Semen 50 Kg kg 2.70000 Rp 1,500.00 Rp 4,050.00
Pasir Pasang m3 0.50000 Rp 175,000.00 Rp 87,500.00
Upah Pekerja org/hari 1.10000 Rp 90,000.00 Rp 99,000.00
Tukang Batu org/hari 1.00000 Rp 120,000.00 Rp 120,000.00
Kepala Tukang org/hari 0.16000 Rp 140,000.00 Rp 22,400.00
Mandor org/hari 0.16000 Rp 110,000.00 Rp 17,600.00
Jumlah Rp 550,550.00
Dinding batako camp. 1 : 4 M2
Bahan Batako biji 12.50000 Rp 2,300.00 Rp 28,750.00
Semen 50 Kg kg 11.50000 Rp 1,500.00 Rp 17,250.00
Pasir Pasang m3 0.04300 Rp 175,000.00 Rp 7,525.00
Upah Pekerja org/hari 0.30000 Rp 90,000.00 Rp 27,000.00
Tukang Batu org/hari 0.10000 Rp 120,000.00 Rp 12,000.00
Kepala Tukang org/hari 0.01000 Rp 140,000.00 Rp 1,400.00
Mandor org/hari 0.01500 Rp 110,000.00 Rp 1,650.00
Jumlah Rp 95,575.00
Roster camp. 1 : 4 M2
Bahan Roster Karang Pilang biji 4.00000 Rp 4,700.00 Rp 18,800.00
Semen 50 Kg kg 11.00000 Rp 1,500.00 Rp 16,500.00
Pasir Pasang m3 0.03500 Rp 175,000.00 Rp 6,125.00
Upah Pekerja org/hari 0.30000 Rp 90,000.00 Rp 27,000.00
Tukang Batu org/hari 0.10000 Rp 120,000.00 Rp 12,000.00
Kepala Tukang org/hari 0.01000 Rp 140,000.00 Rp 1,400.00
Mandor org/hari 0.01500 Rp 110,000.00 Rp 1,650.00
Jumlah Rp 83,475.00
Pekerjaan Plesteran
Plesteran camp. 1 : 4 tbl 15 mm M2
Bahan Semen 50 Kg kg 6.24000 Rp 1,500.00 Rp 9,360.00
Pasir Pasang m3 0.02400 Rp 175,000.00 Rp 4,200.00
Upah Pekerja org/hari 0.30000 Rp 90,000.00 Rp 27,000.00
Tukang Batu org/hari 0.15000 Rp 120,000.00 Rp 18,000.00
Kepala Tukang org/hari 0.01500 Rp 140,000.00 Rp 2,100.00
Mandor org/hari 0.01500 Rp 110,000.00 Rp 1,650.00
Jumlah Rp 62,310.00
Acian M2
Bahan Semen 50 Kg kg 3.25000 Rp 1,500.00 Rp 4,875.00
Upah Pekerja org/hari 0.20000 Rp 90,000.00 Rp 18,000.00
Tukang Batu org/hari 0.10000 Rp 120,000.00 Rp 12,000.00
Kepala Tukang org/hari 0.01000 Rp 140,000.00 Rp 1,400.00
Mandor org/hari 0.01000 Rp 110,000.00 Rp 1,100.00
Jumlah Rp 37,375.00
Pekerjaan Beton Struktur
Mengecor Beton
Beton mutu K - 175 (Beton ringan) M3
Bahan Semen 50 Kg kg 326.00000 Rp 1,200.00 Rp 391,200.00
Pasir Cor m3 0.54286 Rp 76,000.00 Rp 41,257.14
Kerikil m3 0.73500 Rp 156,000.00 Rp 114,660.00
Air liter 215.00000 Rp 25.00 Rp 5,375.00
Upah Pekerja org/hari 1.65000 Rp 90,000.00 Rp 148,500.00
Tukang Batu org/hari 0.27500 Rp 120,000.00 Rp 33,000.00
Kepala Tukang org/hari 0.02800 Rp 140,000.00 Rp 3,920.00
Mandor org/hari 0.08300 Rp 110,000.00 Rp 9,130.00
Jumlah Rp 747,042.14
Pembuatan Bekisting
Bekisting untuk pondasi M2
Bahan Kayu Sengon ( Bekisting ) m3 0.04000 Rp 1,500,000.00 Rp 60,000.00
Paku kg 0.30000 Rp 18,000.00 Rp 5,400.00
Pelumas / minyak bekisting liter 0.10000 Rp 28,800.00 Rp 2,880.00
Upah Pekerja org/hari 0.52000 Rp 90,000.00 Rp 46,800.00
Tukang Kayu org/hari 0.26000 Rp 120,000.00 Rp 31,200.00
Kepala Tukang org/hari 0.02600 Rp 140,000.00 Rp 3,640.00
Mandor org/hari 0.02600 Rp 110,000.00 Rp 2,860.00
Jumlah Rp 152,780.00
Bekisting untuk sloof M2
Bahan Kayu Sengon ( Bekisting ) m3 0.01500 Rp 1,500,000.00 Rp 22,500.00
Paku kg 0.30000 Rp 18,000.00 Rp 5,400.00
Pelumas / minyak bekisting liter 0.10000 Rp 28,800.00 Rp 2,880.00
Upah Pekerja org/hari 0.52000 Rp 90,000.00 Rp 46,800.00
Tukang Kayu org/hari 0.26000 Rp 120,000.00 Rp 31,200.00
Kepala Tukang org/hari 0.02600 Rp 140,000.00 Rp 3,640.00
Mandor org/hari 0.02600 Rp 110,000.00 Rp 2,860.00
Jumlah Rp 115,280.00
Bekisting untuk kolom M2
Bahan Kayu Sengon ( Bekisting ) m3 0.02830 Rp 1,500,000.00 Rp 42,450.00
Paku kg 0.40000 Rp 18,000.00 Rp 7,200.00
Pelumas / minyak bekisting liter 0.20000 Rp 28,800.00 Rp 5,760.00
Bambu lonjor 0.50000 Rp 20,000.00 Rp 10,000.00
Upah Pekerja org/hari 0.66000 Rp 90,000.00 Rp 59,400.00
Tukang Kayu org/hari 0.33000 Rp 120,000.00 Rp 39,600.00
Kepala Tukang org/hari 0.03300 Rp 140,000.00 Rp 4,620.00
Mandor org/hari 0.03300 Rp 110,000.00 Rp 3,630.00
Jumlah Rp 172,660.00
Bekisting untuk balok M2
Bahan Kayu Sengon ( Bekisting ) m3 0.08800 Rp 1,500,000.00 Rp 132,000.00
Paku kg 0.40000 Rp 18,000.00 Rp 7,200.00
Pelumas / minyak bekisting liter 0.20000 Rp 28,800.00 Rp 5,760.00
Bambu lonjor 2.00000 Rp 20,000.00 Rp 40,000.00
Upah Pekerja org/hari 0.66000 Rp 90,000.00 Rp 59,400.00
Tukang Kayu org/hari 0.33000 Rp 120,000.00 Rp 39,600.00
Kepala Tukang org/hari 0.03300 Rp 140,000.00 Rp 4,620.00
Mandor org/hari 0.03300 Rp 110,000.00 Rp 3,630.00
Jumlah Rp 292,210.00
Bekisting untuk lantai M2
Bahan Kayu Sengon ( Bekisting ) m3 0.08500 Rp 1,500,000.00 Rp 127,500.00
Paku kg 0.40000 Rp 18,000.00 Rp 7,200.00
Pelumas / minyak bekisting liter 0.20000 Rp 28,800.00 Rp 5,760.00
Bambu lonjor 6.00000 Rp 20,000.00 Rp 120,000.00
Upah Pekerja org/hari 0.66000 Rp 90,000.00 Rp 59,400.00
Tukang Kayu org/hari 0.33000 Rp 120,000.00 Rp 39,600.00
Kepala Tukang org/hari 0.03300 Rp 140,000.00 Rp 4,620.00
Mandor org/hari 0.03300 Rp 110,000.00 Rp 3,630.00
Jumlah Rp 367,710.00
Bekisting untuk dinding M2
Bahan Kayu Sengon ( Bekisting ) m3 0.08000 Rp 1,500,000.00 Rp 120,000.00
Paku kg 0.40000 Rp 18,000.00 Rp 7,200.00
Pelumas / minyak bekisting liter 0.20000 Rp 28,800.00 Rp 5,760.00
Bambu lonjor 7.00000 Rp 20,000.00 Rp 140,000.00
Upah Pekerja org/hari 0.66000 Rp 90,000.00 Rp 59,400.00
Tukang Kayu org/hari 0.33000 Rp 120,000.00 Rp 39,600.00
Kepala Tukang org/hari 0.03300 Rp 140,000.00 Rp 4,620.00
Mandor org/hari 0.03300 Rp 110,000.00 Rp 3,630.00
Jumlah Rp 380,210.00
Membuat Beton Bertulang
Beton sloof M3
Mengecor beton 1 : 2 : 3 M3 1.00000 Rp 747,042.14 Rp 747,042.14
Bekisting untuk sloof M2 13.33333 Rp 115,280.00 Rp 1,537,066.67
Besi beton polos Kg 197.28000 Rp 15,036.10 Rp 2,966,321.81
Jumlah Rp 5,250,430.62
Membuat Beton Bertulang
Beton kolom M3
Mengecor beton 1 : 2 : 3 M3 1.00000 Rp 747,042.14 Rp 747,042.14
Bekisting untuk kolom M2 13.33333 Rp 172,660.00 Rp 2,302,133.33
Besi beton polos Kg 197.28000 Rp 15,036.10 Rp 2,966,321.81
Jumlah Rp 6,015,497.28
Membuat Beton Bertulang
Beton ring balok M3
Mengecor beton 1 : 2 : 3 M3 1.00000 Rp 747,042.14 Rp 747,042.14
Bekisting untuk ring balok M2 13.33333 Rp 292,210.00 Rp 3,896,133.33
Besi beton polos Kg 197.28000 Rp 15,036.10 Rp 2,966,321.81
Jumlah Rp 7,609,497.28
Pekerjaan Kayu
Konstruksi gording kayu klas II M3
Bahan Kayu 6/12 m3 1.10000 Rp 5,650,000.00 Rp 6,215,000.00
Kawel / Baut ( bahan besi ) kg 15.00000 Rp 13,000.00 Rp 195,000.00
Paku kg 3.00000 Rp 18,000.00 Rp 54,000.00
Upah Pekerja org/hari 2.40000 Rp 90,000.00 Rp 216,000.00
Tukang Kayu org/hari 7.20000 Rp 120,000.00 Rp 864,000.00
Kepala Tukang org/hari 0.72000 Rp 140,000.00 Rp 100,800.00
Mandor org/hari 0.12000 Rp 110,000.00 Rp 13,200.00
Jumlah Rp 7,658,000.00
Usuk kayu klas III M2
Bahan Kayu 5/7 m3 0.00600 Rp 4,000,000.00 Rp 24,000.00
Paku kg 0.25000 Rp 18,000.00 Rp 4,500.00
Upah Pekerja org/hari 0.10000 Rp 90,000.00 Rp 9,000.00
Tukang Kayu org/hari 0.10000 Rp 120,000.00 Rp 12,000.00
Kepala Tukang org/hari 0.01000 Rp 140,000.00 Rp 1,400.00
Mandor org/hari 0.00500 Rp 110,000.00 Rp 550.00
Jumlah Rp 51,450.00
Rangka plafond M2
Bahan Kayu 4/6 m3 0.01575 Rp 4,000,000.00 Rp 63,000.00
Paku kg 0.20000 Rp 18,000.00 Rp 3,600.00
Upah Pekerja org/hari 0.15000 Rp 90,000.00 Rp 13,500.00
Tukang Kayu org/hari 0.30000 Rp 120,000.00 Rp 36,000.00
Kepala Tukang org/hari 0.03000 Rp 140,000.00 Rp 4,200.00
Mandor org/hari 0.07500 Rp 110,000.00 Rp 8,250.00
Jumlah Rp 128,550.00
Listplank 3/30 kayu klas II M2
Bahan Kayu Papan 3/30 m3 0.01100 Rp 8,600,000.00 Rp 94,600.00
Paku kg 0.05000 Rp 18,000.00 Rp 900.00
Upah Pekerja org/hari 0.10000 Rp 90,000.00 Rp 9,000.00
Tukang Kayu org/hari 0.20000 Rp 120,000.00 Rp 24,000.00
Kepala Tukang org/hari 0.02000 Rp 140,000.00 Rp 2,800.00
Mandor org/hari 0.00500 Rp 110,000.00 Rp 550.00
Jumlah Rp 131,850.00
Pekerjaan Penutup Atap
Atap asbes gelombang kecil M2
Bahan Asbes Gelombang kecil 270 x 105 x 4 mm lembar 0.75000 Rp 85,000.00 Rp 63,750.00
Paku kg 0.12000 Rp 18,000.00 Rp 2,160.00
Upah Pekerja org/hari 0.14000 Rp 90,000.00 Rp 12,600.00
Tukang Batu org/hari 0.07000 Rp 120,000.00 Rp 8,400.00
Kepala Tukang org/hari 0.00700 Rp 140,000.00 Rp 980.00
Mandor org/hari 0.00700 Rp 110,000.00 Rp 770.00
Jumlah Rp 88,660.00
Pekerjaan Lantai
Lantai keramik 20 x 20 M2
Bahan Tegel Keramik 20 x 20 (polos) m2 1.00000 Rp 42,900.00 Rp 42,900.00
Semen 50 Kg kg 10.00000 Rp 1,200.00 Rp 12,000.00
Pasir Pasang m3 0.04500 Rp 76,000.00 Rp 3,420.00
Semen Putih 50 Kg kg 1.50000 Rp 2,125.00 Rp 3,187.50
Upah Pekerja org/hari 0.70000 Rp 90,000.00 Rp 63,000.00
Tukang Batu org/hari 0.35000 Rp 120,000.00 Rp 42,000.00
Kepala Tukang org/hari 0.03500 Rp 140,000.00 Rp 4,900.00
Mandor org/hari 0.03500 Rp 110,000.00 Rp 3,850.00
Jumlah Rp 175,257.50
Pekerjaan Plafond
Plafond asbes semen M2
Bahan Enternit Polos m2 1.10000 Rp 9,300.00 Rp 10,230.00
Paku Triplek/Eternit kg 0.01000 Rp 21,000.00 Rp 210.00
Upah Pekerja org/hari 0.03000 Rp 90,000.00 Rp 2,700.00
Tukang Kayu org/hari 0.07000 Rp 120,000.00 Rp 8,400.00
Kepala Tukang org/hari 0.00700 Rp 140,000.00 Rp 980.00
Mandor org/hari 0.00400 Rp 110,000.00 Rp 440.00
Jumlah Rp 22,960.00
List plafond kayu profil M'
Bahan Kayu List 1/5 Meranti m' 1.05000 Rp 2,500.00 Rp 2,625.00
Paku Usuk kg 0.01000 Rp 18,000.00 Rp 180.00
Upah Pekerja org/hari 0.05000 Rp 90,000.00 Rp 4,500.00
Tukang Kayu org/hari 0.05000 Rp 120,000.00 Rp 6,000.00
Kepala Tukang org/hari 0.00500 Rp 140,000.00 Rp 700.00
Mandor org/hari 0.00300 Rp 110,000.00 Rp 330.00
Jumlah Rp 14,335.00
Pekerjaan Pengecatan
Pengecatan tembok M2
Bahan Plamir Tembok kg 0.10000 Rp 9,600.00 Rp 960.00
Cat Tembok (Setara Cathilac) kg 0.36000 Rp 17,500.00 Rp 6,300.00
Upah Pekerja org/hari 0.02000 Rp 90,000.00 Rp 1,800.00
Tukang Cat org/hari 0.06300 Rp 120,000.00 Rp 7,560.00
Kepala Tukang org/hari 0.00630 Rp 140,000.00 Rp 882.00
Mandor org/hari 0.00250 Rp 110,000.00 Rp 275.00
Jumlah Rp 17,777.00
Pengecatan kayu M2
Bahan Cat Kayu (Setara Emco) kg 0.43000 Rp 43,500.00 Rp 18,705.00
Meni Kayu kg 0.20000 Rp 17,000.00 Rp 3,400.00
Plamir Kayu kg 0.15000 Rp 16,500.00 Rp 2,475.00
Upah Pekerja org/hari 0.07000 Rp 90,000.00 Rp 6,300.00
Tukang Cat org/hari 0.00900 Rp 120,000.00 Rp 1,080.00
Kepala Tukang org/hari 0.00600 Rp 140,000.00 Rp 840.00
Mandor org/hari 0.00250 Rp 110,000.00 Rp 275.00
Jumlah Rp 33,075.00
Pek. Listrik
Titik lampu Ttk
Bahan NYM 2,5 mm 15.62500 Rp 2,900.00 Rp 45,312.50
Upah Tukang 0.78125 Rp 50,000.00 Rp 39,062.50
Jumlah Rp 84,375.00
Skakelar tunggal Bh
Bahan Sakelar tunggal ( merk setara Brocco ) 1.00000 Rp 16,000.00 Rp 16,000.00
Jumlah Rp 16,000.00
Pek. Sanitasi
Closet Jongkok Bh
Bahan Closet Jongkok ( setara INA warna muda ) komplit Bh 2.00000 Rp 220,000.00 Rp 440,000.00
Tenaga Pekerja org/hari 3.30000 Rp 90,000.00 Rp 297,000.00
Tukang org/hari 1.10000 Rp 120,000.00 Rp 132,000.00
Kepala tukang org/hari 0.00100 Rp 140,000.00 Rp 140.00
Mandor org/hari 0.16000 Rp 110,000.00 Rp 17,600.00
Jumlah Rp 886,740.00
Saluran Air Kotor Pipa PVC 4" M'
Bahan PIPA PVC 4" M' 1.00000 Rp 53,866.67 Rp 53,866.67
Perlengkapan 6 % harga Pipa Ls 1.00000 Rp 3,232.00 Rp 3,232.00
Tenaga Pekerja org/hari 0.08100 Rp 90,000.00 Rp 7,290.00
Tukang org/hari 0.13500 Rp 120,000.00 Rp 16,200.00
Kepala tukang org/hari 0.01350 Rp 140,000.00 Rp 1,890.00
Mandor org/hari 0.00410 Rp 110,000.00 Rp 451.00
Jumlah Rp 82,929.67
Saluran Air Bersih Pipa PVC 2" M'
Bahan PIPA PVC 2" M' 1.00000 Rp 17,533.33 Rp 17,533.33
Perlengkapan 6 % harga Pipa Ls 1.00000 Rp 1,052.00 Rp 1,052.00
Tenaga Pekerja org/hari 0.08100 Rp 90,000.00 Rp 7,290.00
Tukang org/hari 0.13500 Rp 120,000.00 Rp 16,200.00
Kepala tukang org/hari 0.01350 Rp 140,000.00 Rp 1,890.00
Mandor org/hari 0.00410 Rp 110,000.00 Rp 451.00
Jumlah Rp 44,416.33
Kran air dia 3/4" Bh
Bahan Kran Biasa 3/4" Bh 1.00000 Rp 18,400.00 Rp 18,400.00
Perlengkapan 6 % harga Kran Ls 1.00000 Rp 1,104.00 Rp 1,104.00
Tenaga Pekerja org/hari 0.01000 Rp 90,000.00 Rp 900.00
Tukang org/hari 0.10000 Rp 120,000.00 Rp 12,000.00
Kepala tukang org/hari 0.01000 Rp 140,000.00 Rp 1,400.00
Mandor org/hari 0.00500 Rp 110,000.00 Rp 550.00
Jumlah Rp 34,354.00
Pembuatan Septictank Bh
Bahan Galian Tanah M3 3.00000 Rp 70,250.00 Rp 210,750.00
Urugan Tanah M3 0.82200 Rp 208,100.00 Rp 171,058.20
Urugan Pasir M3 0.10000 Rp 208,100.00 Rp 20,810.00
Pas. Batako 1 : 4 M2 9.00000 Rp 95,575.00 Rp 860,175.00
Pas. Plat Beton tbl. 7 cm M3 0.14000 Rp 5,250,430.62 Rp 735,060.29
Plesteran 1 : 4 M2 2.60000 Rp 62,310.00 Rp 162,006.00
Pas. Pipa GI 1" Ls 1.00000 Rp 50,000.00 Rp 50,000.00
Tenaga Pekerja M3 1.65000 Rp 90,000.00 Rp 148,500.00
Tukang M3 0.27500 Rp 120,000.00 Rp 33,000.00
Kepala tukang M3 0.02800 Rp 140,000.00 Rp 3,920.00
Mandor M2 0.08300 Rp 110,000.00 Rp 9,130.00
Jumlah Rp 2,404,409.49
Pembuatan Resapan Bh
Bahan Galian Tanah M3 1.00000 Rp 70,250.00 Rp 70,250.00
Urugan Tanah M3 0.25400 Rp 208,100.00 Rp 52,857.40
Urugan Pasir M3 0.05000 Rp 208,100.00 Rp 10,405.00
Urugan Kerikil M3 0.10000 Rp 198,200.00 Rp 19,820.00
Pas. Batako 1 : 4 M2 4.00000 Rp 62,310.00 Rp 249,240.00
Pas. Ijuk Ls 1.00000 Rp 90,000.00 Rp 90,000.00
Pas. Plat Beton tbl. 7 cm M3 0.07000 Rp 5,250,430.62 Rp 367,530.14
Tenaga Pekerja M3 1.65000 Rp 90,000.00 Rp 148,500.00
Tukang M3 0.27500 Rp 120,000.00 Rp 33,000.00
Kepala tukang M3 0.02800 Rp 140,000.00 Rp 3,920.00
Mandor M3 0.08300 Rp 110,000.00 Rp 9,130.00
Jumlah Rp 1,054,652.54
RENCANA ANGGARAN BIAYA
KEGIATAN : PEMBANGUNAN TEMPAT MANDI, CUCI DAN KAKUS ( MCK )
LOKASI : DESA PANGI KECAMATAN SANG TOMBOLANG
KABUPATEN : BOLAANG MONGONDOW
TAHUN : 2017

NO URAIAN PEKERJAAN VOLUME HARGA SATUAN


1 2 3 4
I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi 20.00 M2 Rp 14,500.00
2 Papan Nama Proyek 1.00 Bh Rp 600,000.00
JUMLAH
II PEKERJAAN TANAH & URUGAN
1 Galian Tanah Pondasi 3.00 M³ Rp 70,250.00
2 Urugan Pasir Bawah Pondasi 0.50 M³ Rp 208,100.00
3 Urugan Pasir Bawah Lantai 1.00 M³ Rp 208,100.00
4 Urugan Tanah Kembali 3.00 M³ Rp 208,100.00
5 Meratakan Tanah 20.00 M2 Rp 23,416.67
JUMLAH
III PEKERJAAN PASANGAN
1 Pas. Pondasi Batu Kali 1 : 5 4.06 M³ Rp 550,550.00
2 Pas. Batako 1 : 4 33.94 M2 Rp 95,575.00
JUMLAH
IV PEKERJAAN BETON
1 Pas. Beton Sloof 15/15 0.56 M³ Rp 5,250,430.62
2 Pas. Beton Kolom 15/15 0.45 M³ Rp 6,015,497.28
3 Pas. Ring Balk 15/15 0.56 M³ Rp 7,609,497.28
4 Rabat Beton t = 5 Cm 1.00 M³ 747,042.14
JUMLAH
V PEKERJAAN PENULANGAN BETON BERTULANG
1 Tulangan Ø 10 mm Beton Sloof 15/15 9.00 Ujg Rp 60,000.00
2 Tulangan Ø 6 mm Sengkang Beton Sloof 15/15 8.00 Ujg Rp 48,000.00
3 Tulangan Ø 10 mm Beton Kolom 15/15 7.00 Ujg Rp 60,000.00
4 Tulangan Ø 6 mm Sengkang Beton Kolom 15/15 6.00 Ujg Rp 48,000.00
5 Tulangan Ø 10 mm Ring Balk 15/15 9.00 Ujg Rp 60,000.00
6 Tulangan Ø 6 mm Sengkang Ring Balk 15/15 8.00 Ujg Rp 48,000.00
JUMLAH
V PEKERJAAN PLESTERAN
1 Plesteran Dinding 1 : 4 67.88 M2 Rp 62,310.00
2 Acian 67.88 M2 Rp 37,375.00
JUMLAH
VI PEKERJAAN PINTU DAN ROSTER
1 Pas. Pintu PVC 2.00 Bh Rp 275,000.00
2 Pas. Roster #REF! M2 Rp 83,475.00
JUMLAH
VII PEKERJAAN KERAMIK
1 Pas. Keramik Lantai 20/20 20.00 M2 Rp 175,257.50
JUMLAH
VIII PEKERJAAN RANGKA ATAP
1 Pas. Gording Kayu Kruing 6/12 0.09 M3 Rp 7,658,000.00
2 Pas. Usuk Kayu 5/7 0.04 M3 Rp 51,450.00
3 Pas. Listplank 3/30 0.09 M3 131,850.00
JUMLAH
IX PEKERJAAN PENUTUP ATAP
1 Pas. Seng Gelombang 33.04 M2 Rp 88,660.00
JUMLAH
X PEKERJAAN PLAFOND
1 Pas. Rangka plafond 20.00 M2 128,550.00
2 Pas. Plafond Plywood 20.00 M2 Rp 22,960.00
JUMLAH
XI PEKERJAAN PENGECATAN
1 Pengecatan Dinding Baru 67.88 M2 Rp 17,777.00
2 Pengecatan Plafond 20.00 M2 Rp 17,777.00
JUMLAH
XII PEKERJAAN INSTALASI LISTRIK
1 Pas. Titik Lampu #REF! Bh Rp 84,375.00
2 Pas. Lampu PLC 18 watt ( merk setara Philip ) #REF! Bh Rp 94,900.00
3 Pas. Saklar Tunggal ( Setara Broco ) #REF! Bh Rp 16,000.00
4 Kabel NYM #REF! M' Rp 5,000.00
JUMLAH
XIII PEKERJAAN SANITAIR
1 Pas. Avour #REF! Bh Rp 48,400.00
2 Pas. Closet 3.00 Bh Rp 886,740.00
3 Pas. Tempat Bak Mandi & Tempat Closet/cuci #REF! Bh Rp 250,000.00
4 Pas. Pipa PVC Ø 2" Kamar Mandi #REF! M' Rp 44,416.33
5 Pas. Pipa PVC Ø 4" Air Kotor #REF! M' Rp 82,929.67
6 Septictank 1.00 Bh Rp 2,404,409.49
7 Pas. Kran Air #REF! Bh Rp 30,000.00
8 Resapan 1.00 Bh Rp 1,054,652.54
9 Penggalian Sumur 1.00 Ttk Rp 600,000.00

JUMLAH
JUMLAH TOTAL
JUMLAH TOTAL (3 Unit)
OPERASIONAL TPK 3%

JUMLAH TOTAL
RENCANA ANGGARAN BIAYA

JUMLAH HARGA
5

Rp 290,000.00
Rp 600,000.00
Rp 890,000.00

Rp 210,750.00
Rp 104,050.00
Rp 208,100.00
Rp 624,300.00
Rp 468,333.33
Rp 1,615,533.33

Rp 2,236,609.38
Rp 3,243,815.50
Rp 5,480,424.88

Rp 2,953,367.22
Rp 2,679,904.04
Rp 4,280,342.22
Rp 747,042.14
Rp 10,660,655.63

Rp 540,000.00
Rp 384,000.00
Rp 420,000.00
Rp 288,000.00
Rp 540,000.00
Rp 384,000.00
Rp 2,556,000.00

Rp 4,229,602.80
Rp 2,537,015.00
Rp 6,766,617.80

Rp 550,000.00

Rp 550,000.00

Rp 3,505,150.00
Rp 3,505,150.00

Rp 665,951.93
Rp 2,016.84
Rp 11,866.50
Rp 679,835.27
Rp 2,929,326.40
Rp 2,929,326.40

Rp 2,571,000.00
Rp 459,200.00
Rp 3,030,200.00

Rp 1,206,702.76
Rp 355,540.00
Rp 1,562,242.76

Rp 2,660,220.00

Rp 2,404,409.49

Rp 1,054,652.54
Rp 600,000.00

Rp 6,719,282.03
Rp 46,945,268.10
Rp 140,835,804.30
Rp 4,225,074.13

Rp 145,060,878.42
DAFTAR ANALISA HARGA SATUAN

Propinsi : Sulawesi Utara Desa : Pangi


Kabupaten : Bolaang Mongondow Kecamatan : Sang Tombolamg
Jenis Kegiatan : MCK (3 Unit) Ukuran : 2,0 x 1,5 m

Gambar MCK

I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi
Panjang x Lebar
Luas 5 x 4
Luas 20 M²
2 Papan Nama Proyek
Jumlah = 1 Bh
II PEKERJAAN TANAH & URUGAN
1 Galian Tanah Pondasi
Volume = Panjang x Lebar x Tinggi
Volume = 25.00 0.40 x 0.30
Volume = 3.00 M³
2 Urugan Pasir Bawah Pondasi
Volume = Panjang x Lebar x Tinggi
Volume = 25.00 x 0.40 x 0.05
Volume = 0.50 M³
3 Galian Tanah Pondasi (DudukanTendon air)
Volume = Panjang x Lebar x Tinggi
Volume = 4 0.4 x 0.3
Volume = 0.48 M³

4 Urugan Pasir Bawah Pondasi (Dudukan Tendon Air)


Volume = Panjang x Lebar x Tinggi
Volume = 4.00 x 0.40 x 0.05
Volume = 0.08 M³
5 Urugan Pasir Bawah Lantai
Volume = Panjang x Lebar x Tinggi
Volume = 5.00 x 4.00 x 0.05
Volume = 1.00 M³
6 Urugan Tanah Kembali
Volume = Panjang x Lebar x Tinggi
Volume = 5.00 x 4.00 x 0.15
Volume = 3.00 M³
7 Meratakan Tanah
Volume = Panjang x Lebar
Volume = 5.00 x 4.00
Volume = 20.00 M2
III PEKERJAAN PASANGAN
1 Pas. Pondasi Batu Kali 1 : 5
Volume = Panjang x Lebar x Tinggi
Volume = 25.00 x 0.33 x 0.50
Volume = 4.06 M³
2 Pas. Pondasi Batu Kali 1 : 5 (Dudukan Tendon Air)
Volume = Panjang x Lebar x Tinggi
Volume = 4.00 x 0.33 x 1.00
Volume = 1.30 M³
3 Pas. Batako 1 : 4
Luas Seluruh = Panjang x Tinggi
= 16.00 x 2.20
= 35.20 M2
Luas Pintu = 1.80 x 0.70
= 1.26 M2
Luas Dinding = 35.20 - 1.26
= 33.94 M2

IV PEKERJAAN BETON
1 Pas. Beton Sloof 15/15
Volume = Panjang x Lebar x Tinggi
Volume = 25.00 x 0.15 x 0.15
Volume = 0.56 M³
2 Pas. Beton Kolom 15/15
Jumlah = 9.00 buah
Volume = Tinggi x Panjang x Lebar
Volume = 2.20 x 0.15 x 0.15
Volume = 0.45 M³
3 Pas. Ring Balk 15/15
Volume = Panjang x Lebar x Tinggi
Volume = 25.00 x 0.15 x 0.15
Volume = 0.56 M³
4 Rabat Beton t = 5 Cm
Volume = Panjang x Lebar x Tinggi
Volume = 5.00 x 4.00 x 0.05
Volume = 1.00 M³
V PEKERJAAN PENULANGAN BETON BERTULANG
1 Tulangan Beton Sloof 15/15
P. Total Sloof = 25.00 M'
P. Besi = 12.00 M, Ø 10 mm
n.Besi = 4.00 Ujg
P. Total Besi = P.Total Sloof x n.Besi
= 25.00 x 4.00
= 100.00 M'
Jumlah Besi = P. Total Besi / P. Besi
= 100.00 / 12.00
= 8.33 Ujg ≈ 9.00 Ujg
2 Tulangan Sengkang Beton Sloof 15/15
P. Total Sloof = 25.00 M'
P. Besi = 12.00 M, Ø 6 mm
Jarak Sengkang = 0.30 M
Tot. Jumlah Sengkang = P.Total Sloof / Jarak Sengkang
= 25.00 / 0.30
= 83.33 Bh ≈ 84 Bh
P.Besi 1 Bh.Sengkang = 0.65 M'
Tot. Pjg. Sengkang = P.Besi 1 Bh.Sengkang / Tot. Jumlah sengkang
= 0.65 x 84
= 84.65 M'
Jumlah Besi = Tot. Pjg. Sengkang / P. Besi
= 84.65 / 12
= 7.05 Ujg ≈ 8.00 Ujg
3 Tulangan Beton Kolom 15/15
P. Total Kolom = 19.80 M'
P. Besi = 12.00 M, Ø 10 mm
n.Besi = 4.00 Ujg
P. Total Besi = P.Total Kolom x n.Besi
= 19.80 x 4.00
= 79.20 M'
Jumlah Besi = P. Total Besi / P. Besi
= 79.20 / 12
= 6.60 Ujg ≈ 7.00 Ujg
4 Tulangan Sengkang Beton Kolom 15/15
P. Total Sloof = 19.80 M'
P. Besi = 12.00 M, Ø 6 mm
Jarak Sengkang = 0.30 M
Tot. Jumlah Sengkang = P.Total Kolom / Jarak Sengkang
= 19.80 / 0.30
= 66.00 Bh ≈ 67 Bh
P.Besi 1 Bh.Sengkang = 0.65 M'
Tot. Pjg. Sengkang = P.Besi 1 Bh.Sengkang / Tot. Jumlah sengkang
= 0.65 x 67
= 67.65 M'
Jumlah Besi = Tot. Pjg. Sengkang / P. Besi
= 67.65 / 12
= 5.64 Ujg ≈ 6.00 Ujg
5 Tulangan Ring Balk 15/15
P. Ring Balk = 25.00 M'
P. Besi = 12.00 M, Ø 10 mm
n.Besi = 4.00 Ujg
P. Total Besi = P. Ring Balk x n.Besi
= 25.00 x 4.00
= 100.00 M'
Jumlah Besi = P. Total Besi / P. Besi
= 100.00 / 12
= 8.33 Ujg ≈ 9.00 Ujg
6 Tulangan Sengkang Ring Balk 15/15
P. Total Sloof = 25.00 M'
P. Besi = 12.00 M, Ø 6 mm
Jarak Sengkang = 0.30 M
Tot. Jumlah Sengkang = P.Total Kolom / Jarak Sengkang
= 25.00 / 0.30
= 83.33 Bh ≈ 84 Bh
P.Besi 1 Bh.Sengkang = 0.65 M'
Tot. Pjg. Sengkang = P.Besi 1 Bh.Sengkang / Tot. Jumlah sengkang
= 0.65 x 84
= 84.65 M'
Jumlah Besi = Tot. Pjg. Sengkang / P. Besi
= 84.65 / 12
= 7.05 Ujg ≈ 8.00 Ujg
VI PEKERJAAN PLESTERAN
1 Plesteran Dinding 1 : 4 + Acian
Luas Total = Luas Dinding x 2.00
= 33.94 x 2.00
= 67.88 M²
VII PEKERJAAN PINTU
1 Pas. Pintu PVC = 2.00 Bh
VIII PEKERJAAN KERAMIK
1 Pas. Keramik Lantai 20/20
Luas = Panjang x Lebar
= 5 x 4
= 20 M²
IX PEKERJAAN RANGKA ATAP
1 Pas. Gording Kayu 6/12
Jumlah Gording = 6.00 Bh
Panjang 1 Buah = 2.01 M'
Total Panjang = 12.08 M'
Volume = Panjang x Lebar x Tinggi
= 12.08 x 0.06 x 0.12
= 0.09 M³

2 Pas. Kuda Kuda Kayu 6/12


Jumlah Tiang Raja = 4.00 Bh
Panjang 1 Buah = 0.90 M'
Balok Nok = 5.90 M'
Total Panjang = 9.50 M'
Volume = Panjang x Lebar x Tinggi
= 9.50 x 0.06 x 0.12
= 0.07 M³
3 Pas. Usuk Kayu 5/7
Jumlah Usuk = 4.00 Bh
Panjang 1 Buah = 2.80 M'
Total Panjang = 11.20 M'
Volume = Panjang x Lebar x Tinggi
= 11.20 x 0.05 x 0.07
= 0.04 M³
4 Pas. Listplank 3/30
Total Panjang = 10.00 M'
Volume = Panjang x Lebar x Tinggi
= 10.00 x 0.30 x 0.03
= 0.09 M³
X PEKERJAAN PENUTUP ATAP
1 Pas. Seng Gelombang
Luas = Panjang x Lebar
= 5.9 x 5.6
= 33.04 M²
2 Pas. Atap Bubungan
Panjang = 5.9 M

XI PEKERJAAN PLAFOND
1 Pas. Rangka plafond kayu 4/6
Luas = Panjang x Lebar
= 5 x 4
= 20 M²
2 Pas. Plafond Plywood
Luas = Panjang x Lebar
= 5 x 4
= 20 M²
XII PEKERJAAN PENGECATAN
1 Pengecatan Dinding Baru
Luas Total = Luas Dinding x 2
= 33.94 x 2
= 67.88 M²
2 Pengecatan Plafon
Luas = Panjang x Lebar
= 5 x 4
= 20 M²
XIII PEKERJAAN SANITAIR
1 Pas. Avour
Jumlah = 3 Bh

2 Pas. Penguras
Jumlah = 2 Bh

3 Pas. Tempat Sabun


Jumlah = 2 Bh

4 Pas. Closet
Jumlah = 2 Bh

5 Pas. Tempat Bak Mandi & Tempat Closet/cuci


Jumlah = 2 Bh

6 Pas. Pipa PVC Ø 1" Kamar Mandi


Jumlah = 20 M'

7 Pas. Kran Air


Jumlah = 5 Bh

8 Pas. Pipa PVC Ø 4" Air Kotor


Jumlah = 12 M'

Pengeboran Sumur Pompa Komplit dan


9
9
Pipa PVC Ø 4" L = 10 M = 1 Titik

10 Pas. Tandon Air (Profil Tank )


Jumlah = 1 Bh

11 Pompa Air SANYO PWH236


Jumlah = 1 Bh
XIII PEKERJAAN SEPTICTANK
1 Galian Tanah
Volume = Panjang x Lebar x Tinggi
= 1.50 x 1.00 x 1.50
= 2.25 M³
2 Urugan Tanah
Volume = Panjang x Lebar x Tinggi
= 1.50 x 1.00 x 0.15
= 0.23 M³
3 Urugan Pasir
Volume = Panjang x Lebar x Tinggi
= 1.50 x 1.00 x 0.05
= 0.08 M³
4 Pas. Batako
Luas = Panjang x Lebar
= 5.00 x 1.50
= 7.50 M2
5 Pas. Plat Beton tbl. 7 cm
Volume = Panjang x Lebar x Tinggi
= 1.50 x 1.00 x 0.07
= 0.11 M³
Penulangan Plat
- Tulangan Utama 4 Ø 12 mm
1.50 x 4 = 6 m
Jika dalam 1 Btg besi P : 12 m
maka ;
6 : 11 = 0.55 Ujg
- Tulangan Utama Ø 10 - 10 cm
150 : 10 = 15 m
15 x 1.00 = 15 m
Jika dalam 1 Btg besi P : 12 m
maka ;
15 : 11 = 1.36 Ujg
6 Plesteran 1 : 4
Luas = Panjang x Lebar
= 1.50 x 1.00
= 1.50 M2
7 Pas. Pipa GI
Panjang = 12.00 m
ANALISA HARGA SATUAN BAHAN DAN UPAH

KEGIATAN : PEMBANGUNAN TEMPAT MANDI, CUCI DAN KAKUS ( MCK )


LOKASI : DESA PANGI KECAMATAN SANG TOMBOLANG
KABUPATEN : BOLAANG MONGONDOW
TAHUN : 2017

JENIS PEKERJAAN VOLUME SAT INDEKS BAHAN ALAT UPAH


Pekerjaan Persiapan
Pembersihan lokasi 20.00 M2
Upah Pekerja org/hari 0.5630 11.260

Pekerjaan Tanah dan Urugan


Galian Tanah Pondasi 3.48 M3
Upah Pekerja org/hari 0.7500 2.610

Urugan Pasir Bawah Pondasi 0.58 M3


Bahan Pasir Urug/Sirtu m3 1.2000 0.696
Upah Pekerja org/hari 0.3000 0.174

Urugan Pasir Bawah Lantai 1 M3


Bahan Pasir Urug/Sirtu m3 1.2000 1.200
Upah Pekerja org/hari 0.3000 0.300

Urugan Tanah 3 M3
Bahan Tanah Urug m3 1.2000 3.600
Upah Pekerja org/hari 0.3300 0.990

Meratakan kembali 20.00 M2


Upah Pekerja org/hari 0.2500 5.000

Pekerjaan Pasangan
Pondasi Bt. Kali 1 : 5 4.06 M3
Bahan Batu Gunung/Batu Kali m3 1.2000 4.875
Semen 50 Kg kg 163.0000 662.188
Pasir Pasang m3 0.5200 2.113
Upah Pekerja org/hari 1.5000 6.094
Tukang org/hari 0.7500 3.047

Pondasi Bt. Kali 1 : 5 (Dudukan Tendon Air) 1.30 M3


Bahan Batu Gunung/Batu Kali m3 1.2000 4.875
Semen 50 Kg kg 163.0000 211.900
Pasir Pasang m3 0.5200 2.113
Upah Pekerja org/hari 1.5000 1.950
Tukang org/hari 0.7500 0.975

Dinding batako camp. 1 : 4 33.94 M2


Bahan Batako biji 12.5000 424.250
Semen 50 Kg kg 30.3200 1,029.061
Pasir Pasang m3 0.7280 24.708
Upah Pekerja org/hari 0.3500 11.879
Tukang org/hari 0.1500 5.091

Pekerjaan Plesteran
Plesteran camp. 1 : 4 tbl 15 mm 67.88 M2
Bahan Semen 50 Kg kg 10.2240 694.005
Pasir Pasang m3 0.0240 1.629
Upah Pekerja org/hari 0.3000 20.364
Tukang org/hari 0.1500 10.182

Acian 67.88 M2
Bahan Semen 50 Kg kg 3.2500 220.610
Upah Pekerja org/hari 0.2000 13.576
Tukang org/hari 0.1000 6.788
Pekerjaan Beton Bertulang
Beton sloof 0.56 M3
Bahan Kayu ( Bekisting ) m3 0.0150 0.008
Paku kg 1.0000 0.563
Tulangan Utama Besi Ø 10 mm Ujg 9.000
Tulangan Sengkang Besi Ø 6 mm Ujg 8.000
Kawat Bendrat kg 1.0000 0.563
Semen 50 Kg kg 326.0000 183.375
Pasir m3 0.5400 0.304
Kerikil m3 0.8200 0.461
Upah Pekerja org/hari 3.0000 1.688
Tukang org/hari 1.0000 0.563

Beton Kolom 0.45 M3


Bahan Kayu ( Bekisting ) m3 0.0150 0.007
Paku kg 1.0000 0.446
Tulangan Utama Besi Ø 10 mm Ujg 7.000
Tulangan Sengkang Besi Ø 6 mm Ujg 6.000
Kawat Bendrat kg 1.0000 0.446
Semen 50 Kg kg 326.0000 145.233
Pasir m3 0.5400 0.241
Kerikil m3 0.8200 0.365
Upah Pekerja org/hari 3.0000 1.337
Tukang org/hari 1.0000 0.446

Beton Ring Balok 0.56 M3


Bahan Kayu ( Bekisting ) m3 0.0150 0.008
Paku kg 1.0000 0.563
Tulangan Utama Besi Ø 10 mm Ujg 9.000
Tulangan Sengkang Besi Ø 6 mm Ujg 8.000
Kawat Bendrat kg 1.0000 0.563
Semen 50 Kg kg 326.0000 183.375
Pasir m3 0.5400 0.304
Kerikil m3 0.8200 0.461
Upah Pekerja org/hari 3.0000 1.688
Tukang org/hari 1.0000 0.563

Rabat Beton 1.00 M3


Bahan Semen 50 Kg kg 326.0000 326.000
Pasir Pasang m3 1.2000 1.200
Kerikil m3 1.4000 1.400
Upah Pekerja org/hari 1.6500 1.650
Tukang org/hari 0.2750 0.275

Pekerjaan Kayu
Konstruksi gording kayu klas II 0.09 M3
Bahan Kayu 6/12 m3 1.1000 0.096
Paku kg 3.0000 0.261
Upah Pekerja org/hari 2.4000 0.209
Tukang org/hari 7.2000 0.626

Konstruksi kuda-kuda kayu klas II 0.07 M3


Bahan Kayu 6/12 m3 1.1000 0.075
Paku kg 3.0000 0.205
Upah Pekerja org/hari 2.4000 0.164
Tukang org/hari 7.2000 0.492

Usuk kayu klas II 0.04 M2


Bahan Kayu 5/7 m3 0.0060 0.000
Paku kg 0.2500 0.010
Upah Pekerja org/hari 0.1000 0.004
Tukang org/hari 0.1000 0.004

Listplank 3/30 kayu klas II 0.09 M2


Bahan Kayu Papan 3/30 m3 0.5000 0.045
Paku kg 0.0500 0.005
Upah Pekerja org/hari 0.1000 0.009
Tukang org/hari 0.2000 0.018
Pekerjaan Penutup Atap
Atap seng gelombang kecil 33.04 M2
Bahan seng Gelombang kecil 180 x 80 lembar 0.6944 22.943
Paku kg 0.1200 3.965
Upah Pekerja org/hari 0.1400 4.626
Tukang org/hari 0.0700 2.313

Atap Bubungan 5.90 M


Bahan Plat Galvalum M 1.0000 5.900
Paku kg 0.1200 0.708
Upah Pekerja org/hari 0.1400 0.826
Tukang org/hari 0.0700 0.413
Pekerjaan Lantai
Lantai keramik 20 x 20 20.00 M2
Bahan Tegel Keramik 20 x 20 (polos) bh 26.5000 530.000
Semen 50 Kg kg 10.4000 208.000
Pasir Pasang m3 0.0450 0.900
Upah Pekerja org/hari 0.2700 5.400
Tukang org/hari 0.1350 2.700

Pekerjaan Plafond
Rangka plafond 20.00 M2
Bahan Kayu 4/6 m3 0.0158 0.315
Paku kg 0.2000 4.000
Upah Pekerja org/hari 0.1500 3.000
Tukang org/hari 0.3000 6.000

Plafond asbes semen 20.00 M2


Bahan Enternit Polos 150 x 80 x 0.5 Lbr 0.8330 16.660
Paku Triplek/Eternit kg 0.0100 0.200
Upah Pekerja org/hari 0.0300 0.600
Tukang org/hari 0.0700 1.400

Pekerjaan Pengecatan
Pengecatan tembok 67.88 M2
Bahan Plamir Tembok kg 0.1000 6.788
Cat Tembok (Setara Cathilac) kg 0.3600 24.437
Upah Pekerja org/hari 0.0200 1.358
Tukang org/hari 0.0630 4.276

Pengecatan kayu 20.00 M2


Bahan Cat Kayu (Setara Emco) kg 0.4300 8.600
Meni Kayu kg 0.2000 4.000
Plamir Kayu kg 0.1500 3.000
Upah Pekerja org/hari 0.0700 1.400
Tukang org/hari 0.0090 0.180

Pek. Sanitasi
Pas. Avour 3 bh
Bahan Avour bh 3.000
Upah Pekerja org/hari 0.1200 0.360
Tukang org/hari 0.0150 0.045

Pas. Penguras 2 bh
Bahan Peguras bh 2.000
Upah Pekerja org/hari 0.1200 0.240
Tukang org/hari 0.0150 0.030

Pas. Tempat Sabun 2 bh


Bahan Tempat Sabun bh 2.000
Upah Pekerja org/hari 0.1200 0.240
Tukang org/hari 0.0150 0.030

Closet Jongkok 2.00 bh


Bahan Closet Jongkok ### bh 2.0000 4.000
Semen 50 Kg Kg 6.0000 12.000
Pasir M3 0.0100 0.020
Tenaga Pekerja ### org/hari 0.1200 0.240
Tukang ### org/hari 0.0150 0.030
Pas. Tempat Bak Mandi & Tempat Closet/cuci 2 bh
Bahan Semen 50 Kg Kg 6.0000 12.000
Pasir M3 0.0100 0.020
Tenaga Pekerja ### org/hari 0.1200 0.240
Tukang ### org/hari 0.0150 0.030
Pas. Pipa PVC Ø1" Kamar Mandi 20 M
Bahan Pipa PVC Ø 1" M 0.1200 2.400
Upah Pekerja org/hari 0.1200 2.400
Tukang org/hari 0.0150 0.300

Pas. Kran Air 3 bh


Bahan Kran Air bh 0.1200 0.360
Upah Pekerja org/hari 0.1200 0.360
Tukang org/hari 0.0150 0.045

Pas. Pipa PVC Ø 4" Air Kotor 12 M


Bahan Pipa PVC Ø 4" Air Kotor M 0.1200 1.440
Upah Pekerja org/hari 0.1200 1.440
Tukang org/hari 0.0150 0.180

Pas. Tandon Air (Profil Tank ) 1 bh


Bahan Tandon Air (Profil Tank ) bh 0.1200 1.000
Upah Pekerja org/hari 0.1200 0.120
Tukang org/hari 0.0150 0.015

Pompa Air SANYO PWH236 1


Bahan Pompa Air SANYO PWH236 bh 0.1200 1.000
Upah Pekerja org/hari 0.1200 0.120
Tukang org/hari 0.0150 0.015

Pengeboran Sumur Pompa Komplit dan


Pipa PVC Ø 4" L = 10 M 1 Titik
Bahan Pipa PVC Ø 4" L = 10 M bh 0.1200 1.000
Upah Pekerja org/hari 1.2000 1.200
Tukang org/hari 1.2000 1.200
Pekerjaan Septictank Bh
Galian Tanah 2.25 M3
Upah Pekerja org/hari 0.6750 1.519

Urugan Tanah 0.23 M3


Bahan Tanah Urug m3 1.2000 0.270
Upah Pekerja org/hari 0.3000 0.068

Urugan Pasir 0.08 M3


Bahan Pasir Urug/Sirtu M3 1.2000 0.090
Upah Pekerja org/hari 0.3000 0.023

Pas. Batako 1 : 4 7.50 M2


Bahan Batako biji 12.5000 93.750
Semen 50 Kg kg 11.5000 86.250
Pasir Pasang m3 0.0430 0.323
Upah Pekerja org/hari 0.3000 2.250
Tukang org/hari 0.1000 0.750

Pas. Plat Beton tbl. 7 cm 0.11 M³


Bahan Semen 50 kg Kg 250.0000 26.250
Kerikil M³ 0.8200 0.086
Pasir pasang M³ 0.5400 0.057
Besi Ø 10 mm Ujung 1.3636
Besi Ø 12 mm Ujung 0.5455
Bendrat Kg 1.0000 0.105
Paku biasa Kg 1.0000 0.105
kayu kelas II M³ 0.0150 0.002
Upah Pekerja org/hari 3.0000 0.315
Tukang org/hari 1.0000 0.105

Plesteran 1 : 4 1.50 M2
Bahan Semen 50 Kg kg 6.2400 9.360
Pasir Pasang m3 0.0240 0.036
Upah Pekerja org/hari 0.3000 0.450
Tukang org/hari 0.1500 0.225

Pas. Pipa GI 1" 12.00 M


Bahan Pipa 4" M 1.0000 12.000
Upah Pekerja org/hari 0.0600 0.720
Tukang org/hari 0.0300 0.360
RENCANA ANGGARAN BIAYA (RAB)

Kabupaten : Bolaang Mongondow Jenis Kegiatan : MCK


Kecamatan : Sang Tombolang Ukuran : 3 Unit
Desa : Pangi

TOTAL
HARGA SATUAN
URAIAN VOLUME SATUAN ANGGARAN
Rp. Rp.
I Bahan
1 Pasir 33.819 m3 175,000.00 5,918,361.75
2 Tanah Urugan 3.870 m3
54,000.00 208,980.00
3 Batu Gunung/Batu kali 6.175 m3 200,000.00 1,235,000.00
4 Semen 50 Kg 75.714 Zak 75,000.00 5,678,559.63
5 Batako 518.000 Bh 2,300.00 1,191,400.00
6 Besi Ø 12 mm 0.545 Ujg 60,000.00 32,727.27
7 Besi Ø 10 mm 26.364 Ujg 85,000.00 2,240,909.09
8 Besi Ø 6 mm 22.000 Ujg 44,600.00 981,200.00
10 Kayu kelas II 0.121 m3 1,500,000.00 181,538.19
11 Kayu/Papan kelas II 0.045 m3 3,000,000.00 135,000.00
12 Paku 10.12 Kg 20,000.00 202,309.70
13 Kawat Bendrat 1.68 Kg 22,500.00 37,698.75
14 Kerikil 2.77 m3 250,000.00 693,477.50
15 Seng Gelombang kecil 180 x 80 22.94 Bh 85,000.00 1,950,152.96
16 Seng Plat Galvalum 5.90 M 118,000.00 696,200.00
17 Tegel Keramik 20 x 20 (polos) 35.33 Dos 90,000.00 3,180,000.00
18 Enternit Polos 150 x 80 x 0.5 16.66 Lbr 9,300.00 154,938.00
19 Plamir Tembok 6.79 Kg 9,600.00 65,164.80
20 Cat Tembok (Cathilac) 24.44 Kg 17,500.00 427,644.00
21 Cat Kayu (Setara Emco) 8.60 Kg 43,500.00 374,100.00
22 Meni Kayu 4.00 Kg 17,000.00 68,000.00
23 Plamir Kayu 3.00 Kg 16,500.00 49,500.00
24 Pintu PVC 2.00 Bh 275,000.00 550,000.00
25 Avour Type Stailes AJP 3.00 Bh 26,000.00 78,000.00
26 Penguras 2.00 Bh 8,000.00 16,000.00
27 Tempat Sabun Tempel 2.00 Bh 35,000.00 70,000.00
28 Closet Jongkok 2.00 Bh 220,000.00 440,000.00
29 Bak Mandi Fiber kotak 120 L 2.00 Bh 350,000.00 700,000.00
30 Pipa PVC 1" 20.00 M 8,000.00 160,000.00
31 Kran Air 3.00 Bh 30,000.00 90,000.00
32 Pipa Galfanis 4" 12.00 M 150,000.00 1,800,000.00
33 Tendon Air (Pinguin TB55) 1.00 Bh 750,000.00 750,000.00
34 Pompa Air SANYO PWH236 1.00 Bh 650,000.00 650,000.00
35 Pengeboran Sumur Suntik 1.00 Ls 750,000.00 750,000.00
36 Papan Proyek 1.00 Ls 600,000.00 600,000.00
Sub Total 1) 32,356,861.64
II Alat
1 -
2 -
Sub Total 2) -
III Upah
1 Pekerja 100.80 HOK 90,000.00 9,071,714.51
2 Tukang 45.94 HOK 110,000.00 5,053,472.44
Sub Total 3) 14,125,186.94
Total Biaya (1 Unit) 46,482,048.58
Total Biaya (3 Unit) 139,446,145.75
Operasional TPK 3% 4,183,384.37
JUMLAH ANGGARAN 143,629,530.12
DIBULATKAN 143,629,600.00
Enam puluh dua juta lima ratus enam puluh dua ribu tujuh ratus rupiah
RENCANA ANGGARAN BIAYA (RAB)

Kabupaten : Bolaang Mongondow Jenis Kegiatan : MCK


Kecamatan : Sang Tombolang Ukuran : 3 Unit
Desa : Bolangat Timur

TOTAL
HARGA SATUAN
URAIAN VOLUME SATUAN ANGGARAN
Rp. Rp.
I Bahan
1 Pasir 101.458 m3 175,000.00 17,755,085.25
2 Tanah Urugan 11.610 m3 54,000.00 626,940.00
3 Batu Gunung/Batu kali 18.525 m 3
200,000.00 3,705,000.00
4 Semen 50 Kg 227.142 Zak 75,000.00 17,035,678.89
5 Batako 1554.000 Bh 2,300.00 3,574,200.00
6 Besi Ø 12 mm 1.636 Ujg 60,000.00 98,181.82
7 Besi Ø 10 mm 79.091 Ujg 85,000.00 6,722,727.27
8 Besi Ø 6 mm 66.000 Ujg 44,600.00 2,943,600.00
10 Kayu kelas II 0.363 m3 1,500,000.00 544,614.57
11 Kayu/Papan kelas II 0.135 m3 3,000,000.00 405,000.00
12 Paku 30.346 Kg 20,000.00 606,929.09
13 Kawat Bendrat 5.027 Kg 22,500.00 113,096.25
14 Kerikil 8.322 m3 250,000.00 2,080,432.50
15 Seng Gelombang kecil 180 x 80 68.829 Bh 85,000.00 5,850,458.88
16 Seng Plat Galvalum 17.700 M 118,000.00 2,088,600.00
17 Tegel Keramik 20 x 20 (polos) 106.000 Dos 90,000.00 9,540,000.00
18 Enternit Polos 150 x 80 x 0.5 49.980 Lbr 9,300.00 464,814.00
19 Plamir Tembok 20.364 Kg 9,600.00 195,494.40
20 Cat Tembok (Cathilac) 73.310 Kg 17,500.00 1,282,932.00
21 Cat Kayu (Setara Emco) 25.800 Kg 43,500.00 1,122,300.00
22 Meni Kayu 12.000 Kg 17,000.00 204,000.00
23 Plamir Kayu 9.000 Kg 16,500.00 148,500.00
24 Pintu PVC 6.000 Bh 275,000.00 1,650,000.00
25 Avour Type Stailes AJP 9.000 Bh 26,000.00 234,000.00
26 Penguras 6.000 Bh 8,000.00 48,000.00
27 Tempat Sabun Tempel 6.000 Bh 35,000.00 210,000.00
28 Closet Jongkok 6.000 Bh 220,000.00 1,320,000.00
29 Bak Mandi Fiber kotak 120 L 6.000 Bh 350,000.00 2,100,000.00
30 Pipa PVC 1" 60.000 M 8,000.00 480,000.00
31 Kran Air 9.000 Bh 30,000.00 270,000.00
32 Pipa Galfanis 4" 36.000 M 150,000.00 5,400,000.00
33 Tendon Air (Pinguin TB55) 3.000 Bh 750,000.00 2,250,000.00
34 Pompa Air SANYO PWH236 3.000 Bh 650,000.00 1,950,000.00
35 Pengeboran Sumur Suntik 3.000 Ls 750,000.00 2,250,000.00
36 Papan Proyek 1.000 Ls 600,000.00 600,000.00
Sub Total 1) 95,870,584.92
II Alat
1 -
2 -
Sub Total 2) -
III Upah
1 Pekerja 302.390 HOK 90,000.00 27,215,143.52
2 Tukang 137.822 HOK 110,000.00 15,160,417.31
Sub Total 3) 42,375,560.83
Total Biaya 138,246,145.75
Operasional TPK 3% 4,147,384.37
JUMLAH ANGGARAN 142,393,530.12
DIBULATKAN 142,393,600.00
Seratus empat pulih dua juta tiga ratus sembilan puluh tiga ribu enam ratus rupiah